JP2014080811A - Concrete placement system and its method for performance space at tunnel crest - Google Patents
Concrete placement system and its method for performance space at tunnel crest Download PDFInfo
- Publication number
- JP2014080811A JP2014080811A JP2012229992A JP2012229992A JP2014080811A JP 2014080811 A JP2014080811 A JP 2014080811A JP 2012229992 A JP2012229992 A JP 2012229992A JP 2012229992 A JP2012229992 A JP 2012229992A JP 2014080811 A JP2014080811 A JP 2014080811A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- tunnel
- pipe
- lining
- placing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
本発明は、トンネル冠部に覆工コンクリートを打設するシステム及び方法に関する。言い換えれば、トンネル内周面とこれに相対させた型枠との間の覆工空間のうち、特にトンネル冠部(クラウン部、天端部)の覆工空間へのコンクリート打設技術に関する。 The present invention relates to a system and method for placing lining concrete on a tunnel crown. In other words, the present invention relates to a concrete placement technique in a lining space between a tunnel inner peripheral surface and a mold frame opposed to the tunnel, particularly a tunnel crown portion (crown portion, top end portion).
例えば山岳トンネルにおいて、掘削したトンネルの内周面の地山を覆って構築されるトンネル覆工コンクリートを形成するための工法としては、セントルと呼ばれるトンネル覆工用型枠を用いる工法が一般的に採用されている。 For example, in a mountain tunnel, a tunnel lining formwork called a centle is generally used as a method for forming tunnel lining concrete that is built to cover the ground on the inner peripheral surface of an excavated tunnel. It has been adopted.
ここで、トンネル内周面とこれに相対させた型枠との間の覆工空間のうち、左右のトンネル側壁部及びアーチ形状部については、型枠に設けられた検査窓を利用してコンクリートを流し込んで打設し、トンネル冠部については、型枠の天端部に設けられた投入口から吹上げ方式でコンクリートを打設している。 Here, of the lining space between the tunnel inner peripheral surface and the mold opposite to it, the left and right tunnel side walls and the arch-shaped part are made of concrete using inspection windows provided in the mold. As for the tunnel crown, concrete is cast by a blow-up method from the inlet provided at the top end of the formwork.
特許文献1には、トンネル冠部の吹き上げ方式の打設技術として、トンネル冠部の覆工空間に、高い充填圧力でコンクリートを充填することにより、品質の良好な覆工コンクリートを得るためのトンネル覆工コンクリートの打設管理方法が開示されている。
これは、トンネル覆工用型枠の外周面とトンネル内周の覆工面との間のトンネル冠部の覆工空間に、コンクリートを回転式の開閉蓋が取付けられたコンクリート投入口から圧入して打設する際に、圧力計を用いて前記トンネル冠部に充填されたコンクリートの圧力を管理する方法である。特に、前記圧力計を、前記トンネル覆工用型枠のトンネル冠部にトンネル軸方向に間隔をおいて複数配置し、これらにより計測される充填圧力状態が予め定められた状態となるまでコンクリートを圧送し、しかる後に圧送を停止している。
Patent Document 1 discloses a tunnel for obtaining high-quality lining concrete by filling concrete with high filling pressure in the lining space of the tunnel crown as a tunnel crown blowing-up technique. A method for placing lining concrete is disclosed.
This is because concrete is pressed into the lining space at the crown of the tunnel between the outer peripheral surface of the tunnel lining formwork and the inner lining surface of the tunnel from a concrete inlet with a rotary opening / closing lid. This is a method of managing the pressure of the concrete filled in the tunnel crown using a pressure gauge when placing. In particular, a plurality of the pressure gauges are arranged at intervals in the tunnel axial direction at the tunnel crown portion of the tunnel lining formwork, and the concrete is measured until the filling pressure state measured by these is in a predetermined state. Pumping is performed, and then pumping is stopped.
特許文献2には、トンネル冠部の打設に用いるものではなく、左右のトンネル側壁部及びアーチ形状部の打設に用いるものであるが、移動式の打設装置が開示されている。
これは、トンネル内に配設される型枠にコンクリートを供給するコンクリート供給装置(可動供給管及び連結管)をトンネルの長手方向へ移動させる移送手段を備えている。ここで、可動供給管はトンネルの長手方向にレールに沿って移動し得るように車輪により支持されている。また、連結管は案内台に載置され、型枠の頂部にはこの案内台を支持する案内ローラがトンネルの長手方向へ並設されている。
Patent Document 2 discloses a mobile driving device that is not used for driving the tunnel crown but is used for driving the left and right tunnel side walls and the arch-shaped portion.
This is provided with transfer means for moving a concrete supply device (movable supply pipe and connection pipe) for supplying concrete to a mold disposed in the tunnel in the longitudinal direction of the tunnel. Here, the movable supply pipe is supported by wheels so that it can move along the rail in the longitudinal direction of the tunnel. The connecting pipe is placed on a guide stand, and guide rollers for supporting the guide stand are arranged in parallel in the longitudinal direction of the tunnel at the top of the mold.
トンネル冠部を吹上げ方式で打設した場合、コンクリートの充填不足を生じやすい。また、配管により圧送されたコンクリートが型枠内に吐出された後に移動すると、材料分離(例えば、コンクリート中の比較的粒度の小さい骨材が先送りされて、比較的粒度の大きい骨材が手前に留まる等、打設中にフレッシュコンクリートの構成材料の分布が不均一となる現象)が生じる。材料分離の傾向はコンクリートの移動距離が長いほど顕著に現れる。材料分離が生じると、不均一による強度不足や、仕上がりの不良(色むら)の原因となる。 When the tunnel crown is driven by the blow-up method, concrete is insufficiently filled. Also, when the concrete pumped by the pipe moves after being discharged into the formwork, material separation (for example, relatively small aggregate in the concrete is advanced and the relatively large aggregate is brought forward. A phenomenon in which the distribution of the constituent materials of the fresh concrete becomes non-uniform during placement, such as staying. The tendency of material separation appears more prominently as the moving distance of concrete increases. When material separation occurs, it may cause insufficient strength due to non-uniformity or poor finish (color unevenness).
これに対し、特許文献1に記載の技術は、圧力計を用いて充填圧力を管理するものであるが、あくまで吹き上げ式であるため、充填不足を生じやすい。また、コンクリート投入口の位置は一定であるため、コンクリート投入口から覆工空間へコンクリートが移動する際に材料分離が生じてしまう。 On the other hand, although the technique described in Patent Document 1 manages the filling pressure using a pressure gauge, since it is a blow-up type to the last, insufficient filling tends to occur. In addition, since the position of the concrete inlet is constant, material separation occurs when the concrete moves from the concrete inlet to the lining space.
また、特許文献2に記載の技術は、トンネル冠部の打設用ではないが、これをトンネル冠部の打設に用いることも困難である。特許文献2に記載の技術は、左右のトンネル側壁部及びアーチ形状部の打設に用いるものであるため、コンクリート供給装置はトンネル冠部を移動するものの常に覆工空間内に位置している。このため、トンネル冠部の覆工空間内の全てに、言い換えれば、覆工空間の内外を仕切る妻板(妻型枠)の内面まで、コンクリートを打設することは困難である。 Moreover, although the technique of patent document 2 is not for the placement of a tunnel crown, it is difficult to use this for the placement of a tunnel crown. Since the technique described in Patent Document 2 is used for placing the left and right tunnel side wall portions and the arch-shaped portion, the concrete supply device moves in the tunnel crown portion but is always located in the lining space. For this reason, it is difficult to place concrete in the entire lining space of the tunnel crown part, in other words, to the inner surface of the end plate (wife formwork) that partitions the inside and outside of the lining space.
本発明は、このような実状に鑑み、トンネル冠部の打設に最適なトンネル冠部覆工コンクリート打設システム及び方法を提供することを課題とする。 In view of such a situation, it is an object of the present invention to provide a tunnel crown lining concrete placement system and method that are optimal for tunnel crown placement.
本発明に係るトンネル冠部覆工コンクリート打設システムは、
トンネル軸方向に沿って延在し先端部に吐出口を有するコンクリート打設管と、
前記コンクリート打設管の基端部側を支持し、前記コンクリート打設管の先端部をトンネル軸方向に前記トンネル冠部の覆工空間の外部から妻板を貫通させて内部へ前進及び後退移動させる打設管送り装置と、
前記妻板に設けられて前記コンクリート打設管を貫通させる貫通孔と、
前記貫通孔から前記コンクリート打設管を引き抜いたときに前記貫通孔を閉止可能なシャッターと、
を含んで構成される。
Tunnel crown lining concrete placement system according to the present invention,
A concrete placement pipe extending along the tunnel axis direction and having a discharge port at the tip;
Supporting the base end side of the concrete placing pipe, the forward end of the concrete placing pipe is moved forward and backward in the tunnel axial direction through the end plate from the outside of the tunnel crown lining space. A casting tube feeder;
A through hole provided in the end plate and penetrating the concrete placing pipe;
A shutter capable of closing the through hole when the concrete placing pipe is pulled out from the through hole;
It is comprised including.
本発明に係るトンネル冠部覆工コンクリート打設方法は、
トンネル軸方向に沿って延在し先端部に吐出口を有するコンクリート打設管の基端部側を支持して、前記コンクリート打設管の先端部をトンネル軸方向に前記トンネル冠部の覆工空間の外部から妻板の貫通孔を貫通させて内部へ前進移動させるステップと、
前記コンクリート打設管により前記覆工空間内にコンクリートを打設しつつ、前記コンクリート打設管を後退移動させるステップと、
前記コンクリート打設管の後退移動により前記コンクリート打設管の先端部を前記貫通孔から引き抜くと同時に、シャッターにより前記貫通孔を閉止して、覆工コンクリートの打設を終了するステップと、
を含んで構成される。
The tunnel crown lining concrete placing method according to the present invention is as follows.
Supporting the base end side of the concrete placement pipe extending along the tunnel axis direction and having a discharge port at the tip end, and covering the tunnel crown portion with the tip end portion of the concrete placement pipe in the tunnel axis direction A step of moving forward through the through hole of the end plate from the outside of the space,
Retreating the concrete placing pipe while placing concrete in the lining space by the concrete placing pipe;
Simultaneously pulling out the tip of the concrete placement pipe from the through hole by retreating the concrete placement pipe, and simultaneously closing the through hole with a shutter to finish placing the lining concrete;
It is comprised including.
本発明によれば、打設管の吐出口を打設部の直近へ移動させて打設することができ、充填不足を低減することができる。また、打設中のコンクリートの移動を抑制でき、その結果として、コンクリートの材料分離を低減できる。 According to the present invention, it is possible to place the discharge port of the placement tube by moving it to the position close to the placement portion, and to reduce insufficient filling. Moreover, the movement of the concrete during placement can be suppressed, and as a result, the material separation of the concrete can be reduced.
また、コンクリート打設管の後退移動によりコンクリート打設管を妻板の貫通孔から引き抜くと同時にシャッターにより貫通孔を閉止することで、トンネル冠部の覆工空間の全てに、すなわち妻板の内面まで、必要十分な充填圧力で、コンクリートを打設することができ、充填性能を向上させることができる。 In addition, by pulling out the concrete placement pipe from the through hole of the end plate by retreating the concrete placement pipe, and simultaneously closing the through hole with the shutter, to the entire lining space of the tunnel crown, that is, to the inner surface of the end plate, Concrete can be placed at a necessary and sufficient filling pressure, and the filling performance can be improved.
以下、本発明の実施の形態について、詳細に説明する。
図1は本発明の一実施形態に係るトンネル冠部覆工コンクリート打設システムを示すトンネルの側面図であり、図の左側が坑口側(覆工空間ラップ側)、図の右側が切羽側(覆工空間妻側)である。また、「前後」というときは、覆工空間へのコンクリート打設管の挿入方向(妻側からラップ側へ挿入)で見て、ラップ側(図の左側)を前側、妻側(図の右側)を後側とする。図2は同上システムを示す切羽側(妻側)から見たトンネルの断面図、図3は同上システムを示すトンネルの平面図である。また、図4は同上システムでの打設管の引き抜き状態を示すトンネルの側面図である。
Hereinafter, embodiments of the present invention will be described in detail.
FIG. 1 is a side view of a tunnel showing a tunnel crown lining concrete placement system according to an embodiment of the present invention, the left side of the figure is the wellhead side (lining space wrap side), and the right side of the figure is the face side ( Lining space wife side). Also, when referring to “front and back,” seeing the direction of insertion of the concrete placement pipe into the lining space (inserted from the wife side to the lap side), the lap side (left side in the figure) is the front side and the wife side (right side in the figure) ) Is the rear side. 2 is a sectional view of the tunnel as seen from the face side (wife side) showing the system, and FIG. 3 is a plan view of the tunnel showing the system. FIG. 4 is a side view of the tunnel showing the pulled-out state of the casting tube in the system.
本実施形態のトンネルは山岳トンネルであり、トンネル内周面1は、発破掘削でのトンネル掘削後、吹き付けコンクリート等により一次支保されている。そして、このトンネル内周面1に相対させて型枠2をセットし、トンネル内周面1と型枠2との間に覆工コンクリート打設用の覆工空間3を形成している。型枠2のセットには、トンネル底部(インバート)4に敷設されたレール5上を移動可能なガントリー車6が用いられる。 The tunnel of this embodiment is a mountain tunnel, and the tunnel inner peripheral surface 1 is primarily supported by sprayed concrete or the like after tunnel excavation by blast excavation. Then, the mold frame 2 is set so as to be opposed to the inner peripheral surface 1 of the tunnel, and a lining space 3 for placing concrete is formed between the inner peripheral surface 1 of the tunnel and the mold frame 2. A gantry vehicle 6 that can move on a rail 5 laid on a tunnel bottom (invert) 4 is used for setting the formwork 2.
型枠2は、「覆工セントル」とも呼ばれ、トンネル軸方向に所定幅(例えば1.5m)を有する型枠部材をトンネル軸方向に複数(例えば7個)連結し、1スパン(例えば10.5m)として構成される。尚、各型枠部材は周方向に適宜分割されており、組み合わせて使用される。 The formwork 2 is also called “covering centle”, and a plurality of formwork members (for example, seven pieces) having a predetermined width (for example, 1.5 m) in the tunnel axis direction are connected in the tunnel axis direction to form one span (for example, 10 .5m). Each formwork member is appropriately divided in the circumferential direction and used in combination.
図では、トンネル軸方向に7個の型枠部材2A〜2Gにより1スパンの型枠2が構成され、トンネル内周面1と1スパンの型枠2(2A〜2G)との間に覆工コンクリート打設用の覆工空間3が形成される。そして、この覆工空間3は、図2を参照し、左右のトンネル側壁部(トンネル側壁部の覆工空間)3A、3Aと、これに続く左右のアーチ形状部(アーチ形状部の覆工空間)3B、3Bと、中央のトンネル冠部(トンネル冠部の覆工空間)3Cとに大別することができる。このうち、左右のトンネル側壁部3A、3A及びアーチ形状部3B、3Bについては、ガントリー車6に装備されているコンクリート打設管(図示せず)を型枠2に設けられている適宜の検査窓(図示せず)から覆工空間3に挿入して、コンクリートを圧送することにより、コンクリートを打設する。その後に、本発明に係るトンネル冠部覆工コンクリート打設システムを用いて、トンネル冠部3Cにコンクリートを打設する。 In the figure, a seven-span mold 2 is constituted by seven mold members 2A to 2G in the tunnel axis direction, and a lining is provided between the tunnel inner peripheral surface 1 and the one-span mold 2 (2A to 2G). A lining space 3 for placing concrete is formed. And this lining space 3 refers to FIG. 2, and the left and right tunnel side wall portions (covering space of the tunnel side wall portion) 3A, 3A, and the left and right arch shape portions (the lining space of the arch shape portion). ) 3B and 3B and a central tunnel crown (tunnel lining space) 3C. Among these, the right and left tunnel side wall portions 3A, 3A and the arch-shaped portions 3B, 3B are appropriately inspected in which the concrete placing pipe (not shown) provided in the gantry vehicle 6 is provided in the formwork 2. The concrete is placed by inserting into the lining space 3 from a window (not shown) and pumping the concrete. Thereafter, concrete is placed in the tunnel crown 3C using the tunnel crown lining concrete placement system according to the present invention.
従って、本発明に係るトンネル冠部覆工コンクリート打設システムを用いて、トンネル冠部3Cにコンクリートを打設する際には、型枠部材2A〜2Gより切羽側の型枠の覆工空間には、左右のトンネル側壁部3A、3A及びアーチ形状部3B、3Bからトンネル冠部3Cまで既にコンクリートが打設され、型枠部材2A〜2Gの覆工空間3には、トンネル冠部3Cを除く、左右のトンネル側壁部3A、3A及びアーチ形状部3B、3Bに既にコンクリートが打設されているものとする。 Therefore, when concrete is placed in the tunnel crown 3C using the tunnel crown lining concrete placement system according to the present invention, the lining space of the formwork on the face side from the formwork members 2A to 2G. The concrete has already been cast from the left and right tunnel side wall portions 3A and 3A and the arch-shaped portions 3B and 3B to the tunnel crown portion 3C, and the tunnel crown portion 3C is excluded from the lining space 3 of the formwork members 2A to 2G. It is assumed that concrete has already been placed on the left and right tunnel side wall portions 3A and 3A and the arch shape portions 3B and 3B.
また、型枠部材2A〜2Gの覆工空間3のトンネル軸方向の坑口側端部(ラップ側)は、既設コンクリート7により塞がれている。他方、型枠部材2A〜2Gの覆工空間3のトンネル軸方向の切羽側端部(妻側)は、閉塞用の妻板8により塞がれている。 Further, the end portion (lap side) in the tunnel axis direction of the lining space 3 of the formwork members 2 </ b> A to 2 </ b> G is closed by the existing concrete 7. On the other hand, the face side end portion (wife side) in the tunnel axis direction of the lining space 3 of the formwork members 2A to 2G is closed by a closing plate 8.
本実施形態のトンネル冠部覆工コンクリート打設システムは、トンネル内周面1と型枠2(型枠部材2A〜2G)との間の覆工空間3のうち、トンネル冠部(トンネル冠部の覆工空間)3Cに覆工コンクリートを打設するものであり、トンネル冠部用のコンクリート打設管10と、打設管10を移動させる打設管送り装置20と、打設管送り装置20を装備する台車40と、打設管送り装置20側で打設管10の先端部側を支持する配管支持部材50と、型枠2側で打設管10の先端部側を支持する配管支持部材60とを含んで構成される。 The tunnel crown lining concrete placement system of this embodiment includes a tunnel crown (tunnel crown) in the lining space 3 between the tunnel inner peripheral surface 1 and the mold 2 (formwork members 2A to 2G). Lining space) 3C for lining concrete, a concrete placement pipe 10 for a tunnel crown, a placement pipe feeding device 20 for moving the placement pipe 10, and a placement pipe feeding apparatus. 20, a carriage 40 equipped with 20, a pipe support member 50 that supports the distal end side of the casting pipe 10 on the casting pipe feeder 20 side, and a piping that supports the distal end side of the casting pipe 10 on the mold 2 side. And a support member 60.
コンクリート打設管10は、トンネル軸方向に沿って延在する直管であり、先端部に吐出口を有している。打設管10の基端部は、屈曲し、後述する打設管送り装置20の走行架台25に支持されている。打設管10の基端部に接続されるコンクリート供給用配管については後述する。 The concrete placing pipe 10 is a straight pipe extending along the tunnel axis direction, and has a discharge port at the tip. The base end portion of the placement tube 10 is bent and supported by a travel base 25 of the placement tube feeder 20 described later. The concrete supply pipe connected to the base end of the placing pipe 10 will be described later.
打設管送り装置20は、トンネル冠部の覆工空間3Cの外部に配置されており、コンクリート打設管10の基端部を支持し、コンクリート打設管10の先端部をトンネル軸方向にトンネル冠部の覆工空間3Cの外部(妻側)から内部(ラップ側)へ前進及び後退移動させる。 The placement pipe feeding device 20 is arranged outside the lining space 3C of the tunnel crown, supports the proximal end portion of the concrete placement pipe 10, and the distal end portion of the concrete placement pipe 10 in the tunnel axial direction. Move forward and backward from the outside (wife side) to the inside (lap side) of the lining space 3C of the tunnel crown.
打設管送り装置20は、台車40上に装備される。
台車40は、ガントリー車6の後方に配置されて、ガントリー車6と同じくトンネル底部4のレール5上を移動可能な、門型の車両であり、その天板41上に打設管送り装置20が装備される。また、門型の台車40の内部空間には、ダンプトラック、ミキサー車などを通過させることができる。
The placement pipe feeder 20 is mounted on the carriage 40.
The carriage 40 is a portal-type vehicle that is disposed behind the gantry vehicle 6 and is movable on the rail 5 at the bottom 4 of the tunnel, like the gantry vehicle 6. Is equipped. Further, a dump truck, a mixer truck, or the like can be passed through the internal space of the portal-type carriage 40.
打設管送り装置20は、台車40の天板41上に取付けられる前後一対の第1ベース21、21と、第1ベース21、21上に横方向(トンネル横断方向)に位置調整可能に取付けられる前後一対の第2ベース22、22と、第2ベース22、22上に立設される上下方向位置調整用の前後一対の伸縮ジャッキ23、23と、ジャッキ23、23の上端部に支持されて前後方向(トンネル軸方向)に延在する案内レール部材24と、案内レール部材24に沿って前後方向に移動可能な走行架台25と、走行架台25に取付けられてコンクリート打設管10の基端部を保持するホルダ26とを含んで構成される。 The placement pipe feeding device 20 is attached to a top plate 41 of a carriage 40 and a pair of front and rear first bases 21 and 21 and is mounted on the first bases 21 and 21 so that the position can be adjusted in the lateral direction (tunnel crossing direction). A pair of front and rear second bases 22 and 22, a pair of front and rear extension jacks 23 and 23 for vertical position adjustment that are erected on the second bases 22 and 22, and upper ends of the jacks 23 and 23 are supported. A guide rail member 24 extending in the front-rear direction (tunnel axis direction), a travel base 25 movable in the front-rear direction along the guide rail member 24, and a base of the concrete placing pipe 10 attached to the travel base 25 And a holder 26 that holds the end.
図5は打設管送り装置20の要部拡大側面図であり、案内レール部材24、走行架台25、ホルダ26などが示されている。
案内レール部材24の前端部付近及び後端部付近にはそれぞれスプロケット27、28が配置され、これらのスプロケット27、28にチェーン29がエンドレスに巻き掛けられている。そして、チェーン29の一箇所に走行架台25が掛止されている。そして、後端部側のスプロケット28の近傍にモータ30が配置され、このモータ30の出力軸によりベベルギア31を介してスプロケット28を回転駆動可能としている。
FIG. 5 is an enlarged side view of a main part of the placing pipe feeding device 20, and shows a guide rail member 24, a traveling frame 25, a holder 26, and the like.
Sprockets 27 and 28 are arranged near the front end portion and the rear end portion of the guide rail member 24, respectively, and a chain 29 is wound around these sprockets 27 and 28 in an endless manner. The traveling frame 25 is hooked at one place of the chain 29. A motor 30 is arranged in the vicinity of the sprocket 28 on the rear end side, and the sprocket 28 can be driven to rotate via the bevel gear 31 by the output shaft of the motor 30.
従って、モータ30により、スプロケット28を回転させることで、チェーン29を介して、走行架台25を案内レール部材24に沿って移動させることができ、また、モータ30の正転により、走行架台25を前進移動させ、モータ30の逆転により、走行架台25を後退移動させることができる。 Therefore, the traveling base 25 can be moved along the guide rail member 24 via the chain 29 by rotating the sprocket 28 by the motor 30, and the traveling base 25 can be moved by the normal rotation of the motor 30. The traveling platform 25 can be moved backward by moving forward and reversing the motor 30.
ここで、走行架台25はホルダ26を介してコンクリート打設管10の基端部を支持している。従って、モータ30による走行架台25の前進又は後退移動に伴って、コンクリート打設管10を前進又は後退移動させることができる。そして、コンクリート打設管10の前進移動により、コンクリート打設管10の先端部をトンネル冠部の覆工空間3C内へ挿入し、覆工空間3Cの最奥部(既設コンクリート7近傍)まで到達させることができる(図1参照)。そして、この状態から、コンクリート打設管10の後退移動により、コンクリート打設管10を覆工空間3Cから引き抜くことができる(図4参照)。 Here, the traveling frame 25 supports the base end portion of the concrete placing pipe 10 via the holder 26. Therefore, the concrete placement pipe 10 can be moved forward or backward as the traveling frame 25 is moved forward or backward by the motor 30. Then, by the forward movement of the concrete placement pipe 10, the tip of the concrete placement pipe 10 is inserted into the lining space 3C of the tunnel crown and reaches the innermost part of the lining space 3C (near the existing concrete 7). (See FIG. 1). From this state, the concrete placement pipe 10 can be pulled out of the lining space 3C by the backward movement of the concrete placement pipe 10 (see FIG. 4).
また、図5に示されているように、走行架台25を牽引するチェーン29の途中にシリンダ型の圧力センサ32を介在させてある。具体的には、走行架台25と、その前側に掛止するチェーン29a(スプロケット27側)との間に、圧力センサ32を介在させてある。コンクリート打設管10により覆工空間3C内にコンクリートが打設されて、コンクリート打設管10の先端部にコンクリートの充填圧力が作用すると、コンクリート打設管10を介して走行架台25に反力がかかり、スプロケット27側のチェーン29a、したがってシリンダ型の圧力センサ32に引張力が作用する。従って、圧力センサ32は、コンクリート打設管10の先端部付近のコンクリート充填圧力を検出することができる。 Further, as shown in FIG. 5, a cylinder-type pressure sensor 32 is interposed in the middle of a chain 29 that pulls the traveling frame 25. Specifically, a pressure sensor 32 is interposed between the traveling gantry 25 and a chain 29a (on the sprocket 27 side) hooked on the front side thereof. When concrete is placed in the lining space 3 </ b> C by the concrete placement pipe 10 and a concrete filling pressure is applied to the tip of the concrete placement pipe 10, a reaction force is applied to the traveling platform 25 via the concrete placement pipe 10. As a result, a tensile force acts on the chain 29a on the sprocket 27 side, and hence on the cylinder type pressure sensor 32. Therefore, the pressure sensor 32 can detect the concrete filling pressure near the tip of the concrete placing pipe 10.
次に打設管送り装置20側でコンクリート打設管10の先端部側を支持する配管支持部材50について説明する。図6は打設管送り装置20側の配管支持部材50の具体例を示す図である。
打設管送り装置20の案内レール部材24には、その長手方向の複数箇所(例えば3箇所)に配管支持部材50を取付可能である。
Next, the pipe support member 50 that supports the distal end side of the concrete placing pipe 10 on the placing pipe feeding device 20 side will be described. FIG. 6 is a view showing a specific example of the pipe support member 50 on the placement pipe feeder 20 side.
The pipe support members 50 can be attached to a plurality of locations (for example, three locations) in the longitudinal direction of the guide rail member 24 of the placement tube feeder 20.
配管支持部材50は、図6に示されるように、コンクリート打設管10を下方から支持する鼓状のローラ51と、このローラ51を回転自在に支承して上下に延びる支持体52とを含んで構成され、支持体52は案内レール部材24に位置変更可能に取付けられる。ここで、支持体52は、図6(a)のように案内レール部材24より上方へ突出して、ローラ51によりコンクリート打設管10を支持する第1位置と、図6(b)のように案内レール部材24上から没して退避する第2位置とをとることができる。第2位置では案内レール部材24上での走行架台25の移動を妨げることがない。 As shown in FIG. 6, the pipe support member 50 includes a drum-shaped roller 51 that supports the concrete placing pipe 10 from below, and a support body 52 that supports the roller 51 rotatably and extends vertically. The support body 52 is attached to the guide rail member 24 so that its position can be changed. Here, the support body 52 protrudes upward from the guide rail member 24 as shown in FIG. 6A, and supports the concrete placing pipe 10 by the roller 51, as shown in FIG. 6B. It is possible to take the second position where the guide rail member 24 is submerged and retracted. In the second position, the movement of the traveling frame 25 on the guide rail member 24 is not hindered.
次に型枠2側でコンクリート打設管10の先端部側を支持する配管支持部材60について説明する。図7は型枠2側の配管支持部材60の具体例を示す図である。
型枠2には、トンネル冠部におけるトンネル軸方向の複数箇所(例えば4箇所)に配管支持部材60を取付可能である。
Next, the pipe support member 60 that supports the distal end side of the concrete placing pipe 10 on the mold 2 side will be described. FIG. 7 is a view showing a specific example of the pipe support member 60 on the mold 2 side.
Pipe support members 60 can be attached to the mold 2 at a plurality of locations (for example, 4 locations) in the tunnel axis direction at the tunnel crown.
配管支持部材60は、中央の第1ロッド61と、両側の第2及び第3ロッド62、63とを含んで構成され、それぞれ型枠2にその内周面側から取付けられる。 The pipe support member 60 includes a central first rod 61 and second and third rods 62 and 63 on both sides, and is attached to the mold frame 2 from the inner peripheral surface side.
第1ロッド61は、その上端部に案内ローラ64を回転自在に保持している。案内ロータ64は、第1ロッド61のロッド径より小さく、第1ロッド61の軸方向に見たときに第1ロッド61の径内に収まる大きさにしてある。
第1ロッド61は、型枠2に設けた穴、具体的には型枠2の内周面側に固着した筒状体65に下側から挿入されて、覆工空間3C内に進入し、上端部の案内ローラ64でコンクリート打設管10を支持する。
The first rod 61 holds a guide roller 64 rotatably at its upper end. The guide rotor 64 is smaller than the rod diameter of the first rod 61 and is sized to fit within the diameter of the first rod 61 when viewed in the axial direction of the first rod 61.
The first rod 61 is inserted from below into a hole provided in the mold 2, specifically, a cylindrical body 65 fixed to the inner peripheral surface side of the mold 2, and enters the lining space 3 </ b> C, The concrete placing pipe 10 is supported by the guide roller 64 at the upper end.
第2及び第3ロッド62、63は、第1ロッド61よりやや長い。第2及び第3ロッド62、63は、型枠2に設けた穴、具体的には型枠2の内周面側に固着した筒状体66、67に下側から挿入されて、覆工空間3C内に進入し、上端部は第1ロッド61の案内ローラ64により支持されるコンクリート打設管10の左右に位置して、案内ローラ64上からコンクリート打設管10が脱落するのを防止する。 The second and third rods 62 and 63 are slightly longer than the first rod 61. The second and third rods 62 and 63 are inserted from below into the holes provided in the mold 2, specifically, the cylindrical bodies 66 and 67 fixed to the inner peripheral surface of the mold 2, It enters the space 3C, and its upper end is located on the left and right sides of the concrete placing pipe 10 supported by the guide roller 64 of the first rod 61, thereby preventing the concrete placing pipe 10 from dropping off from the guide roller 64. To do.
第1ロッド61は、筒状体65と第1ロッド61とを径方向に貫通する固定ピン65aにより固定される。ここで、第1ロッド61には、ピン65aが貫通可能なピン穴が軸方向に複数設けられ、これらの選択により、覆工空間3C内への第1ロッド61の進入位置を調整可能である。 The first rod 61 is fixed by a fixing pin 65a that penetrates the cylindrical body 65 and the first rod 61 in the radial direction. Here, the first rod 61 is provided with a plurality of pin holes through which the pin 65a can penetrate in the axial direction, and by selecting these, the entry position of the first rod 61 into the lining space 3C can be adjusted. .
第2ロッド62についても同様で、筒状体66と第2ロッド62とを径方向に貫通する固定ピン66aにより固定され、ピン穴の選択により、覆工空間3C内への第2ロッド62の進入位置を調整可能である。
第3ロッド63についても同様で、筒状体67と第3ロッド63とを径方向に貫通する固定ピン67aにより固定され、ピン穴の選択により、覆工空間3C内への第3ロッド63の進入位置を調整可能である。
The same applies to the second rod 62. The second rod 62 is fixed by a fixing pin 66a that penetrates the cylindrical body 66 and the second rod 62 in the radial direction. By selecting the pin hole, the second rod 62 is inserted into the lining space 3C. The approach position can be adjusted.
The same applies to the third rod 63, and is fixed by a fixing pin 67a that penetrates the cylindrical body 67 and the third rod 63 in the radial direction. By selecting a pin hole, the third rod 63 enters the lining space 3C. The approach position can be adjusted.
図8は型枠2側の配管支持部材60の配置を示す図である。この図からわかるように、第1ロッド61と、第2及び第3ロッド62、63とは、トンネル軸方向の位置をずらしている。言い換えれば、筒状体65と、筒状体66、67とは、トンネル軸方向の位置をずらしてある。幅方向の隙間を確保するためである。 FIG. 8 is a diagram showing the arrangement of the pipe support members 60 on the mold 2 side. As can be seen from this figure, the position of the first rod 61 and the second and third rods 62 and 63 are shifted in the tunnel axis direction. In other words, the cylindrical body 65 and the cylindrical bodies 66 and 67 are shifted in position in the tunnel axis direction. This is to ensure a gap in the width direction.
図9は型枠2側の配管支持部材60の穴埋め状態を示す図である。この図からわかるように、第1〜第3ロッド61〜63を筒状体65〜67より抜き去った後に、筒状体65〜67の穴を穴埋め部材65b、66b、67bにより塞ぐことができるようになっている。穴埋め部材65b、66b、67bの固定も固定ピン65a、66a、67aにより行う。 FIG. 9 is a diagram illustrating a state where the pipe support member 60 on the mold 2 side is filled. As can be seen from this figure, after the first to third rods 61 to 63 are removed from the cylindrical bodies 65 to 67, the holes of the cylindrical bodies 65 to 67 can be closed by the filling members 65b, 66b, 67b. It is like that. The hole filling members 65b, 66b, and 67b are also fixed by the fixing pins 65a, 66a, and 67a.
次に妻板8部の構成について説明する。図10は妻板8部の正面図、図11は妻板8部の断面図である。
覆工空間3Cの妻側を閉塞する妻板(妻型枠)8には、コンクリート打設管10を貫通させる貫通孔70が形成される。また、妻板8には、貫通孔70に連なって案内管71が取付けられる。案内管71は、妻板8の貫通孔70に連なって妻板8より覆工空間3Cの外部側に突出しており、コンクリート打設管10を挿入し得る内径を有している。また、案内管71の内周部には、コンクリート打設管10と摺接する例えばブラシ状のシール部材72が設けられる。
Next, the configuration of the 8 parts of the end plate will be described. FIG. 10 is a front view of 8 parts of the end plate, and FIG. 11 is a cross-sectional view of the 8 part of the end plate.
A through-hole 70 through which the concrete placing pipe 10 passes is formed in the end plate (end form) 8 that closes the end side of the lining space 3C. Further, a guide tube 71 is attached to the end plate 8 so as to continue to the through hole 70. The guide tube 71 is connected to the through hole 70 of the end plate 8 and protrudes from the end plate 8 to the outside of the lining space 3C, and has an inner diameter into which the concrete placing tube 10 can be inserted. Further, for example, a brush-like seal member 72 that is in sliding contact with the concrete placing pipe 10 is provided on the inner peripheral portion of the guide pipe 71.
また、妻板8の貫通孔70に対しては、貫通孔70からコンクリート打設管10を引き抜いたときに貫通孔70を閉止可能なシャッター73が設けられる。
シャッター73は、妻板8の外面と案内管71のフランジ部との間に設けられており、貫通孔70を開閉する板状のスライドゲート74と、このスライドゲート74をスライド可能に案内する案内部材75とから構成される。よって、案内部材75は、妻板8の外面と案内管71のフランジ部とから構成される。また、案内部材75には、スライドゲート74と摺接する例えばブラシ状のシール部材76が設けられる。
Further, a shutter 73 that can close the through hole 70 when the concrete placing pipe 10 is pulled out from the through hole 70 is provided for the through hole 70 of the end plate 8.
The shutter 73 is provided between the outer surface of the end plate 8 and the flange portion of the guide tube 71, and has a plate-like slide gate 74 that opens and closes the through hole 70, and a guide member that guides the slide gate 74 so as to be slidable. 75. Therefore, the guide member 75 includes the outer surface of the end plate 8 and the flange portion of the guide tube 71. The guide member 75 is provided with, for example, a brush-like seal member 76 that is in sliding contact with the slide gate 74.
スライドゲート74は手動で上下に移動可能である。下位置では、図11(a)のように貫通孔70(及び案内管71)を開通させ、下側の係止部77aに係止させたロック部材78により位置決めされる。上位置では、図11(b)のように貫通孔70(及び案内管71)を閉止し、上側の係止部77bに係止させたロック部材78により位置決めされる。スライドゲート74の移動は、人力による他、油圧ジャッキやジャーナルジャッキを用いて実施するようにしてもよい。 The slide gate 74 can be manually moved up and down. In the lower position, as shown in FIG. 11A, the through hole 70 (and the guide tube 71) is opened, and the positioning is performed by the lock member 78 engaged with the lower engagement portion 77a. In the upper position, as shown in FIG. 11B, the through hole 70 (and the guide tube 71) is closed and positioned by a lock member 78 engaged with the upper engaging portion 77b. The movement of the slide gate 74 may be performed using a hydraulic jack or a journal jack in addition to human power.
次にコンクリート打設管10へのコンクリート供給用配管について説明する。
図1〜図3を参照し、コンクリート打設管10へのコンクリート供給用配管は、コンクリート打設管10側から供給源側へ、第1連結管11、第2連結管12、第3連結管13及び第4連結管14を含んで構成される。
Next, the concrete supply pipe to the concrete placing pipe 10 will be described.
Referring to FIGS. 1 to 3, the concrete supply pipe to the concrete placement pipe 10 is a first connection pipe 11, a second connection pipe 12, and a third connection pipe from the concrete placement pipe 10 side to the supply source side. 13 and the fourth connecting pipe 14.
コンクリート打設管10の基端部は横方向に屈曲した後、下方向に屈曲し、下向きの第1連結部81を形成している。
第1連結管11は中間部が水平方向に配置され、一端側は上向きに屈曲して、前記第1連結部81にてコンクリート打設管10と回転自在に連結している。第1連結管11の他端側は上向きに屈曲して、第2連結部82を形成している。
The base end portion of the concrete placing pipe 10 is bent in the lateral direction and then bent downward to form a downward first connecting portion 81.
The first connecting pipe 11 has an intermediate portion arranged in the horizontal direction, and one end side is bent upward, and is connected to the concrete placing pipe 10 by the first connecting portion 81 so as to be rotatable. The other end side of the first connecting pipe 11 is bent upward to form a second connecting portion 82.
第2連結管12は中間部が水平方向に配置され(第1連結管11より高位置)、一端側は下向きに屈曲して、前記第2連結部82にて第1連結管11と回転自在に連結している。第2連結管12の他端側は下向きに屈曲して、第3連結部83を形成している。 The second connecting pipe 12 has an intermediate portion arranged in a horizontal direction (a position higher than the first connecting pipe 11), one end side is bent downward, and is rotatable with the first connecting pipe 11 at the second connecting portion 82. It is linked to. The other end side of the second connecting pipe 12 is bent downward to form a third connecting portion 83.
第3連結管13は中間部が水平方向でかつ台車40の長手方向に固定配置され(第2連結管12より低位置)、一端側は上向きに屈曲して、前記第3連結部83にて第2連結管12と回転自在に連結している。第3連結管13の他端側は下向きに屈曲して、台車40の天板41を貫通し、第4連結部84を形成している。 The third connecting pipe 13 has a middle portion fixed in the horizontal direction and in the longitudinal direction of the carriage 40 (lower position than the second connecting pipe 12), and one end side is bent upward, and the third connecting section 83 The second connection pipe 12 is rotatably connected. The other end side of the third connecting pipe 13 is bent downward and penetrates the top plate 41 of the carriage 40 to form a fourth connecting portion 84.
第4連結管14は、第3連結管13の第4連結部84に連結されて門型の台車40の内部空間へ延び、コンクリート供給源(図示せず)に接続される。 The fourth connecting pipe 14 is connected to the fourth connecting portion 84 of the third connecting pipe 13, extends into the internal space of the portal-type carriage 40, and is connected to a concrete supply source (not shown).
従って、図3を参照し、走行架台25の前進によるコンクリート打設管10の前進時には、第2連結管12が第3連結管13との連結部(第3連結部83)を中心として図示実線のように時計方向に回動し、これに追従して第2連結管12とコンクリート打設管10との間で第1連結管11が変位する。 Therefore, referring to FIG. 3, when the concrete placing pipe 10 is advanced by the advancement of the traveling gantry 25, the second connecting pipe 12 is illustrated with a solid connecting line (third connecting part 83) connected to the third connecting pipe 13 as a solid line. The first connecting pipe 11 is displaced between the second connecting pipe 12 and the concrete placing pipe 10 following the rotation.
また、走行架台25の後退によるコンクリート打設管10の後退時には、第2連結管12が第3連結管13との連結部(第3連結部83)を中心として図3の点線示のように反時計方向に回動し、これに追従して第2連結管12とコンクリート打設管10との間で第1連結管11が変位する。尚、図3の点線示の状態の側面図が図4である。 Further, when the concrete placing pipe 10 is retracted due to the retreat of the traveling base 25, the second connecting pipe 12 is centered on the connecting portion (third connecting portion 83) with the third connecting tube 13 as shown by the dotted line in FIG. The first connecting pipe 11 is displaced between the second connecting pipe 12 and the concrete placing pipe 10 following the rotation. FIG. 4 is a side view of the state shown by the dotted line in FIG.
これにより、走行架台25の前進・後退によるコンクリート打設管10の前進・後退を、第1及び第2連結管11、12の水平面内での変位により吸収することができる。 Thereby, the advance / retreat of the concrete placing pipe 10 due to the advance / retreat of the traveling frame 25 can be absorbed by the displacement of the first and second connecting pipes 11, 12 in the horizontal plane.
次に本実施形態のトンネル冠部覆工コンクリート打設システムを用いたトンネル冠部覆工コンクリート打設方法について説明する。
トンネル冠部の覆工空間3Cに覆工コンクリートを打設する際は、図4の状態から、打設管送り装置20のモータ30を正転させて、スプロケット28を回転させ、チェーン29により案内レール部材24上で走行架台25を前進させる。そして、図1に示すように、走行架台25の前進により、これに支持されているコンクリート打設管10を前進させ、コンクリート打設管10の先端部を妻板8部の案内管71に挿入し、貫通孔70を貫通させて、覆工空間3C内に進入させる。そして、最終的にはコンクリート打設管10の先端部を覆工空間3Cの最奥部付近(既設コンクリート7近傍)まで到達させる。
Next, a tunnel crown lining concrete placement method using the tunnel crown lining concrete placement system of this embodiment will be described.
When placing lining concrete in the lining space 3C at the crown of the tunnel, the sprocket 28 is rotated from the state shown in FIG. The traveling frame 25 is moved forward on the rail member 24. Then, as shown in FIG. 1, the concrete placement pipe 10 supported by the traveling base 25 is advanced by the advancement of the travel base 25, and the tip of the concrete placement pipe 10 is inserted into the guide pipe 71 of the end plate 8 part. Then, the through hole 70 is penetrated to enter the lining space 3C. Finally, the tip of the concrete placing pipe 10 is made to reach the vicinity of the innermost part of the lining space 3C (near the existing concrete 7).
このとき、案内レール部材24上で走行架台25が前進する際は、案内レール部材24上では、図4に示されるように配管支持部材50によりコンクリート打設管10を案内するが、走行架台25の前進に伴って案内を終えた配管支持部材50は、図1に示されるように案内位置から退避位置に付け替える。 At this time, when the traveling base 25 moves forward on the guide rail member 24, the concrete placing pipe 10 is guided on the guide rail member 24 by the pipe support member 50 as shown in FIG. As shown in FIG. 1, the pipe support member 50 that has been guided with the forward movement is changed from the guide position to the retracted position.
その一方、型枠2側では、覆工空間3C内でのコンクリート打設管10の前進に伴って、型枠2に取付けられている配管支持部材60を図4の状態から覆工空間3C内に突出させるように付け替えて、図1に示されるようにコンクリート打設管10を案内するようにする。 On the other hand, on the side of the mold 2, the piping support member 60 attached to the mold 2 is moved from the state of FIG. 4 to the inside of the lining space 3 </ b> C as the concrete placing pipe 10 advances in the lining space 3 </ b> C. The concrete placement pipe 10 is guided as shown in FIG.
コンクリート打設管10が最奥部まで移動した段階で、コンクリート供給源からコンクリートを圧送し、コンクリート打設管10の先端部から吐出させて、トンネル冠部の覆工空間3Cへのコンクリートの打設を開始する。 When the concrete placement pipe 10 has moved to the innermost part, the concrete is pumped from the concrete supply source and discharged from the tip of the concrete placement pipe 10 to put the concrete into the lining space 3C of the tunnel crown. Start installation.
覆工空間3C内へのコンクリートの打設に伴って、コンクリート打設管10の先端部付近のコンクリートの充填圧力が上昇すると、これが圧力センサ32により検知される。すなわち、コンクリートの充填圧力がコンクリート打設管10に作用し、コンクリート打設管10を後退させようとする結果、走行架台25を介してチェーン29a(図5)に引張力がかかり、これがシリンダ型の圧力センサ32により検知される。従って、コンクリートの充填圧力が所定値に達するごとに、モータ30を僅かずつ逆転させて、コンクリート打設管10を後退させることにより、所定の充填圧力で覆工コンクリートを打設することができる。 When the concrete filling pressure in the vicinity of the distal end portion of the concrete placement pipe 10 increases with the concrete placement in the lining space 3 </ b> C, this is detected by the pressure sensor 32. That is, as a result of the concrete filling pressure acting on the concrete placing pipe 10 and trying to retreat the concrete placing pipe 10, a tensile force is applied to the chain 29 a (FIG. 5) via the traveling frame 25. Is detected by the pressure sensor 32. Therefore, every time the concrete filling pressure reaches a predetermined value, the lining concrete can be placed with a predetermined filling pressure by reversing the motor 30 little by little and retreating the concrete placing pipe 10.
覆工空間3C内でのコンクリート打設管10の後退に伴って、案内作用を終えた配管支持部材60(第1〜第3ロッド61、62、63)を覆工空間3Cから順次退出させ、筒状体65〜67の穴を穴埋め部材65b〜67bで埋めることにより、コンクリート充填の邪魔にならないようにする。
その一方、案内レール部材24の側では、配管支持部材50を順次突出させて、コンクリート打設管10に対する案内作用を発揮させる。
With the retreat of the concrete placing pipe 10 in the lining space 3C, the pipe support members 60 (first to third rods 61, 62, 63) that have finished the guiding action are sequentially withdrawn from the lining space 3C, By filling the holes of the cylindrical bodies 65 to 67 with the hole filling members 65b to 67b, the concrete filling is not disturbed.
On the other hand, on the side of the guide rail member 24, the pipe support member 50 is sequentially projected to exert a guiding action on the concrete placing pipe 10.
最終的には、覆工空間3C内へのコンクリートの充填完了と共に、コンクリート打設管が覆工空間3C内から引き抜かれる。 Eventually, with the completion of filling of the concrete into the lining space 3C, the concrete placement pipe is pulled out from the lining space 3C.
この際、図11(a)→(b)に示されるように、コンクリート打設管10の後退移動によりコンクリート打設管10の先端部を妻板8の貫通孔70から引き抜くと同時に、シャッター73(スライドゲート74)により貫通孔70を閉止して、覆工コンクリートの打設を終了する。 At this time, as shown in FIGS. 11 (a) → (b), at the same time as the concrete placement pipe 10 is retracted from the through hole 70 of the end plate 8 by the backward movement of the concrete placement pipe 10, the shutter 73 ( The through hole 70 is closed by the slide gate 74), and the placement of the lining concrete is finished.
又は、コンクリート打設管10の後退移動によりコンクリート打設管10の先端部を妻板9の貫通孔70から引き抜いて案内管71内に位置させた状態で、案内管71の妻板8側でシャッター73(スライドゲート74)により案内管71を閉止して、覆工コンクリートの打設を終了する。しかる後、コンクリート打設管10の先端部を案内管71から引き抜く。 Alternatively, the shutter 73 on the side of the guide plate 71 on the side of the end plate 8 in a state where the end of the concrete placement tube 10 is pulled out from the through hole 70 of the end plate 9 and positioned in the guide tube 71 by the backward movement of the concrete placement tube 10. The guide pipe 71 is closed by the (slide gate 74), and the placing of the lining concrete is finished. Thereafter, the distal end portion of the concrete placing pipe 10 is pulled out from the guide pipe 71.
本実施形態によれば、コンクリート打設管10の吐出口を打設部の直近へ移動させて打設することができ、充填不足を低減することができる。また、打設中のコンクリートの移動量を抑制でき、その結果として、コンクリートの材料分離を低減できる。 According to this embodiment, it is possible to place the discharge port of the concrete placing pipe 10 by moving it to the position close to the placing portion, and to reduce insufficient filling. Moreover, the movement amount of the concrete during placement can be suppressed, and as a result, the material separation of the concrete can be reduced.
また、コンクリートの充填圧力を管理しながら、打設の進行に伴ってコンクリート打設管10を移動させるようにすれば、充填圧力をより適正に制御できる。 Moreover, if the concrete placement pipe 10 is moved with the progress of the placement while managing the concrete filling pressure, the filling pressure can be controlled more appropriately.
また、コンクリート打設管10の後退移動によりコンクリート打設管10を妻板8の貫通孔70から引き抜くと同時に、シャッター73(スライドゲート74)により貫通孔70を閉止して、覆工コンクリートの打設を終了することで、トンネル冠部の覆工空間3Cの全てに、すなわち妻板8の内面まで、必要十分な充填圧力で、コンクリートを打設することができ、充填性能を向上させることができる。言い換えれば、覆工空間3Cへの最終打込み(妻板8近傍への打設)をより確実なものとすることができる。 Further, the concrete placement pipe 10 is pulled out from the through hole 70 of the end plate 8 by the backward movement of the concrete placement pipe 10, and at the same time, the through hole 70 is closed by the shutter 73 (slide gate 74), and the lining concrete is placed. By completing the above, concrete can be placed in all the lining space 3C of the tunnel crown, that is, up to the inner surface of the end plate 8 with a necessary and sufficient filling pressure, and the filling performance can be improved. In other words, it is possible to make the final driving into the lining space 3 </ b> C (placement near the end plate 8) more reliable.
また、本実施形態によれば、妻板8の貫通孔70に連なって妻板8より外部側に突出し、コンクリート打設管10を案内する案内管71を備えることにより、コンクリート打設管10を妻板8の貫通孔70から引き抜いて、案内管71内に位置させた状態で、シャッター73(スライドゲート74)により貫通孔70を閉止するようにすれば、引き抜きによる妻板8近傍でのコンクリート充填圧力の低下を抑制することができ、作業性も向上する。 Further, according to the present embodiment, the concrete placing pipe 10 is connected to the through hole 70 of the end plate 8 and protrudes to the outside from the end plate 8, and is provided with the guide pipe 71 that guides the concrete placing pipe 10. If the through-hole 70 is closed by the shutter 73 (slide gate 74) while being pulled out from the through-hole 70 and positioned in the guide tube 71, the concrete filling pressure in the vicinity of the end plate 8 is reduced due to the extraction. Can be suppressed, and workability is also improved.
すなわち、コンクリート打設管10の後退移動によりコンクリート打設管10の先端部を案内管71内に位置させた状態で、案内管71の妻板8側でシャッター73(スライドゲート74)により案内管71を閉止して、覆工コンクリートの打設を終了することで、引き抜きによる妻板8近傍でのコンクリート充填圧力の低下を抑制することができ、作業性も向上する。 That is, the guide tube 71 is moved by the shutter 73 (slide gate 74) on the side of the end plate 8 of the guide tube 71 in a state where the tip of the concrete tube 10 is positioned in the guide tube 71 by the backward movement of the concrete placement tube 10. Is closed and the laying of the lining concrete is finished, so that a decrease in the concrete filling pressure in the vicinity of the end plate 8 due to drawing can be suppressed, and workability is also improved.
また、本実施形態によれば、シャッター73は、貫通孔70を開閉する板状のスライドゲート74と、このスライドゲート74をスライド可能に案内する案内部材75とから構成されることにより、コンパクトな構成で、スムーズに開閉することが可能となる。 Further, according to the present embodiment, the shutter 73 is composed of the plate-like slide gate 74 that opens and closes the through hole 70 and the guide member 75 that guides the slide gate 74 so as to be slidable. With the configuration, it is possible to open and close smoothly.
また、本実施形態によれば、案内管71は、その内周部に、コンクリート打設管10と摺接するシール部材72を有することにより、案内管71とコンクリート打設管10との間の隙間を通じてのコンクリートの洩れや充填圧力の低下を抑制することができる。 Further, according to the present embodiment, the guide pipe 71 has the seal member 72 in sliding contact with the concrete placing pipe 10 on the inner peripheral portion thereof, so that a gap between the guide pipe 71 and the concrete placing pipe 10 is obtained. It is possible to suppress the leakage of concrete and the decrease in filling pressure.
また、本実施形態によれば、シャッター73の案内部材75は、スライドゲート74と摺接するシール部材76を有することにより、案内部材75とスライドゲート74との間の隙間を通じてのコンクリートの洩れや充填圧力の低下を抑制することができる。 In addition, according to the present embodiment, the guide member 75 of the shutter 73 includes the seal member 76 that is in sliding contact with the slide gate 74, thereby leaking or filling the concrete through the gap between the guide member 75 and the slide gate 74. The pressure drop can be suppressed.
また、本実施形態によれば、打設管送り装置20は、台車40に載置されてトンネル軸方向に延在する案内レール部材24と、この案内レール部材24に沿って移動可能でコンクリート打設管10の基端部を支持する走行架台25と、を含んで構成されることにより、コンクリート打設管10を確実に前進及び後退移動させることができる。 Further, according to the present embodiment, the placement pipe feeding device 20 is mounted on the carriage 40 and extends along the tunnel axis direction, and the guide rail member 24 is movable along the guide rail member 24 and is cast into the concrete. By including the traveling platform 25 that supports the base end portion of the installation pipe 10, the concrete installation pipe 10 can be reliably moved forward and backward.
尚、図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。 The illustrated embodiment is merely an example of the present invention, and the present invention is not limited to the embodiment described directly, but includes various improvements and modifications made by those skilled in the art within the scope of the claims. Needless to say, it is included.
1 トンネル内周面
2 型枠
2A〜2G 型枠部材
3 覆工空間
3A トンネル側壁部(トンネル側壁部の覆工空間)
3B アーチ形状部(アーチ形状部の覆工空間)
3C トンネル冠部(トンネル冠部の覆工空間)
4 トンネル底部(インバート)
5 レール
6 ガントリー車
7 既設コンクリート
8 妻板
10 コンクリート打設管
11 第1連結管
12 第2連結管
13 第3連結管
14 第4連結管
20 打設管送り装置
21 第1ベース
22 第2ベース
23 ジャッキ
24 案内レール部材
25 走行架台
26 ホルダ
27、28 スプロケット
29 チェーン
30 モータ
31 ベベルギア
32 圧力センサ
40 台車
41 天板
50 配管支持部材
51 ローラ
52 支持体
60 配管支持部材
61 第1ロッド
62 第2ロッド
63 第3ロッド
64 案内ローラ
65、66、67 筒状体
65a、66a、67a 固定ピン
65b、66b、67b 穴埋め部材
70 貫通孔
71 案内管
72 シール部材
73 シャッター
74 スライドゲート
75 案内部材
76 シール部材
77a、77b 係止部
78 ロック部材
81 第1連結部
82 第2連結部
83 第3連結部
84 第4連結部
DESCRIPTION OF SYMBOLS 1 Tunnel inner peripheral surface 2 Formwork 2A-2G Formwork member 3 Covering space 3A Tunnel side wall part (covering space of tunnel side wall part)
3B Arch shape part (lining space for arch shape part)
3C Tunnel crown (lining space of tunnel crown)
4 Tunnel bottom (invert)
5 rail 6 gantry wheel 7 existing concrete 8 end plate 10 concrete placing pipe 11 first connecting pipe 12 second connecting pipe 13 third connecting pipe 14 fourth connecting pipe 20 placing pipe feeding device 21 first base 22 second base 23 Jack 24 Guide rail member 25 Travel base 26 Holder 27, 28 Sprocket 29 Chain 30 Motor 31 Bevel gear 32 Pressure sensor 40 Dolly 41 Top plate 50 Piping support member 51 Roller 52 Support body 60 Piping support member 61 First rod 62 Second rod 63 Third rod 64 Guide rollers 65, 66, 67 Cylindrical bodies 65a, 66a, 67a Fixing pins 65b, 66b, 67b Filling member 70 Through hole 71 Guide tube 72 Seal member 73 Shutter 74 Slide gate 75 Guide member 76 Seal member 77a, 77b Locking part 78 Locking member 81 No. Connecting portion 82 a second connecting portion 83 third connecting portion 84 fourth connecting portion
Claims (8)
トンネル軸方向に沿って延在し先端部に吐出口を有するコンクリート打設管と、
前記コンクリート打設管の基端部側を支持し、前記コンクリート打設管の先端部をトンネル軸方向に前記トンネル冠部の覆工空間の外部から妻板を貫通させて内部へ前進及び後退移動させる打設管送り装置と、
前記妻板に設けられて前記コンクリート打設管を貫通させる貫通孔と、
前記貫通孔から前記コンクリート打設管を引き抜いたときに前記貫通孔を閉止可能なシャッターと、
を含んで構成される、トンネル冠部覆工コンクリート打設システム。 It is a system for placing lining concrete in the lining space of the tunnel crown out of the lining space between the inner peripheral surface of the tunnel and the formwork opposed thereto,
A concrete placement pipe extending along the tunnel axis direction and having a discharge port at the tip;
Supporting the base end side of the concrete placing pipe, the forward end of the concrete placing pipe is moved forward and backward in the tunnel axial direction through the end plate from the outside of the tunnel crown lining space. A casting tube feeder;
A through hole provided in the end plate and penetrating the concrete placing pipe;
A shutter capable of closing the through hole when the concrete placing pipe is pulled out from the through hole;
A tunnel crown lining concrete placement system composed of
トンネル軸方向に沿って延在し先端部に吐出口を有するコンクリート打設管の基端部側を支持して、前記コンクリート打設管の先端部をトンネル軸方向に前記トンネル冠部の覆工空間の外部から妻板の貫通孔を貫通させて内部へ前進移動させるステップと、
前記コンクリート打設管により前記覆工空間内にコンクリートを打設しつつ、前記コンクリート打設管を後退移動させるステップと、
前記コンクリート打設管の後退移動により前記コンクリート打設管の先端部を前記貫通孔から引き抜くと同時に、シャッターにより前記貫通孔を閉止して、覆工コンクリートの打設を終了するステップと、
を含んで構成される、トンネル冠部覆工コンクリート打設方法。 It is a method of placing lining concrete in the lining space of the tunnel crown out of the lining space between the inner peripheral surface of the tunnel and the formwork opposed thereto,
Supporting the base end side of the concrete placement pipe extending along the tunnel axis direction and having a discharge port at the tip end, and covering the tunnel crown portion with the tip end portion of the concrete placement pipe in the tunnel axis direction A step of moving forward through the through hole of the end plate from the outside of the space,
Retreating the concrete placing pipe while placing concrete in the lining space by the concrete placing pipe;
Simultaneously pulling out the tip of the concrete placement pipe from the through hole by retreating the concrete placement pipe, and simultaneously closing the through hole with a shutter to finish placing the lining concrete;
A tunnel crown lining concrete placing method comprising:
トンネル軸方向に沿って延在し先端部に吐出口を有するコンクリート打設管の基端部側を支持して、前記コンクリート打設管の先端部をトンネル軸方向に前記トンネル冠部の覆工空間の外部から妻板の貫通孔に連なって該妻板より外部側に突出する案内管を貫通させて内部へ前進移動させるステップと、
前記コンクリート打設管により前記覆工空間内にコンクリートを打設しつつ、前記コンクリート打設管を後退移動させるステップと、
前記コンクリート打設管の後退移動により前記コンクリート打設管の先端部を前記案内管内に位置させた状態で、前記案内管の妻板側でシャッターにより前記案内管を閉止して、覆工コンクリートの打設を終了するステップと、
を含んで構成される、トンネル冠部覆工コンクリート打設方法。 It is a method of placing lining concrete in the lining space of the tunnel crown out of the lining space between the inner peripheral surface of the tunnel and the formwork opposed thereto,
Supporting the base end side of the concrete placement pipe extending along the tunnel axis direction and having a discharge port at the tip end, and covering the tunnel crown portion with the tip end portion of the concrete placement pipe in the tunnel axis direction A step of penetrating a guide tube protruding from the outside of the space to the through hole of the end plate and projecting outward from the end plate;
Retreating the concrete placing pipe while placing concrete in the lining space by the concrete placing pipe;
The guide tube is closed with a shutter on the side face of the guide tube while the tip of the concrete placement tube is positioned in the guide tube by the backward movement of the concrete placement tube, and the lining concrete is cast. A step to finish the setting,
A tunnel crown lining concrete placing method comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012229992A JP6074219B2 (en) | 2012-10-17 | 2012-10-17 | Tunnel crown lining concrete placement system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012229992A JP6074219B2 (en) | 2012-10-17 | 2012-10-17 | Tunnel crown lining concrete placement system and method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2014080811A true JP2014080811A (en) | 2014-05-08 |
JP6074219B2 JP6074219B2 (en) | 2017-02-01 |
Family
ID=50785234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2012229992A Active JP6074219B2 (en) | 2012-10-17 | 2012-10-17 | Tunnel crown lining concrete placement system and method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6074219B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110118094A (en) * | 2019-06-11 | 2019-08-13 | 成都睿智达科技有限公司 | Tunnel double-lining concrete longitudinal dispersion device for casting and its construction method |
CN110185473A (en) * | 2019-06-27 | 2019-08-30 | 四川德聚泽明建设工程有限公司 | A kind of the umbrella arch mixed mud casting device and implementation method of movable type |
CN110424985A (en) * | 2019-08-23 | 2019-11-08 | 中铁十一局集团第五工程有限公司 | A kind of anti-forward direction of coming to nothing of tunnel vault concrete is rushed to summit device |
CN110700854A (en) * | 2019-08-16 | 2020-01-17 | 中铁十二局集团有限公司 | Tunnel secondary lining vault concrete longitudinal continuous pouring construction method |
CN114198121A (en) * | 2021-12-15 | 2022-03-18 | 中国电建集团贵阳勘测设计研究院有限公司 | Grouting device for tunnel construction |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4888744A (en) * | 1972-02-24 | 1973-11-20 | ||
JPS53113141A (en) * | 1977-03-14 | 1978-10-03 | Kinki Tsuushin Kensetsu Kk | Method of placing concrete at tunnel secondary erecting time |
JPS60111997U (en) * | 1983-12-29 | 1985-07-29 | 株式会社 奥村組 | Tunnel concrete pouring equipment |
JPH06313399A (en) * | 1993-04-30 | 1994-11-08 | Tekken Constr Co Ltd | Tunnel lining device |
JPH08170495A (en) * | 1994-12-19 | 1996-07-02 | Saga Kogyo Kk | Concrete placing opening |
JPH108898A (en) * | 1996-06-19 | 1998-01-13 | Gifu Kogyo Kk | Method of vibrating placed concrete for tunnel and device therefor |
JP2001012196A (en) * | 2000-05-02 | 2001-01-16 | Saga Kogyo Kk | Compacting method for arch concrete and arch center for placing concrete |
JP2003253988A (en) * | 2002-03-05 | 2003-09-10 | Kawasaki Heavy Ind Ltd | Cutter bit exchanging device, exchanging method, and exchanging implement |
-
2012
- 2012-10-17 JP JP2012229992A patent/JP6074219B2/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4888744A (en) * | 1972-02-24 | 1973-11-20 | ||
JPS53113141A (en) * | 1977-03-14 | 1978-10-03 | Kinki Tsuushin Kensetsu Kk | Method of placing concrete at tunnel secondary erecting time |
JPS60111997U (en) * | 1983-12-29 | 1985-07-29 | 株式会社 奥村組 | Tunnel concrete pouring equipment |
JPH06313399A (en) * | 1993-04-30 | 1994-11-08 | Tekken Constr Co Ltd | Tunnel lining device |
JPH08170495A (en) * | 1994-12-19 | 1996-07-02 | Saga Kogyo Kk | Concrete placing opening |
JPH108898A (en) * | 1996-06-19 | 1998-01-13 | Gifu Kogyo Kk | Method of vibrating placed concrete for tunnel and device therefor |
JP2001012196A (en) * | 2000-05-02 | 2001-01-16 | Saga Kogyo Kk | Compacting method for arch concrete and arch center for placing concrete |
JP2003253988A (en) * | 2002-03-05 | 2003-09-10 | Kawasaki Heavy Ind Ltd | Cutter bit exchanging device, exchanging method, and exchanging implement |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110118094A (en) * | 2019-06-11 | 2019-08-13 | 成都睿智达科技有限公司 | Tunnel double-lining concrete longitudinal dispersion device for casting and its construction method |
CN110118094B (en) * | 2019-06-11 | 2024-02-27 | 成都睿智达科技有限公司 | Tunnel secondary lining concrete longitudinal dispersion pouring device and construction method thereof |
CN110185473A (en) * | 2019-06-27 | 2019-08-30 | 四川德聚泽明建设工程有限公司 | A kind of the umbrella arch mixed mud casting device and implementation method of movable type |
CN110185473B (en) * | 2019-06-27 | 2024-01-30 | 柯宇 | Mobile tunnel roof arch concrete pouring device and implementation method |
CN110700854A (en) * | 2019-08-16 | 2020-01-17 | 中铁十二局集团有限公司 | Tunnel secondary lining vault concrete longitudinal continuous pouring construction method |
CN110424985A (en) * | 2019-08-23 | 2019-11-08 | 中铁十一局集团第五工程有限公司 | A kind of anti-forward direction of coming to nothing of tunnel vault concrete is rushed to summit device |
CN114198121A (en) * | 2021-12-15 | 2022-03-18 | 中国电建集团贵阳勘测设计研究院有限公司 | Grouting device for tunnel construction |
CN114198121B (en) * | 2021-12-15 | 2023-12-19 | 中国电建集团贵阳勘测设计研究院有限公司 | Grouting device for tunnel construction |
Also Published As
Publication number | Publication date |
---|---|
JP6074219B2 (en) | 2017-02-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6074219B2 (en) | Tunnel crown lining concrete placement system and method | |
JP5997574B2 (en) | Tunnel crown lining concrete placement system and method | |
JP6074218B2 (en) | Tunnel crown lining concrete placement system and method | |
KR100951450B1 (en) | Turn-over device for pipe repairing tube with using vertically movable roller bracket | |
CN206987843U (en) | Geotextiles waterproof cloth and two lined steel muscle are plated in integrated bogie hearth | |
CN207598264U (en) | A kind of anchor bar of waterproof plate in tunnels is laid with trolley automatically | |
CN111156029A (en) | Tunnel secondary lining vault pouring construction device and construction method | |
CN102879553B (en) | Testing device for extruding and lining of concrete | |
JPH0358440B2 (en) | ||
CN116136157A (en) | Fully-mechanized coal face coal wall grouting reinforcement equipment and method | |
JP4566891B2 (en) | Tunnel lining concrete placement method | |
KR101712162B1 (en) | tapping machine for tap hole of furnace | |
CN115307568A (en) | Device and method for controlling tunnel excavation and supporting contour line through 3D scanning | |
JPH04302700A (en) | Segment lining device in parallel tunnel excavating shield machine | |
CN110030003B (en) | Anti-collapse excavation device for tunnel construction and process thereof | |
CN206635742U (en) | Steel sheet pile | |
JP3692124B2 (en) | Waste disposal method | |
CN109958458B (en) | Double-lining integrated complete tool construction equipment and application method | |
CN110145323B (en) | Earth excavation device applied to pipe curtain method and excavation method thereof | |
JP4602597B2 (en) | Tunnel construction machine | |
CN110107321B (en) | Fixed support frame mounting device applied to pipe curtain method and mounting method thereof | |
KR101035067B1 (en) | Immersed dry dock for connecting an underground tunnel to an immersed tunnel and the tunnel construction method by using it | |
JP4078988B2 (en) | Lined installation method and lined installation device for existing horseshoe-shaped waterway | |
JP2016017350A (en) | Horizontal erection device and horizontal erection method for board | |
CN114198121B (en) | Grouting device for tunnel construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20150625 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20160516 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20160524 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20160721 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20161220 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20170106 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6074219 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |