JP2011258139A - Project cost prediction apparatus, project cost prediction method, and project cost prediction program - Google Patents

Project cost prediction apparatus, project cost prediction method, and project cost prediction program Download PDF

Info

Publication number
JP2011258139A
JP2011258139A JP2010134390A JP2010134390A JP2011258139A JP 2011258139 A JP2011258139 A JP 2011258139A JP 2010134390 A JP2010134390 A JP 2010134390A JP 2010134390 A JP2010134390 A JP 2010134390A JP 2011258139 A JP2011258139 A JP 2011258139A
Authority
JP
Japan
Prior art keywords
cost
task
information
project
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2010134390A
Other languages
Japanese (ja)
Inventor
Junichi Uematsu
潤一 植松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP2010134390A priority Critical patent/JP2011258139A/en
Publication of JP2011258139A publication Critical patent/JP2011258139A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a project cost prediction apparatus capable of improving prediction accuracy of the final cost of a project.SOLUTION: A project cost prediction apparatus is provided with: a task information storage part 4 for storing task information including a project ID, a task ID, a progress rate of the task, a budget of the task, a functional phase classification of the task, and a work process classification of the task; a cost information storage part 6 for storing cost information including a project ID, a task ID, a resulting cost value, and a cost division; a cost information generation part 9 for every task for generating cost information for every task by adding a determined cost accumulated value and an estimated cost accumulated value that are accumulated for every cost division to the task information; and a cost calculation part 11 for determining a final cost prediction value of the project by summing the determined cost accumulated value and the estimated cost accumulated value of the cost information for every task, and a predicted cost that is calculated from the progress rate and the budget of the task.

Description

本発明は、進行中のプロジェクトの最終コストを予測するプロジェクトコスト予測装置に関する。   The present invention relates to a project cost prediction apparatus for predicting the final cost of an ongoing project.

従来、進行中のプロジェクトの最終コストを予測する方法の1つに、EVM(Earned Value Management)という進捗管理手法がある。この手法では、現在のコスト効率に基づいて、プロジェクト完了時のコストを予測する。   Conventionally, there is a progress management technique called EVM (Earned Value Management) as one method for predicting the final cost of an ongoing project. In this method, the cost at the completion of the project is predicted based on the current cost efficiency.

しかしながら、EVMでは、現在のコスト効率が以降の全ての作業に反映されてしまうため、局所的に一部の作業のみに影響を及ぼすような異常が発生していた場合には、その影響が全体に及び、最終コストの予測精度が低下する、という問題があった。このような問題を解決する技術としては、たとえば、下記特許文献1〜3において開示されているような技術がある。これらの文献では、EVMを改良した方法等によって最終コストの予測精度を改善しており、詳細には、作業中に異常が発生した際の影響を限定的にすることで、最終コストの予測精度を向上させている。   However, in EVM, the current cost efficiency is reflected in all subsequent operations. Therefore, if an abnormality that locally affects only a part of the operation has occurred, the effect is totally affected. Furthermore, there is a problem that the prediction accuracy of the final cost is lowered. As a technique for solving such a problem, for example, there is a technique disclosed in Patent Documents 1 to 3 below. In these documents, the accuracy of predicting the final cost is improved by a method of improving the EVM. Specifically, the accuracy of predicting the final cost is limited by limiting the influence when an abnormality occurs during the work. Has improved.

特開2008−171122号公報JP 2008-171122 A 特開2004−287891号公報JP 2004-287991 A 特開2007−018163号公報JP 2007-018163 A

上記従来の技術によれば、異常が発生した際の影響を限定的に扱うが、実際のプロジェクトでは、ある部門の作業に遅れが生じた場合には、その作業の後工程の部門にも少なからず影響が発生し、また、遅れが発生した部門が次に実行すべき作業にも影響が発生し、その影響の大きさも発生した異常内容によって異なる。しかしながら、異常が発生した場合の影響が将来的に及ぶ範囲と及ばない範囲、および影響が及ぶ場合の大きさ、を個々の各作業(タスク)の単位で検討していないため、飛躍的に予測精度を向上させることはできない、という問題があった。   According to the above-mentioned conventional technology, the impact when an abnormality occurs is dealt with limitedly. However, in the actual project, if there is a delay in the work of a certain department, there is also little in the department in the post-process of that work. There is an effect on the work to be executed next by the department in which the delay has occurred, and the magnitude of the effect varies depending on the content of the abnormality. However, since the scope of impact in the future when it occurs and the extent to which it does not reach and the magnitude of the impact will not be considered for each individual task, it will be predicted dramatically There was a problem that the accuracy could not be improved.

本発明は、上記に鑑みてなされたものであって、プロジェクトの最終コストの予測精度を向上させることが可能なプロジェクトコスト予測装置を得ることを目的とする。   The present invention has been made in view of the above, and an object of the present invention is to obtain a project cost prediction apparatus capable of improving the prediction accuracy of the final cost of a project.

上述した課題を解決し、目的を達成するために、本発明は、機能フェーズまたは作業工程でタスクを分類可能なプロジェクトの最終コストを予測するプロジェクトコスト予測装置において、プロジェクトIDとタスクIDとタスクの進捗率とタスクの予算とタスクの機能フェーズ種別とタスクの作業工程種別とを含むタスク情報を、タスクごとに記憶するためのタスク情報記憶手段と、プロジェクトIDとタスクIDとコスト値と、当該コスト値が確定したコストである確定コストまたは現時点で確定されていないが将来的に確定されるコストである見込コストのいずれかを区分するコスト区分と、を含むコスト情報を、発生したコストごとに外部のシステムから取得するコスト情報取得手段と、前記取得したコスト情報を記憶するためのコスト情報記憶手段と、前記タスク情報記憶手段から同一のプロジェクトIDが記憶されたタスク情報を全て読み出し、前記コスト情報記憶手段から同一のプロジェクトIDが記憶されたコスト情報を全て読み出し、タスク情報ごとに、当該タスク情報のタスクIDと同一のタスクIDを含むコスト情報に記憶されているコスト値をコスト区分ごとに累積した確定コスト累積値および見込コスト累積値を追加することにより、タスク別コスト情報を生成するタスク別コスト情報生成手段と、前記タスク別コスト情報を記憶するためのタスク別コスト情報記憶手段と、前記タスク別コスト情報記憶手段からタスク別コスト情報を読み出し、確定コスト累積値と見込コスト累積値と、進捗率および予算を用いて算出した予測コストと、を加算することによりプロジェクトの最終コスト予測値を求めるコスト計算手段と、を備えることを特徴とする。   In order to solve the above-described problems and achieve the object, the present invention provides a project cost prediction apparatus for predicting a final cost of a project in which tasks can be classified in a functional phase or a work process. Task information storage means for storing task information including progress rate, task budget, task function phase type and task work process type for each task, project ID, task ID, cost value, and cost Cost information that includes either a fixed cost that is a fixed cost or a cost category that classifies either an estimated cost that is not determined at the present time but is determined in the future. Cost information acquisition means for acquiring the acquired cost information, and a cost information acquisition means for acquiring the acquired cost information. All the task information stored with the same project ID from the task information storage means and the task information storage means, and all the cost information stored with the same project ID is read out from the cost information storage means. By adding a fixed cost cumulative value and an estimated cost cumulative value obtained by accumulating the cost value stored in the cost information including the same task ID as the task ID of the task information for each cost category, the task-specific cost information is obtained. Task-specific cost information generating means, task-specific cost information storage means for storing the task-specific cost information, and task-specific cost information are read from the task-specific cost information storage means. Add the cumulative value to the estimated cost calculated using the progress rate and budget. Characterized in that and a cost calculation means for calculating the final cost prediction value of the project by.

本発明によれば、プロジェクトの最終コストの予測精度を向上することができる、という効果を奏する。   According to the present invention, it is possible to improve the accuracy of predicting the final cost of a project.

図1は、プロジェクトコスト予測装置の構成例を示す図である。FIG. 1 is a diagram illustrating a configuration example of a project cost prediction apparatus. 図2は、プロジェクト基本情報の構成例を示す図である。FIG. 2 is a diagram illustrating a configuration example of the basic project information. 図3は、タスク情報の構成例を示す図である。FIG. 3 is a diagram illustrating a configuration example of task information. 図4は、コスト情報の構成例を示す図である。FIG. 4 is a diagram illustrating a configuration example of cost information. 図5は、タスク未割り当てコスト情報の構成例を示す図である。FIG. 5 is a diagram illustrating a configuration example of task unallocated cost information. 図6は、タスク別コスト情報の構成例を示す図である。FIG. 6 is a diagram illustrating a configuration example of task-specific cost information. 図7は、属性項目とタスクの関係およびタスク別コストを示す図である。FIG. 7 is a diagram illustrating the relationship between attribute items and tasks, and the cost for each task. 図8は、プロジェクト最終コスト予測処理を示すフローチャートである。FIG. 8 is a flowchart showing the project final cost prediction process. 図9は、タスクID入力処理を示すフローチャートである。FIG. 9 is a flowchart showing task ID input processing. 図10は、プロジェクトコスト予測プログラムを実行可能な電子計算機の構成例を示す図である。FIG. 10 is a diagram illustrating a configuration example of an electronic computer capable of executing a project cost prediction program.

以下に、本発明にかかるプロジェクトコスト予測装置の実施の形態を図面に基づいて詳細に説明する。なお、この実施の形態によりこの発明が限定されるものではない。   Embodiments of a project cost prediction apparatus according to the present invention will be described below in detail with reference to the drawings. Note that the present invention is not limited to the embodiments.

実施の形態.
図1は、プロジェクトコスト予測装置の構成例を示す図である。プロジェクトコスト予測装置は、プロジェクト基本情報入力部1と、プロジェクト基本情報記憶部2と、タスク情報入力部3と、タスク情報記億部4と、コスト情報取得部5と、コスト情報記憶部6と、タスク未割当情報記憶部7と、タスク割当入力部8と、タスク別コスト情報生成部9と、タスク別コスト情報記憶部10と、コスト計算部11と、を備える。
Embodiment.
FIG. 1 is a diagram illustrating a configuration example of a project cost prediction apparatus. The project cost prediction apparatus includes a project basic information input unit 1, a project basic information storage unit 2, a task information input unit 3, a task information storage unit 4, a cost information acquisition unit 5, and a cost information storage unit 6. , A task non-allocation information storage unit 7, a task allocation input unit 8, a task-specific cost information generation unit 9, a task-specific cost information storage unit 10, and a cost calculation unit 11.

プロジェクト基本情報入力部1は、操作者がプロジェクトに関する基本情報を入力するための入力部である。プロジェクト基本情報記憶部2は、プロジェクト基本情報入力部1において入力されたプロジェクト基本情報を記憶するための記憶部である。   The project basic information input unit 1 is an input unit for an operator to input basic information about a project. The project basic information storage unit 2 is a storage unit for storing the project basic information input in the project basic information input unit 1.

タスク情報入力部3は、操作者がタスクに関する属性情報等の基本情報や予算コストを入力するための入力部である。タスク情報記億部4は、タスク情報入力部3において入力されたタスク情報を記憶するための記憶部である。   The task information input unit 3 is an input unit for an operator to input basic information such as attribute information related to a task and budget costs. The task information storage unit 4 is a storage unit for storing the task information input in the task information input unit 3.

コスト情報取得部5は、周辺の外部システム(プロジェクトに係わる部門のシステム)で作成されたコスト情報を取得する。コスト情報記憶部6は、コスト情報取得部5で取得されたコスト情報を記憶するための記憶部である。   The cost information acquisition unit 5 acquires cost information created by a peripheral external system (a system of a department related to the project). The cost information storage unit 6 is a storage unit for storing the cost information acquired by the cost information acquisition unit 5.

タスク未割当情報記憶部7は、コスト情報取得部5で取得されたコスト情報のうち、タスクが未割り当てのコスト情報を一時的に記憶するための記憶部である。タスク割当入力部8は、タスク未割当情報記憶部7に記憶されているタスク未割り当てコスト情報に対してタスクIDを入力し、入力後のコスト情報をコスト情報記憶部6に記憶する。   The task unassigned information storage unit 7 is a storage unit for temporarily storing cost information to which no task is assigned among the cost information acquired by the cost information acquiring unit 5. The task assignment input unit 8 inputs a task ID for the task unassigned cost information stored in the task unassigned information storage unit 7 and stores the cost information after the input in the cost information storage unit 6.

タスク別コスト情報生成部9は、タスク情報記億部4から読み出したタスク情報、およびコスト情報記憶部6から読み出したコスト情報を用いて、タスク別にコストを累積したタスク別コスト情報を生成する。タスク別コスト情報記憶部10は、タスク別コスト情報生成部9で生成されたタスク別コスト情報を記憶するための記憶部である。   The task-specific cost information generation unit 9 uses the task information read from the task information storage unit 4 and the cost information read from the cost information storage unit 6 to generate task-specific cost information in which costs are accumulated for each task. The task-specific cost information storage unit 10 is a storage unit for storing task-specific cost information generated by the task-specific cost information generation unit 9.

コスト計算部11は、プロジェクト基本情報記憶部2から読み出したプロジェクト基本情報に関連するコスト情報をタスク別コスト情報記憶部10から読み出し、当該プロジェクトについて最終コストを予測する。   The cost calculation unit 11 reads cost information related to the project basic information read from the project basic information storage unit 2 from the task-specific cost information storage unit 10 and predicts a final cost for the project.

つぎに、各記憶部が記憶しているデータの内容について説明する。図2は、プロジェクト基本情報記憶部2が記憶しているプロジェクト基本情報の構成例を示す図である。プロジェクト基本情報は、プロジェクトIDと、プロジェクト名称と、から構成される。   Next, the contents of data stored in each storage unit will be described. FIG. 2 is a diagram illustrating a configuration example of the basic project information stored in the basic project information storage unit 2. The basic project information includes a project ID and a project name.

プロジェクトIDは、各プロジェクトを特定するために付与されたIDである。プロジェクト名称は、前記プロジェクトIDと1対1で対応し、顧客や製品の名称等を含むプロジェクトを表す名称である。プロジェクト基本情報記憶部2は、例えば、プロジェクトID:P0001、プロジェクト名称:XYZ社向けABCシステム導入プロジェクト、のように各情報をプロジェクトごとに記憶する。   The project ID is an ID assigned to identify each project. The project name corresponds to the project ID on a one-to-one basis, and is a name representing a project including the name of a customer or product. The project basic information storage unit 2 stores information for each project, for example, project ID: P0001, project name: ABC system introduction project for XYZ company.

図3は、タスク情報記憶部4が記憶しているタスク情報の構成例を示す図である。タスク情報は、プロジェクトIDと、タスクIDと、タスク名称と、開始予定日と、終了予定日と、開始日と、終了日と、進捗率と、予算コストと、属性項目Aと、属性項目Bと、から構成される。   FIG. 3 is a diagram illustrating a configuration example of task information stored in the task information storage unit 4. The task information includes project ID, task ID, task name, scheduled start date, scheduled end date, start date, end date, progress rate, budget cost, attribute item A, and attribute item B. And.

プロジェクトIDは、各プロジェクトを特定するために付与されたIDである。タスクIDは、各プロジェクトで設定されている個々のタスクを特定するためのIDである。タスク名称は、前記タスクIDと1対1で対応し、当該プロジェクトにおけるタスクの内容を表す名称である。開始予定日は、当該タスクの作業開始の予定日を表す。終了予定日は、当該タスクの作業終了の予定日を表す。開始日は、当該タスクの実際の作業を開始した日を表す。終了日は、当該タスクの実際の作業が終了した日を表す。進捗率は、当該タスクの現在の進捗率を表す。予算コストは、当該タスクに割り当てられた予算を示す。属性項目Aは、当該タスクが属性項目Aの中から所属する属性値を表す。属性項目Aの属性値の種別としては、一例として、情報システム分野における、機能フェーズ(機能1、機能2、機能3、…)がある。属性項目Bは、当該タスクが属性項目Bの中から所属する属性値を表す。属性項目Bの属性値の種別としては、一例として、情報システム分野における、作業工程(設計、プログラム開発、テスト、…)がある。   The project ID is an ID assigned to identify each project. The task ID is an ID for identifying an individual task set in each project. The task name is a name that corresponds to the task ID on a one-to-one basis and represents the content of the task in the project. The scheduled start date represents the scheduled start date of the task. The scheduled end date represents the scheduled end date of the task. The start date represents the date when the actual work of the task is started. The end date represents the date when the actual work of the task has ended. The progress rate represents the current progress rate of the task. The budget cost indicates a budget allocated to the task. The attribute item A represents an attribute value to which the task belongs from the attribute item A. As an example of the attribute value type of the attribute item A, there is a function phase (function 1, function 2, function 3,...) In the information system field. The attribute item B represents an attribute value to which the task belongs from the attribute item B. As an example of the attribute value type of the attribute item B, there is a work process (design, program development, test,...) In the information system field.

タスク情報記憶部4は、例えば、プロジェクトID:P0001、タスクID:T13、タスク名称:ZZZ機能詳細設計、開始予定日:2010/01/18、終了予定日:2010/01/29、開始日:2010/01/18、終了日:(未記入)、進捗率:0.50、予算コスト:500000、属性項目A:A1(ZZZ機能)、属性項目B:B3(詳細設計)、のように各情報をタスクごとに記憶する。   The task information storage unit 4 includes, for example, project ID: P0001, task ID: T13, task name: ZZZ function detailed design, scheduled start date: 2010/01/18, scheduled end date: 2010/01/29, start date: 2010/01/18, end date: (not filled in), progress rate: 0.50, budget cost: 500000, attribute item A: A1 (ZZZ function), attribute item B: B3 (detailed design), etc. Store information for each task.

図4は、コスト情報記憶部6が記憶しているコスト情報の構成例を示す図である。コスト情報は、プロジェクトIDと、タスクIDと、コスト区分と、確定/見込コストと、データ収集日と、データ収集時刻と、収集ファイル名称と、から構成される。プロジェクトIDは、各プロジェクトを特定するために付与されたIDである。タスクIDは、各プロジェクトで設定されている個々のタスクを特定するためのIDである。コスト区分は、当該ファイルに関するコストが確定コストか、見込コストかを示す。確定/見込コストは、発生したコストを示す。データ収集日は、当該コスト情報を読み出した日を示す。データ収集時刻は、当該コスト情報を読み出した時刻を示す。収集ファイル名称は、当該ファイルの名称を示す。   FIG. 4 is a diagram illustrating a configuration example of cost information stored in the cost information storage unit 6. The cost information includes a project ID, a task ID, a cost category, a fixed / expected cost, a data collection date, a data collection time, and a collection file name. The project ID is an ID assigned to identify each project. The task ID is an ID for identifying an individual task set in each project. The cost category indicates whether the cost related to the file is a fixed cost or an expected cost. The fixed / expected cost indicates the cost that has occurred. The data collection date indicates the date when the cost information is read out. The data collection time indicates the time when the cost information is read out. The collection file name indicates the name of the file.

コスト情報記憶部6は、例えば、プロジェクトID:P0001、タスクID:T13、コスト区分:K、確定/見込コスト:10000、データ収集日:2010/01/25、データ収集時刻:08:30:00、収集ファイル名称:sagyo_jikan0125、のような各情報を取得したコスト情報単位で記憶する。   The cost information storage unit 6 includes, for example, project ID: P0001, task ID: T13, cost classification: K, finalized / expected cost: 10000, data collection date: 2010/01/25, data collection time: 08: 30.00. Each information such as collection file name: sagoyo_jikan0125 is stored in units of acquired cost information.

ここで、確定コスト(コスト区分:Kとする)は、当該タスクで発生した費用のうち、既に会計システム等のコストを管理するシステムに計上されているコストとする。また、見込コスト(コスト区分:Mとする)は、当該タスクで発生した費用のうち、会計システム等には計上されていないが、各部門において現時点で発生したコストとする。   Here, the deterministic cost (cost category: K) is a cost already recorded in a system that manages costs such as an accounting system among the costs incurred in the task. Further, the expected cost (cost category: M) is the cost incurred at the present time in each department, although it is not recorded in the accounting system etc. among the costs incurred in the task.

図5は、タスク未割当情報記憶部7が記憶しているタスク未割り当てコスト情報の構成例を示す図である。タスク未割り当てコスト情報は、プロジェクトIDと、コスト区分と、確定/見込コストと、データ収集日と、データ収集時刻と、収集ファイル名称と、から構成される。図4に示すコスト情報から、タスクIDの情報を除いたものである。   FIG. 5 is a diagram illustrating a configuration example of task unallocated cost information stored in the task unallocated information storage unit 7. The task unassigned cost information includes a project ID, a cost category, a fixed / expected cost, a data collection date, a data collection time, and a collection file name. Task ID information is removed from the cost information shown in FIG.

図6は、タスク別コスト情報記憶部10が記憶しているタスク別コスト情報の構成例を示す図である。タスク別コスト情報は、プロジェクトIDと、タスクIDと、タスク名称と、開始予定日と、終了予定日と、開始日と、終了日と、進捗率と、予算コストと、確定コストと、見込コストと、属性項目Aと、属性項目Bと、から構成される。タスク情報記憶部4が記憶しているタスク情報(図3参照)に、コスト情報記憶部6が記憶しているコスト情報(図4参照)のコスト区分および確定/見込コストの情報に基づいて、確定コストおよび見込コストの情報を追加したものである。   FIG. 6 is a diagram illustrating a configuration example of task-specific cost information stored in the task-specific cost information storage unit 10. The cost information by task includes the project ID, task ID, task name, scheduled start date, scheduled end date, start date, end date, progress rate, budget cost, fixed cost, and expected cost. And attribute item A and attribute item B. Based on the information on the cost category and the fixed / expected cost of the cost information (see FIG. 4) stored in the cost information storage unit 6 in the task information (see FIG. 3) stored in the task information storage unit 4, Information of the fixed cost and the expected cost is added.

確定コストは、タスク別に、該当するコスト情報を累積して求めることができる。一方、見込コストは、後に確定コストに計上される。そのため、一度、見込コストに計上されてから後に確定コストに計上された分については、その都度、見込みコストの累積値から減算する。なお、プロジェクト終了時点では、全てのタスクにおいて見込コストは「0」となる。タスク別コスト情報記憶部10は、タスク情報記憶部4が記憶している内容に加えて、確定コスト:280000、見込コスト:50000、のように各情報をタスクごとに記憶する。   The fixed cost can be obtained by accumulating corresponding cost information for each task. On the other hand, the expected cost is recorded as a fixed cost later. For this reason, the amount once recorded in the estimated cost and subsequently recorded in the finalized cost is subtracted from the cumulative value of the expected cost each time. At the end of the project, the expected cost is “0” for all tasks. In addition to the contents stored in the task information storage unit 4, the task-specific cost information storage unit 10 stores information for each task such as a fixed cost: 280000 and an expected cost: 50000.

つづいて、プロジェクトコスト予測装置におけるプロジェクトコスト最終予測処理について説明する。ここでは、一例として、図7に示す属性項目とタスクが設定された進行中のプロジェクトについて説明する。図7は、属性項目とタスクの関係およびタスク別コストを示す図である。ここでは属性項目Aを機能フェーズで分類し、属性値Ai(i=1,2,3,4)について、属性値A1を機能1とし、以下、属性値A2を機能2、属性値A3を機能3、属性値A4を機能4とする。また、属性項目Bを作業工程で分類し、属性値Bj(j=1,2,3)について、属性値B1を設計(工程)とし、以下、属性値B2をプログラム開発(工程)、属性値A3をテスト(工程)とする。また、上記分類で区分けされる個々のタスクをタスクTijとして表す。例えば、タスクT23は、機能2(属性値A2)を担当するテスト工程(属性値B3)に関するものである。各タスクTijには、現時点の各タスクの進捗率、確定コストおよび見込コストと、プロジェクト開始時に割り当てられた予算コストが記載されている。   Next, the project cost final prediction process in the project cost prediction apparatus will be described. Here, as an example, an ongoing project in which attribute items and tasks shown in FIG. 7 are set will be described. FIG. 7 is a diagram illustrating the relationship between attribute items and tasks, and the cost for each task. Here, the attribute item A is classified by the function phase, and for the attribute value Ai (i = 1, 2, 3, 4), the attribute value A1 is the function 1, and the attribute value A2 is the function 2 and the attribute value A3 is the function. 3. Let the attribute value A4 be function 4. Also, attribute item B is classified by work process, and attribute value B1 is designed (process) for attribute value Bj (j = 1, 2, 3). Hereinafter, attribute value B2 is program development (process), attribute value. Let A3 be a test (process). Each task classified by the above classification is represented as a task Tij. For example, task T23 relates to a test process (attribute value B3) in charge of function 2 (attribute value A2). Each task Tij describes a progress rate, a fixed cost and an expected cost of each task at the present time, and a budget cost assigned at the start of the project.

なお、図7に示す表は各タスクの関係とコスト状況を容易に把握するために用いるものであり、プロジェクトコスト予測装置において、プロジェクトコスト最終予測処理の過程で生成しなくてもよい。これらの情報は、それぞれのタスクのタスク別コスト情報に記憶されているものである。   Note that the table shown in FIG. 7 is used to easily grasp the relationship and cost status of each task, and may not be generated in the course of the project cost final prediction process in the project cost prediction apparatus. These pieces of information are stored in the task-specific cost information for each task.

具体的に、プロジェクトの進行状況が図7に示す場合に、当該時点におけるプロジェクト最終コスト予測処理をフローチャートに基づいて説明する。図8は、プロジェクトコスト予測装置のプロジェクト最終コスト予測処理を示すフローチャートである。   Specifically, when the progress of the project is shown in FIG. 7, the project final cost prediction process at the time will be described based on the flowchart. FIG. 8 is a flowchart showing the project final cost prediction process of the project cost prediction apparatus.

まず、プロジェクトコスト予測装置では、プロジェクト開始前に、プロジェクト基本情報入力部1が、プロジェクトに関する基本情報の入力を受け付けて、入力されたプロジェクト基本情報をプロジェクト基本情報記憶部2に記憶する(ステップS1)。このとき、プロジェクト基本情報記憶部2に記億される内容は、図2に示す情報である。   First, in the project cost prediction apparatus, before starting the project, the project basic information input unit 1 accepts input of basic information about the project and stores the input project basic information in the project basic information storage unit 2 (step S1). ). At this time, the contents stored in the project basic information storage unit 2 are the information shown in FIG.

つぎに、タスク情報入力部3が、各タスクに関する情報の入力を受け付けて、入力されたタスク情報をタスク情報記憶部4に記憶する(ステップS2)。タスク情報入力部3は、図3に示すタスク情報において、プロジェクト開始前に、開始日、予定日および進捗率以外の項目の入力を受け付ける。開始日は、実際に当該タスクの作業を開始した日付を、終了日は、実際に当該タスクの作業を終了した日付を記入する。また、進捗率は、定期的に、またはプロジェクトコスト最終予測処理を行う時点で更新する。図7に示すプロジェクトの場合、タスク情報入力部3は、12個のタスクについてタスク情報を入力する。   Next, the task information input unit 3 accepts input of information regarding each task, and stores the input task information in the task information storage unit 4 (step S2). The task information input unit 3 accepts input of items other than the start date, the scheduled date, and the progress rate before starting the project in the task information shown in FIG. The start date is the date when the task is actually started, and the end date is the date when the task is actually completed. The progress rate is updated regularly or when the project cost final prediction process is performed. In the case of the project shown in FIG. 7, the task information input unit 3 inputs task information for 12 tasks.

つぎに、コスト情報取得部5が、周辺システムからコスト情報を取得し、取得したコスト情報をコスト情報記憶部6に記憶する(ステップS3)。   Next, the cost information acquisition part 5 acquires cost information from a peripheral system, and memorize | stores the acquired cost information in the cost information storage part 6 (step S3).

つぎに、タスク別コスト情報生成部9が、タスク情報記億部4からタスク情報を読み出し、また、コスト情報記憶部6からコスト情報を読み出して、タスク情報およびコスト情報を用いてタスク別コスト情報を生成し、生成したタスク別コスト情報をタスク別コスト情報記憶部10に記憶する(ステップS4)。前述のとおり、タスク別コスト情報生成部9は、タスク情報(図3参照)に、コスト情報(図4参照)の確定/見込コストに基づいて、確定コストおよび見込コストの情報を追加して、タスク別にタスク別コスト情報を生成する。図7に示すプロジェクトの場合、タスク別コスト情報生成部9は、タスク別コスト情報を12個生成する。   Next, the task-specific cost information generation unit 9 reads the task information from the task information storage unit 4, and also reads the cost information from the cost information storage unit 6, and uses the task information and the cost information to perform the task-specific cost information. And the generated task-specific cost information is stored in the task-specific cost information storage unit 10 (step S4). As described above, the task-specific cost information generation unit 9 adds to the task information (see FIG. 3) information on the confirmed cost and the estimated cost based on the confirmed / expected cost of the cost information (see FIG. 4). Generate cost information for each task. In the case of the project shown in FIG. 7, the task-specific cost information generation unit 9 generates twelve task-specific cost information.

このとき、確定コストおよび見込コストについては、タスクごとに、該当するコスト情報を累積して求める。すなわち、あるタスクに該当するコスト情報が5つあった場合、タスク別コスト情報生成部9は、この5つのコスト情報に記載されている確定コストおよび見込コストをそれぞれ累積する。なお、タスク別コスト情報生成部9は、見込コストについては必要に応じて減算処理を行って求める。   At this time, the determined cost and the expected cost are obtained by accumulating the corresponding cost information for each task. That is, when there are five pieces of cost information corresponding to a certain task, the task-specific cost information generation unit 9 accumulates the fixed cost and the expected cost described in the five pieces of cost information. The task-specific cost information generation unit 9 obtains the estimated cost by performing a subtraction process as necessary.

つぎに、コスト計算部11は、プロジェクト基本情報記憶部2からプロジェクト基本情報を読み出し、また、タスク別コスト情報記憶部10からタスク別コスト情報を読み出す(ステップS5)。そして、コスト計算部11は、読み出したプロジェクト基本情報およびタスク別コスト情報を用いて、プロジェクト全体の予測コストを算出する。   Next, the cost calculation unit 11 reads the project basic information from the project basic information storage unit 2, and reads the task-specific cost information from the task-specific cost information storage unit 10 (step S5). And the cost calculation part 11 calculates the estimated cost of the whole project using the read project basic information and task-specific cost information.

まず、コスト計算部11は、属性項目ごとに属性値別確定コストと属性値別見込コストを集計する(ステップS6)。具体的に、コスト計算部11は、プロジェクト基本情報記憶部2に記憶されているプロジェクトIDを読み出し、当該プロジェクトIDを持つ全てのタスク情報をタスク別コスト情報記憶部10から読み出す。そして、コスト計算部11は、同一のプロジェクトIDを持つタスク情報について、確定コストおよび見込コストを、属性項目A内の属性値Ai(i=1、2、3、4)ごとに集計する。属性項目Aの場合は、次の式(1)、(2)のようにそれぞれ集計する。   First, the cost calculation part 11 totals the fixed cost classified by attribute value and the estimated cost classified by attribute value for every attribute item (step S6). Specifically, the cost calculation unit 11 reads the project ID stored in the project basic information storage unit 2 and reads all task information having the project ID from the task-specific cost information storage unit 10. Then, the cost calculation unit 11 aggregates the fixed cost and the expected cost for each attribute value Ai (i = 1, 2, 3, 4) in the attribute item A for the task information having the same project ID. In the case of the attribute item A, the calculation is performed as shown in the following formulas (1) and (2).

KAi=属性項目Aに属性値Aiを持つタスクの確定コストの合計値 …(1)
MAi=属性項目Aに属性値Aiを持つタスクの見込コストの合計値 …(2)
KAi = total value of fixed costs of tasks having attribute value Ai in attribute item A (1)
MAi = total value of expected costs of tasks having attribute value Ai in attribute item A (2)

具体的に、図7に示すプロジェクトにおいては、以下のようになる。
KA1=330000+550000+60000=940000
MA1=0+0+10000=10000
KA2=320000+240000+0=560000
MA2=0+30000+0=30000
KA3=140000+0+0=140000
MA3=50000+0+0=50000
KA4=30000+0+0=30000
MA4=0+0+0=0
Specifically, in the project shown in FIG.
KA1 = 330000 + 550000 + 60000 = 940000
MA1 = 0 + 0 + 10000 = 10000
KA2 = 320000 + 240000 + 0 = 560000
MA2 = 0 + 30000 + 0 = 30000
KA3 = 14,000 + 0 + 0 = 14,000
MA3 = 50000 + 0 + 0 = 50000
KA4 = 30000 + 0 + 0 = 30000
MA4 = 0 + 0 + 0 = 0

同様に、コスト計算部11は、読み出した同じコスト情報に対して、属性項目Bについても、確定コストおよび見込コストを、属性項目B内の属性値Bj(j=1、2、3)ごとに集計する。属性項目Bの場合は、次の式(3)、(4)のようにそれぞれ集計する。   Similarly, for the same cost information that has been read, the cost calculation unit 11 also sets a fixed cost and an estimated cost for each attribute value Bj (j = 1, 2, 3) in the attribute item B for the attribute item B. Tally. In the case of the attribute item B, totaling is performed as in the following formulas (3) and (4).

KBj=属性項目Bに属性値Bjを持つタスクの確定コストの合計値 …(3)
MBj=属性項目Bに属性値Bjを持つタスクの見込コストの合計値 …(4)
KBj = total value of fixed costs of tasks having attribute value Bj in attribute item B (3)
MBj = total value of expected cost of task having attribute value Bj in attribute item B (4)

具体的に、図7に示すプロジェクトにおいては、以下のようになる。
KB1=330000+320000+140000+30000=820000
MB1=0+0+50000+0=50000
KB2=550000+240000+0+0=790000
MB2=0+30000+0+0=30000
KB3=60000+0+0+0=60000
MB3=10000+0+0+0=10000
Specifically, in the project shown in FIG.
KB1 = 330000 + 320000 + 140000 + 30000 = 820000
MB1 = 0 + 0 + 50000 + 0 = 50000
KB2 = 550000 + 240000 + 0 + 0 = 790000
MB2 = 0 + 30000 + 0 + 0 = 30000
KB3 = 60000 + 0 + 0 + 0 = 60000
MB3 = 10000 + 0 + 0 + 0 = 10000

なお、属性項目AおよびBによるコスト集計は、各属性項目内の分類が異なるだけであり、集計対象のコスト情報は同一である。そのため、KAiの合計(ΣKAi)とKBjの合計(ΣKBj)は同一の値(1670000)をとり、MAiの合計(ΣMAi)とMBjの合計(ΣMBj)は同一の値(90000)をとる。   Note that the cost totalization by the attribute items A and B only differs in the classification within each attribute item, and the cost information to be aggregated is the same. Therefore, the sum of KAi (ΣKAi) and the sum of KBj (ΣKBj) have the same value (1670000), and the sum of MAi (ΣMAi) and the sum of MBj (ΣMBj) have the same value (90000).

つぎに、コスト計算部11は、完了済みタスクおよび実行中タスクの完了部分に対する予算コストを集計する(ステップS7)。ここでは、完了済みタスクは、タスクT11、タスクT12、タスクT21であり、実行中タスクは、タスクT13、タスクT22、タスクT31、タスクT41である。   Next, the cost calculation unit 11 aggregates the budget costs for the completed task and the completed portion of the task being executed (step S7). Here, the completed tasks are task T11, task T12, and task T21, and the running tasks are task T13, task T22, task T31, and task T41.

コスト計算部11は、ステップS6同様に、属性項目A、Bごとに集計する。このとき、確定コストおよび見込コストと対比すべき予算コストは、完了済みタスクおよび実行中タスクの完了部分に対する予算コスト(すなわち、使用済みであると予想されるコスト)であるので、進捗ベースを合わせるために、各タスクの予算コストに進捗率を乗じた値を用いる。具体的に、当該プロジェクトに関するタスク情報レコードを用いて、属性項目A、Bについて、それぞれ、次の式(5)、(6)のように集計する。   The cost calculation part 11 totals for every attribute item A and B similarly to step S6. At this time, the budget cost to be compared with the final cost and the expected cost is the budget cost for the completed portion of the completed task and the task being executed (that is, the cost that is expected to be used), so the progress base is adjusted. Therefore, a value obtained by multiplying the budget cost of each task by the progress rate is used. Specifically, using the task information record for the project, the attribute items A and B are tabulated as the following formulas (5) and (6), respectively.

YAi=属性項目Aに属性値Aiを持つタスクの(予算コスト×進捗率)の合計値
…(5)
YBj=属性項目Bに属性値Bjを持つタスクの(予算コスト×進捗率)の合計値
…(6)
YAi = total value of (budget cost × progress rate) for tasks having attribute value Ai in attribute item A
... (5)
YBj = total value of (budget cost × progress rate) for tasks having attribute value Bj in attribute item B
(6)

具体的に、図7に示すプロジェクトにおいては、以下のようになる。
YA1=300000×1+500000×1+200000×0.4=880000
YA2=300000×1+500000×0.5+200000×0=550000
YA3=300000×0.6+500000×0+200000×0=180000
YA4=300000×0.1+500000×0+200000×0=30000
YB1=300000×1+300000×1+300000×0.6
+300000×0.1=810000
YB2=500000×1+500000×0.5+500000×0
+500000×0=750000
YB3=200000×0.4+200000×0+200000×0
+200000×0=80000
Specifically, in the project shown in FIG.
YA1 = 300000 × 1 + 500000 × 1 + 200000 × 0.4 = 880000
YA2 = 300000 × 1 + 500000 × 0.5 + 200000 × 0 = 550000
YA3 = 300,000 × 0.6 + 500000 × 0 + 200000 × 0 = 18,000
YA4 = 300,000 × 0.1 + 500000 × 0 + 200000 × 0 = 30000
YB1 = 300000 × 1 + 300000 × 1 + 300000 × 0.6
+ 300000 × 0.1 = 810000
YB2 = 500000 × 1 + 500000 × 0.5 + 500000 × 0
+ 500000 × 0 = 750000
YB3 = 200000 × 0.4 + 200000 × 0 + 200000 × 0
+ 200000 × 0 = 80000

つぎに、コスト計算部11は、ステップS6、S7で求めた値を用いて、属性項目AおよびBの属性値別の効率指数を算出する(ステップS8)。それぞれの効率指数は、次の式(7)、(8)によって算出する。   Next, the cost calculation unit 11 calculates an efficiency index for each attribute value of the attribute items A and B using the values obtained in steps S6 and S7 (step S8). Each efficiency index is calculated by the following formulas (7) and (8).

SAi=属性項目Aの属性値Aiの効率指数=(KAi+MAi)/YAi…(7)
SBj=属性項目Aの属性値Bjの効率指数=(KBj+MBj)/YBj…(8)
SAi = efficiency index of attribute value Ai of attribute item A = (KAi + MAi) / YAi (7)
SBj = efficiency index of attribute value Bj of attribute item A = (KBj + MBj) / YBj (8)

具体的に、図7に示すプロジェクトにおいては、以下のようになる。
SA1=(KA1+MA1)/YA1=1.08
SA2=(KA2+MA2)/YA2=1.07
SA3=(KA3+MA3)/YA3=1.06
SA4=(KA4+MA4)/YA4=1
SB1=(KB1+MB1)/YB1=1.07
SB2=(KB2+MB2)/YB2=1.09
SB3=(KB3+MB3)/YB3=0.86
Specifically, in the project shown in FIG.
SA1 = (KA1 + MA1) /YA1=1.08
SA2 = (KA2 + MA2) /YA2=1.07
SA3 = (KA3 + MA3) /YA3=1.06
SA4 = (KA4 + MA4) / YA4 = 1
SB1 = (KB1 + MB1) /YB1=1.07
SB2 = (KB2 + MB2) /YB2=1.09
SB3 = (KB3 + MB3) /YB3=0.86

つぎに、コスト計算部11は、実行中のタスクについて、未完了部分に該当する予定コストを計算する(ステップS9)。完了済みおよび実行中(完了部分)のコスト効率と同等の効率でコストが発生すると想定し、予算コストに対して、属性項目Aおよび属性項目Bの属性値別の効率指数を乗じた値をコスト効率とする。具体的には、進捗率が1以外のタスクについて、以下の式(9)のように計算する。   Next, the cost calculation unit 11 calculates the scheduled cost corresponding to the uncompleted part for the task being executed (step S9). Assuming that costs are generated with the same cost efficiency as completed and being executed (completed part), the cost is calculated by multiplying the budget cost by the efficiency index for each attribute value of attribute item A and attribute item B. Efficiency. Specifically, for a task with a progress rate other than 1, the calculation is performed as in the following formula (9).

Pij=属性値Ai、属性値Bjを持つタスクTijの予定コスト
=タスクTijの予算コスト×(1−進捗率)×SAi×SBj …(9)
Pij = scheduled cost of task Tij having attribute value Ai and attribute value Bj
= Budget cost of task Tij × (1−progress rate) × SAi × SBj (9)

具体的に、図7に示すプロジェクトにおいては、以下のようになる。
P13=200000×(1−0.4)×SA1×SB3=113352.3
P22=500000×(1−0.5)×SA2×SB2=293212.1
P23=200000×(1−0)×SA2×SB3=187727.3
P31=300000×(1−0.6)×SA3×SB1=136049.4
P32=500000×(1−0)×SA3×SB2=577037
P33=200000×(1−0)×SA3×SB3=184722.2
P41=300000×(1−0.1)×SA4×SB1=290000
P42=500000×(1−0)×SA4×SB2=546666.7
P43=200000×(1−0)×SA4×SB3=175000
Specifically, in the project shown in FIG.
P13 = 200000 × (1-0.4) × SA1 × SB3 = 1133352.3
P22 = 500,000 * (1-0.5) * SA2 * SB2 = 293122.1
P23 = 200000 × (1-0) × SA2 × SB3 = 187727.3
P31 = 300,000 × (1-0.6) × SA3 × SB1 = 136049.4
P32 = 500000 × (1-0) × SA3 × SB2 = 577037
P33 = 200000 × (1-0) × SA3 × SB3 = 184722.2
P41 = 300,000 × (1-0.1) × SA4 × SB1 = 290000
P42 = 500,000 × (1-0) × SA4 × SB2 = 5466666.7
P43 = 200000 × (1-0) × SA4 × SB3 = 175000

そして、コスト計算部11は、算出した確定コスト、見込コスト、および予定コストをそれぞれ加算し、加算した総合計値をプロジェクトの最終コスト予測値とする(ステップS10)。具体的には以下の様に、確定コスト合計値K、見込コスト合計値M、および予定コスト合計値Pを求めて、これらの合計値を加算して、プロジェクト最終コスト予測値Tとする。   Then, the cost calculation unit 11 adds the calculated fixed cost, expected cost, and planned cost, respectively, and sets the added total value as the final cost predicted value of the project (step S10). Specifically, as shown below, a final confirmed cost total value K, an estimated cost total value M, and a planned cost total value P are obtained, and these total values are added to obtain a project final cost predicted value T.

確定コスト合計値K=ΣKAiまたはΣKBj …(10)
見込コスト合計値M=ΣMAiまたはΣMBj …(11)
予定コスト合計値P=ΣPij …(12)
プロジェクト最終コスト予測値T=K+M+P …(13)
Final cost total value K = ΣKAi or ΣKBj (10)
Total expected cost M = ΣMAi or ΣMBj (11)
Scheduled cost total value P = ΣPij (12)
Project final cost estimate T = K + M + P (13)

具体的に、図7に示すプロジェクトにおいては、以下のようになる。
確定コスト合計値K=ΣKAi=ΣKBj=1670000
見込コスト合計値M=ΣMAi=ΣMBj=90000
予定コスト合計値P=ΣPij=P13+P22+P23+P31+P32+P33
+P41+P42+P43=2503767
プロジェクト最終コスト予測値T=K+M+P=4263767
Specifically, in the project shown in FIG.
Final cost total value K = ΣKAi = ΣKBj = 16700000
Total expected cost M = ΣMAi = ΣMBj = 90000
Total scheduled cost P = ΣPij = P13 + P22 + P23 + P31 + P32 + P33
+ P41 + P42 + P43 = 2503767
Project final cost estimate T = K + M + P = 4263767

プロジェクトコスト予測装置は、読み出したプロジェクト基本情報とともに上記算出したプロジェクト最終コスト予測値を図示しない表示部等に出力する。なお、表示する際には、効率指数等の途中の計算過程の値も合わせて表示してもよい。   The project cost prediction apparatus outputs the calculated project final cost prediction value together with the read project basic information to a display unit (not shown). In addition, when displaying, the value of the calculation process in the middle, such as an efficiency index, may also be displayed.

これにより、プロジェクトコスト予測装置は、未着手または実行中(未完了部分)タスクに対する予定コストについて、類似する属性情報を持つ完了済みタスクおよび実行中(完了部分)タスクのコスト効率を適用することで、完了済みタスクおよび実行中(完了部分)タスクが与える未着手または実行中(未完了部分)タスクの影響範囲を、関連するタスクに限定することができる。   As a result, the project cost predicting apparatus applies the cost efficiency of the completed task and the executing (completed part) task having similar attribute information with respect to the planned cost for the unstarted or executing (uncompleted part) task. The influence range of the unstarted or executing (uncompleted part) task given by the completed task and the executing (completed part) task can be limited to related tasks.

具体的には、タスクT12(機能1、プログラム開発)で異常が発生していた場合、その影響はタスクT13(機能1、テスト)、タスクT22(機能2、プログラム開発)、タスクT32(機能3、プログラム開発)、タスクT42(機能4、プログラム開発)に及ぶが、タスクT23(機能2、テスト)、タスクT33(機能3、テスト)、タスクT43(機能4、テスト)には直接の影響は及ばない。   Specifically, if an abnormality has occurred in task T12 (function 1, program development), the effects are task T13 (function 1, test), task T22 (function 2, program development), task T32 (function 3). , Program development), task T42 (function 4, program development), but there is no direct impact on task T23 (function 2, test), task T33 (function 3, test), task T43 (function 4, test). It doesn't reach.

なお、ステップS3において、周辺の外部システムからコスト情報を取得したときに、取得したファイルにタスクが割り当てられていなかった場合には、別途、タスクIDを付与することも可能である。   In step S3, when cost information is acquired from peripheral external systems, if a task is not assigned to the acquired file, a task ID can be separately assigned.

図9は、タスク未割り当てのコスト情報を取得したときのタスクID入力処理を示すフローチャートである。まず、コスト情報取得部5は、周辺の外部システムからコスト情報を取得し(ステップS31)、取得したコスト情報にタスクIDが割り当てられていなかった場合には、当該コスト情報をタスク未割当情報記憶部7に記憶する(ステップS32)。   FIG. 9 is a flowchart showing task ID input processing when cost information not assigned to a task is acquired. First, the cost information acquisition unit 5 acquires cost information from peripheral external systems (step S31), and if no task ID is assigned to the acquired cost information, the cost information is stored in task unassigned information storage. Store in the unit 7 (step S32).

つぎに、タスク割当入力部8が、タスク未割当情報記憶部7から、タスクIDが割り当てられていなかったタスク未割り当てコスト情報を読み出し、外部からのタスクIDの割り当てを受け付けて、当該タスク未割り当てコスト情報にタスクIDを入力する(ステップS33)。そして、タスクIDが入力されたコスト情報をコスト情報記憶部6へ記憶する(ステップS34)。   Next, the task assignment input unit 8 reads out task unassigned cost information that has not been assigned a task ID from the task unassigned information storage unit 7, receives assignment of a task ID from the outside, and receives the task unassigned A task ID is input to the cost information (step S33). Then, the cost information to which the task ID is input is stored in the cost information storage unit 6 (step S34).

実運用上、プロジェクトに関係する各部門が自部門で発生したコストを管理するときの区分けが、必ずしもプロジェクトコストを管理するシステムと一致しない場合がある。このように、タスクIDが未割り当てのコスト情報についても、タスクIDを割り当てた後に通常の処理フローに戻すことができるため、発生したコスト情報のうちタスクが不明確なデータを破棄する事態を回避することができる。   In practice, the division when each department related to a project manages the cost generated in its own department may not always match the system that manages the project cost. In this way, cost information that has not been assigned a task ID can be returned to the normal processing flow after assigning a task ID, thus avoiding a situation in which data in which the task is unclear from among the generated cost information is avoided. can do.

以上説明したように、本実施の形態では、プロジェクトコスト予測装置は、未着手タスクおよび実行中(未完了部分)タスクの予定コストを予測する場合に、機能フェーズや作業工程によって分類できる種別ごとに、完了済みタスクおよび実行中(完了部分)タスクのコスト効率を求め、求めたコスト効率を用いて予測することとした。これにより、完了済みタスクおよび実行中(完了部分)タスクが与える未着手タスクおよび実行中(未完了部分)タスクの影響範囲を、関連するタスクに限定することができ、プロジェクト最終コスト予測を高い精度で行うことができる。   As described above, in the present embodiment, the project cost prediction device predicts the planned costs of unstarted tasks and running (unfinished parts) tasks for each type that can be classified according to functional phase or work process. The cost efficiency of the completed task and the task being executed (completed part) is obtained, and the estimated cost efficiency is used for prediction. This makes it possible to limit the impact of unfinished tasks and running (uncompleted parts) tasks given by completed tasks and running (completed parts) tasks to related tasks, and accurately predict project final costs. Can be done.

なお、図10は、本実施の形態にかかるプロジェクトコスト予測装置としての機能を備え、本実施の形態のプロジェクトコスト予測プログラムを実行可能な電子計算機の構成例を示す図である。   FIG. 10 is a diagram illustrating a configuration example of an electronic computer that has a function as a project cost prediction apparatus according to the present embodiment and can execute the project cost prediction program according to the present embodiment.

この電子計算機は、たとえば、CPUを含む制御ユニット101(上記コスト情報取得部5、タスク別コスト情報生成部9、コスト計算部11に相当)と、メモリユニット102(上記プロジェクト基本情報記憶部2、タスク情報記億部4、コスト情報記憶部6、タスク未割当情報記憶部7、タスク別コスト情報記憶部10に相当)と、表示ユニット103と、入力ユニット104(上記プロジェクト基本情報入力部1、タスク情報入力部3、タスク割当入力部8に相当)と、CD−ROMドライブユニット105と、ディスクユニット106と、外部I/Fユニット107と、を備え、これらの各ユニットは、それぞれシステムバスAを介して接続されている。   This electronic computer includes, for example, a control unit 101 including a CPU (corresponding to the cost information acquisition unit 5, the task-specific cost information generation unit 9, and the cost calculation unit 11) and a memory unit 102 (the project basic information storage unit 2, Task information storage unit 4, cost information storage unit 6, task unallocated information storage unit 7, task-specific cost information storage unit 10), display unit 103, input unit 104 (project basic information input unit 1, Task information input unit 3 and task allocation input unit 8), a CD-ROM drive unit 105, a disk unit 106, and an external I / F unit 107, each of which has a system bus A. Connected through.

図10において、制御ユニット101は、上記プロジェクトコスト予測プログラムを実行する。メモリユニット102は、RAM、ROM等の各種メモリを含み、上記制御ユニット101が実行すべきプログラム、処理の過程で得られた必要なデータ等を記憶する。表示ユニット103は、CRTやLCD(液晶表示パネル)等で構成され、電子計算機の使用者に対して各種画面を表示する。入力ユニット104は、キーボード、マウス等で構成され、電子計算機の使用者が、各種情報の入力を行うために使用する。また、図示のCD−ROM200には、本実施の形態の処理を記述したプロジェクトコスト予測プログラムが格納されている。   In FIG. 10, the control unit 101 executes the project cost prediction program. The memory unit 102 includes various memories such as RAM and ROM, and stores programs to be executed by the control unit 101, necessary data obtained in the course of processing, and the like. The display unit 103 is composed of a CRT, LCD (liquid crystal display panel), or the like, and displays various screens to the user of the electronic computer. The input unit 104 includes a keyboard, a mouse, and the like, and is used by a user of an electronic computer to input various information. The illustrated CD-ROM 200 stores a project cost prediction program describing the processing of the present embodiment.

ここで、上記プロジェクトコスト予測プログラムが実行可能な状態になるまでの電子計算機の動作例について説明する。まず、上記のように構成される電子計算機には、CD−ROMドライブユニット105にセットされたCD−ROM200から、プロジェクトコスト予測プログラムがディスクユニット106にインストールされる。そして、電子計算機の起動時またはプログラムの実行時に、ディスクユニット106から読み出されたプログラムがメモリユニット102に格納される。この状態で、制御ユニット101は、メモリユニット102に格納されたプログラムにしたがって、プロジェクトコスト予測処理を実行する。   Here, an operation example of the electronic computer until the project cost prediction program becomes executable will be described. First, in the electronic computer configured as described above, a project cost prediction program is installed in the disk unit 106 from the CD-ROM 200 set in the CD-ROM drive unit 105. Then, the program read from the disk unit 106 is stored in the memory unit 102 when the electronic computer is activated or when the program is executed. In this state, the control unit 101 executes project cost prediction processing according to the program stored in the memory unit 102.

なお、本実施の形態においては、CD−ROM200にて上記プロジェクトコスト予測プログラムを提供しているが、このプログラムの記録媒体は、これに限定されることなく、システムを構成するコンピュータに応じて、たとえば、フロッピー(登録商標)ディスク、DVD等の他の記録媒体を用いることも可能である。また、電子メール、インターネット等の伝送媒体により提供されたプログラムを用いることとしてもよい。   In the present embodiment, the project cost prediction program is provided by the CD-ROM 200. However, the recording medium of this program is not limited to this, and depending on the computer constituting the system, For example, other recording media such as a floppy (registered trademark) disk and a DVD may be used. Moreover, it is good also as using the program provided by transmission media, such as an email and the internet.

以上のように、本発明にかかるプロジェクトコスト予測装置は、プロジェクト管理に有用であり、特に、プロジェクトのコスト管理に適している。   As described above, the project cost prediction apparatus according to the present invention is useful for project management, and is particularly suitable for project cost management.

1 プロジェクト基本情報入力部
2 プロジェクト基本情報記憶部
3 タスク情報入力部
4 タスク情報記億部
5 コスト情報取得部
6 コスト情報記憶部
7 タスク未割当情報記憶部
8 タスク割当入力部
9 タスク別コスト情報生成部
10 タスク別コスト情報記憶部
11 コスト計算部
DESCRIPTION OF SYMBOLS 1 Project basic information input part 2 Project basic information storage part 3 Task information input part 4 Task information storage part 5 Cost information acquisition part 6 Cost information storage part 7 Task unallocation information storage part 8 Task allocation input part 9 Cost information according to task Generation unit 10 Cost information storage unit by task 11 Cost calculation unit

Claims (7)

機能フェーズまたは作業工程でタスクを分類可能なプロジェクトの最終コストを予測するプロジェクトコスト予測装置において、
プロジェクトIDとタスクIDとタスクの進捗率とタスクの予算とタスクの機能フェーズ種別とタスクの作業工程種別とを含むタスク情報を、タスクごとに記憶するためのタスク情報記憶手段と、
プロジェクトIDとタスクIDとコスト値と、当該コスト値が確定したコストである確定コストまたは現時点で確定されていないが将来的に確定されるコストである見込コストのいずれかを区分するコスト区分と、を含むコスト情報を、発生したコストごとに外部のシステムから取得するコスト情報取得手段と、
前記取得したコスト情報を記憶するためのコスト情報記憶手段と、
前記タスク情報記憶手段から同一のプロジェクトIDが記憶されたタスク情報を全て読み出し、前記コスト情報記憶手段から同一のプロジェクトIDが記憶されたコスト情報を全て読み出し、タスク情報ごとに、当該タスク情報のタスクIDと同一のタスクIDを含むコスト情報に記憶されているコスト値をコスト区分ごとに累積した確定コスト累積値および見込コスト累積値を追加することにより、タスク別コスト情報を生成するタスク別コスト情報生成手段と、
前記タスク別コスト情報を記憶するためのタスク別コスト情報記憶手段と、
前記タスク別コスト情報記憶手段からタスク別コスト情報を読み出し、確定コスト累積値と見込コスト累積値と、進捗率および予算を用いて算出した予測コストと、を加算することによりプロジェクトの最終コスト予測値を求めるコスト計算手段と、
を備えることを特徴とするプロジェクトコスト予測装置。
In a project cost prediction device that predicts the final cost of a project that can classify tasks in the functional phase or work process,
Task information storage means for storing task information including a project ID, task ID, task progress rate, task budget, task function phase type, and task work process type for each task;
A cost ID that classifies either the project ID, the task ID, the cost value, and a fixed cost that is a cost for which the cost value is fixed or an estimated cost that is not determined at the present time but is determined in the future; Cost information acquisition means for acquiring cost information including an external system for each generated cost,
Cost information storage means for storing the acquired cost information;
All the task information in which the same project ID is stored is read from the task information storage means, all the cost information in which the same project ID is stored is read from the cost information storage means, and the task of the task information for each task information Task-specific cost information that generates cost information for each task by adding a fixed cost cumulative value and an estimated cost cumulative value for each cost category that are stored in the cost information that includes the same task ID as the ID Generating means;
Task-specific cost information storage means for storing the task-specific cost information;
The task-specific cost information is read from the task-specific cost information storage means, and the final cost predicted value of the project is obtained by adding the determined cost cumulative value, the estimated cost cumulative value, and the predicted cost calculated using the progress rate and the budget. A cost calculation means for obtaining
A project cost prediction apparatus comprising:
前記コスト計算手段は、
前記タスク別コスト情報記憶手段から同一のプロジェクトIDが記憶されたタスク別コスト情報を全て読み出して、
タスクの機能フェーズ種別および作業工程種別ごとに、各種別に属するタスクのタスク別コスト情報に記憶された確定コスト累積値、見込コスト累積値、およびタスクの予算に進捗率を乗算した値、をそれぞれ累積加算した、属性値別確定コスト、属性値別見込コスト、および属性値別使用済予想コストを求め、
タスクの機能フェーズ種別および作業工程種別ごとに、算出した属性値別確定コストに属性値別見込コストを加算した値を属性値別使用済予想コストで除算した値を当該種別の効率指数として求め、
未完了タスクの未実施部分の予算に、当該タスクが属する機能フェーズ種別の効率指数と当該タスクが属する作業工程種別の効率指数を乗算して、未完了タスクの未実施部分の予測コストを求める処理を、全ての未完了タスクについて実行し、
タスクの機能フェーズ種別または作業工程種別のいずれか一方の種別において、種別ごとの属性値別確定コストおよび種別ごとの属性値別見込コストを加算した値に、全ての未完了タスクで求めた予測コストを加算することによりプロジェクトの最終コスト予測値を求める、
ことを特徴とする請求項1に記載のプロジェクトコスト予測装置。
The cost calculation means includes
Read all the cost information for each task in which the same project ID is stored from the cost information storage means for each task,
For each functional phase type and work process type of the task, the accumulated fixed cost value, the estimated cost accumulated value stored in the task-specific cost information of each task, and the task budget multiplied by the progress rate are accumulated. Calculate the finalized cost by attribute value, estimated cost by attribute value, and estimated used cost by attribute value.
For each functional phase type and work process type of the task, obtain a value obtained by dividing the calculated estimated cost for each attribute value by the estimated cost for each attribute value by the estimated expected cost for each attribute value as the efficiency index for that type,
Processing to calculate the estimated cost of the incomplete part of the incomplete task by multiplying the budget of the incomplete part of the incomplete task by the efficiency index of the function phase type to which the task belongs and the efficiency index of the work process type to which the task belongs For all incomplete tasks,
Predicted cost obtained for all incomplete tasks to the value obtained by adding the fixed cost for each attribute value and the estimated cost for each attribute value for each type in either the functional phase type or work process type of the task The final cost estimate of the project is obtained by adding
The project cost prediction apparatus according to claim 1, wherein:
さらに、
タスクIDが未割り当てのコスト情報を記憶するためのタスク未割当情報記憶手段と、
タスクIDの入力を外部から受け付けて、タスクIDが未割り当てのコスト情報にタスクIDを割り当てるタスク割当入力手段と、
を備え、
前記コスト情報取得手段は、取得したコスト情報のうちタスクIDが未割り当てのコスト情報を前記タスク未割当情報記憶手段へ記憶し、
前記タスク割当入力手段は、前記タスク未割当情報記憶手段からタスクIDが未割り当てのコスト情報を読み出して、当該読み出したコスト情報にタスクIDを割り当てて、当該タスクIDを割り当てたコスト情報を前記コスト情報記憶手段に記憶する、
ことを特徴とする請求項1または2に記載のプロジェクトコスト予測装置。
further,
Task unassigned information storage means for storing cost information to which task IDs are not assigned;
A task assignment input means for accepting an input of a task ID from the outside and assigning a task ID to cost information to which no task ID is assigned;
With
The cost information acquisition unit stores the cost information in which the task ID is not allocated among the acquired cost information in the task unallocation information storage unit,
The task assignment input unit reads cost information with no task ID assigned from the task unassigned information storage unit, assigns a task ID to the read cost information, and sets the cost information with the task ID assigned to the cost Memorize in information storage means,
The project cost prediction apparatus according to claim 1 or 2, characterized in that
機能フェーズまたは作業工程でタスクを分類可能なプロジェクトの最終コストを予測するプロジェクトコスト予測装置におけるプロジェクトコスト予測方法であって、
前記プロジェクトコスト予測装置が、
プロジェクトIDとタスクIDとタスクの進捗率とタスクの予算とタスクの機能フェーズ種別とタスクの作業工程種別とを含むタスク情報を、タスクごとに記憶するためのタスク情報記憶手段と、
プロジェクトIDとタスクIDとコスト値と、当該コスト値が確定したコストである確定コストまたは現時点で確定されていないが将来的に確定されるコストである見込コストのいずれかを区分するコスト区分と、を含むコスト情報を、発生したコストごとに記憶するためのコスト情報記憶手段と、
前記タスク情報に、当該タスクと同一タスクIDを持つコスト情報に記憶されているコスト値をコスト区分ごとに累積した確定コスト累積値および見込コスト累積値を追加したタスク別コスト情報を記憶するためのタスク別コスト情報記憶手段と、
を備える場合に、
外部のシステムから取得したコスト情報を前記コスト情報記憶手段に記憶するコスト情報取得ステップと、
前記タスク情報記憶手段から同一のプロジェクトIDが記憶されたタスク情報を全て読み出し、前記コスト情報記憶手段から同一のプロジェクトIDが記憶されたコスト情報を全て読み出し、タスク情報ごとに、当該タスク情報のタスクIDと同一のタスクIDを含むコスト情報に記憶されているコスト値をコスト区分ごとに累積した確定コスト累積値および見込コスト累積値を追加することによりタスク別コスト情報を生成し、生成したタスク別コスト情報を前記タスク別コスト情報記憶手段に記憶するタスク別コスト情報生成ステップと、
前記タスク別コスト情報記憶手段からタスク別コスト情報を読み出し、確定コスト累積値と見込コスト累積値と、進捗率および予算を用いて算出した予測コストと、を加算することによりプロジェクトの最終コスト予測値を求めるコスト計算ステップと、
を含むことを特徴とするプロジェクトコスト予測方法。
A project cost prediction method in a project cost prediction device for predicting a final cost of a project that can classify tasks in a functional phase or a work process,
The project cost prediction device is
Task information storage means for storing task information including a project ID, task ID, task progress rate, task budget, task function phase type, and task work process type for each task;
A cost ID that classifies either the project ID, the task ID, the cost value, and a fixed cost that is a cost for which the cost value is fixed or an estimated cost that is not determined at the present time but is determined in the future; Cost information storage means for storing cost information including each cost that has occurred,
For storing task-specific cost information in which a fixed cost cumulative value and an estimated cost cumulative value obtained by accumulating the cost value stored in the cost information having the same task ID as the task for each cost category are added to the task information. Cost information storage means for each task;
If you have
A cost information acquisition step of storing cost information acquired from an external system in the cost information storage means;
All the task information in which the same project ID is stored is read from the task information storage means, all the cost information in which the same project ID is stored is read from the cost information storage means, and the task of the task information for each task information Generates cost information for each task by adding a fixed cost accumulation value and an estimated cost accumulation value for each cost category that are stored in the cost information that includes the same task ID as the ID, and for each generated task A cost information generation step by task for storing cost information in the cost information storage means by task;
The task-specific cost information is read from the task-specific cost information storage means, and the final cost predicted value of the project is obtained by adding the determined cost cumulative value, the estimated cost cumulative value, and the predicted cost calculated using the progress rate and the budget. A cost calculation step for
A project cost prediction method characterized by including:
前記コスト計算ステップでは、
前記タスク別コスト情報記憶手段から同一のプロジェクトIDが記憶されたタスク別コスト情報を全て読み出して、
タスクの機能フェーズ種別および作業工程種別ごとに、各種別に属するタスクのタスク別コスト情報に記憶された確定コスト累積値、見込コスト累積値、およびタスクの予算に進捗率を乗算した値、をそれぞれ累積加算した、属性値別確定コスト、属性値別見込コスト、および属性値別使用済予想コストを求め、
タスクの機能フェーズ種別および作業工程種別ごとに、算出した属性値別確定コストに属性値別見込コストを加算した値を属性値別使用済予想コストで除算した値を当該種別の効率指数として求め、
未完了タスクの未実施部分の予算に、当該タスクが属する機能フェーズ種別の効率指数と当該タスクが属する作業工程種別の効率指数を乗算して、未完了タスクの未実施部分の予測コストを求める処理を、全ての未完了タスクについて実行し、
タスクの機能フェーズ種別または作業工程種別のいずれか一方の種別において、種別ごとの属性値別確定コストおよび種別ごとの属性値別見込コストを加算した値に、全ての未完了タスクで求めた予測コストを加算することによりプロジェクトの最終コスト予測値を求める、
ことを特徴とする請求項4に記載のプロジェクトコスト予測方法。
In the cost calculation step,
Read all the cost information for each task in which the same project ID is stored from the cost information storage means for each task,
For each functional phase type and work process type of the task, the accumulated fixed cost value, the estimated cost accumulated value stored in the task-specific cost information of each task, and the task budget multiplied by the progress rate are accumulated. Calculate the finalized cost by attribute value, estimated cost by attribute value, and estimated used cost by attribute value.
For each functional phase type and work process type of the task, obtain a value obtained by dividing the calculated estimated cost for each attribute value by the estimated cost for each attribute value by the estimated expected cost for each attribute value as the efficiency index for that type,
Processing to calculate the estimated cost of the incomplete part of the incomplete task by multiplying the budget of the incomplete part of the incomplete task by the efficiency index of the function phase type to which the task belongs and the efficiency index of the work process type to which the task belongs For all incomplete tasks,
Predicted cost obtained for all incomplete tasks to the value obtained by adding the fixed cost for each attribute value and the estimated cost for each attribute value for each type in either the functional phase type or work process type of the task The final cost estimate of the project is obtained by adding
The project cost prediction method according to claim 4, wherein:
前記プロジェクトコスト予測装置が、さらに、
タスクIDが未割り当てのコスト情報を記憶するためのタスク未割当情報記憶手段、
を備え、
前記コスト情報取得ステップでは、
取得したコスト情報にタスクIDが未割り当てのコスト情報があった場合、
タスクIDが未割り当てのコスト情報を前記タスク未割当情報記憶手段へ記憶し、
前記タスク未割当情報記憶手段からタスクIDが未割り当てのコスト情報を読み出して、当該読み出したコスト情報にタスクIDを割り当てて、当該タスクIDを割り当てたコスト情報を前記コスト情報記憶手段に記憶する、
ことを特徴とする請求項4または5に記載のプロジェクトコスト予測方法。
The project cost prediction device further includes:
Task unassigned information storage means for storing cost information to which task IDs are not assigned;
With
In the cost information acquisition step,
If there is cost information with no task ID assigned to the acquired cost information,
Storing cost information with unassigned task ID in the task unassigned information storage means;
Reads cost information with no task ID assigned from the task unassigned information storage means, assigns a task ID to the read cost information, and stores the cost information assigned the task ID in the cost information storage means,
6. The project cost prediction method according to claim 4, wherein the project cost is predicted.
請求項4、5または6に記載のプロジェクトコスト予測方法をコンピュータに実行させることを特徴とするプロジェクトコスト予測プログラム。   A project cost prediction program that causes a computer to execute the project cost prediction method according to claim 4, 5 or 6.
JP2010134390A 2010-06-11 2010-06-11 Project cost prediction apparatus, project cost prediction method, and project cost prediction program Pending JP2011258139A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010134390A JP2011258139A (en) 2010-06-11 2010-06-11 Project cost prediction apparatus, project cost prediction method, and project cost prediction program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010134390A JP2011258139A (en) 2010-06-11 2010-06-11 Project cost prediction apparatus, project cost prediction method, and project cost prediction program

Publications (1)

Publication Number Publication Date
JP2011258139A true JP2011258139A (en) 2011-12-22

Family

ID=45474217

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010134390A Pending JP2011258139A (en) 2010-06-11 2010-06-11 Project cost prediction apparatus, project cost prediction method, and project cost prediction program

Country Status (1)

Country Link
JP (1) JP2011258139A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004220122A (en) * 2003-01-09 2004-08-05 Fujitsu Ltd Budget execution management method and budget execution management program
JP2007018163A (en) * 2005-07-06 2007-01-25 Ns Solutions Corp Progress management device
JP2009157489A (en) * 2007-12-25 2009-07-16 Canon Marketing Japan Inc Project progress management device and its control method, project progress management system, program and recording medium with the program recorded

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004220122A (en) * 2003-01-09 2004-08-05 Fujitsu Ltd Budget execution management method and budget execution management program
JP2007018163A (en) * 2005-07-06 2007-01-25 Ns Solutions Corp Progress management device
JP2009157489A (en) * 2007-12-25 2009-07-16 Canon Marketing Japan Inc Project progress management device and its control method, project progress management system, program and recording medium with the program recorded

Similar Documents

Publication Publication Date Title
Hanna et al. Quantitative definition of projects impacted by change orders
JP2011134268A (en) Apparatus and method for processing information, and computer program
JP4764490B2 (en) User evaluation device according to hardware usage
Raghuvanshi et al. A time-variant fault detection software reliability model
WO2012063589A1 (en) Investment planning device, investment planning method, and investment planning program
JP5881336B2 (en) Manufacturing cost management system and management method
JP7393244B2 (en) Time series data prediction device and time series data prediction method
JP5351841B2 (en) Exchange effect evaluation apparatus, exchange effect evaluation method, and exchange effect evaluation program
WO2020157927A1 (en) Diagnosis system and diagnosis method
JP6395852B2 (en) Business situation management system and business situation management method
JP2016062382A (en) Sales work support system and sales work support method
JP5652047B2 (en) Information processing apparatus and information processing program
Antsev et al. Management mechanism for continuous improvement of production processes using quality management methods
JP2012238049A (en) Project cost prediction device, project cost prediction method, and project cost prediction program
JP2011258139A (en) Project cost prediction apparatus, project cost prediction method, and project cost prediction program
JP5579526B2 (en) Incentive determination method, program and system
JP2016532949A (en) System and method for deriving critical change attributes from data signals that have been selected and analyzed over a period of time to predict future changes in conventional predictors
JP7218140B2 (en) Simulation device and simulation method
JP6695298B2 (en) Order control device
WO2023042419A1 (en) Information presentation device, information presentation method, and information presentation program
JP2018190187A (en) Work schedule calculating program, work schedule calculating method and information processing device
JP2018150170A (en) Information processing system, information processing method and program
Daclin et al. Product Development Plan Monitoring: Towards a Business Process Digital Twin
JP7308338B1 (en) Business support device, business support method, and business support program
JP2019204180A (en) Information processing apparatus and program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130314

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131224

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140107

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20140715