Prior art keywords
hot water
mat
snow melting
rubber
header
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2014183901A
Other languages
Japanese (ja)
Other versions
JP6357991B2 (en
Inventor
新 松田
Arata Matsuda
新 松田
桂 高橋
Katsura Takahashi
桂 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Proterial Ltd
Original Assignee
Hitachi Metals Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Metals Ltd filed Critical Hitachi Metals Ltd
Priority to JP2014183901A priority Critical patent/JP6357991B2/en
Publication of JP2016056589A publication Critical patent/JP2016056589A/en
Application granted granted Critical
Publication of JP6357991B2 publication Critical patent/JP6357991B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Abstract

PROBLEM TO BE SOLVED: To provide a new technology capable of restraining damage of a plumbing header in a snow melting mat for a track of using hot water.SOLUTION: A snow melting mat for a track comprises a hot water mat body arranged in the rail extension direction, a rubber header extendedly arranged in the hot water mat width direction in an end part of the hot ester mat body, oppositely superposing an upper side member and a lower side member respectively formed in a groove and constituting a plumbing pipeline and an installation metal fitting for installing the rubber header on the track, and the installation metal fitting comprises a root part of extending in the hot water mat width direction and an installation part installed on the track by projecting to the hot water mat opposite side to the pipeline from the root part, and mutual edge parts arranged on the hot water mat opposite side to the pipeline of the upper side member and the lower side member, are adhered by sandwiching the root part without covering the rubber header from the upper side, so that a side surface of the pipeline is closed, and the installation metal fitting is fixed to the rubber header.SELECTED DRAWING: Figure 2

Description

本発明は、軌道用融雪マットに関する。   The present invention relates to a track snow melting mat.

列車持ち込み雪により分岐器が切替不能になることを防止するために、軌道に敷設される融雪マットが開発されている(例えば特許文献1参照)。   In order to prevent the branching device from becoming unswitchable due to snow brought in by a train, a snow melting mat laid on a track has been developed (see, for example, Patent Document 1).

温水を用いた融雪マットでは、温水マット本体の端部に、温水の給排水用のヘッダーが設けられる。列車持ち込み雪の塊がヘッダーに接触することで、ヘッダーが損傷し、漏水が生じる可能性がある。   In a snow melting mat using hot water, a header for supplying and discharging hot water is provided at the end of the hot water mat body. If a snow mass brought into the train contacts the header, the header may be damaged and water leakage may occur.

特開平10−176302号公報JP-A-10-176302

本発明の一目的は、温水を用いた軌道用融雪マットにおいて、給排水用ヘッダーの損傷等を抑制することができる新規な技術を提供することである。   An object of the present invention is to provide a novel technique capable of suppressing damage to a water supply / drainage header in a snow melting mat for tracks using hot water.

本発明の一観点によれば、
レールの延在方向に沿って配置される温水マット本体と、
前記温水マット本体の端部に、前記温水マット本体の幅方向に延在して配置され、それぞれ溝の形成された上側部材と下側部材とが対向するように重ね合わされることで、外部から前記温水マット本体へ温水を給水するための管路、または、外部へ前記温水マット本体から温水を排水するための管路を構成しているゴムヘッダーと、
前記ゴムヘッダーを軌道に取り付けるための取り付け金具と
を有し、
前記取り付け金具は、前記温水マット本体の幅方向に延在する根元部と、前記根元部から前記管路に対し前記温水マット本体と反対側に突出し、前記軌道に取り付けられる取り付け部とを有し、前記ゴムヘッダーを上側から覆わないように配置されており、
前記上側部材および前記下側部材の、前記管路に対し前記温水マット本体と反対側に配置された縁部同士が、前記根元部を挟んで接着されていることにより、前記管路の側面が閉じるとともに、前記取り付け金具が前記ゴムヘッダーに固定されている、
軌道用融雪マット
が提供される。
According to one aspect of the present invention,
A hot water mat body arranged along the extending direction of the rail;
At the end of the hot water mat body, it is arranged extending in the width direction of the hot water mat body, and the upper member and the lower member in which grooves are respectively formed are overlapped so as to face each other, so that from the outside A pipe for supplying hot water to the hot water mat body, or a rubber header constituting a pipe for draining hot water from the hot water mat body to the outside;
A mounting bracket for mounting the rubber header on the track,
The mounting bracket has a root portion extending in the width direction of the hot water mat body, and a mounting portion that protrudes from the root portion to the opposite side of the hot water mat body with respect to the pipe line and is attached to the track. , Arranged so as not to cover the rubber header from above,
Edges of the upper member and the lower member, which are arranged on the opposite side of the hot water mat main body with respect to the pipe line, are bonded with the root part interposed therebetween, whereby the side surface of the pipe line is With the closing, the mounting bracket is fixed to the rubber header,
An orbital snow melting mat is provided.

取り付け金具に覆われずに露出したゴムヘッダーは、列車持ち込み雪の塊と接触しても、弾性的に変形して元の形状に戻る。また、ゴムヘッダーの上側部材および下側部材の温水マット本体と反対側の縁部同士が接着されていることで、管路が強固に形成されている。これにより、管路の損傷が抑制され、温水の漏れが抑制されている。さらに、取り付け金具の根元部が、ゴムヘッダーの上側部材および下側部材の温水マット本体と反対側の縁部に挟まれ覆われていることにより、軌道短絡が抑制されている。   Even if the rubber header exposed without being covered by the mounting bracket comes into contact with the snow lump brought into the train, it is elastically deformed and returns to its original shape. Moreover, the pipe line is firmly formed because the edge parts on the opposite side to the hot-water mat main body of the upper side member and lower side member of a rubber header are adhere | attached. Thereby, the damage of a pipe line is suppressed and the leakage of warm water is suppressed. Furthermore, since the base part of the mounting bracket is sandwiched and covered by the edge part on the opposite side of the hot water mat body of the upper member and the lower member of the rubber header, the track short circuit is suppressed.

図1は、本発明の第1実施形態による融雪マットの敷設態様例を概略的に示す平面図である。FIG. 1 is a plan view schematically showing an example of a laying aspect of a snow melting mat according to a first embodiment of the present invention. 図2(A)および図2(B)は、それぞれ、第1実施形態の融雪マットの一端近傍を示す概略的な平面図および断面図である。FIG. 2A and FIG. 2B are a schematic plan view and a cross-sectional view showing the vicinity of one end of the snow melting mat of the first embodiment, respectively. 図3は、第2実施形態による融雪マットの一端近傍を示す概略的な断面図である。FIG. 3 is a schematic cross-sectional view showing the vicinity of one end of the snow melting mat according to the second embodiment. 図4(A)および図4(B)は、それぞれ、比較形態による融雪マットの一端近傍を示す概略的な平面図および断面図である。FIG. 4A and FIG. 4B are a schematic plan view and a cross-sectional view showing the vicinity of one end of a snow melting mat according to a comparative embodiment, respectively.

図1を参照して、本発明の第1実施形態による融雪マットの概略的な構造と敷設態様とについて説明する。図1は、第1実施形態の融雪マット100の敷設態様例を概略的に示す平面図である。融雪マット100は、鉄道車両が通る道である軌道200に敷設される軌道用融雪マットであり、より具体的には、1対のレール201の間の、まくらぎ202の上側に、レール201の延在方向に沿って敷設される。   With reference to FIG. 1, a schematic structure and laying mode of a snow melting mat according to a first embodiment of the present invention will be described. FIG. 1 is a plan view schematically showing a laying example of the snow melting mat 100 according to the first embodiment. The snow melting mat 100 is a snow melting mat for a track that is laid on a track 200 that is a path through which a railway vehicle passes. More specifically, the snow melting mat 100 is disposed above the sleeper 202 between a pair of rails 201. It is laid along the extending direction.

融雪マット100は、典型的には、分岐器の手前に敷設され、通過列車が雪を落す場所として機能する。これにより、分岐器が列車持ち込み雪により切替不能になることが防止される。   The snow melting mat 100 is typically laid before the turnout and functions as a place where the passing train drops snow. This prevents the turnout from becoming unswitchable due to train snow.

融雪マット100は、温水マット本体110と、ゴムヘッダー120と、取り付け金具130とにより構成されている。温水マット本体110は、レール201の延在方向に沿って配置される細長い形状を有し、温水マット本体110の長さ方向に流れる温水により加温され、温水マット本体110上の雪が、融かされる。   The snow melting mat 100 includes a hot water mat main body 110, a rubber header 120, and a mounting bracket 130. The hot water mat main body 110 has an elongated shape arranged along the extending direction of the rail 201 and is heated by the hot water flowing in the length direction of the hot water mat main body 110 so that the snow on the hot water mat main body 110 is melted. Is done.

ゴムヘッダー120は、温水マット本体110の両端部に設けられており、一方のゴムヘッダー120が、外部から温水マット本体110へ温水を給水するための給水管路を構成し、他方のゴムヘッダー120が、外部へ温水マット本体110から温水を排水するための排水管路を構成している。   The rubber header 120 is provided at both ends of the hot water mat body 110, and one rubber header 120 constitutes a water supply pipe for supplying hot water to the hot water mat body 110 from the outside, and the other rubber header 120. However, it constitutes a drain pipe for draining hot water from the hot water mat body 110 to the outside.

ボイラー等の熱源を有する温水供給装置150が、軌道200の側方に設置されている。温水供給装置150は、給水用配管151を介して給水側ゴムヘッダー120に接続されているとともに、排水用配管152を介して排水側ゴムヘッダー120に接続されている。温水供給装置150から、温水が、給水用配管151および給水側ゴムヘッダー120を介して、温水マット本体110の一端側へ供給される。温水マット本体110内を通って他端側へ達した温水が、排水側ゴムヘッダー120および排水用配管152を介して、温水供給装置150に回収される。   A hot water supply device 150 having a heat source such as a boiler is installed on the side of the track 200. The hot water supply device 150 is connected to the water supply side rubber header 120 via a water supply pipe 151 and is connected to the drainage side rubber header 120 via a drainage pipe 152. Hot water is supplied from the hot water supply device 150 to one end side of the hot water mat body 110 via the water supply pipe 151 and the water supply side rubber header 120. The hot water that has passed through the hot water mat main body 110 and reached the other end side is collected by the hot water supply device 150 via the drain side rubber header 120 and the drain pipe 152.

取り付け金具130は、両端のゴムヘッダー120のそれぞれに設けられており、取り付け金具130を介して、各ゴムヘッダー120が、軌道200に取り付けられる。   The mounting bracket 130 is provided on each of the rubber headers 120 at both ends, and each rubber header 120 is mounted on the track 200 via the mounting bracket 130.

次に、図2(A)および図2(B)を参照して、第1実施形態による融雪マット100の、温水マット本体110、ゴムヘッダー120、および取り付け金具130について、さらに説明する。図2(A)および図2(B)は、それぞれ、第1実施形態の融雪マット100の一端近傍を示す概略的な平面図および断面図である。図2(B)は、図2(A)のAA線に沿った断面図である。   Next, with reference to FIG. 2 (A) and FIG. 2 (B), the hot-water mat main body 110, the rubber header 120, and the attachment metal fitting 130 of the snow melting mat 100 by 1st Embodiment are further demonstrated. FIG. 2A and FIG. 2B are a schematic plan view and a cross-sectional view showing the vicinity of one end of the snow melting mat 100 of the first embodiment, respectively. FIG. 2B is a cross-sectional view taken along the line AA in FIG.

以下、ゴムヘッダー120および取り付け金具130について、例示的に一端側の構造を説明するが、他端側の構造は、対称的に構成されており、同様である。説明の便宜のため、ゴムヘッダー120に形成された給水用または排水用の管路を、まとめて、給排水管路と呼ぶこともある。   Hereinafter, regarding the rubber header 120 and the mounting bracket 130, the structure on one end side will be described as an example, but the structure on the other end side is configured symmetrically and is the same. For convenience of explanation, the water supply or drainage pipes formed in the rubber header 120 may be collectively referred to as a water supply / drainage pipe.

温水マット本体110は、ゴムマット111と、ゴムマット111の上面に貼り付けられた損傷防止布112とにより構成されている。ゴムマット111は、例えばエチレンプロピレンジエンゴム(EPDM)系ゴムで形成されている。損傷防止布112は、ゴムマット111よりも損傷しにくい材料、例えばアラミド繊維等で形成されており、厚さが例えば1mm程度である。   The hot water mat body 110 includes a rubber mat 111 and a damage preventing cloth 112 attached to the upper surface of the rubber mat 111. The rubber mat 111 is made of, for example, ethylene propylene diene rubber (EPDM) rubber. The damage prevention cloth 112 is made of a material that is less likely to be damaged than the rubber mat 111, such as an aramid fiber, and has a thickness of about 1 mm, for example.

温水マット本体110は、例えば、長さが7.5m程度、幅が60cm程度、厚さが1cm程度である。以下、温水マット本体110の長さ方向および幅方向を、それぞれ、マット長さ方向、マット幅方向と呼ぶこともある。   The hot water mat body 110 has, for example, a length of about 7.5 m, a width of about 60 cm, and a thickness of about 1 cm. Hereinafter, the length direction and the width direction of the hot water mat body 110 may be referred to as a mat length direction and a mat width direction, respectively.

温水マット本体110の内部に、マット長さ方向に延在し、温水を流すための本体管路113が、マット幅方向に並んで複数本設けられている。本体管路113は、直径が例えば5mm程度であり、本数が例えば90本程度である。なお、図2(A)では、図示の煩雑さを避けるため、少数の(具体的には5本の)本体管路113を例示する。   Inside the hot water mat main body 110, a plurality of main body pipes 113 extending in the mat length direction and for flowing hot water are provided side by side in the mat width direction. The main body conduit 113 has a diameter of, for example, about 5 mm and a number of, for example, about 90. In FIG. 2A, a small number (specifically, five) of main body conduits 113 are illustrated in order to avoid the complexity of the illustration.

ゴムヘッダー120は、温水マット本体110の端部に、マット幅方向について一端から他端に亘るように延在して、配置されている。ゴムヘッダー120は、上側部材121と下側部材122とにより構成され、それぞれ溝の形成された上側部材121と下側部材122とが対向するように重ね合わされることで、マット幅方向に延在する給排水管路123を構成している。   The rubber header 120 is arranged at the end of the hot water mat body 110 so as to extend from one end to the other end in the mat width direction. The rubber header 120 includes an upper member 121 and a lower member 122, and extends in the mat width direction by overlapping the upper member 121 and the lower member 122 in which grooves are formed so as to face each other. The water supply / drainage pipe line 123 is configured.

本体管路113が、給排水管路123に連通することにより、ゴムヘッダー120を介した給排水が可能となっている。以下、給排水管路123に対し、温水マット本体110側をマット内側あるいは単に内側と呼び、その反対側をマット外側あるいは単に外側と呼ぶこともある。   The main body pipe 113 communicates with the water supply / drainage pipe 123, so that water supply / drainage through the rubber header 120 is possible. Hereinafter, the hot water mat main body 110 side with respect to the water supply / drainage pipe 123 may be referred to as the mat inner side or simply the inner side, and the opposite side may be referred to as the mat outer side or simply the outer side.

上側部材121は、上側ゴム部材124と、上側ゴム部材124の上面に貼り付けられた損傷防止布125とにより構成されている。上側ゴム部材124は、例えばEPDM系ゴムで形成されている。損傷防止布125は、上側ゴム部材124よりも損傷しにくい材料、例えばアラミド繊維等で形成されており、厚さが例えば1mm程度である。下側部材122は、単体のゴム部材であり、例えばEPDM系ゴムで形成されている。   The upper member 121 includes an upper rubber member 124 and a damage prevention cloth 125 attached to the upper surface of the upper rubber member 124. The upper rubber member 124 is made of, for example, EPDM rubber. The damage prevention cloth 125 is made of a material that is less likely to be damaged than the upper rubber member 124, such as an aramid fiber, and has a thickness of about 1 mm, for example. The lower member 122 is a single rubber member, and is formed of, for example, EPDM rubber.

ゴムヘッダー120は、給排水管路123を形成するための溝が形成され相対的に厚くなっている中央部126と、中央部126に対しマット内側に配置された縁部であって、中央部126よりも相対的に薄くなっている内側縁部127と、中央部126に対しマット外側に配置された縁部であって、中央部126よりも相対的に薄くなっている外側縁部128とに、概ね区画される。   The rubber header 120 includes a central portion 126 formed with a groove for forming the water supply / drainage pipe 123 and is relatively thick, and an edge portion disposed on the inner side of the mat with respect to the central portion 126. An inner edge 127 that is relatively thinner than the inner edge 127, and an outer edge 128 that is disposed on the outer side of the mat with respect to the central portion 126 and is thinner than the central portion 126. , Roughly divided.

中央部126は、例えば、幅(マット長さ方向の寸法。以下、内側縁部127と外側縁部128の説明でも同様。)が5cm程度で、厚さが4cm程度である。中央部126内部に形成された給排水管路123の直径は、例えば2.5cm程度である。   The central portion 126 has, for example, a width (dimension in the mat length direction; hereinafter the same applies to the explanation of the inner edge portion 127 and the outer edge portion 128) and a thickness of about 4 cm. The diameter of the water supply / drainage pipe 123 formed inside the central portion 126 is, for example, about 2.5 cm.

内側縁部127は、例えば、幅が5cm程度で、厚さが2cm程度である。なお、図2(B)では、内側縁部127の厚さが、マット内側に向けて薄くなる構造を例示している。外側縁部128は、例えば、幅が2cm程度で、厚さが1cm程度である。   For example, the inner edge 127 has a width of about 5 cm and a thickness of about 2 cm. Note that FIG. 2B illustrates a structure in which the thickness of the inner edge 127 becomes thinner toward the inner side of the mat. The outer edge 128 has a width of about 2 cm and a thickness of about 1 cm, for example.

上側部材121の内側縁部127(上側部材121の給排水管路123に対しマット内側に配置された縁部)と、下側部材122の内側縁部127(下側部材122の給排水管路123に対しマット内側に配置された縁部)とが、温水マット本体110の端部を挟んで接着されていることにより、給排水管路123のマット内側側面と本体管路113とが連通し、隣接する本体管路113同士の間で給排水管路123のマット内側側面が閉じた管路構造が形成されるとともに、ゴムヘッダー120が温水マット本体110に固定されている。   The inner edge 127 of the upper member 121 (the edge disposed inside the mat with respect to the water supply / drainage pipe 123 of the upper member 121) and the inner edge 127 of the lower member 122 (the water supply / drainage pipe 123 of the lower member 122) The edge of the hot water mat main body 110 is sandwiched between the mat inner side surface of the water supply / drainage pipe 123 and the main body pipe 113 so that they are adjacent to each other. A pipe structure in which the mat inner side surface of the water supply / drainage pipe 123 is closed is formed between the main pipes 113, and the rubber header 120 is fixed to the hot water mat main body 110.

取り付け金具130は、マット幅方向に延在する根元部131と、根元部131からマット外側に突出する取り付け部(櫛歯部)132とを有する。取り付け部(櫛歯部)132は、根元部131から櫛歯状に突出しており、取り付け金具130は、櫛歯形状となっている。まくらぎ202に、軌道側の取り付け金具203が固定されている。取り付け金具203に取り付けられたボルト204を、櫛歯部132に形成された貫通孔133を貫通させることにより、融雪マット側の取り付け金具130が、軌道側の取り付け金具203に取り付けられる。このようにして、ゴムヘッダー120が、軌道に取り付けられる。取り付け金具130は、ゴムヘッダー120を上側から覆わないように配置されている。   The mounting bracket 130 includes a root portion 131 that extends in the mat width direction, and a mounting portion (comb portion) 132 that protrudes from the root portion 131 to the outside of the mat. The attachment portion (comb tooth portion) 132 protrudes from the root portion 131 in a comb shape, and the attachment fitting 130 has a comb shape. A track mounting bracket 203 is fixed to the sleeper 202. By attaching the bolt 204 attached to the attachment fitting 203 through the through hole 133 formed in the comb tooth portion 132, the attachment fitting 130 on the snow melting mat side is attached to the attachment fitting 203 on the track side. In this way, the rubber header 120 is attached to the track. The mounting bracket 130 is disposed so as not to cover the rubber header 120 from above.

上側部材121の外側縁部128(上側部材121の給排水管路123に対しマット外側に配置された縁部)と、下側部材122の外側縁部128(下側部材122の給排水管路123に対しマット外側に配置された縁部)とが、根元部131を挟んで接着されていることにより、給排水管路123のマット外側側面が閉じるとともに、取り付け金具130がゴムヘッダー120に固定されている。つまり、取り付け金具130の一部は、ゴムヘッダー120の上側部材121と下側部材122とに挟まれて覆われている。   The outer edge 128 of the upper member 121 (the edge disposed outside the mat with respect to the water supply / drainage pipe 123 of the upper member 121) and the outer edge 128 of the lower member 122 (the water supply / drainage pipe 123 of the lower member 122) The edge portion disposed outside the mat) is bonded to the base portion 131 so that the mat outer side surface of the water supply / drainage pipe 123 is closed, and the attachment fitting 130 is fixed to the rubber header 120. . That is, a part of the mounting bracket 130 is sandwiched and covered by the upper member 121 and the lower member 122 of the rubber header 120.

取り付け金具130は、例えばステンレスで形成され、厚さが例えば2.5mm程度である。根元部131は、例えば、長さ(マット幅方向の寸法)が64.0cm程度で、幅(マット長さ方向の寸法)が6.7cm程度である。櫛歯部132は、例えば、各櫛歯部132の長さ(マット長さ方向の寸法)が3.8cm程度で、幅(マット幅方向の寸法)が3.0cm程度であり、例えば24.5cm間隔で3本程度配置される。   The attachment fitting 130 is made of, for example, stainless steel and has a thickness of, for example, about 2.5 mm. The root portion 131 has, for example, a length (dimension in the mat width direction) of about 64.0 cm and a width (dimension in the mat length direction) of about 6.7 cm. For example, the comb teeth 132 have a length (dimension in the mat length direction) of about 3.8 cm and a width (dimension in the mat width direction) of about 3.0 cm. About three are arranged at intervals of 5 cm.

次に、第1実施形態による融雪マット100の製造方法について説明する。まず、温水マット本体110の端部を、ゴムヘッダー120の上側部材121の内側縁部127と、下側部材122の内側縁部127とで挟んだ状態で、金型を用いて加硫接着する(第1の加硫接着工程)。   Next, a method for manufacturing the snow melting mat 100 according to the first embodiment will be described. First, the end portion of the hot water mat main body 110 is vulcanized and bonded using a mold while being sandwiched between the inner edge portion 127 of the upper member 121 of the rubber header 120 and the inner edge portion 127 of the lower member 122. (First vulcanization adhesion step).

第1の加硫接着工程において加えられる熱での変形により、本体管路113や給排水管路123が潰れたり塞がれたりしないように、第1の加硫接着工程において、本体管路113や給排水管路123には、各管路の太さに対応した円筒形状で例えば金属製の詰め物が挿入される。第1の加硫接着工程の完了後、これらの詰め物が取り除かれる。   In the first vulcanization bonding process, the main body pipe line 113 and the main pipe line 113 and the water supply / drainage pipe line 123 are not crushed or blocked by the deformation caused by heat applied in the first vulcanization bonding process. For example, a metal filling is inserted into the water supply / drainage pipe 123 in a cylindrical shape corresponding to the thickness of each pipe. After the completion of the first vulcanization bonding process, these fillings are removed.

第1の加硫接着工程が完了した段階では、上側部材121および下側部材122の、マット外側の縁部128同士は接着されておらず、ゴムヘッダー120のマット外側端部は開いている。この開口から、本体管路113に挿入されていた詰め物を取り除くことができる。   At the stage where the first vulcanizing and bonding step is completed, the mat member outer edges 128 of the upper member 121 and the lower member 122 are not bonded to each other, and the mat outer end of the rubber header 120 is open. From this opening, the padding that has been inserted into the main body conduit 113 can be removed.

次に、取り付け金具130の接着部となる根元部131をブラスト処理し、根元部131に、接着剤を塗布する。この接着剤としては、例えば、ロード社のケムロック205、ケムロック220(ケムロックは登録商標)等を用いることができる。接着剤乾燥後、根元部131に、密着ゴム層を貼り付ける(圧着する)。密着ゴム層としては、例えば、厚さ0.3mm〜1.0mm程度のEPDM系ゴムを用いることができる。   Next, the base part 131 which becomes an adhesive part of the mounting bracket 130 is blasted, and an adhesive is applied to the base part 131. As this adhesive, for example, Chemlock 205, Chemlock 220 (Chemlock is a registered trademark) manufactured by Lord Corporation can be used. After the adhesive is dried, an adhesive rubber layer is attached (bonded) to the root portion 131. As the adhesion rubber layer, for example, EPDM rubber having a thickness of about 0.3 mm to 1.0 mm can be used.

一方、ゴムヘッダー120の接着部となる、上側部材121および下側部材122の外側縁部128の内面を、サンドペーパー等で荒らしておく。そして、密着ゴム層を貼り付けた取り付け金具130を、上側部材121の外側縁部128と、下側部材122の外側縁部128との間に挿入した状態で、金型を用いて加硫接着する(第2の加硫接着工程)。   On the other hand, the inner surfaces of the outer edge portions 128 of the upper member 121 and the lower member 122 that serve as the bonding portions of the rubber header 120 are roughened with sandpaper or the like. Then, the attachment fitting 130 to which the adhesion rubber layer is attached is vulcanized and bonded using a mold in a state where it is inserted between the outer edge portion 128 of the upper member 121 and the outer edge portion 128 of the lower member 122. (Second vulcanization adhesion step).

第2の加硫接着工程により、ゴムヘッダー120のマット外側端部が閉じられるとともに、ゴムヘッダー120に取り付け金具130が固定される。このようにして、実施形態による融雪マット100が作製される。   The mat outer end of the rubber header 120 is closed by the second vulcanization bonding step, and the mounting bracket 130 is fixed to the rubber header 120. In this way, the snow melting mat 100 according to the embodiment is manufactured.

次に、図4(A)および図4(B)を参照して、比較形態による融雪マット300と、比較形態において生じる課題について説明する。図4(A)および図4(B)は、それぞれ、比較形態による融雪マット300の一端近傍を示す概略的な平面図および断面図である。図4(B)は、図4(A)のAA線に沿った断面図である。   Next, with reference to FIG. 4 (A) and FIG. 4 (B), the snow melting mat 300 by a comparison form and the problem which arises in a comparison form are demonstrated. FIGS. 4A and 4B are a schematic plan view and a cross-sectional view showing the vicinity of one end of the snow melting mat 300 according to the comparative embodiment, respectively. FIG. 4B is a cross-sectional view taken along line AA in FIG.

比較形態による融雪マット300の温水マット本体310は、第1実施形態による温水マット本体110と同様なものである。主として取り付け金具330に関する構造が、比較形態と第1実施形態とで異なっている。   The hot water mat main body 310 of the snow melting mat 300 according to the comparative embodiment is the same as the hot water mat main body 110 according to the first embodiment. The structure mainly relating to the mounting bracket 330 is different between the comparative embodiment and the first embodiment.

比較形態の取り付け金具330は、ゴムヘッダー320の上側部材321の中央部326を上側から覆い外側縁部328上まで延在し、さらにマット外側に突出し、全体がマット幅方向の一端から他端に亘って延在して露出する形状となっている。取り付け金具330は、突出部331で軌道に取り付けられる。また、取り付け金具(上側金具)330の下側に、ゴムヘッダー320の下側部材322の中央部326を下側から覆い外側縁部328下まで延在する下側金具332が設けられている。   The comparative mounting bracket 330 covers the central portion 326 of the upper member 321 of the rubber header 320 from the upper side, extends to the outer edge portion 328, further protrudes to the outer side of the mat, and entirely extends from one end to the other end in the mat width direction. It has a shape that extends and is exposed. The mounting bracket 330 is attached to the track by the protruding portion 331. A lower metal fitting 332 is provided below the attachment metal fitting (upper metal fitting) 330 so as to cover the central portion 326 of the lower member 322 of the rubber header 320 from the lower side and extend under the outer edge 328.

比較形態のゴムヘッダー320は、外側縁部328において、上側部材321と下側部材322とが接着されていない。上側部材321の外側縁部328と下側部材322の外側縁部328とが、取り付け金具(上側金具)330と下側金具332とを介しボルトとナットで圧着されることにより、給排水管路323のマット外側側面が閉じられている。また、この圧着構造により、取り付け金具330および下側金具332が、ゴムヘッダー320に固定されている。   In the rubber header 320 of the comparative form, the upper member 321 and the lower member 322 are not bonded at the outer edge 328. The outer edge 328 of the upper member 321 and the outer edge 328 of the lower member 322 are pressure-bonded with bolts and nuts via attachment fittings (upper fittings) 330 and lower fittings 332, thereby supplying and draining pipes 323. The mat's outer side is closed. In addition, the mounting bracket 330 and the lower bracket 332 are fixed to the rubber header 320 by this crimping structure.

なお、比較形態のゴムヘッダー320では、上側部材321の上面に、損傷防止布が設けられていない。   In the rubber header 320 of the comparative form, no damage prevention cloth is provided on the upper surface of the upper member 321.

比較形態による融雪マット300では、列車がゴムヘッダー320上を通過する際に、列車持ち込み雪の塊が列車と取り付け金具330との間に挟まれることにより、取り付け金具330が変形することがある。取り付け金具330の変形は、塑性的であり持続的なものであるので、その下のゴムヘッダー320の変形も、持続的なものとなる。この変形により、上側部材321と下側部材322との圧着が不良となって給排水管路323が損傷し、温水の漏れが発生することがある。   In the snow melting mat 300 according to the comparative form, when the train passes over the rubber header 320, the snow pieces brought in by the train are sandwiched between the train and the mounting bracket 330, and the mounting bracket 330 may be deformed. Since the deformation of the mounting bracket 330 is plastic and continuous, the deformation of the rubber header 320 below it is also continuous. Due to this deformation, the pressure bonding between the upper member 321 and the lower member 322 may be poor and the water supply / drainage line 323 may be damaged, causing leakage of hot water.

また、比較形態による融雪マット300において、取り付け金具330が、全体がマット幅方向の一端から他端に亘って延在して露出する形状となっていることは、軌道短絡防止の観点から見て、望ましいとはいえない。   In addition, in the snow melting mat 300 according to the comparative embodiment, the mounting bracket 330 is entirely exposed from one end to the other end in the mat width direction. This is not desirable.

次に、第1実施形態の融雪マット100により得られる効果について例示的に説明する。本実施形態の融雪マット100では、弾性部材で形成されたゴムヘッダー120が、取り付け金具130に覆われずに、そのまま露出している。このため、列車持ち込み雪の塊が列車とゴムヘッダー120との間に挟まれ、ゴムヘッダー120が変形することがあっても、一時的な弾性変形であるので、元の形状に戻る。   Next, the effect obtained by the snow melting mat 100 of the first embodiment will be exemplarily described. In the snow melting mat 100 of the present embodiment, the rubber header 120 formed of an elastic member is exposed as it is without being covered with the mounting bracket 130. For this reason, even if the snow lump brought into the train is sandwiched between the train and the rubber header 120 and the rubber header 120 is deformed, it is temporarily elastically deformed, so it returns to its original shape.

また、ゴムヘッダー120の上側部材121と下側部材122の外側縁部128同士が接着されていることにより、給排水管路123が強固に形成されている。このようにして、給排水管路123の損傷が抑制され、温水の漏れが抑制されている。   Further, the outer edge portions 128 of the upper member 121 and the lower member 122 of the rubber header 120 are bonded to each other, so that the water supply / drainage pipe 123 is firmly formed. In this way, damage to the water supply / drainage pipe 123 is suppressed, and leakage of hot water is suppressed.

さらに、第1実施形態の融雪マット100では、取り付け金具130の、マット幅方向に延在する根元部131が、ゴムヘッダー120の上側部材121の外側縁部128と、下側部材122の外側縁部128とに挟まれて、覆われている。軌道に取り付けられる部分であり、露出している取り付け部(櫛歯部)132は、マット幅方向に沿って部分的、離散的に配置されている。このような、マット幅方向の一端から他端に亘って延在する金属部材が露出しない構造により、軌道短絡が抑制されている。   Furthermore, in the snow melting mat 100 according to the first embodiment, the root portion 131 of the mounting bracket 130 extending in the mat width direction includes the outer edge portion 128 of the upper member 121 of the rubber header 120 and the outer edge of the lower member 122. It is sandwiched between and covered with the part 128. The exposed attachment portion (comb tooth portion) 132 that is a portion attached to the track is partially and discretely arranged along the mat width direction. By such a structure in which the metal member extending from one end to the other end in the mat width direction is not exposed, the track short circuit is suppressed.

その他、さらに、第1実施形態の融雪マット100では、ゴムヘッダー120の、上側部材121の上面に、損傷防止布125が設けられている。これにより、ゴムヘッダー120の損傷が抑制されている。   In addition, in the snow melting mat 100 of the first embodiment, a damage preventing cloth 125 is provided on the upper surface of the upper member 121 of the rubber header 120. Thereby, damage to the rubber header 120 is suppressed.

次に、図3を参照して、第2実施形態による融雪マットについて説明する。なお、説明の便宜のため、第1実施形態と対応する部材や構造について、同一の参照符号を流用する。図3は、第2実施形態の融雪マット100の一端近傍を示す概略的な断面図である。第2実施形態の融雪マットの敷設態様や、概略的な平面構造や、製造方法は、第1実施形態の融雪マットについて説明したものと同様である。第2実施形態では、ゴムヘッダー120の(少なくとも上側部材121の)中央部126の断面形状が、第1実施形態のそれと異なっている。その他の構造は、第1実施形態と同様である。   Next, a snow melting mat according to the second embodiment will be described with reference to FIG. For convenience of explanation, the same reference numerals are used for members and structures corresponding to the first embodiment. FIG. 3 is a schematic cross-sectional view showing the vicinity of one end of the snow melting mat 100 of the second embodiment. The laying aspect, schematic planar structure, and manufacturing method of the snow melting mat of the second embodiment are the same as those described for the snow melting mat of the first embodiment. In the second embodiment, the cross-sectional shape of the central portion 126 (at least of the upper member 121) of the rubber header 120 is different from that of the first embodiment. Other structures are the same as those of the first embodiment.

図2(B)に示したように、第1実施形態による上側部材121の中央部126は、外側縁部128側から急激に厚みが増して、中央部126と外側縁部128との境界部に上方側へ突出した角部129を有する形状であり、また、内側縁部127側から急激に厚みが増して、中央部126と内側縁部127との境界部に上方側へ突出した角部129を有する形状である。   As shown in FIG. 2B, the central portion 126 of the upper member 121 according to the first embodiment suddenly increases in thickness from the outer edge portion 128 side, and a boundary portion between the central portion 126 and the outer edge portion 128. The corner portion 129 protrudes upward from the inner edge portion 127 side, and the corner portion 129 protrudes upward from the boundary portion between the central portion 126 and the inner edge portion 127. 129.

一方、図3に示すように、第2実施形態による上側部材121の中央部126は、外側縁部128側からも内側縁部127側からもなだらかに厚みが増して、上方側へ突出した角部を有さない形状である。つまり、第2実施形態のゴムヘッダー120は、上側部材121の給排水管路123周囲を覆う部分の外形形状が、上方側へ突出した角部を有さずに、給排水管路123の両側から給排水管路123の中央部に向かってなだらかに厚みを増す形状となっている。   On the other hand, as shown in FIG. 3, the central portion 126 of the upper member 121 according to the second embodiment gradually increases in thickness from the outer edge 128 side and the inner edge 127 side, and protrudes upward. The shape has no part. That is, in the rubber header 120 of the second embodiment, the outer shape of the portion covering the periphery of the water supply / drainage pipe 123 of the upper member 121 does not have a corner protruding upward, and the water supply / drainage from both sides of the water supply / drainage pipe 123 is performed. The shape gradually increases toward the center of the pipe 123.

第2実施形態の融雪マット100では、第1実施形態の融雪マットについて説明した効果と同様な効果が得られるとともに、さらに、以下のような効果も得られる。   In the snow melting mat 100 of the second embodiment, the same effects as those described for the snow melting mat of the first embodiment are obtained, and the following effects are also obtained.

第1実施形態のゴムヘッダー120は、弾性部材が露出する構造となっているものの、持ち込み雪との接触時に、角部129に応力が集中する可能性がある。第2実施形態のゴムヘッダー120は、上述のような曲面的な形状により、持ち込み雪の塊から受ける圧力を分散してゴムヘッダー全体で吸収しやすい。このため、第2実施形態では、融雪マット端部に設けられたヘッダー構造の損傷が、第1実施形態よりもさらに抑制されている。   Although the rubber header 120 of the first embodiment has a structure in which the elastic member is exposed, there is a possibility that stress is concentrated on the corner portion 129 at the time of contact with the snow brought in. The rubber header 120 of the second embodiment has a curved shape as described above, and easily disperses the pressure received from the snow lump to be absorbed by the entire rubber header. For this reason, in the second embodiment, damage to the header structure provided at the end of the snow melting mat is further suppressed than in the first embodiment.

また、第2実施形態のゴムヘッダー120においては、上側部材121が上側に突出した角部を有さない形状であるので、上側部材121の上面に設けられる損傷防止布125を、上側ゴム部材124と一体化するように貼り付けやすい。このため、損傷防止布125をより剥がれにくくできる。   Further, in the rubber header 120 of the second embodiment, since the upper member 121 has a shape that does not have a protruding corner, the damage preventing cloth 125 provided on the upper surface of the upper member 121 is attached to the upper rubber member 124. Easy to paste so as to be integrated. For this reason, the damage preventing cloth 125 can be more difficult to peel off.

以上、実施形態に沿って本発明を説明したが、本発明はこれらに制限されるものではない。例えば、種々の変更、改良、組み合わせ等が可能なことは当業者に自明であろう。   As mentioned above, although this invention was demonstrated along embodiment, this invention is not restrict | limited to these. It will be apparent to those skilled in the art that various modifications, improvements, combinations, and the like can be made.

100 融雪マット
110 温水マット本体
111 ゴムマット
112 損傷防止布
113 本体管路
120 ゴムヘッダー
121 上側部材
122 下側部材
123 給排水管路
124 上側ゴム部材
125 損傷防止布
126 中央部
127 内側縁部
128 外側縁部
130 取り付け金具
131 根元部
132 取り付け部(櫛歯部)
100 Snow melting mat 110 Hot water mat main body 111 Rubber mat 112 Damage prevention cloth 113 Main body conduit 120 Rubber header 121 Upper member 122 Lower member 123 Water supply / drainage pipe 124 Upper rubber member 125 Damage prevention cloth 126 Central portion 127 Inner edge portion 128 Outer edge portion 130 mounting bracket 131 root portion 132 mounting portion (comb tooth portion)

Claims (5)

レールの延在方向に沿って配置される温水マット本体と、
前記温水マット本体の端部に、前記温水マット本体の幅方向に延在して配置され、それぞれ溝の形成された上側部材と下側部材とが対向するように重ね合わされることで、外部から前記温水マット本体へ温水を給水するための管路、または、外部へ前記温水マット本体から温水を排水するための管路を構成しているゴムヘッダーと、
前記ゴムヘッダーを軌道に取り付けるための取り付け金具と
を有し、
前記取り付け金具は、前記温水マット本体の幅方向に延在する根元部と、前記根元部から前記管路に対し前記温水マット本体と反対側に突出し、前記軌道に取り付けられる取り付け部とを有し、前記ゴムヘッダーを上側から覆わないように配置されており、
前記上側部材および前記下側部材の、前記管路に対し前記温水マット本体と反対側に配置された縁部同士が、前記根元部を挟んで接着されていることにより、前記管路の側面が閉じるとともに、前記取り付け金具が前記ゴムヘッダーに固定されている、
軌道用融雪マット。
A hot water mat body arranged along the extending direction of the rail;
At the end of the hot water mat body, it is arranged extending in the width direction of the hot water mat body, and the upper member and the lower member in which grooves are respectively formed are overlapped so as to face each other, so that from the outside A pipe for supplying hot water to the hot water mat body, or a rubber header constituting a pipe for draining hot water from the hot water mat body to the outside;
A mounting bracket for mounting the rubber header on the track,
The mounting bracket has a root portion extending in the width direction of the hot water mat body, and a mounting portion that protrudes from the root portion to the opposite side of the hot water mat body with respect to the pipe line and is attached to the track. , Arranged so as not to cover the rubber header from above,
Edges of the upper member and the lower member, which are arranged on the opposite side of the hot water mat main body with respect to the pipe line, are bonded with the root part interposed therebetween, whereby the side surface of the pipe line is With the closing, the mounting bracket is fixed to the rubber header,
Snow melting mat for tracks.
前記取り付け部は、前記根元部から櫛歯状に突出する、請求項1に記載の軌道用融雪マット。   The track snow melting mat according to claim 1, wherein the attachment portion protrudes in a comb shape from the root portion. 前記取り付け金具の一部は、前記ゴムヘッダーの前記上側部材と前記下側部材とに挟まれて覆われている、請求項1または2に記載の軌道用融雪マット。   The track snow melting mat according to claim 1 or 2, wherein a part of the mounting bracket is sandwiched and covered by the upper member and the lower member of the rubber header. 前記ゴムヘッダーは、前記上側部材の前記管路周囲を覆う部分の外形形状が、上方側へ突出した角部を有さずに、前記管路の両側から前記管路の中央部に向かってなだらかに厚みを増す形状となっている請求項1乃至3のいずれかに記載の軌道用融雪マット。   In the rubber header, the outer shape of the portion of the upper member that covers the periphery of the pipe line does not have a corner portion protruding upward, and gently from both sides of the pipe line toward the center of the pipe line. The snow melting mat for a track according to any one of claims 1 to 3, wherein the snow melting mat has a shape that increases the thickness. 前記上側部材の上面に、損傷防止布が設けられている請求項1乃至4のいずれかに記載の軌道用融雪マット。   The snow melting mat for tracks according to any one of claims 1 to 4, wherein a damage prevention cloth is provided on an upper surface of the upper member.
JP2014183901A 2014-09-10 2014-09-10 Snow melting mat for track Active JP6357991B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014183901A JP6357991B2 (en) 2014-09-10 2014-09-10 Snow melting mat for track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014183901A JP6357991B2 (en) 2014-09-10 2014-09-10 Snow melting mat for track

Publications (2)

Publication Number Publication Date
JP2016056589A true JP2016056589A (en) 2016-04-21
JP6357991B2 JP6357991B2 (en) 2018-07-18

Family

ID=55757707

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014183901A Active JP6357991B2 (en) 2014-09-10 2014-09-10 Snow melting mat for track

Country Status (1)

Country Link
JP (1) JP6357991B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7456569B2 (en) 2020-09-29 2024-03-27 東北ゴム株式会社 snow melting mat

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS506087Y1 (en) * 1970-12-02 1975-02-21
JPS5561603A (en) * 1978-11-02 1980-05-09 Hitachi Ltd Pavement material and making method thereof
JPH01111720U (en) * 1988-01-12 1989-07-27
JPH02129404U (en) * 1989-03-31 1990-10-25
JPH03187402A (en) * 1989-12-15 1991-08-15 Nippon Tetsudo Kensetsu Kodan Radiator for extinguishing snow
JPH07158002A (en) * 1993-12-07 1995-06-20 Mitsubishi Electric Corp Electric hot air type snow melter
JPH10176302A (en) * 1996-12-18 1998-06-30 Hitachi Cable Ltd Snow melting device of rail of railroad, etc.
US20100108294A1 (en) * 2007-04-25 2010-05-06 Wolfgang Feldmann Heat transfer unit for heating systems and surefaces and railway point heater

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS506087Y1 (en) * 1970-12-02 1975-02-21
JPS5561603A (en) * 1978-11-02 1980-05-09 Hitachi Ltd Pavement material and making method thereof
JPH01111720U (en) * 1988-01-12 1989-07-27
JPH02129404U (en) * 1989-03-31 1990-10-25
JPH03187402A (en) * 1989-12-15 1991-08-15 Nippon Tetsudo Kensetsu Kodan Radiator for extinguishing snow
JPH07158002A (en) * 1993-12-07 1995-06-20 Mitsubishi Electric Corp Electric hot air type snow melter
JPH10176302A (en) * 1996-12-18 1998-06-30 Hitachi Cable Ltd Snow melting device of rail of railroad, etc.
US20100108294A1 (en) * 2007-04-25 2010-05-06 Wolfgang Feldmann Heat transfer unit for heating systems and surefaces and railway point heater

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7456569B2 (en) 2020-09-29 2024-03-27 東北ゴム株式会社 snow melting mat

Also Published As

Publication number Publication date
JP6357991B2 (en) 2018-07-18

Similar Documents

Publication Publication Date Title
WO2018051153A1 (en) Wind turbine blade including protective cover
FI60665B (en) FOERFARANDE FOER PERIFERIFOERNYELSE OCH REPARATION AV GUMMIDAECK FOER ETT FORDON
JP6357991B2 (en) Snow melting mat for track
RU2016117139A (en) TAPE CLIP FOR REPAIR OF PIPELINES
JP6736815B2 (en) Concrete piece protective sheet
JP5874938B2 (en) Concrete piece protection sheet
JP6044981B2 (en) Flowing water pipe repair method
JP5415928B2 (en) Tunnel repair structure
JP5178091B2 (en) Branch joint and sprinkler
JP6660825B2 (en) Water conduction structure and construction method of water conduction structure
JP2000145392A (en) Tunnel execution method
JP5255526B2 (en) Joint water leakage prevention structure and joint water leakage prevention construction method
JP4362209B2 (en) Road bridge expansion joint
JP2020007741A (en) Sleeper with integrated pipe conduit
JP5635739B2 (en) Gas leak temporary stop method
CN104358963A (en) Drainage device for emergency disposal in case of leakage of exposed oil and gas pipelines, and leakage disposal method thereof
RU105303U1 (en) INSULATING JOINT
EP2781669A1 (en) Method for sealing a joint between two adjacent roof covering sections
JP2007120231A (en) Exfoliation preventing net
CA2848081C (en) Peel-resistant mechanism for use in bonding components
JP2014037728A (en) Repair cover for gutter, device for adjusting connection between mutual repair covers for gutter, gutter repair structure and gutter repair method
JP6242110B2 (en) Waterway repair structure and repair method
JP2020063647A (en) Tunnel waterproof sheet and tunnel
CN109312621A (en) For being embedded in the seal profile of curable materials moulded parts
RU2624485C2 (en) Rail vehicle equipped with spillway conduit protected from freezing

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170317

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180112

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180123

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180315

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180522

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180604

R150 Certificate of patent or registration of utility model

Ref document number: 6357991

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350