JP2016108925A - Caisson structure, and application method thereof - Google Patents

Caisson structure, and application method thereof Download PDF

Info

Publication number
JP2016108925A
JP2016108925A JP2015115400A JP2015115400A JP2016108925A JP 2016108925 A JP2016108925 A JP 2016108925A JP 2015115400 A JP2015115400 A JP 2015115400A JP 2015115400 A JP2015115400 A JP 2015115400A JP 2016108925 A JP2016108925 A JP 2016108925A
Authority
JP
Japan
Prior art keywords
caisson
hole
wall surface
caisson structure
opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015115400A
Other languages
Japanese (ja)
Other versions
JP6585930B2 (en
Inventor
浩樹 椋田
Hiroki Mukuda
浩樹 椋田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of JP2016108925A publication Critical patent/JP2016108925A/en
Application granted granted Critical
Publication of JP6585930B2 publication Critical patent/JP6585930B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Earth Drilling (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a kind of caisson structure that may be applied to a traditional caisson method and a press-fit caisson method, along with an application method of the caisson structure.SOLUTION: Thus, application to a caisson method is possible. The caisson structure has a through-hole in a box-form skeleton, in which a first opening on one end of the through-hole is located on a side of a body, with a second opening at a location away from the first opening, and the second opening is also connected to the through-hole. A wall surface body surrounds the first opening, the second opening, and the through-hole, with a plurality of wall surface through-holes formed through the wall surface body in parallel with the wall surface. The present invention significantly curtails time needed for preparation work when crushing a ground for increasing the number of times of excavation and destroying a foreign object underneath a box by inserting a washing device into the wall surface through-hole, thereby enhancing work efficiency for installation work, at the same time preventing deviation of the skeleton when the skeleton comes in contact with the foreign object. Also, cleaning work in a dead corner that cannot be cleaned with a drilling apparatus or a cleaning device is facilitated.SELECTED DRAWING: Figure 1

Description

本発明はケーソン工事に関する一種であり、特に伝統的なケーソン工法及び圧入式ケーソン工法のケーソン構造とその応用工法に関するものである。   The present invention relates to a caisson work, and more particularly to a caisson structure of a traditional caisson method and a press-fitting caisson method and its application method.

ケーソン工法は、道路、鉄道や河川などの橋梁基礎を作ることができ、現場で施工する場所打杭工法と比較して、地上で施工することによって品質や剛性は、良好な耐震性と安定性を有している。   The caisson method can create bridge foundations for roads, railways, rivers, etc. Compared with the cast-in-place pile method, which is constructed on site, the quality and rigidity of the caisson method are good for earthquake resistance and stability. have.

さらに、場所打杭工法は広い施工面積が必要だが、それと比較してケーソン工法は、必要な面積が小さく、市街地に於ける狭窄空間内の施工にも、施工面積が小さい利点を発揮でき、さらに、橋梁基礎工、立坑工や河川改修工、建築基礎工及び地下室工事など幅広い運用が可能である。   Furthermore, the cast-in-place pile construction method requires a large construction area, but the caisson construction method has a smaller required area compared to that, and can also demonstrate the advantage of a small construction area for construction in confined spaces in urban areas. Wide range of operations such as bridge foundation work, shaft work, river repair work, building foundation work and basement work are possible.

ケーソン工法はケーソンを地盤内に沈める工法であるので、ケーソンの沈下作業の可否が施工過程おける非常に重要な工程の一つである。
伝統的なケーソン工法には、オープン・ケーソン工法やニューマチックケーソン工法、水中ケーソン工法、載荷工法がある。
伝統的な工法はケーソン底部の地盤を掘り越す必要があり、ケーソンの自重で沈下させる。
しかし、湧砂や地盤隆起などが発生する可能性があり、しかも、ケーソンの沈下時に不平衡な力を受け、ケーソンの垂直度が偏移する可能性がある。
したがって、現在では圧入式工法が多く採用されるようになった。
圧入式工法では、アンカーで反作用力を負担させ、油圧ジャッキの上下方向の交互作用によって、油圧ジャッキ上の治具が竹節状のロッドを挟んで垂直に動力を伝導し、さらに油圧ジャッキが竹節状のロッド上で刃先の抵抗力及びケーソン周りの摩擦力より大きな力を駆動させて、ケーソンを沈下させる。
Since the caisson method is a method of sinking the caisson in the ground, whether or not the caisson can be subsidized is one of the very important steps in the construction process.
Traditional caisson methods include open caisson method, pneumatic caisson method, underwater caisson method, and loading method.
The traditional method requires digging the ground at the bottom of the caisson and sinks with the caisson's own weight.
However, there is a possibility that spring sand or ground uplift may occur, and the caisson's verticality may shift due to unbalanced forces when the caisson sinks.
Therefore, the press-fitting method is now widely used.
In the press-fitting method, the reaction force is borne by the anchor, and the jig on the hydraulic jack conducts power vertically through the bamboo knot-shaped rod by the vertical interaction of the hydraulic jack, and the hydraulic jack is bamboo-shaped The caisson is sunk by driving a force larger than the resistance force of the cutting edge and the frictional force around the caisson on the rod.

伝統的なケーソン工法や圧入式ケーソン工法でも施工上の克服すべき問題がある。
主因はケーソン工事を始める前に、圧入する地盤の状況を検査しなければならず、固い岩盤がある場合にはそのままではケーソン工事が不可能であるので、先に岩盤を破砕処理し、沈下させる領域の土砂を入れ替えた後でケーソン工事が可能になる。
ここで、破砕や取り出し、置換等の前処理作業に多くの施工時間やスペース、輸送コストを消費し、ケーソンを沈下させる時に同時にこれらの作業が出来ないことからコストも高くなり、時間の浪費にもなる。
Even the traditional caisson method and press-fitting caisson method have problems to overcome in construction.
The main cause is that before starting caisson work, the condition of the ground to be injected must be inspected. If there is a hard rock, caisson work is impossible as it is, so the rock is first crushed and subsidized. Caisson work is possible after replacing the earth and sand in the area.
Here, a lot of construction time, space, and transportation costs are consumed for pre-processing work such as crushing, taking out, and replacement, and since these work cannot be done at the same time when sinking the caisson, the cost becomes high and time is wasted. Also become.

さらに、ケーソンを沈下させる時に遭遇する土砂に高低差がある場合には、土砂をすぐ破壊しないとケーソンが偏移することになる。
図1に示すように、ケーソン1を沈下させている時に遭遇した地盤Rには高低差があり、ケーソンの左下にある刃口10が先に地盤Rに接触し、左の地盤Rをすぐ破壊しないとケーソンが傾いて、ケーソン1の偏移が施工精度に影響を与える。
さらに、図2に示したように、掘削機具を使ってケーソン内部の土砂を掘削する際、ケーソン1の壁11は一定の厚みがあり、死角区域R1を形成することから、掘削機具では壁11の下の区域R1にある土砂を掘ることができず、ケーソン1をスムーズに沈下させることができなくなる。
したがって、現在のケーソン工法は改善する必要がある。
Furthermore, if there is a difference in height between the sediments encountered when sinking the caisson, the caisson will shift if the sediment is not destroyed immediately.
As shown in FIG. 1, the ground R encountered when the caisson 1 is sinking has a height difference, and the blade edge 10 at the lower left of the caisson comes into contact with the ground R first, and the left ground R is immediately destroyed. Otherwise, the caisson will tilt and the shift of the caisson 1 will affect the construction accuracy.
Furthermore, as shown in FIG. 2, when excavating the earth and sand inside the caisson using the excavator, the wall 11 of the caisson 1 has a certain thickness and forms a blind spot area R1. The earth and sand in the lower area R1 cannot be dug, and the caisson 1 cannot sink smoothly.
Therefore, the current caisson method needs to be improved.

本発明の目的は、伝統的なケーソン工法と圧入式ケーソン工法に適用できる一種のケーソン構造及びその応用工法の提示である。   The object of the present invention is to present a kind of caisson structure applicable to the traditional caisson method and the press-fitting caisson method and its application method.

前述した目的のように、本発明は一種のケーソン構造の提出であり、それには一つの躯体が含まれ、その躯体の中には一つの貫通孔があって、その貫通孔に繋がっている第一開口部は本体の片端にあって、第一穴から離れた側にある第二開口部もその貫通孔に繋がっていている。
その第一開口部と第二開口部、貫通孔を囲んで一つの壁面体があり、壁面体を貫通している複数の壁面貫通孔があって、その壁面と平行している。
As described above, the present invention is a submission of a kind of caisson structure, which includes one housing, and there is one through hole in the housing, which is connected to the through hole. One opening is at one end of the main body, and the second opening on the side away from the first hole is also connected to the through hole.
There is one wall surface body surrounding the first opening portion, the second opening portion, and the through hole, and there are a plurality of wall surface through holes penetrating the wall surface body, which are parallel to the wall surface.

また、本発明は、一種の応用を提示することであり、これはこれまで説明したようにケーソン構造のケーソン応用工法であり、以下のステップを含む。
ステップ1:ケーソンを指定区域の地盤に圧入。
ステップ2:掘削機具を用いて地盤上にある異物を掘り出し、ケーソン内部から排出。
ステップ3:ケーソンを地盤に沈下。
さらに、
ステップ4:ステップ2とステップ3を繰り返し、躯体を予定の深度まで沈下。
In addition, the present invention is to present a kind of application, which is a caisson structure construction method of caisson structure as described above, and includes the following steps.
Step 1: Press the caisson into the specified area.
Step 2: Excavate foreign matter on the ground using an excavator and discharge it from the caisson.
Step 3: Sink caisson to the ground.
further,
Step 4: Repeat Step 2 and Step 3 to sink the enclosure to the expected depth.

さらに、ステップ2において、洗浄機具を壁面貫通孔に通して、貫通孔周辺の異物を破壊する。   Further, in step 2, the cleaning tool is passed through the wall surface through hole to destroy the foreign matter around the through hole.

さらに、ステップ4の後でステップ5として、壁面貫通孔を通した洗浄器具で躯体底部にある異物を取り除く。   Further, as a step 5 after the step 4, the foreign matter at the bottom of the housing is removed with a cleaning tool through the wall surface through hole.

そのうえ、本発明はもう一種の応用を提示する。
これはこれまで説明したようにケーソン構造のケーソン応用工法であり、下のステップを含む。
ステップA:箱体を指定区域の地盤に圧入。
ステップB:圧入設備を躯体の上部に設置する。
圧入設備とは、ケーソンに繋がる反力桁と反力桁に繋がるジャッキを含む。
ステップC:掘削機具を用いて地盤上にある異物を掘り出し、躯体内から排出。
ステップD:ジャッキを用いて反力桁を圧し、ケーソンを沈下。
さらに、
ステップE:ステップCとステップDを繰り返し、予定深度まで沈下。
Moreover, the present invention presents another kind of application.
As described above, this is a caisson structure construction method of caisson structure and includes the following steps.
Step A: Press-fit the box into the designated area ground.
Step B: Install the press-fitting equipment on top of the housing.
The press-fitting equipment includes a reaction force girder connected to the caisson and a jack connected to the reaction force girder.
Step C: Excavate foreign matter on the ground using an excavator and discharge it from the enclosure.
Step D: Press the reaction force girder with a jack to sink the caisson.
further,
Step E: Repeat Step C and Step D to sink to the planned depth.

さらに、ステップCにおいて、洗浄機具を壁面貫通孔に通して、貫通孔周辺の異物を破壊する。   Further, in Step C, the cleaning tool is passed through the wall surface through hole to destroy the foreign matter around the through hole.

さらに、ステップEの後で、ステップFとして、壁面貫通孔を通した洗浄器具で躯体底部にある異物を取り除く。   Further, after Step E, as Step F, the foreign matter at the bottom of the housing is removed with a cleaning instrument that has passed through the wall surface through hole.

そこで、この発明は、上述不都合を除去するために、ケーソン構造の一種であり、ケーソン工法に適応できる工法であり、一つの駆体と、その駆体の内部に貫通孔があって、その貫通孔に繋がっている第一開口部は駆体の片側にあって、第一開口部から離れている第二開口部もその貫通孔に繋がり、第一開口部と第二開口部、貫通孔を囲んでいる壁面体があり、その壁面体を貫通している複数の壁面貫通孔があって、壁面体と平行していることを特徴とする。
また、ケーソン構造のケーソン応用工法の応用の一つの種類であり、以下の、
ステップ1:ケーソンを指定区域の地盤に圧入、
ステップ2:掘削機具で地盤にある異物を掘り出し、ケーソンから排出、
ステップ3:ケーソンを地盤に圧入、
ステップ4:ステップ2とステップ3を繰り返し、予定の深さまで沈下、
のステップを含むことを特徴とする。
更に、ケーソン構造のケーソン応用工法の応用の一つの種類であり、以下の、
ステップA:駆体を指定区域の地盤に圧入、
ステップB:圧入設備を駆体の上部に設置し、その圧入設備は駆体に繋がる反力桁と反力桁に繋がるジャッキを含む、
ステップC:掘削機具で地盤にある異物を掘り出し、駆体から排出、
ステップD:ジャッキが反力桁を押す力を利用して駆体を沈下、
ステップE:ステップCとステップDを繰り返し、予定深度に沈設、
のステップを含むことを特徴とする。
Therefore, this invention is a kind of caisson structure to eliminate the inconvenience described above, and is a construction method that can be applied to the caisson construction method. The first opening connected to the hole is on one side of the driver, the second opening away from the first opening is also connected to the through hole, and the first opening, the second opening, and the through hole are connected. There is a wall surface body that surrounds, and there are a plurality of wall surface through holes penetrating the wall surface body, and the wall surface body is parallel to the wall surface body.
In addition, it is one kind of application of caisson construction method of caisson structure,
Step 1: Press the caisson into the ground of the designated area,
Step 2: Excavate foreign material on the ground with an excavator and discharge it from the caisson.
Step 3: Press caisson into the ground,
Step 4: Repeat Step 2 and Step 3 to sink to the planned depth,
These steps are included.
Furthermore, it is one kind of application of the caisson construction method of caisson structure,
Step A: Press the fuselage into the ground of the designated area.
Step B: Install the press-fit equipment on top of the fuselage, and the press-fit equipment includes a reaction force girder connected to the fuselage and a jack connected to the reaction force girder.
Step C: Excavate foreign matter on the ground with an excavator and discharge it from the body.
Step D: Using the force with which the jack pushes the reaction force beam,
Step E: Repeat Step C and Step D, sink to the planned depth,
These steps are included.

本発明の特徴は、以下のようである。
(1)本発明は、ケーソン沈下時に、それぞれの壁面貫通孔を通した洗浄器具を用いて躯体下端で壁面貫通孔周辺の遺物を同時に破壊することによって、沈下操作と岩盤破壊が同時に行えないという欠点を克服し、準備作業時間、施工スペースの浪費を大幅に削減でき、コスト効率の低下を改善し、施工効率を上昇できる。
(2)本発明は、ケーソン沈下時に高低差のある異物に遭遇した際、増設した洗浄機具を壁面貫通孔に通し、躯体下部と壁面貫通孔周辺の異物を破壊でき、ケーソンが不均衡な力を受けて偏移するのを防ぐことができる。
(3)本発明は、洗浄機具を壁面貫通孔に通し、躯体下部と壁面貫通孔周辺の異物を破壊することによって、掘削機具で掘るのが容易でない躯体下部の死角区域内のケーソン沈下の障害となる異物を克服できる。
(4)本発明は、洗浄機具を壁面貫通孔に通し、躯体下部と壁面貫通孔周辺の異物を破壊することによって、異物がケーソン底面の密封作業に影響を与える事を避けることができる。
The features of the present invention are as follows.
(1) According to the present invention, at the time of caisson settlement, by using a cleaning instrument that has passed through each wall through hole, the remnants around the wall through hole are destroyed at the same time at the lower end of the housing, so that the settlement operation and the rock mass destruction cannot be performed simultaneously. Overcoming shortcomings, drastically reducing waste of preparatory work time and construction space, improving cost efficiency and improving construction efficiency.
(2) In the present invention, when a foreign object with a difference in height is encountered when the caisson sinks, the extra cleaning equipment can be passed through the wall through hole, and the foreign material around the lower part of the housing and the wall through hole can be destroyed. Can be prevented from shifting.
(3) The present invention is an obstacle to caisson settlement in the blind spot area in the lower part of the housing that is not easy to dig with the excavating tool by passing the cleaning tool through the wall through hole and destroying the foreign matter around the lower part of the housing and the wall through hole. You can overcome the foreign material.
(4) According to the present invention, it is possible to avoid the foreign matter from affecting the sealing operation of the bottom surface of the caisson by passing the cleaning machine through the wall through hole and destroying the foreign matter around the lower part of the housing and the wall through hole.

図1は本発明の従来技術を示すケーソン工法の欠点の一つを示した透視断面図である。FIG. 1 is a perspective sectional view showing one of the disadvantages of the caisson method showing the prior art of the present invention. 図2はケーソン工法の別の欠点の一つを示した透視断面図である。FIG. 2 is a perspective sectional view showing one of the other disadvantages of the caisson method. 図3は本発明のケーソン構造立体図である。(実施例1)FIG. 3 is a three-dimensional view of the caisson structure of the present invention. Example 1 図4は図3のA−A位置の透視断面図図である。(実施例1)4 is a perspective sectional view taken along the line AA in FIG. Example 1 図5は図3の1種類目のケーソン応用工法のフローチャートである。(実施例1)FIG. 5 is a flowchart of the first type of caisson application method of FIG. Example 1 図6は図5の施工時の透視断面図である。(実施例1)6 is a perspective sectional view of the construction shown in FIG. Example 1 図7は1種類目のケーソン応用工法の洗浄器具の透視断面図である。(実施例1)FIG. 7 is a perspective sectional view of the first type of caisson applied construction cleaning tool. Example 1 図8は図3の2種類目のケーソン応用工法のフローチャート図である。(実施例1)FIG. 8 is a flowchart of the second caisson application method of FIG. Example 1 図9は図8の施工時の透視断面図である。(実施例1)FIG. 9 is a perspective sectional view of the construction shown in FIG. Example 1

以下図面に基づいてこの発明の実施例を詳細に説明する。   Embodiments of the present invention will be described below in detail with reference to the drawings.

以下は添付された図と呼応し、本発明の構造がどのように組み合わされて、使用するかをより詳しく説明することによって、本発明の目的や技術内容、特徴及びその達成される効能をより簡単に理解できる。   The following will be explained in more detail with reference to the accompanying drawings, and by explaining in more detail how the structure of the present invention is combined and used. Easy to understand.

本発明は図3及び図4で示すようなケーソン構造の一種を提示し、更に図6と図8に別々に示したように2種類のケーソン応用工法を提示する。   The present invention presents a kind of caisson structure as shown in FIGS. 3 and 4, and further presents two types of caisson application methods as shown separately in FIGS.

図3と図4に示す通り、ケーソン構造は躯体2が一つ、その躯体内部には貫通孔20があり、貫通孔20に繋がっている第一開口部21は躯体の片端にあって、第一開口部から離れた位置にある第二開口部22もその貫通孔に繋がっていている。
その第一開口部21と第二開口部22、貫通孔20を囲んで一つの壁面体23があり、壁面体23を貫通している複数の壁面貫通孔24があって、その壁面と平行している。
その中で幾つかの壁面貫通孔24は、掘削器具や洗浄器具を壁面貫通孔24に通し、除去機具や洗浄機具で23壁の下にある異物を破壊し、異物が躯体2の偏移や沈下の障害にならないようにする。
その中で、異物というのは、地盤中の岩盤や、岩、土砂や鉱石など、工事に影響を与える媒介物質のことである。躯体2の沈下施工時、躯体2が沈下していく過程で先に金属製刃口25が掘削機具(クラムシェル等)では届かない場所にある異物に接触した場合、掘削器具や洗浄器具を壁面貫通孔24を通して躯体2底端の地盤で用いて躯体2が遭遇した異物を破壊し、躯体2をスムースに沈下できるようにする。
また、箱体2が沈下していく過程で、掘削機具が届かないような死角区域でも、同じように掘削器具や洗浄器具を壁面貫通孔24に通して処理する方法で改善される。
As shown in FIG. 3 and FIG. 4, the caisson structure has one housing 2, and there is a through hole 20 inside the housing, and the first opening 21 connected to the through hole 20 is at one end of the housing. The second opening 22 located away from the one opening is also connected to the through hole.
There is one wall surface body 23 surrounding the first opening portion 21, the second opening portion 22 and the through hole 20, and there are a plurality of wall surface through holes 24 penetrating the wall surface body 23. ing.
Among them, some wall surface through holes 24 pass excavation tools and cleaning tools through the wall surface through holes 24, destroy foreign substances under the 23 walls with a removal machine and a cleaning machine, Try not to be an obstacle to settlement.
Among them, foreign substances are mediators that affect the construction, such as bedrock in the ground, rocks, earth and sand, and ores. When the housing 2 sinks, if the metal blade 25 comes into contact with a foreign object that cannot be reached by an excavator (such as a clamshell) before the housing 2 sinks, It is used on the ground at the bottom end of the casing 2 through the through hole 24 to destroy the foreign matter encountered by the casing 2 so that the casing 2 can be smoothly sunk.
Further, in the process of sinking the box body 2, even in a blind spot area where the excavator does not reach, the drilling tool and the cleaning tool are similarly processed by passing through the wall surface through hole 24.

このようにして、本発明は図1と図2に示すように岩盤に遭遇して沈下作業が難しくなったり、沈下が阻害されるような苦境に陥った場合であっても確実に効果的な改善ができる。
さらに、躯体2の内外の圧力を平衡にする目的で、ケーソン沈下時に地下水位線まで水を躯体内に入れるが、これによって掘削の過程で躯体2内部の水によって、水面下にある異物の状況を正確には把握できなくなり、そして掘削が出来なくなり、躯体2がスムースに沈下出来なくなる。
そのような場合に、除去器具や洗浄器具を壁面貫通孔24に通して、水面下にある異物を破壊できる。
In this way, the present invention is surely effective even when it encounters a bedrock as shown in FIGS. 1 and 2 and the subsidence work becomes difficult or the subsidence is hindered. Can improve.
Furthermore, for the purpose of balancing the pressure inside and outside the enclosure 2, when caisson sinks, water is introduced into the enclosure up to the groundwater level line. Cannot be accurately grasped, and excavation cannot be performed, so that the frame 2 cannot be subsided smoothly.
In such a case, the removal tool or the cleaning tool can be passed through the wall surface through hole 24 to destroy the foreign matter under the water surface.

更に、本発明のケーソン構造は、図3と図4で示しているように、壁面体23の下端に複数の金属製刃口25を含んでいて、それらの金属刃口25は壁面体23の下端で鋭角部を下にした形になっている。
ケーソンを沈下させている時に、それらの金属製刃口25は、土砂を排除し、また岩盤を切り裂く一助となり、それにより躯体2をスムースに沈下させられる。
それ以外にも、本発明は、それらの壁面貫通孔24の効率を最大に発揮するために、本案の実施例において、それぞれの金属製刃口25を躯体2の下端で、尚且つそれぞれの壁面貫通孔24に抵触しないように設置している。
但し、本件は、この実施例の形態に限定されない。
Further, as shown in FIGS. 3 and 4, the caisson structure of the present invention includes a plurality of metal blade edges 25 at the lower end of the wall surface body 23, and these metal blade edges 25 are formed on the wall surface body 23. It has a shape with a sharp corner at the bottom.
When the caisson is sinking, these metal blades 25 help to remove earth and sand and help to tear the bedrock, thereby smoothly sinking the enclosure 2.
In addition, in order to maximize the efficiency of the wall surface through-holes 24, the present invention provides each metal blade edge 25 at the lower end of the housing 2 and each wall surface in the embodiment of the present plan. It is installed so as not to touch the through hole 24.
However, this case is not limited to the form of this embodiment.

さらに、本発明は他の先行技術と違う重要な技術的改善箇所は、図6と図76で示しているように、壁面貫通孔24を通している除去機具5と洗浄機具6を含んでいることである。
本件の沈設工事を行っている時、外部の掘削機具で駆体2の中の岩盤や土砂を除去するが、駆体2の底部に死角ができ、前述の掘削機具では除去するのが難しく、駆体2の沈設の障害になり施工に影響を及ぼし得る。
一旦、駆体2の底部が沈設中に異物に遭遇し、不均衡な力を受けて駆体2が偏移した場合、施工精度に影響を与える。
また大型岩盤や硬い岩盤に遭遇し沈設の障害になった場合には、除去機具5を壁面貫通孔24に通し、壁23の下端と壁面貫通孔24の周囲にある異物を排除し、ケーソンが偏移したり停滞したりせずに、図1と図2に示しているような周知の欠点を克服し、ケーソンをスムースに沈設させられる。
Further, the present invention is different from other prior arts in that significant technical improvements include the removal device 5 and the cleaning device 6 that pass through the wall surface through-hole 24 as shown in FIGS. is there.
When performing the subsidence work of this case, the rocks and earth and sand in the fuselage 2 are removed with an external excavator, but a blind spot is formed at the bottom of the fuselage 2 and is difficult to remove with the aforementioned excavator. It may be an obstacle to the setting of the driving body 2 and affect the construction.
Once the bottom of the fuselage 2 encounters a foreign object while it is being sunk, and the thruster 2 shifts due to an unbalanced force, the construction accuracy is affected.
Also, when encountering a large bedrock or hard bedrock and obstructing the settling, the removal device 5 is passed through the wall surface through hole 24 to remove foreign matters around the lower end of the wall 23 and the wall surface through hole 24, Without shifting or stagnating, the known disadvantages as shown in FIGS. 1 and 2 can be overcome and the caisson can be smoothly laid.

前に述べたように、沈設工事を行っている時、内外の気圧を平衡に保つために駆体2に水を地下水位線まで入れる場合があるが、そのために水中にある異物の状況を正確には把握できなくなる。
そのような時、除去器具5を壁面貫通孔24に通し、水中の異物を破壊する。
それ以外にも、駆体2を予定の深度まで沈設した後で、駆体2底面を密封する工程において、異物がこの作業に影響を与える事を避ける為に、洗浄器具6で駆体2の底部や内部の異物を金属製刃口25に付いている異物を除去する。
これは、除去器具5で壁面体23の下端や壁面貫通孔24の周りにある異物を破壊し、洗浄器具6で駆体2の底部やその内部にある異物を除去することで、工事をより順調に、より効率よく完工させ、現在のケーソン圧入工法が直面している問題を完全に克服できる、新たな発明である。
今回の実施例の中で、地下水位線と予定深度は実際の施工で遭遇する状況であるので、これ以上は述べない。
今件の実施例において、除去器具5はブレーカーやオーガー、その他の壁面貫通孔24を通して異物を破壊する器具を想定していて、洗浄機具6は圧力洗浄機やポンプ、サンドポンプ、或いは駆体2の底面の異物を除去する器具等を想定しているが、本件は、この実施例の形態に限定されない。
As mentioned previously, when performing the construction work, water may be put into the groundwork 2 to maintain the atmospheric pressure inside and outside, so that the condition of foreign matter in the water can be accurately determined. Will not be able to grasp.
At such time, the removal tool 5 is passed through the wall surface through hole 24 to destroy the foreign matter in the water.
In addition, in order to prevent foreign matter from influencing this work in the process of sealing the bottom surface of the main body 2 after the main body 2 has been laid down to a predetermined depth, The foreign matter attached to the metal blade 25 is removed from the bottom and internal foreign matter.
This is because the removal tool 5 destroys the foreign matter around the lower end of the wall surface body 23 and the wall surface through-hole 24, and the cleaning tool 6 removes the foreign matter at the bottom and inside of the fuselage 2, thereby making the construction more efficient. It is a new invention that can be completed smoothly and efficiently, and can completely overcome the problems facing the current caisson press-fitting method.
In this example, the groundwater level line and the planned depth are the situations encountered in actual construction, and will not be described further.
In the present embodiment, the removal device 5 is assumed to be a breaker, an auger, or other device that breaks foreign matter through the wall surface through-hole 24, and the cleaning tool 6 is a pressure washer, pump, sand pump, or fuselage 2. Although the instrument etc. which remove the foreign material of the bottom face of this are assumed, this case is not limited to the form of this Example.

伝統的なケーソン工法に本発明のケーソン構造を応用した説明を続ける。
図5から図7までを参照せよ。
本発明で示したケーソン応用工法の一つは、以下のステップを含む。
ステップ1:上記で述べたケーソン構造の駆体2を指定区域R2の地盤に圧入。
ステップ2:掘削機具3を貫通孔20に通して、地盤上にある異物を掘り出し、駆体2の内部から排出する。
ステップ3:駆体2を地盤に沈める。
ステップ4:ステップ2とステップ3を繰り返し、予定された深度に沈設する。
ステップ5:洗浄器具6を壁面貫通孔24に通して、駆体2の底にある異物を除去し、それによって、異物の影響が駆体2底部の密封作業に影響を及ぼすのを避ける。
そのほかに、洗浄器具6を駆体2の内部の貫通孔2を通して駆体2底面にある異物を除去することもできる。
The explanation of applying the caisson structure of the present invention to the traditional caisson method will be continued.
See FIGS. 5-7.
One of the caisson application methods shown in the present invention includes the following steps.
Step 1: Press-fit the caisson structure body 2 described above into the ground of the designated area R2.
Step 2: The excavator 3 is passed through the through hole 20 to excavate foreign matter on the ground and discharged from the interior of the fuselage 2.
Step 3: Submerge the fuselage 2 on the ground.
Step 4: Repeat Step 2 and Step 3 to set up at the planned depth.
Step 5: The cleaning tool 6 is passed through the wall surface through-hole 24 to remove foreign matter on the bottom of the fuser 2, thereby avoiding the influence of the foreign matter on the sealing operation of the bottom of the fuser 2.
In addition, the foreign material on the bottom surface of the driver 2 can be removed from the cleaning tool 6 through the through hole 2 inside the driver 2.

更に、ステップ2において、除去器具5は壁面貫通孔24の周りにある異物を除去し、それによって駆体2が偏移して施工に影響するのを防ぐ。
その中で、本件の第一種類目のケーソン応用工法の手順は、伝統的なケーソン工法に適用できる。
例えば、オープンケーソン工法や、ニューマチックケーソン工法、水中ケーソン工法、載荷工法など、その工法は当該の地盤を先堀方式で掘削し、駆体2の自重を金属製刃口25に伝達し、金属製刃口25が地盤に切り込むのを利用して駆体2を沈下させる。
しかし、本件はその限りではない。
Furthermore, in step 2, the removal tool 5 removes foreign matter around the wall surface through-hole 24, thereby preventing the precursor 2 from shifting and affecting the construction.
Among them, the procedure of the first type of caisson applied method in this case can be applied to the traditional caisson method.
For example, the open caisson method, the pneumatic caisson method, the underwater caisson method, the loading method, etc., the method excavates the ground by the pre-drilling method, transmits the dead weight of the fuselage 2 to the metal blade 25, and the metal The driving body 2 is sunk using the cutting edge 25 cut into the ground.
However, this is not the case.

上記で説明した圧入式ケーソン工法に対する本発明のケーソン構造への応用について続ける。
図8、9を参考せよ。
本発明は、もう一つ別のケーソン応用工法を示す、その工法は以下のステップを含む。
ステップA:上記で説明したケーソン構造の駆体2を指定区域R2の地盤に圧入。
ステップB:圧入設備4を駆体2の上に設置し、その圧入設備4は、駆体2上端の少なくとも一つの反力桁40に繋がっていて、また反力桁40上端の少なくとも一台のジャッキ41に繋がっている。
本件の実施例中には、反力桁40は一つ、ジャッキ41は二台が想定されているが、本件は、この実施例の形態に限定されない。
ステップC:掘削機具3を貫通孔20から通して、地盤にある異物を掘り出し、更に駆体2の内部から排出する。
ステップD:ジャッキ41の力を利用して反力桁を押し、駆体2を沈下させる。
ステップE:ステップCとステップDを繰り返し、ケーソンを予定深度まで沈下させる。
ステップF:洗浄器具6(図7を参照せよ)を壁面貫通孔24に通して、箱体2の底面にある異物を除去し、さらに、洗浄器具6を貫通孔20から通して、駆体2底部にある異物を除去する。
The application of the caisson structure of the present invention to the press-fitting caisson method described above will be continued.
Refer to FIGS.
The present invention shows another caisson application method, which includes the following steps.
Step A: Press the caisson structure 2 described above into the ground of the designated area R2.
Step B: The press-fitting equipment 4 is installed on the fuselage 2, and the press-fitting equipment 4 is connected to at least one reaction force girder 40 at the upper end of the fuser 2, and at least one of the reaction force girder 40 at the upper end. It is connected to the jack 41.
In this embodiment, one reaction force girder 40 and two jacks 41 are assumed. However, the present embodiment is not limited to this embodiment.
Step C: The excavator 3 is passed through the through-hole 20 to excavate foreign matter on the ground, and then discharged from the inside of the driving body 2.
Step D: The reaction force girder is pushed using the force of the jack 41, and the body 2 is sunk.
Step E: Repeat Step C and Step D to sink the caisson to the expected depth.
Step F: The cleaning tool 6 (see FIG. 7) is passed through the wall surface through-hole 24 to remove foreign matter on the bottom surface of the box body 2, and the cleaning tool 6 is passed through the through-hole 20 to drive the body 2. Remove foreign material at the bottom.

さらに、ステップCにおいて、除去器具5を壁面貫通孔24に通して、その周囲にある異物を除去し、それによって、駆体2が偏移して施工に影響することを防ぐ。   Furthermore, in Step C, the removal tool 5 is passed through the wall surface through hole 24 to remove foreign matter around it, thereby preventing the precursor 2 from shifting and affecting the construction.

本発明の二種類目の応用工法の手順は、圧入式ケーソン工法に適用でき、且つ施工過程において、反力桁架40やジャッキ41の引張部材42が複数交互に垂直に組み合わされて設置され、更に複数の引張部材42の最下端が地盤上のアンカー431に固定されている。
アンカー43が、施工中に反力桁40とジャッキ41、引張部材42の連結強度及び安定度を与え、ジャッキ41が引張部材42上で反作用によって、連続した下向きの動作で反力桁40を押し下げ、それによって駆体2を予定の深度まで押し下げる。
その中で、ジャッキは引張部材を挟む事ができる治具があり、それぞれの引張部材42は、もう一つ別の引張部材42と相互に繋ぐことで連続した一つの金属製連結部材になる。
アンカー43は、複数のPC鋼撚り線をその上に設置し固定した地盤上の一種の装置であり、その機能は、アンカー鋼線が主要な構造体を通して周辺の緊密な地層に伝達することであり、但し前述したジャッキ41や引張部材42、アンカー43は現工法で既にあり、従ってここでは詳細な説明はしない。
The procedure of the second applied construction method of the present invention can be applied to the press-fitting caisson method, and in the construction process, a plurality of tension members 42 of reaction force girders 40 and jacks 41 are installed in a vertical combination, and further, The lowermost ends of the plurality of tension members 42 are fixed to anchors 431 on the ground.
The anchor 43 gives the connection strength and stability of the reaction force girder 40, the jack 41, and the tension member 42 during construction, and the jack 41 pushes down the reaction force girder 40 in a continuous downward motion by reaction on the tension member 42. , Thereby pushing down the fuselage 2 to the expected depth.
Among them, the jack has a jig capable of sandwiching a tension member, and each tension member 42 is connected to another tension member 42 to become one continuous metal connecting member.
The anchor 43 is a kind of device on the ground on which a plurality of PC steel stranded wires are installed and fixed, and the function of the anchor 43 is that the anchor steel wire is transmitted through the main structure to the surrounding close formation. However, the jack 41, the tension member 42, and the anchor 43 described above are already in the present construction method, and therefore will not be described in detail here.

上で述べたように、本発明は除去器具5を駆体2の壁面体23の壁面貫通孔24に通すことで、壁面体23下端で且つそれぞれの壁面貫通孔24周辺の異物を破壊し、周知の三種類の欠点を改善する。
且つ、ケーソン施工中に、駆体2内外を平行にするために駆体2内に水を地下水位線まで注入するが、掘削過程において水位以下にある異物が正確に把握できなくなり、駆体2をスムースに沈下出来なくなる。
また除去器具5を壁面貫通孔24を通して水位以下の異物を破壊する。
それ以外にも、本発明は、洗浄器具6を駆体2の壁面体23の壁面貫通孔24に通すことで、駆体2の底部と金属製刃口25に付着した異物を除去し、駆体2の底部の密封作業に影響するのを防ぐ。
As described above, the present invention destroys the foreign matter at the lower end of the wall surface body 23 and around each wall surface through hole 24 by passing the removal tool 5 through the wall surface through hole 24 of the wall surface body 23 of the drive unit 2. To improve three known drawbacks.
In addition, during caisson construction, water is injected into the groundwork 2 to make the inside and outside of the body 2 parallel to each other. However, foreign matter below the water level cannot be accurately grasped during the excavation process, and the body 2 Can no longer sink smoothly.
In addition, the removal tool 5 is destroyed through the wall surface through-hole 24 to remove foreign substances below the water level.
In addition to this, the present invention removes foreign matter adhering to the bottom of the body 2 and the metal blade 25 by passing the cleaning tool 6 through the wall surface through-hole 24 of the wall surface body 23 of the body 2. This prevents the bottom 2 of the body 2 from being affected.

しかし、上記は、本発明の好ましい実施例に過ぎない。
その目的は、その実施例によって本発明の内容を当該の担当者に十分に理解させるためであり、本発明の実施範囲を限定するものではない。
従って、本発明の実施例において説明した内容、すなわちこれまで記述したような形状や構造、特徴などのいわゆる均等の変更や修飾は、本発明の特許請求の範囲内に含めるべきである。
However, the above is only a preferred embodiment of the present invention.
The purpose is to allow the person in charge to fully understand the contents of the present invention through the embodiments, and does not limit the scope of the present invention.
Therefore, what is described in the embodiments of the present invention, that is, so-called equivalent changes and modifications such as shapes, structures, and features described so far should be included in the scope of the claims of the present invention.

1 ケーソン
10 刃口
11 壁面体
R 地盤
R1 区域
2 躯体
20 貫通孔
21 第一開口部
22 第二開口部
23 壁
24 壁面貫通孔
25 金属製刃口
3 掘削機具
4 圧入設備
40 反力桁
41 ジャッキ
42 引張部材
43 アンカー
5 洗浄器具
6 除去器具
R2 予定区域
DESCRIPTION OF SYMBOLS 1 Caisson 10 Cutting edge 11 Wall body R Ground R1 Area 2 Housing 20 Through-hole 21 1st opening part 22 2nd opening part 23 Wall 24 Wall surface through-hole 25 Metal cutting edge 3 Excavation equipment 4 Press fitting equipment 40 Reaction force girder 41 Jack 42 Tensile member 43 Anchor 5 Cleaning device 6 Removal device R2 Planned area

Claims (10)

ケーソン構造の一種であり、ケーソン工法に適応できる工法であり、一つの駆体と、その駆体の内部に貫通孔があって、その貫通孔に繋がっている第一開口部は駆体の片側にあって、第一開口部から離れている第二開口部もその貫通孔に繋がり、第一開口部と第二開口部、貫通孔を囲んでいる壁面体があり、その壁面体を貫通している複数の壁面貫通孔があって、壁面体と平行していることを特徴とするケーソン構造。   A type of caisson structure that can be adapted to the caisson method, with a single drive unit and a through hole inside the drive unit. The first opening connected to the through hole is on one side of the drive unit. And the second opening that is separated from the first opening is also connected to the through-hole, and there is a wall surface that surrounds the first opening, the second opening, and the through-hole. A caisson structure having a plurality of wall surface through-holes and parallel to the wall surface body. 前記壁面体の下端に複数の金属製刃口が分布されていて、その金属製刃口は壁面体の下端で逆角形の形状をしていることを特徴とする請求項1に記載のケーソン構造。   The caisson structure according to claim 1, wherein a plurality of metal blades are distributed at the lower end of the wall surface, and the metal blades have an inverted square shape at the lower end of the wall surface. . 前記壁面貫通孔を通す洗浄器具を含んでいることを特徴とする請求項1に記載のケーソン構造。   The caisson structure according to claim 1, further comprising a cleaning instrument through which the wall surface through-hole passes. 前記壁面貫通孔を通す除去器具を含んでいることを特徴とする請求項1に記載のケーソン構造。   The caisson structure according to claim 1, further comprising a removal tool through which the wall surface through-hole passes. ケーソン構造のケーソン応用工法の応用の一つの種類であり、以下の、
ステップ1:ケーソンを指定区域の地盤に圧入、
ステップ2:掘削機具で地盤にある異物を掘り出し、ケーソンから排出、
ステップ3:ケーソンを地盤に圧入、
ステップ4:ステップ2とステップ3を繰り返し、予定の深さまで沈下、
のステップを含むことを特徴とするケーソン構造のケーソン応用工法。
It is one kind of application of caisson construction method of caisson structure,
Step 1: Press the caisson into the ground of the designated area,
Step 2: Excavate foreign material on the ground with an excavator and discharge it from the caisson.
Step 3: Press caisson into the ground,
Step 4: Repeat Step 2 and Step 3 to sink to the planned depth,
The caisson structure is applied to the caisson structure.
前記ステップ2において、更に壁面貫通孔を通して壁面貫通孔の周囲にある異物を除去する除去器具の使用を含むことを特徴とする請求項5に記載のケーソン構造のケーソン応用工法。   6. The caisson structure caisson application method according to claim 5, wherein the step 2 further includes the use of a removal tool for removing foreign substances around the wall surface through hole through the wall surface through hole. 前記ステップ4の後で更にステップ5を含む、即ち壁面貫通孔を通す洗浄器具で駆体の底部にある異物を除去することを特徴とする請求項5に記載のケーソン構造のケーソン応用工法。   6. The caisson structure applied to caisson structure according to claim 5, further comprising step 5 after said step 4, i.e., removing foreign matter at the bottom of the fuselage with a cleaning tool that passes through the wall through hole. ケーソン構造のケーソン応用工法の応用の一つの種類であり、以下の、
ステップA:駆体を指定区域の地盤に圧入、
ステップB:圧入設備を駆体の上部に設置し、その圧入設備は駆体に繋がる反力桁と反力桁に繋がるジャッキを含む、
ステップC:掘削機具で地盤にある異物を掘り出し、駆体から排出、
ステップD:ジャッキが反力桁を押す力を利用して駆体を沈下、
ステップE:ステップCとステップDを繰り返し、予定深度に沈設、
のステップを含むことを特徴とするケーソン構造のケーソン応用工法。
It is one kind of application of caisson construction method of caisson structure,
Step A: Press the fuselage into the ground of the designated area.
Step B: Install the press-fit equipment on top of the fuselage, and the press-fit equipment includes a reaction force girder connected to the fuselage and a jack connected to the reaction force girder.
Step C: Excavate foreign matter on the ground with an excavator and discharge it from the body.
Step D: Using the force with which the jack pushes the reaction force beam,
Step E: Repeat Step C and Step D, sink to the planned depth,
The caisson structure is applied to the caisson structure.
前記ステップCに壁面貫通孔に通して壁面貫通孔の周りの異物を除去する洗浄機具を含むことを特徴とする請求項8に記載のケーソン構造のケーソン応用工法。   The caisson structure construction method according to claim 8, wherein the step C includes a cleaning tool that passes through the wall surface through hole and removes foreign matter around the wall surface through hole. 前記ステップEの後でステップFを含む、即ち、壁面貫通孔に通す洗浄器具を利用してケーソンの底部にある異物を除去することを特徴とする請求項8に記載のケーソン構造のケーソン応用工法。   The caisson structure applied to caisson structure according to claim 8, wherein the foreign matter at the bottom of the caisson is removed by using a cleaning tool including step F after the step E, i.e., through a wall through hole. .
JP2015115400A 2014-12-02 2015-06-08 Caisson applied method Active JP6585930B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
TW103141720A TW201621121A (en) 2014-12-02 2014-12-02 Caisson structure and application method thereof
TW103141720 2014-12-02

Publications (2)

Publication Number Publication Date
JP2016108925A true JP2016108925A (en) 2016-06-20
JP6585930B2 JP6585930B2 (en) 2019-10-02

Family

ID=56123396

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015115400A Active JP6585930B2 (en) 2014-12-02 2015-06-08 Caisson applied method

Country Status (2)

Country Link
JP (1) JP6585930B2 (en)
TW (1) TW201621121A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110055991A (en) * 2019-05-30 2019-07-26 安徽省交通控股集团有限公司 A kind of two-wall hollow well foundation and its sinking construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0776844A (en) * 1993-09-06 1995-03-20 Toda Constr Co Ltd Method of settling open caisson
JP2008231810A (en) * 2007-03-22 2008-10-02 Ps Mitsubishi Construction Co Ltd Underground structure construction method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI265224B (en) * 2004-10-15 2006-11-01 Sino Geotechnology Inc Construction method for expanding, grouting and reinforcing bores at stake bottom of stake base
CN201506969U (en) * 2009-08-26 2010-06-16 浙江海桐高新工程技术有限公司 Large-diameter dyke tubular pile and dyke or wharf structure thereof
CN201962644U (en) * 2010-12-17 2011-09-07 浙江海桐高新工程技术有限公司 Pile-supported type caisson seawall

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0776844A (en) * 1993-09-06 1995-03-20 Toda Constr Co Ltd Method of settling open caisson
JP2008231810A (en) * 2007-03-22 2008-10-02 Ps Mitsubishi Construction Co Ltd Underground structure construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110055991A (en) * 2019-05-30 2019-07-26 安徽省交通控股集团有限公司 A kind of two-wall hollow well foundation and its sinking construction method

Also Published As

Publication number Publication date
JP6585930B2 (en) 2019-10-02
TW201621121A (en) 2016-06-16
TWI583850B (en) 2017-05-21

Similar Documents

Publication Publication Date Title
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR100758113B1 (en) Cast-in-place large diameter piling method by casing rotator in underwater rock conditions
CN105133604A (en) Screw anchor pile for earth reinforcement and manufacturing method for the same
JP7381747B2 (en) Foundation pit support method in geological conditions where stones are mixed in the soil layer
JP2008057184A (en) Method of constructing underground wall by using h-shaped pc pile
JP2010222943A (en) Connection fitting for wall member and continuous underground wall construction method
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
JP6319935B2 (en) Tubing pile driving method
JP6585930B2 (en) Caisson applied method
JP2007284866A (en) Steel pipe pile for rotation press fit and press fit construction method using steel pipe pile
CN109989346B (en) Bridge large-diameter precast concrete tubular column foundation and construction method thereof
KR20040039271A (en) Shoe coffering method for new construction and repair, reinforcement of bridge open caisson foundation
JP5039510B2 (en) Repair and reinforcement structure for floating structures
CN108660941A (en) A kind of lock steel pipe splicing pile cofferdam and construction method
Spagnoli et al. Trench cutter case histories and their possible application for offshore piles as relieve drilling
JP4378277B2 (en) Vertical loading test method for existing piles below the groundwater level
KR102059051B1 (en) Method for excavating vertical shaft
JP2018096159A (en) Support column reinforcement construction method
CN108894230B (en) Method for treating boulder during sinking of pile casing
JP2017197910A (en) Construction method of earth retaining wall structure, and earth retaining wall structure
TWI645094B (en) Method for constructing underwater foundation by using caisson and
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
CN215367361U (en) Open caisson pile clamping breaking structure
JP4602919B2 (en) Removal method of underground structure
JP2018048445A (en) Demolition method

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150708

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20170516

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20180604

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20180604

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180605

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190118

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190305

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190404

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190903

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190906

R150 Certificate of patent or registration of utility model

Ref document number: 6585930

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250