JP2011001735A - Bridge pier post structure, bridge pier post system, and construction method of the same - Google Patents
Bridge pier post structure, bridge pier post system, and construction method of the same Download PDFInfo
- Publication number
- JP2011001735A JP2011001735A JP2009145035A JP2009145035A JP2011001735A JP 2011001735 A JP2011001735 A JP 2011001735A JP 2009145035 A JP2009145035 A JP 2009145035A JP 2009145035 A JP2009145035 A JP 2009145035A JP 2011001735 A JP2011001735 A JP 2011001735A
- Authority
- JP
- Japan
- Prior art keywords
- top surface
- cushion
- bridge
- pier column
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は橋脚柱構造と橋脚柱システム及びその施行方法に関する。 The present invention relates to a pier column structure, a pier column system, and an implementation method thereof.
従来の橋梁構造は、通常、橋脚柱構造、橋脚土台及び橋構造を含む。橋脚土台は、たびたび橋脚柱構造の基部に設置して橋構造に特定の支持力を提供し、橋脚柱は、橋構造のコンクリート構造を直接支えるのに用いられる。橋梁構造は、しばしば異なる設計に応じて支持力を調整するので、橋脚土台、橋脚柱構造及び橋構造はそれに基づき相応の調整を行う。一般の橋脚柱構造は通常円柱状であり、その下部は、通常橋脚土台と接続して強固な橋脚コンクリート構造を形成する。橋構造を橋脚構造上に設置すると、橋梁構造は完成する。 Conventional bridge structures typically include pier column structures, pier foundations, and bridge structures. The pier foundation is often installed at the base of the pier column structure to provide specific support for the bridge structure, and the pier column is used to directly support the concrete structure of the bridge structure. Bridge structures often adjust the bearing capacity according to different designs, so the pier foundation, pier column structure and bridge structure will be adjusted accordingly. The general pier column structure is usually cylindrical, and its lower part is usually connected to the pier base to form a strong pier concrete structure. When the bridge structure is installed on the pier structure, the bridge structure is completed.
しかしながら、一般の橋脚構造と橋構造の接続方法は、しばしばプレキャストの橋構造によって掛けて吊るすことで円形の橋脚柱上に設置した後、グラウティング方法で橋構造と橋脚柱構造を接続する。しかしながら、接続箇所の鉄筋の配筋方法は、通常、接続区域が狭くて小さいという制限を受け、このため、鉄筋とコンクリートの保持力は通常不足し、予想を超えた外部圧力に対抗することができない。従って、大地震が来た時、たびたび橋脚と橋構造の接続箇所は橋梁の損傷箇所となる。上記の問題点に鑑み、本発明者は、上述の欠点を改善並びに解決するために、度重なる研究と学術理論の運用の配合により、上述の欠点を改善するのに合理的で有効な設計である本発明を提出する。 However, a common pier structure and bridge structure connection method is that the bridge structure and the pier column structure are connected by a grouting method after being installed on a circular pier column by hanging by a precast bridge structure. However, the method of reinforcing bars at the connection point is usually limited by the fact that the connection area is narrow and small, so that the holding force between the reinforcing bar and concrete is usually insufficient, and it can resist external pressure beyond expectations. Can not. Therefore, when a large earthquake occurs, the connection point between the pier and the bridge structure often becomes a damaged part of the bridge. In view of the above problems, the present inventor has a rational and effective design for improving the above-mentioned drawbacks by combining repeated research and operation of academic theory in order to improve and solve the above-mentioned drawbacks. A certain present invention is submitted.
本発明の主な目的は、施行期間を短縮することができる橋脚柱構造と橋脚柱システムを提供することにある。 The main objective of this invention is to provide the pier column structure and pier column system which can shorten an enforcement period.
本発明のもう一つの目的は、鉄筋コンクリートの保持力を強化することができる橋脚柱構造と橋脚柱システム及びその方法を提供することにある。 Another object of the present invention is to provide a pier column structure, a pier column system, and a method thereof that can reinforce the retention of reinforced concrete.
本発明の橋脚柱システムは、橋脚柱構造と少なくとも一つの緩衝クッション及び橋構造を含む。橋脚柱構造は、本体、少なくとも一つの凹溝構造、少なくとも一つの網状配筋構造及び固定板を含む。本体は頂面と底面を有し、頂面と底面は相互に対応し、相互に平行であることが好ましいが、これに限定されない。少なくとも一つの凹溝構造は頂面に設置され、凹溝構造の開口部は頂面に設置される。従って、凹溝構造は、頂面と同じ高さの開口部によって橋構造と相互に対応する。その他、凹溝構造は凹溝底面を有し、この凹溝底面は、本体の頂面と平行であるのが好ましいが、これに限定されない。 The pier column system of the present invention includes a pier column structure and at least one cushion cushion and a bridge structure. The pier column structure includes a main body, at least one concave groove structure, at least one reticulated reinforcement structure, and a fixing plate. The main body has a top surface and a bottom surface, and the top surface and the bottom surface preferably correspond to each other and are parallel to each other, but are not limited thereto. At least one groove structure is installed on the top surface, and the opening of the groove structure is installed on the top surface. Accordingly, the concave groove structure corresponds to the bridge structure by an opening having the same height as the top surface. In addition, the groove structure has a groove bottom surface, which is preferably parallel to the top surface of the main body, but is not limited thereto.
以下、添付図面を参照して本発明の実施の形態を詳細に説明する。 Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
図1に示すように、橋脚柱構造100は、本体200、少なくとも一つの凹溝構造300、少なくとも一つの網状配筋構造400、及び固定板(図示せず)を含み、凹溝構造300は頂面210上に設置され、これにより、凹溝構造300の開口部310と頂面210は同じ高さになる。その他、凹溝構造300は、凹溝構造開口部310に対応する凹溝底面(図示せず)を有する。凹溝底面は、複数個の空洞320を有し、網状配筋構造400は凹溝構造300内に設置され、前記網状配筋構造400と本体200内の鉄筋(図示せず)は相互に接続する。又、網状配筋構造400は、凹溝構造300の設計に応じて本体200を露出する以外に、その網状配筋構造400は、主に上層鉄筋網(図示せず)と下層鉄筋網(図示せず)が交錯することで形成される。上層鉄筋層、下層鉄筋層を問わず、凹溝底面と平行であるのが好ましいが、これに限定されない。本体200は柱体220を含むのが好ましく、柱体220は底面230と接続し本体200を支持する。前記本体200と柱体220はグラウティングによって一体成形することもできる。 As shown in FIG. 1, the pier column structure 100 includes a main body 200, at least one concave groove structure 300, at least one reticulated reinforcement structure 400, and a fixing plate (not shown). It is installed on the surface 210, so that the opening 310 and the top surface 210 of the groove structure 300 are at the same height. In addition, the groove structure 300 has a groove bottom surface (not shown) corresponding to the groove structure opening 310. The bottom surface of the groove has a plurality of cavities 320, and the reticulated reinforcement structure 400 is installed in the recessed groove structure 300, and the reticulated reinforcement structure 400 and the reinforcing bars (not shown) in the main body 200 are connected to each other. To do. Further, the reticulated bar arrangement structure 400 mainly exposes the main body 200 according to the design of the concave groove structure 300, and the reticulated bar arrangement structure 400 mainly includes an upper layer reinforcing bar net (not shown) and a lower layer reinforcing bar net (see FIG. (Not shown). Regardless of the upper reinforcing steel layer or the lower reinforcing steel layer, it is preferably parallel to the bottom surface of the groove, but is not limited thereto. The main body 200 preferably includes a column body 220, and the column body 220 is connected to the bottom surface 230 and supports the main body 200. The main body 200 and the column 220 can be integrally formed by grouting.
図2に示すように、前記複数の鉄筋330は網状配筋構造400を通り抜け、空洞320に入り込んだ後、底面230に接続される。その接続関係は、ネジ締め、溶接、縛りつけ、又はその他の同様の機能を提供できる接続方法を含むが、これに限定されない。複数の鉄筋330を底面230に接続した後、本体200は、鉄筋330とコンクリート構造の保持力によって、外部圧力を分散し破壊されるのを避けることができる。 As shown in FIG. 2, the plurality of reinforcing bars 330 pass through the reticulated reinforcement structure 400, enter the cavity 320, and then are connected to the bottom surface 230. The connection relationship includes, but is not limited to, connection methods that can provide screw tightening, welding, tying, or other similar functions. After the plurality of reinforcing bars 330 are connected to the bottom surface 230, the main body 200 can be prevented from being dispersed and broken due to the holding force of the reinforcing bars 330 and the concrete structure.
図3に示すように、複数のボルト340は凹溝構造300の周りに垂直に設置され、ボルト340の軸方向は、凹溝構造開口部310の開口方向に平行で、且つお凹溝底面370上に設置する。前記ボルト340上にはネジを有し、ナット350はボルト340のネジ山と螺合することで上下に位置を調整できる。ナット350の上にはガスケット360を設置することができ、物体をガスケット360に設置する時、物体の重量をガスケット360に均等に分散して、ボルト340に伝達させることができる。 As shown in FIG. 3, the plurality of bolts 340 are vertically installed around the concave groove structure 300, and the axial direction of the bolts 340 is parallel to the opening direction of the concave groove structure opening 310 and the concave groove bottom surface 370. Install on top. A screw is provided on the bolt 340, and the nut 350 can be adjusted in the vertical direction by screwing with a screw thread of the bolt 340. A gasket 360 can be installed on the nut 350. When an object is installed on the gasket 360, the weight of the object can be evenly distributed to the gasket 360 and transmitted to the bolt 340.
図4に示すように、前記固定板500は、網状配筋構造400上に設置する頂部表面510を有する。その内、固定板500は、ボルト340が締めたナット350のガスケット360(図示せず)の上に設置するが、網状配筋構造400上に設置することもできる。その他、固定板500の頂部表面510の垂直高さは頂面210より低くない。固定板500の材質は、アルミニウム鉄合金、鋼、ステンレス、アルミニウム合金等の錆びにくい金属とすることができる。従って、本発明の金属固定板500は、上方の物体の強大な圧力に、より対抗することができるようになる。 As shown in FIG. 4, the fixing plate 500 has a top surface 510 that is installed on a reticulated reinforcing bar structure 400. Among them, the fixing plate 500 is installed on the gasket 360 (not shown) of the nut 350 tightened by the bolt 340, but can also be installed on the reticulated bar arrangement structure 400. In addition, the vertical height of the top surface 510 of the fixing plate 500 is not lower than the top surface 210. The material of the fixing plate 500 can be a rust-resistant metal such as an aluminum iron alloy, steel, stainless steel, or aluminum alloy. Therefore, the metal fixing plate 500 of the present invention can more effectively resist the strong pressure of the object above.
図5に示すように、前記固定板500の底部表面(図示せず)の垂直高さは頂面210と同じである。プレスモールドによってグラウティングし、さらにボルト340を取り出した後、コンクリート基礎600は完成する。また、ボルト340を取り出さないでコンクリート基礎600を完成させることもできる。 As shown in FIG. 5, the vertical height of the bottom surface (not shown) of the fixing plate 500 is the same as that of the top surface 210. After grouting with a press mold and further removing the bolt 340, the concrete foundation 600 is completed. Further, the concrete foundation 600 can be completed without removing the bolt 340.
図6に示すように、前記緩衝クッション700は固定板500上に固定し、緩衝クッション700は固定板500によって本体200に接続される。その接続方法は、ネジ締め、溶接、リベット留め、又はその他の同様の機能を提供できる接続方法にすることもできる。緩衝クッション700を固定板500と接続し固定すると、本発明の橋脚柱構造100は完成する。 As shown in FIG. 6, the cushion cushion 700 is fixed on a stationary plate 500, and the cushion cushion 700 is connected to the main body 200 by the stationary plate 500. The connection method can also be a connection method that can provide screw tightening, welding, riveting, or other similar functions. When the cushion cushion 700 is connected to the fixing plate 500 and fixed, the pier column structure 100 of the present invention is completed.
図7に示すように、少なくとも一つのジャッキ800は頂面210に設置し、橋構造(図示せず)を緩衝クッション700上に架設する時、緩衝を提供する。図8に示すように、橋構造820は、橋構造モジュール830と橋構造モジュール830に設置した鉄筋籠構造840を含む。コンクリート850を橋構造モジュール830に流し込んだ時、乾燥するのを待ち、橋構造モジュール830を取り外した後、図9に示す橋構造820が形成され、橋脚柱システム900が完成する。その他の実施例(図示せず)において、橋構造820は必ずしも橋構造モジュール830を取り外さなければならないわけではなく、橋構造モジュール830自体を橋構造820の一部分にすることもできる。 As shown in FIG. 7, at least one jack 800 is installed on the top surface 210 and provides a cushion when a bridge structure (not shown) is installed on the cushion cushion 700. As shown in FIG. 8, the bridge structure 820 includes a bridge structure module 830 and a reinforcing bar structure 840 installed in the bridge structure module 830. When the concrete 850 is poured into the bridge structure module 830, it waits for it to dry, and after removing the bridge structure module 830, the bridge structure 820 shown in FIG. 9 is formed, and the pier column system 900 is completed. In other embodiments (not shown), the bridge structure 820 does not necessarily have to remove the bridge structure module 830, and the bridge structure module 830 itself can be part of the bridge structure 820.
図10の橋脚柱システム施工方法のフローチャートに示すように、本発明の施行方法は、下記の手順を含む。手順4010は橋脚柱構造を提供する。その内、橋脚柱構造は、本体、少なくとも一つの凹溝構造及び少なくとも一つの網状配筋構造を含み、その相互接続関係は上述の実施例に記載した通りである。手順4030は、固定板を網状配筋構造上に設置する。固定板を設置する手順4030においては、更に、固定板を網状配筋構造に設置することで、固定板を本体と接続する。手順4050は、緩衝クッションを固定板上に設置する。緩衝クッションを設置する手順4050において、緩衝クッションと固定板の接続関係は、ネジ締め、溶接、縛りつけ又は同様の機能を提供できる接続方法を含むがそれに限定されない。一旦接続すれば、橋脚柱構造は完成する。手順4070は、橋構造を緩衝クッション上に架設する。この橋構造を架設する手順4070によって、橋構造は緩衝クッション上に設置され、橋脚柱システムが完成する。 As shown in the flowchart of the pier column system construction method in FIG. 10, the enforcement method of the present invention includes the following procedure. Procedure 4010 provides a pier column structure. Among them, the pier column structure includes a main body, at least one concave groove structure, and at least one reticulated reinforcing bar structure, and the interconnection relationship is as described in the above embodiments. In step 4030, the fixing plate is installed on the reticulated reinforcement structure. In the procedure 4030 for installing the fixing plate, the fixing plate is further connected to the main body by installing the fixing plate in the mesh reinforcing structure. Procedure 4050 installs a cushion cushion on a fixed plate. In the procedure 4050 for installing the cushion cushion, the connection relationship between the cushion cushion and the fixing plate includes, but is not limited to, a connection method capable of providing screw fastening, welding, binding, or the like. Once connected, the pier column structure is complete. Procedure 4070 builds the bridge structure on the cushion cushion. By the procedure 4070 for constructing the bridge structure, the bridge structure is installed on the cushion cushion and the bridge pier system is completed.
図11のフローチャートに示すように、橋脚柱システム施工方法は更に、複数個の空洞を凹溝底面に設置する手順4011を含む。この設置方法は、ドリルでの穴あけ、鑿での穴あけ等の方法を含むが、これに限定されない。その内、空洞を設置する手順4011は、更に、複数の鉄筋を空洞に設置し、鉄筋コンクリート構造全体の保持力を強化する手順4012を含む。又、固定板を設置する手順4030は、更に、凹溝構造内にグラウティングし固定板を位置決めさせる手順4031を含み、その内、固定板は頂部表面を有し、この頂部表面の垂直高さは本体の頂面より低くない。その他、橋脚柱システム施工方法は、橋構造を支えるために少なくとも一つのジャッキを頂面に架設する手順4055も含む。図11に示すように、橋構造を架設する手順4070は、橋構造モジュールを緩衝クッション上に設置する手順4071を含み、その内、橋構造モジュールを設置する手順4071は、橋構造モジュール内にグラウティングし、コンクリート構造が乾燥するのを待つ手順4072を含み、橋構造モジュールを設置する手順4071は、更に、橋構造モジュールを取り外して橋脚柱システムを完成させる手順4073を含む。しかしながら、その他の実施例においては、橋構造モジュールを取り外す手順4073を行わずに、橋脚柱システムを完成させることもできる。 As shown in the flowchart of FIG. 11, the pier column system construction method further includes a procedure 4011 for installing a plurality of cavities on the bottom surface of the groove. Although this installation method includes methods, such as drilling with a drill and drilling with a scissors, it is not limited to this. Among them, the procedure 4011 for installing the cavity further includes a procedure 4012 for installing a plurality of reinforcing bars in the cavity and strengthening the holding force of the entire reinforced concrete structure. The procedure 4030 for installing the fixing plate further includes a procedure 4031 for grouting in the groove structure and positioning the fixing plate, of which the fixing plate has a top surface, and the vertical height of the top surface. Is not lower than the top surface of the body. In addition, the pier column system construction method also includes a procedure 4055 for laying at least one jack on the top surface to support the bridge structure. As shown in FIG. 11, the procedure 4070 for installing the bridge structure includes a procedure 4071 for installing the bridge structure module on the cushion cushion, and among them, the procedure 4071 for installing the bridge structure module is included in the bridge structure module. The procedure 4071 includes installing and waiting for the concrete structure to dry, and installing the bridge structure module 4071 further includes a procedure 4073 for removing the bridge structure module and completing the pier column system. However, in other embodiments, the pier column system can be completed without performing the procedure 4073 of removing the bridge structure module.
100 橋脚柱構造
200 本体
210 頂面
220 柱体
230 底面
300 凹溝構造
300 凹溝構造開口部
320 空洞
330 鉄筋
340 ボルト
350 ナット
360 ガスケット
370 凹溝底面
400 網状配筋構造
500 固定板
510 頂部表面
600 コンクリート基礎
700 緩衝クッション
800 ジャッキ
820 橋構造
830 橋構造モジュール
840 鉄筋籠構造
850 コンクリート
900 橋脚柱システム
DESCRIPTION OF SYMBOLS 100 Pier structure 200 Main body 210 Top surface 220 Column body 230 Bottom surface 300 Concave structure 300 Concave structure opening 320 Cavity 330 Reinforcing bar 340 Bolt 350 Nut 360 Gasket 370 Concave groove bottom surface 400 Reinforcement structure 500 Fixing plate 510 Top surface 600 Concrete foundation 700 Buffer cushion 800 Jack 820 Bridge structure 830 Bridge structure module 840 Reinforced steel structure 850 Concrete 900 Bridge pier system
Claims (3)
前記本体は頂面と底面を有し、前記底面は柱体に接続し、
前記凹溝構造は前記頂面に設置し、前記凹溝構造は凹溝底面を有し、並びに、凹溝底面には複数個の空洞を設置し、
前記網状配筋構造は前記凹溝構造内に設置し、
前記固定板は底部表面を有し、且つ前記固定板は前記網状配筋構造上に設置し、前記底部表面の垂直高さは前記頂面より高くないことを特徴とする、橋脚柱構造。 A pier column structure, including a main body, at least one groove structure, at least one reticulated reinforcement structure, and a fixing plate,
The main body has a top surface and a bottom surface, and the bottom surface is connected to a column,
The groove structure is installed on the top surface, the groove structure has a groove bottom surface, and a plurality of cavities are installed on the groove bottom surface,
The reticulated bar arrangement is installed in the groove structure,
The pier column structure, wherein the fixing plate has a bottom surface, and the fixing plate is installed on the reticulated reinforcement structure, and the vertical height of the bottom surface is not higher than the top surface.
前記橋脚柱構造は、本体、少なくとも一つの凹溝構造、少なくとも一つの網状配筋構造、固定板、少なくとも一つの緩衝クッション、及び橋構造を含み、
前記本体は、頂面と底面を有し、
前記凹溝構造は前記頂面に設置し、前記凹溝構造は凹溝底面を有し、
前記網状配筋構造は前記凹溝構造内に設置し、
前記固定板は頂部表面を有し、且つ、前記固定板は前記網状配筋構造上に設置し、前記頂部表面の垂直高さは前記頂面より低くなく、
前記緩衝クッションは前記固定板上に設置し、
前記橋構造は前記緩衝クッション上に設置することを特徴とする、橋脚柱システム。 A pier column system, including a pier column structure,
The pier column structure includes a main body, at least one concave groove structure, at least one reticulated reinforcement structure, a fixing plate, at least one buffer cushion, and a bridge structure,
The body has a top surface and a bottom surface;
The groove structure is installed on the top surface, the groove structure has a groove bottom surface;
The reticulated bar arrangement is installed in the groove structure,
The fixing plate has a top surface, and the fixing plate is installed on the reticulated reinforcement structure, and the vertical height of the top surface is not lower than the top surface,
The cushion cushion is installed on the fixed plate,
The bridge pier system, wherein the bridge structure is installed on the cushion cushion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009145035A JP2011001735A (en) | 2009-06-18 | 2009-06-18 | Bridge pier post structure, bridge pier post system, and construction method of the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009145035A JP2011001735A (en) | 2009-06-18 | 2009-06-18 | Bridge pier post structure, bridge pier post system, and construction method of the same |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2011001735A true JP2011001735A (en) | 2011-01-06 |
Family
ID=43559914
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2009145035A Pending JP2011001735A (en) | 2009-06-18 | 2009-06-18 | Bridge pier post structure, bridge pier post system, and construction method of the same |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2011001735A (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH062313A (en) * | 1992-06-18 | 1994-01-11 | Bridgestone Corp | Level adjustment of bearing part |
JPH08246668A (en) * | 1995-03-07 | 1996-09-24 | Tokyu Constr Co Ltd | Box draft form |
JP2009019493A (en) * | 2007-06-15 | 2009-01-29 | Bbm:Kk | Renewal method and renewal structure for existing bearing apparatus |
-
2009
- 2009-06-18 JP JP2009145035A patent/JP2011001735A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH062313A (en) * | 1992-06-18 | 1994-01-11 | Bridgestone Corp | Level adjustment of bearing part |
JPH08246668A (en) * | 1995-03-07 | 1996-09-24 | Tokyu Constr Co Ltd | Box draft form |
JP2009019493A (en) * | 2007-06-15 | 2009-01-29 | Bbm:Kk | Renewal method and renewal structure for existing bearing apparatus |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100837608B1 (en) | J.K Bracket Method | |
JP3184322U (en) | Solar panel mount | |
JP2013112926A (en) | Foundation structure for photovoltaic generation device, and construction method for the same | |
CN109629424B (en) | Cantilever support and construction method of concrete flange of steel-concrete combined bridge using cantilever support | |
CN102277835A (en) | Method for constructing single-column bent cap by adopting hoop and A-frame composite system | |
CN105544762A (en) | Method for installing seismic isolation layer | |
JP5192251B2 (en) | Tower crane support structure and construction method thereof | |
CN104831639A (en) | Consolidation and release construction method for 0# blocks of ultra-wide non-uniform continuous beam | |
CN202611233U (en) | Template for pouring double-way shear wall with deformation joint in the middle | |
JP2017180058A (en) | Suspension structure with insert fitted on deck plate with reinforcement truss and ceiling equipment hung and supported underneath on lower floor, and fitting method for ceiling equipment underneath deck plate with reinforcement truss using insert | |
CN114517585A (en) | Accurate installation method for building shock insulation support | |
CN104895221B (en) | Assembled shaped steel confined concrete shear wall structure | |
KR20100073881A (en) | Dummy bearing for bridge using sand and upper structure of bridge supporting method thterewith | |
KR20110029454A (en) | Reinforcing structure | |
CN203514200U (en) | Pin rod support for bridge capping beam construction | |
CN109610338B (en) | Construction method for preventing slurry leakage at bottom opening of tower column of suspension bridge | |
CN109441118B (en) | Distributing machine pouring system and method for assembled building construction concrete | |
JP2011001735A (en) | Bridge pier post structure, bridge pier post system, and construction method of the same | |
CN114214961B (en) | Integral-lowering underwater bearing platform mounting structure | |
CN210622366U (en) | Underpinning processing device for damaged reinforced concrete column | |
JP2002339496A (en) | Construction method of slab and construction method of ceiling | |
CN104532743A (en) | Tower girder fixed-connection mechanism, corresponding cable-stayed bridge and building method of cable-stayed bridge | |
JP2001140221A (en) | Repair method for overhanging floor slab, and support construction for form | |
JPH08269912A (en) | Fastening method of steel bridge pier to footing | |
TWI421393B (en) | Pier structure, pier system therewith and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20101108 |
|
A601 | Written request for extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A601 Effective date: 20110204 |
|
A602 | Written permission of extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A602 Effective date: 20110209 |
|
A601 | Written request for extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A601 Effective date: 20110304 |
|
A602 | Written permission of extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A602 Effective date: 20110317 |
|
A601 | Written request for extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A601 Effective date: 20110405 |
|
A602 | Written permission of extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A602 Effective date: 20110418 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20110711 |