JP2015084626A - Load controller, load control method, and program - Google Patents

Load controller, load control method, and program Download PDF

Info

Publication number
JP2015084626A
JP2015084626A JP2013222670A JP2013222670A JP2015084626A JP 2015084626 A JP2015084626 A JP 2015084626A JP 2013222670 A JP2013222670 A JP 2013222670A JP 2013222670 A JP2013222670 A JP 2013222670A JP 2015084626 A JP2015084626 A JP 2015084626A
Authority
JP
Japan
Prior art keywords
price
power
upper limit
load
demand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013222670A
Other languages
Japanese (ja)
Other versions
JP5903088B2 (en
Inventor
明宏 小川
Akihiro Ogawa
明宏 小川
盛一 二宮
Seiichi Ninomiya
盛一 二宮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2013222670A priority Critical patent/JP5903088B2/en
Publication of JP2015084626A publication Critical patent/JP2015084626A/en
Application granted granted Critical
Publication of JP5903088B2 publication Critical patent/JP5903088B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Abstract

PROBLEM TO BE SOLVED: To make it possible to easily control distributed loads.SOLUTION: A server 20 comprises: a control amount determination unit 214 for determining a control amount Qs, which is a target value of total power consumption by a power storage device 10; a demand information reception unit 211 for receiving demand information showing relation between a power price and power consumption from the power storage device 10; an upper limit value storage unit 234 for storing the upper limit value Pm; an appropriate price determination unit 215 for determining an appropriate price Ps corresponding to the control amount Qs on the basis of the demand information so as not to exceed the upper limit value Pm; and a price signal transmission unit 216 for transmitting a price signal showing the appropriate price Ps to the power storage device 10.

Description

本発明は、負荷制御装置、負荷制御方法およびプログラムに関する。   The present invention relates to a load control device, a load control method, and a program.

電気自動車や温水器などの蓄電負荷や蓄熱負荷を用いて需給バランスをとるため、マルチエージェント技術を用いた自律分散制御が研究されている。たとえば、特許文献1では、供給可能な電力量、電源設備の種別などを連絡し合うシステムが開示されている。   Autonomous distributed control using multi-agent technology is being researched to balance supply and demand using power storage loads and heat storage loads such as electric vehicles and water heaters. For example, Patent Document 1 discloses a system that communicates the amount of power that can be supplied, the type of power supply equipment, and the like.

特開2012−249380号公報JP 2012-249380 A

しかしながら、特許文献1に記載の発明では、マルチエージェントの間で協調制御を行うには各種の情報を連絡し合う必要があり、各エージェントは自律制御に加えて協調制御のために複雑な処理を行う必要がある。   However, in the invention described in Patent Document 1, it is necessary to communicate various types of information in order to perform cooperative control among multi-agents, and each agent performs complicated processing for cooperative control in addition to autonomous control. There is a need to do.

本発明は、このような背景を鑑みてなされたものであり、分散した負荷を容易に制御することのできる、負荷制御装置、負荷制御方法およびプログラムを提供することを目的とする。   The present invention has been made in view of such a background, and an object thereof is to provide a load control device, a load control method, and a program capable of easily controlling a distributed load.

上記課題を解決するための本発明の主たる発明は、負荷制御装置であって、電力価格に応じて電力を消費する複数の負荷装置と通信可能に接続され、前記電力価格と前記消費電力との関係を表す情報である需要情報を前記負荷装置から取得する需要情報取得部と、前記負荷装置による消費電力の合計の目標値である制御量を決定する制御量決定部と、前記電力価格の上限値を記憶する上限値記憶部と、前記上限値を超えないように前記需要情報に基づいて前記制御量に応じた電力価格を決定する適正価格決定部と、前記決定した電力価格を示す価格シグナルを前記負荷装置に送信する価格シグナル送信部と、を備えることとする。   A main invention of the present invention for solving the above-described problem is a load control device, which is communicably connected to a plurality of load devices that consume power according to a power price, and the power price and the power consumption A demand information acquisition unit that acquires demand information that is information representing a relationship from the load device, a control amount determination unit that determines a control amount that is a target value of the total power consumption by the load device, and an upper limit of the power price An upper limit value storage unit for storing a value, an appropriate price determination unit for determining an electric power price according to the control amount based on the demand information so as not to exceed the upper limit value, and a price signal indicating the determined electric power price And a price signal transmitting unit that transmits the information to the load device.

また、本発明の負荷制御装置では、前記需要情報に基づいて、前記電力価格ごとの前記消費電力の合計の分布であるヒストグラムの上位所定割合に入るもののうちの最低価格を前記上限値として決定する上限値設定部をさらに備えるようにしてもよい。   Further, in the load control device of the present invention, based on the demand information, the lowest price among the ones in the upper predetermined ratio of the histogram that is the distribution of the total power consumption for each power price is determined as the upper limit value. You may make it further provide an upper limit setting part.

また、本発明の負荷制御装置では、前記所定割合は50%以下であるようにしてもよい。   In the load control device of the present invention, the predetermined ratio may be 50% or less.

また、本発明の負荷制御装置では、前記適正価格決定部は、前記需要情報に基づいて前記電力価格と前記負荷装置による消費電力の合計との関係を表す需要曲線を作成し、前記需要曲線における前記制御量に対応する前記電力価格を決定するようにしてもよい。   Further, in the load control device of the present invention, the appropriate price determination unit creates a demand curve representing a relationship between the power price and the total power consumption by the load device based on the demand information, The power price corresponding to the control amount may be determined.

また、本発明の負荷制御装置では、前記需要情報に基づいて、前記電力価格のヒストグラムの上位から第1割合に入る最低価格を前記上限値として決定する上限値設定部と、前記上限値の履歴を所定数記憶する上限値履歴記憶部と、前記需要曲線の履歴を所定数記憶する需要曲線履歴記憶部と、をさらに備え、前記上限値設定部は、前回の前記上限値および前回の前記需要曲線を前記上限値履歴記憶部および前記需要曲線履歴記憶部から読み出し、前記前回の需要曲線における前記前回の上限値に対応する前回の制御量を特定し、今回の前記需要曲線における前記前回の制御量に対応する前記電力価格が、前記決定した上限値よりも小さい場合には、前記第1割合よりも小さい第2割合に入る最低価格を前記上限値として決定するようにしてもよい。   In the load control device of the present invention, an upper limit setting unit that determines, as the upper limit, the lowest price that enters the first ratio from the top of the histogram of the power price based on the demand information, and the history of the upper limit An upper limit value history storage unit that stores a predetermined number of demands, and a demand curve history storage unit that stores a predetermined number of history of the demand curve, wherein the upper limit value setting unit includes the previous upper limit value and the previous demand. A curve is read from the upper limit value history storage unit and the demand curve history storage unit, the previous control amount corresponding to the previous upper limit value in the previous demand curve is specified, and the previous control in the current demand curve When the power price corresponding to the amount is smaller than the determined upper limit value, the lowest price that falls into a second ratio smaller than the first ratio is determined as the upper limit value. Good.

また、本発明の他の態様は、負荷制御方法であって、電力価格に応じて電力を消費する複数の負荷装置と通信可能に接続されたコンピュータが、前記電力価格と前記消費電力との関係を表す情報である需要情報を前記負荷装置から取得するステップと、前記負荷装置による消費電力の合計の目標値である制御量を決定するステップと、前記電力価格の上限値を記憶するステップと、前記上限値を超えないように前記需要情報に基づいて前記制御量に応じた電力価格を決定するステップと、前記決定した電力価格を示す価格シグナルを前記負荷装置に送信するステップと、を実行することとする。   According to another aspect of the present invention, there is provided a load control method in which a computer that is communicably connected to a plurality of load devices that consume power according to a power price is related to the power price and the power consumption. Acquiring from the load device demand information that is information representing, a step of determining a control amount that is a target value of the total power consumption by the load device, a step of storing an upper limit value of the power price, Executing a step of determining a power price according to the control amount based on the demand information so as not to exceed the upper limit value, and a step of transmitting a price signal indicating the determined power price to the load device I will do it.

また、本発明の他の態様は、負荷を制御するためのプログラムであって、電力価格に応じて電力を消費する複数の負荷装置と通信可能に接続されたコンピュータに、前記電力価格と前記消費電力との関係を表す情報である需要情報を前記負荷装置から取得するステップと、前記負荷装置による消費電力の合計の目標値である制御量を決定するステップと、前記電力価格の上限値を記憶するステップと、前記上限値を超えないように前記需要情報に基づいて前記制御量に応じた電力価格を決定するステップと、前記決定した電力価格を示す価格シグナルを前記負荷装置に送信するステップと、を実行させることとする。   According to another aspect of the present invention, there is provided a program for controlling a load, wherein the power price and the consumption are connected to a computer communicably connected to a plurality of load devices that consume power according to the power price. Storing demand information, which is information representing a relationship with power, from the load device, determining a control amount that is a target value of the total power consumption by the load device, and storing an upper limit value of the power price Determining a power price according to the control amount based on the demand information so as not to exceed the upper limit, and transmitting a price signal indicating the determined power price to the load device. , Are executed.

その他本願が開示する課題やその解決方法については、発明の実施形態の欄及び図面により明らかにされる。   Other problems and solutions to be disclosed by the present application will be made clear by the embodiments of the invention and the drawings.

本発明によれば、分散した負荷を容易に制御することができる。   According to the present invention, a distributed load can be easily controlled.

本実施形態の電力システムの全体構成の一例を示す図である。It is a figure which shows an example of the whole structure of the electric power system of this embodiment. 蓄電装置10のハードウェア構成例を示す図である。2 is a diagram illustrating a hardware configuration example of a power storage device 10. FIG. 蓄電エージェント11のソフトウェア構成例を示す図である。3 is a diagram illustrating a software configuration example of a power storage agent 11. FIG. 蓄電エージェント11による処理の流れを示す図である。It is a figure which shows the flow of the process by the electrical storage agent. 需要情報送信処理の流れを示す図である。It is a figure which shows the flow of a demand information transmission process. サーバ20のハードウェア構成例を示す図である。2 is a diagram illustrating a hardware configuration example of a server 20. FIG. サーバ20のソフトウェア構成例を示す図である。2 is a diagram illustrating an example of a software configuration of a server 20. FIG. 需要情報記憶部231に記憶される需要情報の構成例を示す図である。It is a figure which shows the structural example of the demand information memorize | stored in the demand information storage part. 需要曲線記憶部232に記憶される需要曲線の一例を示す図である。5 is a diagram illustrating an example of a demand curve stored in a demand curve storage unit 232. FIG. 需要曲線において制御量Qsに対応する適正価格Psを求めることを説明する図である。It is a figure explaining calculating | requiring the appropriate price Ps corresponding to the controlled variable Qs in a demand curve. サーバ20による処理の流れを示す図である。It is a figure which shows the flow of the process by the server. 上限値の設定処理の流れを示す図である。It is a figure which shows the flow of the setting process of an upper limit. 制御量の決定処理の流れを示す図である。It is a figure which shows the flow of a control amount determination process. 平準化処理の流れを示す図である。It is a figure which shows the flow of a leveling process.

==システムの全体構成==
以下、本発明の一実施形態に係る電力システムについて説明する。図1は本実施形態の電力システムの全体構成の一例を示す図である。本実施形態の電力システムは、蓄電装置10およびサーバ20を含んで構成される。蓄電装置10およびサーバ20はそれぞれ通信機能を有しており、通信ネットワーク30を介して互いに通信可能に接続されている。通信ネットワーク30は、たとえばインターネットであり、たとえば公衆電話回線、携帯電話回線、無線通信路、専用電話回線、電力線、シリアルケーブル、イーサネット(登録商標)などにより構築される。
== Overall system configuration ==
Hereinafter, a power system according to an embodiment of the present invention will be described. FIG. 1 is a diagram illustrating an example of the overall configuration of the power system according to the present embodiment. The power system according to the present embodiment includes the power storage device 10 and the server 20. The power storage device 10 and the server 20 each have a communication function, and are connected to each other via a communication network 30 so that they can communicate with each other. The communication network 30 is, for example, the Internet, and is constructed by, for example, a public telephone line, a mobile phone line, a wireless communication path, a dedicated telephone line, a power line, a serial cable, Ethernet (registered trademark), or the like.

蓄電装置10は電力価格に応じて蓄電池に対して充電または放電を行う装置である。   The power storage device 10 is a device that charges or discharges the storage battery according to the power price.

サーバ20は、需給バランスをとる適正な電力価格(以下、適正価格という。)を決定する、たとえばパーソナルコンピュータおよびワークステーションなどのコンピュータである。サーバ20は決定した適正価格を示す情報(以下、価格シグナルという。)を負荷システム10に送信する。これにより、本実施形態の電力システムでは、負荷システム10による充電または放電の自律制御を行わせつつ、電力系統における需給バランスがとれるように適正な価格を設定しようとするものである。本実施形態では、サーバ20は電力系ごとに変電所に設置されるものとし、同一エリア(同一電力系統)内の蓄電装置10を制御する。   The server 20 is a computer such as a personal computer and a workstation that determines an appropriate power price (hereinafter referred to as an appropriate price) that balances supply and demand. The server 20 transmits information indicating the determined appropriate price (hereinafter referred to as a price signal) to the load system 10. Thereby, in the electric power system of this embodiment, it is going to set an appropriate price so that the supply-and-demand balance in an electric power system may be taken, performing the autonomous control of charge or discharge by the load system 10. In this embodiment, the server 20 shall be installed in a substation for every electric power system, and controls the electrical storage apparatus 10 in the same area (the same electric power system).

==蓄電装置10の構成==
図2は、蓄電装置10のハードウェア構成例を示す図である。蓄電装置10は、蓄電エージェント11および蓄電池12を備える。蓄電池12は外部からの制御により充電および放電を行う一般的な蓄電池を想定している。蓄電エージェント11は、蓄電池12を制御するコンピュータである。蓄電エージェント11は、後述するように価格シグナルに応じて蓄電池12が充電または放電を行うように蓄電池12を制御する。
== Configuration of Power Storage Device 10 ==
FIG. 2 is a diagram illustrating a hardware configuration example of the power storage device 10. The power storage device 10 includes a power storage agent 11 and a storage battery 12. The storage battery 12 is assumed to be a general storage battery that is charged and discharged by external control. The power storage agent 11 is a computer that controls the storage battery 12. As will be described later, the power storage agent 11 controls the storage battery 12 so that the storage battery 12 is charged or discharged according to the price signal.

蓄電エージェント11は、CPU101、メモリ102、記憶装置103、通信インタフェース104、制御インタフェース105を備える。記憶装置103は、各種のデータやプログラムを記憶する、たとえばフラッシュメモリ、ソリッドステートドライブおよびハードディスクドライブなどである。CPU101は記憶装置103に記憶されているプログラムをメモリ102に読み出して実行することにより各種の機能を実現する。通信インタフェース104は、通信ネットワーク30に接続するためのインタフェースであり、例えば、電力線に接続して電力線通信(PLC;Power Line Communications)を行うためのPLCモデム、公衆電話回線網に接続するためのモデム、無線通信網に接続するための無線通信機、イーサネット(登録商標)に接続するためのアダプタなどである。制御インタフェース105は、蓄電池12と接続するためのインタフェースである。制御インタフェース105は、たとえば、シリアル通信を行うためのインタフェースであってもよいし、電気信号を出力するための端子であってもよいし、蓄電池12と情報通信を行うための通信インタフェースであってもよい。蓄電エージェント11は、制御インタフェース105を介して命令信号を負荷12に送信することにより蓄電池12を制御することができる。   The power storage agent 11 includes a CPU 101, a memory 102, a storage device 103, a communication interface 104, and a control interface 105. The storage device 103 stores various data and programs, for example, a flash memory, a solid state drive, a hard disk drive, and the like. The CPU 101 implements various functions by reading a program stored in the storage device 103 into the memory 102 and executing it. The communication interface 104 is an interface for connecting to the communication network 30. For example, a PLC modem for connecting to a power line to perform power line communication (PLC), a modem for connecting to a public telephone line network A wireless communication device for connecting to a wireless communication network, an adapter for connecting to Ethernet (registered trademark), and the like. The control interface 105 is an interface for connecting to the storage battery 12. The control interface 105 may be, for example, an interface for performing serial communication, a terminal for outputting an electrical signal, or a communication interface for performing information communication with the storage battery 12. Also good. The power storage agent 11 can control the storage battery 12 by transmitting a command signal to the load 12 via the control interface 105.

図3は、蓄電エージェント11のソフトウェア構成例を示す図である。蓄電エージェント11は、蓄電情報取得部111、買電価格決定部112、需要情報送信部113、価格シグナル受信部114、充放電制御部115、蓄電情報記憶部131および価格シグナル記憶部132を備える。   FIG. 3 is a diagram illustrating a software configuration example of the power storage agent 11. The power storage agent 11 includes a power storage information acquisition unit 111, a power purchase price determination unit 112, a demand information transmission unit 113, a price signal reception unit 114, a charge / discharge control unit 115, a power storage information storage unit 131, and a price signal storage unit 132.

なお、蓄電情報取得部111、買電価格決定部112、需要情報送信部113、価格シグナル受信部114および充放電制御部115は、負荷システム10の負荷エージェント11が備えるCPU101が記憶装置103に記憶されているプログラムをメモリ102に読み出して実行することにより実現され、負荷情報記憶部131および価格シグナル記憶部132は、メモリ102および記憶装置103が提供する記憶領域の一部として実現される。   The power storage information acquisition unit 111, the power purchase price determination unit 112, the demand information transmission unit 113, the price signal reception unit 114, and the charge / discharge control unit 115 are stored in the storage device 103 by the CPU 101 included in the load agent 11 of the load system 10. The load information storage unit 131 and the price signal storage unit 132 are realized as part of a storage area provided by the memory 102 and the storage device 103.

蓄電情報記憶部131は、蓄電池12に関する情報(以下、蓄電情報という。)を記憶する。蓄電情報には、蓄電池12の単位時間あたりの消費電力(単位はkWである。以下、Qと表記する。)、蓄電池12の容量(単位はkWhである。以下、Wsと表記する。)、蓄電池12の現在の蓄電量(単位はkWhである。以下、Wと表記する。)、使用開始時刻、電力価格の最高価格(以下、Pmaxと記載する。)などが含まれる。蓄電池12は使用開始時刻までに容量Ws分だけ満充電されるものとし、電力価格が買電価格以下であれば蓄電池12への充電を行い、電力価格がPmaxを超えている場合には充電を行わないものとする。   The storage information storage unit 131 stores information related to the storage battery 12 (hereinafter referred to as storage information). In the storage information, the power consumption per unit time of the storage battery 12 (unit is kW, hereinafter referred to as Q), the capacity of the storage battery 12 (unit is kWh, hereinafter referred to as Ws), The current storage amount of the storage battery 12 (unit is kWh, hereinafter referred to as W), use start time, maximum price of power price (hereinafter referred to as Pmax), and the like are included. The storage battery 12 is assumed to be fully charged by the capacity Ws by the use start time. If the power price is equal to or less than the power purchase price, the storage battery 12 is charged. If the power price exceeds Pmax, the storage battery 12 is charged. Shall not be performed.

蓄電情報取得部111は、蓄電情報を取得し、取得した蓄電情報を蓄電情報記憶部131に登録する。蓄電情報取得部111は、ユーザから蓄電情報の入力を受け付けるようにすることができる。また、たとえば蓄電池12の容量については、蓄電情報取得部111は制御インタフェース105を介して蓄電池12から取得するようにすることもできる。また、蓄電情報取得部111は、たとえば蓄電池12の現在の蓄電量を取得することもできる。蓄電情報取得部111は、ユーザから現在の蓄電量の入力を受け付けるようにしてもよいし、制御インタフェース105を介して蓄電池12から現在の蓄電量を取得するようにしてもよい。   The power storage information acquisition unit 111 acquires power storage information and registers the acquired power storage information in the power storage information storage unit 131. The power storage information acquisition unit 111 can accept input of power storage information from the user. For example, the storage information acquisition unit 111 can acquire the capacity of the storage battery 12 from the storage battery 12 via the control interface 105. Moreover, the electrical storage information acquisition part 111 can also acquire the present electrical storage amount of the storage battery 12, for example. The power storage information acquisition unit 111 may receive an input of the current power storage amount from the user, or may acquire the current power storage amount from the storage battery 12 via the control interface 105.

買電価格決定部112は、蓄電池12に充電を行う価格(以下、買電価格という。以下、Pと表記する。)を決定する。買電価格決定部112は、蓄電池12の現在の蓄電量に応じて買電価格Pを決定する。買電価格決定部112はたとえば、蓄電池12の容量と現在の蓄電量との差が大きいほど安くなるように買電価格を決定する。本実施形態では、使用開始時刻までの時間をTとし、蓄電量0から満充電までにかかる時間をTf0とし、現在の蓄電量Wから満充電までにかかる時間をTfとして、次の式(1)および(2)により買電価格Pを算出する。   The power purchase price determination unit 112 determines a price for charging the storage battery 12 (hereinafter referred to as a power purchase price; hereinafter referred to as P). The power purchase price determination unit 112 determines the power purchase price P according to the current power storage amount of the storage battery 12. For example, the power purchase price determination unit 112 determines the power purchase price so that the larger the difference between the capacity of the storage battery 12 and the current power storage amount, the lower the price. In this embodiment, T is the time from the use start time, Tf0 is the time taken from the charged amount 0 to full charge, and Tf is the time taken from the current charged amount W to full charge. ) And (2) to calculate the power purchase price P.

Tf=(Ws−W)÷Q=Tf0−W÷Q ・・・(1)
P=Pmax×T÷Tf ・・・(2)
Tf = (Ws−W) ÷ Q = Tf0−W ÷ Q (1)
P = Pmax × T ÷ Tf (2)

需要情報送信部113は、蓄電装置10による電力需要に関する情報(以下、需要情報という。)をサーバ20に送信する。需要情報には、蓄電エージェント11を特定するための情報(以下、エージェントIDという。)、買電価格および消費電力が含まれる。需要情報送信部113は、当該蓄電エージェント11のエージェントIDと、蓄電情報記憶部131に記憶されている買電価格および消費電力とを含めた需要情報をサーバ20に送信する。   The demand information transmission unit 113 transmits information related to power demand by the power storage device 10 (hereinafter referred to as demand information) to the server 20. The demand information includes information for identifying the power storage agent 11 (hereinafter referred to as an agent ID), a power purchase price, and power consumption. The demand information transmission unit 113 transmits demand information including the agent ID of the power storage agent 11 and the power purchase price and power consumption stored in the power storage information storage unit 131 to the server 20.

価格シグナル受信部114は、サーバ20から送信される価格シグナル(以下、Psと表記する。)を受信する。価格シグナル受信部114は、サーバ20から受信した価格シグナルPsを価格シグナル記憶部132に登録する。   The price signal receiving unit 114 receives a price signal (hereinafter referred to as Ps) transmitted from the server 20. The price signal receiving unit 114 registers the price signal Ps received from the server 20 in the price signal storage unit 132.

充放電制御部115は、価格シグナルに応じて蓄電池12を制御する。充放電制御部115は、価格シグナル記憶部に132に記憶されている価格シグナルが、蓄電情報記憶部131に記憶されている買電価格以下(Ps≦P)である場合に、蓄電池12への充電を行い、蓄電池12が満充電になった(W=Wsになった)場合、または、価格シグナルが買電価格を超えた(Ps>P)場合には、蓄電池12への充電を停止する。なお、蓄電池12への充電の制御は一般的な制御であるものとして、ここでは説明を省略する。   The charge / discharge control unit 115 controls the storage battery 12 according to the price signal. When the price signal stored in 132 in the price signal storage unit is equal to or less than the power purchase price stored in the storage information storage unit 131 (Ps ≦ P), the charge / discharge control unit 115 supplies the storage battery 12 When the battery 12 is fully charged (W = Ws) or when the price signal exceeds the power purchase price (Ps> P), charging of the battery 12 is stopped. . In addition, control of charge to the storage battery 12 is assumed to be general control, and description thereof is omitted here.

==蓄電装置10の処理==
図4は、蓄電エージェント11による処理の流れを示す図である。
== Processing of Power Storage Device 10 ==
FIG. 4 is a diagram showing a flow of processing by the power storage agent 11.

買電価格決定部112は、蓄電情報記憶部131に記憶されている使用開始時刻をt0とし(S401)、蓄電情報記憶部131に記憶されている容量Wsを、単位時間あたりの消費電力Qで割ってTf0を算出する(S402)。蓄電エージェント11は以下の処理を繰り返す。   The power purchase price determination unit 112 sets the use start time stored in the power storage information storage unit 131 to t0 (S401), and sets the capacity Ws stored in the power storage information storage unit 131 as the power consumption Q per unit time. Tf0 is calculated by dividing (S402). The power storage agent 11 repeats the following processing.

蓄電エージェント11は、図5に示す需要情報送信処理を実行する(S403)。買電価格決定部112は、t0から現在時刻tを引いて、使用開始時刻までの時間Tを算出する(S421)。蓄電情報取得部111は、蓄電池12の現在の蓄電量Wを取得する(S422)。買電価格決定部112は、WをQで割った値をTf0から引いて、満充電までにかかる時間Tfを算出する(S423)。買電価格決定部112は、使用開始時刻までの時間Tを、満充電までにかかる時間Tfで割った値をPmaxに乗じて買電価格Pを算出する(S424)。需要情報送信部113は、買電価格Pと消費電力Qとを含む需要情報をサーバ20に送信する(S425)。   The power storage agent 11 executes the demand information transmission process shown in FIG. 5 (S403). The power purchase price determination unit 112 subtracts the current time t from t0 to calculate the time T until the use start time (S421). The power storage information acquisition unit 111 acquires the current power storage amount W of the storage battery 12 (S422). The power purchase price determining unit 112 subtracts the value obtained by dividing W by Q from Tf0 to calculate the time Tf required until full charge (S423). The power purchase price determining unit 112 calculates the power purchase price P by multiplying Pmax by a value obtained by dividing the time T until the use start time by the time Tf required to fully charge (S424). The demand information transmission unit 113 transmits demand information including the power purchase price P and the power consumption Q to the server 20 (S425).

価格シグナル受信部114が価格シグナルPsを受信していた場合(S404:YES)、充放電制御部115は、価格シグナルPsが買電価格P以下であれば(S405:YES)、充電池12への充電を行い(S406)、価格シグナルPsが買電価格Pより大きければ(S405:NO)、充電池12への充電を停止する(S407)。   When the price signal receiving unit 114 has received the price signal Ps (S404: YES), the charge / discharge control unit 115 proceeds to the rechargeable battery 12 if the price signal Ps is equal to or less than the power purchase price P (S405: YES). If the price signal Ps is larger than the power purchase price P (S405: NO), the charging of the rechargeable battery 12 is stopped (S407).

以上の処理を繰り返し実行することにより、蓄電エージェント11からは、充電までにかかる時間と現在の蓄電量とに応じて買電価格を決定し、これをサーバ20に通知するとともに、価格シグナルに応じて蓄電池12への充電制御を行うことができる。   By repeatedly executing the above processing, the power storage agent 11 determines the power purchase price according to the time taken for charging and the current power storage amount, notifies the server 20 of this, and responds to the price signal. Thus, charging control to the storage battery 12 can be performed.

==サーバ20の構成==
図6は、サーバ20のハードウェア構成例を示す図である。サーバ20は、CPU201、メモリ202、記憶装置203、通信インタフェース204、入力装置205、出力装置206を備える。記憶装置203は、各種のデータやプログラムを記憶する、例えばハードディスクドライブやソリッドステートドライブ、フラッシュメモリなどである。CPU201は記憶装置203に記憶されているプログラムをメモリ202に読み出して実行することにより各種の機能を実現する。通信インタフェース204は、通信ネットワーク30に接続するためのインタフェースであり、たとえば、電力線に接続して電力線通信(PLC;Power Line Communications)を行うためのPLCモデム、公衆電話回線網に接続するためのモデム、イーサネット(登録商標)に接続するためのアダプタ、無線通信網に接続するための無線通信機などである。入力装置205は、データの入力を受け付ける、例えばキーボードやマウス、トラックボール、タッチパネル、マイクロフォンなどである。出力装置206は、データを出力する、例えばディスプレイやプリンタ、スピーカなどである。
== Configuration of Server 20 ==
FIG. 6 is a diagram illustrating a hardware configuration example of the server 20. The server 20 includes a CPU 201, a memory 202, a storage device 203, a communication interface 204, an input device 205, and an output device 206. The storage device 203 is, for example, a hard disk drive, a solid state drive, or a flash memory that stores various data and programs. The CPU 201 implements various functions by reading the program stored in the storage device 203 into the memory 202 and executing it. The communication interface 204 is an interface for connecting to the communication network 30. For example, a PLC modem for connecting to a power line and performing power line communications (PLC), a modem for connecting to a public telephone line network An adapter for connecting to Ethernet (registered trademark), a wireless communication device for connecting to a wireless communication network, and the like. The input device 205 is a keyboard, mouse, trackball, touch panel, microphone, or the like that accepts data input. The output device 206 is, for example, a display, a printer, or a speaker that outputs data.

図7は、サーバ20のソフトウェア構成例を示す図である。サーバ20は、需要情報受信部211、需要曲線作成部212、負荷電流測定部213、制御量決定部214、上限値設定部215、適正価格決定部216、価格シグナル送信部217、需要供給曲線記憶部231、需要曲線記憶部232、需要履歴記憶部233、上限値記憶部234および適正価格記憶部235を備える。   FIG. 7 is a diagram illustrating a software configuration example of the server 20. The server 20 includes a demand information reception unit 211, a demand curve creation unit 212, a load current measurement unit 213, a control amount determination unit 214, an upper limit setting unit 215, an appropriate price determination unit 216, a price signal transmission unit 217, and a demand supply curve storage. Unit 231, demand curve storage unit 232, demand history storage unit 233, upper limit storage unit 234, and reasonable price storage unit 235.

なお、需要情報受信部211、需要曲線作成部212、負荷電流測定部213、制御量決定部214、上限値設定部215、適正価格決定部216および価格シグナル送信部217は、サーバ20が備えるCPU201が記憶装置203に記憶されているプログラムをメモリ202に読み出して実行することにより実現され、需要供給曲線記憶部231、需要曲線記憶部232、需要履歴記憶部233、上限値記憶部234および適正価格記憶部235は、サーバ20が備えるメモリ202および記憶装置203が提供する記憶領域の一部として実現される。   The demand information receiving unit 211, the demand curve creating unit 212, the load current measuring unit 213, the control amount determining unit 214, the upper limit setting unit 215, the appropriate price determining unit 216, and the price signal transmitting unit 217 are included in the CPU 201 included in the server 20. Is realized by reading the program stored in the storage device 203 into the memory 202 and executing it, and the demand supply curve storage unit 231, the demand curve storage unit 232, the demand history storage unit 233, the upper limit value storage unit 234, and the appropriate price The storage unit 235 is realized as part of a storage area provided by the memory 202 and the storage device 203 included in the server 20.

需要情報受信部211は、蓄電装置10から送信される需要情報を受信する。需要情報受信部211は受信した需要情報を需要情報記憶部231に登録する。需要情報記憶部231に記憶される需要情報の構成例を図8に示す。上述したように、需要情報には、エージェントID、買電価格および消費電力が含まれる。   The demand information receiving unit 211 receives demand information transmitted from the power storage device 10. The demand information receiving unit 211 registers the received demand information in the demand information storage unit 231. A configuration example of demand information stored in the demand information storage unit 231 is shown in FIG. As described above, the demand information includes an agent ID, a power purchase price, and power consumption.

需要曲線作成部212は、需要情報に基づいてエリア内における需要曲線を求める。需要曲線作成部212は、たとえば需要情報の消費電力を電力価格ごとに合計し、電力価格の順に累積消費電力を計算していき、電力価格と累積消費電力との関係を表す関数を作成することができる。なお、需要曲線は、幾何的に作成するようにしてもよいし、所定の単位円(たとえば1円)ごとの電力価格に対応付けて累積消費電力量を表形式で記憶するようにしてもよい。需要曲線作成部212は、定期的に(たとえば30分ごと、1時間ごとなど、任意の時間ごとに)需要情報に基づいて需要曲線を作成する。需要曲線作成部212は、作成した需要曲線を需要曲線記憶部212に登録する。需要曲線記憶部232は、需要曲線の履歴を記憶していくものとする。図9は、需要曲線記憶部232に記憶される需要曲線の一例を示す図である。同図の例では、需要曲線作成部212は、最高価格Pmaxから1円単位で、最低価格(たとえば0円とすることができる。)までの電力価格ごとに、買電価格が電力価格に一致する需要情報の消費電力の合計(合計消費電力)と、消費電力の累計値(累積消費電力)とを需要曲線として作成した例を示している。本実施形態では需要曲線記憶部212は、最新の需要曲線と直近に作成した前回の需要曲線との2つの需要曲線を記憶するものとする。   The demand curve creation unit 212 obtains a demand curve in the area based on the demand information. For example, the demand curve creation unit 212 totals the power consumption of the demand information for each power price, calculates the cumulative power consumption in the order of the power price, and creates a function representing the relationship between the power price and the cumulative power consumption. Can do. The demand curve may be created geometrically, or the accumulated power consumption may be stored in a table format in association with the power price for each predetermined unit circle (for example, 1 yen). . The demand curve creation unit 212 creates a demand curve based on demand information periodically (for example, every 30 minutes, every hour, etc.). The demand curve creation unit 212 registers the created demand curve in the demand curve storage unit 212. It is assumed that the demand curve storage unit 232 stores a history of demand curves. FIG. 9 is a diagram illustrating an example of a demand curve stored in the demand curve storage unit 232. In the example of the figure, the demand curve creation unit 212 matches the power purchase price with the power price for each power price from the highest price Pmax to the lowest price (for example, 0 yen) in increments of 1 yen. In this example, the total power consumption (total power consumption) of the demand information to be generated and the cumulative value of power consumption (cumulative power consumption) are created as a demand curve. In this embodiment, the demand curve memory | storage part 212 shall memorize | store two demand curves, the latest demand curve and the last demand curve created most recently.

負荷電流測定部213は、サーバ20が設置されている電力系統の変電所における負荷電流(以下、PLと表記する。)を測定する。なお、負荷電流測定部213による負荷電流の測定処理には公知の手法を用いるものとしてここでは説明を省略する。負荷電流測定部213は負荷電流を測定する度に、測定した負荷電流の履歴を需要履歴記憶部233に登録していくものとする。負荷電流PLは、価格シグナルにより制御可能な負荷(本実施形態では、蓄電装置10である。)による消費電力の合計(以下、Qsと表記する。)と、価格シグナルにより制御することのできない負荷(本実施形態では、蓄電装置10以外の負荷すべてである。以下、非制御負荷という。)による消費電力の合計(以下、PL0と表記する。)との合計値となる。   The load current measuring unit 213 measures a load current (hereinafter referred to as PL) at a substation of the power system in which the server 20 is installed. The load current measurement unit 213 uses a known method for the load current measurement process, and the description thereof is omitted here. It is assumed that the load current measurement unit 213 registers the history of the measured load current in the demand history storage unit 233 every time the load current is measured. The load current PL is a total of power consumption (hereinafter referred to as Qs) by a load (in this embodiment, the power storage device 10) that can be controlled by a price signal, and a load that cannot be controlled by a price signal. (In this embodiment, it is a total value of the total power consumption (hereinafter referred to as PL0) by all loads other than the power storage device 10 and hereinafter referred to as non-control load).

制御量決定部214は、蓄電装置10による消費電力の合計の目標値(以下、制御量といい、これもQsと表記する。)を決定する。制御量決定部214は、たとえば風力発電や太陽光発電などにより電力供給量が変動した場合に、その変動に応じて蓄電装置10による需要量を増やすべき量を制御量Qsとして決定する。なお、制御量Qsの決定処理の詳細については後述する。制御量決定部214は、制御量を決定する度に、決定した制御量の履歴を需要履歴記憶部233に登録していくものとする。   Control amount determination unit 214 determines a target value of the total power consumption by power storage device 10 (hereinafter referred to as a control amount, also referred to as Qs). For example, when the power supply amount fluctuates due to wind power generation, solar power generation, or the like, the control amount determination unit 214 determines, as the control amount Qs, the amount by which the demand amount by the power storage device 10 should be increased according to the variation. Details of the control amount Qs determination process will be described later. It is assumed that the control amount determination unit 214 registers the history of the determined control amount in the demand history storage unit 233 every time the control amount is determined.

上限値記憶部234は、適正価格の上限値(以下、Pmと表記する。)を記憶する。上限値設定部215は、需要情報に応じて上限値を設定する。上限値設定部215は、需要情報に基づいて、所定の最高値から1単位(たとえば1円、0.5円など任意の価格とすることができる。)ごとの買電価格に対応する消費電力を合計して、買電価格ごとの合計消費電力の分布であるヒストグラムを作成する。ヒストグラムは、たとえば横軸に降順の買電価格、縦軸に合計消費電力量をとったグラフとすることができる。上限値設定部215は、作成したヒストグラムの上位30(任意の値とすることができる。)%の買電価格を上限値の初期値として設定する。なお、ヒストグラムの上位からの割合を示す値(初期値「30」である。以下、Xと表記する。)も上限値記憶部234に設定する。また、上限値設定部215は、需要曲線が更新されたことを契機として、需要曲線に応じて上限値を更新する。上限値設定部215は、前回の需要曲線における上限値Pmに対応する消費電力Qmを求め、最新の需要曲線における消費電力Qmに対応する電力価格Pm’を求め、Pm’>Pmであれば割合Xを増加させて上限値Pmを引き下げる。上限値設定部215は、たとえば、Xに10(たとえば1、5など任意のステップ値とすることができる。)を加算し、ヒストグラムの上位X%値を上限値Pmとして上限値記憶部234を更新する。一方、上限値設定部215は、Pm’≦Pmである場合に、Xが30よりも大きい場合には、Xから10(上記任意のステップ値)を減算し、ヒストグラムの上位X%値を上限値Pmとして上限値を引き上げる。   The upper limit storage unit 234 stores an upper limit value (hereinafter referred to as Pm) of the appropriate price. The upper limit setting unit 215 sets an upper limit according to the demand information. The upper limit setting unit 215 consumes power corresponding to the power purchase price for each unit (for example, an arbitrary price such as 1 yen, 0.5 yen, etc.) from the predetermined maximum value based on the demand information. To create a histogram that is a distribution of the total power consumption for each power purchase price. The histogram can be, for example, a graph in which the horizontal axis represents the power purchase price in descending order and the vertical axis represents the total power consumption. The upper limit setting unit 215 sets a power purchase price of the top 30 (can be an arbitrary value)% of the created histogram as an initial value of the upper limit. Note that a value indicating the ratio from the top of the histogram (initial value “30”, hereinafter referred to as X) is also set in the upper limit storage unit 234. Further, the upper limit setting unit 215 updates the upper limit according to the demand curve when the demand curve is updated. The upper limit value setting unit 215 obtains the power consumption Qm corresponding to the upper limit value Pm in the previous demand curve, obtains the power price Pm ′ corresponding to the power consumption Qm in the latest demand curve, and the ratio if Pm ′> Pm X is increased to lower the upper limit value Pm. For example, upper limit setting unit 215 adds 10 (for example, an arbitrary step value such as 1, 5) to X, and sets upper limit value storage unit 234 using upper X% value of the histogram as upper limit value Pm. Update. On the other hand, when Pm ′ ≦ Pm and X is larger than 30, the upper limit setting unit 215 subtracts 10 (the above arbitrary step value) from X to set the upper X% value of the histogram as the upper limit. The upper limit is raised as the value Pm.

適正価格決定部216は、上限値記憶部234に記憶されているPmを上限として適正価格Psを決定する。図10に示すように、適正価格決定部216は、需要曲線における制御量Qsに対応する電力価格を適正価格Psとして決定する。適正価格決定部215は決定した適正価格を適正価格記憶部235に登録する。   The appropriate price determination unit 216 determines the appropriate price Ps with Pm stored in the upper limit value storage unit 234 as an upper limit. As illustrated in FIG. 10, the appropriate price determination unit 216 determines the power price corresponding to the control amount Qs in the demand curve as the appropriate price Ps. The appropriate price determination unit 215 registers the determined appropriate price in the appropriate price storage unit 235.

価格シグナル送信部217は、適正価格記憶部334に記憶されている適正価格を示す価格シグナルを蓄電装置10に送信する。これにより蓄電装置10において、適正価格に応じた充電の制御が行われる。   Price signal transmission unit 217 transmits a price signal indicating an appropriate price stored in appropriate price storage unit 334 to power storage device 10. As a result, in the power storage device 10, charging is controlled according to the appropriate price.

==サーバ20の処理==
図11は、サーバ20による処理の流れを示す図である。
== Processing of Server 20 ==
FIG. 11 is a diagram illustrating a flow of processing by the server 20.

需要情報受信部211が蓄電装置10から送信される需要情報を受信した場合(S501:YES)、受信した需要情報を需要情報記憶部231に登録する(S502)。需要曲線作成部212は、需要情報記憶部231から買電価格ごとに消費電力を集計し、エリア内の需要曲線を作成する(S503)。上限値設定部215は、図12に示す上限値の設定処理を実行する(S504)。   When the demand information receiving unit 211 receives the demand information transmitted from the power storage device 10 (S501: YES), the received demand information is registered in the demand information storage unit 231 (S502). The demand curve creation unit 212 totals power consumption for each power purchase price from the demand information storage unit 231 and creates a demand curve in the area (S503). The upper limit setting unit 215 executes an upper limit setting process shown in FIG. 12 (S504).

上限値設定部215は、需要情報記憶部231に記憶されている需要情報に基づいて、所定の最高値から1単位(たとえば1円)の買電価格ごとに消費電力を合計し、買電価格のヒストグラムを作成する(S521)。上限値設定部215は、需要曲線記憶部232から新しく作成された今回の需要曲線とともに前回の需要曲線を読み出し(S522)、上限値記憶部234から上限値Pmおよび割合Xを読み出す(S523)。上限値設定部215は、前回の需要曲線においてPmに対応する消費電力をQmとし(S524)、今回の需要曲線においてQmに対応する電力価格をPm’とする(S525)。   Based on the demand information stored in the demand information storage unit 231, the upper limit value setting unit 215 totals the power consumption for each unit price (for example, 1 yen) from the predetermined maximum value, and the power purchase price Is created (S521). The upper limit value setting unit 215 reads the previous demand curve together with the current demand curve newly created from the demand curve storage unit 232 (S522), and reads the upper limit value Pm and the ratio X from the upper limit value storage unit 234 (S523). The upper limit setting unit 215 sets the power consumption corresponding to Pm in the previous demand curve to Qm (S524), and sets the power price corresponding to Qm in the current demand curve to Pm ′ (S525).

上限値設定部215は、Pm’がPmよりも大きく(S526:YES)、Xが50(任意の最高値とすることができる。)未満である場合には(S527:YES)、Xに10(任意のステップ値とすることができる。)を加算する(S527)。これにより上限値が引き下げられることになる。   When Pm ′ is larger than Pm (S526: YES) and X is less than 50 (can be any maximum value) (S527: YES), the upper limit setting unit 215 sets 10 to X. (It can be an arbitrary step value.) Is added (S527). As a result, the upper limit value is lowered.

一方、上限値設定部215は、Pm’がPm以上である場合に(S526:NO)、Xが30(任意の値とすることができる。)より大きければ(S529:YES)、Xから10を減算し(S530)、Xが30であれば(S529:NO)、処理を終了する。   On the other hand, when Pm ′ is equal to or greater than Pm (S526: NO), upper limit setting unit 215 determines that X is 10 if X is greater than 30 (can be an arbitrary value) (S529: YES). Is subtracted (S530), and if X is 30 (S529: NO), the process is terminated.

上限値設定部215は、ヒストグラムの上位X%値を上限値Pmとして上限値記憶部234を更新する(S531)。   The upper limit value setting unit 215 updates the upper limit value storage unit 234 with the upper X% value of the histogram as the upper limit value Pm (S531).

図11に戻り、制御量決定部214は図13に示す制御量の算出処理により制御量Qsを算出する(S505)。   Returning to FIG. 11, the control amount determination unit 214 calculates the control amount Qs by the control amount calculation process shown in FIG. 13 (S505).

制御量決定部214は、消費電力の最低値(以下、最低負荷電力という。)Qminを設定する(S541)。最低負荷電力はたとえばオペレータからの入力を受け付けるようにしてもよいし、発電機からの最小発電電力量に応じて決定するようにしてもよい。制御量決定部214は、制御量Qsを0とする(S542)。その後以下の処理が繰り返される。   The control amount determination unit 214 sets a minimum value of power consumption (hereinafter referred to as minimum load power) Qmin (S541). The minimum load power may be received, for example, from an operator, or may be determined according to the minimum amount of generated power from the generator. The control amount determination unit 214 sets the control amount Qs to 0 (S542). Thereafter, the following processing is repeated.

負荷電流測定部213は、変電所における負荷電流PLを計測する(S543)。負荷電流測定部213は、計測した負荷電流PLを需要履歴記憶部233に登録する(S544)。制御量決定部214は、負荷電流PLから制御量Qsを引いた値が最低負荷電力Qmin以下であれば(S545:YES)、負荷電流PLから制御量Qsを引いた値を最低負荷電力から引いて制御量Qsとする(S546)。   The load current measuring unit 213 measures the load current PL at the substation (S543). The load current measurement unit 213 registers the measured load current PL in the demand history storage unit 233 (S544). If the value obtained by subtracting the control amount Qs from the load current PL is equal to or lower than the minimum load power Qmin (S545: YES), the control amount determination unit 214 subtracts the value obtained by subtracting the control amount Qs from the load current PL from the minimum load power. The control amount is Qs (S546).

一方、負荷電流PLから制御量Qsを引いた値が最低負荷電力Qminよりも大きい場合には(S545:NO)、図14に示す需要の平準化処理を行う(S547)。   On the other hand, when the value obtained by subtracting the control amount Qs from the load current PL is larger than the minimum load power Qmin (S545: NO), the demand leveling process shown in FIG. 14 is performed (S547).

制御量決定部214は、需要制御量の最大値Qmaxを2で割った商をQs0とする(S561)。なお、Qs0には任意の値を設定するようにしてもよい。制御量決定部214は、需要履歴記憶部233から現在から所定期間(たとえば1日など任意の期間とすることができる。)前の期間について負荷電流PLから制御量Qsを引いた差L0の移動平均を算出してPL’とし(S562)、PLからQsを引いた値を、Qs0にPL’を加算した値から減じてQsとする(S563)。   The control amount determination unit 214 sets a quotient obtained by dividing the maximum value Qmax of the demand control amount by 2 as Qs0 (S561). An arbitrary value may be set for Qs0. The controlled variable determining unit 214 moves the difference L0 obtained by subtracting the controlled variable Qs from the load current PL for a predetermined period (for example, any period such as one day) from the demand history storage unit 233 before the current period. The average is calculated as PL ′ (S562), and the value obtained by subtracting Qs from PL is subtracted from the value obtained by adding PL ′ to Qs0 to obtain Qs (S563).

図11に戻り、制御量決定部214は決定したQsを需要履歴記憶部233に登録し(S506)、適正価格決定部216は需要曲線からQsに対応する価格を求めて適正価格Psとする(S507)。図10の需要曲線21において制御量Qsに対応する価格Pが適正価格Psとなる。価格シグナル送信部217は、適正価格Psを価格シグナルとして全ての蓄電装置10(蓄電エージェント11)に送信する(S508)。   Returning to FIG. 11, the control amount determination unit 214 registers the determined Qs in the demand history storage unit 233 (S506), and the appropriate price determination unit 216 obtains the price corresponding to Qs from the demand curve and sets it as the appropriate price Ps ( S507). In the demand curve 21 of FIG. 10, the price P corresponding to the control amount Qs is the appropriate price Ps. The price signal transmission unit 217 transmits the appropriate price Ps as a price signal to all the power storage devices 10 (power storage agents 11) (S508).

==本電力システムによる効果==
以上のようにして、本実施形態の電力システムによれば、サーバ20は価格シグナルを蓄電装置10に与えるのみで蓄電装置10を制御することができる。したがって、分散した蓄電装置10の制御を容易に実現することが可能となる。
== Effects of this power system ==
As described above, according to the power system of the present embodiment, the server 20 can control the power storage device 10 only by giving a price signal to the power storage device 10. Therefore, it becomes possible to easily control the dispersed power storage devices 10.

また、本実施形態の電力システムによれば、蓄電装置10から取得した需要情報に基づいてサーバ20が需要曲線を求め、この需要曲線において制御量Qsに対応する価格を適正価格として決定することができる。したがって、需要曲線に基づいていることから、適正価格を容易かつ適切に決定することができる。   Further, according to the power system of the present embodiment, the server 20 obtains a demand curve based on the demand information acquired from the power storage device 10, and the price corresponding to the control amount Qs in the demand curve is determined as an appropriate price. it can. Therefore, since it is based on a demand curve, an appropriate price can be determined easily and appropriately.

また、たとえば、満充電までにかかる時間Tfが長い蓄電装置10が多い場合などには、適正価格Psが高価格となることがあり、このような場合、買電価格がPsをなかなか上回らず、Tfが短くなったところで一斉に買電価格がPsを上回ってしまい、合計消費電力が大きくなりすぎるという状況(この状況のことを需要曲線が飽和するとも呼ばれる。)が起こりうるところ、本実施形態の電力システムによれば、適正価格Psを上限値Pm以下に抑えることができるので、需要曲線の飽和を回避することができる。   In addition, for example, when there are many power storage devices 10 that take a long time Tf to fully charge, the appropriate price Ps may become high. In such a case, the power purchase price does not easily exceed Ps. In the present embodiment, a situation in which the power purchase price simultaneously exceeds Ps when Tf becomes short and the total power consumption becomes excessively large (this situation is also referred to as a demand curve being saturated). According to the power system, the appropriate price Ps can be suppressed to the upper limit value Pm or less, so that saturation of the demand curve can be avoided.

また、本実施形態の電力システムによれば、前回の需要曲線で上限値Pmに対応していた消費電力量Qmと同じ消費電力量に対応する今回の需要曲線での電力価格Pm’が上限値Pmよりも値上がりし、買電価格が高止まりする(すなわち、需要曲線が飽和する)傾向がみられた場合には、割合Xを上げて上限価格Pmを引き下げることができる。これにより需要曲線の飽和を回避することができる。   Further, according to the power system of the present embodiment, the power price Pm ′ in the current demand curve corresponding to the same power consumption amount as the power consumption amount Qm corresponding to the upper limit value Pm in the previous demand curve is the upper limit value. When the price rises above Pm and the power purchase price tends to remain high (that is, the demand curve is saturated), the upper limit price Pm can be lowered by increasing the ratio X. Thereby, saturation of the demand curve can be avoided.

また、本実施形態の電力システムによれば、割合Xは50以下とすることができる。買電価格のヒストグラムの上位50%値を上限値とすることにより、需要曲線が飽和することはない。したがって、必要以上に適正価格が引き下げられるのを防止することができる。   Moreover, according to the electric power system of this embodiment, the ratio X can be 50 or less. By setting the upper 50% value of the histogram of the power purchase price as the upper limit value, the demand curve will not be saturated. Therefore, it is possible to prevent the appropriate price from being lowered more than necessary.

また、本実施形態の電力システムによれば、割合Xは30以上とすることができる。あまり小さい割合Xを設定して上限値Pmが引き上げられると需要曲線が飽和してしまうことから、上位30%値を上限値とすることが望ましい。   Moreover, according to the electric power system of this embodiment, the ratio X can be 30 or more. Since the demand curve will be saturated if the upper limit value Pm is raised by setting a very small ratio X, it is desirable to set the upper 30% value as the upper limit value.

また、本実施形態の電力システムによれば、PLとQsとの差が最低負荷電力Qminよりも低い場合には、この差をQminから引いて制御量Qsとしているため、需要がQminとなるように制御することができる。すなわち、図12に示すように、たとえば風力発電や太陽光発電などにより電力供給量が変動し、みかけの需要PL0が減少して最低負荷電力を下回った期間61および期間62がある場合には、これらの期間について電力需要が最低負荷電力Qminとなるように制御量Qsを決定することができる。これにより、風力発電や太陽光発電などにより電力供給量が変動する場合であっても、需給バランスを維持することが可能となる。   Further, according to the power system of the present embodiment, when the difference between PL and Qs is lower than the minimum load power Qmin, the difference is subtracted from Qmin to obtain the control amount Qs, so that the demand becomes Qmin. Can be controlled. That is, as shown in FIG. 12, when there is a period 61 and a period 62 in which the power supply amount fluctuates due to, for example, wind power generation or solar power generation, and the apparent demand PL0 decreases and falls below the minimum load power, The control amount Qs can be determined so that the power demand becomes the minimum load power Qmin during these periods. This makes it possible to maintain a supply-demand balance even when the amount of power supply varies due to wind power generation or solar power generation.

また、本実施形態の電力システムによれば、非制御負荷の需要PL0(PLとQsとの差)の移動平均PL’を目標として、制御可能な蓄電装置10の需要Qsを調整することができる。これにより、全体の電力需要PLを平滑化することができるので、需要のピークを抑え安定的な電力系統の運営を行うことが可能となる。   Further, according to the power system of the present embodiment, the demand Qs of the controllable power storage device 10 can be adjusted with the target of the moving average PL ′ of the demand PL0 (difference between PL and Qs) of the non-control load. . Thereby, since the whole electric power demand PL can be smoothed, it becomes possible to suppress the peak of a demand and to operate a stable electric power system.

また、本実施形態の電力システムによれば、蓄電装置10は価格シグナルが示す電力価格Psと買電価格Pとの比較に応じて蓄電池12への充電を行うかどうかを決定すればよく、蓄電装置10の充電制御を簡単に行うことができる。   In addition, according to the power system of the present embodiment, the power storage device 10 may determine whether to charge the storage battery 12 according to the comparison between the power price Ps indicated by the price signal and the power purchase price P. The charging control of the device 10 can be easily performed.

==変形例==
本実施形態では、サーバ20からの制御対象となる負荷は蓄電池12への充電を制御する蓄電装置10であるものとしたが、これに限らず、電力を消費するものであればその種類を問わない。たとえば負荷は温水器などの蓄熱装置であってもよい。この場合、蓄熱装置も蓄電エージェント11と同様のエージェントを備えるようにし、図5のステップS422では現在の蓄熱量を取得してWとし、図4のステップS406およびS407では、温水器への加熱の開始(S406)または終了(S407)を行うものとする。
== Modification ==
In the present embodiment, the load to be controlled from the server 20 is the power storage device 10 that controls the charging of the storage battery 12. However, the present invention is not limited to this, and any type can be used as long as it consumes power. Absent. For example, the load may be a heat storage device such as a water heater. In this case, the heat storage device is also provided with the same agent as the power storage agent 11, and the current heat storage amount is acquired as W in step S422 in FIG. 5 and is set to W in steps S406 and S407 in FIG. It is assumed that the start (S406) or the end (S407) is performed.

また、本実施形態では、サーバ20は電力系統の変電所に設置して電力系統ごとの需要を制御するものとしたが、複数の電力系統からの需要情報を1台のサーバ20が受信し、1台のサーバ20が複数の電力系統の需要を調整するように価格シグナルを送信するようにしてもよい。この場合、サーバ20の需要情報記憶部231、需要曲線記憶部232、需要履歴記憶部233および適正価格記憶部235はそれぞれ、電力系統ごとに需要情報、需要曲線、負荷電流および制御量、ならびに適正価格を記憶するようにし、需要曲線作成部212は電力系統ごとの需要曲線を作成し、負荷電流測定部213は電力系統ごとの負荷電流を測定し、制御量決定部214は電力系統ごとに制御量Qsを決定し、適正価格決定部216は電力系統ごとの需要曲線から、当該電力系統についての制御量に対応する電力価格を適正価格として決定し、価格シグナル送信部217は、電力系統ごとの適正価格を、当該電力系統に対応する蓄電装置10にのみ価格シグナルとして送信する。   In the present embodiment, the server 20 is installed in a substation of the power system and controls demand for each power system. However, one server 20 receives demand information from a plurality of power systems, One server 20 may transmit a price signal so as to adjust demands of a plurality of power systems. In this case, the demand information storage unit 231, the demand curve storage unit 232, the demand history storage unit 233, and the appropriate price storage unit 235 of the server 20 each have a demand information, a demand curve, a load current and a control amount, and an appropriate amount for each power system. The price is stored, the demand curve creation unit 212 creates a demand curve for each power system, the load current measurement unit 213 measures the load current for each power system, and the control amount determination unit 214 controls for each power system. The amount Qs is determined, the appropriate price determination unit 216 determines the power price corresponding to the control amount for the power system as the appropriate price from the demand curve for each power system, and the price signal transmission unit 217 The appropriate price is transmitted as a price signal only to the power storage device 10 corresponding to the power system.

また、本実施形態では適正価格が価格シグナルであるものとしたが、価格シグナルは適正価格に応じた値であればよい。たとえば、適正価格を0〜1の間の値に正規化したものを価格シグナルとしてもよい。   In the present embodiment, the appropriate price is the price signal, but the price signal may be a value corresponding to the appropriate price. For example, a price signal obtained by normalizing an appropriate price to a value between 0 and 1 may be used.

また、本実施形態では、需要情報は買電価格と単位時間あたりの消費電力とが含まれるものとしたが、これに限らず、たとえば買電価格に応じて消費電力を求めるための関数など、買電価格と負荷における消費電力との関係を表すものであり、これに基づいてエリア内における需要曲線が作成できるものであればよい。   In the present embodiment, the demand information includes the power purchase price and the power consumption per unit time. However, the demand information is not limited to this, for example, a function for obtaining power consumption according to the power purchase price, etc. Any relationship can be used as long as it represents the relationship between the power purchase price and the power consumption in the load, and a demand curve in the area can be created based on the relationship.

また、本実施形態では、定期的に需要情報をサーバ20に送信するものとしたが、任意のタイミングで送信するようにしてもよい。たとえば、サーバ20からのリクエストに応じて需要情報を応答するようにしてもよいし、オペレータからの指示に応じて送信するようにしてもよい。   In the present embodiment, the demand information is periodically transmitted to the server 20, but may be transmitted at an arbitrary timing. For example, demand information may be returned in response to a request from the server 20, or may be transmitted in response to an instruction from an operator.

また、本実施形態では、サーバ20から価格シグナルが送信されて蓄電装置10はこれを待つものとしたが、これに限らず、たとえば価格シグナル受信部114が、任意のタイミングで(たとえば、蓄電情報が登録されたときや、オペレータから指示のあったときなどに)サーバ20にリクエストを送信し、サーバ20がリクエストに応じて応答した価格シグナルを受信するようにしてもよい。   In the present embodiment, the price signal is transmitted from the server 20 and the power storage device 10 waits for this. However, the present invention is not limited to this. For example, the price signal receiving unit 114 may be at any timing (for example, power storage information). May be transmitted to the server 20 (such as when an operator is registered or when an instruction is received from an operator), and the server 20 may receive a price signal responding to the request.

また、本実施形態では、価格シグナルの示す価格Psが買電価格以下であれば無条件で充電を行うものとしたが、満充電であれば充電を行わないようにしてもよい。   In the present embodiment, charging is unconditionally performed if the price Ps indicated by the price signal is equal to or less than the power purchase price, but charging may not be performed if the battery is fully charged.

また、本実施形態では、容量Wsを消費電力Qで割って充電にかかる時間Tf0を求めるものとしたが、これに限らず、充電に用いる消費電力量を変動させることができる場合には、買電価格よりもより安い価格シグナルの場合により多くの消費電力量となるように充電を行うようにしてもよい。この場合、需要情報として、価格ごとの消費電力量をサーバ20に送信するようにする。   In the present embodiment, the capacity Ts is calculated by dividing the capacity Ws by the power consumption Q. However, the present invention is not limited to this, and if the power consumption used for charging can be changed, the purchase can be made. In the case of a price signal cheaper than the electricity price, charging may be performed so that the amount of power consumption is larger. In this case, the power consumption for each price is transmitted to the server 20 as demand information.

また、本実施形態では、供給関数および蓄電関数(充電関数および放電関数を含む。)は、電力価格を代入して発電量または充放電量を算出する関数であるものとしたが、これに限らず、電力価格と発電量または充放電量との関係を示す情報であればよい。たとえば、所定の単位金額(たとえば1円、5円、10円など任意の金額とすることができる。)ごとの電力価格に対応付けて発電量または充放電量を管理する表としてもよい。   In the present embodiment, the supply function and the storage function (including the charge function and the discharge function) are functions for calculating the power generation amount or the charge / discharge amount by substituting the power price. Instead, it may be information indicating the relationship between the power price and the amount of power generation or charge / discharge. For example, the power generation amount or the charge / discharge amount may be managed in association with the power price for each predetermined unit amount (for example, any amount such as 1 yen, 5 yen, 10 yen, etc.).

また、供給関数および蓄電関数(充電関数および放電関数を含む。)は、電力価格と発電量および充放電量との関係を示す情報であり、電力価格の変化と発電量または充放電量の変化との関係、すなわち発電量または充放電量の価格弾力性を示す情報も含むものとする。   The supply function and the storage function (including the charge function and the discharge function) are information indicating the relationship between the power price, the power generation amount, and the charge / discharge amount, and the change in the power price and the change in the power generation amount / charge / discharge amount. Information indicating the price elasticity of the power generation amount or the charge / discharge amount.

また、本実施形態では、電力価格ごとの総供給量および総充電量を表として記録し、これに基づいて供給曲線および需要曲線を決定するものとしたが、たとえば、発電関数および蓄電関数が方程式により表されているものである場合には、供給関数および需要関数も方程式により表すようにすることも可能であり、この場合、供給関数と需要関数との交点を、方程式を用いて計算により算出するようにしてもよい。   In the present embodiment, the total supply amount and the total charge amount for each power price are recorded as a table, and the supply curve and the demand curve are determined based on the table. For example, the power generation function and the storage function are equations. In this case, the supply function and the demand function can also be expressed by an equation. In this case, the intersection of the supply function and the demand function is calculated by using the equation. You may make it do.

また、本実施形態では、発電装置10が発電エージェント11および発電機12を含んでいるものとしたが、発電エージェント11および発電機12を別の装置として設けるようにしてもよい。同様に、蓄電エージェント21と蓄電池22とを別の装置として設けるようにしてもよい。また、1台の発電エージェント11が複数の発電機12を制御し、1台の蓄電エージェント21が複数の蓄電池22を制御するようにしてもよい。   In the present embodiment, the power generation apparatus 10 includes the power generation agent 11 and the power generator 12. However, the power generation agent 11 and the power generator 12 may be provided as separate apparatuses. Similarly, the power storage agent 21 and the storage battery 22 may be provided as separate devices. One power generation agent 11 may control a plurality of generators 12 and one power storage agent 21 may control a plurality of storage batteries 22.

また、本実施形態では、サーバ30は1台のコンピュータであるものとしたが、複数台のコンピュータにより実現することもできる。この場合、たとえば、複数台のコンピュータで仮想的な1台のコンピュータを実現するようにしてもよいし、記憶部と機能部とを複数のコンピュータに分散させるようにしてもよい。   In the present embodiment, the server 30 is a single computer, but may be realized by a plurality of computers. In this case, for example, one virtual computer may be realized by a plurality of computers, or a storage unit and a function unit may be distributed to a plurality of computers.

以上、本実施形態について説明したが、上記実施形態は本発明の理解を容易にするためのものであり、本発明を限定して解釈するためのものではない。本発明は、その趣旨を逸脱することなく、変更、改良され得ると共に、本発明にはその等価物も含まれる。   Although the present embodiment has been described above, the above embodiment is intended to facilitate understanding of the present invention and is not intended to limit the present invention. The present invention can be changed and improved without departing from the gist thereof, and the present invention includes equivalents thereof.

10 蓄電装置
20 サーバ
111 蓄電情報取得部
112 買電価格決定部
113 需要情報送信部
114 価格シグナル受信部
115 充放電制御部
131 蓄電情報記憶部
132 価格シグナル記憶部
211 需要情報受信部
212 需要曲線作成部
213 負荷電流測定部
214 制御量決定部
215 上限値設定部
216 適正価格決定部
217 価格シグナル送信部
231 需要供給曲線記憶部
232 需要曲線記憶部
233 需要履歴記憶部
234 上限値記憶部
235 適正価格記憶部
DESCRIPTION OF SYMBOLS 10 Power storage device 20 Server 111 Power storage information acquisition part 112 Electric power purchase price determination part 113 Demand information transmission part 114 Price signal reception part 115 Charge / discharge control part 131 Power storage information storage part 132 Price signal storage part 211 Demand information reception part 212 Demand curve creation Unit 213 load current measurement unit 214 control amount determination unit 215 upper limit value setting unit 216 appropriate price determination unit 217 price signal transmission unit 231 demand supply curve storage unit 232 demand curve storage unit 233 demand history storage unit 234 upper limit value storage unit 235 appropriate price Storage

Claims (7)

電力価格に応じて電力を消費する複数の負荷装置と通信可能に接続され、
前記電力価格と前記消費電力との関係を表す情報である需要情報を前記負荷装置から取得する需要情報取得部と、
前記負荷装置による消費電力の合計の目標値である制御量を決定する制御量決定部と、
前記電力価格の上限値を記憶する上限値記憶部と、
前記上限値を超えないように前記需要情報に基づいて前記制御量に応じた電力価格を決定する適正価格決定部と、
前記決定した電力価格を示す価格シグナルを前記負荷装置に送信する価格シグナル送信部と、
を備えることを特徴とする負荷制御装置。
It is communicably connected to multiple load devices that consume power according to the electricity price,
A demand information acquisition unit that acquires demand information, which is information representing a relationship between the power price and the power consumption, from the load device;
A control amount determining unit that determines a control amount that is a target value of the total power consumption by the load device;
An upper limit storage unit for storing the upper limit of the electricity price;
A reasonable price determination unit that determines a power price according to the control amount based on the demand information so as not to exceed the upper limit;
A price signal transmitting unit that transmits a price signal indicating the determined power price to the load device;
A load control device comprising:
請求項1に記載の負荷制御装置であって、
前記需要情報に基づいて、前記電力価格ごとの前記消費電力の合計の分布であるヒストグラムの上位所定割合に入るもののうちの最低価格を前記上限値として決定する上限値設定部をさらに備えること、
を特徴とする負荷制御装置。
The load control device according to claim 1,
Further comprising an upper limit setting unit that determines, as the upper limit, the lowest price among those that fall within the upper predetermined ratio of the histogram, which is a distribution of the total power consumption for each power price, based on the demand information;
A load control device.
請求項2に記載の負荷制御装置であって、
前記所定割合は50%以下であること、
を特徴とする負荷制御装置。
The load control device according to claim 2,
The predetermined ratio is 50% or less;
A load control device.
請求項1に記載の負荷制御装置であって、
前記適正価格決定部は、前記需要情報に基づいて前記電力価格と前記負荷装置による消費電力の合計との関係を表す需要曲線を作成し、前記需要曲線における前記制御量に対応する前記電力価格を決定すること、
を特徴とする負荷制御装置。
The load control device according to claim 1,
The appropriate price determination unit creates a demand curve representing a relationship between the power price and the total power consumption by the load device based on the demand information, and calculates the power price corresponding to the control amount in the demand curve. To decide,
A load control device.
請求項4に記載の負荷制御装置であって、
前記需要情報に基づいて、前記電力価格のヒストグラムの上位から第1割合に入る最低価格を前記上限値として決定する上限値設定部と、
前記上限値の履歴を所定数記憶する上限値履歴記憶部と、
前記需要曲線の履歴を所定数記憶する需要曲線履歴記憶部と、
をさらに備え、
前記上限値設定部は、前回の前記上限値および前回の前記需要曲線を前記上限値履歴記憶部および前記需要曲線履歴記憶部から読み出し、前記前回の需要曲線における前記前回の上限値に対応する前回の制御量を特定し、今回の前記需要曲線における前記前回の制御量に対応する前記電力価格が、前記決定した上限値よりも小さい場合には、前記第1割合よりも小さい第2割合に入る最低価格を前記上限値として決定すること、
を特徴とする負荷制御装置。
The load control device according to claim 4,
An upper limit setting unit that determines, as the upper limit, the lowest price that enters the first ratio from the top of the histogram of the power price based on the demand information;
An upper limit history storage unit for storing a predetermined number of the history of the upper limit;
A demand curve history storage unit for storing a predetermined number of the history of the demand curve;
Further comprising
The upper limit setting unit reads the previous upper limit value and the previous demand curve from the upper limit value history storage unit and the demand curve history storage unit, and corresponds to the previous upper limit value in the previous demand curve. When the power price corresponding to the previous control amount in the current demand curve is smaller than the determined upper limit value, it enters a second ratio that is smaller than the first ratio. Determining the minimum price as the upper limit,
A load control device.
電力価格に応じて電力を消費する複数の負荷装置と通信可能に接続されたコンピュータが、
前記電力価格と前記消費電力との関係を表す情報である需要情報を前記負荷装置から取得するステップと、
前記負荷装置による消費電力の合計の目標値である制御量を決定するステップと、
前記電力価格の上限値を記憶するステップと、
前記上限値を超えないように前記需要情報に基づいて前記制御量に応じた電力価格を決定するステップと、
前記決定した電力価格を示す価格シグナルを前記負荷装置に送信するステップと、
を実行することを特徴とする負荷制御装置。
A computer that is communicably connected to a plurality of load devices that consume power according to the power price.
Obtaining demand information, which is information representing a relationship between the power price and the power consumption, from the load device;
Determining a control amount that is a target value of the total power consumption by the load device;
Storing an upper limit value of the power price;
Determining a power price according to the control amount based on the demand information so as not to exceed the upper limit;
Transmitting a price signal indicating the determined power price to the load device;
A load control device characterized in that
電力価格に応じて電力を消費する複数の負荷装置と通信可能に接続されたコンピュータに、
前記電力価格と前記消費電力との関係を表す情報である需要情報を前記負荷装置から取得するステップと、
前記負荷装置による消費電力の合計の目標値である制御量を決定するステップと、
前記電力価格の上限値を記憶するステップと、
前記上限値を超えないように前記需要情報に基づいて前記制御量に応じた電力価格を決定するステップと、
前記決定した電力価格を示す価格シグナルを前記負荷装置に送信するステップと、
を実行させるためのプログラム。
To a computer that is communicably connected to multiple load devices that consume power according to the power price,
Obtaining demand information, which is information representing a relationship between the power price and the power consumption, from the load device;
Determining a control amount that is a target value of the total power consumption by the load device;
Storing an upper limit value of the power price;
Determining a power price according to the control amount based on the demand information so as not to exceed the upper limit;
Transmitting a price signal indicating the determined power price to the load device;
A program for running
JP2013222670A 2013-10-25 2013-10-25 Load control device, load control method and program Active JP5903088B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013222670A JP5903088B2 (en) 2013-10-25 2013-10-25 Load control device, load control method and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013222670A JP5903088B2 (en) 2013-10-25 2013-10-25 Load control device, load control method and program

Publications (2)

Publication Number Publication Date
JP2015084626A true JP2015084626A (en) 2015-04-30
JP5903088B2 JP5903088B2 (en) 2016-04-13

Family

ID=53047954

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013222670A Active JP5903088B2 (en) 2013-10-25 2013-10-25 Load control device, load control method and program

Country Status (1)

Country Link
JP (1) JP5903088B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5871295B1 (en) * 2015-08-31 2016-03-01 日本テクノ株式会社 Power consumption upper limit target value management system, power consumption upper limit target value management method, power consumption upper limit target value management program, storage medium
JP2017135816A (en) * 2016-01-27 2017-08-03 株式会社デンソー Power storage device, and management server for power supply system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003125535A (en) * 2001-10-11 2003-04-25 Shimizu Corp Electrical power charge unit price change system by measurement of quantity demanded
JP2010166636A (en) * 2009-01-13 2010-07-29 Hitachi Ltd Power demand-supply management server and power demand-supply management system
JP2012115110A (en) * 2010-11-26 2012-06-14 Kyocera Corp Controller and control method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003125535A (en) * 2001-10-11 2003-04-25 Shimizu Corp Electrical power charge unit price change system by measurement of quantity demanded
JP2010166636A (en) * 2009-01-13 2010-07-29 Hitachi Ltd Power demand-supply management server and power demand-supply management system
JP2012115110A (en) * 2010-11-26 2012-06-14 Kyocera Corp Controller and control method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5871295B1 (en) * 2015-08-31 2016-03-01 日本テクノ株式会社 Power consumption upper limit target value management system, power consumption upper limit target value management method, power consumption upper limit target value management program, storage medium
JP2017135816A (en) * 2016-01-27 2017-08-03 株式会社デンソー Power storage device, and management server for power supply system

Also Published As

Publication number Publication date
JP5903088B2 (en) 2016-04-13

Similar Documents

Publication Publication Date Title
US11164111B2 (en) Electric power management system for reducing large and rapid change in power received from electricity delivery system
JP6135763B2 (en) Charging power control method, charging power control system and program
US10615602B2 (en) Power control system and method, and control device
JP6168060B2 (en) Power management method, power management apparatus and program
JP5497594B2 (en) Ancillary service providing device using power storage device
CN111466061B (en) Power management system
US10310587B2 (en) Power-supply control apparatus, power-supply control method, server, power-supply control system, and storage medium
JP6743953B2 (en) Energy management system, energy management method and computer program
JP6699719B2 (en) Control device, power generation control device, control method, system, and program
JP5903088B2 (en) Load control device, load control method and program
KR20150037410A (en) Building energy management system with distributed energy resources of scheduling and real time control
JP5937047B2 (en) Load control device, load control system, load control method and program
JP6674119B1 (en) Charge control device and charge control system
JP5897615B2 (en) Load control device, load control system, load control method and program
EP3116081A1 (en) Received electrical power control method, received electrical power control device, and electrical instrument
US20140288721A1 (en) Power leveling control method and power leveling control device
KR101603045B1 (en) Energy scheduling apparatus and method for estimating user's inconvenience using thereof
JP2018098951A (en) Power control system, power control method and management control center device
JP6075584B2 (en) Control device, energy management system, control method, and program
JP5780827B2 (en) Energy management method, energy management program, energy management device, energy management system
US20180233910A1 (en) Energy management device, energy management method, and energy management program
JP6971158B2 (en) Power management equipment and programs
JP2016158487A (en) Power related information presentation apparatus, electricity related information presentation method, and program
JP2016041002A (en) Charging/discharging control device and charging/discharging control method
CN116826814B (en) Electric energy management method based on battery cluster, energy manager and related medium

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150807

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150818

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151016

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20151110

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160104

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160308

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160311

R150 Certificate of patent or registration of utility model

Ref document number: 5903088

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250