JP2011042997A - Method for constructing joint between column and foundation, and method for arranging ring reinforcement - Google Patents

Method for constructing joint between column and foundation, and method for arranging ring reinforcement Download PDF

Info

Publication number
JP2011042997A
JP2011042997A JP2009192463A JP2009192463A JP2011042997A JP 2011042997 A JP2011042997 A JP 2011042997A JP 2009192463 A JP2009192463 A JP 2009192463A JP 2009192463 A JP2009192463 A JP 2009192463A JP 2011042997 A JP2011042997 A JP 2011042997A
Authority
JP
Japan
Prior art keywords
foundation
steel frame
rebar
fixing
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009192463A
Other languages
Japanese (ja)
Other versions
JP5597952B2 (en
Inventor
Nobuhiko Hayashi
伸彦 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2009192463A priority Critical patent/JP5597952B2/en
Publication of JP2011042997A publication Critical patent/JP2011042997A/en
Application granted granted Critical
Publication of JP5597952B2 publication Critical patent/JP5597952B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To arrange a ring reinforcement around an erected steel frame without setting up a scaffold etc. <P>SOLUTION: In this method for constructing a joint of a foundation structure 20 in which a bridge pier 10 of concrete construction internally undergoing the embedment of a vertically-elongated steel pipe 30 and the lower end of the bridge pier 10 are connected together, a prefabricated bar 40 is constructed by connecting the annular ring reinforcements 42 at spacings by means of a vertical reinforcement 41; the end of the steel pipe 30 is inserted into the prefabricated bar 40; the prefabricated bar 40 is fixed to the steel pipe 30; a lower section of the foundation structure 20 is constructed; the steel pipe 30 is erected on the lower section of the foundation; concrete constituting an upper section of the foundation structure 20 is poured; and concrete constituting the bridge pier 10 is poured. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、例えば、橋脚などの鉄骨が埋設され、この鉄骨の下端部を取り囲むように複数のリング筋が埋設された柱と基礎との接続部の構築方法及びリング筋を鉄骨の周囲に配筋する方法に関する。   In the present invention, for example, a method for constructing a connection portion between a pillar and a foundation in which a steel frame such as a pier is embedded and a plurality of ring bars are embedded so as to surround the lower end of the steel frame, and the ring bars are arranged around the steel frame. It relates to the method of making a line.

従来より、橋脚を施工する方法として、橋脚の内部に相当する位置に複数の鋼管を上下方向に連結しながら立設し、これら鋼管の周囲に縦主筋を配筋するとともに、縦主筋を囲繞するようにPCストランドを巻き付け、鋼管の上端に反力を取って、スリップフォームを上昇させながら、このスリップフォーム内にコンクリートを打設することで橋脚を構築するハイブリッドスリップフォーム工法が用いられている(例えば、特許文献1参照)。   Conventionally, as a method of constructing piers, a plurality of steel pipes are erected in the vertical direction at positions corresponding to the inside of the piers, and vertical main bars are arranged around these steel pipes, and the vertical main bars are surrounded. As described above, a hybrid slip foam method is used in which a PC strand is wound and a reaction force is taken at the upper end of the steel pipe to raise the slip foam, and concrete is placed in the slip foam to construct a pier ( For example, see Patent Document 1).

上記の工法により構築された橋脚において、鋼管の下端部の周囲の基礎を構成するコンクリートには大きな荷重が作用する。このため、鋼管の周囲のコンクリートを補強すべく、最下段の鋼管を立設した後、コンクリートの鋼管の周囲に円環状のリング筋を配筋している。   In the pier constructed by the above construction method, a large load acts on the concrete constituting the foundation around the lower end of the steel pipe. For this reason, in order to reinforce the concrete around the steel pipe, the lowermost steel pipe is erected, and then an annular ring bar is arranged around the concrete steel pipe.

リング筋の配筋作業は、従来、最下段の鋼管の周囲に足場を組み、足場上で行っている。しかしながら、このような方法では、足場の組立、解体作業に手間がかかるとともに、矩形の足場材を用いると、鋼管と足場の間に隙間があいてしまうため、作業に制約が生じ、施工性が損なわれていた。   Conventionally, the ring reinforcement work is performed on the scaffold by assembling a scaffold around the lowermost steel pipe. However, in such a method, assembling and dismantling work of the scaffold is time-consuming, and when a rectangular scaffold material is used, there is a gap between the steel pipe and the scaffold, resulting in work restrictions and workability. It was damaged.

そこで、リング筋の配筋方法として、施工性を向上するため、例えば、特許文献1に記載されているように、予め、複数のフープ筋を縦筋で接続して筒状に組み立てておき、この筒状の組立鉄筋を、内部に鋼管が挿入されるように建て込む方法を適用することが考えられる。   Therefore, as a ring reinforcement arrangement method, in order to improve workability, for example, as described in Patent Document 1, a plurality of hoop reinforcements are connected in advance by a vertical reinforcement and assembled into a cylindrical shape, It is conceivable to apply a method of building this cylindrical assembly rebar so that a steel pipe is inserted therein.

特開平11―152899号公報Japanese Patent Laid-Open No. 11-152899

しかしながら、上記の方法では、組立鉄筋はクレーンにより揚重して建て込む必要があるが、組立鉄筋と鋼管との間の隙間は狭く、組立鉄筋を建て込む際に鋼管の上部において作業員が組立鉄筋の位置を調整する必要があるため、高所作業が発生してしまう。
また、通常、鋼管の上部には溶接作業の際に鋼管の周囲に設けられる足場を支持するための支持部材が表面から突出しており、組立鉄筋を建て込む際にこの支持部材が組立鉄筋と干渉してしまう。
However, in the above method, the assembled rebar needs to be lifted and built by a crane, but the gap between the assembled rebar and the steel pipe is narrow, and when the assembled rebar is built, an operator can assemble it at the upper part of the steel pipe. Since it is necessary to adjust the position of the reinforcing bar, work at high places will occur.
In addition, a support member for supporting a scaffold provided around the steel pipe is usually protruded from the surface of the upper part of the steel pipe during welding work, and this support member interferes with the assembly rebar when building the assembly rebar. Resulting in.

本発明は、上記の問題に鑑みなされたものであり、その目的は、足場などを組むことなく、柱に埋設される鉄骨の周囲にリング筋を配筋できるようにすることである。   The present invention has been made in view of the above problems, and an object of the present invention is to enable ring reinforcement to be arranged around a steel frame embedded in a pillar without assembling a scaffold or the like.

本発明の柱と基礎の接続部の構築方法は、内部に上下方向に延びる鉄骨が埋設されたコンクリート造の柱と、前記柱の下端が接続された基礎の接続部の構築方法であって、 複数のリング筋を互いに間隔をあけて縦筋により固定することにより筒状の組立鉄筋を組み立てる鉄筋組立ステップと、前記組立鉄筋内に前記鉄骨の端部が挿入されるように前記組立鉄筋と前記鉄骨とを相対移動させ、この状態で前記組立鉄筋を前記鉄骨に固定する固定ステップと、前記基礎の下部を構築する基礎下部構築ステップと、前記組立鉄筋が固定された前記鉄骨を前記構築した基礎の下部の上に建て込む建込ステップと、前記基礎の上部を構成するコンクリートを打設する基礎上部構築ステップと、前記柱を構成するコンクリートを打設するコンクリート打設ステップと、を備えることを特徴とする。   The method for constructing a pillar-to-foundation connecting portion according to the present invention is a concrete pillar in which a steel frame extending in the vertical direction is embedded, and a foundation connecting portion to which the lower end of the pillar is connected, Reinforcing bar assembling step for assembling a cylindrical assembling rebar by fixing a plurality of ring bars with vertical bars spaced apart from each other; and Relative movement of the steel frame, and in this state, the fixing step of fixing the assembled rebar to the steel frame, the foundation lower part construction step of constructing the lower part of the foundation, and the foundation on which the constructed steel frame is fixed A step of erection on the lower part of the foundation, a step of constructing the upper part of the foundation for placing the concrete constituting the upper part of the foundation, and a concrete placing for placing the concrete constituting the column A step, characterized in that it comprises a.

上記の柱と基礎の接続部の構築方法において、前記固定ステップは、前記鉄骨を横に寝かした状態で行ってもよく、前記柱は橋脚であってもよい。
また、前記固定ステップでは、前記鉄骨を寝かした状態で前記組立鉄筋と前記鉄骨とを相対移動させ、この状態で前記組立鉄筋を前記鉄骨に固定してもよい。また、前記コンクリート打設ステップでは、スリップフォームを用いてコンクリートを打設してもよい。
In the above-described method for constructing the connection portion between the pillar and the foundation, the fixing step may be performed in a state where the steel frame is laid sideways, and the pillar may be a bridge pier.
Further, in the fixing step, the assembled reinforcing bar and the steel frame may be relatively moved while the steel frame is laid down, and the assembled reinforcing bar may be fixed to the steel frame in this state. In the concrete placing step, concrete may be placed using slip foam.

また、本発明のリング筋の配筋方法は、コンクリート内に上下方向に延びるように立設された鉄骨を取り囲むように上下方向に間隔をあけて複数のリング筋を配筋する方法であって、前記複数のリング筋を互いに間隔をあけて縦筋に固定することにより筒状の組立鉄筋を組み立てる鉄筋組立ステップと、前記組立鉄筋内に前記鉄骨の端部が挿入されるように前記組立鉄筋と前記鉄骨とを相対移動させ、この状態で前記組立鉄筋を前記鉄骨に固定する固定ステップと、前記組立鉄筋が固定された前記鉄骨を建て込む建込ステップと、を備えることを特徴とする。
上記のリング筋の配筋方法において、前記固定ステップは、前記鉄骨を横に寝かした状態で行ってもよい。
Also, the ring reinforcement arrangement method of the present invention is a method of arranging a plurality of ring reinforcements at intervals in the vertical direction so as to surround a steel frame erected in the concrete so as to extend in the vertical direction. A rebar assembling step for assembling a cylindrical rebar by fixing the plurality of ring bars to the vertical bars at intervals, and the assembly rebar so that the end of the steel frame is inserted into the rebar And a step of fixing the assembled rebar to the steel frame in this state, and a step of building the steel frame to which the assembled rebar is fixed.
In the above-described ring reinforcement arrangement method, the fixing step may be performed in a state where the steel frame is laid sideways.

本発明によれば、予め、筒状に組まれた組立鉄骨内に鉄骨の端部を挿入し、組立鉄筋と鉄骨とを固定した状態で、鉄骨を建て込むこととしたため、リング筋を配筋するための作業足場が不要となる。   According to the present invention, since the steel frame is built in a state where the end of the steel frame is inserted into the assembled steel frame assembled in a cylindrical shape in advance and the assembled reinforcing bar and the steel frame are fixed, the ring reinforcement is arranged. A work scaffold is not required.

本実施形態のリング筋の配筋方法を適用して構築された橋脚の柱基部を示し、(A)は鉛直断面図、(B)は水平断面図である。The column base part of the pier constructed | assembled applying the ring reinforcement arrangement method of this embodiment is shown, (A) is a vertical sectional view, (B) is a horizontal sectional view. 橋脚の構築方法を説明するための図(その1)である。It is FIG. (1) for demonstrating the construction method of a pier. 橋脚の構築方法を説明するための図(その2)である。It is FIG. (2) for demonstrating the construction method of a pier. 橋脚の構築方法を説明するための図(その3)である。It is FIG. (3) for demonstrating the construction method of a pier. 橋脚の構築方法を説明するための図(その4)である。It is FIG. (4) for demonstrating the construction method of a pier. 組立鉄筋を鋼管に取付ける方法を示す図(その1)である。It is a figure (the 1) which shows the method of attaching an assembly reinforcing bar to a steel pipe. 組立鉄筋を鋼管に取付ける方法を示す図(その2)である。It is a figure (the 2) which shows the method of attaching an assembly reinforcing bar to a steel pipe.

以下、本発明のリング筋の配筋方法の一実施形態について図面を参照しながら詳細に説明する。
図1は、本実施形態のリング筋42の配筋方法を適用して構築された橋脚10の基部11を示し、(A)は鉛直断面図、(B)は水平断面図である。なお、図1(A)では、左半分には同図(B)におけるI−I断面を、右半分には、II−II断面を示す。同図に示すように、橋脚10は、略矩形の柱状に構築されたコンクリート部材12内に上下に複数連結された状態で埋設された鋼管30と、これら複数の鋼管30の外周に配筋された複数の縦筋51と、複数の鋼管30及び縦筋51を外周側から取り囲むように巻き付けられたPCストランド52と、を備えてなる。鋼管30は、コンクリート部材12内に平面視において縦横に複数列に配置されている。
Hereinafter, an embodiment of a ring reinforcing method according to the present invention will be described in detail with reference to the drawings.
1A and 1B show a base 11 of a pier 10 constructed by applying a method for arranging ring bars 42 according to the present embodiment, in which FIG. 1A is a vertical sectional view and FIG. 1B is a horizontal sectional view. In FIG. 1A, the left half shows the II cross section in FIG. 1B, and the right half shows the II-II cross section. As shown in the figure, the pier 10 is provided with a steel pipe 30 embedded in a state where a plurality of steel pipes 30 are vertically connected in a concrete member 12 constructed in a substantially rectangular column shape, and is arranged on the outer periphery of the plurality of steel pipes 30. The plurality of vertical bars 51, and the PC strands 52 wound so as to surround the plurality of steel pipes 30 and the vertical bars 51 from the outer peripheral side. The steel pipes 30 are arranged in a plurality of rows vertically and horizontally in the concrete member 12 in plan view.

最下段の鋼管30は、その下部が基礎構造20内に埋入されており、最下段の鋼管30の下部外周面には、基礎を構成するコンクリート21との付着強度を向上するため、凹凸が形成されている(以下、この部分を凹凸形成部31という)。そして、この凹凸形成部31の周囲を取り囲むように、上下に間隔をあけて複数のリング筋42と、これらリング筋42を連結する縦筋41とからなる組立鉄筋40が配置されている。   The lowermost steel pipe 30 has a lower portion embedded in the foundation structure 20, and the lower outer circumferential surface of the lowermost steel pipe 30 has unevenness in order to improve adhesion strength with the concrete 21 constituting the foundation. It is formed (hereinafter, this portion is referred to as an uneven portion forming portion 31). An assembly reinforcing bar 40 including a plurality of ring bars 42 and vertical bars 41 connecting the ring bars 42 is arranged so as to surround the periphery of the unevenness forming part 31.

以下、かかる橋脚の構築方法を図2A〜図2D、及び図3、4を参照しながら説明する。
まず、予め、図3(A)に示すように、複数のリング筋42を上下方向に間隔をあけて配置し、縦筋41により保持されるように組立て、組立鉄筋40を構築しておく。
次に、図3(B)に示すように、最下段の鋼管30を保持部材110上に寝かせて、鋼管30の下部の凹凸形成部31と、地表との間に隙間が形成されるように保持する。
Hereinafter, the construction method of this pier is demonstrated, referring FIG. 2A-FIG. 2D and FIG.
First, as shown in FIG. 3A, a plurality of ring bars 42 are arranged at intervals in the vertical direction and assembled so as to be held by the vertical bars 41 to construct an assembled reinforcing bar 40.
Next, as shown in FIG. 3 (B), the lowermost steel pipe 30 is laid on the holding member 110 so that a gap is formed between the concavo-convex forming portion 31 below the steel pipe 30 and the ground surface. Hold.

次に、図3(C)に示すように、最下段の鋼管30の凹凸形成部31が内部に配置されるように組立鉄筋40を水平方向に移動させる。そして、図4に示すように、少なくとも組立鉄筋40の上部と下部において、縦筋41と鋼管30表面との間に夫々周方向に間隔をあけて、例えば、チャンネル材などからなるスペーサ61を介挿し、このスペーサ61を鋼管30に溶接して取付ける。また、鋼管30の表面にL字型に折り曲げられた段取筋60を溶接して、この段取筋60に組立鉄筋の縦筋41を結束線などにより固定する。   Next, as shown in FIG. 3 (C), the assembly rebar 40 is moved in the horizontal direction so that the unevenness forming portion 31 of the lowermost steel pipe 30 is disposed inside. Then, as shown in FIG. 4, at least in the upper and lower parts of the assembly reinforcing bar 40, a space 61 is provided between the vertical bar 41 and the surface of the steel pipe 30 in the circumferential direction. The spacer 61 is attached to the steel pipe 30 by welding. Further, a setup bar 60 bent in an L-shape is welded to the surface of the steel pipe 30, and the vertical bar 41 of the assembly reinforcing bar is fixed to the setup bar 60 with a binding wire or the like.

また、上記の工程と並行して、図2Aに示すように、基礎構造20の、鋼管の下端に相当する深さまでの部分(以下、基礎下部20Aという)を構築する。基礎下部20Aの構築作業は、地盤を掘削して掘削孔22を形成し、掘削孔22内に鉄筋を配筋した後、所定の深さまでコンクリート21を打設することにより行われる。   In parallel with the above steps, as shown in FIG. 2A, a portion of the foundation structure 20 up to a depth corresponding to the lower end of the steel pipe (hereinafter referred to as a foundation lower portion 20A) is constructed. The construction work of the lower foundation 20A is performed by excavating the ground to form the excavation hole 22, placing a reinforcing bar in the excavation hole 22, and then placing the concrete 21 to a predetermined depth.

次に、基礎下部20Aの上部に、組立鉄筋40を取付けた状態の最下段の鋼管30を建て込む。この際、段取筋60を介して組立鉄筋40が鋼管30に接続されているため、鋼管30を略鉛直に起こしても、組立鉄筋40が落下することなく、また、組立鉄筋40と鋼管30との間にスペーサ61が介在するため組立鉄筋40と鋼管30との隙間が保たれる。   Next, the lowermost steel pipe 30 with the assembled rebar 40 attached is installed on the upper part of the foundation lower part 20A. At this time, since the assembled rebar 40 is connected to the steel pipe 30 via the setup bar 60, the assembled rebar 40 does not fall even when the steel pipe 30 is raised substantially vertically, and the assembled rebar 40 and the steel pipe 30 are not dropped. Since the spacer 61 is interposed therebetween, the gap between the assembled reinforcing bar 40 and the steel pipe 30 is maintained.

次に、図2Bに示すように、鋼管30を上方に向かって、順次接続していく。鋼管30の接続作業は、まず、新たな鋼管30を既に建て込まれている鋼管30の上方に配置し、仮止め冶具を用いて、所定の位置に仮止めし、上下に仮止めされた鋼管30の間を溶接接続することにより行う。また、鋼管30の接続作業と並行して鋼管30を取り囲むように縦筋51を配筋する。   Next, as shown in FIG. 2B, the steel pipes 30 are sequentially connected upward. The steel pipe 30 is connected by first placing a new steel pipe 30 above the already built steel pipe 30, temporarily fixing it in place using a temporary fixing jig, and temporarily fixing the steel pipe 30 up and down. This is performed by welding between 30. In addition, the vertical bars 51 are arranged so as to surround the steel pipe 30 in parallel with the connection work of the steel pipe 30.

最上段の鋼管30の接続作業が完了した後、最上段の鋼管30に作業足場を設け、この作業足場上で柱頭部にあたる部分の鋼管30に複数のリング筋を上下方向に間隔をあけて巻き付ける。なお、リング筋は周状に形成され、端部が重なり合うような形状を有しており、この重なり合った部分の間に鋼管30を通すことで、鋼管30の周囲に取付けることができる。   After the connection work of the uppermost steel pipe 30 is completed, a work scaffold is provided in the uppermost steel pipe 30, and a plurality of ring bars are wound around the steel pipe 30 corresponding to the column head on the work scaffold at intervals in the vertical direction. . In addition, a ring line | wire is formed in the periphery shape and has a shape which an edge part overlaps, and it can attach to the circumference | surroundings of the steel pipe 30 by letting the steel pipe 30 pass between this overlapped parts.

次に、図2Cに示すように、鋼管30の最上部に反力架台200を設け、反力架台200により吊持されるようにスリップフォーム装置210を設置する。なお、スリップフォーム装置210の上部にはPCストランド52を巻き付けるための送り出し装置220が設けられている。   Next, as shown in FIG. 2C, a reaction force stand 200 is provided on the uppermost portion of the steel pipe 30, and the slip foam device 210 is installed so as to be suspended by the reaction force stand 200. Note that a delivery device 220 for winding the PC strand 52 is provided on the slip foam device 210.

次に、スリップフォーム装置210を上昇させながら上部において縦筋51の周囲にPCストランド52を巻き付ける。また、これと並行してスリップフォーム装置210を型枠として用いて、PCストランド52を巻き付けた部分にコンクリートを打設しながらスリップフォーム装置210を上昇させる。そして、橋脚10の最上部までコンクリートの打設が完了し、打設したコンクリートが硬化した後、図2Dに示すように、スリップフォーム装置210を地上高さまで下降させて撤去し、反力架台200をクレーン100により撤去する。
以上の工程により、橋脚10の構築作業が完了する。
Next, the PC strand 52 is wound around the longitudinal bars 51 in the upper part while the slip foam device 210 is raised. In parallel with this, the slip foam apparatus 210 is used as a mold, and the slip foam apparatus 210 is raised while placing concrete around the portion where the PC strand 52 is wound. After the concrete placement to the top of the pier 10 is completed and the placed concrete is hardened, as shown in FIG. 2D, the slip foam device 210 is lowered to the ground level and removed, and the reaction force platform 200 is removed. Is removed by the crane 100.
The construction work of the pier 10 is completed by the above steps.

本実施形態によれば、最下段の鋼管30を寝かした状態で、予め筒状に形成された組立鉄筋40を固定することとしたため、作業足場が不要となり、施工性を向上することができる。このため、高所作業が発生せず、安全に施工を行うことができる。   According to the present embodiment, since the assembly rebar 40 formed in a cylindrical shape is fixed in a state where the lowermost steel pipe 30 is laid down, a work scaffold becomes unnecessary, and workability can be improved. For this reason, work in high places does not occur and construction can be performed safely.

また、予め、組立鉄筋40を組み立てておき、鋼管30に取付けておくことができるため、配筋の手間を削減できる。   Moreover, since the assembly rebar 40 can be assembled and attached to the steel pipe 30 in advance, the labor of bar arrangement can be reduced.

なお、本実施形態では、ハイブリッドスリップフォーム工法により橋脚10を構築する際に、最下段の鋼管30の周囲にリング筋42を配置する場合を例として説明したが、これに限らず、鋼管30を立設し、この鋼管30の周囲にリング筋42を配置する必要がある場合には、本発明を適用できる。   In the present embodiment, when the pier 10 is constructed by the hybrid slip foam method, the case where the ring bars 42 are arranged around the lowermost steel pipe 30 has been described as an example. The present invention can be applied when it is necessary to stand and arrange the ring bars 42 around the steel pipe 30.

また、本発明では、鋼管30の周囲にリング筋42を配置する場合について説明したが、これに限らず、H型鋼や角形鋼の周囲にリング筋を配置する場合にも適用できる。また、リング筋の形状は円環状に限らず、矩形環状などの形状としてもよい。   Moreover, in this invention, although the case where the ring reinforcement 42 was arrange | positioned around the steel pipe 30 was demonstrated, it is applicable not only to this but when a ring reinforcement is arrange | positioned around H-shaped steel or square steel. The shape of the ring line is not limited to an annular shape, and may be a rectangular shape.

10 橋脚 11 柱基部
12 コンクリート部材 20 基礎構造
21 コンクリート 22 掘削孔
30 鋼管 40 組立鉄筋
41 縦筋 42 リング筋
51 縦筋 52 PCストランド
60 段取筋 61 スペーサ
DESCRIPTION OF SYMBOLS 10 Pier 11 Pillar base 12 Concrete member 20 Foundation structure 21 Concrete 22 Drilling hole 30 Steel pipe 40 Reinforcement bar 41 Vertical bar 42 Ring bar 51 Vertical bar 52 PC strand 60 Set-up bar 61 Spacer

Claims (7)

内部に上下方向に延びる鉄骨が埋設されたコンクリート造の柱と、前記柱の下端が接続された基礎の接続部の構築方法であって、
複数のリング筋を互いに間隔をあけて縦筋により固定することにより筒状の組立鉄筋を組み立てる鉄筋組立ステップと、
前記組立鉄筋内に前記鉄骨の端部が挿入されるように前記組立鉄筋と前記鉄骨とを相対移動させ、この状態で前記組立鉄筋を前記鉄骨に固定する固定ステップと、
前記基礎の下部を構築する基礎下部構築ステップと、
前記組立鉄筋が固定された前記鉄骨を前記構築した基礎の下部の上に建て込む建込ステップと、
前記基礎の上部を構成するコンクリートを打設する基礎上部構築ステップと、
前記柱を構成するコンクリートを打設するコンクリート打設ステップと、を備えることを特徴とする柱と基礎の接続部の構築方法。
A concrete column in which a steel frame extending in the vertical direction is embedded inside, and a construction method of a connecting portion of a foundation to which the lower end of the column is connected,
A rebar assembly step for assembling a cylindrical assembly rebar by fixing a plurality of ring bars with vertical bars spaced apart from each other;
A fixing step of relatively moving the assembled rebar and the steel frame so that an end of the steel frame is inserted into the assembled rebar, and fixing the assembled rebar to the steel frame in this state;
A foundation lower part construction step for constructing a lower part of the foundation;
A build-in step of building the steel frame on which the assembly rebar is fixed on the lower part of the constructed foundation;
A foundation upper construction step for placing concrete constituting the upper part of the foundation;
A concrete placing step for placing concrete constituting the pillar, and a method for constructing a connecting portion between the pillar and the foundation.
請求項1記載の柱と基礎の接続部の構築方法であって、
前記固定ステップは、前記鉄骨を横に寝かした状態で行うことを特徴とする柱と基礎の接続部の構築方法。
A method for constructing a connecting portion between a pillar and a foundation according to claim 1,
The fixing step is performed in a state where the steel frame is laid down sideways.
前記柱は橋脚であることを特徴とする請求項1又は2記載の柱と基礎の接続部の構築方法。   The method for constructing a connection portion between a pillar and a foundation according to claim 1, wherein the pillar is a pier. 前記固定ステップでは、前記鉄骨と前記組立鉄筋との間にスペーサを介在させるとともに、前記鉄骨に段取筋を取付け、この段取筋と前記組立鉄筋とを固定することを特徴とする請求項1から3のうち何れか1項に記載の柱と基礎の接続部の構築方法。   2. The fixing step includes interposing a spacer between the steel frame and the assembled reinforcing bar, attaching a setup bar to the steel frame, and fixing the setup bar and the assembled reinforcing bar. The construction method of the connection part of the pillar and foundation of any one of 3 to 3. 前記コンクリート打設ステップでは、スリップフォームを用いてコンクリートを打設することを特徴とする請求項1から4のうち何れか1項に記載の柱と基礎の接続部の構築方法。   5. The method for constructing a pillar-to-foundation connection part according to claim 1, wherein in the concrete placing step, concrete is placed using slip foam. コンクリート内に上下方向に延びるように立設された鉄骨を取り囲むように上下方向に間隔をあけて複数のリング筋を配筋する方法であって、
前記複数のリング筋を互いに間隔をあけて縦筋に固定することにより筒状の組立鉄筋を組み立てる鉄筋組立ステップと、
前記組立鉄筋内に前記鉄骨の端部が挿入されるように前記組立鉄筋と前記鉄骨とを相対移動させ、この状態で前記組立鉄筋を前記鉄骨に固定する固定ステップと、
前記組立鉄筋が固定された前記鉄骨を建て込む建込ステップと、を備えることを特徴とするリング筋の配筋方法。
It is a method of arranging a plurality of ring bars at intervals in the vertical direction so as to surround a steel frame erected so as to extend in the vertical direction in the concrete,
Rebar assembling step for assembling a cylindrical assembling rebar by fixing the plurality of ring rebars to the vertical rebars at intervals;
A fixing step of relatively moving the assembled rebar and the steel frame so that an end of the steel frame is inserted into the assembled rebar, and fixing the assembled rebar to the steel frame in this state;
And a laying step for building the steel frame to which the assembly reinforcing bar is fixed.
請求項6記載のリング筋の配筋方法であって、
前記固定ステップは、前記鉄骨を横に寝かした状態で行うことを特徴とするリング筋の配筋方法。
A ring reinforcement method according to claim 6,
The method of arranging a ring muscle, wherein the fixing step is performed with the steel frame lying on its side.
JP2009192463A 2009-08-21 2009-08-21 How to build the connection between the column and foundation, and how to place the ring reinforcement Active JP5597952B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009192463A JP5597952B2 (en) 2009-08-21 2009-08-21 How to build the connection between the column and foundation, and how to place the ring reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009192463A JP5597952B2 (en) 2009-08-21 2009-08-21 How to build the connection between the column and foundation, and how to place the ring reinforcement

Publications (2)

Publication Number Publication Date
JP2011042997A true JP2011042997A (en) 2011-03-03
JP5597952B2 JP5597952B2 (en) 2014-10-01

Family

ID=43830598

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009192463A Active JP5597952B2 (en) 2009-08-21 2009-08-21 How to build the connection between the column and foundation, and how to place the ring reinforcement

Country Status (1)

Country Link
JP (1) JP5597952B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323386A (en) * 2021-06-02 2021-08-31 中国海诚工程科技股份有限公司 Installation method of modular steel structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55159073A (en) * 1979-05-29 1980-12-10 Shii Bii Esu Yuugen Method of synthesizing internal reinforcing iron with prefabricated reinforcing iron basket
JPS57172071A (en) * 1981-04-15 1982-10-22 Taisei Corp Assembling of reinforcing steel rod
JPH11152899A (en) * 1997-11-21 1999-06-08 Pub Works Res Inst Ministry Of Constr Construction method of tower structure and construction thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55159073A (en) * 1979-05-29 1980-12-10 Shii Bii Esu Yuugen Method of synthesizing internal reinforcing iron with prefabricated reinforcing iron basket
JPS57172071A (en) * 1981-04-15 1982-10-22 Taisei Corp Assembling of reinforcing steel rod
JPH11152899A (en) * 1997-11-21 1999-06-08 Pub Works Res Inst Ministry Of Constr Construction method of tower structure and construction thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323386A (en) * 2021-06-02 2021-08-31 中国海诚工程科技股份有限公司 Installation method of modular steel structure

Also Published As

Publication number Publication date
JP5597952B2 (en) 2014-10-01

Similar Documents

Publication Publication Date Title
JP2008208634A (en) Power transmission steel tower reinforcing method
JP7134070B2 (en) Construction method of top slab of underground structure
JP6543077B2 (en) Construction method of structure
JP2639361B2 (en) Construction method of steel pipe / concrete composite structure pier
JP7033468B2 (en) Construction method of liquid barrier and liquid barrier
KR101632006B1 (en) Installation method of equipment and anchor member supporting mechanism and anchor bolt unit
JP5597952B2 (en) How to build the connection between the column and foundation, and how to place the ring reinforcement
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP6228836B2 (en) Reverse winding method
JP5749620B2 (en) Seismic isolation method for existing buildings
JP2011208419A (en) Erection method of bridge girder
JP5223701B2 (en) Construction method of side wall of underground tank structure
JP5368040B2 (en) Horizontal force restraint method in seismic isolation work
JP2010168806A (en) Method of constructing sidewall of underground tank structure
JP3777543B2 (en) Side wall construction method for underground tank
JP2001271366A (en) Joint structre between flat slab and concrete filled steel pipe column, and installation method for flat slab
JP5925231B2 (en) Building construction method and underground building of new building
JP2000273946A (en) Method for constructing reinforced concrete structure
JP6720761B2 (en) How to build a ramen structure
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
JP5201719B2 (en) Column construction method and column structure
JP5506057B2 (en) Building construction method
JP2008255636A (en) Construction method for rc girder
JP7202413B2 (en) Concrete structure construction method
JP7470011B2 (en) Method for constructing underground structures and lifting equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120720

A977 Report on retrieval

Effective date: 20130823

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20130903

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Effective date: 20131018

Free format text: JAPANESE INTERMEDIATE CODE: A523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20140715

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Effective date: 20140728

Free format text: JAPANESE INTERMEDIATE CODE: A61

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Country of ref document: JP

Ref document number: 5597952