JP2013155485A JP2012014679A JP2012014679A JP2013155485A JP 2013155485 A JP2013155485 A JP 2013155485A JP 2012014679 A JP2012014679 A JP 2012014679A JP 2012014679 A JP2012014679 A JP 2012014679A JP 2013155485 A JP2013155485 A JP 2013155485A
Authority
JP
Japan
Prior art keywords
ground
tip
grout
ground improvement
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2012014679A
Other languages
Japanese (ja)
Other versions
JP5858574B2 (en
Inventor
Minoru Okuno
稔 奥野
Naoto Watanabe
直人 渡邊
Takeshi Inoue
武 井上
Taketo Kato
健人 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KFC Ltd
Original Assignee
KFC Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KFC Ltd filed Critical KFC Ltd
Priority to JP2012014679A priority Critical patent/JP5858574B2/en
Publication of JP2013155485A publication Critical patent/JP2013155485A/en
Application granted granted Critical
Publication of JP5858574B2 publication Critical patent/JP5858574B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a ground reinforcement structure capable of securely exhibiting the most effective bearing force on the whole ground reinforcement structure by securely forming a ground improvement body exhibiting bearing force necessary for a ground area at a periphery of a tip part of a rotary penetration tube.SOLUTION: There is provided a ground reinforcement structure including: a rotary penetration tube 10 which is provided with a closure surface 23 nearby a tip of a tube body and with a spiral blade 22 nearby the tip, has grout discharge holes 26, 28 nearby a peripheral wall and the tip of the tube body, and is driven rotating and penetrating the ground 100; a first ground improvement body 50 which is provided at the periphery of the tip part of the tube body, and formed by discharging grout so that soil grains of the ground 100 and the grout are mixed; and a second ground improvement body 60 which is provided on a rear end side of the first ground improvement body 50 at the periphery of the tube body substantially adjacently to the first ground improvement body 50, and formed by discharging grout.

Description

本発明は、先端近傍に螺旋羽根を有する回転貫入管を地盤に打設し、その周囲にグラウトによる地盤改良体を造成して地盤を補強する地盤補強構造及びその形成方法に関する。   The present invention relates to a ground reinforcement structure in which a rotary penetration pipe having a spiral blade in the vicinity of a tip is placed on the ground, and a ground improvement body by a grout is formed around the ground to reinforce the ground, and a method for forming the ground reinforcement structure.

従来、先端近傍に螺旋羽根を有する回転貫入管を地盤に打設し、その周囲にグラウトによる地盤改良体を造成することにより、螺旋羽根による先端支持力と地盤改良体の摩擦抵抗による支持力によって、支持力の増大を図るようにした地盤補強構造が知られている(特許文献1、2参照)。   Conventionally, a rotary penetrating pipe having a spiral blade near the tip is placed on the ground, and a ground improvement body by a grout is created around it, so that the tip support force by the spiral blade and the support force by the frictional resistance of the ground improvement body In addition, a ground reinforcement structure is known in which support force is increased (see Patent Documents 1 and 2).

このような地盤補強構造の例を図11に示す。図11の例では、回転貫入管110が下部補強管120と上部補強管130と接続管140とで構成され、地盤160に打設されている。下部補強管120には、管本体121の先端に螺旋羽根122が形成されていると共に、その外周に長手方向に間隔を開けて円周状の節突起123が形成され、更に、節突起123とは異なる位置に長手方向に間隔を開けて逆止弁付きのグラウト吐出孔124が形成されている。下部補強管120の後端部には図時省略するネジ構造の継ぎ手が設けられている。   An example of such a ground reinforcement structure is shown in FIG. In the example of FIG. 11, the rotary penetrating pipe 110 includes a lower reinforcing pipe 120, an upper reinforcing pipe 130, and a connecting pipe 140, and is placed on the ground 160. The lower reinforcing pipe 120 has a spiral blade 122 formed at the tip of the pipe body 121 and a circumferential node protrusion 123 formed on the outer periphery of the lower reinforcing pipe 120 with a space in the longitudinal direction. Grout discharge holes 124 with check valves are formed at different positions at intervals in the longitudinal direction. At the rear end of the lower reinforcing tube 120, a joint having a screw structure which is omitted in the drawing is provided.

上部補強管130には、管本体131の先端部に図時省略するネジ構造の継ぎ手が設けられている。また、接続管140は、本体141の外周に螺旋羽根142が設けられ、その両端にネジ構造の継ぎ手が形成されているものであり、本体141の両端に下部補強管120の継ぎ手と上部補強管130の継ぎ手がそれぞれ接続され、下部補強管120と上部補強管130が接続されるようになっている。接続管140の螺旋羽根142は、下部補強管120の先端の螺旋羽根122よりも大径に形成されている。   The upper reinforcing pipe 130 is provided with a screw-structure joint which is omitted in the drawing at the tip of the pipe body 131. In addition, the connecting pipe 140 is provided with spiral blades 142 on the outer periphery of the main body 141, and screw-type joints are formed at both ends thereof. The joint of the lower reinforcing pipe 120 and the upper reinforcing pipe are provided at both ends of the main body 141. 130 joints are connected to each other, and the lower reinforcing pipe 120 and the upper reinforcing pipe 130 are connected. The spiral blade 142 of the connection tube 140 is formed with a larger diameter than the spiral blade 122 at the tip of the lower reinforcing tube 120.

そして、地盤160に打設された回転貫入管110の周囲には、下部補強管120の先端の螺旋羽根122と接続管140の螺旋羽根142との間に、地盤改良体150が形成されている。この地盤改良体150は、回転貫入管110を地盤に回転圧入後、或いは地盤に回転圧入しながらグラウトを加圧注入し、グラウト吐出孔124から周囲の地盤にグラウトを吐出して形成されている。地盤改良体150が形成されている下部補強管120の先端の螺旋羽根122と接続管140の螺旋羽根142との間は定着長領域、接続管140の螺旋羽根142と地表面161との間は自由長領域である。   A ground improvement body 150 is formed around the rotary penetration pipe 110 placed on the ground 160 between the spiral blade 122 at the tip of the lower reinforcing pipe 120 and the spiral blade 142 of the connection pipe 140. . The ground improvement body 150 is formed by injecting the grout after the rotary penetration tube 110 is rotationally press-fitted into the ground or while being rotationally press-fitted into the ground, and discharging the grout from the grout discharge hole 124 to the surrounding ground. . Between the spiral blade 122 at the tip of the lower reinforcing pipe 120 where the ground improvement body 150 is formed and the spiral blade 142 of the connection pipe 140, there is a fixed length region, and between the spiral blade 142 of the connection pipe 140 and the ground surface 161. It is a free length area.

特開2008−57113号公報JP 2008-57113 A 特開2011−26910号公報JP 2011-26910 A

しかしながら、上記地盤補強構造では、回転貫入管110の先端が開放されている場合、回転貫入管110の先端近傍の内部に土砂が入り込み、先端部周囲の地盤領域Rにグラウトを十分に注入できなくなり、地盤領域Rに必要な支持力を発揮する地盤改良体を形成できないことがある。また、回転貫入管110の先端が閉塞されている場合にも、回転貫入管110の打設時に回転貫入管110の先端部周囲の地盤領域Rがかなり圧密となり、先端部周囲の地盤領域Rにグラウトを十分に注入できなくなり、地盤領域Rに必要な支持力を発揮する地盤改良体を形成することが難しい場合がある。   However, in the ground reinforcement structure, when the tip of the rotary penetrating pipe 110 is open, earth and sand enter the vicinity of the tip of the rotary penetrating pipe 110, and the grout cannot be sufficiently injected into the ground region R around the tip portion. In some cases, it is not possible to form a ground improvement body that exhibits the supporting force necessary for the ground region R. Further, even when the tip of the rotary penetrating tube 110 is closed, the ground region R around the tip of the rotary penetrating tube 110 becomes considerably compacted when the rotary penetrating tube 110 is placed, and the ground region R around the tip portion is compressed. In some cases, it becomes difficult to form a ground improvement body that cannot sufficiently inject the grout and exhibits the supporting force necessary for the ground region R.

即ち、図11例は、螺旋羽根142より下の回転貫入管110の周囲全体に同一径で均質なグラウトによる定着長領域を形成し、摩擦力により杭支持力を得るものであるにもかかわらず、定着長領域のグラウト径や密度にムラが生じている可能性がある。この種の地盤補強構造では、所定長の回転貫入管110に対し、グラウトによって最も効果的な地盤改良体が形成され、且つその地盤改良体と回転貫入管110自体が最も的確に一体をなしていることが肝要であるのに、地盤に対するグラウト状態が不安定では安定的な地盤補強構造が得られない。   That is, in the example of FIG. 11, a fixed length region by a uniform grout having the same diameter is formed around the rotary penetration tube 110 below the spiral blade 142, and a pile supporting force is obtained by a frictional force. There is a possibility that the grout diameter and density in the fixing length region are uneven. In this type of ground reinforcement structure, the most effective ground improvement body is formed by the grout with respect to the predetermined length of the rotary penetration pipe 110, and the ground improvement body and the rotary penetration pipe 110 itself are most accurately integrated. However, if the grout state with respect to the ground is unstable, a stable ground reinforcement structure cannot be obtained.

本発明は上記課題を解決するために提案するものであり、回転貫入管の先端部周囲の地盤領域に必要な支持力を発揮する地盤改良体を確実に形成し、延いては地盤補強構造全体として最も効果的な支持力を確実に且つ安定して発揮することができる地盤補強構造及びその形成方法を提供することを目的とする。   The present invention proposes to solve the above-mentioned problems, and reliably forms a ground improvement body that exhibits a necessary supporting force in the ground area around the distal end portion of the rotary penetrating pipe, thereby extending the entire ground reinforcing structure. An object of the present invention is to provide a ground reinforcement structure capable of reliably and stably exhibiting the most effective support force and a method for forming the same.

本発明の地盤補強構造は、管本体の先端等の先端近傍に土砂侵入防止部が設けられ且つ先端近傍に螺旋羽根が設けられており、前記管本体の周壁と先端等の先端近傍にグラウト吐出孔が形成され、地盤に回転貫入して打設されている回転貫入管と、前記管本体の先端部の周囲に設けられ、地盤の土粒子とグラウトが混合されるようにグラウトを吐出して形成されている第1の地盤改良体と、前記管本体の周囲における前記第1の地盤改良体の後端側に前記第1の地盤改良体と略隣接して設けられ、グラウトを吐出して形成されている第2の地盤改良体とを有することを特徴とする。
この構成によれば、回転貫入管の先端部周囲の地盤領域に地盤の土粒子とグラウトが混合されるように第1の地盤改良体が形成され、回転貫入管の先端部周囲の地盤領域に必要な支持力を発揮する第1の地盤改良体を確実に形成することができる。また、先端部周囲の地盤領域に形成された第1の地盤改良体は、先端近傍の螺旋羽根の変形を抑制することが可能であり、この螺旋羽根によって所要の先端支持力を得ることができる。また、先端近傍の螺旋羽根の形状維持により、第1、第2の地盤改良体に集中的な応力が伝播することを低減することが可能であり、第1、第2の地盤改良体の破壊を防止することができる。また、第1、第2の地盤改良体が安定して存置されるので、第1、第2の地盤改良体により大きな周面摩擦力とその支持力を安定して得ることができる。また、第1、第2の地盤改良体が略隣接することにより、第1、第2の地盤改良体で応力の分散を図ることができる。従って、回転貫入管、及びその先端近傍の螺旋羽根、第1、第2の地盤改良体を一体的に機能させ、地盤補強構造全体として最も効果的な支持力を確実に且つ安定して発揮することができる。
The ground reinforcing structure of the present invention is provided with a sediment intrusion prevention portion near the tip such as the tip of the pipe body and a spiral blade near the tip, and the grout is discharged near the peripheral wall of the pipe body and the tip such as the tip. A hole is formed and provided around the tip of the tube main body and a rotary penetrating tube that is driven to rotate into the ground, and the grout is discharged so that the soil particles and grout of the ground are mixed. A first ground improvement body that is formed, and a rear end side of the first ground improvement body around the pipe body, provided substantially adjacent to the first ground improvement body, and discharging a grout It has the 2nd ground improvement body currently formed, It is characterized by the above-mentioned.
According to this configuration, the first ground improvement body is formed so that the soil particles and the grout of the ground are mixed in the ground area around the tip of the rotary penetrating pipe, and the ground area around the tip of the rotary penetrating pipe is formed. The 1st ground improvement body which exhibits required support power can be formed reliably. In addition, the first ground improvement body formed in the ground region around the tip can suppress the deformation of the spiral blade near the tip, and a required tip support force can be obtained by the spiral blade. . Further, by maintaining the shape of the spiral blade near the tip, it is possible to reduce the propagation of intensive stress to the first and second ground improvement bodies, and the destruction of the first and second ground improvement bodies. Can be prevented. In addition, since the first and second ground improvement bodies are stably placed, a large peripheral friction force and its supporting force can be stably obtained by the first and second ground improvement bodies. In addition, since the first and second ground improvement bodies are substantially adjacent to each other, the first and second ground improvement bodies can distribute stress. Therefore, the rotary penetration pipe, the spiral blade near the tip thereof, and the first and second ground improvement bodies function integrally, and the most effective support force as the entire ground reinforcing structure is reliably and stably exhibited. be able to.

本発明の地盤補強構造は、前記第2の地盤改良体が、前記第1の地盤改良体と隣接する箇所から後端側に向かって略テーパ状に拡径するテーパ部から構成されていることを特徴とする。
この構成によれば、第2の地盤改良体のテーパ部により、周面摩擦力を一層増大させ、地盤補強構造の支持力を増大することができる。
In the ground reinforcing structure of the present invention, the second ground improvement body is configured by a taper portion that expands in a substantially tapered shape from a position adjacent to the first ground improvement body toward the rear end side. It is characterized by.
According to this configuration, the peripheral frictional force can be further increased by the tapered portion of the second ground improvement body, and the supporting force of the ground reinforcing structure can be increased.

本発明の地盤補強構造は、前記回転貫入管の前記管本体の中間部位に、前記螺旋羽根より大径の別の螺旋羽根が設けられており、前記第2の地盤改良体が、前記別の螺旋羽根に対して前記管本体の先端側と後端側に形成されていることを特徴とする。
この構成によれば、第2の地盤改良体の先端側の部分を別の螺旋羽根で押圧し、第1、第2の地盤改良体に対する押込力を高めることができる。また、第2の地盤改良体の後端側の部分で別の螺旋羽根を押圧し、第1、第2の地盤改良体及び回転貫入管の押込力を一層高めることができる。
In the ground reinforcing structure of the present invention, another spiral blade having a diameter larger than that of the spiral blade is provided at an intermediate portion of the tube main body of the rotary penetrating pipe, and the second ground improvement body is the other It is formed in the front end side and rear end side of the said tube main body with respect to a spiral blade.
According to this configuration, it is possible to increase the pushing force against the first and second ground improvement bodies by pressing the tip side portion of the second ground improvement body with the other spiral blade. Further, another spiral blade is pressed at the rear end portion of the second ground improvement body, and the pushing force of the first and second ground improvement bodies and the rotary penetrating pipe can be further increased.

本発明の地盤補強構造は、前記第2の地盤改良体の前記別の螺旋羽根に対して前記管本体の先端側に形成されている部分のグラウト密度が、前記第1の地盤改良体のグラウト密度より高いことを特徴とする。
この構成によれば、比較的大きな応力が負荷されやすい第2の地盤改良体の先端側の部分について、グラウト密度が高く圧縮強度やせん断強度が高いものとすることができ、地盤補強構造全体としての強度、支持力をより一層高めることができる。
In the ground reinforcement structure of the present invention, the grout density of the portion formed on the distal end side of the tube main body with respect to the other spiral blade of the second ground improvement body is the grout of the first ground improvement body. It is characterized by higher density.
According to this configuration, the portion on the tip side of the second ground improvement body that is likely to be loaded with a relatively large stress can have a high grout density and a high compressive strength or shear strength. The strength and supporting force can be further increased.

本発明の地盤補強構造は、前記回転貫入管の先端に爪状部が突出して形成されていることを特徴とする。
この構成によれば、回転貫入管の爪状部と第1の地盤改良体等が相俟って、地盤の支持層への荷重伝達性能が一層良好となり、地盤補強構造全体としての強度、支持力をより一層高めることができる。
The ground reinforcing structure of the present invention is characterized in that a claw-like portion protrudes from the tip of the rotary penetrating tube.
According to this structure, the claw-like portion of the rotary penetrating pipe and the first ground improvement body combine to improve the load transmission performance to the ground support layer, and the strength and support of the ground reinforcement structure as a whole. The power can be further increased.

本発明の地盤補強構造の形成方法は、管本体の先端等の先端近傍に土砂侵入防止部が設けられ且つ先端近傍に螺旋羽根が設けられ、前記管本体の周壁と先端等の先端近傍にグラウト吐出孔が形成されている回転貫入管を、地盤に回転貫入して打設する第1工程と、地盤の土粒子とグラウトが混合されるように、前記グラウト吐出孔からグラウトを吐出すると共に前記回転貫入管を長手方向に前後動させ、前記管本体の先端部の周囲に第1の地盤改良体を形成する第2工程と、前記管本体の周囲における前記第1の地盤改良体の後端側に、グラウトを吐出して前記第1の地盤改良体と略隣接するように第2の地盤改良体を形成する第3工程とを備えることを特徴とする。
この構成によれば、回転貫入管の先端部周囲の地盤領域に地盤の土粒子とグラウトが混合された第1の地盤改良体を簡易且つ効率的に形成することができると共に、回転貫入管の先端部周囲の地盤領域に必要な支持力を発揮する第1の地盤改良体を確実に形成することができる。また、先端部周囲の地盤領域に形成された第1の地盤改良体は、先端近傍の螺旋羽根の変形を抑制することが可能であり、この螺旋羽根によって所要の先端支持力を得ることができる。また、先端近傍の螺旋羽根の形状維持により、第1、第2の地盤改良体に集中的な応力が伝播することを低減することが可能であり、第1、第2の地盤改良体の破壊を防止することができる。また、第1、第2の地盤改良体を安定して存置することができるので、第1、第2の地盤改良体により大きな周面摩擦力とその支持力を安定して得ることができる。また、第1、第2の地盤改良体が略隣接することにより、第1、第2の地盤改良体で応力の分散を図ることができる。従って、回転貫入管、及びその先端近傍の螺旋羽根、第1、第2の地盤改良体を一体的に機能させ、地盤補強構造全体として最も効果的な支持力を確実に且つ安定して発揮することができる。
The method for forming a ground reinforcing structure according to the present invention includes a sand intrusion prevention portion provided near the tip of the pipe body such as a tip, and a spiral blade provided near the tip, and a grout near the tip of the peripheral wall and the tip of the pipe body. A first step of driving the rotary penetration pipe formed with the discharge hole into the ground by rotating, and discharging the grout from the grout discharge hole so that the soil particles and the grout of the ground are mixed. A second step of moving the rotary penetrating pipe back and forth in the longitudinal direction to form a first ground improvement body around the tip of the pipe body; and a rear end of the first ground improvement body around the pipe body And a third step of forming a second ground improvement body by discharging grout on the side so as to be substantially adjacent to the first ground improvement body.
According to this configuration, the first ground improvement body in which the soil particles and the grout of the ground are mixed can be easily and efficiently formed in the ground area around the tip of the rotary penetration pipe. It is possible to reliably form the first ground improvement body that exhibits the necessary supporting force in the ground area around the tip. In addition, the first ground improvement body formed in the ground region around the tip can suppress the deformation of the spiral blade near the tip, and a required tip support force can be obtained by the spiral blade. . Further, by maintaining the shape of the spiral blade near the tip, it is possible to reduce the propagation of intensive stress to the first and second ground improvement bodies, and the destruction of the first and second ground improvement bodies. Can be prevented. In addition, since the first and second ground improvement bodies can be stably placed, a large peripheral friction force and a supporting force can be stably obtained by the first and second ground improvement bodies. In addition, since the first and second ground improvement bodies are substantially adjacent to each other, the first and second ground improvement bodies can distribute stress. Therefore, the rotary penetration pipe, the spiral blade near the tip thereof, and the first and second ground improvement bodies function integrally, and the most effective support force as the entire ground reinforcing structure is reliably and stably exhibited. be able to.

本発明の地盤補強構造或いはその形成方法によれば、回転貫入管の先端部周囲の地盤領域に必要な支持力を発揮する地盤改良体を確実に形成し、延いては地盤補強構造全体として最も効果的な支持力を確実に且つ安定して発揮することができる地盤補強構造とすることができる。   According to the ground reinforcement structure of the present invention or the method of forming the ground reinforcement structure, the ground improvement body that exhibits the necessary supporting force is reliably formed in the ground area around the distal end portion of the rotary penetrating pipe. It can be set as the ground reinforcement structure which can exhibit an effective supporting force reliably and stably.

実施形態の地盤補強構造の断面説明図。Cross-sectional explanatory drawing of the ground reinforcement structure of embodiment. 実施形態の地盤補強構造における回転貫入管を示す正面図。The front view which shows the rotation penetration pipe in the ground reinforcement structure of embodiment. (a)〜(c)は回転貫入管の接続を説明する説明図。(A)-(c) is explanatory drawing explaining the connection of a rotation penetration pipe. (a)は図2の回転貫入管の螺旋羽根近傍を示す正面図、(b)はその回転貫入管先端の爪状部の配置を示す底面図、(c)は同図(b)のA−A線矢視図、(d)は同図(b)のB−B線矢視図。(A) is a front view showing the vicinity of the spiral blade of the rotary penetrating pipe in FIG. 2, (b) is a bottom view showing the arrangement of the claw-like portions at the tip of the rotary penetrating pipe, and (c) is A in FIG. -A line arrow directional view, (d) is the BB line arrow directional view of the same figure (b). (a)〜(f)は実施形態の地盤補強構造の形成方法における施工手順を示す説明図。(A)-(f) is explanatory drawing which shows the construction procedure in the formation method of the ground reinforcement structure of embodiment. (a)は口元バルブ方式による第2の地盤改良体の形成を示す説明図、(b)はシングルパッカー方式による第2の地盤改良体の形成を示す説明図、(c)はダブルパッカー方式による第2の地盤改良体の形成を示す説明図。(A) is explanatory drawing which shows formation of the 2nd ground improvement body by a mouth valve system, (b) is explanatory drawing which shows formation of the 2nd ground improvement body by a single packer system, (c) is by a double packer system Explanatory drawing which shows formation of a 2nd ground improvement body. (a)は第1変形例における回転貫入管の螺旋羽根近傍を示す正面図、(b)はその回転貫入管先端の爪状部の配置を示す底面図、(c)は第1の爪状部の正面図、(d)は第2の爪状部の正面図。(A) is a front view showing the vicinity of the spiral blade of the rotary penetration pipe in the first modification, (b) is a bottom view showing the arrangement of the claw-like portions at the tip of the rotary penetration pipe, and (c) is the first claw-like shape. The front view of a part, (d) is a front view of a 2nd nail | claw-shaped part. (a)は第2変形例における回転貫入管の螺旋羽根近傍を示す正面図、(b)はその断面図、(c)はその底面図。(A) is a front view which shows the spiral blade vicinity of the rotation penetration pipe | tube in a 2nd modification, (b) is the sectional drawing, (c) is the bottom view. (a)は実施形態及び変形例の地盤補強構造に発生する垂直応力の応力分布図、(b)はそのせん断応力の応力分布図。(A) is a stress distribution diagram of the normal stress which generate | occur | produces in the ground reinforcement structure of embodiment and a modification, (b) is a stress distribution diagram of the shear stress. 実施形態及び変形例の地盤補強構造と従来例の地盤補強構造の荷重−変位量曲線を示す図。The figure which shows the load-displacement amount curve of the ground reinforcement structure of embodiment and a modification, and the ground reinforcement structure of a prior art example. 従来例の地盤補強構造を示す断面説明図。Cross-sectional explanatory drawing which shows the ground reinforcement structure of a prior art example.

〔実施形態の地盤補強構造及びその形成方法〕
本実施形態の地盤補強構造は、図1に示すように、地表面101から地盤100に回転貫入して打設されている回転貫入管10と、回転貫入管10の先端部の周囲に設けられる第1の地盤改良体50、第1の地盤改良体50の後端側の位置で、回転貫入管10の周囲に設けられる第2の地盤改良体60とから構成される。
[Embodiment of ground reinforcement structure and method of forming the same]
As shown in FIG. 1, the ground reinforcing structure of the present embodiment is provided around a rotary penetrating tube 10 that is driven to rotate from the ground surface 101 to the ground 100, and a distal end portion of the rotating penetrating tube 10. The first ground improvement body 50 and the second ground improvement body 60 provided around the rotary penetrating pipe 10 at a position on the rear end side of the first ground improvement body 50 are configured.

図1及び図2の例の回転貫入管10は、図3(a)の先端補強管20と図3(b)の後続補強管30とが接続されているものであるが、更に、地盤補強に必要な打込み深さが深い場合等の必要に応じて、後続補強管30の後側に別の後続補強管40を接続して、回転貫入管10を構成することが可能である。後続補強管30の後側に接続する別の後続補強管40は、単数或いは複数とすることが可能である。また、別の後続補強管40を接続する位置は、地盤によって後続補強管30の前側に接続して使用することもできる。   The rotary penetrating pipe 10 in the example of FIGS. 1 and 2 is such that the tip reinforcing pipe 20 in FIG. 3A and the subsequent reinforcing pipe 30 in FIG. 3B are connected. The rotary penetration tube 10 can be configured by connecting another subsequent reinforcement tube 40 to the rear side of the subsequent reinforcement tube 30 as necessary, for example, when the driving depth required for the above is deep. The number of other subsequent reinforcing pipes 40 connected to the rear side of the subsequent reinforcing pipe 30 can be one or more. Moreover, the position which connects another subsequent reinforcement pipe | tube 40 can also be connected and used for the front side of the subsequent reinforcement pipe | tube 30 by the ground.

先端補強管20は、図1〜図4に示すように、管本体21の先端近傍に螺旋羽根22が形成されていると共に、その先端には、回転貫入管10の管本体の土砂侵入防止部に相当する閉塞面23が設けられている。更に、閉塞面23には爪状部24が設けられており、爪状部24は先端補強管20の先端面である閉塞面23から突出形成されている。本例の各爪状部24は、その先端面がスロープ状の傾斜面で底面視では直線状になっており、略円周方向に所定間隔を開けて複数個(本例では4個)設けられ、周方向に山と谷を有する形状で配置されている。   As shown in FIGS. 1 to 4, the tip reinforcing pipe 20 has a spiral blade 22 formed in the vicinity of the tip of the pipe main body 21. A closing surface 23 corresponding to is provided. Further, a claw-like portion 24 is provided on the closing surface 23, and the claw-like portion 24 is formed so as to protrude from the closing surface 23 that is the tip surface of the tip reinforcing tube 20. Each claw-like portion 24 of this example has a sloped inclined surface and a straight line when viewed from the bottom, and a plurality of (four in this example) are provided at predetermined intervals in the circumferential direction. It is arranged in a shape having a mountain and a valley in the circumferential direction.

先端補強管20の外周には、地盤100と先端補強管20との荷重伝達性能を高めるため、長手方向に間隔を開けて円周状の節突起25が形成されている。更に、節突起25とは異なる位置に長手方向に間隔を開けて逆止弁付きのグラウト吐出孔26が形成され、回転貫入管10の管本体周壁のグラウト吐出孔を構成している。先端補強管20の後端部には、雄ねじの継ぎ手27が形成されている。   In order to enhance the load transmission performance between the ground 100 and the tip reinforcing tube 20, circumferential node protrusions 25 are formed on the outer periphery of the tip reinforcing tube 20 at intervals in the longitudinal direction. Further, a grout discharge hole 26 with a check valve is formed at a position different from the node protrusion 25 in the longitudinal direction, and constitutes a grout discharge hole on the peripheral wall of the rotary penetrating pipe 10. A male threaded joint 27 is formed at the rear end of the tip reinforcing tube 20.

更に、先端補強管20の閉塞面23には、その略中央に逆止弁付きのグラウト吐出孔28が形成されていると共に、先端補強管20の先端部内にはグラウト吐出孔28の逆止弁であるバネ式逆止弁281が設けられており、先端補強管20の閉塞面23より先端側にもグラウトを吐出可能になっている。   Further, a grout discharge hole 28 with a check valve is formed at the approximate center of the closing surface 23 of the tip reinforcing pipe 20, and a check valve of the grout discharge hole 28 is provided in the tip of the tip reinforcing pipe 20. The spring type check valve 281 is provided so that the grout can be discharged to the tip side from the closing surface 23 of the tip reinforcing pipe 20.

後続補強管30は、管本体31の先端部に雌ねじの継ぎ手32が形成されていると共に、その後端部に雄ねじの継ぎ手33が形成されており、周壁にはグラウト吐出孔34が形成されている。後続補強管30の管本体31の外周には螺旋羽根35が設けられており、螺旋羽根35は先端補強管20の先端補強管20の先端の螺旋羽根22よりも大径に形成されている。管本体31の長手方向における螺旋羽根35の取付位置は任意であり、螺旋羽根35は管本体31の所要位置に工場で加工して取り付けられる。尚、必要に応じて後続補強管30に接続される別の後続補強管40は、管本体41の先端部に雌ねじの継ぎ手42、その後端部に雄ねじの継ぎ手43が形成され、周壁にはグラウト吐出孔44が形成されている。   The subsequent reinforcing pipe 30 has a female threaded joint 32 formed at the distal end of the pipe body 31 and a male threaded joint 33 formed at the rear end thereof, and a grout discharge hole 34 is formed in the peripheral wall. . A spiral blade 35 is provided on the outer periphery of the tube body 31 of the subsequent reinforcing tube 30, and the spiral blade 35 is formed to have a larger diameter than the spiral blade 22 at the tip of the tip reinforcing tube 20 of the tip reinforcing tube 20. The attachment position of the spiral blade 35 in the longitudinal direction of the tube body 31 is arbitrary, and the spiral blade 35 is processed and attached to a required position of the tube body 31 at the factory. If necessary, another succeeding reinforcing pipe 40 connected to the succeeding reinforcing pipe 30 is formed with a female threaded joint 42 at the distal end of the pipe body 41 and a male threaded joint 43 at the rear end, and a grout on the peripheral wall. A discharge hole 44 is formed.

そして、先端補強管20の継ぎ手27と後続補強管30の継ぎ手32とを螺合して接続することにより、或いは、先端補強管20の継ぎ手27と後続補強管30の継ぎ手32とを螺合して接続し、且つ後続補強管30の継ぎ手33と別の後続補強管40の継ぎ手42とを螺合して接続することにより、先端補強管20と後続補強管30、或いは先端補強管20と後続補強管30、40が地盤100に打設される。打設された回転貫入管10において後続補強管30の螺旋羽根35は、回転貫入管10の管本体の中間部位に配置される。   Then, the joint 27 of the tip reinforcing pipe 20 and the joint 32 of the subsequent reinforcing pipe 30 are screwed together and connected, or the joint 27 of the tip reinforcing pipe 20 and the joint 32 of the subsequent reinforcing pipe 30 are screwed together. And connecting the joint 33 of the subsequent reinforcing pipe 30 and the joint 42 of another subsequent reinforcing pipe 40 to each other, thereby connecting the tip reinforcing pipe 20 and the succeeding reinforcing pipe 30 or the tip reinforcing pipe 20 and the following. The reinforcing pipes 30 and 40 are driven on the ground 100. In the rotary penetrating pipe 10 that has been placed, the spiral blade 35 of the subsequent reinforcing pipe 30 is disposed at an intermediate portion of the pipe body of the rotary penetrating pipe 10.

第1の地盤改良体50は、回転貫入管10の管本体の先端部の周囲に設けられ、図示例では先端補強管20の略先端側の半分程度の長さで先端補強管20の周囲に設けられ、更に先端補強管20の先端側にも設けられている。第1の地盤改良体50は、地盤100の土粒子とグラウトが混合されるようにグラウトを吐出して形成されている。   The first ground improvement body 50 is provided around the distal end portion of the tube main body of the rotary penetrating tube 10. In the illustrated example, the first ground improvement body 50 is approximately half the length of the distal end reinforcing tube 20 around the distal end reinforcing tube 20. It is also provided on the tip side of the tip reinforcing tube 20. The first ground improvement body 50 is formed by discharging the grout so that the soil particles of the ground 100 and the grout are mixed.

第2の地盤改良体60は、回転貫入管10の管本体の周囲における第1の地盤改良体50の後端側に第1の地盤改良体50と略隣接して設けられており、地盤100にグラウトを吐出して形成されている。第2の地盤改良体60は、別の螺旋羽根に相当する螺旋羽根35に対して、回転貫入管10の管本体の先端側と後端側に形成されており、第1の地盤改良体50と隣接する箇所から螺旋羽根35に略対応する箇所まで、後端側に向かって略テーパ状に拡径するテーパ部61と、テーパ部61の後側に設けられる略筒状若しくは螺旋羽根35に略対応する箇所から後端側に向かって略テーパ状に縮径する後部62とから構成される。   The second ground improvement body 60 is provided substantially adjacent to the first ground improvement body 50 on the rear end side of the first ground improvement body 50 around the pipe body of the rotary penetrating pipe 10. It is formed by discharging grout. The second ground improvement body 60 is formed on the front end side and the rear end side of the pipe body of the rotary penetrating pipe 10 with respect to the spiral blade 35 corresponding to another spiral blade, and the first ground improvement body 50. From the location adjacent to the spiral blade 35 to the location substantially corresponding to the spiral blade 35, the taper portion 61 that expands in a substantially tapered shape toward the rear end side, and the substantially cylindrical or spiral blade 35 provided on the rear side of the taper portion 61 It is comprised from the rear part 62 which diameter-reduces in a substantially taper shape toward the rear-end side from the substantially corresponding location.

第2の地盤改良体60において、少なくとも螺旋羽根35に対して管本体の先端側に形成されている部分、即ちテーパ部61のグラウト密度は、第1の地盤改良体50のグラウト密度より高くなるようにして形成されており、少なくとも第2の地盤改良体60におけるテーパ部61の強度は、第1の地盤改良体50の強度より高くなっている。   In the second ground improvement body 60, at least the portion formed on the distal end side of the pipe body with respect to the spiral blade 35, that is, the grout density of the taper portion 61 is higher than the grout density of the first ground improvement body 50. Thus, the strength of the tapered portion 61 in at least the second ground improvement body 60 is higher than the strength of the first ground improvement body 50.

本実施形態の地盤補強構造を形成する際には、図5(a)、(b)に示すように、回転貫入管10を地盤100に回転貫入する。回転貫入管10の回転貫入では、図示省略する削孔機に先端補強管20を取り付けて地盤100に回転貫入し、先端補強管20を所定深さまで貫入した後に後続補強管30を接続し、後続補強管30を削孔機に取り付け、更に、先端補強管20、後続補強管30を所定深さまで回転貫入する。尚、後続補強管30の後側に別の後続補強管40を接続する場合には、前述の工程を繰り返して回転貫入する。   When forming the ground reinforcement structure of the present embodiment, the rotary penetration pipe 10 is rotated and penetrated into the ground 100 as shown in FIGS. In the rotation penetration of the rotary penetration tube 10, the tip reinforcing tube 20 is attached to a drilling machine (not shown) to rotate into the ground 100, the tip reinforcing tube 20 is penetrated to a predetermined depth, and then the subsequent reinforcing tube 30 is connected. The reinforcing pipe 30 is attached to the drilling machine, and the tip reinforcing pipe 20 and the subsequent reinforcing pipe 30 are rotated and penetrated to a predetermined depth. In the case where another subsequent reinforcing pipe 40 is connected to the rear side of the subsequent reinforcing pipe 30, the above-described steps are repeated to penetrate the rotation.

その後、図5(c)、(d)に示すように、回転貫入した回転貫入管10の内部にグラウトの注入管71を接続しながら挿入し、接続した注入管71の先端が回転貫入管10の先端部近くになるまで挿入して配置する。   Thereafter, as shown in FIGS. 5C and 5D, the grout injection pipe 71 is inserted into the rotary penetration pipe 10 that is rotated and inserted, and the tip of the connected injection pipe 71 is inserted into the rotary penetration pipe 10. Insert until it is close to the tip of.

そして、図5(e)、(f)に示すように、グラウト注入装置(図示省略)から注入管71を介してグラウトを注入し、注入管71の先端近傍の吐出孔と回転貫入管10のグラウト吐出孔26、28を介して先端補強管20の周囲と先端側の地盤100にグラウトを吐出すると共に、このグラウトの吐出と合わせて回転貫入管10を長手方向に前後動させる。このグラウトの地盤100への吐出と回転貫入管10の前後動により、地盤100の土粒子とグラウトが混合されるようにして、回転貫入管10の管本体の先端部の周囲に第1の地盤改良体50を形成し、更に、本例では回転貫入管10の先端側にも第1の地盤改良体50を形成する。   Then, as shown in FIGS. 5 (e) and 5 (f), grout is injected from the grout injection device (not shown) through the injection pipe 71, and the discharge hole near the tip of the injection pipe 71 and the rotary penetrating pipe 10. The grout is discharged to the periphery of the tip reinforcing pipe 20 and the ground 100 on the tip side through the grout discharge holes 26 and 28, and the rotary penetrating pipe 10 is moved back and forth in the longitudinal direction together with the discharge of the grout. By discharging the grout to the ground 100 and moving the rotary penetrating pipe 10 back and forth, the soil particles and the grout of the ground 100 are mixed so that the first ground is formed around the tip of the pipe body of the rotary penetrating pipe 10. The improved body 50 is formed, and in this example, the first ground improved body 50 is also formed on the tip side of the rotary penetrating tube 10.

第1の地盤改良体50を形成する際のグラウトは、グラウトを回転貫入管10の先端部近傍で確実に吐出させると共に地盤100の土粒子とグラウトをより均質に混合して均質な第1の地盤改良体50を形成するため、例えば0.2MPa〜1MPa程度の注入圧で加圧注入とすると好適である。更に、この際に、回転貫入管10の長手方向の前後動距離を0.5〜1.5m程度とすると、グラウトを良好に砂と混合することができる。   The grout when forming the first ground improvement body 50 is a homogeneous first by discharging the grout in the vicinity of the tip of the rotary penetrating pipe 10 and mixing the soil particles and grout of the ground 100 more homogeneously. In order to form the ground improvement body 50, it is preferable to perform pressure injection at an injection pressure of about 0.2 MPa to 1 MPa, for example. Further, at this time, when the longitudinal moving distance of the rotary penetrating tube 10 in the longitudinal direction is about 0.5 to 1.5 m, the grout can be well mixed with the sand.

第1の地盤改良体50の形成後、回転貫入管10の管本体の周囲における第1の地盤改良体50の後端側の地盤100に、グラウトを吐出して第2の地盤改良体60を形成する。第2の地盤改良体60を形成する際には、注入管71の吐出孔を所定位置に配置すると共に、図示省略するグラウト注入装置と後続補強管30の口元に閉塞するように設けたバルブによってグラウトを注入する口元バルブ方式により(図6(a)参照)、地盤100の所定領域にグラウトを吐出して形成する構成、或いは注入管71を回転貫入管10の管本体内の注入すべき箇所までおろし、その吐出孔より上側にパッカー72をセットして順次グラウトしながら注入管71を引き上げてくるシングルパッカー方式(図6(b)参照)、或いは注入管71の所定領域の先後にパッカー72で隔壁を形成して隔壁間の領域にグラウトを注入するダブルパッカー方式により(図6(c)参照)、地盤100の所定領域にグラウトを吐出して形成する構成等とすることが可能である。尚、図6の太線矢印は注入されるグラウトを示している。   After the formation of the first ground improvement body 50, the second ground improvement body 60 is discharged by discharging grout to the ground 100 on the rear end side of the first ground improvement body 50 around the pipe body of the rotary penetrating pipe 10. Form. When the second ground improvement body 60 is formed, the discharge hole of the injection pipe 71 is arranged at a predetermined position, and a grout injection device (not shown) and a valve provided to be closed at the mouth of the subsequent reinforcing pipe 30 are used. A structure in which the grout is injected and formed by discharging the grout in a predetermined region of the ground 100 by the mouth valve system (see FIG. 6A), or the injection pipe 71 is to be injected into the pipe body of the rotary penetration pipe 10 A single packer system (see FIG. 6B) in which the packer 72 is set above the discharge hole and the injection tube 71 is pulled up while being sequentially grouting, or the packer 72 after the predetermined area of the injection tube 71. A partition is formed by a double packer method in which a grout is injected into a region between the partitions (see FIG. 6C), and the grout is discharged to a predetermined region of the ground 100. It is possible to adopt a configuration or the like. In addition, the thick line arrow of FIG. 6 has shown the grout injected.

第2の地盤改良体60を形成する際のグラウトは、地盤100の所定領域にグラウトを行き渡らせるため、例えば0.2MPa〜1MPa程度の注入圧で加圧注入すると好適である。   In order to spread the grout in a predetermined region of the ground 100, it is preferable that the grout at the time of forming the second ground improvement body 60 is pressurized and injected at an injection pressure of about 0.2 MPa to 1 MPa, for example.

また、第2の地盤改良体60を、グラウトを加圧注入、吐出して形成することにより、第1の地盤改良体50と隣接する箇所から螺旋羽根35に略対応する箇所まで、後端側に向かって略テーパ状に拡径するテーパ部61と、テーパ部61の後側に設けられる後部62を有する形状で、第2の地盤改良体60が形成される。更に、第2の地盤改良体60のうち、少なくともテーパ部61のグラウト密度は、第1の地盤改良体50のグラウト密度より高くなるように形成される。   In addition, by forming the second ground improvement body 60 by injecting and discharging grout under pressure, from the position adjacent to the first ground improvement body 50 to the position substantially corresponding to the spiral blade 35, the rear end side The second ground improvement body 60 is formed in a shape having a taper portion 61 that expands in a substantially tapered shape toward the rear and a rear portion 62 provided on the rear side of the taper portion 61. Further, the second ground improvement body 60 is formed so that the grout density of at least the taper portion 61 is higher than the grout density of the first ground improvement body 50.

本実施形態の地盤補強構造及びその形成方法によれば、回転貫入管10の先端部周囲の地盤100の領域に地盤100の土粒子とグラウトが混合された第1の地盤改良体50を簡易且つ効率的に形成することができると共に、回転貫入管10の先端部周囲の地盤100の領域に、必要な支持力を発揮する第1の地盤改良体50を確実に形成することができる。   According to the ground reinforcing structure and the method of forming the ground of the present embodiment, the first ground improvement body 50 in which the soil particles and grout of the ground 100 are mixed in the region of the ground 100 around the distal end portion of the rotary penetrating pipe 10 is simple and easy. While being able to form efficiently, the 1st ground improvement body 50 which exhibits required supporting force in the area | region of the ground 100 around the front-end | tip part of the rotation penetration pipe 10 can be formed reliably.

また、第1の地盤改良体50は、引抜力等に対して先端近傍の螺旋羽根22の変形を抑制することが可能であり、螺旋羽根22によって所要の先端支持力を得ることができる。また、先端近傍の螺旋羽根22の形状維持により、第1、第2の地盤改良体50、60に集中的な応力が伝播することを低減することが可能であり、第1、第2の地盤改良体50、60の破壊を防止することができる。また、第1、第2の地盤改良体50、60を安定して存置することができるので、第1、第2の地盤改良体50、60による大きな周面摩擦力とその支持力を安定して得ることができる。また、第1、第2の地盤改良体50、60を略隣接して設けることにより、第1、第2の地盤改良体50、60で応力の分散を図ることができる。従って、回転貫入管10、及びその先端近傍の螺旋羽根22、第1、第2の地盤改良体50、60が一体的に機能して大きな支持力が得られ、形成された地盤補強構造は全体として最も効果的な支持力を確実に且つ安定して発揮することができ、回転貫入管10が降伏するまで支持することも可能となる。   Further, the first ground improvement body 50 can suppress deformation of the spiral blade 22 in the vicinity of the tip against the pulling force or the like, and the required tip support force can be obtained by the spiral blade 22. Further, by maintaining the shape of the spiral blade 22 in the vicinity of the tip, it is possible to reduce the propagation of intensive stress to the first and second ground improvement bodies 50 and 60, and the first and second grounds. Breakage of the improved bodies 50 and 60 can be prevented. Further, since the first and second ground improvement bodies 50 and 60 can be stably placed, the large circumferential frictional force and the supporting force by the first and second ground improvement bodies 50 and 60 are stabilized. Can be obtained. Further, by providing the first and second ground improvement bodies 50 and 60 substantially adjacent to each other, the first and second ground improvement bodies 50 and 60 can distribute stress. Therefore, the rotary penetration tube 10 and the spiral blade 22 near the tip, the first and second ground improvement bodies 50, 60 function integrally to obtain a large support force, and the formed ground reinforcing structure is the whole. As a result, the most effective support force can be reliably and stably exhibited, and it is possible to support the rotary penetrating tube 10 until it yields.

また、第2の地盤改良体60のテーパ部61により、周面摩擦力を一層増大させ、地盤補強構造の支持力を増大することができる。また、第2の地盤改良体60の先端側の部分に相当するテーパ部61を螺旋羽根35で押圧し、第1、第2の地盤改良体50、60に対する押込力を高めることができる。また、第2の地盤改良体60の後端側の部分に相当する後部62で螺旋羽根35を押圧し、第1、第2の地盤改良体50、60及び回転貫入管10の押込力を一層高めることができる。   Moreover, the circumferential surface friction force can be further increased by the tapered portion 61 of the second ground improvement body 60, and the support force of the ground reinforcement structure can be increased. Moreover, the taper part 61 equivalent to the front end side part of the 2nd ground improvement body 60 can be pressed with the spiral blade 35, and the pushing force with respect to the 1st, 2nd ground improvement bodies 50 and 60 can be heightened. Further, the spiral blade 35 is pressed by the rear portion 62 corresponding to the rear end portion of the second ground improvement body 60, and the pushing force of the first and second ground improvement bodies 50, 60 and the rotary penetrating pipe 10 is further increased. Can be increased.

また、第2の地盤改良体60のうち少なくともテーパ部61のグラウト密度が第1の地盤改良体50のグラウト密度より高いことから、比較的大きな応力が負荷されやすい第2の地盤改良体60の先端側の部分について(図9参照)、圧縮強度やせん断強度を高くすることができ、地盤補強構造全体としての強度、支持力をより一層高めることができる。また、回転貫入管10の先端で突出する爪状部24と第1の地盤改良体50等が相俟って、地盤100の支持層への荷重伝達性能が一層良好となり(図10参照)、地盤補強構造全体としての強度、支持力をより一層高めることができる。   Moreover, since the grout density of at least the taper part 61 is higher than the grout density of the 1st ground improvement body 50 among the 2nd ground improvement bodies 60, the 2nd ground improvement body 60 in which a comparatively big stress is easy to be loaded. With respect to the tip side portion (see FIG. 9), the compressive strength and shear strength can be increased, and the strength and supporting force of the ground reinforcement structure as a whole can be further increased. In addition, the claw-like portion 24 projecting at the tip of the rotary penetrating tube 10, the first ground improvement body 50, and the like combine to further improve the load transmission performance to the support layer of the ground 100 (see FIG. 10). The strength and supporting force of the ground reinforcement structure as a whole can be further increased.

〔実施形態の地盤補強構造の変形例〕
次に、上記実施形態の地盤補強構造の変形例について説明する。図7は第1変形例、図8は第2変形例に関する図である。
[Modification of Ground Reinforcement Structure of Embodiment]
Next, the modification of the ground reinforcement structure of the said embodiment is demonstrated. FIG. 7 is a diagram related to the first modification, and FIG. 8 is a diagram related to the second modification.

第1変形例では、図7に示すように、先端補強管20の先端近傍或いは先端には、円形板である閉塞面231が設けられ、閉塞面231から複数(本例では4個)の弧状板233が突出するように立設されている。各弧状板233は、閉塞面231の内側から外側に延びて外側端部が他の弧状板233の内側端部の外側に位置するように渦巻状に配置され、弧状板233・233相互の間には間隙234が設けられている。弧状板233の先端には円形板である保護板232が固定して設けられ、保護板232には、第1の爪状部24a、第2の爪状部24bが設けられている。本例では、閉塞面231と渦巻配置の複数の弧状板233と保護板232、或いは閉塞面231が、回転貫入管10の回転時に土砂の侵入を防止する土砂侵入防止部に相当する。   In the first modified example, as shown in FIG. 7, a closed surface 231 that is a circular plate is provided in the vicinity of the distal end of the distal end reinforcing tube 20 or at the distal end, and a plurality of (four in this example) arcuate shapes are formed from the closed surface 231. The plate 233 is erected so as to protrude. Each arc-shaped plate 233 is arranged in a spiral shape so that the outer end extends from the inner side of the closing surface 231 and the outer end is located outside the inner end of the other arc-shaped plate 233. Is provided with a gap 234. A protective plate 232 that is a circular plate is fixedly provided at the tip of the arc-shaped plate 233, and the first claw-like portion 24a and the second claw-like portion 24b are provided on the protective plate 232. In this example, the closed surface 231 and the plurality of arcuate plates 233 and the protective plate 232 arranged in a spiral manner, or the closed surface 231 correspond to a sediment intrusion prevention unit that prevents intrusion of earth and sand when the rotary penetration tube 10 rotates.

第1変形例は、上記実施形態の地盤補強構造に対して、回転貫入管10の爪状部の形状が異なるものであり、第1の爪状部24aは、先端面がスロープ状の傾斜面であり、底面視では弓状に若干湾曲した形状になっている。また、第2の爪状部24bは、先端面が山形の傾斜面であり、底面視では弓状に若干湾曲した形状になっている。   The first modification differs from the ground reinforcement structure of the above embodiment in that the shape of the claw-shaped portion of the rotary penetrating tube 10 is different, and the first claw-shaped portion 24a is an inclined surface having a sloped tip surface. In the bottom view, it has a slightly curved shape. The second claw-like portion 24b has a mountain-shaped inclined surface at the front end surface, and has a slightly curved shape in a bow shape when viewed from the bottom.

爪状部24a、24bは先端補強管20の先端から突出して形成され、その突出量は上記実施形態の爪状部24よりも大きくなっている。この爪状部24a、24bの閉塞面231或いは保護板232からの突出量は、例えば平均で20mm〜100mm程度とすると好適である。また、爪状部24a、24bは略円周方向に所定間隔を開けて複数個(本例では各2個)設けられ、爪状部24aと爪状部24bが交互に配置されていると共に、爪状部24a、24bは保護板232の中心から放射状に延びて設けられ、爪状部24aは先端の傾斜面の高い方を外側にして配置されている。   The claw-like portions 24a and 24b are formed so as to protrude from the tip of the tip reinforcing tube 20, and the protruding amount is larger than that of the claw-like portion 24 of the above embodiment. The amount of protrusion of the claw-like portions 24a and 24b from the closing surface 231 or the protective plate 232 is preferably about 20 to 100 mm on average, for example. Further, the claw-like portions 24a and 24b are provided in plural (two in this example) at predetermined intervals in the substantially circumferential direction, and the claw-like portions 24a and the claw-like portions 24b are alternately arranged, The claw-like portions 24a and 24b are provided so as to extend radially from the center of the protective plate 232, and the claw-like portion 24a is arranged with the higher end inclined surface at the outer side.

更に、第1変形例の先端補強管20の先端部内では、閉塞面231に逆止弁であるゴム式逆止弁付きのグラウト吐出孔28aが複数形成され、先端補強管20の閉塞面231より先端側にグラウトを吐出可能になっている。グラウト吐出孔28aから吐出されたグラウトは弧状板233・233相互間の間隙234を介して地盤100に注入される。   Furthermore, a plurality of grout discharge holes 28 a with a rubber check valve, which is a check valve, are formed in the closing surface 231 in the tip portion of the tip reinforcing tube 20 of the first modified example, and from the closing surface 231 of the tip reinforcing tube 20. Grout can be discharged to the tip side. The grout discharged from the grout discharge hole 28a is injected into the ground 100 through the gap 234 between the arcuate plates 233 and 233.

第1変形例では、上記実施形態と同様の効果を奏することに加え、突出量の大きい爪状部24a、24bにより、上記実施形態よりも、荷重伝達性能を一層良好にして支持力を強化することが可能であり(図10参照)、地盤補強構造全体としての強度、支持力をより一層高めることができる。   In the first modified example, in addition to the same effects as in the above embodiment, the nail-like portions 24a and 24b having a large protruding amount further enhance the load transmission performance and strengthen the supporting force than in the above embodiment. It is possible (refer FIG. 10), and the intensity | strength and supporting force as the whole ground reinforcement structure can be improved further.

また、第2変形例は、上記実施形態の地盤補強構造に対して、図8に示すように回転貫入管10の先端補強管80の構成が異なる。先端補強管80は、管本体81の先端近傍に螺旋羽根82を有し、外周に長手方向に間隔を開けて円周状の節突起83が形成され、更に、節突起83とは異なる位置に長手方向に間隔を開けて逆止弁付きのグラウト吐出孔84が形成されている。先端補強管80の後端部には、図示省略する雄ねじの継ぎ手が形成され、上記実施形態と同様に後続補強管30が接続可能になっている。   Moreover, the 2nd modification differs in the structure of the front end reinforcement pipe | tube 80 of the rotation penetration pipe 10 as shown in FIG. 8 with respect to the ground reinforcement structure of the said embodiment. The tip reinforcing tube 80 has a spiral blade 82 in the vicinity of the tip of the tube main body 81, a circumferential node projection 83 is formed on the outer periphery at intervals in the longitudinal direction, and at a position different from the node projection 83. Grout discharge holes 84 with check valves are formed at intervals in the longitudinal direction. An unillustrated male threaded joint is formed at the rear end of the tip reinforcing tube 80, and the subsequent reinforcing tube 30 can be connected in the same manner as in the above embodiment.

更に、先端補強管80は、内管85と、内管85と一体的に形成された蓋部86とを有する。蓋部86の外周縁は先端補強管80の管本体81と溶接等で固着され、管本体81と内管85との間に形成される円筒形の隙間87の先端が蓋部86で閉塞されており、蓋部86は土砂侵入防止部に相当し、回転貫入時に発生する土砂は内管85内に取り込まれるようになっている。また、内管85と管本体81とを同心円状に保持して隙間87を維持するために、先端補強管80の後部における内管85と管本体81との間には図示省略するスペーサーが設けられている。   Further, the tip reinforcing tube 80 has an inner tube 85 and a lid portion 86 formed integrally with the inner tube 85. The outer peripheral edge of the lid part 86 is fixed to the pipe body 81 of the tip reinforcing pipe 80 by welding or the like, and the tip of a cylindrical gap 87 formed between the pipe body 81 and the inner pipe 85 is closed by the lid part 86. The lid portion 86 corresponds to a sediment intrusion prevention unit, and the sediment generated during the rotation penetration is taken into the inner tube 85. In order to maintain the inner pipe 85 and the pipe main body 81 concentrically and maintain the gap 87, a spacer (not shown) is provided between the inner pipe 85 and the pipe main body 81 at the rear portion of the tip reinforcing pipe 80. It has been.

蓋部86には、回転貫入管10の先端からもグラウトを地盤100に注入可能にするため、円周方向に間隔を開けて隙間87に貫通する複数個(本例では4個)のグラウト吐出孔861が形成されている。また、蓋部86には、各グラウト吐出孔861を覆うように防護板862が溶接等により取り付けられている。防護板862は、その内側領域で蓋部86との間に空間ができるように取り付けられ、回転貫入時に土砂がグラウト吐出孔861から隙間87に侵入することを防止可能であると共に、グラウトを前記空間を介して地盤100に吐出可能になっている。   In order to allow the grout to be injected into the ground 100 also from the tip of the rotary penetrating tube 10, a plurality of (four in this example) grout discharges that are spaced in the circumferential direction and pass through the gap 87. A hole 861 is formed. Further, a protection plate 862 is attached to the lid portion 86 by welding or the like so as to cover each grout discharge hole 861. The protective plate 862 is attached so that a space is formed between the protective plate 862 and the lid portion 86 in its inner region, and it is possible to prevent earth and sand from entering the gap 87 from the grout discharge hole 861 at the time of rotation penetration. It is possible to discharge to the ground 100 through the space.

第2変形例において第1の地盤改良体50を形成する際には、図示省略するグラウト注入装置から注入管を介して隙間87に入るようにグラウトを注入する。そして、先端補強管80の隙間87、グラウト吐出孔84、861を介して周囲の地盤100と先端補強管80の先端側の地盤100とにグラウトを吐出すると共に、このグラウトの吐出と合わせて回転貫入管10を長手方向に前後動させる。このグラウトの地盤100への吐出と回転貫入管10の前後動により、地盤100の土粒子とグラウトが混合されるようにして、回転貫入管10の管本体の先端部の周囲と先端側の地盤100に第1の地盤改良体50を形成する。この場合のグラウトの注入圧も、例えば0.2MPa〜1MPa程度の注入圧で加圧注入とすると好適である。その後は上記実施形態と同様に口元バルブ方式等により第2の地盤改良体60を形成する。   When the first ground improvement body 50 is formed in the second modification, grout is injected from a grout injection device (not shown) so as to enter the gap 87 through the injection pipe. Then, the grout is discharged to the surrounding ground 100 and the ground 100 on the distal end side of the tip reinforcing tube 80 through the gap 87 of the tip reinforcing tube 80 and the grout discharge holes 84 and 861, and rotated together with the discharge of the grout. The penetration tube 10 is moved back and forth in the longitudinal direction. By discharging the grout to the ground 100 and moving the rotary penetrating pipe 10 back and forth, the soil particles and the grout of the ground 100 are mixed so that the ground around the tip of the pipe body of the rotary penetrating pipe 10 and the ground on the tip side. A first ground improvement body 50 is formed at 100. In this case, the injection pressure of the grout is also preferably a pressure injection with an injection pressure of about 0.2 MPa to 1 MPa, for example. After that, the second ground improvement body 60 is formed by the mouth valve method or the like as in the above embodiment.

第2変形例では、上記実施形態と同様の効果を奏することに加え、回転貫入管10の貫入抵抗を低減することができる。   In the second modified example, the penetration resistance of the rotary penetration tube 10 can be reduced in addition to the same effects as those of the above embodiment.

〔実施形態及び変形例の地盤補強構造の性能評価〕
上記実施形態及び変形例の地盤補強構造において、第1の地盤改良体50、第2の地盤改良体60に、管頭変位が螺旋羽根22の外径の10%に到達する荷重を管頭荷重として載荷したときに発生する応力分布の解析結果を図9に示す。図9に示すように、第1の地盤改良体50と、第2の地盤改良体60の後部62では、垂直応力とせん断応力がともに小さく、第2の地盤改良体60のテーパ部61では垂直応力、せん断応力がともに最大になっている。また、第1の地盤改良体50には螺旋羽根22の隙間から比較的高い応力が伝播している。
[Performance evaluation of ground reinforcement structure of embodiment and modification]
In the ground reinforcement structure of the above-described embodiment and the modified example, a load at which the head displacement reaches 10% of the outer diameter of the spiral blade 22 is applied to the first ground improvement body 50 and the second ground improvement body 60. FIG. 9 shows the analysis result of the stress distribution generated when the load is loaded. As shown in FIG. 9, the vertical stress and the shear stress are both small in the first ground improvement body 50 and the rear portion 62 of the second ground improvement body 60, and the taper portion 61 of the second ground improvement body 60 is vertical. Both stress and shear stress are maximized. Further, a relatively high stress is transmitted to the first ground improvement body 50 from the gap between the spiral blades 22.

ここで第1の地盤改良体50、第2の地盤改良体60の後部62の破壊応力を垂直応力:5,000kN/m程度、最大せん断応力:2,500kN/m程度を目安とし、第2の地盤改良体60のテーパ部61の破壊応力を60,000kN/m程度、最大せん断応力:30,000kN/m程度を目安とすると、発生する最大の垂直応力は、例えば第1の地盤改良体50に螺旋羽根22の隙間から最大2,500kN/m程度、第2の地盤改良体60のテーパ部61に最大3,500kN/m程度であり、いずれも破壊応力に達する垂直応力ではない。更に、発生する最大せん断応力は、例えば第1の地盤改良体50に螺旋羽根22の隙間から最大1,500kN/m程度、第2の地盤改良体60のテーパ部61に最大75kN/m程度であり、いずれも破壊応力に達する最大せん断応力ではない。 Here, with respect to the fracture stress of the rear portion 62 of the first ground improvement body 50 and the second ground improvement body 60, the normal stress is about 5,000 kN / m 2 and the maximum shear stress is about 2,500 kN / m 2 , 60,000kN / m 2 about the fracture strength of the tapered portion 61 of the second ground improvement body 60, the maximum shear stress: when 30,000kN / m 2 extent as a guide, the maximum vertical stress generated, for example, the first The ground improvement body 50 has a maximum of about 2500 kN / m 2 from the gap between the spiral blades 22 and the taper portion 61 of the second ground improvement body 60 has a maximum of about 3,500 kN / m 2. It is not normal stress. Further, the generated maximum shear stress is, for example, about 1,500 kN / m 2 at the maximum from the gap between the spiral blades 22 in the first ground improvement body 50 and 75 kN / m 2 at the maximum in the taper portion 61 of the second ground improvement body 60. Neither is the maximum shear stress that reaches the fracture stress.

また、回転貫入管10の先端近傍の螺旋羽根22の隙間部分から第1の地盤改良体50に垂直応力、最大せん断応力を伝達している応力分布から、螺旋羽根22が第1の地盤改良体50、第2の地盤改良体60への集中的な応力伝播を抑制していることが分かる。   Further, from the stress distribution that transmits the vertical stress and the maximum shear stress to the first ground improvement body 50 from the gap portion of the spiral blade 22 near the tip of the rotary penetrating pipe 10, the spiral blade 22 is the first ground improvement body. 50, it turns out that the intensive stress propagation to the 2nd ground improvement body 60 is suppressed.

次に、図10に実施形態及び変形例の地盤補強構造と従来例の地盤補強構造の荷重−変位量曲線を示す。図10において、1点鎖線は図11の従来例の地盤補強構造、点線は上記実施形態の地盤補強構造、実線は第1変形例の地盤補強構造の押込み試験の荷重と変位量の関係である。押込み試験は、静的載荷方式とし、載荷方法は連続載荷、反力装置は反力アンカーで引き抜き抵抗力を用いた。   Next, FIG. 10 shows load-displacement amount curves of the ground reinforcement structure of the embodiment and the modification and the ground reinforcement structure of the conventional example. In FIG. 10, the one-dot chain line is the ground reinforcing structure of the conventional example of FIG. 11, the dotted line is the ground reinforcing structure of the above embodiment, and the solid line is the relationship between the load and displacement amount of the indentation test of the ground reinforcing structure of the first modification. . The indentation test was a static loading method, the loading method was continuous loading, and the reaction force device was a pulling resistance force with a reaction force anchor.

図10に示すように、実施形態及び第1変形例の地盤補強構造では、従来例の地盤補強構造に比べて、同じ荷重に対する変位が小さく、従来例の2.7〜4.9倍程度の極限支持力(管頭変位が螺旋羽根22の外径の10%に到達する荷重)が得られる。また、爪状部24a、24bの突出量が大きい第1変形例の地盤補強構造の方が、実施形態の地盤補強構造よりも、同じ荷重に対する変位が小さく、非常に高い極限支持力を得ることができる。   As shown in FIG. 10, in the ground reinforcement structure of the embodiment and the first modified example, the displacement with respect to the same load is small compared to the ground reinforcement structure of the conventional example, which is about 2.7 to 4.9 times that of the conventional example. Ultimate support force (load at which the head displacement reaches 10% of the outer diameter of the spiral blade 22) is obtained. In addition, the ground reinforcement structure of the first modified example in which the protrusions of the claw-like parts 24a and 24b have a large amount of displacement has a smaller displacement with respect to the same load than the ground reinforcement structure of the embodiment, and obtains extremely high ultimate support force. Can do.

〔その他の変形例等〕
本明細書開示の発明は、各発明、実施形態、第1、第2変形例の他に、適用可能な範囲で、これらの部分的な構成を本明細書開示の他の構成に変更して特定したもの、或いはこれらの構成に本明細書開示の他の構成を付加して特定したもの、或いはこれらの部分的な構成を部分的な作用効果が得られる限度で削除して特定した上位概念化したものを含むものであり、下記変形例も包含する。
[Other variations, etc.]
In the invention disclosed in this specification, in addition to the inventions, embodiments, first and second modifications, these partial configurations may be changed to other configurations disclosed in this specification within the applicable range. Higher-level conceptualization that has been specified or specified by adding other configurations disclosed in this specification to these configurations, or by deleting these partial configurations to the extent that partial effects can be obtained The following modifications are also included.

例えば上記実施形態では、第1の地盤改良体50の先端と第2の地盤改良体60の後端との間を定着長領域、第2の地盤改良体60と地表面101との間を自由長領域としたが、地盤100における第1の地盤改良体50と第2の地盤改良体60の形成領域は適宜であり、例えば第2の地盤改良体60を地表面101に達するまで或いは近接するまで形成し、全体を定着長領域とする地盤補強構造等としてもよい。   For example, in the above embodiment, a fixed length region is provided between the front end of the first ground improvement body 50 and the rear end of the second ground improvement body 60, and a space between the second ground improvement body 60 and the ground surface 101 is freely set. Although the long region is used, the formation region of the first ground improvement body 50 and the second ground improvement body 60 in the ground 100 is appropriate, for example, until the second ground improvement body 60 reaches the ground surface 101 or is close thereto. It is good also as the ground reinforcement structure etc. which form to the whole and make the whole fixing length area | region.

また、爪状部の形状、配置は爪状部24、24a、24bとその配置以外にも適宜であるが、爪状部或いは一体的な形状等の爪状部の部分が、略円周方向に所定間隔を開けて配置される構成とすることが好ましい。また、第2の地盤改良体60のテーパ部61に対応する部分が略筒状等の他の形状になる構成や、別の螺旋羽根35を設けない構成等とすることも可能である。   Further, the shape and arrangement of the claw-shaped portions are appropriate in addition to the claw-shaped portions 24, 24a, 24b and their arrangement, but the claw-shaped portions or the portions of the claw-shaped portions such as an integral shape are substantially in the circumferential direction It is preferable that the configuration is arranged with a predetermined interval. In addition, a configuration in which the portion corresponding to the tapered portion 61 of the second ground improvement body 60 has another shape such as a substantially cylindrical shape, a configuration in which another spiral blade 35 is not provided, or the like is also possible.

本発明は、螺旋羽根を有する回転貫入管を地盤に打設し、その周囲にグラウトによる地盤改良体を造成して地盤を補強する際に利用することができる。   INDUSTRIAL APPLICABILITY The present invention can be used when a rotary penetration pipe having spiral blades is placed on the ground, and a ground improvement body using a grout is formed around the ground to reinforce the ground.

10、110…回転貫入管 20、80…先端補強管 21、31、41、81、121、131…管本体 22、35、82、122、142…螺旋羽根 23…閉塞面 231…閉塞面 232…保護板 233…弧状板 234…間隙 24、24a、24b…爪状部 25、83、123…節突起 26、28、28a、34、44、84、861、124…グラウト吐出孔 27、32、33、42、43…継ぎ手 281…バネ式逆止弁 30…後続補強管 40…後続補強管 50…第1の地盤改良体 60…第2の地盤改良体 61…テーパ部 62…後部 71…注入管 72…パッカー 85…内管 86…蓋部 862…防護板 87…隙間 100、160…地盤 101、161…地表面 120…下部補強管 130…上部補強管 140…接続管 141…本体 150…地盤改良体

DESCRIPTION OF SYMBOLS 10,110 ... Rotating penetration pipe 20, 80 ... Tip reinforcement pipe 21, 31, 41, 81, 121, 131 ... Pipe body 22, 35, 82, 122, 142 ... Spiral blade 23 ... Blocking surface 231 ... Blocking surface 232 ... Protective plate 233 ... Arc-shaped plate 234 ... Gap 24, 24a, 24b ... Claw-like portion 25, 83, 123 ... Node projection 26, 28, 28a, 34, 44, 84, 861, 124 ... Grout discharge holes 27, 32, 33 , 42, 43 ... Joint 281 ... Spring check valve 30 ... Subsequent reinforcement pipe 40 ... Subsequent reinforcement pipe 50 ... First ground improvement body 60 ... Second ground improvement body 61 ... Taper part 62 ... Rear part 71 ... Injection pipe 72: Packer 85 ... Inner pipe 86 ... Lid 862 ... Protection plate 87 ... Gap 100, 160 ... Ground 101, 161 ... Ground surface 120 ... Lower reinforcement pipe 130 ... Upper reinforcement pipe 140 ... Connection pipe 141 ... Main body 150 ... Ground improvement body

Claims (6)

管本体の先端近傍に土砂侵入防止部が設けられ且つ先端近傍に螺旋羽根が設けられており、前記管本体の周壁と先端近傍にグラウト吐出孔が形成され、地盤に回転貫入して打設されている回転貫入管と、
前記管本体の先端部の周囲に設けられ、地盤の土粒子とグラウトが混合されるようにグラウトを吐出して形成されている第1の地盤改良体と、
前記管本体の周囲における前記第1の地盤改良体の後端側に前記第1の地盤改良体と略隣接して設けられ、グラウトを吐出して形成されている第2の地盤改良体と、
を有することを特徴とする地盤補強構造。
An earth and sand intrusion prevention part is provided near the tip of the pipe body, and a spiral blade is provided near the tip, and a grout discharge hole is formed near the peripheral wall and the tip of the pipe body. A rotating penetrating pipe,
A first ground improvement body provided around the tip of the tube body and formed by discharging the grout so that the soil particles and the grout of the ground are mixed;
A second ground improvement body which is provided on the rear end side of the first ground improvement body around the pipe body and substantially adjacent to the first ground improvement body, and is formed by discharging a grout;
The ground reinforcement structure characterized by having.
前記第2の地盤改良体が、前記第1の地盤改良体と隣接する箇所から後端側に向かって略テーパ状に拡径するテーパ部から構成されていることを特徴とする請求項1記載の地盤補強構造。   The said 2nd ground improvement body is comprised from the taper part which diameter-expands in a substantially taper shape toward the back end side from the location adjacent to the said 1st ground improvement body. Ground reinforcement structure. 前記回転貫入管の前記管本体の中間部位に、前記螺旋羽根より大径の別の螺旋羽根が設けられており、
前記第2の地盤改良体が、前記別の螺旋羽根に対して前記管本体の先端側と後端側に形成されていることを特徴とする請求項1又は2記載の地盤補強構造。
Another spiral blade having a larger diameter than the spiral blade is provided at an intermediate portion of the tube main body of the rotary penetrating tube,
3. The ground reinforcing structure according to claim 1, wherein the second ground improvement body is formed on a front end side and a rear end side of the pipe main body with respect to the another spiral blade.
前記第2の地盤改良体の前記別の螺旋羽根に対して前記管本体の先端側に形成されている部分のグラウト密度が、前記第1の地盤改良体のグラウト密度より高いことを特徴とする請求項3記載の地盤補強構造。   The grout density of the portion formed on the tip end side of the tube main body with respect to the another spiral blade of the second ground improvement body is higher than the grout density of the first ground improvement body. The ground reinforcement structure according to claim 3. 前記回転貫入管の先端に爪状部が突出して形成されていることを特徴とする請求項1〜4の何れかに記載の地盤補強構造。   The ground reinforcing structure according to any one of claims 1 to 4, wherein a claw-like portion protrudes from a tip of the rotary penetrating tube. 管本体の先端近傍に土砂侵入防止部が設けられ且つ先端近傍に螺旋羽根が設けられ、前記管本体の周壁と先端近傍にグラウト吐出孔が形成されている回転貫入管を、地盤に回転貫入して打設する第1工程と、
地盤の土粒子とグラウトが混合されるように、前記グラウト吐出孔からグラウトを吐出すると共に前記回転貫入管を長手方向に前後動させ、前記管本体の先端部の周囲に第1の地盤改良体を形成する第2工程と、
前記管本体の周囲における前記第1の地盤改良体の後端側に、グラウトを吐出して前記第1の地盤改良体と略隣接するように第2の地盤改良体を形成する第3工程と、
を備えることを特徴とする地盤補強構造の形成方法。

A rotary penetrating pipe provided with a sediment intrusion prevention part near the tip of the pipe body and a spiral blade near the tip, and formed with a grout discharge hole near the tip of the pipe body, is pierced into the ground. A first step of placing
A first ground improvement body is formed around the distal end portion of the pipe body by discharging the grout from the grout discharge hole and moving the rotary penetrating pipe back and forth in the longitudinal direction so that soil particles and grout of the ground are mixed. A second step of forming
A third step of forming a second ground improvement body by discharging grout on the rear end side of the first ground improvement body around the pipe body so as to be substantially adjacent to the first ground improvement body; ,
A method for forming a ground reinforcing structure, comprising:

JP2012014679A 2012-01-26 2012-01-26 Method for forming ground reinforcement structure Active JP5858574B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012014679A JP5858574B2 (en) 2012-01-26 2012-01-26 Method for forming ground reinforcement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012014679A JP5858574B2 (en) 2012-01-26 2012-01-26 Method for forming ground reinforcement structure

Publications (2)

Publication Number Publication Date
JP2013155485A true JP2013155485A (en) 2013-08-15
JP5858574B2 JP5858574B2 (en) 2016-02-10

Family

ID=49050956

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012014679A Active JP5858574B2 (en) 2012-01-26 2012-01-26 Method for forming ground reinforcement structure

Country Status (1)

Country Link
JP (1) JP5858574B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103498467A (en) * 2013-10-14 2014-01-08 成军 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
JP2016089597A (en) * 2014-10-30 2016-05-23 光弘 南馬越 Reinforced concrete filled quadrangular steel pipe pile column

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07189249A (en) * 1993-12-27 1995-07-28 Chiyoda Koei Kk Method of burying construction of inverted conical-shaped multi-blade steel pipe pile
US20080031695A1 (en) * 2006-08-07 2008-02-07 Nasr Mamdouh A Method for installing a screw pile
JP2008057113A (en) * 2006-08-29 2008-03-13 Kfc Ltd Rotary press-in pile and its construction method
JP2008248524A (en) * 2007-03-29 2008-10-16 Shimizu Corp Method of placing steel pipe pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07189249A (en) * 1993-12-27 1995-07-28 Chiyoda Koei Kk Method of burying construction of inverted conical-shaped multi-blade steel pipe pile
US20080031695A1 (en) * 2006-08-07 2008-02-07 Nasr Mamdouh A Method for installing a screw pile
JP2008057113A (en) * 2006-08-29 2008-03-13 Kfc Ltd Rotary press-in pile and its construction method
JP2008248524A (en) * 2007-03-29 2008-10-16 Shimizu Corp Method of placing steel pipe pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103498467A (en) * 2013-10-14 2014-01-08 成军 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
CN103498467B (en) * 2013-10-14 2015-07-22 江苏溧阳城建集团有限公司 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
JP2016089597A (en) * 2014-10-30 2016-05-23 光弘 南馬越 Reinforced concrete filled quadrangular steel pipe pile column

Also Published As

Publication number Publication date
JP5858574B2 (en) 2016-02-10

Similar Documents

Publication Publication Date Title
KR101447080B1 (en) Helical Pile having Structure for Preventing Torsion Failure and Buckling, and Constructing Method thereof
JP4716134B2 (en) Slope stabilization method
KR102090305B1 (en) Big helical pile with easy grouting construction and construction method using the same
JP5867301B2 (en) Pipe pile and its construction method
JP6462512B2 (en) Anchor head fixing member for anchor rust prevention and anchor head fixing structure thereof
KR102464394B1 (en) Driving rod for forming reinforced part of piles
KR101552139B1 (en) Helical anchor pile
KR20160025180A (en) Helical pile and construction method thereof
CN108222014B (en) A kind of rock bolt device and the foundation pit supporting construction with the device
JP2008057113A (en) Rotary press-in pile and its construction method
JP5858574B2 (en) Method for forming ground reinforcement structure
JP2017186801A (en) Lock bolt
KR101288885B1 (en) Micro steel pipe pile for increasing load carrying capacity and construction method thereof
JP2007051486A (en) Sheet pile-combined spread foundation and its construction method
KR101424736B1 (en) Pile molding apparatus
KR101644098B1 (en) Bulbed cable bolt
KR101620558B1 (en) Composite pile using multi support plate and the construction method therefor
KR20100088469A (en) Rock bolt and fixation method the rock bolt
KR102432882B1 (en) External packer simultaneous injection steel pipe and construction method using this
KR102259937B1 (en) Helical pile
KR101270832B1 (en) Concrete-Filled Tube Type Rotary File
KR101791211B1 (en) Helix steel pipe pile construction method for reinforcement of buckling
JP4853132B2 (en) Construction method of foundation pile
KR102115509B1 (en) Reinforced steel pipe one shot grouting
US20180291582A1 (en) Anchor having fixing device at side of pressure plate to depress land slope and method of installing same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20141128

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150806

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150824

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151013

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20151214

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20151214

R150 Certificate of patent or registration of utility model

Ref document number: 5858574

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250