JP2015094086A - Lining concrete construction method of shaft, and platform for shaft - Google Patents

Lining concrete construction method of shaft, and platform for shaft Download PDF

Info

Publication number
JP2015094086A
JP2015094086A JP2013232713A JP2013232713A JP2015094086A JP 2015094086 A JP2015094086 A JP 2015094086A JP 2013232713 A JP2013232713 A JP 2013232713A JP 2013232713 A JP2013232713 A JP 2013232713A JP 2015094086 A JP2015094086 A JP 2015094086A
Authority
JP
Japan
Prior art keywords
platform
shaft
bracket
work
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013232713A
Other languages
Japanese (ja)
Other versions
JP2015094086A5 (en
JP6204153B2 (en
Inventor
良光 中島
Yoshimitsu Nakajima
良光 中島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP2013232713A priority Critical patent/JP6204153B2/en
Publication of JP2015094086A publication Critical patent/JP2015094086A/en
Publication of JP2015094086A5 publication Critical patent/JP2015094086A5/ja
Application granted granted Critical
Publication of JP6204153B2 publication Critical patent/JP6204153B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To omit conventional large scale scaffold assembling work, at the time of placing a lining concrete in a shaft, to shorten a construction period and reduce a cost, and also to prevent falling from a high place and disaster due to flying objects.SOLUTION: An anchor is provided in a lining concrete 2 of a shaft 1. A bracket is attached to the anchor, and on the bracket, a platform 10 which covers the entire cross section in the shaft 1 is installed. On the platform 10, assembling work of a form for placing concrete which accompanies embedding of the anchor is performed, and then, concrete placing work is performed. After the concrete solidifies, dismounting work of the form is performed on the platform 10, and then, the platform 10 is lifted by a crane and stopped at a predetermined position. The bracket is attached to the anchor on the platform 10, and the platform 10 is installed on the bracket.

Description

本発明は、立坑のライニングコンクリートを施工する方法と、その施工方法の実施作業に用いる立坑用プラットフォームに関する。   The present invention relates to a method for constructing a lining concrete for a shaft, and a shaft for a shaft used for performing the construction method.

立坑において、ライニングコンクリートを施工する際、従来は足場を立坑の底から組み立て、その足場上で、鉄筋や型枠の組み立て、コンクリート打設などの作業を行っていた。   When constructing lining concrete in a shaft, conventionally, a scaffold is assembled from the bottom of the shaft, and rebars and formwork are assembled and concrete is placed on the scaffold.

また、主として大深度の地下に設けられる地下タンクなどの大型地下構造物を構築する際の岩盤掘削面に対して、コンクリート内面ライニングを施工する際、足場やコンクリート打設の型枠板を削減し、その費用の低減や工期の短縮を計り得るコンクリート内面ライニングの構築装置が特許文献1に提案される。
すなわち、特許文献1のコンクリート内面ライニングの構築装置は、ライニング板を取込み、かつ、ライニング板を型に接合させる接合作業用最上段ステージと、ライニング板を型枠板としてコンクリート打設時の打設圧を負担可能な中段ステージと、コンクリート打設完了後のライニング面の検査が可能な最下段ステージとからなるスライド足場を、掘削岩盤に対して上下移動可能に設けた構成である。
In addition, when constructing a concrete inner lining against a rock excavation surface when constructing a large underground structure such as an underground tank that is mainly installed in a deep underground, the number of scaffolding and formwork for placing concrete is reduced. Patent Document 1 proposes a construction apparatus for a concrete inner lining that can reduce the cost and shorten the construction period.
That is, the construction apparatus for a concrete inner surface lining disclosed in Patent Document 1 takes in a lining plate and joins the lining plate to a mold, and the upper stage for joining work, and placing the lining plate at the time of concrete placement using the lining plate as a formwork plate A slide scaffold comprising a middle stage capable of bearing pressure and a bottom stage capable of inspecting the lining surface after completion of concrete placement is provided so as to be movable up and down with respect to the excavated rock.

特開平9−316899号公報JP 9-316899 A

しかし、立坑が深い場合、足場の自重が大きくなり、補強が必要となる。
また、足場が高くなれば、落下事故、飛来事故などの災害が重大化する。
However, if the shaft is deep, the weight of the scaffold will increase and reinforcement will be required.
Moreover, if the scaffolding becomes high, disasters such as fall accidents and flying accidents will become serious.

本発明の課題は、立坑にライニングコンクリートを打設する際において、従来の大掛かりな足場組立作業を省略して、工期短縮と低コスト化を図るとともに、高所からの落下や飛来災害を防止することである。   The object of the present invention is to eliminate the conventional large-scale scaffold assembling work when placing lining concrete in a vertical shaft, to shorten the construction period and to reduce the cost, and to prevent a fall or flying disaster from a high place That is.

以上の課題を解決するため、請求項1に記載の発明は、
立坑のライニングコンクリートにアンカーを設けておき、
そのアンカーにブラケットを取り付け、
そのブラケットの上に、前記立坑内の全断面を覆うプラットフォームを設置して、
そのプラットフォーム上において、前記アンカーの埋設を伴う前記コンクリート打設用の型枠の組み立て作業を行ってから、前記コンクリートの打設作業を行う、立坑のライニングコンクリート施工方法を特徴とする。
In order to solve the above problems, the invention described in claim 1
An anchor is installed on the lining concrete of the shaft,
Attach the bracket to the anchor,
On that bracket, install a platform that covers the entire cross section in the shaft,
The lining concrete construction method for a shaft is characterized in that the concrete placing work is performed on the platform after the concrete placing form accompanied by the anchor is buried.

請求項2に記載の発明は、
請求項1に記載の立坑のライニングコンクリート施工方法であって、
コンクリート硬化後、前記プラットフォーム上において、前記型枠の取り外し作業を行ってから、
前記プラットフォームをクレーンにより上昇させて所定位置に停止し、
そのプラットフォームから前記アンカーに前記ブラケットを取り付けて、
そのブラケット上に前記プラットフォームを設置することを特徴とする。
The invention described in claim 2
It is the lining concrete construction method of the shaft according to claim 1,
After hardening the concrete, on the platform, after removing the formwork,
The platform is raised by a crane and stopped at a predetermined position,
Attach the bracket from the platform to the anchor,
The platform is installed on the bracket.

請求項3に記載の発明は、
請求項2に記載の立坑のライニングコンクリート施工方法であって、
前記プラットフォームの下に設けられる作業用籠において、前記アンカーに対する前記ブラケットの取付作業を行うことを特徴とする。
The invention according to claim 3
It is the lining concrete construction method of the shaft according to claim 2,
In the working rod provided under the platform, the bracket is attached to the anchor.

請求項4に記載の発明は、
請求項1から3のいずれか一項に記載の立坑のライニングコンクリート施工方法であって、
前記プラットフォームは、地上もしくは立坑内最下部で組み立てられて、クレーンにより最初の前記ブラケットの取付位置に移動して前記ブラケット上に設置されることを特徴とする。
The invention according to claim 4
It is the lining concrete construction method of the shaft according to any one of claims 1 to 3,
The platform is assembled on the ground or at the bottom of the shaft, moved to the first bracket mounting position by a crane, and installed on the bracket.

請求項5に記載の発明は、
請求項1から4のいずれか一項に記載の立坑のライニングコンクリート施工方法の実施作業に用いられ、
前記立坑内の全断面を覆う形状に骨材を組み付けられたフレームと、
前記フレーム上に張り付けられた床パネルと、を備える立坑用プラットフォームを特徴とする。
The invention described in claim 5
It is used for the implementation work of the lining concrete construction method of the shaft according to any one of claims 1 to 4,
A frame assembled with aggregates in a shape covering the entire cross section in the shaft,
A vertical shaft platform comprising a floor panel attached to the frame.

請求項6に記載の発明は、
請求項5に記載の立坑用プラットフォームであって、
前記床パネルは前記フレーム上の略中央部を除いて張り付けられ、
前記フレームの少なくとも前記略中央部にエキスパンドメタルが張り付けられていることを特徴とする。
The invention described in claim 6
The shaft platform according to claim 5,
The floor panel is pasted except for a substantially central portion on the frame,
An expanded metal is attached to at least the substantially central portion of the frame.

請求項7に記載の発明は、
請求項5または6に記載の立坑用プラットフォームであって、
前記フレーム下の周囲に作業用籠を備えることを特徴とする。
The invention described in claim 7
The shaft platform according to claim 5 or 6,
A work basket is provided around the frame.

請求項8に記載の発明は、
請求項7に記載の立坑用プラットフォームであって、
前記作業用籠上の前記床パネルに、作業員が出入りするための開閉蓋が設けられることを特徴とする。
The invention according to claim 8 provides:
A shaft platform according to claim 7,
An opening / closing lid for an operator to enter and exit is provided on the floor panel on the work basket.

請求項9に記載の発明は、
請求項8に記載の立坑用プラットフォームであって、
前記作業用籠に、前記開閉蓋を開けて降りるための階段が設けられることを特徴とする。
The invention according to claim 9 is:
A shaft platform according to claim 8,
The work basket is provided with a stairway for opening and closing the opening / closing lid.

本発明によれば、立坑にライニングコンクリートを打設する際において、従来の大掛かりな足場組立作業を省略して、工期短縮と低コスト化を達成できるとともに、高所からの落下や飛来災害を防止できる。   According to the present invention, when placing lining concrete in a vertical shaft, the conventional large-scale scaffold assembly work can be omitted, and the construction period can be shortened and the cost can be reduced. it can.

本発明を適用した立坑及びプラットフォームの一実施形態の構成を示すもので、立坑を縦断面で示してプラットフォームを降ろした状態を示した斜視図である。BRIEF DESCRIPTION OF THE DRAWINGS The structure of one Embodiment of the shaft and platform to which this invention is applied is shown, It is the perspective view which showed the state which showed the shaft in the longitudinal cross-section and lowered | hung the platform. 図1のプラットフォーム上に円周状に足場を設置した状態を示した拡大図である。It is the enlarged view which showed the state which installed the scaffold in the circumferential shape on the platform of FIG. 図2のプラットフォームのフレーム構成例を示す図である。It is a figure which shows the example of a flame | frame structure of the platform of FIG. 図3のフレーム上にエキスパンドメタルを張り付けた例を示す図である。It is a figure which shows the example which affixed the expanded metal on the flame | frame of FIG. 図4のエキスパンドメタル上に床パネルを張り付けた例を示す図である。It is a figure which shows the example which stuck the floor panel on the expanded metal of FIG. 図1の立坑内のブラケット上にプラットフォームを設置した状態を示す図である。It is a figure which shows the state which installed the platform on the bracket in the shaft of FIG. 図6のプラットフォーム下の作業用籠の詳細を示す斜視図である。It is a perspective view which shows the detail of the work basket under the platform of FIG. プラットフォームに設ける開閉蓋を示す斜視図である。It is a perspective view which shows the opening-and-closing lid | cover provided in a platform. 図1の立坑内に型枠を設置した状態を示す図である。It is a figure which shows the state which installed the formwork in the shaft of FIG. 図9の型枠設置状態の部分平面図である。FIG. 10 is a partial plan view of the mold installation state of FIG. 9.

以下、図を参照して本発明を実施するための形態を詳細に説明する。
(実施形態)
図1は本発明を適用した立坑及びプラットフォームの一実施形態の構成として立坑1を縦断面で示してプラットフォーム10を降ろした状態を斜視図で示したものである。
なお、立坑1の地上部には、図示しない門型クレーンが設置されていて、地上または立坑1内の最下部で組み立てられたプラットフォーム10が、門型クレーンにより地上から立坑1内の所定位置に下降、または立坑1内最下部から前記所定位置に上昇される。
DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments for carrying out the present invention will be described in detail with reference to the drawings.
(Embodiment)
FIG. 1 is a perspective view showing a state in which a vertical shaft 1 is shown in a vertical section and a platform 10 is lowered as a configuration of an embodiment of a vertical shaft and a platform to which the present invention is applied.
A portal crane (not shown) is installed on the ground portion of the vertical shaft 1, and the platform 10 assembled on the ground or in the lowermost portion of the vertical shaft 1 is moved from the ground to a predetermined position in the vertical shaft 1 by the portal crane. It descends or rises to the predetermined position from the bottom of the shaft 1.

プラットフォーム10は、例えば内径12mで深さ100m程度の立坑1において、その全断面を覆う円形状で、ライニングコンクリート2の打設用型枠の組み立て作業を行ってから、コンクリートの打設作業を行うためのもので、作業中の下方への飛来落下を完全に防止し、常にコンクリートの打設リフトとともに上昇し、一定の作業空間をキープするものである。
従って、従来の大掛かりな足場組立作業を省略して、工期短縮・低コスト化を達成できる。
For example, in the shaft 1 having an inner diameter of 12 m and a depth of about 100 m, the platform 10 has a circular shape that covers the entire cross section, and after the assembly work of the casting form of the lining concrete 2 is performed, the concrete is placed. Therefore, it is possible to completely prevent a downward drop during work, and it always rises with a concrete placing lift to keep a certain work space.
Therefore, the conventional large-scale scaffold assembly work can be omitted, and the construction period can be shortened and the cost can be reduced.

図2はプラットフォーム10上に円周状に足場20を設置した状態を示したものである。
このように、プラットフォーム10上に円周状に設置した足場20により、型枠作業を安全に実施する。
FIG. 2 shows a state where the scaffold 20 is installed on the platform 10 in a circumferential shape.
In this way, the formwork is safely performed by the scaffold 20 installed circumferentially on the platform 10.

プラットフォーム10は、フレーム11上にエキスパンドメタル12を介して床パネル13を張り付けたものである。
図示例では、フレーム11上の中央四角形を除いて床パネル13が張り付けられて、その中央四角形にエキスパンドメタル12が露出している。この中央四角形のエキスパンドメタル12が空気抜けとして機能する。
The platform 10 is obtained by attaching a floor panel 13 on a frame 11 via an expanded metal 12.
In the illustrated example, the floor panel 13 is pasted except for the central rectangle on the frame 11, and the expanded metal 12 is exposed in the central rectangle. This central square expanded metal 12 functions as an air vent.

すなわち、フレーム11は、図3に示すように、立坑1内の全断面を覆う円形状に骨材を組み付けて構成される。
このフレーム11上に、図4に示すように、エキスパンドメタル12が張り付けられる。
このエキスパンドメタル12上に、図5に示すように、中央四角形を除いて床パネル13が張り付けられる。
That is, as shown in FIG. 3, the frame 11 is configured by assembling aggregates in a circular shape covering the entire cross section in the shaft 1.
As shown in FIG. 4, the expanded metal 12 is pasted on the frame 11.
As shown in FIG. 5, the floor panel 13 is pasted on the expanded metal 12 except for the central square.

図6は立坑1のライニングコンクリート2から突出するブラケット5の上にプラットフォーム10を設置した状態を示すものである。
図示のように、ライニングコンクリート2には、ブラケット5を取付支持するための長いアンカー3と短いアンカー4が上下一対ずつで円周8箇所に埋設されている。
ここで、プラットフォーム10を載せるブラケット5の荷重モーメントと剪断力に対抗して、長いアンカー3が上方で短いアンカー4が下方に配置されている。
FIG. 6 shows a state in which the platform 10 is installed on the bracket 5 protruding from the lining concrete 2 of the shaft 1.
As shown in the figure, a long anchor 3 and a short anchor 4 for attaching and supporting the bracket 5 are embedded in the lining concrete 2 at eight positions on the circumference in pairs.
Here, the long anchor 3 is disposed above and the short anchor 4 is disposed below against the load moment and the shearing force of the bracket 5 on which the platform 10 is placed.

ブラケット5の取付作業は、プラットフォーム10の周囲下に備えられる作業用籠14から、ブラケット5を上下のアンカー3・4にそれぞれボルト結合して行う。   The mounting operation of the bracket 5 is performed by bolting the bracket 5 to the upper and lower anchors 3 and 4 from a work rod 14 provided below the periphery of the platform 10.

作業用籠14は、図7に示すように、フレーム11下の円周8箇所に骨材14aを組み付けてボックス状に構成されており、作業床14b、周囲の保護用の金網14c、作業員が昇降する階段14dが備えられている。   As shown in FIG. 7, the work cage 14 is formed in a box shape by assembling aggregates 14 a at eight places around the circumference of the frame 11, and includes a work floor 14 b, a surrounding protective wire mesh 14 c, and a worker 14d is provided to move up and down.

そして、作業用籠14の上方のプラットフォーム10の床パネル13には、図8に示すように、作業員が出入りするための開閉蓋15が設けられる。   The floor panel 13 of the platform 10 above the work bar 14 is provided with an open / close lid 15 for an operator to enter and exit, as shown in FIG.

ところで、プラットフォーム10は、クレーンを使って上下動するため、ライニングコンクリート2の内径に対して僅かに小さく外径が形成されていることから、ライニングコンクリート2とプラットフォーム10との間には5cm程度の隙間が形成されている。
このため、その隙間からの物の落下を防ぐために、図8に示すように、ライニングコンクリート2とプラットフォーム10との隙間を設置撤去可能な隙間塞ぎ部材16で塞ぐことにより、落下物の発生を完全に防いでいる。
By the way, since the platform 10 moves up and down using a crane, an outer diameter is formed slightly smaller than the inner diameter of the lining concrete 2, so that the distance between the lining concrete 2 and the platform 10 is about 5 cm. A gap is formed.
For this reason, in order to prevent the fall of the object from the gap, as shown in FIG. 8, the gap between the lining concrete 2 and the platform 10 is closed with a gap closing member 16 that can be installed and removed, thereby completely preventing the fallen object from being generated. To prevent.

図9及び図10は立坑1内に型枠6を設置した状態を示すものである。
図示のように、型枠6の内面上部には、長いアンカー3と短いアンカー4が上下一対ずつで円周8箇所に備えられている。これら両アンカー3・4は型枠6に対し分離可能とされている。
9 and 10 show a state where the mold 6 is installed in the shaft 1.
As shown in the figure, a long anchor 3 and a short anchor 4 are provided on the inner surface of the mold 6 at eight positions on the circumference in pairs. Both anchors 3 and 4 are separable from the mold 6.

そして、型枠6は、H形鋼による横端太材7を介して更に大型のH形鋼による縦端太材8で固定される。
なお、長いアンカー3は、図示のように、縦端太材8の固定ボルト取付用としても兼用される。
And the formwork 6 is fixed with the vertical end thick material 8 made of a larger H-shaped steel through the horizontal end thick material 7 made of H-shaped steel.
In addition, the long anchor 3 is also used for fixing bolts for the vertical end thick member 8 as shown in the drawing.

以上の型枠6は円周8分割の大型のシステム型枠で、これにより、型枠6の組立・脱型作業が省力化される。   The above-mentioned mold 6 is a large system mold with a circumference of eight, and thereby, labor for assembling and removing the mold 6 is saved.

次に、立坑1のライニングコンクリート2の施工方法について手順を追って説明する。   Next, the construction method of the lining concrete 2 of the vertical shaft 1 will be described following the procedure.

1)立坑1のライニングコンクリート2に上下のアンカー3・4を設けておく(図6参照)。
この場合、立坑1の底部あるいは所定高さ位置において、ライニングコンクリート2に最初のアンカー3・4を設けておく。
1) Upper and lower anchors 3 and 4 are provided on the lining concrete 2 of the shaft 1 (see FIG. 6).
In this case, the first anchors 3 and 4 are provided on the lining concrete 2 at the bottom of the shaft 1 or at a predetermined height position.

2)その上下のアンカー3・4にブラケット5をそれぞれボルト結合して取り付ける(図6参照)。 2) Attach the brackets 5 to the upper and lower anchors 3 and 4 by bolts (see FIG. 6).

3)門型クレーンにより立坑1内にプラットフォーム10を地上から下降または立坑内最下部から上昇させて、そのプラットフォーム10をブラケット5の上に設置する(図6参照)。 3) The platform 10 is lowered from the ground or raised from the bottom in the shaft by the portal crane to install the platform 10 on the bracket 5 (see FIG. 6).

4)プラットフォーム10上において、アンカー3・4の埋設を伴う型枠6の組み立て作業を行う(図2、図7、図8参照)。
この場合、プラットフォーム10上に円周状に設置した足場20も用いて作業を行う。
4) On the platform 10, the assembling work of the mold 6 accompanied with the embedment of the anchors 3 and 4 is performed (see FIGS. 2, 7, and 8).
In this case, the work is also performed using the scaffold 20 installed circumferentially on the platform 10.

5)コンクリートの打設作業を行う。 5) Perform concrete placement work.

6)コンクリート硬化後、プラットフォーム10上、及びその円周状設置の足場20上において、型枠6の取り外し作業を行う。 6) After the concrete is hardened, the mold 6 is removed on the platform 10 and the circumferentially installed scaffolding 20.

7)プラットフォーム10を門型クレーンにより上昇させて所定位置に停止する。
具体的には、プラットフォーム10を例えば2m上昇させて停止する。
7) The platform 10 is raised by the portal crane and stopped at a predetermined position.
Specifically, the platform 10 is raised by 2 m, for example, and stopped.

8)プラットフォーム10下の作業用籠14から上下のアンカー3・4にブラケット5をそれぞれボルト結合して取り付ける(図6参照)。 8) The brackets 5 are respectively bolted and attached to the upper and lower anchors 3 and 4 from the work rod 14 under the platform 10 (see FIG. 6).

9)門型クレーンによりプラットフォーム10を下降して、ブラケット5上に設置する(図6参照)。
具体的には、プラットフォーム10を例えば5cm下降させて停止する。
9) The platform 10 is lowered by the portal crane and installed on the bracket 5 (see FIG. 6).
Specifically, the platform 10 is lowered by, for example, 5 cm and stopped.

10)その後、前記4)〜9)の工程を繰り返して、立坑1の地上開口部までライニングコンクリート2を施工していく。 10) Thereafter, the steps 4) to 9) are repeated, and the lining concrete 2 is constructed up to the ground opening of the shaft 1.

なお、ライニングコンクリート2の施工後は、プラットフォーム10を撤去して、次の施工現場に備える。   In addition, after construction of the lining concrete 2, the platform 10 is removed and prepared for the next construction site.

以上、実施形態の立坑1のプラットフォーム10によれば、立坑1にライニングコンクリート2を打設する際にアンカー3・4を埋設し、そのコンクリート硬化後にアンカー3・4にブラケット5を取り付け、そのブラケット5上に立坑1内の全断面を覆うプラットフォーム10を設置することで、足場組立作業を省略することができるとともに、高所からの落下や飛来災害を防止できるため、工期短縮と低コスト化を達成することができる。   As described above, according to the platform 10 of the shaft 1 of the embodiment, the anchors 3 and 4 are embedded when the lining concrete 2 is placed in the shaft 1, and the brackets 5 are attached to the anchors 3 and 4 after the concrete is hardened. By installing the platform 10 that covers the entire cross section of the vertical shaft 1 on 5, it is possible to omit the scaffold assembly work and to prevent a fall or flying disaster from a high place. Can be achieved.

(変形例)
以上の実施形態においては、円形の立坑としたが、本発明はこれに限定されるものではなく、四角形など多角形の立坑であってもよい。
また、実施形態では、アンカーをコンクリートに埋設したが、後付けであってもよい。
さらに、プラットフォーム及びその各部の形状等も任意であり、その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。
(Modification)
In the above embodiment, a circular shaft is used, but the present invention is not limited to this, and may be a polygonal shaft such as a square.
Moreover, in embodiment, although the anchor was embed | buried under concrete, a retrofit may be sufficient.
Furthermore, the shape of the platform and each part thereof is arbitrary, and it is needless to say that other detailed structures can be appropriately changed.

1 立坑
2 ライニングコンクリート
3 長いアンカー
4 短いアンカー
5 ブラケット
6 型枠
7 横端太材
8 縦端太材
10 プラットフォーム
11 フレーム
12 エキスパンドメタル
13 床パネル
14 作業用籠
15 開閉蓋
16 隙間埋め部材
20 足場
DESCRIPTION OF SYMBOLS 1 Vertical shaft 2 Lining concrete 3 Long anchor 4 Short anchor 5 Bracket 6 Formwork 7 Horizontal end thick material 8 Vertical end thick material 10 Platform 11 Frame 12 Expanded metal 13 Floor panel 14 Work rod 15 Opening lid 16 Gap filling member 20 Scaffolding

Claims (9)

立坑のライニングコンクリートにアンカーを設けておき、
そのアンカーにブラケットを取り付け、
そのブラケットの上に、前記立坑内の全断面を覆うプラットフォームを設置して、
そのプラットフォーム上において、前記アンカーの埋設を伴う前記コンクリート打設用の型枠の組み立て作業を行ってから、前記コンクリートの打設作業を行うことを特徴とする立坑のライニングコンクリート施工方法。
An anchor is installed on the lining concrete of the shaft,
Attach the bracket to the anchor,
On that bracket, install a platform that covers the entire cross section in the shaft,
A lining concrete construction method for a shaft, wherein the concrete placement work is performed after assembling the concrete casting form with the anchor embedding on the platform.
コンクリート硬化後、前記プラットフォーム上において、前記型枠の取り外し作業を行ってから、
前記プラットフォームをクレーンにより上昇させて所定位置に停止し、
そのプラットフォームから前記アンカーに前記ブラケットを取り付けて、
そのブラケット上に前記プラットフォームを設置することを特徴とする請求項1に記載の立坑のライニングコンクリート施工方法。
After hardening the concrete, on the platform, after removing the formwork,
The platform is raised by a crane and stopped at a predetermined position,
Attach the bracket from the platform to the anchor,
2. The lining concrete construction method for a shaft according to claim 1, wherein the platform is installed on the bracket.
前記プラットフォームの下に設けられる作業用籠において、前記アンカーに対する前記ブラケットの取付作業を行うことを特徴とする請求項2に記載の立坑のライニングコンクリート施工方法。   The lining concrete construction method for a shaft according to claim 2, wherein the work for attaching the bracket to the anchor is performed in a work rod provided under the platform. 前記プラットフォームは、地上もしくは立坑内最下部で組み立てられて、クレーンにより最初の前記ブラケットの取付位置に移動して前記ブラケット上に設置されることを特徴とする請求項1から3のいずれか一項に記載の立坑のライニングコンクリート施工方法。   4. The platform according to claim 1, wherein the platform is assembled on the ground or in the lowest part of the shaft, and is moved to the first mounting position of the bracket by a crane and installed on the bracket. The lining concrete construction method of the shaft described in 1. 請求項1から4のいずれか一項に記載の立坑のライニングコンクリート施工方法の実施作業に用いられ、
前記立坑内の全断面を覆う形状に骨材を組み付けられたフレームと、
前記フレーム上に張り付けられた床パネルと、を備えることを特徴とする立坑用プラットフォーム。
It is used for the implementation work of the lining concrete construction method of the shaft according to any one of claims 1 to 4,
A frame assembled with aggregates in a shape covering the entire cross section in the shaft,
A shaft platform comprising: a floor panel attached on the frame.
前記床パネルは前記フレーム上の略中央部を除いて張り付けられ、
前記フレームの少なくとも前記略中央部にエキスパンドメタルが張り付けられていることを特徴とする請求項5に記載の立坑用プラットフォーム。
The floor panel is pasted except for a substantially central portion on the frame,
6. The shaft for shafts according to claim 5, wherein an expanded metal is attached to at least the substantially central portion of the frame.
前記フレーム下の周囲に作業用籠を備えることを特徴とする請求項5または6に記載の立坑用プラットフォーム。   The shaft platform according to claim 5 or 6, further comprising a work rod around the lower part of the frame. 前記作業用籠上の前記床パネルに、作業員が出入りするための開閉蓋が設けられることを特徴とする請求項7に記載の立坑用プラットフォーム。   The platform for shafts according to claim 7, wherein an opening / closing lid for an operator to enter and exit is provided on the floor panel on the work fence. 前記作業用籠に、前記開閉蓋を開けて降りるための階段が設けられることを特徴とする請求項8に記載の立坑用プラットフォーム。   The platform for shafts according to claim 8, wherein a step for opening the opening / closing lid and descending is provided on the work rod.
JP2013232713A 2013-11-11 2013-11-11 Lined lining concrete construction method and shaft platform Active JP6204153B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013232713A JP6204153B2 (en) 2013-11-11 2013-11-11 Lined lining concrete construction method and shaft platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013232713A JP6204153B2 (en) 2013-11-11 2013-11-11 Lined lining concrete construction method and shaft platform

Publications (3)

Publication Number Publication Date
JP2015094086A true JP2015094086A (en) 2015-05-18
JP2015094086A5 JP2015094086A5 (en) 2016-12-01
JP6204153B2 JP6204153B2 (en) 2017-09-27

Family

ID=53196698

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013232713A Active JP6204153B2 (en) 2013-11-11 2013-11-11 Lined lining concrete construction method and shaft platform

Country Status (1)

Country Link
JP (1) JP6204153B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593449A (en) * 2017-01-13 2017-04-26 马钢(集团)控股有限公司 Platform for repairing damaged well wall of vertical shaft, ladder plate girder support structure and construction method
CN110284888A (en) * 2019-07-10 2019-09-27 福州大学 It is applicable in the construction method of deep big Pass drawing secondary system reparation
CN113356859A (en) * 2021-06-10 2021-09-07 山东黄金矿业(莱州)有限公司三山岛金矿 Pouring and mounting construction method between permanent engineering layers of blind shaft well cap
JP7407222B2 (en) 2022-04-18 2023-12-28 大成建設株式会社 Shaft slide form and shaft lining method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001207774A (en) * 2000-01-26 2001-08-03 Mitsui Constr Co Ltd Shaft excavating method
JP2004027658A (en) * 2002-06-26 2004-01-29 Kajima Corp Bracket for temporary work scaffolding

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001207774A (en) * 2000-01-26 2001-08-03 Mitsui Constr Co Ltd Shaft excavating method
JP2004027658A (en) * 2002-06-26 2004-01-29 Kajima Corp Bracket for temporary work scaffolding

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593449A (en) * 2017-01-13 2017-04-26 马钢(集团)控股有限公司 Platform for repairing damaged well wall of vertical shaft, ladder plate girder support structure and construction method
CN110284888A (en) * 2019-07-10 2019-09-27 福州大学 It is applicable in the construction method of deep big Pass drawing secondary system reparation
CN113356859A (en) * 2021-06-10 2021-09-07 山东黄金矿业(莱州)有限公司三山岛金矿 Pouring and mounting construction method between permanent engineering layers of blind shaft well cap
CN113356859B (en) * 2021-06-10 2024-02-20 山东黄金矿业(莱州)有限公司三山岛金矿 Interlayer pouring and installing construction method for permanent engineering of blind vertical shaft cap
JP7407222B2 (en) 2022-04-18 2023-12-28 大成建設株式会社 Shaft slide form and shaft lining method

Also Published As

Publication number Publication date
JP6204153B2 (en) 2017-09-27

Similar Documents

Publication Publication Date Title
KR100913381B1 (en) Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
JP6204153B2 (en) Lined lining concrete construction method and shaft platform
KR100822712B1 (en) Construction method for gang form falling protection and construction structure thereof
KR101027860B1 (en) Eco automatic building demolition method and demolition device
JP2017014853A (en) Method for replacing seismic isolator
JP6603824B2 (en) Upper scattering prevention curing system and upper scattering prevention curing method at the time of multi-story building dismantling
JP6181505B2 (en) Scattering prevention device and method of demolishing building using the same
JP6622504B2 (en) Chimney demolition scaffold and chimney demolition method
KR100944458B1 (en) Apparatus preventing separation of cage for construction
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
JP3881343B2 (en) Method and apparatus for disassembling cylindrical structure
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP2021055508A (en) Upward scattering preventing curing system and upward scattering preventing curing method used in demolishing multi-story building
JP5749620B2 (en) Seismic isolation method for existing buildings
JP3028071B2 (en) Top removal method and scaffold for removal work of ultra-high tubular structure
JP5368040B2 (en) Horizontal force restraint method in seismic isolation work
KR101367227B1 (en) Apparatus for installing liner plate for deep foundation construction of power transmission steel tower and method constructing deep foundation using the same
JP3107458U (en) Work floor for shaft construction and its mounting device
JP5746984B2 (en) Handrail repair method
JP6418825B2 (en) Jack reaction force support member and building dismantling method using the reaction force support member
JP6052541B2 (en) Seismic isolation method for existing buildings
JP6099377B2 (en) Building curing frame
JP5180718B2 (en) How to build an elevator shaft for a base-isolated building
KR101303350B1 (en) Liner plate for constructing deep foundation of power transmission steel tower
JP6774209B2 (en) Multi-story scaffolding

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20161013

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20161013

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170814

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170829

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170831

R150 Certificate of patent or registration of utility model

Ref document number: 6204153

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150