JP2015132345A - Fluid conduction blocking method of pipe - Google Patents

Fluid conduction blocking method of pipe Download PDF

Info

Publication number
JP2015132345A
JP2015132345A JP2014004740A JP2014004740A JP2015132345A JP 2015132345 A JP2015132345 A JP 2015132345A JP 2014004740 A JP2014004740 A JP 2014004740A JP 2014004740 A JP2014004740 A JP 2014004740A JP 2015132345 A JP2015132345 A JP 2015132345A
Authority
JP
Japan
Prior art keywords
partition plate
fluid
spacer
pipe
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2014004740A
Other languages
Japanese (ja)
Inventor
貴道 土田
Takamichi Tsuchida
貴道 土田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Priority to JP2014004740A priority Critical patent/JP2015132345A/en
Publication of JP2015132345A publication Critical patent/JP2015132345A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a fluid conduction blocking method of a pipe capable of easily, inexpensively and properly blocking conduction of a fluid so that a liquid does not flow to a construction portion-side pipe in executing a construction of a pipe in which a fluid is conducted.SOLUTION: In a method of blocking conduction of a fluid by inserting a partition plate jig to a flange connecting portion of a pipe in which a fluid is conducted, and tightening the same by a bolt with the flange, the partition plate jig includes two sheets of partition plates having bolt holes corresponding to bolt fastening positions of the flange, and a discharge flow channel having a spacer held between two sheets of partition plates to form a clearance between the two sheets of partition plates, and discharging the fluid flowing into the clearance to the outside of the pipe.

Description

本発明は、配管の流体導通遮断方法に関するものである。   The present invention relates to a method for interrupting fluid conduction in piping.

内部を流体が導通している配管(例えば、燃料ガスの供給配管)の工事を行う場合には、工事を施工する個所の配管に流体が流入しないようにするために、工事を施工する側(工事施工側)の配管と、流体が導通している側(流体導通側)の配管の間で、流体の導通を遮断する必要がある。   When constructing pipes where fluid is conducted inside (for example, fuel gas supply pipes), in order to prevent fluid from flowing into the pipes at the construction site, It is necessary to cut off the fluid conduction between the piping on the construction side) and the piping on the fluid conducting side (fluid conducting side).

そして、上記のように流体の導通を遮断する際には、一般的に配管には所定の間隔でフランジ接続部が設けられていて、対向するフランジ間の隙間をリング状の板で塞いでいるので、工事施工個所に近い位置のフランジ接続部において、リング状の板を抜いて仕切板を挿入する方法がとられている(例えば、特許文献1参照)。   When the fluid is interrupted as described above, generally, the pipe is provided with flange connection portions at a predetermined interval, and the gap between the opposing flanges is closed with a ring-shaped plate. Therefore, a method has been adopted in which a ring-shaped plate is pulled out and a partition plate is inserted at a flange connection portion at a position close to a construction site (for example, see Patent Document 1).

また、場合によっては、配管内にバルーンを設置する方法や、配管に仕切弁を切り込む方法が用いられることもある。   In some cases, a method of installing a balloon in the pipe or a method of cutting a gate valve into the pipe may be used.

ただし、上述した方法では、流体の導通を十分に遮断し切れない場合があり、万一、遮断した個所に漏洩が生じたとしても、漏洩した流体が工事施工部側の配管に流入することのないように、二重の遮断を行うことがある。   However, in the above-described method, there is a case where the fluid conduction cannot be sufficiently cut off, and even if a leak occurs in the cut off location, the leaked fluid may flow into the construction side piping. There may be a double shut-off.

図5は、そのように、二重の遮断を行う場合の例である。   FIG. 5 shows an example in which double blocking is performed as described above.

図5(a)は、仕切板を2段に設置して、二重の遮断を行う場合である。工事施工部21側の配管4aと流体導通部22側の配管4bの間に、緩衝部23として不活性ガスが満たされた配管4cを設け、工事施工部側配管4aのフランジ1aと緩衝部配管4cのフランジ1cの間に仕切板31を挿入してボルト32とナット33で固定するとともに、緩衝部配管4cのフランジ1dと液体導通部側配管4bのフランジ1bとの間に仕切板34を挿入してボルト35とナット36で固定している。これによって、流体導通部側配管4b内の流体が仕切板34から漏洩したとしても、漏洩した流体は仕切板31で遮断され、工事施工部側配管4aに流入することが防止される。   Fig.5 (a) is a case where a partition plate is installed in two steps and double interruption | blocking is performed. Between the pipe 4a on the construction work section 21 side and the pipe 4b on the fluid conduction section 22 side, a pipe 4c filled with an inert gas is provided as the buffer section 23, and the flange 1a and the buffer section pipe of the construction work section side pipe 4a are provided. The partition plate 31 is inserted between the flanges 1c of the 4c and fixed with bolts 32 and nuts 33, and the partition plate 34 is inserted between the flange 1d of the buffer portion piping 4c and the flange 1b of the liquid conduction portion side piping 4b. The bolt 35 and the nut 36 are fixed. Thereby, even if the fluid in the fluid conduction part side piping 4b leaks from the partition plate 34, the leaked fluid is blocked by the partition plate 31 and is prevented from flowing into the construction part piping 4a.

また、図5(b)は、仕切板とバルーンを設置して、二重の遮断を行う場合である。工事施工部側配管4aのフランジ1aと流体導通部側配管4bのフランジ1bとの間に仕切板31を挿入してボルト32とナット33で固定するとともに、流体導通部側配管4b内にバルーン37を設置している。これによって、流体導通部側配管4b内の流体がバルーン37から漏洩したとしても、漏洩した流体は仕切板31で遮断され、工事施工部側配管4aに流入することが防止される。   FIG. 5B shows a case where a partition plate and a balloon are installed to perform double blocking. A partition plate 31 is inserted between the flange 1a of the construction work section side pipe 4a and the flange 1b of the fluid conduction section side pipe 4b and fixed with bolts 32 and nuts 33, and a balloon 37 is placed in the fluid conduction section side pipe 4b. Is installed. As a result, even if the fluid in the fluid conducting portion side pipe 4b leaks from the balloon 37, the leaked fluid is blocked by the partition plate 31 and is prevented from flowing into the construction portion side piping 4a.

また、図5(c)は、仕切板と仕切弁を設置して、二重の遮断を行う場合である。工事施工側配管4aのフランジ1aと流体導通部側配管4bのフランジ1bとの間に仕切板31を挿入してボルト32とナット33で固定するとともに、流体導通部側配管4bに仕切弁38を切り込んでいる。これによって、流体導通部側配管4b内の流体が仕切弁38から漏洩したとしても、漏洩した流体は仕切板31で遮断され、工事施工部側配管4aに流入することが防止される。   Moreover, FIG.5 (c) is a case where a partition plate and a gate valve are installed and double interruption | blocking is performed. The partition plate 31 is inserted between the flange 1a of the construction side pipe 4a and the flange 1b of the fluid conduction part side pipe 4b and fixed with bolts 32 and nuts 33, and the gate valve 38 is provided on the fluid conduction part side pipe 4b. Cut in. Thereby, even if the fluid in the fluid conduction part side pipe 4b leaks from the gate valve 38, the leaked fluid is blocked by the partition plate 31 and is prevented from flowing into the construction part side pipe 4a.

特開2006−144824号公報JP 2006-144824 A

しかし、図5に示したような、仕切板、バルーン、仕切弁を組み合わせて二重の遮断を行う方法は、工事施工部側配管に流体が流入しないように、確実に流体の導通を遮断する可能性が高まるものの、配管の複数個所で新たな設置加工が必要になるため、手間が掛かるとともに高価になるという問題がある。   However, as shown in FIG. 5, the method of performing the double shutoff by combining the partition plate, the balloon, and the gate valve reliably shuts off the fluid conduction so that the fluid does not flow into the construction work side piping. Although the possibility increases, there is a problem that it takes time and cost because new installation processing is required at a plurality of locations of the piping.

本発明は、上記のような事情に鑑みてなされたものであり、内部を流体が導通している配管の工事を行うに際して、工事施工部側配管に流体が流入しないように、簡便かつ安価で的確に流体の導通を遮断することができる配管の流体導通遮断方法を提供することを目的とするものである。   The present invention has been made in view of the circumstances as described above, and is simple and inexpensive so that the fluid does not flow into the construction work side piping when the construction of the piping in which the fluid is conducted is performed. It is an object of the present invention to provide a fluid conduction blocking method for piping capable of accurately blocking fluid conduction.

上記課題を解決するために、本発明は以下の特徴を有している。   In order to solve the above problems, the present invention has the following features.

[1]内部を流体が導通している配管のフランジ接続部に仕切板治具を挿入してフランジごとボルト留めすることにより流体の導通を遮断する方法であって、前記仕切板治具は、フランジのボルト留め位置に対応するボルト孔を有する2枚の仕切板と、当該2枚の仕切板の間に空隙を形成するために、当該2枚の仕切板の間に挟まれたスペーサーを有するとともに、前記空隙に流入した流体を配管外に放出するための放出流路を備えていることを特徴とする配管の流体導通遮断方法。   [1] A method of cutting off fluid conduction by inserting a partition plate jig into a flange connection portion of a pipe through which fluid is conducted and bolting the flange together with the flange, Two partition plates having bolt holes corresponding to the bolting positions of the flanges, and a spacer sandwiched between the two partition plates to form a gap between the two partition plates, and the gap A fluid conduction blocking method for piping, comprising a discharge passage for discharging the fluid flowing into the pipe to the outside of the piping.

[2]前記スペーサーが、少なくとも一方の仕切板に接合されていることを特徴とする前記[1]に記載の配管の流体導通遮断方法。   [2] The fluid conduction cutoff method for piping according to [1], wherein the spacer is joined to at least one partition plate.

[3]前記スペーサーが、前記仕切板に設けられた前記ボルト留め用のボルト孔に近接して設けられていることを特徴とする前記[1]または[2]に記載の配管の流体導通遮断方法。   [3] The fluid conduction cutoff of the pipe according to [1] or [2], wherein the spacer is provided in the vicinity of the bolt hole for bolting provided in the partition plate. Method.

[4]前記スペーサーが、前記仕切板と同心のリング形状であり、前記放出流路として、リング形状の内側から外側に貫通した切り込みを有していることを特徴とする前記[1]〜[3]のいずれかに記載の配管の流体導通遮断方法。   [4] The above [1] to [1], wherein the spacer has a ring shape concentric with the partition plate, and has a notch penetrating from the inside to the outside of the ring shape as the discharge channel. 3] The fluid conduction cutoff method for piping according to any one of [3].

[5]内部を流体が導通している配管のフランジ接続部に挿入して、流体の導通を遮断するための仕切板治具であって、フランジのボルト留め位置に対応するボルト孔を有する2枚の仕切板と、当該2枚の仕切板の間に空隙を形成するために、当該2枚の仕切板の間に挟まれたスペーサーを有するとともに、前記空隙に流入した流体を配管外に放出するための放出流路を備えていることを特徴とする仕切板治具。   [5] A partition plate jig for inserting the inside into a flange connection portion of a pipe through which fluid is conducted to cut off the fluid conduction, and having a bolt hole corresponding to the bolting position of the flange 2 In order to form a gap between the two partition plates and the two partition plates, the spacer has a spacer sandwiched between the two partition plates, and discharge for discharging the fluid flowing into the gap to the outside of the pipe A partition plate jig comprising a flow path.

[6]前記スペーサーが、少なくとも一方の仕切板に接合されていることを特徴とする前記[5]に記載の仕切板治具。   [6] The partition plate jig according to [5], wherein the spacer is joined to at least one partition plate.

[7]前記スペーサーが、前記仕切板に設けられた前記ボルト留め用のボルト孔に近接して設けられていることを特徴とする前記[5]または[6]に記載の仕切板治具。   [7] The partition plate jig according to [5] or [6], wherein the spacer is provided in the vicinity of the bolt hole for bolting provided in the partition plate.

[8]前記スペーサーが、前記仕切板と同心のリング形状であり、前記放出流路として、リング形状の内側から外側に貫通した切り込みを有していることを特徴とする前記[5]〜[7]のいずれかに記載の仕切板治具。   [8] The above [5] to [5], wherein the spacer has a ring shape concentric with the partition plate, and has a notch penetrating from the inside to the outside of the ring shape as the discharge channel. 7] The partition plate jig according to any one of the above.

本発明においては、内部を流体が導通している配管の工事を行うに際して、工事施工部側配管に流体が流入しないように、簡便かつ安価で的確に流体の導通を遮断することができる。   In the present invention, when performing construction of a pipe through which fluid is conducted, the fluid conduction can be cut off simply, inexpensively and accurately so that the fluid does not flow into the construction section side pipe.

すなわち、本発明においては、配管のフランジ接続部に挿入する仕切板治具が、2枚の仕切板を有するとともに、当該2枚の仕切板の間に形成された空隙に流入した流体を配管外に放出するための放出流路を備えており、1枚の仕切板から流体が漏洩したとしても、前記空隙から放出流路を経由して配管外に放出されるので、的確に流体の導通を遮断することができる。しかも、配管の1個所での設置加工で済むため、簡便かつ安価に実施することができる。   That is, in the present invention, the partition plate jig to be inserted into the flange connection portion of the pipe has two partition plates, and discharges the fluid that has flowed into the gap formed between the two partition plates to the outside of the pipe. Even if the fluid leaks from one partition plate, the fluid is discharged from the gap via the discharge channel to the outside of the pipe. be able to. In addition, since installation processing at one place of the piping is sufficient, it can be carried out simply and inexpensively.

本発明の実施形態1を示す縦断面図である。It is a longitudinal cross-sectional view which shows Embodiment 1 of this invention. 図1のA−A矢視図である。It is an AA arrow line view of FIG. 本発明の実施形態2を示す図である(図2に対応)。It is a figure which shows Embodiment 2 of this invention (corresponding to FIG. 2). 本発明の実施形態3を示す図である(図2に対応)。It is a figure which shows Embodiment 3 of this invention (corresponding to FIG. 2). 従来技術を示す図である。It is a figure which shows a prior art.

本発明の実施形態(実施形態1〜3)を図面に基づいて説明する。   Embodiments (Embodiments 1 to 3) of the present invention will be described with reference to the drawings.

[実施形態1]
図1は、本発明の実施形態1を示す縦断面図であり、図2は、図1のA−A矢視図である。
[Embodiment 1]
FIG. 1 is a longitudinal sectional view showing Embodiment 1 of the present invention, and FIG. 2 is a view taken along arrow AA of FIG.

図1、図2に示すように、本発明の実施形態1においては、内部を流体(例えば、高炉ガス、コークス炉ガスなどの燃料ガス)が導通している配管の工事を行うに際して、工事施工部21側の配管4aに流体導通部22側の配管4bから流体が流入しないようするために、工事施工部21側のフランジ1aと流体導通部22側のフランジ1bの間に仕切板治具2を挿入して、フランジ1a、1bごとボルト7とナット8で留めることにより、流体の導通を遮断するようにしている。   As shown in FIG. 1 and FIG. 2, in the first embodiment of the present invention, the construction work is performed when the piping in which fluid (for example, fuel gas such as blast furnace gas or coke oven gas) is conducted is conducted. In order to prevent fluid from flowing into the pipe 4a on the part 21 side from the pipe 4b on the fluid conduction part 22 side, the partition plate jig 2 is provided between the flange 1a on the construction work part 21 side and the flange 1b on the fluid conduction part 22 side. Is inserted, and the flanges 1a and 1b are fastened together with bolts 7 and nuts 8 so as to cut off the fluid conduction.

そして、前記仕切板治具2は、フランジ1a、1bのボルト留め位置に対応するボルト孔9を有する2枚の仕切板(工事施工部21側の仕切板2a、流体導通部22側の仕切板2b)と、その2枚の仕切板2a、2bの間に空隙6を形成するために、当該2枚の仕切板2a、2bの間に挟まれたスペーサー3(3A)を有している。   The partition plate jig 2 includes two partition plates having a bolt hole 9 corresponding to the bolting positions of the flanges 1a and 1b (the partition plate 2a on the construction work portion 21 side and the partition plate on the fluid conduction portion 22 side). 2b) and a spacer 3 (3A) sandwiched between the two partition plates 2a and 2b in order to form a gap 6 between the two partition plates 2a and 2b.

ここで、仕切板2a、2bの外形は円形であり、外径はフランジ1a、1bの外径にほぼ等しくなっている。また、仕切板2bの厚さは、流体の最高使用圧力に耐える厚さが望ましい。一方、仕切板2aの厚さは、仕切板2bと同じである必要はない。なお、仕切板2a、2bには、ハンドリング用の突起15を設けてもよい。   Here, the outer shape of the partition plates 2a and 2b is circular, and the outer diameter is substantially equal to the outer diameter of the flanges 1a and 1b. Further, the thickness of the partition plate 2b is desirably a thickness that can withstand the maximum working pressure of the fluid. On the other hand, the thickness of the partition plate 2a is not necessarily the same as that of the partition plate 2b. In addition, you may provide the processus | protrusion 15 for the partition plates 2a and 2b.

そして、この実施形態1におけるスペーサー3Aは、仕切板2a、2bに設けられたボルト留め用のボルト孔9に近接して設けられていて、1個のボルト孔9に対応して1個のスペーサー3Aが配置されており、それぞれのスペーサー3Aは、ボルト孔9に重なるようにボルト孔10を有している。スペーサー3Aの厚さは、仕切板2aと仕切板2bが接触しない厚さとしている。フランジ1a、1bの間隔は配管目的に応じて予め定められていることが多いので、仕切板2a、2bおよびスペーサー3Aの合計厚みが当該間隔に大体一致するよう設計するのが好ましい。   The spacer 3A in the first embodiment is provided in the vicinity of the bolt holes 9 for fastening the bolts provided in the partition plates 2a and 2b, and one spacer corresponding to one bolt hole 9 is provided. 3A is arranged, and each spacer 3A has a bolt hole 10 so as to overlap the bolt hole 9. The thickness of the spacer 3A is set so that the partition plate 2a and the partition plate 2b do not contact each other. Since the interval between the flanges 1a and 1b is often determined in advance according to the purpose of the piping, it is preferable to design the total thickness of the partition plates 2a and 2b and the spacer 3A to substantially match the interval.

加えて、隣接するスペーサー3A、3Aの間には、隙間11が設けられており、この隙間11が、空隙6に流入した流体を配管4a、4b外に放出するための放出流路14となっている。   In addition, a gap 11 is provided between the adjacent spacers 3A and 3A. The gap 11 serves as a discharge flow path 14 for discharging the fluid flowing into the gap 6 out of the pipes 4a and 4b. ing.

また、スペーサー3Aは、少なくとも仕切板2a、2bのいずれか一方に溶接してもよい。これによって、仕切板治具2をフランジ1a、1bの間に設置する作業が一層簡便になる。   The spacer 3A may be welded to at least one of the partition plates 2a and 2b. This further simplifies the operation of installing the partition plate jig 2 between the flanges 1a and 1b.

ただし、スペーサー3Aを仕切板2a、2bに溶接せずに、仕切板2a、2bと揃えてフランジ1a、1b間に挿入し、ボルト留めするだけにしてもよい。これによって、仕切板2a、2bとスペーサー3Aの組み合わせを自在に変更して、フランジ1a、1bの間の隙間に合わせることができる。   However, instead of welding the spacer 3A to the partition plates 2a and 2b, the spacer 3A may be aligned with the partition plates 2a and 2b and inserted between the flanges 1a and 1b and bolted. Thereby, the combination of the partition plates 2a and 2b and the spacer 3A can be freely changed to match the gap between the flanges 1a and 1b.

さらに、スペーサー3Aとして、ボルト締め用のワッシャーを流用してもよい。これによって、既存の部材を活用することができる。   Further, a bolt washer may be used as the spacer 3A. As a result, existing members can be utilized.

なお、ここでは、スペーサー3Aの外形は円形になっているが、他の形状でもよい。   Here, the outer shape of the spacer 3A is circular, but may be other shapes.

また、ここでは、フランジ1aと仕切板2aの間と、フランジ1bと仕切板2bの間に、それぞれパッキン5aとパッキン5bが取り付けられているが、工事施工部21が空気雰囲気である場合には、パッキン5aは無くともよい。   Here, packing 5a and packing 5b are attached between the flange 1a and the partition plate 2a and between the flange 1b and the partition plate 2b, respectively, but when the construction work part 21 is in an air atmosphere. The packing 5a may not be provided.

このようにして、本発明の実施形態1においては、配管(工事施工部側配管4a、流体導通部側配管4b)のフランジ接続部(工事施工部側フランジ1a、流体導通部側フランジ1b)に挿入する仕切板治具2が、2枚の仕切板(工事施工部側仕切板2a、流体導通部側仕切板2b)を有するとともに、当該2枚の仕切板2a、2bの間に形成された空隙6に流入した流体を配管4a、4b外に放出するための放出流路14を備えており、図2に漏洩個所19として示したように、流体導通部側仕切板2bから流体が漏洩したとしても、空隙6から放出流路14を経由して配管4a、4b外に放出されるので、的確に流体の導通を遮断することができる。しかも、配管の1個所での設置加工で済むため、簡便かつ安価に実施することができる。   Thus, in Embodiment 1 of the present invention, the flange connection part (the construction part side flange 1a, the fluid conduction part side flange 1b) of the pipe (the construction part side pipe 4a, the fluid conduction part side pipe 4b) is used. The partition plate jig 2 to be inserted has two partition plates (the construction portion side partition plate 2a and the fluid conduction portion side partition plate 2b) and is formed between the two partition plates 2a and 2b. A discharge flow path 14 is provided for discharging the fluid that has flowed into the gap 6 to the outside of the pipes 4a and 4b. As shown as the leak point 19 in FIG. 2, the fluid leaks from the fluid conduction part side partition plate 2b. Even so, since the fluid is discharged from the gap 6 to the outside of the pipes 4a and 4b via the discharge channel 14, the fluid conduction can be accurately cut off. In addition, since installation processing at one place of the piping is sufficient, it can be carried out simply and inexpensively.

[実施形態2]
本発明の実施形態2は、基本的には上記の実施形態1と同じ構成であるが、スペーサー3の形状と配置が異なっている。
[Embodiment 2]
Embodiment 2 of the present invention basically has the same configuration as that of Embodiment 1 described above, but the shape and arrangement of the spacer 3 are different.

図3は、本発明の実施形態2を示すものであり、実施形態1における図2(図1のA−A矢視図)に対応している。   FIG. 3 shows Embodiment 2 of the present invention, and corresponds to FIG. 2 in Embodiment 1 (a view taken along the line AA in FIG. 1).

図3に示すように、この実施形態2におけるスペーサー3(3B)は、仕切板2a、2bに設けられたボルト留め用のボルト孔9に近接して設けられていて、仕切板2a、2bと同心で仕切板2a、2bの外径とほぼ同じ外径を有するリング形状であり、仕切板2a、2bのボルト孔9に重なるようにボルト孔10を有している。   As shown in FIG. 3, the spacer 3 (3B) in the second embodiment is provided in the vicinity of the bolt holes 9 for bolting provided in the partition plates 2a and 2b, and the partition plates 2a and 2b The ring shape is concentric and has an outer diameter substantially the same as the outer diameter of the partition plates 2a and 2b, and has bolt holes 10 so as to overlap the bolt holes 9 of the partition plates 2a and 2b.

そして、スペーサー3Bは、少なくとも一個所に、リング形状の内側から外側に貫通した切り込み(溝、穴)12が設けられており、この切り込み12が、空隙6に流入した流体を配管4a、4b外に放出するための放出流路14となっている。   The spacer 3B is provided with at least one notch (groove, hole) 12 penetrating from the inside to the outside of the ring shape at least at one place, and this notch 12 allows the fluid flowing into the gap 6 to flow outside the pipes 4a and 4b. It becomes the discharge flow path 14 for discharge | emission to.

なお、切り込み12はスペーサー3Bの全厚を切り欠いたものである必要は無く、流体がリング形状の内側から外側に流れ出る大きさであればよい。   Note that the notch 12 does not have to be cut out of the entire thickness of the spacer 3B, and may have a size that allows fluid to flow from the inside to the outside of the ring shape.

このようにして、本発明の実施形態2においては、配管(工事施工部側配管4a、流体導通部側配管4b)のフランジ接続部(工事施工部側フランジ1a、流体導通部側フランジ1b)に挿入する仕切板治具2が、2枚の仕切板(工事施工部側仕切板2a、流体導通部側仕切板2b)を有するとともに、当該2枚の仕切板2a、2bの間に形成された空隙6に流入した流体を配管4a、4b外に放出するための放出流路14を備えており、図3に漏洩個所19として示したように、流体導通部側仕切板2bから流体が漏洩したとしても、空隙6から放出流路14を経由して配管4a、4b外に放出されるので、的確に流体の導通を遮断することができる。しかも、配管の1個所での設置加工で済むため、簡便かつ安価に実施することができる。   Thus, in Embodiment 2 of the present invention, the flange connection part (the construction part side flange 1a, the fluid conduction part side flange 1b) of the pipe (the construction part side pipe 4a, the fluid conduction part side pipe 4b) is used. The partition plate jig 2 to be inserted has two partition plates (the construction portion side partition plate 2a and the fluid conduction portion side partition plate 2b) and is formed between the two partition plates 2a and 2b. A discharge passage 14 is provided for discharging the fluid that has flowed into the gap 6 to the outside of the pipes 4a and 4b, and as shown as the leakage portion 19 in FIG. 3, the fluid leaks from the fluid conduction part side partition plate 2b. Even so, since the fluid is discharged from the gap 6 to the outside of the pipes 4a and 4b via the discharge channel 14, the fluid conduction can be accurately cut off. In addition, since installation processing at one place of the piping is sufficient, it can be carried out simply and inexpensively.

スペーサー3Bはリングを2〜数箇所で切断して得られる円弧形状としてもよい。   The spacer 3B may have an arc shape obtained by cutting the ring at two to several places.

この実施形態2のスペーサー3Bは、1個あるいはせいぜい数個で済むので、仕切板2aおよび/または仕切板2bに接合しなくてもフランジ1a、1bの間に設置しやすい利点がある。   Since only one spacer or only a few spacers 3B of Embodiment 2 are required, there is an advantage that the spacers 3B can be easily installed between the flanges 1a and 1b without being joined to the partition plate 2a and / or the partition plate 2b.

[実施形態3]
本発明の実施形態3は、基本的には上記の実施形態1、2と同じ構成であるが、スペーサー3の形状と配置が異なっている。
[Embodiment 3]
The third embodiment of the present invention basically has the same configuration as the first and second embodiments, but the shape and arrangement of the spacer 3 are different.

図4は、本発明の実施形態3を示すものであり、実施形態1における図2(図1のA−A矢視図)に対応している。   FIG. 4 shows a third embodiment of the present invention, and corresponds to FIG. 2 (a view taken along the line AA in FIG. 1) in the first embodiment.

図4に示すように、この実施形態3におけるスペーサー3(3C)は、仕切板2a、2bに設けられたボルト留め用のボルト孔9に近接して設けられていて、隣接するボルト孔9、9の間に1個ずつ配置されている。   As shown in FIG. 4, the spacer 3 (3C) in the third embodiment is provided in the vicinity of the bolt holes 9 for bolting provided in the partition plates 2a and 2b, and the adjacent bolt holes 9, One is arranged between 9.

そして、ボルト孔9とスペーサー3Cとの間には、隙間13が設けられており、この隙間13が、空隙6に流入した流体を配管4a、4b外に放出するための放出流路14となっている。   A gap 13 is provided between the bolt hole 9 and the spacer 3C. The gap 13 serves as a discharge flow path 14 for discharging the fluid flowing into the gap 6 to the outside of the pipes 4a and 4b. ing.

このようにして、本発明の実施形態3においては、配管(工事施工部側配管4a、流体導通部側配管4b)のフランジ接続部(工事施工部側フランジ1a、流体導通部側フランジ1b)に挿入する仕切板治具2が、2枚の仕切板(工事施工部側仕切板2a、流体導通部側仕切板2b)を有するとともに、当該2枚の仕切板2a、2bの間に形成された空隙6に流入した流体を配管4a、4b外に放出するための放出流路14を備えており、図4に漏洩個所19として示したように、流体導通部側仕切板2bから流体が漏洩したとしても、空隙6から放出流路14を経由して配管4a、4b外に放出されるので、的確に流体の導通を遮断することができる。しかも、配管の1個所での設置加工で済むため、簡便かつ安価に実施することができる。   In this way, in Embodiment 3 of the present invention, the flange connection part (the construction part side flange 1a, the fluid conduction part side flange 1b) of the pipe (the construction part side pipe 4a, the fluid conduction part side pipe 4b) is used. The partition plate jig 2 to be inserted has two partition plates (the construction portion side partition plate 2a and the fluid conduction portion side partition plate 2b) and is formed between the two partition plates 2a and 2b. A discharge flow path 14 is provided for discharging the fluid that has flowed into the gap 6 to the outside of the pipes 4a and 4b, and as shown as the leak point 19 in FIG. 4, the fluid leaked from the fluid conduction part side partition plate 2b. Even so, since the fluid is discharged from the gap 6 to the outside of the pipes 4a and 4b via the discharge channel 14, the fluid conduction can be accurately cut off. In addition, since installation processing at one place of the piping is sufficient, it can be carried out simply and inexpensively.

図4においてはスペーサー3Cが全てのボルト孔9の間に設けられているが、1つおきに配置するなど、適宜スペーサー3Cを間引いてもよい。   In FIG. 4, the spacers 3 </ b> C are provided between all the bolt holes 9, but the spacers 3 </ b> C may be thinned out as appropriate, such as arranging every other spacer.

本発明の実施例(本発明例)として、内部を流体(燃料ガス:高炉ガス、コークス炉ガスなど)が導通している配管の工事を行うに際して、上述した本発明の実施形態1〜3のそれぞれに基づいて、配管内の流体(燃料ガス)の導通を遮断した。   As an example of the present invention (example of the present invention), when performing construction of piping in which fluid (fuel gas: blast furnace gas, coke oven gas, etc.) is conducted, Based on each, conduction | electrical_connection of the fluid (fuel gas) in piping was interrupted | blocked.

その際に、各部の諸元は以下のようにした。   At that time, the specifications of each part were as follows.

(本発明例1)
工事施工部側フランジと流体導通部側フランジとの間の隙間:約36.5mm
フランジ部の外径および内径:それぞれ1645mm、1400mm
フランジ部のボルト穴:PCD1535mm、個数36個、直径33mm
工事施工側の仕切板の厚み:約6mm
流体導通側の仕切板の厚み:約16mm
パッキンの厚み:約5mm
スペーサーの厚み:約4.5mm
スペーサーの平面形状:M30の丸平座金
実施形態1対応・・・内径31.5mmφ、外径58mmφのワッシャー形
(各ボルト穴に配置し、仕切板2aまたは2bに溶接)
実施形態2対応・・・内径1400mmφ、外径1645mmφのリング形
(幅40mmの切込みを1箇所設け、仕切板には接合せず。
なお、仕切板に接合してもよい)
(フランジと同じ位置にボルト穴が設けられている)
実施形態3対応・・・65mm×100mmの長方形
(各ボルト穴間に配置し、仕切板2aまたは2bに溶接)
(Invention Example 1)
Gap between the construction work side flange and the fluid conduction part side flange: about 36.5 mm
Outer diameter and inner diameter of the flange: 1645 mm and 1400 mm, respectively
Bolt hole in flange: PCD 1535mm, 36 pieces, diameter 33mm
Construction side partition plate thickness: approx. 6mm
The thickness of the partition plate on the fluid conduction side: about 16mm
Packing thickness: about 5mm
Spacer thickness: about 4.5mm
Planar shape of spacer: Round flat washer of M30 Corresponding to Embodiment 1 ... Washer type with inner diameter of 31.5 mmφ and outer diameter of 58 mmφ
(Disposed in each bolt hole and welded to the partition plate 2a or 2b)
Corresponding to Embodiment 2 ... Ring shape with inner diameter of 1400mmφ and outer diameter of 1645mmφ
(One cut with a width of 40 mm is provided and not joined to the partition plate.
(It may be joined to the partition plate)
(A bolt hole is provided at the same position as the flange)
Corresponding to Embodiment 3 ... 65 mm x 100 mm rectangle
(Disposed between each bolt hole and welded to the partition plate 2a or 2b)

(本発明例2)
工事施工部側フランジと流体導通部側フランジとの間の隙間:約45.5mm
フランジ部の外径および内径:それぞれ2405mm、2200mm
フランジ部のボルト穴:PCD2310mm、個数52個、直径35mm
工事施工側の仕切板の厚み:約6mm
流体導通側の仕切板の厚み:約19mm
パッキンの厚み:約8mm
スペーサーの厚み:約4.5mm
実施形態1対応・・・内径31.5mmφ、外径58mmφのワッシャー形
(各ボルト穴に配置し、仕切板2bに溶接)
実施形態2対応・・・内径2200mmφ、外径2405mmφのリング形
(幅45mm、深さ4mm溝みを5箇所設け、
仕切板には接合せず。なお、仕切板に接合してもよい)
(フランジと同じ位置にボルト穴が設けられている)
実施形態3対応・・・100mm×50mmの長方形
(各ボルト穴間に配置)
(Invention Example 2)
Gap between the construction work part side flange and the fluid conduction part side flange: about 45.5 mm
Outer diameter and inner diameter of flange part: 2405 mm and 2200 mm, respectively
Bolt hole in flange: PCD 2310mm, 52 pieces, diameter 35mm
Construction side partition plate thickness: approx. 6mm
The thickness of the partition plate on the fluid conduction side: about 19mm
Packing thickness: about 8mm
Spacer thickness: about 4.5mm
Corresponding to Embodiment 1 ... Washer type with inner diameter of 31.5 mmφ and outer diameter of 58 mmφ
(Disposed in each bolt hole and welded to the partition plate 2b)
Corresponding to the second embodiment: a ring shape with an inner diameter of 2200 mmφ and an outer diameter of 2405 mmφ
(Wave 45mm, depth 4mm 5 grooves are provided,
Do not join the partition plate. (It may be joined to the partition plate)
(A bolt hole is provided at the same position as the flange)
Corresponding to Embodiment 3 ... Rectangle of 100 mm x 50 mm
(Arranged between each bolt hole)

その結果、いずれの場合でも、流体導通部側配管の燃料ガスが工事施工部側配管に流入することはなく、簡便かつ安価で的確に燃料ガスの導通を遮断することができた。   As a result, in any case, the fuel gas in the fluid conduction portion side piping did not flow into the construction portion side piping, and the conduction of the fuel gas could be cut off accurately simply and inexpensively.

1a 工事施工部側フランジ
1b 流体導通部側フランジ
1c 緩衝部フランジ
1d 緩衝部フランジ
2 仕切板治具
2a 工事施工部側仕切板
2b 流体導通部側仕切板
3 スペーサー
3A スペーサー
3B スペーサー
3C スペーサー
4a 工事施工部側配管
4b 流体導通部側配管
4c 緩衝部配管
5a 工事施工部側パッキン
5b 流体導通部側パッキン
6 空隙
7 ボルト
8 ナット
9 仕切板のボルト孔
10 スペーサーのボルト孔
11 隙間
12 切り込み
13 隙間
14 放出流路
15 ハンドリング用突起
19 漏洩個所
21 工事施工部
22 流体導通部
23 緩衝部
31 仕切板
32 ボルト
33 ナット
34 仕切板
35 ボルト
36 ナット
37 バルーン
38 仕切弁
1a Construction work part side flange 1b Fluid conduction part side flange 1c Buffer part flange 1d Buffer part flange 2 Partition plate jig 2a Construction work part side partition plate 2b Fluid conduction part side partition plate 3 Spacer 3A Spacer 3B Spacer 3C Spacer 4a Construction work Part side piping 4b Fluid conduction part side piping 4c Buffer part piping 5a Construction work part side packing 5b Fluid conduction part side packing 6 Gap 7 Bolt 8 Nut 9 Bolt hole of spacer 10 Spacer bolt hole 11 Gap 12 Notch 13 Gap 14 Release Flow path 15 Protrusion for handling 19 Leakage location 21 Construction work section 22 Fluid conducting section 23 Buffer section 31 Partition plate 32 Bolt 33 Nut 34 Partition plate 35 Bolt 36 Nut 37 Balloon 38 Gate valve

Claims (8)

内部を流体が導通している配管のフランジ接続部に仕切板治具を挿入してフランジごとボルト留めすることにより流体の導通を遮断する方法であって、前記仕切板治具は、フランジのボルト留め位置に対応するボルト孔を有する2枚の仕切板と、当該2枚の仕切板の間に空隙を形成するために、当該2枚の仕切板の間に挟まれたスペーサーを有するとともに、前記空隙に流入した流体を配管外に放出するための放出流路を備えていることを特徴とする配管の流体導通遮断方法。   It is a method of cutting off fluid conduction by inserting a partition plate jig into a flange connection portion of a pipe through which fluid is internally connected and bolting together with the flange, and the partition plate jig is a flange bolt In order to form a gap between the two partition plates having bolt holes corresponding to the fastening positions and the two partition plates, the spacer has a spacer sandwiched between the two partition plates and flows into the gap. A fluid conduction blocking method for piping, comprising a discharge channel for discharging fluid out of the piping. 前記スペーサーが、少なくとも一方の仕切板に接合されていることを特徴とする請求項1に記載の配管の流体導通遮断方法。   The method of claim 1, wherein the spacer is joined to at least one partition plate. 前記スペーサーが、前記仕切板に設けられた前記ボルト留め用のボルト孔に近接して設けられていることを特徴とする請求項1または2に記載の配管の流体導通遮断方法。   3. The fluid conduction blocking method for piping according to claim 1 or 2, wherein the spacer is provided in the vicinity of the bolt hole for bolting provided in the partition plate. 前記スペーサーが、前記仕切板と同心のリング形状であり、前記放出流路として、リング形状の内側から外側に貫通した切り込みを有していることを特徴とする請求項1〜3のいずれかに記載の配管の流体導通遮断方法。   The said spacer is a ring shape concentric with the said partition plate, It has the notch penetrated from the inner side of the ring shape to the outer side as the said discharge flow path. The fluid conduction blocking method for the pipe described. 内部を流体が導通している配管のフランジ接続部に挿入して、流体の導通を遮断するための仕切板治具であって、フランジのボルト留め位置に対応するボルト孔を有する2枚の仕切板と、当該2枚の仕切板の間に空隙を形成するために、当該2枚の仕切板の間に挟まれたスペーサーを有するとともに、前記空隙に流入した流体を配管外に放出するための放出流路を備えていることを特徴とする仕切板治具。   A partition plate jig for inserting the inside into a flange connection portion of a pipe through which fluid is conducted to cut off fluid conduction, and having two bolt holes having bolt holes corresponding to the bolting positions of the flange In order to form a gap between the plate and the two partition plates, there is a spacer sandwiched between the two partition plates, and a discharge channel for discharging the fluid flowing into the gap to the outside of the pipe A partition plate jig characterized by comprising: 前記スペーサーが、少なくとも一方の仕切板に接合されていることを特徴とする請求項5に記載の仕切板治具。   The partition plate jig according to claim 5, wherein the spacer is joined to at least one partition plate. 前記スペーサーが、前記仕切板に設けられた前記ボルト留め用のボルト孔に近接して設けられていることを特徴とする請求項5または6に記載の仕切板治具。   The partition plate jig according to claim 5 or 6, wherein the spacer is provided in the vicinity of the bolt hole for bolting provided in the partition plate. 前記スペーサーが、前記仕切板と同心のリング形状であり、前記放出流路として、リング形状の内側から外側に貫通した切り込みを有していることを特徴とする請求項5〜7のいずれかに記載の仕切板治具。   8. The spacer according to claim 5, wherein the spacer has a ring shape concentric with the partition plate, and has a notch penetrating from the inside to the outside of the ring shape as the discharge channel. The partition plate jig of description.
JP2014004740A 2014-01-15 2014-01-15 Fluid conduction blocking method of pipe Pending JP2015132345A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014004740A JP2015132345A (en) 2014-01-15 2014-01-15 Fluid conduction blocking method of pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014004740A JP2015132345A (en) 2014-01-15 2014-01-15 Fluid conduction blocking method of pipe

Publications (1)

Publication Number Publication Date
JP2015132345A true JP2015132345A (en) 2015-07-23

Family

ID=53899698

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014004740A Pending JP2015132345A (en) 2014-01-15 2014-01-15 Fluid conduction blocking method of pipe

Country Status (1)

Country Link
JP (1) JP2015132345A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431906A (en) * 2021-08-26 2021-09-24 启东市永安阀门有限公司 Valve easy to assemble
CN113431955A (en) * 2021-08-26 2021-09-24 启东市永安阀门有限公司 Protection valve at gas pipeline terminal

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2726683A (en) * 1951-08-30 1955-12-13 Standard Oil Co Pipe blind with failure indicator
GB854542A (en) * 1958-02-26 1960-11-23 Stewarts & Lloyds Ltd Improvements relating to plate valves or goggle valves
JPS55104162U (en) * 1979-01-18 1980-07-21
JPS584892U (en) * 1981-07-02 1983-01-12 川崎製鉄株式会社 blind board
KR100739340B1 (en) * 2006-01-27 2007-07-24 김태조 Glasses type pipe opening / closing separator

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2726683A (en) * 1951-08-30 1955-12-13 Standard Oil Co Pipe blind with failure indicator
GB854542A (en) * 1958-02-26 1960-11-23 Stewarts & Lloyds Ltd Improvements relating to plate valves or goggle valves
JPS55104162U (en) * 1979-01-18 1980-07-21
JPS584892U (en) * 1981-07-02 1983-01-12 川崎製鉄株式会社 blind board
KR100739340B1 (en) * 2006-01-27 2007-07-24 김태조 Glasses type pipe opening / closing separator

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431906A (en) * 2021-08-26 2021-09-24 启东市永安阀门有限公司 Valve easy to assemble
CN113431955A (en) * 2021-08-26 2021-09-24 启东市永安阀门有限公司 Protection valve at gas pipeline terminal
CN113431955B (en) * 2021-08-26 2021-11-09 启东市永安阀门有限公司 Protection valve at gas pipeline terminal

Similar Documents

Publication Publication Date Title
ES2444426T3 (en) Insulation joint, manufacturing system and procedure
US8636035B2 (en) Dual inflatable plug assembly
US20100186484A1 (en) Apparatus and Method for Isolating or Testing a Pipe Segment with Axial Reinforcement
KR200399091Y1 (en) Fitting for intercepting fluid flow in the pipe
JP2015132345A (en) Fluid conduction blocking method of pipe
CN104697722A (en) Pipeline air tightness detection device
AU2018399234A1 (en) Pipe coupling capsulation assembly with retaining elements
JP2010286320A (en) High pressure pipe closing jig
CN203115384U (en) Water supply and drainage pipeline leakage on-line processing device
CN108379761B (en) Damping flame arrester
CN104121449B (en) A kind of pipe pressurized blocking device and method for blocking
US5582211A (en) Purging blind
CN204704541U (en) A kind of pipe connection sealer
JP4921919B2 (en) Existing pipe blocking method
KR102541108B1 (en) flange assembly
KR101951935B1 (en) Apparatus for repairing pipe
KR101342103B1 (en) Repair cover for connections of high-pressure hydraulic piping
JP6450632B2 (en) Corrosion prevention apparatus and corrosion prevention method for pipe cut surface
KR200477548Y1 (en) Silencer
CN216952248U (en) Anti-throwing limiting piece for axial tearing
JP2016020729A (en) Pipeline joint cover, fitting method of pipeline joint cover and fluid scattering prevention device of pipeline joint part
CN217503045U (en) Pressure relief device for internally inserting ground pipeline
JP6242681B2 (en) Leakage repair device and method of mounting the leak repair device
CN210398109U (en) Device for quickly and blindly cutting off power medium pipeline
JP2019178769A (en) Piping blocking jig and piping blocking method using the jig

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150825

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20160621

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160628

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20170104