JP2018165445A - Temporary fixing pin of perforated pipe and method of constructing multi-stage drain pipe using the same - Google Patents

Temporary fixing pin of perforated pipe and method of constructing multi-stage drain pipe using the same Download PDF

Info

Publication number
JP2018165445A
JP2018165445A JP2017062935A JP2017062935A JP2018165445A JP 2018165445 A JP2018165445 A JP 2018165445A JP 2017062935 A JP2017062935 A JP 2017062935A JP 2017062935 A JP2017062935 A JP 2017062935A JP 2018165445 A JP2018165445 A JP 2018165445A
Authority
JP
Japan
Prior art keywords
temporary fixing
fixing pin
perforated
pipe
pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017062935A
Other languages
Japanese (ja)
Other versions
JP6916019B2 (en
Inventor
拓也 石垣
Takuya Ishigaki
拓也 石垣
懸一 安冨
Kenichi Yasutomi
懸一 安冨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Metal Products Co Ltd
Original Assignee
Nippon Steel and Sumikin Metal Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel and Sumikin Metal Products Co Ltd filed Critical Nippon Steel and Sumikin Metal Products Co Ltd
Priority to JP2017062935A priority Critical patent/JP6916019B2/en
Publication of JP2018165445A publication Critical patent/JP2018165445A/en
Application granted granted Critical
Publication of JP6916019B2 publication Critical patent/JP6916019B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

PROBLEM TO BE SOLVED: To provide a temporary fixing pin for perforated pipes which can collectively arrange a plurality of perforated pipes having different pipe diameters without requiring packaging and the like, is free from anxiety about load collapse at the time of transportation, and is easy to be attached and detached.SOLUTION: In the state that all pipes of a plurality of perforated pipes having different pipe diameters are inserted into a pipe having the maximum diameter, a temporary fixing pin 1 of a removable perforated pipe which temporarily fixes the sliding movement of the plurality of perforated pipes by being inserted into holes of all the pipes of the plurality of perforated pipes includes: a grip portion 2 gripped and grasped during insertion and removal; and a leg portion 3 connected to the grip portion 2 and having one end folded back. The leg portion 3 is provided with: a linear guide portion 30 which is provided at a tip not connected to the grip portion 2 and serves as a guide when passing through the holes of the respective pipes of the plurality of perforated pipes; an engaging portion 31 connected to the guide portion 30 and engaged with the hole of the pipe of any of the plurality of perforated pipes; and a linear temporary fixing portion 32 connected to the engaging portion 31 and having a length inserted through all the pipes of the plurality of perforated pipes.SELECTED DRAWING: Figure 5

Description

本発明は、管径の異なる複数の有孔管(孔空き管)の全ての管を最大径の管内に挿入した状態で、前記複数の有孔管の全ての管の孔に挿通されることで前記数の有孔管同士のスライド移動を一時的に仮固定する挿抜自在の有孔管の仮固定ピンに関する。より詳しくは、本発明は、排水用の孔が穿設された管径の異なる複数の有孔管がそれぞれ突没自在に嵌合された多段式排水パイプを運搬時に仮固定する多段式排水パイプ用の仮固定ピン、及びそれを用いた多段式排水パイプの施工方法に関する。   In the present invention, all of the plurality of perforated pipes (perforated pipes) having different pipe diameters are inserted into the holes of the plurality of perforated pipes in a state where all the pipes are inserted into the maximum diameter pipe. The present invention relates to a temporary fixing pin for an insertable / removable perforated tube that temporarily fixes the sliding movement of the perforated tubes of the number. More specifically, the present invention relates to a multistage drainage pipe that temporarily fixes a multistage drainage pipe in which a plurality of perforated pipes having different diameters, each having a hole for drainage, are slidably fitted into each other during transportation. The present invention relates to a temporary fixing pin for use, and a construction method of a multistage drainage pipe using the pin.

従来、切土や盛土、自然斜面などの土の斜面内を流れる地下水を排水して斜面崩壊を防止する排水パイプにおいて、打ち込み時の抵抗力を少なくするために多段式とした多段式排水パイプが知られている。   Conventionally, multi-stage drainage pipes that have been multi-staged to reduce the resistance when driving in drainage pipes that prevent ground collapse by draining groundwater flowing in the slopes of soil such as cut, banking, and natural slopes. Are known.

例えば、特許文献1には、土砂部5の斜面に打ち込まれ、周壁に水抜き孔が形成された管体を備える排水パイプ1において、先端部12の内径が根本部より縮径化された第1の管体10と、第1の管体10の先端部12の内径よりも小径の本管部21及び当該内径よりも拡径化された根本部24を有する第2の管体20とを備え、第2の管体20は、挿入される第1の管体10内の先端部22に根本部24を係止させつつ本管部21を第1の管体10から突出自在とされている多段式排水パイプ1が開示されている(特許文献1の特許請求の範囲の請求項1、明細書の段落[0020]〜[0029]図面の図1〜図4、等参照)。   For example, in Patent Document 1, in a drainage pipe 1 having a tubular body that is driven into the slope of the earth and sand portion 5 and has a drain hole formed in the peripheral wall, the inner diameter of the tip portion 12 is reduced from the root portion. A first tubular body 10, a main pipe portion 21 having a diameter smaller than the inner diameter of the distal end portion 12 of the first tubular body 10, and a second tubular body 20 having a root portion 24 having a diameter larger than the inner diameter. The second tubular body 20 is configured such that the main pipe portion 21 can protrude from the first tubular body 10 while the root portion 24 is locked to the distal end portion 22 in the first tubular body 10 to be inserted. A multistage drainage pipe 1 is disclosed (see claim 1 of patent document 1 and paragraphs [0020] to [0029] of FIGS. 1 to 4 of the drawings, etc.).

従来、このような多段式排水パイプは、製作工場等から施工現場まで運搬する際には、複数の有孔管が不用意にスライドして突出してしまわないように、全ての管を最大径の管内に一纏めに収めた状態で管端をテープや包装紙等で梱包する必要があった。このため、梱包に時間が掛かる上、施工現場での梱包を外す作業にも時間が掛かってしまうという問題があった。   Conventionally, such multistage drainage pipes have all the maximum diameters so that multiple perforated pipes do not slide out and protrude when they are transported from the production factory to the construction site. It was necessary to pack the end of the tube with tape, wrapping paper, etc. in a state of being packed together in the tube. For this reason, there is a problem that it takes time for packing and also takes time for removing the packing at the construction site.

その上、運搬車両から多段式排水パイプを荷降ろしした後施工現場まで移動する際に施工現場まで到着する前に、管端の梱包が破けて、多段式排水パイプの移動が困難になるというおそれもあった。   In addition, when unloading the multistage drain pipe from the transport vehicle and moving to the construction site, it may be difficult to move the multistage drain pipe due to tearing of the packing at the pipe end before arriving at the construction site. There was also.

なお、特許文献2には、地下水、浸透水等を排除するために地中に埋設される塩ビ管等の合成樹脂からなる有孔排水管1において、長孔5を介してピン6で嵌挿固定し、管の伸縮や輪圧等で地盤に変動が生じた場合でも、有孔排水管1同士が外れないようにした有孔排水管が開示されている(特許文献2の明細書の第2頁第8行目〜第19行目、図面の第4図等参照)。   In Patent Document 2, in a perforated drainage pipe 1 made of a synthetic resin such as a vinyl chloride pipe buried in the ground in order to exclude groundwater, permeated water, etc., it is inserted with a pin 6 through a long hole 5. A perforated drainage pipe is disclosed in which the perforated drainage pipes 1 are not detached even when the ground is fluctuated due to expansion and contraction of the pipe, ring pressure or the like (No. 1 in the specification of Patent Document 2). (Refer to page 8, lines 8 to 19 and FIG. 4).

しかし、特許文献2に記載の有孔排水管1のピン6は、運搬時に仮固定するために適用することはできず、前記問題を解決することができるものではなかった。   However, the pin 6 of the perforated drainage pipe 1 described in Patent Document 2 cannot be applied to temporarily fix it during transportation, and cannot solve the above problem.

特開2015−166519号公報JP2015-166519A 実公昭63−35066号公報Japanese Utility Model Publication No. 63-35066

そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、梱包等の必要がなく管径の異なる複数の有孔管を一纏めにすることができ、運搬時の荷崩れの心配がなく、且つ、着脱が容易な有孔管の仮固定ピン及びそれを用いた多段式排水パイプの施工方法を提供することにある。   Therefore, the present invention has been devised in view of the above-described problems, and the object of the present invention is to collect a plurality of perforated pipes having different pipe diameters without the need for packaging or the like, An object of the present invention is to provide a temporary fixing pin for a perforated pipe that is not worried about collapse of goods during transportation and can be easily attached and detached, and a construction method for a multistage drainage pipe using the pin.

第1発明に係る有孔管の仮固定ピンは、管径の異なる複数の有孔管の全ての管を最大径の管内に挿入した状態で、前記複数の有孔管の全ての管の孔に挿通されることで前記数の有孔管同士のスライド移動を一時的に仮固定する挿抜自在の有孔管の仮固定ピンであって、挿抜の際に把持して掴む把持部と、前記把持部と接続してその一端が折り返された脚部と、を備え、前記脚部は、前記把持部と接続しない先端に設けられて前記複数の有孔管の各管の孔に挿通する際のガイドとなる直線状のガイド部と、前記ガイド部と接続して前記複数の有孔管のいずれかの管の前記孔に係止される係止部と、前記係止部と接続して前記複数の有孔管の全ての管に亘って挿通される長さを有する直線状の仮固定部と、を有することを特徴とする。   A temporary fixing pin for a perforated pipe according to a first aspect of the present invention is the hole of all the plurality of perforated pipes in a state where all of the plurality of perforated pipes having different pipe diameters are inserted into the maximum diameter pipe. A temporary fixing pin of a removable perforated tube that temporarily fixes the sliding movement of the number of perforated tubes by being inserted into the gripper, and grips and grips at the time of insertion and removal, and A leg portion that is connected to the grip portion and whose one end is folded back, and the leg portion is provided at a tip that is not connected to the grip portion and is inserted into a hole of each of the plurality of perforated tubes. A linear guide portion serving as a guide, a locking portion connected to the guide portion and locked to the hole of any one of the plurality of perforated tubes, and connected to the locking portion And a linear temporary fixing portion having a length inserted through all of the plurality of perforated tubes.

第2発明に係る有孔管の仮固定ピンは、第1発明において、前記係止部は、前記ガイド部と前記仮固定部の線材の軸と傾斜し、挿入時に前記孔と当接する第一傾斜部と、記ガイド部と前記仮固定部の線材の軸と傾斜し、引き抜き時に前記孔と当接する第二傾斜部と、を有することを特徴とすることを特徴とする。   The temporary fixing pin of the perforated pipe according to the second invention is the first invention, wherein the locking part is inclined with respect to the shaft of the wire of the guide part and the temporary fixing part and contacts the hole during insertion. It has an inclined portion, a second inclined portion that is inclined with respect to the shaft of the wire rod of the guide portion and the temporary fixing portion and abuts on the hole when pulled out.

第3発明に係る有孔管の仮固定ピンは、第1発明又は第2発明において、前記脚部は、前記把持部の両端が折り返されて左右一対設けられ、全体として一端が開放された側面視コの字状となっていることを特徴とする。   A temporary fixing pin for a perforated tube according to a third aspect of the present invention is the side of the first or second aspect, wherein the leg portion is provided with a pair of left and right ends by folding back both ends of the grip portion, and one end is opened as a whole. It is characterized by a U-shape.

第4発明に係る有孔管の仮固定ピンは、第3発明において、前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記脚部の開放された一端からの距離が同じ位置に形成されていることを特徴とする。   According to a fourth aspect of the present invention, there is provided the temporary fixing pin for a perforated tube according to the third aspect, wherein the locking portion is provided on each of the pair of left and right legs, and the distance from the open end of the legs is set. They are formed at the same position.

第5発明に係る有孔管の仮固定ピンは、第3発明において、前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記脚部の開放された一端からの距離が異なる位置に形成されていることを特徴とする。   A temporary fixing pin for a perforated pipe according to a fifth invention is the temporary fixing pin according to the third invention, wherein the locking portion is provided on each of the pair of left and right legs, and the distance from one end of the legs that is opened is It is characterized by being formed at different positions.

第6発明に係る有孔管の仮固定ピンは、第3発明〜第5発明において、前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記係止部の前記線材の軸から突出する向きが左右対称となっていることを特徴とする。   A temporary fixing pin for a perforated tube according to a sixth aspect of the present invention is the third to fifth aspects of the present invention, wherein the locking portion is provided on each of the pair of left and right legs, and the wire rod of the locking portion is The direction protruding from the shaft is symmetrical.

第7発明に係る有孔管の仮固定ピンは、第3発明又は第5発明において、前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記係止部の前記線材の軸から突出する向きが左右非対称となっていることを特徴とする。   A temporary fixing pin for a perforated pipe according to a seventh aspect of the present invention is the third aspect or the fifth aspect, wherein the locking portion is provided on each of the pair of left and right legs, and the wire rod of the locking portion is The direction protruding from the shaft is asymmetrical in the left-right direction.

第8発明に係る多段式排水パイプの施工方法は、排水用の孔が穿設された管径の異なる複数の有孔管がそれぞれ突没自在に嵌合された多段式排水パイプを地中に貫入する多段式排水パイプの施工方法において、請求項1〜7のいずれか一項記載の有孔管の仮固定ピンを用いて、運搬前に前記多段式排水パイプの全ての管の孔に前記脚部を挿通し、前記係止部を前記多段式排水パイプのいずれかの管の前記孔に係止して、運搬し、前記多段式排水パイプを地中に貫入する直前に前記仮固定ピンを引き抜くことを特徴とする。   According to an eighth aspect of the present invention, there is provided a method for constructing a multistage drainage pipe, wherein a plurality of perforated pipes having different diameters and having holes for drainage are respectively fitted into the ground so that they can be projected and retracted. In the construction method of the multistage drainage pipe to penetrate, using the temporary fixing pin of the perforated pipe according to any one of claims 1 to 7, the holes in all the pipes of the multistage drainage pipe before transporting The temporary fixing pin is inserted immediately before the multi-stage drainage pipe is inserted into the ground through the legs, the latching section being latched in the hole of any one of the pipes of the multi-stage drainage pipe and transported. It is characterized by pulling out.

第1発明〜第7発明によれば、管径の異なる複数の有孔管の全ての管を最大径の管内に挿入した状態で一纏めにして仮固定ピンで仮固定するので、梱包等の必要がなく管径の異なる複数の有孔管を一纏めにすることができる。また、仮固定ピンの係止部が複数の有孔管のいずれかの管の孔に係止されているとともに、複数の有孔管は仮固定部で管同士のスライド移動が拘束されているので、運搬時の荷崩れの心配がなく不用意に複数の有孔管の一部が突出する事故を確実に防止することができる。また、仮固定ピンは、把持部を把持して引き抜くだけで、管同士のスライド移動が可能となるため、施工現場での梱包を外す作業も必要ない。   According to the first to seventh inventions, all of the plurality of perforated tubes having different tube diameters are collectively fixed in a state where they are inserted into the maximum diameter tube, and temporarily fixed with a temporary fixing pin. A plurality of perforated pipes having different pipe diameters can be grouped together. Moreover, while the latching | locking part of a temporarily fixed pin is latched by the hole of one of several perforated pipes, the slide movement of tubes is restrained by the temporarily fixed part. Therefore, it is possible to reliably prevent an accident in which a part of the plurality of perforated pipes is inadvertently protruded without worrying about collapse of goods during transportation. Further, since the temporary fixing pin can be slid between the pipes simply by gripping and pulling the gripping portion, it is not necessary to remove the packaging at the construction site.

特に、第2発明によれば、挿入方向にも引き抜き方向にも傾斜部が形成されているので、仮固定ピンの挿抜が極めて容易に短時間で行える。   In particular, according to the second invention, since the inclined portion is formed both in the insertion direction and in the drawing direction, the temporary fixing pin can be inserted and removed very easily in a short time.

特に、第3発明によれば、仮固定ピンが全体として一端が開放された側面視コの字状となっているので、2か所の孔で係止されていることとなり、仮固定ピンが不用意に抜け落ちるおそれが低減される。   In particular, according to the third aspect of the invention, the temporary fixing pin as a whole has a U-shaped side view with one end open, so that the temporary fixing pin is locked by two holes. The risk of inadvertent falling off is reduced.

特に、第4発明によれば、仮固定ピンの係止部が同じ高さに設けられているので、仮固定ピンの挿入と引き抜きが容易に行える。   In particular, according to the fourth aspect of the present invention, since the locking portions of the temporary fixing pins are provided at the same height, the temporary fixing pins can be easily inserted and pulled out.

特に、第5発明によれば、仮固定ピンの係止部が異なる高さに設けられているので、係止部が係止される管が異なることとなる。よって、仮固定ピンが振動等によりガタついて抜けるおそれを低減することができる。   In particular, according to the fifth aspect, since the locking portions of the temporarily fixing pins are provided at different heights, the pipes on which the locking portions are locked are different. Therefore, it is possible to reduce the possibility that the temporarily fixing pin rattles due to vibration or the like.

特に、第6発明によれば、係止部の突出する向きが左右対称となっているので、左右の係止部を加工する手間が一度で行え、加工工数を削減して仮固定ピンの製作コストを低減することができる。   In particular, according to the sixth invention, since the protruding direction of the locking portion is symmetrical, the labor for processing the left and right locking portions can be done in one time, and the number of processing steps can be reduced to produce the temporary fixing pin. Cost can be reduced.

第8発明によれば、多段式排水パイプを容易に安全に施工現場まで運搬して搬入することができるとともに、不用意に多段式排水パイプの一部が突出する事故を確実に防止するができる。   According to the eighth invention, the multi-stage drain pipe can be easily and safely transported to the construction site and carried in, and an accident in which a part of the multi-stage drain pipe protrudes can be reliably prevented. .

本実施形態に係る多段式排水パイプを傾斜した地面に設置した状態を鉛直断面で模式的に示した断面図である。It is sectional drawing which showed typically the state installed in the ground which inclined the multistage type drain pipe which concerns on this embodiment in the vertical cross section. 本発明の実施形態に係る多段式排水パイプを示す斜視図である。It is a perspective view which shows the multistage type drainage pipe which concerns on embodiment of this invention. 同上の多段式排水パイプを中間省略して示す側面図である。It is a side view which abbreviate | omits the multistage type drainage pipe same as the above and shows. 同上の多段式排水パイプの外管と中管との接合部分である継手形状を、中管部分を断面で示し、中管部分を側面図で示す部分切断断面図である。It is a partial cutaway sectional view which shows the joint shape which is a joined part of an outer pipe and a middle pipe of a multistage type drainage pipe same as the above, the middle pipe part is shown in a section, and the middle pipe part is shown in a side view. 本発明の第1実施形態に係る有孔管の仮固定ピンを示す斜視図である。It is a perspective view which shows the temporary fixing pin of the perforated tube which concerns on 1st Embodiment of this invention. 同上の有孔管の仮固定ピンを示す正面図である。It is a front view which shows the temporary fixing pin of the porous tube same as the above. 本発明の仮固定ピンの把持部の変形例を示す正面図であり、(a)が変形例1に係る仮固定ピン、(b)が変形例2に係る仮固定ピン、(c)が変形例3に係る仮固定ピンを示している。It is a front view which shows the modification of the holding part of the temporarily fixed pin of this invention, (a) is the temporarily fixed pin which concerns on the modification 1, (b) is the temporarily fixed pin which concerns on the modified example 2, (c) is deformed. The temporary fixing pin concerning Example 3 is shown. 本発明の仮固定ピンの脚部の変形例を示す正面図であり、(a)が変形例1に係る仮固定ピン、(b)が変形例2に係る仮固定ピン、(c)が変形例3に係る仮固定ピンを示している。It is a front view which shows the modification of the leg part of the temporarily fixing pin of this invention, (a) is the temporarily fixing pin which concerns on the modification 1, (b) is the temporarily fixing pin which concerns on the modification 2, (c) is deformed. The temporary fixing pin concerning Example 3 is shown. 本発明の仮固定ピンの脚部の変形例を示す正面図であり、(a)が変形例4に係る仮固定ピン、(b)が変形例5に係る仮固定ピンを示している。It is a front view which shows the modification of the leg part of the temporary fixing pin of this invention, (a) has shown the temporary fixing pin which concerns on the modification 4, (b) has shown the temporary fixing pin which concerns on the modification 5. FIG. 本実施形態に係る仮固定ピンの挿入方法を示す多段式排水パイプの拡大側面図である。It is an enlarged side view of the multistage type drainage pipe which shows the insertion method of the temporary fixing pin which concerns on this embodiment. 仮固定ピンを挿入した状態を示す多段式排水パイプの拡大断面図である。It is an expanded sectional view of the multistage type drainage pipe which shows the state where the temporary fixing pin was inserted. 本実施形態に係る多段式排水パイプの施工方法の各工程を示すフローチャートである。It is a flowchart which shows each process of the construction method of the multistage type drainage pipe which concerns on this embodiment. 同上の多段式排水パイプの施工方法における多段式排水パイプの運搬時の状態を中間省略で示す側面図である。It is a side view which shows the state at the time of conveyance of the multistage type drainage pipe in the construction method of a multistage type drainage pipe same as the above, and omits intermediate. 同上の多段式排水パイプの施工方法の架台設置工程を示す写真である。It is a photograph which shows the mount installation process of the construction method of a multistage type drain pipe same as the above. 同上の多段式パイプの施工方法の第1押出工程を示す工程説明図である。It is process explanatory drawing which shows the 1st extrusion process of the construction method of a multistage type pipe same as the above. 同上の多段式パイプの施工方法の第2押出工程を示す工程説明図である。It is process explanatory drawing which shows the 2nd extrusion process of the construction method of a multistage type pipe same as the above. 同上の多段式パイプの施工方法の第3押出工程を示す工程説明図である。It is process explanatory drawing which shows the 3rd extrusion process of the construction method of a multistage type pipe same as the above.

以下、本発明の実施形態に係る有孔管の仮固定ピン及びそれを用いた多段式排水パイプの施工方法について、図面を参照しながら詳細に説明する。   Hereinafter, a temporary fixing pin for a perforated pipe according to an embodiment of the present invention and a construction method for a multistage drainage pipe using the pin will be described in detail with reference to the drawings.

<多段式排水パイプ>
先ず、図1〜図4を用いて、本発明に係る有孔管の仮固定ピンで仮固定する有孔管として多段式排水パイプを例示して簡単に説明する。
<Multistage drainage pipe>
First, with reference to FIGS. 1 to 4, a multistage drainage pipe will be briefly described as an example of a perforated pipe temporarily fixed with a temporary fixing pin of a perforated pipe according to the present invention.

図1は、本実施形態に係る多段式パイプを傾斜した地面に設置した状態を鉛直断面で模式的に示した断面図である。図1に示すように、本実施形態に係る有孔管である多段式排水パイプ10は、鉄道、道路、宅地等の盛土や切土などの土工構造物において、セメント被覆等がされていない未被覆の土の斜面に貫入される。そして、この多段式排水パイプ10は、地下水を排水して、降雨時の地下水位の上昇を抑制するとともに、地震時の過剰間隙水圧を消散して、前記斜面の耐降雨性や耐震性を高める機能を有している。勿論、この多段式排水パイプ10は、土工構造物などの人工斜面だけでなく丘陵地や段差地などの自然斜面にも適用できることは云うまでもない。   FIG. 1 is a cross-sectional view schematically showing a state in which a multistage pipe according to this embodiment is installed on an inclined ground surface in a vertical cross section. As shown in FIG. 1, the multistage drainage pipe 10 that is a perforated pipe according to the present embodiment is not yet covered with cement or the like in earthwork structures such as embankments and cuts such as railways, roads, and residential land. Penetration into the soil slope of the covering And this multistage drain pipe 10 drains groundwater, suppresses the rise of the groundwater level at the time of rain, and dissipates excess pore water pressure at the time of an earthquake, thereby improving the rain resistance and earthquake resistance of the slope. It has a function. Of course, this multistage drainage pipe 10 can be applied not only to artificial slopes such as earthwork structures but also to natural slopes such as hills and steps.

この多段式排水パイプ10は、板厚2.3mmの高耐食性のメッキ鋼管で長さが2m程度となった大中小の管径の異なる3つの管を備えている。多段式排水パイプ10は、図2、図3に示すように、最大径の管である外管11と、中管12と、最小径の管である内管13と、内管13の先端に装着される先端キャップ14など、から構成されている。このため、中管12は、外管11に収容可能であり、内管13は、中管12に収容可能となっている。   This multistage drainage pipe 10 is provided with three pipes of large, medium and small diameters, each having a length of about 2 m made of a highly corrosion-resistant plated steel pipe having a thickness of 2.3 mm. As shown in FIGS. 2 and 3, the multistage drain pipe 10 includes an outer tube 11 that is the largest diameter tube, an intermediate tube 12, an inner tube 13 that is the smallest diameter tube, and a tip of the inner tube 13. It is comprised from the front-end | tip cap 14 etc. which are mounted | worn. For this reason, the intermediate tube 12 can be accommodated in the outer tube 11, and the inner tube 13 can be accommodated in the intermediate tube 12.

また、これらの外管11、中管12、内管13には、図3、図4等に示すように、共通してそれぞれ地下水や過剰間隙水を透水する集水孔H1が、多数穿設されており、一度に多くの排水が可能となっている。このため、近年の異常降雨にも対応することができる。   In addition, as shown in FIGS. 3 and 4, the outer pipe 11, the intermediate pipe 12, and the inner pipe 13 are provided with a large number of water collecting holes H <b> 1 through which ground water and excess interstitial water are permeable in common. It is possible to drain a lot of water at once. For this reason, it can cope with recent abnormal rainfall.

図4は、本実施形態に係る多段式排水パイプ10の外管11と中管12との接合部分である継手形状を、外管11部分を断面で示し、中管12部分を側面図で示す部分切断断面図である。図4に示すように、外管11の先端部は、テーパー部分を経て徐々に縮径されているとともに、中管12の後端部は、テーパー部分を経て徐々に拡径されている。また、伸長時に外管11の先端部と中管12の後端部とがテーパー部分において互いに嵌合するように構成されている。   FIG. 4 shows a joint shape which is a joint portion between the outer tube 11 and the middle tube 12 of the multistage drain pipe 10 according to the present embodiment, the outer tube 11 is shown in cross section, and the middle tube 12 is shown in a side view. FIG. As shown in FIG. 4, the distal end portion of the outer tube 11 is gradually reduced in diameter through a tapered portion, and the rear end portion of the intermediate tube 12 is gradually expanded in diameter through the tapered portion. Moreover, it is comprised so that the front-end | tip part of the outer tube | pipe 11 and the rear-end part of the middle pipe | tube 12 may mutually fit in a taper part at the time of expansion | extension.

同様に、中管12の先端部は、縮径されているとともに、内管13の後端部は、拡径され、伸長時に中管12の先端部と内管13の後端部とが互いに嵌り合って突没自在に嵌合する構成となっている。なお、先端とは、多段式排水パイプ10を地面に押し出して貫入させる際の進行方向(貫入方向)の管体の端部を指し、後端とは、その反対側の端部を指している(以下同じ)。   Similarly, the distal end portion of the intermediate tube 12 is reduced in diameter, and the rear end portion of the inner tube 13 is expanded in diameter, and when extended, the distal end portion of the intermediate tube 12 and the rear end portion of the inner tube 13 are mutually connected. It is the structure which fits and can be inserted and retracted freely. The front end refers to the end of the tube body in the traveling direction (penetration direction) when the multistage drain pipe 10 is pushed out and penetrated into the ground, and the rear end refers to the opposite end. (same as below).

多段式排水パイプ10は、管体同士の接合部分がこのような構成となっているため、貫入治具を用いて多段式排水パイプ10の後端が押し出されるので、外管11、中管12、内管13を順次地中に押し出して突没自在で伸縮可能となっている。また、前述のように、管同士の接合部分が、それぞれ先端が縮径されているとともに、後端が拡径されているため、管同士の嵌合が完了する長さまで、多段式排水パイプ10を伸ばして貫入することができる仕組みとなっている。本実施形態に係る多段式排水パイプ10は、伸長時において全長6m程度となる。   Since the multi-stage drainage pipe 10 has such a configuration of the joint portion between the pipes, the rear end of the multistage drainage pipe 10 is pushed out by using a penetration jig. The inner tube 13 is sequentially pushed out into the ground so that it can be extended and retracted. In addition, as described above, the joint portions of the pipes each have a reduced diameter at the tip and a diameter at the rear end, so that the multistage drainage pipe 10 has a length until the fitting between the pipes is completed. It is a mechanism that can extend and penetrate. The multistage drainage pipe 10 according to the present embodiment has a total length of about 6 m when extended.

以上説明した本実施形態に係る多段式排水パイプ10によれば、入れ子形式の押出式構造となっているので、貫入治具により多段式排水パイプ10の後端が押し出されるので、外側の径の大きな外管11から順次土の斜面への貫入が完了する仕組みとなっている。このため、貫入時のパイプと土の摩擦抵抗を分割でき、従来であれば、プレボーリングが必要な長尺な排水パイプであっても斜面の地盤を緩めることなく、設置することができる。   According to the multistage drainage pipe 10 according to the present embodiment described above, the rear end of the multistage drainage pipe 10 is pushed out by the penetrating jig because the rear end of the multistage drainage pipe 10 is pushed out. The structure is such that the penetration from the large outer pipe 11 into the soil slope is completed. For this reason, the frictional resistance between the pipe and the soil at the time of penetration can be divided, and conventionally, even a long drain pipe that requires pre-boring can be installed without loosening the ground of the slope.

また、多段式排水パイプ10によれば、貫入時の摩擦抵抗を分割できるため、大型の重機を必要とせず、狭隘な現場や重機の搬入ができない場所でも排水パイプの設置が可能である。そのうえ、従来の排水パイプより長尺な排水パイプを設置できるため、広範囲の地中水を集水して排水可能である。   Moreover, according to the multistage drainage pipe 10, since the frictional resistance at the time of penetration can be divided, a large-sized heavy machine is not required, and it is possible to install a drainage pipe even in a narrow site or where a heavy machine cannot be carried. In addition, since a drain pipe longer than the conventional drain pipe can be installed, a wide range of underground water can be collected and drained.

それに加え、多段式排水パイプ10によれば、プレボーリングを不要とすることで、排水パイプの施工コストを低減することができる。また、高耐食性のめっき鋼管を用いることにより、材料コストを低減することができるだけでなく、メンテナンス費用を低減してライフサイクルコストを削減することができる。   In addition, according to the multistage drainage pipe 10, the construction cost of the drainage pipe can be reduced by eliminating the need for preboring. Further, by using a highly corrosion-resistant plated steel pipe, not only the material cost can be reduced, but also the maintenance cost can be reduced and the life cycle cost can be reduced.

<仮固定ピン>
[第1実施形態]
次に、図5、図6を用いて、本発明の第1実施形態に係る有孔管の仮固定ピン1について説明する。前述の多段式排水パイプ10の集水孔H1に挿入されて、多段式排水パイプ10の外管11、中管12、内管13の各管がスライド移動して不用意に外管11から中管12や内管13が突出することを防止する場合を例示して説明する。図5は、本発明の第1実施形態に係る有孔管の仮固定ピン1を示す斜視図であり、図6は、図5の有孔管の仮固定ピン1を示す正面図である。
<Temporary fixing pin>
[First Embodiment]
Next, the temporary fixing pin 1 of the perforated pipe according to the first embodiment of the present invention will be described with reference to FIGS. Inserted into the water collecting hole H1 of the multi-stage drain pipe 10 described above, the outer pipe 11, the middle pipe 12 and the inner pipe 13 of the multi-stage drain pipe 10 slide and move inadvertently from the outer pipe 11. A case where the tube 12 and the inner tube 13 are prevented from protruding will be described as an example. FIG. 5 is a perspective view showing the temporary fixing pin 1 of the perforated tube according to the first embodiment of the present invention, and FIG. 6 is a front view showing the temporary fixing pin 1 of the perforated tube of FIG.

第1実施形態に係る仮固定ピン1は、ステンレスなどの線材から全ての部位が折り曲げ加工され、下端が開放された側面視コの字状の止め金具である。この仮固定ピン1は、挿抜の際に把持して掴む把持部2と、この把持部2と接続して把持部2の両端が折り返された左右一対の脚部3など、から構成されている。   The temporary fixing pin 1 according to the first embodiment is a U-shaped stopper having a U-shaped side view in which all parts are bent from a wire rod such as stainless steel and the lower end is opened. The temporary fixing pin 1 includes a grip portion 2 that is gripped and gripped at the time of insertion / extraction, and a pair of left and right leg portions 3 that are connected to the grip portion 2 and folded at both ends of the grip portion 2. .

この仮固定ピン1は、有孔管の孔である前述の多段式排水パイプ10の集水孔H1などに脚部3が差し込まれて、多段式排水パイプ10の外管11、中管12、内管13の各管のスライド移動を一時的に仮固定するものとして用いられる。   The temporary fixing pin 1 has a leg 3 inserted into the water collecting hole H1 of the multistage drainage pipe 10 which is a hole of a perforated pipe, and the outer pipe 11, the middle pipe 12 of the multistage drainage pipe 10, This is used to temporarily fix the sliding movement of each tube of the inner tube 13.

(把持部)
本実施形態に係る仮固定ピン1の把持部2は、図5、図6に示すように、直線状の把持部本体20を備えた挿抜の際に把持して掴む部位である。この把持部2は、直線状の把持部本体20に指を掛け、仮固定ピン1を引き抜いたり、把持部本体20を押圧して押し込んだりして脚部3を集水孔H1に挿抜するのに用いられる。
(Gripping part)
As shown in FIGS. 5 and 6, the holding portion 2 of the temporary fixing pin 1 according to the present embodiment is a portion that is held and gripped when the insertion / extraction is provided with the linear holding portion main body 20. This gripping part 2 puts a finger on the linear gripping part main body 20 and pulls out the temporary fixing pin 1 or presses and pushes the gripping part main body 20 to insert and remove the leg part 3 into the water collecting hole H1. Used for.

次に、図7を用いて、本発明の仮固定ピンの把持部の別の実施形態である変形例1〜3について説明する。図7は、本発明の仮固定ピンの把持部の変形例を示す正面図であり、(a)が変形例1に係る仮固定ピン、(b)が変形例2に係る仮固定ピン、(c)が変形例3に係る仮固定ピンを示している。   Next, modified examples 1 to 3 which are other embodiments of the holding portion of the temporary fixing pin of the present invention will be described with reference to FIG. FIG. 7 is a front view showing a modified example of the holding portion of the temporary fixing pin of the present invention, in which (a) is a temporary fixing pin according to the first modification, (b) is a temporary fixing pin according to the second modification, c) shows a temporary fixing pin according to the third modification.

図7に示すように、前述の把持部2の変形例としては、(a)に示す変形例1に係る把持部である半円の円弧状の把持部本体21が考えられる。また、(b)に示す変形例2に係る把持部である円形状の把持部本体22、(c)に示す変形例3に係る把持部である円形状のものを前述の直線状の把持部本体20に溶接した把持部本体23等が考えられる。このような把持部とすることで、後述の仮固定部32の長さL3に拘わらず、指の掛かり代(スペース)をとることができ、仮固定ピンの挿抜がより一層容易となる。勿論、本発明に係る把持部は、これら図示したものに限られず、把持して仮固定ピンを孔から挿抜可能な構成であればよいことは云うまでもない。   As shown in FIG. 7, as a modified example of the above-described gripping part 2, a semicircular arc-shaped gripping part body 21 which is the gripping part according to the modified example 1 shown in FIG. Further, the circular gripping part main body 22 which is a gripping part according to the modification 2 shown in FIG. 5B, and the circular gripping part which is the gripping part according to the modification 3 shown in FIG. A gripping part main body 23 welded to the main body 20 is conceivable. By setting it as such a holding part, regardless of length L3 of the temporary fixing part 32 mentioned later, the finger | toe allowance (space) can be taken and insertion / extraction of a temporary fixing pin becomes still easier. Of course, the gripping portion according to the present invention is not limited to those shown in the drawings, and it is needless to say that the gripping portion may be configured so that it can be gripped and the temporary fixing pin can be inserted and removed from the hole.

(脚部)
本実施形態に係る仮固定ピン1の脚部3は、把持部本体20を左右均等に分断する中心線を軸として線対称に左右一対設けられ、多段式排水パイプ10の集水孔H1にそれぞれ差し込まれる部位である。本実施形態に係る仮固定ピン1の脚部3と脚部3の間隔は、多段式排水パイプ10の軸方向に沿った集水孔H1の間隔と同程度(例えば、25mm程度)に設定されている。勿論、本発明に係る脚部同士の間隔は、仮固定する管の孔の間隔に合せればよく、適宜設定すればよいことは云うまでもない。
(leg)
The leg portions 3 of the temporary fixing pin 1 according to the present embodiment are provided in a pair of left and right symmetrically about a center line that equally divides the grip portion main body 20 on the left and right sides, and are respectively provided in the water collecting holes H1 of the multistage drainage pipe 10. It is the part to be inserted. The interval between the leg 3 and the leg 3 of the temporary fixing pin 1 according to the present embodiment is set to be approximately the same as the interval between the water collecting holes H1 along the axial direction of the multistage drainage pipe 10 (for example, about 25 mm). ing. Needless to say, the distance between the legs according to the present invention may be set according to the distance between the holes of the tube to be temporarily fixed, and may be set as appropriate.

各脚部3は、それぞれ先端から順に、ガイド部30と、係止部31と、仮固定部32となっている。なお、先端とは、把持部2と接続しない側面視コの字状の開放された端を指し、図示状態では下端を指す(以下同じ)。   Each leg part 3 is a guide part 30, a locking part 31, and a temporary fixing part 32 in order from the tip. Note that the tip refers to an open end that is U-shaped when viewed from the side and is not connected to the grip portion 2, and refers to the lower end in the illustrated state (the same applies hereinafter).

(ガイド部)
ガイド部30は、線材からなる直線状の部位であり、孔に挿通する際のガイドとして機能する。このため、ガイド部30の長さL1(直線部分の長さ)は、仮止めする有孔管の孔同士の間隔、即ち、重ね合わせて収容している際の多段式排水パイプ10の外管11と中管12の集水孔H1同士の外−外の間隔(最大間隔)以上あることが望ましい。また、ガイド部30の長さL1は、多段式排水パイプ10を仮止めする場合は、外管11の集水孔H1と内管13の集水孔H1の外−外の間隔以上であることがさらに好ましい。
(Guide part)
The guide part 30 is a linear part which consists of a wire, and functions as a guide at the time of inserting in a hole. For this reason, the length L1 (length of the straight line portion) of the guide portion 30 is the interval between the holes of the perforated tube to be temporarily fixed, that is, the outer tube of the multistage drainage pipe 10 when being accommodated in an overlapping manner. It is desirable that the outer-outer distance (maximum distance) between the water collecting holes H <b> 1 of the intermediate pipe 11 and the middle pipe 12 is equal to or greater. Further, the length L1 of the guide portion 30 is not less than the distance between the outside and the outside of the water collecting hole H1 of the outer pipe 11 and the water collecting hole H1 of the inner pipe 13 when the multistage drainage pipe 10 is temporarily fixed. Is more preferable.

ガイド部30の長さL1が、前記間隔以上であれば、仮固定ピン1を差し込む際に、後述の係止部31が、外管11の集水孔H1に当接する前に、直線状のガイド部30が内管13の集水孔Hに挿通されることとなる。このため、係止部31が外管11の集水孔H1に当接しても、仮固定ピン1が内管13の集水孔H1からずれるおそれがなく、仮固定ピン1をスムーズに多段式排水パイプ10の集水孔H1に挿通することができるからである。   If the length L1 of the guide part 30 is equal to or greater than the above-mentioned distance, the linear fixing pin 31 is inserted into the linear pipe before the locking part 31 described later comes into contact with the water collecting hole H1 of the outer pipe 11 when the temporary fixing pin 1 is inserted. The guide portion 30 is inserted into the water collecting hole H of the inner tube 13. For this reason, even if the locking portion 31 contacts the water collecting hole H1 of the outer tube 11, there is no possibility that the temporary fixing pin 1 is displaced from the water collecting hole H1 of the inner tube 13, and the temporary fixing pin 1 is smoothly multi-staged. This is because the water can be inserted into the water collecting hole H1 of the drain pipe 10.

(係止部)
係止部31は、ガイド部30と同一の線材からなり、ガイド部30と連続し、脚部3の間となる内側へ折り曲げられて湾曲した「くの字状」の部位である。この係止部31は、図6に示すように、前述の直線状のガイド部30の軸と傾斜し、挿入時に集水孔H1と当接する第一傾斜部31aと、後述の仮固定部32の軸と傾斜し、引き抜き時に集水孔H1と当接する第二傾斜部31bと、を有している。
(Locking part)
The locking portion 31 is made of the same wire material as the guide portion 30, is a “character-shaped” portion that is continuous with the guide portion 30 and bent and bent inward between the leg portions 3. As shown in FIG. 6, the locking portion 31 is inclined with respect to the axis of the linear guide portion 30 described above, and a first inclined portion 31 a that comes into contact with the water collecting hole H <b> 1 during insertion, and a temporary fixing portion 32 described later. And a second inclined portion 31b that comes into contact with the water collecting hole H1 when pulled out.

また、第一傾斜部31aと第二傾斜部31bが接合する係止部31の頂部31cは、ガイド部30又は仮固定部32が集水孔H1に挿通されている状態で、集水孔H1を越えない高さとなっている。即ち、ガイド部30及び仮固定部32の外側から頂部31cまでの水平距離L2は、集水孔H1の外径より大きくなっている。   Moreover, the top part 31c of the latching | locking part 31 which the 1st inclination part 31a and the 2nd inclination part 31b join is the water collection hole H1 in the state by which the guide part 30 or the temporary fixing part 32 is penetrated by the water collection hole H1. It does not exceed the height. That is, the horizontal distance L2 from the outer side of the guide part 30 and the temporary fixing part 32 to the top part 31c is larger than the outer diameter of the water collecting hole H1.

このため、仮固定ピン1を集水孔H1に挿入又は引き抜く際は、係止部31が弾性変形しながら集水孔H1を通過することとなり、一定の力を加えないと引き抜き等がされないようになっている。よって、仮固定ピン1が係止部31により各管の集水孔H1の内周面に係止可能で、且つ、挿抜自在となっている。   For this reason, when the temporary fixing pin 1 is inserted into or pulled out from the water collecting hole H1, the locking portion 31 passes through the water collecting hole H1 while being elastically deformed. It has become. Therefore, the temporary fixing pin 1 can be locked to the inner peripheral surface of the water collecting hole H1 of each pipe by the locking portion 31, and can be inserted and removed.

(仮固定部)
仮固定部32は、第二傾斜部31bと連続し、前述のガイド部30及び係止部31と同一の線材からなる直線状の部位であり、外管11、中管12、内管13の各管の集水孔H1に挿通されることで、スライド移動を一時的に拘束する機能を有している。
(Temporary fixing part)
The temporary fixing portion 32 is a linear portion that is continuous with the second inclined portion 31 b and is made of the same wire material as the guide portion 30 and the locking portion 31 described above, and includes the outer tube 11, the intermediate tube 12, and the inner tube 13. By being inserted into the water collecting hole H1 of each pipe, it has a function of temporarily restraining the slide movement.

このため、仮固定部32の長さL3は、外管11の集水孔H1と内管13の集水孔H1の外−外の間隔以上であることが好ましく、さらに前記間隔に、指を差し込むスペース(例えば、12〜14mm程度)を加えた間隔以上であることが好ましい。指を外管11と把持部2との間に差し込んで、仮固定ピン1を脱着することが容易となるからである。   For this reason, the length L3 of the temporary fixing part 32 is preferably equal to or greater than the outer-outer distance between the water collecting hole H1 of the outer tube 11 and the water collecting hole H1 of the inner tube 13, and the finger is placed at the interval. It is preferable that it is more than the space | interval which added the space (for example, about 12-14 mm) to insert. This is because it is easy to insert and remove the temporary fixing pin 1 by inserting a finger between the outer tube 11 and the grip portion 2.

次に、図8、図9を用いて、本発明の仮固定ピンの脚部の別の実施形態である変形例1〜5について説明する。図8は、本発明の仮固定ピンの脚部の変形例を示す正面図であり、(a)が変形例1に係る仮固定ピン、(b)が変形例2に係る仮固定ピン、(c)が変形例3に係る仮固定ピンを示している。図9は、本発明の仮固定ピンの脚部の変形例を示す正面図であり、(a)が変形例4に係る仮固定ピン、(b)が変形例5に係る仮固定ピンを示している。   Next, modified examples 1 to 5, which are other embodiments of the leg portion of the temporary fixing pin of the present invention, will be described with reference to FIGS. FIG. 8 is a front view showing a modification of the leg portion of the temporary fixing pin of the present invention, in which (a) is a temporary fixing pin according to Modification 1, (b) is a temporary fixing pin according to Modification 2, c) shows a temporary fixing pin according to the third modification. FIG. 9 is a front view showing a modification of the leg portion of the temporary fixing pin of the present invention, where (a) shows the temporary fixing pin according to the modified example 4 and (b) shows the temporary fixing pin according to the modified example 5. ing.

図8(a)に示す変形例1に係る脚部3が、第1実施例に係る脚部3と相違する点は、係止部の突出方向が逆で外側へ折り曲げられて湾曲した「くの字状」の係止部33となっている点だけである。   The difference between the leg 3 according to the first modification shown in FIG. 8A and the leg 3 according to the first embodiment is that the protruding direction of the locking portion is reversed and bent outward and curved. It is only the point which becomes the latching | locking part 33 of "character shape".

図8(b)に示す変形例2に係る脚部3が、第1実施例に係る脚部3と相違する点は、図示右側の脚部が全部直線状となった直線状脚部34となっている点だけである。また、図8(c)に示す変形例3に係る脚部3は、図示左側の脚部が、変形例1に係る脚部3と同一形状であり、右側の脚部が直線状脚部34となっている。   The difference between the leg 3 according to the second modification shown in FIG. 8B and the leg 3 according to the first embodiment is that the leg on the right side of the figure is straight and the leg 34 is straight. It is only a point. Further, in the leg 3 according to the modification 3 shown in FIG. 8C, the left leg in the figure has the same shape as the leg 3 according to the modification 1, and the right leg is a straight leg 34. It has become.

図9(a)に示す変形例4に係る脚部3は、左側の脚部3が内側へ湾曲した係止部31となっており、右側の脚部3が外側へ湾曲した係止部33となっている。そして、左側のガイド部30’の長さL4が、第1実施形態に係るガイド部30の長さL1より長くなっているとともに、左側の仮固定部32’の長さL5が、第1実施形態に係る仮固定部32の長さL3より短くなっている。また、右側のガイド部30”の長さL6が、第1実施形態に係るガイド部30の長さL1より短くなっているとともに、右側の仮固定部32”の長さL7が、第1実施形態に係る仮固定部32の長さL3より長くなっている。   The leg part 3 according to the modified example 4 shown in FIG. 9A is a locking part 31 in which the left leg part 3 is curved inward, and the locking part 33 in which the right leg part 3 is curved outward. It has become. The length L4 of the left guide portion 30 ′ is longer than the length L1 of the guide portion 30 according to the first embodiment, and the length L5 of the left temporary fixing portion 32 ′ is the first embodiment. It is shorter than the length L3 of the temporarily fixed part 32 which concerns on a form. Further, the length L6 of the right guide portion 30 ″ is shorter than the length L1 of the guide portion 30 according to the first embodiment, and the length L7 of the right temporary fixing portion 32 ″ is the first embodiment. It is longer than the length L3 of the temporarily fixed part 32 which concerns on a form.

図9(b)に示す変形例5に係る脚部3は、変形例4に係る脚部3と係止部の湾曲方向が相違しているだけである。即ち、変形例5に係る脚部3は、左側の脚部3が外側へ湾曲した係止部33となっており、右側の脚部3が内側へ湾曲した係止部31となっている。そして、左側のガイド部30’の長さL4が、第1実施形態に係るガイド部30の長さL1より長くなっているとともに、左側の仮固定部32’の長さL5が、第1実施形態に係る仮固定部32の長さL3より短くなっている。また、右側のガイド部30”の長さL6が、第1実施形態に係るガイド部30の長さL1より短くなっているとともに、右側の仮固定部32”の長さL7が、第1実施形態に係る仮固定部32の長さL3より長くなっている。   The leg portion 3 according to the modified example 5 shown in FIG. 9B is different from the leg portion 3 according to the modified example 4 only in the bending direction of the locking portion. That is, the leg part 3 according to the modified example 5 is a locking part 33 in which the left leg part 3 is curved outward, and the right leg part 3 is a locking part 31 curved inward. The length L4 of the left guide portion 30 ′ is longer than the length L1 of the guide portion 30 according to the first embodiment, and the length L5 of the left temporary fixing portion 32 ′ is the first embodiment. It is shorter than the length L3 of the temporarily fixed part 32 which concerns on a form. Further, the length L6 of the right guide portion 30 ″ is shorter than the length L1 of the guide portion 30 according to the first embodiment, and the length L7 of the right temporary fixing portion 32 ″ is the first embodiment. It is longer than the length L3 of the temporarily fixed part 32 which concerns on a form.

なお、仮固定部32’の長さL5は、外管11の集水孔H1と内管13の集水孔H1の外−外の間隔以上であることが好ましい。勿論、本発明に係る脚部は、これら図示したものに限られず、左右いずれか一方に係止部が形成され、複数の有孔管の孔同士を挿通する長さがあれば構わない。   The length L5 of the temporary fixing portion 32 'is preferably equal to or greater than the outer-outer distance between the water collecting hole H1 of the outer tube 11 and the water collecting hole H1 of the inner tube 13. Of course, the leg part according to the present invention is not limited to those shown in the drawings, and any locking part may be formed on either the left or right side, and the leg part may be long enough to pass through the holes of the plurality of perforated tubes.

以上、第1実施形態に係る仮固定ピン1及び別の実施形態である変形例を説明したが、把持部2の第1実施形態及びその変形例1〜3と、脚部3の第1実施形態及びその変形例1〜5組み合わせてさらに別の実施形態としてもよいことは云うまでもない。   As described above, the temporary fixing pin 1 according to the first embodiment and the modified example which is another embodiment have been described. However, the first embodiment of the grip 2 and the modified examples 1 to 3 and the first embodiment of the leg 3 are described. Needless to say, the embodiment and the modifications 1 to 5 may be combined to form still another embodiment.

<仮固定ピンの挿抜方法>
次に、図10、図11を用いて、本実施形態に係る仮固定ピン1の挿抜方法(着脱方法)について説明する。図10は、本実施形態に係る仮固定ピン1の挿入方法を示す多段式排水パイプの拡大側面図であり、図11は、仮固定ピン1を挿入(装着)した状態を示す多段式排水パイプの拡大断面図である。前述の多段式排水パイプ10の集水孔H1に第1実施形態に係る仮固定ピン1を装着して外管11、中管12、内管13の各管の相対的なスライド移動を一時的に仮固定する場合を例示して説明する。
<Temporary fixing pin insertion / extraction method>
Next, the insertion / extraction method (detachment method) of the temporarily fixing pin 1 which concerns on this embodiment is demonstrated using FIG. 10, FIG. FIG. 10 is an enlarged side view of a multistage drainage pipe showing a method of inserting the temporarily fixing pin 1 according to the present embodiment, and FIG. 11 is a multistage drainage pipe showing a state where the temporarily fixing pin 1 is inserted (mounted). FIG. The temporary fixing pin 1 according to the first embodiment is attached to the water collecting hole H1 of the multistage drain pipe 10 described above, and the relative sliding movement of each of the outer tube 11, the intermediate tube 12, and the inner tube 13 is temporarily performed. The case of temporarily fixing to will be described as an example.

先ず、管径の異なる複数の有孔管である多段式排水パイプ10の外管11、中管12、内管13の全ての管を最大径の外管11の管内に収容して一纏めにし、罫書や治具等を利用して外管11、中管12、内管13の各管の集水孔H1の位置を揃える。次に、図10、図11に示すように、外管11の軸方向に沿って隣接する2つの集水孔H1に、前述の仮固定ピン1の左右一対の脚部3、3をそれぞれ挿通する。   First, all of the outer tube 11, the middle tube 12 and the inner tube 13 of the multistage drainage pipe 10 which are a plurality of perforated tubes having different tube diameters are accommodated in the tube of the outer tube 11 having the maximum diameter, and are gathered together. The positions of the water collecting holes H1 of the outer tube 11, the intermediate tube 12, and the inner tube 13 are aligned using a ruled line, a jig, or the like. Next, as shown in FIGS. 10 and 11, the pair of left and right legs 3, 3 of the temporary fixing pin 1 is inserted into two water collecting holes H 1 adjacent to each other along the axial direction of the outer tube 11. To do.

集水孔H1に脚部3を挿通する際は、縦に揃った状態の各管の集水孔H1に前述の直線状のガイド部30(図6等参照)をまっすぐに指し込む。すると係止部31の第一傾斜部31aが外管11の集水孔H1周りの外周面に当接する際には、ガイド部30の先端は、内管13の集水孔H1に挿通されている。このため、係止部31を集水孔H1に押し込んで弾性変形させる際には、ガイド部30が内管13の集水孔H1に係止されることとなり、横方向(水平方向)に脚部3がずれることを防止することができる。つまり、ガイド部30でガイドしつつ集水孔H1に脚部3を挿入することができ、仮固定ピン1の挿入が極めて容易に短時間で行える。   When the leg portion 3 is inserted into the water collecting hole H1, the above-described linear guide portion 30 (see FIG. 6 and the like) is straightly inserted into the water collecting hole H1 of each pipe in a vertically aligned state. Then, when the first inclined portion 31a of the locking portion 31 comes into contact with the outer peripheral surface of the outer tube 11 around the water collecting hole H1, the tip of the guide portion 30 is inserted into the water collecting hole H1 of the inner tube 13. Yes. For this reason, when the locking portion 31 is pushed into the water collecting hole H1 to be elastically deformed, the guide portion 30 is locked to the water collecting hole H1 of the inner tube 13, and the legs are laterally (horizontal). It is possible to prevent the portion 3 from shifting. That is, the leg portion 3 can be inserted into the water collecting hole H1 while being guided by the guide portion 30, and the temporary fixing pin 1 can be inserted very easily in a short time.

仮固定ピン1を引き抜く場合も、係止部31の第二傾斜部31bが内管13の集水孔H1の内周面に当接させて引き抜く際には、仮固定部32が外管11や中管12の集水孔H1に挿通されている。このため、脚部3の横方向への移動が拘束されることとなり、仮固定ピン1の引き抜きが極めて容易に短時間で行える。   Even when the temporary fixing pin 1 is pulled out, when the second inclined portion 31b of the locking portion 31 is brought into contact with the inner peripheral surface of the water collecting hole H1 of the inner tube 13 and pulled out, the temporary fixing portion 32 is removed from the outer tube 11. And the water collecting hole H1 of the middle pipe 12 is inserted. For this reason, the movement of the leg 3 in the lateral direction is restricted, and the temporary fixing pin 1 can be pulled out very easily and in a short time.

[多段式排水パイプの施工方法]
次に、図10〜図17を用いて、本発明の実施形態に係る多段式排水パイプの施工方法について説明する。貫入治具を用いて前述の多段式排水パイプ10を地面(土の斜面)に貫入させて施工する場合で説明する。なお、多段式排水パイプ10の貫入に用いる重機は、油圧重機である油圧ショベルの先端にブレーカーBを取り付けた0.2m3級の重機等が好ましいが、手持ちの振動圧入装置を用いて貫入してもよい。
[Construction method of multistage drainage pipe]
Next, the construction method of the multistage drainage pipe which concerns on embodiment of this invention is demonstrated using FIGS. A description will be given of a case where the multistage drainage pipe 10 described above is inserted into the ground (soil slope) using a penetration jig. The heavy machine used for penetration of the multistage drainage pipe 10 is preferably a 0.2 m 3 class heavy machine with a breaker B attached to the tip of a hydraulic excavator, which is a hydraulic heavy machine, but is penetrated using a hand-held vibration press-fitting device. May be.

図12は、本実施形態に係る多段式排水パイプの施工方法の各工程を示すフローチャートであり、図13は、本実施形態に係る多段式排水パイプの施工方法における多段式排水パイプの運搬時の状態を中間省略で示す側面図である。   FIG. 12 is a flowchart showing each step of the construction method of the multistage drainage pipe according to the present embodiment, and FIG. 13 is a diagram of the multistage drainage pipe construction method according to the present embodiment when transporting the multistage drainage pipe. It is a side view which shows a state by middle omission.

(1)仮固定ピン装着工程
先ず、本実施形態に係る多段式排水パイプの施工方法では、図12、図13に示すように、多段式排水パイプ10を製造した工場等で仮固定ピン1を集水孔H1に挿入して多段式排水パイプ10に仮固定ピン1を装着する仮固定ピン装着工程を行う。具体的には、前述の仮固定ピンの挿入方法に従って、仮固定ピン1を集水孔H1に挿入する(図10、図11、図13参照)。
(1) Temporary fixing pin mounting process First, in the construction method of the multistage drainage pipe according to the present embodiment, as shown in FIGS. 12 and 13, the temporary fixing pin 1 is installed in a factory or the like where the multistage drainage pipe 10 is manufactured. A temporary fixing pin mounting step is performed in which the temporary fixing pin 1 is mounted on the multistage drainage pipe 10 by being inserted into the water collecting hole H1. Specifically, the temporary fixing pin 1 is inserted into the water collecting hole H1 in accordance with the above-described temporary fixing pin insertion method (see FIGS. 10, 11, and 13).

これにより、多段式排水パイプ10の外管11、中管12、内管13の各管のスライド移動を一時的に仮固定し、運搬時に外管11から中管12や内管13が不用意に突出することを防止できるとともに、従来必要であった梱包作業等を省略することができる。   As a result, the sliding movement of each of the outer tube 11, the middle tube 12 and the inner tube 13 of the multistage drainage pipe 10 is temporarily temporarily fixed, and the middle tube 12 and the inner tube 13 are not prepared from the outer tube 11 during transportation. Can be prevented, and packing operations and the like that have been conventionally required can be omitted.

(2)排水パイプ搬入工程
次に、本実施形態に係る多段式排水パイプの施工方法では、図12に示すように、前工程で一纏めにした多段式排水パイプ10を設置する施工現場まで搬送する排水パイプ搬入工程を行う(図示せず)。
(2) Drainage pipe carrying-in process Next, in the construction method of the multistage drainage pipe concerning this embodiment, as shown in FIG. 12, it conveys to the construction site where the multistage drainage pipe 10 put together in the previous process is installed. A drain pipe carrying-in process is performed (not shown).

具体的には、搬送車両で搬送した後、多段式排水パイプ10を搬送車両から揚重装置等を用いて荷降ろしし、手運びや台車等を用いて設置位置まで搬送する。このため、梱包を外す作業も必要ない。   Specifically, after being transported by the transport vehicle, the multistage drainage pipe 10 is unloaded from the transport vehicle using a lifting device or the like, and transported to the installation position using hand transport or a carriage. For this reason, the work which removes a packing is also unnecessary.

(3)位置決め工程
次に、本実施形態に係る多段式排水パイプの施工方法では、図12に示すように、多段式排水パイプ10の貫入位置を位置決めする位置決め工程を行う(図示せず)。具体的には、本工程では、地盤調査や測量等により多段式排水パイプ10を斜面に貫入させる位置、貫入角度等を特定し、マーキング等により目印を付ける。
(3) Positioning process Next, in the construction method of the multistage drainage pipe according to this embodiment, as shown in FIG. 12, a positioning process for positioning the penetration position of the multistage drainage pipe 10 is performed (not shown). Specifically, in this process, the position where the multistage drainage pipe 10 penetrates into the slope, the penetration angle, etc. are specified by ground survey, surveying, etc., and a mark is given by marking or the like.

(4)架台設置工程
次に、本実施形態に係る多段式排水パイプの施工方法では、図12に示すように、多段式排水パイプ10を貫入させる作業の事前準備として、架台を組み立てて設置する架台設置工程を行う。図14は、本実施形態に係る多段式排水パイプの施工方法の架台設置工程を示す写真である。図14に示すように、具体的には、本工程では、クランプ等を用いて単管パイプを鳥居状に組むとともに、倒れないように斜面に対して控えの単管パイプを組み、その控えのパイプがずれないように支保工で支える。この架台の鳥居状の横パイプにより多段式排水パイプ10の貫入方向の規定が容易となる。
(4) Base installation step Next, in the construction method of the multistage drainage pipe according to the present embodiment, as shown in FIG. 12, the base is assembled and installed as a preliminary preparation for the work of penetrating the multistage drainage pipe 10. Perform the gantry installation process. FIG. 14 is a photograph showing a gantry installation process of the construction method of the multistage drainage pipe according to the present embodiment. As shown in FIG. 14, specifically, in this step, a single pipe is assembled in a torii-like shape using a clamp or the like, and a single pipe is set against the slope so as not to fall down. Support the pipes so that they do not slip. It is easy to define the penetration direction of the multistage drainage pipe 10 by the torii-shaped horizontal pipe of the gantry.

(5)仮固定ピン引き抜き工程
設置位置において、前述の仮固定ピンの挿抜方法に従って把持部2に指を引っ掛けて仮固定ピン1を引き抜く。これにより、多段式パイプ10はスライド可能になり、貫入が可能になる。
(5) Temporary fixing pin extraction step At the installation position, the temporary fixing pin 1 is extracted by hooking a finger on the grip portion 2 in accordance with the above-described method of inserting and extracting the temporary fixing pin. Thereby, the multistage pipe 10 becomes slidable, and penetration becomes possible.

(6)第1押出工程
次に、本実施形態に係る多段式パイプの施工方法では、図12に示すように、ブレーカーBに装着した貫入治具を用いて、仮固定ピン1が引き抜かれた多段式排水パイプ10全体を斜面に貫入させる第1押出工程を行う。図15は、本実施形態に係る多段式パイプの施工方法の第1押出工程を示す工程説明図である。本工程では、図15に示すように、ブレーカーBでチゼルTを振動させつつ、チゼルTに装着された貫入治具で多段式排水パイプ10全体を押し出して斜面に貫入させる。
(6) 1st extrusion process Next, in the construction method of the multistage type pipe concerning this embodiment, as shown in FIG. 12, the temporary fixing pin 1 was pulled out using the penetration jig | tool with which the breaker B was mounted | worn. A first extrusion process is performed for penetrating the entire multistage drainage pipe 10 into the slope. FIG. 15 is a process explanatory view showing a first extrusion process of the construction method of the multistage pipe according to the present embodiment. In this step, as shown in FIG. 15, while the chisel T is vibrated by the breaker B, the entire multistage drainage pipe 10 is pushed out by the penetration jig attached to the chisel T and penetrated into the slope.

(7)第2押出工程
次に、本実施形態に係る多段式パイプの施工方法では、図12に示すように、押出プレートを装着した貫入治具Jを用いて、中管12及び内管13を斜面にさらに貫入させる第2押出工程を行う。図16は、本実施形態に係る多段式パイプの施工方法の第2押出工程を示す工程説明図である。
(7) Second Extrusion Step Next, in the multistage pipe construction method according to the present embodiment, as shown in FIG. 12, the intermediate tube 12 and the inner tube 13 are used by using a penetration jig J equipped with an extrusion plate. The 2nd extrusion process which penetrates further into a slope is performed. FIG. 16 is a process explanatory view showing a second extrusion process of the construction method of the multistage pipe according to the present embodiment.

本工程では、図16に示すように、ブレーカーBでチゼルTを振動させつつ、チゼルTに装着された貫入治具Jの押出プレートで中管12の後端部を押圧する。それと同時に、貫入治具Jの押出ナットで内管13の後端部を押し出す。これにより、中管12と内管13を斜面の奥深くにさらに貫入させる。   In this step, as shown in FIG. 16, while the chisel T is vibrated by the breaker B, the rear end portion of the intermediate tube 12 is pressed by the extrusion plate of the penetration jig J attached to the chisel T. At the same time, the rear end portion of the inner tube 13 is pushed out by the extrusion nut of the penetration jig J. Thereby, the middle pipe 12 and the inner pipe 13 are further penetrated deep into the slope.

(8)第3押出工程
次に、本実施形態に係る多段式パイプの施工方法では、図12に示すように、押出プレートを撤去した貫入治具Jを用いて、多段式排水パイプ10の内管13を斜面にさらに貫入させる第3押出工程を行う。図17は、本実施形態に係る多段式パイプの施工方法の第3押出工程を示す工程説明図である。
(8) Third Extrusion Step Next, in the construction method of the multistage pipe according to the present embodiment, as shown in FIG. 12, using the penetration jig J from which the extrusion plate has been removed, A third extrusion process is performed to further penetrate the pipe 13 into the slope. FIG. 17 is a process explanatory view showing a third extrusion process of the construction method of the multistage pipe according to the present embodiment.

本工程では、図17に示すように、ブレーカーBでチゼルTを振動させつつ、チゼルTに装着された貫入治具Jの押出ナットで内管13の後端部を押し出して、内管13を所定の深さまで斜面に貫入させる。   In this step, as shown in FIG. 17, while the chisel T is vibrated by the breaker B, the rear end portion of the inner pipe 13 is pushed out by the extrusion nut of the penetration jig J attached to the chisel T, and the inner pipe 13 is It penetrates into the slope to a predetermined depth.

本工程が終了すれば、設置した架台等を撤去し、後片付けをすることにより、多段式排水パイプ10の設置作業が全て終了する。   When this step is completed, the installation work of the multistage drainage pipe 10 is completed by removing the installed base and cleaning up.

以上説明した本実施形態に係る仮固定ピン1及び仮固定ピン1を用いた多段式パイプの施工方法によれば、多段式排水パイプ等を一纏めにする際に仮固定ピン1を一か所に差し込むだけで梱包等の必要がない。また、仮固定ピン1の係止部31が内管13の集水孔H1に係止されているとともに、仮固定部32で外管11〜内管13の管同士のスライド移動が拘束されている。このため、運搬時の多段式排水パイプ10の荷崩れの心配がなく運搬時に外管11から中管12や内管13が不用意に突出することを防止することができる。その上、仮固定ピン1は、把持部2を把持して引き抜くだけで、管同士のスライド移動が可能となるため、施工現場での梱包を外す作業も必要ない。   According to the temporary fixing pin 1 and the multistage pipe construction method using the temporary fixing pin 1 according to the present embodiment described above, the temporary fixing pin 1 is placed in one place when the multistage drainage pipes and the like are grouped together. Just plug it in and there is no need for packing. In addition, the locking portion 31 of the temporary fixing pin 1 is locked in the water collecting hole H1 of the inner tube 13, and the sliding movement between the tubes of the outer tube 11 to the inner tube 13 is restricted by the temporary fixing portion 32. Yes. For this reason, there is no fear of collapse of the multistage drainage pipe 10 during transportation, and it is possible to prevent the middle tube 12 and the inner tube 13 from inadvertently protruding from the outer tube 11 during transportation. In addition, the temporary fixing pin 1 can be slid between the pipes simply by gripping and pulling the grip portion 2, so that it is not necessary to remove the packaging at the construction site.

以上、本発明の実施形態に係る仮固定ピン1及び仮固定ピン1を用いた多段式パイプの施工方法について詳細に説明したが、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ない。よって、例示した実施形態によって本発明の技術的範囲が限定的に解釈されてはならないものである。   As mentioned above, although the construction method of the multistage pipe using the temporary fixing pin 1 and the temporary fixing pin 1 according to the embodiment of the present invention has been described in detail, any of the above-described or illustrated embodiments implements the present invention. It is only what showed one embodiment actualized in that case. Therefore, the technical scope of the present invention should not be limitedly interpreted by the illustrated embodiments.

特に、ステンレスの線材からなる仮固定ピンを例示して説明したが、他の鋼材やその他の金属又は樹脂等から構成されていても構わない。要するに、本発明に係る仮固定ピンは、弾性変形可能で有孔管のスライド移動を拘束できる強度を有していればどのような素材から構成されていてもよい。   In particular, the temporary fixing pin made of a stainless wire has been described as an example, but it may be made of other steel materials, other metals, resins, or the like. In short, the temporary fixing pin according to the present invention may be made of any material as long as it has the strength that can be elastically deformed and can restrain the sliding movement of the perforated tube.

1:仮固定ピン
2:把持部
20、21、22、23:把持部本体
3:脚部
30、30’:ガイド部
31、33:係止部
31a:第一傾斜部
31b:第二傾斜部
31c:頂部
32、32’:仮固定部
34:直線状部
10:多段式排水パイプ
11:外管
12:中管
13:内管
H1:集水孔
B:ブレーカー
T:チゼル
J:貫入治具
1: Temporary fixing pin 2: Grasping part 20, 21, 22, 23: Grasping part main body 3: Leg part 30, 30 ': Guide part 31, 33: Locking part 31a: First inclined part 31b: Second inclined part 31c: Top part 32, 32 ': Temporary fixing part 34: Linear part 10: Multistage drainage pipe 11: Outer pipe 12: Middle pipe 13: Inner pipe H1: Water collecting hole B: Breaker T: Chisel J: Penetration jig

Claims (8)

管径の異なる複数の有孔管の全ての管を最大径の管内に挿入した状態で、前記複数の有孔管の全ての管の孔に挿通されることで前記復数の有孔管同士のスライド移動を一時的に仮固定する挿抜自在の有孔管の仮固定ピンであって、
挿抜の際に把持して掴む把持部と、前記把持部と接続してその一端が折り返された脚部と、を備え、
前記脚部は、前記把持部と接続しない先端に設けられて前記複数の有孔管の各管の孔に挿通する際のガイドとなる直線状のガイド部と、前記ガイド部と接続して前記複数の有孔管のいずれかの管の前記孔に係止される係止部と、前記係止部と接続して前記複数の有孔管の全ての管に亘って挿通される長さを有する直線状の仮固定部と、を有すること
を特徴とする有孔管の仮固定ピン。
In a state where all of the plurality of perforated pipes having different diameters are inserted into the maximum diameter pipe, the plurality of perforated pipes are inserted into the holes of all of the plurality of perforated pipes. A temporary fixing pin of a removable perforated tube that temporarily fixes the sliding movement of
A gripping part that grips and grips at the time of insertion / extraction, and a leg part that is connected to the gripping part and folded at one end thereof,
The leg portion is provided at a distal end that is not connected to the gripping portion, and is connected to the guide portion and a linear guide portion that serves as a guide when being inserted into a hole of each of the plurality of perforated tubes. A locking portion locked to the hole of any one of the plurality of perforated tubes, and a length inserted through all the tubes of the plurality of perforated tubes connected to the locking portion. A perforated tube temporary fixing pin, characterized by having a linear temporary fixing portion.
前記係止部は、前記ガイド部と前記仮固定部の線材の軸と傾斜し、挿入時に前記孔と当接する第一傾斜部と、前記ガイド部と前記仮固定部の線材の軸と傾斜し、引き抜き時に前記孔と当接する第二傾斜部と、を有すること
を特徴とする請求項1に記載の有孔管の仮固定ピン。
The locking portion is inclined with respect to the shaft of the wire rod of the guide portion and the temporary fixing portion, and is inclined with respect to the axis of the wire rod of the guide portion and the temporary fixing portion, the first inclined portion contacting the hole during insertion. The perforated tube temporary fixing pin according to claim 1, further comprising: a second inclined portion that comes into contact with the hole when pulled out.
前記脚部は、前記把持部の両端が折り返されて左右一対設けられ、
全体として一端が開放された側面視コの字状となっていること
を特徴とする請求項1又は2に記載の有孔管の仮固定ピン。
The leg portion is provided with a pair of right and left by folding both ends of the grip portion,
3. The temporary fixing pin for a perforated tube according to claim 1, wherein the pin is a U-shaped side view with one end opened as a whole.
前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記脚部の開放された一端からの距離が同じ位置に形成されていること
を特徴とする請求項3に記載の有孔管の仮固定ピン。
The said latching | locking part is provided in the said left-right paired leg part, respectively, The distance from the open | released one end of the said leg part is formed in the same position, The existence of Claim 3 characterized by the above-mentioned. Temporary fixing pin for hole tube.
前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記脚部の開放された一端からの距離が異なる位置に形成されていること
を特徴とする請求項3に記載の有孔管の仮固定ピン。
The said latching | locking part is respectively provided in the said left-right paired leg part, and is formed in the position where the distance from the open | released one end of the said leg part differs. Temporary fixing pin for hole tube.
前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記係止部の前記線材の軸から突出する向きが左右対称となっていること
を特徴とする請求項3〜5いずれか1項に記載の有孔管の仮固定ピン。
The said latching | locking part is provided in the said left-right paired leg part, respectively, and the direction which protrudes from the axis | shaft of the said wire rod of the said latching | locking part is left-right symmetric. A temporary fixing pin for a perforated tube according to claim 1.
前記係止部は、前記左右一対の脚部にそれぞれ設けられ、且つ、前記係止部の前記線材の軸から突出する向きが左右非対称となっていること
を特徴とする請求項3又は5に記載の有孔管の仮固定ピン。
The locking portion is provided on each of the pair of left and right legs, and the direction of the locking portion protruding from the shaft of the wire is asymmetrical to the left and right. Temporary fixing pin of the perforated tube as described.
排水用の孔が穿設された管径の異なる複数の有孔管がそれぞれ突没自在に嵌合された多段式排水パイプを地中に貫入する多段式排水パイプの施工方法において、
請求項1〜7のいずれか1項に記載の有孔管の仮固定ピンを用いて、運搬前に前記多段式排水パイプの全ての管の孔に前記脚部を挿通し、前記係止部を複数の有孔管のいずれかの管の前記孔に係止して、
前記多段式排水パイプを地中に貫入する直前に前記仮固定ピンを引き抜くことを
特徴とする多段式排水パイプの施工方法。
In the construction method of a multistage drainage pipe that penetrates into the ground a multistage drainage pipe in which a plurality of perforated pipes with different diameters with holes for drainage are fitted into each other,
Using the temporary fixing pin of the perforated pipe according to any one of claims 1 to 7, the leg section is inserted into the holes of all the pipes of the multistage drainage pipe before transportation, and the locking section Is locked in the hole of any one of the plurality of perforated pipes,
The construction method of a multistage drainage pipe, wherein the temporary fixing pin is pulled out immediately before the multistage drainage pipe penetrates into the ground.
JP2017062935A 2017-03-28 2017-03-28 Temporary fixing pin for perforated pipe and construction method for multi-stage drainage pipe using it Active JP6916019B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017062935A JP6916019B2 (en) 2017-03-28 2017-03-28 Temporary fixing pin for perforated pipe and construction method for multi-stage drainage pipe using it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017062935A JP6916019B2 (en) 2017-03-28 2017-03-28 Temporary fixing pin for perforated pipe and construction method for multi-stage drainage pipe using it

Publications (2)

Publication Number Publication Date
JP2018165445A true JP2018165445A (en) 2018-10-25
JP6916019B2 JP6916019B2 (en) 2021-08-11

Family

ID=63922473

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017062935A Active JP6916019B2 (en) 2017-03-28 2017-03-28 Temporary fixing pin for perforated pipe and construction method for multi-stage drainage pipe using it

Country Status (1)

Country Link
JP (1) JP6916019B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750657A (en) * 2019-03-12 2019-05-14 中国电建集团中南勘测设计研究院有限公司 A kind of slope drainage system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6036416U (en) * 1983-08-16 1985-03-13 三菱樹脂株式会社 perforated drain pipe
JPH0365739U (en) * 1989-10-31 1991-06-26
EP0505218A1 (en) * 1991-03-22 1992-09-23 Westpile Limited Improvements in venting of landfill and control of leachate
JPH08196327A (en) * 1995-01-20 1996-08-06 Lucky Corp:Kk Hairpin
JPH10159078A (en) * 1996-11-27 1998-06-16 Asanumagumi:Kk Drain pipe and dewatering method of soft ground
JP2005074053A (en) * 2003-09-02 2005-03-24 Lucky Corp:Kk Hair pin
JP2005194806A (en) * 2004-01-09 2005-07-21 Ashimori Ind Co Ltd Drain material and its manufacturing method
JP2013036216A (en) * 2011-08-08 2013-02-21 Sun Quest:Kk Reinforcement method of retaining wall
JP2014119019A (en) * 2012-12-17 2014-06-30 Rinnai Corp Connection mechanism
JP2015166519A (en) * 2014-03-03 2015-09-24 日鐵住金建材株式会社 Drain pipe and driving method therefor

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6036416U (en) * 1983-08-16 1985-03-13 三菱樹脂株式会社 perforated drain pipe
JPH0365739U (en) * 1989-10-31 1991-06-26
EP0505218A1 (en) * 1991-03-22 1992-09-23 Westpile Limited Improvements in venting of landfill and control of leachate
JPH08196327A (en) * 1995-01-20 1996-08-06 Lucky Corp:Kk Hairpin
JPH10159078A (en) * 1996-11-27 1998-06-16 Asanumagumi:Kk Drain pipe and dewatering method of soft ground
JP2005074053A (en) * 2003-09-02 2005-03-24 Lucky Corp:Kk Hair pin
JP2005194806A (en) * 2004-01-09 2005-07-21 Ashimori Ind Co Ltd Drain material and its manufacturing method
JP2013036216A (en) * 2011-08-08 2013-02-21 Sun Quest:Kk Reinforcement method of retaining wall
JP2014119019A (en) * 2012-12-17 2014-06-30 Rinnai Corp Connection mechanism
JP2015166519A (en) * 2014-03-03 2015-09-24 日鐵住金建材株式会社 Drain pipe and driving method therefor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750657A (en) * 2019-03-12 2019-05-14 中国电建集团中南勘测设计研究院有限公司 A kind of slope drainage system
CN109750657B (en) * 2019-03-12 2023-11-07 中国电建集团中南勘测设计研究院有限公司 Slope drainage system

Also Published As

Publication number Publication date
JP6916019B2 (en) 2021-08-11

Similar Documents

Publication Publication Date Title
JP6309310B2 (en) Drainage pipe and its driving method
EP3298201B1 (en) System for supporting a ditch
CN101851922B (en) Method for eliminating underground anchor rope/rod by using all casing drill
US2074003A (en) Method of culverting embankments
JP2018165445A (en) Temporary fixing pin of perforated pipe and method of constructing multi-stage drain pipe using the same
JP2009046832A (en) Pile device for foundation, vertical connecting means for use in it, and method for driving and installing foundation pile
CN208579946U (en) A kind of complete soil column sample collector
JP5674582B2 (en) Cast-in-place concrete pile construction method and concrete recovery equipment
CN212454485U (en) Novel soft soil supporting extrusion type grouting anchor cable
JP6681931B2 (en) Drainage pipe and its driving method
KR101527431B1 (en) Block anchor with pre-bored multi-grout and method for constructing thereof
CN107083773A (en) Detain tubular type pile extractor
JP3486824B2 (en) Sliding sheet pile and soil retaining method using it
CN104790397A (en) Sleeve method damaged pile treatment and construction method and construction device using same
JP6747959B2 (en) Penetration jig for multistage pipe and penetration method for multistage pipe
US6238140B1 (en) Method for laying tile or pipe underground
ES2424805T3 (en) Tuning device to trench trenches
JP5904585B2 (en) Pile concrete placement method
CN217629848U (en) Protective arm of reinforcement cage of rotary excavating pile
JP6465511B2 (en) Plucking machine chucking mechanism and pile removal method
JP3761173B2 (en) Connecting device for pipes in excavation grooves
JP4322795B2 (en) Long tip receiving method
KR101649210B1 (en) Steel pipe wall temporary construction
JP2009121218A (en) Pile head separating method
CN208669324U (en) Steel tube component is used in a kind of construction of pipe curtain

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200120

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201215

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20201222

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210222

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210713

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210715

R150 Certificate of patent or registration of utility model

Ref document number: 6916019

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150