JP2016115114A - Construction method and construction system for electric instrument equipment in power station by using rfid - Google Patents

Construction method and construction system for electric instrument equipment in power station by using rfid Download PDF

Info

Publication number
JP2016115114A
JP2016115114A JP2014252829A JP2014252829A JP2016115114A JP 2016115114 A JP2016115114 A JP 2016115114A JP 2014252829 A JP2014252829 A JP 2014252829A JP 2014252829 A JP2014252829 A JP 2014252829A JP 2016115114 A JP2016115114 A JP 2016115114A
Authority
JP
Japan
Prior art keywords
conduit
stored
data server
installation image
image information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2014252829A
Other languages
Japanese (ja)
Inventor
智貴 坂田
Tomotaka Sakata
智貴 坂田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi GE Nuclear Energy Ltd
Original Assignee
Hitachi GE Nuclear Energy Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi GE Nuclear Energy Ltd filed Critical Hitachi GE Nuclear Energy Ltd
Priority to JP2014252829A priority Critical patent/JP2016115114A/en
Publication of JP2016115114A publication Critical patent/JP2016115114A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Electric Cable Installation (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To realize a construction system for electric instrument equipment in a power station by using RFID so as to make it possible to easily confirm an installation position of an electrical conduit to be buried and a specification of the electrical conduit without fault and to easily confirm the difference between the installation position after installation of the electrical conduit and the specification of the electrical conduit and those in design information.SOLUTION: A contractor installs a buried electrical conduit 3 in accordance with installation information on the buried electrical conduit 3 displayed on a mobile terminal 13 in three dimensions, reads information of an RFID tag 12 bonded to the buried electrical conduit 3 after installation, and transfers installation position information after constructing the buried electrical conduit 3 to a data server 10. A processing unit 10B of the data server 10 compares the installation position information after constructing the buried electrical conduit 3 with design information, and transfers a different portion between the construction and the design information, if any, and a re-construction instruction to the mobile terminal 13 so that the different portion and the re-construction instruction are displayed on the mobile terminal 13.SELECTED DRAWING: Figure 4

Description

本発明は、原子力発電所等の発電所における電気計装設備に係り、RFIDを用いた埋設電線管の施工方法および施工システムに関する。   The present invention relates to an electrical instrumentation facility in a power plant such as a nuclear power plant, and more particularly to a construction method and a construction system for a buried conduit using RFID.

国内の原子力発電所等の発電所における電気計装設備の施工を行う際、電源用ケーブルや制御計装用ケーブルの布設を行う場合には、ケーブル布設ルート(電路)として埋設電線管の施工が実施されている。埋設電線管は建屋躯体(床・壁・天井)の内部に電線管を設置する施工方法であり、コンクリートの打設前に鉄筋の間に電線管を設定し、コンクリート打設後に躯体内部に設定された電線管を利用してケーブルを布設する施工方法である。   When installing electrical instrumentation equipment at power stations such as nuclear power stations in Japan, when installing power cables and control instrumentation cables, construction of buried conduits as cable installation routes (electric circuits) Has been. The buried conduit is a construction method in which the conduit is installed inside the building housing (floor, wall, ceiling). The conduit is set between the reinforcing bars before placing concrete and set inside the housing after placing concrete. This is a construction method in which a cable is laid using the formed conduit.

埋設電線管は、電気計装設備の機能に応じて要求される系統分離(安全系異区分の分離、安全系設備・常用系設備の分離)を実現するため、異区分のケーブルが混在することが無いように、各区分のケーブルを纏めて布設することができるように設計される。   For buried conduits, cables of different categories must be mixed to achieve system separation (separation of different types of safety systems, separation of safety system facilities and normal system facilities) required according to the function of the electrical instrumentation equipment. It is designed so that the cables of each section can be laid together so that there is no occurrence.

また、埋設電線管はケーブル布設長を最短にし、ケーブル布設に要する工事期間を短縮することを目的として、ケーブルの発点・着点機器の配置を明確にした上で、各機器の端子台近傍に立ち上がるように設計される。   In addition, for the purpose of shortening the cable laying length and shortening the construction period required for cable laying for buried conduits, the location of the cable starting and landing equipment is clarified and the vicinity of the terminal block of each equipment Designed to stand up to.

上記の埋設電線管施工は、国内では一般的に使用される施工方法であり、工事期間短縮・工程管理のためには必須の方法と考えられる。   The above-mentioned buried conduit construction is a construction method generally used in Japan, and is considered an indispensable method for shortening the construction period and managing the process.

特許文献1には原子力発電所の埋設電線管位置案内システムが記載され、このシステムにおいては、埋設電電線管の位置を施工後に容易に確認することを可能とするため、電線管にRFIDタグとアンテナを設け、タグリーダで埋設物の位置情報を読み取るとともに、周囲の近接物を確認可能とし、工事完了後の埋設電線管の位置特定を行うことができる。   Patent Document 1 describes a buried electric conduit position guide system for a nuclear power plant. In this system, an RFID tag and an electric conduit are attached to a conduit so that the position of the buried electric conduit can be easily confirmed after construction. An antenna is provided, and the position information of the embedded object can be read with a tag reader, and nearby objects can be confirmed, and the position of the embedded conduit after the completion of construction can be specified.

また、特許文献2には、原子力発電所の建設工事において、機器及び配管の完成状態を現実空間に投影し、位置を合わせて据付を行う方法が記載されている。この特許文献2に記載された方法は、機器及び配管の周辺設備との干渉有無を確認する目的に有効である。   Patent Document 2 describes a method for projecting a completed state of equipment and piping to a real space and performing installation by matching the positions in construction work of a nuclear power plant. The method described in Patent Document 2 is effective for the purpose of confirming the presence or absence of interference with peripheral equipment of equipment and piping.

特開2010−164353号公報JP 2010-164353 A 特開2009−002803号公報JP 2009-002803 A

建物の躯体が設置される前、ケーブルを接続する機器が配置される前に、必要な位置に電線管の設置を行う必要がある。このため、設計者から図面にて電線管等の施工の指示を施行者に行い、施工を行う現地では情報が輻輳して記載された図面に従って、電線管のルート並びに立上げ位置どおりに施工する必要がある。   It is necessary to install the conduit at the required position before the building frame is installed and before the equipment for connecting the cables is placed. For this reason, the construction instructions for the conduits, etc. are given to the enforcer from the designer in the drawings, and the construction is carried out according to the route of the conduits and the start-up position according to the drawings where the information is congested. There is a need.

電線管等の施工作業において施工ミスが発生すると、ケーブルを要求された位置に接続することができなくなるが、コンクリート打設後の電線管の再設定は不可能である。   If a construction error occurs in the construction work of the conduit, etc., the cable cannot be connected to the required position, but the conduit cannot be reset after placing the concrete.

また、施工する電線管にはサイズ・管壁厚さ・材質等の仕様に相違があり、内部に布設するケーブルの用途(動力回路/制御回路/計測回路、安全系/常用系システム、安全系の区分等)にも相違があり、設計にて指摘する仕様の電線管を、離隔距離や発・着点を考慮して設計した経路に合わせて布設する必要があり、誤った仕様の電線管を設定してしまうと、コンクリート打設後の電線管再設定は不可能となる。   In addition, there are differences in specifications such as size, pipe wall thickness, and material for the construction conduits, and the use of cables laid inside (power circuit / control circuit / measurement circuit, safety system / usual system, safety system) ), Etc.), there is also a difference, and it is necessary to install the conduit with the specification pointed out in the design according to the route designed in consideration of the separation distance and the start / end point. If it is set, it is impossible to reset the conduit after placing concrete.

一方、欧州を始めとする海外での原子力発電所建設工事を調査した結果、海外では埋設電線管は一般的に施工されていない。今後、海外での原子力発電所等の発電所建設を計画する場合、工事期間短縮・工程管理のために埋設電線管の施工を実施する必要があるが、現地の施工業者は埋設電線管の施工経験を持っていない場合が多く、埋設電線管施工図による詳細な施工指示も受けた経験が少ないことから、施工時のトラブルや施工ミス、後戻り作業が発生することが予想される。   On the other hand, as a result of investigating the construction of nuclear power plants overseas, including Europe, buried conduits are not generally constructed overseas. In the future, when planning the construction of a power plant such as a nuclear power plant overseas, it will be necessary to construct a buried conduit to shorten the construction period and control the process. Since there are many cases where there is no experience and there is little experience of receiving detailed construction instructions based on the buried conduit construction drawings, it is expected that troubles during construction, construction mistakes, and back work will occur.

したがって、経験の少ない施工業者による施工ミスを低減するためには、施工業者に対する明確な施工指示や施工前確認の方法が必要である。   Therefore, in order to reduce construction mistakes by construction contractors with little experience, clear construction instructions for construction contractors and confirmation methods before construction are necessary.

特許文献1に記載された原子力発電所の埋設電線管位置案内システムは、工事完了後の埋設電線管の位置特定には有効であるが、工事前・工事中に電線管設定位置を確認する目的には適しておらず、経験の少ない施工業者による施工ミスを低減するために、施工業者に対する明確な施工指示や施工前確認の方法として利用することはできない。   The buried electric pipe position guidance system of nuclear power plant described in Patent Document 1 is effective for specifying the position of the buried electric pipe after the completion of construction, but the purpose is to confirm the conduit setting position before and during construction. In order to reduce construction mistakes by contractors with little experience, it cannot be used as a clear construction instruction or confirmation method prior to construction.

また、特許文献2は、機器及び配管の周辺設備との干渉有無を確認する目的には有効であるが、工事前に埋設電線管の施工位置を確認するためには、躯体(床・壁・天井)が建設される前に確認を実施する必要があり、躯体建設前に空中に電線管を投影することは困難であると考える。更に、完成状態の投影では電線管の位置情報以外は確認できず、電線管のサイズ・材質や搭載されるケーブルの安全区分等、施工ミスを防ぐために必要となる情報の確認ができないことから、施工業者に対する明確な施工指示や施工前確認の方法として利用することはできない。   Patent Document 2 is effective for the purpose of confirming the presence or absence of interference with peripheral equipment of equipment and piping. However, in order to confirm the construction position of the buried conduit before construction, a frame (floor, wall, It is necessary to carry out confirmation before the ceiling) is constructed, and it is difficult to project the conduit in the air before constructing the frame. Furthermore, since the projection of the completed state can not be confirmed except for the position information of the conduit, information necessary to prevent construction errors such as the size and material of the conduit and the safety classification of the cable to be installed cannot be confirmed. It cannot be used as a clear construction instruction or confirmation method prior to construction.

上記課題を解決するためには、現地にて施工業者が、設計にて指示された埋設電線管の設定位置を誤りなく容易に確認することができると同時に、設定する電線管の仕様(サイズ・材質等)を誤りなく容易に確認することが可能となる方法を実現する必要がある。   In order to solve the above problems, the contractor at the site can easily confirm the setting position of the buried conduit specified by the design without any errors, and at the same time, the specifications (size, size, It is necessary to realize a method that enables easy confirmation of material and the like without error.

本発明の目的は、埋設すべき電線管の設置位置及びその電線管の仕様を誤りなく、容易に確認できるとともに、電線管設置後の設置位置及びその電線管の仕様と設計情報との相違を容易に確認可能な、RFIDを用いた発電所における電気計装設備の施工方法および施工システムを実現することである。   The object of the present invention is to easily confirm the installation position of the conduit to be buried and the specification of the conduit without error, and to determine the difference between the installation position after the conduit installation and the specification and design information of the conduit. It is to realize a construction method and construction system for electrical instrumentation equipment in a power plant using RFID that can be easily confirmed.

上記目的を達成するため、本発明は次のように構成される。   In order to achieve the above object, the present invention is configured as follows.

RFIDを用いた発電所における電気計装設備の施工方法において、発電所の構造物に埋設する電線管に、この電線管の仕様情報が格納されたRFIDタグを貼付し、上記RFIDタグが貼付された上記電線管を、上記構造物への上記電線管の設置位置を示す3次元表示電線管設置画像情報に従って上記構造物に設置し、設置した電線管に貼付されたRFIDタグに格納された上記電線管の仕様情報を読み取り、上記構造物に設置した上記電線管が、上記3次元表示電線管設置画像情報に示された電線管配置位置に設置されているか否かを判断する。   In the construction method of electrical instrumentation equipment in a power plant using RFID, an RFID tag storing specification information of the conduit is pasted on a conduit embedded in the power plant structure, and the RFID tag is pasted. The conduit is installed in the structure according to the three-dimensional display conduit installation image information indicating the installation position of the conduit on the structure, and stored in an RFID tag attached to the installed conduit. The specification information of the conduit is read, and it is determined whether or not the conduit installed in the structure is installed at the conduit arrangement position indicated in the three-dimensional display conduit installation image information.

また、RFIDを用いた発電所における電気計装設備の施工システムにおいて、発電所の構造物に埋設する電線管の設置位置を表示する3次元表示電線管設置画像情報が格納されるデータサーバの記憶部と、この記憶部に格納された電線管の仕様情報が格納され、上記電線管に貼付されるRFIDタグと、上記記憶部に格納された上記3次元表示電線管設置画像を表示するモバイル端末と、上記構造物に設置された電線管に貼付された上記RFIDタグに格納された上記電線管の仕様情報を読み取るRFIDリーダーと、このRFIDリーダーにより読み取られた上記電線管の仕様情報に基いて、上記3次元表示電線管設置画像情報に示された電線管の設置位置に上記電線管が設置されているか否かを判断するデータサーバの処理部とを備える。   In addition, in a construction system for electrical instrumentation equipment in a power plant using RFID, memory of a data server in which three-dimensional display conduit installation image information for displaying the installation position of the conduit embedded in the power plant structure is stored. Mobile terminal for storing specification information of the conduits stored in the storage unit, the RFID tag attached to the conduits, and the three-dimensional display conduit installation image stored in the storage unit And an RFID reader that reads the specification information of the conduit that is stored in the RFID tag attached to the conduit installed in the structure, and the specification information of the conduit that is read by the RFID reader. A data server processing unit for determining whether or not the conduit is installed at the conduit installation position indicated in the three-dimensional display conduit installation image information. .

埋設すべき電線管の設置位置及びその電線管の仕様を誤りなく、容易に確認できるとともに、電線管設置後の設置位置及びその電線管の仕様と設計情報との相違を容易に確認可能な、RFIDを用いた発電所における電気計装設備の施工方法および施工システムを実現することができる。   The installation position of the conduit to be buried and the specification of the conduit can be easily confirmed without error, and the difference between the installation position after the conduit installation and the specification and design information of the conduit can be easily confirmed. A construction method and construction system for electrical instrumentation equipment in a power plant using RFID can be realized.

原子力発電所等の発電所内に設置される埋設電線管(電気計装設備)の概要を示す図である。It is a figure which shows the outline | summary of the buried conduit (electrical instrumentation equipment) installed in power plants, such as a nuclear power plant. 埋設電線管の施工方法の説明図である。It is explanatory drawing of the construction method of a buried electric conduit. 埋設電線管3の曲加工及び埋設電線管3同士の接続の説明図である。It is explanatory drawing of the bending process of the buried electrical conduit 3, and the connection between the buried electrical conduits 3. FIG. RFIDを用いた埋設電線管施工確認システムの全体構成図である。1 is an overall configuration diagram of a buried conduit construction confirmation system using RFID. FIG. 本願の実施例1による設電線管施工管理システムを用いた電線管確認作業の手順フローを示す図である。It is a figure which shows the procedure flow of the conduit confirmation operation | work using the installation conduit construction management system by Example 1 of this application. 本発明の実施例2による埋設電線管施工管理システムにおける電線管設計変更作業の説明図である。It is explanatory drawing of the conduit design change work in the buried conduit construction management system by Example 2 of this invention. 本発明の実施例2による埋設電線管施工管理システムを用いた電線管設計変更作業の手順フローを示す図である。It is a figure which shows the procedure flow of the conduit design change work using the buried conduit construction management system by Example 2 of this invention.

本発明は、施工業者がモバイル端末を現場に持ち込み、設計情報を入力した3D−CADにより埋設電線管の設定位置を目視で確認することができる構成を備える。   The present invention has a configuration in which a contractor brings a mobile terminal to the site and can visually confirm the set position of the buried conduit by 3D-CAD into which design information is input.

更に、施工する電線管の仕様(サイズ・材質等)が設計情報と相違ないことを確認するために、RFIDタグに電線管の仕様(サイズ・材質等)及び設計情報(管理番号、施工図の図書番号および改定番号等)を登録し、対象とする電線管にRFIDタグを貼り付けると共に、RFIDリーダーを用いて現場で情報を確認し、モバイル端末に表示される設計情報と相違が無いことを目視で確認することができる。   Furthermore, in order to confirm that the specifications (size, material, etc.) of the conduit to be constructed are not different from the design information, the specifications (size, material, etc.) and design information (control number, construction drawing) (Book number, revision number, etc.) are registered, RFID tags are affixed to the target conduits, information is confirmed on site using an RFID reader, and there is no difference from design information displayed on the mobile terminal. It can be confirmed visually.

埋設電線管の施工情報(設定位置、電線管の仕様等)は設計者がデータベースに登録し、3D−CADを用いて設定位置や立上げ箇所等が3次元的に確認できるものとする。また、設計者が3D−CADに登録する電線管データには、電線管のサイズ・材質等の仕様、電線管毎に指定される管理番号、参照する施工図の図書番号と改定番号、その他必要な設計情報を登録可能なものとし、設計情報の決定あるいは変更が生じた際に、設計者が各情報を登録するものとする。   The construction information (setting position, conduit specification, etc.) of the buried conduit is registered in the database by the designer, and the setting position, the start-up location, etc. can be confirmed three-dimensionally using 3D-CAD. In addition, the conduit data registered by the designer in 3D-CAD includes specifications such as the size and material of the conduit, the control number specified for each conduit, the book number and revision number of the construction drawing to be referenced, and other necessary information. Design information can be registered, and when the design information is determined or changed, the designer registers each piece of information.

更に、施工業者が現地に持ち込むモバイル端末は、3D−CADのデータベースから情報を参照することが可能なものとし、現場にて埋設電線管の施工前に3D−CADを用いて対象となる電線管の設定位置や立ち上げ箇所が3次元的に確認できるものとする。また、上記のモバイル端末にはRFIDリーダーを接続可能なものとし、RFIDリーダーを用いて対象の電線管に貼り付けたRFIDタグを読み込むことで、当該電線管の仕様(サイズ・材質等)を確認することができるとともに、3D−CADに登録された情報と比較することで、当該電線管が設計情報と相違が無いことを確認することが可能となる。   In addition, mobile terminals brought into the site by contractors can refer to information from the 3D-CAD database, and the target conduits using 3D-CAD before construction of buried conduits at the site. It is assumed that the set position and start-up location can be confirmed three-dimensionally. In addition, an RFID reader can be connected to the above mobile terminal, and the RFID tag attached to the target conduit using the RFID reader is read to confirm the specifications (size, material, etc.) of the conduit. In addition, it is possible to confirm that the conduit does not differ from the design information by comparing with information registered in 3D-CAD.

モバイル端末は、最低1回/日の頻度で3D−CADデータベースの最新データを読み込むものとし、設計者による設計変更が現地の施工業者に連絡されることがなく、誤った施工を実施してしまうリスクを低減するものとする。   The mobile terminal reads the latest data in the 3D-CAD database at a frequency of at least once a day, and the design change by the designer is not communicated to the local contractor, and the wrong construction is performed. Risk shall be reduced.

また、本発明は施工業者が現地にて設計変更を要する事象を確認した場合、モバイル端末を用いて設計者に現場の状況を容易に伝達することを可能とする。3D−CADを利用して現地の干渉箇所を設計者に容易に伝達し、設計者による再設計と施工業者への指示を遅滞なく推進することが可能となる。   In addition, the present invention makes it possible to easily transmit the site situation to the designer using the mobile terminal when the contractor confirms an event that requires a design change on site. By using 3D-CAD, it is possible to easily communicate the local interference location to the designer, and to promote redesign by the designer and instructions to the contractor without delay.

以下、図面を参照して本発明の実施例を説明する。   Embodiments of the present invention will be described below with reference to the drawings.

(実施例1)
図1は、原子力発電所等の発電所内に設置される埋設電線管(電気計装設備)の概要を示す図である。図1において、原子力発電所にケーブル1を布設する場合、ケーブルの保護や系統分離を考慮して、ケーブルトレイ2や埋設電線管3を用いて、発点機器から着点機器(電気盤4)の間に電路を構築した後、電路内にケーブル1を布設することとしている。通常、埋設電線管3は、最短長でケーブルを発点・着点機器と接続するために、発電所内の他計画物(機器、配管、ダクト等)を避けることを目的として、鉄筋コンクリート製の躯体5(床・壁・天井等の構造物)の内部に埋め込まれて設定される。
Example 1
FIG. 1 is a diagram showing an outline of a buried electric conduit (electrical instrumentation equipment) installed in a power plant such as a nuclear power plant. In FIG. 1, when laying the cable 1 in the nuclear power plant, the cable tray 2 and the buried electric conduit 3 are used from the starting device to the landing device (electric panel 4) in consideration of cable protection and system separation. After constructing the electric circuit between the cables, the cable 1 is laid in the electric circuit. Normally, the buried conduit 3 is a reinforced concrete enclosure for the purpose of avoiding other planned items (equipment, piping, ducts, etc.) in the power plant in order to connect the cable with the starting and landing equipment in the shortest length. It is set by being embedded in 5 (structure such as floor, wall, ceiling, etc.).

図2は、埋設電線管の施工方法の説明図であり、図3は、埋設電線管3の曲加工及び埋設電線管3同士の接続の説明図である。   FIG. 2 is an explanatory diagram of a method for constructing the buried electric conduit, and FIG. 3 is an explanatory diagram of bending of the buried conduit 3 and connection between the buried conduits 3.

図2において、(A)は埋設電線管3の断面を示し、(B)は埋設電線管3の側面を示している。埋設電線管3を設定する場合、鉄筋コンクリート製の躯体5(床・壁・天井)に対して、コンクリートの打設前に、配筋6に固定する形で設定される。埋設電線管3の設定位置とサイズ等の仕様は、設計者が提示する施工図によって指定され、施工業者は現地にて図面を確認しながら電線管の施工を行うこととしている。   In FIG. 2, (A) shows a cross section of the buried conduit 3, and (B) shows a side surface of the buried conduit 3. When setting the buried electric conduit 3, it is set in such a manner that it is fixed to the reinforcing bar 6 before placing concrete on the reinforced concrete frame 5 (floor / wall / ceiling). Specifications such as the setting position and size of the buried conduit 3 are specified by a construction drawing presented by the designer, and the construction contractor constructs the conduit while confirming the drawing on site.

施工業者は施工図に示された電線管の情報に合わせて、埋設電線管3の施工場所である現地に納入された電線管の中から施工対象となる電線管の選定(サイズ等)を行う。そして、図3に示すように、現地にて必要な曲げ加工やカップリング7を用いた接続を行った上で、施工図にて指定される位置に電線管の設定を行う。   The contractor selects the size (size, etc.) of the conduit to be constructed from the conduits delivered to the site where the buried conduit 3 is constructed, in accordance with the conduit information shown in the construction drawing. . And as shown in FIG. 3, after performing the bending process required in the field and the connection using the coupling 7, a conduit is set in the position designated by a construction drawing.

上記の埋設電線管3の施工後にコンクリートの打設を行うことにより、埋設電線管3は躯体5の内部に埋設されることとなるが、埋設電線管3の施工時に埋設電線管3の選定誤りや加工ミス、設置位置の誤りがあった場合でも、コンクリート打設後のやり直し施工は不可能である。   By placing concrete after the construction of the above-mentioned buried conduit 3, the buried conduit 3 is buried inside the housing 5. However, when the buried conduit 3 is constructed, the selection of the buried conduit 3 is incorrect. Even if there is a mistake in machining, installation position, etc., it is impossible to start over after concrete placement.

本発明の実施例1は、施工業者による施工ミスを低減するため、現地施工前に3D−CADを用いて設計情報を確認することが可能な埋設電線管の施工と、線管の仕様情報が格納されるRFIDタグとモバイル端末とを用いて、施工後に埋設電線管3の施工ミスを容易に発見し、再施工が可能となる埋設電線管の施工方法および施工システムである。   In the first embodiment of the present invention, in order to reduce construction mistakes by the contractor, the construction of the buried conduit that can confirm the design information using 3D-CAD before the construction on site and the specification information of the conduit are It is a construction method and a construction system for a buried conduit that enables a construction error of the buried conduit 3 to be easily found after construction using a stored RFID tag and a mobile terminal.

図4は、RFIDを用いた埋設電線管施工確認システム(RFIDを用いた発電所における電気計装設備の施工システム)の全体構成図である。図4において、埋設電線管施工確認システムは、設計事務所(設計部門)100に設置される設計用PC8と、この設計用PC(設計用装置)8を用いて、設計者により入力される埋設電線管の設計情報(3D−CAD、電線管仕様、電線管番号、施工図番号等)を登録する施工情報データベース9とを備える。   FIG. 4 is an overall configuration diagram of a buried conduit construction confirmation system using RFID (an electrical instrumentation construction system in a power plant using RFID). In FIG. 4, the buried conduit construction confirmation system uses a design PC 8 installed in a design office (design department) 100 and a design PC (design device) 8 to be embedded by a designer. A construction information database 9 for registering design information (3D-CAD, conduit specification, conduit number, construction drawing number, etc.) of the conduit.

また、埋設電線管施工確認システムは、現地(現場)200に設置され、施工情報データベース9からインターネット等の情報通信機器を介して埋設電線管の設計情報を参照し、記憶部10Aに情報を記録すると共に、必要な電線管の設計情報をモバイル端末13に無線アンテナを用いて伝送する機能を持つ処理部10Bを有するデータサーバ10と、設計情報を登録し、電線管3および付属品(カップリング等)に貼り付け可能な構造を持つRFIDタグ12と、データサーバ10から必要な電線管3の設計情報を参照し、RFIDタグ12に情報を書き込むことが可能なデータ出力装置11と、を備える。このデータ出力装置11は、データ表示部及びデータ印字部を有する。   The buried conduit construction confirmation system is installed at the site (site) 200, refers to the construction information database 9 through the information communication device such as the Internet, and records the information in the storage unit 10A. At the same time, the data server 10 having the processing unit 10B having a function of transmitting the necessary conduit design information to the mobile terminal 13 using a wireless antenna, the design information is registered, and the conduit 3 and the accessory (coupling) And the like, and a data output device 11 that can write information to the RFID tag 12 by referring to the design information of the required conduit 3 from the data server 10. . The data output device 11 has a data display unit and a data printing unit.

さらに、埋設電線管施工確認システムは、施工業者が施工現場に持ち込み、データサーバ11から伝送される埋設電線管3の設計情報を参照する機能を持つモバイル端末13と、モバイル端末13に接続され、電線管3に貼り付けたRFIDタグ12の情報を読み取り、モバイル端末13を介してデータサーバ10に情報を転送する機能を有するRFIDリーダー14とを備える。   Further, the buried conduit construction confirmation system is connected to the mobile terminal 13 and the mobile terminal 13 having a function that the contractor brings into the construction site and refers to the design information of the buried conduit 3 transmitted from the data server 11, An RFID reader 14 having a function of reading information of the RFID tag 12 attached to the conduit 3 and transferring the information to the data server 10 via the mobile terminal 13 is provided.

図5は、本願の実施例1による設電線管施工管理システムを用いた電線管確認作業の手順フローを示す図である。以下、本フロー図5に従い作業の手順を説明する。   FIG. 5: is a figure which shows the procedure flow of the conduit confirmation operation | work using the installation conduit construction management system by Example 1 of this application. Hereinafter, the work procedure will be described with reference to FIG.

まず、設計者100Aは、埋設電線管の設計を行う(ステップS1)。そして、設計者100Aは、埋設電線管の設計情報(3D−CADを用いた配置並びに立上げ位置の図示情報(3次元表示電線管設置画像情報)、電線管及び付属品のサイズ・材質等の仕様情報、電線管番号、施工図の図面番号等)を、設計用PC8を用いて施工情報データベース9に入力し、登録する(ステップS2、S3)。   First, the designer 100A designs a buried conduit (step S1). Then, the designer 100A determines the design information of the buried conduit (such as the placement and 3D-CAD display information (3D display conduit installation image information), the size and material of the conduit and accessories, etc. Specification information, conduit numbers, construction drawing drawing numbers, etc.) are entered into the construction information database 9 using the design PC 8 and registered (steps S2, S3).

現地(施工現地)で施工業者200Aは、データサーバ7を用いて施工情報データベース9から埋設電線管の設計情報を呼び出し(ステップS4)、現地工程に従って(ステップS5A)、設計情報の中から施工対象となる埋設電線管3の選定を行う(ステップS5)。   At the site (construction site), the contractor 200A uses the data server 7 to call up the design information of the buried conduit from the construction information database 9 (step S4), and follows the local process (step S5A). The buried conduit 3 is selected (step S5).

次に、施工対象となる埋設電線管の情報を、データ出力装置11を用いてRFIDタグ12に登録する(ステップS6)。RFIDタグ12は、施工する電線管および付属品(カップリング等)の一つ一つに貼り付ける必要があることから、施工業者200Aは工事対象を明確にし、必要な個数のRFIDタグ12を作成する。更に、施工業者200Aは現地に納入された電線管3および付属品の中から、RFIDタグ12に登録された仕様(サイズ・材質等)のものを選定し(ステップS7)、各電線管3および付属品にRFIDタグ12を貼り付ける(ステップS8)。RFIDタグ12の貼り付け後に、電線管および付属品を工事現場に持ち込む。   Next, information on the buried conduit to be constructed is registered in the RFID tag 12 using the data output device 11 (step S6). Since the RFID tag 12 needs to be attached to each of the conduits and accessories (coupling, etc.) to be constructed, the contractor 200A makes the construction object clear and creates the necessary number of RFID tags 12. To do. Further, the contractor 200A selects a specification (size, material, etc.) registered in the RFID tag 12 from the conduit 3 and accessories delivered to the site (step S7), and each conduit 3 and The RFID tag 12 is attached to the accessory (step S8). After the RFID tag 12 is attached, the conduit and accessories are brought into the construction site.

施工業者200Aはモバイル端末13を施工場所に持ち込み、無線接続を利用してデータサーバ10から埋設電線管の設計情報をモバイル端末13に伝送する。施工業者200Aは、モバイル端末13に表示される3D−CADを用いて、埋設電線管3の配置と立上げ位置を確認する(ステップS9)。施工業者200Aは、設計情報にて指示される通りに電線管3の曲げ加工および付属品を用いた接続を実施する(ステップS10)。   The contractor 200A brings the mobile terminal 13 to the construction site, and transmits the design information of the buried conduit from the data server 10 to the mobile terminal 13 using wireless connection. The contractor 200A uses the 3D-CAD displayed on the mobile terminal 13 to confirm the arrangement and the startup position of the buried conduit 3 (step S9). The contractor 200A performs bending of the conduit 3 and connection using accessories as instructed by the design information (step S10).

埋設電線管3の施工後、RFIDリーダー14を用いて電線管3および付属品に貼り付けたRFIDタグ12の情報を読み取り、モバイル端末13での操作により、施工した電線管3の仕様(設置位置、電線管サイズ等)が3D−CADにて示される対象の電線管3の仕様と相違ないかを比較・確認する指示をデータサーバ10の処理部10Bに伝送する。データサーバ10の処理部10Bでは、RFIDタグ12から読み取った情報(電線管が実際に設置された状況)が記憶部10Aに登録された設計情報と相違ないか否かを比較・確認する(ステップS11)。   After the construction of the buried conduit 3, the RFID reader 12 is used to read information on the RFID tag 12 attached to the conduit 3 and the accessory, and the specification (installation position) of the constructed conduit 3 by operation on the mobile terminal 13. , Conduit size, etc.) is transmitted to the processing unit 10B of the data server 10 for comparing / confirming whether or not the specification of the target conduit 3 indicated by 3D-CAD is different. The processing unit 10B of the data server 10 compares and confirms whether the information read from the RFID tag 12 (the situation where the conduit is actually installed) is different from the design information registered in the storage unit 10A (step) S11).

相違が無ければ、データサーバ10の処理部10Bは、施工完了の情報をモバイル端末13に転送する(ステップS12、S15)。また、RFIDタグ12から読み取った情報が設計情報と相違がある場合には、データサーバ10の処理部10Bは、設計情報の3D−CADとの比較を行い、相違がある箇所を3D−CAD上に明示し、対象箇所のやり直し施工を指示する情報をモバイル端末13に転送する(ステップS12、S13)。施工業者200Aはモバイル端末13に明示される3D−CADからやり直し施工箇所を確認し、適切な電線管3および付属品を選定して再施工を行う。施工完了後に、RFIDリーダー14を用いて、電線管および付属品に貼り付けたRFIDタグ12から情報を読み取り、モバイル端末13を介してデータサーバ10に転送して、処理部10Bが設計情報との相違が無いことを確認する(ステップS14)。   If there is no difference, the processing unit 10B of the data server 10 transfers the construction completion information to the mobile terminal 13 (steps S12 and S15). When the information read from the RFID tag 12 is different from the design information, the processing unit 10B of the data server 10 compares the design information with the 3D-CAD and identifies the difference on the 3D-CAD. And instructing to redo the target location is transferred to the mobile terminal 13 (steps S12 and S13). The construction contractor 200A starts over from the 3D-CAD specified on the mobile terminal 13, confirms the construction location, selects the appropriate conduit 3 and accessories, and performs the construction again. After the completion of the construction, information is read from the RFID tag 12 attached to the conduit and accessories using the RFID reader 14 and transferred to the data server 10 via the mobile terminal 13 so that the processing unit 10B receives the design information. It is confirmed that there is no difference (step S14).

処理部10Bは、相違が無ければ施工完了の情報をモバイル端末13に転送する(ステップS15)。   If there is no difference, the processing unit 10B transfers the construction completion information to the mobile terminal 13 (step S15).

以上のように、本発明の実施例1によれば、施工業者は、モバイル端末13に3D表示された埋設電線管3の設置情報に従って、埋設電線管3を設置し、設置後に埋設電線管3に貼付されたRFIDタグ12の情報を読み取り、埋設電線管3の施工後の設置位置情報を、データサーバ10に転送する。そして、データサーバ10の処理部10Bは、埋設電線管3の施工後の設置位置情報と、設計情報とを比較し、施工と設計情報とに相違箇所があれば、その相違箇所と再施行指示をモバイル端末13に転送し、表示させるように構成されているので、埋設すべき電線管の設置位置及びその電線管の仕様を誤りなく、容易に確認できるとともに、電線管設置後の設置位置及びその電線管の仕様と設計情報との相違を容易に確認可能な、RFIDを用いた発電所における電気計装設備の施工方法および施工システムを実現することができる。   As described above, according to the first embodiment of the present invention, the contractor installs the buried conduit 3 according to the installation information of the buried conduit 3 displayed in 3D on the mobile terminal 13, and after the installation, the buried conduit 3 The information of the RFID tag 12 affixed to is read, and the installation position information after the construction of the buried conduit 3 is transferred to the data server 10. Then, the processing unit 10B of the data server 10 compares the installation position information after the construction of the buried conduit 3 and the design information, and if there is a difference between the construction and the design information, the difference and the re-execution instruction. Is transmitted to the mobile terminal 13 and displayed, so that the installation position of the conduit to be buried and the specification of the conduit can be easily confirmed without error, and the installation position after installation of the conduit and It is possible to realize a construction method and a construction system for an electrical instrumentation facility in a power plant using RFID, in which the difference between the specification of the conduit and the design information can be easily confirmed.

なお、構造物への電線3の設置位置を示す3次元表示電線管設置画像は、データ出力装置11の表示部にも表示することができる。   A three-dimensional display conduit installation image showing the installation position of the electric wire 3 on the structure can also be displayed on the display unit of the data output device 11.

(実施例2)
次に、本発明の実施例2について説明する。
(Example 2)
Next, a second embodiment of the present invention will be described.

上述した実施例においては、一度設定され、記憶部10に格納された埋設電線管の設置設計情報に従って、施工を行う例であるが、施工前に現地の躯体および他計画物の施工状態を確認した結果、埋設電線管の設置設計位置と躯体等との干渉が発生し、設計情報の通りに埋設電線管を施工することができない事象が発生する可能性がある。   In the above-mentioned embodiment, it is an example in which construction is performed in accordance with the installation design information of the buried conduit that is set once and stored in the storage unit 10, but the construction state of the local frame and other planned objects is confirmed before construction. As a result, there is a possibility that an interference between the installation design position of the buried conduit and the frame or the like occurs, and an event in which the buried conduit cannot be constructed according to the design information may occur.

その場合、早急に現場状況に合わせて埋設電線管の配置を検討し、再設計を行って現地に施工指示を行う必要がある。この場合、干渉の発生する箇所と現場状況を現場の施工業者から設計者に連絡する必要があり、施工経験の少ない海外の施工業者からの情報連絡に時間を要し、工程遅延等の影響が生じる可能性が考えられる。   In that case, it is necessary to immediately examine the arrangement of the buried conduit in accordance with the site conditions, redesign, and give construction instructions to the site. In this case, it is necessary to inform the designer from the site where the interference occurs and the site situation, and it takes time to communicate information from overseas contractors with little construction experience, which may affect the effects of process delays, etc. It is possible that it will occur.

国内の原子力発電所等の発電所の建設工事においては、現地において施工図に干渉箇所を朱記し、現場の状況を設計者に連絡することにより、設計者は干渉回避を考慮した再設計を行い、改めて現地に施工指示を行うものとしている。しかし、施工経験の少ない海外の施工業者からは、設計者が早急に再設計を行うのに必要十分な情報が提示されず、施工業者と設計者との間の連絡に時間を要することで設計指示が遅くなり、工程遅延を引き起こす等の可能性が考えられる。   In the construction work of power plants such as nuclear power plants in Japan, the designer performs redesign in consideration of interference avoidance by marking the interference points in the construction drawings locally and informing the designer of the situation at the site. The construction instructions will be given to the site again. However, overseas construction contractors with little construction experience do not provide sufficient information necessary for designers to redesign quickly, and it takes time to communicate between the contractors and designers. There is a possibility that the instruction is delayed and a process delay is caused.

本発明の実施例2は、再設計が必要な事態が発生した場合にも、容易に再設計情報を転送可能とする例である。   The second embodiment of the present invention is an example in which redesign information can be easily transferred even when a situation requiring redesign occurs.

図6は、本発明の実施例2による埋設電線管施工管理システムにおける電線管設計変更作業の説明図である。また、図7は、本発明の実施例2による埋設電線管施工管理システムを用いた電線管設計変更作業の手順フローを示す図である。   FIG. 6 is an explanatory diagram of the conduit design change work in the buried conduit construction management system according to Embodiment 2 of the present invention. Moreover, FIG. 7 is a figure which shows the procedure flow of the conduit design change work using the buried conduit construction management system by Example 2 of this invention.

以下、図6、図7を参照して本発明の実施例2について説明する。   The second embodiment of the present invention will be described below with reference to FIGS.

上述したように、施工業者が、現場を確認したところ、躯体や他計画物と埋設電線管との干渉が確認され、設計情報通りの施工が実施できないという事象が発生する可能性がある。   As described above, when the contractor confirms the site, there is a possibility that an interference between the frame or other planned object and the buried electric conduit will be confirmed and the construction according to the design information cannot be performed.

施工業者200Aは現場にて、設計指示による対象電線管の配置16を確認し(ステップS20)、対象電線管と躯体や対象電線管以外の計画物15との干渉が発見されない場合は、ステップS21からステップS22に進み、以降は実施例1と同様にして、埋設電線管3の設置を実施する。   The contractor 200A confirms the arrangement 16 of the target conduit according to the design instruction at the site (step S20), and if no interference between the target conduit and the plan 15 other than the casing or the target conduit is found, step S21. The process proceeds from step S22 to step S22, and the installation of the buried conduit 3 is performed in the same manner as in the first embodiment.

ステップS21で、対象電線管と躯体や対象電線管以外の計画物15との干渉を発見した場合、施工業者200Aはモバイル端末13を用いて、記憶部10Aに格納された対象電線管の3D−CADを呼び出し、3D−CAD上に干渉する位置と現場状況を書き込み、データサーバ10に転送する。また、モバイル端末13を用いて、干渉する現場写真を撮影し、上記の情報と共にデータサーバ10に転送する(ステップS23、S24)。   In step S21, when the interference between the target conduit and the planned object 15 other than the casing and the target conduit is found, the contractor 200A uses the mobile terminal 13 to perform the 3D- of the target conduit stored in the storage unit 10A. The CAD is called, and the position and field situation of interference on 3D-CAD are written and transferred to the data server 10. In addition, the mobile terminal 13 is used to take an interfering scene photograph and transfer it to the data server 10 together with the above information (steps S23 and S24).

上記の情報を受けて、データサーバ10の処理部10Bでは、施工業者200Aからの設計不具合連絡を作成し(ステップS24)、情報データベース9を介して設計用PC8に設計不具合連絡を転送する(ステップS25、S26)。設計者100Aは設計不具合連絡を受け、現地から連絡された3D−CAD上の干渉位置と現場状況、現場写真等を参考に、埋設電線管3の干渉回避を達成するために設計見直しを実施する(ステップS27)。   Receiving the above information, the processing unit 10B of the data server 10 creates a design defect communication from the contractor 200A (step S24), and transfers the design defect communication to the design PC 8 via the information database 9 (step S24). S25, S26). The designer 100A receives a design defect report and reviews the design in order to achieve interference avoidance of the buried conduit 3 with reference to the interference position on the 3D-CAD, the field situation, the field photograph, etc. that are reported from the field. (Step S27).

設計見直しを実施した後、設計者100Aは設計不具合連絡に対する返信として、施工情報データベース9を介して、新たな設計情報を現地のデータサーバ10に転送する(ステップS28)。データサーバ10の処理部10Bでは設計不具合連絡の返信を受信した後、モバイル端末13に新たな設計情報を転送する(ステップS29)。施工業者200Aは、モバイル端末13を用いて新たな設計情報を確認し(ステップS30)、埋設電線管3が干渉回避されたことを確認した上で、実施例1と同様にして、埋設電線管3の施工を行う(ステップS31、S32)。   After implementing the design review, the designer 100A transfers the new design information to the local data server 10 via the construction information database 9 as a reply to the design defect notification (step S28). The processing unit 10B of the data server 10 receives the design failure notification reply, and then transfers new design information to the mobile terminal 13 (step S29). The contractor 200A confirms the new design information using the mobile terminal 13 (step S30), confirms that the embedded conduit 3 has avoided interference, and then performs the embedded conduit as in the first embodiment. 3 is performed (steps S31 and S32).

ステップS31において、埋設電線管3が他計画物との干渉が回避されていないと施工業者200Aが判断すると、ステップS33に進む。ステップS33において、施工業者200Aは、モバイル端末13を用いて3D−CAD上に干渉箇所を明示し、かつ、写真を撮影する。そして、ステップS24に戻り、データサーバ10に、3D−CAD上に明示した干渉箇所及び撮影した写真を転送する。   In step S31, when the contractor 200A determines that interference with the other planned object is not avoided, the process proceeds to step S33. In step S <b> 33, the contractor 200 </ b> A uses the mobile terminal 13 to clearly indicate the interference location on the 3D-CAD and take a photograph. Then, the process returns to step S <b> 24, and the interference location specified on the 3D-CAD and the photographed image are transferred to the data server 10.

その後、ステップS24〜S33が、干渉が回避されるまで繰り返される。   Thereafter, steps S24 to S33 are repeated until interference is avoided.

以上のように、本発明の実施例2は、実施例1と同様な効果を有する他、埋設電線管の設置設計位置と躯体等との干渉が発生し、埋設電線再設計が必要な事態が発生した場合にも、容易に再設計情報を転送可能となり、情報連絡に時間を要し、工程遅延等の影響が生じることを回避することができる。   As described above, the second embodiment of the present invention has the same effect as that of the first embodiment. In addition, there is an interference between the installation design position of the buried electric pipe and the housing, and the situation where the buried electric wire needs to be redesigned. Even when it occurs, it is possible to easily transfer the redesign information, and it takes time for information communication, and it is possible to avoid the influence of process delay and the like.

(実施例3)
次に、本発明の実施例3について説明する。
(Example 3)
Next, Embodiment 3 of the present invention will be described.

本発明の実施例3は、実施例1による埋設電線管施工管理システムを用いた埋設電線管の施工を実施する際に、施工完了したエリア毎に、埋設電線管3の電線管番号と施工図番号等をデータサーバ10の記憶部10Aに登録する例である。また、実施例3においては、対象の埋設電線管の施工に要した電線管および付属品の情報(仕様、員数等)を、同様にデータサーバ10の記憶部10Aに登録する。   In the third embodiment of the present invention, when carrying out the construction of the buried conduit using the buried conduit construction management system according to the first embodiment, the conduit number and construction diagram of the buried conduit 3 for each completed area. In this example, numbers and the like are registered in the storage unit 10 </ b> A of the data server 10. Moreover, in Example 3, the information (specification, number, etc.) of the conduit and accessories required for the construction of the target buried conduit is similarly registered in the storage unit 10A of the data server 10.

発電所等における電線管の設置工事の工程は、発電所等に設定されたエリア毎に定められる。このため、一つのエリアの施工完了時に、埋設電線管3の電線管番号と施工図番号、施工に要した電線管および付属品の情報(仕様、員数等)を記憶部10Aに登録する。この登録は、施工業者が行うこともできるし、処理部10Bが自動的に行うことも可能である。処理部10Bが自動的に行う場合は、図5のステップS5において、付属品の情報を施工業者が記憶部10Aに格納しておくことにより、一つのエリアの施工完了時に、処理部10Bが、電線管番号と施工図番号、施工に要した電線管および付属品の情報(仕様、員数等)を記憶部10Aに施工完了情報として登録する。   The process of installing conduits in a power plant or the like is determined for each area set in the power plant or the like. For this reason, when the construction of one area is completed, the conduit number and construction diagram number of the buried conduit 3 and the information (specifications, number, etc.) of the conduit and accessories required for construction are registered in the storage unit 10A. This registration can be performed by a contractor, or can be automatically performed by the processing unit 10B. When the processing unit 10B automatically performs, in step S5 of FIG. 5, when the construction company stores the accessory information in the storage unit 10A, the processing unit 10B The conduit number and construction diagram number, and information (specifications, number, etc.) of conduits and accessories required for construction are registered in the storage unit 10A as construction completion information.

記憶部10Aには、電線管の在庫情報が予め記憶され、電線管が使用される毎に更新されており、データサーバ10の処理部10Bは、記憶部10Aに登録された施工完了情報と現地工程および電線管の在庫情報との比較を行い、現地工程に対する埋設電線管工事の施工進捗状況と納入材料の使用状況(在庫数)を、施工エリアの施工完了時に、自動で計算して出力する(データ出力装置11の表示部や印刷部にて表示、印刷される)。   In the storage unit 10A, stock information of the conduit is stored in advance and updated every time the conduit is used. The processing unit 10B of the data server 10 stores the construction completion information registered in the storage unit 10A and the site information. Compare the process and conduit inventory information, and automatically calculate and output the progress of the buried conduit construction for the local process and the usage status (inventory number) of the delivered materials when construction in the construction area is complete. (Displayed and printed by the display unit and printing unit of the data output device 11).

さらに、上記の施工進捗状況と納入材料の使用状況は、施工情報データベース9に転送されて格納され、設計用PC8で確認可能となっている。これにより、設計事務所100にて、現地の施工進捗状況と納入材料の在庫数を容易に確認することが可能である。   Furthermore, the above-mentioned construction progress status and usage status of delivered materials are transferred to and stored in the construction information database 9 and can be confirmed by the design PC 8. As a result, the design office 100 can easily check the local construction progress status and the inventory quantity of delivered materials.

他の構成は、実施例1と同様であるので、図示及び詳細な説明は省略する。   Since other configurations are the same as those of the first embodiment, illustration and detailed description thereof are omitted.

以上のように、本発明の実施例3によれば、実施例1と同様な効果を得ることができる他、現地の施工進捗状況と納入材料の在庫を容易に確認することが可能である。   As described above, according to the third embodiment of the present invention, it is possible to obtain the same effect as that of the first embodiment, and it is possible to easily confirm the local construction progress status and the inventory of delivered materials.

なお、実施例2においても、実施例3のように、現地の施工進捗状況と納入材料の在庫を容易に確認することが可能なように構成することも可能である。   Note that, in the second embodiment, as in the third embodiment, it is also possible to configure so that it is possible to easily confirm the local construction progress status and the stock of the delivered material.

1・・・ケーブル、2・・・ケーブルトレイ、3・・・埋設電線管、4・・・電気盤、5・・・躯体(壁、床、天井)、6・・・配筋、7・・・カップリング、8・・・設計用PC、9・・・施工情報データベース、10・・・データサーバ、10A・・・記憶部、10B・・・処理部、11・・・データ出力装置、12・・・RFIDタグ、13・・・モバイル端末、14・・・RFIDリーダー、15・・・対象電線管以外の計画物、16・・・設計指示による対象電線管の配置、100・・・設計事務所、100A・・・設計者、200・・・現場、200A・・・施工業者   DESCRIPTION OF SYMBOLS 1 ... Cable, 2 ... Cable tray, 3 ... Buried conduit, 4 ... Electric board, 5 ... Housing (wall, floor, ceiling), 6 ... Reinforcement, 7. ..Coupling, 8 ... PC for design, 9 ... construction information database, 10 ... data server, 10A ... storage unit, 10B ... processing unit, 11 ... data output device, DESCRIPTION OF SYMBOLS 12 ... RFID tag, 13 ... Mobile terminal, 14 ... RFID reader, 15 ... Plan other than target conduit, 16 ... Arrangement of target conduit according to design instruction, 100 ... Design office, 100A ... Designer, 200 ... Site, 200A ... Contractor

Claims (8)

発電所の構造物に埋設する電線管に、この電線管の仕様情報が格納されたRFIDタグを貼付し、
上記RFIDタグが貼付された上記電線管を、上記構造物への上記電線管の設置位置を示す3次元表示電線管設置画像情報に従って上記構造物に設置し、
設置した電線管に貼付されたRFIDタグに格納された上記電線管の仕様情報を読み取り、
上記構造物に設置した上記電線管が、上記3次元表示電線管設置画像情報に示された電線管配置位置に設置されているか否かを判断することを特徴とするRFIDを用いた発電所における電気計装設備の施工方法。
Attach an RFID tag that stores the specification information of this conduit to the conduit embedded in the power plant structure,
The conduit with the RFID tag attached is installed on the structure according to the three-dimensional display conduit installation image information indicating the installation position of the conduit on the structure,
Read the specification information of the conduits stored in the RFID tag attached to the installed conduits,
In a power plant using RFID, wherein it is determined whether or not the conduit installed in the structure is installed at a conduit placement position indicated in the three-dimensional display conduit installation image information. Construction method of electrical instrumentation equipment.
請求項1に記載のRFIDを用いた発電所における電気計装設備の施工方法において、
上記構造物に埋設される電線管の仕様情報及び上記構造物への上記電線管の設置位置を示す3次元表示電線管設置画像情報を、設計部門から、上記構造物が存在する現地に配置されたデータサーバに転送し、上記データサーバの記憶部に格納させ、
上記記憶部に格納された電線管の仕様情報を、上記FRIDタグに格納し、
上記構造物に設置した上記電線管が、上記3次元表示電線管設置画像情報に示された電線管配置位置に設置されているか否かを判断した結果、上記電線管が上記3次元表示電線管設置画像に示された電線管配置位置に設置されていないと判断した場合は、上記電線管配置位置に設置されていない箇所を上記3次元表示電線管設置画像情報に明示することを特徴とするRFIDを用いた発電所における電気計装設備の施工方法。
In the construction method of the electric instrumentation equipment in the power plant using the RFID according to claim 1,
The specification information of the conduits embedded in the structure and the 3D display conduit installation image information indicating the installation position of the conduits in the structure are placed from the design department on the site where the structure exists. Transferred to the data server, stored in the storage unit of the data server,
The specification information of the conduits stored in the storage unit is stored in the FRID tag,
As a result of determining whether or not the conduit installed in the structure is installed at the conduit placement position indicated in the three-dimensional display conduit installation image information, the conduit is the three-dimensional display conduit. When it is determined that the conduit is not installed at the conduit arrangement position indicated in the installation image, the portion not installed at the conduit arrangement position is clearly indicated in the three-dimensional display conduit installation image information. Construction method of electrical instrumentation equipment in a power plant using RFID.
請求項1に記載のRFIDを用いた発電所における電気計装設備の施工方法において、
上記構造物に埋設される電線管の仕様情報及び上記構造物への上記電線管の設置位置を示す3次元表示電線管設置画像情報を、設計部門のデータベースに格納し、上記データベースに格納した上記仕様情報及び上記3次元表示電線管設置画像情報を、上記設計部門から、上記構造物が存在する現地に配置されたデータサーバに転送し、上記データサーバの記憶部に格納させ、
上記格納された上記3次元表示電線管設置画像情報に基いて、上記電線管と干渉する物が、実際の構造物に存在するか否かを判断し、
上記電線管と干渉する物が、実際の構造物に存在すると判断した場合は、上記3次元表示電線管設置画像に上記干渉する物が上記電線管と干渉する位置を明示し、上記データサーバから上記データベースに転送し、
上記設計部門にて上記電線管と干渉する位置を明示した上記3次元表示電線管設置画像に基づいて、3次元表示電線管設置画像情報を修正し、
修正した上記3次元表示電線管設置画像情報を上記データベースに格納するとともに、上記現地に配置されたデータサーバに転送し、上記データサーバの記憶部に格納させ、
上記記憶部に格納された電線管の仕様情報を、上記FRIDタグに格納し、
上記構造物に設置した上記電線管が、上記3次元表示電線管設置画像情報に示された電線管配置位置に設置されているか否かを判断することを特徴とするRFIDを用いた発電所における電気計装設備の施工方法。
In the construction method of the electric instrumentation equipment in the power plant using the RFID according to claim 1,
The specification information of the conduits embedded in the structure and the three-dimensional display conduit installation image information indicating the installation position of the conduits in the structure are stored in the database of the design department and stored in the database. The specification information and the 3D display conduit installation image information are transferred from the design department to a data server arranged on the site where the structure exists, and stored in the storage unit of the data server,
Based on the stored three-dimensional display conduit installation image information, determine whether an object that interferes with the conduit is present in the actual structure;
When it is determined that an object that interferes with the conduit is present in the actual structure, the position where the interfered object interferes with the conduit is clearly indicated on the three-dimensional display conduit installation image, and the data server Transfer to the above database,
Based on the 3D display conduit installation image that clearly indicates the position of interference with the conduit in the design department, modify the 3D display conduit installation image information,
The corrected 3D display conduit installation image information is stored in the database, transferred to the data server located on the site, and stored in the storage unit of the data server,
The specification information of the conduits stored in the storage unit is stored in the FRID tag,
In a power plant using RFID, wherein it is determined whether or not the conduit installed in the structure is installed at a conduit placement position indicated in the three-dimensional display conduit installation image information. Construction method of electrical instrumentation equipment.
請求項1に記載のRFIDを用いた発電所における電気計装設備の施工方法において、
上記構造物に埋設される電線管の仕様情報及び上記構造物への上記電線管の設置位置を示す3次元表示電線管設置画像情報を、設計部門から、上記構造物が存在する現地に配置されたデータサーバに転送し、上記データサーバの記憶部に格納させ、
上記記憶部に格納された電線管の仕様情報を、上記FRIDタグに格納し、
上記構造物に設置した上記電線管が、上記3次元表示電線管設置画像情報に示された電線管配置位置に設置されているか否かを判断した結果、上記電線管が上記3次元表示電線管設置画像に示された電線管配置位置に設置されていると判断した場合は、設置した電線管の仕様情報を、上記データサーバの記憶部に格納し、
上記記憶部に格納した上記設置した電線管の仕様情報に基いて、設置すべき電線管の在庫数を計算し、計算した電線管の在庫数をデータサーバの出力装置により出力し、かつ、上記設計部門のデータベースに転送し、格納させることを特徴とするRFIDを用いた発電所における電気計装設備の施工方法。
In the construction method of the electric instrumentation equipment in the power plant using the RFID according to claim 1,
The specification information of the conduits embedded in the structure and the 3D display conduit installation image information indicating the installation position of the conduits in the structure are placed from the design department on the site where the structure exists. Transferred to the data server, stored in the storage unit of the data server,
The specification information of the conduits stored in the storage unit is stored in the FRID tag,
As a result of determining whether or not the conduit installed in the structure is installed at the conduit placement position indicated in the three-dimensional display conduit installation image information, the conduit is the three-dimensional display conduit. When it is determined that the conduit is installed at the conduit placement position shown in the installation image, the specification information of the installed conduit is stored in the storage unit of the data server,
Based on the specification information of the installed conduits stored in the storage unit, calculate the inventory number of conduits to be installed, output the calculated inventory number of conduits by the output device of the data server, and A method for constructing an electrical instrumentation facility in a power plant using RFID, which is transferred to a database of a design department and stored.
発電所の構造物に埋設する電線管の設置位置を表示する3次元表示電線管設置画像情報が格納されるデータサーバの記憶部と、
上記記憶部に格納された電線管の仕様情報が格納され、上記電線管に貼付されるRFIDタグと、
上記記憶部に格納された上記3次元表示電線管設置画像を表示するモバイル端末と、
上記構造物に設置された電線管に貼付された上記RFIDタグに格納された上記電線管の仕様情報を読み取るRFIDリーダーと、
上記RFIDリーダーにより読み取られた上記電線管の仕様情報に基いて、上記3次元表示電線管設置画像情報に示された電線管の設置位置に上記電線管が設置されているか否かを判断するデータサーバの処理部と、
を備えることを特徴とするRFIDを用いた発電所における電気計装設備の施工システム。
A storage unit of a data server in which three-dimensional display conduit installation image information for displaying the installation position of the conduit to be embedded in the structure of the power plant is stored;
The specification information of the conduit stored in the storage unit is stored, and the RFID tag attached to the conduit,
A mobile terminal for displaying the three-dimensional display conduit installation image stored in the storage unit;
An RFID reader that reads the specification information of the conduit stored in the RFID tag attached to the conduit installed in the structure;
Data for determining whether or not the conduit is installed at the conduit installation position indicated in the three-dimensional display conduit installation image information based on the specification information of the conduit read by the RFID reader The processing part of the server;
An installation system for electrical instrumentation equipment in a power plant using RFID, comprising:
請求項5に記載のRFIDを用いた発電所における電気計装設備の施工システムにおいて、
上記3次元表示電線管設置画像情報を生成する設計用装置と、
上記設計用装置により生成された上記3次元表示電線管設置画像情報が格納されるデータベースと、
をさらに備え、
上記データベースに格納された上記3次元表示電線管設置画像情報が上記データサーバに転送されて、上記記憶部に格納され、上記データサーバの上記処理部が、上記電線管が上記3次元表示電線管設置画像に示された電線管配置位置に設置されていないと判断した場合は、上記電線管配置位置に設置されていない位置を上記3次元表示電線管設置画像情報に明示することを特徴とするRFIDを用いた発電所における電気計装設備の施工システム。
In the construction system of the electrical instrumentation equipment in the power plant using the RFID according to claim 5,
A design device for generating the three-dimensional display conduit installation image information;
A database in which the 3D display conduit installation image information generated by the design device is stored;
Further comprising
The three-dimensional display conduit installation image information stored in the database is transferred to the data server and stored in the storage unit, and the processing unit of the data server is connected to the three-dimensional display conduit. When it is determined that the conduit is not installed at the conduit arrangement position shown in the installation image, the position not installed at the conduit arrangement position is clearly indicated in the three-dimensional display conduit installation image information. Electric instrumentation construction system at power plants using RFID.
請求項5に記載のRFIDを用いた発電所における電気計装設備の施工システムにおいて、
上記3次元表示電線管設置画像情報を生成する設計用装置と、
上記設計用装置により生成された上記3次元表示電線管設置画像情報が格納されるデータベースと、
をさらに備え、
上記データベースに格納された上記3次元表示電線管設置画像情報が上記データサーバに転送されて、上記記憶部に格納され、上記データサーバの上記処理部は、上記電線管と干渉する物が、実際の構造物に存在することを示す指令に従って、上記3次元表示電線管設置画像に上記干渉する物が上記電線管と干渉する位置を明示し、上記データサーバから上記データベースに転送し、上記設計用装置にて上記電線管と干渉する位置を明示した上記3次元表示電線管設置画像に基づいて、3次元表示電線管設置画像情報を修正し、修正した上記3次元表示電線管設置画像情報を上記データベースに格納するとともに、上記データサーバに転送し、上記データサーバの記憶部に格納させることを特徴とするRFIDを用いた発電所における電気計装設備の施工システム。
In the construction system of the electrical instrumentation equipment in the power plant using the RFID according to claim 5,
A design device for generating the three-dimensional display conduit installation image information;
A database in which the 3D display conduit installation image information generated by the design device is stored;
Further comprising
The three-dimensional display conduit installation image information stored in the database is transferred to the data server and stored in the storage unit, and the processing unit of the data server is configured such that an object that interferes with the conduit is actually In accordance with a command indicating that the structure exists, the position where the interfering object interferes with the conduit is specified in the three-dimensional display conduit installation image, transferred from the data server to the database, and used for the design. 3D display conduit installation image information is corrected based on the three-dimensional display conduit installation image clearly indicating the position of interference with the conduit in the apparatus, and the corrected three-dimensional display conduit installation image information is An electric meter in a power plant using RFID, which is stored in a database, transferred to the data server, and stored in a storage unit of the data server Equipment and construction systems.
請求項5に記載のRFIDを用いた発電所における電気計装設備の施工システムにおいて、
上記3次元表示電線管設置画像情報を生成する設計用装置と、
上記設計用装置により生成された上記3次元表示電線管設置画像情報が格納されるデータベースと、
上記データサーバに接続された出力装置と、
をさらに備え、
上記データベースに格納された上記3次元表示電線管設置画像情報が上記データサーバに転送されて、上記記憶部に格納され、上記データサーバの上記処理部が、上記電線管が上記3次元表示電線管設置画像に示された電線管配置位置に設置されていると判断した場合は、設置した電線管の仕様情報を、上記データサーバの記憶部に格納し、上記記憶部に格納した上記設置した電線管の仕様情報に基いて、設置すべき電線管の在庫数を計算し、計算した電線管の在庫数をデータサーバの出力装置により出力し、かつ、上記データベースに転送し、格納させることを特徴とするRFIDを用いた発電所における電気計装設備の施工システム。
In the construction system of the electrical instrumentation equipment in the power plant using the RFID according to claim 5,
A design device for generating the three-dimensional display conduit installation image information;
A database in which the 3D display conduit installation image information generated by the design device is stored;
An output device connected to the data server;
Further comprising
The three-dimensional display conduit installation image information stored in the database is transferred to the data server and stored in the storage unit, and the processing unit of the data server is connected to the three-dimensional display conduit. When it is determined that the installation position is indicated at the conduit arrangement position shown in the installation image, the specification information of the installed conduit is stored in the storage unit of the data server, and the installed electric wire stored in the storage unit is stored. The number of conduits to be installed is calculated based on the specification information of the tube, and the calculated number of conduits is output by the output device of the data server, transferred to the database, and stored. A construction system for electrical instrumentation equipment at a power plant using RFID.
JP2014252829A 2014-12-15 2014-12-15 Construction method and construction system for electric instrument equipment in power station by using rfid Pending JP2016115114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014252829A JP2016115114A (en) 2014-12-15 2014-12-15 Construction method and construction system for electric instrument equipment in power station by using rfid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014252829A JP2016115114A (en) 2014-12-15 2014-12-15 Construction method and construction system for electric instrument equipment in power station by using rfid

Publications (1)

Publication Number Publication Date
JP2016115114A true JP2016115114A (en) 2016-06-23

Family

ID=56140025

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014252829A Pending JP2016115114A (en) 2014-12-15 2014-12-15 Construction method and construction system for electric instrument equipment in power station by using rfid

Country Status (1)

Country Link
JP (1) JP2016115114A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6221192B1 (en) * 2016-11-11 2017-11-01 株式会社大和精機 Cable protector and pedestrian guidance system
JP2018147440A (en) * 2017-03-09 2018-09-20 株式会社日立プラントコンストラクション Cable construction management system
JP2020009307A (en) * 2018-07-11 2020-01-16 東芝プラントシステム株式会社 Material management device and material management method
JP2020200696A (en) * 2019-06-12 2020-12-17 日立Geニュークリア・エナジー株式会社 Method for constructing structure and closing plug for embedded pipe
KR20220165577A (en) * 2021-06-08 2022-12-15 한국전력공사 Indicator system and indicator for power installations
JP7486458B2 (en) 2021-04-21 2024-05-17 三菱重工業株式会社 Underfloor wiring structure and underfloor wiring method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004252851A (en) * 2003-02-21 2004-09-09 Nippon Telegr & Teleph Corp <Ntt> Processing method and device for operating passive component management, work support terminal, program for operating passive component management, and storage medium using it
JP2007272508A (en) * 2006-03-31 2007-10-18 Ffc Ltd Wiring and piping management method and wiring and piping management system
JP2009211454A (en) * 2008-03-05 2009-09-17 Hitachi Ltd Execution confirmation apparatus and design support system using it
JP2012122209A (en) * 2010-12-07 2012-06-28 Komei Mfg Co Ltd Temporary pipe conduit for indoor use, and control and supply system for temporary pipe conduit for indoor use
US20130321131A1 (en) * 2012-05-29 2013-12-05 Utilystar, Llp System and method for quality control, inspection and audit of utility assets

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004252851A (en) * 2003-02-21 2004-09-09 Nippon Telegr & Teleph Corp <Ntt> Processing method and device for operating passive component management, work support terminal, program for operating passive component management, and storage medium using it
JP2007272508A (en) * 2006-03-31 2007-10-18 Ffc Ltd Wiring and piping management method and wiring and piping management system
JP2009211454A (en) * 2008-03-05 2009-09-17 Hitachi Ltd Execution confirmation apparatus and design support system using it
JP2012122209A (en) * 2010-12-07 2012-06-28 Komei Mfg Co Ltd Temporary pipe conduit for indoor use, and control and supply system for temporary pipe conduit for indoor use
US20130321131A1 (en) * 2012-05-29 2013-12-05 Utilystar, Llp System and method for quality control, inspection and audit of utility assets

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
川畑淳一: "電力・エネルギー分野の最新開発技術", 日立評論, vol. 第88巻,第2号, JPN6018007729, 1 February 2006 (2006-02-01), JP, pages 25 - 28, ISSN: 0003927549 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6221192B1 (en) * 2016-11-11 2017-11-01 株式会社大和精機 Cable protector and pedestrian guidance system
JP2018078766A (en) * 2016-11-11 2018-05-17 株式会社大和精機 Cable protector and pedestrian guide system
JP2018147440A (en) * 2017-03-09 2018-09-20 株式会社日立プラントコンストラクション Cable construction management system
JP2020009307A (en) * 2018-07-11 2020-01-16 東芝プラントシステム株式会社 Material management device and material management method
JP7373269B2 (en) 2018-07-11 2023-11-02 東芝プラントシステム株式会社 Cable management device and cable management method
JP2020200696A (en) * 2019-06-12 2020-12-17 日立Geニュークリア・エナジー株式会社 Method for constructing structure and closing plug for embedded pipe
JP7178963B2 (en) 2019-06-12 2022-11-28 日立Geニュークリア・エナジー株式会社 Structure construction method
JP7486458B2 (en) 2021-04-21 2024-05-17 三菱重工業株式会社 Underfloor wiring structure and underfloor wiring method
KR20220165577A (en) * 2021-06-08 2022-12-15 한국전력공사 Indicator system and indicator for power installations
KR102523552B1 (en) 2021-06-08 2023-04-20 한국전력공사 Indicator system and indicator for power installations

Similar Documents

Publication Publication Date Title
JP2016115114A (en) Construction method and construction system for electric instrument equipment in power station by using rfid
US10380273B2 (en) System and method for testing the validity of BIM-designed electrical wiring pathways
EP3477512B1 (en) Total supporting method and total supporting system of wire harness
US20240029581A1 (en) Method for assembling or repairing a connectorized electrical equipment in an environment
JP6607424B2 (en) Wire harness manufacturing support apparatus and wire harness manufacturing support method
US10705135B2 (en) Method for assembling a connectorized equipment
JP2009211454A (en) Execution confirmation apparatus and design support system using it
JP4452190B2 (en) Piping support construction drawing editing method, drawing editing system and editing support device
JP5113676B2 (en) Control panel design support system
JP2016143223A (en) Manufacturing support system for wire harness
JP2003281196A (en) Device connection management system
JP4812700B2 (en) Work support method
JP2007272508A (en) Wiring and piping management method and wiring and piping management system
JP2014142823A (en) Data creation device and method
JP2004252851A (en) Processing method and device for operating passive component management, work support terminal, program for operating passive component management, and storage medium using it
JP2001297116A (en) Integrated design system of plant and integrated management system of plant construction project
WO2020113329A1 (en) Augmented reality or virtual reality apparatus for producing connectorized equipment and managing the production thereof
JP6754239B2 (en) Piping construction drawing creation method and piping construction drawing creation device
JP2021039479A (en) Apparatus and method for plant engineering assistance
JP6476446B2 (en) Work approval support method and work approval support system
EP4254288A1 (en) Data management system, management method, and management program
JP2019140712A (en) Cable laying management device, cable laying management method and program
JP2018092521A (en) Operation time adjustment system accompanied with power failure work
JP2006268491A (en) Electric apparatus introduction examination program
JP2017111735A (en) Underground pipe information management device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170208

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180228

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180306

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20180413

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180613

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20181204

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190116

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20190702