JP2011030098A JP2009175758A JP2009175758A JP2011030098A JP 2011030098 A JP2011030098 A JP 2011030098A JP 2009175758 A JP2009175758 A JP 2009175758A JP 2009175758 A JP2009175758 A JP 2009175758A JP 2011030098 A JP2011030098 A JP 2011030098A
Authority
JP
Japan
Prior art keywords
work
information
equipment
stop
terminal device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009175758A
Other languages
Japanese (ja)
Other versions
JP5568914B2 (en
Inventor
Satoshi Inohana
敏 猪鼻
Hideyuki Maruya
英之 丸矢
Tomoyuki Soma
智幸 相馬
Toru Ueki
亨 上木
Atsuo Nomoto
充生 野本
Teruhiko Sumi
輝彦 角
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Company Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2009175758A priority Critical patent/JP5568914B2/en
Publication of JP2011030098A publication Critical patent/JP2011030098A/en
Application granted granted Critical
Publication of JP5568914B2 publication Critical patent/JP5568914B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Telephonic Communication Services (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To determine, prior to the start of actual work, whether a system is still suspended, to grasp the content of determination of the system suspension, based on the state of communication facility, so as to increase efficiency of network communication facility suspension work. <P>SOLUTION: The network management control system is equipped with: a server 111; a terminal device 10 that is connected with the server 111 so that it exchanges work information with the server 111; and a communication facility 112 that is connected with the server 111 so that it may exchange information I-ap and I-cb concerning the operation state of the communication facility with the server 111. When work start notification S-pr is transmitted to the server 111 from a work terminal device 10X in charge, the communication facility 112 to be worked is asked for the information I-ap and I-cb concerning operation state of the communication facility, and then, when the information I-ap and I-cb are transmitted from the facility 112 to be worked, they are stored in databases 141 and 143. The stored information I-ap and I-cb are used to determine whether the network system is suspended, and the determination result SD-y is transmitted to the work terminal device 10X in charge for displaying. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、通信ネットワークの作業管理システムとその管理方法に関し、特に、通信ケーブルおよび通信ネットワークにおけるコンピュータによるネットワークの作業管理システムとその管理方法に関するものである。   The present invention relates to a communication network work management system and a management method thereof, and more particularly, to a network work management system using a computer in a communication cable and a communication network and a management method thereof.

一般に、通信ネットワークの通信設備において予め決められた作業計画に基づいて停止作業を行う場合、事前に運用管理システムに予定停止計画(停止日時、停止対象物(例えば、回線と機器))を入力するようになっている。この予定停止計画に従って実際に停止作業を行う際、作業がインターネットプロトコル機器(以下、IP機器と称す。)のポート閉塞またはポート閉塞解除を伴う場合、閉塞または閉塞解除の対象となる機器(例えば、ルータ、スイッチ、伝送装置等)と対象となるポートとを、実作業前に予め紙による資料の中から人力による手作業で選び出し、ピックアップしておく。そして、ピックアップされた機器について、作業日の前に、停止日時、停止対象設備を含む予定停止計画を予め運用管理システムに登録するようにしている。この予定停止作業が、作業予定者の保守担当域と異なる担当外の保守担当域で行われる場合、作業予定者は、当該予定停止作業が行われる地域を担当する保守担当者に、予め、予定停止計画を送り、作業実行の承認を得ておく必要がある。承認を得た予定停止計画は最終的に決定処理を行い、監視制御システムに送られることで当日の作業管理を行う。また、作業予定者は作業当日も作業開始前に作業実行の確認の連絡を行い、監視制御システムにて作業開始の登録を行う。実作業終了後は、作業終了の連絡を行って閉塞解除を依頼し、回線状態を確認した後、監視制御システムに作業終了の登録を行うようになっている。   Generally, when a stop operation is performed based on a predetermined work plan in a communication facility of a communication network, a scheduled stop plan (stop date / time, stop target (for example, line and equipment)) is input to the operation management system in advance. It is like that. When actually performing a stop operation in accordance with this scheduled stop plan, if the operation involves port blockage or port block release of an Internet protocol device (hereinafter referred to as IP device), the device to be blocked or released (for example, Routers, switches, transmission devices, etc.) and target ports are selected and manually picked up from paper materials by hand before actual work. And about the picked-up apparatus, the scheduled stop plan including a stop date and a stop target facility is registered into an operation management system beforehand before a work day. When this scheduled stop operation is performed in a maintenance area other than the maintenance area for the scheduled work person, the scheduled work person will schedule the scheduled maintenance work in advance to the maintenance person in charge of the area where the scheduled stop work will be performed. It is necessary to send an outage plan and obtain approval for work execution. The scheduled stop plan that has been approved is finally determined and sent to the supervisory control system for work management on the day. In addition, the scheduled work person contacts the work execution confirmation on the day of the work before starting the work, and registers the work start in the monitoring control system. After the actual work is completed, the end of work is notified, the release of the block is requested, the line status is confirmed, and the end of work is registered in the monitoring control system.

従来、通信ネットワークを管理運用するシステムとして、予め伝送媒体を含む回線・設備情報がデータ化された設備系データを格納したデータベースに基づいて、この設備系データに連繋させて画面に表示された回線に対し、所望の始端および終端装置の区間の伝送媒体を伝搬路として指定し、指定された伝搬路上の回線を、始・終端側の一方から他方に向かって順次隣接する装置間の単一伝送媒体ごとに構成回線として定義付けして回線登録し、回線登録された構成回線に基づいて回線を管理する回線管理システムが提案されている。従来の回線管理システムでは、複数の装置を伝送媒体でループ状に形成したループ回線を含み、かつ、このループ回線の伝送媒体が存在する伝搬路に対し、ループ回線自体を上記単一の伝送媒体に準じて定義付けして回線構成するようにしている。このため、始端装置および終端装置が変わる毎に、回線の繋がりが多様に変化するループ回線区間の伝送媒体を回線構成に含める必要がなく、指定された伝搬路上にいくらループ回線が存在しようとも、ループ回線が単一の伝送媒体と見なされるので、伝搬路上には単一の通信経路が形成され、ループ回線を含めた回線構成を迅速かつ容易に行うことができ、ループ回線の有無やループ回線の多少に拘わらず回線構成を単純化して回線管理を実現することができるようになっている(特許文献1参照)。   Conventionally, as a system for managing and operating a communication network, a line displayed on a screen linked to this equipment data based on a database storing equipment data in which transmission line and equipment information including transmission media has been converted into data. On the other hand, the transmission medium of the desired start and end device sections is specified as a propagation path, and the line on the specified propagation path is transmitted in a single transmission between adjacent devices in sequence from one of the start and end sides to the other. There has been proposed a line management system in which lines are defined and defined as constituent lines for each medium, and the lines are managed based on the registered constituent lines. In the conventional line management system, a loop line itself is included in the single transmission medium with respect to a propagation path including a loop line in which a plurality of devices are formed in a loop shape with a transmission medium. The line configuration is defined according to the definition. For this reason, it is not necessary to include the transmission medium of the loop line section where the connection of the line changes variously every time the start device and the end device are changed. Since the loop line is regarded as a single transmission medium, a single communication path is formed on the propagation path, and the line configuration including the loop line can be quickly and easily performed. Regardless of the number of lines, the line configuration can be simplified and line management can be realized (see Patent Document 1).

特開2005−65046号公報(第9−12頁、図4、5)JP-A-2005-65046 (pages 9-12, FIGS. 4, 5)

しかしながら、従来のシステムでは、予定され登録された停止作業計画に基づいて、作業当日、実作業を開始すると、設備や回線などの通信設備については、どの保守担当域のどの通信設備が停止するか把握できるものの、実作業時、作業対象通信設備の停止に伴い、通信ネットワークの健全性を確認することができないという問題がある。つまり、実作業を予定している何日か前に、予定された停止作業計画が他の保守担当域の承認を得て登録されたときには、その時点における通信設備の状態に基づいて通信ネットワークの健全性を、すなわち、システム停止の有無を確認することができるものの、時間の経過に伴い設備や回線等の通信設備の状態に変化があると、実作業直前における通信ネットワークの健全性を把握することができないという問題がある。このため、計画時点でシステム停止の可能性があれば、システム停止を避けるための作業計画も準備しなければならず、作業計画決定までに手間がかかるという問題がある。   However, in the conventional system, when the actual work is started on the day of work based on the scheduled and registered stop work plan, for which communication equipment such as equipment and lines, which communication equipment in which maintenance area is stopped. Although it can be grasped, there is a problem that the soundness of the communication network cannot be confirmed during the actual work due to the suspension of the communication equipment to be worked. In other words, when a scheduled stop work plan is registered with the approval of other maintenance departments several days before the actual work is scheduled, the communication network is determined based on the state of the communication equipment at that time. You can check the soundness, that is, whether or not the system has stopped, but if the state of communication equipment such as equipment and lines changes over time, grasp the soundness of the communication network immediately before the actual work. There is a problem that can not be. For this reason, if there is a possibility of system stop at the time of planning, a work plan for avoiding system stop must be prepared, and there is a problem that it takes time to determine the work plan.

本発明は、上記課題を解決するためになされたもので、簡素な構成でしかも作業直前に正確かつ迅速にシステム停止の有無を判定し、判定に基づいてリアルタイムでネットワークの健全性を監視し、健全性を確認した上で実際の停止作業にとりかかることができるネットワークの作業管理システムとその管理方法を提供することを目的とするものである。   The present invention was made in order to solve the above-mentioned problems, and it is determined whether or not the system has been stopped accurately and quickly with a simple configuration and immediately before work, and monitors the health of the network in real time based on the determination, It is an object of the present invention to provide a network work management system and a management method thereof that can start actual stop work after confirming soundness.

本発明の請求項1に係るネットワークの作業管理システムは、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、通信設備を、センターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させることを特徴とするものである。   The network work management system according to claim 1 of the present invention is capable of exchanging work information through communication with the center server for managing and operating the lines of the entire network based on the information of the communication equipment stored in the database. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. The communication equipment is configured to be released, and the communication equipment is in an operational state through communication with the center server. When the work start notification is sent to the center server for the stop work plan set from the work terminal device, the center server sends the information to the communication equipment of the work target. When information on the operation status of the communication equipment is obtained and information about the operation status of the communication equipment is sent from the work target equipment to the center server, the information is stored in the database, and the center server stores the communication stored in the database. Based on the information on the operating state of the facility, it is determined whether or not the system is stopped in the network, and the system stop determination result is transmitted to the terminal device in charge for display.

本発明の請求項1に係るネットワークの作業管理システムでは、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、通信設備を、センターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させるようにしたことにより、作業開始前に、最新の通信設備の状態に基づいてシステム停止の可能性の有無を把握することができ、停止作業によりネットワークにシステム停止が発生するのを回避することができる。   In the network work management system according to claim 1 of the present invention, a center server that manages and operates the lines of the entire network based on communication facility information stored in the database, and work information can be exchanged through communication with the center server. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. The communication facility is configured to be released, and the communication facility is operated through communication with the center server. When the work start notification is sent to the center server for the stop work plan set from the work terminal device, the center server sends the information to the communication equipment of the work target. When information on the operation status of the communication equipment is obtained and information about the operation status of the communication equipment is sent from the work target equipment to the center server, the information is stored in the database, and the center server stores the communication stored in the database. Based on the information on the operating state of the equipment, it is determined whether or not the network system has been stopped, and this system stop determination result is transmitted to the work terminal device for display, so that the latest Based on the state of the communication equipment, it is possible to know whether there is a possibility of system stoppage. Stem stop it is possible to avoid the occurrence.

本発明の請求項2に係るネットワークの作業管理システムは、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定することを特徴とするものである。   In the work management system for a network according to claim 2 of the present invention, when the center server receives a request for inquiry about the state of equipment related to the communication equipment to be worked from the work terminal device, The response to the status of the equipment received from the work target communication equipment is sent to the work terminal device that requested the inquiry and displayed, and the information about the equipment and the status of the equipment Answers are stored in the database, and when there is a request for inquiry about the line status of the communication equipment to be worked from the terminal device in charge of work, the work target communication equipment is asked to answer the line status and the work target An answer about the line status received from the communication equipment is sent to the work terminal device that requested the inquiry and displayed. Store line information and line status answers in a database, and determine whether there is a system outage based on at least one of equipment status information and line status information stored in the database It is characterized by.

本発明の請求項2に係るネットワークの作業管理システムでは、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定するようにしたことにより、システム停止の判定を設備の状態と回線の状態とのうち少なくともいずれか1に基づいて行うので、判定の精度が向上する。また、システム停止の可能性がある場合、作業担当端末装置側で設備の状態や回線の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性を監視し、健全性を確認した上で、作業を行うことができる。   In the work management system for a network according to claim 2 of the present invention, when the center server receives a request for inquiry about the state of the equipment related to the communication equipment to be worked from the work terminal device, the center server installs the equipment for the work target communication equipment. The response to the status of the equipment received from the work target communication equipment is sent to the terminal in charge of the work requesting the inquiry and displayed, and the information about the equipment and the status of the equipment Answers are stored in the database, and when there is a request for inquiry about the line status of the communication equipment to be worked from the terminal device in charge of work, the work target communication equipment is asked to answer the line status and the work target Sending and displaying the response about the line status received from the communication equipment to the work terminal device that requested the inquiry, The line information and the answer about the line state are stored in a database, and whether or not the system is stopped is determined based on at least one of the facility state information and the line state information stored in the database. By doing so, since the determination of the system stop is performed based on at least one of the equipment state and the line state, the determination accuracy is improved. In addition, if there is a possibility of system shutdown, it is possible to grasp the state of equipment and the line state on the work terminal side, and to grasp the health of the network. The operator monitors the health of the network, Work can be done after confirming soundness.

本発明の請求項3に係るネットワークの作業管理システムは、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の設定状態について照会の要求があると、当該作業対象通信設備に対して設備の設定状態を回答するよう求め、当該作業対象通信設備から受け取った設備の設定状態についての回答を照会要求のあった作業担当端末装置に送信して表示させ、作業担当端末装置から作業対象の通信設備に関し作業対象設備を経由する経路について照会の要求があると、作業担当端末装置から提供された始端設備情報と終端設備情報とに基づいて、当該作業対象通信設備に対して経路の状態を回答するよう求め、当該作業対象通信設備から受け取った経路の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させることを特徴とするものである。   In the work management system for a network according to claim 3 of the present invention, when the center server receives a request for inquiry about the set state of the equipment related to the work equipment to be worked from the work terminal device, the center server requests the work equipment to be worked. It asks to answer the setting status of the equipment, sends the answer about the setting status of the equipment received from the work target communication equipment to the work terminal device that requested the inquiry and displays it. When there is a request for inquiring about a route that passes through the work target facility with respect to the communication facility, the state of the route for the work target communication facility is determined based on the start facility information and the end facility information provided from the work terminal device. Send a reply about the status of the route received from the work target communication equipment to the terminal in charge of the work that requested the inquiry. It is characterized in that that presents.

本発明の請求項3に係るネットワークの作業管理システムでは、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の設定状態について照会の要求があると、当該作業対象通信設備に対して設備の設定状態を回答するよう求め、当該作業対象通信設備から受け取った設備の設定状態についての回答を照会要求のあった作業担当端末装置に送信して表示させ、作業担当端末装置から作業対象の通信設備に関し作業対象設備を経由する経路について照会の要求があると、作業担当端末装置から提供された始端設備情報と終端設備情報とに基づいて、当該作業対象通信設備に対して経路の状態を回答するよう求め、当該作業対象通信設備から受け取った経路の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるようにしたことにより、システム停止の可能性がある場合、作業担当端末装置側で設備の設定状態や経路の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性をより細かく監視することができる。   In the network work management system according to claim 3 of the present invention, when the center server receives a request for inquiry about the setting state of the equipment regarding the communication equipment to be worked from the work terminal device, It asks to answer the setting status of the equipment, sends the answer about the setting status of the equipment received from the work target communication equipment to the work terminal device that requested the inquiry and displays it. When there is a request for inquiring about a route that passes through the work target facility with respect to the communication facility, the state of the route for the work target communication facility is determined based on the start facility information and end facility information provided from the work terminal device Sends a reply about the status of the route received from the work target communication equipment to the terminal in charge of the work that requested the inquiry. If there is a possibility that the system will stop due to the display, the terminal in charge of the work can grasp the setting status of the equipment and the state of the route to understand the soundness of the network. Can be monitored more closely.

本発明の請求項4に係るネットワークの作業管理システムは、センターサーバに作業計画が入力されると、データベースに格納された通信設備の情報に基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補を抽出し、抽出された候補を作業を担当する作業担当端末装置に表示させ、作業担当端末装置により表示された候補から作業対象設備が選択されると、この選択情報をセンターサーバに送信し、センターサーバは、この選択された情報に基づいて最終的な作業計画を決定し、その決定された最終的な作業計画を作業担当端末装置に送信して表示させることを特徴とするものである。   When a work plan is input to the center server, the network work management system according to claim 4 of the present invention is a device or equipment related to the line of the work target equipment based on the information of the communication equipment stored in the database. When at least one candidate is extracted from the port part of the above, the extracted candidate is displayed on the work terminal device in charge of work, and the work target facility is selected from the candidates displayed by the work charge terminal device The selected information is transmitted to the center server, and the center server determines a final work plan based on the selected information, and transmits the determined final work plan to the work terminal device. It is characterized by being displayed.

本発明の請求項4に係るネットワークの作業管理システムでは、センターサーバに作業計画が入力されると、データベースに格納された通信設備の情報に基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補を抽出し、抽出された候補を作業を担当する作業担当端末装置に表示させ、作業担当端末装置により表示された候補から作業対象設備が選択されると、この選択情報をセンターサーバに送信し、センターサーバは、この選択された情報に基づいて最終的な作業計画を決定し、その決定された最終的な作業計画を作業担当端末装置に送信して表示させるようにしたことにより、人手を介さず停止対象とすべき通信設備の候補が表示されるので、検討する時間を短縮することができ、停止対象とすべき通信設備を決定する作業が迅速化される。   In the network work management system according to claim 4 of the present invention, when a work plan is input to the center server, the equipment or equipment related to the line of the work target equipment based on the information of the communication equipment stored in the database When at least one candidate is extracted from the port part of the above, the extracted candidate is displayed on the work terminal device in charge of work, and the work target facility is selected from the candidates displayed by the work charge terminal device The selected information is transmitted to the center server, and the center server determines a final work plan based on the selected information, and transmits the determined final work plan to the work terminal device. By displaying it, candidates for communication equipment that should be subject to suspension are displayed without human intervention, so the time to consider can be shortened and Task of determining the communication equipment to be elephant is faster.

本発明の請求項5に係るネットワークの作業管理システムは、センターサーバに作業日時と作業設備との情報が入力されると、データベースに格納された通信設備の情報に基づいて、停止予定設備の回線に関連する機器を自らの保守担当域に有し当該作業対象通信設備を管理する端末装置を作業対象設備担当端末装置として抽出し、抽出された作業対象設備担当端末装置に予定された作業日時と作業設備との情報を送信し、当該作業対象設備担当端末装置が、予定された作業日時と作業設備との情報を受け取ると、この情報に基づいて、停止予定または停止解除予定の通信設備について予定された作業を承認するか否かの判別を行い、その判別結果をセンターサーバに送信し、センターサーバは、作業対象設備担当端末装置から作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とするものである。   In the network work management system according to claim 5 of the present invention, when the information about the work date and time and work equipment is input to the center server, the line of the scheduled stop equipment is based on the information of the communication equipment stored in the database. The terminal device that has the equipment related to the maintenance in its own maintenance charge area and manages the work target communication equipment is extracted as the work target equipment charge terminal device, and the work date and time scheduled for the extracted work target equipment charge terminal device and When the information on the work equipment is transmitted, and the terminal device in charge of the work target equipment receives the information on the scheduled work date and time and the work equipment, the communication equipment scheduled to be stopped or released is scheduled based on this information. Whether the approved work is approved or not, and transmits the result of the determination to the center server. Upon receipt of the determination result, whether or not to perform the scheduled work is determined based on the determination result, and the determination of whether or not the work is to be performed is transmitted to the terminal terminal in charge for display. is there.

本発明の請求項5に係るネットワークの作業管理システムでは、センターサーバに作業日時と作業設備との情報が入力されると、データベースに格納された通信設備の情報に基づいて、停止予定設備の回線に関連する機器を自らの保守担当域に有し当該作業対象通信設備を管理する端末装置を作業対象設備担当端末装置として抽出し、抽出された作業対象設備担当端末装置に予定された作業日時と作業設備との情報を送信し、当該作業対象設備担当端末装置が、予定された作業日時と作業設備との情報を受け取ると、この情報に基づいて、停止予定または停止解除予定の通信設備について予定された作業を承認するか否かの判別を行い、その判別結果をセンターサーバに送信し、センターサーバは、作業対象設備担当端末装置から作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させるようにしたことにより、自らの保守担当域と異なる他の保守担当域で停止作業を行う際、停止作業承認の依頼と承認の通知との遣り取りをセンターサーバと端末装置とを通じて行うので、作業者側と停止作業対象設備を有する被作業者側との間の調整が自動化される。   In the network work management system according to claim 5 of the present invention, when the information about the work date and time and work equipment is input to the center server, the line of the scheduled stop equipment based on the communication equipment information stored in the database The terminal device that has the equipment related to the maintenance in its own maintenance charge area and manages the work target communication equipment is extracted as the work target equipment charge terminal device, and the work date and time scheduled for the extracted work target equipment charge terminal device and When the information on the work equipment is transmitted and the terminal device in charge of the work target equipment receives the information on the scheduled work date and time and the work equipment, the communication equipment scheduled to be stopped or scheduled to be released is scheduled based on this information. Whether the approved work is approved or not, and sends the result of the determination to the center server. Upon receiving the acceptance / rejection determination result, whether or not to perform the scheduled work execution is determined based on the determination result, and the determination of whether or not the work execution is performed is transmitted to the terminal terminal in charge for display, and thus, When performing a stop operation in another maintenance area that is different from the maintenance area, the request for the approval of the stop operation and the notification of the approval are exchanged between the center server and the terminal device. Adjustment with the worker side is automated.

本発明の請求項6に係るネットワークの作業管理システムは、作業担当端末装置は、表示された作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補に対し、オペレータにより作業対象とすべき機器または機器のポート部のうち少なくともいずれか1が選択されると、その選択結果をセンターサーバに送信し、
センターサーバは、作業担当端末装置から選択結果を受け取ると、この選択結果に基づいて、選択された機器または機器のポート部を作業対象として決定し、この作業対象として決定された機器または機器のポート部を自らの保守担当域に有する作業対象設備担当端末装置を抽出し、抽出された作業対象設備担当端末装置に作業日時の情報とともに作業対象として決定された機器または機器のポート部の情報を送信し、当該作業対象設備担当端末装置が、作業日時の情報と作業対象として決定された機器または機器のポート部の情報とを受け取ると、これら情報を表示して予定された作業を承認するか否かの入力を求め、オペレータにより入力が行われるとその入力結果をセンターサーバに送信し、センターサーバは、作業対象設備担当端末装置から作業実施について諾否の入力結果を受け取ると、この入力結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とするものである。
The network work management system according to claim 6 of the present invention is such that the work terminal unit operates the operator with respect to at least one of the equipment or the port portion of the equipment related to the displayed line of the work target equipment. When at least one of the device to be worked on or the port portion of the device is selected by the above, the selection result is transmitted to the center server,
When the center server receives the selection result from the terminal in charge of work, based on the selection result, the center server determines the selected device or the port portion of the device as a work target, and the device or device port determined as the work target. The equipment in charge of the work target equipment that has the department in its maintenance area is extracted, and the information on the device or the port part of the equipment determined as the work target is sent to the extracted work target equipment charge terminal device together with the work date and time information When the work target facility terminal device receives the information of the work date and time and the information of the device or the port portion of the device determined as the work target, whether or not to approve the scheduled work by displaying these information When the operator inputs it, the input result is sent to the center server. The center server When an input result indicating acceptance / rejection of the work execution is received from the device, whether or not the scheduled work execution is determined is determined based on the input result, and the determination of whether or not the work execution is possible is transmitted to the terminal terminal in charge for display. It is a feature.

本発明の請求項6に係るネットワークの作業管理システムは、作業担当端末装置は、表示された作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補に対し、オペレータにより作業対象とすべき機器または機器のポート部のうち少なくともいずれか1が選択されると、その選択結果をセンターサーバに送信し、センターサーバは、作業担当端末装置から選択結果を受け取ると、この選択結果に基づいて、選択された機器または機器のポート部を作業対象として決定し、この作業対象として決定された機器または機器のポート部を自らの保守担当域に有する作業対象設備担当端末装置を抽出し、抽出された作業対象設備担当端末装置に作業日時の情報とともに作業対象として決定された機器または機器のポート部の情報を送信し、当該作業対象設備担当端末装置が、作業日時の情報と作業対象として決定された機器または機器のポート部の情報とを受け取ると、これら情報を表示して予定された作業を承認するか否かの入力を求め、オペレータにより入力が行われるとその入力結果をセンターサーバに送信し、センターサーバは、作業対象設備担当端末装置から作業実施について諾否の入力結果を受け取ると、この入力結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させるようにしたことにより、停止対象とすべき通信設備を検討する時間を短縮することができ、停止対象とすべき通信設備を決定する作業が迅速化される。また、作業者側と停止作業対象設備を有する被作業者側との間の調整が自動化される。   The network work management system according to claim 6 of the present invention is such that the work terminal unit operates the operator with respect to at least one of the equipment or the port portion of the equipment related to the displayed line of the work target equipment. When at least one of the devices to be worked on or one of the port portions of the devices is selected, the selection result is transmitted to the center server. When the center server receives the selection result from the work terminal device, Based on the selection result, a terminal unit in charge of the work target facility that determines the selected device or the port part of the device as a work target and has the device or the port part of the device determined as the work target in its own maintenance charge area. The equipment or equipment that was determined as the work target along with the work date and time information to the extracted work target facility terminal device When the work target equipment terminal device receives the information on the work date and time and the information on the device or the port part of the device determined as the work target, the information is scheduled to be displayed. Requesting whether or not to approve the work, and when the input is made by the operator, the input result is transmitted to the center server, and the center server receives the input result of approval or disapproval for the work execution from the work target facility terminal device. And determining whether or not the scheduled work can be performed based on the input result, and transmitting and displaying the determination as to whether or not the work can be performed to the work terminal device. Can be shortened, and the work of determining the communication equipment to be stopped is expedited. Moreover, the adjustment between the worker side and the worker side having the facility to be stopped is automated.

本発明の請求項7に係るネットワークの作業管理システムは、作業計画が予め計画された停止日時と停止設備との情報を含む停止計画であり、この停止計画に対し、停止作業開始前に、実施が決定された停止作業を最終的な停止計画としてデータベースに登録することを特徴とするものである。   The network work management system according to claim 7 of the present invention is a stop plan including information on a stop date and time and a stop facility in which the work plan is planned in advance. This is characterized in that the stop operation for which is determined is registered in the database as a final stop plan.

本発明の請求項7に係るネットワークの作業管理システムでは、作業計画が予め計画された停止日時と停止設備との情報を含む停止計画であり、この停止計画に対し、停止作業開始前に、実施が決定された停止作業を最終的な停止計画としてデータベースに登録するようにしたことにより、停止計画を早めに多数作成することができ、計画作成の時間を有効に利用することができる。   In the work management system for a network according to claim 7 of the present invention, the work plan is a stop plan including information on the stop date and time and the stop equipment planned in advance, and this stop plan is executed before the stop work is started. By registering the stop operation determined in the database as a final stop plan, a large number of stop plans can be created early, and the time for creating the plan can be used effectively.

本発明の請求項8に係るネットワークの作業管理システムは、データベースには、停止作業日前に最終的な停止計画を登録するとともに、センターサーバは、停止作業日の作業開始前に、登録された最終的な停止計画を、停止作業を承認する判別結果を送信した作業対象設備担当端末装置に送信し、作業対象設備担当端末装置は、センターサーバから登録された最終的な停止計画を受け取ると、登録された停止作業を当日作業として承認するか否かの入力を求め、入力が行われるとその入力結果をセンターサーバに送信し、センターサーバは、作業対象設備担当端末装置から当日の停止作業について諾否の入力結果を受け取ると、この入力結果に基づいて登録された最終的な停止計画実施について開始の可否を作業担当端末装置に送信して表示させることを特徴とするものである。   In the network work management system according to claim 8 of the present invention, the final stop plan is registered in the database before the stop work day, and the center server stores the last registered before the work start on the stop work day. When a final stop plan registered from the center server is received, the work target equipment terminal device is registered. Asks for an input as to whether or not to approve the stopped work as the work of the day, and when input is made, sends the input result to the center server. When the input result is received, whether or not the final stop plan execution registered based on this input result can be started is sent to the work terminal unit and displayed. It is characterized in that to.

本発明の請求項8に係るネットワークの作業管理システムでは、データベースには、停止作業日前に最終的な停止計画を登録するとともに、センターサーバは、停止作業日の作業開始前に、登録された最終的な停止計画を、停止作業を承認する判別結果を送信した作業対象設備担当端末装置に送信し、作業対象設備担当端末装置は、センターサーバから登録された最終的な停止計画を受け取ると、登録された停止作業を当日作業として承認するか否かの入力を求め、入力が行われるとその入力結果をセンターサーバに送信し、センターサーバは、作業対象設備担当端末装置から当日の停止作業について諾否の入力結果を受け取ると、この入力結果に基づいて登録された最終的な停止計画実施について開始の可否を作業担当端末装置に送信して表示させるようにしたことにより、最新の通信設備情報に基づいて、停止作業の実施を確認するので、確実性が増す。   In the network work management system according to claim 8 of the present invention, the final stop plan is registered in the database before the stop work day, and the center server registers the final plan registered before the start of the stop work day. When a final stop plan registered from the center server is received, the work target facility terminal device registers the final stop plan. Asks for an input as to whether or not to approve the stopped work as the work of the day, and when input is made, sends the input result to the center server. If the input result is received, whether or not the final stop plan registered based on this input result can be started is transmitted to the work terminal device. By that so as to indicated, based on the latest communication facility information, so confirming the stop work, reliability is increased.

本発明の請求項9に係るネットワークの作業管理システムは、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、通信設備は、インターネットプロトコルを有し、センターサーバからの指令に基づいて、通信設備の状態の情報をセンターサーバに送信する通信設備状態情報送信手段を備え、データベースは、センターサーバにより設定され作業日時と作業設備の情報を含む停止作業計画の情報を格納して構成される作業計画データベースと、作業対象の通信設備から通信設備の設備運用状態の情報が送られてくると、その設備運用状態の情報を格納して構成される設備運用状態管理データベースと、作業対象の通信設備から通信設備の回線状態の情報が送られてくると、その回線状態の情報を格納して構成される回線状態管理データベースとを備え、センターサーバは、停止作業の当日、作業担当端末装置から当該停止作業開始の所定時間前に作業開始の通知を受け取ると、作業計画データベースから設定された停止計画情報を取り出し、作業開始情報とこの停止計画情報を外部に出力する当日作業計画管理手段と、当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し設備運用状況の確認を要求し、当該作業対象設備から設備運用状況の回答を得ると、設備運用状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる設備運用状態管理手段と、当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し回線状況の確認を要求し、当該作業対象設備から回線状況の回答を得ると、回線状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる回線状態管理手段と、当日作業計画管理手段から作業開始情報を受け取ると、設備運用状態管理データベースと回線状態管理データベースとから設備運用状態の情報と回線運用状態の情報とを求め、これら設備運用状態の情報と回線運用状態の情報とを外部に出力するシステム停止管理手段と、システム停止管理手段から設備運用状態の情報と回線運用状態の情報とのうち少なくともいずれか一方を受け取ると、当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるシステム停止判定手段とを備え、当日作業計画管理手段は、作業担当端末装置から作業開始の通知を受け取ると、設備運用状態管理手段と回線状態管理手段とにより当該作業対象の設備から設備運用状態の情報と回線運用状態の情報とを設備運用状態管理データベースと回線状態管理データベースとにそれぞれ格納させ、システム停止管理手段がシステム停止判定手段にこれら格納された設備運用状態の情報と回線運用状態の情報とを送出すると、システム停止判定手段が当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるとともに、当日作業計画管理手段は、作業担当端末装置からの求めに応じて設備運用状態管理手段を通じて設備運用状態の情報を、回線状態管理手段を通じて回線運用状態の情報をそれぞれ作業担当端末装置に送信して表示させることを特徴とするものである。   A network work management system according to claim 9 of the present invention is capable of exchanging work information through communication with a center server that manages and operates the lines of the entire network based on communication facility information stored in a database. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. The communication facility has an internet protocol, and is configured to release the center server The communication facility state information transmitting means for transmitting the state information of the communication facility to the center server based on these instructions, the database is set by the center server, and information on the stop work plan including the work date and time and work facility information Operation plan database configured to store information on the equipment operation status of the communication equipment from the work target communication equipment, and equipment operation status management configured to store the information on the equipment operation status When the communication equipment line status information is sent from the communication equipment to be worked on, the center server includes a line status management database configured to store the information on the line status. On the day, when a work start notification is received from the work-in-charge terminal device a predetermined time before the stop work start, the stop meter set from the work plan database Information is taken out, the work start information and the work plan management means for outputting the stop plan information to the outside, and when the stop plan information is received from the work plan management means on the day, the work target equipment is based on the information of the work target equipment. If the equipment operation status is requested from the work target equipment and the response of the equipment operation status is obtained from the work target equipment, the information is stored in the equipment operation status management database and sent to the terminal device in charge for display. When the stop plan information is received from the management means and the work plan management means on the day, the work target equipment is requested to confirm the line status based on the information on the work target equipment, and the line status answer is sent from the work target equipment. The line status management means for storing the information in the line status management database and sending it to the work terminal device for display, When the work start information is received from the work plan management means, the equipment operation state information and the line operation state information are obtained from the equipment operation state management database and the line state management database, and the equipment operation state information and the line operation state information are obtained. System outage management means for outputting information to the outside, and when at least one of facility operation state information and line operation state information is received from the system outage management means, there is a system outage of the network due to the outage work System stop determination means for transmitting the system stop determination result to the work terminal device and displaying the result, and the work plan management means on the day notifies the start of work from the work terminal device. When received, the equipment operation state management means and the line state management means carry out information on the equipment operation state from the target equipment. And the line operation state information are stored in the facility operation state management database and the line state management database, respectively, and the system stop management unit stores the facility operation state information and the line operation state information stored in the system stop determination unit. The system stop determination means determines whether or not there is a system stop of the network due to the stop work, and the result of the system stop determination is transmitted to the work terminal device and displayed, and the work plan management on the day The means transmits the equipment operation state information through the equipment operation state management means and the line operation state information through the line state management means to the work terminal device in response to a request from the work terminal device. It is a feature.

本発明の請求項9に係るネットワークの作業管理システムでは、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、通信設備は、インターネットプロトコルを有し、センターサーバからの指令に基づいて、通信設備の状態の情報をセンターサーバに送信する通信設備状態情報送信手段を備え、データベースは、センターサーバにより設定され作業日時と作業設備の情報を含む停止作業計画の情報を格納して構成される作業計画データベースと、作業対象の通信設備から通信設備の設備運用状態の情報が送られてくると、その設備運用状態の情報を格納して構成される設備運用状態管理データベースと、作業対象の通信設備から通信設備の回線状態の情報が送られてくると、その回線状態の情報を格納して構成される回線状態管理データベースとを備え、センターサーバは、停止作業の当日、作業担当端末装置から当該停止作業開始の所定時間前に作業開始の通知を受け取ると、作業計画データベースから設定された停止計画情報を取り出し、作業開始情報とこの停止計画情報を外部に出力する当日作業計画管理手段と、当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し設備運用状況の確認を要求し、当該作業対象設備から設備運用状況の回答を得ると、設備運用状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる設備運用状態管理手段と、当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し回線状況の確認を要求し、当該作業対象設備から回線状況の回答を得ると、回線状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる回線状態管理手段と、当日作業計画管理手段から作業開始情報を受け取ると、設備運用状態管理データベースと回線状態管理データベースとから設備運用状態の情報と回線運用状態の情報とを求め、これら設備運用状態の情報と回線運用状態の情報とを外部に出力するシステム停止管理手段と、システム停止管理手段から設備運用状態の情報と回線運用状態の情報とのうち少なくともいずれか一方を受け取ると、当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるシステム停止判定手段とを備え、当日作業計画管理手段は、作業担当端末装置から作業開始の通知を受け取ると、設備運用状態管理手段と回線状態管理手段とにより当該作業対象の設備から設備運用状態の情報と回線運用状態の情報とを設備運用状態管理データベースと回線状態管理データベースとにそれぞれ格納させ、システム停止管理手段がシステム停止判定手段にこれら格納された設備運用状態の情報と回線運用状態の情報とを送出すると、システム停止判定手段が当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるとともに、当日作業計画管理手段は、作業担当端末装置からの求めに応じて設備運用状態管理手段を通じて設備運用状態の情報を、回線状態管理手段を通じて回線運用状態の情報をそれぞれ作業担当端末装置に送信して表示させるようにしたことにより、システム停止の可能性がある場合、作業担当端末装置側で設備の状態や回線の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性を監視し、健全性を確認した上で、実際の停止作業を開始することができる。   In the work management system for a network according to claim 9 of the present invention, a center server that manages and operates the lines of the entire network based on communication facility information stored in a database, and work information can be exchanged through communication with the center server. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. And the communication facility has an Internet protocol and is Communication facility state information transmitting means for transmitting information on the state of communication facilities to the center server based on the command from the information, the database is set by the center server, and information on the stop work plan including work date and time and work facility information Operation plan database configured to store information on the equipment operation status of the communication equipment from the work target communication equipment, and equipment operation status management configured to store the information on the equipment operation status When the communication equipment line status information is sent from the communication equipment to be worked on, the center server includes a line status management database configured to store the information on the line status. On the day, when a work start notification is received from the work terminal device a predetermined time before the stop work start, the stop set from the work plan database The work plan management means for outputting the work start information and the stop plan information to the outside, and when the stop plan information is received from the work plan management means for the day, the work target is based on the information of the work target equipment. When the facility is requested to confirm the facility operation status, and the response of the facility operation status is obtained from the work target facility, the information is stored in the facility operation state management database and transmitted to the work terminal device for display. When the stop plan information is received from the state management means and the work plan management means on the day, the work target equipment is requested to confirm the line status based on the information on the work target equipment, and the line status is answered from the work target equipment. Is stored in the line state management database and transmitted to the work terminal unit for display, and When the work start information is received from the daily work plan management means, the equipment operation state information and the line operation state information are obtained from the equipment operation state management database and the line state management database, and the equipment operation state information and the line operation state are obtained. System outage management means for outputting the information on the outside, and when at least one of the equipment operation state information and the line operation state information is received from the system outage management means, System stop determination means for determining whether or not there is, and transmitting and displaying the result of the system stop determination to the work terminal device, and the work plan management means for the day notifies the work start from the work terminal device Is received from the target equipment by the equipment operation state management means and the line state management means. Information and line operation state information are stored in the facility operation state management database and the line state management database, respectively, and the system stop management means stores the equipment operation state information and line operation state information stored in the system stop determination means. The system stop determination means determines whether there is a system stop of the network due to the stop work, and transmits and displays the result of the system stop determination to the terminal terminal in charge of work, and the work plan for the day. The management means transmits the equipment operation state information through the equipment operation state management means and the line operation state information through the line state management means to the work terminal device in response to a request from the work terminal device. If there is a possibility of system shutdown due to the To grasp the state of the line, it is possible to understand the health of the network, the operator monitors the health of the network, after confirming the soundness, it is possible to start the actual stop working.

本発明の請求項10に係るネットワークの作業管理システムは、センターサーバは、作業担当端末装置から作業対象の通信設備に関して設備の設定について照会要求があると、当該作業対象通信設備に対して設備の設定状況を回答するよう求め、当該作業対象通信設備から受け取った回答を照会要求のあった作業担当端末装置に送信して表示させる設備設定管理手段と、作業担当端末装置から作業対象設備を経由する始端設備情報と終端設備情報とに基づいて作業対象の通信設備に関して経路の照会要求があると、当該作業対象通信設備に対して経路の状況を回答するよう求め、当該作業対象通信設備から受け取った回答を照会要求のあった作業担当端末装置に送信して表示させる経路確認手段とを備えていることを特徴とするものである。   In the work management system for a network according to claim 10 of the present invention, when the center server receives an inquiry request for setting of equipment with respect to the work target communication equipment from the work terminal device, the center server sends the equipment to the work target communication equipment. Requests that the setting status be answered, sends the response received from the work target communication equipment to the work terminal device that requested the inquiry, and displays the setting from the work terminal device via the work target equipment When there is a route inquiry request regarding the communication equipment to be worked on based on the start equipment information and the end equipment information, the work target communication equipment is requested to answer the route status and received from the work target communication equipment. It is characterized by comprising route confirmation means for transmitting and displaying the response to the work-in-charge terminal device that requested the inquiry.

本発明の請求項10に係るネットワークの作業管理システムでは、センターサーバは、作業担当端末装置から作業対象の通信設備に関して設備の設定について照会要求があると、当該作業対象通信設備に対して設備の設定状況を回答するよう求め、当該作業対象通信設備から受け取った回答を照会要求のあった作業担当端末装置に送信して表示させる設備設定管理手段と、作業担当端末装置から作業対象設備を経由する始端設備情報と終端設備情報とに基づいて作業対象の通信設備に関して経路の照会要求があると、当該作業対象通信設備に対して経路の状況を回答するよう求め、当該作業対象通信設備から受け取った回答を照会要求のあった作業担当端末装置に送信して表示させる経路確認手段とを備えたことにより、システム停止の可能性がある場合、作業担当端末装置側で設備の設定状態や経路の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性をより細かく監視することができる。   In the work management system for a network according to claim 10 of the present invention, when the center server receives an inquiry request for setting of equipment with respect to the communication equipment to be worked from the work staff terminal device, Requests that the setting status be answered, sends the response received from the work target communication equipment to the work terminal device that requested the inquiry, and displays the setting from the work terminal device via the work target equipment When there is a route inquiry request regarding the communication equipment to be worked on based on the start equipment information and the end equipment information, the work target communication equipment is requested to answer the route status and received from the work target communication equipment. The system can be shut down by providing a route confirmation means to send the response to the terminal in charge of the inquiry request and display it. If there is, to know the state of the equipment of the setting state and route the work assigned terminal apparatus can grasp the health of the network, the operator can more precisely monitor the health of the network.

本発明の請求項11に係るネットワークの作業管理システムは、センターサーバは、制御コマンドを生成する文法が格納された制御コマンド文法データベースと、外部から入力される指令に基づいて制御コマンド文法データベースにより通信設備の状態の情報を要求する通信設備状態情報要求コマンドを生成し、この通信設備状態情報要求コマンドを該当する通信設備に送信する制御コマンド生成手段とを備え、センターサーバは、作業担当端末装置から設備の運用状態を確認するよう求める照会要求を受け取ると、当日作業計画管理手段から作業計画データベースにより得られた当該設備の情報に基づいて設備運用状態管理手段を通じて制御コマンド生成手段に当該設備の運用状態情報を回答するよう当該設備に求めるコマンドを生成するよう要求し、制御コマンド生成手段は制御コマンド文法データベースに格納された制御コマンドを生成する文法に基づいて当該設備の運用状態を確認して回答するよう求めるコマンドを生成し、このコマンドを対象となる当該設備に投入し、当該対象設備がこのコマンドに対する回答結果をセンターサーバに送出すると、設備運用状態管理手段はこの回答結果を設備運用状態管理データベースに格納するとともに、照会要求のあった作業担当端末装置に送信して表示させ、作業担当端末装置から回線状態を確認するよう求める照会要求を受け取ると、当日作業計画管理手段から作業計画データベースにより得られた当該回線の情報に基づいて回線状態管理手段を通じて制御コマンド生成手段に当該回線の状態情報を回答するよう対象となる設備に求めるコマンドを生成するよう要求し、制御コマンド生成手段は制御コマンド文法データベースに格納された制御コマンドを生成する文法に基づいて当該回線の状態を確認して回答するよう求めるコマンドを生成し、このコマンドを対象となる当該設備に投入し、当該対象設備がこのコマンドに対する回答結果をセンターサーバに送出すると、回線状態管理手段はこの回答結果を回線状態管理データベースに格納するとともに、照会要求のあった作業担当端末装置に送信して表示させることを特徴とするものである。   In the network work management system according to claim 11 of the present invention, the center server communicates with a control command grammar database in which a grammar for generating a control command is stored, and a control command grammar database based on a command input from the outside. A communication equipment state information request command for requesting equipment state information, and a control command generation means for transmitting the communication equipment state information request command to the corresponding communication equipment. When an inquiry request for confirming the operation state of the equipment is received, the operation of the equipment is transmitted to the control command generation means through the equipment operation state management means based on the information of the equipment obtained from the work plan management means on the day from the work plan database. Generate a command that asks the equipment to answer the status information The control command generation means generates a command to check and reply to the operation status of the equipment based on the grammar for generating the control command stored in the control command grammar database, and this command is targeted. When the target equipment sends the response result to this command to the center server, the equipment operation status management means stores this answer result in the equipment operation status management database, and the terminal in charge of the inquiry request. When the inquiry request for confirming the line state is received from the terminal in charge of the work, the line state management means based on the information on the line obtained from the work plan database from the work plan management means on the day The target setting is to return the status information of the line to the control command generator through The control command generation means generates a command for confirming and answering the status of the line based on the grammar for generating the control command stored in the control command grammar database. When the command is input to the target equipment, and the target equipment sends the response result to this command to the center server, the line status management means stores the response result in the line status management database and receives an inquiry request. It is characterized by being transmitted to a work terminal device and displayed.

本発明の請求項11に係るネットワークの作業管理システムでは、センターサーバは、制御コマンドを生成する文法が格納された制御コマンド文法データベースと、外部から入力される指令に基づいて制御コマンド文法データベースにより通信設備の状態の情報を要求する通信設備状態情報要求コマンドを生成し、この通信設備状態情報要求コマンドを該当する通信設備に送信する制御コマンド生成手段とを備え、センターサーバは、作業担当端末装置から設備の運用状態を確認するよう求める照会要求を受け取ると、当日作業計画管理手段から作業計画データベースにより得られた当該設備の情報に基づいて設備運用状態管理手段を通じて制御コマンド生成手段に当該設備の運用状態情報を回答するよう当該設備に求めるコマンドを生成するよう要求し、制御コマンド生成手段は制御コマンド文法データベースに格納された制御コマンドを生成する文法に基づいて当該設備の運用状態を確認して回答するよう求めるコマンドを生成し、このコマンドを対象となる当該設備に投入し、当該対象設備がこのコマンドに対する回答結果をセンターサーバに送出すると、設備運用状態管理手段はこの回答結果を設備運用状態管理データベースに格納するとともに、照会要求のあった作業担当端末装置に送信して表示させ、作業担当端末装置から回線状態を確認するよう求める照会要求を受け取ると、当日作業計画管理手段から作業計画データベースにより得られた当該回線の情報に基づいて回線状態管理手段を通じて制御コマンド生成手段に当該回線の状態情報を回答するよう対象となる設備に求めるコマンドを生成するよう要求し、制御コマンド生成手段は制御コマンド文法データベースに格納された制御コマンドを生成する文法に基づいて当該回線の状態を確認して回答するよう求めるコマンドを生成し、このコマンドを対象となる当該設備に投入し、当該対象設備がこのコマンドに対する回答結果をセンターサーバに送出すると、回線状態管理手段はこの回答結果を回線状態管理データベースに格納するとともに、照会要求のあった作業担当端末装置に送信して表示させるようにしたことにより、オペレータが作業担当端末装置を操作して通信設備の状態を確認する照会要求をセンターサーバ側に送信するだけで、設備の運用状態、回線状態、設備の設定状態、経路の状態のうち少なくともいずれか1を作業担当端末装置に表示させて知ることができる。   In the work management system for a network according to claim 11 of the present invention, the center server communicates with the control command grammar database storing the grammar for generating the control command and the control command grammar database based on the command input from the outside. A communication equipment state information request command for requesting equipment state information, and a control command generation means for transmitting the communication equipment state information request command to the corresponding communication equipment. When an inquiry request for confirming the operation state of the equipment is received, the operation of the equipment is transmitted to the control command generation means through the equipment operation state management means based on the information of the equipment obtained from the work plan management means on the day from the work plan database. Generate a command that asks the equipment to return status information The control command generation means generates a command for confirming and replying to the operation status of the equipment based on the grammar for generating the control command stored in the control command grammar database, and this command is targeted. When the target equipment sends the response result to this command to the center server, the equipment operation status management means stores this answer result in the equipment operation status management database, and the terminal in charge of the inquiry request. When the inquiry request for confirming the line state is received from the terminal in charge of the work, the line state management means based on the information on the line obtained from the work plan database from the work plan management means on the day Through the control command generation means through the status information of the line The control command generation means generates a command for confirming and answering the status of the line based on the grammar for generating the control command stored in the control command grammar database. When this command is input to the target equipment, and the target equipment sends the response result to this command to the center server, the line status management means stores the response result in the line status management database, and receives an inquiry request. The operation status of the equipment can be displayed simply by sending an inquiry request to the center server to confirm the status of the communication equipment by operating the work charge terminal device. , Line status, equipment setting status, route status at least one of the statuses to the work terminal device You can know by displaying.

本発明の請求項12に係るネットワークの作業管理システムは、データベースには、網構成および局内構成を含む物理回線構成情報と機器および機器内の部位情報を含む装置構成情報と論理回線名および論理回線構成を含む論理回線構成情報とが格納されるよう構成され、センターサーバは、作業担当端末装置から設備の停止または停止解除の作業計画が入力されるとこの作業計画を外部に出力し、作業担当端末装置から作業計画の作業対象設備について選択情報が入力されるとこの選択情報に基づいて作業計画を決定する作業計画管理手段と、作業計画管理手段から作業対象設備の情報を受け取ると、受け取った作業対象設備の情報に基づき、データベースから物理回線構成情報と装置構成情報と論理回線構成情報とを抽出して物理網構成図、論理網構成図および局内構成図のうち少なくともいずれか1を描画処理し、これらを作業担当端末装置に送信して表示させるとともに、抽出された各構成情報と上記作業対象設備の情報とを外部に出力する物理網・論理網・局内構成図描画処理手段と、物理網・論理網・局内構成図描画処理手段から受け取った各構成情報と作業対象設備の情報とに基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1についての候補を抽出し、抽出された候補情報を物理網・論理網・局内構成図描画処理手段に出力する作業対象候補抽出手段とを備え、物理網・論理網・局内構成図描画処理手段は、作業対象候補抽出手段から抽出された候補情報を受け取ると、この候補情報に基づいて、作業担当端末装置に表示される描画処理された各構成図上に候補情報を含ませるとともに、作業担当端末装置は表示された候補情報から作業対象設備が選択されると、選択情報を作業計画管理手段に送信し、作業計画管理手段は選択情報に基づいて最終的な作業計画を決定することを特徴とするものである。   In a network work management system according to a twelfth aspect of the present invention, the database includes physical line configuration information including network configuration and in-station configuration, device configuration information including device and part information in the device, logical line name and logical line. The logical line configuration information including the configuration is stored, and the center server outputs the work plan to the outside when a work plan for stopping or canceling the equipment is input from the work terminal device. When selection information is input from the terminal device regarding the work target equipment of the work plan, the work plan management means for determining the work plan based on the selection information and the information on the work target equipment from the work plan management means are received. Physical network configuration by extracting physical line configuration information, equipment configuration information, and logical line configuration information from the database based on the information of the work target equipment In addition, at least one of the logical network configuration diagram and the intra-station configuration diagram is drawn and transmitted to the work terminal device for display, and the extracted configuration information and the work facility information are externally displayed. The physical network / logical network / intra-station configuration diagram drawing processing means to be output to the physical network / logical network / intra-station configuration diagram drawing processing means, and each piece of configuration information received from the physical network / logical network / intra-station configuration diagram drawing processing means and information on the work target facility A work candidate extraction unit that extracts a candidate for at least one of a device related to a line or a port portion of the device and outputs the extracted candidate information to a physical network / logical network / internal station configuration diagram drawing processing unit; When the candidate information extracted from the work target candidate extraction unit is received, the physical network / logical network / intra-station configuration diagram drawing processing unit receives the candidate information based on the candidate information. In addition to including candidate information on each rendered configuration diagram shown, the work terminal device transmits the selected information to the work plan management means when the work target equipment is selected from the displayed candidate information, The plan management means is characterized in that a final work plan is determined based on the selection information.

本発明の請求項12に係るネットワークの作業管理システムでは、データベースには、網構成および局内構成を含む物理回線構成情報と機器および機器内の部位情報を含む装置構成情報と論理回線名および論理回線構成を含む論理回線構成情報とが格納されるよう構成され、センターサーバは、作業担当端末装置から設備の停止または停止解除の作業計画が入力されるとこの作業計画を外部に出力し、作業担当端末装置から作業計画の作業対象設備について選択情報が入力されるとこの選択情報に基づいて作業計画を決定する作業計画管理手段と、作業計画管理手段から作業対象設備の情報を受け取ると、受け取った作業対象設備の情報に基づき、データベースから物理回線構成情報と装置構成情報と論理回線構成情報とを抽出して物理網構成図、論理網構成図および局内構成図のうち少なくともいずれか1を描画処理し、これらを作業担当端末装置に送信して表示させるとともに、抽出された各構成情報と上記作業対象設備の情報とを外部に出力する物理網・論理網・局内構成図描画処理手段と、物理網・論理網・局内構成図描画処理手段から受け取った各構成情報と作業対象設備の情報とに基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1についての候補を抽出し、抽出された候補情報を物理網・論理網・局内構成図描画処理手段に出力する作業対象候補抽出手段とを備え、物理網・論理網・局内構成図描画処理手段は、作業対象候補抽出手段から抽出された候補情報を受け取ると、この候補情報に基づいて、作業担当端末装置に表示される描画処理された各構成図上に候補情報を含ませるとともに、作業担当端末装置は表示された候補情報から作業対象設備が選択されると、選択情報を作業計画管理手段に送信し、作業計画管理手段は選択情報に基づいて最終的な作業計画を決定するようにしたことにより、センターサーバに作業担当端末装置から設備の停止または停止解除の作業計画が入力されると、作業計画管理手段はこの作業計画を仮の作業計画として保持するとともに、作業計画情報を物理網・論理網・局内構成図描画処理手段に出力する。物理網・論理網・局内構成図描画処理手段は、受け取った作業対象設備の情報に基づき、データベースから物理回線構成情報と装置構成情報と論理回線構成情報とを抽出して物理網構成図、論理網構成図および局内構成図のうち少なくともいずれか1を描画処理し、これらを作業担当端末装置に送信して表示させるとともに、抽出された各構成情報と上記作業対象設備の情報とを作業対象候補抽出手段に出力する。作業対象候補抽出手段は、受け取った各構成情報と作業対象設備の情報とに基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1についての候補を抽出し、抽出された候補情報を物理網・論理網・局内構成図描画処理手段に出力する。物理網・論理網・局内構成図描画処理手段は、作業対象候補抽出手段から抽出された候補情報を受け取ると、この候補情報に基づいて、作業担当端末装置に表示される描画処理された各構成図上に候補情報を含ませて表示させる。作業担当端末装置は、オペレータにより表示された候補情報から作業対象設備が選択されると、選択情報を作業計画管理手段に送信する。作業計画管理手段は、作業計画管理手段は選択情報に基づいて最終的な作業計画を決定する。このため、停止対象とすべき通信設備の候補が関連する図面に含まれて表示されることになり、オペレータは、停止対象とすべき通信設備を決定する作業がし易くなる。   In the network work management system according to the twelfth aspect of the present invention, the database includes physical line configuration information including network configuration and in-station configuration, device configuration information including device and part information in the device, logical line name and logical line. The logical line configuration information including the configuration is stored, and the center server outputs the work plan to the outside when a work plan for stopping or canceling the equipment is input from the work terminal device. When selection information is input from the terminal device regarding the work target equipment of the work plan, the work plan management means for determining the work plan based on the selection information and the information on the work target equipment from the work plan management means are received. Based on the information on the work target facility, the physical network configuration information, device configuration information, and logical line configuration information are extracted from the database. At least one of the diagram, the logical network configuration diagram, and the intra-station configuration diagram is drawn and transmitted to the work terminal unit for display, and the extracted configuration information and the work target facility information are displayed. Based on the physical network / logical network / intra-station configuration diagram drawing processing means to be output to the outside, each configuration information received from the physical network / logical network / intra-station configuration diagram drawing processing means and information on the work target equipment Candidate extraction means for extracting a candidate for at least one of a device or a port portion of the device related to the line and outputting the extracted candidate information to a physical network / logical network / intra-station configuration diagram drawing processing means When the candidate information extracted from the work target candidate extraction unit is received, the physical network / logical network / internal station configuration diagram drawing processing unit receives the candidate information based on the candidate information. In addition to including candidate information on each rendered configuration diagram that is displayed, when the work target terminal device is selected from the displayed candidate information, the work responsible terminal device transmits the selection information to the work plan management means, Since the work plan management means determines the final work plan based on the selected information, the work plan management is performed when the work plan for stopping or canceling the equipment is input from the work terminal device to the center server. The means holds the work plan as a temporary work plan, and outputs the work plan information to the physical network / logical network / internal station configuration diagram drawing processing means. The physical network / logical network / intra-station configuration diagram drawing processing means extracts physical line configuration information, device configuration information, and logical line configuration information from the database based on the received work target facility information, and creates a physical network configuration diagram, logical At least one of the network configuration diagram and the intra-station configuration diagram is drawn and transmitted to the work terminal device for display, and the extracted configuration information and the information on the work target equipment are the work target candidates. Output to extraction means. The work target candidate extracting means extracts a candidate for at least one of a device related to the line of the work target facility or a port portion of the device based on each received configuration information and information of the work target facility, The extracted candidate information is output to the physical network / logical network / internal station configuration diagram drawing processing means. When the physical network / logical network / intra-station configuration diagram drawing processing means receives the candidate information extracted from the work target candidate extracting means, each drawing-processed configuration displayed on the work terminal unit is displayed based on the candidate information. Candidate information is included and displayed on the figure. When the work target equipment is selected from the candidate information displayed by the operator, the work charge terminal device transmits the selection information to the work plan management means. The work plan management means determines a final work plan based on the selection information. For this reason, the candidate of the communication equipment that should be the stop target is included and displayed in the related drawings, and the operator can easily determine the communication equipment that should be the stop target.

本発明の請求項13に係るネットワークの作業管理システムは、データベースには、各保守担当域の通信設備に関連付けされた端末装置の情報が格納され、センターサーバは、作業担当端末装置から設備の停止または停止解除の作業計画が入力されると、外部からの承認情報に基づいてこの作業計画を決定する作業計画管理手段と、作業担当端末装置から作業対象設備について機器または機器のポート部のうち少なくともいずれか1を選択する選択情報が入力されると、機器または機器のポート部のうち少なくともいずれか1を決定し決定情報を外部に出力する作業対象設備決定手段と、作業対象設備決定手段から決定情報を受け取ると、この決定情報に基づき、データベースからこの決定された作業対象設備が属する保守担当域を所管する端末装置を抽出し、この作業対象設備を担当する端末装置を特定する情報を外部に出力する作業対象設備担当端末装置抽出手段と、作業対象設備担当端末装置抽出手段から出力された作業対象設備担当端末装置の特定情報を受け取り、この特定情報に基づき、当該作業対象設備担当端末装置に当該決定情報と作業日時情報とを送信し作業実施を承認するか否かの承認要求を行うとともに、この作業対象設備担当端末装置から作業実施の承認の諾否の情報を受け取ると、この諾否情報を作業計画管理手段に出力する承認処理手段とを備えて構成され、作業計画管理手段は、承認処理手段から作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とするものである。   In the network work management system according to claim 13 of the present invention, the database stores information on terminal devices associated with the communication equipment in each maintenance area, and the center server stops the equipment from the work terminal equipment. Alternatively, when the work plan for canceling the stop is input, the work plan management means for determining the work plan based on the external approval information, and at least the device or the port portion of the device for the work target facility from the work terminal device When selection information for selecting any one is input, it is determined from the work target facility determining means for determining at least one of the devices or the port portion of the device and outputting the determined information to the outside, and the work target facility determining means. When the information is received, based on this decision information, the maintenance area to which the determined work target equipment belongs is managed from the database. The terminal device extracting means for extracting the terminal device and specifying the terminal device in charge of the work target equipment to the outside, the work target facility terminal device extracting means for outputting the information, and the work target equipment charge output from the work target facility charge terminal device extracting means The terminal device specific information is received, and based on this specific information, the decision information and the work date information are transmitted to the work target facility charge terminal device, and an approval request is made as to whether or not to approve the work. Upon receipt of approval / disapproval information for approval of work execution from the terminal equipment in charge of the target facility, the approval processing means is configured to output the approval / disapproval information to the work plan management means. When the acceptance / rejection determination result is received, whether or not the scheduled work can be performed is determined based on the determination result, and the determination of whether or not the work can be performed is performed. It is characterized in that the display in the transmission device to.

本発明の請求項13に係るネットワークの作業管理システムでは、データベースには、各保守担当域の通信設備に関連付けされた端末装置の情報が格納され、センターサーバは、作業担当端末装置から設備の停止または停止解除の作業計画が入力されると、外部からの承認情報に基づいてこの作業計画を決定する作業計画管理手段と、作業担当端末装置から作業対象設備について機器または機器のポート部のうち少なくともいずれか1を選択する選択情報が入力されると、機器または機器のポート部のうち少なくともいずれか1を決定し決定情報を外部に出力する作業対象設備決定手段と、作業対象設備決定手段から決定情報を受け取ると、この決定情報に基づき、データベースからこの決定された作業対象設備が属する保守担当域を所管する端末装置を抽出し、この作業対象設備を担当する端末装置を特定する情報を外部に出力する作業対象設備担当端末装置抽出手段と、作業対象設備担当端末装置抽出手段から出力された作業対象設備担当端末装置の特定情報を受け取り、この特定情報に基づき、当該作業対象設備担当端末装置に当該決定情報と作業日時情報とを送信し作業実施を承認するか否かの承認要求を行うとともに、この作業対象設備担当端末装置から作業実施の承認の諾否の情報を受け取ると、この諾否情報を作業計画管理手段に出力する承認処理手段とを備えて構成され、作業計画管理手段は、承認処理手段から作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させるようにしたことにより、センターサーバに作業担当端末装置から作業計画が入力されると、作業計画管理手段は仮の作業計画として保持するとともに、センターサーバに作業担当端末装置から作業対象設備について機器または機器のポート部のうち少なくともいずれか1を選択する選択情報が入力されると、作業対象設備決定手段は機器または機器のポート部のうち少なくともいずれか1を決定し決定情報を作業対象設備担当端末装置抽出手段に出力する。作業対象設備担当端末装置抽出手段は、決定情報に基づき、データベースからこの決定された作業対象設備が属する保守担当域を所管する端末装置を抽出し、この作業対象設備を担当する端末装置を特定する特定情報を承認処理手段に出力する。承認処理手段は、作業対象設備担当端末装置の特定情報を受け取り、この特定情報に基づき、特定された作業対象設備担当端末装置に当該決定情報と作業日時情報とを送信し作業実施の承認要求を行う。作業対象設備担当端末装置は承認処理手段から当該決定情報と作業日時情報と作業実施の承認要求とを受け取ると、オペレータにより作業の実施を承認するか否かを判別し、作業実施承認諾否情報を承認処理手段に送信する。承認処理手段は、作業対象設備担当端末装置から承認諾否情報を受け取ると、作業計画管理手段に出力する。作業計画管理手段は受け取った承認諾否情報に基づいて、作業承諾の情報の場合、仮の作業計画を最終的な作業計画としてデータベースに登録するとともに、作業承諾の情報を作業担当端末装置に送信して表示させ、作業承諾拒否の情報の場合、仮の作業計画をキャンセルし、作業承諾拒否の情報を作業担当端末装置に送信して表示させる。このため、自らの保守担当域と異なる他の保守担当域で停止作業を行う際、停止作業承認の依頼と承認の通知との遣り取りをセンターサーバと端末装置とを通じて行うので、作業者側と停止作業対象設備を有する被作業者側との間の停止作業に関する調整が自動化される。   In the network work management system according to the thirteenth aspect of the present invention, the database stores information on terminal devices associated with the communication equipment in each maintenance area, and the center server stops the equipment from the work terminal equipment. Alternatively, when a work plan for canceling a stop is input, a work plan management means for determining the work plan based on external approval information and at least one of the equipment or the port portion of the equipment for the work target equipment from the work terminal device When selection information for selecting any one is input, it is determined from the work target facility determining means for determining at least one of the devices or the port portion of the device and outputting the determined information to the outside, and the work target facility determining means. When the information is received, the maintenance area to which the determined work target equipment belongs is managed from the database based on the determined information. The terminal device is extracted, and the work target facility responsible terminal device extracting means for outputting the information specifying the terminal device in charge of the work target facility to the outside, and the work target facility responsible output from the work target facility responsible terminal device extracting means The terminal device specific information is received, and based on this specific information, the decision information and the work date / time information are transmitted to the work target facility terminal device and an approval request is made as to whether or not to approve the work. Upon receipt of approval / disapproval information for the approval of work execution from the terminal equipment in charge of the target facility, the approval processing means is configured to output the approval / disapproval information to the work plan management means. When the acceptance / rejection determination result is received, whether or not the scheduled work can be performed is determined based on the determination result, and the determination of whether or not the work can be performed is in charge of the work. When the work plan is input from the work terminal device to the center server, the work plan management means holds it as a temporary work plan and also sends the work plan to the center server. When selection information for selecting at least one of the equipment and the port portion of the equipment is input from the apparatus to the work target equipment, the work target equipment determining unit determines at least one of the equipment or the port portion of the equipment. The decision information is output to the work target facility terminal device extraction means. Based on the determination information, the work target facility terminal device extraction means extracts a terminal device that has jurisdiction over the maintenance area to which the determined work target facility belongs, and identifies the terminal device in charge of the work target facility. The specific information is output to the approval processing means. The approval processing means receives the specific information of the work target equipment responsible terminal device, and based on this specific information, transmits the decision information and the work date and time information to the specified work target equipment responsible terminal device, and issues a work execution approval request. Do. Upon receiving the determination information, the work date and time information, and the work execution approval request from the approval processing means, the work target facility terminal device determines whether or not to approve the execution of the work by the operator. Send to approval processing means. When the approval processing means receives approval approval / disapproval information from the work object facility terminal device, the approval processing means outputs it to the work plan management means. Based on the received approval approval / disapproval information, the work plan management means, in the case of work approval information, registers the temporary work plan in the database as the final work plan, and transmits the work approval information to the work terminal device. In the case of work acceptance refusal information, the temporary work plan is canceled and the work acceptance refusal information is transmitted to the work terminal unit for display. For this reason, when a stop operation is performed in another maintenance area different from its own maintenance area, the stop server approval request and the notification of approval are exchanged through the center server and the terminal device. Adjustment regarding stop work with the worker side having the work target facility is automated.

本発明の請求項14に係るネットワークの作業管理システムは、データベースには、網構成および局内構成を含む物理回線構成情報と機器内部位情報を含む装置構成情報と論理回線名および論理回線構成を含む論理回線構成情報とが格納されるとともに、各保守担当域の通信設備に関連付けされた端末装置の情報が格納され、センターサーバは、作業計画管理手段と物理網・論理網・局内構成図描画処理手段と作業対象候補抽出手段と作業対象設備決定手段と作業対象設備担当端末装置抽出手段と承認処理手段とを備えて構成され、
作業担当端末装置は、表示された作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補に対し、オペレータにより作業対象とすべき機器または機器のポート部のうち少なくともいずれか1が選択されると、その選択情報をセンターサーバに送信し、作業対象設備決定手段は、作業担当端末装置からこの選択情報を受け取ると、選択情報に基づいて機器または機器のポート部のうち少なくともいずれか1を決定して決定情報を出力し、作業対象設備担当端末装置抽出手段は、この決定情報を受け取ると、この決定情報と作業計画の情報とに基づいて、決定された機器または機器のポート部を自らの保守担当域に有しそれらを管理する作業対象設備担当端末装置を抽出し、
承認処理手段は、抽出された作業対象設備担当端末装置の特定情報に基づいて、抽出された作業対象設備担当端末装置に作業日時の情報とともに決定された機器または決定されたポート部を有する機器の決定情報を送信し、当該作業対象設備担当端末装置は、作業日時の情報と決定情報とを受け取ると、これら情報に基づいて、予定された作業の実施を承認するか否かの判別を行い、その判別結果をセンターサーバに送信し、作業計画管理手段は、作業対象設備担当端末装置から承認処理手段を通じて作業実施について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とするものである。
In the network work management system according to the fourteenth aspect of the present invention, the database includes physical line configuration information including network configuration and in-station configuration, device configuration information including in-apparatus part information, logical line name, and logical line configuration. In addition to storing logical line configuration information, information on terminal devices associated with communication facilities in each maintenance area is stored, and the center server performs work plan management means and physical network / logical network / internal station configuration diagram drawing processing. Comprising means, work target candidate extraction means, work target equipment determination means, work target equipment responsible terminal device extraction means, and approval processing means,
The work-in-use terminal device has at least one of the device or the port portion of the device to be worked by the operator with respect to at least one candidate of the device or the device port portion related to the displayed line of the work target facility. When any one is selected, the selection information is transmitted to the center server, and the work target equipment determining means receives the selection information from the work terminal unit, and receives the selection information from the device or the port portion of the device based on the selection information. At least one of them is determined and the determination information is output, and the work target facility terminal device extracting means receives the determination information, and based on the determination information and the information of the work plan, Extract the terminal equipment in charge of the work equipment that has the port part of the equipment in its own maintenance area and manages them,
The approval processing means, based on the extracted identification information of the work target facility terminal device, the device of the extracted work target facility terminal device together with the information of the work date and time of the device having the determined port unit Sending the decision information, when the work target equipment responsible terminal device receives the work date information and the decision information, based on these information, determine whether to approve the execution of the scheduled work, The determination result is transmitted to the center server, and when the work plan management means receives the determination result of approval or disapproval for the work execution from the work object facility terminal device through the approval processing means, the work plan management means performs the scheduled work execution based on the determination result. In addition to determining whether or not work is possible, the determination as to whether or not work can be performed is transmitted to the work terminal unit and displayed.

本発明の請求項14に係るネットワークの作業管理システムでは、データベースには、網構成および局内構成を含む物理回線構成情報と機器内部位情報を含む装置構成情報と論理回線名および論理回線構成を含む論理回線構成情報とが格納されるとともに、各保守担当域の通信設備に関連付けされた端末装置の情報が格納され、センターサーバは、作業計画管理手段と物理網・論理網・局内構成図描画処理手段と作業対象候補抽出手段と作業対象設備決定手段と作業対象設備担当端末装置抽出手段と承認処理手段とを備えて構成され、作業担当端末装置は、表示された作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補に対し、オペレータにより作業対象とすべき機器または機器のポート部のうち少なくともいずれか1が選択されると、その選択情報をセンターサーバに送信し、作業対象設備決定手段は、作業担当端末装置からこの選択情報を受け取ると、選択情報に基づいて機器または機器のポート部のうち少なくともいずれか1を決定して決定情報を出力し、作業対象設備担当端末装置抽出手段は、この決定情報を受け取ると、この決定情報と作業計画の情報とに基づいて、決定された機器または機器のポート部を自らの保守担当域に有しそれらを管理する作業対象設備担当端末装置を抽出し、
承認処理手段は、抽出された作業対象設備担当端末装置の特定情報に基づいて、抽出された作業対象設備担当端末装置に作業日時の情報とともに決定された機器または決定されたポート部を有する機器の決定情報を送信し、当該作業対象設備担当端末装置は、作業日時の情報と決定情報とを受け取ると、これら情報に基づいて、予定された作業の実施を承認するか否かの判別を行い、その判別結果をセンターサーバに送信し、作業計画管理手段は、作業対象設備担当端末装置から承認処理手段を通じて作業実施について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させるようにしたことにより、センターサーバに作業担当端末装置から設備の停止または停止解除の作業計画が入力されると、作業計画管理手段はこの作業計画を第1の仮の作業計画として保持するとともに、作業計画情報を物理網・論理網・局内構成図描画処理手段に出力する。物理網・論理網・局内構成図描画処理手段は、受け取った作業対象設備の情報に基づき、データベースから物理回線構成情報と装置構成情報と論理回線構成情報とを抽出して物理網構成図、論理網構成図および局内構成図のうち少なくともいずれか1を描画処理し、これらを作業担当端末装置に送信して表示させるとともに、抽出された各構成情報と上記作業対象設備の情報とを作業対象候補抽出手段に出力する。作業対象候補抽出手段は、受け取った各構成情報と作業対象設備の情報とに基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1についての候補を抽出し、抽出された候補情報を物理網・論理網・局内構成図描画処理手段に出力する。物理網・論理網・局内構成図描画処理手段は、作業対象候補抽出手段から抽出された候補情報を受け取ると、この候補情報に基づいて、作業担当端末装置に表示される描画処理された各構成図上に候補情報を含ませて表示させる。作業担当端末装置は、オペレータにより表示された候補情報から作業対象設備が選択されると、選択情報を作業計画管理手段に送信する。作業計画管理手段は作業担当端末装置から選択情報が入力されるとこの選択情報に基づいて第1の仮の作業計画を候補選択による第2の仮の作業計画として決定し、データベースに登録するとともに、決定された第2の仮の作業計画を作業担当端末に表示させる。センターサーバに作業担当端末装置から抽出された候補情報の作業対象設備について機器または機器のポート部のうち少なくともいずれか1を選択する選択情報が入力されると、作業対象設備決定手段は機器または機器のポート部のうち少なくともいずれか1を決定し決定情報を作業対象設備担当端末装置抽出手段に出力する。作業対象設備担当端末装置抽出手段は、決定情報に基づき、データベースからこの決定された作業対象設備が属する保守担当域を所管する端末装置を抽出し、この作業対象設備を担当する端末装置を特定する特定情報を承認処理手段に出力する。承認処理手段は、作業対象設備担当端末装置の特定情報を受け取り、この特定情報に基づき、特定された作業対象設備担当端末装置に当該決定情報と作業日時情報とを送信し作業実施の承認要求を行う。作業対象設備担当端末装置は承認処理手段から当該決定情報と作業日時情報とを受け取ると、オペレータが作業の実施を承認するか否かを判別し、作業実施承認諾否情報を承認処理手段に送信する。承認処理手段は、作業対象設備担当端末装置から承認諾否情報を受け取ると、作業計画管理手段に出力する。作業計画管理手段は受け取った承認諾否情報に基づいて、作業承諾の情報の場合、第2の仮の作業計画を最終的な作業計画としてデータベースに登録するとともに、作業承諾の情報を作業担当端末装置に送信して表示させ、作業承諾拒否の情報の場合、第2の仮の作業計画をキャンセルし、作業承諾拒否の情報を作業担当端末装置に送信して表示させる。このため、オペレータにより半自動で停止作業対象の候補を選択することができ、停止対象とすべき通信設備を検討する時間を短縮することができ、停止対象とすべき通信設備を決定する作業が迅速化される。また、作業者側と停止作業対象設備を有する被作業者側との間の調整が自動化される。作業者側と被作業者側とに停止作業に関する調整の負担がかからなくなる。
In the network work management system according to the fourteenth aspect of the present invention, the database includes physical line configuration information including network configuration and in-station configuration, device configuration information including in-apparatus part information, logical line name and logical line configuration. In addition to storing logical line configuration information, information on terminal devices associated with communication facilities in each maintenance area is stored, and the center server performs work plan management means and physical network / logical network / internal station configuration diagram drawing processing. Means, work target candidate extraction means, work target equipment determination means, work target equipment responsible terminal device extraction means, and approval processing means, and the work responsible terminal device relates to the line of the displayed work target equipment. Of the equipment or the port portion of the equipment, at least one candidate of the equipment or the port portion of the equipment should be a small number of equipment or the port portion of the equipment to be worked by the operator. When at least any one is selected, the selection information is transmitted to the center server, and the work target equipment determining means receives the selection information from the work terminal unit, and receives the selection information from the equipment or the port of the equipment based on the selection information. At least any one of the units is determined and the determination information is output, and the work target facility terminal device extracting means receives the determination information, and is determined based on the determination information and the information of the work plan. Extract the equipment or terminal unit in charge of the work equipment that has the port part of the equipment in its own maintenance area and manages them,
The approval processing means, based on the extracted identification information of the work target facility terminal device, the device of the extracted work target facility terminal device together with the information of the work date and time of the device having the determined port unit Sending the decision information, when the work target equipment responsible terminal device receives the work date information and the decision information, based on these information, determine whether to approve the execution of the scheduled work, The determination result is transmitted to the center server, and when the work plan management means receives the determination result of approval or disapproval for the work execution from the work object facility terminal device through the approval processing means, the work plan management means performs the scheduled work execution based on the determination result. In addition to determining whether or not work can be performed, the determination of whether or not work can be performed is sent to the terminal unit in charge for display and displayed on the center server. When a work plan for stopping or canceling the equipment is input from the device, the work plan management means holds this work plan as a first temporary work plan, and the work plan information includes physical network / logical network / intra-station configuration. Output to the figure drawing processing means. The physical network / logical network / intra-station configuration diagram drawing processing means extracts physical line configuration information, device configuration information, and logical line configuration information from the database based on the received work target facility information, and creates a physical network configuration diagram, logical At least one of the network configuration diagram and the intra-station configuration diagram is drawn and transmitted to the work terminal device for display, and the extracted configuration information and the information on the work target equipment are the work target candidates. Output to extraction means. The work target candidate extracting means extracts a candidate for at least one of a device related to the line of the work target facility or a port portion of the device based on each received configuration information and information of the work target facility, The extracted candidate information is output to the physical network / logical network / internal station configuration diagram drawing processing means. When the physical network / logical network / intra-station configuration diagram drawing processing means receives the candidate information extracted from the work target candidate extracting means, each drawing-processed configuration displayed on the work terminal unit based on the candidate information. Candidate information is included and displayed on the figure. When the work target equipment is selected from the candidate information displayed by the operator, the work charge terminal device transmits the selection information to the work plan management means. When the selection information is input from the work terminal device, the work plan management means determines the first temporary work plan as the second temporary work plan by candidate selection based on this selection information, and registers it in the database. The determined second temporary work plan is displayed on the work terminal. When selection information for selecting at least one of the equipment and the port part of the equipment is input to the center server for the work target equipment of the candidate information extracted from the work terminal device, the work target equipment determination means is the equipment or equipment. At least one of the port portions is determined, and the determination information is output to the work equipment-in-charge terminal device extraction means. Based on the determination information, the work target facility terminal device extraction means extracts a terminal device that has jurisdiction over the maintenance area to which the determined work target facility belongs, and identifies the terminal device in charge of the work target facility. The specific information is output to the approval processing means. The approval processing means receives the specific information of the work target equipment responsible terminal device, and based on this specific information, transmits the decision information and the work date and time information to the specified work target equipment responsible terminal device, and issues a work execution approval request. Do. Upon receiving the determination information and work date / time information from the approval processing unit, the work target facility terminal device determines whether or not the operator approves the execution of the work, and transmits the work execution approval approval / disapproval information to the approval processing unit. . When the approval processing means receives approval approval / disapproval information from the work object facility terminal device, the approval processing means outputs it to the work plan management means. The work plan management means registers the second provisional work plan in the database as a final work plan based on the received approval / denial information, and stores the work approval information in the work terminal device. In the case of work acceptance refusal information, the second provisional work plan is canceled, and work acceptance refusal information is sent to the work terminal device for display. For this reason, the operator can select a candidate for a stop work target semi-automatically, can reduce the time for considering the communication equipment to be stopped, and can quickly determine the communication equipment to be stopped. It becomes. In addition, the adjustment between the worker side and the worker side having the facility to be stopped is automated. The burden of adjustment on stop work is not applied to the worker side and the worker side.

本発明の請求項15に係るネットワークの作業管理システムは、作業計画が予め計画された停止日時と停止設備との情報を含む停止計画であり、作業計画管理手段は、停止作業日前に、データベースに停止計画に対し実施が決定された停止作業を最終的な停止計画として登録し、作業対象設備担当端末装置は、停止作業の当日、停止作業開始の所定時間前に、センターサーバから登録された最終的な停止計画を受け取ると、登録された停止作業を当日作業として承認するか否かの判別を行い、その判別結果を、センターサーバに送信するよう構成するとともに、当日作業計画管理手段を、停止作業の当日、停止作業開始の所定時間前になると、データベースから登録された最終的な停止計画情報を取り出し、この最終的な停止計画情報に基づいて当日の停止作業の対象となる作業対象設備担当端末装置の特定情報を外部に出力するとともに、上記作業対象設備担当端末装置から停止作業当日の停止作業実施について諾否の判別結果を受け取ると、この判別結果に基づいて登録された最終的な停止計画の実施について開始の可否を作業担当端末装置に送信して表示させるよう構成し、センターサーバには、当日作業計画手段から受け取った作業対象設備担当端末装置の特定情報に基づいて、当日の停止作業の対象となる作業対象設備担当端末装置に、最終的な停止計画情報に含まれる停止日時情報と停止対象設備情報とを送信し、当該作業対象設備担当端末装置から停止作業を当日作業として承認するか否かの判別結果を受け取ると、その判別結果を当日作業計画管理手段に出力する当日作業承認処理手段を設けたことを特徴とするものである。   A network work management system according to a fifteenth aspect of the present invention is a stop plan that includes information on a stop date and a stop facility in which the work plan is planned in advance, and the work plan management means stores the information in the database before the stop work date. The stop work decided to be implemented for the stop plan is registered as the final stop plan, and the terminal equipment in charge of the work target equipment is registered with the center server on the day of the stop work, a predetermined time before the start of the stop work. When a typical stop plan is received, it is determined whether or not the registered stop work is approved as the current day work, and the determination result is transmitted to the center server, and the current day work plan management means is stopped. On the day of the work, if it is a predetermined time before the start of the stop work, the final stop plan information registered from the database is taken out, and based on this final stop plan information. When the specific information of the work target facility terminal device that is the target of the stop work on the current day is output to the outside, The final stop plan registered based on the determination result is configured to be sent to the work terminal device for display of whether or not it can be started. The center server is in charge of the work target equipment received from the work plan means on the day. Based on the specific information of the terminal device, the stop date and time information and the stop target facility information included in the final stop plan information are transmitted to the work target facility charge terminal device that is the target of the stop operation on the current day, and the target work When receiving the determination result of whether or not to approve the stop work as the current day work from the equipment terminal device, the determination result is output to the current day work plan management means. In which it characterized in that a day working approval processing unit.

本発明の請求項15に係るネットワークの作業管理システムでは、作業計画が予め計画された停止日時と停止設備との情報を含む停止計画であり、作業計画管理手段は、停止作業日前に、データベースに停止計画に対し実施が決定された停止作業を最終的な停止計画として登録し、作業対象設備担当端末装置は、停止作業の当日、停止作業開始の所定時間前に、センターサーバから登録された最終的な停止計画を受け取ると、登録された停止作業を当日作業として承認するか否かの判別を行い、その判別結果を、センターサーバに送信するよう構成するとともに、当日作業計画管理手段を、停止作業の当日、停止作業開始の所定時間前になると、データベースから登録された最終的な停止計画情報を取り出し、この最終的な停止計画情報に基づいて当日の停止作業の対象となる作業対象設備担当端末装置の特定情報を外部に出力するとともに、上記作業対象設備担当端末装置から停止作業当日の停止作業実施について諾否の判別結果を受け取ると、この判別結果に基づいて登録された最終的な停止計画の実施について開始の可否を作業担当端末装置に送信して表示させるよう構成し、センターサーバには、当日作業計画手段から受け取った作業対象設備担当端末装置の特定情報に基づいて、当日の停止作業の対象となる作業対象設備担当端末装置に、最終的な停止計画情報に含まれる停止日時情報と停止対象設備情報とを送信し、当該作業対象設備担当端末装置から停止作業を当日作業として承認するか否かの判別結果を受け取ると、その判別結果を当日作業計画管理手段に出力する当日作業承認処理手段を設けたことにより、最新の通信設備情報に基づいて、停止作業の実施を停止作業当日に改めて確認することができ、確実性が増す。   In the work management system for a network according to the fifteenth aspect of the present invention, the work plan is a stop plan including information on the stop date and time and the stop equipment planned in advance, and the work plan management means stores the information in the database before the stop work date. The stop work decided to be implemented for the stop plan is registered as the final stop plan, and the terminal equipment in charge of the work target equipment is registered with the center server on the day of the stop work, a predetermined time before the start of the stop work. When a typical stop plan is received, it is determined whether or not the registered stop work is approved as the current day work, and the determination result is transmitted to the center server, and the current day work plan management means is stopped. On the day of the work, if it is a predetermined time before the start of the stop work, the final stop plan information registered from the database is extracted, and based on this final stop plan information. When the specific information of the work target equipment terminal device that is the target of the stop work of the day is output to the outside, and when the determination result of acceptance / rejection about the stop work execution of the stop work day is received from the work target facility charge terminal device, this The final stop plan registered based on the determination result is configured to be sent to the work terminal device for display of whether or not it can be started. The center server is in charge of the work target equipment received from the work plan means on the day. Based on the specific information of the terminal device, the stop date and time information and the stop target facility information included in the final stop plan information are transmitted to the work target facility charge terminal device that is the target of the stop operation on the current day, and the target work When receiving the determination result of whether or not to approve the stop work as the current day work from the terminal in charge of equipment, the determination result is output to the current day work plan management means By providing the day work approval processing unit, based on the latest communication facility information can be reconfirmed to stop working day implementation of stop work, reliability is increased.

本発明の請求項16に係るネットワークの作業管理システムは、停止作業の対象となる通信設備はインターネットプロトコルを有し、ポート部は上記通信設備のIPポートであって、当該通信設備は、ポートを開閉制御する設備側制御手段と、設備側制御手段により制御され実行された結果をセンターサーバに送信する制御情報送信手段とを備え、センターサーバは、通信により設備側と情報の遣り取りを行うとともに、作業担当端末装置から通信設備のポートを停止または停止解除を要求する指令を受け取ると、当該通信設備またはポートの情報に基づいて設備側制御手段に当該通信設備のポートの停止または停止解除を実行させ、設備側制御手段により制御され実行された結果を制御情報送信手段から受け取ると、受け取った実行結果を作業担当端末装置に送信して表示させる監視制御システムを備えていることを特徴とするものである。   In the network work management system according to the sixteenth aspect of the present invention, the communication equipment to be stopped is provided with an Internet protocol, the port section is an IP port of the communication equipment, and the communication equipment includes a port. The facility side control means for controlling the opening and closing, and the control information transmission means for transmitting the result controlled and executed by the equipment side control means to the center server, the center server exchanges information with the equipment side by communication, When receiving a command to stop or release the port of the communication facility from the terminal device in charge of work, the facility side control means executes the stop or release of the port of the communication facility based on the information on the communication facility or port. When the result controlled and executed by the facility-side control means is received from the control information transmitting means, the received execution result is And it is characterized in that it comprises a monitoring and control system to be displayed and transmitted to the business representative terminal.

本発明の請求項16に係るネットワークの作業管理システムでは、停止作業の対象となる通信設備はインターネットプロトコルを有し、ポート部は上記通信設備のIPポートであって、当該通信設備は、ポートを開閉制御する設備側制御手段と、設備側制御手段により制御され実行された結果をセンターサーバに送信する制御情報送信手段とを備え、センターサーバは、通信により設備側と情報の遣り取りを行うとともに、作業担当端末装置から通信設備のポートを停止または停止解除を要求する指令を受け取ると、当該通信設備またはポートの情報に基づいて設備側制御手段に当該通信設備のポートの停止または停止解除を実行させ、設備側制御手段により制御され実行された結果を制御情報送信手段から受け取ると、受け取った実行結果を作業担当端末装置に送信して表示させる監視制御システムを備えていることにより、オペレータが作業担当端末装置を操作するだけで、作業対象の機器のポートを開閉する制御が行われ、制御の実行結果も確認することができる。   In the network work management system according to the sixteenth aspect of the present invention, the communication equipment to be stopped is provided with an Internet protocol, the port portion is an IP port of the communication equipment, and the communication equipment includes a port. The facility side control means for controlling the opening and closing, and the control information transmission means for transmitting the result controlled and executed by the equipment side control means to the center server, the center server exchanges information with the equipment side by communication, When receiving a command to stop or release the port of the communication facility from the terminal device in charge of work, the facility side control means executes the stop or release of the port of the communication facility based on the information on the communication facility or port. When the result controlled and executed by the facility-side control means is received from the control information transmission means, the received execution result By providing a monitoring control system that transmits to the work terminal device and displays it, the operator can control the opening and closing of the port of the work target device simply by operating the work terminal device. Can also be confirmed.

本発明の請求項17に係るネットワークの作業管理システムは、監視制御システムは、当日作業計画管理手段と当日作業承認処理手段と制御コマンド文法データベースと制御コマンド生成手段とを備えるとともに、制御コマンド生成手段は、外部から入力される指令に基づいて制御コマンド文法データベースにより該当する機器のポートに対する停止または停止解除要求コマンドを生成し、これら停止または停止解除要求コマンドを該当する通信設備に送信するよう構成され、センターサーバは、当日作業計画管理手段が、作業担当端末装置から選択された機器のポートについて停止または停止解除を要求する指令を受け取ると、この指令に基づいて停止または停止解除要求コマンドを生成するよう制御コマンド生成手段に指令し、これら生成された停止または停止解除要求コマンドを制御コマンド生成手段を通じて通信設備の設備側制御手段に送信させ、実行された結果が通信設備の制御情報送信手段から送られてくると、この実行結果を作業担当端末装置に送信して表示させる停止・停止解除制御手段とを備えて構成されることを特徴とするものである。   According to a seventeenth aspect of the present invention, in the network work management system, the supervisory control system comprises a day work plan management means, a day work approval processing means, a control command grammar database, and a control command generation means, and a control command generation means. Is configured to generate a stop or stop release request command for the port of the corresponding device from the control command grammar database based on a command input from the outside, and send the stop or stop release request command to the corresponding communication facility. The center server generates a stop or stop release request command based on this command when the work plan management means on the day receives a command to request stop or stop release for the port of the device selected from the work terminal device Control command generation means When the execution result is sent from the control information transmission means of the communication equipment, the stop or release request command is sent to the equipment control means of the communication equipment through the control command generation means. It is characterized by comprising stop / stop cancellation control means for transmitting and displaying to the terminal device.

本発明の請求項17に係るネットワークの作業管理システムでは、監視制御システムは、当日作業計画管理手段と当日作業承認処理手段と制御コマンド文法データベースと制御コマンド生成手段とを備えるとともに、制御コマンド生成手段は、外部から入力される指令に基づいて制御コマンド文法データベースにより該当する機器のポートに対する停止または停止解除要求コマンドを生成し、これら停止または停止解除要求コマンドを該当する通信設備に送信するよう構成され、センターサーバは、当日作業計画管理手段が、作業担当端末装置から選択された機器のポートについて停止または停止解除を要求する指令を受け取ると、この指令に基づいて停止または停止解除要求コマンドを生成するよう制御コマンド生成手段に指令し、これら生成された停止または停止解除要求コマンドを制御コマンド生成手段を通じて通信設備の設備側制御手段に送信させ、実行された結果が通信設備の制御情報送信手段から送られてくると、この実行結果を作業担当端末装置に送信して表示させる停止・停止解除制御手段とを備えて構成されるようにしたことにより、オペレータは作業担当端末装置を通じて、選択された機器のポートについて停止または停止解除の制御を実行し、実行されたかどうかの確認をすることができる。このため、作業を確実かつ迅速に行うことができ、作業ミスの発生を防止することができる。   In the network work management system according to the seventeenth aspect of the present invention, the monitoring control system includes a current day work plan management means, a current day work approval processing means, a control command grammar database, and a control command generation means, and a control command generation means. Is configured to generate a stop or stop release request command for the port of the corresponding device from the control command grammar database based on a command input from the outside, and send the stop or stop release request command to the corresponding communication facility. The center server generates a stop or stop release request command based on this command when the work plan management means on the day receives a command to request stop or stop release for the port of the device selected from the work terminal device Command the control command generation means The generated stop or stop release request command is transmitted to the equipment side control means of the communication equipment through the control command generation means, and when the execution result is sent from the control information transmission means of the communication equipment, the execution result is processed. By including a stop / stop release control means for transmitting to the responsible terminal device and displaying it, the operator can control the stop or release of the selected device port through the work responsible terminal device. You can execute it and check if it has been executed. For this reason, work can be performed reliably and quickly, and occurrence of work mistakes can be prevented.

本発明の請求項18に係るネットワークの作業管理方法は、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するネットワークの作業管理方法であって、通信設備をセンターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させることを特徴とするものである。   The network work management method according to claim 18 of the present invention is capable of exchanging work information through communication with the center server for managing and operating the lines of the entire network based on communication facility information stored in a database. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. A work management method for a network to be released, wherein the communication facility is communicated with the center server through communication with the center server. When the work server is informed of the stop work plan set from the work terminal device, the center server sends the information to the communication equipment of the work target. When the information about the operation status of the communication equipment is obtained from the work target equipment and sent to the center server, the information is stored in the database, and the center server is stored in the database. On the basis of the information on the operating state of the communication facility, it is determined whether or not the network system has been stopped, and the system stop determination result is transmitted to and displayed on the work terminal unit.

本発明の請求項18に係るネットワークの作業管理方法では、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するネットワークの作業管理方法であって、通信設備をセンターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させるようにしたことにより、作業開始前に、最新の通信設備の状態に基づいてシステム停止の可能性の有無を把握することができるので、停止作業によりネットワークにシステム停止が発生するのを回避することができる。   In the network work management method according to claim 18 of the present invention, a center server that manages and operates the lines of the entire network based on information of communication facilities stored in a database, and work information can be exchanged through communication with the center server. And a terminal device for managing the network line of each maintenance area, and a work plan including information on the work date and time and the work equipment planned in advance by the work terminal terminal in charge of the stop work is stored in the center server. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. A work management method for a network to be released, wherein the communication equipment is communicated with the center server through communication. When the operation status is sent to the center server from the terminal device in charge of work, the center server sends the work start notification to the communication equipment of the work target. When the information on the operation status of the communication equipment is obtained from the work target equipment and sent to the center server, the information is stored in the database, and the center server is stored in the database. Based on the information on the operation status of the communication equipment, it is determined whether or not the network system is stopped, and the system stop determination result is transmitted and displayed on the terminal unit in charge of the work. Based on the state of the latest communication equipment, it is possible to know whether there is a possibility of system shutdown. System stop can be prevented from occurring Ttowaku.

本発明の請求項19に係るネットワークの作業管理方法は、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定することを特徴とするものである。   In the network work management method according to claim 19 of the present invention, when the center server receives a request for an inquiry about the state of the equipment related to the work target communication equipment from the work terminal device, the center server sets the equipment for the work target communication equipment. The response to the status of the equipment received from the work target communication equipment is sent to the work terminal device that requested the inquiry and displayed, and the information about the equipment and the status of the equipment Answers are stored in the database, and when there is a request for inquiry about the line status of the communication equipment to be worked from the terminal device in charge of work, the work target communication equipment is asked to answer the line status and the work target An answer about the status of the line received from the communication equipment is sent to the terminal in charge of the work that requested the inquiry and displayed. Line information and line status answers are stored in a database, and whether there is a system outage is determined based on at least one of equipment status information and line status information stored in the database. It is characterized by.

本発明の請求項19に係るネットワークの作業管理方法では、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定するようにしたことにより、システム停止の判定を設備の状態と回線の状態とのうち少なくともいずれか1に基づいて行うので、判定の精度が向上する。また、システム停止の可能性がある場合、作業担当端末装置側で設備の状態や回線の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性を監視し、健全性を確認した上で、作業を行うことができる。   In the network work management method according to the nineteenth aspect of the present invention, when the center server receives a request for inquiry about the state of the equipment related to the work target communication equipment from the work terminal device, the center server sets the equipment for the work target communication equipment. The response to the status of the equipment received from the work target communication equipment is sent to the work terminal device that requested the inquiry and displayed, and the information about the equipment and the status of the equipment Answers are stored in the database, and when there is a request for inquiry about the line status of the communication equipment to be worked from the terminal device in charge of work, the work target communication equipment is asked to answer the line status and the work target An answer to the status of the line received from the communication equipment is sent to the terminal in charge of the work requesting the inquiry and displayed. The line information and the answer about the line state are stored in a database, and whether or not the system is stopped is determined based on at least one of the facility state information and the line state information stored in the database. By doing so, the determination of the system stop is made based on at least one of the facility state and the line state, so that the determination accuracy is improved. In addition, if there is a possibility of system shutdown, it is possible to grasp the state of equipment and the line state on the work terminal side, and to grasp the health of the network. The operator monitors the health of the network, Work can be done after confirming soundness.

本発明の請求項20に係るネットワークの作業管理方法は、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の設定状態について照会の要求があると、当該作業対象通信設備に対して設備の設定状態を回答するよう求め、当該作業対象通信設備から受け取った設備の設定状態についての回答を照会要求のあった作業担当端末装置に送信して表示させ、作業担当端末装置から作業対象の通信設備に関し作業対象設備を経由する経路について照会の要求があると、作業担当端末装置から提供された始端設備情報と終端設備情報とに基づいて、当該作業対象通信設備に対して経路の状態を回答するよう求め、当該作業対象通信設備から受け取った経路の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させることを特徴とするものである。   In the network work management method according to claim 20 of the present invention, when the center server receives a request for inquiry about the set state of the equipment related to the work target communication equipment from the work terminal device, It asks to answer the setting status of the equipment, sends the answer about the setting status of the equipment received from the work target communication equipment to the work terminal device that requested the inquiry and displays it. When there is a request for inquiring about a route that passes through the work target facility with respect to the communication facility, the state of the route for the work target communication facility is determined based on the start facility information and the end facility information provided from the work terminal device. Send a response to the work terminal device that requested the inquiry and display the answer about the status of the route received from the work target communication equipment. It is characterized in that to.

本発明の請求項20に係るネットワークの作業管理方法では、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の設定状態について照会の要求があると、当該作業対象通信設備に対して設備の設定状態を回答するよう求め、当該作業対象通信設備から受け取った設備の設定状態についての回答を照会要求のあった作業担当端末装置に送信して表示させ、作業担当端末装置から作業対象の通信設備に関し作業対象設備を経由する経路について照会の要求があると、作業担当端末装置から提供された始端設備情報と終端設備情報とに基づいて、当該作業対象通信設備に対して経路の状態を回答するよう求め、当該作業対象通信設備から受け取った経路の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるようにしたことにより、システム停止の可能性がある場合、作業担当端末装置側で設備の設定状態や経路の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性をより細かく監視することができる。   In the network work management method according to claim 20 of the present invention, when the center server receives a request for inquiry about the set state of the equipment related to the work target communication facility from the work terminal device, the center server requests the work target communication facility. It asks to answer the setting status of the equipment, sends the answer about the setting status of the equipment received from the work target communication equipment to the work terminal device that requested the inquiry and displays it. When there is a request for inquiring about a route that passes through the work target facility with respect to the communication facility, the state of the route for the work target communication facility is determined based on the start facility information and the end facility information provided from the work terminal device. Send a reply about the status of the route received from the work target communication equipment to the work terminal that requested the inquiry. If there is a possibility that the system will stop due to the fact that it has been shown, the operator terminal side can grasp the setting status of the equipment and the state of the route to understand the soundness of the network. Can be monitored more closely.

本発明の請求項1に係るネットワークの作業管理システムでは、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、通信設備を、センターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させるようにしたので、作業開始前に、最新の通信設備の状態に基づいてシステム停止の可能性の有無を把握することができ、予め停止作業によるネットワークのシステム停止発生を回避することができる。   In the network work management system according to claim 1 of the present invention, a center server that manages and operates the lines of the entire network based on communication facility information stored in the database, and work information can be exchanged through communication with the center server. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. The communication facility is configured to be released, and the communication facility is operated through communication with the center server. When the work start notification is sent to the center server from the work terminal device, the center server sends the information to the communication equipment of the work target. When information on the operational status of the communication equipment is obtained and information about the operational status of the communication equipment is sent from the work target equipment to the center server, the information is stored in the database, and the center server stores the communication stored in the database. Based on the information on the operational status of the equipment, it is determined whether or not the network system has been stopped, and the system stop determination result is transmitted to the terminal device in charge for display. Based on the state of the equipment, it is possible to ascertain whether there is a possibility of system stoppage. It is possible to avoid the Temu stop occurrence.

本発明の請求項9に係るネットワークの作業管理システムでは、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、通信設備は、インターネットプロトコルを有し、センターサーバからの指令に基づいて、通信設備の状態の情報をセンターサーバに送信する通信設備状態情報送信手段を備え、データベースは、センターサーバにより設定され作業日時と作業設備の情報を含む停止作業計画の情報を格納して構成される作業計画データベースと、作業対象の通信設備から通信設備の設備運用状態の情報が送られてくると、その設備運用状態の情報を格納して構成される設備運用状態管理データベースと、作業対象の通信設備から通信設備の回線状態の情報が送られてくると、その回線状態の情報を格納して構成される回線状態管理データベースとを備え、センターサーバは、停止作業の当日、作業担当端末装置から当該停止作業開始の所定時間前に作業開始の通知を受け取ると、作業計画データベースから設定された停止計画情報を取り出し、作業開始情報とこの停止計画情報を外部に出力する当日作業計画管理手段と、当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し設備運用状況の確認を要求し、当該作業対象設備から設備運用状況の回答を得ると、設備運用状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる設備運用状態管理手段と、当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し回線状況の確認を要求し、当該作業対象設備から回線状況の回答を得ると、回線状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる回線状態管理手段と、当日作業計画管理手段から作業開始情報を受け取ると、設備運用状態管理データベースと回線状態管理データベースとから設備運用状態の情報と回線運用状態の情報とを求め、これら設備運用状態の情報と回線運用状態の情報とを外部に出力するシステム停止管理手段と、システム停止管理手段から設備運用状態の情報と回線運用状態の情報とのうち少なくともいずれか一方を受け取ると、当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるシステム停止判定手段とを備え、当日作業計画管理手段は、作業担当端末装置から作業開始の通知を受け取ると、設備運用状態管理手段と回線状態管理手段とにより当該作業対象の設備から設備運用状態の情報と回線運用状態の情報とを設備運用状態管理データベースと回線状態管理データベースとにそれぞれ格納させ、システム停止管理手段がシステム停止判定手段にこれら格納された設備運用状態の情報と回線運用状態の情報とを送出すると、システム停止判定手段が当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるとともに、当日作業計画管理手段は、作業担当端末装置からの求めに応じて設備運用状態管理手段を通じて設備運用状態の情報を、回線状態管理手段を通じて回線運用状態の情報をそれぞれ作業担当端末装置に送信して表示させるようにしたので、作業開始前に、最新の通信設備の状態に基づいてシステム停止の可能性の有無を把握することができるので、停止作業によるネットワークのシステム停止発生を回避することができる。また、システム停止の可能性がある場合、作業担当端末装置側で設備の状態や回線の状態を把握して、ネットワークの健全性を把握することができ、オペレータはネットワークの健全性を確認した上で、実際の停止作業を行うことができる。このため、システム停止の判定結果が示されても、作業担当端末装置側のオペレータの判断で停止作業を行うことができ、作業が効率化される。   In the work management system for a network according to claim 9 of the present invention, a center server that manages and operates the lines of the entire network based on communication facility information stored in a database, and work information can be exchanged through communication with the center server. A work plan including information on the work date and time and work equipment planned in advance by the work charge terminal device in charge of the stop work. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. And the communication facility has an Internet protocol and is Communication facility state information transmitting means for transmitting information on the state of communication facilities to the center server based on the command from the information, the database is set by the center server, and information on the stop work plan including work date and time and work facility information Operation plan database configured to store information on the equipment operation status of the communication equipment from the work target communication equipment, and equipment operation status management configured to store the information on the equipment operation status When the communication equipment line status information is sent from the communication equipment to be worked on, the center server includes a line status management database configured to store the information on the line status. On the day, when a work start notification is received from the work terminal device a predetermined time before the stop work start, the stop set from the work plan database The work plan management means for outputting the work start information and the stop plan information to the outside, and when the stop plan information is received from the work plan management means for the day, the work target is based on the information of the work target equipment. When the facility is requested to confirm the facility operation status, and the response of the facility operation status is obtained from the work target facility, the information is stored in the facility operation state management database and transmitted to the work terminal device for display. When the stop plan information is received from the state management means and the work plan management means on the day, the work target equipment is requested to confirm the line status based on the information on the work target equipment, and the line status is answered from the work target equipment. Is stored in the line state management database and transmitted to the work terminal unit for display, and When the work start information is received from the daily work plan management means, the equipment operation state information and the line operation state information are obtained from the equipment operation state management database and the line state management database, and the equipment operation state information and the line operation state are obtained. System outage management means for outputting the information on the outside, and when at least one of the equipment operation state information and the line operation state information is received from the system outage management means, System stop determination means for determining whether or not there is, and transmitting and displaying the result of the system stop determination to the work terminal device, and the work plan management means for the day notifies the work start from the work terminal device Is received from the target equipment by the equipment operation state management means and the line state management means. Information and line operation state information are stored in the facility operation state management database and the line state management database, respectively, and the system stop management means stores the equipment operation state information and line operation state information stored in the system stop determination means. The system stop determination means determines whether there is a system stop of the network due to the stop work, and transmits and displays the result of the system stop determination to the terminal terminal in charge of work, and the work plan for the day. The management means transmits the equipment operation state information through the equipment operation state management means and the line operation state information through the line state management means to the work terminal device in response to a request from the work terminal device. Therefore, before starting work, whether there is a possibility of system shutdown based on the latest communication equipment status It is possible to grasp, it is possible to avoid the system stops the generation of the network by stopping the work. Also, if there is a possibility of system stoppage, the terminal in charge of work can grasp the state of equipment and the state of the line to grasp the soundness of the network, and the operator confirms the soundness of the network. Thus, the actual stop operation can be performed. For this reason, even if the determination result of the system stop is shown, the stop work can be performed based on the judgment of the operator on the work terminal side, and the work is made more efficient.

本発明の請求項18に係るネットワークの作業管理方法では、データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するネットワークの作業管理方法であって、通信設備をセンターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させるようにしたので、作業開始前に、最新の通信設備の状態に基づいてシステム停止の可能性の有無を把握することができるので、停止作業によるネットワークのシステム停止発生を回避することができる。   In the network work management method according to claim 18 of the present invention, a center server that manages and operates the lines of the entire network based on information of communication facilities stored in a database, and work information can be exchanged through communication with the center server. And a terminal device for managing the network line of each maintenance area, and a work plan including information on the work date and time and the work equipment planned in advance by the work terminal terminal in charge of the stop work is stored in the center server. When sent, the center server sets the stop information for the work target communication equipment before starting the stop work, and after the actual work is finished, when the work end notification is sent from the work terminal device to the center server, the stop information is set. A work management method for a network to be released, wherein the communication equipment is communicated with the center server through communication. When the operation status is sent to the center server from the terminal device in charge of work, the center server sends the work start notification to the communication equipment of the work target. When the information on the operation status of the communication equipment is obtained from the work target equipment and sent to the center server, the information is stored in the database, and the center server is stored in the database. Based on the information on the operation status of the communication equipment, the presence / absence of the system stoppage of the network is determined, and the result of the system stoppage determination is transmitted to the terminal device in charge for display. Based on the state of the communication equipment, it is possible to know whether there is a possibility of system shutdown. It is possible to avoid the system stops the generation of over click.

図1は本発明の第1の実施例に係るネットワークの作業管理システムを示すシステム構成図である。(実施例1)FIG. 1 is a system configuration diagram showing a network work management system according to a first embodiment of the present invention. Example 1 図2は図1のネットワークの作業管理システムの概念説明図である。FIG. 2 is a conceptual explanatory diagram of the work management system for the network shown in FIG. 図3は図1のネットワークの作業管理システムによる管理方法を時系列に従って説明した説明図であり、図中、IないしIVはそれぞれ、作業当日前工程、作業当日の作業開始前工程、作業当日の回線状態確認および閉塞作業工程および作業当日の実作業中から実作業終了工程を示す。FIG. 3 is an explanatory diagram illustrating the management method by the work management system of the network in FIG. 1 according to time series. In FIG. 3, I to IV respectively indicate the process before the work day, the work start process on the work day, and the work day. The line status confirmation and blocking work process and the actual work end process from the actual work on the day of work are shown. 図4は図1のネットワークの作業管理システムにおける作業対象となる停止予定設備の回線に関連する機器または機器のポート部の候補を抽出する例を示す説明図である。FIG. 4 is an explanatory diagram showing an example of extracting a candidate of a device or a port portion of a device related to a line of a planned shutdown facility that is a work target in the work management system of the network of FIG. 図5は図4の一例における事業所と回線と回線に関連する機器ならびにポート部の構成を示す説明図である。FIG. 5 is an explanatory diagram showing the configuration of the office, the line, the equipment related to the line, and the port unit in the example of FIG. 図6は図4の一例における事業所と回線と回線に関連する機器ならびにポート部の構成を示す説明図である。FIG. 6 is an explanatory diagram showing the configuration of the office, the line, the equipment related to the line and the port part in the example of FIG. 図7は停止作業当日前までに最終的な停止計画を登録する手順を示すフローチャートである。FIG. 7 is a flowchart showing a procedure for registering a final stop plan before the stop work day. 図8は閉塞候補を抽出する手順を示すフローチャートである。FIG. 8 is a flowchart showing a procedure for extracting occlusion candidates. 図9は作業対象設備担当端末装置を特定し作業実施の諾否を求める手順を示すフローチャートである。FIG. 9 is a flowchart showing a procedure for specifying a work target facility terminal device and obtaining approval or disapproval of work execution. 図10は本発明の第2の実施例に係るネットワークの作業管理システムのシステム構成図である。(実施例2)FIG. 10 is a system configuration diagram of a network work management system according to the second embodiment of the present invention. (Example 2) 図11は図10のネットワークの作業管理システムの要部の概念説明図である。FIG. 11 is a conceptual explanatory diagram of a main part of the network work management system of FIG. 図12は図10のネットワークの作業管理システムによる管理方法を時系列に従って説明した説明図であり、図中、IIないしIVはそれぞれ、作業当日の作業開始前工程、作業当日の通信設備運用状態確認並びに閉塞作業工程および作業当日の実作業中から実作業終了工程を示す。FIG. 12 is an explanatory diagram illustrating the management method by the work management system of the network in FIG. 10 in time series. In FIG. In addition, the closing work process and the actual work end process from the actual work on the day of work are shown. 図13は従来の、紙資料の中から人力による手作業で選び出して作成した作業計画を、監視制御システムに登録する例を示す概念説明図である。FIG. 13 is a conceptual explanatory diagram showing an example of registering a conventional work plan selected and created manually from paper materials in a supervisory control system.

実作業開始前にシステム停止判定を行い、停止ありの場合、システム停止の内容を通信設備の状態に基づいて把握し停止作業の効率化を図るという目的を、通信設備をセンターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させるとともに、センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定するようにしたことにより実現した。   Communication stoppage is communicated with the center server for the purpose of grasping the contents of the system stop based on the state of the communication equipment and improving the efficiency of the stop work. When the operation status of the equipment is connected and exchanged, the center server receives the work start notification for the stop work plan set from the work terminal device, and the center server communicates with the work target. When the information on the operational status of the communication equipment is obtained from the equipment, and the information on the operational status of the communication equipment is sent from the work target equipment to the center server, the information is stored in the database. Based on the stored information on the operational status of the communication equipment, it is determined whether or not the network system has been stopped. The determination result is transmitted to the work terminal device and displayed, and when the center server receives a request for inquiry about the state of the equipment from the work terminal device, the center server We ask you to answer the status of the equipment, send the answer about the status of the equipment received from the work target communication equipment to the work terminal device that requested the inquiry, and display the information about the equipment and the status of the equipment. Is stored in the database, and if there is a request for inquiry about the line status regarding the communication equipment to be worked from the terminal device in charge of work, the work-related communication equipment is requested to answer the line status and the work An answer about the line status received from the target communication equipment is sent to the terminal in charge of the work requesting the inquiry and displayed. The information on the line and the answer about the line status are stored in a database, and whether or not the system is stopped is determined based on at least one of the facility status information and the line status information stored in the database. Realized by doing so.

以下、図面に示す実施例により本発明を説明する。図1は本発明の第1の実施例に係るネットワークの作業管理システムのシステム構成図であり、図2は該システムの概念説明図である。本実施例に係るネットワークの作業管理システムは、図1に示すように、エントリー端末10Aと表示端末10Bとが一体に構成され、予め決められた保守担当域の通信設備12を管理する箇所端末(パーソナルコンピュータ、移動端末も含む。以下、端末装置と称す。)10と、これら端末装置10と通信回線(IP網、専用線網、公衆電話網等を含む)を通じて接続され、情報の遣り取りを行うとともに、通信設備12と通信回線を通じて接続され、通信設備12を制御するとともに、通信設備12の回線状態を問い合わせ可能なセンターサーバ11とを備えて構成される。本実施例でいうネットワークは、通信ネットワークをいう。   Hereinafter, the present invention will be described with reference to embodiments shown in the drawings. FIG. 1 is a system configuration diagram of a network work management system according to a first embodiment of the present invention, and FIG. 2 is a conceptual explanatory diagram of the system. As shown in FIG. 1, in the network work management system according to the present embodiment, an entry terminal 10A and a display terminal 10B are integrally configured, and a location terminal (managing communication facilities 12 in a predetermined maintenance area) ( Including personal computers and mobile terminals (hereinafter referred to as terminal devices) 10 and these terminal devices 10 are connected to each other through communication lines (including IP networks, private line networks, public telephone networks, etc.) to exchange information. At the same time, it is configured to include a center server 11 that is connected to the communication facility 12 through a communication line, controls the communication facility 12, and inquires about the line state of the communication facility 12. The network in this embodiment refers to a communication network.

センターサーバ11は、監視制御システムとしての役割を果たすようになっている。すなわち、センターサーバ11を通じて、通信ネットワークの運用および保守管理と監視とを行うようになっている。通信設備、すなわち、作業対象は、回線(多重回線を含む。)および機器(光ケーブル、メタルケーブル、メカニカルクロージャ(光接続箱)、伝送装置等)を含む。本実施例では、通信設備12は、インターネットプロトコル機器(例えば、ルータ、スイッチ、伝送装置等のIP機器。以下、機器と称す。)またはIP機器のポート部(ポート)であって、センターサーバ11から送信される制御コマンドにより閉塞制御(停止制御)されたり、閉塞解除制御(停止解除制御)されたりする機器またはその機器の一部(ポート)である。また、通信設備12は、センターサーバ11から制御コマンドが送られてくると、制御コマンドの投入結果をセンターサーバ11に送信するようになっている。さらに、通信設備12は、センターサーバ11から回線状態の情報を要求する問い合わせのコマンドが送られてくると、回線状態の情報をセンターサーバ11に送信するようになっている。   The center server 11 plays a role as a monitoring control system. That is, operation, maintenance, and monitoring of the communication network are performed through the center server 11. Communication facilities, that is, work objects include lines (including multiple lines) and equipment (optical cables, metal cables, mechanical closures (optical connection boxes), transmission devices, etc.). In this embodiment, the communication facility 12 is an Internet protocol device (for example, an IP device such as a router, a switch, a transmission device, etc .; hereinafter referred to as a device) or a port part (port) of the IP device, and the center server 11. Is a device or a part (port) of the device that is subjected to block control (stop control) or block release control (stop release control) by a control command transmitted from. In addition, when a control command is sent from the center server 11, the communication facility 12 transmits a control command input result to the center server 11. Further, when an inquiry command requesting line state information is sent from the center server 11, the communication facility 12 transmits the line state information to the center server 11.

端末装置10は、保守担当者が所定の保守担当域における多数の通信設備12を管理するため設置される。端末装置10には、それぞれの保守担当域におけるネットワーク回線の情報および通信設備の情報が更新可能に格納されている。この端末装置10に、作業担当者が自らの保守担当域に属する通信設備や他の保守担当域に属する通信設備に関して停止作業の予定計画情報(停止予定日時情報Idtと停止予定通信設備情報Imcを含む作業計画情報)PLを立案して入力すると、その予定停止計画情報PLは端末装置10を通じてセンターサーバ11に送信されるようになっている。以下、このように保守担当域に関係なく、停止作業計画情報PLに基づいて停止作業が予定された作業対象の通信設備12をセンターサーバ11を通じて制御する端末装置10を、作業担当端末装置(自支社の箇所端末)10Xという。また、作業担当端末装置10Xを除く端末装置であって、予定停止計画情報PLに記載され停止作業が予定されている通信設備12を自らの保守担当域に有しこの作業対象通信設備12を管理する端末装置10を作業対象設備担当端末装置(他支社の箇所端末)10Yという。これら作業担当端末装置10Xと作業対象設備担当端末装置10Yはそれぞれ固定されたものではなく、予定停止計画情報PLが入力される端末装置10が作業担当端末装置10Xとされ、作業担当端末装置10Xの保守担当域と異なる保守担当域の端末装置10であって、この保守担当域に含まれる作業対象通信設備12を管理する端末装置10が作業対象設備担当端末装置10Yとされるようになっている。   The terminal device 10 is installed so that a maintenance person manages a large number of communication facilities 12 in a predetermined maintenance area. The terminal device 10 stores information on network lines and information on communication facilities in each maintenance area in an updatable manner. In this terminal device 10, the scheduled work information (scheduled stop date / time information Idt and scheduled stop communication facility information Imc) of the stop work regarding the communication equipment belonging to the maintenance charge area or the communication equipment belonging to another maintenance charge area is stored in the terminal device 10. Including the planned work plan information PL), the scheduled stop plan information PL is transmitted to the center server 11 through the terminal device 10. Hereinafter, regardless of the maintenance area, the terminal device 10 that controls the communication facility 12 that is the work to be stopped based on the stop work plan information PL through the center server 11 is referred to as the work terminal apparatus (self Branch office terminal) 10X. Moreover, it is a terminal device other than the work-in-charge terminal device 10X, and has the communication equipment 12 described in the scheduled stop plan information PL and scheduled for stop work in its own maintenance charge area, and manages this work target communication equipment 12 The terminal device 10 to be operated is referred to as a work target facility terminal device (location terminal of another branch office) 10Y. These work charge terminal device 10X and work target facility charge terminal device 10Y are not fixed, and the terminal device 10 to which the scheduled stop plan information PL is input is set as the work charge terminal device 10X. The terminal device 10 in the maintenance charge area different from the maintenance charge area, and the terminal device 10 that manages the work target communication equipment 12 included in the maintenance charge area is set as the work target facility charge terminal apparatus 10Y. .

各保守担当域の通信設備12を管理する端末装置10には、所管するエリアにおける通信設備のデータが更新自在に格納され、常に最新のデータをセンターサーバ11とリアルタイムで共有するようになっている。作業担当端末装置10Xは、図2に示すように、ある保守担当域における計画された予定停止の情報、すなわち、停止日時の情報Idtおよび停止設備の情報Imcを予定された変更の可能性のある停止計画情報PLとして作業開始前にセンターサーバ11に送信して入力するようになっている。センターサーバ11は作業計画管理部(作業計画管理手段)21を備え、この作業計画管理部21は、作業担当端末装置10Xから通信制御部20を通じて入力された予定停止計画情報PLに基づいて、その予定停止計画情報PLについて所定の時間で締め切り処理を行い、その作業計画を決定する処理を行うようになっている。   In the terminal device 10 that manages the communication equipment 12 in each maintenance area, the data of the communication equipment in the area in charge is stored in an updatable manner, and the latest data is always shared with the center server 11 in real time. . As shown in FIG. 2, the work-in-charge terminal device 10 </ b> X has a possibility of scheduled changes in planned scheduled stop information, that is, stop date / time information Idt and stop facility information Imc in a certain maintenance charge area. The stop plan information PL is transmitted to the center server 11 and input before the work starts. The center server 11 includes a work plan management unit (work plan management means) 21, which is based on the scheduled stop plan information PL input from the work terminal device 10 </ b> X through the communication control unit 20. The scheduled stop plan information PL is subjected to a deadline process at a predetermined time, and a process for determining the work plan is performed.

センターサーバ11は、運用管理系システム部11Aと監視制御系システム部11Bとを備えて構成される。運用管理系システム部11Aには、データベースとして構成管理データベース22と作業計画データベース23とが備えられる。構成管理データベース22には、ネットワークの回線情報および通信設備情報とともに、物理回線構成情報、設備構成情報(装置構成情報)および論理回線構成情報が格納されるようになっている。物理回線構成情報は、網構成および局内構成を含み、設備構成情報は、機器および機器内の部位(ポート)情報を含み、論理回線構成情報は、論理回線名および論理回線構成を含む。作業計画データベース23には、ネットワークの回線情報および通信設備情報が格納されるとともに、作業計画管理部21により停止のエントリーが決定された最終的な登録済み停止計画情報PLf、すなわち、停止日時の情報Idt、停止設備の情報Imcが、当該停止設備の閉塞対象機器または閉塞対象ポート部の情報として格納され、実作業終了後、作業担当端末装置10Xから作業計画管理部21を通じて作業終了の情報が送られてくると、停止の設定が解除され、実作業の結果が登録されるようになっている。   The center server 11 includes an operation management system unit 11A and a monitoring control system unit 11B. The operation management system unit 11A includes a configuration management database 22 and a work plan database 23 as databases. The configuration management database 22 stores physical line configuration information, facility configuration information (device configuration information), and logical line configuration information along with network line information and communication facility information. The physical line configuration information includes the network configuration and the intra-station configuration, the facility configuration information includes equipment and part (port) information in the equipment, and the logical line configuration information includes a logical line name and a logical line configuration. The work plan database 23 stores network line information and communication equipment information, and finally registered stop plan information PLf for which a stop entry has been determined by the work plan management unit 21, that is, stop date and time information. Idt and stop facility information Imc are stored as information on the shutdown target device or shutdown target port of the stop facility, and after completion of the actual work, work end information is sent from the work terminal device 10X through the work plan management unit 21. Then, the stop setting is canceled and the result of actual work is registered.

センターサーバ11の運用管理系システム部11Aは、作業計画管理部21と、データベース22、23と、物理網・論理網・局内構成図描画部(物理網・論理網・局内構成図描画処理手段)24と、停止予定設備の回線に関連する閉塞対象機器候補または閉塞対象ポート候補を抽出する閉塞対象候補抽出部(作業対象候補抽出手段)25と、作業担当端末装置10Xから送信される選択された閉塞対象機器・閉塞対象ポート情報(または閉塞解除対象機器・閉塞解除対象ポート情報)に基づいて、対象となる機器を決定して対象機器の決定情報を外部に出力する作業対象設備決定部(作業対象設備担当端末装置抽出手段)26と、作業対象設備決定部26から出力された対象機器の決定情報を受け取り、決定された作業対象となる機器の情報に基づいて、この作業対象の機器を自らの保守担当域に有し、この作業対象の機器を管理する端末装置10Y1・・・10Yn(nは任意の整数)を抽出する作業対象設備担当端末装置抽出部(作業対象設備担当端末装置抽出手段)27と、作業対象設備担当端末装置抽出部27により抽出された作業対象設備担当端末装置10Y1〜10Ynに対し停止のエントリーが決定された最終的な登録済み停止計画情報PLfに基づいて停止作業実施の承認要求を行うとともに、当該作業対象設備担当端末装置10Y1〜10Ynから承認の諾否情報が送られてくると、この諾否情報を作業計画管理部21に送出する承認処理部(承認処理手段)28とを備えて構成される。   The operation management system unit 11A of the center server 11 includes a work plan management unit 21, databases 22, 23, and a physical network / logical network / internal station configuration diagram drawing unit (physical network / logical network / internal station configuration diagram drawing processing means). 24, a block target candidate extraction unit (work target candidate extraction means) 25 for extracting a block target device candidate or a block target port candidate related to the line of the facility scheduled to be stopped, and the work terminal device 10X selected. Based on the target device / blocking target port information (or target device / blocking target port information), the target device determining unit (work) determines the target device and outputs the target device determination information to the outside. The target equipment responsible terminal device extraction means) 26 and the target equipment determination information output from the work target equipment determination unit 26 are received, and the information of the equipment to be determined as the work target is received. , 10Yn (n is an arbitrary integer) that has this work target device in its own maintenance charge area and manages this work target device. Final registration in which an entry for stop is determined for the extraction unit (work target facility responsible terminal device extracting means) 27 and the work target facility responsible terminal devices 10Y1 to 10Yn extracted by the work target facility responsible terminal device extraction unit 27 When an approval request for stop work is issued based on the completed stop plan information PLf and approval approval / disapproval information is sent from the work target facility terminal devices 10Y1 to 10Yn, the approval / disapproval information is sent to the work plan management unit 21. And an approval processing unit (approval processing means) 28 to be sent out.

作業計画管理部21は、作業担当端末装置10Xから作業対象通信設備12について予定停止計画情報PLが入力されると、この予定停止計画情報PLの停止予定設備の情報Imcを物理網・論理網・局内構成図描画部24に出力するようになっている。また、作業計画管理部21は、停止作業予定日より前に、承認処理部28から作業対象設備担当端末装置10Y1〜10Ynから停止作業承認の諾否情報(諾否の判別結果)を受け取ると、この諾否情報に基づいて予定された停止作業実施の可否を決定するとともに、停止作業実施の可否の決定を作業担当端末装置10Xに送信して表示させるようになっている。作業計画管理部21は、この諾否情報に基づいて予定された停止作業実施を可とする決定を行うと、作業計画データベース23に停止計画に対し実施が決定された停止作業を最終的な停止計画情報PLfとして登録するとともに、この最終的な停止計画情報PLfを作業計画データベース23から後述する当日作業計画管理部30に送出するようになっている。この最終的な停止計画情報PLfには、停止日時の情報と作業対象通信設備の情報とが、すなわち、停止日時の情報Idtと閉塞対象(停止対象)の機器の情報Imc−Cdfまたはポート部の情報p00n−Cdfとの各情報Cdfが含まれる。作業計画管理部21は、実作業終了後に、作業担当端末装置10Xから作業終了の通知がセンターサーバ11に送信されると停止情報PLfの設定を解除するようになっている。   When the planned stop plan information PL for the work target communication equipment 12 is input from the work terminal device 10X, the work plan management unit 21 obtains the information Imc of the planned stoppage plan information PL of the planned stop plan information PL from the physical network, the logical network, The data is output to the intra-station configuration diagram drawing unit 24. Also, when the work plan management unit 21 receives approval / disapproval information (approval result of approval / disapproval) of the stop work approval from the work processing facility terminal terminals 10Y1 to 10Yn from the approval processing unit 28 before the scheduled stop work date, this approval / disapproval Based on the information, whether or not scheduled stop work can be performed is determined, and the determination of whether or not stop work can be performed is transmitted to the work terminal device 10X for display. When the work plan management unit 21 determines that the scheduled stop work can be performed based on the approval / disapproval information, the work plan management unit 21 determines the stop work that has been determined to be executed for the stop plan in the work plan database 23 as the final stop plan. The information is registered as information PLf, and the final stop plan information PLf is sent from the work plan database 23 to the work plan management unit 30 to be described later. The final stop plan information PLf includes stop date and time information and work target communication equipment information, that is, stop date information Idt and block target (stop target) device information Imc-Cdf or port portion information. Each information Cdf including information p00n-Cdf is included. The work plan management unit 21 is configured to cancel the setting of the stop information PLf when a work end notification is transmitted from the work terminal device 10X to the center server 11 after the actual work is finished.

物理網・論理網・局内構成図描画部24は、物理網構成図、論理網構成図および局内構成図を描画処理することができ、これらを通信制御部20を介して作業担当端末装置10Xに送信して表示させるようになっている。物理網・論理網・局内構成図描画部24は、作業計画部21または閉塞対象候補抽出部25から、入力された設備情報に基づいて構成管理データベース22から物理回線構成情報Phと装置構成情報Apと論理回線構成情報Lgとを抽出して描画処理し、これら描画処理された構成図上に入力された設備情報を反映させて作業担当端末装置10Xに表示させるようになっている。また、物理網・論理網・局内構成図描画部24は、作業計画管理部21から仮の予定停止計画情報PL(停止日時情報Idtと停止予定設備情報Imcとを含む)を受け取ると、閉塞対象候補抽出部25に出力するようになっている。物理網・論理網・局内構成図描画部24は、閉塞対象候補抽出部25から閉塞予定機器またはポート部の候補情報Cd(閉塞予定候補の機器情報Imc−Cdと閉塞予定候補のポート部情報p00n−Cdと停止日時情報Idt)を受け取ると、この候補情報Cdに基づき、構成管理データベース22から候補情報Cdに対応した物理回線構成情報Phと装置構成情報Apと論理回線構成情報Lgを抽出し、抽出された情報に関連付けして候補情報Cdを、作業担当端末装置10Xの上記描画処理された構成図に反映させて表示させるようになっている。以下、停止予定設備の候補情報Cd(Imc−Cd、p00n−Cd、Idt)には常に停止日時情報Idtも添付されるが、その説明については省略し、停止予定設備の候補情報Cdfには停止日時情報Idtも含まれるものとして説明する。ここでいう停止予定設備の情報Imc−Cdとは、例えば、図4ないし図6に示すように、作業担当端末装置10Xで所管していない事業所[X][Y][Z][W]のうち事業所[Y]のルータ装置「A」を停止予定している場合、ルータ装置「A」を指す。   The physical network / logical network / intra-station configuration diagram drawing unit 24 can perform a drawing process on the physical network configuration diagram, the logical network configuration diagram, and the intra-station configuration diagram, and send them to the work terminal device 10X via the communication control unit 20. Send and display. The physical network / logical network / intra-station configuration diagram drawing unit 24 receives physical line configuration information Ph and device configuration information Ap from the configuration management database 22 based on the facility information input from the work planning unit 21 or the block target candidate extraction unit 25. And the logical line configuration information Lg are extracted and rendered, and the facility information input on the rendered configuration diagram is reflected and displayed on the work terminal device 10X. When the physical network / logical network / intra-station configuration diagram drawing unit 24 receives provisional scheduled stop plan information PL (including stop date / time information Idt and scheduled stop facility information Imc) from the work plan management unit 21, The data is output to the candidate extraction unit 25. The physical network / logical network / intra-station configuration diagram drawing unit 24 sends the block target candidate or port unit candidate information Cd (block unit candidate information Imc-Cd and block unit candidate port part information p00n from the block target candidate extraction unit 25). -Cd and stop date / time information Idt), physical line configuration information Ph, device configuration information Ap, and logical line configuration information Lg corresponding to the candidate information Cd are extracted from the configuration management database 22 based on the candidate information Cd, In association with the extracted information, the candidate information Cd is reflected in the drawing-processed configuration diagram of the work terminal device 10X and displayed. Hereinafter, the stop date and time information Idt is always attached to the candidate information Cd (Imc-Cd, p00n-Cd, Idt) of the planned facility to be stopped, but the description thereof is omitted, and the candidate information Cdf of the planned facility to be stopped is stopped. The description will be made assuming that the date / time information Idt is also included. For example, as shown in FIGS. 4 to 6, the stop scheduled facility information Imc-Cd is an office [X] [Y] [Z] [W] that is not in charge of the work terminal device 10X. If the router device “A” at the office [Y] is scheduled to stop, the router device “A” is indicated.

閉塞対象候補抽出部25は、物理網・論理網・局内構成図描画部24から仮の予定停止計画情報PL(停止日時情報Idtと停止予定設備情報Imcとを含む)を受け取ると、物理網・論理網・局内構成図描画部24が構成管理データベース22により抽出した物理回線構成情報Phと装置構成情報Apと論理回線構成情報Lgとに基づいて、停止予定設備の回線に関連する機器またはポート部の候補を抽出し、抽出された閉塞候補の機器またはポート部の候補情報Cdを物理網・論理網・局内構成図描画部24に出力するようになっている。物理網・論理網・局内構成図描画部24は、上述のように、閉塞対象候補抽出部25から閉塞予定機器またはポート部の候補情報Cdを受け取ると、この候補情報Cdに基づき、構成管理データベース22から候補情報Cdに対応した物理回線構成情報Phと装置構成情報Apと論理回線構成情報Lgを抽出し、抽出された情報に関連付けして候補情報Cdを、作業担当端末装置10Xの描画処理された構成図に反映させて表示させる。このため、作業担当端末装置10Xの表示端末10Bには、停止予定通信設備の停止計画情報PLに基づいて表示された物理網構成図、論理網構成図および局内構成図のうちいずれかの構成図上に、停止予定設備Imcの回線に関連する機器またはポート部の候補情報Cdが表示されるようになっている。作業担当端末装置10Xに表示された閉塞対象とすべき機器またはポート部の候補Cdに対し、オペレータが、作業対象とすべき機器またはポート部を選択すると、作業対象設備として選択された機器またはポート部の情報Cdfは、センターサーバ11に送信され、後述する作業対象設備決定部26に送られるようになっている。ここでいう閉塞対象候補抽出部25により抽出された閉塞候補の機器またはポート部の候補情報Cdとは、例えば、図4ないし図6に示すように、停止予定設備の情報Imcが事業所[Y]のルータ装置「A」である場合、停止予定設備Imcの回線に関連する機器の候補は、図4の「(II)閉塞対象候補:回線」に示すように、事業所[W]のルータ装置「C」、事業所[Z]のルータ装置「B」、同じ事業所[Y]のルータ装置「I」となる。そして、停止予定設備Imcの回線に関連する機器のポート部候補は、事業所[W]のルータ装置「C」についてはポート番号p002(以下、C:p002と表記する。)、事業所[Z]のルータ装置「B」についてはポート番号p003(以下、B:p003と表記する。)、同じ事業所[Y]のルータ装置「I」についてはポート番号p001(以下、I:p001と表記する。)となる。また、ポート部候補には、オペレータにより閉塞順序が選択できるよう、閉塞順序選択情報が付されようになっている(図5および図6の閉塞候補を選択する欄参照)。オペレータは、閉塞順序を選択することができるので、作業手順を効率化することができる。   Upon receiving the temporary planned stop plan information PL (including stop date / time information Idt and planned stop facility information Imc) from the physical network / logical network / internal station configuration diagram drawing unit 24, the blocking target candidate extraction unit 25 receives the physical network Based on the physical line configuration information Ph, device configuration information Ap, and logical line configuration information Lg extracted by the configuration management database 22 by the logical network / station configuration diagram drawing unit 24, a device or port unit related to the line of the facility to be stopped And the candidate information Cd of the extracted blockage candidate device or port portion is output to the physical network / logical network / intra-station configuration diagram drawing unit 24. As described above, when the physical network / logical network / intra-station configuration diagram drawing unit 24 receives candidate information Cd of the block target device or port unit from the block target candidate extraction unit 25, the configuration management database is based on the candidate information Cd. 22, the physical line configuration information Ph, the device configuration information Ap, and the logical line configuration information Lg corresponding to the candidate information Cd are extracted, and the candidate information Cd is associated with the extracted information and the drawing processing of the work charge terminal device 10X is performed. To be reflected in the configuration diagram. Therefore, any one of the physical network configuration diagram, the logical network configuration diagram, and the intra-station configuration diagram displayed on the display terminal 10B of the work charge terminal device 10X based on the stop plan information PL of the scheduled stop communication facility. The candidate information Cd of the device or port part related to the line of the planned shutdown facility Imc is displayed above. When the operator selects a device or port part to be a work target for the device or port part candidate Cd to be blocked displayed on the work terminal device 10X, the device or port selected as the work target facility is selected. The part information Cdf is transmitted to the center server 11 and is sent to the work target equipment determination unit 26 described later. The blockage candidate device or port unit candidate information Cd extracted by the block target candidate extraction unit 25 here is, for example, as shown in FIGS. ] Of the router device “A” in FIG. 4, the device candidates related to the line of the facility Imc to be stopped are the routers of the office [W], as shown in “(II) Candidate to be blocked: line” in FIG. The device “C”, the router device “B” of the office [Z], and the router device “I” of the same office [Y]. And the port part candidate of the equipment related to the line of the planned shutdown facility Imc is the port number p002 (hereinafter referred to as C: p002) and the office [Z] for the router device “C” of the office [W]. ] For router device “B” of port number p003 (hereinafter referred to as B: p003), and for router device “I” of the same office [Y] as port number p001 (hereinafter referred to as I: p001). .) In addition, block order selection information is attached to the port part candidates so that the block order can be selected by the operator (see the column for selecting block candidates in FIGS. 5 and 6). Since the operator can select the closing order, the work procedure can be made more efficient.

作業対象設備決定部26は、作業担当端末装置10Xから作業対象設備として選択された機器またはポート部の情報を受け取ると、受け取った停止予定設備の選択情報Cdfを作業対象設備として決定し、この選択された作業対象設備情報Cdfを作業対象設備担当端末装置抽出部27に出力するようになっている。作業対象設備担当端末装置抽出部27は、作業対象設備決定部26から選択された作業対象設備情報Cdfを受け取ると、この選択された作業対象設備情報Cdfに基づき、構成管理データベース22からこの停止作業対象設備Cdfが属する保守担当域を所管する端末装置10Y1、10Y2・・・10Ynを抽出し、抽出された作業対象設備担当端末装置10Y1〜10Ynの特定情報を承認処理部28に出力するようになっている。   When the work target facility determination unit 26 receives information on the device or port unit selected as the work target facility from the work terminal device 10X, the work target facility determination unit 26 determines the received stop planned facility selection information Cdf as the work target facility, and selects this The work target facility information Cdf thus output is output to the work target facility responsible terminal device extraction unit 27. When receiving the work target facility information Cdf selected from the work target facility determination unit 26, the work target facility terminal device extraction unit 27 receives the stop operation from the configuration management database 22 based on the selected work target facility information Cdf. The terminal devices 10Y1, 10Y2,... 10Yn having jurisdiction over the maintenance charge area to which the target facility Cdf belongs are extracted, and the specific information of the extracted work target facility charge terminal devices 10Y1 to 10Yn is output to the approval processing unit 28. ing.

承認処理部28は、受け取った作業対象設備担当端末装置10Y1〜10Ynの特定情報に基づき、特定された作業対象設備担当端末装置10Y1〜10Ynに、作業担当端末装置10Xにより選択され、それぞれ対応する保守担当域に属する停止作業の対象とすべき通信設備の情報Cdf(機器の情報Imc−Cdf、ポート部の情報p00n−Cdf)と停止日時の情報Idtとを送信し、当該作業対象設備担当端末装置10Y1〜10Ynが停止作業の実施を承認するか否かの承認要求を行うようになっている。また、承認処理部28は、この承認要求を行った後、これら作業対象設備担当端末装置10Y1〜10Ynから停止作業実施承認の諾否の情報を受け取ると、この諾否情報を作業計画管理部21に出力するようになっている。作業計画管理部21は、上述のように、承認処理部28から停止作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された停止作業計画情報PLの可否を決定するとともに、停止作業実施の可否の決定を作業担当端末装置10Xに送信して表示させるようになっている。停止作業の実施が可の場合、最終的な停止計画情報PLfが作業計画管理部21を通じて作業計画データベースに23に登録され、後述する当日作業計画管理部30に出力されるとともに作業担当端末装置10Xに表示される。停止作業の実施が不可の場合、一連の停止作業の処理は終了して仮の停止計画情報PLはキャンセルされ、作業担当のオペレータは、改めて後日の作業計画を練り直す。   The approval processing unit 28 selects the identified work target facility charge terminal devices 10Y1 to 10Yn by the work charge terminal device 10X based on the received identification information of the work target facility charge terminal devices 10Y1 to 10Yn, and performs maintenance corresponding to each of them. The communication equipment information Cdf (device information Imc-Cdf, port section information p00n-Cdf) and stop date / time information Idt to be the target of the stop work belonging to the work area is transmitted, and the work target equipment charge terminal device 10Y1 to 10Yn make an approval request as to whether or not to approve execution of the stop work. Further, after making the approval request, the approval processing unit 28 receives the approval / disapproval information of the stop operation execution approval from the work target facility terminal devices 10Y1 to 10Yn, and outputs the approval / disapproval information to the work plan management unit 21. It is supposed to be. As described above, when the work plan management unit 21 receives the determination result of acceptance / rejection for the stop work from the approval processing unit 28, the work plan management unit 21 determines whether or not the stop work plan information PL scheduled based on the determination result is acceptable, and also stops. The decision as to whether or not the work can be performed is transmitted to the work terminal device 10X for display. When the stop work can be performed, the final stop plan information PLf is registered in the work plan database 23 through the work plan management unit 21 and is output to the later-described day work plan management unit 30 and the work-in-use terminal device 10X. Is displayed. When the stop work cannot be performed, a series of stop work processes are completed, the temporary stop plan information PL is canceled, and the operator in charge of the work revisits the work plan at a later date.

このようにして、センターサーバ11の運用管理系システム部11Aでは、停止作業当日の前に、作業担当のオペレータにより作業担当端末装置10Xを通じて予定された停止計画情報PLが入力されると、作業計画部21がこの停止計画情報PLを物理網・論理網・局内構成図描画部24に出力し、物理網・論理網・局内構成図描画部24は、受け取った停止計画情報PLを閉塞対象候補抽出部25に出力する。閉塞対象候補抽出部25は、構成管理データベース22に格納された通信設備の情報に基づいて、停止予定設備の回線に関連する機器またはポート部の候補を抽出し、抽出された候補情報Cdを物理網・論理網・局内構成図描画部24に出力する。物理網・論理網・局内構成図描画部24は、受け取った候補情報Cdに基づいて、作業担当端末10Xの画面上で、停止予定通信設備の停止計画情報PLに基づいて表示された物理網構成図、論理網構成図および局内構成図のうちいずれかの構成図に、停止予定設備Imcの回線に関連する機器またはポート部の候補情報Cdを表示させるようになっている。そして、作業担当のオペレータにより作業担当端末装置10Xを通じて候補情報Cdから作業対象とすべき機器または機器のポート部Cdfが選択されると、その選択された選択情報Cdfがセンターサーバ11の運用管理系システム部11Aに送信される。運用管理系システム部11Aでは、受け取った停止予定設備の選択情報Cdfを作業対象設備として決定するとともに、構成管理データベース22に格納された通信設備の情報に基づいて、作業対象として選択された機器Imc−Cdfまたはポート部p00n−Cdfを自らの保守担当域に有し当該機器Imc−Cdfまたは当該ポート部p00n−Cdfを管理する端末装置10Y1〜10Ynを作業対象設備担当端末装置として抽出し、抽出された作業対象設備担当端末装置10Y1〜10Ynにそれぞれの保守担当域毎に予定された停止日時Idtと選択された機器または機器のポート部の情報Cdfを送信して、停止作業実施承認の諾否を求め、作業対象設備担当端末装置10Y1〜10Ynから停止作業について諾否の判別結果Ay/nを受け取ると、この判別結果Ay/nに基づいて予定された停止作業実施の可否を最終的に決定するとともに、停止作業実施の可否の決定を作業担当端末装置10Xに送信して表示させるようになっている。   In this way, in the operation management system unit 11A of the center server 11, when the stop plan information PL scheduled through the work terminal device 10X is input by the operator in charge before the stop work day, the work plan The unit 21 outputs the stop plan information PL to the physical network / logical network / intra-station configuration diagram drawing unit 24, and the physical network / logical network / intra-station configuration diagram drawing unit 24 extracts the received stop plan information PL as a blocking target candidate. To the unit 25. The block target candidate extraction unit 25 extracts a device or port unit candidate related to the line of the planned shutdown facility based on the communication facility information stored in the configuration management database 22, and physically extracts the extracted candidate information Cd. The data is output to the network / logical network / intra-station configuration diagram drawing unit 24. Based on the received candidate information Cd, the physical network / logical network / intra-station configuration diagram drawing unit 24 displays the physical network configuration displayed on the screen of the work terminal 10X based on the stop plan information PL of the planned stop communication facility. The candidate information Cd of the device or port part related to the line of the planned shutdown facility Imc is displayed in any one of the diagram, the logical network configuration diagram, and the intra-station configuration diagram. Then, when the operator in charge of the work selects the device or the port portion Cdf of the device to be worked from the candidate information Cd through the work charge terminal device 10X, the selected selection information Cdf is used as the operation management system of the center server 11. It is transmitted to the system unit 11A. In the operation management system unit 11A, the received stop planned facility selection information Cdf is determined as the work target facility, and the device Imc selected as the work target based on the communication facility information stored in the configuration management database 22 is used. -The terminal devices 10Y1 to 10Yn having the Cdf or the port part p00n-Cdf in their own maintenance charge area and managing the device Imc-Cdf or the port part p00n-Cdf are extracted as the work target equipment charge terminal devices. The scheduled stop date / time Idt for each maintenance charge area and the information Cdf of the selected device or the port portion of the device are transmitted to the work target facility responsible terminal devices 10Y1 to 10Yn, and the approval or disapproval of the stop work execution approval is requested. , The result of determination of acceptance or disapproval for the stop work from the work target facility terminal devices 10Y1 to 10Yn When y / n is received, whether or not the scheduled stop work can be performed is finally determined based on the determination result Ay / n, and the determination as to whether or not the stop work can be performed is transmitted to the work terminal device 10X for display. It is supposed to let you.

センターサーバ11の監視制御系システム部11Bは、作業計画データベース(データベース)23と、当日作業計画管理部(当日作業計画管理手段)30と、当日承認処理部(当日承認処理手段)31と、制御コマンド文法データベース(制御コマンド生成手段)32と、制御コマンド生成部(制御コマンド生成手段)33と、回線状態確認部(回線状態確認手段)34と、閉塞・閉塞解除制御部(停止・停止解除制御手段)35とを備えて構成される。   The monitoring control system section 11B of the center server 11 includes a work plan database (database) 23, a current day work plan management section (current day work plan management means) 30, a current day approval processing section (current day approval processing means) 31, and a control. Command grammar database (control command generation means) 32, control command generation section (control command generation means) 33, line state confirmation section (line state confirmation means) 34, block / block release control section (stop / stop release control) Means) 35.

当日作業計画管理部30は、停止作業当日の作業開始所定時間前(本実施例では作業開始t1分前、t1分は、例えば、30分、60分、180分というように、すなわち、t1分前は30分前、1時間前、3時間前というように作業に応じて決定される。)、停止作業当日前に予め作業計画データベース23から受け取った最終的な登録済み停止計画情報PLfに基づいて、この最終的な登録済み停止計画情報PLfとすでに特定されている停止作業の通信設備を管理する作業対象設備担当端末装置10Y1〜10Ynの特定情報を当日承認処理部31に出力する。また、当日作業計画管理部30は、上記作業対象設備担当端末装置10Y1〜10Ynから当日の停止作業について諾否の判別結果Afy/nを当日承認処理部31を通じて受け取ると、この判別結果Afy/nに基づいて登録された最終的な登録済み停止計画情報PLfによる当日実施について開始の可否を作業担当端末装置10Xに送信して表示させるようになっている。さらに、当日作業計画管理部30は、作業担当端末装置10Xから作業対象となる機器Imc−Cdfまたはポート部p00n−Cdfに対し回線状態を確認するよう要求する指令を受け取ると、この指令を回線状態確認部34に送出するようになっている。また、当日作業計画管理部30は、作業担当端末装置10Xから作業対象となる機器Imc−Cdfまたはポート部p00n−Cdfについて閉塞(停止)または閉塞解除(停止解除)を要求する指令を受け取ると、この指令を閉塞・閉塞解除制御部35に送出するようになっている。   The work plan management unit 30 on the day is a predetermined time before the start of work on the stop work day (in this embodiment, t1 minutes before the work start, t1 minutes are, for example, 30 minutes, 60 minutes, 180 minutes, that is, t1 minutes) The previous is determined according to the work, such as 30 minutes ago, 1 hour ago, 3 hours ago.) Based on the final registered stop plan information PLf received from the work plan database 23 in advance before the stop work day. Thus, the final registered stop plan information PLf and the specific information of the work target equipment terminal devices 10Y1 to 10Yn for managing the communication equipment for the stop work already specified are output to the day approval processor 31. In addition, when the day work plan management unit 30 receives the determination result Afy / n of approval / disapproval for the stop work on the day from the work target facility terminal devices 10Y1 to 10Yn through the day approval processing unit 31, the day determination plan Afy / n Based on the final registered stop plan information PLf registered on the basis, whether or not to start the day implementation is transmitted to the work terminal device 10X and displayed. Further, when the work plan management unit 30 on the day receives a command for requesting the device Imc-Cdf or the port unit p00n-Cdf to check the line state from the work terminal device 10X, the line state is received. The data is sent to the confirmation unit 34. In addition, when the work plan management unit 30 on the day receives a command for requesting blockage (stop) or blockage release (stop release) for the device Imc-Cdf or the port unit p00n-Cdf to be worked from the work terminal device 10X, This command is sent to the block / block release controller 35.

当日承認処理部31は、当日作業計画管理部30から最終的な登録済み停止計画情報PLfと作業対象設備担当端末装置10Y1〜10Ynの特定情報とを受け取ると、この特定情報に基づき、特定された作業対象設備担当端末装置10Y1〜10Ynに、最終的な登録済み停止計画情報PLfに基づいて、作業当日の作業対象とすべき機器Imc−Cdfまたはポート部p00n−Cdfの情報Cdfと停止日時の情報Idtを送信し、当該作業対象設備担当端末装置10Y1〜10Ynが当日の停止作業実施を承認するか否かの当日承認要求を行うとともに、これら作業対象設備担当端末装置10Y1〜10Ynから承認の諾否の情報Afy/nを受け取ると、この当日作業諾否情報Afy/nを当日作業計画管理部30に出力するようになっている。当日作業計画管理部30は、当日承認処理部31から当日の停止作業について諾否の判別結果Afy/nを受け取ると、この判別結果Afy/nに基づいて登録された停止計画情報PLfによる当日作業実施の可否を決定するとともに、当日停止作業開始の可否の決定を作業担当端末装置10Xに送信して表示させるようになっている。当日停止作業の開始が可の場合、作業担当端末装置10Xを通じて、実作業が開始される。当日停止作業の開始が不可の場合、一連の停止作業の処理は終了し登録された停止計画情報PLfはキャンセルされ、作業担当のオペレータは、改めて後日の作業計画を練り直す。   Upon receipt of the final registered stop plan information PLf and the specific information on the work target facility terminal devices 10Y1 to 10Yn from the current day work plan management unit 30, the same day approval processing unit 31 is specified based on this specific information. Based on the final registered stop plan information PLf, the device Imc-Cdf or the port part p00n-Cdf information Cdf and the stop date / time information to be the work target on the work day based on the final registered stop plan information PLf. Idt is transmitted, and the work target facility terminal devices 10Y1 to 10Yn make a request for approval on the day as to whether or not to approve the stop operation of the day, and approval / rejection of approval from these work target facility terminal devices 10Y1 to 10Yn When the information Afy / n is received, the current day work approval / disapproval information Afy / n is output to the current day work plan management unit 30. Going on. When the current day work plan management unit 30 receives the determination result Afy / n of acceptance / rejection for the current day's stop operation from the current day approval processing unit 31, the current day work plan management unit 30 performs the current day work by the stop plan information PLf registered based on the determination result Afy / n. The determination as to whether or not to start the stop work on the day is sent to the work terminal device 10X for display. When it is possible to start the stop work on that day, the actual work is started through the work terminal device 10X. If it is impossible to start the stop work on that day, the series of stop work processes ends, the registered stop plan information PLf is cancelled, and the operator in charge of the work revisits the work plan at a later date.

回線状態確認部34は、作業担当端末装置10Xから当日作業計画管理部30を通じて、回線状態を確認するよう要求する指令を受け取ると、この指令に基づいて制御コマンド生成部33に回線状態情報要求コマンド生成とそのコマンド投入の要求を指令するようになっている。制御コマンド生成部33は、回線状態確認部34からの指令に基づき、制御コマンドを生成する文法が格納された制御コマンド文法データベース32により回線状態情報要求コマンドを生成し、作業対象の機器Imc−Cdfまたはポート部p00n−Cdfに対し、回線状態の確認を要求する情報を送出するようになっている。回線状態確認部34は、作業対象の機器Imc−Cdfまたはポート部p00n−Cdfが回線状態確認要求に応え、回線状態の情報をセンターサーバ11に送ってくると、この回線状態の情報を受け取り、作業担当端末装置10Xに送信して表示させるようになっている。   When the line status confirmation unit 34 receives a command for confirming the line status from the work terminal device 10X through the work plan management unit 30 on the day, the line status information request command is sent to the control command generation unit 33 based on this command. A request for generation and input of the command is issued. The control command generation unit 33 generates a line state information request command from the control command grammar database 32 in which a grammar for generating a control command is stored based on a command from the line state confirmation unit 34, and the device Imc-Cdf to be worked on Alternatively, information requesting confirmation of the line state is transmitted to the port unit p00n-Cdf. When the work target device Imc-Cdf or the port unit p00n-Cdf responds to the line state confirmation request and sends the line state information to the center server 11, the line state confirmation unit 34 receives the line state information, It is transmitted to the work terminal device 10X and displayed.

閉塞・閉塞解除制御部35は、作業担当端末装置10Xから当日作業計画管理部30を通じて、作業対象の機器Imc−Cdfまたはポート部p00n−Cdfについて閉塞を要求する指令を受け取ると、この指令に基づいて制御コマンド生成部33に閉塞要求コマンドを生成するように指令する。制御コマンド生成部33は、閉塞・閉塞解除制御部35からの指令に基づき、制御コマンド文法データベース32により閉塞要求コマンドを生成し、作業対象の機器Imc−Cdfまたはポート部p00n−Cdfに対し、閉塞を要求する情報を送出するようになっている。閉塞・閉塞解除制御部35は、閉塞要求を受けた作業対象の機器または機器のポート部Cdfから閉塞実行の結果が送信されてくると、その実行結果を作業担当端末装置10Xに送信して表示させるようになっている。また、閉塞・閉塞解除制御部35は、作業担当端末装置10Xから当日作業計画管理部31を通じて、閉塞中の機器Imc−Cdfまたはポート部p00n−Cdfについて閉塞解除を要求する指令を受け取ると、この指令に基づいて制御コマンド生成部33に閉塞解除要求コマンドを生成するよう指令するようになっている。制御コマンド生成部33は、閉塞・閉塞解除制御部35からの指令に基づき、制御コマンド文法データベース32により閉塞解除要求コマンドを生成し、閉塞中の機器Imc−Cdfまたはポート部p00n−Cdfに対し、閉塞解除を要求する情報を送出するようになっている。閉塞・閉塞解除制御部35は、閉塞解除要求を受けた閉塞中の機器Imc−Cdfまたはポート部p00n−Cdfから閉塞解除実行の結果が送信されてくると、その実行結果を作業担当端末装置10Xに送信して表示させるようになっている。以下、閉塞対象(停止対象)となるのは、機器(IP機器)Imc−CdfまたはIP機器のポート部p00n−Cdfのうち少なくともいずれか一方であればよい。   When the blockage / blockage release control unit 35 receives a command for requesting blockage of the device Imc-Cdf or the port unit p00n-Cdf to be worked from the work terminal device 10X through the work plan management unit 30 on the day, based on this command The control command generator 33 is instructed to generate a block request command. The control command generator 33 generates a block request command from the control command grammar database 32 based on a command from the block / block release controller 35, and blocks the work target device Imc-Cdf or the port unit p00n-Cdf. Information that requests is sent. When the blocking execution result is transmitted from the work target device that has received the blocking request or the port part Cdf of the device, the blocking / blocking release control unit 35 transmits the execution result to the work terminal device 10X for display. It is supposed to let you. Further, when the blockage / blockage release control unit 35 receives a command for requesting blockage release for the device Imc-Cdf or the port unit p00n-Cdf being blocked from the work terminal device 10X through the work plan management unit 31 on the day, Based on the command, the control command generating unit 33 is instructed to generate a closure release request command. The control command generation unit 33 generates a block release request command from the control command grammar database 32 based on a command from the block / block release control unit 35, and sends the block device Imc-Cdf or the port unit p00n-Cdf to the block unit. Information requesting release of blockage is transmitted. When the blocking / unblocking control unit 35 receives the blocking release execution result from the blocked device Imc-Cdf or the port unit p00n-Cdf that has received the blocking cancellation request, the blocking / unblocking control unit 35 sends the execution result to the work terminal device 10X. Sent to and displayed. Hereinafter, it is sufficient that at least one of the device (IP device) Imc-Cdf or the port portion p00n-Cdf of the IP device is to be blocked (stopped).

次に、本発明に係るネットワークの作業管理方法について、上記実施例に係るネットワークの作業管理システムの作用に基づいて説明する。
まず、当日作業前に、作業担当者は作業担当端末装置10Xを通じて、仮の予定停止計画情報PLをセンターサーバ11に送信し、閉塞予定候補の絞り込みを行う。
すなわち、図2および図3に示すように、ネットワークの回線について将来の停止作業を予定している作業担当者は、自らの保守担当域を所管する端末装置、すなわち、作業担当端末装置10Xを通じて、事前に仮の予定停止計画情報PLをセンターサーバ11に送信すると(図2のA−1参照)、この予定停止計画情報PLはセンターサーバ11の作業計画管理部21に入力される。次に、作業計画管理部21が、この予定停止計画情報PLのうち停止予定設備の情報Imcを物理網・論理網・局内構成図描画部24に送出すると(図2のA−2参照)、物理網・論理網・局内構成図描画部24は、入力された停止予定設備の情報Imcに基づいて、構成管理データベース22から物理回線構成情報Phと装置構成情報Apと論理回線構成情報Lgとを抽出する(図2のA−3参照)。そして、物理網・論理網・局内構成図描画部24は、これら抽出された物理回線構成情報Ph、装置構成情報Apおよび論理回線構成情報Lgとに基づいて網構成図や装置構成図などの構成図を描画処理して作業担当端末装置10Xに表示させる。また、物理網・論理網・局内構成図描画部24は作業計画管理部21から受け取った停止予定設備の情報Imcを閉塞対象候補抽出部25に送出する(図2のA−4参照)。閉塞対象候補抽出部25は、物理網・論理網・局内構成図描画部24から受け取った停止予定設備の情報Imcに基づいて、停止予定設備Imc(例えば、図4に示すルータ装置「A」)の回線に関連する機器とそのポート部の候補を抽出し、抽出された停止予定設備Imcの回線に関連する機器(例えば、図4に示すルータ装置「C」、「B」、「I」)とそのポート部(例えば、図4に示す「C:p002」、「A:p001」、「B:p003」、「A:p002」、「I:p001」、「A:p003」で、「機器:p00n」(nは自然数)で表す。)の候補情報Cdを物理網・論理網・局内構成図描画部24に出力する(図2のA−5、図5および図6参照)。物理網・論理網・局内構成図描画部24は、閉塞対象候補抽出部25から受け取った抽出された閉塞予定の機器とそのポート部の候補情報Cdに基づいて、作業担当端末装置10Xに表示させ描画処理されている構成図にこれら候補情報Cdを反映させる(図2のA−6参照)。
Next, a network work management method according to the present invention will be described based on the operation of the network work management system according to the embodiment.
First, before the work on the day, the worker in charge transmits provisional scheduled stop plan information PL to the center server 11 through the work-in-charge terminal device 10X, and narrows down the scheduled closure candidates.
That is, as shown in FIG. 2 and FIG. 3, a worker who is planning a future stop work on a network line, through a terminal device having jurisdiction over his / her maintenance area, that is, the worker terminal device 10X, When the temporary planned stop plan information PL is transmitted to the center server 11 in advance (see A-1 in FIG. 2), the planned stop plan information PL is input to the work plan management unit 21 of the center server 11. Next, when the work plan management unit 21 sends out the information Imc of the planned outage of the planned outage plan information PL to the physical network / logical network / intra-station configuration diagram drawing unit 24 (see A-2 in FIG. 2), The physical network / logical network / intra-station configuration diagram drawing unit 24 obtains the physical line configuration information Ph, the device configuration information Ap, and the logical line configuration information Lg from the configuration management database 22 based on the input information Imc of the planned outage facility. Extract (see A-3 in FIG. 2). Then, the physical network / logical network / intra-station configuration diagram drawing unit 24 configures a network configuration diagram, a device configuration diagram, and the like based on the extracted physical line configuration information Ph, device configuration information Ap, and logical line configuration information Lg. The drawing is processed and displayed on the work terminal device 10X. Further, the physical network / logical network / intra-station configuration diagram drawing unit 24 sends the information Imc of the planned shutdown facility received from the work plan management unit 21 to the block target candidate extraction unit 25 (see A-4 in FIG. 2). The blocking target candidate extraction unit 25 is based on the scheduled shutdown facility information Imc received from the physical network / logical network / intra-station configuration diagram drawing unit 24 (for example, the router device “A” shown in FIG. 4). The equipment related to the line and the port part candidate are extracted, and the equipment related to the extracted line of the planned shutdown facility Imc (for example, router devices “C”, “B”, “I” shown in FIG. 4). And its port part (for example, “C: p002”, “A: p001”, “B: p003”, “A: p002”, “I: p001”, “A: p003” shown in FIG. : P00n "(n is a natural number) candidate information Cd is output to the physical network / logical network / intra-station configuration diagram drawing unit 24 (see A-5 in FIG. 2, FIGS. 5 and 6). The physical network / logical network / intra-station configuration diagram drawing unit 24 causes the work-in-use terminal device 10X to display the block to be blocked received from the block target candidate extraction unit 25 and the candidate information Cd of the port unit. The candidate information Cd is reflected in the configuration diagram being rendered (see A-6 in FIG. 2).

次に、作業担当端末装置10Xのオペレータにより閉塞予定候補のうち停止作業対象とすべき通信設備を選択し、選択された候補情報Cdfに基づいて、その候補の属する保守担当域の作業対象設備担当端末装置10Ynを特定し、特定された作業対象設備担当端末装置10Ynに停止作業の承認を求める。
すなわち、作業担当端末装置10Xでは、閉塞予定の候補情報Cdが反映された物理網構成図、論理網構成図および局内構成図が表示されると、オペレータは、閉塞作業の対応を調整し、この候補の中から閉塞作業の対象とすべき機器Imc−Cdf(例えば、図4に示すルータ装置「A」と「C」)とそのポート部p00n−Cdf(例えば、図4に示すルータ装置「C」のポート部p002「C:p002」とルータ装置「A」のポート部p001「A:p001」)を選択する。オペレータが閉塞作業の対象とすべき機器Imc−Cdfのポート部p00n−Cdfを選択すると、これら選択された閉塞作業の対象とすべき機器Imc−Cdfとそのポート部p00n−Cdfの情報Cdfは作業対象設備決定部26に送信される(図2のA−7参照)。作業対象設備決定部26は、作業担当端末装置10Xから作業対象設備として選択された機器Imc−Cdfとそのポート部p00n−Cdfの情報Cdfを受け取ると、受け取った停止予定設備の情報Cdfを作業対象設備として仮決定し、この作業対象設備情報Cdfを作業対象設備担当端末装置抽出部27に出力する(図2のA−8参照)。作業対象設備担当端末装置抽出部27は、作業対象設備決定部26から作業対象設備情報Cdfを受け取ると、この作業対象設備情報Cdfに基づき、構成管理データベース22からこの停止作業対象設備Cdfが属する保守担当域を所管する端末装置10Y1、10Y2・・・10Ynを抽出し、抽出された作業対象設備担当端末装置10Y1〜10Ynを特定する特定情報を承認処理部28に出力する。承認処理部28は、受け取った作業対象設備担当端末装置10Y1〜10Ynの特定情報に基づき、特定された作業対象設備担当端末装置10Y1〜10Ynに、それぞれ対応する保守担当域に属する選択された停止作業の対象とすべき機器Imc−Cdfとそのポート部p00n−Cdfの情報Cdfと停止日時の情報Idtを送信し、該当する作業対象設備担当端末装置10Y1〜10Ynが停止作業の実施を承認するか否かの承認要求を行う(図2のA−9参照)。
Next, the operator of the work terminal apparatus 10X selects a communication facility to be a stop work target from among the planned shutdown candidates, and based on the selected candidate information Cdf, the work target equipment manager in the maintenance charge area to which the candidate belongs. The terminal device 10Yn is specified, and the specified work target facility terminal device 10Yn is requested to approve the stop operation.
That is, when the physical network configuration diagram, the logical network configuration diagram, and the intra-station configuration diagram reflecting the candidate information Cd to be blocked are displayed, the operator in charge of the work terminal device 10X adjusts the response of the blocking work, Among the candidates, the device Imc-Cdf (for example, the router devices “A” and “C” shown in FIG. 4) to be blocked and its port part p00n-Cdf (for example, the router device “C” shown in FIG. 4). Port portion p002 “C: p002” and router device “A” port portion p001 “A: p001”). When the operator selects the port part p00n-Cdf of the device Imc-Cdf to be blocked, the selected device Imc-Cdf to be blocked and the information Cdf of the port part p00n-Cdf is the work. It transmits to the object installation determination part 26 (refer A-7 of FIG. 2). Upon receiving the device Imc-Cdf selected as the work target facility from the work terminal device 10X and the information Cdf of the port part p00n-Cdf, the work target facility determination unit 26 receives the information Cdf of the planned shutdown facility as the work target. Temporarily determined as equipment, and this work target equipment information Cdf is output to the work target equipment terminal device extraction unit 27 (see A-8 in FIG. 2). When receiving the work target facility information Cdf from the work target facility determining unit 26, the work target facility terminal device extracting unit 27 performs maintenance to which the stopped work target facility Cdf belongs from the configuration management database 22 based on the work target facility information Cdf. The terminal devices 10Y1, 10Y2,... 10Yn having jurisdiction over the assigned area are extracted, and specific information specifying the extracted work target facility responsible terminal devices 10Y1 to 10Yn is output to the approval processing unit 28. The approval processing unit 28 selects the selected stop work belonging to the maintenance area corresponding to the identified work target facility terminal devices 10Y1 to 10Yn based on the received identification information of the work target facility terminal devices 10Y1 to 10Yn. Whether the device Imc-Cdf to be targeted, the information Cdf of its port part p00n-Cdf, and the stop date / time information Idt, and whether or not the corresponding work target facility terminal units 10Y1 to 10Yn approve the execution of the stop operation. (See A-9 in FIG. 2).

次に、特定された作業対象設備担当端末装置10Ynから受け取った停止作業の諾否情報Ay/nを、作業担当端末装置10Xに知らせ、作業当日前までに最終的な停止計画情報PLfを登録する。
作業対象設備担当端末装置10Y1〜10Ynは、承認処理部28から停止作業承認の諾否を求められると、これら該当する作業対象設備担当端末装置10Y1〜10Ynのオペレータは、自らが管理する通信設備について、停止作業の実施を承認するかどうか、内容を確認して閉塞作業の対応を調整し、承認の諾否情報Ay/nを承認処理部28に送信する(図2のA−10参照)。承認処理部28は該当する作業対象設備担当端末装置10Y1〜10Ynのすべてから承認の諾否情報Ay/nを受け取ると、これら諾否情報Ay/nを作業計画管理部21に出力する(図2のA−11参照)。作業計画管理部21は、諾否情報Ay/nを受け取ると、この諾否情報Ay/nに基づいて予定された停止作業実施の可否を決定するとともに、停止作業実施の可否の決定の情報(実施可:Ay、実施不可:An)を作業担当端末装置10Xに送信して表示させる。
Next, stop work acceptance / rejection information Ay / n received from the identified work target facility terminal device 10Yn is notified to the work terminal device 10X, and final stop plan information PLf is registered before the work day.
When the work target facility terminal devices 10Y1 to 10Yn are asked by the approval processing unit 28 to approve the stop work approval, the operators of the corresponding work target facility terminal devices 10Y1 to 10Yn are responsible for the communication facilities that they manage. Whether or not to approve the execution of the stop work is confirmed, the content is confirmed, the response of the blocking work is adjusted, and approval approval / disapproval information Ay / n is transmitted to the approval processing unit 28 (see A-10 in FIG. 2). When the approval processing unit 28 receives approval approval / disapproval information Ay / n from all of the corresponding work target facility terminal devices 10Y1 to 10Yn, the approval processing unit 28 outputs the approval / disapproval information Ay / n to the work plan management unit 21 (A in FIG. 2). -11). When the work plan management unit 21 receives the acceptance / rejection information Ay / n, the work plan management unit 21 determines whether or not the scheduled stop work can be performed based on the acceptance / rejection information Ay / n, and information on whether or not the stop work can be performed (permitted) : Ay, Impossible to implement: An) is transmitted to the work terminal device 10X and displayed.

すなわち、作業計画管理部21は、承認処理部28からの判別結果Ay/nに基づいて予定された停止作業の実施を決定すると、この停止作業を最終的な停止計画情報PLfとして停止のエントリーを最終的に決定する。つまり、作業計画管理部21は、この予定停止計画情報PLについて所定の時間で締め切り処理を行ってその作業計画を決定する処理を行い、停止のエントリーが決定された最終的な停止計画情報PLf(停止日時の情報Idtと停止予定設備の情報Imc−Cdfとそのポート部p00n−Cdfの情報Cdf)を作業計画データベース23に格納させて登録する(図2のA−12、図3の作業当日前工程Iおよび図7参照)。逆に、作業計画管理部21が、承認処理部28からの判別結果Ay/nに基づいて予定された停止作業PLの不実施を決定すると、その不実施の結果Anを作業担当端末装置10Xに送信して表示させるとともに、一連の処理を終了し停止作業計画PLはキャンセルされる。作業担当端末装置10Xは不実施の結果Anが送られてくると、停止作業PLについての作業計画を破棄し、作業担当のオペレータは改めて作業計画を練り直す。以上の工程(A−1〜A−12)は、作業当日前までに行われる。作業当日前までに予め該当する作業対象設備担当端末装置10Y1〜10Ynすべてから承認を受けた最終的な停止計画情報PLfが登録されると、作業当日を待つ。なお、最終的な停止計画情報PLfの登録は、作業担当者自らの保守担当域(自支社の担当域、本実施例の場合、作業担当端末装置10Xが所管する保守担当域)に属する通信設備12であろうと、他の保守担当域(他支社の担当域、本実施例の場合、作業対象設備担当端末装置10Ynが所管する保守担当域)に属する通信設備12であろうと関係なく行われる。すなわち、承認処理部28による停止作業承認要求は、停止作業対象に作業担当端末装置10Xが所管する保守担当域に属する通信設備12が含まれている場合、作業担当端末装置10Xにも停止作業承認要求が行われる。   That is, when the work plan management unit 21 decides to perform the scheduled stop work based on the determination result Ay / n from the approval processing unit 28, the work plan management unit 21 sets the stop entry as the final stop plan information PLf. Final decision. In other words, the work plan management unit 21 performs a process for determining the work plan by performing a deadline process for the scheduled stop plan information PL at a predetermined time, and final stop plan information PLf ( Stop date and time information Idt, planned stoppage facility information Imc-Cdf and its port part p00n-Cdf information Cdf) are stored and registered in the work plan database 23 (A-12 in FIG. 2, before the work day in FIG. 3) Step I and FIG. 7). Conversely, when the work plan management unit 21 determines not to execute the scheduled stop operation PL based on the determination result Ay / n from the approval processing unit 28, the non-execution result An is sent to the work terminal device 10X. While transmitting and displaying, a series of processing is complete | finished and the stop work plan PL is canceled. When the non-execution result An is sent to the work charge terminal device 10X, the work plan for the stop work PL is discarded, and the work charge operator revisits the work plan. The above steps (A-1 to A-12) are performed before the work day. When the final stop plan information PLf approved by all the work target facility terminal devices 10Y1 to 10Yn corresponding in advance is registered before the work day, the work day is awaited. It should be noted that the final stop plan information PLf is registered in the communication facility belonging to the maintenance person's own maintenance area (the maintenance area of the local branch office, in this embodiment, the maintenance area in charge of the work terminal device 10X). 12, it is performed regardless of whether the communication equipment 12 belongs to another maintenance charge area (area in charge of another branch office, in the case of this embodiment, the maintenance charge area in charge of the work target equipment charge terminal device 10Yn). That is, the stop work approval request by the approval processing unit 28 is approved for the stop work also when the communication facility 12 belonging to the maintenance charge area that the work charge terminal apparatus 10X has is included in the stop work target. A request is made.

作業当日は、作業開始の所定時間前に、すでに特定されている作業対象設備担当端末装置10Ynに当日の停止作業の承認を再度求め、承認を得る。
作業当日、当日作業計画管理部30は、作業開始の所定時間前(本実施例では、作業開始のt1分以上前)に、最終的な停止計画情報PLfが登録されてから作業当日までの間に、停止作業に対する状況の変化があったかどうかの確認を行う。すなわち、当日作業計画管理部30は、作業開始のt1分前になると、作業計画データベース23から最終的な登録済み停止計画情報PLfを取り出し(図2のB−1、図3の作業当日の作業開始前工程II参照)、作業計画データベース23より得た停止日時の情報Idtと停止予定設備の情報Imc−Cdfとその閉塞対象ポート部p00n−Cdfの情報Cdfと、当日の停止作業の通信設備を管理する作業対象設備担当端末装置10Y1〜10Ynを特定する特定情報とを当日承認処理部31に送出する。当日承認処理部31は、受け取った各情報に基づき、特定された作業対象設備担当端末装置10Y1〜10Ynに、作業当日の作業対象とすべき機器とポート部の情報Cdfと停止日時の情報Idtを送信し、当該作業対象設備担当端末装置10Y1〜10Ynが当日の停止作業実施を承認するか否かの当日承認要求を行う(図2のB−2参照)。作業対象設備担当端末装置10Y1〜10Ynは、当日承認処理部31から当日の停止作業承認の諾否を求める情報が送られてきて、該当するその当日停止作業承認の諾否を求める情報を表示すると、これら該当する作業対象設備担当端末装置10Y1〜10Ynのオペレータが、自らが所管する通信設備について、当日停止作業を承認するかどうか、内容を確認し、承認の諾否情報Afy/nを当日承認処理部31に送信する。そして、当日承認処理部31は、これら該当する作業対象設備担当端末装置10Y1〜10Ynすべてから承認の諾否情報Afy/nを受け取ると(図2のB−3参照)、この当日作業諾否情報Afy/nを当日作業計画管理部30に出力する(図2のB−4参照)。当日作業計画管理部30は、当日承認処理部31から当日作業諾否情報Afy/nを受け取ると、この諾否の判別結果Afy/nに基づいて登録された停止作業計画PLfによる当日作業実施または当日作業不実施を決定するとともに、当日停止作業実施の可否の決定(当日停止作業実施可:Afy、当日停止作業実施不可:Afn)を作業担当端末装置10Xに送信して表示させる。
On the work day, before the predetermined time before the work start, the work target facility terminal device 10Yn that has already been identified is asked again for approval of the stop work of the day, and the approval is obtained.
On the day of the work, the day-to-day work plan management unit 30 performs a period from the time when the final stop plan information PLf is registered to the work day before a predetermined time (in the present embodiment, t1 minutes or more before the work start). In addition, it is confirmed whether there has been a change in the situation due to the stop work. That is, the current day work plan management unit 30 retrieves the final registered stop plan information PLf from the work plan database 23 at t1 minutes before the work start (B-1 in FIG. 2, work on the work day in FIG. 3). The information Idt of the stop date and time obtained from the work plan database 23, the information Imc-Cdf of the scheduled stop equipment, the information Cdf of the port part p00n-Cdf to be closed, and the communication equipment for the stop work of the day The specific information for identifying the work target facility terminal devices 10Y1 to 10Yn to be managed is sent to the day approval processing unit 31. On the basis of each piece of received information, the day-of-day approval processing unit 31 sends the equipment C to be worked on on the work day, the port part information Cdf, and the stop date / time information Idt to the identified work target facility terminal devices 10Y1 to 10Yn. Then, the work target facility terminal devices 10Y1 to 10Yn make a day approval request as to whether or not to approve execution of the stop work on the day (see B-2 in FIG. 2). When the work target facility terminal devices 10Y1 to 10Yn receive information asking whether to accept the stop work approval for the day from the day approval processing unit 31, and display the information asking whether to accept the stop work approval for the day, these The operator of the corresponding work target equipment terminal devices 10Y1 to 10Yn confirms whether or not to approve the day stop work for the communication equipment he / she is in charge of, and confirms approval approval / disapproval information Afy / n on the day approval processing unit 31. Send to. Then, when the day approval processing unit 31 receives approval approval / disapproval information Afy / n from all the corresponding work target facility terminal devices 10Y1 to 10Yn (see B-3 in FIG. 2), this day work approval / disapproval information Afy / n is output to the current day work plan management unit 30 (see B-4 in FIG. 2). When the current day work plan management unit 30 receives the current day work approval / disapproval information Afy / n from the current day approval processing unit 31, the current day work plan or the current day work based on the stop work plan PLf registered based on the determination result Afy / n. In addition to deciding not to execute, the determination of whether or not to perform the current day stop work (current day stop work possible: Afy, current day stop work not possible: Afn) is transmitted to the work terminal device 10X for display.

すなわち、当日作業計画管理部30は、当日承認処理部31からの判別結果Afy/nに基づいて登録された停止計画情報PLfによる当日実施を決定すると、この停止計画情報PLfについて当日作業が開始可能である旨の通知Afyを作業担当端末装置10Xに送信して表示させる(図2のB−5参照)。他方、当日作業計画管理部30は、当日承認処理部31からの判別結果Afy/nに基づいて最終的な停止計画情報PLfによる当日不実施を決定すると、その当日不実施の結果Afnを作業担当端末装置10Xに送信して表示させるとともに、一連の処理を終了し登録された停止計画情報PLfをキャンセルする。作業担当端末装置10Xは当日不実施の結果Afnが送られてくると、予定された停止計画情報PLfによる作業計画を破棄し、作業担当のオペレータは新たに作業計画を練り直す。   That is, when the current day work plan management unit 30 determines to perform the current day using the stop plan information PLf registered based on the determination result Afy / n from the same day approval processing unit 31, the current day work plan can be started with respect to the stop plan information PLf. Is sent to the work terminal device 10X for display (see B-5 in FIG. 2). On the other hand, when the current day work plan management unit 30 determines that the current day non-execution based on the final stop plan information PLf based on the determination result Afy / n from the same day approval processing unit 31, the current day non-execution result Afn is in charge of work. While transmitting and displaying on the terminal device 10X, a series of processing is complete | finished and the stop plan information PLf registered is canceled. When the work-in-progress terminal device 10X receives Afn as a result of non-execution on the day, the work plan based on the scheduled stop plan information PLf is discarded, and the operator in charge of work re-defines the work plan.

作業対象設備担当端末装置10Ynから当日の停止作業実施の承認を得れば、回線状態を確認して閉塞制御を実行し、さらに、その閉塞制御実行後の回線状態を確認し、異常がなければ実作業を開始する。
作業担当端末装置10Xのオペレータは、当日作業計画管理部30から停止計画情報PLfによる当日作業実施が開始可能である旨の通知Afyを受け取ると、サーバ11に予定時刻をもって作業を開始する旨の通知を送信する(図2のC−1参照)。また、作業担当端末装置10Xのオペレータは、サーバ11に作業を開始する旨の通知を送信すると、次に、サーバ11に回線状態の確認を求める(図2のC−2および図3の作業当日の回線状態確認および閉塞作業工程III参照)。
If approval is received from the work target facility terminal device 10Yn for the current day's stop operation, the line status is checked and the block control is executed, and the line status after the block control is executed is checked. Start real work.
When the operator of the work terminal device 10X receives a notification Afy from the current day work plan management unit 30 that the current day work can be started based on the stop plan information PLf, the server 11 notifies the server 11 that the work starts at the scheduled time. Is transmitted (see C-1 in FIG. 2). When the operator in charge of the work terminal device 10X transmits a notification to start work to the server 11, next, the server 11 asks the server 11 to confirm the line state (C-2 in FIG. 2 and work day in FIG. 3). (See line status confirmation and blocking work process III).

当日作業計画管理部30は、作業担当端末装置10Xから回線状態の確認要求を受け取ると、回線状態確認部34に回線状態の確認が必要な機器とそのポート部の情報Cdf(停止予定設備の情報Imc−Cdfとそのポート部p00n−Cdfの情報Cdf)を送出する(図2のC−3参照)。回線状態確認部34は、この情報Cdfを受け取ると、この情報Cdfに基づいて、制御コマンド生成部33に回線状態確認用のコマンドの生成要求とそのコマンド投入の要求を行う(図2のC−4参照)。制御コマンド生成部33は、回線状態確認用のコマンドの生成要求とそのコマンド投入の要求とを受け取ると、制御コマンド文法データベース32の情報に基づいて、回線状態確認コマンドを生成し、この回線状態確認コマンドを対象となる機器Imc−Cdfとポート部p00n−Cdfに通信制御部20を介して投入する(図2のC−5参照)。   When the work plan management unit 30 receives a request for confirmation of the line state from the work-in-use terminal device 10X, the line state confirmation unit 34 receives information Cdf (information on the scheduled facility to be shut down) and a device that requires confirmation of the line state. Imc-Cdf and its port part p00n-Cdf information Cdf) are transmitted (see C-3 in FIG. 2). Upon receiving this information Cdf, the line state confirmation unit 34 makes a request to generate a command for line state confirmation and a request to input the command to the control command generation unit 33 based on this information Cdf (C- in FIG. 2). 4). When the control command generator 33 receives the request for generating the command for checking the line state and the request for inputting the command, it generates a line state check command based on the information in the control command grammar database 32, and this line state check The command is input to the target device Imc-Cdf and the port unit p00n-Cdf via the communication control unit 20 (see C-5 in FIG. 2).

通信設備12のうち、対象となる機器Imc−Cdfとポート部p00n−Cdfに回線状態確認コマンドが投入されると、対象となる機器Imc−Cdfとポート部p00n−Cdf、すなわち、作業対象となる通信設備12は、回線状態を確認し、回線状態確認コマンドの投入結果Rcnf1をサーバ11に送信する(図2のC−6参照)。回線状態確認部34は、作業対象となる通信設備12から回線状態を確認する回線状態結果Rcnf1を受け取ると、この回線状態結果Rcnf1を作業担当端末装置10Xに送信して表示させる(図2のC−7参照)。作業担当端末装置10Xのオペレータは、表示された作業対象となる通信設備12の回線状態結果Rcnf1から回線状態が確認された通信設備12について、サーバ11に閉塞制御実行の要求を行う(図2のC−8参照)。閉塞制御実行の要求は、作業対象となる通信設備12が作業担当者自らの保守担当域(自支社の担当域)に属する通信設備12であろうと、他の保守担当域(他支社の担当域)に属する通信設備12であろうと関係なく行われる。   When the line status confirmation command is input to the target device Imc-Cdf and the port unit p00n-Cdf in the communication facility 12, the target device Imc-Cdf and the port unit p00n-Cdf, that is, the work target. The communication facility 12 confirms the line state and transmits a line state confirmation command input result Rcnf1 to the server 11 (see C-6 in FIG. 2). When the line state confirmation unit 34 receives the line state result Rcnf1 for confirming the line state from the communication equipment 12 to be worked, the line state confirmation unit 34 transmits the line state result Rcnf1 to the work terminal apparatus 10X for display (C in FIG. 2). See -7). The operator of the work terminal device 10X requests the server 11 to execute block control for the communication facility 12 whose line state is confirmed from the line state result Rcnf1 of the displayed communication facility 12 to be worked (FIG. 2). C-8). The request for block control execution is that the communication equipment 12 that is the work target is the communication equipment 12 belonging to the maintenance person's own maintenance area (the responsible area of the own branch office), or the other maintenance area (the responsible area of the other branch office). ) Regardless of whether the communication equipment 12 belongs to.

当日作業計画管理部30は、作業担当端末装置10Xから閉塞制御実行の要求が送られてくると、閉塞・閉塞解除制御部35に閉塞制御を実行する対象となる機器とそのポート部の情報Cdfを送出する(図2のC−9参照)。閉塞・閉塞解除制御部35は、当日作業計画管理部30から閉塞制御の対象となる機器とそのポート部の情報Cdfを受け取ると、この情報Cdfに基づいて、制御コマンド生成部33に閉塞制御用のコマンドの生成要求とそのコマンド投入の要求を行う(図2のC−10参照)。制御コマンド生成部33は、閉塞制御用のコマンドの生成要求とそのコマンド投入の要求とを受け取ると、制御コマンド文法データベース32の情報に基づいて、閉塞制御コマンドを生成し、この閉塞制御コマンドを対象となる機器Imc−Cdfとポート部p00n−Cdfとに通信制御部20を介して投入する(図2のC−11参照)。対象となる機器Imc−Cdfとポート部p00n−Cdfとに閉塞制御コマンドが投入されると、対象となる機器Imc−Cdfとポート部p00n−Cdfは、閉塞され、閉塞制御コマンドの投入結果Rcnf2をサーバ11に送信する(図2のC−12参照)。閉塞・閉塞解除制御部35は、作業対象となる通信設備12から閉塞制御を確認する閉塞制御コマンドの投入結果Rcnf2を受け取ると、この閉塞制御コマンドの投入結果Rcnf2を作業担当端末装置10Xに送信して表示させる(図2のC−13参照)。作業担当端末装置10Xのオペレータは、表示された作業対象となる通信設備12の閉塞制御コマンドの投入結果Rcnf2から閉塞制御が実行されたかどうか確認する。   When a request for execution of blockage control is sent from the work terminal device 10X, the work plan management unit 30 on the day receives information Cdf on the device to be subjected to blockage control to the blockage / blockage release control unit 35 and its port part. (See C-9 in FIG. 2). When the block / block release control unit 35 receives the information Cdf of the device to be blocked and its port unit from the work plan management unit 30 on the day, the block / block release control unit 35 sends the block control information to the control command generation unit 33 based on the information Cdf. A command generation request and a command input request are made (see C-10 in FIG. 2). When the control command generation unit 33 receives a request for generating a command for blocking control and a request for inputting the command, the control command generating unit 33 generates a blocking control command based on the information in the control command grammar database 32, and targets this blocking control command. To the device Imc-Cdf and the port unit p00n-Cdf to be connected via the communication control unit 20 (see C-11 in FIG. 2). When the block control command is input to the target device Imc-Cdf and the port unit p00n-Cdf, the target device Imc-Cdf and the port unit p00n-Cdf are blocked, and the block control command input result Rcnf2 is obtained. The data is transmitted to the server 11 (see C-12 in FIG. 2). When receiving the blocking control command input result Rcnf2 for confirming the blocking control from the communication equipment 12 to be worked, the blocking / blocking release control unit 35 transmits the blocking control command input result Rcnf2 to the work terminal device 10X. Are displayed (see C-13 in FIG. 2). The operator of the work terminal device 10X confirms whether or not the block control has been executed from the input result Rcnf2 of the block control command of the communication equipment 12 to be displayed.

次に、作業担当端末装置10Xのオペレータは、表示された閉塞制御コマンドの投入結果Rcnf2から閉塞制御が実行されたかどうか確認すると、再度、閉塞実行後の回線状態を確認する。つまり、作業担当端末装置10Xのオペレータは、閉塞制御実行の確認後、サーバ11に回線状態の確認を求め(図2のC−14参照)、サーバ11の当日作業計画管理部30は、回線状態の確認要求を受け取ると、回線状態確認部34に閉塞制御実行後の、回線状態の確認が必要な機器とポート部の情報Cdf−off(閉塞制御実行後の設備の情報Imc−Cdf−offとポート部p00n−Cdf−offの情報Cdf−off)を送出し(図2のC−15参照)、回線状態確認部34は、回線状態の確認が必要な機器とポート部の情報Cdf−offを受け取ると、この情報Cdf−offに基づいて、制御コマンド生成部33に回線状態確認用のコマンドの生成要求とそのコマンド投入の要求を行う(図2のC−16参照)。制御コマンド生成部33は、回線状態確認部34から回線状態確認用のコマンドの生成要求とそのコマンド投入の要求とを受け取ると、制御コマンド文法データベース32の情報に基づいて、回線状態確認コマンドを生成し、この回線状態確認コマンドを対象となる機器Imc−Cdf−offとポート部p00n−Cdf−offに通信制御部20を介して投入し(図2のC−17参照)、対象となる機器Imc−Cdf−offとポート部p00n−Cdf−offとに回線状態確認コマンドが投入されると、対象となる機器Imc−Cdf−offとポート部p00n−Cdf−offは、回線状態を確認し、回線状態確認コマンドの投入結果Rcnf3をサーバ11に送信する(図2のC−18参照)。回線状態確認部34は、閉塞制御された通信設備12から回線状態を確認する回線状態結果Rcnf3を受け取ると、この回線状態結果Rcnf3を作業担当端末装置10Xに送信して表示させる(図2のC−19参照)。こうして、作業担当のオペレータは、作業担当端末装置10Xを通じて、閉塞制御実行後の回線状態を確認することができ、異常がなければ、工事作業者に実作業の許可を与える。工事作業者は作業担当のオペレータの許可により実作業を開始する。   Next, when the operator of the work terminal device 10X confirms whether or not the block control is executed from the displayed block control command input result Rcnf2, the line state after the block execution is confirmed again. That is, the operator of the work terminal device 10X asks the server 11 to confirm the line status after confirming the execution of the block control (see C-14 in FIG. 2), and the work plan management unit 30 on the day of the server 11 When the confirmation request is received, information Cdf-off (device information Imc-Cdf-off of the equipment after execution of the block control) and information on the device and the port part that need to be checked for the line state after execution of the block control are sent to the line state confirmation unit 34. Port portion p00n-Cdf-off information Cdf-off) (see C-15 in FIG. 2), and the line state confirmation unit 34 obtains information Cdf-off of the device and the port part that require confirmation of the line state. When received, based on this information Cdf-off, the control command generator 33 is requested to generate a command for confirming the line state and to input the command (see C-16 in FIG. 2). When the control command generator 33 receives a request for generating a command for line status confirmation and a request for inputting the command from the line status checker 34, the control command generator 33 generates a line status check command based on the information in the control command grammar database 32. Then, this line state confirmation command is input to the target device Imc-Cdf-off and the port unit p00n-Cdf-off via the communication control unit 20 (see C-17 in FIG. 2), and the target device Imc When a line status confirmation command is input to -Cdf-off and port part p00n-Cdf-off, the target device Imc-Cdf-off and port part p00n-Cdf-off confirm the line state and The status confirmation command input result Rcnf3 is transmitted to the server 11 (see C-18 in FIG. 2). When the line state confirmation unit 34 receives the line state result Rcnf3 for confirming the line state from the communication equipment 12 controlled to be blocked, the line state result Rcnf3 is transmitted to the work terminal device 10X for display (C in FIG. 2). -19). In this way, the operator in charge of work can check the line status after execution of the block control through the work charge terminal device 10X, and if there is no abnormality, gives the construction worker permission for actual work. The construction worker starts actual work with the permission of the operator in charge.

次に、作業担当端末装置10Xのオペレータは、実作業終了前に、作業対象設備担当端末装置10Ynに閉塞解除の事前承認を求め、実作業終了後、閉塞解除を行い、回線の復旧を確認し、停止作業を終了する。
まず、作業担当端末装置10Xのオペレータは、実作業終了の所定時間前(本実施例では、実作業終了予定t1分前)に、作業対象設備担当端末装置10Y1〜10Ynに対し閉塞中のポート部p00n−Cdf−offについて閉塞解除の事前承認を求める。つまり、上述した図2のB−2〜B−5の工程を繰り返して閉塞解除承認の諾否を求める。実作業終了予定のt1分前、作業担当のオペレータは、作業担当端末装置10Xを通じて、サーバ11に閉塞解除承認の依頼を行う(図3の作業当日の実作業中から実作業終了工程IV参照)。当日作業計画管理部30は、作業担当端末装置10Xから閉塞解除承認の諾否請求の依頼を受けると、作業計画データベース23から閉塞対象であって実作業中に閉塞制御された状態の機器Imc−Cdf−offとポート部p00n−Cdf−offとの情報Cdf−offを抽出して、当日承認処理部31に送出し、当日承認処理部31は、実作業中で、閉塞制御状態の通信設備を管理する作業対象設備担当端末装置10Y1〜10Ynを特定し、この特定情報に基づき、特定された作業対象設備担当端末装置10Y1〜10Ynに、実作業中、閉塞制御状態の機器Imc−Cdf−offと閉塞制御状態のポート部p00n−Cdf−offとの情報Cdf−offと停止日時の情報Idt(実作業終了予定時間)を送信し、当該作業対象設備担当端末装置10Y1〜10Ynが閉塞解除を承認するか否かの閉塞解除承認要求を行う(図2のB−2参照)。作業対象設備担当端末装置10Y1〜10Ynは、当日承認処理部31から閉塞解除承認の諾否を求める情報が送られてきて、該当するその閉塞解除承認の諾否を求める情報を表示すると、これら該当する作業対象設備担当端末装置10Y1〜10Ynのオペレータが、自らが所管する通信設備について、閉塞解除を承認するかどうか、内容を確認し、承認の諾否情報Afy/nを当日承認処理部31に送信する。そして、当日承認処理部31は、これら作業対象設備担当端末装置10Y1〜10Ynから承認の諾否の情報Afy/nを受け取ると(図2のB−3参照)、この当日作業諾否情報Afy/nを当日作業計画管理部30に出力し(図2のB−4参照)、当日作業計画管理部30は、当日承認処理部31から閉塞解除諾否情報Afy/nを受け取ると、この諾否の判別結果Afy/nに基づいて閉塞解除承認または不承認を決定するとともに、閉塞解除の承認または不承認の決定Afy、Afnを作業担当端末装置10Xに送信して表示させる(図2のB−5参照)。不承認の決定Afnの場合、承認が得られるまでB−2〜B−5の工程を繰り返す。
Next, the operator of the work terminal device 10X asks the work target facility charge terminal device 10Yn for prior approval of the block release before the end of the actual work, performs the block release after the end of the actual operation, and confirms the restoration of the line. Stop the stop operation.
First, the operator of the work charge terminal device 10X has a port section that is closed with respect to the work target equipment charge terminal devices 10Y1 to 10Yn a predetermined time before the end of the actual work (in this embodiment, the actual work end scheduled time t1 minutes). Pre-approval of occlusion release is requested for p00n-Cdf-off. That is, the above-described steps B-2 to B-5 in FIG. T1 minute before the actual work is scheduled to end, the operator in charge of work requests the server 11 to approve the blockage release through the work terminal device 10X (refer to the actual work end process IV from the actual work on the day of the work in FIG. 3). . Upon receiving a request for approval or disapproval of the approval for blockage release from the work terminal device 10X, the work plan management unit 30 on the day receives from the work plan database 23 the device Imc-Cdf that is the blockage target and is in the blockage control state during the actual work. -Off and port part p00n-Cdf-off information Cdf-off is extracted and sent to the day approval processor 31. The day approval processor 31 manages the communication equipment in the closed control state during actual work. The work target facility terminal devices 10Y1 to 10Yn to be identified are identified, and based on this identification information, the specified work target facility terminal devices 10Y1 to 10Yn are closed with the device Imc-Cdf-off in the closed control state during actual work. Information Cdf-off with the port part p00n-Cdf-off in the control state and stop date and time information Idt (actual work end scheduled time) are transmitted, and the work Elephant facilities charge terminal 10Y1~10Yn performs unblocking approval request whether to approve the unblocked (see B-2 of FIG. 2). When the work object facility terminal devices 10Y1 to 10Yn receive information requesting approval / disapproval of the blockage release approval from the approval processing unit 31 on the day and display the information requesting approval / disapproval of the corresponding blockage release approval, these corresponding operations are performed. The operator of the target facility terminal devices 10Y1 to 10Yn confirms whether or not to approve blockage release for the communication facility he / she is responsible for, and transmits approval approval / disapproval information Afy / n to the day approval processing unit 31. And the day approval process part 31 will receive this day work approval / disapproval information Afy / n, if the information Afy / n of approval approval / disapproval is received from these work object equipment terminal devices 10Y1-10Yn (refer to B-3 in FIG. 2). When output to the day work plan management unit 30 (see B-4 in FIG. 2), the day work plan management unit 30 receives the blockage release approval / disapproval information Afy / n from the day approval processing unit 31, and the determination result Afy of the approval / disapproval Based on / n, blockage release approval or disapproval is determined, and blockage release approval or disapproval determinations Afy and Afn are transmitted to the work terminal unit 10X for display (see B-5 in FIG. 2). In the case of non-approval decision Afn, steps B-2 to B-5 are repeated until approval is obtained.

作業担当端末装置10Xのオペレータは、当日作業計画管理部30から実作業中で、閉塞制御状態の機器Imc−Cdf−offとそのポート部p00n−Cdf−offを管理する作業対象設備担当端末装置10Y1〜10Ynすべてから承認を得た旨の通知を受け取ると、実作業終了確認後、上述した図2のC−2〜C−19の工程を繰り返して、閉塞制御状態のポート部p00n−Cdf−offに対し、回線状態確認の指令、回線状態確認後閉塞解除の指令、閉塞解除後回線状態確認の指令を順に送り、閉塞解除後回線状態を確認すると、回線復旧と見なし、作業終了通知をサーバ11の作業計画管理部21に送信し、登録された停止計画情報PLfによる実作業完了を伝える。作業計画管理部21は、作業計画データベース23に作業完了を登録して全作業を終了する。   The operator in charge of the work terminal device 10X performs the actual work from the work plan management unit 30 on the day, and the work target facility charge terminal device 10Y1 that manages the device Imc-Cdf-off in the closed control state and its port part p00n-Cdf-off. -10Yn, when the notification that the approval has been obtained is received, after confirming the end of the actual work, the above-described steps C-2 to C-19 in FIG. 2 are repeated, and the port part p00n-Cdf-off in the block control state is repeated. On the other hand, if a command for confirming the line status, a command for releasing the block after confirming the channel status, and a command for confirming the channel status after canceling the block are sent in order, and the channel status is confirmed after releasing the block, it is considered that the line has been restored, and the work end notification is sent to the server 11. To the work plan management unit 21 and informs the completion of the actual work by the registered stop plan information PLf. The work plan management unit 21 registers work completion in the work plan database 23 and finishes all work.

閉塞制御状態の通信設備Imc−Cdf−offと閉塞制御状態のポート部p00n−Cdf−offの閉塞解除は、閉塞制御と同様の手順で行われる。すなわち、作業担当端末装置10Xのオペレータは、サーバ11に回線状態の確認を求め(図2のC−2および図3の作業当日の実作業中から実作業終了工程IV参照)、回線状態結果Rcnf1を得ると(図2のC−7参照)、作業担当端末装置10Xのオペレータは、表示された閉塞解除の対象となる通信設備12の回線状態結果Rcnf1から回線状態が確認された通信設備12について、サーバ11に閉塞解除制御実行の要求を行う(図2のC−8参照)。当日作業計画管理部30は、閉塞解除制御実行の要求が送られてくると、閉塞・閉塞解除制御部35に閉塞解除制御を実行する対象となる機器とポート部の情報Cdf−offを送出し(図2のC−9参照)、閉塞・閉塞解除制御部35は、この情報Cdf−offを受け取ると、この情報Cdf−offに基づいて、制御コマンド生成部33に閉塞解除制御用のコマンドの生成要求とそのコマンド投入の要求を行い(図2のC−10参照)、制御コマンド生成部33は、これらの要求を受け取ると、制御コマンド文法データベース32の情報に基づいて、閉塞解除制御コマンドを生成し、この閉塞解除制御コマンドを対象となる機器Imc−Cdf−offとポート部p00n−Cdf−offに投入する(図2のC−11参照)。対象となる機器Imc−Cdf−offとポート部p00n−Cdf−offに閉塞解除制御コマンドが投入されると、機器Imc−Cdf−offとそのポート部p00n−Cdf−offは閉塞解除され、閉塞解除制御コマンドの投入結果Rcnf2をサーバ11に送信する(図2のC−12参照)。閉塞・閉塞解除制御部35は、閉塞解除制御コマンドの投入結果Rcnf2を受け取ると、この投入結果Rcnf2を作業担当端末装置10Xに送信して表示させ(図2のC−13参照)、作業担当端末装置10Xのオペレータは、表示された作業対象となる通信設備12の閉塞解除制御コマンドの投入結果Rcnf2から閉塞解除制御が実行されたかどうか確認する。   The block release of the communication equipment Imc-Cdf-off in the block control state and the port part p00n-Cdf-off in the block control state is performed in the same procedure as the block control. In other words, the operator of the work terminal device 10X asks the server 11 to confirm the line state (see C-2 in FIG. 2 and the actual work end process IV from the actual work on the work day in FIG. 3), and the line state result Rcnf1. (See C-7 in FIG. 2), the operator of the work terminal device 10X selects the communication equipment 12 whose line status is confirmed from the displayed line status result Rcnf1 of the communication equipment 12 to be released from the blockage. Then, the server 11 is requested to execute the block release control (see C-8 in FIG. 2). When a request for execution of blockage release control is sent, the work plan management unit 30 on the day sends information Cdf-off of the device and port unit to be subjected to blockage release control to the blockage / blockage release control unit 35. (See C-9 in FIG. 2) Upon receiving this information Cdf-off, the blocking / blocking release control unit 35 sends a command for blocking release control to the control command generation unit 33 based on this information Cdf-off. When the control command generator 33 receives these requests, the control command generator 33 sends a block release control command based on the information in the control command grammar database 32. The block release control command is generated and input to the target device Imc-Cdf-off and the port unit p00n-Cdf-off (see C-11 in FIG. 2). When the closure release control command is input to the target device Imc-Cdf-off and the port unit p00n-Cdf-off, the device Imc-Cdf-off and its port unit p00n-Cdf-off are unblocked and unblocked. The control command input result Rcnf2 is transmitted to the server 11 (see C-12 in FIG. 2). Upon receiving the closing release control command input result Rcnf2, the closing / blocking release control unit 35 transmits the input result Rcnf2 to the work terminal device 10X for display (see C-13 in FIG. 2). The operator of the device 10X confirms whether or not the block release control is executed from the input result Rcnf2 of the block release control command of the communication equipment 12 to be displayed.

次に、作業担当端末装置10Xのオペレータは、表示された閉塞解除制御コマンドの投入結果Rcnf2から閉塞制御が実行されたかどうか確認すると、再度、閉塞解除実行後の回線状態を確認する。こうして、作業担当端末装置10Xのオペレータは、回線状態を確認する回線状態結果Rcnf3を受け取ると、閉塞解除制御実行後の回線状態を確認することができ、異常がなければ、工事作業者に回線の復旧と実作業完了を知らせる。   Next, when the operator of the work terminal device 10X confirms whether or not the block control is executed from the input result Rcnf2 of the displayed block release control command, the operator confirms the line state after the block release is executed again. In this way, when the operator of the work terminal device 10X receives the line state result Rcnf3 for confirming the line state, the operator can confirm the line state after the execution of the block release control. Notify recovery and completion of actual work.

このように、上記実施例に係るネットワークの作業管理方法では、人手を介さず停止対象とすべき通信設備の候補が表示されるので、検討する時間を短縮することができ、停止対象とすべき通信設備を決定する作業が迅速化される。また、自らの保守担当域と異なる他の保守担当域で停止作業を行う際、停止作業承認の依頼と承認の通知との遣り取りをセンターサーバと端末装置とを通じて行うので、作業者側と停止作業対象設備を有する被作業者側との間の調整が自動化される。   As described above, in the network work management method according to the above-described embodiment, the candidate of the communication equipment that should be the stop target is displayed without human intervention, so that the time to consider can be shortened and should be the stop target. Work to determine communication facilities is expedited. In addition, when performing a stop operation in another maintenance area different from its own maintenance area, since the center server and the terminal device exchange the request for approval of the stop operation and the notification of the approval, the operator side and the stop operation Adjustment with the worker side having the target equipment is automated.

次に、本発明の第2の実施例に係るネットワークの作業管理システムについて説明する。本実施例に係るネットワークの作業管理システムは、前記第1の実施例に係るネットワークの作業管理システムでは、作業担当端末装置10Xのオペレータが、サーバ11に作業を開始する旨の通知を送信すると(図2のC−1参照)、サーバ11に回線状態の確認を求め(図2のC−2、C−14および図3の作業当日の回線状態確認および閉塞作業工程III参照)、サーバ11は、回線状態確認部34と制御コマンド生成部33とを通じて通信設備12から回線状態を確認する回線状態結果Rcnf1(Rcnf3)を受け取ると、この回線状態結果Rcnf1(Rcnf3)を作業担当端末装置10Xに送信して表示させるようになっているのに対し(図2のC−7、C−19参照)、本発明の第2の実施例に係るネットワークの作業管理システムでは、作業担当端末装置10Xのオペレータが、サーバ(センターサーバ)111に作業を開始する旨の通知S−prを送信すると、サーバ111は、作業計画データベース23からのデータに基づいて作業対象の通信設備112にネットワークの運用状態、すなわち、通信設備の設備運用状態、回線状態等の情報を応答するよう求め、作業対象の通信設備112から得られた情報に基づいてシステム停止の可能性を判定し、判定結果を作業開始の通知S−prを送ってきた作業担当端末装置10Xに送信して表示させるとともに、判定結果を入手した作業担当端末装置10Xのオペレータがサーバ111に設備の状態や回線の状態の確認を求めると、サーバ111はそれら設備の運用状態や回線状態の情報I−ap、I−cbを送信して表示させるようにした点が異なっている。係る構成とすることにより、判定結果に基づいて通信設備停止実行の前後のタイミングで、あるいは、通信設備停止解除実行の前後のタイミングで、リアルタイムでネットワークの健全性を監視することができ、健全性を確認した上で実作業にとりかかることができるようになっている。なお、図中、同一符号は同一または相当部分を示す。   Next, a network work management system according to a second embodiment of the present invention will be described. In the network work management system according to the first embodiment, in the network work management system according to the first embodiment, when the operator of the work terminal device 10X transmits a notification to the server 11 to start work ( 2), the server 11 is requested to confirm the line state (see C-2 and C-14 in FIG. 2 and the line state confirmation and closing work process III in FIG. 3), and the server 11 When the line state result Rcnf1 (Rcnf3) for confirming the line state is received from the communication equipment 12 through the line state confirmation unit 34 and the control command generation unit 33, the line state result Rcnf1 (Rcnf3) is transmitted to the work terminal device 10X. (See C-7 and C-19 in FIG. 2), the network configuration according to the second embodiment of the present invention is displayed. In the management system, when the operator of the work terminal device 10 </ b> X transmits a notification S-pr to start work to the server (center server) 111, the server 111 operates based on data from the work plan database 23. The communication equipment 112 is requested to respond with information such as the network operation status, that is, the equipment operation status and the line status of the communication equipment, and the possibility of system shutdown is determined based on the information obtained from the communication equipment 112 to be worked on. The determination result is transmitted to and displayed on the work terminal device 10X that has sent the work start notification S-pr, and the operator of the work terminal device 10X that has obtained the determination result causes the server 111 to When the confirmation of the line status is requested, the server 111 determines the operation status and line status information I-ap, Ic of these facilities Submit and are different points so as to display a. By adopting such a configuration, it is possible to monitor the health of the network in real time at the timing before and after the execution of the communication equipment stop based on the determination result, or at the timing before and after the execution of the communication equipment stop release. After confirming, you can start working. In the drawings, the same reference numerals indicate the same or corresponding parts.

すなわち、第1の実施例に係るネットワークの作業管理システムでは、図1および図2に示すように、センターサーバ11は運用管理系システム部11Aと監視制御系システム部11Bとを備え、監視制御系システム部11Bが、作業計画データベース23と、当日作業計画管理部30と、当日承認処理部31と、制御コマンド文法データベース32と、制御コマンド生成部33と、回線状態確認部34と、閉塞・閉塞解除制御部35とを備えて構成されるのに対し、第2の実施例に係るサーバ111は、図10および図11に示すように、運用管理系システム部11Aと監視制御系システム部111Bとを備えて構成される点が異なっている。第2の実施例に係るネットワークの作業管理システムの監視制御系システム部111Bは、作業計画データベース(データベース)23と、当日作業計画管理部(当日作業計画管理手段)130と、制御コマンド文法データベース(制御コマンド生成手段)132と、制御コマンド生成部(制御コマンド生成手段)133と、閉塞・閉塞解除制御部(停止・停止解除制御手段)135と、設備運用状態管理部(設備運用状態管理手段)140と、設備運用状態管理データベース141と、回線状態管理部(回線状態管理手段)142と、回線状態管理データベース143と、システム停止管理部(システム停止管理手段)144と、システム停止判定部(システム停止判定手段)145と、設備設定管理部(設備設定管理手段)146と、経路確認部(経路確認手段)147とを備えて構成される。通信設備112は、インターネットプロトコルを有し、サーバ111からの指令に基づいて、通信設備112の状態の情報をサーバ111に送信する通信設備状態情報送信部(通信設備状態情報送信手段)112Aを備えている。   That is, in the network work management system according to the first embodiment, as shown in FIGS. 1 and 2, the center server 11 includes an operation management system unit 11A and a monitoring control system unit 11B, and a monitoring control system. The system unit 11B includes a work plan database 23, a current day work plan management unit 30, a current day approval processing unit 31, a control command grammar database 32, a control command generation unit 33, a line state confirmation unit 34, a block / block block The server 111 according to the second embodiment, as shown in FIGS. 10 and 11, includes an operation management system unit 11A, a monitoring control system unit 111B, and a release control unit 35. It is different in that it is configured with. The monitoring control system unit 111B of the network work management system according to the second embodiment includes a work plan database (database) 23, a current day work plan management unit (current day work plan management means) 130, and a control command grammar database ( Control command generation unit) 132, control command generation unit (control command generation unit) 133, blockage / blockage release control unit (stop / stop release control unit) 135, facility operation state management unit (facility operation state management unit) 140, an equipment operation state management database 141, a line state management unit (line state management means) 142, a line state management database 143, a system stop management unit (system stop management means) 144, and a system stop determination unit (system) Stop determination means) 145, equipment setting management unit (equipment setting management means) 146, Configured with check section (route checking means) 147. The communication facility 112 includes an Internet protocol, and includes a communication facility state information transmission unit (communication facility state information transmission unit) 112A that transmits information on the state of the communication facility 112 to the server 111 based on a command from the server 111. ing.

当日作業計画管理部130は、第1の実施例の当日作業計画管理部30の構成に加え、作業担当端末装置10Xから、停止作業の当日、最終的な登録済み停止計画情報PLf(Idt,Imc)に基づいて、当該停止作業開始の所定時間t2(t2は例えば、30分、60分等)前に作業開始の通知S−prを受け取ると(図11のD−1参照)、作業計画データベース23から登録された停止計画情報PLfを取り出し、作業開始の通知情報S−prとこの停止計画情報PLfを、システム停止管理部144に出力するようになっている(図11のD−2参照)。また、当日作業計画管理部130は、作業担当端末装置10Xから設備運用状態の情報(通信設備の状態の情報)を要求する照会要求RQ1を受け取ると(図11のD−5参照)、その照会要求RQ1を停止計画情報PLfとともに設備運用状態管理部140に送出するようになっている(図11のD−6参照)。さらに当日作業計画管理部130は、作業担当端末装置10Xから回線状態の情報(通信設備の状態の情報)を要求する照会要求RQ2を受け取ると(図11のD−11参照)、その照会要求RQ2を停止計画情報PLfとともに回線状態管理部142に送出するようになっている(図11のD−12参照)。また、当日作業計画管理部130は、作業担当端末装置10Xから作業対象となる機器Imc−Cdfまたはポート部p00n−Cdfについて閉塞(停止)または閉塞解除(停止解除)を要求する指令RQ3、RQ4を受け取ると(図11のD−27参照)、この指令RQ3、RQ4を閉塞・閉塞解除制御部135に送出するようになっている(図11のD−28参照)。さらに、当日作業計画管理部130は、作業担当端末装置10Xからシステム停止判定の照会要求RQ7を受け取ると(図11のE−1参照)、作業計画データベース23から取り出された停止計画情報PLfを取り出し、システム停止判定要求の照会要求情報RQ7とをシステム停止管理部144に出力するようになっている(図11のE−2参照)。   In addition to the configuration of the current day work plan management unit 30 of the first embodiment, the current day work plan management unit 130 receives the final registered stop plan information PLf (Idt, Imc) from the work terminal device 10X on the day of the stop work. ) To receive a work start notification S-pr before a predetermined time t2 (for example, 30 minutes or 60 minutes) (see D-1 in FIG. 11). 23, the registered stop plan information PLf is taken out, and the work start notification information S-pr and the stop plan information PLf are output to the system stop management unit 144 (see D-2 in FIG. 11). . When the work plan management unit 130 receives the inquiry request RQ1 for requesting equipment operation state information (communication equipment state information) from the work terminal device 10X (see D-5 in FIG. 11), the inquiry is made. The request RQ1 is sent to the facility operation state management unit 140 together with the stop plan information PLf (see D-6 in FIG. 11). Further, on the day work plan management unit 130 receives the inquiry request RQ2 for requesting line state information (communication equipment state information) from the work terminal device 10X (see D-11 in FIG. 11), the inquiry request RQ2 Is sent to the line state management unit 142 together with the stop plan information PLf (see D-12 in FIG. 11). In addition, the work plan management unit 130 on the day sends commands RQ3 and RQ4 for requesting blockage (stop) or release (stop release) of the device Imc-Cdf or the port unit p00n-Cdf to be worked from the work terminal device 10X. When received (see D-27 in FIG. 11), the commands RQ3 and RQ4 are sent to the block / block release controller 135 (see D-28 in FIG. 11). Further, when receiving the system stop determination inquiry request RQ7 from the work terminal device 10X (see E-1 in FIG. 11), the current day work plan management unit 130 takes out the stop plan information PLf extracted from the work plan database 23. Then, the system stop determination request inquiry request information RQ7 is output to the system stop management unit 144 (see E-2 in FIG. 11).

制御コマンド生成部133は、当日作業計画管理部130から設備運用状態管理部140を通じて設備運用状態の情報を要求する照会要求RQ1が送られてくると(図11のD−7参照)、制御コマンドを生成する文法が格納された制御コマンド文法データベース132により設備運用状態の情報を要求する通信設備状態情報要求コマンドを生成し、この通信設備状態情報要求コマンドを該当する通信設備112に投入するようになっている(図11のD−8参照)。また、制御コマンド生成部133は、当日作業計画管理部130から回線状態管理部142を通じて回線状態の情報を要求する照会要求RQ2が送られてくると(図11のD−13参照)、制御コマンド文法データベース132により回線状態の情報を要求する回線状態情報要求コマンドを生成し、この回線状態情報要求コマンドを該当する通信設備112に投入するようになっている(図11のD−14参照)。さらに、制御コマンド生成部133は、作業担当端末装置10Xから設備設定管理部146を通じて作業対象の通信設備に関して設備の設定について照会要求RQ5を受け取ると(図11のD−18参照)、当該作業対象通信設備112に対して設備の設定状況を回答するよう求める設備設定状況情報要求コマンドを生成し、この設備設定状況情報要求コマンドを該当する通信設備112に投入するようになっている(図11のD−19参照)。また、制御コマンド生成部133は、作業担当端末装置10Xから経路確認部147を通じて作業対象設備を経由する始端設備情報と終端設備情報とに基づいて作業対象の通信設備に関して経路の照会要求RQ6を受け取ると(図11のD−23参照)、当該作業対象通信設備112に対して経路の状況を回答するよう求める経路情報要求コマンドを生成し、この経路情報要求コマンドを該当する通信設備112に投入するようになっている(図11のD−24参照)。さらに、制御コマンド生成部133は、閉塞・閉塞解除制御部135から作業対象通信設備112に対する閉塞要求の指令を受け取ると(図11のD−29参照)、当該作業対象通信設備112に対して閉塞制御のコマンドを生成し、この閉塞制御コマンドを該当する通信設備112に投入するようになっている(図11のD−30参照)。また、制御コマンド生成部133は、閉塞・閉塞解除制御部135から作業対象通信設備112に対する閉塞解除要求の指令を受け取ると(図11のD−29参照)、当該作業対象通信設備112に対して閉塞解除制御のコマンドを生成し、この閉塞解除制御コマンドを該当する通信設備112に投入するようになっている(図11のD−30参照)。   When the inquiry request RQ1 for requesting the equipment operation state information is sent from the work plan management unit 130 through the equipment operation state management unit 140 (see D-7 in FIG. 11), the control command generation unit 133 receives the control command. A communication equipment state information request command for requesting equipment operation state information is generated from the control command grammar database 132 in which the grammar for generating the communication equipment is stored, and the communication equipment state information request command is input to the corresponding communication equipment 112. (See D-8 in FIG. 11). When the inquiry request RQ2 for requesting line state information is sent from the work plan management unit 130 through the line state management unit 142 (see D-13 in FIG. 11), the control command generation unit 133 receives the control command. A line state information request command for requesting line state information is generated from the grammar database 132, and this line state information request command is input to the corresponding communication facility 112 (see D-14 in FIG. 11). Furthermore, when the control command generation unit 133 receives an inquiry request RQ5 regarding the setting of equipment regarding the communication equipment to be worked from the work terminal device 10X through the equipment setting management unit 146 (see D-18 in FIG. 11), the work target A facility setting status information request command for requesting the communication facility 112 to answer the facility setting status is generated, and this facility setting status information request command is input to the corresponding communication facility 112 (FIG. 11). D-19). In addition, the control command generation unit 133 receives the route inquiry request RQ6 regarding the communication equipment to be worked based on the start equipment information and the end equipment information passing through the work equipment from the work terminal device 10X through the route confirmation unit 147. (Refer to D-23 in FIG. 11), a route information request command for requesting the work target communication facility 112 to return the route status is generated, and this route information request command is input to the corresponding communication facility 112. (See D-24 in FIG. 11). Furthermore, when the control command generation unit 133 receives a command for blocking the work target communication facility 112 from the blockage / blockage release control unit 135 (see D-29 in FIG. 11), the control command generation unit 133 blocks the work target communication facility 112. A control command is generated, and this block control command is input to the corresponding communication equipment 112 (see D-30 in FIG. 11). When the control command generation unit 133 receives a command for requesting release of the work target communication facility 112 from the blockage / blockage release control unit 135 (see D-29 in FIG. 11), A block release control command is generated, and this block release control command is input to the corresponding communication equipment 112 (see D-30 in FIG. 11).

閉塞・閉塞解除制御部135は、作業担当端末装置10Xから当日作業計画管理部130を通じて作業対象となる機器Imc−Cdfまたはポート部p00n−Cdfについて閉塞(停止)を要求する指令RQ3を受け取ると(図11のD−28参照)、この指令RQ3に基づいて制御コマンド生成部133に閉塞要求コマンドを生成するように指令するとともに(図11のD−29参照)、当日作業計画管理部130を通じて閉塞解除(停止解除)を要求する指令RQ4を受け取ると(図11のD−28参照)、この指令RQ4に基づいて制御コマンド生成部133に閉塞解除要求コマンドを生成するよう指令するようになっている(図11のD−29参照)。また、閉塞・閉塞解除制御部135は、作業対象の通信設備112が制御コマンド生成部133から閉塞制御コマンドを受け取り、閉塞制御コマンドの投入結果、すなわち、閉塞実行の結果Rcnf2−cをサーバ111に返信すると(図11のD−31参照)、この閉塞実行の結果を作業担当端末装置10Xに送信して表示させるとともに、設備運用状態管理データベース141と回線状態管理データベース143とに格納させるようになっている(図11のD−32参照)。さらに、閉塞・閉塞解除制御部135は、作業対象の通信設備112が制御コマンド生成部133から閉塞解除制御コマンドを受け取り、閉塞解除制御コマンドの投入結果、すなわち、閉塞解除実行の結果Rcnf2−rをサーバ111に返信すると(図11のD−31参照)、この閉塞解除実行の結果を作業担当端末装置10Xに送信して表示させるとともに、設備運用状態管理データベース141と回線状態管理データベース143とに格納させるようになっている(図11のD−32参照)。   When the blockage / blockage release control unit 135 receives a command RQ3 for requesting blockage (stop) for the device Imc-Cdf or the port unit p00n-Cdf to be worked through the work plan management unit 130 on the same day from the work terminal device 10X ( Based on this command RQ3, the control command generator 133 is instructed to generate a block request command (see D-29 in FIG. 11), and is blocked through the work plan management unit 130 on the day. When a command RQ4 requesting release (stop release) is received (see D-28 in FIG. 11), the control command generation unit 133 is instructed to generate a closure release request command based on the command RQ4. (See D-29 in FIG. 11). Further, the block / block release control unit 135 receives the block control command from the control command generation unit 133 when the communication equipment 112 to be worked on receives the block control command input result, that is, the block execution result Rcnf2-c to the server 111. When a reply is made (see D-31 in FIG. 11), the result of this blockage execution is transmitted to the work terminal device 10X for display and stored in the facility operation state management database 141 and the line state management database 143. (See D-32 in FIG. 11). Further, the block / block release control unit 135 receives the block release control command from the control command generation unit 133 when the communication equipment 112 to be worked on receives the block release control command input result, that is, the block release execution result Rcnf2-r. When a reply is made to the server 111 (see D-31 in FIG. 11), the result of this blockage release execution is transmitted to the work terminal device 10X for display and stored in the facility operation state management database 141 and the line state management database 143. (See D-32 in FIG. 11).

設備運用状態管理部140は、作業担当端末装置10Xからの設備運用状態情報を要求する照会要求RQ1に基づいて当日作業計画管理部130を通じて作業計画データベース23から作業対象設備情報を受け取ると(図11のD−6参照)、制御コマンド生成部133に通信設備状態情報要求コマンドを生成するよう要求するようになっている(図11のD−7参照)。また、設備運用状態管理部140は、通信設備112が制御コマンド生成部133から受け取った通信設備状態情報要求コマンドに基づいて通信設備状態の情報I−apをサーバ111に送信すると、その通信設備状態の情報I−apを設備運用状態管理データベース141に書き込むとともに照会要求RQ1のあった作業担当端末装置10Xに送信して表示させるようになっている(図11のD−10参照)。   When the equipment operation state management unit 140 receives the work object facility information from the work plan database 23 through the work plan management unit 130 on the day based on the inquiry request RQ1 for requesting the equipment operation state information from the work terminal device 10X (FIG. 11). The control command generator 133 is requested to generate a communication facility state information request command (see D-7 in FIG. 11). The facility operation state management unit 140 transmits the communication facility state information I-ap to the server 111 based on the communication facility state information request command received by the communication facility 112 from the control command generation unit 133. Information I-ap is written in the equipment operation state management database 141 and transmitted to the work terminal device 10X having the inquiry request RQ1 for display (see D-10 in FIG. 11).

回線状態管理部142は、作業担当端末装置10Xからの回線状態情報を要求する照会要求RQ2に基づいて当日作業計画管理部130を通じて作業計画データベース23から作業対象回線情報を受け取ると(図11のD−12参照)、制御コマンド生成部133に回線状態情報要求コマンドを生成するよう要求するようになっている(図11のD−13参照)。また、回線状態管理部142は、通信設備112が制御コマンド生成部133から受け取った回線状態情報要求コマンドに基づいて回線状態の情報I−cbをサーバ111に送信すると、その回線状態の情報I−cbを回線状態管理データベース143に書き込むとともに照会要求RQ2のあった作業担当端末装置10Xに送信して表示させるようになっている(図11のD−16参照)。   When the line state management unit 142 receives the work target line information from the work plan database 23 through the work plan management unit 130 on the day based on the inquiry request RQ2 for requesting the line state information from the work terminal device 10X (D in FIG. 11). The control command generator 133 is requested to generate a line state information request command (see D-13 in FIG. 11). When the communication facility 112 transmits the line state information I-cb to the server 111 based on the line state information request command received from the control command generation unit 133 by the communication equipment 112, the line state information I- cb is written in the line state management database 143 and transmitted to the work terminal device 10X having the inquiry request RQ2 for display (see D-16 in FIG. 11).

ところで、第2の実施例に係るネットワークの作業管理システムでは、システム停止管理部144は、作業担当端末装置10Xから作業開始の通知情報S−prまたは照会要求RQ7を当日作業計画管理部130を通じて受け取ると、設備運用状態管理部140の設備運用状態管理データベース141と回線状態管理部142の回線状態管理データベース143とにそれぞれ設備運用状態の情報I−apと回線状態の情報I−cbとを要求し(図11のD−2、E−2参照)、設備運用状態管理データベース141と回線状態管理データベース143とからそれぞれ設備運用状態の情報I−apと回線状態の情報I−cbとを受け取ると、当日作業計画管理部130を通じて作業計画データベース23から取り出した登録済み停止計画情報PLfとこれら設備運用状態の情報I−apと回線状態の情報I−cbとをシステム停止判定部145に送出するようになっている(図11のD−3、E−3参照)。システム停止判定部145は、システム停止管理部144から停止計画情報PLfと設備運用状態の情報I−apと回線状態の情報I−cbとを受け取ると、これら停止計画情報PLfと設備運用状態の情報I−apと回線状態の情報I−cbとに基づいてネットワークのシステム停止判定を行い、その判定結果がシステム停止の可能性ありの判定結果SD−yの場合、このシステム停止の可能性ありの判定結果SD−yを作業開始通知S−prをサーバ111に送信してきた作業担当端末装置10Xに送信して音声で通報をおこなうとともに表示させるようになっている(図11のD−4参照)。システム停止判定部145は、ネットワークのシステム停止判定の結果がシステム停止の可能性なしの判定結果SD−nの場合も、この判定結果SD−nを当該作業担当端末装置10Xに送信して表示させるようになっている。   By the way, in the network work management system according to the second embodiment, the system stop management unit 144 receives the work start notification information S-pr or the inquiry request RQ7 from the work terminal device 10X through the work plan management unit 130 on the day. And the equipment operation state management database 141 of the equipment operation state management unit 140 and the line state management database 143 of the line state management unit 142 respectively request the equipment operation state information I-ap and the line state information I-cb. (Refer to D-2 and E-2 in FIG. 11), when the equipment operation state information I-ap and the line state information I-cb are received from the equipment operation state management database 141 and the line state management database 143, respectively. Registered stop plan information P extracted from the work plan database 23 through the work plan management unit 130 on the day It has f and the information I-cb information I-ap and line status of these facilities operations state to be sent to the system stop determination unit 145 (see D-3, E-3 in Figure 11). Upon receiving the stop plan information PLf, the equipment operation state information I-ap, and the line state information I-cb from the system stop management unit 144, the system stop determination unit 145 receives the stop plan information PLf and the equipment operation state information. Based on the I-ap and the line status information I-cb, a network system stoppage determination is performed, and if the determination result is a determination result SD-y that there is a possibility of system stoppage, there is a possibility of this system stoppage. The determination result SD-y is transmitted to the work-in-charge terminal device 10X that has transmitted the work start notification S-pr to the server 111 so as to be notified and displayed (see D-4 in FIG. 11). . The system stop determination unit 145 transmits the determination result SD-n to the work terminal device 10X for display even when the result of the network system stop determination is the determination result SD-n indicating that there is no possibility of system stop. It is like that.

設備設定管理部146は、作業担当端末装置10Xから作業対象設備の設備設定状態の情報を要求する照会要求RQ5が送信されてくると(図11のD−17参照)、制御コマンド生成部133に設備設定状態の情報要求コマンドを生成するよう要求するようになっている(図11のD−18参照)。また、設備設定管理部146は、通信設備112が制御コマンド生成部133から受け取った設備設定状態情報要求コマンドに基づいて設備設定状態の情報I−setをサーバ111に送信すると(図11のD−20参照)、その通信設備状態の情報I−setを照会要求RQ5のあった作業担当端末装置10Xに送信して表示させるようになっている(図11のD−21参照)。経路確認部147は、作業担当端末装置10Xから作業対象通信設備に対して始端設備情報と終端設備情報とを特定して、経路の状態を照会するよう要求する照会要求RQ6が送信されてくると(図11のD−22参照)、制御コマンド生成部133に回線の経路状態情報要求コマンドを生成するよう要求するようになっている(図11のD−23参照)。また、経路確認部147は、通信設備112が制御コマンド生成部133から受け取った経路状態情報要求コマンドに基づいて経路状態の情報I−pathをサーバ111に送信すると(図11のD−25参照)、その経路状態の情報I−pathを照会要求RQ6のあった作業担当端末装置10Xに送信して表示させるようになっている(図11のD−26参照)。   When the inquiry request RQ5 for requesting information on the equipment setting state of the work target equipment is transmitted from the work terminal device 10X (see D-17 in FIG. 11), the equipment setting management unit 146 transmits to the control command generating unit 133. A request is made to generate an information request command for equipment setting status (see D-18 in FIG. 11). In addition, the facility setting management unit 146 transmits the facility setting state information I-set to the server 111 based on the facility setting state information request command received by the communication facility 112 from the control command generating unit 133 (D- in FIG. 11). 20), the communication facility state information I-set is transmitted to the work terminal device 10X having the inquiry request RQ5 and displayed (see D-21 in FIG. 11). When the route confirmation unit 147 receives the inquiry request RQ6 for requesting to inquire about the state of the route by specifying the start-end equipment information and the end-use equipment information to the work target communication equipment from the work terminal device 10X. (See D-22 in FIG. 11), the control command generator 133 is requested to generate a line path state information request command (see D-23 in FIG. 11). Also, the route confirmation unit 147 transmits the route state information I-path to the server 111 based on the route state information request command received by the communication equipment 112 from the control command generation unit 133 (see D-25 in FIG. 11). The route state information I-path is transmitted to the work terminal device 10X having the inquiry request RQ6 and displayed (see D-26 in FIG. 11).

通信設備112の通信設備状態情報送信部112Aは、制御コマンド生成部133から閉塞制御コマンドを受け取ると(図11のD−30参照)、閉塞を実行し、閉塞制御コマンドの投入結果、すなわち、閉塞実行の結果Rcnf2−cをサーバ111に送信するようになっている(図11のD−31参照)。また、通信設備状態情報送信部112Aは、制御コマンド生成部133から閉塞解除制御コマンドを受け取ると(図11のD−30参照)、閉塞の解除を実行し、閉塞解除制御コマンドの投入結果、すなわち、閉塞解除実行の結果Rcnf2−rをサーバ111に送信するようになっている(図11のD−31参照)。さらに、通信設備状態情報送信部112Aは、制御コマンド生成部133から通信設備状態情報要求コマンドを受け取ると(図11のD−8参照)、この通信設備状態情報要求コマンドに基づいて通信設備状態の情報I−apをサーバ111に送信するようになっている(図11のD−9参照)。また、通信設備状態情報送信部112Aは、制御コマンド生成部133から回線状態情報要求コマンドを受け取ると(図11のD−14参照)、この回線状態情報要求コマンドに基づいて回線状態の情報I−cbをサーバ111に送信するようになっている(図11のD−15参照)。さらに、通信設備状態情報送信部112Aは、制御コマンド生成部133から設備設定状況情報要求コマンドを受け取ると(図11のD−19参照)、この設備設定状況情報要求コマンドに基づいて設備の設定状態の情報I−setをサーバ111に送信するようになっている(図11のD−20参照)。また、通信設備状態情報送信部112Aは、制御コマンド生成部133から経路情報要求コマンドを受け取ると(図11のD−24参照)、この経路情報要求コマンドに基づいて経路状態の情報I−pathをサーバ111に送信するようになっている(図11のD−25参照)。   Upon receiving the block control command from the control command generation unit 133 (see D-30 in FIG. 11), the communication facility state information transmission unit 112A of the communication facility 112 executes the block and performs the block control command input result, that is, the block As a result of execution, Rcnf2-c is transmitted to the server 111 (see D-31 in FIG. 11). When the communication facility state information transmission unit 112A receives the block release control command from the control command generation unit 133 (see D-30 in FIG. 11), the communication facility state information transmission unit 112A executes the block release, that is, the input result of the block release control command, The result Rcnf2-r of the block release execution is transmitted to the server 111 (see D-31 in FIG. 11). Furthermore, when the communication facility state information transmission unit 112A receives the communication facility state information request command from the control command generation unit 133 (see D-8 in FIG. 11), the communication facility state information transmission unit 112A determines the communication facility state information based on the communication facility state information request command. Information I-ap is transmitted to the server 111 (see D-9 in FIG. 11). When the communication equipment state information transmitting unit 112A receives the line state information request command from the control command generating unit 133 (see D-14 in FIG. 11), the line state information I- cb is transmitted to the server 111 (see D-15 in FIG. 11). Further, upon receiving the equipment setting status information request command from the control command generator 133 (see D-19 in FIG. 11), the communication equipment status information transmitting unit 112A receives the equipment setting status information request command based on the equipment setting status information request command. The information I-set is transmitted to the server 111 (see D-20 in FIG. 11). When the communication equipment state information transmitting unit 112A receives the route information request command from the control command generating unit 133 (see D-24 in FIG. 11), the communication facility state information transmitting unit 112A returns the route state information I-path based on the route information request command. The data is transmitted to the server 111 (see D-25 in FIG. 11).

次に、本発明の第2の実施例に係るネットワークの作業管理方法について、上記第2の実施例に係るネットワークの作業管理システムの作用に基づいて説明する。
まず、当日作業前に、作業担当者が作業担当端末装置10Xを通じて、作業対象設備担当端末装置10Yから承認を受け登録された停止計画情報PLfについて、サーバ111に予定時刻をもって作業を開始する旨の通知S−prを所定時間t2前に送信すると(図11のD−1および図12の作業当日の作業開始前工程II参照)、サーバ111の当日作業計画管理部130は作業担当端末装置10Xからの通知S−prを受け取る。当日作業計画管理部130は通知S−prを受け取ると、作業計画データベース23から登録された停止計画情報PLfを取り出し、作業開始の通知情報S−prとこの停止計画情報PLfをシステム停止管理部144に送出する。システム停止管理部144は、当日作業計画管理部130から作業開始の情報S−prおよび停止計画情報PLfを、設備運用状態管理部140の設備運用状態管理データベース141から設備運用状態の情報I−apを、回線状態管理部142の回線状態管理データベース143から回線状態の情報I−cbをそれぞれ受け取ると(図11のD−2および図12の作業当日の通信設備状態確認および閉塞作業工程III参照)、これら停止計画情報PLfと設備運用状態の情報I−apと回線状態の情報I−cbとをシステム停止判定部145に送出する(図11のD−3参照)。システム停止判定部145は、これら停止計画情報PLfと設備運用状態の情報I−apと回線状態の情報I−cbとに基づいてネットワークのシステム停止判定を行い、その判定結果がシステム停止の可能性ありの判定結果SD−yの場合、このシステム停止の判定結果SD−yを作業開始通知S−prをサーバ111に送信してきた作業担当端末装置10Xに送信して音声通報するとともに表示させる(図11のD−4参照)。判定結果がシステム停止の可能性なしの判定結果SD−nの場合も、このシステム停止の判定結果SD−nを作業開始通知S−prをサーバ111に送信してきた作業担当端末装置10Xに送信して表示させる。
Next, a network work management method according to the second embodiment of the present invention will be described based on the operation of the network work management system according to the second embodiment.
First, before the work on the day, the work person starts the work at the scheduled time in the server 111 with respect to the stop plan information PLf that has been approved and registered from the work object facility terminal apparatus 10Y through the work terminal apparatus 10X. When the notification S-pr is transmitted before a predetermined time t2 (see D-1 in FIG. 11 and the work pre-work process II on the work day in FIG. 12), the work plan management unit 130 on the day of the server 111 from the work terminal device 10X. The notification S-pr is received. Upon receipt of the notification S-pr, the work plan management unit 130 on the day extracts the stop plan information PLf registered from the work plan database 23, and obtains the work start notification information S-pr and the stop plan information PLf from the system stop management unit 144. To send. The system stop management unit 144 receives the work start information S-pr and the stop plan information PLf from the work plan management unit 130 on the day, and the facility operation state information I-ap from the facility operation state management database 141 of the facility operation state management unit 140. Are received from the line state management database 143 of the line state management unit 142 (see D-2 in FIG. 11 and the communication facility state confirmation and blocking work process III on the work day in FIG. 12). The stop plan information PLf, the equipment operation state information I-ap, and the line state information I-cb are sent to the system stop determination unit 145 (see D-3 in FIG. 11). The system stop determination unit 145 determines the system stop of the network based on the stop plan information PLf, the equipment operation state information I-ap, and the line state information I-cb, and the determination result indicates the possibility of the system stop. In the case of the determination result SD-y, the system stop determination result SD-y is transmitted to the work terminal unit 10X that has transmitted the work start notification S-pr to the server 111, and a voice notification is displayed (see FIG. 11 D-4). Even when the determination result is the determination result SD-n indicating that there is no possibility of the system being stopped, the system stop determination result SD-n is transmitted to the work terminal unit 10X that has transmitted the work start notification S-pr to the server 111. To display.

作業開始通知S−prをサーバ111に送信してこれから作業を開始しようとしている作業担当端末装置10Xのオペレータは、システム停止の可能性ありの判定結果SD−yを表示端末10Bで確認すると、システム停止の可能性がどういう理由によるものか、照会要求RQ1・RQ2、RQ5・RQ6を行い、作業対象の通信設備の設備運用状態、回線状態、設備の設定状態、始端設備−終端設備の指定に基づく経路状態を確認しつつ、停止計画情報PLfに基づく停止作業について、通信設備112に対し閉塞実行または閉塞解除実行を行うことができるようになっている。   When the operator of the work terminal device 10X who is about to start work by sending the work start notification S-pr to the server 111 confirms the determination result SD-y of the possibility of system stoppage on the display terminal 10B, the system Inquire request RQ1, RQ2, RQ5, RQ6 based on the reason of the possibility of the stoppage, based on the equipment operation state, line state, equipment setting state of the work target communication equipment, and designation of the start-end equipment-termination equipment While confirming the route state, it is possible to perform blockade execution or blockage release execution on the communication facility 112 for the stop work based on the stop plan information PLf.

すなわち、作業担当端末装置10Xのオペレータは、サーバ111からシステム停止の可能性ありの判定結果SD−yを受け取ると、設備運用状態情報を要求する照会要求RQ1をサーバ111に送信し、設備運用状態の確認を求める。サーバ111の当日作業計画管理部130は、作業担当端末装置10Xから照会要求RQ1を受け取ると(図11のD−5参照)、状態確認が必要な設備の情報を作業担当端末装置10Xに提供するため、作業計画データベース23から取り出した停止計画情報PLfを設備運用状態管理部140に送出する(図11のD−6参照)。設備運用状態管理部140は、停止計画情報PLfに基づいて制御コマンド生成部133に通信設備状態情報要求コマンドを生成して投入するよう要求し(図11のD−7参照)、制御コマンド生成部133は生成した通信設備状態情報要求コマンドを該当する通信設備112に投入する(図11のD−8参照)。通信設備112はサーバ111から通信設備状態情報要求コマンドを受け取ると、通信設備状態情報送信部112Aにより通信設備状態情報要求コマンドに基づいて通信設備状態の情報I−apをサーバ111に送信する。サーバ111が設備運用状態の情報I−apを受け取ると(図11のD−9参照)、設備運用状態管理部140は受け取った通信設備の状態の情報I−apを照会要求RQ1のあった作業担当端末装置10Xに送信して表示させるとともに設備運用状態管理データベース141に書き込む(図11のD−10参照)。このため、作業担当端末装置10Xには、通信設備状態の情報I−apが表示されるので、作業担当端末装置10Xのオペレータは、設備の運用状態からシステム停止の理由となる状況を把握し、ネットワークの健全性を確認して作業を開始することができる。   That is, when the operator in charge of the work terminal device 10X receives the determination result SD-y indicating that the system may be stopped from the server 111, the operator in charge of the work terminal device 10X transmits an inquiry request RQ1 for requesting facility operation state information to the server 111. Ask for confirmation. Upon receiving the inquiry request RQ1 from the work charge terminal device 10X (see D-5 in FIG. 11), the current day work plan management unit 130 of the server 111 provides the work charge terminal device 10X with information on the facility that requires state confirmation. Therefore, the stop plan information PLf extracted from the work plan database 23 is sent to the equipment operation state management unit 140 (see D-6 in FIG. 11). The facility operation state management unit 140 requests the control command generation unit 133 to generate and input a communication facility state information request command based on the stop plan information PLf (see D-7 in FIG. 11), and the control command generation unit 133 inputs the generated communication equipment state information request command to the corresponding communication equipment 112 (see D-8 in FIG. 11). When the communication facility 112 receives the communication facility state information request command from the server 111, the communication facility state information transmission unit 112A transmits the communication facility state information I-ap to the server 111 based on the communication facility state information request command. When the server 111 receives the equipment operation state information I-ap (see D-9 in FIG. 11), the equipment operation state management unit 140 performs the work for which the inquiry request RQ1 is received for the received communication equipment state information I-ap. The data is transmitted to the responsible terminal device 10X for display and written in the equipment operation state management database 141 (see D-10 in FIG. 11). For this reason, since the information I-ap of the communication equipment state is displayed on the work terminal apparatus 10X, the operator of the work terminal apparatus 10X grasps the situation that causes the system stop from the operation state of the equipment, You can check the health of the network and start work.

同様に、作業担当端末装置10Xにシステム停止の可能性ありの判定結果SD−yが表示されると、オペレータは、照会要求RQ2をサーバ111に送信し、回線状態の確認を求めることもできる。すなわち、作業担当端末装置10Xのオペレータは、回線状態情報を要求する照会要求RQ2をサーバ111に送信し、回線状態の確認を求める。サーバ111の当日作業計画管理部130は、作業担当端末装置10Xから照会要求RQ2を受け取ると(図11のD−11参照)、状態確認が必要な回線の情報を作業担当端末装置10Xに提供するため、作業計画データベース23から取り出した停止計画情報PLfを回線状態管理部142に送出する(図11のD−12参照)。回線状態管理部142は、停止計画情報PLfに基づいて制御コマンド生成部133に回線状態情報要求コマンドを生成して投入するよう要求し(図11のD−13参照)、制御コマンド生成部133は生成した回線状態情報要求コマンドを該当する通信設備112に投入する(図11のD−14参照)。通信設備112はサーバ111から回線状態情報要求コマンドを受け取ると、通信設備状態情報送信部112Aにより回線状態情報要求コマンドに基づいて回線状態の情報I−cbをサーバ111に送信する。サーバ111が回線状態の情報I−cbを受け取ると(図11のD−15参照)、回線状態管理部142は受け取った回線状態の情報I−cbを照会要求RQ2のあった作業担当端末装置10Xに送信して表示させるとともに回線状態管理データベース143に書き込む(図11のD−16参照)。このため、作業担当端末装置10Xには回線状態の情報I−cbが表示されるので、作業担当端末装置10Xのオペレータは、回線状態からシステム停止の理由となる状況を把握し、ネットワークの健全性を確認して作業を開始することができる。   Similarly, when the determination result SD-y indicating that the system may be stopped is displayed on the work terminal device 10X, the operator can send an inquiry request RQ2 to the server 111 to request confirmation of the line state. That is, the operator of the work terminal apparatus 10X transmits an inquiry request RQ2 for requesting line state information to the server 111 and requests confirmation of the line state. Upon receiving the inquiry request RQ2 from the work charge terminal device 10X (see D-11 in FIG. 11), the current day work plan management unit 130 of the server 111 provides the work charge terminal device 10X with information on the line that requires state confirmation. Therefore, the stop plan information PLf extracted from the work plan database 23 is sent to the line state management unit 142 (see D-12 in FIG. 11). The line state management unit 142 requests the control command generation unit 133 to generate and input a line state information request command based on the stop plan information PLf (see D-13 in FIG. 11), and the control command generation unit 133 The generated line state information request command is input to the corresponding communication facility 112 (see D-14 in FIG. 11). When the communication facility 112 receives the line state information request command from the server 111, the communication facility state information transmission unit 112A transmits line state information I-cb to the server 111 based on the line state information request command. When the server 111 receives the line state information I-cb (see D-15 in FIG. 11), the line state management unit 142 uses the received line state information I-cb to the work terminal device 10X having the inquiry request RQ2. And is displayed in the line state management database 143 (see D-16 in FIG. 11). For this reason, since the line status information I-cb is displayed on the work charge terminal device 10X, the operator of the work charge terminal device 10X grasps the situation that causes the system stop from the line status, and the soundness of the network. Confirm that you can start work.

設備運用状態管理部140の設備運用状態管理データベース141と回線状態管理部142の回線状態管理データベース143とにはそれぞれ、通信設備状態情報I−apと回線状態情報I−cbとが照会の度に格納されるので、システム停止管理部144は、登録された停止計画情報PLfに加えてリアルタイムで最新の情報を参照してシステム停止判定部145にシステムの停止判定を行わせることができ、システム停止判定の精度が向上する。   In the facility operation state management database 141 of the facility operation state management unit 140 and the line state management database 143 of the line state management unit 142, respectively, the communication facility state information I-ap and the line state information I-cb are respectively inquired. Therefore, the system stop management unit 144 can cause the system stop determination unit 145 to make a system stop determination by referring to the latest information in real time in addition to the registered stop plan information PLf. The accuracy of judgment is improved.

さらに、作業担当端末装置10Xのオペレータは、サーバ111から通信設備状態の情報I−apや回線状態の情報I−cbを受け取ると、これらの情報I−ap、I−cbに基づいて、より具体的に設備の設定状態や、作業対象設備を経由する始端設備と終端設備を抽出させて経路を確認することができるようになっている。設備の設定状態を確認する場合、作業担当端末装置10Xのオペレータは、画面端末10Bに表示された通信設備状態情報I−apや回線状態情報I−cbにより、ある設備について設定状態の確認を求める照会要求RQ5をサーバ111に送信すると(図11のD−17参照)、設備設定管理部146は、受け取った設備の情報に基づいて、制御コマンド生成部133に設備設定状態情報要求コマンドを生成するよう要求し(図11のD−18参照)、制御コマンド生成部133は生成した設備設定状態情報要求コマンドを該当する通信設備112に投入する(図11のD−19参照)。通信設備112はサーバ111から設備設定状態情報要求コマンドを受け取ると、通信設備状態情報送信部112Aにより設備設定状態情報要求コマンドに基づいて設備の設定状態の情報I−setをサーバ111に送信する。サーバ111が設定状態の情報I−setを受け取ると(図11のD−20参照)、設備設定管理部146は受け取った設備設定状態の情報I−setを照会要求RQ5のあった作業担当端末装置10Xに送信して表示させる(図11のD−21参照)。このため、作業担当端末装置10Xには設備の設定状態の情報I−setが表示されるので、作業担当端末装置10Xのオペレータは、設備の設定状態からシステム停止の理由となる状況(ネットワークの健全性)を把握することができ、それを確認して作業を開始することができる。   Furthermore, when the operator of the work terminal device 10X receives the communication equipment state information I-ap and the line state information I-cb from the server 111, the operator is more specific based on the information I-ap and I-cb. In particular, it is possible to check the path by setting the equipment setting state and extracting the start and end equipment via the work target equipment. When confirming the setting state of the equipment, the operator of the work terminal device 10X requests confirmation of the setting state of a certain equipment from the communication equipment state information I-ap and the line state information I-cb displayed on the screen terminal 10B. When the inquiry request RQ5 is transmitted to the server 111 (see D-17 in FIG. 11), the facility setting management unit 146 generates a facility setting state information request command in the control command generating unit 133 based on the received facility information. The control command generation unit 133 inputs the generated equipment setting state information request command to the corresponding communication equipment 112 (see D-19 in FIG. 11). When the communication facility 112 receives the facility setting state information request command from the server 111, the communication facility state information transmission unit 112A transmits the facility setting state information I-set to the server 111 based on the facility setting state information request command. When the server 111 receives the setting state information I-set (see D-20 in FIG. 11), the equipment setting management unit 146 receives the equipment setting state information I-set, and the work terminal device that has received the inquiry request RQ5. 10X is transmitted and displayed (see D-21 in FIG. 11). For this reason, since the equipment setting state information I-set is displayed on the work terminal apparatus 10X, the operator of the work terminal apparatus 10X may be in a situation that causes the system to stop from the equipment setting state (network health). Gender) can be grasped, work can be confirmed and started.

また、作業担当端末装置10Xのオペレータは、経路の状態を確認する場合、画面端末10Bに表示された通信設備状態情報I−apや回線状態情報I−cbにより、ある作業対象設備を経由する始端設備の情報と終端設備との情報を入力し、経路状態の確認を求める照会要求RQ6をサーバ111に送信すると(図11のD−22参照)、経路確認部147は、受け取った始端設備の情報と終端設備の情報とに基づいて、制御コマンド生成部133に経路状態情報要求コマンドを生成するよう要求し(図11のD−23参照)、制御コマンド生成部133は生成した経路状態情報要求コマンドを該当する通信設備112に投入する(図11のD−24参照)。通信設備112はサーバ111から経路状態情報要求コマンドを受け取ると、通信設備状態情報送信部112Aにより経路状態情報要求コマンドに基づいて経路の状態情報I−pathをサーバ111に送信する。サーバ111が経路の状態情報I−pathを受け取ると(図11のD−25参照)、経路確認部147は受け取った経路の状態情報I−pathを照会要求RQ6のあった作業担当端末装置10Xに送信して表示させる(図11のD−26参照)。このため、作業担当端末装置10Xには作業対象設備を経由する経路の状態情報I−pathが表示されるので、作業担当端末装置10Xのオペレータは、経路の状態からシステム停止の理由となる状況(ネットワークの健全性)を把握することができ、それを確認して作業を開始することができる。   Further, when the operator of the work terminal device 10X confirms the state of the route, the operator starts the route through a certain work target facility based on the communication facility state information I-ap and the line state information I-cb displayed on the screen terminal 10B. When the facility information and the terminal facility information are input and an inquiry request RQ6 for confirming the route state is transmitted to the server 111 (see D-22 in FIG. 11), the route confirming unit 147 receives the received information on the starting end facility. And the terminal equipment information, the control command generator 133 is requested to generate a route state information request command (see D-23 in FIG. 11), and the control command generator 133 generates the generated route state information request command. To the corresponding communication equipment 112 (see D-24 in FIG. 11). When the communication facility 112 receives the route state information request command from the server 111, the communication facility state information transmission unit 112A transmits the route state information I-path to the server 111 based on the route state information request command. When the server 111 receives the route state information I-path (see D-25 in FIG. 11), the route confirmation unit 147 sends the received route state information I-path to the work terminal device 10X having the inquiry request RQ6. Send and display (see D-26 in FIG. 11). For this reason, since the state information I-path of the route passing through the work target facility is displayed on the work terminal device 10X, the operator of the work terminal device 10X is in a situation that causes the system to stop from the state of the route ( The health of the network can be ascertained, and the work can be confirmed and started.

さらに、作業担当端末装置10Xのオペレータは、表示された各種情報I−ap、I−cb、I−set、I−pathを確認し問題がなければ、作業対象となる機器Imc−Cdfまたはポート部p00n−Cdfについて閉塞制御の実行を要求する指令RQ3をサーバ111に送信する(図11のD−27参照)。当日作業計画管理部130は作業計画データベース23から停止計画情報PLfを取り出して必要な通信設備の情報を指令RQ3の情報とともに閉塞・閉塞解除制御部135に送出する(図11のD−28参照)。閉塞・閉塞解除制御部135は、閉塞対象となる機器Imc−Cdfのポート部p00n−Cdfについて制御コマンド生成部133に対して閉塞制御のコマンドを生成して投入するよう要求し(図11のD−29参照)、制御コマンド生成部133は受け取った通信設備の情報に基づいて生成した閉塞制御コマンドを該当する通信設備112に投入する(図11のD−30参照)。閉塞制御コマンドを受け取った通信設備112は、通信設備状態情報送信部112Aが、作業対象となる機器Imc−Cdfのポート部p00n−Cdfについて閉塞を実行し、閉塞制御コマンドの投入結果、すなわち、閉塞実行の結果Rcnf2−cをサーバ111に送信する(図11のD−31参照)。サーバ111は閉塞実行の結果Rcnf2−cを受け取ると、閉塞・閉塞解除制御部135がこの閉塞実行の結果Rcnf2−cを作業担当端末装置10Xに送信して表示させるとともに、設備運用状態管理データベース141と回線状態管理データベース143とに格納させる(図11のD−32参照)。   Further, the operator of the work terminal device 10X checks the displayed various information I-ap, I-cb, I-set, and I-path, and if there is no problem, the device Imc-Cdf or the port unit that is the work target. A command RQ3 for requesting execution of blockage control for p00n-Cdf is transmitted to the server 111 (see D-27 in FIG. 11). The work plan management unit 130 on the day extracts the stop plan information PLf from the work plan database 23 and sends the necessary communication facility information to the block / block release control unit 135 together with the information of the command RQ3 (see D-28 in FIG. 11). . The blocking / blocking release control unit 135 requests the control command generating unit 133 to generate and input a blocking control command for the port unit p00n-Cdf of the device Imc-Cdf to be blocked (D in FIG. 11). The control command generation unit 133 inputs the blockage control command generated based on the received communication facility information to the corresponding communication facility 112 (see D-30 in FIG. 11). In the communication facility 112 that has received the block control command, the communication facility state information transmission unit 112A executes block for the port unit p00n-Cdf of the device Imc-Cdf to be worked, that is, the block control command input result, that is, block The execution result Rcnf2-c is transmitted to the server 111 (see D-31 in FIG. 11). When the server 111 receives the blocking execution result Rcnf2-c, the blocking / blocking release control unit 135 transmits the blocking execution result Rcnf2-c to the work terminal device 10X for display, and the equipment operation state management database 141. And the line state management database 143 (see D-32 in FIG. 11).

閉塞実行の結果Rcnf2−cが作業担当端末装置10Xに表示されると、次に、作業担当端末装置10Xのオペレータは、再び、照会要求RQ1、RQ2、RQ5、RQ6をサーバ111に送信し、上述と同様の過程(図11のD−5〜D−26参照)を経て閉塞実行後の通信設備状態情報I−apや回線状態情報I−cb、設備設定状態情報I−setや経路状態情報I−pathを確認する。通信設備閉塞実行後のこれら各種情報I−ap、I−cb、I−set、I−pathを確認し異常や問題がなければ、すなわち、実作業開始前に、閉塞実行のシミュレーションを行ってネットワークの健全性に問題がなければ、作業担当端末装置10Xのオペレータはサーバ111に対して作業開始を要求し、実作業を開始する(図12の工程IIIのSTART参照)。   When the result of the blocking execution Rcnf2-c is displayed on the work terminal device 10X, the operator of the work terminal device 10X next transmits the inquiry request RQ1, RQ2, RQ5, RQ6 to the server 111 again, and The communication equipment state information I-ap, the line state information I-cb, the equipment setting state information I-set, and the route state information I after execution of the blockade through the same process (see D-5 to D-26 in FIG. 11). -Check path. After confirming the various information I-ap, I-cb, I-set, and I-path after executing the communication facility blockage, if there is no abnormality or problem, that is, before starting the actual work, the blockage execution simulation is performed to perform the network. If there is no problem with the soundness of the work, the operator of the work terminal device 10X requests the server 111 to start work, and starts the actual work (see START in step III in FIG. 12).

実作業が終了する所定時間t1前になると、サーバ111は閉塞解除の承認を作業対象設備担当端末装置10Yから得る(第1の実施例における図3の作業当日の実作業中から実作業終了工程IVのB−1〜B−5参照、図12の作業当日の実作業中から実作業終了工程IV参照)。そして、作業担当端末装置10Xのオペレータは、実作業が終了すると(図12の工程IVのFINISH参照)、閉塞解除制御の実行を要求する指令RQ4をサーバ111に送信する(図11のD−27参照)。当日作業計画管理部130は作業計画データベース23から必要な通信設備の情報を指令RQ4の情報とともに閉塞・閉塞解除制御部135に送出する(図11のD−28参照)。閉塞・閉塞解除制御部135は、閉塞解除対象となる機器Imc−Cdfのポート部p00n−Cdfについて制御コマンド生成部133に対して閉塞解除制御のコマンドを生成して投入するよう要求し(図11のD−29参照)、制御コマンド生成部133は受け取った通信設備の情報に基づいて生成した閉塞解除制御コマンドを該当する通信設備112に投入する(図11のD−30参照)。閉塞解除制御コマンドを受け取った通信設備112は、通信設備状態情報送信部112Aが、作業対象となる機器Imc−Cdfのポート部p00n−Cdfについて閉塞解除を実行し、閉塞解除制御コマンドの投入結果、すなわち、閉塞実行の結果Rcnf2−rをサーバ111に送信する(図11のD−31参照)。サーバ111は閉塞解除実行の結果Rcnf2−rを受け取ると、閉塞・閉塞解除制御部135がこの閉塞解除実行の結果Rcnf2−rを作業担当端末装置10Xに送信して表示させるとともに、設備運用状態管理データベース141と回線状態管理データベース143とに格納させる(図11のD−32参照)。   When a predetermined time t1 before the actual work ends, the server 111 obtains the approval of the release of the closure from the work target facility terminal device 10Y (from the actual work on the day of the work in FIG. 3 in the first embodiment to the actual work end process). IV, see B-1 to B-5, see actual work end process IV from actual work on the day of work in FIG. 12). When the operator of the work charge terminal device 10X finishes the actual work (see FINISH in step IV in FIG. 12), the operator RQ4 that requests execution of the closure release control is transmitted to the server 111 (D-27 in FIG. 11). reference). The work plan management unit 130 on the day sends necessary communication equipment information from the work plan database 23 to the block / block release control unit 135 together with the information of the command RQ4 (see D-28 in FIG. 11). The blockage / blockage release control unit 135 requests the control command generation unit 133 to generate and input a blockage release control command for the port part p00n-Cdf of the device Imc-Cdf that is the blockage release target (FIG. 11). The control command generation unit 133 inputs the blockage release control command generated based on the received communication facility information to the corresponding communication facility 112 (see D-30 in FIG. 11). In the communication facility 112 that has received the block release control command, the communication facility state information transmission unit 112A executes block release for the port part p00n-Cdf of the device Imc-Cdf that is the work target, and the input result of the block release control command That is, the result Rcnf2-r of the blocking execution is transmitted to the server 111 (see D-31 in FIG. 11). When the server 111 receives the result Rcnf2-r of the blockage release execution, the blockage / blockage release control unit 135 transmits the result Rcnf2-r of the blockage release execution to the work terminal device 10X for display, and also manages the facility operation state management It is stored in the database 141 and the line state management database 143 (see D-32 in FIG. 11).

作業担当端末装置10Xのオペレータは、サーバ111の閉塞・閉塞解除制御部135から受け取り画像端末10Bに表示された閉塞解除実行の結果Rcnf2−rを確認すると、その時点でのシステムの健全性を確認するため、サーバ111にシステム停止判定の照会要求RQ7を送信する(図11のE−1参照)。サーバ111の当日作業計画管理部130は作業担当端末装置10Xからの照会要求RQ7を受け取ると、作業計画データベース23から取り出された停止計画情報PLfと、システム停止判定要求の照会要求情報RQ7とをシステム停止管理部144に送出する。システム停止管理部144は当日作業計画管理部130より照会要求の情報を受け取ると、閉塞解除実行の結果Rcnf2−rがそれぞれ格納された設備運用状態管理データベース141から現時点での設備運用状態の情報I−apを、回線状態管理データベース143から現時点での回線状態の情報I−cbとをそれぞれ受け取ると(図11のE−2参照)、これら設備運用状態の情報I−apと回線状態の情報I−cbとをシステム停止判定部145に送出する(図11のE−3参照)。システム停止判定部145は、これら現時点での設備運用状態の情報I−apと回線状態の情報I−cbとに基づいてネットワークのシステム停止判定を行い、その判定結果がシステム停止の可能性ありの判定結果SD−yの場合、このシステム停止の判定結果SD−yを照会要求RQ7をサーバ111に送信してきた作業担当端末装置10Xに送信して音声通報するとともに表示させる(図11のE−4参照)。作業担当端末装置10Xは、システム停止の可能性ありの判定結果SD−yを受け取ると、照会要求RQ1〜RQ2、RQ5〜RQ6をサーバ111に送信し、通信設備状態の情報I−apや回線状態の情報I−cb、設備の設定状態の情報I−setや作業対象設備を経由する経路の状態情報I−pathを入手することができ(図11のD−5〜D−26参照)、作業担当端末装置10Xのオペレータは、設備の設定状態からシステム停止の理由となる状況(ネットワークの健全性)を把握することができ、それを確認して停止計画に基づいた作業を終了することができる(図12のE−5参照)。   The operator of the work terminal device 10X confirms the soundness of the system at that point when confirming the result Rcnf2-r received from the blockage / blockage release control unit 135 of the server 111 and displayed on the image terminal 10B. Therefore, a system stop determination inquiry request RQ7 is transmitted to the server 111 (see E-1 in FIG. 11). When receiving the inquiry request RQ7 from the work terminal device 10X, the current day work plan management unit 130 of the server 111 receives the stop plan information PLf retrieved from the work plan database 23 and the inquiry request information RQ7 for the system stop determination request from the system. It is sent to the stop management unit 144. When the system stop management unit 144 receives the inquiry request information from the work plan management unit 130 on the day, the facility operation state information I at the present time is obtained from the facility operation state management database 141 in which the result Rcnf2-r of the closure release execution is stored. When -ap is received from the line state management database 143, the current line state information I-cb (see E-2 in FIG. 11), the equipment operation state information I-ap and the line state information I -Cb is sent to the system stop determination unit 145 (see E-3 in FIG. 11). The system stop determination unit 145 determines the system stop of the network based on the current equipment operation state information I-ap and the line state information I-cb, and the determination result may be a system stop. In the case of the determination result SD-y, this system stop determination result SD-y is transmitted to the work terminal unit 10X that has transmitted the inquiry request RQ7 to the server 111, and is displayed and displayed (E-4 in FIG. 11). reference). Upon receiving the determination result SD-y indicating that the system may be stopped, the work terminal device 10X transmits inquiry requests RQ1 to RQ2 and RQ5 to RQ6 to the server 111, and the communication equipment state information I-ap and the line state Information I-cb, equipment setting state information I-set and route state information I-path via the work target equipment can be obtained (see D-5 to D-26 in FIG. 11). The operator of the responsible terminal device 10X can grasp the situation (network health) that causes the system stop from the setting state of the equipment, and can confirm the situation and finish the work based on the stop plan. (See E-5 in FIG. 12).

このように、第2の実施例に係るネットワークの管理作業システムとその方法では、作業担当端末装置10Xのオペレータは、システム停止の可能性ありの判定結果を受け取ってもネットワークの通信設備の運用状態を把握することができるので、システム停止を避けて停止作業を実行することができる。また、システム停止の判定も通信設備の運用状態や閉塞実行または閉塞解除の情報も反映させた最新の情報に基づいて行われるので、リアルタイムの情報に基づいて判定が行われ精度が向上する。   As described above, in the network management work system and method according to the second embodiment, even if the operator of the work terminal device 10X receives the determination result indicating that the system may be stopped, the operation state of the communication equipment on the network Therefore, the stop operation can be executed while avoiding the system stop. Further, since the determination of the system stop is performed based on the latest information reflecting the operation state of the communication equipment and the information on the execution or the release of the blockage, the determination is performed based on the real-time information and the accuracy is improved.

なお、上記実施例では、作業対象となる通信設備12の閉塞制御および閉塞解除制御を機器Imcとポート部p00nについて行うようにしているが、これに限られるものではなく、機器Imc(ルータ、スイッチ、伝送装置等のIP機器)自体を停止または停止解除するようにしてもよいし、機器Imcと他の機器のポート部p00nとの両者を停止または停止解除するようにしてもよいことはいうまでもない。また、作業対象設備担当端末装置抽出手段が、作業担当端末装置10Xにより作業対象候補の中から選択された機器またはポート部の選択結果に基づいて、作業対象設備担当端末装置10Yを抽出するようにしているがこれに限られるものではなく、作業計画管理部21に作業担当端末装置10Xから停止計画PLが入力されると、この停止計画PLに基づいて、構成管理データベース22から停止計画PLに含まれる停止予定設備を保守担当域に有する作業対象設備担当端末装置10Yを抽出するようにしてもよい。この場合、停止計画PLのうち、当該作業対象設備担当端末装置10Yに関する情報も添付して送信するようにしてもよい。さらに、物理網・論理網・局内構成図描画部24は、物理網構成図、論理網構成図および局内構成図を描画処理するようにしているが、これに限られるものではなく、物理網構成図、論理網構成図および局内構成図のうち少なくともいずれか1を描画処理するようにしてもよい。また、上記実施例では、作業担当端末装置10Xを所定の保守担当域を所管する端末装置としているが、これに限られるものではなく、保守担当域を有していない端末装置であってもよいことはいうまでもない。さらに、上記実施例では、オペレータが、ポート部の候補に対してマニュアルで閉塞順序を選択することができるようにしているがこれに限られるものではなく、階層の位に応じて、閉塞候補の閉塞順序を決定する閉塞順位決定手段を設けるようにしてもよい。また、上記実施例のネットワークは、通信ネットワークについて述べているが、これに限られるものではなく、ネットワーク一般について適用可能であることはいうまでもない。
さらに、上記第2の実施例では、データベース141、143に格納された設備の状態情報I−apと回線の状態情報I−cbとの両方の情報に基づいてシステム停止の有無を判定するようにしているがこれに限られるものではなく、これら情報I−ap、I−cbのうち少なくともいずれか一方に基づいてシステム停止の有無を判定するようにしてもよい。
In the above embodiment, the block control and block release control of the communication equipment 12 to be worked are performed on the device Imc and the port part p00n. However, the present invention is not limited to this, and the device Imc (router, switch It goes without saying that the IP device such as the transmission device) itself may be stopped or released, or both the device Imc and the port part p00n of the other device may be stopped or released. Nor. In addition, the work target facility terminal device 10Y extracts the work target facility terminal device 10Y based on the selection result of the device or port part selected from the work target candidates by the work terminal device 10X. However, the present invention is not limited to this. When the stop plan PL is input from the work terminal device 10X to the work plan management unit 21, it is included in the stop plan PL from the configuration management database 22 based on the stop plan PL. It is also possible to extract the work object facility terminal device 10Y having the scheduled stop facility in the maintenance charge area. In this case, in the stop plan PL, information related to the work target facility terminal device 10Y may be attached and transmitted. Further, the physical network / logical network / intra-station configuration diagram drawing unit 24 performs a drawing process on the physical network configuration diagram, the logical network configuration diagram, and the intra-station configuration diagram, but the present invention is not limited to this. At least one of the diagram, the logical network configuration diagram, and the intra-station configuration diagram may be rendered. In the above embodiment, the work terminal device 10X is a terminal device that has jurisdiction over a predetermined maintenance area. However, the present invention is not limited to this, and a terminal apparatus that does not have a maintenance area may be used. Needless to say. Furthermore, in the above-described embodiment, the operator can manually select the blocking order for the port part candidates. However, the present invention is not limited to this. You may make it provide the obstruction | occlusion order determination means which determines the obstruction | occlusion order. Moreover, although the network of the said Example has described the communication network, it is not restricted to this, It cannot be overemphasized that it is applicable about the network in general.
Further, in the second embodiment, the presence or absence of the system stop is determined based on both the equipment state information I-ap and the line state information I-cb stored in the databases 141 and 143. However, the present invention is not limited to this, and the presence or absence of a system stop may be determined based on at least one of the information I-ap and I-cb.

上記実施例では、通信ネットワーク機器の閉塞作業や作業管理について述べているが、これに限られるものではなく、一般のネットワーク機器の閉塞作業や作業管理についても適用できる。   In the above embodiment, the communication network device blocking work and work management are described. However, the present invention is not limited to this, and can be applied to general network device blocking work and work management.

10(10X、10Y) 端末装置
10X 作業担当端末装置
22、23、141、143 データベース
111 サーバ(センターサーバ)
112 通信設備
PL 作業計画
PLf 最終的な作業計画
S−pr 作業開始の通知
I−ap、I−cb 通信設備の運用状態の情報
SD−y システム停止判定結果
10 (10X, 10Y) terminal device 10X work charge terminal device 22, 23, 141, 143 database 111 server (center server)
112 Communication equipment PL Work plan PLf Final work plan S-pr Work start notification I-ap, I-cb Communication equipment operation state information SD-y System stop judgment result

Claims (20)

データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、
停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、
通信設備を、センターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、
センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させることを特徴とするネットワークの作業管理システム。
A center server that manages and operates the lines of the entire network based on communication facility information stored in the database, and a terminal that manages the network lines of each maintenance area by connecting to the center server so that work information can be exchanged through communication With the device,
When a work plan including information on the work date and time and work equipment planned in advance by the work terminal device in charge of the stop work is transmitted to the center server, the stop information on the work target communication equipment before the center server starts the stop work Is configured to cancel the setting of the stop information when a work end notification is transmitted from the work terminal device to the center server after the actual work ends,
The communication equipment is configured so that information about the operation status of the communication equipment can be exchanged through communication with the center server.
When a notification of the start of work is sent to the center server from the work terminal device, the center server obtains information on the operation status of the communication equipment from the communication equipment of the work target, and When information about the operational status of the communication equipment is sent from the target equipment to the center server, the information is stored in the database, and the center server stores information on the operational status of the communication equipment stored in the database. A network work management system characterized by determining whether or not there is a system stop and transmitting and displaying the result of the system stop determination to the work terminal device.
センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、
作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、
これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定することを特徴とする請求項1に記載のネットワークの作業管理システム。
When the center server receives a request for inquiry about the state of the equipment related to the work target communication equipment from the work terminal device, the center server asks the work target communication equipment to return the state of the equipment and receives it from the work target communication equipment. The response about the status of the installed equipment is sent to the work terminal device that requested the inquiry and displayed, and the information about the equipment and the answer about the status of the equipment are stored in the database.
When there is a request for inquiry about the line status of the communication equipment to be worked from the terminal device in charge of work, the state of the line received from the work target communication equipment is requested to return the line status to the work target communication equipment. Send the response to the work terminal device that requested the inquiry and display it, and store the information about the line and the answer about the line status in the database,
2. The network work management system according to claim 1, wherein whether or not the system is stopped is determined based on at least one of facility status information and line status information stored in the database.
センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の設定状態について照会の要求があると、当該作業対象通信設備に対して設備の設定状態を回答するよう求め、当該作業対象通信設備から受け取った設備の設定状態についての回答を照会要求のあった作業担当端末装置に送信して表示させ、
作業担当端末装置から作業対象の通信設備に関し作業対象設備を経由する経路について照会の要求があると、作業担当端末装置から提供された始端設備情報と終端設備情報とに基づいて、当該作業対象通信設備に対して経路の状態を回答するよう求め、当該作業対象通信設備から受け取った経路の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させることを特徴とする請求項1または2に記載のネットワークの作業管理システム。
When there is a request for inquiry about the setting state of the equipment related to the work target communication equipment from the work terminal device, the center server requests the work target communication equipment to return the equipment setting state, and the work target communication equipment Send the response about the setting status of the equipment received from the work terminal device that requested the inquiry to display it,
When there is a request for inquiry about the route through the work target equipment regarding the communication equipment to be worked from the work charge terminal device, the work target communication is performed based on the start equipment information and the end equipment information provided from the work work terminal device. Claiming the equipment to answer the status of the route, and sending the answer about the status of the route received from the work object communication equipment to the work-in-charge terminal device that requested the inquiry, and displaying it. The network work management system according to 1 or 2.
センターサーバに作業計画が入力されると、データベースに格納された通信設備の情報に基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補を抽出し、抽出された候補を作業を担当する作業担当端末装置に表示させ、作業担当端末装置により表示された候補から作業対象設備が選択されると、この選択情報をセンターサーバに送信し、センターサーバは、この選択された情報に基づいて最終的な作業計画を決定し、その決定された最終的な作業計画を作業担当端末装置に送信して表示させることを特徴とする請求項1ないし3のうちいずれか1に記載のネットワークの作業管理システム。   When the work plan is input to the center server, based on the information on the communication equipment stored in the database, extract at least one candidate of the equipment related to the line of the work target equipment or the port portion of the equipment, When the extracted candidate is displayed on the work charge terminal device in charge of work, and the work target facility is selected from the candidates displayed by the work charge terminal device, this selection information is transmitted to the center server. 4. The final work plan is determined based on the selected information, and the determined final work plan is transmitted to the work terminal unit for display. The work management system for a network according to claim 1. センターサーバに作業日時と作業設備との情報が入力されると、データベースに格納された通信設備の情報に基づいて、停止予定設備の回線に関連する機器を自らの保守担当域に有し当該作業対象通信設備を管理する端末装置を作業対象設備担当端末装置として抽出し、抽出された作業対象設備担当端末装置に予定された作業日時と作業設備との情報を送信し、
当該作業対象設備担当端末装置が、予定された作業日時と作業設備との情報を受け取ると、この情報に基づいて、停止予定または停止解除予定の通信設備について予定された作業を承認するか否かの判別を行い、その判別結果をセンターサーバに送信し、
センターサーバは、作業対象設備担当端末装置から作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とする請求項4に記載のネットワークの作業管理システム。
When information on the work date and time and work equipment is input to the center server, based on the information on the communication equipment stored in the database, the equipment related to the line of the equipment to be shut down is in its maintenance area and the work concerned The terminal device that manages the target communication facility is extracted as the work target facility charge terminal device, and the scheduled work date and time and work facility information are transmitted to the extracted work target facility charge terminal device,
When the work target facility terminal device receives information on the scheduled work date and time and the work facility, whether or not to approve the scheduled work for the communication facility scheduled to be stopped or released based on this information And send the result to the center server.
When the center server receives the result of the acceptance / rejection of the work from the work target facility terminal device, the center server determines whether or not to perform the scheduled work based on the determination result, and determines whether or not the work can be performed. The network work management system according to claim 4, wherein the network work management system is transmitted to and displayed.
作業担当端末装置は、表示された作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補に対し、オペレータにより作業対象とすべき機器または機器のポート部のうち少なくともいずれか1が選択されると、その選択結果をセンターサーバに送信し、
センターサーバは、作業担当端末装置から選択結果を受け取ると、この選択結果に基づいて、選択された機器または機器のポート部を作業対象として決定し、この作業対象として決定された機器または機器のポート部を自らの保守担当域に有する作業対象設備担当端末装置を抽出し、抽出された作業対象設備担当端末装置に作業日時の情報とともに作業対象として決定された機器または機器のポート部の情報を送信し、
当該作業対象設備担当端末装置が、作業日時の情報と作業対象として決定された機器または機器のポート部の情報とを受け取ると、これら情報を表示して予定された作業を承認するか否かの入力を求め、オペレータにより入力が行われるとその入力結果をセンターサーバに送信し、
センターサーバは、作業対象設備担当端末装置から作業実施について諾否の入力結果を受け取ると、この入力結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とする請求項5に記載のネットワークの作業管理システム。
The work-in-use terminal device has at least one of the device or the port portion of the device to be worked by the operator with respect to at least one candidate of the device or the device port portion related to the displayed line of the work target facility. When any one is selected, the selection result is sent to the center server,
When the center server receives the selection result from the terminal in charge of work, based on the selection result, the center server determines the selected device or the port portion of the device as a work target, and the device or device port determined as the work target. The equipment in charge of the work target equipment that has the department in its maintenance area is extracted, and the information on the device or the port part of the equipment determined as the work target is sent to the extracted work target equipment charge terminal device together with the work date and time information And
When the work target facility terminal device receives information on the work date and time and information on the device or the port part of the device determined as the work target, whether or not to approve the scheduled work by displaying these information When input is requested by the operator, the input result is sent to the center server,
When the center server receives an input result indicating whether or not to accept the work execution from the work target facility terminal device, the center server determines whether or not the scheduled work execution is possible based on the input result, and determines whether or not the work execution is possible. The network work management system according to claim 5, wherein the network work management system is transmitted to an apparatus for display.
作業計画が予め計画された停止日時と停止設備との情報を含む停止計画であり、この停止計画に対し、停止作業開始前に、実施が決定された停止作業を最終的な停止計画としてデータベースに登録することを特徴とする請求項6に記載のネットワークの作業管理システム。   The work plan is a stop plan that includes information about the planned stop date and time and the stop equipment. For this stop plan, the stop work that has been decided to be implemented before the start of the stop work is stored in the database as the final stop plan. The network work management system according to claim 6, wherein registration is performed. データベースには、停止作業日前に最終的な停止計画を登録するとともに、
センターサーバは、停止作業日の作業開始前に、登録された最終的な停止計画を、停止作業を承認する判別結果を送信した作業対象設備担当端末装置に送信し、
作業対象設備担当端末装置は、センターサーバから登録された最終的な停止計画を受け取ると、登録された停止作業を当日作業として承認するか否かの入力を求め、入力が行われるとその入力結果をセンターサーバに送信し、
センターサーバは、作業対象設備担当端末装置から当日の停止作業について諾否の入力結果を受け取ると、この入力結果に基づいて登録された最終的な停止計画実施について開始の可否を作業担当端末装置に送信して表示させることを特徴とする請求項7に記載のネットワークの作業管理システム。
In the database, the final outage plan is registered before the outage date,
The center server sends the registered final stop plan before the start of work on the stop work day, to the work target facility terminal device that sent the determination result for approving the stop work,
Upon receiving the final stop plan registered from the center server, the work target facility terminal device asks for an input as to whether or not to approve the registered stop work as a work on the day, and when the input is performed, the input result To the center server,
When the center server receives an input result indicating acceptance or disapproval for the current day's stop operation from the work target facility terminal device, the center server transmits to the work terminal device whether or not to start the final stop plan registered based on the input result. The network work management system according to claim 7, wherein the network work management system is displayed.
データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、
停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するよう構成されるとともに、
通信設備は、インターネットプロトコルを有し、センターサーバからの指令に基づいて、通信設備の状態の情報をセンターサーバに送信する通信設備状態情報送信手段を備え、
データベースは、センターサーバにより設定され作業日時と作業設備の情報を含む停止作業計画の情報を格納して構成される作業計画データベースと、
作業対象の通信設備から通信設備の設備運用状態の情報が送られてくると、その設備運用状態の情報を格納して構成される設備運用状態管理データベースと、
作業対象の通信設備から通信設備の回線状態の情報が送られてくると、その回線状態の情報を格納して構成される回線状態管理データベースとを備え、
センターサーバは、停止作業の当日、作業担当端末装置から当該停止作業開始の所定時間前に作業開始の通知を受け取ると、作業計画データベースから設定された停止計画情報を取り出し、作業開始情報とこの停止計画情報を外部に出力する当日作業計画管理手段と、
当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し設備運用状況の確認を要求し、当該作業対象設備から設備運用状況の回答を得ると、設備運用状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる設備運用状態管理手段と、
当日作業計画管理手段から停止計画情報を受け取ると、当該作業対象設備の情報に基づいて当該作業対象設備に対し回線状況の確認を要求し、当該作業対象設備から回線状況の回答を得ると、回線状態管理データベースにその情報を格納するとともに作業担当端末装置に送信して表示させる回線状態管理手段と、
当日作業計画管理手段から作業開始情報を受け取ると、設備運用状態管理データベースと回線状態管理データベースとから設備運用状態の情報と回線運用状態の情報とを求め、これら設備運用状態の情報と回線運用状態の情報とを外部に出力するシステム停止管理手段と、
システム停止管理手段から設備運用状態の情報と回線運用状態の情報とのうち少なくともいずれか一方を受け取ると、当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるシステム停止判定手段とを備え、
当日作業計画管理手段は、作業担当端末装置から作業開始の通知を受け取ると、設備運用状態管理手段と回線状態管理手段とにより当該作業対象の設備から設備運用状態の情報と回線運用状態の情報とを設備運用状態管理データベースと回線状態管理データベースとにそれぞれ格納させ、システム停止管理手段がシステム停止判定手段にこれら格納された設備運用状態の情報と回線運用状態の情報とを送出すると、システム停止判定手段が当該停止作業によりネットワークのシステム停止があるか否かの判定を行い、このシステム停止判定の結果を作業担当端末装置に送信して表示させるとともに、
当日作業計画管理手段は、作業担当端末装置からの求めに応じて設備運用状態管理手段を通じて設備運用状態の情報を、回線状態管理手段を通じて回線運用状態の情報をそれぞれ作業担当端末装置に送信して表示させることを特徴とするネットワークの作業管理システム。
A center server that manages and operates the lines of the entire network based on communication facility information stored in the database, and a terminal that manages the network lines of each maintenance area by connecting to the center server so that work information can be exchanged through communication With the device,
When a work plan including information on the work date and time and work equipment planned in advance by the work terminal device in charge of the stop work is transmitted to the center server, the stop information on the work target communication equipment before the center server starts the stop work Is configured to cancel the setting of the stop information when a work end notification is transmitted from the work terminal device to the center server after the actual work ends,
The communication facility has an Internet protocol, and includes communication facility state information transmission means for transmitting information on the state of the communication facility to the center server based on a command from the center server.
The database is a work plan database configured by storing information on a stop work plan that is set by the center server and includes work date and time and work equipment information,
When the equipment operation state information of the communication equipment is sent from the work target communication equipment, the equipment operation state management database configured to store the equipment operation state information,
When the line status information of the communication equipment is sent from the communication equipment to be worked on, the line status management database configured to store the line status information is provided,
When the center server receives a work start notification from the work terminal device on the day of the stop work, the stop plan information set from the work plan database is extracted, and the work start information and the stop On-day work plan management means for outputting plan information to the outside,
When stop plan information is received from the work plan management means on the day, a request for confirmation of the equipment operation status is made to the work target equipment based on the information on the work target equipment, and an answer to the equipment operation status is obtained from the work target equipment. The facility operation state management means for storing the information in the facility operation state management database and transmitting and displaying the information to the work terminal device;
When the stop plan information is received from the work plan management means on the day, the work target equipment is requested to confirm the line status based on the information on the work target equipment, and when the line status answer is obtained from the work target equipment, Line status management means for storing the information in the status management database and transmitting and displaying the information to the work terminal device;
When the work start information is received from the work plan management means on the day, the equipment operation state information and the line operation state information are obtained from the equipment operation state management database and the line state management database, and the equipment operation state information and the line operation state are obtained. System stop management means for outputting the information on the outside,
When at least one of facility operation status information and line operation status information is received from the system stop management means, it is determined whether or not there is a system stop of the network due to the stop operation, and this system stop determination System stop determination means for transmitting and displaying the result to the work terminal device,
When the work plan management means receives work start notification from the terminal device in charge of the day, the equipment operation state management means and the line state management means perform the facility operation state information and the line operation state information from the work target equipment. Are stored in the equipment operation state management database and the line state management database, respectively, and when the system stop management means sends the stored equipment operation state information and line operation state information to the system stop judgment means, the system stop judgment is performed. The means determines whether there is a system stop of the network due to the stop work, and transmits and displays the result of the system stop determination to the work terminal device,
The work plan management means on the day sends the equipment operation state information through the equipment operation state management means and the line operation state information through the line state management means to the work terminal device in response to a request from the work terminal device. A network work management system characterized by display.
センターサーバは、作業担当端末装置から作業対象の通信設備に関して設備の設定について照会要求があると、当該作業対象通信設備に対して設備の設定状況を回答するよう求め、当該作業対象通信設備から受け取った回答を照会要求のあった作業担当端末装置に送信して表示させる設備設定管理手段と、
作業担当端末装置から作業対象設備を経由する始端設備情報と終端設備情報とに基づいて作業対象の通信設備に関して経路の照会要求があると、当該作業対象通信設備に対して経路の状況を回答するよう求め、当該作業対象通信設備から受け取った回答を照会要求のあった作業担当端末装置に送信して表示させる経路確認手段とを備えていることを特徴とする請求項9に記載のネットワークの作業管理システム。
When the center server receives an inquiry request for setting of equipment related to the communication equipment to be worked from the terminal device in charge of work, the center server asks the work communication equipment to return the setting status of the equipment and receives it from the work communication equipment. Equipment setting management means for sending and displaying the response to the terminal device in charge of the inquiry request,
When there is a route inquiry request for the communication equipment to be worked based on the start equipment information and the terminal equipment information that passes through the work equipment from the work terminal device, the status of the route is returned to the work equipment to be worked. The network operation according to claim 9, further comprising: route confirmation means for transmitting and displaying the response received from the work target communication equipment to the work-in-charge terminal device that requested the inquiry. Management system.
センターサーバは、制御コマンドを生成する文法が格納された制御コマンド文法データベースと、外部から入力される指令に基づいて制御コマンド文法データベースにより通信設備の状態の情報を要求する通信設備状態情報要求コマンドを生成し、この通信設備状態情報要求コマンドを該当する通信設備に送信する制御コマンド生成手段とを備え、
センターサーバは、作業担当端末装置から設備の運用状態を確認するよう求める照会要求を受け取ると、当日作業計画管理手段から作業計画データベースにより得られた当該設備の情報に基づいて設備運用状態管理手段を通じて制御コマンド生成手段に当該設備の運用状態情報を回答するよう当該設備に求めるコマンドを生成するよう要求し、制御コマンド生成手段は制御コマンド文法データベースに格納された制御コマンドを生成する文法に基づいて当該設備の運用状態を確認して回答するよう求めるコマンドを生成し、このコマンドを対象となる当該設備に投入し、当該対象設備がこのコマンドに対する回答結果をセンターサーバに送出すると、設備運用状態管理手段はこの回答結果を設備運用状態管理データベースに格納するとともに、照会要求のあった作業担当端末装置に送信して表示させ、
作業担当端末装置から回線状態を確認するよう求める照会要求を受け取ると、当日作業計画管理手段から作業計画データベースにより得られた当該回線の情報に基づいて回線状態管理手段を通じて制御コマンド生成手段に当該回線の状態情報を回答するよう対象となる設備に求めるコマンドを生成するよう要求し、制御コマンド生成手段は制御コマンド文法データベースに格納された制御コマンドを生成する文法に基づいて当該回線の状態を確認して回答するよう求めるコマンドを生成し、このコマンドを対象となる当該設備に投入し、当該対象設備がこのコマンドに対する回答結果をセンターサーバに送出すると、回線状態管理手段はこの回答結果を回線状態管理データベースに格納するとともに、照会要求のあった作業担当端末装置に送信して表示させることを特徴とする請求項9または10に記載の通信ネットワークの作業管理システム。
The center server has a control command grammar database storing a grammar for generating a control command, and a communication facility state information request command for requesting communication facility state information from the control command grammar database based on a command input from the outside. Control command generating means for generating and transmitting this communication equipment state information request command to the corresponding communication equipment,
When the center server receives an inquiry request for confirming the operation state of the equipment from the work terminal device, the center server passes the equipment operation state management means based on the information on the equipment obtained from the work plan database on the day from the work plan management means. Requesting the control command generation means to generate a command to be requested to the equipment so as to reply the operation status information of the equipment, the control command generation means is based on the grammar for generating the control command stored in the control command grammar database. When a command for checking and replying to the operation status of the equipment is generated, the command is input to the target equipment, and the target equipment sends a response result to the command to the center server. Stores this answer result in the equipment operation state management database and And transmitted to the working charge terminal device for which the inquiry request is displayed,
When an inquiry request for confirming the line state is received from the terminal in charge of work, the line is sent to the control command generation unit through the line state management unit based on the information on the line obtained from the work plan database from the work plan management unit on the day. Requesting the target equipment to respond to the status information of the target, and the control command generation means confirms the status of the line based on the grammar for generating the control command stored in the control command grammar database. When the target equipment sends the response result to this command to the center server, the line status management means sends the response result to the line status management. Store it in the database and send it to the work terminal that requested the inquiry. Communication network work management system according to claim 9 or 10, characterized in that to to view.
データベースには、網構成および局内構成を含む物理回線構成情報と機器および機器内の部位情報を含む装置構成情報と論理回線名および論理回線構成を含む論理回線構成情報とが格納されるよう構成され、
センターサーバは、作業担当端末装置から設備の停止または停止解除の作業計画が入力されるとこの作業計画を外部に出力し、作業担当端末装置から作業計画の作業対象設備について選択情報が入力されるとこの選択情報に基づいて作業計画を決定する作業計画管理手段と、
作業計画管理手段から作業対象設備の情報を受け取ると、受け取った作業対象設備の情報に基づき、データベースから物理回線構成情報と装置構成情報と論理回線構成情報とを抽出して物理網構成図、論理網構成図および局内構成図のうち少なくともいずれか1を描画処理し、これらを作業担当端末装置に送信して表示させるとともに、抽出された各構成情報と上記作業対象設備の情報とを外部に出力する物理網・論理網・局内構成図描画処理手段と、
物理網・論理網・局内構成図描画処理手段から受け取った各構成情報と作業対象設備の情報とに基づいて、作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1についての候補を抽出し、抽出された候補情報を物理網・論理網・局内構成図描画処理手段に出力する作業対象候補抽出手段とを備え、
物理網・論理網・局内構成図描画処理手段は、作業対象候補抽出手段から抽出された候補情報を受け取ると、この候補情報に基づいて、作業担当端末装置に表示される描画処理された各構成図上に候補情報を含ませるとともに、作業担当端末装置は表示された候補情報から作業対象設備が選択されると、選択情報を作業計画管理手段に送信し、作業計画管理手段は選択情報に基づいて最終的な作業計画を決定することを特徴とする請求項11に記載のネットワークの作業管理システム。
The database is configured to store physical line configuration information including network configuration and intra-station configuration, device configuration information including device and part information within the device, and logical line configuration information including logical line name and logical line configuration. ,
The center server outputs the work plan to the outside when a work plan for stopping or canceling the equipment is input from the work terminal device, and selection information is input about the work target equipment of the work plan from the work terminal device. And a work plan management means for determining a work plan based on the selected information,
When the information on the work target facility is received from the work plan management means, the physical line configuration information, the device configuration information, and the logical line configuration information are extracted from the database based on the received work target facility information, and the physical network configuration diagram, logical At least one of the network configuration diagram and the in-station configuration diagram is drawn, transmitted to the work terminal device for display, and the extracted configuration information and information on the work target equipment are output to the outside. Physical network / logical network / intra-station configuration diagram drawing processing means,
Based on each configuration information received from the physical network / logical network / intra-station configuration diagram drawing processing means and information on the work target equipment, at least one of the equipment related to the line of the work target equipment or the port portion of the equipment A candidate for operation target extracting means for extracting the candidate information and outputting the extracted candidate information to the physical network / logical network / intra-station configuration diagram drawing processing means,
When the physical network / logical network / intra-station configuration diagram drawing processing means receives the candidate information extracted from the work target candidate extracting means, each drawing-processed configuration displayed on the work terminal unit based on the candidate information. In addition to including candidate information on the diagram, the work terminal device transmits the selection information to the work plan management means when the work target equipment is selected from the displayed candidate information, and the work plan management means is based on the selection information. 12. The network work management system according to claim 11, wherein a final work plan is determined.
データベースには、各保守担当域の通信設備に関連付けされた端末装置の情報が格納され、
センターサーバは、作業担当端末装置から設備の停止または停止解除の作業計画が入力されると、外部からの承認情報に基づいてこの作業計画を決定する作業計画管理手段と、
作業担当端末装置から作業対象設備について機器または機器のポート部のうち少なくともいずれか1を選択する選択情報が入力されると、機器または機器のポート部のうち少なくともいずれか1を決定し決定情報を外部に出力する作業対象設備決定手段と、
作業対象設備決定手段から決定情報を受け取ると、この決定情報に基づき、データベースからこの決定された作業対象設備が属する保守担当域を所管する端末装置を抽出し、この作業対象設備を担当する端末装置を特定する情報を外部に出力する作業対象設備担当端末装置抽出手段と、
作業対象設備担当端末装置抽出手段から出力された作業対象設備担当端末装置の特定情報を受け取り、この特定情報に基づき、当該作業対象設備担当端末装置に当該決定情報と作業日時情報とを送信し作業実施を承認するか否かの承認要求を行うとともに、この作業対象設備担当端末装置から作業実施の承認の諾否の情報を受け取ると、この諾否情報を作業計画管理手段に出力する承認処理手段とを備えて構成され、
作業計画管理手段は、承認処理手段から作業について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とする請求項12に記載のネットワークの作業管理システム。
The database stores information on terminal devices associated with communication equipment in each maintenance area,
The center server, when a work plan for stopping or canceling the facility is input from the work terminal device, a work plan management means for determining the work plan based on external approval information;
When selection information for selecting at least one of the equipment and the port portion of the equipment is input from the work terminal device to the work target facility, at least one of the equipment or the port portion of the equipment is determined and the determination information is determined. Work target equipment determination means to output to the outside,
When receiving the decision information from the work target equipment determining means, based on this decision information, the terminal device responsible for the work target equipment is extracted from the database, and the terminal device responsible for the maintenance area to which the determined work target equipment belongs is extracted. Work terminal equipment responsible terminal device extraction means for outputting information identifying the outside,
The specific information of the work target equipment charge terminal device output from the work target equipment charge terminal device extraction means is received, and based on this specific information, the determination information and the work date and time information are transmitted to the work target equipment charge terminal device. An approval request is made as to whether or not to approve the operation, and upon receiving information on approval or disapproval of the work execution from this work object facility terminal device, an approval processing means for outputting the approval or disapproval information to the work plan management means, Configured with
When the work plan management means receives the determination result of approval or disapproval for the work from the approval processing means, the work plan management means determines whether or not the scheduled work execution is performed based on the determination result, and determines whether the work execution is possible or not to the work terminal apparatus. 13. The network work management system according to claim 12, wherein the network work management system is transmitted and displayed.
データベースには、網構成および局内構成を含む物理回線構成情報と機器内部位情報を含む装置構成情報と論理回線名および論理回線構成を含む論理回線構成情報とが格納されるとともに、各保守担当域の通信設備に関連付けされた端末装置の情報が格納され、
センターサーバは、作業計画管理手段と物理網・論理網・局内構成図描画処理手段と作業対象候補抽出手段と作業対象設備決定手段と作業対象設備担当端末装置抽出手段と承認処理手段とを備えて構成され、
作業担当端末装置は、表示された作業対象設備の回線に関連する機器または機器のポート部のうち少なくともいずれか1の候補に対し、オペレータにより作業対象とすべき機器または機器のポート部のうち少なくともいずれか1が選択されると、その選択情報をセンターサーバに送信し、
作業対象設備決定手段は、作業担当端末装置からこの選択情報を受け取ると、選択情報に基づいて機器または機器のポート部のうち少なくともいずれか1を決定して決定情報を出力し、
作業対象設備担当端末装置抽出手段は、この決定情報を受け取ると、この決定情報と作業計画の情報とに基づいて、決定された機器または機器のポート部を自らの保守担当域に有しそれらを管理する作業対象設備担当端末装置を抽出し、
承認処理手段は、抽出された作業対象設備担当端末装置の特定情報に基づいて、抽出された作業対象設備担当端末装置に作業日時の情報とともに決定された機器または決定されたポート部を有する機器の決定情報を送信し、
当該作業対象設備担当端末装置は、作業日時の情報と決定情報とを受け取ると、これら情報に基づいて、予定された作業の実施を承認するか否かの判別を行い、その判別結果をセンターサーバに送信し、
作業計画管理手段は、作業対象設備担当端末装置から承認処理手段を通じて作業実施について諾否の判別結果を受け取ると、この判別結果に基づいて予定された作業実施の可否を決定するとともに、作業実施の可否の決定を作業担当端末装置に送信して表示させることを特徴とする請求項13に記載のネットワークの作業管理システム。
The database stores physical line configuration information including the network configuration and intra-station configuration, device configuration information including the in-device part information, and logical line configuration information including the logical line name and logical line configuration, and each maintenance area. Stores information about terminal devices associated with
The center server includes work plan management means, physical network / logical network / internal station configuration drawing drawing means, work target candidate extraction means, work target equipment determination means, work target equipment responsible terminal device extraction means, and approval processing means. Configured,
The work-in-use terminal device has at least one of the device or the port portion of the device to be worked by the operator with respect to at least one candidate of the device or the device port portion related to the displayed line of the work target facility. When any one is selected, the selection information is transmitted to the center server,
The work target facility determining means, upon receiving this selection information from the work terminal device, determines at least one of the device or the port portion of the device based on the selection information and outputs the determination information,
Upon receiving this determination information, the work target facility terminal device extracting means has the determined device or the port part of the device in its maintenance area based on the determination information and the information of the work plan. Extract the terminal equipment in charge of the equipment to be managed,
The approval processing means, based on the extracted identification information of the work target facility terminal device, the device of the extracted work target facility terminal device together with the information of the work date and time of the device having the determined port unit Send decision information,
When receiving the work date and time information and the decision information, the work target facility terminal device determines whether or not to approve the scheduled work based on the information, and the determination result is sent to the center server. To
When the work plan management means receives the result of approval / disapproval for work execution from the work target facility terminal device through the approval processing means, the work plan management means determines whether or not the scheduled work execution is possible based on the determination result, and whether the work execution is possible or not 14. The network work management system according to claim 13, wherein the determination is transmitted to a work terminal device for display.
作業計画が予め計画された停止日時と停止設備との情報を含む停止計画であり、
作業計画管理手段は、停止作業日前に、データベースに停止計画に対し実施が決定された停止作業を最終的な停止計画として登録し、
作業対象設備担当端末装置は、停止作業の当日、停止作業開始の所定時間前に、センターサーバから登録された最終的な停止計画を受け取ると、登録された停止作業を当日作業として承認するか否かの判別を行い、その判別結果を、センターサーバに送信するよう構成するとともに、
当日作業計画管理手段を、停止作業の当日、停止作業開始の所定時間前になると、データベースから登録された最終的な停止計画情報を取り出し、この最終的な停止計画情報に基づいて当日の停止作業の対象となる作業対象設備担当端末装置の特定情報を外部に出力するとともに、上記作業対象設備担当端末装置から停止作業当日の停止作業実施について諾否の判別結果を受け取ると、この判別結果に基づいて登録された最終的な停止計画の実施について開始の可否を作業担当端末装置に送信して表示させるよう構成し、
センターサーバには、当日作業計画手段から受け取った作業対象設備担当端末装置の特定情報に基づいて、当日の停止作業の対象となる作業対象設備担当端末装置に、最終的な停止計画情報に含まれる停止日時情報と停止対象設備情報とを送信し、当該作業対象設備担当端末装置から停止作業を当日作業として承認するか否かの判別結果を受け取ると、その判別結果を当日作業計画管理手段に出力する当日作業承認処理手段を設けたことを特徴とする請求項14に記載のネットワークの作業管理システム。
The work plan is a stop plan that includes information about the scheduled stop date and time and the stop equipment,
The work plan management means registers, as a final stop plan, the stop work determined to be executed for the stop plan in the database before the stop work day,
When the terminal device in charge of the work target receives the final stop plan registered from the center server on the day of the stop work, a predetermined time before the start of the stop work, whether or not to approve the registered stop work as the day work Is configured to transmit the determination result to the center server,
When the current day work plan management means reaches a predetermined time before the start of the stop work on the day of the stop work, the final stop plan information registered from the database is extracted, and the stop work of the day is based on this final stop plan information. Output the specific information of the terminal equipment in charge of the work target to be subject to the outside, and when receiving a determination result of acceptance or disapproval for the stop work implementation on the stop work day from the above-mentioned work target equipment charge terminal device, based on this determination result Configured to send and display to the work terminal device whether or not to start the implementation of the registered final stop plan,
In the center server, based on the identification information of the work target facility terminal device received from the work plan means on the day, the final stop plan information is included in the work target facility terminal device that is the target of the current day's stop operation. Stop date / time information and stop target equipment information are transmitted, and when the determination result of whether or not the stop work is approved as the current day work is received from the terminal device in charge of the work target, the determination result is output to the current day work plan management means 15. The network work management system according to claim 14, further comprising day-of-day work approval processing means.
停止作業の対象となる通信設備はインターネットプロトコルを有し、ポート部は上記通信設備のIPポートであって、
当該通信設備は、ポートを開閉制御する設備側制御手段と、設備側制御手段により制御され実行された結果をセンターサーバに送信する制御情報送信手段とを備え、
センターサーバは、通信により設備側と情報の遣り取りを行うとともに、作業担当端末装置から通信設備のポートを停止または停止解除を要求する指令を受け取ると、当該通信設備またはポートの情報に基づいて設備側制御手段に当該通信設備のポートの停止または停止解除を実行させ、設備側制御手段により制御され実行された結果を制御情報送信手段から受け取ると、受け取った実行結果を作業担当端末装置に送信して表示させる監視制御システムを備えていることを特徴とする請求項15に記載の通信ネットワークの作業管理システム。
The communication equipment to be stopped has an Internet protocol, and the port part is the IP port of the communication equipment,
The communication facility includes facility-side control means for controlling opening and closing of the port, and control information transmitting means for transmitting the result controlled and executed by the facility-side control means to the center server,
When the center server exchanges information with the equipment side by communication and receives a command for requesting stop or release of the port of the communication equipment from the work terminal device, the center server is based on the information on the communication equipment or the port. When the control unit is caused to stop or release the port of the communication facility, and the result controlled and executed by the facility-side control unit is received from the control information transmitting unit, the received execution result is transmitted to the work terminal unit. 16. The work management system for a communication network according to claim 15, further comprising a monitoring control system for displaying.
監視制御システムは、当日作業計画管理手段と当日作業承認処理手段と制御コマンド文法データベースと制御コマンド生成手段とを備えるとともに、
制御コマンド生成手段は、外部から入力される指令に基づいて制御コマンド文法データベースにより該当する機器のポートに対する停止または停止解除要求コマンドを生成し、これら停止または停止解除要求コマンドを該当する通信設備に送信するよう構成され、
センターサーバは、当日作業計画管理手段が、作業担当端末装置から選択された機器またはポートについて停止または停止解除を要求する指令を受け取ると、この指令に基づいて停止または停止解除要求コマンドを生成するよう制御コマンド生成手段に指令し、これら生成された停止または停止解除要求コマンドを制御コマンド生成手段を通じて通信設備の設備側制御手段に送信させ、実行された結果が通信設備の制御情報送信手段から送られてくると、この実行結果を作業担当端末装置に送信して表示させる停止・停止解除制御手段とを備えて構成されることを特徴とする請求項16に記載の通信ネットワークの作業管理システム。
The monitoring control system includes a day work plan management means, a day work approval processing means, a control command grammar database, and a control command generation means.
The control command generation means generates a stop or stop release request command for the corresponding device port from the control command grammar database based on a command input from the outside, and transmits the stop or stop release request command to the corresponding communication equipment. Configured to
When the center server receives a command for requesting stop or stop release for the device or port selected from the work terminal device, the center server generates a stop or stop release request command based on the command. The control command generation means is instructed, and the generated stop or stop release request command is transmitted to the communication facility equipment control means through the control command generation means, and the execution result is sent from the communication equipment control information transmission means. 17. The work management system for a communication network according to claim 16, further comprising stop / stop release control means for transmitting and displaying the execution result to a work terminal device.
データベースに格納された通信設備の情報に基づいてネットワーク全体の回線を管理運用するセンターサーバと、このセンターサーバと通信を通じて作業情報を遣り取り可能に接続され各保守担当域のネットワークの回線を管理する端末装置とを備え、
停止作業を担当する作業担当端末装置により予め計画された作業日時と作業設備との情報を含む作業計画がセンターサーバに送信されると、センターサーバが停止作業開始前に作業対象通信設備について停止情報を設定し、実作業終了後に、作業担当端末装置から作業終了通知がセンターサーバに送信されると停止情報の設定を解除するネットワークの作業管理方法であって、
通信設備をセンターサーバと通信を通じて通信設備の運用状態について情報を遣り取り可能に接続して構成し、
センターサーバに作業担当端末装置から設定された停止作業計画について作業開始の通知が送られてくると、センターサーバは当該作業対象の通信設備に対して通信設備の運用状態の情報を求め、当該作業対象設備から通信設備の運用状態についての情報がセンターサーバに送られてくると、その情報をデータベースに格納し、センターサーバはデータベースに格納された通信設備の運用状態の情報に基づいて、ネットワークのシステム停止の有無を判定し、このシステム停止判定結果を前記作業担当端末装置に送信して表示させることを特徴とするネットワークの作業管理方法。
A center server that manages and operates the lines of the entire network based on communication facility information stored in the database, and a terminal that manages the network lines of each maintenance area by connecting to the center server so that work information can be exchanged through communication With the device,
When a work plan including information on the work date and time and work equipment planned in advance by the work terminal device in charge of the stop work is transmitted to the center server, the stop information on the work target communication equipment before the center server starts the stop work A work management method for a network that cancels the setting of stop information when a work end notification is transmitted from the work terminal device to the center server after the actual work ends,
The communication equipment is configured so that it can exchange information about the operational status of the communication equipment through communication with the center server.
When a notification of the start of work is sent to the center server from the work terminal device, the center server obtains information on the operation status of the communication equipment from the communication equipment of the work target, and When information about the operational status of the communication equipment is sent from the target equipment to the center server, the information is stored in the database, and the center server stores information on the operational status of the communication equipment stored in the database. A network work management method, comprising: determining whether or not a system is stopped; and transmitting and displaying the system stop determination result to the work terminal device.
センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の状態について照会の要求があると、当該作業対象通信設備に対して設備の状態を回答するよう求め、当該作業対象通信設備から受け取った設備の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該設備の情報と設備の状態についての回答とをデータベースに格納し、
作業担当端末装置から作業対象の通信設備に関し回線の状態について照会の要求があると、当該作業対象通信設備に対して回線の状態を回答するよう求め、当該作業対象通信設備から受け取った回線の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させるとともに、当該回線の情報と回線の状態についての回答とをデータベースに格納し、
これらデータベースに格納された設備の状態情報と回線の状態情報とのうち少なくともいずれか一方に基づいてシステム停止の有無を判定することを特徴とする請求項18に記載のネットワークの作業管理方法。
When the center server receives a request for inquiry about the state of the equipment related to the work target communication equipment from the work terminal device, the center server asks the work target communication equipment to return the state of the equipment and receives it from the work target communication equipment. The response about the status of the installed equipment is sent to the work terminal device that requested the inquiry and displayed, and the information about the equipment and the answer about the status of the equipment are stored in the database.
When there is a request for inquiry about the line status of the communication equipment to be worked from the terminal device in charge of work, the state of the line received from the work target communication equipment is requested to return the line status to the work target communication equipment. Send the response to the work terminal device that requested the inquiry and display it, and store the information about the line and the answer about the line status in the database,
19. The network work management method according to claim 18, wherein whether or not the system is stopped is determined based on at least one of the facility state information and the line state information stored in the database.
センターサーバは、作業担当端末装置から作業対象の通信設備に関し設備の設定状態について照会の要求があると、当該作業対象通信設備に対して設備の設定状態を回答するよう求め、当該作業対象通信設備から受け取った設備の設定状態についての回答を照会要求のあった作業担当端末装置に送信して表示させ、
作業担当端末装置から作業対象の通信設備に関し作業対象設備を経由する経路について照会の要求があると、作業担当端末装置から提供された始端設備情報と終端設備情報とに基づいて、当該作業対象通信設備に対して経路の状態を回答するよう求め、当該作業対象通信設備から受け取った経路の状態についての回答を照会要求のあった作業担当端末装置に送信して表示させることを特徴とする請求項18または19に記載のネットワークの作業管理方法。
When there is a request for inquiry about the setting state of the equipment related to the work target communication equipment from the work terminal device, the center server requests the work target communication equipment to return the equipment setting state, and the work target communication equipment Send the response about the setting status of the equipment received from the work terminal device that requested the inquiry to display it,
When there is a request for inquiry about the route through the work target equipment regarding the communication equipment to be worked from the work charge terminal device, the work target communication is performed based on the start equipment information and the end equipment information provided from the work work terminal device. Claiming the equipment to answer the status of the route, and sending the answer about the status of the route received from the work object communication equipment to the work-in-charge terminal device that requested the inquiry, and displaying it. The network work management method according to 18 or 19.
JP2009175758A 2009-07-28 2009-07-28 Network work management system and management method Active JP5568914B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009175758A JP5568914B2 (en) 2009-07-28 2009-07-28 Network work management system and management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009175758A JP5568914B2 (en) 2009-07-28 2009-07-28 Network work management system and management method

Publications (2)

Publication Number Publication Date
JP2011030098A true JP2011030098A (en) 2011-02-10
JP5568914B2 JP5568914B2 (en) 2014-08-13

Family

ID=43638267

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009175758A Active JP5568914B2 (en) 2009-07-28 2009-07-28 Network work management system and management method

Country Status (1)

Country Link
JP (1) JP5568914B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012010151A (en) * 2010-06-25 2012-01-12 Tokyo Electric Power Co Inc:The Control management system of communication network and method thereof
US20220277255A1 (en) * 2019-08-19 2022-09-01 Yanmar Power Technology Co., Ltd. Work reliever mediation system and farm machine sharer mediation system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005080471A (en) * 2003-09-02 2005-03-24 Chugoku Electric Power Co Inc:The Planning system and method for power-failure work, and program
JP2008108022A (en) * 2006-10-25 2008-05-08 Chugoku Electric Power Co Inc:The Operation maintenance management device
JP2008252448A (en) * 2007-03-30 2008-10-16 Toshiba Corp Stop control system
JP2008306634A (en) * 2007-06-11 2008-12-18 Tokyo Electric Power Co Inc:The Alarm mask management system of communication network, and management method therefor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005080471A (en) * 2003-09-02 2005-03-24 Chugoku Electric Power Co Inc:The Planning system and method for power-failure work, and program
JP2008108022A (en) * 2006-10-25 2008-05-08 Chugoku Electric Power Co Inc:The Operation maintenance management device
JP2008252448A (en) * 2007-03-30 2008-10-16 Toshiba Corp Stop control system
JP2008306634A (en) * 2007-06-11 2008-12-18 Tokyo Electric Power Co Inc:The Alarm mask management system of communication network, and management method therefor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012010151A (en) * 2010-06-25 2012-01-12 Tokyo Electric Power Co Inc:The Control management system of communication network and method thereof
US20220277255A1 (en) * 2019-08-19 2022-09-01 Yanmar Power Technology Co., Ltd. Work reliever mediation system and farm machine sharer mediation system

Also Published As

Publication number Publication date
JP5568914B2 (en) 2014-08-13

Similar Documents

Publication Publication Date Title
US20010027407A1 (en) Control and inquiry system for construction work
JP2001504257A (en) Resource allocation
CN103093303A (en) Outage schedule management apparatus and method in ems
KR20180092371A (en) Method for maintaining and managing facility
JP5568914B2 (en) Network work management system and management method
JP2007042014A (en) System and method for monitoring plant condition
JP2006106861A (en) Maintenance management method and maintenance management program
JP2008306634A (en) Alarm mask management system of communication network, and management method therefor
JPH096428A (en) Plant monitoring equipment
JP5076943B2 (en) Network work management system and management method
WO2010042524A1 (en) Systems and methods of integrated and automated generation of work packages
Sadiq et al. Architectural considerations in systems supporting dynamic workflow modification
JP2021149185A (en) Periodic inspection information cooperation system and periodic inspection information cooperation method
Siu Resource budget for workface planning in industrial-construction
JP4597076B2 (en) Power system blackout work plan setting method and system
CN110980533B (en) Tower crane safety monitoring management system
CN112734366A (en) Dynamic management method, system and storage medium for construction cost in whole process of engineering settlement
Tackenberg et al. Actor-oriented optimization model for maintenance tasks
JP5477194B2 (en) Communication network control management system and method
JPH086783A (en) Software quality guarantee supporting device
JP5062003B2 (en) Circuit plan adjustment system and method
US20160314435A1 (en) System that creates a unique calendar event for an associated calendar resource in a standard calendaring system, for work to be performed in a critical infrastructure environment, based on a method of procedure document.
JP2014134840A (en) Work check sheet proofread/registration method and work check sheet proofread/registration system
Greasley Case study: A simulation of a rail carriage maintenance depot
Ismail Lesson Learned To Mantain And Widespread Implementation Of Precast Concrete Building In Malaysian Construction Industry

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120508

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130614

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130702

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140311

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140501

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140527

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140609

R150 Certificate of patent or registration of utility model

Ref document number: 5568914

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350