JP2017133608A - Piping suspending and supporting device - Google Patents

Piping suspending and supporting device Download PDF

Info

Publication number
JP2017133608A
JP2017133608A JP2016014346A JP2016014346A JP2017133608A JP 2017133608 A JP2017133608 A JP 2017133608A JP 2016014346 A JP2016014346 A JP 2016014346A JP 2016014346 A JP2016014346 A JP 2016014346A JP 2017133608 A JP2017133608 A JP 2017133608A
Authority
JP
Japan
Prior art keywords
pipe
suspension
support
band holding
band
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016014346A
Other languages
Japanese (ja)
Other versions
JP6160719B1 (en
Inventor
隆次郎 渋谷
Ryujiro Shibuya
隆次郎 渋谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rstone Co Ltd
Original Assignee
Rstone Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rstone Co Ltd filed Critical Rstone Co Ltd
Priority to JP2016014346A priority Critical patent/JP6160719B1/en
Application granted granted Critical
Publication of JP6160719B1 publication Critical patent/JP6160719B1/en
Publication of JP2017133608A publication Critical patent/JP2017133608A/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)
  • Vibration Prevention Devices (AREA)
  • Supports For Pipes And Cables (AREA)
  • Clamps And Clips (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a piping suspending and supporting device capable of suppressing a cost increase without increasing component management and labor in mounting at a site, exhibiting vibration-proofness (seismic isolation) to strong rolling, suitable for holding and supporting a light-weight synthetic resin conduit, and effective even when supporting a plurality of pipings in a parallel state.SOLUTION: A piping suspending and supporting device for supporting a piping P at two or three points from a mounting surface of a ceiling slab is such that: a first piping supporting device 1 suspended from a suspending bolt 3 and holding a first piping has a band holding part formed with an overlappedly engaged part where an upper engaged part and a lower engaged part which are cut and raised to the transverse direction outside are overlapped; a second piping supporting device 4 for holding a second piping PP is connected and mounted in a parallel state on the overlappedly engaged part; and one or two suspending and supporting rods 5 suspending from the mounting surface are fixed by inserting into a suspended and engaged part of the second piping supporting device so as to be supported at two or three points.SELECTED DRAWING: Figure 1

Description

本発明は配管吊下支持具に関し、詳しくは天井スラブ等の取付面に、1〜3本の水道管、ガス管、冷・暖房管等の各種配管を2点又は3点吊下支持する配管吊下支持具に関する。   The present invention relates to a pipe suspension support tool, and more specifically, a pipe that supports suspension of various pipes such as 1 to 3 water pipes, gas pipes, and cooling / heating pipes on a mounting surface such as a ceiling slab. The present invention relates to a hanging support.

天井スラブ等の取付面に吊りボルト等の支持部材による吊下支持に加えて前記取付面から斜めに垂設した1本又は2本の吊下支持杆を付加すること等によって2点支持乃至は3点吊下支持したり、或いは2本の吊下支持杆によって2点吊下支持することで防振(防震)構造とした技術としては、例えば、特許文献1〜3に記載のもの等が知られている。   In addition to suspension support by a support member such as a suspension bolt on a mounting surface such as a ceiling slab, one or two suspension support rods obliquely suspended from the mounting surface are added, etc. For example, the techniques described in Patent Documents 1 to 3 include a three-point suspension support or a two-point suspension support by two suspension support rods to achieve a vibration-proof (seismic isolation) structure. Are known.

特許文献1に示す技術では、従来構成のままの既存のタンバックル及び配管支持具に装着することで3点吊下支持可能な技術であるが、他部材である2枚の板状部材を必要とするため、かかる部品点数の増加によって現場での部品管理の煩雑さや装着時の手間等が新たに加わることとなっている。   The technique shown in Patent Document 1 is a technique that can be suspended and supported at three points by mounting it on an existing tangle buckle and pipe support with the conventional configuration, but requires two plate-like members as other members. For this reason, the increase in the number of parts adds to the complexity of part management at the site and the trouble of mounting.

特許文献2及び3に示す技術は、配管支持具のバンド抱持部の外面に吊下支持杆との係合部が設けられているため、新たな部材の追加の問題はなく部品管理等の煩雑さ等は無いが、配管支持具自体のコストが上昇せざるを得ない。   Since the technology shown in Patent Documents 2 and 3 is provided with an engaging portion with a suspension support rod on the outer surface of the band holding portion of the pipe support tool, there is no problem of adding new members and parts management and the like. There is no complication or the like, but the cost of the pipe support itself is inevitably increased.

以上のことから、現場での部品管理や装着時の手間等が増すことなく、コストアップを抑制することができる配管吊下支持具の要請があることが判った。   From the above, it has been found that there is a demand for a pipe suspension supporter that can suppress the cost increase without increasing the labor at the time of parts management or installation.

更に本発明者が当該技術について鋭意研究を続けたところ、強い横揺れが発生した場合、配管を抱持した状態で取付面から吊下げられる配管支持具は、取付面と吊りボルトとの接続部、吊りボルトとタンバックルとの接続部、タンバックルと配管支持具との接続部からバンド抱持部の上端部分までの部分、等の箇所に負荷がかかり、特に配管を抱持する部分の直上であるバンド抱持部の上端部分に大きな負荷がかかることが判った。   Furthermore, when the present inventor has continued earnestly researching the technology, when a strong roll occurs, the pipe support that can be hung from the mounting surface while holding the pipe is a connecting portion between the mounting surface and the suspension bolt. , A load is applied to the connection part between the suspension bolt and the tambuckle, the connection part between the tan buckle and the pipe support and the upper part of the band holding part, etc., especially directly above the part holding the pipe It was found that a large load is applied to the upper end portion of the band holding portion.

本発明者の研究によれば、前記特許文献1〜3に示す技術では強い横揺れが発生した際には、取付面と吊りボルトとの接続部、吊りボルトとタンバックルとの接続部、タンバックルと配管支持具との接続部については防振(防震)性を発揮することができるが、バンド抱持部の上端部分での防振(防震)性については不充分な場合があることが判った。   According to the inventor's research, when strong rolling occurs in the techniques shown in Patent Documents 1 to 3, the connection portion between the mounting surface and the suspension bolt, the connection portion between the suspension bolt and the tangle buckle, The connection part between the buckle and the pipe support can exhibit anti-vibration (anti-vibration) properties, but the anti-vibration (anti-vibration) property at the upper end of the band holding part may be insufficient. understood.

そこで本発明者は、配管を抱持するバンド抱持部の一部を切り起して切起し係止部を形成し、この切起し係止部に、取付面から吊下げられた1本又は2本の吊下げ支持杆を係合可能とすることにより、2点又は3点吊下げ支持可能な配管吊下支持具を先に提案した(特許文献4〜6参照)。   Therefore, the present inventor cuts and raises a part of the band holding portion that holds the pipe to form a locking portion, and the cut and raised locking portion is hung from the mounting surface. A pipe suspension support that can be suspended at two or three points by making it possible to engage one or two suspension support rods has been proposed (see Patent Documents 4 to 6).

特開2004−150452号JP2004150452 実用新案登録第2524340号Utility Model Registration No. 2524340 登録実用新案第3148361号Registered Utility Model No. 3148361 登録実用新案第3153185号Registered Utility Model No. 3153185 登録実用新案第3153545号Registered Utility Model No. 3153545 登録実用新案第3153546号Registered Utility Model No. 3153546

本発明者はかかる技術について更に研究を進めたところ、近年、配管類として鋼管に代わって合成樹脂管(ポリエチレン管、架橋ポリエチレン管、ポリブデン管、塩化ビニル管、プロピレン管、ABS管等)が用いられるようになってきており、今後、大部分の配管類が鋼管から合成樹脂管に代わることが予想されている。   As a result of further research on this technology, the present inventor has recently used synthetic resin pipes (polyethylene pipes, cross-linked polyethylene pipes, polybuden pipes, vinyl chloride pipes, propylene pipes, ABS pipes, etc.) instead of steel pipes. In the future, it is expected that most of pipes will be replaced with synthetic resin pipes instead of steel pipes.

合成樹脂管は、高い耐蝕性を有し、しかも鋼管と同等乃至同等以上の耐熱性及び耐衝撃性を有するのに鋼管に比して軽量であり、更に加工が容易であるため、取扱性等の点で優れている。   Synthetic resin pipes have high corrosion resistance, and have heat resistance and impact resistance equivalent to or better than steel pipes, but they are lighter than steel pipes, and are easier to work with. Is excellent in terms of.

本発明者は、かかる合成樹脂管の配管支持技術について鋭意研究を続けたところ、合成樹脂管は上記したように軽量であるため、従来の鋼管用の支持具が求められるほどの堅牢度・強度等が不要であることを見出した。また、複数本の並列状態で支持する場合においても同様である。   The present inventor has continued earnestly researching on the pipe support technology of such a synthetic resin pipe, and since the synthetic resin pipe is lightweight as described above, it is so fast and strong that a conventional steel pipe support is required. Etc. were found unnecessary. The same applies to the case of supporting in a plurality of parallel states.

そこで本発明の課題は、現場での部品管理や装着時の手間等が増すことなくコストアップを抑制することができ、且つ強い横揺れに対しても防振(防震)性を発揮することができ、しかも軽量な合成樹脂管の抱持支持に適しており、更に複数本の配管を並列状態で支持する場合であっても有効な配管吊下支持具を提供することにある。   Therefore, the problem of the present invention is that it is possible to suppress the cost increase without increasing the troubles at the time of parts management and mounting at the site, and to exhibit the vibration proof (seismic proof) property against strong roll. It is also possible to provide a pipe suspension support that is suitable for holding and supporting lightweight synthetic resin pipes and that is effective even when a plurality of pipes are supported in parallel.

上記課題を解決する本発明は下記構成を有する。   The present invention for solving the above problems has the following configuration.

1.配管を抱持するバンド抱持部と該バンド抱持部の上端部に連接されたバンド端部を有する配管支持具であって、抱持した配管を、天井スラブ等の取付面から2点又は3点支持する配管吊下支持具において、
配管支持具本体である第1配管支持具が、2つのバンド抱持部によって配管を抱持可能であり、該2つのバンド抱持部の下端部分を組式又は蝶番式の如き接続部により拡開可能に接続され、前記バンド端部がタンバックルの如き吊下接続部材に接続されることで吊りボルトからの吊下げが可能な構成の配管支持バンドから成り、
前記2つのバンド抱持部の各々について、
該バンド抱持部の略中央部より上方部分を該略中央部を基点として切起された状態で横方向外側に延伸する上方側取付部が形成され、
且つ、該バンド抱持部の略中央部より下方部分を該略中央部を基点として切起された状態で横方向外側に延伸する下方側取付部が形成され、
この横方向外側に切起した上方側取付部と下方側取付部とが重合された状態で重合取付部が形成され、
更に、この重合取付部の重合した部分にボルトの如き固定手段を挿通する透孔が貫通形成され、
この重合取付部に、別なる配管支持具である第2配管支持具が重連状態で接続取付されて該第2配管支持具に別なる配管である第2配管の抱持支持が可能である構成であり、
該第2配管支持具が、第2バンド抱持部によって配管を抱持可能であり、該第2バンド抱持部の上端部に連設された重連用取付部と、該第2バンド抱持部の下端部分に設けられた吊下用係止部と、を有して成り、
前記重連用取付部が、ボルトの如き固定手段を挿通する透孔が形成され、この重連用取付部を前記第1配管支持具の重合取付部に前記固定手段を用いて取付固定して重連状態での接続取付が可能な構成であり、
前記吊下係止部が、前記取付面に一端が固定されて吊下げられる1本又は2本の吊りボルトの如き吊下支持杆を挿通する透孔が形成され、この吊下係止部の透孔に前記吊下支持杆の他端を挿通固定して2点又は3点支持された状態とする構成であること、
を特徴とする配管吊下支持具。
1. A pipe support having a band holding part for holding a pipe and a band end connected to the upper end of the band holding part, and holding the pipe from the mounting surface such as a ceiling slab or the like. In the pipe suspension support that supports three points,
The first pipe support, which is the main body of the pipe support, can hold the pipe by the two band holding parts, and the lower end portion of the two band holding parts is expanded by a connecting part such as a combination type or a hinge type. It consists of a pipe support band that is configured to be able to be suspended from a suspension bolt by being connected so as to be able to be opened and being connected to a suspension connection member such as a tan buckle.
For each of the two band holding portions,
An upper mounting portion is formed that extends outward in the lateral direction in a state where the upper portion of the band holding portion is cut and raised from the substantially central portion as a base point.
In addition, a lower attachment portion is formed that extends outward in the lateral direction in a state where the lower portion is cut and raised from the substantially central portion as a base point from the substantially central portion of the band holding portion,
A superposed mounting portion is formed in a state where the upper mounting portion and the lower mounting portion which are cut up to the outside in the lateral direction are superposed,
Furthermore, a through hole through which a fixing means such as a bolt is inserted is formed through the overlapped portion of the overlapping mounting portion,
A second pipe support, which is another pipe support, is connected and attached to the superposition attachment portion in a continuous state, and the second pipe, which is another pipe, can be held and supported by the second pipe support. Configuration,
The second pipe support is capable of holding a pipe by a second band holding part, and a double continuous attachment part connected to the upper end part of the second band holding part, and the second band holding part A suspension locking portion provided at the lower end portion of the portion,
The multi-continuous mounting portion is formed with a through hole through which a fixing means such as a bolt is inserted. The multi-continuous mounting portion is attached and fixed to the overlapping mounting portion of the first pipe support by using the fixing means. It is a configuration that can be connected and installed in the state,
The suspension latch is formed with a through-hole through which a suspension support rod such as one or two suspension bolts suspended at one end fixed to the mounting surface. The other end of the suspension support rod is inserted into and fixed to the through hole, and is in a state of being supported at two or three points,
A piping suspension support characterized by the following.

2.前記重合取付部の各々が、外側斜め下方に向かった状態で延伸する構成であることを特徴とする上記1に記載の配管吊下支持具。 2. 2. The pipe suspension support device according to 1 above, wherein each of the overlapping attachment portions is configured to extend in a state of being directed obliquely outward and downward.

3.前記重合取付部の各々が、前記した略中央部の基点から外側斜め上方に向かって延伸すると共に、この延伸した部分の中途部分であって且つ前記透孔よりも基点側の部分において折曲られた状態又は湾曲された状態で外側斜め下方に向かった状態で延伸する構成であることを特徴とする上記1に記載の配管吊下支持具。 3. Each of the overlapping attachment portions extends obliquely outward and upward from the base point of the substantially central portion described above, and is bent in a middle portion of the extended portion and at a portion closer to the base point than the through hole. 2. The pipe suspension support device according to 1 above, wherein the pipe suspension support tool is configured to extend in a state of being in a bent state or in a curved state and directed obliquely downward toward the outside.

4.前記重合取付部の各々が、前記した略中央部の基点から外側水平方向に向かって延伸すると共に、この延伸した部分の中途部分であって且つ前記透孔よりも基点側の部分において折曲られた状態又は湾曲された状態で外側斜め下方に向かった状態で延伸する構成であることを特徴とする上記1に記載の配管吊下支持具。 4). Each of the overlapping mounting portions extends from the base point of the substantially central portion toward the outer horizontal direction, and is bent in a portion in the middle of the extended portion and on the base point side of the through hole. 2. The pipe suspension support device according to 1 above, wherein the pipe suspension support tool is configured to extend in a state of being in a bent state or in a curved state and directed obliquely downward toward the outside.

5.前記上方側取付部と前記下方側取付部の各々が、その基点部分から前記バンド抱持部の外周面に沿って折り返し横方向外側に延伸するように折曲された状態で重合された構成であることを特徴とする上記1〜4のいずれかに記載の配管吊下支持具。 5. Each of the upper side attachment portion and the lower side attachment portion is polymerized in a state in which the upper side attachment portion and the lower side attachment portion are folded so as to extend outward in the lateral direction along the outer peripheral surface of the band holding portion. The pipe suspension support according to any one of the above 1 to 4, wherein the pipe suspension support is provided.

6.前記第2配管支持具が、
両端が接触又は近接して略円形を成して前記第2配管を抱持する第2バンド抱持部と、
該第2バンド抱持部の両端部の各々に連設され、前記第1配管支持具の重合取付部に接続取付けする重連用取付部と、
前記第2バンド抱持部の下端部分に垂設する1枚又は2枚の吊下係止部と、
を有する構成であり、
この1枚又は2枚の吊下係止部は、前記下端部分の1箇所又は平行する2箇所を基端として該下端部分より端部方向部分の切り起された状態で該下端部分から垂設する構成であり、
更にこの1枚又は2枚の吊下係止部には、前記吊下支持杆を挿通する透孔が形成された構成であること、
を特徴とする上記1〜5のいずれかに記載の配管吊下支持具。
6). The second pipe support is
A second band holding portion for holding the second pipe in a substantially circular shape with both ends in contact or close to each other;
A continuous attachment part connected to and attached to the overlapping attachment part of the first pipe support, connected to each of both ends of the second band holding part;
One or two suspension latching portions suspended from the lower end portion of the second band holding portion;
And a configuration having
The one or two suspension latching portions are suspended from the lower end portion in a state where the end direction portion is cut and raised from the lower end portion, with one base of the lower end portion or two parallel portions as the base ends. Is a configuration to
Furthermore, the one or two suspension locking portions have a structure in which a through hole is formed through which the suspension support rod is inserted.
The pipe suspension support according to any one of 1 to 5 above.

本明細書において、「上方」、「上端」、「下方」、「下端」の上下位置を示す語は、本発明の配管支持バンドが取り付けられる取付面を基準にして、該取付面に近い位置を「上」とし、該取付面から離れた位置を「下」としている。
即ち、吊下支持に用いる場合の「上方」「上端」は文字通りの「上」であり、「下方」「下端」は文字通りの「下」であるが、床面からの立上支持に用いる場合の「上方」「上端」は文字通りとは正反対の「下」となり、「下方」「下端」は文字通りとは正反対の「上」となる。また、壁面からの立上支持に用いる場合の「上方」「上端」は壁面に近い側であり、「下方」「下端」は壁面から遠い位置である。
In the present specification, the terms indicating the upper and lower positions of “upper”, “upper end”, “lower”, and “lower end” are positions close to the mounting surface on the basis of the mounting surface to which the pipe support band of the present invention is mounted. Is “upper”, and the position away from the mounting surface is “lower”.
That is, when used for suspension support, “upper” and “upper end” are literally “upper”, and “lower” and “lower end” are literally “lower”, but are used for standing support from the floor. The “upper” and “upper” of the text are “lower”, which is the opposite of literally, and the “lower” and “lower” are “upper” of the opposite of literal. In addition, the “upper” and “upper end” when used for standing support from the wall surface are near the wall surface, and the “lower” and “lower end” are positions far from the wall surface.

請求項1に示す発明によれば、現場での部品管理や装着時の手間等が増すことなくコストアップを抑制することができ、且つ強い横揺れに対しても防振(防震)性を発揮することができ、しかも軽量な合成樹脂管の抱持支持に適しており、更に複数本の配管を並列状態で支持する場合であっても有効な配管吊下支持具を提供することができる。   According to the first aspect of the present invention, it is possible to suppress the cost increase without increasing the troubles at the time of part management and mounting at the site, and also exhibit the vibration proof (seismic proof) property against strong rolls. In addition, it is suitable for holding and supporting lightweight synthetic resin pipes, and even when a plurality of pipes are supported in parallel, an effective pipe suspension support tool can be provided.

特に、吊りボルトによる吊下支持に加えて、横揺れに対する防振(防震)性を発揮する吊下支持杆を、第2配管支持具のバンド抱持部に形成した吊下係止部に挿通固定する構成によって、配管を抱持する部分であるバンド抱持部の最大振れ幅箇所となる真横部を支持することになるので、極めて効果的に横揺れに対する防振(防震)性を発揮させることができる。従って、横揺れ時に生じる、取付面と吊りボルトとの接続部、吊りボルトとタンバックルとの接続部、タンバックルと配管支持具との接続部からバンド抱持部の上端部分までの部分、等の各箇所への負荷を著しく減じることができ、極めて強力な耐震性を発揮させることができる。   In particular, in addition to suspension support by suspension bolts, a suspension support rod that exhibits vibration proofing (seismic isolation) against rolling is inserted into the suspension latch portion formed in the band holding portion of the second pipe support. By fixing the structure, it supports the right lateral part, which is the maximum swing width part of the band holding part, which is the part that holds the pipe, so that the vibration resistance (anti-vibration) against the roll is extremely effectively exhibited. be able to. Therefore, the connection part between the mounting surface and the suspension bolt, the connection part between the suspension bolt and the tambour, the part from the connection part between the tumble buckle and the pipe support to the upper end part of the band holding part, etc. that occur when rolling It is possible to significantly reduce the load on each of the parts, and to exhibit extremely strong earthquake resistance.

特に、重合取付部は、バンド抱持部を切り起こすだけで加工可能であるため、別部材を付加することもないし、切取加工等によって廃棄が必要となる部材も生じることもなく、低コスト化が可能な上に環境適性にも優れている。   In particular, the overlapping mounting part can be processed by simply raising the band-holding part, so there is no need to add another member, and there is no need for disposal due to cutting, etc. In addition to being environmentally friendly.

更に、重合取付部は、上方側取付部と下方側取付部とを重合させた2枚構成を有するので1枚構成に比して強度が増すことになり、別なる配管である第2配管を安定した状態で抱持支持することができる。   Furthermore, since the overlapping attachment portion has a two-sheet configuration in which the upper-side attachment portion and the lower-side attachment portion are overlapped, the strength is increased as compared with the one-sheet configuration. It can be held and supported in a stable state.

請求項2に示す発明によれば、重合取付部の角度を調整することにより吊下支持杆との係合角度等を施工現場の状況に合わせて容易に調整することができる。   According to the second aspect of the present invention, the angle of engagement with the suspension support rod and the like can be easily adjusted according to the situation at the construction site by adjusting the angle of the overlapping mounting portion.

請求項3に示す発明によれば、重合取付部の角度を調整することにより吊下支持杆との係合角度等を施工現場の状況に合わせて容易に調整することができる。特に、この重合取付部の角度の調整は、切起し部分の切起し角度と中途部分の折曲角度又は彎曲角度の二箇所で調整することができるので調整の自由度が極めて高い。   According to the third aspect of the present invention, the angle of engagement with the suspension support rod and the like can be easily adjusted according to the situation at the construction site by adjusting the angle of the overlapping mounting portion. In particular, the adjustment of the angle of the overlapping mounting portion can be adjusted at two points, that is, the cut-and-raised angle of the cut-and-raised portion and the bending angle or the bending angle of the midway portion.

更に、重合取付部が中途部分で折曲又は彎曲する構成によって、この折曲又は彎曲した中途部分が横揺れ時に緩衝機能を発揮することになるので振動(震動)を吸収することができる。従って、極めて高い防振(防震)効果を発揮することができる。   Furthermore, the configuration in which the overlapping attachment portion bends or bends at the midway portion, and the bent or bent midway portion exhibits a buffering function when rolling, so that vibration (vibration) can be absorbed. Accordingly, it is possible to exhibit an extremely high anti-vibration (anti-vibration) effect.

請求項4に示す発明によれば、重合取付部の角度を調整することにより吊下支持杆との係合角度等を施工現場の状況に合わせて容易に調整することができる。特に、この重合重合部の角度の調整は、切起し部分の切起し角度と中途部分の折曲角度又は彎曲角度の二箇所で調整することができるので調整の自由度が極めて高い。   According to the fourth aspect of the present invention, the angle of engagement with the suspension support rod can be easily adjusted according to the situation at the construction site by adjusting the angle of the overlapping mounting portion. In particular, the adjustment of the angle of the polymerization polymerization portion can be adjusted at two places, that is, the cut-and-raised angle of the cut-and-raised portion and the bending angle or the bending angle of the midway portion, so that the degree of freedom of adjustment is extremely high.

更に、重合取付部が中途部分で折曲又は彎曲する構成によって、この折曲又は彎曲した中途部分が横揺れ時に緩衝機能を発揮することになるので振動(震動)を吸収することができる。従って、極めて高い防振(防震)効果を発揮することができる。   Furthermore, the configuration in which the overlapping attachment portion bends or bends at the midway portion, and the bent or bent midway portion exhibits a buffering function when rolling, so that vibration (vibration) can be absorbed. Accordingly, it is possible to exhibit an extremely high anti-vibration (anti-vibration) effect.

請求項5に示す発明によれば、重合取付部の基点部分の強度低下を抑制することができる。   According to the fifth aspect of the present invention, it is possible to suppress a decrease in the strength of the base portion of the polymerization attachment portion.

請求項6に示す発明によれば、第2バンド抱持部の一部を切り起こすだけで吊下支持部が加工可能であるため、別部材を付加することもないし、切取加工等によって廃棄が必要となる部材も生じることもなく、低コスト化が可能な上に環境適性にも優れている。   According to the sixth aspect of the present invention, since the suspension support part can be processed only by raising a part of the second band holding part, there is no need to add another member, and it is discarded by cutting or the like. No necessary members are produced, the cost can be reduced, and the environmental suitability is excellent.

本発明に係る配管吊下支持具の使用状態の第1実施例を示す概略正面図The schematic front view which shows 1st Example of the use condition of the piping suspension support tool which concerns on this invention 図1の配管吊下支持具の第1配管支持具のみを示す5面図(正面図、平面図、底面図、左側面図、A−A断面図)FIG. 5 is a five-side view (front view, plan view, bottom view, left side view, AA sectional view) showing only the first pipe support of the pipe suspension support of FIG. 重合取付部の一例を示す要部拡大断面図An enlarged cross-sectional view of the main part showing an example of a polymerization attachment 第2配管支持具の一例を示す5面図(正面図、平面図、底面図、左側面図、B−B段面図)5-side view showing an example of the second pipe support (front view, plan view, bottom view, left side view, BB step view) 本発明に係る配管吊下支持具の使用状態の第2実施例を示す概略正面図The schematic front view which shows 2nd Example of the use condition of the piping suspension support tool which concerns on this invention 本発明に係る配管吊下支持具の使用状態の第3実施例を示す概略正面図The schematic front view which shows 3rd Example of the use condition of the piping suspension support tool which concerns on this invention

次に、添付の図面に従って本発明を詳細に説明する。   Next, the present invention will be described in detail with reference to the accompanying drawings.

本発明に係る配管吊下支持具は、1〜3本の給水管、給湯管、排水管等の種々配管を、天井スラブに垂設固定された吊りボルトと更に前記天井スラブから斜めに垂設した1本又は2本の吊下支持杆によって防振(防震)状態で2点支持乃至は3点吊下支持するものである。   The pipe suspension support tool according to the present invention includes 1 to 3 water supply pipes, hot water supply pipes, drainage pipes, and other various pipes that are suspended from a ceiling slab and obliquely suspended from the ceiling slab. The one or two suspension support rods are used to support two points or three points in a vibration-proof (vibration-proof) state.

固定支持する種々の配管としては、従来一般的であった鋼管に代わって近年多く用いられるようになった合成樹脂管(ポリエチレン管、架橋ポリエチレン管、ポリブデン管、塩化ビニル管、プロピレン管、ABS管等)の固定支持に本発明は特に有効である。尚、本発明は合成樹脂管の固定支持に特に有効であるが、従来の鋼管の固定支持も可能であり、固定支持する配管として鋼管を排除するものではない。   Synthetic resin pipes (polyethylene pipes, cross-linked polyethylene pipes, polybutene pipes, vinyl chloride pipes, propylene pipes, ABS pipes) that have come to be used in recent years in place of steel pipes that have been generally used as fixed pipes. The present invention is particularly effective for the fixing support. Although the present invention is particularly effective for fixing and supporting synthetic resin pipes, conventional steel pipes can also be fixed and supported, and steel pipes are not excluded as piping for fixing and supporting.

本発明の配管吊下支持具の具体的構成としては、図1及び図2に示すように、配管Pを抱持するバンド抱持部11と該バンド抱持部11の上端部に連接されたバンド端部13を有する配管支持具であって、抱持した配管Pを、天井スラブ等の取付面2から2点又は3点支持するものであり、
配管支持具本体である第1配管支持具1が、2つのバンド抱持部11・11によって配管Pを抱持可能であり、該2つのバンド抱持部11・11の下端部分を組式又は蝶番式の如き接続部12により拡開可能に接続され、前記バンド端部13がタンバックルの如き吊下接続部材31に接続されることで吊りボルト3からの吊下げが可能な構成の配管支持バンドから成り、
前記2つのバンド抱持部11・11の各々について、
該バンド抱持部11の略中央部より上方部分を該略中央部を基点として切起された状態で横方向外側に延伸する上方側取付部14Aが形成され、
且つ、該バンド抱持部11の略中央部より下方部分を該略中央部を基点として切起された状態で横方向外側に延伸する下方側取付部14Bが形成され、
この横方向外側に切起した上方側取付部14Aと下方側取付部14Bとが重合された状態で重合取付部14が形成されており、
更に、この重合取付部14の重合した部分にボルトの如き固定手段(本実施例ではボルト・ナット17)を挿通する透孔15が貫通形成され、
この重合取付部14に、別なる配管支持具である第2配管支持具4が重連状態で接続取付されて該第2配管支持具4に別なる配管である第2配管PPの抱持支持が可能な構成であり、
該第2配管支持具4が、第2バンド抱持部41によって第2配管PPを抱持可能であり、該第2バンド抱持部41の上端部に連設された重連用取付部43と、該第2バンド抱持部41の下端部分に設けられた吊下用係止部44と、を有して成り、
前記重連用取付部43が、ボルトの如き固定手段(本実施例ではボルト・ナット17)を挿通する透孔45が形成され、この重連用取付部43を前記第1配管支持具1の重合取付部14に前記固定手段(本実施例ではボルト・ナット17)を用いて取付固定して重連状態での接続取付が可能な構成であり、
前記吊下係止部44が、前記取付面2に一端が固定されて吊下げられる1本又は2本(本実施例では2本)の吊りボルトの如き吊下支持杆5を挿通する透孔46が形成され、この吊下係止部44の透孔46に前記吊下支持杆5の他端を挿通しナット51により固定して2点又は3点支持(本実施例では3点支持)された状態とする構成である。
As shown in FIGS. 1 and 2, the specific structure of the pipe suspension support tool of the present invention is connected to the band holding part 11 that holds the pipe P and the upper end part of the band holding part 11. A pipe support having a band end 13, which supports the pipe P held at two or three points from the mounting surface 2 such as a ceiling slab,
The 1st piping support tool 1 which is a piping support main body can hold piping P by two band holding parts 11 * 11, and the lower end part of these two band holding parts 11 * 11 is combined or A pipe support having a configuration that can be hung from the suspension bolt 3 by being connected to be able to expand by a connection portion 12 such as a hinge type, and the band end portion 13 is connected to a suspension connection member 31 such as a tangle Consist of bands,
For each of the two band holding portions 11 and 11,
An upper attachment portion 14A is formed that extends outward in the lateral direction in a state where the upper portion of the band holding portion 11 is cut and raised from the substantially central portion.
In addition, a lower attachment portion 14B is formed that extends outward in the lateral direction in a state where the lower portion of the band holding portion 11 is cut and raised from the substantially central portion as a base point.
The overlapping attachment portion 14 is formed in a state in which the upper attachment portion 14A and the lower attachment portion 14B that are cut and raised outward in the lateral direction are superposed.
Furthermore, a through hole 15 through which a fixing means such as a bolt (bolt / nut 17 in this embodiment) is inserted is formed through the overlapped portion of the overlap mounting portion 14.
A second pipe support 4 that is another pipe support is connected and attached to the overlapping mounting portion 14 in a continuous state, and the second pipe PP that is another pipe is held and supported by the second pipe support 4. Is a possible configuration,
The second pipe support 4 is capable of holding the second pipe PP by the second band holding part 41, and a double continuous attachment part 43 provided continuously with the upper end part of the second band holding part 41; A suspension locking portion 44 provided at the lower end portion of the second band holding portion 41,
The multi-continuous mounting portion 43 is formed with a through hole 45 through which a fixing means such as a bolt (bolt / nut 17 in this embodiment) is inserted, and this multi-continuous mounting portion 43 is overlapped with the first pipe support 1. It is a structure that can be connected and fixed in a continuous state by mounting and fixing to the portion 14 using the fixing means (bolts and nuts 17 in this embodiment),
A through hole through which the suspension locking portion 44 is inserted through a suspension support rod 5 such as one or two (two in this embodiment) suspension bolts that are suspended at one end fixed to the mounting surface 2. 46 is formed, and the other end of the suspension support rod 5 is inserted into the through hole 46 of the suspension latching portion 44 and fixed by the nut 51 to support two or three points (in this embodiment, three-point support). It is the structure made into the state made into.

尚、図2に示す符号11A・11Bは、上方側取付部14A・下方側取付部14Bが切り起こされることで孔部となったバンド抱持部11の被切起し孔部である。尚また、図2に示す符号16は、吊下接続部材31にバンド端部13を接続固定するためのボルト・ナットである。   In addition, the code | symbol 11A * 11B shown in FIG. 2 is the to-be-cut-and-raised hole part of the band holding part 11 which became a hole part by cutting and raising the upper side attaching part 14A and the lower side attaching part 14B. In addition, the code | symbol 16 shown in FIG. 2 is a volt | bolt nut for connecting and fixing the band edge part 13 to the suspension connection member 31. FIG.

以下、本発明の構成について更に詳説する。   Hereinafter, the configuration of the present invention will be described in more detail.

本発明の配管支持具を構成する第1配管支持具1及び第2配管支持具4の各々は、この種の配管支持具に用いられる材料として公知公用のものを特別の制限なく用いることができ、好ましくはステンレスやその他の金属製である。   As each of the first pipe support 1 and the second pipe support 4 constituting the pipe support of the present invention, a publicly known material can be used without particular limitation as a material used for this kind of pipe support. Preferably, it is made of stainless steel or other metal.

重合取付部14を構成する上方側取付部14Aと下方側取付部14Bの各々は、バンド抱持部11の略中央部を基点として切起してから外側に方向に向かって立ち上げる際に、図3に示すように、各々の基点部分から前記バンド抱持部11・11の外周面に沿って折り返してから横方向外側に延伸するように折り曲げて重合される構成とすることが好ましい。図3に示す符号14Cは、バンド抱持部11の外周面に沿って折り返した折り返し部である。かかる構成によれば、上方側取付部14A・下方側取付部14Bの基点部分の強度低下を抑制することができる。   When each of the upper side mounting portion 14A and the lower side mounting portion 14B constituting the overlapping mounting portion 14 is raised from the substantially central portion of the band holding portion 11 as a base point and then rising toward the outside, As shown in FIG. 3, it is preferable to be configured to be folded and polymerized from each base portion along the outer peripheral surface of the band holding portions 11 and 11 and then extended outward in the lateral direction. Reference numeral 14 </ b> C illustrated in FIG. 3 is a folded portion that is folded along the outer peripheral surface of the band holding portion 11. According to such a configuration, it is possible to suppress a decrease in strength of the base point portions of the upper attachment portion 14A and the lower attachment portion 14B.

更に、重合取付部14を構成する上方側取付部14Aと下方側取付部14Bの各々について、各々の切起した基点部分をスポット溶接の如き補強手段を用いて補強する構成が好ましく、かかる構成によれば、切起し部分の破断や裂けを抑制できるので、この切起した起点部分の強度を高くすることができる。   Further, for each of the upper side attachment portion 14A and the lower side attachment portion 14B constituting the overlapping attachment portion 14, a configuration in which each cut base point portion is reinforced using a reinforcing means such as spot welding is preferable. According to this, since breakage and tearing of the cut and raised portion can be suppressed, the strength of the cut and raised starting portion can be increased.

更にまた、重合取付部14を構成する上方側取付部14Aと下方側取付部14Bとは、その重合部分をスポット溶接の如き接合手段を用いて接合する構成が好ましく、かかる構成によれば、重合取付部14の重合部分の強度を高くすることができる。   Furthermore, it is preferable that the upper mounting portion 14A and the lower mounting portion 14B constituting the overlapping mounting portion 14 are bonded to each other using a bonding means such as spot welding. The strength of the overlapping portion of the attachment portion 14 can be increased.

重合取付部14の延伸方向構成としては、図1及び図2に示す本第1実施例では、第1配管支持具1の重合取付部14・14の各々が、バンド抱持部11・11の各々の略中央部の基点から外側斜め下方に向かって延伸した形状を有する構成となっている。かかる構成によれば、重合取付部14・14の基点部分からの切起し角度を調整することにより第2配管支持具4による第2配管PPの抱持固定位置を所望の高さに調整することができる。   In the first embodiment shown in FIG. 1 and FIG. 2, the overlapping attachment portions 14 and 14 of the first pipe support 1 are respectively connected to the band holding portions 11 and 11 as the extending direction configuration of the overlapping attachment portions 14. It has the structure which has the shape extended toward the outer side diagonally downward from the base point of each substantially central part. According to such a configuration, the holding and fixing position of the second pipe PP by the second pipe support 4 is adjusted to a desired height by adjusting the cut-and-raised angle from the base part of the overlapping attachment portions 14 and 14. be able to.

また、図1に示す配管吊下支持具の第1実施例に用いられている第2配管支持具4は、図4に示す構成を有している。
即ち、第2配管支持具4が、
両端が接触又は近接して略円形を成して前記第2配管を抱持する第2バンド抱持部41と、
該第2バンド抱持部41の両端部の各々に連設され、前記第1配管支持具1の重合取付部14に接続取付けする重連用取付部43・43と、
前記第2バンド抱持部41の下端部分に垂設する1枚又は2枚(本実施例では2枚)の吊下係止部44・44と、
を有する構成であり、
この吊下係止部44・44は、前記下端部分の1箇所又は平行する2箇所(本実施例では2箇所)を基端として該下端部分より端部方向部分の切り起された状態で該下端部分から垂設する構成であり、
更にこの吊下係止部44・44には、前記吊下支持杆5を挿通する透孔46が形成された構成である。
Moreover, the 2nd piping support tool 4 used for the 1st Example of the piping suspension support tool shown in FIG. 1 has the structure shown in FIG.
That is, the second pipe support 4 is
A second band holding portion 41 for holding the second pipe in a substantially circular shape with both ends in contact or close to each other;
A plurality of attachment portions 43 and 43 connected to and attached to the overlapping attachment portion 14 of the first pipe support 1 connected to both ends of the second band holding portion 41;
One or two (two in this embodiment) suspension locking portions 44, 44 suspended from the lower end portion of the second band holding portion 41;
And a configuration having
The suspension locking portions 44 and 44 are formed in a state where one end portion of the lower end portion or two parallel portions (two portions in this embodiment) are cut and raised in the end direction portion from the lower end portion. It is a structure that hangs from the lower end part,
Further, the suspension locking portions 44 and 44 are formed with a through hole 46 through which the suspension support rod 5 is inserted.

尚、図4に示す符号44Aは、吊下係止部44が切り起こされることで孔部となった第2バンド抱持部41の被切起し孔部である。   In addition, the code | symbol 44A shown in FIG. 4 is a to-be-cut-raised hole part of the 2nd band holding part 41 which became a hole part when the suspension latching | locking part 44 was cut and raised.

上記構成を有する本第1実施例の使用に際しては、図1に示すように、天井スラブ等の取付面2に一端が固定された吊りボルト3にタンバックルの如き吊下接続部材31を介してバンド端部13をボルト・ナット16により固定することで第1配管支持具1を前記取付面2に吊下支持し、この第1配管支持具1の重合取付部14・14に第2配管支持具4・4の重連用取付部43・43をボルト・ナット17・17により固定することで前記第1配管支持具1に第2配管支持具4・4を重連状態で接続取付し、次に、この第2配管支持具4・4の吊下係止部44・44に、前記取付面2に一端が固定され、斜め吊下げする2本の公知公用の吊りボルトの如き吊下支持杆5・5の他端をナット51・51を用いて係合することによって、第1配管支持具1によって1本の配管Pを抱持支持すると共に、2つの第2配管支持具4によって2本の第2配管PPを抱持した状態で、且つ吊りボルト3と2本の吊下支持杆5・5による3点吊下支持が可能となる。   In using the first embodiment having the above-described configuration, as shown in FIG. 1, a suspension bolt 31 having one end fixed to a mounting surface 2 such as a ceiling slab is attached to a suspension bolt 31 such as a tumble buckle. The first pipe support 1 is suspended and supported on the mounting surface 2 by fixing the band end portion 13 with bolts and nuts 16, and the second pipe support is supported on the overlapping mounting parts 14 and 14 of the first pipe support 1. The second pipe support tools 4 and 4 are connected and attached to the first pipe support tool 1 in a continuous state by fixing the multi-continuous mounting parts 43 and 43 of the tools 4 and 4 with bolts and nuts 17 and 17. In addition, a suspension support rod such as two publicly-known suspension bolts, one end of which is fixed to the mounting surface 2 and suspended obliquely to the suspension locking portions 44 and 44 of the second pipe support 4 and 4. By engaging the other ends of 5 and 5 with nuts 51 and 51, the first arrangement The support tool 1 holds and supports one pipe P, and the two second pipe support tools 4 hold the two second pipes PP, and the suspension bolt 3 and the two suspension supports. Three-point suspension support is possible with the hooks 5 and 5.

以上、本発明に係る配管吊下支持具の実施例について説明したが、本発明は上記実施例に限定されず、本発明の範囲内において種々の他の態様を採ることもできる。   As mentioned above, although the Example of the piping suspension support tool which concerns on this invention was described, this invention is not limited to the said Example, A various other aspect can also be taken within the scope of the present invention.

例えば、図5に示す第2実施例では、第1配管支持具1の重合取付部14・14の各々が、バンド抱持部11・11の各々の略中央部の基点から外側斜め上方に向かって延伸すると共に、この延伸した部分の中途部分14Dであって且つ前記透孔15よりも基点側の部分から外側斜め下方に向かって折曲又は彎曲する構成となっている。かかる構成によれば、重合取付部14・14の中途部分14Dの折曲角度又は彎曲角度を調整することにより第2配管支持具4による第2配管PPの抱持固定位置を所望の高さに調整することができる。   For example, in the second embodiment shown in FIG. 5, each of the overlapping attachment portions 14, 14 of the first pipe support 1 is directed obliquely upward and outward from the base point of the substantially central portion of each of the band holding portions 11, 11. In addition, the intermediate portion 14D of the extended portion is bent or bent from the portion closer to the base point than the through hole 15 toward the outer side obliquely downward. According to this structure, the holding fixing position of the 2nd piping PP by the 2nd piping support 4 is made into desired height by adjusting the bending angle or bending angle of the middle part 14D of the superposition | attachment attachment parts 14 * 14. Can be adjusted.

また、図6に示す第3実施例では、第1配管支持具1の重合取付部14・14の各々が、バンド抱持部11・11の各々の略中央部の基点から外側水平方向に向かって延伸すると共に、この延伸した部分の中途部分14Dであって且つ前記透孔15よりも基点側の部分から外側斜め下方に向かって折曲又は彎曲する構成となっている。かかる構成によれば、重合取付部14・14の中途部分14Dの折曲角度又は彎曲角度を調整することにより第2配管支持具4による第2配管PPの抱持固定位置を所望の高さに調整することができる。   Further, in the third embodiment shown in FIG. 6, each of the overlapping attachment portions 14, 14 of the first pipe support 1 is directed in the outer horizontal direction from the base point of the substantially central portion of each of the band holding portions 11, 11. In addition, the intermediate portion 14D of the extended portion is bent or bent from the portion closer to the base point than the through hole 15 toward the outer side obliquely downward. According to this structure, the holding fixing position of the 2nd piping PP by the 2nd piping support 4 is made into desired height by adjusting the bending angle or bending angle of the middle part 14D of the superposition | attachment attachment parts 14 * 14. Can be adjusted.

更に、図1、図4に示す実施例では、第2配管支持具4として第2バンド抱持部41の下端部分が分離していない提灯式構成の配管支持バンドを用いているが、第2バンド抱持部41の加担部分が組式構成や蝶番式構成等の配管支持バンドを用いることもできる。また、第2バンド抱持部41に形成される吊下係止部44は、上記した実施例のように切起し形成に限らず、別部材を付加して形成することもできる。尚、図5に示す第2実施例、図6に示す第3実施例についても同様である。   Further, in the embodiment shown in FIGS. 1 and 4, a pipe support band having a lantern type structure in which the lower end portion of the second band holding part 41 is not separated is used as the second pipe support 4. The supporting part of the band holding part 41 can use a pipe support band such as a combination type structure or a hinge type structure. Moreover, the suspension latching | locking part 44 formed in the 2nd band holding | maintenance part 41 can also be formed not only by raising and raising like the above-mentioned Example but adding another member. The same applies to the second embodiment shown in FIG. 5 and the third embodiment shown in FIG.

更に、図1、図5及び図6に示す実施例では、第1配管支持具1の左右両側に2つの第2配管支持具4を重連状態で接続取付することによって、2本の第2配管PPを抱持支持しているが、左又は右のいずれか一方のみに第2配管支持具4を接続取付することによって1本の第2配管PPを抱持することも本発明に包含される。   Furthermore, in the embodiment shown in FIGS. 1, 5 and 6, two second pipe supports 4 are connected and attached in a continuous state on the left and right sides of the first pipe support 1 so that two second pipe supports 2 are connected. Although the piping PP is held and supported, it is also included in the present invention to hold one second piping PP by connecting and attaching the second piping support 4 only to either the left or the right. The

更にまた、図1、図5及び図6に示す実施例では、吊りボルト3と2本の吊下支持杆5・5による3点吊下支持としているが、施工現場の状況等の諸条件に応じて吊下支持杆5を1本とする2点吊下支持とすることも本発明に包含される。   Furthermore, in the embodiment shown in FIG. 1, FIG. 5 and FIG. 6, it is a three-point suspension support by the suspension bolt 3 and the two suspension support rods 5 and 5, but it is subject to various conditions such as the situation at the construction site. Accordingly, the present invention also includes a two-point suspension support with one suspension support bar 5.

1 第1配管支持具
11 バンド抱持部
11A 被切起し孔部
11B 被切起し孔部
12 接続部
13 バンド端部
14 重合取付部
14A 上方側取付部
14B 下方側取付部
14C 折り返し部
14D 中途部分
15 透孔
16 ボルト・ナット
17 ボルト・ナット
2 天井スラブ・壁面・床面の如き取付面
3 吊りボルト
31 タンバックルの如き吊下接続部材
4 第2配管支持具
41 第2バンド抱持部
43 重連用取付部
44 吊下係止部
44A 被切起し孔部
45 透孔
46 透孔
5 吊下支持杆
51 ナット
P 配管
PP 第2配管
DESCRIPTION OF SYMBOLS 1 1st piping support tool 11 Band holding part 11A Cut-and-raised hole part 11B Cut-and-raised hole part 12 Connection part 13 Band edge part 14 Superimposition attachment part 14A Upper side attachment part 14B Lower side attachment part 14C Folding part 14D Midway portion 15 Through hole 16 Bolt / nut 17 Bolt / nut 2 Mounting surface such as ceiling slab / wall / floor 3 Hanging bolt 31 Suspended connecting member such as tumble buck 4 Second piping support 41 Second band holding portion 43 Double-mounting attachment portion 44 Suspension locking portion 44A Cut-and-raised hole portion 45 Through-hole 46 Through-hole 5 Suspension support rod 51 Nut P Piping PP Second piping

1.配管を抱持するバンド抱持部と該バンド抱持部の上端部に連接されたバンド端部を有する配管支持具であって、抱持した配管を、天井スラブ等の取付面から2点又は3点支持する配管吊下支持具において、
配管支持具本体である第1配管支持具が、2つのバンド抱持部によって配管を抱持可能であり、該2つのバンド抱持部の下端部分を組式又は蝶番式の如き接続部により拡開可能に接続され、前記バンド端部がタンバックルの如き吊下接続部材に接続されることで吊りボルトからの吊下げが可能な構成の配管支持バンドから成り、
前記2つのバンド抱持部の各々について、
該バンド抱持部の略中央部より上方部分を該略中央部を基点として切起された状態で横方向外側に延伸する上方側取付部が形成され、
且つ、該バンド抱持部の略中央部より下方部分を該略中央部を基点として切起された状態で横方向外側に延伸する下方側取付部が形成され、
この横方向外側に切起した上方側取付部と下方側取付部とが重合された状態で重合取付部が形成され、
更に、この重合取付部の重合した部分にボルトの如き固定手段を挿通する透孔が貫通形成され、
この重合取付部に、別なる配管支持具である第2配管支持具が重連状態で接続取付されて該第2配管支持具に別なる配管である第2配管の抱持支持が可能である構成であり、
該第2配管支持具が、第2バンド抱持部によって第2配管を抱持可能であり、該第2バンド抱持部の上端部に連設された重連用取付部と、該第2バンド抱持部の下端部分に設けられた吊下係止部と、を有して成り、
前記重連用取付部が、ボルトの如き固定手段を挿通する透孔が形成され、この重連用取付部を前記第1配管支持具の重合取付部に前記固定手段を用いて取付固定して重連状態での接続取付が可能な構成であり、
前記吊下係止部が、前記取付面に一端が固定されて吊下げられる1本又は2本の吊りボルトの如き吊下支持杆を挿通する透孔が形成され、この吊下係止部の透孔に前記吊下支持杆の他端を挿通固定して2点又は3点支持された状態とする構成であること、
を特徴とする配管吊下支持具。
1. A pipe support having a band holding part for holding a pipe and a band end connected to the upper end of the band holding part, and holding the pipe from the mounting surface such as a ceiling slab or the like. In the pipe suspension support that supports three points,
The first pipe support, which is the main body of the pipe support, can hold the pipe by the two band holding parts, and the lower end portion of the two band holding parts is expanded by a connecting part such as a combination type or a hinge type. It consists of a pipe support band that is configured to be able to be suspended from a suspension bolt by being connected so as to be able to be opened and being connected to a suspension connection member such as a tan buckle.
For each of the two band holding portions,
An upper mounting portion is formed that extends outward in the lateral direction in a state where the upper portion of the band holding portion is cut and raised from the substantially central portion as a base point.
In addition, a lower attachment portion is formed that extends outward in the lateral direction in a state where the lower portion is cut and raised from the substantially central portion as a base point from the substantially central portion of the band holding portion,
A superposed mounting portion is formed in a state where the upper mounting portion and the lower mounting portion which are cut up to the outside in the lateral direction are superposed,
Furthermore, a through hole through which a fixing means such as a bolt is inserted is formed through the overlapped portion of the overlapping mounting portion,
A second pipe support, which is another pipe support, is connected and attached to the superposition attachment portion in a continuous state, and the second pipe, which is another pipe, can be held and supported by the second pipe support. Configuration,
The second pipe support is capable of holding the second pipe by the second band holding part, and the double continuous attachment part connected to the upper end part of the second band holding part, and the second band A suspension locking portion provided at the lower end portion of the holding portion ,
The multi-continuous mounting portion is formed with a through hole through which a fixing means such as a bolt is inserted. The multi-continuous mounting portion is attached and fixed to the overlapping mounting portion of the first pipe support by using the fixing means. It is a configuration that can be connected and installed in the state,
The suspension latch is formed with a through-hole through which a suspension support rod such as one or two suspension bolts suspended at one end fixed to the mounting surface. The other end of the suspension support rod is inserted into and fixed to the through hole, and is in a state of being supported at two or three points,
A piping suspension support characterized by the following.

本発明の配管吊下支持具の具体的構成としては、図1及び図2に示すように、配管Pを抱持するバンド抱持部11と該バンド抱持部11の上端部に連接されたバンド端部13を有する配管支持具であって、抱持した配管Pを、天井スラブ等の取付面2から2点又は3点支持するものであり、
配管支持具本体である第1配管支持具1が、2つのバンド抱持部11・11によって配管Pを抱持可能であり、該2つのバンド抱持部11・11の下端部分を組式又は蝶番式の如き接続部12により拡開可能に接続され、前記バンド端部13がタンバックルの如き吊下接続部材31に接続されることで吊りボルト3からの吊下げが可能な構成の配管支持バンドから成り、
前記2つのバンド抱持部11・11の各々について、
該バンド抱持部11の略中央部より上方部分を該略中央部を基点として切起された状態で横方向外側に延伸する上方側取付部14Aが形成され、
且つ、該バンド抱持部11の略中央部より下方部分を該略中央部を基点として切起された状態で横方向外側に延伸する下方側取付部14Bが形成され、
この横方向外側に切起した上方側取付部14Aと下方側取付部14Bとが重合された状態で重合取付部14が形成されており、
更に、この重合取付部14の重合した部分にボルトの如き固定手段(本実施例ではボルト・ナット17)を挿通する透孔15が貫通形成され、
この重合取付部14に、別なる配管支持具である第2配管支持具4が重連状態で接続取付されて該第2配管支持具4に別なる配管である第2配管PPの抱持支持が可能な構成であり、
該第2配管支持具4が、第2バンド抱持部41によって第2配管PPを抱持可能であり、該第2バンド抱持部41の上端部に連設された重連用取付部43と、該第2バンド抱持部41の下端部分に設けられた吊下係止部44と、を有して成り、
前記重連用取付部43が、ボルトの如き固定手段(本実施例ではボルト・ナット17)を挿通する透孔45が形成され、この重連用取付部43を前記第1配管支持具1の重合取付部14に前記固定手段(本実施例ではボルト・ナット17)を用いて取付固定して重連状態での接続取付が可能な構成であり、
前記吊下係止部44が、前記取付面2に一端が固定されて吊下げられる1本又は2本(本実施例では2本)の吊りボルトの如き吊下支持杆5を挿通する透孔46が形成され、この吊下係止部44の透孔46に前記吊下支持杆5の他端を挿通しナット51により固定して2点又は3点支持(本実施例では3点支持)された状態とする構成である。
As shown in FIGS. 1 and 2, the specific structure of the pipe suspension support tool of the present invention is connected to the band holding part 11 that holds the pipe P and the upper end part of the band holding part 11. A pipe support having a band end 13, which supports the pipe P held at two or three points from the mounting surface 2 such as a ceiling slab,
The 1st piping support tool 1 which is a piping support main body can hold piping P by two band holding parts 11 * 11, and the lower end part of these two band holding parts 11 * 11 is combined or A pipe support having a configuration that can be hung from the suspension bolt 3 by being connected to be able to expand by a connection portion 12 such as a hinge type, and the band end portion 13 is connected to a suspension connection member 31 such as a tangle Consist of bands,
For each of the two band holding portions 11 and 11,
An upper attachment portion 14A is formed that extends outward in the lateral direction in a state where the upper portion of the band holding portion 11 is cut and raised from the substantially central portion.
In addition, a lower attachment portion 14B is formed that extends outward in the lateral direction in a state where the lower portion of the band holding portion 11 is cut and raised from the substantially central portion as a base point.
The overlapping attachment portion 14 is formed in a state in which the upper attachment portion 14A and the lower attachment portion 14B that are cut and raised outward in the lateral direction are superposed.
Furthermore, a through hole 15 through which a fixing means such as a bolt (bolt / nut 17 in this embodiment) is inserted is formed through the overlapped portion of the overlap mounting portion 14.
A second pipe support 4 that is another pipe support is connected and attached to the overlapping mounting portion 14 in a continuous state, and the second pipe PP that is another pipe is held and supported by the second pipe support 4. Is a possible configuration,
The second pipe support 4 is capable of holding the second pipe PP by the second band holding part 41, and a double continuous attachment part 43 provided continuously with the upper end part of the second band holding part 41; A suspension locking portion 44 provided at the lower end portion of the second band holding portion 41,
The multi-continuous mounting portion 43 is formed with a through hole 45 through which a fixing means such as a bolt (bolt / nut 17 in this embodiment) is inserted, and this multi-continuous mounting portion 43 is overlapped with the first pipe support 1. It is a structure that can be connected and fixed in a continuous state by mounting and fixing to the portion 14 using the fixing means (bolts and nuts 17 in this embodiment),
A through hole through which the suspension locking portion 44 is inserted through a suspension support rod 5 such as one or two (two in this embodiment) suspension bolts that are suspended at one end fixed to the mounting surface 2. 46 is formed, and the other end of the suspension support rod 5 is inserted into the through hole 46 of the suspension latching portion 44 and fixed by the nut 51 to support two or three points (in this embodiment, three-point support). It is the structure made into the state made into.

Claims (6)

配管を抱持するバンド抱持部と該バンド抱持部の上端部に連接されたバンド端部を有する配管支持具であって、抱持した配管を、天井スラブ等の取付面から2点又は3点支持する配管吊下支持具において、
配管支持具本体である第1配管支持具が、2つのバンド抱持部によって配管を抱持可能であり、該2つのバンド抱持部の下端部分を組式又は蝶番式の如き接続部により拡開可能に接続され、前記バンド端部がタンバックルの如き吊下接続部材に接続されることで吊りボルトからの吊下げが可能な構成の配管支持バンドから成り、
前記2つのバンド抱持部の各々について、
該バンド抱持部の略中央部より上方部分を該略中央部を基点として切起された状態で横方向外側に延伸する上方側取付部が形成され、
且つ、該バンド抱持部の略中央部より下方部分を該略中央部を基点として切起された状態で横方向外側に延伸する下方側取付部が形成され、
この横方向外側に切起した上方側取付部と下方側取付部とが重合された状態で重合取付部が形成され、
更に、この重合取付部の重合した部分にボルトの如き固定手段を挿通する透孔が貫通形成され、
この重合取付部に、別なる配管支持具である第2配管支持具が重連状態で接続取付されて該第2配管支持具に別なる配管である第2配管の抱持支持が可能である構成であり、
該第2配管支持具が、第2バンド抱持部によって第2配管を抱持可能であり、該第2バンド抱持部の上端部に連設された重連用取付部と、該第2バンド抱持部の下端部分に設けられた吊下用係止部と、を有して成り、
前記重連用取付部が、ボルトの如き固定手段を挿通する透孔が形成され、この重連用取付部を前記第1配管支持具の重合取付部に前記固定手段を用いて取付固定して重連状態での接続取付が可能な構成であり、
前記吊下係止部が、前記取付面に一端が固定されて吊下げられる1本又は2本の吊りボルトの如き吊下支持杆を挿通する透孔が形成され、この吊下係止部の透孔に前記吊下支持杆の他端を挿通固定して2点又は3点支持された状態とする構成であること、
を特徴とする配管吊下支持具。
A pipe support having a band holding part for holding a pipe and a band end connected to the upper end of the band holding part, and holding the pipe from the mounting surface such as a ceiling slab or the like. In the pipe suspension support that supports three points,
The first pipe support, which is the main body of the pipe support, can hold the pipe by the two band holding parts, and the lower end portion of the two band holding parts is expanded by a connecting part such as a combination type or a hinge type. It consists of a pipe support band that is configured to be able to be suspended from a suspension bolt by being connected so as to be able to be opened and being connected to a suspension connection member such as a tan buckle.
For each of the two band holding portions,
An upper mounting portion is formed that extends outward in the lateral direction in a state where the upper portion of the band holding portion is cut and raised from the substantially central portion as a base point.
In addition, a lower attachment portion is formed that extends outward in the lateral direction in a state where the lower portion is cut and raised from the substantially central portion as a base point from the substantially central portion of the band holding portion,
A superposed mounting portion is formed in a state where the upper mounting portion and the lower mounting portion which are cut up to the outside in the lateral direction are superposed,
Furthermore, a through hole through which a fixing means such as a bolt is inserted is formed through the overlapped portion of the overlapping mounting portion,
A second pipe support, which is another pipe support, is connected and attached to the superposition attachment portion in a continuous state, and the second pipe, which is another pipe, can be held and supported by the second pipe support. Configuration,
The second pipe support is capable of holding the second pipe by the second band holding part, and the double continuous attachment part connected to the upper end part of the second band holding part, and the second band A suspension locking portion provided at the lower end portion of the holding portion,
The multi-continuous mounting portion is formed with a through hole through which a fixing means such as a bolt is inserted. The multi-continuous mounting portion is attached and fixed to the overlapping mounting portion of the first pipe support by using the fixing means. It is a configuration that can be connected and installed in the state,
The suspension latch is formed with a through-hole through which a suspension support rod such as one or two suspension bolts suspended at one end fixed to the mounting surface. The other end of the suspension support rod is inserted into and fixed to the through hole, and is in a state of being supported at two or three points,
A piping suspension support characterized by the following.
前記重合取付部の各々が、外側斜め下方に向かった状態で延伸する構成であることを特徴とする請求項1に記載の配管吊下支持具。 The pipe suspension support according to claim 1, wherein each of the overlapping attachment portions is configured to extend in a state of being directed obliquely outward and downward. 前記重合取付部の各々が、前記した略中央部の基点から外側斜め上方に向かって延伸すると共に、この延伸した部分の中途部分であって且つ前記透孔よりも基点つ側の部分において折曲られた状態又は湾曲された状態で外側斜め下方に向かった状態で延伸する構成であることを特徴とする請求項1に記載の配管吊下支持具。 Each of the overlapping mounting portions extends obliquely upward and outward from the base point of the substantially central portion described above, and is bent at a midway portion of the extended portion and at a portion closer to the base point than the through hole. The pipe suspension support tool according to claim 1, wherein the pipe suspension support tool is configured to extend in a state of being bent or curved and facing outward and obliquely downward. 前記重合取付部の各々が、前記した略中央部の基点から外側水平方向に向かって延伸すると共に、この延伸した部分の中途部分であって且つ前記透孔よりも基点側の部分において折曲られた状態又は湾曲された状態で外側斜め下方に向かった状態で延伸する構成であることを特徴とする請求項1に記載の配管吊下支持具。 Each of the overlapping mounting portions extends from the base point of the substantially central portion toward the outer horizontal direction, and is bent in a portion in the middle of the extended portion and on the base point side of the through hole. The pipe suspension support tool according to claim 1, wherein the pipe suspension support tool is configured to extend in a state of being bent or curved and directed obliquely downward toward the outside. 前記上方側取付部と前記下方側取付部の各々が、その基点部分から前記バンド抱持部の外周面に沿って折り返し横方向外側に延伸するように折曲された状態で重合された構成であることを特徴とする請求項1〜4のいずれかに記載の配管吊下支持具。 Each of the upper side attachment portion and the lower side attachment portion is polymerized in a state in which the upper side attachment portion and the lower side attachment portion are folded so as to extend outward in the lateral direction along the outer peripheral surface of the band holding portion. The pipe suspension support tool according to claim 1, wherein the pipe suspension support tool is provided. 前記第2配管支持具が、
両端が接触又は近接して略円形を成して前記第2配管を抱持する第2バンド抱持部と、
該第2バンド抱持部の両端部の各々に連設され、前記第1配管支持具の重合取付部に接続取付けする重連用取付部と、
前記第2バンド抱持部の下端部分に垂設する1枚又は2枚の吊下係止部と、
を有する構成であり、
この1枚又は2枚の吊下係止部は、前記下端部分の1箇所又は平行する2箇所を基端として該下端部分より端部方向部分の切り起された状態で該下端部分から垂設する構成であり、
更にこの1枚又は2枚の吊下係止部には、前記吊下支持杆を挿通する透孔が形成された構成であること、
を特徴とする請求項1〜5のいずれかに記載の配管吊下支持具。
The second pipe support is
A second band holding portion for holding the second pipe in a substantially circular shape with both ends in contact or close to each other;
A continuous attachment part connected to and attached to the overlapping attachment part of the first pipe support, connected to each of both ends of the second band holding part;
One or two suspension latching portions suspended from the lower end portion of the second band holding portion;
And a configuration having
The one or two suspension latching portions are suspended from the lower end portion in a state where the end direction portion is cut and raised from the lower end portion, with one base of the lower end portion or two parallel portions as the base ends. Is a configuration to
Furthermore, the one or two suspension locking portions have a structure in which a through hole is formed through which the suspension support rod is inserted.
The pipe suspension support according to any one of claims 1 to 5.
JP2016014346A 2016-01-28 2016-01-28 Pipe suspension support Expired - Fee Related JP6160719B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016014346A JP6160719B1 (en) 2016-01-28 2016-01-28 Pipe suspension support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016014346A JP6160719B1 (en) 2016-01-28 2016-01-28 Pipe suspension support

Publications (2)

Publication Number Publication Date
JP6160719B1 JP6160719B1 (en) 2017-07-12
JP2017133608A true JP2017133608A (en) 2017-08-03

Family

ID=59308860

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016014346A Expired - Fee Related JP6160719B1 (en) 2016-01-28 2016-01-28 Pipe suspension support

Country Status (1)

Country Link
JP (1) JP6160719B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6326683B1 (en) * 2016-12-22 2018-05-23 株式会社アカギ Pipe suspension support
JP6326682B1 (en) * 2016-12-22 2018-05-23 株式会社アカギ Pipe suspension support
JP6326681B1 (en) * 2016-12-22 2018-05-23 株式会社アカギ Pipe suspension support
WO2019009045A1 (en) 2017-07-07 2019-01-10 三菱重工サーマルシステムズ株式会社 Air conditioning control device, environment setting terminal, air conditioning control method, and program

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108397510B (en) * 2018-03-28 2022-03-08 深圳市德达医疗科技集团有限公司 Vibration damper of compressor for oxygenerator
CN111853363B (en) * 2020-07-14 2021-09-07 合肥元康环境科技有限公司 Rectangular air pipe steel wire rope anti-seismic support system
CN111895181B (en) * 2020-08-13 2021-12-14 泉州元品顿机械科技有限公司 Circular pipe gallery supporting and hanging frame

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60137290U (en) * 1984-02-22 1985-09-11 石川島播磨重工業株式会社 Piping support device
US4793578A (en) * 1987-11-09 1988-12-27 Howard Harold L Multiple conduit support system
JPH06117576A (en) * 1992-10-06 1994-04-26 Takenaka Komuten Co Ltd Support device for piping
JP2001074170A (en) * 1999-09-02 2001-03-23 Takeo Hanaoka Earthquake resisting support for pipe
JP3152068U (en) * 2009-05-01 2009-07-16 有限会社アールストーン Suspension for pipe support

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60137290U (en) * 1984-02-22 1985-09-11 石川島播磨重工業株式会社 Piping support device
US4793578A (en) * 1987-11-09 1988-12-27 Howard Harold L Multiple conduit support system
JPH06117576A (en) * 1992-10-06 1994-04-26 Takenaka Komuten Co Ltd Support device for piping
JP2001074170A (en) * 1999-09-02 2001-03-23 Takeo Hanaoka Earthquake resisting support for pipe
JP3152068U (en) * 2009-05-01 2009-07-16 有限会社アールストーン Suspension for pipe support

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6326683B1 (en) * 2016-12-22 2018-05-23 株式会社アカギ Pipe suspension support
JP6326682B1 (en) * 2016-12-22 2018-05-23 株式会社アカギ Pipe suspension support
JP6326681B1 (en) * 2016-12-22 2018-05-23 株式会社アカギ Pipe suspension support
JP2018105321A (en) * 2016-12-22 2018-07-05 株式会社アカギ Piping suspension support tool
JP2018105320A (en) * 2016-12-22 2018-07-05 株式会社アカギ Piping suspension support tool
JP2018105322A (en) * 2016-12-22 2018-07-05 株式会社アカギ Piping suspension support tool
WO2019009045A1 (en) 2017-07-07 2019-01-10 三菱重工サーマルシステムズ株式会社 Air conditioning control device, environment setting terminal, air conditioning control method, and program

Also Published As

Publication number Publication date
JP6160719B1 (en) 2017-07-12

Similar Documents

Publication Publication Date Title
JP6160719B1 (en) Pipe suspension support
JP6142438B2 (en) Pipe suspension support
JP3153187U (en) Pipe suspension support
JP5900761B1 (en) Pipe suspension support
JP3153185U (en) Pipe suspension support
JP3153546U (en) Pipe suspension support
JP6083584B1 (en) Pipe suspension support
JP3153186U (en) Pipe suspension support
JP5995024B1 (en) Piping support
JP5900765B1 (en) Pipe suspension support
JP3152657U (en) Pipe suspension support
JP5900762B1 (en) Pipe suspension support
JP6326680B1 (en) Pipe suspension support
JP6424411B2 (en) Plumbing suspension support
JP2017206884A (en) Substrate structure of suspended ceiling
JP6326683B1 (en) Pipe suspension support
JP6273659B1 (en) Pipe suspension support
JP6326681B1 (en) Pipe suspension support
JP6326682B1 (en) Pipe suspension support
JP6273660B1 (en) Pipe suspension support
JP5995026B1 (en) Piping support
JP5995025B1 (en) Piping support
JP6123141B1 (en) Piping support
JP6550616B2 (en) Suspension support structure for piping provided with a plurality of piping suspension supports
RU2330205C1 (en) Device to fasten pipeline, primarily, air duct

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170516

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20170529

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170529

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20170529

R150 Certificate of patent or registration of utility model

Ref document number: 6160719

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees