Prior art keywords
scaffold
veranda
stair
landing
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009229890A
Other languages
Japanese (ja)
Other versions
JP5143105B2 (en
Inventor
Katsumasa Kato
勝征 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ASAHI GAKUEN GROUP KK
TAKEKAWA YOSHIHISA
Original Assignee
ASAHI GAKUEN GROUP KK
TAKEKAWA YOSHIHISA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ASAHI GAKUEN GROUP KK, TAKEKAWA YOSHIHISA filed Critical ASAHI GAKUEN GROUP KK
Priority to JP2009229890A priority Critical patent/JP5143105B2/en
Publication of JP2011074725A publication Critical patent/JP2011074725A/en
Application granted granted Critical
Publication of JP5143105B2 publication Critical patent/JP5143105B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a scaffold for stair veranda construction, which is installed in a stair veranda of a high-rise apartment building, and is firmly supported by the veranda without being tilted due to wind blowing. <P>SOLUTION: The scaffold M is constituted by landing scaffolds 10A which are installed on a lower landing 4 and an upper landing 5, and stair scaffolds 10 which are connected with the landing scaffolds 10A and configured so as to tightly stick between the tread surfaces 3 of stairs 2 and a slanting ceiling wall 9. The stair scaffold 10 is constituted by a support body 11 and a scaffold stage 16. The support body 11 is provided with a vertical support 12 disposed between the tread surface 3 of the stairs 2 and the slanting ceiling wall 9, and a scaffold stage stay 15 protruding over a veranda side wall 7 from the vertical support 12. The scaffold stages 16 are disposed by spanning a plurality of the scaffold stage stays 15. The upper part of the vertical support 12 is provided with a pressing part 13 for pressing the slanting ceiling wall 9. By operating a jack part 122 of the vertical support 12, the slanting ceiling wall 9 is pressed thereby tightly supporting the vertical support 12. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、高層住宅又は超高層住宅等における階段ベランダに設置して階段ベランダの外壁の清掃工事や改修工事を行うための階段ベランダ工事用足場に関する。   The present invention relates to a staircase veranda work scaffold for installation on a stair veranda in a high-rise house or a super-high-rise house or the like to perform cleaning work or repair work on the outer wall of a staircase veranda.

地上20階以上を越える高層住宅や超高層住宅での階段ベランダ側壁の清掃工事や改修工事等の外壁工事を行う場合、高層で発生するビル風が建物に当たって舞い上がったり、また吹き抜けたりすることによって、地上では考え難い風の影響を受けやすい。このため、従来から行われていた階段ベランダ外壁工事、例えば、屋上からゴンドラを吊り下げて行う作業は、危険が大きいことから実施できにくい状況にあった。近年、超高層住宅が立ち並ぶ中、ベランダ外壁工事の際にゴンドラの落下する事故が発生している。また、地上から積み上げて構成するピケ足場の場合、高層住宅の場合では、足場作りが大掛かりな作業となって工事の長期化又は莫大な工事費用がかかり、現実には足場を構成することに無理が生じていた。   When performing exterior wall construction such as cleaning and renovation of the side walls of the stairs veranda in high-rise houses and super high-rise houses over 20 floors above the ground, the building wind generated by the high rises soars and blows through the building, It is easily affected by wind that is difficult to think on the ground. For this reason, the work on the outer wall of the staircase veranda, which has been conventionally performed, such as the work performed by hanging the gondola from the roof, is difficult to perform because of the great danger. In recent years, there has been an accident where a gondola falls during the construction of the outer wall of the veranda, while super high-rise houses are lined up. In addition, in the case of a picket scaffold that is built up from the ground, in the case of high-rise housing, the construction of the scaffold becomes a major work, which requires a long construction period or enormous construction costs, and in reality it is impossible to construct a scaffold. Has occurred.

このことから、従来においては、特許文献1に知られるように、ベランダで組み付けることができる足場が提供されていた。これによると、足場は、ベランダの床面と天井壁とを突っ張るように支持する支柱を設けて足場本体を構成し、足場本体からベランダ外側に、張り出し枠体を突出させて作業枠体としていた。これによって、足場本体を簡略化することができるとともに、工期も短くすることができ、工事費用も廉価にすることができることとなっていた。   For this reason, conventionally, as known in Patent Document 1, a scaffold that can be assembled with a veranda has been provided. According to this, the scaffold was configured as a work frame body by providing a support body that supports the floor surface and ceiling wall of the veranda so as to stretch, and projecting an overhanging frame body from the scaffold body to the outside of the veranda. . As a result, the scaffold body can be simplified, the construction period can be shortened, and the construction cost can be reduced.

特開平11−223012号公報JP 11-2223012 A

しかし、高層住宅が20階を越えて50階以上に至る、いわゆるタワー型超高層マンション群では、冒頭に述べた、ビル風の影響を大いに受けることとなり、少しでも危険な作業を想定できるような構成にすることはできない。つまり100%近い安全な足場を構成する必要があり、また、工事の長期化を防止して廉価な費用で提供できる足場でなくてはならなかった。   However, in the so-called tower-type high-rise condominiums where the high-rise houses extend from the 20th floor to the 50th floor or higher, the building-like effects described at the beginning are greatly affected, and even a little dangerous work can be assumed. It cannot be configured. In other words, it was necessary to construct a nearly 100% safe scaffold, and the scaffold had to be able to be provided at low cost by preventing the construction from being prolonged.

特許文献1の足場では、例えば、ビル風でベランダ天井壁を押圧する押圧部が破損した場合、足場自体が傾いて落下する虞があり、危険を伴うこととなっていた。また、この足場は、段状に形成されている階段ベランダには適用することはできなかった。   In the scaffold of Patent Document 1, for example, when a pressing part that presses the veranda ceiling wall in a building style is damaged, the scaffold itself may be inclined and fall, which is dangerous. Further, this scaffold could not be applied to a stepped veranda formed in a step shape.

本発明は、上述の課題を解決するものであり、高層ビルの階段ベランダに設置されて安全に構成された階段ベランダ工事用足場を提供することを目的とする。そのため、本発明に係る工事用足場は、以下のように構成するものである。すなわち、
請求項1記載の発明では、高層住宅の階段ベランダに設置する階段ベランダ工事用足場であって、段差を有して配設された階段における2段の踏み面と、斜め平面状に形成されて前記踏み面の直上に配設された上層階段の裏面との間に設置され、一端を高さ調整可能なジャッキ部を有して前記踏み面に当接するとともに、他端に前記上層階段の裏面を押圧する押圧部を配設して構成された縦支柱と、前記縦支柱から前記階段ベランダの外壁側に突出した足場台用ステーと、を備えた支持体が構成され、段差を有する前記2段の踏み面に隣り合って設置される2基の前記支持体における2個の前記足場台用ステー上に、作業者が作業する足場台を架け渡して構成されていることを特徴とするものである。
This invention solves the above-mentioned subject, and it aims at providing the scaffold for construction of the stair veranda installed in the stair veranda of a high-rise building and comprised safely. Therefore, the construction scaffold according to the present invention is configured as follows. That is,
The invention according to claim 1 is a staircase veranda construction scaffolding installed on a staircase veranda of a high-rise house, and is formed in a two-step tread surface on a staircase having a step and an oblique plane. Installed between the upper surface of the upper staircase disposed immediately above the tread surface, has a jack portion whose height is adjustable at one end and abuts against the tread surface, and the rear surface of the upper staircase at the other end. A support body comprising a vertical column configured by disposing a pressing part that presses and a scaffolding stay projecting from the vertical column to the outer wall side of the staircase veranda is configured, and has the step. A structure in which a scaffold base on which an operator works is bridged over two scaffold base stays in the two supports installed adjacent to the stepped surface of the step. It is.

請求項2記載の発明は、請求項1の発明に係るものであって、前記支持体には、前記縦支柱が立設する踏み面より上段の踏み面から立ち上がって前記縦支柱を支持する補助支柱が配設されていることを特徴としている。   The invention according to claim 2 relates to the invention according to claim 1, wherein the support body is provided with an auxiliary to stand up from a tread surface above the tread surface on which the vertical support column stands to support the vertical support column. It is characterized in that a support is provided.

請求項3記載の発明は、高層住宅の階段ベランダに設置する階段ベランダ工事用足場であって、段差を有して配設された階段における複数の踏み面と、最上段に配設された前記踏み面の上面側に配設された上層階踊り場の床面と、最下段に配設された前記踏み面の下方に配設された下層階踊り場の床面と、前記上層階踊り場と前記下層階踊り場との間を階段踊り場の外側に配設される前記階段ベランダ側壁と、斜め平面状に形成されて前記踏み面の直上に配設された上層階段の裏面との間に設置され、前記下層階踊り場の床面又は上層階踊り場の床面あるいは前記階段の踏み面に、一端を高さ調整可能なジャッキ部を有して当接するように支持されるとともに、他端に前記上層階段の裏面を押圧する押圧部を配設して構成された縦支柱と、前記縦支柱から前記階段ベランダ側壁側に突出した足場台用ステーと、を備えた支持体が構成され、段差を有する少なくとも2段の踏み面に設置された隣り合う前記支持体における前記足場台用ステー上に、作業者が作業する足場台を架け渡して、複数の前記足場台が段状に構成されることを特徴とするものである。   The invention according to claim 3 is a staircase veranda construction scaffolding to be installed on a staircase veranda of a high-rise house, wherein a plurality of treads in a staircase arranged with steps are provided on the uppermost stage. The floor of the upper floor landing arranged on the upper surface side of the tread, the floor of the lower floor landing arranged below the tread arranged at the bottom, the upper floor landing and the lower layer Between the side of the staircase veranda disposed outside the staircase landing between the floor landing and the back of the upper staircase formed in an oblique plane and directly above the tread surface, The floor of the lower floor landing or the floor of the upper floor landing or the tread of the staircase is supported so that one end has a jack portion whose height can be adjusted, and the other end of the upper staircase is supported. A vertical support composed of a pressing part that presses the back surface, and the front A scaffold base stay projecting from a vertical column to the side of the staircase veranda side wall, and the scaffold base stay in the adjacent support body installed on at least two steps of treads having a step. On top of this, a plurality of scaffolding platforms are formed in a step shape across a scaffolding platform on which an operator works.

請求項4記載の発明は、請求項3の発明に係るものであって、前記階段に配設された支持体には、設置された前記縦支柱が立設する踏み面より上段の踏み面から立ち上がって前記縦支柱を支持する補助支柱が配設されていることを特徴としている。   Invention of Claim 4 concerns on invention of Claim 3, Comprising: The support body arrange | positioned at the said staircase WHEREIN: From the tread surface above the tread surface which the said vertical support | pillar installed erects Auxiliary struts that stand and support the vertical struts are provided.

請求項5記載の発明は、請求項2又は4のいずれかの発明に係るものであって、前記押圧部は、前記縦支柱の延長線上に配設されて前記上層階段の裏面を押圧する押圧体と、前記上層階段の裏面の幅方向に沿って、前記押圧体と離れた位置で前記上層階段の裏面を押圧する副押圧体とを備えていることを特徴としている。   Invention of Claim 5 concerns on invention of any one of Claim 2 or 4, Comprising: The said press part is arrange | positioned on the extension line of the said vertical support | pillar, and the press which presses the back surface of the said upper-layer staircase And a sub-pressing body that presses the back surface of the upper layer staircase at a position away from the pressing body along the width direction of the back surface of the upper layer staircase.

請求項6記載の発明は、請求項5の発明に係るものであって、前記押圧体は、前記縦支柱の先端に載設された押圧体ベースに前記上層階段の裏面の傾斜面に沿って回動可能に連結されるとともに、段差を有して隣り合う前記縦支柱に連結補助ステーを介して連結されていることを特徴としている。   The invention according to claim 6 relates to the invention according to claim 5, wherein the pressing body is formed on a pressing body base mounted on a tip of the vertical support along an inclined surface of a back surface of the upper step. It is connected so that it can rotate, and it is connected to the said vertical support | pillar adjacent with a level | step difference via a connection auxiliary stay.

請求項7記載の発明は、請求項5,6の発明に係るものであって、前記副押圧体は、押圧体ベースに摺動可能に配設された副押圧体ベースに回動可能に連結されるとともに、前記補助支柱の一端が連結されていることを特徴としている。   The invention according to claim 7 relates to the invention of claims 5 and 6, wherein the sub-pressing body is rotatably connected to a sub-pressing body base slidably disposed on the pressing body base. In addition, one end of the auxiliary column is connected.

本発明の請求項1の構成によれば、階段の踏み面に一端を当接するとともに段差を有して配設された2本の縦支柱は、それぞれ上端に上層階段の裏面を押圧する押圧部を有している。縦支柱のジャッキ部を操作することにより、縦支柱は、階段ベランダ内で突っ張るように支持され、支持体は縦支柱により強固に支持されることになる。この状態で、段差を有して立設された2基の支持体の各縦支柱には、足場台用ステーが突出して配設され、2本の足場台用ステーに足場台が架け渡されている。したがって、強固に配設された2本の縦支柱に支持された足場台は、段状の階段ベランダであっても強固に配設されることとなって、安心して階段ベランダの外壁を清掃工事することができる。   According to the configuration of the first aspect of the present invention, the two vertical struts having one step abutting against the tread surface of the staircase and having a step are respectively pressed against the back surface of the upper layer staircase. have. By operating the jack portion of the vertical column, the vertical column is supported so as to be stretched in the stair veranda, and the support is firmly supported by the vertical column. In this state, scaffolding stays protrude from each of the vertical supports of the two supports that are erected with a step, and the scaffolding stands are spanned between the two scaffolding stays. ing. Therefore, even if it is a stepped stair veranda, the scaffolding platform supported by the two vertically arranged struts will be firmly placed, and the outer wall of the stair veranda can be safely cleaned. can do.

本発明の請求項2の構成によれば、支持体は、縦支柱が立設された踏み面より上段の踏み面に一端を当接された補助支柱で支持されることにより、さらに階段ベランダ内で強固に支持されることとなる。   According to the configuration of the second aspect of the present invention, the support body is further supported in the stair veranda by being supported by the auxiliary strut whose one end is in contact with the tread surface above the tread surface on which the vertical strut is erected. It will be firmly supported by.

本発明の請求項3の構成によれば、階段ベランダ工事用足場は、段状に配設される複数の踏み面を間にして、下層階踊り場と上層階踊り場との間に複数の踏み面に下端を当接した縦支柱を配設する。それぞれの縦支柱の上端には上層階の階段の裏面を押圧する押圧部が配設され、縦支柱のジャッキ部を操作することにより、各支持体は、縦支柱で階段ベランダの裏面と踏み面との間を突っ張るように支持されることになる。この状態で各縦支柱には、階段ベランダ側壁側に突出した足場台用ステーを配設し、隣り合う足場台用ステーに足場台を架け渡す。これにより、足場台は、下層階踊り場と上層階踊り場との間において複数の足場台が段状に設置されることとなり、階段ベランダにおいても外壁の清掃工事を行うことができる。   According to the configuration of claim 3 of the present invention, the staircase veranda construction scaffold has a plurality of treads arranged in a step shape, and a plurality of treads between the lower floor landing and the upper floor landing. A vertical column having a lower end abutted on is disposed. At the upper end of each vertical strut, a pressing part that presses the back of the upper floor staircase is arranged, and by operating the jack part of the vertical strut, each support is supported by the back of the stair veranda with the vertical strut and the tread surface It will be supported to stretch between. In this state, each vertical column is provided with a scaffold base stay protruding to the side wall of the staircase veranda, and the scaffold base is bridged between adjacent scaffold base stays. Thereby, as for the scaffolding, a plurality of scaffolding will be installed in a step shape between the lower floor landing and the upper floor landing, and the outer wall can be cleaned even on the stairs veranda.

請求項4記載の構成によれば、各支持体は、縦支柱が立設された踏み面より上段の踏み面に一端を当接された補助支柱で支持されることにより、さらに階段ベランダ内で強固に支持されることとなる。   According to the structure of Claim 4, each support body is further supported in the stair veranda by being supported by the auxiliary strut whose one end is in contact with the tread surface above the tread surface on which the vertical strut is erected. It will be firmly supported.

また、請求項5記載の構成によれば、上層階段の裏面を押圧する押圧部は、縦支柱の延長線上に配設された押圧体と、上層階段の裏面の幅方向に沿って、押圧体と離れた位置に配設された副押圧体と、によって上層階段の裏面を押圧するので、各支持体をさらに強固に支持することができる。   Moreover, according to the structure of Claim 5, the press part which presses the back surface of an upper layer step is a press body arrange | positioned on the extension line of a vertical support | pillar, and the width direction of the back surface of an upper layer step. Since the back surface of the upper stairs is pressed by the sub-pressing body disposed at a position apart from each other, each support body can be supported more firmly.

請求項6の構成によれば、縦支柱の先端に配設された押圧体ベースに上層階段の裏面の傾斜面に沿って回動可能に配設された押圧体は、隣り合う縦支柱と連結補助ステーで連結されているから、押圧体で上層階段の裏面を押圧する際に、上層階段の裏面の上方に沿って移動しようとする押圧体を連結補助ステーで抑えることができる。そのため、縦支柱のジャッキ部を調整する際に、上層階段の裏面を押圧する力を、設定した位置に集中させることができる。   According to the structure of Claim 6, the press body arrange | positioned by the press body base arrange | positioned at the front-end | tip of a vertical support | pillar so that rotation along the inclined surface of the back surface of an upper-layer staircase is connected with an adjacent vertical support | pillar. Since it is connected by the auxiliary stay, when pressing the back surface of the upper layer staircase with the pressing body, the pressing body that tries to move along the upper surface of the upper layer staircase can be suppressed by the connection auxiliary stay. Therefore, when adjusting the jack part of a vertical support | pillar, the force which presses the back surface of an upper-layer staircase can be concentrated on the set position.

請求項7の構成によれば、上層階段の裏面の幅方向に沿って押圧体と離れた位置で配設される副押圧体は、補助支柱に連結されていることから上層階段の裏面の上方に沿って移動しようとする副押圧体を補助支柱で抑えることができる。そのため、縦支柱のジャッキ部を調整する際に、上層階段の裏面を押圧する力を、設定した位置に集中させることができる。   According to the structure of Claim 7, since the sub-pressing body disposed at a position away from the pressing body along the width direction of the back surface of the upper layer staircase is connected to the auxiliary strut, it is above the back surface of the upper layer staircase. It is possible to suppress the sub-pressing body that is about to move along the auxiliary strut with the auxiliary strut. Therefore, when adjusting the jack part of a vertical support | pillar, the force which presses the back surface of an upper-layer staircase can be concentrated on the set position.

本発明における実施形態の足場を示す全体正面図である。It is a whole front view which shows the scaffold of embodiment in this invention. 図1の足場の一部を図1の背面から見た斜視図である。It is the perspective view which looked at a part of scaffold of FIG. 1 from the back surface of FIG. 同側面図である。It is the same side view. 一実施形態の押圧体の連結状態を示す支持体構成図である。It is a support body block diagram which shows the connection state of the press body of one Embodiment. 一実施形態の副押圧体の連結状態を示す支持体構成図である。It is a support body block diagram which shows the connection state of the sub-pressing body of one Embodiment. 図3における押圧部を示す拡大図である。It is an enlarged view which shows the press part in FIG. ロックピンを示す組み込み断面図である。It is an assembly sectional view showing a lock pin. 図1における足場台を示す分解斜視図である。It is a disassembled perspective view which shows the scaffold base in FIG. 上踊り場に設置する踊り場足場を示す斜視図である。It is a perspective view which shows the landing scaffold installed in an upper landing. 図9における踊り場足場の正面図である。It is a front view of the landing scaffold in FIG. 図9における踊り場足場の平面図である。It is a top view of the landing scaffold in FIG. 足場を使用して清掃工事を行う状態を示す側面図である。It is a side view which shows the state which performs a cleaning construction using a scaffold.

次に、本発明の工事用足場に係る実施形態を図面に基づいて説明する。本発明の階段ベランダ工事用足場(以下工事用足場という)は、ビル風が吹き付ける超高層住宅に設置する足場として好適に使用できるものであるが、もちろん超高層住宅でなくても、階段ベランダが設置されている高層住宅にも適用することができる。なお、図1に示すように、階段ベランダ1は、階段2における複数の踏み面3と、最下段に配置される踏み面3の下段にある下層階踊り場床面(以下、下踊り場という)4と最上段に配置される踏み面3の上段にある上層階踊り場床面(以下、上踊り場という)5と、下踊り場4と上踊り場5との間に配置されて踏み面3の外側に立設する階段ベランダ側壁(以下、側壁という)7と、複数の踏み面3の上層階段の裏面(以下、斜め天井壁という)9からなるものとする。   Next, an embodiment according to the construction scaffold of the present invention will be described based on the drawings. The stair veranda construction scaffold (hereinafter referred to as construction scaffold) according to the present invention can be suitably used as a scaffold installed in a high-rise house that is blown by a building wind. It can also be applied to installed high-rise housing. As shown in FIG. 1, the stairs veranda 1 includes a plurality of treads 3 in the stairs 2 and a lower floor landing floor (hereinafter referred to as a lower landing) 4 on the lower stage of the tread 3 arranged at the lowest level. And the upper floor landing floor (hereinafter referred to as the upper landing) 5 on the upper stage of the tread 3 arranged at the top, and the lower landing 4 and the upper landing 5 are placed on the outside of the tread 3 It is assumed that it is composed of a staircase veranda side wall (hereinafter referred to as a side wall) 7 to be provided and a back surface (hereinafter referred to as an oblique ceiling wall) 9 of the upper stairs of the plurality of treads 3.

図1は、実施形態の工事用足場(以下、単に足場という)Mの全体正面図であり、図2はその一部を背面から見た斜視図であり、図3はその側面図である。足場Mは、階段2上に設置される単体の階段足場10と、下踊り場4及び上踊り場5上に設置される踊り場足場10A、10Aとを連結して構成されている。また、この足場Mは、超高層住宅で作業を行うために、例えば、ビル風にあおられても、傾くことなくまた落下することのないように、階段ベランダ1に強固に支持されて安全な作業を行えるように構成されている。   FIG. 1 is an overall front view of a construction scaffold (hereinafter, simply referred to as a scaffold) M according to an embodiment, FIG. 2 is a perspective view of a part thereof viewed from the back, and FIG. 3 is a side view thereof. The scaffold M is configured by connecting a single stair scaffold 10 installed on the stairs 2 and landing scaffolds 10A and 10A installed on the lower landing 4 and the upper landing 5. In addition, since the scaffold M is used for work in a super high-rise house, for example, even if it is covered with a building wind, it is firmly supported by the staircase veranda 1 so that it does not tilt and does not fall. It is configured to work.

階段2上に設置される階段足場10は、図1〜3に示すように、2段の踏み面3、3に立設して配置された一対の支持体11、11と、一対の支持体11、11から離れた位置で側壁7の外方に位置する足場台16を備えて構成されている。各支持体11は、段状に配置された踏み面3に下端部を当接し、上端部に斜め天井壁9を押圧する押圧部13を装着した縦支柱12と、下端を上段の踏み面3に当接させて押圧部13に連結された補助支柱14と、縦支柱12から、側壁7側に向かって突出する前述の足場台用ステー15とを備えて構成されている。足場台16は、複数の足場台用ステー15上に架け渡されている。   As shown in FIGS. 1 to 3, the stair scaffolding 10 installed on the staircase 2 includes a pair of support bodies 11 and 11 that are erected on the two-step treads 3 and 3, and a pair of support bodies. 11 and 11 are provided with a scaffolding base 16 positioned outside the side wall 7 at a position away from the side wall 11. Each support body 11 has a lower end abutted against a stepped surface 3 arranged in a step shape, and a vertical column 12 having a pressing portion 13 that presses the oblique ceiling wall 9 on the upper end, and a lower end with an upper stepped surface 3. The support column 14 is connected to the pressing part 13 in contact with the pressing unit 13, and the above-described scaffolding stay 15 protrudes from the vertical column 12 toward the side wall 7. The scaffold base 16 is bridged over a plurality of scaffold base stays 15.

実施形態における縦支柱12は、角筒状に形成された支柱本体121と支柱本体121の下部に配置されるジャッキ部122とからなる。縦支柱12の上部には、押圧部13が構成されている。また、縦支柱12には、上端部と中間部との2箇所において足場台用ステー15の元部が装着されている。足場台用ステー15の元部には角筒状の支柱本体121を摺動可能に外嵌する装着部151が形成されている。なお、支柱本体121においては、その長さが長くてエレベータに入らない場合には、長さ方向に対して2分割して形成してもよい。ジャッキ部122は、縦支柱12の高さ調整を可能として縦支柱12の先端に配置された押圧部13を斜め天井壁9に押し付けることができるように構成されている。ジャッキ部122は、雄ネジ部を有するネジ棒122aとネジ棒122aに螺合するナット部材122bとを有し、下端部に踏み面3又は下踊り場4に当接するフランジ板123が装着されている。   The vertical column 12 in the embodiment includes a column main body 121 formed in a rectangular tube shape and a jack portion 122 disposed at a lower portion of the column main body 121. A pressing portion 13 is formed on the upper portion of the vertical column 12. In addition, the vertical struts 12 are provided with base portions of scaffolding stays 15 at two locations, an upper end portion and an intermediate portion. A mounting portion 151 for slidably fitting a square cylindrical column main body 121 is formed at the base portion of the scaffold base stay 15. In addition, in the support | pillar main body 121, when the length is long and it does not enter an elevator, you may divide | segment into 2 with respect to the length direction. The jack portion 122 is configured so that the height of the vertical column 12 can be adjusted and the pressing portion 13 disposed at the tip of the vertical column 12 can be pressed against the oblique ceiling wall 9. The jack portion 122 includes a screw rod 122a having a male screw portion and a nut member 122b that is screwed to the screw rod 122a, and a flange plate 123 that contacts the tread surface 3 or the lower landing 4 is attached to the lower end portion. .

図4〜6に示すように、押圧部13は、縦支柱12の上端部で、縦支柱12から斜め天井壁9の幅方向に向かって延設される角筒状の押圧体ベース131と、押圧体ベース131内を摺動可能な角筒状のスライダ132と、斜め天井壁9を押圧する押圧体134とを備えている。押圧体134は、斜め天井壁9に接触して押圧可能な矩形板状の押圧板134aと押圧板134aから押圧体ベース131側に向かって突出する取付け片134bとを有して形成され、取付け片134bが押圧体ベース131から上方に突出した一対の突出片133に回動可能に取付けられている。そして押圧板134aを斜め天井壁9の傾斜角度に合わせて回動することによって、押圧板134aにおける斜め天井壁9との接触面が全面接触できるように形成されている。なお、図4、6に示すように、押圧体134の取付け片134bには、上段に配置されて階段足場10を構成する一方の縦支柱12の上端部あたりで一端が装着された連結補助ステー19の他端が装着されている。これにより、押圧体134で斜め天井壁9を押圧する際に、斜め天井壁9の上方に沿って移動しようとする押圧体134を連結補助ステー19で抑えることができる。そのため、縦支柱12のジャッキ部122をネジ調整する際に、斜め天井壁9を押圧する力を、設定した位置に集中させることができる。   As shown in FIGS. 4 to 6, the pressing portion 13 is an upper end portion of the vertical column 12, a rectangular tube-shaped pressing body base 131 extending from the vertical column 12 toward the width direction of the oblique ceiling wall 9, A rectangular cylindrical slider 132 that can slide in the pressing body base 131 and a pressing body 134 that presses the oblique ceiling wall 9 are provided. The pressing body 134 is formed to have a rectangular plate-shaped pressing plate 134a that can be pressed by contacting the oblique ceiling wall 9, and an attachment piece 134b that protrudes from the pressing plate 134a toward the pressing body base 131. The piece 134b is rotatably attached to a pair of protruding pieces 133 protruding upward from the pressing body base 131. Then, the pressing plate 134a is formed so that the contact surface of the pressing plate 134a with the inclined ceiling wall 9 can be brought into full contact with the inclined ceiling wall 9 by rotating according to the inclination angle of the inclined ceiling wall 9. As shown in FIGS. 4 and 6, the attachment piece 134 b of the pressing body 134 has a connection auxiliary stay with one end attached to the upper end of one vertical column 12 that is arranged in the upper stage and constitutes the stair scaffolding 10. The other end of 19 is mounted. Thereby, when the diagonal ceiling wall 9 is pressed by the pressing body 134, the pressing body 134 that attempts to move along the upper side of the diagonal ceiling wall 9 can be suppressed by the connection auxiliary stay 19. Therefore, when adjusting the screw of the jack portion 122 of the vertical column 12, the force for pressing the oblique ceiling wall 9 can be concentrated at the set position.

連結補助ステー19には、中間部にネジ調整可能なジャッキ部191が配置されて、階段足場10を構成する一対の縦支柱12、12間における連結補助ステー19の適度な突っ張り力を付与するように構成されている。   The connection auxiliary stay 19 is provided with a jack portion 191 that can be screw-adjusted at an intermediate portion so as to give an appropriate tension force of the connection auxiliary stay 19 between the pair of vertical struts 12 and 12 constituting the stair scaffolding 10. It is configured.

また、図6に示すように、スライダ132には、押圧体ベース131からベランダ室内側に向かって離れた位置に角筒状の副押圧体ベース135がスライダ132に摺動可能に外嵌されている。図5に示すように、副押圧体ベース135の上方には、副押圧体137が斜め天井壁9を押圧可能に配置されている。副押圧体137は、押圧体134と同様、斜め天井壁9に接触して押圧可能な矩形板状の押圧板137aと押圧板137aから副押圧体ベース135側に向かって突出する取付け片137bとを有して形成され、取付け片137bが副押圧体ベース135から上方に突出した一対の突出片136に回動可能に取付けられている。そして押圧板137aを斜め天井壁9の傾斜角度に合わせて回動することによって、押圧板137aにおける斜め天井壁9との接触面が全面接触できるように形成されている。なお、スライダ132は、押圧体ベース131に摺動可能に配置されていることから、副押圧体ベース135を、斜め天井壁9の適宜な位置で押圧することができる。そして、位置決定がなされると、押圧体ベース131とスライダ132、スライダ132と副押圧体ベース135とは、それぞれ図7に示すロックピン17で固着される。   In addition, as shown in FIG. 6, a square cylindrical sub-pressing body base 135 is slidably fitted to the slider 132 at a position away from the pressing body base 131 toward the veranda chamber side. Yes. As shown in FIG. 5, a sub-pressing body 137 is disposed above the sub-pressing body base 135 so as to press the oblique ceiling wall 9. Similar to the pressing body 134, the sub pressing body 137 is a rectangular plate-shaped pressing plate 137a that can be pressed in contact with the oblique ceiling wall 9, and a mounting piece 137b that protrudes from the pressing plate 137a toward the sub pressing body base 135 side. The attachment piece 137b is rotatably attached to a pair of protruding pieces 136 protruding upward from the sub-pressing body base 135. Then, the pressing plate 137a is formed so that the contact surface of the pressing plate 137a with the oblique ceiling wall 9 can be brought into full contact by rotating according to the inclination angle of the oblique ceiling wall 9. Since the slider 132 is slidably disposed on the pressing body base 131, the sub pressing body base 135 can be pressed at an appropriate position on the oblique ceiling wall 9. When the position is determined, the pressing body base 131 and the slider 132, and the slider 132 and the auxiliary pressing body base 135 are fixed by the lock pins 17 shown in FIG.

なお、図5、図6に示すように、副押圧体137の取付け片137bには、補助支柱14の一端が装着されている。補助支柱14は、縦支柱12が支持される踏み面3の上段の踏み面3に下端部が当接支持され、押圧部13の副押圧体137の取付け片137bに連結されている。補助支柱14は、副押圧体137と踏み面3との間を突っ張るように支持するために、ジャッキ部143を間にして先端側に配置される第1パイプ部141と元部側に配置される第2パイプ部142を分割して構成されている。   As shown in FIGS. 5 and 6, one end of the auxiliary column 14 is attached to the attachment piece 137 b of the sub-pressing body 137. The auxiliary strut 14 is supported at its lower end by the upper tread surface 3 of the tread surface 3 on which the vertical strut 12 is supported, and is connected to the attachment piece 137 b of the sub-pressing body 137 of the pressing portion 13. The auxiliary strut 14 is disposed on the base portion side and the first pipe portion 141 disposed on the distal end side with the jack portion 143 interposed therebetween in order to support the auxiliary pressing body 137 so as to stretch between the sub pressing body 137 and the tread surface 3. The second pipe portion 142 is divided.

補助支柱14は、縦支柱12に対して斜め方向に配置されることから、第2パイプ部142の下端部は踏み面3の角部を押圧するために、L字状のアングル支持部材144を介して踏み面3に当接されている。ジャッキ部143には、第1パイプ部141の下端部に第1アジャスタ145が螺合されて第1パイプ部141を高さ調整可能とし、第2パイプ部142の上端部に第2アジャスタ146が螺合されて第2パイプ部142を高さ調整可能としている。これにより斜め天井壁9の上方に沿って移動しようとする副押圧体137を補助支柱14で抑えることができる。そのため、縦支柱12のジャッキ部122を調整する際に、斜め天井壁9を押圧する力、を設定した位置に集中させることができる。また、補助支柱14のアングル支持部材144と縦支柱12の支柱本体121とは、それぞれ耳片144a、121dを介してタンパックル18で連結されている。   Since the auxiliary support column 14 is disposed obliquely with respect to the vertical support column 12, the lower end portion of the second pipe portion 142 is provided with an L-shaped angle support member 144 in order to press the corner portion of the tread surface 3. Via the tread surface 3. A first adjuster 145 is screwed to the lower end portion of the first pipe portion 141 so that the height of the first pipe portion 141 can be adjusted, and a second adjuster 146 is provided at the upper end portion of the second pipe portion 142. The height of the second pipe portion 142 can be adjusted by screwing. As a result, the auxiliary pressing body 137 trying to move along the upper side of the oblique ceiling wall 9 can be suppressed by the auxiliary column 14. Therefore, when adjusting the jack part 122 of the vertical support | pillar 12, the force which presses the diagonal ceiling wall 9 can be concentrated on the set position. Further, the angle support member 144 of the auxiliary column 14 and the column main body 121 of the vertical column 12 are connected to each other by the tampackle 18 via ear pieces 144a and 121d.

実施形態のロックピン17には、図7に示すように、頭部171と胴体部172との間に磁石173が装着されて、例えば、押圧体ベース131のいずれかの挿通孔131a、スライダ132のいずれかの挿入孔132aに挿通すると磁石173が押圧体ベース131に吸着されてロックピン17が固定される。   As shown in FIG. 7, the lock pin 17 according to the embodiment is provided with a magnet 173 between the head 171 and the body portion 172, for example, one of the insertion holes 131 a of the pressing body base 131 and the slider 132. When one of the insertion holes 132a is inserted, the magnet 173 is attracted to the pressing body base 131 and the lock pin 17 is fixed.

足場台用ステー15は、図3に示すように、一端を縦支柱12の支柱本体121上に外嵌して側壁7の外方に向かって突出されている。つまり、図8に示すように、足場台用ステー15の元部には、支柱本体121に外嵌する角パイプで形成された装着部151と装着部151から側壁7の外方に延設するアーム部152とが形成されている。装着部151には、支柱本体121を外嵌する嵌合孔151aとアーム部152の元部を嵌合する溝部151bが形成されている。また、支柱本体121には、挿通孔121cが複数形成され、装着部151の側部に形成された挿通孔151cと支柱本体121のいずれかの挿通孔121cに、ロックピン17が挿通される。ロックピン17を挿通することにより、足場台用ステー15と支柱本体121とが固定されることとなる。   As shown in FIG. 3, one end of the scaffolding stay 15 is fitted onto the column main body 121 of the vertical column 12 and protrudes outward from the side wall 7. That is, as shown in FIG. 8, the base portion of the scaffolding stay 15 is extended to the outside of the side wall 7 from the mounting portion 151 and the mounting portion 151 formed by a square pipe that is externally fitted to the column main body 121. An arm portion 152 is formed. The mounting portion 151 is formed with a fitting hole 151 a for fitting the column main body 121 and a groove portion 151 b for fitting the base portion of the arm portion 152. In addition, a plurality of insertion holes 121 c are formed in the column main body 121, and the lock pin 17 is inserted into one of the insertion holes 151 c formed in the side portion of the mounting portion 151 and the insertion hole 121 c of the column main body 121. By inserting the lock pin 17, the scaffold base stay 15 and the column main body 121 are fixed.

アーム部152には、先端面に後述の手摺20のストッパとなるストッパ片153が配置され、先端部側面にアーム部152の両側部から突出するボス部154が配置されている。また、アーム部152の装着部付近に、ロックピン17が挿通する挿通孔152aが形成されている。   In the arm portion 152, a stopper piece 153 serving as a stopper of a handrail 20 described later is disposed on the distal end surface, and a boss portion 154 protruding from both sides of the arm portion 152 is disposed on the side surface of the distal end portion. Further, an insertion hole 152 a through which the lock pin 17 is inserted is formed in the vicinity of the mounting portion of the arm portion 152.

なお、足場台用ステー15は、段差のある両隣の支持体11に足場台16を架け渡すために、1本の縦支柱12に上下方向に2個配置されることになる。足場台用ステー15の装着部151を縦支柱12の支柱本体121に外嵌させて、支柱本体121に形成された挿通孔121cと装着部151の複数の嵌合孔151aのいずれか1個とを一致させてロックピン17でロックすることになる。この位置は、支柱本体121の上端部付近と中間部に配置されることになるが、足場台16を水平状態に維持するために、装着部151の位置は、階段における踏み面3の段差高さ及びジャッキ部122の高さ調整によって決定される。   Note that two scaffolding stays 15 are arranged in the vertical direction on one vertical column 12 in order to bridge the scaffolding 16 to the adjacent support bodies 11 having steps. The mounting portion 151 of the scaffold base stay 15 is externally fitted to the column main body 121 of the vertical column 12, and the insertion hole 121c formed in the column main body 121 and any one of the plurality of fitting holes 151a of the mounting unit 151 And are locked by the lock pin 17. This position is arranged in the vicinity of the upper end portion and the middle portion of the column main body 121. In order to maintain the scaffold base 16 in a horizontal state, the position of the mounting portion 151 is set to a step height of the tread surface 3 on the stairs. It is determined by adjusting the height of the jack portion 122.

図8に示すように、隣り合う2本の縦支柱12の足場台用ステー15には足場台16が架け渡されている。また、足場台16を囲むように手摺20及び安全カバー21が装着され、さらに足場台16と階段2との間には、隙間カバー22が装着され、足場台16に搭乗するための階段ステップ23が懸吊されている。   As shown in FIG. 8, a scaffold base 16 is bridged between the scaffold base stays 15 of the two adjacent vertical struts 12. A handrail 20 and a safety cover 21 are mounted so as to surround the scaffold base 16, and a gap cover 22 is mounted between the scaffold base 16 and the stairs 2, and a stair step 23 for boarding the scaffold base 16. Is suspended.

手摺20は、一対の足場台用ステー15のアーム部152の先端が水平方向に広がることを防止するためのステー嵌合溝部201aを4隅に備えるステー支持部201と、ステー支持部201の上方に配置されてそれぞれのステー嵌合溝部201aの内側面に溶着され複数の横支柱202aを有する防護柵202と、から構成されている。防護柵202は、階段ベランダ1側を除いた三方から作業者を囲むことができるように配置されている。防護柵202の内側面には、防護柵202と同様、階段ベランダ1側を除いた3方から作業者を囲むことができる板状の安全カバー21が装着されている。安全カバー21の下端部には、足場台16を装着するための雌ネジ金具211が4箇所に配置されている。   The handrail 20 includes a stay support portion 201 having four corners of stay fitting groove portions 201a for preventing the distal ends of the arm portions 152 of the pair of scaffolding stays 15 from spreading in the horizontal direction, and an upper portion of the stay support portion 201. And a guard fence 202 having a plurality of lateral struts 202a welded to the inner side surface of each stay fitting groove 201a. The protective fence 202 is arranged so as to be able to surround the worker from three sides except the stair veranda 1 side. On the inner side surface of the protective fence 202, a plate-shaped safety cover 21 that can surround the operator from three sides except for the stair veranda 1 side is mounted similarly to the protective fence 202. At the lower end portion of the safety cover 21, female screw fittings 211 for mounting the scaffold base 16 are arranged at four locations.

足場台16は、手摺20及び安全カバー21内に挿入して配置される。足場台16はプレート本体161と、プレート本体161の前後端に、一対の足場台用ステー15のアーム部152に嵌合する嵌合溝164を形成したそれぞれ一対の装着金具162、163と、を備えている。プレート本体161の元部側に配置されている一対の装着金具162には、ロックピン17が挿通する挿通孔162aが形成されている。プレート本体161の外方先端側に配置されている一対の装着金具163には、アーム部152の側面に配置されたボス部154の厚み方向に係合する係合溝163aが形成されている。なお、プレート本体161の元部側上面には階段ステップ23を支持する元部プレート165が装着され、元部プレート165には階段ステップ23の上端のステップ231Aを掛止する掛止部165aが配置されている。プレート本体161には、安全カバー21の雌ネジ金具211に螺合する蝶ネジ24を挿通するためのネジ挿通孔161aが4箇所に形成されている。   The scaffold base 16 is inserted and arranged in the handrail 20 and the safety cover 21. The scaffold base 16 includes a plate main body 161 and a pair of mounting brackets 162 and 163 each having a fitting groove 164 formed in the front and rear ends of the plate main body 161 and fitted to the arm portion 152 of the pair of scaffold base stays 15. I have. An insertion hole 162 a through which the lock pin 17 is inserted is formed in the pair of mounting brackets 162 arranged on the base side of the plate body 161. An engagement groove 163 a that engages in the thickness direction of the boss portion 154 disposed on the side surface of the arm portion 152 is formed in the pair of mounting brackets 163 disposed on the outer front end side of the plate body 161. In addition, a base plate 165 that supports the stair step 23 is mounted on the top surface of the base of the plate body 161, and a hook 165a that hooks the step 231A at the upper end of the stair step 23 is disposed on the base plate 165. Has been. The plate body 161 is formed with four screw insertion holes 161a through which the thumbscrews 24 to be screwed into the female screw fitting 211 of the safety cover 21 are inserted.

階段ステップ23には、足場台16を登降するための複数のステップ231が、両側に配置された手摺棒232、232に支持されている。最上段のステップ231Aは元部プレート165の掛止部165aに掛止されている。   In the stair step 23, a plurality of steps 231 for ascending and descending the scaffold base 16 are supported by handrail bars 232, 232 arranged on both sides. The uppermost step 231A is hooked on the hooking portion 165a of the base plate 165.

また、階段2の側壁7上面から足場台16のプレート本体161との間の隙間には、作業者又は道具の進入を防止するための樹脂製の隙間カバー22が装着されている。隙間カバー22は、階段ステップ23と足場台16との間に配置されて、元部プレート165上に載置する上面部221と上面部221から直下に延設する側面部222とでL字状に形成されている。また、隙間カバー22における元部プレート165の掛止部165aに切り欠き部223を形成している。さらに、側面部222の下面は、階段2の傾斜角度に合わせて傾斜して形成され、側面部222の裏面側には隙間カバー22がぐらつかないように側壁7に当接して支持される支持部222aが配置されている。   Further, a resin gap cover 22 for preventing an operator or a tool from entering is installed in the gap between the upper surface of the side wall 7 of the staircase 2 and the plate body 161 of the scaffold base 16. The gap cover 22 is disposed between the stair step 23 and the scaffolding base 16, and has an L shape with an upper surface portion 221 placed on the base plate 165 and a side surface portion 222 extending directly below the upper surface portion 221. Is formed. Further, a notch 223 is formed in the latching portion 165 a of the base plate 165 in the gap cover 22. Further, the lower surface of the side surface portion 222 is formed to be inclined in accordance with the inclination angle of the staircase 2, and the support portion is supported by contacting the side wall 7 so that the gap cover 22 does not wobble on the back surface side of the side surface portion 222. 222a is arranged.

図1及び図9〜11に示すように、下踊り場4又は上踊り場5に設置される踊り場足場10Aは、階段足場10の延長線上に配置される支持体11A1と、階段足場10の支持体11と支持体11A1とを結ぶ線上に対して直交して配置される支持体11A2を備えている。図9〜11は上踊り場5における踊り場足場10Aを説明するものであり、下踊り場4に設置される踊り場足場10Aも同様に構成されている。上踊り場5の周りには、階段2の側壁7から延設する側壁7A1(7A)と階段2の正面側に配置されて側壁7と直交する正面側壁7A2(7A)とが形成され、上部には水平面状の踊り場天井壁9Aが形成されている。   As shown in FIGS. 1 and 9 to 11, a landing scaffold 10 </ b> A installed in the lower landing 4 or the upper landing 5 includes a support 11 </ b> A <b> 1 arranged on an extension line of the stair scaffold 10 and a support 11 of the stair scaffold 10. And a support 11A2 arranged orthogonal to a line connecting the support 11A1 and the support 11A1. 9 to 11 illustrate the landing scaffold 10A in the upper landing 5 and the landing scaffold 10A installed in the lower landing 4 is configured similarly. Around the upper landing 5 are formed a side wall 7A1 (7A) extending from the side wall 7 of the stairs 2 and a front side wall 7A2 (7A) arranged on the front side of the stairs 2 and orthogonal to the side wall 7, A horizontal landing plate ceiling wall 9A is formed.

それぞれの支持体11A(11A1、11A2)は、それぞれ同一踊り場5上から立設する縦支柱12A(12A1、12A2)と、各縦支柱12Aの上方に配置されるとともに各縦支柱12Aどうしを連結する支柱連結部13A(13A1、13A2)と、縦支柱12Aと支柱連結部13Aとの間に配置されて支柱連結部13Aを踊り場天井壁9A側に向かって押圧する連結ジャッキ部31A(31A1、31A2)と、縦支柱12Aからそれぞれ上踊り場5の側壁7A1、正面側壁7A2から外側に突出して縦支柱12Aに装着される足場台用ステー15A(15A1、15A2)と備えている。支持体11A1の足場台用ステー15A1と支持体11A2の足場台用ステー15A2とは直交する方向に延設されている。なお、下踊り場4又は上踊り場5に配置される足場台用ステー15A1は、階段2に設置される階段足場10における足場台用ステー15と同様の構成である。   Each support 11A (11A1, 11A2) is disposed above each vertical support 12A and is connected to each vertical support 12A, and the vertical support 12A (12A1, 12A2) standing from the same landing 5 respectively. Supporting jack portion 31A (31A1, 31A2) arranged between support post 13A (13A1, 13A2) and vertical support post 12A and support post connecting portion 13A to press support post connecting portion 13A toward landing ceiling wall 9A. And scaffolding stays 15A (15A1, 15A2) mounted on the vertical struts 12A so as to protrude outward from the vertical struts 12A and the side walls 7A1 and 7A2 of the upper landing 5 respectively. The scaffold base stay 15A1 of the support 11A1 and the scaffold base stay 15A2 of the support 11A2 extend in a direction orthogonal to each other. The scaffold base stay 15A1 arranged in the lower landing 4 or the upper landing 5 has the same configuration as the scaffold base stay 15 in the stair scaffold 10 installed in the stairs 2.

この踊り場足場10Aは、上踊り場5における下踊り場4から上踊り場5に向かって延設する側に1セット設置(図9に示されている状態)され、上踊り場5における上踊り場5から上層階の下踊り場4に向かう側に1セット設置(図9には図示されていない)されている。したがって、踊り場足場10Aにおける足場台用ステー15A1は階段2上に設置された最上端の支持体11に配置された足場台用ステー15と同じ高さに設定されて、足場台16A1(16A)が懸架されることになる。また、上踊り場5の正面側壁7Aから外方に突出する一対の足場台用ステー15A2上には足場台16A2(16A)が懸架されることになる。なお、足場台16Aは、階段2に設置される階段足場10における足場台用ステー15と同様の構成である。   The landing platform 10A is installed on the side extending from the lower landing 4 to the upper landing 5 in the upper landing 5 (the state shown in FIG. 9), and the upper landing 5 from the upper landing 5 to the upper floor. One set is installed on the side toward the lower landing 4 (not shown in FIG. 9). Accordingly, the scaffold base stay 15A1 in the landing platform 10A is set to the same height as the scaffold base stay 15 disposed on the uppermost support 11 installed on the stairs 2, and the scaffold base 16A1 (16A) is provided. It will be suspended. Further, the scaffold base 16A2 (16A) is suspended on the pair of scaffold base stays 15A2 protruding outward from the front side wall 7A of the upper landing 5. The scaffold base 16 </ b> A has the same configuration as the scaffold base stay 15 in the stair scaffold 10 installed on the stairs 2.

支柱連結部13Aには、上面を踊り場天井壁9Aに当接して押圧する角筒状の押圧パイプ32A(32A1、32A2)が配置されて、押圧パイプ32A内に、断面正方形で平面視十字状に形成された十字状クロスアーム33の一部を、角筒状のスライドパイプ34A(34A1,34A2)を介して内嵌可能としている。縦支柱12Aは、階段2に設置される縦支柱12と同様、支柱本体121Aと支柱本体121Aを昇降可能に調整するジャッキ部122A(122A1、122A2)とを備えている。ジャッキ部122Aに配置されたネジ部を回すことにより、支柱本体121Aを上昇可能にして押圧パイプ32Aで踊り場天井壁9Aを押圧することができる。なお、押圧パイプ32A1の上面に緩衝部材を設けて踊り場天井壁9Aを押圧するようにしてもよい。なお、実施形態においては、縦支柱12Aを階段2上に配置する縦支柱12を使用して支柱連結部13Aとの間に連結ジャッキ部31A(31A1,31A2)を配置するようにしている。   The column connecting portion 13A is provided with a rectangular tube-shaped pressing pipe 32A (32A1, 32A2) that presses the upper surface in contact with the landing ceiling wall 9A. The pressing pipe 32A has a square cross section and a cross shape in plan view. A part of the formed cross-shaped cross arm 33 can be internally fitted via a square cylindrical slide pipe 34A (34A1, 34A2). The vertical column 12A includes a column main body 121A and a jack portion 122A (122A1, 122A2) that adjusts the column main body 121A so that the column main body 121A can be moved up and down, similarly to the vertical column 12 installed on the stairs 2. By turning the screw part arranged in the jack part 122A, the support body 121A can be raised and the landing wall 9A can be pressed by the pressing pipe 32A. A buffer member may be provided on the upper surface of the pressing pipe 32A1 to press the landing ceiling wall 9A. In the embodiment, the connecting jack portion 31A (31A1, 31A2) is arranged between the supporting column connecting portion 13A and the supporting column connecting portion 13A using the vertical supporting column 12 that arranges the vertical supporting column 12A on the stairs 2.

連結ジャッキ部31Aは、それぞれ、雄ネジ部311と、縦支柱12A1、12A2側に配置されて雄ネジ部311に螺合する下ナット部312と、支柱連結側31A1、31A2側に配置されて雄ネジ部311に螺合する上ナット部313とから構成されている。下ナット部312には、アジャスタ314が装着されて、支柱連結部13Aを踊り場天井壁9A側に押圧調整できるようにしている。   The connection jack portion 31A includes a male screw portion 311, a lower nut portion 312 that is disposed on the vertical struts 12A1 and 12A2 side and is screwed into the male screw portion 311, and a male side that is disposed on the strut connection side 31A1 and 31A2 side. The upper nut portion 313 is screwed into the screw portion 311. An adjuster 314 is attached to the lower nut portion 312 so that the strut connecting portion 13A can be pressed and adjusted toward the landing ceiling wall 9A.

また、押圧パイプ32Aと、スライドパイプ34A及び十字状クロスアーム33には、それぞれ図示しない挿通孔が十字状クロスアーム33の挿入方向に沿って複数形成され、挿通孔内に前述のロックピン17が挿通される。ロックピン17をスライドパイプ34Aの挿通孔の適宜な位置に挿通することによって、十字状クロスアーム33を適宜な位置に配置可能にしている。   Further, a plurality of insertion holes (not shown) are formed in the pressing pipe 32A, the slide pipe 34A, and the cross-shaped cross arm 33 along the insertion direction of the cross-shaped cross arm 33, and the lock pin 17 described above is formed in the insertion hole. It is inserted. The cross-shaped cross arm 33 can be disposed at an appropriate position by inserting the lock pin 17 into an appropriate position of the insertion hole of the slide pipe 34A.

次に、上述のように構成された足場Mの組立手順や外壁工事の作業手順について説明する。   Next, the assembly procedure of the scaffold M configured as described above and the work procedure of the outer wall construction will be described.

まず、作業を行う階層に、分割された複数の階段足場10、踊り場足場10Aのそれぞれの部位をエレベータによって運搬する。分割された部位は、縦支柱12、12Aや足場台用ステー15、15A、足場台16、16A、補助支柱14、140、押圧部13、支柱連結部13A等の各分割体であり、全てエレベータに収納できる大きさに形成されている。   First, the respective parts of the plurality of divided stair scaffolds 10 and landing scaffolds 10A are transported by elevator to the level where work is performed. The divided parts are the divided bodies such as the vertical struts 12 and 12A, the scaffolding stays 15 and 15A, the scaffolding bases 16 and 16A, the auxiliary struts 14 and 140, the pressing portion 13 and the strut connecting portion 13A, all of which are elevators. It is formed in a size that can be stored in the box.

上記の部位を階段ベランダ1内に持ち運んだ後、階段2に複数の階段足場10、下踊り場4及び上踊り場5に踊り場足場10Aを組み立てる。階段2上に設置する階段足場10は、支柱本体121、ジャッキ部122を組み付けて縦支柱12を形成した後、足場台用ステー15を縦支柱12に組みつけて支柱本体121の上端に押圧部13を装着する。フランジ板123を踏み面3に当て、押圧部13の押圧体134を斜め天井壁9の傾斜角度に合わせて斜め天井壁9に当接させる。ジャッキ部122を操作して縦支柱12を踏み面3と斜め天井壁9との間で押圧して突っ張らせる。また、段差を有して隣り合わせに配置された縦支柱12、12間に連結補助ステー19を組みつけて、押圧部13の斜め上方への移動を防止させる。さらに縦支柱12を支持するための補助支柱14を取付けて、支持体11を構成する。また、下踊り場4及び上踊り場5に設置する踊り場足場10Aにおいて、縦支柱12A、連結ジャッキ部31A、支柱連結部13Aを組み付けて下踊り場4、上踊り場5と踊り場天井壁9A間で押圧して突っ張らせる。下踊り場4、上踊り場5においては、縦支柱12Aと支柱連結部13Aとの間に配置された連結ジャッキ部31Aを調整することにより、踊り場天井壁9Aを押圧する。この支持体11、11Aを、階段2、下踊り場4、上踊り場5に設置することによって、階段2及び下踊り場4、上踊り場5に足場台16、16Aのない足場Mが構成される。その後、同じ高さに配置された一対の足場台用ステー15上に手摺20、安全カバー21を上層階から懸吊して足場台用ステー15、15Aに取付ける。つまり、手摺20のステー支持部201を一対の足場台用ステー15、15Aのアーム部152に嵌合し、先端のステー支持部201の先端面を足場台用ステー15のストッパ片153に当接させて位置決めをする。そして安全カバー21を手摺20の防護柵202内に収納する。   After carrying the above part into the staircase veranda 1, the landing scaffold 10 </ b> A is assembled to the plurality of stair scaffolds 10, the lower landing 4, and the upper landing 5 on the stairs 2. The stair scaffolding 10 installed on the staircase 2 is formed by assembling the column main body 121 and the jack portion 122 to form the vertical column 12, and then assembling the scaffolding base stay 15 to the vertical column 12 to press the upper end of the column main body 121. 13 is installed. The flange plate 123 is brought into contact with the tread surface 3, and the pressing body 134 of the pressing portion 13 is brought into contact with the oblique ceiling wall 9 according to the inclination angle of the oblique ceiling wall 9. The jack part 122 is operated and the vertical support 12 is pressed and stretched between the tread surface 3 and the oblique ceiling wall 9. Moreover, the connection auxiliary stay 19 is assembled | attached between the vertical support | pillars 12 and 12 which have a level | step difference and are arrange | positioned adjacently, and the movement of the press part 13 diagonally upward is prevented. Further, an auxiliary column 14 for supporting the vertical column 12 is attached to constitute the support 11. In addition, in the landing scaffold 10A installed in the lower landing 4 and the upper landing 5, the vertical support 12A, the connecting jack 31A, and the support connecting part 13A are assembled and pressed between the lower landing 4, the upper landing 5 and the landing ceiling wall 9A. Stretch. In the lower landing 4 and the upper landing 5, the landing wall 9 </ b> A is pressed by adjusting the connecting jack portion 31 </ b> A disposed between the vertical support 12 </ b> A and the support connecting portion 13 </ b> A. By installing the supports 11 and 11A on the stairs 2, the lower landing 4 and the upper landing 5, the stairway 2, the lower landing 4 and the upper landing 5 constitute a scaffold M without the scaffolding platforms 16 and 16A. Thereafter, the handrail 20 and the safety cover 21 are suspended from the upper floor on the pair of scaffolding stays 15 arranged at the same height, and attached to the scaffolding stays 15 and 15A. That is, the stay support portion 201 of the handrail 20 is fitted to the arm portion 152 of the pair of scaffolding stays 15 and 15A, and the distal end surface of the stay supporting portion 201 at the distal end is brought into contact with the stopper piece 153 of the scaffolding stay 15. To position. Then, the safety cover 21 is stored in the protective fence 202 of the handrail 20.

次に、足場台16、16Aを架け渡す。足場台16、16Aの一対の装着金具162を足場台用ステー15のアーム部152に嵌合させ、一対の装着金具163をアーム部152のボス部154に嵌め込む。同時にプレート本体161を安全カバー21内に収納する。そして4本の蝶ネジ24をプレート本体161のネジ挿通孔161aに挿通させて安全カバー21の雌ネジ金具211に係合させて、足場台16、16Aを手摺20に固定する。さらに、足場台用ステー15、15Aの挿通孔152aと足場台16の装着金具162の挿通孔162aを一致させてロックピン17を挿通する。これによって、足場台16、16Aは、安全カバー21に固定されるとともに足場台用ステー15、15Aにも一体的に固定される。   Next, the scaffold bases 16 and 16A are bridged. The pair of mounting brackets 162 of the scaffolding bases 16 and 16A are fitted into the arm portion 152 of the scaffolding base stay 15, and the pair of mounting brackets 163 are fitted into the boss portions 154 of the arm portion 152. At the same time, the plate body 161 is accommodated in the safety cover 21. Then, the four thumbscrews 24 are inserted into the screw insertion holes 161 a of the plate body 161 and engaged with the female screw fitting 211 of the safety cover 21, and the scaffold bases 16 and 16 A are fixed to the handrail 20. Further, the lock pin 17 is inserted by aligning the insertion holes 152a of the scaffolding stays 15 and 15A with the insertion holes 162a of the mounting bracket 162 of the scaffolding base 16. As a result, the scaffolding bases 16 and 16A are fixed to the safety cover 21 and are also integrally fixed to the scaffolding base stays 15 and 15A.

最後に階段ステップ23を足場台16、16Aの元部プレート165の掛止部165aに掛止させ、隙間カバー22を階段2と足場台16との間に装着して、階段足場が構成される。この階段足場を階段2上に複数個設置し、下踊り場4と上踊り場5とに踊り場足場10Aを設置することにより、足場Mが構成されることとなる。   Finally, the stair step 23 is hooked on the hook portion 165a of the base plate 165 of the scaffolding platform 16 and 16A, and the gap cover 22 is attached between the staircase 2 and the scaffolding platform 16 to form the stair scaffolding. . A plurality of such stair scaffolds are installed on the staircase 2 and the landing scaffold 10A is installed in the lower landing 4 and the upper landing 5 to constitute the scaffold M.

足場Mの組付が完了すると、次に、例えば、ベランダ清掃作業を行う。清掃作業を行うにあたって、水洗浄やバイオ洗浄を行うために、清掃作業を行う場所に図示しない防水シートを掛けて水や塗料等の地上への落下防止を図ることが望ましい。   When the assembly of the scaffold M is completed, for example, a veranda cleaning operation is performed. In performing the cleaning operation, in order to perform water cleaning or bio-cleaning, it is desirable to prevent water or paint from falling to the ground by placing a waterproof sheet (not shown) on the site where the cleaning operation is performed.

次に、清掃作業を行う。図12に示すように、作業者Pは、下踊り場4(図12には付記せず)に設置された踊り場足場10A(図12に付記せず)から、階段2の階段足場10及び上踊り場5に設置された踊り場足場10Aの順に清掃工事を行うことになる。この階段足場10や踊り場足場10Aでは、階段ステップ23から足場台16、16Aのプレート本体161に上って所定の作業を行うことになる。なお、作業者Pは、命綱Rで懸吊されて作業することが望ましい。   Next, cleaning work is performed. As shown in FIG. 12, the worker P moves from the landing scaffold 10 </ b> A (not shown in FIG. 12) installed in the lower landing 4 (not shown in FIG. 12) to the stairway scaffold 10 and the upper landing. The cleaning work will be performed in the order of the landing platform 10A installed at No.5. In the stair scaffold 10 and the landing scaffold 10A, a predetermined work is performed from the stair step 23 to the plate body 161 of the scaffold bases 16 and 16A. In addition, it is desirable for the worker P to work by being suspended by the lifeline R.

実施形態の足場Mを使用して作業する作業内容は、清掃工事の場合、主に、階段ベランダ1の側壁7、踊り場側壁7Aの水洗浄あるいはバイオ洗浄作業を行うものであって、階段ベランダ1の側壁7の清掃作業を順に行う。   In the case of cleaning work, the content of work performed using the scaffold M according to the embodiment mainly performs water washing or bio-cleaning work on the side wall 7 of the staircase veranda 1 and the landing side wall 7A. The side wall 7 is cleaned in order.

所定の場所での作業を終了すると、作業者Pは足場Mを分解する。   When the work at the predetermined place is completed, the worker P disassembles the scaffold M.

上述のように、実施形態の足場Mでは、下踊り場4及び上踊り場5において踊り場天井壁9Aとの間で突っ張るように踊り場足場10A(図12には付記せず)を設置し、階段2上において、階段2の踏み面3と上層階の斜め天井壁9との間で突っ張るように縦支柱12を支持して階段足場10及び踊り場足場10Aを設置できるから、階段ベランダ1において、足場Mを構成することができ、高層住宅のいずれの階であっても、外壁工事を行うことができる。しかも、安全に作業できるとともに、工期を短縮できて廉価な費用で行うことが可能となる。   As described above, in the scaffold M of the embodiment, the landing scaffold 10A (not shown in FIG. 12) is installed so as to stretch between the landing landing ceiling wall 9A in the lower landing 4 and the upper landing 5 and on the stairs 2 , The stair scaffolding 10 and the landing scaffolding 10A can be installed by supporting the vertical struts 12 so as to stretch between the tread surface 3 of the stairs 2 and the oblique ceiling wall 9 of the upper floor. It can be configured, and the outer wall can be constructed on any floor of a high-rise house. In addition, the work can be performed safely and the work period can be shortened, so that the work can be performed at low cost.

また、斜め天井壁9を押圧する押圧部13が、斜め天井壁9に、斜め天井壁9の長さ方向に沿って配置され、ジャッキ部122の操作で、強く押圧するとともに、段差を有して隣り合わせた支持体11の押圧部13を連結補助ステー19で連結することにより、押圧部13を上方に移動させることなく斜め天井壁9を押圧することができることから、縦支柱12を強固に支持することができる。   A pressing portion 13 that presses the oblique ceiling wall 9 is disposed on the oblique ceiling wall 9 along the length direction of the oblique ceiling wall 9 and is pressed strongly by the operation of the jack portion 122 and has a step. By connecting the pressing portions 13 of the support bodies 11 adjacent to each other by the connection auxiliary stay 19, the oblique ceiling wall 9 can be pressed without moving the pressing portion 13 upward, so that the vertical column 12 is firmly supported. can do.

M、足場(階段ベランダ工事用足場)
1、階段ベランダ
2、階段
3、踏み面
4、下踊り場
5、上踊り場
7、側壁(階段ベランダ側壁)
9、斜め天井壁(上層階の階段ベランダの裏面)
10、単体足場
11、支持体
12、縦支柱
13、押圧部
131、押圧体ベース
132、スライダ
134、押圧体
135、副押圧体ベース
137、副押圧体
14、補助支柱
15、足場台用ステー
16、足場台
19、連結補助ステー
M, Scaffolding (scaffolding for stairs veranda)
1, Stairs veranda 2, Stairs 3, Tread 4, Lower landing 5, Upper landing 7, Side wall (Stairs veranda side wall)
9. Diagonal ceiling wall (the back of the upper floor staircase veranda)
DESCRIPTION OF SYMBOLS 10, Single scaffold 11, Support body 12, Vertical support | pillar 13, Press part 131, Press body base 132, Slider 134, Press body 135, Sub press body base 137, Sub press body 14, Auxiliary support post 15, Scaffold stand stay 16 , Scaffolding stand 19, Linkage auxiliary stay

Claims (7)

高層住宅の階段ベランダに設置する階段ベランダ工事用足場であって、
段差を有して配設された階段における2段の踏み面と、斜め平面状に形成されて前記踏み面の直上に配設された上層階段の裏面との間に設置され、
一端を高さ調整可能なジャッキ部を有して前記踏み面に当接するとともに、他端に前記上層階段の裏面を押圧する押圧部を配設して構成された縦支柱と、前記縦支柱から前記階段ベランダの外壁側に突出した足場台用ステーと、を備えた支持体が構成され、
段差を有する前記2段の踏み面に隣り合って設置される2基の前記支持体における2個の前記足場台用ステー上に、作業者が作業する足場台を架け渡して構成されていることを特徴とする階段ベランダ工事用足場。
It is a scaffold for stair verandah construction installed on the stair veranda of a high-rise house,
It is installed between the two-step treads in the stairs arranged with steps and the back surface of the upper stairs formed in an oblique plane and disposed immediately above the treads,
A vertical column having a jack part whose height is adjustable at one end and abutting against the tread surface, and a pressing unit that presses the back surface of the upper layer step on the other end, and the vertical column. A support provided with a scaffold base stay protruding to the outer wall side of the staircase veranda,
The scaffolding platform on which the operator works is bridged on the two scaffolding stays in the two support bodies installed adjacent to the two-step treads having a step. A staircase veranda for construction.
前記支持体には、前記縦支柱が立設する踏み面より上段の踏み面から立ち上がって前記縦支柱を支持する補助支柱が配設されていることを特徴とする請求項1記載の階段ベランダ工事用足場。   The stair veranda work according to claim 1, wherein the support is provided with auxiliary struts that stand up from a tread surface above the tread surface on which the vertical strut stands and support the vertical strut. Scaffolding. 高層住宅の階段ベランダに設置する階段ベランダ工事用足場であって、
段差を有して配設された階段における複数の踏み面と、最上段に配設された前記踏み面の上面側に配設された上層階踊り場の床面と、最下段に配設された前記踏み面の下方に配設された下層階踊り場の床面と、前記上層階踊り場と前記下層階踊り場との間を階段踊り場の外側に配設される前記階段ベランダ側壁と、斜め平面状に形成されて前記踏み面の直上に配設された上層階段の裏面との間に設置され、
前記下層階踊り場の床面又は上層階踊り場の床面あるいは前記階段の踏み面に、一端を高さ調整可能なジャッキ部を有して当接するように支持されるとともに、他端に前記上層階段の裏面を押圧する押圧部を配設して構成された縦支柱と、前記縦支柱から前記階段ベランダ側壁側に突出した足場台用ステーと、を備えた支持体が構成され、
段差を有する少なくとも2段の踏み面に設置された隣り合う前記支持体における前記足場台用ステー上に、作業者が作業する足場台を架け渡して、複数の前記足場台が段状に構成されることを特徴とする階段ベランダ工事用足場。
It is a scaffold for stair verandah construction installed on the stair veranda of a high-rise house,
A plurality of treads in the stairs arranged with steps, a floor surface of the upper floor landing arranged on the upper surface side of the tread arranged on the uppermost stage, and arranged on the lowermost stage The floor surface of the lower floor landing located below the tread, the side wall of the staircase veranda disposed outside the stair landing between the upper floor landing and the lower floor landing, and in an oblique plane shape Formed and installed between the upper surface of the upper stairs arranged just above the tread surface,
One end of the lower floor landing or the floor of the upper floor landing or the tread of the staircase is supported so that one end has a jack portion whose height can be adjusted, and the upper staircase is supported at the other end. A support body is provided that includes a vertical strut configured by disposing a pressing portion that presses the back surface thereof, and a scaffolding stay that protrudes from the vertical strut to the side of the stair veranda side wall.
A plurality of scaffolding platforms are formed in a step shape by bridging a scaffolding platform on which the operator works on the stays for the scaffolding platforms in the adjacent support bodies installed on at least two steps of treads having steps. A staircase veranda construction scaffold characterized by that.
前記階段に配設された支持体には、設置された前記縦支柱が立設する踏み面より上段の踏み面から立ち上がって前記縦支柱を支持する補助支柱が配設されていることを特徴とする請求項3記載の階段ベランダ工事用足場。   The support disposed on the staircase is provided with auxiliary struts that stand up from the tread surface above the tread surface on which the installed vertical strut stands to support the vertical strut. The staircase veranda construction scaffold according to claim 3. 前記押圧部は、前記縦支柱の延長線上に配設されて前記上層階段の裏面を押圧する押圧体と、前記上層階段の裏面の幅方向に沿って、前記押圧体と離れた位置で前記上層階段の裏面を押圧する副押圧体とを備えていることを特徴とする請求項2又は4のいずれかに記載の階段ベランダ工事用足場。   The pressing portion is disposed on an extension line of the vertical support and presses the back surface of the upper step, and the upper layer at a position away from the pressing member along the width direction of the back surface of the upper step. The scaffold for stair verandah construction according to claim 2, further comprising a sub-pressing body that presses the back surface of the staircase. 前記押圧体は、前記縦支柱の先端に載設された押圧体ベースに前記上層階段の裏面の傾斜面に沿って回動可能に連結されるとともに、段差を有して隣り合う前記縦支柱に連結補助ステーを介して連結されていることを特徴とする請求項5記載の階段ベランダ工事用足場。   The pressing body is connected to a pressing body base mounted on the tip of the vertical column so as to be rotatable along the inclined surface of the back surface of the upper step, and to the adjacent vertical column having a step. The stair veranda construction scaffold according to claim 5, wherein the scaffold is connected via a connection auxiliary stay. 前記副押圧体は、押圧体ベースに摺動可能に配設された副押圧体ベースに回動可能に連結されるとともに、前記補助支柱の一端が連結されていることを特徴とする請求項5又は6記載の階段ベランダ工事用足場。   6. The sub-pressing body is rotatably connected to a sub-pressing body base that is slidably disposed on the pressing body base, and one end of the auxiliary column is connected. Or the scaffold for the stair veranda construction described in 6.
JP2009229890A 2009-10-01 2009-10-01 Stair balcony work platform Expired - Fee Related JP5143105B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009229890A JP5143105B2 (en) 2009-10-01 2009-10-01 Stair balcony work platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009229890A JP5143105B2 (en) 2009-10-01 2009-10-01 Stair balcony work platform

Publications (2)

Publication Number Publication Date
JP2011074725A true JP2011074725A (en) 2011-04-14
JP5143105B2 JP5143105B2 (en) 2013-02-13

Family

ID=44018980

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009229890A Expired - Fee Related JP5143105B2 (en) 2009-10-01 2009-10-01 Stair balcony work platform

Country Status (1)

Country Link
JP (1) JP5143105B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200486758Y1 (en) * 2018-02-20 2018-06-27 김도균 Scaffolding for turbine generator
JP2018168663A (en) * 2017-03-30 2018-11-01 株式会社熊谷組 Temporary scaffold for staircase work
CN110700544A (en) * 2019-10-16 2020-01-17 上海建工一建集团有限公司 Progressive cantilever structure aiming at complex facade modeling and construction method thereof
JP7131891B2 (en) 2017-06-29 2022-09-06 ハイランド株式会社 Aerial work vehicle cover
CN115613798A (en) * 2022-10-27 2023-01-17 北京房地集团有限公司 Mounting structure and mounting method for cantilever beam of cantilever scaffold

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS619451U (en) * 1984-06-22 1986-01-20 株式会社 鴻池組 Fabric board members for temporary suspended scaffolding in stairwells
JPH08232478A (en) * 1995-02-23 1996-09-10 Kunimoto Shokai:Kk Supporting device of support, etc.
JPH11223012A (en) * 1998-02-06 1999-08-17 Alinco Inc Scaffolding device
JP2001012072A (en) * 1999-06-25 2001-01-16 Hitachi Building Systems Co Ltd Scaffolding device for high lift work
JP2003193677A (en) * 2001-12-26 2003-07-09 Masashi Sato Supporting device of constructing temporary scaffolding

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS619451U (en) * 1984-06-22 1986-01-20 株式会社 鴻池組 Fabric board members for temporary suspended scaffolding in stairwells
JPH08232478A (en) * 1995-02-23 1996-09-10 Kunimoto Shokai:Kk Supporting device of support, etc.
JPH11223012A (en) * 1998-02-06 1999-08-17 Alinco Inc Scaffolding device
JP2001012072A (en) * 1999-06-25 2001-01-16 Hitachi Building Systems Co Ltd Scaffolding device for high lift work
JP2003193677A (en) * 2001-12-26 2003-07-09 Masashi Sato Supporting device of constructing temporary scaffolding

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018168663A (en) * 2017-03-30 2018-11-01 株式会社熊谷組 Temporary scaffold for staircase work
JP7131891B2 (en) 2017-06-29 2022-09-06 ハイランド株式会社 Aerial work vehicle cover
KR200486758Y1 (en) * 2018-02-20 2018-06-27 김도균 Scaffolding for turbine generator
CN110700544A (en) * 2019-10-16 2020-01-17 上海建工一建集团有限公司 Progressive cantilever structure aiming at complex facade modeling and construction method thereof
CN115613798A (en) * 2022-10-27 2023-01-17 北京房地集团有限公司 Mounting structure and mounting method for cantilever beam of cantilever scaffold
CN115613798B (en) * 2022-10-27 2023-10-03 北京房地集团有限公司 Mounting structure and mounting method of cantilever beam of cantilever scaffold

Also Published As

Publication number Publication date
JP5143105B2 (en) 2013-02-13

Similar Documents

Publication Publication Date Title
JP5143105B2 (en) Stair balcony work platform
JP2009541612A (en) Construction site stairs
JP2011111869A (en) Scaffold platform elevating structure in construction scaffolding
US20160201313A1 (en) High-rise architectural structure and maintenance method therefor
JP5174709B2 (en) Assembly structure for construction scaffolding
JP5201633B2 (en) Two-stage handrail leading structure in construction scaffolding
JP2009235816A (en) Stairway
JP4958861B2 (en) Construction scaffolding
DK167580B1 (en) BEARING CONSTRUCTION FOR TRIBUNES
KR20190096187A (en) Prefabricated cage
KR100559118B1 (en) Working tower for a high place
JP2002089033A (en) Work scaffold for roof construction work and installation method therefor
JP5174642B2 (en) Construction scaffolding
JP4641871B2 (en) Scaffold for roof construction
JP2010090633A (en) Prefabricated work platform for cylindrical concrete structure
KR20100055605A (en) Improved model assembly stairway
KR200384963Y1 (en) Elevator access stair moving together with ladder angle
JP2007070939A (en) Liftable work scaffolding
JP2007284916A (en) Stair handrail structure
CN220487168U (en) Safety construction protection frame for assembled stairway
CN219491671U (en) Foldable PC stair construction operation platform
JP5410407B2 (en) Construction scaffolding
CN217027984U (en) Movable overhanging construction platform
JP5647772B2 (en) Lifting movable overhang scaffold
JP5383613B2 (en) Temporary scaffolding staircase frame

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120213

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120221

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120418

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121023

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121120

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151130

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5143105

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees