JP2017203284A - Bridge widening method - Google Patents

Bridge widening method Download PDF

Info

Publication number
JP2017203284A
JP2017203284A JP2016094852A JP2016094852A JP2017203284A JP 2017203284 A JP2017203284 A JP 2017203284A JP 2016094852 A JP2016094852 A JP 2016094852A JP 2016094852 A JP2016094852 A JP 2016094852A JP 2017203284 A JP2017203284 A JP 2017203284A
Authority
JP
Japan
Prior art keywords
floor slab
holding
new
existing
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016094852A
Other languages
Japanese (ja)
Other versions
JP6717656B2 (en
Inventor
雅司 鍋谷
Masashi Nabeya
雅司 鍋谷
知義 小野
Tomoyoshi Ono
知義 小野
哲史 勝見
Tetsushi Katsumi
哲史 勝見
達也 斎藤
Tatsuya Saito
達也 斎藤
真也 北川
Shinya Kitagawa
真也 北川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sato Kogyo Co Ltd
Original Assignee
Sato Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sato Kogyo Co Ltd filed Critical Sato Kogyo Co Ltd
Priority to JP2016094852A priority Critical patent/JP6717656B2/en
Publication of JP2017203284A publication Critical patent/JP2017203284A/en
Application granted granted Critical
Publication of JP6717656B2 publication Critical patent/JP6717656B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a bridge widening method which can shorten the construction period.SOLUTION: A bridge widening method for bridges which have concrete floor slabs arranged to span abutments or piers, comprises: a preloading process which holds at least one side of an existing floor slab 11, the side facing a new floor slab 12 and being applied with upward load; a forming process of the new floor slab 12, in which concrete is cast while the new floor slab 12 for the widening is placed adjacently to the existing floor slab 11 with the level held practically the same as the holding level of the existing floor slab 11 set during the preloading process; and a hold-release process which releases the holding of the existing floor slab 11 and the new floor slab 12 after casting concrete.SELECTED DRAWING: Figure 7

Description

本発明は、RC床版橋の拡幅を図る橋梁拡幅工法に関する。   The present invention relates to a bridge widening method for widening an RC floor slab bridge.

橋梁として、鉄道橋のほか道路橋がある。後者の道路橋において拡幅が必要な場合がある。その場合、交通遮断や走行規制をすることなく、既設床版において一般車の走行を許容しながら拡幅する方法を採ることの要請が高い。   There are road bridges as well as railway bridges. The latter road bridge may require widening. In that case, there is a high demand for adopting a method of widening the existing floor slab while permitting the traveling of a general vehicle without blocking traffic or restricting traveling.

従来は、既設床版での車両走行による活荷重およびそれに伴う振動を考慮して、既設床版に対し、新設床版を離隔して設置する方法を採るのが一般である。   Conventionally, in consideration of a live load caused by traveling of a vehicle on an existing floor slab and vibration associated therewith, a method of installing a new floor slab apart from an existing floor slab is generally employed.

この従来の道路及び道路橋の拡幅例を、図1〜図4を参照しながら説明する。
まず、図1のように、(1)橋梁の前後の道路1及び2の拡幅を行うものである。道路橋3の既設床版11は、その自重及び車両走行による活荷重が作用し中央部が下方に撓み、車両走行の都度、振動が生じる。
An example of widening the conventional road and road bridge will be described with reference to FIGS.
First, as shown in FIG. 1, (1) the roads 1 and 2 before and after the bridge are widened. The existing floor slab 11 of the road bridge 3 is subjected to its own weight and a live load due to vehicle travel, and the central portion bends downward, causing vibration every time the vehicle travels.

次に、図2のように、(2)既設床版11から離隔して、新設の一次床版12の型枠と鉄筋を設置する。この場合、一次床版12の型枠と鉄筋は、型枠支保工4(矢印で概念的に図示した。)により支保して、一次床版12の型枠の平面維持を図る。   Next, as shown in FIG. 2, (2) the new primary floor slab 12 and the rebar are installed separately from the existing floor slab 11. In this case, the formwork and reinforcing bars of the primary floor slab 12 are supported by the formwork support 4 (illustrated schematically by arrows) to maintain the plane of the formwork of the primary floor slab 12.

その後、(3)この状態で、一次床版12の型枠内にコンクリート打設を行い、所定の強度が発現するまで養生を図る。   Thereafter, (3) In this state, concrete is placed in the mold of the primary floor slab 12, and curing is performed until a predetermined strength is developed.

次いで、型枠支保工4による支保を解放する。これによって、図3のように、一次床版12は自重により下方に撓む。   Next, the support by the mold support 4 is released. Thereby, as shown in FIG. 3, the primary floor slab 12 is bent downward by its own weight.

最後に、図4のように(4)それぞれ下方に撓んでいる既設床版11と一次床版12との間に二次床版13の型枠を設置し、その内部にコンクリート打設を行い、その養生を図る。   Finally, as shown in FIG. 4, (4) the formwork of the secondary floor slab 13 is installed between the existing floor slab 11 and the primary floor slab 12 that are bent downward, and concrete is placed in the form. , Plan the curing.

最終的に、(5)所定の強度の発現を待って拡幅橋部分の供用を行う。   Finally, (5) waiting for the expression of a predetermined strength, the wide bridge part is used.

この従来例では、一次床版12内へのコンクリート打設後に、その強度発現を待ってから型枠支保工4を撤去して自重を開放し、さらにその後のクリープや乾燥収縮がある程度収まるのを待つ必要があるために、二次床版13内部へのコンクリート打設開始時点まで、通常は3か月程度要している。   In this conventional example, after casting concrete into the primary floor slab 12, after waiting for the strength to be developed, the formwork supporter 4 is removed to release its own weight, and the subsequent creep and drying shrinkage can be accommodated to some extent. Since it is necessary to wait, it usually takes about three months until the start of placing concrete into the secondary floor slab 13.

特許第3806951号公報Japanese Patent No. 3806951

しかし、可能な限り早急に供用したいとの要望は多い。
そこで、本発明の主たる課題は、既設床版側からの影響を防止しながら、工期の短縮を図ることができる拡幅工法を提供することにある。
However, there are many requests to use it as soon as possible.
Then, the main subject of this invention is providing the widening method which can aim at shortening of a construction period, preventing the influence from the existing floor slab side.

上記課題を解決するための本発明は、橋台又は橋脚間上に跨がってコンクリート床版が配置された橋梁の拡幅に際し、
既設床版の少なくとも新設床版側を、上向きに荷重をかけて保持するプレロード工程、
拡幅用新設床版の型枠を、前記既設床版に隣接させて、そのレベルを前記プレロード工程における既設床版の保持レベルと実質的に同一に保持する保持工程、
保持工程と共に又は保持工程後に拡幅用新設床版の型枠内にコンクリート打設を行う新設床版形成工程、
前記新設床版形成工程後に、前記既設床版の保持及び前記新設床版の保持を解放する保持解放工程、
を有して橋梁の拡幅を図る工法である。
The present invention for solving the above-mentioned problems is in the case of widening a bridge in which a concrete floor slab is arranged across between abutments or piers,
A preloading process in which at least the new floor slab side of the existing floor slab is held with an upward load;
A holding step of holding the formwork of the new floor slab for widening adjacent to the existing floor slab and holding the level thereof substantially the same as the holding level of the existing floor slab in the preloading step;
A new floor slab forming process in which concrete is placed in the formwork of the new floor slab for widening together with or after the holding process;
A holding release step for releasing the holding of the existing floor slab and the holding of the new floor slab after the new floor slab forming step;
It is a construction method to widen the bridge with

前述のように、道路橋3の既設床版11には、その自重が作用することにより下方に撓む。また、拡幅工事過程で例えば車両交通を許容する場合には、車両走行による活荷重が作用し、車両走行の都度、振動が生じる。その結果、仮に、既設床版11に新設床版を隣接して設置しコンクリート打設を行うと、車両走行の都度、生じた振動が新設床版側に伝搬し、コンクリート打設・養生過程でコンクリート版の品質に悪影響を与えることがある。
しかるに、本発明では、既設床版の少なくとも新設床版側を、上向きに荷重をかけて保持するプレロード工程を有する。したがって、拡幅工事過程で例えば車両交通を許容する場合であっても、車両走行による活荷重が作用して振動が生じ、その影響が新設床版側へ伝搬することを防止できる。
As described above, the existing floor slab 11 of the road bridge 3 is bent downward by its own weight. In addition, for example, when vehicle traffic is permitted during the widening work, a live load is applied due to vehicle travel, and vibration occurs every time the vehicle travels. As a result, if a new floor slab is installed adjacent to the existing floor slab 11 and concrete placement is performed, the generated vibration propagates to the new floor slab each time the vehicle travels, and during the concrete placement and curing process. May adversely affect the quality of the concrete plate.
However, the present invention includes a preloading step in which at least the new floor slab side of the existing floor slab is held with an upward load. Therefore, even when, for example, vehicle traffic is permitted during the widening work, it is possible to prevent the live load caused by the vehicle running from causing vibration and causing the influence to propagate to the new floor slab side.

他方で、本発明は、拡幅用新設床版の型枠を、前記既設床版に隣接させて、そのレベルを前記プレロード工程における既設床版の保持レベルと実質的に同一に保持し、この保持工程後に拡幅用新設床版の型枠内にコンクリート打設を行うことにより新設床版を形成する工程を有する。
したがって、新設床版形成工程後に、前記既設床版の保持及び前記新設床版の保持を解放する段階でも同様に下方に撓み、道路面の均一性を保持できる。
On the other hand, according to the present invention, the formwork of the new floor slab for widening is placed adjacent to the existing floor slab, and the level thereof is held substantially the same as the holding level of the existing floor slab in the preloading process. It has the process of forming a new floor slab by performing concrete placement in the formwork of the new floor slab for widening after a process.
Therefore, after the new floor slab forming step, even when the holding of the existing floor slab and the holding of the new floor slab are released, it can be similarly bent downward to maintain the road surface uniformity.

本発明において、前記既設床版と前記新設床版とに跨がる根太材により支保するとともに、その支保部が橋の長手方向に複数ある形態を採るのが望ましい。
既設床版と新設床版とに跨がる根太材により支保すると、既設床版から新設床版への振動に、新設床版が追従するようになり、既設床版のプレロードと、並びに既設床版及び新設床版の実質的な同一レベルの保持との組み合せ効果が顕著に現われることになる。
In the present invention, it is desirable to take a form in which a plurality of support portions are provided in the longitudinal direction of the bridge while being supported by a joist straddling the existing floor slab and the newly installed floor slab.
When supported by the joist straddling the existing floor slab and the new floor slab, the new floor slab follows the vibration from the existing floor slab to the new floor slab, preloading the existing floor slab, and the existing floor slab. The combined effect of maintaining the same level of the plate and the newly installed floor slab will be prominent.

前記既設床版と前記新設床版とに跨がる根太材により支保するとともに、その支保部が橋の長手方向に複数あり、
既設床版の少なくとも新設床版側を、上向きに荷重をかけて保持するプレロード工程において、前記根太材の複数を支承する保持材の下方からジャッキアップしてプレロードを図る形態が好適である。
プレロードと、既設床版と新設床版とに跨がる根太材による支保とを、それぞれ別に行うことも可能であるが、前記根太材の複数を支承する保持材の下方からジャッキアップしてプレロードを図るようにすると、プレロード過程及び新設床版の設置・コンクリート打設・養生過程における既設床版と新設床版との一体性を高め相手側への影響を極力防止でき、新設床版形成工程後に、既設床版の保持及び新設床版の保持を解放する段階で、一体性の高い道路を形成できる。
While supporting by the joist straddling the existing floor slab and the newly installed floor slab, there are a plurality of support portions in the longitudinal direction of the bridge,
In a preloading step in which at least a new floor slab side of an existing floor slab is held by applying an upward load, a form in which jacking up from below the holding material for supporting the plurality of joists is performed for preloading.
It is possible to preload and support with joist timber straddling the existing slab and new slab separately, but jack up from the lower part of the retainer that supports the joist timber and preload By doing so, it is possible to improve the integrity of the existing floor slab and the new floor slab in the preloading process, installation of the new floor slab, concrete placement, and curing process, and to prevent the influence on the other side as much as possible. Later, in the stage of releasing the holding of the existing floor slab and the holding of the new floor slab, a highly integrated road can be formed.

新設床版形成工程後において、地覆及び高欄を形成することができる。   After the new floor slab forming step, the ground cover and the railing can be formed.

以上のとおり、本発明によれば、二次床版の設置を行わないので、従来例のように、一次床版12の型枠内へのコンクリート打設後に、その強度発現を待って二次床版の型枠内へのコンクリート打設時点までに要する期間の必要がなく、施工期間を短縮できるとともに、その短縮期間が占める全施工期間に対して占める割合には大きなものがある。その結果、橋梁の全面供用を早期に開始できるようになる。   As described above, according to the present invention, since the secondary floor slab is not installed, after the concrete is placed in the formwork of the primary floor slab 12 as in the conventional example, the secondary floor slab is awaited for its strength development. There is no need for the time required for placing concrete into the formwork of the floor slab, the construction period can be shortened, and the ratio of the shortened period to the total construction period is large. As a result, full service of the bridge can be started early.

従来例の第1の段階の斜視図である。It is a perspective view of the 1st step of a prior art example. 従来例の第2の段階の斜視図である。It is a perspective view of the 2nd step of a prior art example. 従来例の第3の段階の斜視図である。It is a perspective view of the 3rd step of a prior art example. 従来例の第4の段階の斜視図である。It is a perspective view of the 4th step of a prior art example. 本発明例の第1の段階の斜視図である。It is a perspective view of the 1st step of the example of the present invention. 本発明例の第2の段階の斜視図である。It is a perspective view of the 2nd step of the example of the present invention. 本発明例の第3の段階の斜視図である。It is a perspective view of the 3rd step of the example of the present invention. 本発明例の第4の段階の斜視図である。It is a perspective view of the 4th step of the example of the present invention. 本発明の施工例の平面図である。It is a top view of the example of construction of the present invention. 図9のX−X線矢視図である。It is the XX arrow directional view of FIG. 図9のY−Y矢視図である。It is a YY arrow line view of FIG. 従来例の工期(a)と本発明の施工例の工期(b)の比較説明図である。It is comparative explanatory drawing of the construction period (a) of a prior art example, and the construction period (b) of the construction example of this invention.

次に、発明を実施するための形態を説明する。
本発明例を図5〜図8によって説明する。ただし、これは概要を説明するものである。
Next, modes for carrying out the invention will be described.
An example of the present invention will be described with reference to FIGS. However, this is only an overview.

例えば高速道路のインターチェンジにおける橋梁の例である。
本発明は、新設又は既設を問われることなく、橋台6,6又は橋脚間上に跨がってコンクリート床版が配置された橋梁の拡幅に係るものである。図示の例では、橋脚は設けられておらず、橋台6,6間にコンクリート床版が設けられている。橋脚がある場合には、その橋脚と橋台との間に跨がって、あるいは橋脚間に跨がって、あるいは橋台と橋脚の上を連続して跨ってコンクリート床版が配置される。
An example is a bridge in an interchange on a highway.
The present invention relates to the widening of a bridge in which a concrete slab is arranged across abutments 6, 6 or between piers, regardless of whether they are newly installed or existing. In the illustrated example, no pier is provided, and a concrete slab is provided between the abutments 6 and 6. When there is a pier, a concrete floor slab is arranged straddling between the pier and the abutment, straddling the pier, or straddling the abutment and the pier continuously.

本発明例では、下方に撓んでいる既設床版11の少なくとも新設床版側を、たとえば型枠合板や根太材などを挟み込んだうえで、ジャッキにより上向きに荷重をかけて、例えばジャッキアップして保持するプレロード工程を有する。図5はプレロード工程前で、既設床版11は破線に対しての偏位で示すように下方に撓んでいる。図6はジャッキアップ5によるプレロード工程状態を示している。   In the present invention example, at least the new floor slab side of the existing floor slab 11 bent downward is sandwiched between, for example, a formwork plywood or a joist, and a load is applied upward by a jack. It has a preload process to hold. FIG. 5 shows the pre-loading step, and the existing floor slab 11 is bent downward as shown by the displacement with respect to the broken line. FIG. 6 shows a preload process state by the jack-up 5.

次に、図7に示すように、拡幅用新設床版12の型枠を、既設床版11に隣接させて、そのレベルをプレロードしている既設床版の保持レベルと実質的に同一に保持する。この保持工程では、例えば適宜の支保部材を利用して行う。符号4は型枠支保工を示しており、新設床版12の下方への撓みを防止するものであるから、上向き矢印で示したものである。   Next, as shown in FIG. 7, the formwork of the new floor slab 12 for widening is made adjacent to the existing floor slab 11, and the level is held substantially the same as the holding level of the existing floor slab preloaded. To do. In this holding step, for example, an appropriate support member is used. Reference numeral 4 denotes a formwork support, which prevents the new floor slab 12 from being bent downward, and is indicated by an upward arrow.

好適にはこの保持工程と共に、又は保持工程後に拡幅用新設床版12の型枠内に鉄筋を配筋したうえでコンクリート打設を行う新設床版形成工程を有する。   Preferably, there is a new floor slab forming step in which concrete is placed after reinforcing bars are placed in the formwork of the new floor slab 12 for widening after the holding step.

さらに、前記新設床版形成工程後に、既設床版11の保持及び新設床版12の保持を解放する保持解放工程を有する。   Furthermore, after the said new floor slab formation process, it has the holding | maintenance release process of releasing the holding | maintenance of the existing floor slab 11 and the holding | maintenance of the new floor slab 12.

必要により、新設床版形成工程前もしくは工程中、又は好適には新設床版形成工程後において、地覆及び高欄を形成する。これをコンクリート壁とする場合には、鉄筋、型枠の組立て、コンクリート打設及び養生のステップを有する。   If necessary, the ground cover and railing are formed before or during the new floor slab forming process, or preferably after the new floor slab forming process. When this is a concrete wall, it has steps of rebar, formwork assembly, concrete placement and curing.

地覆及び高欄の施工時期は適宜選定すればよいが、コンクリート壁とする場合には、新設床版を形成し、地覆及び高欄の養生を待って、既設床版11の保持及び新設床版12の保持を解放するのが望ましい。   The construction period of the ground cover and handrail may be selected as appropriate, but in the case of a concrete wall, a new floor slab is formed, and after the ground cover and handrail is cured, the existing floor slab 11 is held and the new floor slab is placed. It is desirable to release 12 holds.

続いて、既設床版11のプレロード例、及び既設床版11及び新設床版12の保持例を図9以下において図示した。   Subsequently, a preload example of the existing floor slab 11 and a holding example of the existing floor slab 11 and the new floor slab 12 are illustrated in FIG.

図示例は、橋台6、6間に橋脚7を有する例である。図9及び図10を参照すると、既設床版11は、その内部に鋼管パイプ11bが設けられ、その内部は空洞となっており、鋼管パイプ11bの外部においては鉄筋(図示せず)が配筋され、コンクリート(図示せず)が打設されているものである。
この既設床版11に隣接して、新設床版12が設けられる。この新設床版12においても、その内部に鋼管パイプ12bが設けられ、鉄筋(図示せず)が配筋され、コンクリート(図示せず)が打設されるものである。
In the illustrated example, an abutment 7 is provided between the abutments 6 and 6. Referring to FIGS. 9 and 10, the existing floor slab 11 is provided with a steel pipe 11b inside thereof, and the inside thereof is hollow, and a reinforcing bar (not shown) is arranged outside the steel pipe 11b. Concrete (not shown) is placed.
A new floor slab 12 is provided adjacent to the existing floor slab 11. The new floor slab 12 is also provided with a steel pipe 12b therein, a reinforcing bar (not shown) is arranged, and concrete (not shown) is placed.

さらに、図11をも参照すると、図示例においては、既設床版11と新設床版12とを、これらに跨がる根太材14、14…により支保するとともに、その支保部としての根太材14が橋の長手方向に複数設ける形態を採るのが望ましい。
既設床版11と新設床版12とに跨がる根太材14、14…により支保すると、既設床版11から新設床版12への振動に、新設床版12が追従するようになる。
Furthermore, referring also to FIG. 11, in the illustrated example, the existing floor slab 11 and the new floor slab 12 are supported by the joist members 14, 14... It is desirable to adopt a form in which a plurality is provided in the longitudinal direction of the bridge.
When supported by the joists 14, 14... Straddling the existing floor slab 11 and the new floor slab 12, the new floor slab 12 follows the vibration from the existing floor slab 11 to the new floor slab 12.

この場合、既設床版11のプレロードを別に行うことも可能であるが、望ましくは既設床版11のプレロードを併せて行う。すなわち、既設床版11のプレロードと、並びに既設床版11及び新設床版12の実質的な同一レベルの保持とを併せて行うと、既設床版11から新設床版12への振動に新設床版12が追従して振動するようになり、例えば新設床版12のコンクリート打設における特に若材齢時期における影響を極力抑止でき、ひび割れ等の問題発生を防止できる。   In this case, the existing floor slab 11 can be preloaded separately, but preferably the existing floor slab 11 is preloaded together. That is, when the preloading of the existing floor slab 11 and the holding of the existing floor slab 11 and the new floor slab 12 at substantially the same level are performed together, the vibration of the existing floor slab 11 to the new floor slab 12 is caused by vibration. The plate 12 follows and vibrates. For example, the influence on the concrete placement of the new floor slab 12 especially at the young age can be suppressed as much as possible, and the occurrence of problems such as cracks can be prevented.

具体例では、このために、新設床版12側においては支持台15上に支保組み16を設けるとともに、新設床版12の下方に配置した角管などからなる根太材14、14…を通り方向に配置した角管などからなる大引17を支保組み16により支持することにより、新設床版12を支保している。この支保は、図7に基づいて説明した支保工4に該当する。   In the specific example, for this purpose, on the side of the new floor slab 12, a support assembly 16 is provided on the support base 15, and the direction passes through the joists 14, 14. The newly installed floor slab 12 is supported by supporting a large drawing 17 made of a square tube or the like disposed on the support assembly 16. This support corresponds to the support work 4 described with reference to FIG.

図10に示すように、既設床版11側においては、支持台18上に通り方向に配置した形鋼などからなる通し材19が配置され、その上に適宜数のジャッキ20を設置し、既設床版11の新設床版12側の側縁部下方に、前記根太材14、14…の端部を延在して配置し、その端部を通り方向に配置した角管などからなる大引21により支持することにより、既設床版11を支持している。   As shown in FIG. 10, on the existing floor slab 11 side, a threading member 19 made of a shape steel or the like disposed in the passing direction is disposed on a support base 18, and an appropriate number of jacks 20 are installed thereon, An end portion of the joist members 14, 14... Is extended below the side edge portion of the floor slab 11 on the side of the newly installed slab 12, and a large tube made of a square tube or the like disposed in the direction passing through the end portion. The existing floor slab 11 is supported by being supported by 21.

ジャッキ20群により大引21を持ち上げ、根太材14を介して既設床版11にプレロードを与える。ジャッキ20によるこのプレロードは、図6に基づいて説明したジャッキアップ5に該当する。
既設床版11に対するプレロードは、例えば、支持がない場合の死荷重による下方への撓みを打ち消す程度とすることができる。
The large pull 21 is lifted by the jack 20 group, and a preload is given to the existing floor slab 11 through the joist material 14. This preloading by the jack 20 corresponds to the jack-up 5 described with reference to FIG.
The preload for the existing floor slab 11 can be, for example, to cancel the downward deflection due to the dead load when there is no support.

前述のように、新設床版形成工程前もしくは工程中、又は好適にはコンクリート打設及び養生により新設床版12を形成した後において、地覆及び高欄22を形成することができる。新設床版12の端部は、別の支保工16Aにより支保できる。なお、符号23は仮設壁である。   As described above, the ground cover and the rail 22 can be formed before or during the new floor slab forming process, or preferably after the new floor slab 12 is formed by concrete placement and curing. The end portion of the new floor slab 12 can be supported by another supporting work 16A. Reference numeral 23 denotes a temporary wall.

本発明者らは、本発明に従うと、図12(b)のように、図12(a)の従来例と比較して工期の短縮及び早急な道路供用を行うことができることを知見している。   The present inventors know that according to the present invention, as shown in FIG. 12 (b), the construction period can be shortened and the road can be used quickly compared to the conventional example of FIG. 12 (a). .

上記例のプレロード工程は、既設床版の新設床版側のみを、上向きに荷重をかけて保持するものである。これを選択した理由は、計画段階でのシミュレーションにおいて、既設床版の新設床版側のみを上向きに荷重をかけて保持すれば足りることを知見したことに拠っている。しかるに、本発明に係るプレロード工程において、既設床版の新設床版側のみならず、反対側においても上向きに荷重をかけて保持することができるものである。   In the preloading process of the above example, only the new floor slab side of the existing floor slab is held by applying a load upward. The reason for selecting this is based on the knowledge that it is sufficient to hold only the new floor slab side of the existing floor slab with an upward load in the simulation at the planning stage. However, in the preloading process according to the present invention, not only the new floor slab side of the existing floor slab but also the opposite side can be held with an upward load.

1、2…道路、3…橋梁、4…型枠支保工、5…ジャッキアップ、6…橋台、7…橋脚、11…既設床版、12…新設床版、14…根太材、17…大引、20…ジャッキ、21…大引、22…高欄。   1, 2 ... road, 3 ... bridge, 4 ... formwork support, 5 ... jack up, 6 ... abutment, 7 ... pier, 11 ... existing floor slab, 12 ... new floor slab, 14 ... joist, 17 ... large Pull, 20 ... Jack, 21 ... Large draw, 22 ... High rail.

Claims (4)

橋台又は橋脚間上に跨がってコンクリート床版が配置された橋梁の拡幅に際し、
既設床版の少なくとも新設床版側を、上向きに荷重をかけて保持するプレロード工程、
拡幅用新設床版の型枠を、前記既設床版に隣接させて、そのレベルを前記プレロード工程における既設床版の保持レベルと実質的に同一に保持する保持工程、
保持工程と共に又は保持工程後に拡幅用新設床版の型枠内にコンクリート打設を行う新設床版形成工程、
前記新設床版形成工程後に、前記既設床版の保持及び前記新設床版の保持を解放する保持解放工程、
を有することを特徴とする橋梁拡幅工法。
When widening a bridge with concrete slabs straddling between abutments or piers,
A preloading process in which at least the new floor slab side of the existing floor slab is held with an upward load;
A holding step of holding the formwork of the new floor slab for widening adjacent to the existing floor slab and holding the level thereof substantially the same as the holding level of the existing floor slab in the preloading step;
A new floor slab forming process in which concrete is placed in the formwork of the new floor slab for widening together with or after the holding process;
A holding release step for releasing the holding of the existing floor slab and the holding of the new floor slab after the new floor slab forming step;
A bridge widening method characterized by comprising:
前記既設床版と前記新設床版とに跨がる根太材により支保するとともに、その支保部が橋の長手方向に複数ある請求項1に記載の橋梁拡幅工法。   The bridge widening method according to claim 1, wherein the bridge is widened by a joist straddling the existing floor slab and the new floor slab, and there are a plurality of support portions in the longitudinal direction of the bridge. 前記既設床版と前記新設床版とに跨がる根太材により支保するとともに、その支保部が橋の長手方向に複数あり、
既設床版の少なくとも新設床版側を上向きに荷重をかけて保持するプレロード工程において、前記根太材の複数を支承する保持材の下方からジャッキアップしてプレロードを図る請求項1に記載の橋梁拡幅工法。
While supporting by the joist straddling the existing floor slab and the newly installed floor slab, there are a plurality of support portions in the longitudinal direction of the bridge,
The bridge widening according to claim 1, wherein in a preloading step of holding at least a new floor slab side of an existing floor slab with an upward load, jacking up is performed from below a retaining material for supporting a plurality of joists. Construction method.
新設床版形成工程後において、地覆及び高欄を形成する請求項1に記載の橋梁拡幅工法。   The bridge widening method according to claim 1, wherein a ground cover and a rail are formed after the new floor slab forming step.
JP2016094852A 2016-05-10 2016-05-10 Bridge widening method Active JP6717656B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016094852A JP6717656B2 (en) 2016-05-10 2016-05-10 Bridge widening method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016094852A JP6717656B2 (en) 2016-05-10 2016-05-10 Bridge widening method

Publications (2)

Publication Number Publication Date
JP2017203284A true JP2017203284A (en) 2017-11-16
JP6717656B2 JP6717656B2 (en) 2020-07-01

Family

ID=60323175

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016094852A Active JP6717656B2 (en) 2016-05-10 2016-05-10 Bridge widening method

Country Status (1)

Country Link
JP (1) JP6717656B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281663A (en) * 2020-10-21 2021-01-29 广东精特建设工程有限公司 Construction method for widening connection of upper structures of new and old bridges
JP2023043201A (en) * 2021-09-16 2023-03-29 忠 阿部 Slab girder bridge construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5277405A (en) * 1992-11-30 1994-01-11 Mcswain Gregory A Temporary decking support
JPH10219626A (en) * 1997-02-13 1998-08-18 Taisei Corp Movable form timbering device to install bridge and moving execution method thereof
JP2001336116A (en) * 2000-05-29 2001-12-07 Ishikawajima Harima Heavy Ind Co Ltd Reinforcing structure of floor slab
JP2004060312A (en) * 2002-07-30 2004-02-26 Sumitomo Metal Steel Products Inc Timbering for bridge
JP2009287286A (en) * 2008-05-29 2009-12-10 Nippon Steel & Sumikin Metal Products Co Ltd Support for overhanging floor slab
JP2011021384A (en) * 2009-07-16 2011-02-03 Sho-Bond Corp Structure and method for widening road bridge
KR101124337B1 (en) * 2011-04-20 2012-03-16 부림산업개발(주) A construct for a bicycle track or a sidewalk, and constructing method of it
JP2013237989A (en) * 2012-05-11 2013-11-28 Free Kogyo Kk Method for restoring bridge
JP2016008406A (en) * 2014-06-23 2016-01-18 首都高速道路株式会社 Temporary bearing method for main girder in floor slab replacement work with composite girder, floor slab replacement method with composite girder, and temporary bearing structure for main girder in floor slab replacement work with composite girder

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5277405A (en) * 1992-11-30 1994-01-11 Mcswain Gregory A Temporary decking support
JPH10219626A (en) * 1997-02-13 1998-08-18 Taisei Corp Movable form timbering device to install bridge and moving execution method thereof
JP2001336116A (en) * 2000-05-29 2001-12-07 Ishikawajima Harima Heavy Ind Co Ltd Reinforcing structure of floor slab
JP2004060312A (en) * 2002-07-30 2004-02-26 Sumitomo Metal Steel Products Inc Timbering for bridge
JP2009287286A (en) * 2008-05-29 2009-12-10 Nippon Steel & Sumikin Metal Products Co Ltd Support for overhanging floor slab
JP2011021384A (en) * 2009-07-16 2011-02-03 Sho-Bond Corp Structure and method for widening road bridge
KR101124337B1 (en) * 2011-04-20 2012-03-16 부림산업개발(주) A construct for a bicycle track or a sidewalk, and constructing method of it
JP2013237989A (en) * 2012-05-11 2013-11-28 Free Kogyo Kk Method for restoring bridge
JP2016008406A (en) * 2014-06-23 2016-01-18 首都高速道路株式会社 Temporary bearing method for main girder in floor slab replacement work with composite girder, floor slab replacement method with composite girder, and temporary bearing structure for main girder in floor slab replacement work with composite girder

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281663A (en) * 2020-10-21 2021-01-29 广东精特建设工程有限公司 Construction method for widening connection of upper structures of new and old bridges
JP2023043201A (en) * 2021-09-16 2023-03-29 忠 阿部 Slab girder bridge construction method

Also Published As

Publication number Publication date
JP6717656B2 (en) 2020-07-01

Similar Documents

Publication Publication Date Title
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
KR100819833B1 (en) Apparatus and method for building slab of a concrete build
KR101101204B1 (en) Cantilever of slab for steel box bridge using steel supporter and the method thereof
KR101198812B1 (en) composite rahmen bridge using a preflex girder
JP5937898B2 (en) Construction method of box girder bridge
KR101198376B1 (en) Fcm pier table construction method using girder
KR20170014821A (en) Cable-Stayed Bridge having Precast Core, and Constructing Method thereof
KR102080492B1 (en) Construction method for cantilever in steel composite girder bridge
JP6717656B2 (en) Bridge widening method
JP4977110B2 (en) Composite digit structure and composite digit construction method
JP5143666B2 (en) PC bridge erection method
KR101223753B1 (en) Incremental launching apparatus for launching concrete slab of tunnel type for composite bridge, and constructing method for the same
KR101607485B1 (en) Curved-psc girder with outrigger and curved-psc girder bridge construction method therewith
JP2017096057A (en) Bridge construction method
JP7012486B2 (en) Bridge construction method
JP6761264B2 (en) Construction management method for horizontal members
KR20130090455A (en) Construction method for continuous bridge using confined concrete
JP7134133B2 (en) Bridge railing construction method
JP2016211195A (en) Manufacturing method of prestressed concrete girder
KR100776671B1 (en) Construction method for confine concrete member of steel plate girder
KR101232706B1 (en) Block supporting inner form and rail used in movable scaffolding system
JP2019015139A (en) Precast concrete plate and concrete structure slab
KR101022448B1 (en) Method for manufacturing of precast panel deck
KR101172442B1 (en) Construction method for girder using confined concrete
KR102187182B1 (en) Rhamen bridge and construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190419

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200110

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200117

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200312

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200529

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200611

R150 Certificate of patent or registration of utility model

Ref document number: 6717656

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150