JP2011111849A - Method of constructing mass concrete structure - Google Patents

Method of constructing mass concrete structure Download PDF

Info

Publication number
JP2011111849A
JP2011111849A JP2009271474A JP2009271474A JP2011111849A JP 2011111849 A JP2011111849 A JP 2011111849A JP 2009271474 A JP2009271474 A JP 2009271474A JP 2009271474 A JP2009271474 A JP 2009271474A JP 2011111849 A JP2011111849 A JP 2011111849A
Authority
JP
Japan
Prior art keywords
concrete structure
concrete
temperature
new
heating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009271474A
Other languages
Japanese (ja)
Other versions
JP5308316B2 (en
Inventor
Shigechika Miyajima
滋近 宮島
Takahiro Yoshizaki
貴博 吉崎
Fusao Yamamoto
富佐雄 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IDOWR ENGINEERING KK
Ministry Of Land Infrastructure & Transport Hokkaido Regional Development Bureau
Original Assignee
IDOWR ENGINEERING KK
Ministry Of Land Infrastructure & Transport Hokkaido Regional Development Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IDOWR ENGINEERING KK, Ministry Of Land Infrastructure & Transport Hokkaido Regional Development Bureau filed Critical IDOWR ENGINEERING KK
Priority to JP2009271474A priority Critical patent/JP5308316B2/en
Publication of JP2011111849A publication Critical patent/JP2011111849A/en
Application granted granted Critical
Publication of JP5308316B2 publication Critical patent/JP5308316B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method of constructing a mass concrete structure capable of restraining stress/strain generated on the surface layer thereof so as to restrain the occurrence of cracks on its surface. <P>SOLUTION: In the construction method of the mass concrete structure 1 wherein concrete is sequentially cast one lift by one lift from below so as to construct a plurality of concrete layers 2 in a vertical direction, the concrete layer 2 located at least in the uppermost part out of a plurality of the old cast concrete layers 2 is heated during the down period of its casting thereby alleviating a difference in temperature between the surface layer 4 and the inner layers 5 of an old cast concrete structure 3 consisting of a plurality of the old cast concrete layers 2, and further alleviating a difference in temperature between the surface layer 4 of the old cast concrete structure 3 and the inner layers of a new concrete structure which is newly cast on the top thereof. <P>COPYRIGHT: (C)2011,JPO&amp;INPIT

Description

本発明は、マスコンクリート構造体の構築方法に関する。   The present invention relates to a method for constructing a mass concrete structure.

ダム堤体や橋梁の橋脚部に用いられるマスコンクリート構造体は、下部から例えば1〜2m程度の高さの1リフトごとにコンクリートを順次打設して上下方向に複数のコンクリート層を形成する工法によって構築されている。   Mass concrete structure used for dam dam bodies and bridge piers is a method of forming multiple concrete layers in the vertical direction by placing concrete sequentially from the bottom for each lift of about 1 to 2 meters in height, for example. Is built by.

ところで、近年、既存のダム堤体(旧堤体)に新堤体コンクリートを腹付けして、嵩上げする再開発工事が行われることがあるが、この新堤体コンクリートも体積の大きいマスコンクリート構造体であるので、所定高さの1リフトごとにコンクリートを順次打設する工法が採用されている。   By the way, in recent years, redevelopment construction is sometimes carried out to raise the bulk of the existing dam body (old bank body) with new levee body concrete, but this new dam body concrete is also a mass concrete structure with a large volume. For this reason, a construction method in which concrete is sequentially placed for each lift of a predetermined height is employed.

以上のようなマスコンクリート構造体を積雪量の多い寒冷地で構築する場合、越冬によるコンクリートの打設休止期間を設けなければならないことがある。この打設休止期間では、図13に示すように、新堤体コンクリート100の内層部101がコンクリートの水和反応によって温度上昇するのに対して、表層部102が外気によって冷却されるので、内層部101と表層部102との温度差が大きくなり、応力ひずみが発生する。この応力ひずみは、新堤体コンクリート100の上端と、旧堤体110との接合部103に集中して発生し、この接合部103にひび割れが発生してしまうことがあった。このひび割れが接合面に沿って伸展すると、新旧堤体の一体化を阻害する要因となる可能性があった。   When constructing a mass concrete structure as described above in a cold region with a large amount of snow, it may be necessary to provide a concrete placement stoppage period due to wintering. In this placing suspension period, as shown in FIG. 13, the temperature of the inner layer portion 101 of the new leve body concrete 100 rises due to the hydration reaction of the concrete, whereas the surface layer portion 102 is cooled by the outside air. The temperature difference between 101 and the surface layer portion 102 becomes large, and stress strain occurs. This stress strain is concentrated at the joint 103 between the upper end of the new dam body concrete 100 and the old dam body 110, and the joint 103 may be cracked. If these cracks extend along the joint surface, there is a possibility that the integration of the old and new levee bodies may be hindered.

そこで、新堤体コンクリート100の内層部101と表層部102との温度差を小さくするために、従来より、新堤体コンクリート100の表面に断熱養生マットを敷設して表層部の温度低下を抑制する対策や、打設するコンクリートの温度を予め低くするプレクーリング(例えば、特許文献1参照)を行うといった対策が施されていた。   Therefore, in order to reduce the temperature difference between the inner layer portion 101 and the surface layer portion 102 of the new levee body concrete 100, conventionally, a measure to suppress the temperature drop of the surface layer portion by laying a heat insulating curing mat on the surface of the new dam body concrete 100 In addition, countermeasures have been taken such as precooling (for example, see Patent Document 1) for lowering the temperature of concrete to be placed in advance.

特開2007−130971号公報JP 2007-130971 A

しかしながら、前記した断熱養生マットを敷設する対策では、表面部の温度低下をある程度抑えることができたが、接合部103にはひび割れが発生して伸展してしまう可能性があった。また、前記したコンクリートをプレクーリングする対策では、夏期のコンクリート温度を5℃程度低下させることができるが、冬期の越冬面(表面部)と内部との温度差については殆んど変化なく、越冬時の応力ひずみの発生の抑制に対しての効果は小さいと考えられる。   However, the above-described measures for laying the heat-insulating curing mat can suppress the temperature drop of the surface portion to some extent, but there is a possibility that the joint portion 103 is cracked and extended. In addition, the above-mentioned measures for precooling concrete can reduce the concrete temperature in summer by about 5 ° C, but there is almost no change in the temperature difference between the wintering surface (surface part) and the inside in winter. It is considered that the effect on suppressing the occurrence of stress strain at the time is small.

そこで、本発明は前記の問題を解決すべく案出されたものであって、マスコンクリート構造体の表層部に発生する応力ひずみを抑制して、表面のひび割れの発生を抑えることができるマスコンクリート構造体の構築方法を提供することを課題とする。   Accordingly, the present invention has been devised to solve the above-described problem, and is capable of suppressing the occurrence of surface cracks by suppressing the stress strain generated in the surface layer portion of the mass concrete structure. It is an object to provide a method for constructing a structure.

前記課題を解決するため、請求項1に係る発明は、下部から1リフトごとにコンクリートを順次打設して上下方向に複数のコンクリート層を構築するマスコンクリート構造体の構築方法において、打設済の複数の前記コンクリート層のうち、少なくとも最上部に位置する前記コンクリート層を打設休止期間中に加熱することで、打設済の複数の前記コンクリート層からなる打設済コンクリート構造体の表層部と内層部との温度差を緩和することを特徴とするマスコンクリート構造体の構築方法である。   In order to solve the above-mentioned problem, the invention according to claim 1 is in a construction method of a mass concrete structure in which concrete is sequentially placed from the lower portion for each lift to construct a plurality of concrete layers in the vertical direction. Of the plurality of concrete layers, the surface layer portion of the placed concrete structure composed of the plurality of concrete layers already placed by heating the concrete layer located at least at the uppermost part during the placement suspension period This is a method for constructing a mass concrete structure characterized in that the temperature difference between the inner layer and the inner layer is reduced.

このような方法によれば、少なくとも最上部に位置するコンクリート層を打設休止期間中に加熱することで、打設済コンクリート構造体の表層部と内層部との温度差を効率的に緩和することができるので、マスコンクリート構造体の表層部に発生する応力ひずみを抑制して、表面のひび割れの発生を抑えることができる。   According to such a method, the temperature difference between the surface layer portion and the inner layer portion of the placed concrete structure is efficiently reduced by heating at least the concrete layer positioned at the uppermost part during the placing suspension period. Therefore, the stress strain generated in the surface layer portion of the mass concrete structure can be suppressed, and the occurrence of surface cracks can be suppressed.

請求項2に係る発明は、下部から1リフトごとにコンクリートを順次打設して上下方向に複数のコンクリート層を構築するマスコンクリート構造体の構築方法において、打設済の複数の前記コンクリート層のうち、少なくとも最上部に位置する前記コンクリート層を、打設済の複数の前記コンクリート層からなる打設済コンクリート構造体の表層部と内層部との温度差を緩和するとともに前記打設済コンクリート構造体の前記表層部とその上部に新たに増打ちされる新設コンクリート構造体の内層部との温度差を緩和するように、打設休止期間中に加熱することを特徴とするマスコンクリート構造体の構築方法である。   The invention according to claim 2 is a construction method of a mass concrete structure in which concrete is sequentially placed from the lower portion for each lift to construct a plurality of concrete layers in the vertical direction. Among them, at least the concrete layer positioned at the uppermost portion is used to alleviate the temperature difference between the surface layer portion and the inner layer portion of the cast concrete structure composed of the plurality of cast concrete layers, and the cast concrete structure. The mass concrete structure is heated during the suspension period so as to alleviate the temperature difference between the surface layer part of the body and the inner layer part of the new concrete structure newly added to the upper part thereof. It is a construction method.

このような方法によれば、少なくとも最上部に位置するコンクリート層を打設休止期間中に加熱することで、打設済コンクリート構造体の表層部と内層部との温度差を効率的に緩和することができるので、マスコンクリート構造体の表層部に発生する応力ひずみを抑制して、表面のひび割れの発生を抑えることができる。さらに、前記の加熱によって、打設済コンクリート構造体の表層部と新設コンクリート構造体の内層部との温度差を効率的に緩和することができるので、打設済コンクリート構造体と新設コンクリート構造体との接合部に発生する応力ひずみを抑制して、その部分のひび割れの発生も抑えることができる。   According to such a method, the temperature difference between the surface layer portion and the inner layer portion of the cast concrete structure is efficiently reduced by heating at least the concrete layer located at the uppermost part during the casting pause period. Therefore, the stress strain generated in the surface layer portion of the mass concrete structure can be suppressed, and the occurrence of surface cracks can be suppressed. Furthermore, since the temperature difference between the surface layer portion of the cast concrete structure and the inner layer portion of the new concrete structure can be effectively reduced by the heating, the cast concrete structure and the new concrete structure can be reduced. It is also possible to suppress the stress strain generated at the joint portion and to prevent the occurrence of cracks at that portion.

請求項3に係る発明は、前記コンクリート層の加熱は、前記コンクリート層内に熱媒体流路を形成し、前記熱媒体流路内に熱媒体を流すことで行われることを特徴とする請求項1または請求項2に記載のマスコンクリート構造体の構築方法である。   The invention according to claim 3 is characterized in that the heating of the concrete layer is performed by forming a heat medium flow path in the concrete layer and flowing the heat medium in the heat medium flow path. It is the construction method of the mass concrete structure of Claim 1 or Claim 2.

このような方法によれば、簡単な構成で容易にコンクリート層内を効率的に加熱することができる。   According to such a method, the inside of the concrete layer can be efficiently heated easily with a simple configuration.

本発明によれば、マスコンクリート構造体の表層部に発生する応力ひずみを抑制して、表面のひび割れの発生を抑えることができるといった優れた効果を発揮する。   ADVANTAGE OF THE INVENTION According to this invention, the outstanding effect that the stress distortion generate | occur | produced in the surface layer part of a mass concrete structure can be suppressed, and generation | occurrence | production of the crack of a surface can be suppressed is exhibited.

本発明の実施形態に係るマスコンクリート構造体の構築方法の1年目の施工状態を示した断面図である。It is sectional drawing which showed the construction state of the 1st year of the construction method of the mass concrete structure which concerns on embodiment of this invention. 本発明の実施形態に係るマスコンクリート構造体の構築方法の2年目の施工状態を示した断面図である。It is sectional drawing which showed the construction state of the 2nd year of the construction method of the mass concrete structure which concerns on embodiment of this invention. 本発明の実施形態に係るマスコンクリート構造体の構築方法の3年目の施工状態を示した断面図である。It is sectional drawing which showed the construction state of the 3rd year of the construction method of the mass concrete structure which concerns on embodiment of this invention. (a)は、1リフト分のコンクリート層を加熱する構造を示した断面図、(b)は、2リフト分のコンクリート層を加熱する構造を示した断面図、(c)は、3リフト分のコンクリート層を加熱する構造を示した断面図である。(A) is a sectional view showing a structure for heating a concrete layer for one lift, (b) is a sectional view for showing a structure for heating a concrete layer for two lifts, and (c) is for three lifts. It is sectional drawing which showed the structure which heats the concrete layer of. 加熱するリフト数と新堤体コンクリート構造体の最低温度との関係を示したグラフである。It is the graph which showed the relationship between the number of lifts to heat, and the minimum temperature of a new dam body concrete structure. 加熱するリフト数と新堤体コンクリート構造体の最大ひずみとの関係を示したグラフである。It is the graph which showed the relationship between the number of lifts to heat and the maximum distortion of a new dam body concrete structure. (a)は、表面から1リフト分下部のコンクリート層を加熱した状態を示した断面図、(b)は、表面からハーフリフト分下部のコンクリート層を加熱した状態を示した断面図である。(A) is sectional drawing which showed the state which heated the concrete layer of the lower part by 1 lift from the surface, (b) is sectional drawing which showed the state which heated the concrete layer of the half lift part from the surface. 加熱する温水の通水温度と新堤体コンクリート構造体の最低温度との関係を示したグラフである。It is the graph which showed the relationship between the flowing temperature of the warm water to heat, and the minimum temperature of a new dam body concrete structure. 加熱する温水の通水温度と新堤体コンクリート構造体の最大ひずみとの関係を示したグラフである。It is the graph which showed the relationship between the flow temperature of the warm water to heat, and the maximum distortion of a new dam body concrete structure. 本発明の実施形態に係るマスコンクリート構造体の構築方法によって構築されたダム堤体の1年目の越冬時の状態を示した断面図であって、(a)は温度分布図、(b)はひずみ分布図である。It is sectional drawing which showed the state at the time of the wintering of the 1st year of the dam dam body constructed | assembled by the construction method of the mass concrete structure which concerns on embodiment of this invention, (a) is a temperature distribution figure, (b) Is a strain distribution diagram. 本発明の実施形態に係るマスコンクリート構造体の構築方法によって構築されたダム堤体の2年目の越冬時の状態を示した断面図であって、(a)は温度分布図、(b)はひずみ分布図である。It is sectional drawing which showed the state at the time of the wintering of the 2nd year of the dam dam body constructed | assembled by the construction method of the mass concrete structure which concerns on embodiment of this invention, Comprising: (a) is a temperature distribution figure, (b) Is a strain distribution diagram. 本発明の実施形態に係るマスコンクリート構造体の構築方法によって構築されたダム堤体の3年目の越冬時の状態を示した断面図であって、(a)は温度分布図、(b)はひずみ分布図である。It is sectional drawing which showed the state at the time of the wintering of the 3rd year of the dam dam body constructed | assembled by the construction method of the mass concrete structure which concerns on embodiment of this invention, Comprising: (a) is a temperature distribution figure, (b) Is a strain distribution diagram. 従来のマスコンクリート構造体の構築方法によって構築されたダム堤体の越冬時の状態を示した断面図である。It is sectional drawing which showed the state at the time of wintering of the dam dam body constructed | assembled by the construction method of the conventional mass concrete structure.

本発明に係るマスコンクリート構造体の構築方法を実施するための形態について、添付図面を参照しながら詳細に説明する。なお、本実施形態では、積雪量の多い寒冷地で、既設のダム堤体(旧堤体)に新堤体コンクリートを腹付けしてダム堤体を嵩上げする再開発工事における新堤体コンクリート構造体をマスコンクリート構造体の一例として挙げて、その構築方向を説明する。   The form for implementing the construction method of the mass concrete structure which concerns on this invention is demonstrated in detail, referring an accompanying drawing. In this embodiment, the new dam body concrete structure in the redevelopment work that raises the dam dam body by adding the new dam body concrete to the existing dam body (old dam body) in a cold region with a lot of snow. The construction direction will be described as an example of a mass concrete structure.

図1乃至図3に示すように、旧堤体50の傾斜面51に沿って形成される新堤体コンクリート構造体(マスコンクリート構造体)1は、下部から1リフトごとにコンクリートを順次打設して上下方向に複数のコンクリート層2を構築することで形成される。1リフトとは、コンクリート層2の一層分の打設高さ(厚さ)を示し、例えば、1.5mに設定されている。積雪量の多い寒冷地では、越冬によるコンクリートの打設休止期間(例えば、11月から翌年3月まで)が設けられる。   As shown in FIGS. 1 to 3, the new levee concrete structure (mass concrete structure) 1 formed along the inclined surface 51 of the old levee body 50 is sequentially cast from the lower portion for each lift. Thus, it is formed by constructing a plurality of concrete layers 2 in the vertical direction. One lift indicates the placement height (thickness) of one layer of the concrete layer 2, and is set to 1.5 m, for example. In cold regions where there is a lot of snow, concrete is suspended during wintering (for example, from November to March of the following year).

ところで、本発明は、図1及び図2に示すように、打設済の複数のコンクリート層2のうち、少なくとも打設休止期間中(以下「越冬中」と言う場合がある)に最上部に位置するコンクリート層2を、打設休止期間中に加熱することで、打設済の複数のコンクリート層2,2…からなる打設済コンクリート構造体3の表層部4と内層部5との温度差を緩和することを特徴とする。   By the way, as shown in FIGS. 1 and 2, the present invention is at the top of the plurality of concrete layers 2 that have been placed at least during the placement suspension period (hereinafter sometimes referred to as “over wintering”). The temperature of the surface layer part 4 and the inner layer part 5 of the cast-in concrete structure 3 composed of a plurality of cast-in concrete layers 2, 2... By heating the positioned concrete layer 2 during the placing pause period. It is characterized by alleviating the difference.

コンクリート層2の加熱は、図4の(a)に示すように、コンクリート層2内に熱媒体流路10を形成し、熱媒体流路10内に熱媒体を流すことで行われる。熱媒体流路10は、最上部に位置するコンクリート層2とその下側に位置するコンクリート層2との間に敷設された配管にて構成されている。熱媒体流路10は、例えば、1.5mピッチで蛇行して配置されており、内部に熱媒体として所定の温度に加熱された温水が通水される。熱媒体流路10を形成するに際しては、最上部の下側に位置するコンクリート層2を構築した後に、その表面に配管を敷設し、この配管を覆うようにコンクリートを打設して最上部のコンクリート層2を構築する。これによって、熱媒体流路10が、打設済コンクリート構造体3の表層部4に内蔵されて配置されることとなる。なお、コンクリート層2の加熱は、前記のように熱媒体流路10内に熱媒体を流す方法に限定されるものではなく、流体を用いずに電熱線や触媒等で加熱する等、他の方法で行うようにしてもよい。   The heating of the concrete layer 2 is performed by forming the heat medium flow path 10 in the concrete layer 2 and flowing the heat medium in the heat medium flow path 10 as shown in FIG. The heat medium flow path 10 is constituted by a pipe laid between the concrete layer 2 located at the uppermost part and the concrete layer 2 located below the concrete layer 2. For example, the heat medium flow path 10 is arranged meandering at a pitch of 1.5 m, and hot water heated to a predetermined temperature as a heat medium is passed through the heat medium flow path 10. When forming the heat medium flow path 10, after the concrete layer 2 located on the lower side of the uppermost part is constructed, a pipe is laid on the surface, and concrete is placed so as to cover the pipe, and the uppermost part is placed. The concrete layer 2 is constructed. As a result, the heat medium flow path 10 is built in and disposed in the surface layer portion 4 of the placed concrete structure 3. The heating of the concrete layer 2 is not limited to the method of flowing the heat medium in the heat medium flow path 10 as described above, and other methods such as heating with a heating wire or a catalyst without using a fluid. You may make it carry out by the method.

なお、熱媒体流路10の敷設位置は、最上部に位置するコンクリート層2とその下側に位置するコンクリート層2との間のみに限定されるものではない。例えば、前記位置に加えて、さらに上から2層目のコンクリート層2と3層目のコンクリート層2との間に熱媒体流路10を設けてもよいし(図4の(b)参照)、さらに下方に熱媒体流路10を設けてもよい(図4の(c)参照)。   In addition, the laying position of the heat medium flow path 10 is not limited only between the concrete layer 2 positioned at the uppermost portion and the concrete layer 2 positioned below the uppermost concrete layer 2. For example, in addition to the above position, a heat medium flow path 10 may be provided between the second concrete layer 2 and the third concrete layer 2 from above (see FIG. 4B). Further, the heat medium flow path 10 may be further provided below (see FIG. 4C).

また、図7の(b)に示すように、最上部のコンクリート層2の内部で、1リフトの半分(ハーフリフト)の高さ位置に熱媒体流路10を設けてもよい。この場合、一旦、ハーフリフトの高さまでコンクリートを打設してコンクリート層2の半分を構築した後に、その上に熱媒体流路10を敷設してから、上部のコンクリートを打設することで、熱媒体流路10をコンクリート層2の中間部に配置させる。   Further, as shown in FIG. 7B, the heat medium flow path 10 may be provided at a height position of half of one lift (half lift) inside the uppermost concrete layer 2. In this case, once the concrete is cast to the height of the half lift and the half of the concrete layer 2 is constructed, the heat medium flow path 10 is laid thereon, and then the upper concrete is cast, The heat medium flow path 10 is arranged in the middle part of the concrete layer 2.

以上のような熱媒体流路10を備えた新堤体コンクリート構造体1の1年目の越冬中は、図1に示すように、熱媒体流路10内に温水を通水させて打設済コンクリート構造体3の表層部4を加熱する。   During the first year of wintering of the new dyke concrete structure 1 having the heat medium flow path 10 as described above, as shown in FIG. The surface layer portion 4 of the concrete structure 3 is heated.

このように、打設済コンクリート構造体3の表層部4を加熱することで、越冬中の外気温による表層部4の温度低下を抑えることができる。これによって、打設済コンクリート構造体3の表層部4と、コンクリートの水和反応によって温度上昇する内層部5との温度差を効率的に緩和することができる。したがって、新堤体コンクリート構造体1の表層部4に発生する応力ひずみを抑制できるので、表面のひび割れの発生を抑えることができる。特に応力ひずみが集中する新堤体コンクリート構造体1と旧堤体50との接合部6のひび割れの発生も抑えることができる。なお、熱媒体流路10の設置位置、設置数や通水温度に応じて、具体的な温度変化や応力ひずみを検討した結果については後述する。   In this way, by heating the surface layer portion 4 of the placed concrete structure 3, it is possible to suppress the temperature drop of the surface layer portion 4 due to the outside air temperature during wintering. Thereby, the temperature difference between the surface layer portion 4 of the cast concrete structure 3 and the inner layer portion 5 that rises in temperature due to the hydration reaction of the concrete can be effectively reduced. Therefore, since the stress distortion which generate | occur | produces in the surface layer part 4 of the new bank body concrete structure 1 can be suppressed, generation | occurrence | production of the crack of a surface can be suppressed. In particular, the occurrence of cracks in the joint 6 between the new dam body concrete structure 1 and the old dam body 50 where stress strain is concentrated can also be suppressed. In addition, the result of having examined the concrete temperature change and stress distortion according to the installation position of the heat-medium flow path 10, the number of installation, and water flow temperature is mentioned later.

1年目の打設休止期間が終了したら、図2に示すように、1年目の打設済コンクリート構造体3の上部に、2年目の新設コンクリート構造体7を順次構築して新堤体コンクリート構造体1を構築していく。   When the 1st year placement suspension period ends, as shown in FIG. 2, a new dam body is constructed by sequentially constructing a new concrete structure 7 for the 2nd year on top of the concrete structure 3 for the 1st year. The concrete structure 1 is constructed.

以上のように、打設休止期間(越冬期間)中に打設済コンクリート構造体3の表層部4を加熱しておくことで、新設コンクリート構造体7の構築期間においても、打設済コンクリート構造体3の表層部4と、新設コンクリート構造体7のコンクリートの水和反応によって温度上昇する内層部8との温度差を効率的に緩和することができるので、1年目の打設済コンクリート構造体3と2年目の新設コンクリート構造体7との接合部9に発生する応力ひずみを抑制して、その部分のひび割れの発生を抑えることができる。   As described above, by placing the surface layer portion 4 of the cast concrete structure 3 during the potting suspension period (overwintering period), the cast concrete structure is also constructed during the construction period of the new concrete structure 7. The temperature difference between the surface layer portion 4 of the body 3 and the inner layer portion 8 that rises in temperature due to the hydration reaction of the concrete of the new concrete structure 7 can be effectively mitigated. It is possible to suppress the stress strain generated at the joint portion 9 between the body 3 and the new concrete structure 7 in the second year, and to suppress the occurrence of cracks at that portion.

その後、2年目の越冬面となる、2年目の打設済コンクリート構造体3の最上部に位置するコンクリート層2内に熱媒体流路10を形成する。熱媒体流路10は、1年目の越冬面近傍に形成された熱媒体流路10と同様の構成で、同様の工程によって形成される。そして、新堤体コンクリート構造体1の2年目の越冬中は、前記熱媒体流路10内に熱媒体を流すことで、2年目の打設済コンクリート構造体3の表層部4を加熱する。   Then, the heat medium flow path 10 is formed in the concrete layer 2 located in the uppermost part of the concrete structure 3 in the 2nd year, which becomes a wintering surface in the 2nd year. The heat medium flow path 10 has the same configuration as that of the heat medium flow path 10 formed near the wintering surface in the first year, and is formed by the same process. During the second year of wintering of the new dam body concrete structure 1, the surface layer 4 of the concrete structure 3 placed in the second year is heated by flowing a heat medium in the heat medium flow path 10. .

このように、2年目の越冬中においても、打設済コンクリート構造体3の表層部4を加熱することで、打設済コンクリート構造体3の表層部4と内層部5との温度差を効率的に緩和することができるので、マスコンクリート構造体1の表層部4に発生する応力ひずみを抑制して、表面のひび割れの発生を抑えることができる。   Thus, even during the wintering of the second year, by heating the surface layer part 4 of the cast concrete structure 3, the temperature difference between the surface layer part 4 and the inner layer part 5 of the cast concrete structure 3 is reduced. Since it can relieve | moderate efficiently, the stress distortion generate | occur | produced in the surface layer part 4 of the mass concrete structure 1 can be suppressed, and generation | occurrence | production of the crack of a surface can be suppressed.

2年目の打設休止期間が終了したら、図3に示すように、2年目の打設済コンクリート構造体3の上部に、3年目の新設コンクリート構造体7を順次構築して新堤体コンクリート構造体1を構築していく。   When the second-year placement suspension period ends, as shown in FIG. 3, a new dam body is constructed by sequentially constructing a new concrete structure 7 for the third year on top of the concrete structure 3 for the second year. The concrete structure 1 is constructed.

以上のように、打設休止期間(越冬期間)中に打設済コンクリート構造体3の表層部4を加熱しておくことで、新設コンクリート構造体7の構築期間においても、2年目の打設済コンクリート構造体3の表層部4と、3年目の新設コンクリート構造体7の内層部8との温度差を効率的に緩和することができるので、打設済コンクリート構造体3と新設コンクリート構造体7との接合部9に発生する応力ひずみを抑制して、その部分のひび割れの発生を抑えることができる。   As described above, by heating the surface layer portion 4 of the cast concrete structure 3 during the potting suspension period (overwintering period), the second-year driving is also performed during the construction period of the new concrete structure 7. Since the temperature difference between the surface layer portion 4 of the installed concrete structure 3 and the inner layer portion 8 of the new concrete structure 7 in the third year can be effectively mitigated, the placed concrete structure 3 and the new concrete It is possible to suppress the stress strain generated at the joint portion 9 with the structure 7 and to suppress the occurrence of cracks at that portion.

なお、本実施形態では、3年目の施工によって新堤体コンクリート構造体1が完成するが、施工年数は3年に限定されるものではなく、ダム堤体の規模や、打設休止期間を除いた施工可能期間に応じて、施工年数が決定される。   In this embodiment, the new dyke body concrete structure 1 is completed by the construction in the third year, but the construction year is not limited to three years, except for the size of the dam dam body and the laying suspension period. The number of years of construction is determined according to the available construction period.

次に、熱媒体流路10の設置数をパラメータとして、新堤体コンクリート構造体1内部の最低温度と発生する応力ひずみを検討した結果を説明する。   Next, the result of examining the minimum temperature inside the new dam body concrete structure 1 and the generated stress strain using the number of installed heat medium flow paths 10 as a parameter will be described.

まず、図4の(a)に示すように、最上部のコンクリート層2の下部のみに熱媒体流路10を設けた場合(1リフト加熱)と、図4の(b)に示すように、最上部のコンクリート層2の下部と、その下側のコンクリート層2の下部に熱媒体流路10を二段で設けた場合(2リフト加熱)と、図4の(c)に示すように、最上部のコンクリート層2の下部と、その下側のコンクリート層2の下部と、さらに下側のコンクリート層2の下部に熱媒体流路10を三段で設けた場合(3リフト加熱)の三形態について、1年目と2年目における越冬時の新堤体コンクリート構造体1の最低温度と、新堤体コンクリート構造体1に発生する最大ひずみをFEM解析によって算出した。ここで、1リフト高さは1.5m、熱媒体流路10の配置ピッチは1.5m、熱媒体流路10内に流す温水の通水温度は20℃とする。また、越冬用の養生マット(図示せず)を、新堤体コンクリート構造体1の表面だけでなく、旧堤体50にも越冬面から2リフト上部の高さまで設置する。   First, as shown in FIG. 4A, when the heat medium flow path 10 is provided only in the lower part of the uppermost concrete layer 2 (1 lift heating), as shown in FIG. When the heat medium flow path 10 is provided in two steps at the lower part of the uppermost concrete layer 2 and the lower part of the concrete layer 2 below (2 lift heating), as shown in FIG. When the heat medium flow path 10 is provided in three stages in the lower part of the uppermost concrete layer 2, the lower part of the lower concrete layer 2, and the lower part of the lower concrete layer 2 (three lift heating). About the form, the minimum temperature of the new levee body concrete structure 1 at the time of wintering in the first year and the second year and the maximum strain generated in the new dam body concrete structure 1 were calculated by FEM analysis. Here, it is assumed that the height of one lift is 1.5 m, the arrangement pitch of the heat medium flow path 10 is 1.5 m, and the temperature of hot water flowing through the heat medium flow path 10 is 20 ° C. Further, a curing mat for wintering (not shown) is installed not only on the surface of the new dam body concrete structure 1 but also on the old dam body 50 from the wintering surface to the height of 2 lifts.

新堤体コンクリート構造体1内部(表層部4)の最低温度は、図5に示すように、1年目の越冬時では、1リフト加熱で「4.11℃」、2リフト加熱で「4.18℃」、3リフト加熱で「4.19℃」となる。なお、加熱なしの場合は、最低温度が「3.47℃」となる(図5中、黒三角参照)。また、2年目の越冬時では、1リフト加熱で「4.38℃」、2リフト加熱で「4.43℃」、3リフト加熱で「4.42℃」となり、加熱なしの場合は「3.73℃」となる(図5中、白三角参照)。   As shown in FIG. 5, the minimum temperature inside the new dyke concrete structure 1 (surface layer part 4) is “4.11 ° C.” for 1 lift heating and “4. “18 ° C.” and “4.19 ° C.” after 3 lift heating. In the case of no heating, the minimum temperature is “3.47 ° C.” (see the black triangle in FIG. 5). Also, during wintering in the second year, it is “4.38 ° C.” with 1 lift heating, “4.43 ° C.” with 2 lift heating, and “4.42 ° C.” with 3 lift heating. 3.73 ° C. ”(see white triangle in FIG. 5).

新堤体コンクリート構造体1に発生する最大ひずみは、図6に示すように、1年目の越冬時では、1リフト加熱で「131.1μ」、2リフト加熱で「134.8μ」、3リフト加熱で「135.4μ」となる。なお、加熱なしの場合は、最大ひずみが「148.4μ」となる(図6中、黒三角参照)。また、2年目の越冬時では、1リフト加熱で「100.0μ」、2リフト加熱で「101.5μ」、3リフト加熱で「99.7μ」となり、加熱なしの場合は「109.9μ」となる(図6中、白三角参照)。   As shown in FIG. 6, the maximum strain generated in the new dam concrete structure 1 is “131.1 μ” for 1 lift heating and “134.8 μ” for 2 lift heating, It becomes “135.4μ” by heating. In the case of no heating, the maximum strain is “148.4 μ” (see the black triangle in FIG. 6). In addition, during the winter of the second year, “100.0 μ” is obtained by 1 lift heating, “101.5 μ” is obtained by 2 lift heating, “99.7 μ” is obtained by 3 lift heating, and “109.9 μ” is obtained without heating. (See white triangle in FIG. 6).

以上の結果より、新堤体コンクリート構造体1の表層部4の加熱を行うことによって、表層部4の最低温度が、加熱なしの場合よりも高くなり、新堤体コンクリート構造体1に発生する最大ひずみを小さくできることが解った。なお、1リフト加熱から3リフト加熱にかけては、どのケースも略同等の最低温度と最大ひずみとなるので、表面に近い部分を加熱するのが効果的であることが解った。そして、加熱による費用と最大ひずみの低減効率を考慮して、1リフト加熱とするのが好ましいことが解った。   From the above results, by heating the surface layer portion 4 of the new dam body concrete structure 1, the minimum temperature of the surface layer portion 4 becomes higher than that without heating, and the maximum strain generated in the new dam body concrete structure 1 It was found that can be reduced. In addition, it was found that it is effective to heat the portion close to the surface since the minimum temperature and the maximum strain are almost the same in each case from 1 lift heating to 3 lift heating. And it turned out that it is preferable to set it as 1 lift heating in consideration of the cost by heating and the reduction efficiency of maximum distortion.

次に、図7の(a)に示すように、最上部のコンクリート層2の下部に熱媒体流路10を設けた場合(1リフト加熱)において、温水の通水温度を、20℃,30℃,40℃と変化させて、1年目と2年目における越冬時の新堤体コンクリート構造体1の最低温度と、新堤体コンクリート構造体1に発生する最大ひずみをFEM解析によって算出した。また、図7の(b)に示すように、最上部のコンクリート層2の中間部に熱媒体流路10を設けた場合(ハーフリフト加熱)において、温水の通水温度を、30℃として、1年目と2年目における越冬時の新堤体コンクリート構造体1の最低温度と、新堤体コンクリート構造体1に発生する最大ひずみをFEM解析によって算出した。   Next, as shown in FIG. 7A, in the case where the heat medium flow path 10 is provided below the uppermost concrete layer 2 (one lift heating), the hot water flow temperature is set to 20 ° C. and 30 ° C. The minimum temperature of the new dam body concrete structure 1 during the wintering in the first year and the second year and the maximum strain generated in the new dam body concrete structure 1 were calculated by FEM analysis while changing the temperature to 40 ° C. Moreover, as shown in (b) of FIG. 7, in the case where the heat medium flow path 10 is provided in the middle part of the uppermost concrete layer 2 (half lift heating), the water flow temperature of hot water is set to 30 ° C. The minimum temperature of the new dam body concrete structure 1 during the wintering in the first year and the second year and the maximum strain generated in the new dam body concrete structure 1 were calculated by FEM analysis.

新堤体コンクリート構造体1内部(表層部4)の最低温度は、図8に示すように、1年目の越冬時では、1リフト加熱における通水温度20℃で「4.11℃」、通水温度30℃で「5.28℃」、通水温度40℃で「6.45℃」となる。ハーフリフト加熱(通水温度30℃)では、最低温度が「6.18℃」となる(図8中、黒丸参照)。なお、加熱なしの場合は、最低温度が「3.47℃」(図8中、黒三角参照)となる。また、2年目の越冬時では、1リフト加熱における通水温度20℃で「4.38℃」、通水温度30℃で「5.60℃」、通水温度40℃で「6.82℃」となる。ハーフリフト加熱(通水温度30℃)では、最低温度が「6.54℃」となる(図8中、白丸参照)。なお、加熱なしの場合は、最低温度が「3.73℃」となる(図8中、白三角参照)。   As shown in FIG. 8, the minimum temperature inside the new dyke concrete structure 1 (surface layer part 4) is “4.11 ° C.” at a water flow temperature of 20 ° C. in 1 lift heating during the wintering of the first year. It becomes “5.28 ° C.” at a water temperature of 30 ° C. and “6.45 ° C.” at a water passing temperature of 40 ° C. In the half lift heating (water flow temperature 30 ° C.), the minimum temperature becomes “6.18 ° C.” (see the black circle in FIG. 8). In the case of no heating, the minimum temperature is “3.47 ° C.” (see the black triangle in FIG. 8). In winter of the second year, “4.38 ° C.” at a water flow temperature of 20 ° C., “5.60 ° C.” at a water flow temperature of 30 ° C., and “6.82” at a water flow temperature of 40 ° C. ° C ". In the half lift heating (water flow temperature 30 ° C.), the minimum temperature is “6.54 ° C.” (see white circles in FIG. 8). In the case of no heating, the minimum temperature is “3.73 ° C.” (see the white triangle in FIG. 8).

新堤体コンクリート構造体1に発生する最大ひずみは、図9に示すように、1年目の越冬時では、1リフト加熱における通水温度20℃で「131.1μ」、通水温度30℃で「102.6μ」、通水温度40℃で「74.8μ」となる。ハーフリフト加熱(通水温度30℃)では、最大ひずみが「69.8μ」となる(図9中、黒丸参照)。なお、加熱なしの場合は、最大ひずみが「148.4μ」となる(図9中、黒三角参照)。また、2年目の越冬時では、1リフト加熱における通水温度20℃で「100.0μ」、通水温度30℃で「83.6μ」、通水温度40℃で「67.5μ」となる。ハーフリフト加熱(通水温度30℃)では、最大ひずみが「72.1μ」となる(図9中、白丸参照)。なお、加熱なしの場合は、最大ひずみが「109.9μ」となる(図9中、白三角参照)。   As shown in FIG. 9, the maximum strain generated in the new dam body concrete structure 1 is “131.1μ” at a water flow temperature of 20 ° C. and 1 ° C. at a water flow temperature of 30 ° C. “102.6μ” and “74.8μ” at a water flow temperature of 40 ° C. In half lift heating (water flow temperature 30 ° C.), the maximum strain is “69.8 μ” (see the black circle in FIG. 9). In the case of no heating, the maximum strain is “148.4 μ” (see the black triangle in FIG. 9). In winter of the second year, “100.0μ” at a water flow temperature of 20 ° C., “83.6μ” at a water flow temperature of 30 ° C., and “67.5μ” at a water flow temperature of 40 ° C. Become. In half lift heating (water flow temperature 30 ° C.), the maximum strain is “72.1 μ” (see white circles in FIG. 9). In the case of no heating, the maximum strain is “109.9 μ” (see white triangles in FIG. 9).

以上の結果より、新堤体コンクリート構造体1の表層部4の加熱を行う際に、温水の通水温度を40℃とした場合が最も表層部4の最低温度が高くなる。つまり、通水温度を高くするほど、温度低下を抑制できるので、内層部5との温度差を小さくでき、新堤体コンクリート構造体1に発生する最大ひずみを小さくできることが解った。   From the above results, when heating the surface layer portion 4 of the new dam body concrete structure 1, the lowest temperature of the surface layer portion 4 is highest when the water flow temperature is 40 ° C. That is, it was found that the higher the water flow temperature, the lower the temperature drop, so that the temperature difference with the inner layer portion 5 can be reduced and the maximum strain generated in the new dam body concrete structure 1 can be reduced.

また、1リフト加熱とハーフリフト加熱を比較すると、同じ条件の場合、ハーフリフト加熱の方が、新堤体コンクリート構造体1の表層部4の最低温度が高くなり、温度低下を抑制できるので、内層部5との温度差を小さくでき、新堤体コンクリート構造体1に発生する最大ひずみを小さくできることが解った。特に、1年目の越冬時には、1リフト加熱で通水温度40℃の場合よりもハーフリフト加熱で通水温度30℃の場合の方が、最大ひずみが小さくなる。   Further, when comparing 1 lift heating and half lift heating, in the case of the same condition, the half lift heating increases the minimum temperature of the surface layer portion 4 of the new dam body concrete structure 1 and can suppress the temperature drop. It was found that the temperature difference with the part 5 can be reduced and the maximum strain generated in the new dam concrete structure 1 can be reduced. In particular, during wintering in the first year, the maximum strain is smaller in the case of half lift heating and a water flow temperature of 30 ° C. than in the case of water flow temperature of 40 ° C. in one lift heating.

次に、一段のハーフリフト加熱で通水温度30℃の場合について、1年目、2年目、3年目の越冬時の旧堤体50および新堤体コンクリート構造体1内部の温度分布とひずみ分布をFEM解析にて算出する。なお、図10乃至図12の(a)では、新堤体コンクリート構造体1内部の温度分布を濃淡で示しており、右側に温度分布と濃淡の対応を示している。また、図10乃至図12の(b)では、新堤体コンクリート構造体1内部のひずみ分布を濃淡で示しており、右側にひずみ分布と濃淡の対応を示している。   Next, the temperature distribution and strain in the old levee body 50 and the new dam body concrete structure 1 during the first year, the second year, and the third year overwintering when the water flow temperature is 30 ° C. by one-stage half lift heating. Distribution is calculated by FEM analysis. 10A to 12A, the temperature distribution inside the new dyke concrete structure 1 is shown in shades, and the correspondence between the temperature distribution and the shades is shown on the right side. Moreover, in FIG. 10 thru | or FIG.12 (b), the strain distribution inside the new dyke body concrete structure 1 is shown with the shading, and the correspondence of the strain distribution and the shading is shown on the right side.

1年目の越冬時の温度分布は、図10の(a)に示すように、新堤体コンクリート構造体1の内層部5の温度が一番高く(29.2℃)、内層部5から離間するに連れて徐々に温度が低下している。また、熱媒体流路10の周囲も若干温度が高くなっており、新堤体コンクリート構造体1の上端面の旧堤体50との接合部6は、「6.5℃」となっている。このような温度分布によって、発生するひずみ分布は、図10の(b)に示すように、ひび割れが一番発生しやすい新堤体コンクリート構造体1の上端面の旧堤体50との接合部6では、引張側である「20μ」と非常に小さい値となり、ひび割れの発生を防止することができる。また、旧堤体50と新堤体コンクリート構造体1との接合面12でのひずみは、例えば「43μ」であって、図の濃淡から全体を見ても「50μ」以下となり、旧堤体50と新堤体コンクリート構造体1との一体化を阻害するようなことはない。なお、図10中、堤体内に示された濃淡の濃い部分は、数値の低い側が示されている。   As shown in FIG. 10A, the temperature distribution during wintering in the first year is the highest in the inner layer 5 of the new dyke concrete structure 1 (29.2 ° C.) and is separated from the inner layer 5. As it goes on, the temperature gradually decreases. In addition, the temperature around the heat medium flow path 10 is also slightly higher, and the joint portion 6 of the upper end surface of the new dam body concrete structure 1 with the old dam body 50 is “6.5 ° C.”. As shown in FIG. 10B, the strain distribution generated by such a temperature distribution is a joint 6 with the old dam body 50 at the upper end surface of the new dam body concrete structure 1 where cracks are most likely to occur. Then, it becomes a very small value of “20 μ” on the tension side, and the occurrence of cracks can be prevented. In addition, the strain at the joint surface 12 between the old levee body 50 and the new dam body concrete structure 1 is, for example, “43 μ”. And the integration of the new dam body concrete structure 1 is not hindered. In FIG. 10, the darker shaded portion shown in the levee body shows the lower value side.

2年目の越冬時の温度分布は、図11の(a)に示すように、2年目に構築された新堤体コンクリート構造体1の内層部5の温度が一番高く(27.0℃)、内層部5から離間するに連れて徐々に温度が低下している。また、2年目に形成された熱媒体流路10の周囲も若干温度が高くなっており、新堤体コンクリート構造体1の上端面の旧堤体50との接合部6は、「7.0℃」となっている。このような温度分布によって、発生するひずみ分布は、図11の(b)に示すように、ひび割れが一番発生しやすい新堤体コンクリート構造体1の上端面の旧堤体50との接合部では、引張側である「53μ」と非常に小さい値となり、ひび割れの発生を防止することができる。また、このとき、1年目の越冬面の旧堤体50との接合部6では、圧縮側である「−15μ」となり、ひび割れの発生を防止することができる。さらに、2年目においても、旧堤体50と新堤体コンクリート構造体1との接合面12でのひずみは、図の濃淡から全体を見ても「50μ」以下となり、旧堤体50と新堤体コンクリート構造体1との一体化を阻害するようなことはない。なお、図11中、堤体内に示された濃淡の濃い部分は、数値の低い側が示されている。   As shown in FIG. 11A, the temperature distribution during wintering in the second year is the highest (27.0 ° C.) in the inner layer 5 of the new dyke concrete structure 1 constructed in the second year. ), The temperature gradually decreases as the distance from the inner layer portion 5 increases. Further, the temperature around the heat medium flow path 10 formed in the second year is also slightly higher, and the joint portion 6 of the upper end surface of the new dam body concrete structure 1 with the old dam body 50 is “7.0. It is “℃”. As shown in FIG. 11 (b), the strain distribution generated by such temperature distribution is as follows at the junction with the old dam body 50 on the upper end surface of the new dam body concrete structure 1 where cracks are most likely to occur. , Which is a very small value of “53 μ” on the tension side, and the occurrence of cracks can be prevented. At this time, the joint 6 with the old dyke body 50 on the first year wintering surface becomes “−15 μ” on the compression side, and the occurrence of cracks can be prevented. Further, even in the second year, the strain at the joint surface 12 between the old levee body 50 and the new dam body concrete structure 1 is less than “50 μ” even when viewed as a whole from the shading of the figure. There is no such thing as hindering integration with the body concrete structure 1. In addition, in FIG. 11, the dark part shown in the levee body has a low numerical value side.

3年目の越冬時の温度分布は、図12の(a)に示すように、3年目に構築された新堤体コンクリート構造体1の内層部5の温度が一番高いが、その部分の厚さが薄い為、外気温に冷やされて、「20.6℃」となっており、表層部4と内層部5との温度差が小さくなっている。このような温度分布によって、発生するひずみ分布は、図12の(b)に示すように、1年目の越冬面の旧堤体50と新堤体コンクリート構造体1との接合部6では、圧縮側である「−13μ」となり、2年目の越冬面の旧堤体50と新堤体コンクリート構造体1との接合部6では、圧縮側である「−9μ」となるので、ひび割れの発生を防止することができる。また、3年目の越冬時においても、旧堤体50と新堤体コンクリート構造体1との接合面12でのひずみは、全体を見ても「50μ」以下となり、旧堤体50と新堤体コンクリート構造体1との一体化を阻害するようなことはない。図12中、堤体内に示された濃淡の濃い部分は、数値の低い側が示されている。   As shown in FIG. 12 (a), the temperature distribution during wintering in the third year is the highest in the inner layer portion 5 of the new dyke concrete structure 1 constructed in the third year. Since the thickness is thin, it is cooled to the outside air temperature and becomes “20.6 ° C.”, and the temperature difference between the surface layer portion 4 and the inner layer portion 5 is small. As shown in FIG. 12B, the strain distribution generated by such temperature distribution is compressed at the junction 6 between the old levee body 50 and the new levee body concrete structure 1 on the first year wintering surface. It becomes “−13μ” on the side, and the joint 6 between the old levee body 50 and the new dam body concrete structure 1 in the wintering surface in the second year becomes “−9μ” on the compression side, so that cracking occurs. Can be prevented. Even during the wintering of the third year, the strain at the joint surface 12 between the old levee body 50 and the new levee body concrete structure 1 is not more than “50 μ” when viewed as a whole. There is no such thing as inhibiting the integration with the concrete structure 1. In FIG. 12, the darker portion shown in the levee body shows the lower value side.

以上説明したように、本実施形態によれば、新堤体コンクリート構造体1の表層部4に発生する応力ひずみを抑制して、表面のひび割れの発生を抑えることができる。また、旧堤体50と新堤体コンクリート構造体1との間のひび割れの発生も抑えることができるので、旧堤体50と新堤体コンクリート構造体1とを確実に一体化することができる。   As described above, according to the present embodiment, the stress strain generated in the surface layer portion 4 of the new dam body concrete structure 1 can be suppressed, and the occurrence of cracks on the surface can be suppressed. Moreover, since generation | occurrence | production of the crack between the old bank body 50 and the new bank body concrete structure 1 can also be suppressed, the old bank body 50 and the new bank body concrete structure 1 can be integrated reliably.

以上、本発明を実施するための形態について説明したが、本発明は前記実施の形態に限定されず、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。たとえば、前記実施形態では、旧堤体50の斜面部に沿って構築される新堤体コンクリート構造体1をマスコンクリート構造体の一例としたが、マスコンクリート構造体は、これに限定されるものではなく、例えば、新設のダム堤体や、橋梁の橋脚部等のマスコンクリート構造体に対しても本発明は適用することができる。   As mentioned above, although the form for implementing this invention was demonstrated, this invention is not limited to the said embodiment, In the range which does not deviate from the meaning of this invention, a design change is possible suitably. For example, in the said embodiment, although the new levee body concrete structure 1 constructed | assembled along the slope part of the old levee body 50 was made into an example of a mass concrete structure, a mass concrete structure is not limited to this. For example, the present invention can also be applied to a mass concrete structure such as a newly installed dam body and a bridge pier.

1 新堤体コンクリート構造体(マスコンクリート構造体)
2 コンクリート層
3 打設済コンクリート構造体
4 表層部
5 (打設済コンクリート構造体の)内層部
7 新設コンクリート構造体
8 (新設コンクリート構造体の)内層部
10 熱媒体流路
1 New dyke body concrete structure (mass concrete structure)
2 Concrete layer 3 Placed concrete structure 4 Surface layer 5 Inner layer part (of cast concrete structure) 7 New concrete structure 8 Inner layer part (of new concrete structure) 10 Heat medium flow path

Claims (3)

下部から1リフトごとにコンクリートを順次打設して上下方向に複数のコンクリート層を構築するマスコンクリート構造体の構築方法において、
打設済の複数の前記コンクリート層のうち、少なくとも最上部に位置する前記コンクリート層を打設休止期間中に加熱することで、打設済の複数の前記コンクリート層からなる打設済コンクリート構造体の表層部と内層部との温度差を緩和する
ことを特徴とするマスコンクリート構造体の構築方法。
In the construction method of a mass concrete structure in which concrete is sequentially placed from the bottom for each lift and a plurality of concrete layers are constructed in the vertical direction,
Of the plurality of cast concrete layers, at least the concrete layer located at the uppermost part is heated during the casting pause period, thereby forming a cast concrete structure composed of the plurality of cast concrete layers. A method for constructing a mass concrete structure, characterized in that a temperature difference between a surface layer portion and an inner layer portion of the material is alleviated.
下部から1リフトごとにコンクリートを順次打設して上下方向に複数のコンクリート層を構築するマスコンクリート構造体の構築方法において、
打設済の複数の前記コンクリート層のうち、少なくとも最上部に位置する前記コンクリート層を、打設済の複数の前記コンクリート層からなる打設済コンクリート構造体の表層部と内層部との温度差を緩和するとともに前記打設済コンクリート構造体の前記表層部とその上部に新たに増打ちされる新設コンクリート構造体の内層部との温度差を緩和するように、打設休止期間中に加熱する
ことを特徴とするマスコンクリート構造体の構築方法。
In the construction method of a mass concrete structure in which concrete is sequentially placed from the bottom for each lift and a plurality of concrete layers are constructed in the vertical direction,
The temperature difference between the surface layer portion and the inner layer portion of the cast concrete structure composed of the plurality of cast concrete layers, at least the concrete layer positioned at the top of the plurality of cast concrete layers. And heating during the placing pause period so as to reduce the temperature difference between the surface layer portion of the placed concrete structure and the inner layer portion of the new concrete structure newly added to the upper portion thereof. A method for constructing a mass concrete structure.
前記コンクリート層の加熱は、前記コンクリート層内に熱媒体流路を形成し、前記熱媒体流路内に熱媒体を流すことで行われる
ことを特徴とする請求項1または請求項2に記載のマスコンクリート構造体の構築方法。
The heating of the concrete layer is performed by forming a heat medium flow path in the concrete layer and flowing a heat medium in the heat medium flow path. Construction method of mass concrete structure.
JP2009271474A 2009-11-30 2009-11-30 Construction method of mass concrete structure Expired - Fee Related JP5308316B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009271474A JP5308316B2 (en) 2009-11-30 2009-11-30 Construction method of mass concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009271474A JP5308316B2 (en) 2009-11-30 2009-11-30 Construction method of mass concrete structure

Publications (2)

Publication Number Publication Date
JP2011111849A true JP2011111849A (en) 2011-06-09
JP5308316B2 JP5308316B2 (en) 2013-10-09

Family

ID=44234394

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009271474A Expired - Fee Related JP5308316B2 (en) 2009-11-30 2009-11-30 Construction method of mass concrete structure

Country Status (1)

Country Link
JP (1) JP5308316B2 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296819A (en) * 2011-06-15 2011-12-28 四川路桥建设股份有限公司 Construction method for mass pipe concrete without temperature reduction
CN103603312A (en) * 2013-10-30 2014-02-26 中国水利水电科学研究院 Ideal temperature control curve model of concrete dam and intelligent control method utilizing same
CN104195937A (en) * 2014-08-21 2014-12-10 四川金锋建设有限公司 Cracking-preventing bridge structure
CN105544578A (en) * 2015-12-18 2016-05-04 中冶建筑研究总院有限公司 Method for determining construction and curing methods for mass concrete structures
KR101755157B1 (en) 2016-05-13 2017-07-06 한국수자원공사 Hybrid Dam Combined Concrete Zone and Fill Zone
CN111188492A (en) * 2020-01-10 2020-05-22 中国华西企业股份有限公司 Processing method for improving interface binding power of new and old concrete
CN113235451A (en) * 2021-06-10 2021-08-10 惠州晖华混凝土有限公司 Construction method of mass concrete
CN113897912A (en) * 2021-10-16 2022-01-07 浙江钱塘江水利建筑工程有限公司 Rock-fill concrete masonry structure and construction method thereof
CN114351655A (en) * 2021-12-09 2022-04-15 长江勘测规划设计研究有限责任公司 Construction method for raising structure of back slope limited combined gravity dam
CN114872197A (en) * 2022-04-19 2022-08-09 江西省交通工程集团建设有限公司 Control method for mold-entering temperature of mass concrete
CN115584860A (en) * 2022-10-11 2023-01-10 中国水利水电第六工程局有限公司 Large-volume concrete pouring device and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0146672B2 (en) * 1980-03-18 1989-10-09 Obayashi Constr Co Ltd
JPH0874229A (en) * 1994-09-08 1996-03-19 Fujita Corp Form of dam body and construction of dam body
JP2521740B2 (en) * 1987-01-30 1996-08-07 義之 大串 Dam reinforcement / repair method
JP2009084790A (en) * 2007-09-27 2009-04-23 Kajima Corp Construction method for concrete dam body

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0146672B2 (en) * 1980-03-18 1989-10-09 Obayashi Constr Co Ltd
JP2521740B2 (en) * 1987-01-30 1996-08-07 義之 大串 Dam reinforcement / repair method
JPH0874229A (en) * 1994-09-08 1996-03-19 Fujita Corp Form of dam body and construction of dam body
JP2009084790A (en) * 2007-09-27 2009-04-23 Kajima Corp Construction method for concrete dam body

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296819A (en) * 2011-06-15 2011-12-28 四川路桥建设股份有限公司 Construction method for mass pipe concrete without temperature reduction
CN103603312A (en) * 2013-10-30 2014-02-26 中国水利水电科学研究院 Ideal temperature control curve model of concrete dam and intelligent control method utilizing same
CN103603312B (en) * 2013-10-30 2016-06-22 中国水利水电科学研究院 A kind of concrete dam ideal temperature control curve model and utilize its intelligent control method
CN104195937A (en) * 2014-08-21 2014-12-10 四川金锋建设有限公司 Cracking-preventing bridge structure
CN105544578A (en) * 2015-12-18 2016-05-04 中冶建筑研究总院有限公司 Method for determining construction and curing methods for mass concrete structures
KR101755157B1 (en) 2016-05-13 2017-07-06 한국수자원공사 Hybrid Dam Combined Concrete Zone and Fill Zone
CN111188492A (en) * 2020-01-10 2020-05-22 中国华西企业股份有限公司 Processing method for improving interface binding power of new and old concrete
CN113235451A (en) * 2021-06-10 2021-08-10 惠州晖华混凝土有限公司 Construction method of mass concrete
CN113897912A (en) * 2021-10-16 2022-01-07 浙江钱塘江水利建筑工程有限公司 Rock-fill concrete masonry structure and construction method thereof
CN113897912B (en) * 2021-10-16 2022-07-26 浙江钱塘江水利建筑工程有限公司 Rock-fill concrete masonry structure and construction method thereof
CN114351655A (en) * 2021-12-09 2022-04-15 长江勘测规划设计研究有限责任公司 Construction method for raising structure of back slope limited combined gravity dam
CN114872197A (en) * 2022-04-19 2022-08-09 江西省交通工程集团建设有限公司 Control method for mold-entering temperature of mass concrete
CN115584860A (en) * 2022-10-11 2023-01-10 中国水利水电第六工程局有限公司 Large-volume concrete pouring device and method

Also Published As

Publication number Publication date
JP5308316B2 (en) 2013-10-09

Similar Documents

Publication Publication Date Title
JP5308316B2 (en) Construction method of mass concrete structure
JP4108544B2 (en) Mass concrete pipe cooling method
CN103643626B (en) A kind of control method of superrelation on curve type bridge pier pier shaft thermal stress cracks
JP6347667B2 (en) Method for controlling temperature cracks in concrete
JP2018071217A (en) Concrete placing method
KR101367495B1 (en) Reinforcing system in super columns to reduce the concrete hydration heat and enhance the seismic performance of columns
JP6678488B2 (en) Construction method of concrete embankment
JP6261995B2 (en) Concrete temperature control method
JP6041951B2 (en) Method for suppressing thermal stress cracking of wall-like concrete structures
CN110569553A (en) Method for controlling cooling age of coal ash doped low-calorific-value lining concrete through water
JP6172587B2 (en) Floor heating system
JP5814139B2 (en) Method for suppressing thermal stress cracking in wall-shaped reinforced concrete structures and thermal stress crack-inhibiting wall-shaped reinforced concrete structures
JPH0146672B2 (en)
JP6181436B2 (en) Method for curing cast concrete and concrete structure
CN203404504U (en) FRP (Fiber Reinforced Plastics) pipeline
CN205857838U (en) Thermal power plant heater island arrangement
JP5261508B2 (en) Method for manufacturing reinforced concrete member
CN104480848A (en) Concrete box structure with temperature difference stress influence resistance and bridge box
CN217679630U (en) Structure for preventing self-restrained cracks of mass concrete
CN205822798U (en) A kind of cooling water self-circulating device for mass concrete
JPH0557389B2 (en)
KR101274768B1 (en) Seat for caring concrete including phase change material, concrete caring system comprising the same, and controlling method of concrete caring system
CN105317001A (en) Variable box variable cross section continuous rigid frame aqueduct single-box single-chamber box girder and design method thereof
JP2534080B2 (en) Cooling method in concrete gravity dam
CN103292062B (en) A kind of fiber reinforced plastic pipe

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20110922

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20110922

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111206

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20120117

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20120118

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120203

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120214

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120911

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121109

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130618

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130628

R150 Certificate of patent or registration of utility model

Ref document number: 5308316

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees