JP2012012877A - Bridge construction method - Google Patents

Bridge construction method Download PDF

Info

Publication number
JP2012012877A
JP2012012877A JP2010151898A JP2010151898A JP2012012877A JP 2012012877 A JP2012012877 A JP 2012012877A JP 2010151898 A JP2010151898 A JP 2010151898A JP 2010151898 A JP2010151898 A JP 2010151898A JP 2012012877 A JP2012012877 A JP 2012012877A
Authority
JP
Japan
Prior art keywords
girder
bridge
erection
pair
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010151898A
Other languages
Japanese (ja)
Other versions
JP5487031B2 (en
Inventor
Toshiyuki Tachikawa
俊之 舘川
Masanori Suzuki
政則 鈴木
Hiroyuki Ochiai
博幸 落合
Masaki Ogasawara
正樹 小笠原
Susumu Nagai
進 永井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SMCTECH CO Ltd
Sumitomo Mitsui Construction Co Ltd
Original Assignee
SMCTECH CO Ltd
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SMCTECH CO Ltd, Sumitomo Mitsui Construction Co Ltd filed Critical SMCTECH CO Ltd
Priority to JP2010151898A priority Critical patent/JP5487031B2/en
Publication of JP2012012877A publication Critical patent/JP2012012877A/en
Application granted granted Critical
Publication of JP5487031B2 publication Critical patent/JP5487031B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To shorten a construction period and to reduce a construction cost of a bridge-construction method with which a plurality of precast beams are installed at prescribed intervals in the bridge axis orthogonal direction, even in the case that a pair of bridge piers are nonparallel to each other.SOLUTION: In a bridge construction method, a beam-installation work is efficiently carried out by; lifting up precast beams 14 with a construction girder 104 in a carrying-in yard Y located on the side of an installation span S0; and shifting them in the bridge axis orthogonal direction up to a designated installation position and lowering them down by the same construction girder. The construction girder 104 is placed so as to be turnable around a vertical axis Ax relative to each of lateral-transfer rails 102A and 102B, and to be movable in the bridge-axis direction relative to one of them. Each of a pair of lifting devices 106 is placed so as to be movable in the longitudinal direction of the construction girder 104. With all these arrangements, precast beams 14 can be smoothly laterally transferred and be suspended and supported at appropriate positions, even in the case that a pair of bridge piers 12A and 12B are nonparallel to each other.

Description

本願発明は、架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する橋梁架設方法に関するものである。   The present invention relates to a bridge erection method in which a plurality of precast girders are erected at a predetermined interval in a direction perpendicular to the bridge axis between a pair of bridge piers located on both sides in the bridge axis direction between erection diameters.

従来より、多径間連続橋等の橋梁架設方法として、架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する方法が知られている。   Conventionally, as a method of erection of bridges such as multi-span continuous bridges, a plurality of precast girders are erected at predetermined intervals in the direction perpendicular to the bridge axis between a pair of bridge piers located on both sides of the bridge axis between the installation diameters. How to do is known.

その際「特許文献1」には、橋軸方向に延びる架設用ガーダによりプレキャスト桁を吊り支持した状態で、プレキャスト桁の横取りを行うようにした橋梁架設方法が記載されている。   In this case, “Patent Document 1” describes a bridge erection method in which the precast girder is intercepted while the precast girder is suspended and supported by a girder for erection extending in the bridge axis direction.

すなわち、この「特許文献1」に記載された橋梁架設方法においては、1対の橋脚の各々の上面に設置された橋軸直交方向に延びる横取りレールに対して、その長手方向に移動可能な態様で架設用ガーダを設置しておき、この架設用ガーダにより、架設径間の側端位置において複数のプレキャスト桁を順次吊り上げて、その架設予定位置まで橋軸直交方向に移動させて吊り下ろすようにしている。   That is, in the bridge erection method described in “Patent Document 1”, a mode in which it is movable in the longitudinal direction with respect to a horizontal rail that extends in a direction perpendicular to the bridge axis and is installed on the upper surface of each pair of bridge piers. The installation girder is installed in advance, and with this installation girder, multiple precast girders are sequentially lifted at the side end positions between the installation diameters, and moved to the planned installation position in the direction perpendicular to the bridge axis and suspended. ing.

一方「特許文献2」には、複数の横取りレールのうちの1つが橋軸直交方向に対して傾斜している場合において、この横取りレールに対してその長手方向に移動可能なスライド装置を設置した上で、このスライド装置に対して、長尺の桁ブロックを橋軸方向に移動可能な態様で載置しておくことにより、桁ブロックの横取りを円滑に行い得るようにした橋梁架設方法が記載されている。   On the other hand, in “Patent Document 2”, when one of a plurality of horizontal rails is inclined with respect to the direction orthogonal to the bridge axis, a slide device is installed that is movable in the longitudinal direction with respect to the horizontal rail. Above, a bridge laying method is described in which a long girder block is placed in such a manner that it can be moved in the direction of the bridge axis so that the girder block can be smoothly intercepted. Has been.

また「特許文献3」には、1対の横取りレールを互いに非平行に配置しておくとともに、これら各横取りレールに対してその長手方向に移動可能なスライド装置を設置した上で、これら1対のスライド装置に橋桁を架け渡し、その際、この橋桁を、各スライド装置に対して橋軸方向に移動可能な態様で載置しておくことにより、橋桁を横取りする際の橋桁の姿勢の自由度を高めるようにした橋梁架設方法が記載されている。   In “Patent Document 3”, a pair of horizontal rails are arranged non-parallel to each other, and a slide device that can move in the longitudinal direction is installed on each horizontal rail. The bridge girder is bridged to the slide device, and the bridge girder is placed in such a manner that it can be moved in the direction of the bridge axis with respect to each slide device. The bridge erection method which raised the degree is described.

特開2009−68249号公報JP 2009-68249 A 特開平2−256705号公報JP-A-2-256705 特開2006−16795号公報JP 2006-16795 A

上記「特許文献1」に記載された橋梁架設方法のように、架設用ガーダによりプレキャスト桁を吊り支持した状態で、プレキャスト桁の横取りを行うようにすれば、架設作業を効率良く行うことができ、しかもその際、軽量の架設用ガーダを用いることができるので、工期短縮および工費低減を図ることができる。   If the precast girder is intercepted in a state where the precast girder is suspended and supported by the girder for erection as in the bridge erection method described in “Patent Document 1”, the erection work can be performed efficiently. Moreover, since a lightweight construction girder can be used at that time, the construction period can be shortened and the construction cost can be reduced.

しかしながら、この橋梁架設方法では、1対の橋脚が非平行に配置されている場合、あるいは、複数のプレキャスト桁が互いに非平行に架設されるようになっている場合(以下これらをまとめて「1対の橋脚が非平行である場合等」ともいう)には、横取りの際、架設用ガーダに対して、その両横取りレール間の距離を変化させようとする外力や、架設用ガーダを橋軸方向に延びる状態から旋回させようとする外力が作用するため、架設用ガーダを各プレキャスト桁の架設予定位置まで移動させることができない、という問題がある。   However, in this bridge construction method, when a pair of piers are arranged non-parallel, or when a plurality of precast girders are constructed so as to be non-parallel to each other (hereinafter collectively referred to as “1 For example, when a pair of bridge piers are non-parallel ”, the external girder that tries to change the distance between the two horizontal rails and the girder for installation are applied to the bridge girder. There is a problem that the girder for erection cannot be moved to the planned erection position of each precast girder because an external force is applied to turn from a state extending in the direction.

そして、このような場合には、大型のトラッククレーンを用いて各プレキャスト桁を直接架設することが必要となるが、架設環境によっては(例えば架設径間の地盤が軟弱であったり平坦でない場合等には)、これを実現することが不可能または困難となり、このため工期短縮および工費低減を図ることができない、という問題がある。   In such a case, it is necessary to install each precast girder directly using a large truck crane. However, depending on the installation environment (for example, when the ground between the installation diameters is soft or uneven) However, there is a problem that it becomes impossible or difficult to realize this, and therefore it is not possible to shorten the construction period and the construction cost.

一方、このような架設用ガーダを用いた橋梁架設方法において、上記「特許文献2」や「特許文献3」に記載されているような、2方向の相対移動を許容するスライド装置を用いることも考えられる。しかしながら、このようなスライド装置を単に用いるようにしただけでは、1対の橋脚が非平行である場合等において架設用ガーダに吊り支持されたプレキャスト桁をその架設予定位置まで確実に移動させることは困難である。   On the other hand, in such a bridge erection method using the erection girder, a slide device that allows relative movement in two directions as described in the above-mentioned “Patent Document 2” and “Patent Document 3” may be used. Conceivable. However, by simply using such a slide device, it is possible to reliably move the precast girder suspended and supported by the erection girder to the erection planned position when the pair of piers are non-parallel. Have difficulty.

本願発明は、このような事情に鑑みてなされたものであって、架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する橋梁架設方法において、1対の橋脚が非平行である場合等においても工期短縮および工費低減を図ることができる橋梁架設方法を提供することを目的とするものである。   The present invention has been made in view of such circumstances, and a plurality of precast girders are provided at predetermined intervals in a direction perpendicular to the bridge axis between a pair of bridge piers located on both sides of the bridge axis direction between the spanning diameters. It is an object of the present invention to provide a bridge erection method that can shorten the construction period and reduce the construction cost even when a pair of piers are non-parallel.

本願発明は、架設用ガーダを用いてプレキャスト桁の横取りを行うようにした上で、そのプレキャスト桁に対する吊り支持の方法に工夫を施すことにより、上記目的達成を図るようにしたものである。   In the present invention, the precast girder is intercepted by using a girder for installation, and the above object is achieved by devising a method for supporting the precast girder.

すなわち、本願発明に係る橋梁架設方法は、
架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する橋梁架設方法において、
上記1対の橋脚の各々の上面に、略橋軸直交方向に延びる横取りレールを、該横取りレールの一端部が上記架設径間の側方に位置する搬入ヤードまで張り出す態様で設置するとともに、橋軸方向に延びる架設用ガーダを、上記架設径間を跨ぐ位置において、上記1対の横取りレールの各々に対して該横取りレールの長手方向に移動可能な態様で設置した状態で、
上記搬入ヤードにおいて、上記架設用ガーダに設置された1対の吊上げ装置により、上記複数のプレキャスト桁のうちの1つを架設対象プレキャスト桁として吊り上げて、上記架設用ガーダを上記架設対象プレキャスト桁の架設予定位置まで橋軸直交方向に移動させた後、上記1対の吊上げ装置により上記架設対象プレキャスト桁を上記1対の橋脚上に吊り下ろし、以下これを繰り返すことにより上記複数のプレキャスト桁の架設を行うようにし、
その際、上記架設用ガーダを、上記1対の横取りレールの各々に対して鉛直軸線回りに回動可能な態様で、かつ、上記1対の横取りレールのうちの一方に対して橋軸方向に移動可能な態様で設置しておくとともに、上記1対の吊上げ装置の各々を、上記架設用ガーダに対して該架設用ガーダの長手方向に移動可能な態様で設置しておく、ことを特徴とするものである。
That is, the bridge erection method according to the present invention is:
In the bridge erection method, a plurality of precast girders are erected at a predetermined interval in a direction perpendicular to the bridge axis between a pair of piers located on both sides in the bridge axis direction between the erection diameters.
On the upper surface of each of the pair of bridge piers, a horizontal rail extending in a direction substantially perpendicular to the bridge axis is installed in such a manner that one end of the horizontal rail extends to a carry-in yard located on the side between the spanning diameters, In the state where the girder for installation extending in the bridge axis direction is installed in a manner movable in the longitudinal direction of the horizontal rail with respect to each of the pair of horizontal rails at a position straddling the span between the installation diameters,
In the carry-in yard, one of the plurality of precast girders is lifted as a precast girder for installation by a pair of lifting devices installed on the girder for construction, and the girder for construction is installed in the precast girder for construction. After moving in the direction perpendicular to the bridge axis to the planned installation position, the above-described precast girders are suspended on the above-mentioned pair of bridge piers by the above-described pair of lifting devices, and the above-described steps are repeated to construct the plurality of precast girders. And do
In that case, the construction girder is configured to be rotatable around a vertical axis with respect to each of the pair of horizontal rails, and in a bridge axis direction with respect to one of the pair of horizontal rails. It is installed in a movable manner, and each of the pair of lifting devices is installed in a manner movable in the longitudinal direction of the erection girder with respect to the erection girder. To do.

上記各「横取りレール」は、その一端部が搬入ヤードまで張り出すように設置されたものであれば、その具体的な構成は特に限定されるものではない。   The specific configuration of each of the above-mentioned “horizontal rails” is not particularly limited as long as one end portion thereof is installed so as to project to the carry-in yard.

上記「架設用ガーダ」を、1対の横取りレールの各々に対して鉛直軸線回りに回動可能な態様で、かつ、その一方に対して橋軸方向に移動可能な態様で設置しておくための具体的な構成は特に限定されるものではない。   To install the “erection girder” in such a manner that it can rotate around the vertical axis with respect to each of the pair of horizontal rails, and can move in the direction of the bridge axis with respect to one of the rails. The specific configuration is not particularly limited.

上記1対の「吊上げ装置」の各々を、架設用ガーダに対してその長手方向に移動可能な態様で設置しておくための具体的な構成は特に限定されるものではない。   The specific configuration for installing each of the pair of “lifting devices” in a manner movable in the longitudinal direction with respect to the girder for installation is not particularly limited.

上記構成に示すように、本願発明に係る橋梁架設方法においては、架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する際、1対の橋脚の各々の上面に、略橋軸直交方向に延びる横取りレールを、その一端部が架設径間の側方に位置する搬入ヤードまで張り出す態様で設置するとともに、橋軸方向に延びる架設用ガーダを、架設径間を跨ぐ位置において、1対の横取りレールの各々に対して該横取りレールの長手方向に移動可能な態様で設置した状態で、搬入ヤードにおいて、架設用ガーダに設置された1対の吊上げ装置により、複数のプレキャスト桁のうちの1つを架設対象プレキャスト桁として吊り上げて、架設用ガーダを架設対象プレキャスト桁の架設予定位置まで橋軸直交方向に移動させた後、1対の吊上げ装置により架設対象プレキャスト桁を1対の橋脚上に吊り下ろし、以下これを繰り返すことにより複数のプレキャスト桁の架設を行うようになっているので、次のような作用効果を得ることができる。   As shown in the above configuration, in the bridge erection method according to the present invention, a plurality of precast girders are placed at a predetermined interval in the direction perpendicular to the bridge axis between a pair of bridge piers located on both sides in the bridge axis direction between the installation diameters. When installing, on the upper surface of each of the pair of bridge piers, a horizontal rail extending in a direction substantially orthogonal to the bridge axis is installed in such a manner that one end portion extends to a carry-in yard located on the side between the installation diameters, A girder for installation extending in the direction of the bridge axis is installed in the carry-in yard in a state where the girder for installation is movable in the longitudinal direction of the horizontal rails with respect to each of the pair of horizontal rails at a position straddling the span between the installation diameters. One pair of precast girders is lifted as a precast girder for installation by a pair of lifting devices installed on the girder for construction, and the girder for construction is set to the planned construction position of the precast girder for construction. After moving in the direction perpendicular to the bridge axis, the precast girders to be erected are hung on a pair of bridge piers by a pair of lifting devices, and a plurality of precast girders are constructed by repeating this procedure. The following effects can be obtained.

すなわち、架設用ガーダを用いてプレキャスト桁の横取りを行うようになっているので、架設作業を効率良く行うことができる。しかもその際、軽量の架設用ガーダを用いることができるので、工期短縮および工費低減を図ることができる。さらに、架設径間の側方に搬入ヤードを確保することができれば、架設径間の地盤が軟弱であったり平坦でない場合等においても、架設対象プレキャスト桁の架設作業を容易に行うことができる。   That is, since the precast girder is intercepted using the girder for erection, the erection work can be performed efficiently. In addition, since a lightweight construction girder can be used at that time, the construction period can be shortened and the construction cost can be reduced. Furthermore, if a carry-in yard can be secured to the side between the installation diameters, the installation work of the installation target precast girder can be easily performed even when the ground between the installation diameters is soft or not flat.

その上で、本願発明に係る橋梁架設方法においては、架設用ガーダを、1対の横取りレールの各々に対して鉛直軸線回りに回動可能な態様で、かつ、1対の横取りレールのうちの一方に対して橋軸方向に移動可能な態様で設置しておくようになっているので、1対の橋脚が非平行に配置されていたり、複数のプレキャスト桁が互いに非平行に架設されるようになっていることに起因して、横取りの際、架設用ガーダに対して、その両横取りレール間の距離を変化させようとする外力や、架設用ガーダを橋軸方向に延びる状態から旋回させようとする外力が作用したとき、これらに追従させて架設用ガーダを相対移動させることができる。そしてこれにより、架設用ガーダを架設対象プレキャスト桁の架設予定位置まで円滑に移動させることができる。   In addition, in the bridge erection method according to the present invention, the girder for erection can be rotated around the vertical axis with respect to each of the pair of horizontal rails, and of the pair of horizontal rails. Since it is installed in such a manner that it can move in the direction of the bridge axis, a pair of bridge piers are arranged non-parallel, or a plurality of precast girders are installed non-parallel to each other Due to the fact that, in the case of a horizontal take-off, the installation girder is swung from an external force that attempts to change the distance between the both horizontal take-off rails or a state in which the installation girder extends in the direction of the bridge axis. When an external force is applied, the erection girder can be moved relative to the external force. Thus, the erection girder can be smoothly moved to the erection planned position of the erection target precast girder.

しかも、本願発明に係る橋梁架設方法においては、1対の吊上げ装置の各々を、架設用ガーダに対してその長手方向に移動可能な態様で設置しておくようになっているので、横取りの際、架設用ガーダの両横取りレール間の距離が変化するようなことがあっても、架設対象プレキャスト桁を架設径間において両橋脚と干渉するおそれのない適正な位置に吊下げ支持された状態に維持しておくことが容易に可能となる。そしてこれにより、架設対象プレキャスト桁を架設予定位置まで確実に移動させることができる。   Moreover, in the bridge erection method according to the present invention, each of the pair of lifting devices is installed in a manner movable in the longitudinal direction with respect to the erection girder. Even if the distance between the horizontal rails of the girder for erection may change, the precast girder for erection is suspended and supported at an appropriate position that does not interfere with both piers between the erection diameters. It can be easily maintained. As a result, the erection target precast girder can be reliably moved to the erection planned position.

このように本願発明によれば、架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する橋梁架設方法において、1対の橋脚が非平行である場合等においても、各プレキャスト桁を架設予定位置まで確実に移動させることができる。そしてこれにより工期短縮および工費低減を図ることができる。   Thus, according to the present invention, in the bridge erection method, a plurality of precast girders are erected at a predetermined interval in the direction perpendicular to the bridge axis between a pair of piers located on both sides of the bridge axis direction between the erection diameters. Even when the pair of bridge piers are non-parallel, each precast girder can be reliably moved to the planned installation position. As a result, the construction period can be shortened and the construction cost can be reduced.

上記構成において、架設用ガーダの、上記一方の横取りレール(すなわち架設用ガーダが橋軸方向に移動可能な態様で設置されている横取りレール)に対する橋軸方向の移動を、ころがり機構を用いたころがり移動により行わせるようにすれば、上記外力の作用に応じた架設用ガーダの相対移動を円滑に行わせることができ、その追従性を高めることができる。   In the above configuration, the rolling girder is moved by using a rolling mechanism to move the girder in the bridge axis direction with respect to the one side rail (that is, the girder rail installed in such a manner that the girder for construction can move in the bridge axis direction). If it is made to move, the relative movement of the girder for installation according to the action of the external force can be smoothly performed, and the followability can be improved.

その際、このころがり機構を、架設用ガーダを上記各横取りレールの長手方向に移動させるための機構に対して橋軸方向両側に位置する少なくとも2箇所に配置しておくようにすれば、次のような作用効果を得ることができる。   At that time, if this rolling mechanism is arranged in at least two places located on both sides in the bridge axis direction with respect to the mechanism for moving the girder for installation in the longitudinal direction of each of the horizontal rails, Such effects can be obtained.

すなわち、1対の橋脚が非平行である場合等には、横取りの際、架設用ガーダが橋軸直交方向に移動するのに伴って、この架設用ガーダは上記一方の横取りレールに対しては橋軸方向に移動しようとする。その際、この橋軸方向の相対移動に伴って、架設用ガーダを各横取りレールの長手方向に移動させるための機構の部分には橋軸方向の反力が生じるが、この橋軸方向の反力を、その橋軸方向両側に位置する少なくとも2箇所に配置されたころがり機構において容易に吸収することができる。そしてこれにより架設用ガーダの橋軸方向の相対移動を円滑に行わせることができる。   That is, when a pair of bridge piers are non-parallel, etc., when the girder for construction moves in the direction perpendicular to the bridge axis at the time of the horizontal take-off, Try to move in the direction of the bridge axis. At that time, along with the relative movement in the bridge axis direction, a reaction force in the bridge axis direction is generated in the portion of the mechanism for moving the erection girder in the longitudinal direction of each horizontal rail. The force can be easily absorbed by the rolling mechanisms arranged at least at two positions on both sides in the bridge axis direction. And thereby, the relative movement of the bridge girder in the bridge axis direction can be performed smoothly.

この場合において、架設用ガーダの、各横取りレールの長手方向の移動についても、ころがり機構を用いたころがり移動により行わせるようにすれば、上記外力の作用に応じた架設用ガーダの相対移動を一層円滑に行わせることができ、その追従性を一層高めることができる。   In this case, if the girder for construction is moved in the longitudinal direction of each horizontal rail by rolling movement using a rolling mechanism, the relative movement of the construction girder according to the action of the external force is further increased. This can be performed smoothly, and the follow-up performance can be further enhanced.

上記構成において、各吊上げ装置の、架設用ガーダの長手方向の移動を、すべり移動により行わせる構成としておくようにすれば、これをころがり移動により行わせるようにした場合に比して、横取りの際、各吊上げ装置が必要以上に移動して、架設対象プレキャスト桁が両橋脚と不用意に干渉してしまうのを未然に防止することができる。なお、横取りの際における、各吊上げ装置の、架設用ガーダの長手方向の移動量はさほど大きくはならないので、すべり移動を採用しても架設作業の効率を実質的に低下させてしまうことはない。   In the above configuration, if the lifting device is configured to move in the longitudinal direction of the girder for installation by sliding movement, it is possible to obtain a side effect as compared with the case of performing this by rolling movement. At this time, it is possible to prevent in advance that each lifting device moves more than necessary and the erection target precast girder inadvertently interferes with both piers. In addition, since the amount of movement of the elevating girder in the longitudinal direction of each lifting device at the time of horizontal capture does not increase so much, even if sliding movement is adopted, the efficiency of the erection work is not substantially reduced. .

本願発明の一実施形態に係る橋梁架設方法の概要を示す平面図The top view which shows the outline | summary of the bridge construction method which concerns on one Embodiment of this invention 図1のII−II線矢視図II-II arrow view of FIG. 図1のIII 部詳細図Detailed view of part III in Fig. 1 図2のIV−IV線断面図IV-IV sectional view of FIG. 図2のV部詳細図Detailed view of part V in FIG. 図2のVI部詳細図Detailed view of VI section in Fig. 2 図4のVII 部詳細図Detail view of part VII in Fig. 4

以下、図面を用いて、本願発明の実施の形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

図1は、本願発明の一実施形態に係る橋梁架設方法の概要を示す平面図である。また、図2は、図1のII−II線矢視図である。   FIG. 1 is a plan view showing an outline of a bridge erection method according to an embodiment of the present invention. 2 is a view taken along the line II-II in FIG.

図1に示すように、本実施形態に係る橋梁架設方法の適用対象は、多径間連続橋における架設径間S0の部分であって、この架設径間S0の橋軸方向両側に位置する1対の橋脚12A、12B相互間に、複数のプレキャスト桁14が橋軸直交方向に所定間隔をおいて架設されるようになっている。なお、図1においては、各プレキャスト桁14について、その架設予定位置の中心軸のみを1点鎖線で示している。   As shown in FIG. 1, the application target of the bridge erection method according to the present embodiment is a portion of the span span S0 in the multi-span continuous bridge, and is located on both sides in the bridge axis direction of the span span S0. A plurality of precast girders 14 are installed between the pair of bridge piers 12A and 12B at a predetermined interval in the direction perpendicular to the bridge axis. In FIG. 1, for each precast girder 14, only the central axis of the planned installation position is indicated by a one-dot chain line.

図2に示すように、各橋脚12A、12Bの上端部には、L字形の桁受け部12Aa、12Baがそれぞれ形成されており、一方、各プレキャスト桁14の長手方向両端部には、逆L字形の凹部14aが形成されている。そして、これら各プレキャスト桁14は、その各凹部14aにおいて各橋脚12A、12Bの桁受け部12Aa、12Baに載置されるようになっている。なお、図2において架設径間S0の左側に位置する橋脚12Aの桁受け部12Aaは、架設径間S0の右側に位置する橋脚12Bの桁受け部12Baに対してやや下方に位置している。これに伴い、各プレキャスト桁14は、水平方向に対して図2においてやや左下がりに傾斜した状態で架設されるようになっている。   As shown in FIG. 2, L-shaped girder receiving portions 12Aa and 12Ba are formed at the upper ends of the piers 12A and 12B, respectively. A letter-shaped recess 14a is formed. The precast girders 14 are placed on the girder receiving portions 12Aa and 12Ba of the piers 12A and 12B in the concave portions 14a. In FIG. 2, the girder receiving portion 12Aa of the pier 12A located on the left side of the span span S0 is located slightly below the girder portion 12Ba of the pier 12B located on the right side of the span span S0. Accordingly, each precast girder 14 is constructed so as to be inclined slightly downwardly downward in FIG. 2 with respect to the horizontal direction.

図1に示すように、架設径間S0の橋軸方向両側に隣接する架設径間S−1、S+1においては、複数のプレキャスト桁14が互いに平行に架設されるようになっているのに対し、架設径間S0においては、複数のプレキャスト桁14が互いに非平行に架設されるようになっている。また、この架設径間S0においては、その橋軸方向両側に位置する1対の橋脚12A、12Bが非平行に配置されている。   As shown in FIG. 1, in the span spans S-1 and S + 1 adjacent to both sides of the span span S0 in the bridge axis direction, a plurality of precast girders 14 are spanned in parallel to each other. In the span S0, a plurality of precast girders 14 are constructed non-parallel to each other. Further, in this spanning span S0, a pair of bridge piers 12A and 12B located on both sides in the bridge axis direction are arranged non-parallel.

具体的には、この架設径間S0においては、複数のプレキャスト桁14は、図1において架設径間S0の右側に位置する橋脚12Bからその左側に位置する橋脚12Aへ向けて、プレキャスト桁14相互間の間隔が多少拡がるようにした状態で架設されるようになっている。また、1対の橋脚12A、12Bは、図1において手前側から奥側へ向けて、その径間距離が多少狭まるように配置されている。これに伴って、この架設径間S0に架設される複数のプレキャスト桁14は、図1において手前側から奥側へ向けて、その橋軸方向の長さが徐々に短くなるように設定されている。なお、これら各プレキャスト桁14は、断面略U字形の軽量構造を有している(図4参照)。   Specifically, in the span span S0, the plurality of precast girders 14 are connected to each other from the pier 12B located on the right side of the span span S0 in FIG. 1 toward the pier 12A located on the left side. It is constructed in such a way that the interval between them is somewhat widened. Further, the pair of bridge piers 12A and 12B are arranged such that the distance between the spans thereof is somewhat narrowed from the near side to the far side in FIG. Accordingly, the plurality of precast girders 14 installed in the installation span S0 are set so that the length in the bridge axis direction gradually decreases from the front side to the back side in FIG. Yes. Each of these precast girders 14 has a lightweight structure with a substantially U-shaped cross section (see FIG. 4).

本実施形態に係る橋梁架設方法の概要について説明すると以下のとおりである。   The outline of the bridge erection method according to this embodiment will be described as follows.

まず、架設径間S0の側方(図1において架設径間S0の手前側)に位置する搬入ヤードYに、この架設径間S0に架設すべき複数のプレキャスト桁14のうちの1つをトレーラ等により搬入する。   First, one of a plurality of precast girders 14 to be installed in the installation span S0 is trailered in the carry-in yard Y located on the side of the installation span S0 (the front side of the installation span S0 in FIG. 1). Carry in by etc.

次に、この搬入ヤードYにおいて、搬入されたプレキャスト桁14を架設対象プレキャスト桁14oとして、その架設高さよりも上方位置まで吊り上げる。   Next, in the carry-in yard Y, the carried precast girder 14 is lifted as a construction target precast girder 14o to a position above the construction height.

次に、この架設対象プレキャスト桁14oを、架設予定位置まで橋軸直交方向に移動させ、この架設予定位置において1対の橋脚12A、12B上に吊り下ろす。   Next, the erection target precast girder 14o is moved in a direction perpendicular to the bridge axis to the erection planned position, and is suspended on the pair of piers 12A and 12B at the erection planned position.

以下、これを繰り返すことにより複数のプレキャスト桁14の架設を行う。   Hereinafter, by repeating this, a plurality of precast girders 14 are installed.

その後、これら各プレキャスト桁14と1対の橋脚12A、12Bの上端部との間に橋軸方向のプレストレスを導入する。   Thereafter, prestress in the direction of the bridge axis is introduced between each of these precast girders 14 and the upper ends of the pair of bridge piers 12A and 12B.

次に、本実施形態に係る橋梁架設方法における、架設対象プレキャスト桁14oの吊上げおよび横取りの工程について具体的に説明する。   Next, the steps of lifting and pretending the installation target precast girder 14o in the bridge erection method according to the present embodiment will be specifically described.

まず、1対の橋脚12A、12Bの各々の上面に、略橋軸直交方向に延びる横取りレール102A、102Bを、該横取りレール102A、102Bの一端部102Aa、102Baが搬入ヤードYまで張り出す態様で設置する。   First, on the upper surface of each of the pair of bridge piers 12A and 12B, horizontal rails 102A and 102B extending in a direction substantially orthogonal to the bridge axis are arranged such that one end portions 102Aa and 102Ba of the horizontal rails 102A and 102B extend to the carry-in yard Y. Install.

その際、これら各横取りレール102A、102Bは、その一端部102Aa、102Ba寄りの部分がそれ以外の部分よりも高い剛性を有する構造としておき、搬入ヤードYでの架設対象プレキャスト桁14oの吊上げに十分耐えられるようにしておく。なお、これら各横取りレール102A、102Bは、その他端部102Ab、102Bbが各橋脚12A、12Bから架設径間S0の搬入ヤードY側とは反対側の側方まで張り出す長さを有していれば、同一構造のものを用いることが可能である。   At this time, each of the horizontal rails 102A and 102B has a structure in which a portion near one end portion 102Aa and 102Ba has higher rigidity than the other portions, and is sufficient for lifting the precast girder 14o to be installed in the loading yard Y. Be ready to withstand. Each of the horizontal rails 102A and 102B has such a length that the other end portions 102Ab and 102Bb protrude from the bridge piers 12A and 12B to the side opposite to the loading yard Y side of the span span S0. In this case, the same structure can be used.

次に、橋軸方向に延びる架設用ガーダ104を、図示しない小型クレーン等により、架設径間S0を跨ぐ位置に吊り上げて、1対の横取りレール102A、102Bの上に設置する。   Next, the erection girder 104 extending in the bridge axis direction is lifted to a position straddling the erection span S0 by a small crane (not shown) and installed on the pair of horizontal rails 102A and 102B.

この架設用ガーダ104の設置は、両横取りレール102A、102Bの一端部102Aa、102Baの位置(すなわち搬入ヤードYの上方位置)において行う。また、この架設用ガーダ104の設置は、両横取りレール102A、102Bに対して、それぞれ横移動装置110A、110Bを介して行う。これにより、架設用ガーダ104を、各横取りレール102A、102Bに対して該横取りレール102A、102Bの長手方向に移動可能としておく。   The installation girder 104 is installed at the positions of the one end portions 102Aa and 102Ba (that is, the upper position of the carry-in yard Y) of the both side rails 102A and 102B. In addition, the installation girder 104 is installed on the both side rails 102A and 102B via the lateral movement devices 110A and 110B, respectively. Thereby, the erection girder 104 can be moved in the longitudinal direction of the horizontal rails 102A and 102B with respect to the horizontal rails 102A and 102B.

その際、これら1対の横移動装置110A、110Bは、橋脚12A側の横移動装置110Aを橋脚12B側の横移動装置110Bよりも背の高い構成としておく。これにより、1対の橋脚12A、12Bの上端面相互間に高低差があるにもかかわらず架設用ガーダ104を水平に設置可能とする。また、この架設用ガーダ104としては、平行に配置された左右1対のI型鋼が複数の鋼材で連結されてなる軽量の架設用ガーダを用いる。なお、架設対象プレキャスト桁14oは断面略U字形の軽量構造を有しているので、軽量の架設用ガーダ104でも十分に対応可能である。この架設用ガーダ104の吊上げは、その長手方向両端近傍部位の上面に取り付けられた1対のガーダ吊上げ金具104aにおいて行う。   At that time, the pair of lateral movement devices 110A and 110B is configured such that the lateral movement device 110A on the pier 12A side is taller than the lateral movement device 110B on the pier 12B side. Accordingly, the erection girder 104 can be installed horizontally regardless of the height difference between the upper end surfaces of the pair of piers 12A and 12B. Further, as this erection girder 104, a lightweight erection girder in which a pair of left and right I-shaped steels arranged in parallel is connected by a plurality of steel materials is used. Since the precast girder 14o to be installed has a light-weight structure with a substantially U-shaped cross section, even a lightweight installation girder 104 can be sufficiently accommodated. The erection girder 104 is lifted by a pair of girder lifting brackets 104a attached to the upper surface of the vicinity of both ends in the longitudinal direction.

次に、架設用ガーダ104の上面に設置された1対の吊上げ装置106により、搬入ヤードYに搬入された架設対象プレキャスト桁14oを、その架設高さよりも上方位置まで吊り上げる。   Next, the pair of lifting devices 106 installed on the upper surface of the erection girder 104 lifts the erection target precast girder 14o carried into the carry-in yard Y to a position above the erection height.

その際、1対の吊上げ装置106は、1対のガーダ吊上げ金具104aよりもやや長手方向中心寄りの位置に設置しておく。また、架設対象プレキャスト桁14oには、その長手方向両端近傍部位に1対の桁吊り金具108を取り付けておき、これら1対の桁吊り金具108を介して架設対象プレキャスト桁14oを吊り上げる。   At that time, the pair of lifting devices 106 are installed at positions slightly closer to the center in the longitudinal direction than the pair of girder lifting brackets 104a. In addition, a pair of girder hanging brackets 108 are attached to the construction target precast girder 14o in the vicinity of both ends in the longitudinal direction, and the construction target precast girder 14o is lifted through the pair of girder hanging brackets 108.

次に、架設用ガーダ104を、架設対象プレキャスト桁14oの架設予定位置まで略橋軸直交方向に移動させる。そして、この架設予定位置において、1対の吊上げ装置106により、架設対象プレキャスト桁14oを、その1対の凹部14aを各橋脚12A、12Bの桁受け部12Aa、12Baに載置させるようにして、1対の橋脚12A、12B上に吊り下ろす。   Next, the erection girder 104 is moved in a direction substantially perpendicular to the bridge axis to the erection planned position of the erection target precast girder 14o. Then, at this planned installation position, the pair of lifting devices 106 are used to place the installation target precast girder 14o and the pair of recesses 14a on the girder receiving portions 12Aa and 12Ba of the respective piers 12A and 12B. Suspend on a pair of bridge piers 12A, 12B.

本実施形態に係る橋梁架設方法においては、架設用ガーダ104の長手方向両端部に配置された1対の横移動装置110A、110Bを用いることにより、架設用ガーダ104を、1対の横取りレール102A、102Bの各々に対して、該横取りレール102A、102Bの長手方向に移動可能な態様で設置するだけでなく、鉛直軸線Ax回りに回動可能な態様で設置しておく。また、一方の橋脚12Aに設置された横取りレール102Aに対しては、この横取りレール102Aに配置された横移動装置110Aを利用して、架設用ガーダ104を橋軸方向に移動可能な態様で設置しておく。   In the bridge erection method according to the present embodiment, by using a pair of lateral movement devices 110A and 110B disposed at both longitudinal ends of the erection girder 104, the erection girder 104 is paired with a pair of lateral rails 102A. , 102B are installed not only in such a manner that they can move in the longitudinal direction of the horizontal rails 102A, 102B but also in a manner in which they can be rotated around the vertical axis Ax. Also, for the horizontal rail 102A installed on one bridge pier 12A, the girder 104 for installation is installed in such a manner that it can be moved in the direction of the bridge axis by using the horizontal movement device 110A arranged on the horizontal rail 102A. Keep it.

架設径間S0においては、複数のプレキャスト桁14が互いに非平行に架設されるようになっており、かつ、1対の橋脚12A、12Bが非平行に配置されていることに起因して、横取りの際、架設用ガーダ104に対して、その両横取りレール102A、102B間の距離変化させようとする外力や、架設用ガーダ104を橋軸方向に延びる状態から旋回させようとする外力が作用するが、これらに対して各横移動装置110A、110Bを追従させ、これにより架設用ガーダ104を架設対象プレキャスト桁14oの架設予定位置まで円滑に移動させるようにする。   In the span span S0, a plurality of precast girders 14 are constructed in a non-parallel manner, and the pair of bridge piers 12A and 12B are arranged in a non-parallel manner. At this time, an external force that tries to change the distance between the two horizontal rails 102A and 102B and an external force that tries to turn the erection girder 104 from a state extending in the bridge axis direction act on the erection girder 104. However, the lateral movement devices 110A and 110B are caused to follow these, so that the erection girder 104 can be smoothly moved to the erected planned position of the erection target precast girder 14o.

また、本実施形態に係る橋梁架設方法においては、1対の吊上げ装置106の各々を、架設用ガーダ104に対して該架設用ガーダ104の長手方向に移動可能な態様で設置しておく。これにより、横取りの際、これら各吊上げ装置106を適宜移動させ、架設対象プレキャスト桁14oを、架設径間S0において両橋脚12A、12Bと干渉するおそれのない適正な位置に吊下げ支持された状態に維持しておく。   Further, in the bridge erection method according to the present embodiment, each of the pair of lifting devices 106 is installed with respect to the erection girder 104 so as to be movable in the longitudinal direction of the erection girder 104. Thereby, at the time of the horizontal capture, each of the lifting devices 106 is appropriately moved, and the erection target precast girder 14o is suspended and supported at an appropriate position without interfering with the both piers 12A and 12B in the erection span S0. Keep it on.

次に、本実施形態に係る橋梁架設方法に用いられる横移動装置110A、110Bおよび吊上げ装置106の構成について説明する。   Next, the configuration of the lateral movement devices 110A and 110B and the lifting device 106 used in the bridge construction method according to the present embodiment will be described.

図3は、図1のIII 部詳細図である。また、図4は、図2のIV−IV線断面図であり、図5は、図2のV部詳細図であり、図6は、図2のVI部詳細図である。さらに、図7は、図4のVII 部詳細図である。   FIG. 3 is a detailed view of part III in FIG. 4 is a cross-sectional view taken along line IV-IV in FIG. 2, FIG. 5 is a detailed view of a portion V in FIG. 2, and FIG. 6 is a detailed view of a portion VI in FIG. FIG. 7 is a detailed view of a portion VII in FIG.

まず、橋脚12A側に配置された横移動装置110Aの構成について説明する。   First, the configuration of the lateral movement device 110A disposed on the pier 12A side will be described.

図3〜5および7に示すように、この横移動装置110Aは、架設用ガーダ104を、横取りレール102Aの長手方向に移動させるための動力原としてのセンタホールジャッキ112と、この移動をころがり移動により行わせるためのころがり機構114と、架設用ガーダ104を、横取りレール102Aに対して橋軸方向(正確には架設用ガーダ104の長手方向)に、ころがり移動により移動させるためのころがり機構116と、架設用ガーダ104を、横取りレール102Aに対して鉛直軸線Ax回りに回動させるための回動機構118とを備えた構成となっている。   As shown in FIGS. 3 to 5 and 7, this lateral movement device 110A includes a center hole jack 112 as a power source for moving the erection girder 104 in the longitudinal direction of the horizontal rail 102A, and this movement by rolling. A rolling mechanism 114 for moving the rolling girder 104, and a rolling mechanism 116 for moving the erection girder 104 in the bridge axis direction (more precisely, the longitudinal direction of the girder 104 for erection) by rolling movement. The construction girder 104 is provided with a rotation mechanism 118 for rotating the girder 104 about the vertical rail line AA about the vertical axis Ax.

この横移動装置110Aにおいて、回動機構118よりも下方側に位置する部分を下部構造部110ALとし、回動機構118よりも上方側に位置する部分を上部構造部110AUとしたとき、センタホールジャッキ112およびころがり機構114は下部構造部110ALの構成要素となっており、ころがり機構116は上部構造部110AUの構成要素となっている。   In this lateral movement device 110A, when a portion located below the rotation mechanism 118 is a lower structure portion 110AL and a portion located above the rotation mechanism 118 is an upper structure portion 110AU, a center hole jack is used. 112 and the rolling mechanism 114 are constituent elements of the lower structure portion 110AL, and the rolling mechanism 116 is a constituent element of the upper structure portion 110AU.

センタホールジャッキ112は、横取りレール102Aの上方近傍において横取りレール102Aの長手方向に延びる横取り鋼棒120に装着されている。そして、このセンタホールジャッキ112を駆動することにより、架設用ガーダ104を横移動装置110Aと共に横取りレール102Aの長手方向に所定長ずつ移動させるようになっている。   The center hole jack 112 is mounted on a horizontal steel rod 120 extending in the longitudinal direction of the horizontal rail 102A in the vicinity of the upper side of the horizontal rail 102A. By driving the center hole jack 112, the erection girder 104 is moved along with the lateral movement device 110A by a predetermined length in the longitudinal direction of the horizontal rail 102A.

ころがり機構114は、横取りレール102Aのレール部102Acに、その長手方向に所定間隔をおいて直列に配置された2つの無限軌道ローラで構成されている。そして、図5〜7に示すように、下部構造部110ALには、これら2つのころがり機構114の各々を構成する無限軌道ローラをガイドするための2組のガイド部材124が、横取りレール102Aの長手方向に所定間隔をおいて、そのレール部102Acを挟持するようにして配置されている。   The rolling mechanism 114 is composed of two endless track rollers arranged in series at a predetermined interval in the longitudinal direction of the rail portion 102Ac of the horizontal rail 102A. As shown in FIGS. 5 to 7, two sets of guide members 124 for guiding the endless track rollers constituting each of the two rolling mechanisms 114 are provided in the lower structure portion 110AL. The rail portions 102Ac are arranged so as to be sandwiched at predetermined intervals in the direction.

ころがり機構116は、2つのころがり機構114の各々に対して、その略真上でかつその橋軸方向両側に位置する2箇所に1対ずつ配置された計4つの無限軌道ローラで構成されている。そして、図5〜7に示すように、上部構造部110AUには、これら4つのころがり機構116の各々を構成する無限軌道ローラをガイドするための4組のガイド部材126が、橋軸方向に所定間隔をおいて、架設用ガーダ104を構成する1対のI型鋼の各々を挟持するようにして配置されている。   The rolling mechanism 116 is composed of a total of four endless track rollers that are arranged in pairs at two locations that are located directly above each of the two rolling mechanisms 114 and on both sides in the bridge axis direction. . As shown in FIGS. 5 to 7, the upper structure portion 110AU is provided with four sets of guide members 126 for guiding the endless track rollers constituting each of the four rolling mechanisms 116 in the bridge axis direction. It arrange | positions so that each of a pair of I-shaped steel which comprises the installation girder 104 may be pinched | interposed at intervals.

回動機構118は、下部構造部110ALと上部構造部110AUとの間に、鉛直軸線Axに沿って上下方向に延びる鉛直軸部材が配置されるとともにこの鉛直軸部材を囲む複数の環状プレートが積層配置されることによって構成されている。その際、複数の環状プレートとしては、ステンレス鋼鈑およびテフロン(登録商標)板が用いられている。   In the rotation mechanism 118, a vertical shaft member extending in the vertical direction along the vertical axis Ax is disposed between the lower structure portion 110AL and the upper structure portion 110AU, and a plurality of annular plates surrounding the vertical shaft member are stacked. It is constituted by being arranged. At that time, stainless steel plates and Teflon (registered trademark) plates are used as the plurality of annular plates.

上部構造部110AUには、この回動機構118ところがり機構116との間に、ころがり機構114の高さ位置を調整するためのスペーサ122が配置されている。なお、このようなスペーサ122が配置されるのは、橋脚12Aの上端面が橋脚12Bの上端面に対してやや下方に位置している状態において、架設用ガーダ104を水平方向に延びるように設置するためである。   A spacer 122 for adjusting the height position of the rolling mechanism 114 is disposed between the rotating mechanism 118 and the rolling mechanism 116 in the upper structure portion 110AU. Such a spacer 122 is disposed so that the construction girder 104 extends in the horizontal direction when the upper end surface of the pier 12A is located slightly below the upper end surface of the pier 12B. It is to do.

次に、橋脚12B側に配置された横移動装置110Bの構成について説明する。   Next, the configuration of the lateral movement device 110B disposed on the pier 12B side will be described.

図6に示すように、この横移動装置110Bは、その回動機構118および下部構造部110BLについては、横移動装置110Aの場合と同様の構成と有しているが、その上部構造部110BUについては、横移動装置110Aの場合とは異なる構成を有している。   As shown in FIG. 6, the lateral movement device 110B has the same configuration as the lateral movement device 110A with respect to the rotation mechanism 118 and the lower structure portion 110BL, but the upper structure portion 110BU. Has a configuration different from that of the lateral movement device 110A.

すなわち、この横移動装置110Bの上部構造部110BUは、回動機構118の上部において架設用ガーダ104を直接支持する構成となっており、横移動装置110Aの上部構造部110AUのようなころがり機構116およびスペーサ122は存在しない。ころがり機構116が存在しないのは、架設用ガーダ104を横取りレール102Bに対して橋軸方向に移動させる必要がないためである。また、スペーサ122が存在しないのは、橋脚12Aの上端面と橋脚12Bの上端面との高低差に対する調整が、橋脚12Aに配置された横移動装置110Aにスペーサ122が配置されることにより行われているためである。   That is, the upper structure portion 110BU of the lateral movement device 110B is configured to directly support the erection girder 104 at the upper portion of the rotation mechanism 118, and the rolling mechanism 116 like the upper structure portion 110AU of the lateral movement device 110A. And the spacer 122 does not exist. The reason why the rolling mechanism 116 does not exist is that it is not necessary to move the erection girder 104 in the direction of the bridge axis with respect to the horizontal rail 102B. The spacer 122 does not exist because the height difference between the upper end surface of the pier 12A and the upper end surface of the pier 12B is adjusted by the spacer 122 being disposed on the lateral movement device 110A disposed on the pier 12A. This is because.

ただし、この横移動装置110Bの上部構造部110AUには、架設用ガーダ104を直接支持する際に、横移動装置110Aの上部構造部110AUの場合と同様の4組のガイド部材128が用いられている。その際、これら4組のガイド部材128の橋軸方向の相互間の間隔は、横移動装置110Aにおける4組のガイド部材126の場合よりも狭くなっている。   However, the upper structure portion 110AU of the lateral movement device 110B uses four sets of guide members 128 similar to the case of the upper structure portion 110AU of the lateral movement device 110A when directly supporting the erection girder 104. Yes. At that time, the distance between the four sets of guide members 128 in the bridge axis direction is narrower than that of the four sets of guide members 126 in the lateral movement device 110A.

次に、吊上げ装置106の構成について説明する。   Next, the configuration of the lifting device 106 will be described.

図3〜7に示すように、この吊上げ装置106は、ウインチで構成されており、架設用ガーダ104を構成する左右1対のI型鋼の間において架設対象プレキャスト桁14oを吊り支持するようになっている。   As shown in FIGS. 3 to 7, the lifting device 106 is formed of a winch, and suspends and supports the precast girder 14 o to be installed between a pair of left and right I-shaped steels constituting the installation girder 104. ing.

この吊上げ装置106は、架設用ガーダ104を構成する左右1対のI型鋼の上面に固定された左右1対の支持鋼材130に跨るようにして設置されている。その際、この吊上げ装置106の下端面における、左右1対の支持鋼材130に当接する4箇所の位置には、それぞれテフロン板132が取り付けられている。これら4つのテフロン板132は、左右1対の支持鋼材130の各々における長手方向に所定間隔をおいた位置に配置されている。これにより、この吊上げ装置106は、架設用ガーダ104に対してその長手方向に移動可能な態様で、左右1対の支持鋼材130に対する設置が行われている。   The lifting device 106 is installed so as to straddle a pair of left and right support steel members 130 fixed to the upper surfaces of a pair of left and right I-shaped steels constituting the erection girder 104. At that time, Teflon plates 132 are respectively attached to four positions on the lower end surface of the lifting device 106 that contact the pair of left and right support steel members 130. These four Teflon plates 132 are arranged at predetermined intervals in the longitudinal direction of each of the pair of left and right support steel members 130. Accordingly, the lifting device 106 is installed on the pair of left and right support steel members 130 in such a manner that the lifting device 106 can move in the longitudinal direction with respect to the erection girder 104.

次に、本実施形態の作用について説明する。   Next, the operation of this embodiment will be described.

本実施形態に係る橋梁架設方法においては、架設径間S0の橋軸方向両側に位置する1対の橋脚12A、12B相互間に、複数のプレキャスト桁14を橋軸直交方向に所定間隔をおいて架設する際、1対の橋脚12A、12Bの各々の上面に、略橋軸直交方向に延びる横取りレール102A、102Bを、その一端部102Aa、102Baが架設径間S0の側方に位置する搬入ヤードYまで張り出す態様で設置するとともに、橋軸方向に延びる架設用ガーダ104を、架設径間S0を跨ぐ位置において、1対の横取りレール102A、102Bの各々に対して該横取りレール102A、102Bの長手方向に移動可能な態様で設置した状態で、搬入ヤードYにおいて、架設用ガーダ104に設置された1対の吊上げ装置106により、複数のプレキャスト桁14のうちの1つを架設対象プレキャスト桁14oとして吊り上げて、架設用ガーダ104を架設対象プレキャスト桁14oの架設予定位置まで橋軸直交方向に移動させた後、1対の吊上げ装置106により架設対象プレキャスト桁14oを1対の橋脚12A、12B上に吊り下ろし、以下これを繰り返すことにより複数のプレキャスト桁14の架設を行うようになっているので、次のような作用効果を得ることができる。   In the bridge erection method according to the present embodiment, a plurality of precast girders 14 are arranged at predetermined intervals in the direction perpendicular to the bridge axis between a pair of bridge piers 12A and 12B located on both sides in the bridge axis direction of the span S0. When erected, on the upper surface of each of the pair of bridge piers 12A, 12B, take-in rails 102A, 102B extending in a direction substantially orthogonal to the bridge axis, a carrying-in yard in which one end portions 102Aa, 102Ba are located on the side of the erected span S0. The installation girder 104 extending in the direction of the bridge axis is installed in a manner that extends to Y, and the crossing rails 102A and 102B are arranged with respect to each of the pair of horizontal installation rails 102A and 102B at a position straddling the installation span S0. A plurality of lifting devices 106 installed in the erection girder 104 are installed in the carry-in yard Y in a state of being installed in a manner movable in the longitudinal direction. One of the precast girders 14 is lifted as an erection target precast girder 14o, and the erection girder 104 is moved in the direction perpendicular to the bridge axis to the erection target position of the erection target precast girder 14o. Since the precast girder 14o to be erected is suspended on a pair of bridge piers 12A and 12B and this is repeated thereafter, a plurality of precast girders 14 are constructed, so that the following effects can be obtained. it can.

すなわち、架設用ガーダ104を用いてプレキャスト桁14の横取りを行うようになっているので、架設作業を効率良く行うことができる。しかもその際、軽量の架設用ガーダ104を用いることができるので、工期短縮および工費低減を図ることができる。さらに、架設径間S0の側方に搬入ヤードYを確保することができれば、架設径間S0の地盤が軟弱であったり平坦でない場合等においても、架設対象プレキャスト桁14oの架設作業を容易に行うことができる。   That is, since the precast girder 14 is intercepted using the erection girder 104, the erection operation can be performed efficiently. Moreover, since the lightweight construction girder 104 can be used at that time, the construction period can be shortened and the construction cost can be reduced. Furthermore, if the carry-in yard Y can be secured to the side of the span span S0, the construction work of the precast girder 14o to be constructed is easily performed even when the ground of the span span S0 is soft or not flat. be able to.

その上で、本実施形態に係る橋梁架設方法においては、架設用ガーダ104を、1対の横取りレール102A、102Bの各々に対して鉛直軸線Ax回りに回動可能な態様で、かつ、1対の横取りレール102A、102Bのうちの一方(すなわち横取りレール102A)に対して橋軸方向に移動可能な態様で設置しておくようになっているので、1対の橋脚12A、12Bが非平行に配置されているとともに、複数のプレキャスト桁14が互いに非平行に架設されるようになっていることに起因して、横取りの際、架設用ガーダ104に対して、その両横取りレール102A、102B間の距離を変化させようとする外力や、架設用ガーダ104を橋軸方向に延びる状態から旋回させようとする外力が作用したとき、これらに追従させて架設用ガーダ104を相対移動させることができる。そしてこれにより、架設用ガーダ104を架設対象プレキャスト桁14oの架設予定位置まで円滑に移動させることができる。   In addition, in the bridge erection method according to the present embodiment, the erection girder 104 can be rotated around the vertical axis Ax with respect to each of the pair of horizontal rails 102A and 102B, and The pair of bridge piers 12A and 12B are non-parallel because they are installed in such a manner as to be movable in the bridge axis direction with respect to one of the horizontal rails 102A and 102B (that is, the horizontal rail 102A). In addition, the precast girder 14 is installed non-parallel to each other, and therefore, between the horizontal rails 102A and 102B with respect to the girder 104 for horizontal installation. When an external force that attempts to change the distance between the two or an external force that tries to turn the erection girder 104 from a state extending in the direction of the bridge axis acts, The use girder 104 can be moved relative. Thus, the erection girder 104 can be smoothly moved to the expected erection position of the erection target precast girder 14o.

しかも、本実施形態に係る橋梁架設方法においては、1対の吊上げ装置106の各々を、架設用ガーダ104に対してその長手方向に移動可能な態様で設置しておくようになっているので、横取りの際、架設用ガーダ104の両横取りレール102A、102B間の距離が変化するようなことがあっても、架設対象プレキャスト桁14oを、架設径間S0において両橋脚12A、12Bと干渉するおそれのない適正な位置に吊下げ支持された状態に維持しておくことが容易に可能となる。そしてこれにより、架設対象プレキャスト桁14oを架設予定位置まで確実に移動させることができる。   Moreover, in the bridge erection method according to the present embodiment, each of the pair of lifting devices 106 is installed in a manner movable in the longitudinal direction with respect to the erection girder 104, Even if the distance between the two horizontal rails 102A and 102B of the girder 104 for installation changes during the horizontal installation, the installation target precast girder 14o may interfere with the two piers 12A and 12B in the installation span S0. It can be easily maintained in a state where it is suspended and supported at an appropriate position without any gap. As a result, the installation target precast girder 14o can be reliably moved to the planned installation position.

このように本実施形態によれば、架設径間S0の橋軸方向両側に位置する1対の橋脚12A、12B相互間に、複数のプレキャスト桁14を橋軸直交方向に所定間隔をおいて架設する橋梁架設方法において、1対の橋脚12A、12Bが非平行である場合等においても、各プレキャスト桁14を架設予定位置まで確実に移動させることができる。そしてこれにより工期短縮および工費低減を図ることができる。   Thus, according to the present embodiment, a plurality of precast girders 14 are installed at predetermined intervals in the direction perpendicular to the bridge axis between the pair of bridge legs 12A and 12B located on both sides in the bridge axis direction of the installation span S0. In the bridge construction method, the precast girders 14 can be reliably moved to the planned construction position even when the pair of piers 12A and 12B are non-parallel. As a result, the construction period can be shortened and the construction cost can be reduced.

その際、本実施形態においては、架設用ガーダ104の、一方の横取りレール102A(すなわち架設用ガーダ104が橋軸方向に移動可能な態様で設置されている横取りレール102A)に対する橋軸方向の移動を、ころがり機構116を用いたころがり移動により行わせるようになっているので、上記外力の作用に応じた架設用ガーダ104の相対移動を円滑に行わせることができ、その追従性を高めることができる。   At this time, in this embodiment, the bridge girder 104 moves in the bridge axis direction with respect to one of the horizontal rails 102A (that is, the horizontal rail 102A in which the girder 104 for installation is installed in such a manner that it can move in the bridge axis direction). Can be performed by rolling movement using the rolling mechanism 116, so that the erection girder 104 can be smoothly moved relative to the action of the external force, and the followability can be improved. it can.

しかもその際、ころがり機構116を、架設用ガーダ104を各横取りレール102A、102Bの長手方向に移動させるためのころがり機構114に対して橋軸方向両側に位置する2箇所に配置しておくようになっているので、次のような作用効果を得ることができる。   In addition, at that time, the rolling mechanisms 116 are arranged at two positions located on both sides in the bridge axis direction with respect to the rolling mechanism 114 for moving the erection girder 104 in the longitudinal direction of the horizontal rails 102A and 102B. Therefore, the following effects can be obtained.

すなわち、1対の橋脚12A、12Bが非平行である場合等には、横取りの際、架設用ガーダ104が橋軸直交方向に移動するのに伴って、この架設用ガーダ104は横取りレール102Aに対しては橋軸方向に移動しようとする。その際、この橋軸方向の相対移動に伴って、ころがり機構114の部分には橋軸方向の反力が生じるが、この橋軸方向の反力を、その橋軸方向両側に位置する2箇所に配置されたころがり機構116において容易に吸収することができる。そしてこれにより架設用ガーダ104の橋軸方向の相対移動を円滑に行わせることができる。 特に本実施形態においては、横移動装置110Aの上部構造部110AUに高さ調整用のスペーサ122が配置されており、このためころがり機構116はころがり機構114に対してかなり上方に離れた位置にあるので、ころがり機構116を、ころがり機構114に対して橋軸方向両側に位置する2箇所に配置しておくようにすることが極めて効果的である。その際、架設用ガーダ104の橋軸方向の相対移動を十分円滑に行わせるためには、図5において、橋軸方向の2箇所に配置されたころがり機構116の各々の中心と、ころがり機構114の中心とを結ぶ2つの直線の交角θを、θ=30°以上の値に設定しておくことが好ましく、θ=40°以上の値に設定しておくことがより好ましい。   In other words, when the pair of bridge piers 12A and 12B are non-parallel, etc., when the girder 104 for installation moves in the direction orthogonal to the bridge axis at the time of the horizontal take-off, On the other hand, it tries to move in the direction of the bridge axis. At that time, with the relative movement in the bridge axis direction, a reaction force in the bridge axis direction is generated in the portion of the rolling mechanism 114, and this reaction force in the bridge axis direction is generated at two locations on both sides of the bridge axis direction. It can be easily absorbed by the rolling mechanism 116 arranged in the above. As a result, the relative movement of the erection girder 104 in the bridge axis direction can be performed smoothly. In particular, in the present embodiment, the height adjusting spacer 122 is disposed in the upper structure portion 110AU of the lateral movement device 110A, and thus the rolling mechanism 116 is located at a position far above the rolling mechanism 114. Therefore, it is extremely effective to dispose the rolling mechanism 116 at two positions located on both sides in the bridge axis direction with respect to the rolling mechanism 114. At this time, in order to perform the relative movement of the erection girder 104 in the bridge axis direction sufficiently smoothly, the centers of the rolling mechanisms 116 arranged at two positions in the bridge axis direction and the rolling mechanism 114 in FIG. It is preferable to set the intersection angle θ of two straight lines connecting to the center of θ to a value of θ = 30 ° or more, and more preferably to a value of θ = 40 ° or more.

本実施形態においては、架設用ガーダ104の、各横取りレール102A、102Bの長手方向の移動についても、ころがり機構116を用いたころがり移動により行わせるようになっているので、上記外力の作用に応じた架設用ガーダ104の相対移動を一層円滑に行わせることができ、その追従性を一層高めることができる。   In the present embodiment, the longitudinal movement of the horizontal rails 102A and 102B of the girder 104 for installation is also performed by rolling movement using the rolling mechanism 116, so that it depends on the action of the external force. Further, the relative movement of the erection girder 104 can be performed more smoothly, and the followability can be further enhanced.

また本実施形態においては、各吊上げ装置106の、架設用ガーダ104の長手方向の移動を、すべり移動により行わせる構成となっているので、これをころがり移動により行わせるようにした場合に比して、横取りの際、各吊上げ装置106が必要以上に移動して、架設対象プレキャスト桁14oが両橋脚12A、12Bと不用意に干渉してしまうのを未然に防止することができる。なお、横取りの際における、各吊上げ装置106の、架設用ガーダ104の長手方向の移動量はさほど大きくはならないので、すべり移動を採用しても架設作業の効率を実質的に低下させてしまうことはない。   Further, in the present embodiment, since the longitudinal movement of the erection girder 104 of each lifting device 106 is performed by sliding movement, this is compared with the case where it is performed by rolling movement. Thus, it is possible to prevent in advance that each lifting device 106 moves more than necessary and the installation target precast girder 14o inadvertently interferes with both piers 12A and 12B. In addition, since the moving amount of each lifting device 106 in the longitudinal direction of the erection girder 104 does not increase so much in the case of the horizontal interception, the efficiency of the erection work is substantially reduced even if the sliding movement is adopted. There is no.

さらに本実施形態においては、各吊上げ装置106をウインチで構成しておくようになっているので、各吊上げ装置106をコンパクトに構成することができる。また、このように各吊上げ装置106をウインチで構成しておくことにより、その架設用ガーダ104の長手方向の移動を、すべり移動で行わせるようにすることが容易に可能となる。   Furthermore, in this embodiment, since each lifting device 106 is configured by a winch, each lifting device 106 can be configured compactly. Further, by constituting each lifting device 106 with a winch in this way, it is possible to easily move the erection girder 104 in the longitudinal direction by sliding movement.

また、本実施形態に係る橋梁架設方法を採用することにより、架設径間S0での架設作業に用いた横取りレール102A、102B、架設用ガーダ104、吊上げ装置106および横移動装置110A、110Bを、他の架設径間S−1、S+1等での架設作業にも、そのまま用いることができる。   Further, by adopting the bridge erection method according to the present embodiment, the pre-installed rails 102A and 102B, the erection girder 104, the lifting device 106, and the lateral movement devices 110A and 110B used for the erection work between the erection spans S0, It can also be used as it is for erection work in other erection spans S-1, S + 1 and the like.

上記実施形態においては、ころがり機構116を、ころがり機構114に対して、橋軸方向両側に位置する2箇所に配置しておくものとして説明したが、このころがり機構116を、ころがり機構114に対して、橋軸方向両側に位置する2箇所を含む3箇所以上に配置しておくようにしてもよく、このようにした場合においても上記実施形態の場合と同様の作用効果を得ることができる。   In the above embodiment, the rolling mechanism 116 has been described as being disposed at two locations on both sides of the bridge axis direction with respect to the rolling mechanism 114. However, the rolling mechanism 116 is disposed with respect to the rolling mechanism 114. Further, it may be arranged in three or more places including two places located on both sides in the bridge axis direction, and even in this case, the same effect as in the case of the above embodiment can be obtained.

上記実施形態においては、架設径間S0において、複数のプレキャスト桁14が互いに非平行に架設されるようになっており、かつ、1対の橋脚12A、12Bが非平行に配置されている場合における橋梁架設方法について説明したが、これ以外にも、複数のプレキャスト桁14が互いに非平行に架設されるようになってはいるが、1対の橋脚12A、12Bが平行に配置されている場合、あるいは、1対の橋脚12A、12Bが非平行に配置されてはいるが、複数のプレキャスト桁14が互いに平行に架設されるようになっている場合においても、上記実施形態に係る橋梁架設方法を採用することにより、上記実施形態の場合と同様の作用効果を得ることができる。   In the above embodiment, in the span between spans S0, the plurality of precast girders 14 are constructed so as to be non-parallel to each other, and the pair of bridge piers 12A and 12B are arranged non-parallel. Although the bridge erection method has been described, in addition to this, a plurality of precast girders 14 are erected non-parallel to each other, but when a pair of piers 12A and 12B are arranged in parallel, Alternatively, although the pair of bridge piers 12A and 12B are arranged non-parallel, the bridge erection method according to the above embodiment can be used even when a plurality of precast girders 14 are erected in parallel to each other. By adopting, the same operational effects as in the case of the above-described embodiment can be obtained.

なお、上記実施形態において諸元として示した数値は一例にすぎず、これらを適宜異なる値に設定してもよいことはもちろんである。   In addition, the numerical value shown as a specification in the said embodiment is only an example, and of course, you may set these to a different value suitably.

12A、12B 橋脚
12Aa、12Ba 桁受け部
14 プレキャスト桁
14a 凹部
14o 架設対象プレキャスト桁
102A、102B 横取りレール
102Aa、102Ba 一端部
102Ab、102Bb 他端部
102Ac レール部
104 架設用ガーダ
104a ガーダ吊上げ金具
106 吊上げ装置
108 桁吊り金具
110A、110B 横移動装置
110AL、110BL 下部構造部
110AU、110BU 上部構造部
112 センタホールジャッキ
114、116 ころがり機構
118 回動機構
120 横取り鋼棒
122 スペーサ
124、126、128 ガイド部材
130 支持鋼材
132 テフロン板
Ax 鉛直軸線
S0、S−1、S+1 架設径間
Y 搬入ヤード
θ 交角
12A, 12B Pier 12Aa, 12Ba Girder receiving part 14 Precast girder 14a Recessed part 14o Precast girder 102A, 102B Horizontal rail 102Aa, 102Ba One end part 102Ab, 102Bb Other end part 102Ac Rail part 104 Girder lifting apparatus 104a Girder lifting bracket 104a 108 Girder hanging bracket 110A, 110B Lateral moving device 110AL, 110BL Lower structure 110AU, 110BU Upper structure 112 Center hole jack 114, 116 Rolling mechanism 118 Rotating mechanism 120 Horizontal steel rod 122 Spacer 124, 126, 128 Guide member 130 Support Steel 132 Teflon plate Ax Vertical axis S0, S-1, S + 1 Construction span Y Loading yard θ Intersection angle

Claims (4)

架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数のプレキャスト桁を橋軸直交方向に所定間隔をおいて架設する橋梁架設方法において、
上記1対の橋脚の各々の上面に、略橋軸直交方向に延びる横取りレールを、該横取りレールの一端部が上記架設径間の側方に位置する搬入ヤードまで張り出す態様で設置するとともに、橋軸方向に延びる架設用ガーダを、上記架設径間を跨ぐ位置において、上記1対の横取りレールの各々に対して該横取りレールの長手方向に移動可能な態様で設置した状態で、
上記搬入ヤードにおいて、上記架設用ガーダに設置された1対の吊上げ装置により、上記複数のプレキャスト桁のうちの1つを架設対象プレキャスト桁として吊り上げて、上記架設用ガーダを上記架設対象プレキャスト桁の架設予定位置まで橋軸直交方向に移動させた後、上記1対の吊上げ装置により上記架設対象プレキャスト桁を上記1対の橋脚上に吊り下ろし、以下これを繰り返すことにより上記複数のプレキャスト桁の架設を行うようにし、
その際、上記架設用ガーダを、上記1対の横取りレールの各々に対して鉛直軸線回りに回動可能な態様で、かつ、上記1対の横取りレールのうちの一方に対して橋軸方向に移動可能な態様で設置しておくとともに、上記1対の吊上げ装置の各々を、上記架設用ガーダに対して該架設用ガーダの長手方向に移動可能な態様で設置しておく、ことを特徴とする橋梁架設方法。
In the bridge erection method, a plurality of precast girders are erected at a predetermined interval in a direction perpendicular to the bridge axis between a pair of piers located on both sides in the bridge axis direction between the erection diameters.
On the upper surface of each of the pair of bridge piers, a horizontal rail extending in a direction substantially perpendicular to the bridge axis is installed in such a manner that one end of the horizontal rail extends to a carry-in yard located on the side between the spanning diameters, In the state where the girder for installation extending in the bridge axis direction is installed in a manner movable in the longitudinal direction of the horizontal rail with respect to each of the pair of horizontal rails at a position straddling the span between the installation diameters,
In the carry-in yard, one of the plurality of precast girders is lifted as a precast girder for installation by a pair of lifting devices installed on the girder for construction, and the girder for construction is installed in the precast girder for construction. After moving in the direction perpendicular to the bridge axis to the planned installation position, the above-described precast girders are suspended on the above-mentioned pair of bridge piers by the above-described pair of lifting devices, and the above-described steps are repeated to construct the plurality of precast girders. And do
In that case, the construction girder is configured to be rotatable around a vertical axis with respect to each of the pair of horizontal rails, and in a bridge axis direction with respect to one of the pair of horizontal rails. It is installed in a movable manner, and each of the pair of lifting devices is installed in a manner movable in the longitudinal direction of the erection girder with respect to the erection girder. How to build a bridge.
上記架設用ガーダの、上記一方の横取りレールに対する橋軸方向の移動を、ころがり機構を用いたころがり移動により行わせるようにした上で、
上記ころがり機構を、上記架設用ガーダを上記各横取りレールの長手方向に移動させるための機構に対して橋軸方向両側に位置する少なくとも2箇所に配置しておく、ことを特徴とする請求項1記載の橋梁架設方法。
After making the construction girder move in the direction of the bridge axis with respect to the one of the horizontal rails by rolling movement using a rolling mechanism,
2. The rolling mechanism is arranged at least at two positions located on both sides in the bridge axis direction with respect to a mechanism for moving the erection girder in the longitudinal direction of each of the horizontal rails. The bridge construction method described.
上記架設用ガーダの、上記各横取りレールの長手方向の移動を、ころがり機構を用いたころがり移動により行わせる、ことを特徴とする請求項2記載の橋梁架設方法。   3. The bridge erection method according to claim 2, wherein the erection girder is caused to move in the longitudinal direction of each of the horizontal rails by rolling movement using a rolling mechanism. 上記各吊上げ装置の、上記架設用ガーダの長手方向の移動を、すべり移動により行わせる、ことを特徴とする請求項1〜3いずれか記載の橋梁架設方法。   The bridge erection method according to any one of claims 1 to 3, wherein each lifting device is caused to move in the longitudinal direction of the erection girder by sliding movement.
JP2010151898A 2010-07-02 2010-07-02 Bridge erection method Active JP5487031B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010151898A JP5487031B2 (en) 2010-07-02 2010-07-02 Bridge erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010151898A JP5487031B2 (en) 2010-07-02 2010-07-02 Bridge erection method

Publications (2)

Publication Number Publication Date
JP2012012877A true JP2012012877A (en) 2012-01-19
JP5487031B2 JP5487031B2 (en) 2014-05-07

Family

ID=45599624

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010151898A Active JP5487031B2 (en) 2010-07-02 2010-07-02 Bridge erection method

Country Status (1)

Country Link
JP (1) JP5487031B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101239621B1 (en) 2012-11-29 2013-03-07 주식회사 인터컨스텍 Beam launching method using beam launcher with end strut having roller guide
CN109629456A (en) * 2019-01-16 2019-04-16 中交公局海威工程建设有限公司 A kind of precast beam traverse displacement unit and precast beam crossing system
JP2020153184A (en) * 2019-03-22 2020-09-24 株式会社横河ブリッジ Existing superstructure rebuilding method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02256705A (en) * 1989-03-30 1990-10-17 Mitsui Miike Mach Co Ltd Horizontally feeding and bridging method of girder beam block, and apparatus thereof
JPH0959930A (en) * 1995-08-18 1997-03-04 P S Co Ltd Bridge girder construction method and device thereof
JP2003253623A (en) * 2002-03-04 2003-09-10 Taisei Corp Rebuilding construction method for bridge beam
JP2006016795A (en) * 2004-06-30 2006-01-19 Otaki Yuatsu:Kk Heavy load set-off technique
JP2009068249A (en) * 2007-09-13 2009-04-02 Sumitomo Mitsui Construction Co Ltd Bridge construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02256705A (en) * 1989-03-30 1990-10-17 Mitsui Miike Mach Co Ltd Horizontally feeding and bridging method of girder beam block, and apparatus thereof
JPH0959930A (en) * 1995-08-18 1997-03-04 P S Co Ltd Bridge girder construction method and device thereof
JP2003253623A (en) * 2002-03-04 2003-09-10 Taisei Corp Rebuilding construction method for bridge beam
JP2006016795A (en) * 2004-06-30 2006-01-19 Otaki Yuatsu:Kk Heavy load set-off technique
JP2009068249A (en) * 2007-09-13 2009-04-02 Sumitomo Mitsui Construction Co Ltd Bridge construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101239621B1 (en) 2012-11-29 2013-03-07 주식회사 인터컨스텍 Beam launching method using beam launcher with end strut having roller guide
CN109629456A (en) * 2019-01-16 2019-04-16 中交公局海威工程建设有限公司 A kind of precast beam traverse displacement unit and precast beam crossing system
CN109629456B (en) * 2019-01-16 2024-03-22 中交一公局海威工程建设有限公司 Precast beam sideslip device and precast beam sideslip system
JP2020153184A (en) * 2019-03-22 2020-09-24 株式会社横河ブリッジ Existing superstructure rebuilding method
JP7296751B2 (en) 2019-03-22 2023-06-23 株式会社横河ブリッジ Existing superstructure replacement method

Also Published As

Publication number Publication date
JP5487031B2 (en) 2014-05-07

Similar Documents

Publication Publication Date Title
JP5179804B2 (en) Mobile suspension support
KR101040665B1 (en) Crane for constructing girder
JP5203662B2 (en) Bridge main girder erection method and erection girder horizontal mechanism
JP2018100564A (en) Device and method of floor slab rebuilding
JP2008088782A (en) Cantilever overhang erection method of corrugated steel plate web bridge
JP2009299418A (en) Retreating and removing method and retreating device for travelling work vehicle for cantilever construction
JP4777319B2 (en) Bridge erection method
JP7045936B2 (en) Hanger unit in deck erection machine
TW201508143A (en) Construction operating device and construction operating method for vertical plane
JP5487031B2 (en) Bridge erection method
EA201000934A1 (en) LIFTING DEVICES INCLUDING THE KEYSTONE TRAPPED LOCKING BEAM STRUCTURES
JP5702640B2 (en) Bridge crane, bridge erection method, and bridge removal method
JP7144978B2 (en) Floor slab erection machine
JP6917948B2 (en) Lifting device for heavy objects and lifting method
KR101040664B1 (en) Crane for constructing girder
CN214939324U (en) Rail device suitable for construction of laminated beam floor
JP5772273B2 (en) Installation apparatus and installation method
KR20140122488A (en) rotary lift crane
JP2016142097A (en) Portable hoist unit and horizontal member dismantling method
JP4704279B2 (en) Bridge construction method
JPH1181246A (en) Tension jack moving device for precast concrete block construction method
JP2013036287A (en) Device and method for lifting floor unit
JP2023058220A (en) Slide type turning device
JP2005132557A (en) Overhead traveling crane
CN110356967A (en) A kind of gantry crane

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130204

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130927

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140218

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140224

R150 Certificate of patent or registration of utility model

Ref document number: 5487031

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250