CN112734366A - Dynamic management method, system and storage medium for construction cost in whole process of engineering settlement - Google Patents

Dynamic management method, system and storage medium for construction cost in whole process of engineering settlement Download PDF

Info

Publication number
CN112734366A
CN112734366A CN202011630166.3A CN202011630166A CN112734366A CN 112734366 A CN112734366 A CN 112734366A CN 202011630166 A CN202011630166 A CN 202011630166A CN 112734366 A CN112734366 A CN 112734366A
Authority
CN
China
Prior art keywords
approval
next process
personnel
cost
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011630166.3A
Other languages
Chinese (zh)
Other versions
CN112734366B (en
Inventor
欧阳艳
程彬
李锦华
李利民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dawei International Engineering Consulting Co Ltd
Original Assignee
Dawei International Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dawei International Engineering Consulting Co Ltd filed Critical Dawei International Engineering Consulting Co Ltd
Priority to CN202011630166.3A priority Critical patent/CN112734366B/en
Publication of CN112734366A publication Critical patent/CN112734366A/en
Application granted granted Critical
Publication of CN112734366B publication Critical patent/CN112734366B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to a dynamic management method, a system and a storage medium for construction cost in the whole process of engineering settlement, which relate to the technical field of engineering settlement and solve the problem that when the current process of an engineering project is finished and the actual investment and the planned investment are inconsistent, the analysis and the corresponding approval of related reasons can be carried out, so that the control of the whole engineering cost by a manager is delayed; the need for approval and the corresponding approval of the person is ascertained on the basis of the predicted deviation of the expenditure. This application can let managers know the prediction cost of next process in advance to be favorable to the control of managers to whole engineering cost.

Description

Dynamic management method, system and storage medium for construction cost in whole process of engineering settlement
Technical Field
The present application relates to the field of engineering settlement technology, and in particular, to a dynamic management method, system and storage medium for construction cost in the whole process of engineering settlement.
Background
The project settlement is directly related to the vital interests of construction units and construction units. In the process of editing and reviewing settlement, because the positions, the places and the purposes of editing and reviewing personnel are different, and the working levels of the editing and reviewing personnel are also different, the difference of different degrees of editing and reviewing results is normal. However, if the difference is too large, the cost may be intentionally reduced or the cost may be overestimated.
The prior patent with the application number of CN201911160731.1 and the name of CN201911160731.1 is a dynamic management method for the whole process of engineering settlement cost, which compares the actual investment and the planned investment situation of each process of an engineering project and enables an examining and approving person to know the deviation data and the deviation reason when the deviation occurs, thereby facilitating the subsequent planned investment adjustment when needed and entering the next process after the examination and approval of the examining and approving person is finished.
With respect to the related art in the above, the inventors consider that there are the following drawbacks: when the current working procedure of the engineering project is finished and the actual investment and the planned investment are inconsistent, the analysis of relevant reasons and the corresponding approval are carried out, so that the control of the whole engineering cost by a manager is delayed.
Disclosure of Invention
In order to enable a manager to know the predicted construction cost of the next procedure in advance and be beneficial to the manager to control the whole construction cost, the application provides a dynamic construction cost management method, a dynamic construction cost management system and a storage medium in the whole construction settlement process.
In a first aspect, the present application provides a dynamic management method for construction cost in the whole process of engineering settlement, which adopts the following technical scheme:
a dynamic management method for construction cost in the whole process of engineering settlement comprises the following steps:
acquiring building materials and building material weight required by completing each process, and the number of workers required by completing the corresponding process and the number of technicians required to be matched with the corresponding workers;
predicting the cost of the building materials applied in the next process based on the cost of the building materials of which the process is finished in the current project, predicting the cost of the building materials required by the next process in the project, and synchronously predicting the personnel expense required by the next process in the project based on the personnel expense of technicians of the work type matched with the process finished in the current project;
the sum of the predicted building material cost required by the next process of the project and the personnel expense required by the next process of the project is subtracted from the sum of the predicted building material cost and the personnel expense of the next process of the project, and the obtained difference value is used as the predicted expense deviation;
confirming whether the examination and approval is needed or not and corresponding examination and approval personnel based on the predicted expense deviation, and if the examination and approval is needed, sending information to terminal equipment of the examination and approval personnel to remind the examination and approval personnel of examining and approving;
and acquiring the information which does not need to be approved or approval completion information, and starting the next process.
By adopting the technical scheme, the construction material cost and the expenditure condition of personnel of the next process can be effectively analyzed and predicted, and when the construction material cost and the expenditure condition of personnel exceed the planning, the examination and approval personnel are timely notified to examine and approve.
Optionally, the step of predicting the building material cost required by the next engineering process is as follows:
the method comprises the steps that building materials required by the next process of the project are taken as query objects one by one from a preset first database which stores the finished processes of the project and actual unit weight prices of different building materials of the corresponding processes, and the unit weight prices of each building material required by the next process in the finished processes are queried and obtained;
if the building materials required by the next process of the project are all obtained by querying the first database, constructing the building materials based on the mean value of the unit weight prices of the finished processes of the building materials and the unit weight prices of the last application of the corresponding building materialsThe unit weight price of each building material required by the next process of the engineering is calculated one by a weight formula, wherein the weight formula is as follows: zi=(A1+....Ai+....An)/n*q1+An*q2N represents the total number of processes using the corresponding building material, AiRepresents the unit weight price of the building material at the ith application process, AnRepresenting the unit weight price of the building material at the nth application of the building material, wherein the nth application also refers to the latest application of the building material, q1Q is the weight ratio of the mean value of the finished process unit weight prices of the building materials2The weight ratio of the unit weight price of the last application of the corresponding building material is Z, and the unit weight price of the corresponding building material is Z;
obtaining the unit weight price of the building materials required to be applied in the next process, multiplying the unit weight price by the weight of the same building material required to be applied in the next process, obtaining the total cost of the building materials required to be applied in the next process one by one, and adding the total cost of each building material required to be applied in the next process to obtain the building material cost required by the next process;
if the building materials required by the next process of the project are not inquired and obtained in the first database, determining the building materials which are not inquired and obtained, and taking the product of the unit weight price of the building materials which are not inquired and obtained in the local area and the weight of the corresponding building materials which are not inquired and obtained as the cost of the building materials which are not inquired and obtained in the next process;
and taking the sum of the building material cost which is not inquired and obtained in the next process and the building material cost which is inquired and obtained in the next process as the building material cost required by the next process of the project.
By adopting the technical scheme, the unit weight price of each building material required by the next process of the project can be effectively analyzed based on the mean value of the unit weight prices of the finished processes of the building materials and the unit weight price of the last application of the corresponding building material, so that the building material cost required by the next process of the project can be more accurately predicted.
Optionally, the step of predicting the personnel cost required for the next process of engineering is as follows:
acquiring the actual wages of the wage technicians in the finished process in the next process in the unit time by taking the wage technicians required by the next process as query objects from a preset second database storing the finished process of the project and the actual wages in the unit time of the different wage technicians in the corresponding process;
screening out the wages in unit time given by the technicians of the work type required by the next process of the engineering for the last time, multiplying the wages by the product of the time consumption of the work type corresponding to the next process and the number of the technicians of the work type required by the next process, and taking the finally obtained product as the expense expenditure of the technicians of the work type required by the next process of the engineering;
and taking the sum of the expenses of all the workers and technicians required by the next process as the expense of the personnel required by the next process of the project.
By adopting the technical scheme, the wages in unit time given by the technical personnel who select the required wages of the next process of the project for the last time can be obtained, the technical personnel who apply the same wages of the next process can be directly referred, and therefore the personnel cost expense required by the next process of the project can be better predicted.
Optionally, the steps of confirming whether an approval is required and the personnel to be approved accordingly based on the predicted deviation of the expenses are as follows:
acquiring an expense deviation range in which the predicted expense deviation falls and a contact way of an approving person corresponding to the corresponding expense deviation range from a preset third database in which the expense deviation range is stored and the contact way of the approving person corresponding to the corresponding expense deviation range are stored by taking the predicted expense deviation as a query object;
if the predicted expense deviation is not queried in the third database to obtain a corresponding expense deviation range, judging that approval is not needed; otherwise, determining approval and synchronously determining the persons to be approved.
By adopting the technical scheme, the prediction expense deviation condition can be corresponding to different examination and approval personnel, and compared with the situation that all examination and approval are accumulated on one person, the examination and approval personnel can have more definite cognition on own examination and approval tasks, and the possibility of examination and approval errors is avoided.
Optionally, if the approval is required, the step of sending information to the terminal device of the approval staff to remind the approval staff of approval is as follows:
sending the approval information to the terminal equipment of the confirmed approval personnel;
if the approval personnel do not confirm within the preset time, the position of the terminal equipment of the approval personnel is obtained, the approval personnel closest to the confirmed approval personnel is selected as generation reminding personnel based on the position of the terminal equipment of the approval personnel and the positions of the terminals of the other approval personnel, and the generation reminding information and the path information from the generation reminding personnel to the confirmed approval personnel are sent to the terminal equipment of the generation reminding personnel.
By adopting the technical scheme, the nearest generation reminding personnel can be found in time to carry out on-site reminding on the examining and approving personnel when the examining and approving personnel are not in contact, so that the smooth proceeding of the examining and approving is guaranteed.
Optionally, if the approval is required, the step of sending information to the terminal device of the approval staff to remind the approval staff of approval further comprises the step of sending the approval information to the confirmed approval staff synchronously, wherein the approval staff is reminded synchronously through voice dialing.
By adopting the technical scheme, the addition of the voice prompt mode further ensures the reminding of the examination and approval personnel, and avoids the examination and approval personnel from neglecting examination and approval items due to doing other things.
In a second aspect, the present application provides a dynamic management system for construction cost in the whole process of project settlement, which adopts the following technical scheme:
a dynamic project settlement whole-process cost management system comprising a memory, a processor and a program stored in the memory and executable on the processor, the program being capable of being loaded and executed by the processor to implement the dynamic project settlement whole-process cost management method according to any one of the preceding claims.
Through adopting above-mentioned technical scheme, through the transfer of procedure, can effective analysis predict the building materials cost of next process and personnel's expense condition to when building materials cost and personnel's expense condition surpass the planning, in time inform the examination and approval personnel to examine and approve, compare in the present current mode that just examines and approve the cost report after accomplishing, accomplished the advancing of examining and approving, avoided because the influence of examining and approving to the process delay, and let staff's cost have better understanding and management and control.
In a third aspect, the present application provides a computer storage medium, which adopts the following technical solutions:
a computer storage medium comprising a program that is capable of being loaded and executed by a processor to implement the dynamic management method for project settlement overall process construction costs as claimed in any one of the preceding claims.
Through adopting above-mentioned technical scheme, through the transfer of procedure, can effective analysis predict the building materials cost of next process and personnel's expense condition to when building materials cost and personnel's expense condition surpass the planning, in time inform the examination and approval personnel to examine and approve, compare in the present current mode that just examines and approve the cost report after accomplishing, accomplished the advancing of examining and approving, avoided because the influence of examining and approving to the process delay, and let staff's cost have better understanding and management and control.
To sum up, the beneficial technical effect of this application does:
1. whether the expenditure of the next procedure exceeds the plan or not can be judged in advance, and the examination and approval are carried out in advance, so that the working personnel can more comprehensively know the construction cost;
2. when the examination and approval personnel are required to carry out examination and approval and the corresponding examination and approval personnel can not be informed, the examination and approval personnel nearby can be found to carry out the site.
Drawings
FIG. 1 is a schematic diagram illustrating the overall steps of a dynamic management method for construction cost in the whole process of engineering settlement according to an embodiment of the present application.
Fig. 2 is a schematic diagram of the step of predicting the building material cost required for the next process of the engineering process in step S200 in fig. 1.
Fig. 3 is a schematic diagram of the step of acquiring the personnel cost required for the next process of the project mentioned in step S200 of fig. 1.
Fig. 4 is a schematic diagram of the steps of personnel confirming whether an approval is required and a corresponding approval based on the predicted deviation of expenses as mentioned in step S400 of fig. 1.
Fig. 5 is a schematic diagram of the step of sending a message to the terminal device of the approver to remind the approver of approval if the approval is required in step S400 in fig. 1.
Detailed Description
The present application is described in further detail below with reference to the attached drawings.
Referring to fig. 1, a dynamic management method for construction cost in the whole process of project settlement disclosed in the present application includes steps S100 to S500.
In step S100, the building material and the weight of the building material required to complete each process, and the number of workers required to complete the corresponding process and the number of technicians required to match the corresponding workers are obtained.
The building materials, the weight of the building materials, the work types and the number of technicians required to be matched with the corresponding work types mentioned in the step S100 are obtained by calling the relevant database.
In step S200, the cost of the building material applied in the next process is predicted based on the cost of the building material of the process completed in the current process, the cost of the building material required in the next process is predicted, and the personnel expense required in the next process is predicted synchronously based on the personnel expense of the technician of the work type matched with the process completed in the current process.
Referring to fig. 2, the step of predicting the building material cost required for the next process of the engineering mentioned in step S200 can be divided into steps Sa10, step SaA0, step SaB0, step Saa0 and step Sab0, wherein step SaA0 and step Saa0 are parallel steps.
In step Sa10, from a first database in which the completed process of the project and the actual unit weight prices of the building materials in the different processes are stored, the building materials required for the next process of the project are searched one by one as the query object, and the unit weight price of each building material required for the next process in the completed process is obtained.
In step SaA0, if the building material required by the next process is the first oneA database is inquired and obtained, and a weight formula is constructed based on the mean value of the unit weight prices of the finished working procedures of the building materials and the unit weight prices of the last application of the corresponding building materials, so that the unit weight price of each building material required by the next working procedure of the engineering is calculated one by one, wherein the weight formula is as follows: z = (A)1+....Ai+....An)/n*q1+An*q2N represents the total number of processes using the corresponding building material, AiRepresents the unit weight price of the building material at the ith application process, AnRepresenting the unit weight price of the building material at the nth application of the building material, wherein the nth application also refers to the latest application of the building material, q1Q is the weight ratio of the mean value of the finished process unit weight prices of the building materials2The weight ratio of the unit weight price of the last application of the corresponding building material; z is the unit weight price of the corresponding building material.
In step SaB0, the unit weight price of the building material to be used in the next process is obtained and multiplied by the weight of the same building material to be used in the next process to obtain the total cost of the building materials to be used in the next process one by one, and the sum of the total cost of each building material to be used in the next process is used as the building material cost to be used in the next process.
For example, the building material required by the next process of the engineering is A, which is applied in the previous three processes, and the prices of the building materials of A are a-element, b-element and c-element in the three processes according to the time sequence, and the prices of the building materials of A are (q + b + c)/3 x 0.5+ c 0.5 on the assumption that q1 is 0.5 and q2 is 0.5.
In the step Saa0, if the building material required for the next process of the engineering is not obtained by querying the first database, the building material which is not obtained by querying is determined, and the product of the unit weight price of the building material which is not obtained by querying in the local area and the weight of the corresponding building material which is not obtained by querying is used as the cost of the building material which is not obtained by querying in the next process.
In step Sab0, the sum of the cost of all building materials obtained by the next process without querying the first database and the cost of all building materials obtained by the next process querying the first database is used as the building material cost required for the next process of the project.
Referring to fig. 3, the step of predicting the personnel expenses required for the next process of the project, which is mentioned in step S200, may be divided into steps Sb10 to Sb 30.
In step Sb10, the payroll per unit time of the payroll technician required by the next process in the process after the process is completed is obtained by using the payroll technician required by the next process as the query object from the preset second database storing the process completed by the process and the actual payroll per unit time of the different payroll technicians in the corresponding processes.
In step Sb20, the unit time wages given by the technicians of the work category required for the next process of the project are screened out, and multiplied by the product of the planned time consumption of the work category corresponding to the next process and the number of the technicians of the work category required for the next process, and the finally obtained product is used as the cost expenditure of the technicians of the work category corresponding to the next process of the project.
In step Sb30, the sum of the costs of all the workers and technicians required for the next process is used as the cost of the personnel required for the next process.
For example, the payroll of a certain kind of technical staff at the last time of application is t yuan per day, the number of applications of the kind of technology in the next process is 10, the time required by the kind of technical staff in the next process is 10 days, and the cost of the corresponding process in the next process is 100 t.
In step S300, the sum of the predicted building material cost and the personnel expense required for the next process of the project is subtracted from the sum of the predicted building material cost and the personnel expense for the next process of the project, and the obtained difference is used as the predicted expense deviation.
In step S400, whether an approval is required and a corresponding approved person is determined based on the predicted expense deviation, and if the approval is required, information is sent to a terminal device of the approver to remind the approver of approval.
Referring to fig. 4, the step of confirming whether approval is required based on the case of the predicted expense deviation mentioned in step S400 and the personnel approved accordingly may be divided into steps S4a0 through S4b 0.
In step S4a0, the predicted expense deviation is used as a query object from a preset third database storing the expense deviation range and the contact manner of the approver corresponding to the expense deviation range, and the expense deviation range in which the predicted expense deviation falls and the contact manner of the approver corresponding to the corresponding expense deviation range are obtained.
In step S4b0, if the predicted expense deviation is not queried in the third database to obtain a corresponding expense deviation range, it is determined that approval is not required; otherwise, determining approval and synchronously determining the persons to be approved.
For example, the ranges of deviation of expenses stored in the third database are as follows: [10, 50] ten thousand yuan, (50, 100] ten thousand yuan, if the expense deviation is less than 10 ten thousand yuan, then the examination and approval are not required.
Referring to fig. 5, if the approval is required in step S400, the step of sending information to the terminal device of the approver to remind the approver of approval may be divided into step S4a0 to step S4B 0.
In step S4a0, approval information is sent to the terminal device of the confirmed approver.
The step of sending information to the terminal equipment of the examination and approval personnel to remind the examination and approval personnel of examination and approval further comprises the step of sending the examination and approval information to the confirmed examination and approval personnel to remind the examination and approval personnel through voice dialing.
The terminal devices mentioned in step S4a0 include, but are not limited to, a cell phone and a computer of an approver.
In step S4B0, if the approver does not confirm within the preset time, the location of the terminal device of the approver is obtained, and based on the location of the approver terminal device and the locations of the terminals of the other approvers, the approver closest to the confirmed approver is selected as the generation reminder, and the generation reminder information and the path information from the generation reminder to the confirmed approver are sent to the terminal device of the generation reminder.
The position of the terminal device of the approval staff and the position of the terminal of the remaining approval staff mentioned in the step S4B0 may be obtained by a tracker provided on the terminal device of the corresponding approval staff, and if the approval staff uses a mobile phone, the position may be obtained by tracking the approval staff through the mobile phone tracker.
The selection of the approver closest to the approver identified in step S4B0 is mainly performed by the trip planner, and the corresponding path is planned by the trip planner with the identified approver as the end point and the positions of the other approvers as the start points.
In step S500, the information that the examination and approval is not required or the information that the examination and approval is completed is acquired, and the next process is started.
The embodiment of the application also provides a computer readable storage medium, which comprises a program capable of realizing the method of any one of fig. 1-5 when being loaded and executed by a processor.
The computer-readable storage medium includes, for example: various media capable of storing program codes, such as a usb disk, a removable hard disk, a Read-only memory (ROM), a Random Access Memory (RAM), a magnetic disk, or an optical disk.
Based on the same inventive concept, the embodiment of the present application further provides a dynamic management system for construction cost in the whole process of engineering settlement, which includes a memory and a processor, wherein the memory stores a program capable of running on the processor to implement any one of the methods shown in fig. 1 to 5.
It will be clear to those skilled in the art that, for convenience and simplicity of description, the foregoing division of the functional modules is merely used as an example, and in practical applications, the above function distribution may be performed by different functional modules according to needs, that is, the internal structure of the device is divided into different functional modules to perform all or part of the above described functions. For the specific working processes of the system, the apparatus and the unit described above, reference may be made to the corresponding processes in the foregoing method embodiments, and details are not described here again.
In the several embodiments provided in the present application, it should be understood that the disclosed system, apparatus and method may be implemented in other manners. For example, the above-described apparatus embodiments are merely illustrative, and for example, a module or a unit may be divided into only one logical function, and may be implemented in other ways, for example, a plurality of units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, devices or units, and may be in an electrical, mechanical or other form.
Units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present application may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present application may be substantially implemented or contributed by the prior art, or all or part of the technical solution may be embodied in a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, a network device, or the like) or a processor (processor) to execute all or part of the steps of the method according to the embodiments of the present application. And the aforementioned storage medium includes: u disk, removable hard disk, read only memory, random access memory, magnetic or optical disk, etc. for storing program codes.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (8)

1. A dynamic management method for construction cost in the whole process of engineering settlement is characterized by comprising the following steps:
acquiring building materials and building material weight required by completing each process, and the number of workers required by completing the corresponding process and the number of technicians required to be matched with the corresponding workers;
predicting the cost of the building materials applied in the next process based on the cost of the building materials of which the process is finished in the current project, predicting the cost of the building materials required by the next process in the project, and synchronously predicting the personnel expense required by the next process in the project based on the personnel expense of technicians of the work type matched with the process finished in the current project;
the sum of the predicted building material cost required by the next process of the project and the personnel expense required by the next process of the project is subtracted from the sum of the predicted building material cost and the personnel expense of the next process of the project, and the obtained difference value is used as the predicted expense deviation;
confirming whether the examination and approval is needed or not and corresponding examination and approval personnel based on the predicted expense deviation, and if the examination and approval is needed, sending information to terminal equipment of the examination and approval personnel to remind the examination and approval personnel of examining and approving;
and acquiring the information which does not need to be approved or approval completion information, and starting the next process.
2. The dynamic management method for construction settlement whole-process construction cost according to claim 1, characterized in that the prediction step of construction material cost required by the next process of the construction is as follows:
the method comprises the steps that building materials required by the next process of the project are taken as query objects one by one from a preset first database which stores the finished processes of the project and actual unit weight prices of different building materials of the corresponding processes, and the unit weight prices of each building material required by the next process in the finished processes are queried and obtained;
if the building materials required by the next process of the engineering are all obtained by querying the first database, constructing a weight formula one by one based on the mean value of the unit weight prices of the finished processes of the building materials and the unit weight price of the last application of the corresponding building materials, wherein the weight formula is as follows: zi=(A1+....Ai+....An)/n*q1+An*q2N represents the total number of processes using the corresponding building material, AiRepresents the unit weight price of the building material at the ith application process, AnRepresenting the unit weight price of the building material at the nth application of the building material, wherein the nth application also refers to the latest application of the building material, q1Q is the weight ratio of the mean value of the finished process unit weight prices of the building materials2The weight ratio of the unit weight price of the last application of the corresponding building material is Z, and the unit weight price of the corresponding building material is Z;
obtaining the unit weight price of the building materials required to be applied in the next process, multiplying the unit weight price by the weight of the same building material required to be applied in the next process, obtaining the total cost of the building materials required to be applied in the next process one by one, and adding the total cost of each building material required to be applied in the next process to obtain the building material cost required by the next process;
if the building materials required by the next process of the project are not inquired and obtained in the first database, determining the building materials which are not inquired and obtained, and taking the product of the unit weight price of the building materials which are not inquired and obtained in the local area and the weight of the corresponding building materials which are not inquired and obtained as the cost of the building materials which are not inquired and obtained in the next process;
and taking the sum of the cost of all the building materials obtained by the first database which is not inquired in the next process and the cost of all the building materials obtained by the first database which is inquired in the next process as the building material cost required by the next process of the project.
3. The dynamic management method for construction settlement whole-process construction cost according to claim 1, characterized in that: the steps for predicting the personnel cost required by the next process of the project are as follows:
acquiring the actual wages of the wage technicians in the finished process in the next process in the unit time by taking the wage technicians required by the next process as query objects from a preset second database storing the finished process of the project and the actual wages in the unit time of the different wage technicians in the corresponding process;
screening out the wages in unit time given by the technicians of the work type required by the next process of the engineering for the last time, multiplying the wages by the product of the time consumption of the work type corresponding to the next process and the number of the technicians of the work type required by the next process, and taking the finally obtained product as the expense expenditure of the technicians of the work type required by the next process of the engineering;
and taking the sum of the expenses of all the workers and technicians required by the next process as the expense of the personnel required by the next process of the project.
4. The dynamic management method for construction settlement whole-process construction cost according to claim 1, characterized in that: the procedure for identifying whether an approval is required and the personnel to be approved accordingly, based on the predicted deviation of the expenditure, is as follows:
acquiring an expense deviation range in which the predicted expense deviation falls and a contact way of an approving person corresponding to the corresponding expense deviation range from a preset third database in which the expense deviation range is stored and the contact way of the approving person corresponding to the corresponding expense deviation range are stored by taking the predicted expense deviation as a query object;
if the predicted expense deviation is not queried in the third database to obtain a corresponding expense deviation range, judging that approval is not needed; otherwise, determining approval and synchronously determining the persons to be approved.
5. The dynamic management method for construction settlement whole-process construction cost according to claim 1, characterized in that: if the examination and approval is needed, the step of sending information to the terminal equipment of the examination and approval personnel to remind the examination and approval personnel of examination and approval is as follows:
sending the approval information to the terminal equipment of the confirmed approval personnel;
if the approval personnel do not confirm within the preset time, the position of the terminal equipment of the approval personnel is obtained, the approval personnel closest to the confirmed approval personnel is selected as generation reminding personnel based on the position of the terminal equipment of the approval personnel and the positions of the terminals of the other approval personnel, and the generation reminding information and the path information from the generation reminding personnel to the confirmed approval personnel are sent to the terminal equipment of the generation reminding personnel.
6. The dynamic management method for the construction cost in the whole process of engineering settlement as claimed in claim 5, wherein if the approval is required, the step of sending information to the terminal equipment of the approver to remind the approver of approval further comprises the step of sending the approval information to the confirmed approver synchronously, wherein the approver is reminded synchronously by voice dialing.
7. A dynamic project settlement whole-process construction cost management system, comprising a memory, a processor and a program stored in the memory and capable of running on the processor, wherein the program can be loaded and executed by the processor to realize the dynamic project settlement whole-process construction cost management method according to any one of claims 1 to 6.
8. A computer storage medium, characterized in that: a program capable of being loaded and executed by a processor to implement the dynamic management method for construction settlement overall-process construction costs according to any one of claims 1 to 6.
CN202011630166.3A 2020-12-31 2020-12-31 Dynamic management method, system and storage medium for whole engineering settlement process cost Active CN112734366B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011630166.3A CN112734366B (en) 2020-12-31 2020-12-31 Dynamic management method, system and storage medium for whole engineering settlement process cost

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011630166.3A CN112734366B (en) 2020-12-31 2020-12-31 Dynamic management method, system and storage medium for whole engineering settlement process cost

Publications (2)

Publication Number Publication Date
CN112734366A true CN112734366A (en) 2021-04-30
CN112734366B CN112734366B (en) 2023-09-15

Family

ID=75608291

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011630166.3A Active CN112734366B (en) 2020-12-31 2020-12-31 Dynamic management method, system and storage medium for whole engineering settlement process cost

Country Status (1)

Country Link
CN (1) CN112734366B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114792176A (en) * 2022-06-24 2022-07-26 北京天辰信科技有限公司 Engineering cost prediction method and system based on engineering data and field data

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105956788A (en) * 2016-05-24 2016-09-21 国家电网公司 Dynamic management control method for cost of power transmission and transformation project
US20170308934A1 (en) * 2016-04-22 2017-10-26 Economy Research Institute of State Grid Zhejiang Electric Power Management method of power engineering cost
CN110490442A (en) * 2019-08-07 2019-11-22 嘉兴市华信工程咨询有限公司 A kind of Engineering Cost Consulting project risk management system and method
CN110570133A (en) * 2019-09-18 2019-12-13 赖玲玲 building engineering dynamic cost analysis and control system based on big data
CN111008816A (en) * 2019-11-23 2020-04-14 湖南新泉工程造价咨询有限公司 Dynamic management method for construction cost in whole process of engineering settlement
CN111695833A (en) * 2020-06-22 2020-09-22 陕西国防工业职业技术学院 Engineering cost risk prediction and assessment method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20170308934A1 (en) * 2016-04-22 2017-10-26 Economy Research Institute of State Grid Zhejiang Electric Power Management method of power engineering cost
CN105956788A (en) * 2016-05-24 2016-09-21 国家电网公司 Dynamic management control method for cost of power transmission and transformation project
CN110490442A (en) * 2019-08-07 2019-11-22 嘉兴市华信工程咨询有限公司 A kind of Engineering Cost Consulting project risk management system and method
CN110570133A (en) * 2019-09-18 2019-12-13 赖玲玲 building engineering dynamic cost analysis and control system based on big data
CN111008816A (en) * 2019-11-23 2020-04-14 湖南新泉工程造价咨询有限公司 Dynamic management method for construction cost in whole process of engineering settlement
CN111695833A (en) * 2020-06-22 2020-09-22 陕西国防工业职业技术学院 Engineering cost risk prediction and assessment method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114792176A (en) * 2022-06-24 2022-07-26 北京天辰信科技有限公司 Engineering cost prediction method and system based on engineering data and field data

Also Published As

Publication number Publication date
CN112734366B (en) 2023-09-15

Similar Documents

Publication Publication Date Title
US20210295984A1 (en) Optimized patient schedules based on patient workflow and resource availability
US7212987B2 (en) System and method for planning a design project, coordinating project resources and tools and monitoring project progress
Maass et al. Incorporating nurse absenteeism into staffing with demand uncertainty
US20190147379A1 (en) Risk assessment and mitigation planning, systems and methods
US8015043B2 (en) Method and apparatus for workforce demand forecasting
WO2001026011A1 (en) Method and estimator for providing operation management strategic planning
Kayis et al. IRMAS–development of a risk management tool for collaborative multi‐site, multi‐partner new product development projects
Moon et al. Process-waste reduction in the construction supply chain using proactive information network
Karimi-Majd et al. A reinforcement learning methodology for a human resource planning problem considering knowledge-based promotion
US20150242782A1 (en) Interactive Planning Method And Tool
Dakhil et al. BIM benefits-maturity relationship awareness among UK construction clients
US8867728B2 (en) Managing reserve agents in a contact center
CN112734366A (en) Dynamic management method, system and storage medium for construction cost in whole process of engineering settlement
US20090063223A1 (en) Systems and methods for assessing the level of conformance of a business process
Alpers et al. A systematic approach for evaluation and selection of ERP systems
CN115796814B (en) Construction management method and system
CN116630082A (en) Method and device for allocating production resources, electronic equipment and storage medium
CN115423305A (en) IT service management method and device and server
CN113205221A (en) Work amount evaluation-based construction period prediction method
JP2003067535A (en) Interview support system
JPH086783A (en) Software quality guarantee supporting device
US20170315980A1 (en) System that documents work to be performed at a specific location over a specific period of time by specific personnel on designated equipment by guiding a human user to create a unique, accurate, and complete method of procedure document
JP2006119917A (en) Process management support system, process management support method, and process management support program
WO2017187197A1 (en) A system that creates a unique calendar event for an associated calendar resource in a standard calendaring system, for work to be performed in a critical infrastructure environment, based on a method of procedure document.
Snijkers et al. Planning the survey

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant