JP4378277B2 - Vertical loading test method for existing piles below the groundwater level - Google Patents

Vertical loading test method for existing piles below the groundwater level Download PDF

Info

Publication number
JP4378277B2
JP4378277B2 JP2004373397A JP2004373397A JP4378277B2 JP 4378277 B2 JP4378277 B2 JP 4378277B2 JP 2004373397 A JP2004373397 A JP 2004373397A JP 2004373397 A JP2004373397 A JP 2004373397A JP 4378277 B2 JP4378277 B2 JP 4378277B2
Authority
JP
Japan
Prior art keywords
existing
pile
loading test
foundation member
vertical loading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2004373397A
Other languages
Japanese (ja)
Other versions
JP2006177097A (en
Inventor
崇史 柴田
富男 土屋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2004373397A priority Critical patent/JP4378277B2/en
Publication of JP2006177097A publication Critical patent/JP2006177097A/en
Application granted granted Critical
Publication of JP4378277B2 publication Critical patent/JP4378277B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Foundations (AREA)

Description

この発明は、建物の建て替えに際し、既存建物に使用された既存杭を、新築建物の杭として再利用できるかどうか、同杭の支持性能を確認するために実施する既存杭の鉛直載荷試験方法(以下、単に載荷試験方法という場合がある。)の技術分野に属し、更に云うと、地下水位以深における既存杭の先端支持力及び周面摩擦力を既存状態若しくは再利用した状態で測定して適正な支持性能の評価が可能な既存杭の鉛直載荷試験方法に関する。   This invention is a vertical loading test method for existing piles to confirm whether the existing pile used in the existing building can be reused as a pile in a new building, and to check the support performance of the pile. In the following technical field, it is appropriate to measure the tip support force and peripheral frictional force of existing piles deeper than the groundwater level in the existing state or in a reused state. The present invention relates to a vertical loading test method for existing piles that can be evaluated for proper support performance.

従来から、建物の建て替えに際し、既存建物に使用された既存杭を新築建物の杭として再利用して、工期の短縮やコストの削減、環境負荷低減等が図られている。この際、既存杭に鉛直載荷試験を実施し、同既存杭の先端支持力、周面摩擦力等の支持性能及び総合的な健全性を確認して、利用価値のある既存杭を再利用するか否かを評価している。既存杭の鉛直載荷試験方法としては、例えば以下のような技術が公知である。   Conventionally, when rebuilding a building, the existing pile used in the existing building is reused as a pile of a new building to shorten the construction period, reduce the cost, reduce the environmental load, and the like. At this time, a vertical loading test is carried out on the existing pile, and the existing pile with useful value is reused by confirming the support performance and comprehensive soundness of the existing pile such as tip support force and peripheral friction force. Evaluate whether or not. For example, the following techniques are known as vertical loading test methods for existing piles.

特許文献1の「既設杭を利用した建物の構築方法」には、既存建物における所定の既存杭(既設杭)の頭部を所定の高さで切断して基礎スラブと縁切りし、該縁切りした基礎スラブと既存杭の間にジャッキを設置し、前記基礎スラブに反力をとって既存杭の鉛直載荷試験を実施する技術が開示されている。   In “Building Building Method Using Existing Pile” of Patent Document 1, the head of a predetermined existing pile (existing pile) in an existing building is cut at a predetermined height to be cut off from the foundation slab, and the edge cut. A technique is disclosed in which a jack is installed between a foundation slab and an existing pile, and a vertical load test is performed on the existing pile by taking a reaction force on the foundation slab.

特許文献2の「既存の場所打ちコンクリート杭の利用方法」には、既存建物を解体し既存杭の頭部まで地盤を掘削した後に、前記既存杭の長さ方向の貫通孔を穿設し、更に杭下の地盤まで削孔する。前記貫通孔に除去式アンカーを挿入して杭下の地盤中に固定し、前記アンカー筋を緊張して既存杭の鉛直載荷試験を実施する技術が開示されている。
特開平11−264247号公報 特許第2851537号公報
In the “utilization method of existing cast-in-place concrete pile” of Patent Document 2, after dismantling the existing building and excavating the ground to the head of the existing pile, a through-hole in the length direction of the existing pile is drilled, Drill holes to the ground below the pile. A technique is disclosed in which a removable anchor is inserted into the through-hole and fixed in the ground under the pile, and the anchor bar is tensioned to perform a vertical loading test of the existing pile.
Japanese Patent Laid-Open No. 11-264247 Japanese Patent No. 2851537

しかし、特許文献1及び特許文献2の既存杭の鉛直載荷試験には、以下のような問題点がある。即ち、これらの発明は載荷位置が地下水位以上で実施されるものであり、地下水位以深のレベルである場合についての対策については何ら記載されていない。地下水位以深の場合には載荷装置の組み立て時、また載荷試験最中に湧水を水中ポンプ等により揚水する作業を連続的に行う必要がある。したがって、非常に面倒で手間が掛かるしコストが嵩む。のみならず、既存杭の周辺に湧水の流れが発生してしまうので既存杭の周面摩擦力や先端支持力を実際より小さく測定してしまい支持性能を適正に評価できない。また、特許文献2については、既存杭の頭部まで地盤を掘削するため試験装置が地下水に浸かってしまうことになり機器等を故障させてしまう虞がある。   However, the vertical loading test of the existing piles of Patent Document 1 and Patent Document 2 has the following problems. That is, these inventions are carried out at the loading level above the groundwater level, and no measures are described regarding the case where the loading position is deeper than the groundwater level. In the case of deeper than the groundwater level, it is necessary to continuously perform the work of pumping up the spring water using a submersible pump or the like during assembly of the loading device and during the loading test. Therefore, it is very troublesome and time-consuming, and costs increase. Moreover, since the flow of spring water is generated around the existing pile, the peripheral friction force and the tip support force of the existing pile are measured smaller than the actual one, and the support performance cannot be evaluated appropriately. Moreover, about patent document 2, in order to excavate the ground to the head of the existing pile, there exists a possibility that a test apparatus will be immersed in groundwater, and an apparatus etc. may be damaged.

前記湧水の流れを防止するため、既存山留め壁、連壁等を利用する方法や、載荷試験に先行して止水山留め壁を構築し、ディープウェルやウェルポイントを用いて揚水を行い載荷試験実施場所でのドライワークを確保する方法が考えられる。しかし、これらの方法は非常に手間と時間が掛かるだけでなく、杭周面の地盤を締め固めた後に載荷試験をするので、既存杭の周面摩擦力を実際より大きく測定してしまい支持性能を適正に評価できない。   In order to prevent the flow of the spring water, a method using existing retaining walls, connecting walls, etc., or constructing a retaining water retaining wall prior to the loading test, pumping water using deep wells and well points, and loading test A method to secure dry work at the place of implementation is conceivable. However, these methods are not only very time-consuming and time-consuming, but also the load test is performed after the ground surface of the pile is compacted. Cannot be evaluated properly.

上記特許文献1及び2は、既存建物を解体した後、又は既存杭の頭部まで地盤を掘削した後に鉛直載荷試験を行う手順である。そのため、既存杭の先端支持力、周面摩擦力等の支持性能及び総合的な健全性の把握には時間が掛かり設計工程において工期が長期化される問題がある。更に地下水位以深である場合には揚水井戸の掘削や揚水作業が付加されるためその問題は深刻となる。   Patent Documents 1 and 2 are procedures for performing a vertical loading test after dismantling an existing building or excavating the ground to the head of an existing pile. For this reason, it takes time to grasp the support performance such as the tip support force and the peripheral friction force of the existing pile and the overall soundness, and there is a problem that the construction period is prolonged in the design process. In addition, when the water level is deeper than the groundwater level, the problem becomes serious because excavation of the pumping well and pumping work are added.

本発明の目的は、既存杭の載荷位置が地下水位以深において、既存杭周辺に湧水の流れを引き起すことを防止して既存杭の先端支持力及び周面摩擦力を既存状態若しくは再利用した状態で測定でき、安価で簡易な構造で実施可能であり、載荷試験を先行して行ない工期の短縮を図れる地下水位以深の既存杭の鉛直載荷試験方法を提供することにある。   The object of the present invention is to prevent the flow of spring water around the existing pile when the loading position of the existing pile is deeper than the groundwater level, and to use the existing pile tip support force and peripheral frictional force in the existing state or reuse. It is to provide a vertical loading test method for existing piles deeper than the groundwater level, which can be measured in a reduced state, can be implemented with an inexpensive and simple structure, and can shorten the construction period by conducting the loading test in advance.

上記従来技術の課題を解決するための手段として、請求項1に記載した発明に係る地下水位以深における既存杭の鉛直載荷試験方法は、
建物の建て替えに際し、既存建物に使用された既存杭を再利用するための鉛直載荷試験方法であって、
試験対象の既存杭の杭頭をのみ込んだ基礎部材における杭頭の外周位置又は杭頭の外周位置から離れた近傍位置で杭頭と基礎部材との縁切りを、基礎部材の下端部を一部残して行う工程と、
前記縁切りにより形成した凹部又は切り口を可撓性又は伸び縮み性と止水性を備えたジョイント部材で水密的に遮蔽して止水処理する工程と、
前記既存杭の上端部へ、載荷試験装置を組み立て、既存杭に鉛直荷重を加え、先ず基礎部材の前記残存部を破断させて既存杭の支持性能を測定することを特徴とする。
As a means for solving the above-mentioned problems of the prior art, a vertical loading test method for existing piles at a depth below the groundwater level according to the invention described in claim 1 is:
A vertical loading test method for reusing existing piles used in an existing building when rebuilding a building,
The edge of the pile head and the foundation member at the outer peripheral position of the pile head or in the vicinity away from the outer circumference of the pile head in the foundation member including the pile head of the existing pile to be tested, and part of the lower end of the foundation member The remaining steps,
A step of water-stopping the recess or cut formed by the edge cutting by watertightly sealing with a joint member having flexibility or stretchability and water-stopping, and
A loading test device is assembled to the upper end portion of the existing pile, a vertical load is applied to the existing pile, and the remaining portion of the foundation member is first broken to measure the support performance of the existing pile.

請求項2記載の発明は、請求項1に記載した地下水位以深における既存杭の鉛直載荷試験方法において、
基礎部材の下端部を一部残して縁切りした凹部又は切り口へ、地下水の噴出に抵抗する補助材を充填することを特徴とする。
Invention of Claim 2 is the vertical loading test method of the existing pile in the depth below the groundwater level described in Claim 1,
An auxiliary material that resists the ejection of groundwater is filled into a recessed portion or a cut end that is partially cut off with the lower end portion of the foundation member partially left.

請求項3記載の発明は、請求項1又は2に記載した地下水位以深における既存杭の鉛直載荷試験方法において、
基礎部材の下端部を一部残して縁切りする工程は、基礎部材の下側に位置する捨てコンクリート部分の全部又は一部の厚さを残して縁切りすることを含むことを特徴とする。
Invention of Claim 3 is the vertical loading test method of the existing pile in the depth below the groundwater level described in Claim 1 or 2,
The step of edging leaving a part of the lower end of the foundation member includes edging leaving the thickness of all or part of the discarded concrete portion located below the foundation member.

本発明は、地下水位以深の既存杭の鉛直載荷試験方法として、基礎部材の下端部を一部残して縁切りした凹部又は切り口に可撓性又は伸び縮み性と止水性を備えたジョイントを設置する構成としたので、以下のような効果を奏する。
(1)既存杭2周辺に湧水の流れが発生することを防止して先端支持力及び周面摩擦力の低下の因子を排除できる。しかるに、既存状態若しくは再利用した状態での既存杭2aの先端支持力及び周面摩擦力を測定して支持性能を適正に評価し再利用するか否かの正確な判断ができる。
(2)載荷位置に水が及ぶことがないので、ジャッキ90等の載荷試験装置9が水に浸かるなどして機器の故障を招くという問題を低減することができる。
(3)既存建物1の解体作業を待つことなく、また揚水作業をすることなく載荷試験を先行して行えるため設計工程の確保もっては全体の工期の短縮を図ることができる。
As a vertical loading test method for existing piles deeper than the groundwater level, the present invention installs a joint having flexibility or expansion / contraction and water-stopping in a recess or cut edge that leaves a part of the lower end of the foundation member. Since it is configured, the following effects are obtained.
(1) It is possible to prevent the flow of spring water from occurring around the existing pile 2 and to eliminate the factors of lowering the tip support force and the peripheral friction force. However, it is possible to accurately determine whether or not to reuse by measuring the tip support force and peripheral friction force of the existing pile 2a in the existing state or in a reused state, and appropriately evaluating the support performance.
(2) Since water does not reach the loading position, it is possible to reduce the problem that the loading test apparatus 9 such as the jack 90 immerses in water, resulting in equipment failure.
(3) Since the loading test can be performed in advance without waiting for the dismantling work of the existing building 1 and without performing the pumping work, the entire construction period can be shortened by ensuring the design process.

本発明は、建物の建て替えに際し、既存建物1に使用された既存杭2を再利用するための鉛直載荷試験方法である。
試験対象の既存杭2aの杭頭をのみ込んだ基礎部材3における杭頭の外周位置又は杭頭の外周位置から離れた近傍位置で杭頭と基礎部材3との縁切りを、基礎部材3の下端部を一部残して行う。
前記縁切りにより形成した凹部4を可撓性又は伸び縮み性と止水性を備えたジョイント部材5で水密的に遮蔽して止水処理する。
前記既存杭2aの上端部へ、載荷試験装置9を組み立て、既存杭2aに鉛直荷重を加え、先ず基礎部材3の前記残存部Sを破断させて既存杭2aの支持性能を測定する。
The present invention is a vertical loading test method for reusing an existing pile 2 used in an existing building 1 when rebuilding a building.
The edge of the pile head and the foundation member 3 is cut off at the outer peripheral position of the pile head in the foundation member 3 including the pile head of the existing pile 2a to be tested or in the vicinity of the outer circumference of the pile head. This is done with some parts left.
The concave portion 4 formed by the edge cutting is watertightly shielded by a joint member 5 having flexibility or expansion / contraction property and water-stopping property, and water-stopping treatment is performed.
The loading test apparatus 9 is assembled to the upper end portion of the existing pile 2a, a vertical load is applied to the existing pile 2a, and the remaining portion S of the foundation member 3 is first broken to measure the support performance of the existing pile 2a.

以下、本発明を図面に基づいて説明する。本発明の載荷試験方法は、建物の建て替えに際し、既存建物1に使用された地下水位以深の既存杭2を再利用できるかを、試験対象の既存杭2aの支持性能を確認することにより実施される。   Hereinafter, the present invention will be described with reference to the drawings. The loading test method of the present invention is carried out by confirming the supporting performance of the existing pile 2a to be tested to determine whether the existing pile 2 deeper than the groundwater level used in the existing building 1 can be reused when rebuilding the building. The

先ず、図1に示すように、試験対象の地下水位以深の既存杭2aの杭頭をのみ込んだ基礎部材3における杭頭の外周位置から離れた近傍位置で杭頭と基礎部材3の縁切りを行う。図示例の基礎部材3は、マットスラブ3a又は耐圧板3aとした構成を示した。
具体的には、複数本の既存杭2…の中から試験対象の試験杭2a(以下、単に既存杭2aと云う)を選択し、同杭頭の外周位置から離れた近傍位置で例えば2重管式コアリングを行い縁切りする。この際、前記基礎部材3の下端部を一部を残して残存部Sを形成するようにコアリングを行う。これは基礎部材3(若しくは残存部S)の直下位置に存在する地下水が湧き出る問題を防止するためである。
縁切り箇所はこの限りではなく、杭頭の外周位置に沿う位置としても良い。また、前記縁切りの方法はコアリングに限らず、コンクリートカッター又ははつり機械で切り込みを入れて行う方法でも良い。
First, as shown in FIG. 1, the edge of the pile head and the foundation member 3 is cut at a position away from the outer peripheral position of the pile head in the foundation member 3 including the pile head of the existing pile 2 a deeper than the groundwater level to be tested. Do. The base member 3 in the illustrated example is configured as a mat slab 3a or a pressure plate 3a.
Specifically, a test pile 2a to be tested (hereinafter simply referred to as an existing pile 2a) is selected from a plurality of existing piles 2... Perform pipe coring and trim. At this time, coring is performed so that the remaining portion S is formed leaving a part of the lower end portion of the foundation member 3. This is to prevent the problem that the groundwater existing immediately below the foundation member 3 (or the remaining portion S) springs up.
The edge cutting part is not limited to this, and may be a position along the outer peripheral position of the pile head. Further, the edge cutting method is not limited to coring, and may be performed by cutting with a concrete cutter or a lifting machine.

図2に、前記基礎部材3が基礎梁3b又はフーチング3bを有する構成の場合を示した。この場合、杭頭の外周位置に沿って縁切りすることは施工上行わなず、杭頭の外周位置から離れた近傍位置から縁切りを行う。その縁切り箇所は、図示例の如くフーチング3bの近傍位置とされるが、同フーチング3bの外周面に沿う位置としても良い。
したがって、本発明は基礎部材3の構成に影響されることなく実施することができる。
FIG. 2 shows a case where the foundation member 3 has a foundation beam 3b or a footing 3b. In this case, the edge cutting along the outer peripheral position of the pile head is not performed in construction, but the edge cutting is performed from the vicinity position away from the outer peripheral position of the pile head. The edge cut portion is a position in the vicinity of the footing 3b as in the illustrated example, but may be a position along the outer peripheral surface of the footing 3b.
Therefore, the present invention can be implemented without being influenced by the configuration of the base member 3.

また、上記基礎部材3(マットスラブ3aとフーチング3bの両方の場合を含む)の下端部を一部残して縁切りする他の手段として、図3Aに示すように基礎部材3の下側に位置する捨てコンクリート3cの上面まで縁切りして、同捨てコンクリート3cの全部の厚さを残すこと。また、図3Bに示すように前記捨てコンクリート3cに潜り込みその一部(下端部)の厚さを残すように縁切りすることもなされる(請求項3記載の発明)。図示例では、捨てコンクリート3cを有する場合を示したが、勿論、捨てコンクリート3cを有さない基礎部材においても、同基礎部材の下端部の一部を残して縁切りを行うことがなされる。   Moreover, as shown in FIG. 3A, the base member 3 is positioned on the lower side of the base member 3 as a means for cutting out the edge while leaving a part of the lower end of the base member 3 (including both the mat slab 3a and the footing 3b). Cutting the top of the discarded concrete 3c to leave the entire thickness of the discarded concrete 3c. Further, as shown in FIG. 3B, the material is cut into the discarded concrete 3c so as to leave a part (lower end) of the thickness (the invention according to claim 3). In the illustrated example, the case where the discarded concrete 3c is provided is shown. Of course, even in a foundation member that does not have the discarded concrete 3c, edge cutting is performed while leaving a part of the lower end portion of the foundation member.

次に、図4に示すように、前記縁切りにより形成した凹部4(又はコンクリートカッターにより形成された切り口)を水密的に遮蔽する可撓性又は伸び縮み性と止水性を備えたジョイント部材5を設置して止水処理を行う。
図示したジョイント部材5は、例えばクロロプレンゴムや硬いゴム材又は金属製の成形板とされ、断面形状がU字型に突出した中央部5aとその両端の水平部5bとから構成されている。前記ジョイント部材5は凹部4を跨ぎ且つ前記中央部5aが凹部4の上方に位置する配置で、水平部5b、5bが基礎部材3(3a)、3(3a)とボルト6により固定されて凹部4を水密的に遮蔽している。
Next, as shown in FIG. 4, the joint member 5 having flexibility or expansion / contraction property and water-stopping property that watertightly shields the recess 4 (or the cut formed by the concrete cutter) formed by the edge cutting. Install and stop water treatment.
The illustrated joint member 5 is, for example, a molded plate made of chloroprene rubber, hard rubber material, or metal, and includes a central portion 5a having a U-shaped cross section and horizontal portions 5b at both ends thereof. The joint member 5 is arranged so as to straddle the concave portion 4 and the central portion 5a is positioned above the concave portion 4, and the horizontal portions 5b and 5b are fixed by the base members 3 (3a) and 3 (3a) and the bolts 6 to be concave portions. 4 is watertightly shielded.

前記中央部5aがU字型に突出されているのは、載荷試験時に荷重段階に応じて可撓性又は伸び縮み性が発揮されて沈下に追従するためである。勿論、形状はこの限りではなく図5に示すような断面形状がM字型のもの又は断面形状が一定していない波状のものをとしてもよい。
止水性を更に向上させるために、図4に示したように、前記縁切りした凹部4へ、地下水の噴出に抵抗する補助材7を充填することが望ましい(請求項2記載の発明)。補助材7としては、例えばウエス(布きれ)、土嚢、水膨張系のゴム材、ウレタン等が好適に使用される。また、ジョイント部材5の水平部5bの両壁面にシーリング処理8を施すことも好適に行われる。
The reason why the central portion 5a protrudes in a U-shape is to exhibit flexibility or expansion / contraction according to the load stage during the loading test and follow the settlement. Of course, the shape is not limited to this, and the cross-sectional shape shown in FIG. 5 may be M-shaped, or the cross-sectional shape may be wavy.
In order to further improve the water stoppage, as shown in FIG. 4, it is desirable to fill the edge-cut concave portion 4 with an auxiliary material 7 that resists ejection of groundwater (the invention according to claim 2). As the auxiliary material 7, for example, a waste cloth, a sandbag, a water expansion rubber material, urethane, or the like is preferably used. Moreover, it is also suitably performed to perform the sealing process 8 on both wall surfaces of the horizontal portion 5b of the joint member 5.

前記基礎部材3が基礎梁3b又はフーチング3bを有する構成において、前記凹部4が同フーチング3bの外周面に沿って形成さられている場合、前記ジョイント部材5の水平部5b、5bは、図6に示すように基礎部材3とフーチング3bの外壁面とにボルト接合して設置される。   In the configuration in which the foundation member 3 includes the foundation beam 3b or the footing 3b, when the concave portion 4 is formed along the outer peripheral surface of the footing 3b, the horizontal portions 5b and 5b of the joint member 5 are as shown in FIG. As shown in FIG. 4, the base member 3 and the outer wall surface of the footing 3b are bolted and installed.

最後に、載荷試験装置9を組み立て、既存杭2aに鉛直荷重を加える。具体的には例えば図1及び図2に示すように既存杭2aの上端部へ、近傍の既存建物躯体1aに反力をとるジャッキ90を含む載荷試験装置9を組み立て、前記ジャッキ90により試験荷重を加え、基礎部材3の前記残存部Sを破断させて支持性能を測定する。載荷試験装置9としては、前記ジャッキ90による方法ではなく、反力杭及び載荷桁を利用する方法又は建物荷重を利用した方法若しくは他の急速載荷試験方法等のいずれの方法でも実施することができる。因みに上記の鉛直載荷試験方法は、既存建物1の解体作業を待つことなく、また地下水の揚水作業をすることなく、最も早い段階で先行して行うことができる。   Finally, the loading test apparatus 9 is assembled and a vertical load is applied to the existing pile 2a. Specifically, for example, as shown in FIG. 1 and FIG. 2, a loading test apparatus 9 including a jack 90 that takes a reaction force on the adjacent existing building frame 1 a is assembled at the upper end of the existing pile 2 a, and the test load is applied by the jack 90. Then, the remaining portion S of the base member 3 is broken and the support performance is measured. The loading test apparatus 9 can be implemented by any method such as a method using a reaction force pile and a loading girder, a method using a building load, or another rapid loading test method, not the method using the jack 90. . Incidentally, the above-described vertical loading test method can be performed at the earliest stage without waiting for the dismantling work of the existing building 1 and without pumping the groundwater.

残存部Sの破断時に、地下水を誘引するが前記ジョイント部材5が凹部4を水密的に遮蔽して止水性を十分に発揮して、地下水を止めて載荷面に水が及ばないし、既存杭の周面に湧水の流れが発生することも防止している。この状況は、既存杭を再利用した状況(既存状態)と同様であると見なすことができる。   When the remaining portion S breaks, the ground water is attracted, but the joint member 5 shields the concave portion 4 in a water-tight manner and sufficiently exhibits a water-stopping property so that the ground water is stopped and water does not reach the loading surface. It also prevents the flow of spring water from occurring on the periphery. This situation can be regarded as the same as the situation where the existing piles are reused (existing state).

したがって、既存杭の先端支持力、周面摩擦力を既存状態若しくは再利用した状態で測定し再利用するか否かの正確な評価ができるし、ジャッキ等の載荷装置が水に浸かるなどして機器の故障を招くという問題を低減することができる。更には、既存建物1の解体作業を待つことなく、更には揚水作業を行う必要がないため、載荷試験を先行して最も早い段階で行うことができ、設計工程の確保もっては全体の工期の短縮を図ることができるのである。   Therefore, it is possible to accurately evaluate whether or not the tip support force and peripheral friction force of the existing pile are measured and reused in the existing state or reused, and the loading device such as a jack is immersed in water. It is possible to reduce the problem of causing equipment failure. Furthermore, since it is not necessary to perform the pumping work without waiting for the dismantling work of the existing building 1, the loading test can be performed at the earliest stage, and the entire construction period can be ensured by ensuring the design process. It can be shortened.

その後、既存建物1を解体し、支持性能を確認した既存杭2aを、新築建物の杭として再利用する。この際、新規建物荷重に対し、既存杭の支持性が小さい場合には、増し杭を打設し合算することにより支持性能を確保しても良い。   Thereafter, the existing building 1 is dismantled and the existing pile 2a whose supporting performance is confirmed is reused as a pile of a new building. At this time, when the supportability of the existing pile is small with respect to the new building load, the support performance may be ensured by driving and adding the additional piles.

図7に前記ジョイント部材5の他の実施例を示した。即ち、縁切りにより形成した凹部4の直上位置から更に同凹部4より口径の広い埋め戻し孔10をコアリングによりその上層に設ける。その後、ジョイントユニット50を前記埋め戻し孔10に嵌入する。前記ジョイントユニット50は、埋め戻し孔10の形状と略同形同大の下地板50aと、その底部に設けられる上記ジョイント部材5とで構成とされている。このジョイントユニット50は載荷試験後に解体することなく前記埋め戻し孔10にコンクリート等を流し込むという簡易な方法で後処理を行える。   FIG. 7 shows another embodiment of the joint member 5. That is, a back-filling hole 10 having a diameter larger than that of the concave portion 4 is provided in an upper layer by coring from a position immediately above the concave portion 4 formed by edge cutting. Thereafter, the joint unit 50 is fitted into the backfill hole 10. The joint unit 50 is composed of a base plate 50a having approximately the same shape and size as the shape of the backfill hole 10 and the joint member 5 provided at the bottom thereof. This joint unit 50 can be post-processed by a simple method in which concrete or the like is poured into the backfill hole 10 without being disassembled after the loading test.

なお、以上に本発明の実施例を説明したが、本発明はこうした実施例に何ら限定されるものではなく、本発明の要旨を逸脱しない範囲において、種々の形態で実施し得る。   In addition, although the Example of this invention was described above, this invention is not limited to such an Example at all, In the range which does not deviate from the summary of this invention, it can implement with a various form.

基礎部材が耐圧板又はマットスラブの場合の本発明の地下水以深における既存杭の鉛直載荷試験方法を概念的に示した立面図である。It is the elevation which showed notionally the vertical loading test method of the existing pile in the deep underground water of this invention in case a foundation member is a pressure plate or a mat slab. 基礎部材が基礎梁又はフーチングを有する場合の本発明の地下水以深における既存杭の鉛直載荷試験方法を概念的に示した立面図である。It is the elevation which showed notionally the vertical loading test method of the existing pile in the depth below the ground water of this invention in case a foundation member has a foundation beam or a footing. A、Bは基礎部材の下端部を一部残して縁切りする他の実施例を示した図である。A and B are the figures which showed the other Example which cuts out a margin, leaving a part of lower end part of a base member. 図1にジョイント部材を設置した一例を示した図である。It is the figure which showed an example which installed the joint member in FIG. ジョイント部材の他の実施形態を示した図である。It is the figure which showed other embodiment of the joint member. 図2にジョイント部材を設置した一例を示した図である。It is the figure which showed an example which installed the joint member in FIG. 止水ジョイントユニットを設置した一実地例を示した図である。It is the figure which showed one actual example which installed the water stop joint unit.

符号の説明Explanation of symbols

1 既存建物
2 既存杭
2a 試験対象の既存杭(試験杭)
3 基礎部材
3a 耐圧板又はマットスラブ
3b フーチング
4 凹部
5 ジョイント部材
50 ジョイントユニット
6 ボルト
7 補助材
9 載荷試験装置
90 ジャッキ
1 Existing building 2 Existing pile 2a Existing pile to be tested (test pile)
DESCRIPTION OF SYMBOLS 3 Base member 3a Pressure-resistant board or mat slab 3b Footing 4 Recessed part 5 Joint member 50 Joint unit 6 Bolt 7 Auxiliary material 9 Loading test apparatus 90 Jack

Claims (3)

建物の建て替えに際し、既存建物に使用された既存杭を再利用するための鉛直載荷試験方法であって、
試験対象の既存杭の杭頭をのみ込んだ基礎部材における杭頭の外周位置又は杭頭の外周位置から離れた近傍位置で杭頭と基礎部材との縁切りを、基礎部材の下端部を一部残して行う工程と、
前記縁切りにより形成した凹部又は切り口を可撓性又は伸び縮み性と止水性を備えたジョイント部材で水密的に遮蔽して止水処理する工程と、
前記既存杭の上端部へ、載荷試験装置を組み立て、既存杭に鉛直荷重を加え、先ず基礎部材の前記残存部を破断させて既存杭の支持性能を測定することを特徴とする、地下水位以深における既存杭の鉛直載荷試験方法。
A vertical loading test method for reusing existing piles used in an existing building when rebuilding a building,
The edge of the pile head and the foundation member at the outer peripheral position of the pile head or in the vicinity away from the outer circumference of the pile head in the foundation member including the pile head of the existing pile to be tested, and part of the lower end of the foundation member The remaining steps,
A step of water-stopping the recess or cut formed by the edge cutting by watertightly sealing with a joint member having flexibility or stretchability and water-stopping, and
Assembling a loading test device on the upper end of the existing pile, applying a vertical load to the existing pile, and first measuring the support performance of the existing pile by breaking the remaining portion of the foundation member, Test method for vertical loading of existing piles.
基礎部材の下端部を一部残して縁切りした凹部又は切り口へ、地下水の噴出に抵抗する補助材を充填することを特徴とする、請求項1に記載した地下水位以深における既存杭の鉛直載荷試験方法。   The vertical loading test of an existing pile at a depth below the groundwater level according to claim 1, wherein an auxiliary material that resists the ejection of groundwater is filled into a recessed portion or a cut end that leaves a part of the lower end portion of the foundation member. Method. 基礎部材の下端部を一部残して縁切りする工程は、基礎部材の下側に位置する捨てコンクリート部分の全部又は一部の厚さを残して縁切りすることを含むことを特徴とする、請求項1又は2に記載した地下水位以深における既存杭の鉛直載荷試験方法。   The step of cutting out the edge of the foundation member by leaving a part thereof includes cutting out the edge of the part of the discarded concrete part located below the foundation member by leaving the thickness of the part. A vertical loading test method for existing piles at a depth below the groundwater level described in 1 or 2.
JP2004373397A 2004-12-24 2004-12-24 Vertical loading test method for existing piles below the groundwater level Expired - Fee Related JP4378277B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004373397A JP4378277B2 (en) 2004-12-24 2004-12-24 Vertical loading test method for existing piles below the groundwater level

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004373397A JP4378277B2 (en) 2004-12-24 2004-12-24 Vertical loading test method for existing piles below the groundwater level

Publications (2)

Publication Number Publication Date
JP2006177097A JP2006177097A (en) 2006-07-06
JP4378277B2 true JP4378277B2 (en) 2009-12-02

Family

ID=36731452

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004373397A Expired - Fee Related JP4378277B2 (en) 2004-12-24 2004-12-24 Vertical loading test method for existing piles below the groundwater level

Country Status (1)

Country Link
JP (1) JP4378277B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296646A (en) * 2011-06-08 2011-12-28 绍兴文理学院 Test pile loading method and device of inflatable multistage water bag

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7661799B2 (en) 2006-06-27 2010-02-16 Brother Kogyo Kabushiki Kaisha Recording apparatus and method for producing the same
JP6133621B2 (en) * 2013-02-25 2017-05-24 株式会社竹中工務店 Yamadome wall
CN105821913B (en) * 2016-04-06 2019-03-05 江苏苏州地质工程勘察院 Foundation model test counter-force load bringing device and test method
CN106193138B (en) * 2016-08-29 2018-10-09 广东舍卫工程技术咨询有限公司 Dynamometry pile cover
CN106939621A (en) * 2017-03-08 2017-07-11 浙江大学 Detachable water tank loading test pile apparatus and pile testing method
CN112854176A (en) * 2021-03-22 2021-05-28 广州诚安路桥检测有限公司 Assembled composite foundation load test bearing plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296646A (en) * 2011-06-08 2011-12-28 绍兴文理学院 Test pile loading method and device of inflatable multistage water bag

Also Published As

Publication number Publication date
JP2006177097A (en) 2006-07-06

Similar Documents

Publication Publication Date Title
KR101652967B1 (en) Soil retaining wall for sheathing work
KR100807810B1 (en) Structural impression construction method by foundation reinforcement
KR101018282B1 (en) How to install the structure for underground tunnel formation
KR20120130589A (en) method for constructing pile using reaction force frame reinforced upper part of pillar in constructed building
JP4502797B2 (en) Vertical loading test method for existing piles
JP3908752B2 (en) Strain and settlement measurement method for pile vertical loading test
JP5378066B2 (en) Mountain fastening method
JP2006177097A (en) Vertical loading test method for existing piles below the groundwater level
KR100975988B1 (en) Construction method of underwater structure
KR20040039271A (en) Sugar barrier construction for new foundation of steel well and reinforcement of foundation.
JP2016023540A (en) Environmentally-considerate pile head processing method
JP5367452B2 (en) Underground wall construction method and underground wall body
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
JP4488889B2 (en) Vertical loading test method for existing piles below the groundwater level
JP6585930B2 (en) Caisson applied method
JPH09184144A (en) Construction method for base isolation pit for existing building
JP3736555B2 (en) Method for measuring ground contact pressure between foundation and supporting ground to use foundation of existing structure
JP2977805B1 (en) Straightening method and straightening device for buildings with uneven settlement
JP2006207152A (en) Open caisson press-fitting method
JP2017197910A (en) Method for constructing retaining wall structure and retaining wall structure
JP5116827B2 (en) Press-in caisson and press-in caisson method using this press-in caisson
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP4837618B2 (en) Caisson press-in method
KR101347763B1 (en) A structure and method of underwater construction repair
KR102268882B1 (en) Three-way thumb pile reinforcement type self-supporting soil barrier construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070927

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090820

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090901

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090914

R150 Certificate of patent or registration of utility model

Ref document number: 4378277

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120918

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130918

Year of fee payment: 4

LAPS Cancellation because of no payment of annual fees