JP2012246696A - Erection engineering method of steel column and base member used for the same - Google Patents

Erection engineering method of steel column and base member used for the same Download PDF

Info

Publication number
JP2012246696A
JP2012246696A JP2011120055A JP2011120055A JP2012246696A JP 2012246696 A JP2012246696 A JP 2012246696A JP 2011120055 A JP2011120055 A JP 2011120055A JP 2011120055 A JP2011120055 A JP 2011120055A JP 2012246696 A JP2012246696 A JP 2012246696A
Authority
JP
Japan
Prior art keywords
steel column
pipe
steel
horizontal position
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2011120055A
Other languages
Japanese (ja)
Other versions
JP5721221B2 (en
Inventor
Hideyuki Kosaka
英之 小坂
Hiroshi Shinjo
浩 新上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2011120055A priority Critical patent/JP5721221B2/en
Publication of JP2012246696A publication Critical patent/JP2012246696A/en
Application granted granted Critical
Publication of JP5721221B2 publication Critical patent/JP5721221B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To simplify erection work of a steel column.SOLUTION: A base member 1 is prepared by connecting an anchor part (rolled steel) 11 to a pipe part (steel pipe) 10, reinforcing bars (which are not illustrated) are disposed to enclose the anchor part 11, and concrete is piled to the anchor part 11 and the reinforcing-bars. Thus, a footing is formed. On the stage where a steel column 2 is carried in, a lower end of the steel column 2 is inserted to the pipe part 10, and the steel column 2 is erected. In such a case, a horizontal position adjusting bolt 12 mounted to the pipe part 10 is turned to adjust a horizontal position of the steel column 2, and a perpendicular position adjusting bolt 6 is turned to adjust a height of the steel column 2. Since the anchor part 11 is connected to the pipe part 10, the number of reinforcing-bars can be decreased and since the horizontal position or the height of the steel column 2 can also be adjusted easily, the erection work of the steel column can be simplified.

Description

本発明は、鉄骨柱を建て込む鉄骨柱の建込工法、及び該工法に使用されるベース部材に関する。   The present invention relates to a steel column mounting method for building a steel column and a base member used in the method.

鉄骨柱脚形式の一つである埋め込み柱脚は剛性や耐力などの構造性能面で比較的優れているが、一般的な埋込み柱脚工法の場合は、基礎部のRC造の施工は鉄骨柱が現場に搬入された後に開始する必要があった。しかしながら、この鉄骨柱は、発注の遅れや製作の遅れなどが原因で必要な期日までに納品されないこともあり、鉄骨柱の搬入が遅れた場合には現場の工事も遅れてしまうという問題があった。   The embedded column base, which is one of the types of steel column bases, is relatively superior in terms of structural performance such as rigidity and proof strength. However, in the case of a general embedded column base method, the RC construction of the foundation is a steel column. Had to be started after it was brought into the field. However, this steel column may not be delivered by the necessary date due to delays in ordering or production, and there is a problem that construction work on site will be delayed if the delivery of steel columns is delayed. It was.

そこで、そのような問題を解決する鉄骨柱の建込工法については種々の方法が提案されている(例えば、特許文献1及び2参照)。   Therefore, various methods have been proposed for steel column erection methods that solve such problems (see, for example, Patent Documents 1 and 2).

図6は、鉄骨柱の建込工法の従来例を示す斜視図であって、符号100は、鉄骨柱102を建て込むための穴(箱抜きにした穴)を示し、符号103は、該穴100の周囲に配置される鉄筋を示し、符号104は、該鉄筋103を埋設するように打設されたコンクリートを示す。この図6に示す方法では、鉄骨柱が納入されなくとも基礎工事(つまり、鉄筋103の配置、及びコンクリート104の打設)を完了することが出来、鉄骨柱の納期に左右されにくいというメリットがある。   FIG. 6 is a perspective view showing a conventional example of a steel column embedding method, in which reference numeral 100 indicates a hole (a hole in a box) for installing the steel column 102, and reference numeral 103 indicates the hole. Reinforcing bars arranged around 100 are shown, and reference numeral 104 denotes concrete placed so as to bury the reinforcing bars 103. The method shown in FIG. 6 is advantageous in that the foundation work (that is, the arrangement of the reinforcing bars 103 and the placement of the concrete 104) can be completed even if the steel column is not delivered, and it is difficult to depend on the delivery date of the steel column. is there.

Press Release「鉄骨柱脚箱抜工法“SMART JOINT工法”を開発 −安藤建設・ハザマ 共同開発−[平成23年5月9日検索]、インターネット<http://www.hazama.co.jp/pressrelease/2005/050831.html>Press Release “Development of Steel Column Base Box Construction Method“ SMART JOINT Construction Method ”-Jointly developed by Ando Construction and Hazama-[Search May 9, 2011], Internet <http://www.hazama.co.jp/pressrelease /2005/050831.html> 西原寛、田端卓、外2名、「鉄骨柱脚箱抜き工法の構造性能に関する実験的研究(その1 実験概要)」、日本建築学会大会学術講演梗概集(近畿)、2005年9月Hiroshi Nishihara, Takashi Tabata, and two others, “Experimental Study on Structural Performance of Steel Column Base Boxing Method (Part 1 Outline of Experiment)”, Annual Meeting of the Architectural Institute of Japan (Kinki), September 2005

しかしながら、図6に示す従来工法の場合、鉄骨柱を埋め込む部分を箱抜き状態にしなければならないため、型枠等を用いた作業が必要となり、その作業が煩雑になるという問題があった。また、鉄骨柱を埋め込む穴の周囲には多量の鉄筋103を配置する必要があり、その配筋作業も繁雑になるという問題もあった。さらに、鉄骨柱の高さ調整は高さ調整用のモルタル105によって行われているが、その作業が煩雑になるという問題もあった。   However, in the case of the conventional method shown in FIG. 6, the portion in which the steel column is to be embedded has to be unboxed, which requires a work using a mold or the like, and there is a problem that the work becomes complicated. In addition, it is necessary to arrange a large amount of reinforcing bars 103 around the hole for embedding a steel column, and there is a problem that the work of arranging the bars becomes complicated. Furthermore, although the height adjustment of the steel column is performed by the mortar 105 for height adjustment, there is a problem that the work becomes complicated.

本発明は、上述の問題を解消することのできる鉄骨柱の建込工法、及び該工法に使用されるベース部材を提供することを目的とするものである。   An object of the present invention is to provide a steel column erection method that can solve the above-described problems, and a base member used in the method.

請求項1に係る発明は、図1及び図2に例示するものであって、鋼管からなる管部(10)と、該管部(10)に連結されると共に該管部(10)の軸方向(+z)と略直交する方向(±x,±y)に延設されてなる圧延鋼材(以下、「アンカー部」とする)(11)と、を有するベース部材(1)を、前記管部(10)が略上下方向に延設されると共に前記アンカー部(11)が略水平方向に延設されるように設置する工程と、
該アンカー部(11)を囲繞するように鉄筋(3)を配置する工程と、
該アンカー部(11)及び該鉄筋(3)を埋設するようにコンクリート(4)を打設する工程と、
鉄骨柱(2)の下端部を前記管部(10)に挿入して該鉄骨柱(2)を建て込む工程と、
該管部(10)の側に配置された第1ナット部材(図3(b) の符号13参照)に螺合されると共に管壁を貫通して前記管部(10)の内部(図3(b) の符号S参照)に略水平に突出されてなる水平位置調整ボルト(12)を操作して該水平位置調整ボルト(12)の該管部(10)の内部への突出量を調整することにより前記鉄骨柱(2)の水平位置を調整する工程と、
前記管部(10)の内部(図3(b) の符号S参照)にコンクリートを打設して該鉄骨柱(2)を固定する工程と、を備えたことを特徴とする。
The invention according to claim 1 is illustrated in FIG. 1 and FIG. 2, and includes a pipe part (10) made of a steel pipe, and a shaft of the pipe part (10) connected to the pipe part (10). A base member (1) having a rolled steel material (hereinafter referred to as "anchor portion") (11) extending in a direction (± x, ± y) substantially orthogonal to the direction (+ z), A step of installing the portion (10) so as to extend substantially vertically and the anchor portion (11) extending substantially horizontally;
Arranging the reinforcing bars (3) so as to surround the anchor portion (11);
Placing concrete (4) so as to embed the anchor portion (11) and the reinforcing bar (3);
Inserting the lower end portion of the steel column (2) into the pipe portion (10) to build the steel column (2);
It is screwed into a first nut member (see reference numeral 13 in FIG. 3 (b)) arranged on the side of the pipe part (10) and penetrates the pipe wall so that the inside of the pipe part (10) (FIG. The horizontal position adjusting bolt (12) protruding substantially horizontally is operated by adjusting the amount of protrusion of the horizontal position adjusting bolt (12) to the inside of the pipe part (10). Adjusting the horizontal position of the steel column (2) by:
A step of placing concrete in the pipe portion (10) (see S in FIG. 3B) to fix the steel column (2).

請求項2に係る発明は、図3(b) に例示するものであって、請求項1に係る発明において、前記水平位置調整ボルト(12)は少なくとも四方から前記鉄骨柱(2)を押し付けるように配置されていることを特徴とする。   The invention according to claim 2 is illustrated in FIG. 3B, and in the invention according to claim 1, the horizontal position adjusting bolt (12) presses the steel column (2) from at least four directions. It is characterized by being arranged in.

請求項3に係る発明は、図1及び図2に例示するものであって、請求項1又は2に係る発明において、前記水平位置調整ボルト(12)は、異なる高さに複数配置されていて、前記鉄骨柱(2)の建込角度を調整できるように構成されたことを特徴とする。   The invention according to claim 3 is illustrated in FIG. 1 and FIG. 2. In the invention according to claim 1 or 2, a plurality of the horizontal position adjusting bolts (12) are arranged at different heights. The steel column (2) is constructed so that the erection angle can be adjusted.

請求項4に係る発明は、図1及び図2に例示するものであって、請求項1乃至3のいずれか1項に記載の発明において、上下に貫通する第1貫通孔(不図示)を有する支持部材(5)を前記管部(10)の上端縁に載置し、
前記鉄骨柱(2)の側であって前記第1貫通孔の下方に相当する位置に、上下に貫通する第2貫通孔(2a)を形成し、
これらの第1貫通孔及び第2貫通孔(2a)に挿通されるように鉛直位置調整ボルト(6)を配置し、
前記1貫通孔が形成された部分及び前記第2貫通孔(2a)が形成された部分のいずれか一方は、他方の側に前記鉛直位置調整ボルト(6)が移動しないような状態で該鉛直位置調整ボルト(6)を回転自在に支持し、
該他方の側には、前記鉛直位置調整ボルト(6)に螺合されてなる第2ナット部材(不図示)を配置し、
該鉛直位置調整ボルト(6)を操作することにより前記鉄骨柱(2)の上下位置を調整することを特徴とする。
The invention according to claim 4 is illustrated in FIGS. 1 and 2, and in the invention according to any one of claims 1 to 3, a first through hole (not shown) penetrating vertically is provided. Placing the supporting member (5) on the upper edge of the pipe part (10);
Forming a second through hole (2a) penetrating vertically at a position corresponding to the lower side of the first through hole on the steel column (2) side;
The vertical position adjusting bolt (6) is disposed so as to be inserted through the first through hole and the second through hole (2a),
One of the portion where the first through hole is formed and the portion where the second through hole (2a) is formed is such that the vertical position adjusting bolt (6) does not move to the other side. The position adjustment bolt (6) is supported rotatably,
On the other side, a second nut member (not shown) screwed to the vertical position adjusting bolt (6) is disposed,
The vertical position of the steel column (2) is adjusted by operating the vertical position adjusting bolt (6).

請求項5に係る発明は、少なくとも一部がコンクリート(4)に埋設された状態で配置されると共に鉄骨柱(2)の下端部を支持するように構成されたベース部材(1)において、
略上下方向に延設された鋼管にて形成されて鉄骨柱(2)の下端部が挿入されるように構成された管部(10)と、
該管部(10)に連結されると共に略水平方向に延設された圧延鋼材からなるアンカー部(11)と、
を備え、
該アンカー部(11)はコンクリート(4)に埋設された状態に配置され、
前記管部(10)には、第1ナット部材(13)と、該第1ナット部材(13)に螺合されると共に管壁を貫通して該管部(10)の内部に略水平に突出されて前記鉄骨柱(2)の水平位置を規定する水平位置調整ボルト(12)と、が配置されてなることを特徴とする。
The invention according to claim 5 is the base member (1) configured to support the lower end portion of the steel column (2) while being arranged with at least a part embedded in the concrete (4).
A pipe portion (10) formed of a steel pipe extending in a substantially vertical direction and configured to be inserted into the lower end portion of the steel column (2);
An anchor part (11) made of a rolled steel material connected to the pipe part (10) and extending in a substantially horizontal direction;
With
The anchor part (11) is arranged in a state embedded in the concrete (4),
The pipe part (10) is screwed into the first nut member (13) and the first nut member (13) and penetrates the pipe wall so as to be substantially horizontal in the pipe part (10). A horizontal position adjusting bolt (12) protruding and defining a horizontal position of the steel column (2) is arranged.

なお、括弧内の番号などは、図面における対応する要素を示す便宜的なものであり、従って、本記述は図面上の記載に限定拘束されるものではない。   Note that the numbers in parentheses are for the sake of convenience indicating the corresponding elements in the drawings, and therefore the present description is not limited to the descriptions on the drawings.

請求項1及び5に係る発明によれば、鉄骨柱が現場に搬入されなくても基礎工事(つまり、鉄筋の配置、及びコンクリートの打設)を完了することが出来、基礎工事が鉄骨柱の納期の影響を受けないというメリットがある。また、本発明によれば、型枠として機能する管部をコンクリート打設後に取り外す必要が無いため、その分、作業が簡素化される。さらに、該管部の固定は、その周囲に埋設される鉄筋だけでなく該管部に連結されたアンカー部によっても行われるため、アンカー部を使用しない場合に比べて鉄筋の数を減らすことが出来、その配筋作業が簡素化される。またさらに、本発明によれば、鉄骨柱を建て込む穴は、鋼管からなる管部にて形成されているため、該管部を利用して上述のような水平位置調整ボルトを設けることができる。その結果、水平位置調整ボルトを時計回り又は反時計回りに回転させるだけで鉄骨柱の水平位置等を簡単に調整することができる。   According to the inventions according to claims 1 and 5, the foundation work (that is, the arrangement of the reinforcing bars and the placement of the concrete) can be completed even if the steel column is not carried into the site. There is an advantage that it is not affected by the delivery date. In addition, according to the present invention, it is not necessary to remove the pipe portion functioning as a mold after the concrete is placed, so that the work is simplified correspondingly. Furthermore, since the fixing of the pipe part is performed not only by the reinforcing bars embedded around the pipe part but also by an anchor part connected to the pipe part, the number of reinforcing bars can be reduced as compared with the case where the anchor part is not used. It is possible to simplify the bar arrangement work. Still further, according to the present invention, since the hole for installing the steel column is formed by a pipe portion made of a steel pipe, the horizontal position adjusting bolt as described above can be provided using the pipe portion. . As a result, the horizontal position and the like of the steel column can be easily adjusted simply by rotating the horizontal position adjusting bolt clockwise or counterclockwise.

請求項2に係る発明によれば、各水平位置調整ボルトを回転操作することにより、該鉄骨柱の位置調整を4つの方向に対して行うことができる。   According to the invention which concerns on Claim 2, the position adjustment of this steel column can be performed with respect to four directions by rotating each horizontal position adjustment bolt.

請求項3に係る発明によれば、前記鉄骨柱の建込角度を調整することができる。   According to the invention which concerns on Claim 3, the erection angle of the said steel column can be adjusted.

請求項4に係る発明によれば、高さ調整用のモルタルを使用しなくても、前記鉛直位置調整ボルトを操作するだけで鉄骨柱の高さ調整を簡単に行うことができる。   According to the invention which concerns on Claim 4, even if it does not use the mortar for height adjustment, the height adjustment of a steel column can be easily performed only by operating the said vertical position adjustment volt | bolt.

図1は、本発明に用いるベース部材及び鉄骨柱の構成の一例を示す斜視図である。FIG. 1 is a perspective view showing an example of the configuration of a base member and a steel column used in the present invention. 図2は、本発明に係る鉄骨柱の建込工法の一例を示す鉛直断面図である。FIG. 2 is a vertical sectional view showing an example of a steel column erection method according to the present invention. 図3(a) は図2のA−A断面図であり、図3(b) は図2のB−B断面図である。3A is a cross-sectional view taken along the line AA in FIG. 2, and FIG. 3B is a cross-sectional view taken along the line BB in FIG. 図4は、本発明に係る鉄骨柱の建込工法の一例を示す平面図である。FIG. 4 is a plan view showing an example of a steel column erection method according to the present invention. 図5は、ベース部材の構造の一例を示す分解斜視図である。FIG. 5 is an exploded perspective view showing an example of the structure of the base member. 図6は、鉄骨柱の建込工法の従来例を示す斜視図である。FIG. 6 is a perspective view showing a conventional example of a steel column embedding method.

以下、図1乃至図5に沿って、本発明の実施の形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to FIGS. 1 to 5.

本発明に係る鉄骨柱の建込工法は、建築物(例えば、集合住宅やオフィスビルや工場や倉庫や商業施設など)を建築する際に鉄骨柱を建て込む方法であって、図1に例示するような部材(少なくとも一部がコンクリート4に埋設された状態で配置されると共に鉄骨柱2の下端部を支持するように構成された部材であって、本明細書においては「ベース部材」とする)1を使用して鉄骨柱2を建て込む方法である。このベース部材1は、
・ 鋼管からなる管部10と、
・ 該管部10に連結されると共に該管部10の軸方向+zと略直交する方向±x,±yに延設されてなる圧延鋼材(本明細書においては「アンカー部」とする)11と、
を有している。なお、このベース部材1は、後述するように、前記管部10が略上下方向に延設される(つまり、前記軸方向+zが略上方を向く)と共に前記アンカー部11が略水平方向に延設される(つまり、前記方向±x,±yが略水平方向を向く)ように配置されることとなる。また、該アンカー部11は後述のようにコンクリート4に埋設された状態に配置される。
The steel column embedding method according to the present invention is a method of building a steel column when building a building (for example, an apartment house, an office building, a factory, a warehouse, a commercial facility, etc.), and is exemplified in FIG. Such a member (a member arranged at least partially embedded in the concrete 4 and configured to support the lower end portion of the steel column 2, in the present specification, a “base member”. This is a method of building a steel column 2 using 1. This base member 1 is
A pipe section 10 made of steel pipe;
A rolled steel material 11 (hereinafter referred to as “anchor portion”) 11 connected to the tube portion 10 and extended in the directions ± x and ± y substantially orthogonal to the axial direction + z of the tube portion 10 When,
have. As will be described later, in this base member 1, the tube portion 10 extends substantially in the vertical direction (that is, the axial direction + z faces substantially upward), and the anchor portion 11 extends in a substantially horizontal direction. (That is, the directions ± x and ± y are directed substantially in the horizontal direction). The anchor portion 11 is arranged in a state of being embedded in the concrete 4 as will be described later.

ところで、図1に示すベース部材1ではアンカー部11の数は4本であるが、もちろんこれに限られるものではなく、5本以上であっても、3本以下であっても良い。また、図1に示すアンカー部11は、その挟角θが略90度となるように設定されているが、もちろんこれに限られるものではなく、任意の角度にすると良い。さらに、このアンカー部11に使用する圧延鋼材としては、H形鋼やT形鋼等の形鋼、或いは棒鋼を挙げることができる。   By the way, in the base member 1 shown in FIG. 1, the number of the anchor portions 11 is four, but of course it is not limited to this, and may be five or more or three or less. In addition, the anchor portion 11 shown in FIG. 1 is set so that the included angle θ is approximately 90 degrees, but of course it is not limited to this, and may be an arbitrary angle. Furthermore, examples of the rolled steel material used for the anchor portion 11 include a shape steel such as an H-shaped steel and a T-shaped steel, or a bar steel.

一方、図1に示す管部10はいわゆる四角形鋼管であるが、もちろんこれに限られるものではなく、鉄骨柱2の下端部を挿入できるものであれば他の形状であっても良い。   On the other hand, although the pipe part 10 shown in FIG. 1 is what is called a square steel pipe, of course, it is not restricted to this, As long as the lower end part of the steel column 2 can be inserted, another shape may be sufficient.

また一方、この管部10には、挿入された鉄骨柱2の水平位置を調整するためのボルト(本明細書においては「水平位置調整ボルト」とする)12が取り付けられている。すなわち、該管部10の管壁には貫通孔(図3(b) に符号10aで示すように水平に貫通される貫通孔であって、以下、適宜「第3貫通孔」とする)が穿設されていて、該水平位置調整ボルト12が該第3貫通孔10aに挿通された状態で略水平に配置されている。したがって、該水平位置調整ボルト12は、前記管壁を貫通して該管部10の内部Sに略水平に突出されることとなる。また、この管部10の側には、前記第3貫通孔10aに略一致するようにナット部材(以下、「第1ナット部材」とする)13が配置されており、前記水平位置調整ボルト12がこの第1ナット部材13に螺合されて回転自在に支持されている。したがって、該水平位置調整ボルト12を時計回り又は反時計回りに回転させるとその突出量(つまり、前記管部10の内部Sへの突出量)も変化することとなり、その変化によって前記鉄骨柱2の水平位置を調整できるようになっている。   On the other hand, a bolt (referred to as “horizontal position adjusting bolt” in this specification) 12 for adjusting the horizontal position of the inserted steel column 2 is attached to the pipe portion 10. That is, the tube wall of the tube portion 10 has a through hole (a through hole that is horizontally penetrated as indicated by reference numeral 10a in FIG. 3 (b), hereinafter referred to as a “third through hole” as appropriate). The horizontal position adjusting bolts 12 are formed substantially horizontally in a state of being inserted through the third through holes 10a. Therefore, the horizontal position adjusting bolt 12 penetrates the tube wall and protrudes substantially horizontally into the interior S of the tube portion 10. Further, a nut member (hereinafter referred to as “first nut member”) 13 is disposed on the tube portion 10 side so as to substantially coincide with the third through hole 10 a, and the horizontal position adjusting bolt 12. Is screwed into the first nut member 13 and is rotatably supported. Therefore, when the horizontal position adjusting bolt 12 is rotated clockwise or counterclockwise, the amount of protrusion (that is, the amount of protrusion to the inside S of the tube portion 10) also changes. The horizontal position of can be adjusted.

そして、本発明に係る鉄骨柱の建込方法は以下の工程を備えている。すなわち、
・ 図2に示すように、上述したベース部材1の管部10が略上下方向に延設されると共に前記アンカー部11が略水平方向に延設されるように該ベース部材1を設置する工程
・ 前記アンカー部11を囲繞するように鉄筋(図2の符号3参照)を配置する工程
・ 該アンカー部11及び該鉄筋3を埋設するようにコンクリート4を打設する工程
・ 鉄骨柱2の下端部を前記管部10に挿入して該鉄骨柱2を建て込む工程
・ 該水平位置調整ボルト12を時計回り又は反時計回りに回転操作して該水平位置調整ボルト12の前記管部10の内部Sへの突出量を調整することにより前記鉄骨柱2の水平位置を調整する工程
・ 前記管部10の内部S(つまり、該管部10の内周壁と前記鉄骨柱2との間)にコンクリートを打設して該鉄骨柱2を固定する工程
And the construction method of the steel column which concerns on this invention is equipped with the following processes. That is,
As shown in FIG. 2, the step of installing the base member 1 so that the pipe portion 10 of the base member 1 described above extends substantially in the vertical direction and the anchor portion 11 extends in the substantially horizontal direction. A step of arranging a reinforcing bar (see reference numeral 3 in FIG. 2) so as to surround the anchor part 11 A step of placing concrete 4 so as to bury the anchor part 11 and the reinforcing bar 3 A lower end of the steel column 2 The step of inserting the steel part 2 into the pipe part 10 and installing the steel column 2 The inside of the pipe part 10 of the horizontal position adjusting bolt 12 by rotating the horizontal position adjusting bolt 12 clockwise or counterclockwise. Adjusting the horizontal position of the steel column 2 by adjusting the amount of protrusion to S. Concrete inside the tube portion 10 (that is, between the inner peripheral wall of the tube portion 10 and the steel column 2). To fix the steel column 2 Degree

本発明によれば、鉄骨柱が現場に搬入されなくても基礎工事(つまり、鉄筋3の配置、及びコンクリート4の打設)を完了することが出来、基礎工事が鉄骨柱の納期の影響を受けないというメリットがある。また、本発明によれば、型枠として機能する管部10をコンクリート打設後に取り外す必要が無いため、その分、作業が簡素化される。さらに、該管部10の固定は、その周囲に埋設される鉄筋3だけでなく該管部10に連結されたアンカー部11によっても行われるため、図6に示す従来工法に比べて鉄筋の数を減らすことが出来、その配筋作業が簡素化される。またさらに、本発明によれば、鉄骨柱2を建て込む穴は、鋼管からなる管部10にて形成されているため、該管部10を利用して上述のような水平位置調整ボルト12を設けることができる。その結果、水平位置調整ボルト12を時計回り又は反時計回りに回転させるだけで鉄骨柱2の水平位置等を簡単に調整することができる。   According to the present invention, the foundation work (that is, the placement of the reinforcing bars 3 and the placement of the concrete 4) can be completed even if the steel column is not carried to the site. There is merit that we do not receive. Further, according to the present invention, it is not necessary to remove the pipe portion 10 functioning as a mold after the concrete is placed, so that the work is simplified accordingly. Furthermore, since the fixing of the pipe portion 10 is performed not only by the reinforcing bars 3 embedded around the pipe portion 10 but also by the anchor portions 11 connected to the pipe portion 10, the number of reinforcing bars is larger than that of the conventional method shown in FIG. Can be reduced, and the bar arrangement work is simplified. Furthermore, according to the present invention, since the hole for installing the steel column 2 is formed in the pipe portion 10 made of a steel pipe, the horizontal position adjusting bolt 12 as described above is used by using the pipe portion 10. Can be provided. As a result, the horizontal position and the like of the steel column 2 can be easily adjusted simply by rotating the horizontal position adjusting bolt 12 clockwise or counterclockwise.

ところで、前記水平位置調整ボルト12は、図3(b) に例示するように、少なくとも四方から前記鉄骨柱2を押し付けるように配置しておくと良い。そのようにした場合には、各水平位置調整ボルト12を回転操作することにより、該鉄骨柱2の位置調整を4つの方向に対して行うことができる。   Incidentally, the horizontal position adjusting bolt 12 is preferably arranged so as to press the steel column 2 from at least four directions as illustrated in FIG. 3B. In such a case, the position adjustment of the steel column 2 can be performed in four directions by rotating each horizontal position adjustment bolt 12.

また、上述の水平位置調整ボルト12を、図1及び図2に例示するように、異なる高さに複数配置しておくと良い。そのようにした場合には、前記鉄骨柱2の建込角度を調整することができる。   Also, a plurality of the horizontal position adjusting bolts 12 described above may be arranged at different heights as illustrated in FIGS. 1 and 2. In such a case, the erection angle of the steel column 2 can be adjusted.

一方、図1及び図2に例示するように、上下に貫通する第1貫通孔(不図示)を有する支持部材5を前記管部10の上端縁に載置し、前記鉄骨柱2の側であって前記第1貫通孔の下方に相当する位置に、上下に貫通する第2貫通孔(図1の符号2a参照)を形成し、これらの第1貫通孔及び第2貫通孔2aに挿通されるように鉛直位置調整ボルト6を配置すると良い。そして、前記1貫通孔が形成された部分(つまり、前記支持部材5)及び前記第2貫通孔2aが形成された部分のいずれか一方は、他方の側に前記鉛直位置調整ボルト6が移動しないような状態で該鉛直位置調整ボルト6を回転自在に支持するようにし、該他方の側には、前記鉛直位置調整ボルト6に螺合されてなる第2ナット部材(不図示)を配置し、該鉛直位置調整ボルト6を操作することにより前記鉄骨柱2の上下位置を調整するようにすると良い。そのようにした場合には、高さ調整用のモルタルを使用しなくても、該鉛直位置調整ボルト6を操作するだけで鉄骨柱の高さ調整を簡単に行うことができる。   On the other hand, as illustrated in FIGS. 1 and 2, a support member 5 having a first through hole (not shown) penetrating vertically is placed on the upper edge of the tube portion 10, and on the steel column 2 side. A second through hole (see reference numeral 2a in FIG. 1) penetrating vertically is formed at a position corresponding to the lower side of the first through hole, and is inserted into the first through hole and the second through hole 2a. The vertical position adjusting bolt 6 may be arranged so The vertical position adjusting bolt 6 does not move to the other side of either the portion where the first through hole is formed (that is, the support member 5) or the portion where the second through hole 2a is formed. In such a state, the vertical position adjusting bolt 6 is rotatably supported, and a second nut member (not shown) screwed to the vertical position adjusting bolt 6 is disposed on the other side. It is preferable that the vertical position of the steel column 2 is adjusted by operating the vertical position adjusting bolt 6. In such a case, the height adjustment of the steel column can be easily performed only by operating the vertical position adjusting bolt 6 without using a mortar for height adjustment.

本実施例においては、鉄骨柱2を建て込む地盤を基礎底まで掘削し、砕石敷きを行い(図2の符号7参照)、捨てコンクリート8を打設した。なお、砕石の厚さは100mmとし、捨てコンクリートの厚さは50mmとした。   In this example, the ground into which the steel column 2 was built was excavated to the bottom of the foundation, crushed with stone (see reference numeral 7 in FIG. 2), and discarded concrete 8 was cast. The thickness of crushed stone was 100 mm, and the thickness of discarded concrete was 50 mm.

次に、図1に示す構造のベース部材1を作製した。すなわち、図5に示すように、150mm×150mmのH形鋼(アンカー部)11を十字形に組み、その交差部に四角形鋼管10Aを溶接し、該鋼管10Aの下方には鋼片10Bを溶接した。なお、このベース部材1には上述の水平位置調整ボルト12を12本取り付けておき、管部10が略上下方向に延設されるように該ベース部材1を捨てコンクリート8の上に配置した。   Next, the base member 1 having the structure shown in FIG. 1 was produced. That is, as shown in FIG. 5, a 150 mm × 150 mm H-shaped steel (anchor part) 11 is assembled in a cross shape, a rectangular steel pipe 10A is welded to the intersecting part, and a steel piece 10B is welded below the steel pipe 10A. did. Note that twelve horizontal position adjusting bolts 12 described above were attached to the base member 1, and the base member 1 was discarded and placed on the concrete 8 so that the pipe portion 10 was extended substantially in the vertical direction.

そして、図4に詳示するように、前記アンカー部11を囲繞するように鉄筋3を配置し、該アンカー部11及び該鉄筋3を埋設するようにコンクリート4を打設してフーチングを形成した。   Then, as shown in detail in FIG. 4, the reinforcing bar 3 is arranged so as to surround the anchor part 11, and the concrete 4 is placed so as to bury the anchor part 11 and the reinforcing bar 3 to form a footing. .

一方、鉄骨柱2の底面には、第2貫通孔2aが穿設されたベースプレート(図1の符号2b参照)を取り付け、該ベースプレート2bの下方には鉤状の部材2cを突出させておいた。この鉄骨柱2が現場に搬入されると、該鉄骨柱2の下端部を前記管部10に挿入して該鉄骨柱2を建て込んだ。その後、前記水平位置調整ボルト12を時計回り又は反時計回りに回転操作して該水平位置調整ボルト12の前記管部10の内部Sへの突出量を調整することにより前記鉄骨柱2の水平位置を調整した。さらに、第1貫通孔が穿設された支持部材5(75×75×6の等辺山形鋼)を2本、前記管部10の上端面に載置し、前記第1貫通孔及び前記第2貫通孔2aに鉛直位置調整ボルト6を挿通させて、該ボルト6を回転操作することにより前記鉄骨柱2の高さ調整を行った。   On the other hand, a base plate (see reference numeral 2b in FIG. 1) having a second through hole 2a is attached to the bottom surface of the steel column 2, and a bowl-shaped member 2c is projected below the base plate 2b. . When the steel column 2 was carried into the site, the lower end portion of the steel column 2 was inserted into the pipe portion 10 and the steel column 2 was built. Thereafter, the horizontal position adjusting bolt 12 is rotated clockwise or counterclockwise to adjust the amount of protrusion of the horizontal position adjusting bolt 12 into the inside S of the pipe portion 10, thereby adjusting the horizontal position of the steel column 2. Adjusted. Further, two support members 5 (75 × 75 × 6 equilateral mountain steel) having a first through hole are placed on the upper end surface of the tube portion 10, and the first through hole and the second The vertical position adjusting bolt 6 was inserted into the through hole 2a, and the bolt 6 was rotated to adjust the height of the steel column 2.

このようにして鉄骨柱2の水平位置及び高さを適正位置に調整した後、管部10の内部Sにコンクリート(又はモルタル)を打設して該鉄骨柱2を固定した。その際、上述の鉤状の部材2cはコンクリートに埋設されることとなり、鉄骨柱2を引き抜こうとする外力に抵抗するように機能することとなる。   Thus, after adjusting the horizontal position and height of the steel column 2 to an appropriate position, concrete (or mortar) was cast in the inside S of the pipe part 10, and this steel column 2 was fixed. At that time, the above-described bowl-shaped member 2c is embedded in the concrete, and functions to resist an external force trying to pull out the steel column 2.

1 ベース部材
2 鉄骨柱
2a 第2貫通孔
3 鉄筋
4 コンクリート
5 支持部材
6 鉛直位置調整ボルト
10 管部
11 アンカー部
12 水平位置調整ボルト
13 第1ナット部材
+z 管部の軸方向
DESCRIPTION OF SYMBOLS 1 Base member 2 Steel column 2a 2nd through-hole 3 Reinforcement 4 Concrete 5 Support member 6 Vertical position adjustment bolt 10 Pipe part 11 Anchor part 12 Horizontal position adjustment bolt 13 1st nut member + z Axial direction of pipe part

Claims (5)

鋼管からなる管部と、該管部に連結されると共に該管部の軸方向と略直交する方向に延設されてなる圧延鋼材(以下、「アンカー部」とする)と、を有するベース部材を、前記管部が略上下方向に延設されると共に前記アンカー部が略水平方向に延設されるように設置する工程と、
該アンカー部を囲繞するように鉄筋を配置する工程と、
該アンカー部及び該鉄筋を埋設するようにコンクリートを打設する工程と、
鉄骨柱の下端部を前記管部に挿入して該鉄骨柱を建て込む工程と、
該管部の側に配置された第1ナット部材に螺合されると共に管壁を貫通して前記管部の内部に略水平に突出されてなる水平位置調整ボルトを操作して該水平位置調整ボルトの該管部の内部への突出量を調整することにより前記鉄骨柱の水平位置を調整する工程と、
前記管部の内部にコンクリートを打設して該鉄骨柱を固定する工程と、
を備えたことを特徴とする鉄骨柱の建込工法。
A base member having a pipe portion made of a steel pipe and a rolled steel material (hereinafter referred to as “anchor portion”) connected to the pipe portion and extending in a direction substantially orthogonal to the axial direction of the pipe portion. A step of installing the pipe portion so as to extend in a substantially vertical direction and the anchor portion so as to extend in a substantially horizontal direction;
Arranging a reinforcing bar so as to surround the anchor part;
Placing concrete so as to bury the anchor part and the reinforcing bar;
Inserting the lower end of the steel column into the pipe part and building the steel column;
The horizontal position adjustment is performed by operating a horizontal position adjusting bolt which is screwed into a first nut member arranged on the side of the pipe part and penetrates the pipe wall and protrudes substantially horizontally into the pipe part. Adjusting the horizontal position of the steel column by adjusting the amount of protrusion of the bolt into the tube part; and
Placing the concrete inside the pipe portion and fixing the steel column; and
A steel column construction method characterized by comprising:
前記水平位置調整ボルトは少なくとも四方から前記鉄骨柱を押し付けるように配置されている、
ことを特徴とする請求項1に記載の鉄骨柱の建込工法。
The horizontal position adjustment bolt is arranged to press the steel column from at least four sides.
The steel column embedding method according to claim 1.
前記水平位置調整ボルトは、異なる高さに複数配置されていて、前記鉄骨柱の建込角度を調整できるように構成された、
ことを特徴とする請求項1又は2に記載の鉄骨柱の建込工法。
A plurality of the horizontal position adjustment bolts are arranged at different heights, and configured to be able to adjust the erection angle of the steel column,
The steel column embedding method according to claim 1 or 2.
上下に貫通する第1貫通孔を有する支持部材を前記管部の上端縁に載置し、
前記鉄骨柱の側であって前記第1貫通孔の下方に相当する位置に、上下に貫通する第2貫通孔を形成し、
これらの第1貫通孔及び第2貫通孔に挿通されるように鉛直位置調整ボルトを配置し、
前記1貫通孔が形成された部分及び前記第2貫通孔が形成された部分のいずれか一方は、他方の側に前記鉛直位置調整ボルトが移動しないような状態で該鉛直位置調整ボルトを回転自在に支持し、
該他方の側には、前記鉛直位置調整ボルトに螺合されてなる第2ナット部材を配置し、
該鉛直位置調整ボルトを操作することにより前記鉄骨柱の上下位置を調整する、
ことを特徴とする請求項1乃至3のいずれか1項に記載の鉄骨柱の建込工法。
A support member having a first through-hole penetrating vertically is placed on the upper edge of the pipe part,
Forming a second through-hole penetrating vertically at a position corresponding to the lower side of the first through-hole on the steel column side;
The vertical position adjustment bolt is arranged so as to be inserted into these first through hole and second through hole,
Either the portion where the first through hole is formed or the portion where the second through hole is formed can freely rotate the vertical position adjusting bolt in a state where the vertical position adjusting bolt does not move to the other side. To support
On the other side, a second nut member screwed to the vertical position adjusting bolt is disposed,
Adjusting the vertical position of the steel column by operating the vertical position adjustment bolt;
The steel column erection method according to any one of claims 1 to 3.
少なくとも一部がコンクリートに埋設された状態で配置されると共に鉄骨柱の下端部を支持するように構成されたベース部材において、
略上下方向に延設された鋼管にて形成されて鉄骨柱の下端部が挿入されるように構成された管部と、
該管部に連結されると共に略水平方向に延設された圧延鋼材からなるアンカー部と、
を備え、
該アンカー部はコンクリートに埋設された状態に配置され、
前記管部には、第1ナット部材と、該第1ナット部材に螺合されると共に管壁を貫通して該管部の内部に略水平に突出されて前記鉄骨柱の水平位置を規定する水平位置調整ボルトと、が配置されてなる、
ことを特徴とするベース部材。
In a base member that is arranged with at least a portion embedded in concrete and is configured to support the lower end of a steel column,
A pipe portion formed of a steel pipe extending substantially in the vertical direction and configured to be inserted into the lower end of the steel column;
An anchor portion made of a rolled steel material connected to the pipe portion and extending in a substantially horizontal direction;
With
The anchor portion is arranged in a state embedded in concrete,
A first nut member and a first nut member are screwed onto the tube portion and penetrate the tube wall and project substantially horizontally into the tube portion to define the horizontal position of the steel column. A horizontal position adjusting bolt, and
A base member characterized by that.
JP2011120055A 2011-05-30 2011-05-30 Steel column construction method Active JP5721221B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011120055A JP5721221B2 (en) 2011-05-30 2011-05-30 Steel column construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011120055A JP5721221B2 (en) 2011-05-30 2011-05-30 Steel column construction method

Publications (2)

Publication Number Publication Date
JP2012246696A true JP2012246696A (en) 2012-12-13
JP5721221B2 JP5721221B2 (en) 2015-05-20

Family

ID=47467403

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011120055A Active JP5721221B2 (en) 2011-05-30 2011-05-30 Steel column construction method

Country Status (1)

Country Link
JP (1) JP5721221B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018204379A (en) * 2017-06-08 2018-12-27 新日鐵住金株式会社 Joint structure for steel material
KR20220039327A (en) * 2020-09-22 2022-03-29 삼성엔지니어링 주식회사 Shear Reinforcement Integrated with Vertical Rebars that can be Constructed with a Crane and its Installation Method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227735B (en) * 2020-09-30 2021-04-20 中建鸿腾建设集团有限公司 Centering assembly for hoisting assembled column

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH032107U (en) * 1989-05-30 1991-01-10
JPH0535902U (en) * 1991-10-16 1993-05-18 清水建設株式会社 Steel column joint structure
JPH10219700A (en) * 1996-12-03 1998-08-18 Nkk Corp Joint structure of column base part and steel-made underground beam
JP2002146800A (en) * 2000-11-14 2002-05-22 Nippon Steel Corp Connecting structure between superstructure and foundation pile, and support hardware
JP2003105858A (en) * 2001-09-28 2003-04-09 Daiwa House Ind Co Ltd Embedded-in-concrete type column base structure of square steel tube column

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH032107U (en) * 1989-05-30 1991-01-10
JPH0535902U (en) * 1991-10-16 1993-05-18 清水建設株式会社 Steel column joint structure
JPH10219700A (en) * 1996-12-03 1998-08-18 Nkk Corp Joint structure of column base part and steel-made underground beam
JP2002146800A (en) * 2000-11-14 2002-05-22 Nippon Steel Corp Connecting structure between superstructure and foundation pile, and support hardware
JP2003105858A (en) * 2001-09-28 2003-04-09 Daiwa House Ind Co Ltd Embedded-in-concrete type column base structure of square steel tube column

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018204379A (en) * 2017-06-08 2018-12-27 新日鐵住金株式会社 Joint structure for steel material
KR20220039327A (en) * 2020-09-22 2022-03-29 삼성엔지니어링 주식회사 Shear Reinforcement Integrated with Vertical Rebars that can be Constructed with a Crane and its Installation Method
KR102429445B1 (en) * 2020-09-22 2022-08-04 삼성엔지니어링 주식회사 Shear Reinforcement Integrated with Vertical Rebars that can be Constructed with a Crane and its Installation Method

Also Published As

Publication number Publication date
JP5721221B2 (en) 2015-05-20

Similar Documents

Publication Publication Date Title
JP2008025125A (en) Column unit and construction method for building using it
JP6815183B2 (en) Complex building
JP6111922B2 (en) Column base reinforcement method and apparatus
JP4284056B2 (en) Non-embedded column base construction method and non-embedded column base structure
JP5721221B2 (en) Steel column construction method
JP5896441B1 (en) Assembly block
JP5662677B2 (en) Multistory building
JP2006265980A (en) Steel foundation structure
JP5159942B1 (en) Column base of building
JP2007321400A (en) Pile head jointing structure and jointing material for use in it
JP5129297B2 (en) Building installation tools
JP2008223242A (en) Manufacturing method for precast concrete panel
JP2008223466A (en) Log fence and components for fence
JP5379277B2 (en) Seismic structure of tombstone
JP2012229531A (en) Column base part of building and method of fixing column base part of building
JP6300228B2 (en) Flat slab structure
KR101692151B1 (en) A deck support frame
JP5828572B2 (en) How to build steel columns
JP7083285B2 (en) Seismic isolation upper foundation structure and its manufacturing method
JP6873302B2 (en) Complex building
JP6807157B2 (en) Joint member and joint structure
JP6331089B2 (en) Extension structure and construction method of extension building
JP5501294B2 (en) Support device for anchor bolt for foundation
JP2020133199A (en) Deck, deck structure, and method of constructing deck
JP2004353254A (en) Foundation structure of building and its construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20131129

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140822

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140909

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20141030

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150320

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150320

R150 Certificate of patent or registration of utility model

Ref document number: 5721221

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250