JP2010257407A - Scheduling device - Google Patents
Scheduling device Download PDFInfo
- Publication number
- JP2010257407A JP2010257407A JP2009109671A JP2009109671A JP2010257407A JP 2010257407 A JP2010257407 A JP 2010257407A JP 2009109671 A JP2009109671 A JP 2009109671A JP 2009109671 A JP2009109671 A JP 2009109671A JP 2010257407 A JP2010257407 A JP 2010257407A
- Authority
- JP
- Japan
- Prior art keywords
- tank
- mixing
- schedule
- piping
- product
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 claims abstract description 57
- 239000011159 matrix material Substances 0.000 claims abstract description 37
- 238000004364 calculation method Methods 0.000 claims abstract description 27
- 238000004140 cleaning Methods 0.000 claims abstract description 25
- 230000008859 change Effects 0.000 claims abstract description 8
- 238000002156 mixing Methods 0.000 claims description 99
- 238000007689 inspection Methods 0.000 claims description 6
- 238000013500 data storage Methods 0.000 claims description 4
- 238000002922 simulated annealing Methods 0.000 claims description 4
- 238000011049 filling Methods 0.000 description 86
- 238000004519 manufacturing process Methods 0.000 description 69
- 239000003921 oil Substances 0.000 description 37
- 230000014509 gene expression Effects 0.000 description 24
- 230000008569 process Effects 0.000 description 24
- 239000010687 lubricating oil Substances 0.000 description 17
- 238000003860 storage Methods 0.000 description 14
- 239000002994 raw material Substances 0.000 description 13
- 230000006870 function Effects 0.000 description 12
- 239000010779 crude oil Substances 0.000 description 7
- 238000010586 diagram Methods 0.000 description 7
- 230000009467 reduction Effects 0.000 description 5
- 239000000314 lubricant Substances 0.000 description 4
- 239000000203 mixture Substances 0.000 description 3
- 238000002360 preparation method Methods 0.000 description 3
- 238000005406 washing Methods 0.000 description 3
- 238000004220 aggregation Methods 0.000 description 2
- 230000002776 aggregation Effects 0.000 description 2
- 238000005429 filling process Methods 0.000 description 2
- 238000009472 formulation Methods 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 238000011068 loading method Methods 0.000 description 2
- 239000003208 petroleum Substances 0.000 description 2
- 238000011144 upstream manufacturing Methods 0.000 description 2
- 239000002199 base oil Substances 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 239000003209 petroleum derivative Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 230000003442 weekly effect Effects 0.000 description 1
- 210000000707 wrist Anatomy 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Abstract
Description
本発明は、複数種類の原料を混合して、多品種の製品を生産することが可能な混合プラントにおける作業スケジュールを作成するスケジューリング装置に関する。 The present invention relates to a scheduling apparatus that creates a work schedule in a mixing plant capable of producing a variety of products by mixing a plurality of types of raw materials.
従来のスケジューリング方法として、特開平11−53006号公報がある。この公報に記載されたスケジューリング方法では、所定作業のシステムに与えられた複数のジョブに対して、ジョブを実施する所定作業を工程毎に分割し、この各工程毎に、このジョブの工程での作業を行うための情報を取り込み、それぞれの作業スケジュールの作成と、各工程間でスケジュールを作成するための情報交換との処理ステップを繰り返して、システム全体の作業スケジュールを作成するものである。 As a conventional scheduling method, there is JP-A-11-53006. In the scheduling method described in this publication, for a plurality of jobs given to a system of predetermined work, the predetermined work for performing the job is divided for each process, and for each process, the process of this job is divided. Information for performing work is taken in, and processing steps of creation of each work schedule and information exchange for creating a schedule between each process are repeated to create a work schedule for the entire system.
また、複数種類の原料を混合して、多品種の製品を生産することが可能な混合プラントとして、例えば、潤滑油混合プラントがある。潤滑油混合プラントの混合工程では、基油タンクから原料を移送し、バッチブレンダや連続ブレンダによって混合する。混合された潤滑油は、タンクで貯留され、充填ラインを介してドラム缶、ローリー車へ充填されて、製品として出荷される。 Further, as a mixing plant capable of mixing a plurality of types of raw materials to produce a wide variety of products, for example, there is a lubricating oil mixing plant. In the mixing process of the lubricating oil mixing plant, the raw material is transferred from the base oil tank and mixed by a batch blender or a continuous blender. The mixed lubricating oil is stored in a tank, filled into drums and lorries through a filling line, and shipped as a product.
また、大型の原油タンカー(VLCC)内の複数種類の原油を複数のタンクに分配する際の、各原油の各タンクへの分配量を決定するためのタンクスケジュール作成支援として、特開平11−167652号公報がある。この公報に記載されたタンクスケジュール作成支援装置では、計算対象原油と計算対象タンクのペアを順次特定しつつ、当該ペア間で、計算対象原油と計算対象タンクのAPI度によって定まる量だけ仮想的な原油移動を行い、仮想的な原油移動が行えなくなった状態で、満たしていない制約条件が残っていた場合には、当該条件に応じたペア間の仮想的な原油移動を禁止した状態で、再度、最初から仮想的な原油移動が行われるようにしている。なお、API度とは、米国石油協会(American Petroleum Institute)が定めた原油および石油製品の比重を示す単位である。 Further, as a tank schedule creation support for determining a distribution amount of each crude oil to each tank when distributing a plurality of types of crude oil in a large-scale crude oil tanker (VLCC) to a plurality of tanks, JP-A-11-167852 There is a gazette. In the tank schedule creation support device described in this publication, a pair of calculation target crude oil and a calculation target tank is identified sequentially, and a virtual amount is determined between the pair according to the API degree of the calculation target crude oil and the calculation target tank. If there are unsatisfied constraint conditions in the state where the crude oil movement is no longer possible and the virtual crude oil movement cannot be performed, the virtual crude oil movement between the pair according to the conditions is prohibited, and again From the beginning, a virtual crude oil movement is carried out. In addition, API degree is a unit which shows the specific gravity of the crude oil and petroleum product which American Petroleum Institute (American Petroleum Institute) established.
また、特開2004−162756号公報に記載された配管システムは、上流側の機器群と、下流側の機器群とを連結する配管システムであって、上流側の機器群のうち複数の機器とを対応させてそれぞれ個別に接続する専用配管と、各専用配管に切替装置を介して接続される循環配管とを備えるものである。このような構成により、少品種の製品を多量に製造する場合には、循環配管を利用することなく各々の系統設備を個別に稼動させて複数の製品を個別に製造することができ、循環配管を利用することにより、主力品種と生産頻度が少ない品種とを工程管理しながら製造することが可能となる。 Moreover, the piping system described in JP-A-2004-162756 is a piping system that connects an upstream device group and a downstream device group, and includes a plurality of devices in the upstream device group. And a dedicated pipe that is individually connected to each other and a circulation pipe that is connected to each dedicated pipe via a switching device. With such a configuration, when manufacturing a small quantity of products in large quantities, it is possible to individually manufacture each product by operating each system facility without using the circulation piping. By using, it becomes possible to manufacture main varieties and varieties with low production frequency while managing the process.
また、スケジューリングシステムとして、特開2000−137502号公報がある。この公報に記載されたスケジューリングシステムは、性状の異なる原料を複数の原料タンクで受け払いするスケジューリングシステムであり、原料毎に複数の要件の組み合わせで原料タンクの受入れ優先順位を設定する手段、払い出し原料の性状変化幅を変化制限値内に抑える払い出し目標値を決定する手段、払い出し性状目標値に最も近くなる払い出しタンクの組み合わせと各タンクからの払い出し流量を選択し決定する手段を有するものである。このような構成により、製造装置による主製品の生産量の制御性を高めるために、製造装置へ払い出す原料の性状を、迅速に精度良く予測し、または制御することができる。 Moreover, there exists Unexamined-Japanese-Patent No. 2000-137502 as a scheduling system. The scheduling system described in this publication is a scheduling system in which raw materials having different properties are received and received by a plurality of raw material tanks, and means for setting the receiving priority of raw material tanks by a combination of a plurality of requirements for each raw material. There are means for determining a payout target value that suppresses the property change range within the change limit value, and means for selecting and determining a combination of payout tanks closest to the payout property target value and a discharge flow rate from each tank. With such a configuration, in order to improve the controllability of the production amount of the main product by the manufacturing apparatus, the properties of the raw material dispensed to the manufacturing apparatus can be predicted or controlled quickly and accurately.
多品種の製品を製造可能な混合プラントでは、タンクの入口側や出口側における配管競合、品目変更時の切り替えによる洗浄コストの削減、混合ロット集約による混合工程の能力向上を考慮した生産計画の立案が求められている。従来の混合プラントにおける生産計画の作成は、現場オペレータの知識や経験によるスケジューリングが行われていたため、その業務効率は、作業者の判断と工夫に頼るものであり、業務効率の向上が求められていた。また、従来は、商用のソフトウェアパッケージをカスタマイズしたスケジューリング装置が主に利用され、混合プラントのさまざまな制約条件を従来のソフトウェアに反映させることは困難であった。 In a mixing plant capable of producing a wide variety of products, drafting a production plan that takes into account piping competition at the inlet and outlet sides of the tank, reduction of cleaning costs by switching when changing items, and improvement of mixing process capability by consolidating mixed lots Is required. Production planning in a conventional mixed plant has been scheduled based on the knowledge and experience of field operators, so the operational efficiency depends on the judgment and ingenuity of the operator, and improvement in operational efficiency is required. It was. Conventionally, a scheduling device in which a commercial software package is customized is mainly used, and it is difficult to reflect various constraint conditions of the mixing plant in the conventional software.
また、特許文献5に記載のスケジュールシステムでは、受入れ優先順位を設定して、スケジュールを作成することができるものの、コストなどの制約を最適化することができないという問題があった。
In addition, the schedule system described in
本発明は、このような課題を解決するために成されたものであり、混合プラント、充填プラントなどの複数のタンクと配管などから構成される化学プラントにおける制約条件を加味したスケジュールを作成することが可能なスケジューリング装置を提供することを目的とする。 The present invention has been made to solve such problems, and creates a schedule that takes into account the constraints in a chemical plant composed of a plurality of tanks and piping such as a mixing plant and a filling plant. It is an object of the present invention to provide a scheduling device capable of performing the above.
本発明によるスケジューリング装置は、複数のタンク、混合装置、タンク及び混合装置を接続する配管を備えた混合プラントにおける作業スケジュールを作成するスケジューリング装置であって、製品ごとにタンクの割付優先度を示す優先度行列を設定する優先度行列設定手段と、製品の納期を満たすように、配管の競合及び混合装置の競合を回避するバックワード法を用い優先度行列に基づいて、作業の割付けを行うことで作業スケジュールを作成するスケジュール演算手段とを備えることを特徴としている。 A scheduling device according to the present invention is a scheduling device that creates a work schedule in a mixing plant having a plurality of tanks, a mixing device, and a pipe connecting the tanks and the mixing device, and indicates the priority of tank allocation for each product. By assigning work based on the priority matrix using the priority matrix setting means to set the degree matrix and the backward method to avoid the competition of piping and mixing equipment so as to meet the delivery date of the product And a schedule calculation means for creating a work schedule.
このようなスケジューリング装置は、タンクと配管の接続関係、配管競合、混合装置の競合、洗浄量、製品銘柄、製品ごとにタンクの割付優先度を表現する優先度行列を設定する。スケジューリング装置では、バックワード法の考え方をベースとし、与えられた充填要求の納期を必ず満たすように配管競合と混合装置の競合を回避し、優先度行列に基づいて作業を割り付けることができる。これにより、複数の配管競合、複数の混合装置の競合を回避しながら、ロット集約を考慮して、製品の銘柄変更による洗浄量を最小化するスケジュールを作成することができる。 Such a scheduling device sets a priority matrix that expresses tank allocation priority for each tank and piping connection relationship, piping contention, mixing device contention, cleaning amount, product brand, and product. In the scheduling device, based on the idea of the backward method, it is possible to avoid the competition between the piping and the mixing device so as to satisfy the delivery date of the given filling request, and to assign the work based on the priority matrix. This makes it possible to create a schedule that minimizes the amount of washing due to product brand change in consideration of lot aggregation while avoiding competition among a plurality of pipes and a plurality of mixing devices.
また、シミュレーティッドアニーリング法を用いて許容される計算時間に応じて最適に近い解を得ることを可能とし、作業の割付順序リストを作成することが好適である。これにより、コスト削減を図ることができる。 In addition, it is possible to obtain a solution close to the optimum according to the allowable calculation time by using the simulated annealing method, and it is preferable to create a work assignment order list. Thereby, cost reduction can be aimed at.
また、優先度行列設定手段は、優先度行列を3種類の整数で表現するものであり、優先度行列は、必ず割り付けられる状況を表現する第1の整数、割付可能である状況を表現する第2の整数、割付不可能である状況を表現する第3の整数によって表現されることが好ましい。例えば、優先度行列を1〜3の整数で表現し、「3:必ず割り付けられる状況」、「2:割付可能である状況」、「1:割付不可能である状況」と表現することができ、これらの優先度行列を反映した作業の割り付けを行うことが可能となる。 The priority matrix setting means expresses the priority matrix with three kinds of integers. The priority matrix is a first integer that represents a situation that is always assigned, and a first integer that represents a situation that can be assigned. It is preferably represented by an integer of 2 and a third integer that represents a situation that cannot be assigned. For example, the priority matrix can be expressed as an integer from 1 to 3, and expressed as “3: a situation that is always assigned”, “2: a situation that can be assigned”, and “1: a situation that cannot be assigned”. Therefore, it is possible to assign work reflecting these priority matrices.
また、スケジューリング演算手段は、作業について、プラントにおける制約条件を満たさないことに対するペナルティ値が最小となるように、作業を割り付けるものであり、ペナルティ値は、制約条件を満たさないことで発生するコスト増加に応じて設定されることが好ましい。ここで、ペナルティ値は、タンクの最大中間在庫量を超えることに対するコスト、定められた混合回数(設備能力)を上回ることに対するコスト、混合量の不足分の補充に対するコスト、休日に作業が発生することに対するコスト、製品検査作業の不足に対するコスト、混合装置の生産能力の制約を上回ることに対するコスト、混合作業の競合制約に違反することに対するペナルティコスト、充填能力制約を違反する(充填容器の能力を超える)ことに対するコスト、充填要求制約を違反することに対するペナルティコストなどに応じて設定されることが好適である。 In addition, the scheduling calculation means assigns the work so that the penalty value for not satisfying the constraint condition in the plant is minimized, and the penalty value increases the cost caused by not satisfying the constraint condition. It is preferable to set according to. Here, the penalty value is the cost for exceeding the maximum intermediate inventory amount of the tank, the cost for exceeding the specified number of mixing (equipment capacity), the cost for replenishment of the shortage of the mixing amount, and work occurs on holidays Cost for product inspection, lack of product inspection work, cost for exceeding the production capacity of mixing equipment, penalty cost for violating competition restrictions of mixing work, violation of filling capacity constraints It is preferable to set the cost according to the cost for exceeding, the penalty cost for violating the filling requirement constraint, and the like.
また、スケジューリング演算手段は、選択された作業を固定化して、再スケジュールの作成を行うことが好ましい。 In addition, it is preferable that the scheduling calculation unit fixes the selected work and creates a reschedule.
また、スケジューリング演算手段を実現するためのシステム構成としては、共有データベース、ガントチャート出力システム、データベース変更システムを備える構成が挙げられる。これにより、さまざまな銘柄の追加変更やタンクの接続関係の変更に対して柔軟に対応することができる。 Moreover, as a system configuration for realizing the scheduling calculation means, a configuration including a shared database, a Gantt chart output system, and a database change system can be mentioned. As a result, it is possible to flexibly cope with various changes of brands and changes in tank connection relations.
また、スケジューリング演算手段は、タンクでの混合量および混合時期を汎用タンクと専用タンクとに区別して、タンクの最小混合量及び最大混合量の制約を考慮し、洗浄量が最小となるように、混合、検査、洗浄の作業スケジュールを作成することが好ましい。 In addition, the scheduling calculation means distinguishes the mixing amount and mixing timing in the tank into a general-purpose tank and a dedicated tank, and considers the restrictions on the minimum mixing amount and the maximum mixing amount of the tank, so that the cleaning amount is minimized. It is preferable to create a work schedule for mixing, inspection and cleaning.
また、配管の接続関係、複数の銘柄間での配管競合、配管内の流速に関するデータである配管データを記憶する配管データ記憶手段を更に備え、スケジュール演算手段は、複数の銘柄間での配管競合、及び流速を考慮して、作業スケジュールを作成することが好ましい。 In addition, it further includes piping data storage means for storing piping data, which is data relating to piping connection relations, piping competition between multiple brands, and flow velocity in the pipe, and the schedule calculation means is pipe competition between multiple brands. It is preferable to create a work schedule in consideration of the flow rate.
また、複数の銘柄に関するデータである銘柄データを記憶する銘柄データ記憶手段を更に備え、スケジュール演算手段は、銘柄データの追加、変更に応じて、作業スケジュールを追加更新することが好ましい。 Moreover, it is preferable to further include brand data storage means for storing brand data that is data relating to a plurality of brands, and the schedule calculation means preferably additionally updates the work schedule according to addition or change of brand data.
本発明のスケジューリング装置によれば、混合プラントにおける制約条件を加味したスケジュールを作成することができる。 According to the scheduling apparatus of the present invention, it is possible to create a schedule that takes into account the constraints in the mixing plant.
以下、本発明の好適な実施形態について図面を参照しながら説明する。なお、図面の説明において同一または相当要素には同一の符号を付し、重複する説明は省略する。本発明の実施形態に係るスケジューリング装置は、多品種の製品を製造可能な混合プラントにおける作業スケジュールの作成を支援するものである。以下、潤滑油混合プラントにおける作業スケジュールを作成するスケジューリング装置について説明する。 Preferred embodiments of the present invention will be described below with reference to the drawings. In the description of the drawings, the same or corresponding elements are denoted by the same reference numerals, and redundant description is omitted. A scheduling apparatus according to an embodiment of the present invention supports creation of a work schedule in a mixing plant capable of manufacturing a wide variety of products. Hereinafter, a scheduling device for creating a work schedule in the lubricating oil mixing plant will be described.
図1は、潤滑油混合プラントの概略構成図である。図1に示す潤滑油混合プラント1は、原料油を貯留する原料タンクTA〜TC、複数種類の原料油を混合する混合装置Mk(連続処理装置M1、バッチブレンダM2)、混合装置Mkによって混合された潤滑油(製品)を貯留する製品タンクTk(T1〜T4)、潤滑油を充填容器(例えば、ドラム缶5、ローリー6、P/L缶、4L缶、運搬船など)に充填するための充填装置4を備えている。これらのタンクTA〜TC、混合装置Mk、タンクTk、充填装置4は、複数の配管L1〜L6によって接続されている。また、これらの配管L1〜L6には、内部流体(潤滑油、洗浄油)を移送するためのポンプが接続されている。
FIG. 1 is a schematic configuration diagram of a lubricating oil mixing plant. A lubricating
図2は、本発明の実施形態に係るスケジューリング装置の概略図である。図2に示すスケジューリング装置10は、ジョブ(充填要求)データなど各種データを入力する入力部11、入力されたデータに基づいて、スケジュールを作成する電子制御ユニット20、この電子制御ユニット20による処理の結果を出力する出力部12を備えている。
FIG. 2 is a schematic diagram of the scheduling apparatus according to the embodiment of the present invention. The
入力部11は、操作者(ユーザ)によって操作される入力手段(例えば、キーボードなど)や、各種記録媒体との接続を可能とする接続部を有するものである。
The
出力部12は、電子制御ユニット20によって作成されたスケジュールを出力するものであり、画像表示装置や印字装置を有するものである。
The
電子制御ユニット20は、演算処理を行うCPU、記憶部となるROM及びRAM、入力信号回路、出力信号回路、電源回路などにより構成されている。電子制御ユニット20の記憶部には、ジョブDB31、製品タンクDB32、製品DB33、制約条件DB34が構築されている。電子制御ユニット20では、記憶部に記憶されたプログラムを実行することで、作業設定部21、優先度行列設定部22、スケジュール演算部23が構築される。
The
制約条件DB31は、潤滑油混合プラントにおける制約条件に関するデータが記憶されている。制約条件に関するデータとしては、充填納期制約条件、使用可能な混合装置に関する制約条件、1日の混合回数制限(バッチブレンダM2)、1日の混合量の制限(連続処理装置M1)、タンクTk入口側配管L2の競合制約条件、充填装置4入口側配管L3,L4の競合制約条件、検査作業制約条件などに関するデータがある。
The
図3は、記憶部に記憶されているデータリストの一例を示す図である。ジョブDB32は、ジョブ(充填要求)に関するデータを記憶するデータベースであり、リクエストID、(製品)油種、(製品)要求量、納期が記憶されている。
FIG. 3 is a diagram illustrating an example of a data list stored in the storage unit. The
製品タンクDB33は、製品タンクに関するデータを記憶するデータベースであり、タンクID(タンク番号)、(製品)油種、タンク容量、接続配管データ、最小ロット、最大ロットが記憶されている。接続配管データとは、タンクに接続された配管に関する情報であり、配管の接続先、配管の接続元、配管の分岐などに関するデータである。また、製品タンクDB32には、競合配管に関するデータを記憶している。配管の接続先、接続元、配管の分岐などのデータは、例えば図12に示すものを数値化したものである。
The
製品DB34は、製品(銘柄)に関するデータを記憶するデータベースであり、製品ID、(製品)油種、混合時間、検査時間、充填時間、洗浄時間などのデータが記憶されている。
The
電子制御ユニット20は、記憶部に記憶されたプログラムを実行することで、スケジュール演算部が構築される。スケジュール演算部21は、本発明の優先度行列設定手段、スケジュール演算手段として機能するものである。
The
電子制御ユニット20のスケジュール演算部21によって実行される優先度割付けは、バックワード法の考え方をベースにメタ戦略とルールベースを組み合わせたアルゴリズムである。納期から逆向きにジョブを割付けるバックワード法を用いることで納期の保障が可能となる。
The priority assignment executed by the
まず処理を行うジョブの順序リスト:Lf={f1,f2,…,fn}…(1)を作成しておき、この順序リストに順にジョブの割り付けを実行する(各ジョブを実行するタンクを決定する)。図4は、スケジュール作成の処理手順を示すフローチャートである。以下、ステップをSと略記することがある。順序リストに従うスケジュール作成を行う場合には、ジョブの作成(S1)、充填計画の作成(S2)、混合計画の作成(S3)を実行する。換言すれば、充填ジョブ割付け順序リスト作成ステップ(S1)、充填ジョブ割付けステップ(S2)、混合ジョブ割付けステップ(S3)を行う。 First, an order list of jobs to be processed: L f = {f 1 , f 2 ,..., F n } (1) is created, and job assignment is executed in order on this order list (each job is executed). Decide which tank to play). FIG. 4 is a flowchart showing a procedure for creating a schedule. Hereinafter, the step may be abbreviated as S. When creating a schedule according to the order list, job creation (S1), filling plan creation (S2), and mixed plan creation (S3) are executed. In other words, a filling job assignment order list creation step (S1), a filling job assignment step (S2), and a mixed job assignment step (S3) are performed.
ステップ1では、充填ジョブ割付け順序リストを作成する。ステップ2では、順序リスト順にタンクへ優先度割付けを行う。ステップ3では、充填が実行できるように各タンクに混合ジョブを割付ける。そして、これらのS1〜S3を繰り返し、目的関数の最適化を行う。すなわち、混合コスト、洗浄コストを示す目的関数を最小とする生産計画を作成することで、最適化する。
In
次に、充填ジョブ割付け順序リストの作成について説明する。ここでは、メタヒューリスティクスの一種であるシミュレーティッドアニーリング法(Simulated Annealing、以下、「SA法」という。)を用いて、充填ジョブ割付け順序リストを作成する。SA法を用いることで、許容される計算時間に応じて最適に近い解を得ることができる。 Next, creation of a filling job allocation order list will be described. Here, a filling job allocation order list is created using a simulated annealing method (hereinafter referred to as “SA method”), which is a kind of metaheuristics. By using the SA method, a nearly optimal solution can be obtained according to an allowable calculation time.
図5は、SA法を用いた充填ジョブ割付け順序リストの作成手順を示すフローチャートである。SA法を用いた充填ジョブ割付け順序リストの作成では、ステップ11〜ステップ22の処理を実行する。ステップ11では、SA法で用いるパラメータ(T0:初期温度、N0:同一目的関数値での最大繰り返し数、NS:同一温度で生成するリストの数、δ:温度更新率)を設定する。Ncount←0とする。
FIG. 5 is a flowchart showing a procedure for creating a filling job allocation order list using the SA method. In the creation of the filling job allocation order list using the SA method, the processing of
次に、ステップ12では、納期が早い要求順に1から番号を割振り、充填ジョブ割付け順序リストLfを作成し、順序リストLf順に、後述する手順で充填ジョブの割付けと混合ジョブの割付けを行い、生産計画Rを立てる。また、現時点の最適の生産計画Rを最適生産計画Roptと設定する。さらに、温度パラメータtをt=Tsと設定する。
Next, in
次に、ステップ13では、図6に示すステップ31〜ステップ33を実行することで、新たな最適生産計画Roptを作成する。図6は、新たな生産計画Rnewの作成手順を示すフローチャートである。ステップ31では、充填ジョブ割付け順序リストLfから2つのジョブをランダムに選択する。ステップ32では、ステップ31で選択された2つのジョブを入れ替え、入れ替えられたものを新たな充填ジョブ割付け順序リストLfnewとする。ステップ33では、ステップ32で設定された新たな充填ジョブ割付け順序リストLfnewに従って後述する処理手順に従って充填ジョブの割付けと混合ジョブの割付けを行い、生産計画Rnewを作成する。
Next, in
図5に戻り、ステップ14の処理を実行する。ここでは、生産計画Rに対する目的関数値をy(R)と表すことにする。y(Rnew)≦y(R)であるか否かの判定を行う。y(Rnew)がy(R)より良い場合には、y(Rnew)≦y(R)であると判定する。y(Rnew)≦y(R)であると判定された場合には、ステップ15に進み、y(Rnew)≦y(R)であると判定されなかった場合には、ステップ16に進む。
Returning to FIG. 5, the process of
ステップ15では、R←Rnew,Lf←Lfnewとし、新たな生産計画Rnewと充填ジョブ割付け順序リストLfnewを無条件で受け入れ、ステップ18に進む。ステップ16では、確率e−Δ/tでR←Rnew,Lf←Lfnewとして、受け入れ、ステップ17に進む。ステップ17では、新たな生産計画Rnewと充填ジョブ割付け順序リストLfnewが受け入れられたか否かを判定する。新たな生産計画Rnewと充填ジョブ割付け順序リストLfnewが受け入れられた場合には、ステップ18に進み、新たな生産計画Rnewと充填ジョブ割付け順序リストLfnewが受け入れられなかった場合には、ステップ19に進む。
In
ステップ18では、同一の目的関数値が続いた回数Ncount=0とする。ステップ19では、Ncountに1を加算する。
In
続くステップ20では、y(R)≦y(Ropt)であれば、Ropt←Rとする。ステップ21では、Ncount≧N0ならば終了する。そうでなければステップ13へ戻る。
In the
ステップ22では、ステップ13〜ステップ21をNS回繰り返す。t=δ・tとして、ステップ13に戻る。
In
次に、割付けの順番が回ってきた充填ジョブのタンクへの割付け手順について説明する。まず、優先度行列について説明する。従来の潤滑油混合プラントでは、オペレータが、後々の生産計画を考慮して、各製品の製造時に使用するタンクを決定している。そのようなジョブ割付け基準を数値に反映させた行列を優先度行列として設定する。 Next, a procedure for assigning filling jobs to tanks that have been assigned in the order of assignment will be described. First, the priority matrix will be described. In a conventional lubricating oil mixing plant, an operator determines a tank to be used at the time of manufacturing each product in consideration of later production plans. A matrix that reflects such job allocation criteria in a numerical value is set as a priority matrix.
図7は、タンクに対する製品の割付け優先度を表現する優先度行列を示す図である。図7では、製品油種が5種類(P1〜P5)、タンク基数が4基(T1〜T4)の場合の優先度行列の一例を示している。ここでは、充填ジョブの割付け易さを1〜3の3段階の整数を用いて表現している。各数値が表す意味は、「3:必ず割付けられる」、「2:たまに割付けられる」、「1:割付けられない」である。例えば、製品油P1の場合、タンクT1,T4に対しては、「1:割付けられない」、タンクT2に対しては、「2:たまに割付けられる」、タンクT2に対しては、「3:必ず割付けられる」と設定されている。この場合、製品油P1は、タンクT2に最も割付けられ易く、次に、タンクT3に割付けられ易いことを表している。 FIG. 7 is a diagram illustrating a priority matrix that represents the priority of product allocation to tanks. FIG. 7 shows an example of a priority matrix when there are five types of product oil types (P1 to P5) and the number of tank bases is four (T1 to T4). Here, the ease of allocation of the filling job is expressed using integers in three stages of 1 to 3. The meanings of the numerical values are “3: always assigned”, “2: occasionally assigned”, and “1: not assigned”. For example, in the case of product oil P1, for tanks T1 and T4, “1: not allocated”, for tank T2, “2: occasionally allocated”, and for tank T2, “3: “Always assigned” is set. In this case, the product oil P1 is most easily allocated to the tank T2, and then represents that the product oil P1 is easily allocated to the tank T3.
次に、優先度行列を用いた充填ジョブの割付け方法について説明する。洗浄コストは充填ジョブを割付けるタンクを決定した段階で決まる。故に、各タンクに割付けた場合に必要となる洗浄コストと、割付けるタンクの優先度を考慮して作業を行うタンクを決定することで、最適な充填工程の計画を作成する。 Next, a filling job allocation method using a priority matrix will be described. The cleaning cost is determined when the tank to which the filling job is assigned is determined. Therefore, the optimal filling process plan is created by determining the tank to be operated in consideration of the cleaning cost required when the tank is allocated and the priority of the tank to be allocated.
次に、充填ジョブ割付け順序リストLf={f1,f2,…,fi,…,fn−1,fn}の中の充填ジョブfiを割付ける場合について説明する。充填ジョブfiの製品をIfiとすると、割付けアルゴリズムは以下のようになる。図8は、充填ジョブ割付け順序リストLf中の充填ジョブfiを割付ける手順を示すフローチャートである。
Next, the filling job
まず、ステップ41では、タンク番号kの製品Ifiに対する優先度をPk Ifiとし、fiの割付けを行う期をDiとする。また、製品Ifiに対する優先度の高いタンク順にソートする。
First, in
次に、ステップ42では、q=1とし、q番のタンクTkqに充填ジョブfiに割付けを試みる。割付けを行う際には以下の制約条件を考慮する。制約条件としては、「タンクTkqのDi期に他の充填要求が割付けられていないこと」、「タンクTkqのDi期、またはDi+1期に他品種の充填要求が割付けられていないこと(後で混合ジョブを割付けるための制約条件)」がある。ステップ43では、制約条件が成立するか否かを判定する。
Next, in
タンクTkqへの割付けが制約条件を満たす場合には、ステップ44に進み、製品Ifiに対する最大優先度Pmax Ifi←Pkq Ifiとする。また、タンクTkを現時点の最適割付けタンクkopt←kqとして、ステップ46に進む。一方、タンクTkqへの割付けが制約条件を満たさない場合には、qに1を加算して、ステップ42を繰り返す。 When the allocation to the tank T kq satisfies the constraint condition, the process proceeds to step 44, where the maximum priority P max Ifi <P kq Ifi for the product I fi is set. Further, the tank T k is set as the current optimum allocation tank k opt ← k q , and the process proceeds to step 46. On the other hand, if the allocation to the tank T kq does not satisfy the constraint condition, 1 is added to q and step 42 is repeated.
ステップ46では、タンクTkoptに仮の充填ジョブ割付けを行う。その際に、gmin=Cjkq,Ifi…(2)を用いて割付けに必要となるペナルティgを計算する。ここで、現時点の最小ペナルティ値gmin←gとする。jkpはタンクkの前油,Cjkq,Ifiはjkqから製品種Ifiへの切り替えコストを示している。
In
ステップ46では、q=q+1とし、仮の割付けを行う。その際に、g=Cjkq,Ifi+A・(Pmax Ifi−Pkq Ifi)…(3)を用いてペナルティgを算出する。なお、式(3)中のAは優先度が1小さくなることに対するペナルティ係数を示している。ここで、g<gminが成立するならば、現時点の最小ペナルティgmin←gとする。また、kopt←kqとし、kqを最適割付けタンクとして受け入れる。
In
次に、混合ジョブの割付け手順について説明する。図9は、混合ジョブの割付け手順を示すフローチャートである。まず、ステップ51では、計画開始期Df,計画終了期Deを読み込む。このとき、混合ジョブの割付けを行うタンク番号をkで表現し、k=1とする。
Next, a procedure for assigning mixed jobs will be described. FIG. 9 is a flowchart showing the mixed job allocation procedure. First, in
続く、ステップ52では、d=Dfとし、混合ジョブの割付けを行う期xをx=d−1とする。
Subsequently, in
次に、ステップ53では、タンクTkのd期の予定に製品Ifiの充填ジョブfiが入っていれば、以下に示す制約条件が成立しているか否かを判定する。制約条件としては、タンク番号kのタンクTkと互いに混合装置Mk−タンク間配管競合しているタンクTk0のx期の予定に混合予定がないこと、タンク番号kに接続されている混合装置Mkの使用回数LMkが混合装置Mkの一日の最大混合ロット数を超えていないことがある。
Next, at
すなわち、混合装置Mkの使用回数LMkが一日の最大混合ロット数を超えていない場合であり、かつ、タンクTkと互いに混合装置Mk−タンク間配管競合しているタンクTk0のx期の予定に混合予定がない場合に制約条件が成立している(制約条件に反していない)と判定する。 That is, this is a case where the number of use L Mk of the mixing device M k does not exceed the maximum number of mixing lots per day, and the tank T k and the tank T k0 that competes with each other for the piping between the mixing device M k and the tank. It is determined that the constraint condition is satisfied (does not violate the constraint condition) when there is no mixture plan in the schedule of the x period.
制約条件が成立している場合、タンク番号kのx期に充填ジョブfiと同量の混合予定BIfiを立案し、タンク番号kにおけるd期以降の前油データ品目をIfiに書き換える。また、LMk=LMk+1,d=d+1とし、ステップ54へ進む。 If the constraint is satisfied, formulates mixed schedule B Ifi filling job f i the same amount in the x-life of tank numbers k, rewrites the pre-oil data item d period after the tank number k to I fi. Further, L Mk = L Mk +1 and d = d + 1 are set, and the process proceeds to step 54.
一方、制約条件が成立していない場合、x=x−1として、ステップ53を繰り返す。また、d期に充填予定が入っていなければ、d=d+1とし、ステップ53を繰り返す。d=Deとなればk=k+1としてステップ52へ戻る。 On the other hand, if the constraint condition is not satisfied, step 53 is repeated with x = x-1. If there is no filling schedule in d period, d = d + 1 and step 53 is repeated. If d = De, k = k + 1 and the process returns to step 52.
ステップ55では、d期の予定を参照して、ステップ56で作った混合ジョブの製品油Ifiと同じ製品油の充填ジョブfiがあればBiの量に充填ジョブfiの充填量を足し合わせる。また、d=d+1とする。異なる製品油の充填ジョブが入っている場合はステップ53へ戻る。充填ジョブがない場合はステップ54を繰り返す。d=Deであればk=k+1としてステップ52へ戻る。kが総タンク数K0に等しくなれば、混合ジョブの割付けを終了する。
In step 55, with reference to the schedule of d-life, the loading amount into the filling job f i of the filling job f i if there is B i of the same product oil as product oil I fi mixed jobs created in
図10は、スケジューリング装置によって作成された生産計画の一例を示す生産計画ガントチャートである。欄中のデータは、上段に油種を示し、下段に量(単位:kL)を示している。また、色の濃い欄は、混合計画を示し、その他の欄は、充填計画を示している。例えば、対象設備「Tank1」では、7月3日に、油種「oil8」を230kL混合する。その後の充填計画としては、4日に66kL、6日に84kL、8日に80kL充填する計画が立てられている。
FIG. 10 is a production plan Gantt chart showing an example of the production plan created by the scheduling device. The data in the column shows the oil type in the upper part and the amount (unit: kL) in the lower part. The dark column indicates the mixing plan, and the other columns indicate the filling plan. For example, in the target facility “
このようなスケジューリング装置10では、タンクと配管の接続関係、配管競合、混合装置の競合、洗浄量、製品銘柄、製品ごとにタンクの割付優先度を表現する優先度行列を設定し、バックワード法の考え方をベースとし、与えられた充填要求の納期を必ず満たすように配管競合と混合装置の競合を回避し、優先度行列に基づいて作業を割り付けることができる。これにより、複数の配管競合、複数の混合装置の競合を回避しながら、ロット集約を考慮して、製品の銘柄変更による洗浄量を最小化するスケジュールを作成することができる。また、スケジューリング装置によって、生産計画を作成することで、計画立案者の業務効率を向上させることができる。
In such a
また、スケジューリング装置10では、充填ジョブ割付け順序リストLfを、メタヒューリスティック手法の一つであるシミュレーティッドアニーリング法を用いて許容される計算時間に応じて最適に近い解を得ることができるため、コスト削減が図られた生産計画を作成することができる。
Further, the
また、スケジューリング装置10は、充填作業と混合作業について、制約条件を満たさないことに対するペナルティ値が最小となる割付けを行うことができる。これにより、制約条件に反することで発生するコスト増加を抑制することができる。
Moreover, the
また、スケジューリング装置では、選択された作業を固定化して、再スケジュールを作成する機能を有する構成であるため、スケジュールの最適化を図り、コスト削減を実現することができる。 In addition, since the scheduling apparatus has a function of fixing the selected work and creating a reschedule, the schedule can be optimized and cost reduction can be realized.
以上、本発明をその実施形態に基づき具体的に説明したが、本発明は、上記実施形態に限定されるものではない。上記実施形態では、スケジューリング装置を潤滑油混合プラントの生産計画の作成に利用しているが、その他の原料を混合して、製品を生産する製造装置における生産計画の作成に利用しても良い。また、バッファに制限を有する混合組立ラインとするスケジューリング装置としてもよい。 As mentioned above, although this invention was concretely demonstrated based on the embodiment, this invention is not limited to the said embodiment. In the above embodiment, the scheduling device is used to create a production plan for a lubricating oil mixing plant. However, it may be used to create a production plan in a manufacturing apparatus that produces a product by mixing other raw materials. Moreover, it is good also as a scheduling apparatus made into the mixing assembly line which has a restriction | limiting in a buffer.
以下、本発明を実施例により更に詳細に説明するが、本発明はこれらの実施例に限定されるものではない。 EXAMPLES Hereinafter, although an Example demonstrates this invention still in detail, this invention is not limited to these Examples.
本実施例では、混合機(混合装置)を3機、タンクを51基、充填ラインを51ライン、総生産品目(銘柄)166種の潤滑油製造工場に対して、本発明のスケジューリング装置を適用した。 In the present embodiment, the scheduling device of the present invention is applied to a lubricating oil manufacturing plant of three mixers (mixing devices), 51 tanks, 51 filling lines, and 166 types of total production items (brands). did.
混合機MLは、バッチ処理を行う際に利用されるバッチラインと連続処理を行う際に利用されるコーネルラインの2系統存在するが、本実施例では、バッチラインのみ考慮するものとした。図11は、混合機の性能を示す表である。各タンクには、3つ存在する混合機ML1〜ML3のうち1基だけが繋がっているものとする。 The mixer ML has two systems, a batch line used when performing batch processing and a Cornell line used when performing continuous processing. In this embodiment, only the batch line is considered. FIG. 11 is a table showing the performance of the mixer. It is assumed that only one of the three mixers ML1 to ML3 is connected to each tank.
図12は、タンク設備データを示す図である。図12のタンク設備データでは、タンク容量、使用可能混合機、混合機−タンク間の配管について示している。混合機−タンク間の配管は各タンクに1ラインずつ存在しているわけではなく、図12に示すように競合しているラインが存在している。同一ラインに繋がっているタンク同士は、同時に混合作業が行うことができない。また、充填ラインについては各タンクに一つずつ接続されているものとし、それらに能力の差は無いものとする。 FIG. 12 is a diagram showing tank facility data. The tank facility data in FIG. 12 shows the tank capacity, the usable mixer, and the pipe between the mixer and the tank. There is not one line between the mixer and the tank in each tank, but there are competing lines as shown in FIG. Tanks connected to the same line cannot be mixed at the same time. The filling line is connected to each tank one by one, and there is no difference in capacity between them.
(決定変数)
生産計画を作成する際に与えられるデータは充填要求データである。充填要求データは期日までに指定の製品を所与の量を充填しなければならないという制約条件として与えられるものである。生産計画は充填要求と設備とによる制約を満たすように、各工程の詳細な生産計画が決定される。潤滑油製造工場の生産計画では以下の変数を決定変数とする。決定変数としては、「作業を行うタンク」、「混合する製品と混合工程の日程」、「混合量」、「充填する製品と充填工程の日程」、「充填量」、「タンクに貯蔵されている中間在庫量」、「タンクに貯蔵する製品の切り替えの有無」が挙げられる。これらの変数を全て決定することで生産計画が決定される。
(Decision variable)
The data given when creating the production plan is filling request data. Filling request data is given as a constraint that a given product must be filled by a given amount by the due date. A detailed production plan for each process is determined so that the production plan satisfies the constraints due to filling requirements and equipment. The following variables are used as decision variables in the production plan of the lubricant manufacturing plant. The decision variables are: “work tank”, “product to be mixed and schedule of mixing process”, “mixing amount”, “product to be filled and schedule of filling process”, “filling amount”, “stored in tank Intermediate inventory amount ”and“ whether or not the product stored in the tank is switched ”. The production plan is determined by determining all these variables.
(目的関数)
潤滑油製造工場における生産計画では、与えられた充填要求を満たし、コストが最小となるように決定変数の値が決められる。ここでは、充填要求を必ず満たさなければならない条件として扱うこととし、生産計画を作成する際に最適化すべき項目は、生産コストとする。本実施例では、削減することができるコストとして、混合コストと洗浄コストの二つのコストを考慮した。混合コストは、混合工程の際の段取り(準備作業)に必要なコストである。また、洗浄コストは前回に処理された製品の銘柄(前油銘柄)と製造製品の銘柄が異なる際に、タンク内の洗浄を行うために必要なコストである。
(Objective function)
In the production plan in the lubricant manufacturing factory, the value of the decision variable is determined so as to satisfy the given filling requirement and minimize the cost. Here, the filling request is treated as a condition that must be satisfied, and the item to be optimized when creating the production plan is the production cost. In this embodiment, two costs, a mixing cost and a cleaning cost, are considered as the costs that can be reduced. The mixing cost is a cost required for setup (preparation work) in the mixing process. The cleaning cost is a cost necessary for cleaning the tank when the brand of the product processed last time (pre-oil brand) and the brand of the manufactured product are different.
図13及び図14は、洗浄コストの一例を示す表である。表になっていない品目については、洗浄コストが0であることを意味する。表中、左側の欄には、前油品目が記載され、上側の欄には、生産品目が記載されている。 13 and 14 are tables showing an example of the cleaning cost. For items not listed in the table, the cleaning cost is zero. In the table, the front oil item is described in the left column, and the production item is described in the upper column.
(制約条件)
制約条件とは生産計画を作成する上で必ず満たさなければならない条件のことを指すものである。本実施例の潤滑油製造工場の生産計画の以下に示す制約条件を必ず満たしていなければならない。制約条件としては、「混合作業と充填作業に関する制約条件」、「前油に関する制約条件」、「切り替えに関する制約条件」、「貯蔵在庫に関する制約条件」がある。
(Restrictions)
A constraint condition refers to a condition that must be satisfied when creating a production plan. The following constraints of the production plan of the lubricating oil manufacturing plant of this embodiment must be satisfied. As the constraint conditions, there are “a constraint condition related to mixing and filling operations”, “a constraint condition related to pre-oil”, “a constraint condition related to switching”, and “a constraint condition related to storage stock”.
「混合作業と充填作業に関する制約条件」としては、「混合機から繋がる配管は複数のタンクで共有しているため、一日に同時に混合できる製品が限られること」、「各混合機には、一日の生産能力(混合ロット数)の上限があり、それを超えて混合することはできないこと」、「混合作業と充填作業とにおいて、充填要求以上の量を処理(生産)しないこと」が挙げられる。 "Restrictions on mixing and filling operations" include: "The piping connected from the mixer is shared by multiple tanks, so the products that can be mixed at the same time are limited." There is an upper limit on the production capacity (number of mixed lots) per day, and it is not possible to mix beyond that, "" Do not process (produce) more than the required amount in mixing and filling operations " Can be mentioned.
「前油に関する制約条件」としては、「製品の充填後、タンク内には別の製品を製造するまで、過去に製造した製品の残り油(前油)が残ること」が挙げられる。「切り替えに関する制約条件」としては、「前油と異なる製品を製造する場合、洗浄作業を行わなければならないこと」が挙げられる。「貯蔵在庫に関する制約条件」としては、「各タンクは最大でタンクの容量までしか製品を貯蔵できないこと」が挙げられる。 As the “restriction condition regarding the pre-oil”, “after the product is filled, the remaining oil (pre-oil) of the product manufactured in the past remains in the tank until another product is manufactured”. “Constraining conditions for switching” include “when a product different from the pre-oil is manufactured, a cleaning operation must be performed”. “Restrictions on storage stock” include “each tank can only store products up to the capacity of the tank”.
(定式化の詳細)
次に、本実施例の潤滑油製造工場の生産計画モデルにおける混合整数線形計画問題(Mixed Integer Linear Programming Problem : MILP問題)への定式化について詳しい説明を行う。
(Details of formulation)
Next, a detailed description will be given of the formulation of the mixed integer linear programming problem (MILP problem) in the production planning model of the lubricating oil factory of the present embodiment.
(定数)
まず、使用する定数を以下に示す。
k :タンク番号 (1)
Ck:タンクkの容量 (2)
Wi,j:製品種iから製品種jへ切り替えるときに必要な洗浄コスト (3)
ft,i:品目iのt期での充填量 (4)
kはタンク番号でありk=1〜51の値をとる。Ckはタンクkの最大容量である。ft,iはt期の製品iの生産要求量(充填要求量)である。なお、タンク番号k(1〜51)は、プラント固有の数値であり、プラント内に設置されたタンクの個数(51基)に応じた値である。
(constant)
First, the constants used are shown below.
k: Tank number (1)
C k : Capacity of tank k (2)
W i , j : Cleaning cost required when switching from product type i to product type j (3)
f t , i : filling amount of item i in period t (4)
k is a tank number and takes a value of k = 1 to 51. C k is the maximum capacity of the tank k. ft , i is the production request amount (filling request amount) of the product i in the t period. The tank number k (1 to 51) is a numerical value specific to the plant, and is a value corresponding to the number of tanks (51) installed in the plant.
(決定変数)
決定変数として以下の4つの変数を定義する。
(Decision variable)
The following four variables are defined as decision variables.
式(5),式(6)は、混合作業を表す決定変数(δk 0,i=0,Bk 0,i=0)である。式(5)の決定変数δk t,iが1のとき、タンクkのt期で製品種iが混合されることを表し、式(6)の決定変数Bk t,iはそのときの混合量を表している。 Expressions (5) and (6) are decision variables (δ k 0, i = 0, B k 0, i = 0) representing the mixing operation. When the decision variable δ k t, i in the equation (5) is 1, it represents that the product type i is mixed in the t period of the tank k, and the decision variable B k t, i in the equation (6) The amount of mixing is shown.
式(7),式(8)は充填作業を表す決定変数(γk 0,i=0,Fk 0,i=0)である。式(7)の決定変数γk t,iが1のとき、タンクkのt期で製品種iを充填することを表し、式(8)の決定変数Fk t,iはそのときの充填量を表している。 Equations (7) and (8) are decision variables (γ k 0, i = 0, F k 0, i = 0) representing the filling operation. When the decision variable γ k t, i in the equation (7) is 1, it represents that the product type i is filled in the t period of the tank k, and the decision variable F k t, i in the equation (8) is the filling at that time Represents quantity.
式(9)は、タンクk内の製品種iの容量を表す決定変数(xk 0,i=0)である。式(10)は、タンクkの前油種を表す決定変数(αk 0,iは所与)である。例えばα2 3,16、が1の場合はタンク番号2の3期の前油品目は製品種番号16であることを示す。式(11)は、切り替えの有無を表す決定変数である。
Equation (9) is a decision variable (x k 0, i = 0) representing the capacity of the product type i in the tank k. Equation (10) is a decision variable (α k 0, i is given) representing the pre-oil type of tank k. For example, if α 2 3,16 is 1, it indicates that the previous oil item in the third period of
(目的関数)
生産計画問題は以下の関数を最小化する問題として記述できる。
式(12)の第一項では全混合回数を計算し、第二項では総洗浄コストを表す。式(12)の目的関数を最小とするような生産計画を作成することを目的とする。
(Objective function)
The production planning problem can be described as a problem that minimizes the following function.
The first term of equation (12) calculates the total number of mixings, and the second term represents the total cleaning cost. The purpose is to create a production plan that minimizes the objective function of equation (12).
(混合作業と充填作業に関する制約条件)
本実施例で扱う制約条件について説明する。以下の式で、T0は計画期間を表し、i∈P0,P0は生産性品種集合を表し、k∈K0,K0は全タンク集合を表すものとする。以下に混合作業と充填作業に関する制約条件を示す。ここで、TCは混合機−タンク間配管競合の関係にあるタンク集合である。K1,K2,K3はそれぞれ混合機ML1,ML2,ML3に接続されているタンク集合を示す。
K1={1,9,10,12〜14,17〜19,36,37,45,46,49}
K2={2〜8,11,15,16,20〜35}
K3={38〜44,47,49〜51}
(Restrictions on mixing and filling operations)
The constraint conditions handled in this embodiment will be described. In the following equation, T 0 represents a planning period, iεP 0 , P 0 represents a productivity variety set, and kεK 0 , K 0 represents an entire tank set. The following are the restrictions on mixing and filling operations. Here, TC is a tank set having a competing relationship between the mixer and the tank. K 1 , K 2 , and K 3 represent tank sets connected to the mixers ML1, ML2, and ML3, respectively.
K 1 = { 1, 9, 10, 12-14, 17-19, 36, 37, 45, 46, 49}
K 2 = {2-8, 11, 15, 16, 20-35}
K 3 = {38 to 44, 47, 49 to 51}
また、KCは同じ配管を共有しているタンクの集合を表す。以下に制約条件式を示す。
式(13)〜式(16)は混合作業の制約を表す式である。式(13)は混合機−タンク間の配管の設備条件によるによる混合回数の制限を表している。式(14)〜式(16)は混合機の能力の上限による混合回数の制約を表す式である。式(14)は混合機ML1に繋がれているタンクの混合作業の制約を表す式である。式(15)は混合機ML2に繋がれているタンクの混合作業の制約を表す式である。式(16)は混合機ML3に繋がれているタンクの混合作業の制約を表す式である。
Also, K C represents a set of tanks that share the same pipe. The constraint conditions are shown below.
Expressions (13) to (16) are expressions representing restrictions on the mixing work. Expression (13) represents the limitation of the number of mixing depending on the equipment condition of the pipe between the mixer and the tank. Expressions (14) to (16) are expressions representing restrictions on the number of times of mixing depending on the upper limit of the mixer capacity. Formula (14) is a formula showing the restrictions of the mixing operation of the tank connected to the mixer ML1. Expression (15) is an expression representing the restriction of the mixing operation of the tank connected to the mixer ML2. Expression (16) is an expression representing the restriction of the mixing operation of the tank connected to the mixer ML3.
式(17),式(18)は、上記式(5)の「混合作業を表す決定変数δk t,i」の定義式である。上記式(6)の「混合作業の混合量を表す決定変数Bk t,i」が1〜Ckの間の値を取るときのみ、上記式(5)の「混合作業を表す決定変数δk t,i」の値は1を取ることを表している。
Expressions (17) and (18) are definition expressions of “determining variable δ k t, i representing the mixing operation” in the above expression (5). Only when the “decision variable B k t, i representing the mixing amount of the mixing operation” in the above equation (6) takes a value between 1 and C k , the “decision variable δ representing the mixing operation” in the above equation (5). The value of “ k t, i ” represents taking 1.
式(19),式(20)は、上記式(7)の「充填作業を表す決定変数γk t,i」の定義式である。上記式(8)の「充填作業の充填量を表す決定変数Fk t,i」が1〜Ckの間の値を取るときのみ、上記式(7)の「充填作業を表す決定変数γk t,i」の値は1を取ることを表している。
Expressions (19) and (20) are definition expressions of “decision variable γ k t, i representing the filling operation” in the above expression (7). "Decision variable F k t which represents the loading of the filling operation, i" of the above formula (8) only when takes a value between 1 through C k, the decision variable representing the "filling operation of the above formula (7) gamma The value of “ k t, i ” represents taking 1.
式(21)は充填要求と充填量総和が等しいことを表している。式(22)は、総混合量と総充填量が等しいことを示している。式(23)は各タンクで1期間に行える仕事は、混合作業、または充填作業のどちらか1作業のみということを示している。
Expression (21) represents that the filling request and the filling amount sum are equal. Equation (22) shows that the total mixing amount and the total filling amount are equal. Equation (23) shows that the work that can be performed in each tank in one period is only one work of either the mixing work or the filling work.
(前油についての制約条件)
下記式(24)〜式(27)は、前油についての制約条件を示すものである。
式(24)は、各タンクには必ずタンク内に1種類の前油が残っていることを表している。式(25)はタンクkのt期において製品iの混合作業をする場合、タンクkのt期の前油が製品iに変わることを示している。式(26),式(27)のKは十分大きい整数を表している。また、t=1のときの前油種を表す決定変数αk t−1,i、すなわち決定変数αk 0,iは、生産計画を行う前の0期の前油データを表しており、所与のデータである。これらの式(26),式(27)は混合作業がない場合は、一つ前の期の前油がそのままタンク内に残ることを表している。
(Restrictions on pre-oil)
The following formulas (24) to (27) show the constraint conditions for the pre-oil.
Expression (24) indicates that one type of front oil always remains in each tank. Equation (25) indicates that when the product i is mixed in the t period of the tank k, the previous oil in the t period of the tank k is changed to the product i. K in the equations (26) and (27) represents a sufficiently large integer. Moreover, the decision variable α k t−1, i representing the previous oil type when t = 1, that is, the decision variable α k 0, i represents the previous oil data in the zero period before the production plan is performed, Given data. These formulas (26) and (27) represent that the previous oil in the previous period remains in the tank as it is when there is no mixing operation.
(貯蔵在庫についての制約条件)
以下に貯蔵在庫について制約条件を示す。
式(28)は、タンクに貯めておく貯蔵在庫の最小値を表している。式(29)は0期の各タンクの貯蔵在庫がすべて0であることを表している。式(30)は貯蔵在庫の最大値を表している。式(31)はタンクkのt期に製品iをFk t,iだけ充填を行わなければならない場合、タンクkのt−1期における製品iの貯蔵在庫量を表すxk t−1,iは、充填量Fk t,i以上でなければならないことを表す。式(32)は、t−1期末の在庫xk t−1,iに対して、t期にFk t,iだけ充填され、Bk t,iだけ混合された場合のt期末の貯蔵在庫量を表すものである。式(33)はタンクkのt期における前油が製品iのときタンク内には製品i以外の貯蔵在庫量がないことを表している。
(Restrictions on storage stock)
The following are the constraints on storage stock.
Expression (28) represents the minimum value of the storage stock stored in the tank. Expression (29) represents that the storage stock of each tank in the zero period is all zero. Expression (30) represents the maximum value of the storage stock. Equation (31) indicates that if product i has to be filled by F k t, i in t period of tank k, x k t-1, i indicates that the filling amount must be greater than or equal to F k t, i . Equation (32) shows that the stock at the end of t-1 x k t-1, i is filled at the end of t by F k t, i and mixed at the end of t when B k t, i is mixed. It represents the stock quantity. Expression (33) represents that when the previous oil in the t period of the tank k is the product i, there is no storage stock amount other than the product i in the tank.
(切り替えについての制約条件)
以下に切り替えについての制約条件を示す。
式(34),式(35)は、前油種を表す決定変数αk t−1,i,αk t,jがともに1である場合、切り替えの有無を表す決定関数βk t,i,jの値を1とすることを表している。すなわち、これら二つの式(34),式(35)は、タンクkのt期末において、製品iから製品jに製造製品の切り替えの有無を表している。
(Restrictions on switching)
The restriction conditions for switching are shown below.
Expressions (34) and (35) are determined by the decision function β k t, i indicating whether or not switching is performed when the decision variables α k t-1, i and α k t, j representing the previous oil type are both 1. , J is set to 1. That is, these two formulas (34) and (35) indicate whether or not the manufactured product is switched from the product i to the product j at the end of the period of the tank k.
(割付け優先度行列)
従来、潤滑油製造工場のオペレータは、後々の生産計画のことを考え、各製品の製造時に用いるタンクをある程度決めていた。割付け優先度行列とは、そのようなジョブ割付け基準を数値に反映した行列である。図15及び図16は、本実施例に係る割付け優先度行列を示す図である。図15及び図16では、左側欄にタンク番号を示し、上段に製品油種を示している。図中の数値は、「3:必ず割付けられる」、「2:たまに割付けられる」、「1:割付けられない」を表している。
(Assignment priority matrix)
Conventionally, an operator of a lubricant manufacturing factory has decided a certain tank to be used for manufacturing each product in consideration of a later production plan. The allocation priority matrix is a matrix that reflects such job allocation criteria in numerical values. 15 and 16 are diagrams showing an allocation priority matrix according to the present embodiment. In FIG.15 and FIG.16, the tank number is shown in the left column, and the product oil kind is shown in the upper stage. The numerical values in the figure represent “3: always assigned”, “2: occasionally assigned”, and “1: not assigned”.
(実験結果)
本実施例では、潤滑油製造工場を対象として生産計画モデルに、上記実施形態で説明したスケジューリング装置を適用した。ここでは、CPU:Celeron(商品名)2GHz、メモリ:512MBの計算機を使用して数値実験を行った。上述したように、図10に、実験結果による生産計画のガントチャートが示されている。
(Experimental result)
In this example, the scheduling apparatus described in the above embodiment is applied to a production plan model for a lubricant manufacturing factory. Here, a numerical experiment was performed using a computer of CPU: Celeron (trade name) 2 GHz, memory: 512 MB. As described above, FIG. 10 shows a Gantt chart of a production plan based on experimental results.
本発明のスケジューリング装置では、月間の充填データを約30分で作成することができた。従来、生産計画担当者が、月間の充填データを作成した場合には、約15時間かかっていた。また、本発明のスケジューリング装置では、充填データを元に調合データを作成し、設備への割当て計画を作成する場合、約30分で行うことができた。従来、生産計画担当者が、設備への割当て計画を作成する場合、約6時間かかっていた。これにより、生産計画担当者の1ヶ月の作業時間を約20時間短縮することが可能となる。すわなち、年間で、約240時間の作業時間の短縮を達成することができる。 In the scheduling device of the present invention, monthly filling data could be created in about 30 minutes. Conventionally, it takes about 15 hours when a production planner creates monthly filling data. Further, in the scheduling device of the present invention, when preparing the blending data based on the filling data and creating the allocation plan for the equipment, it can be performed in about 30 minutes. Conventionally, it takes about 6 hours for a production planner to create an allocation plan for equipment. As a result, it is possible to shorten the monthly work time of the person in charge of production planning by about 20 hours. In other words, a reduction in work time of about 240 hours per year can be achieved.
また、本発明のスケジューリング装置では、週間生産計画において、充填データを元に調合データを作成し、設備への割当て計画を作成する場合、約30分で行うことができた。従来、生産計画担当者が、設備への割当て計画を作成する場合、約2時間かかっていた。これにより、生産計画担当者の1週間の作業時間を約1時間30分短縮することが可能となる。すわなち、年間で、約72時間の作業時間の短縮を達成することができる。
Further, in the scheduling device of the present invention, in the weekly production plan, when the blending data is created based on the filling data and the allocation plan to the equipment is created, it can be performed in about 30 minutes. Conventionally, it took about two hours for a production planner to create an allocation plan for equipment. As a result, it is possible to shorten the work time for one week of the production planner by about 1
1…潤滑油混合プラント、4…充填装置、5…ドラム缶、6…ローリー、10…スケジューリング装置、11…入力部、12…出力部、20…電子制御ユニット、21…スケジュール演算部、31…制約条件DB、32…ジョブDB、33…製品タンクDB、34…製品DB、TA〜TC…原料タンク、T1〜T4…製品タンク、L1〜L6…配管、Mk…混合装置、M1…連続処理装置、M2…バッチブレンダ。
DESCRIPTION OF
Claims (8)
製品ごとに前記タンクの割付優先度を示す優先度行列を設定する優先度行列設定手段と、
前記製品の納期を満たすように、前記配管の競合及び前記混合装置の競合を回避するバックワード法を用い前記優先度行列に基づいて、作業の割付けを行うことで作業スケジュールを作成するスケジュール演算手段とを備えることを特徴とするスケジューリング装置。 A scheduling device for creating a work schedule in a mixing plant having a plurality of tanks, a mixing device, a pipe connecting the tank and the mixing device,
A priority matrix setting means for setting a priority matrix indicating the allocation priority of the tank for each product;
Schedule calculation means for creating a work schedule by assigning work based on the priority matrix using a backward method that avoids competition of the piping and competition of the mixing device so as to satisfy the delivery date of the product A scheduling apparatus comprising:
前記優先度行列は、必ず割り付けられる状況を表現する第1の整数、割付可能である状況を表現する第2の整数、割付不可能である状況を表現する第3の整数によって表現されることを特徴とする請求項1又は2記載のスケジューリング装置。 The priority matrix setting means expresses the priority matrix with three kinds of integers,
The priority matrix is represented by a first integer that represents a situation that must be assigned, a second integer that represents a situation that can be assigned, and a third integer that represents a situation that cannot be assigned. The scheduling apparatus according to claim 1 or 2, characterized in that:
前記ペナルティ値は、前記制約条件を満たさないことで発生するコスト増加に応じて設定されることを特徴とする請求項1〜3の何れか1項に記載のスケジューリング装置。 The scheduling calculation means allocates the work so that a penalty value for not satisfying the constraint condition in the plant is minimized.
The scheduling apparatus according to claim 1, wherein the penalty value is set according to an increase in cost that occurs due to not satisfying the constraint condition.
前記スケジュール演算手段は、複数の銘柄間での配管競合、及び前記流速を考慮して、作業スケジュールを作成する請求項1〜6の何れか1項に記載のスケジューリング装置。 Piping data storage means for storing piping data, which is data relating to the piping connection relationship, piping competition between multiple brands, and flow velocity in the piping;
The scheduling apparatus according to claim 1, wherein the schedule calculation unit creates a work schedule in consideration of piping competition between a plurality of brands and the flow velocity.
前記スケジュール演算手段は、前記銘柄データの追加、変更に応じて、前記作業スケジュールを追加更新する請求項1〜7の何れか1項に記載のスケジューリング装置。 It further comprises brand data storage means for storing brand data that is data relating to a plurality of brands,
The scheduling apparatus according to claim 1, wherein the schedule calculation unit additionally updates the work schedule in accordance with addition or change of the brand data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009109671A JP5543129B2 (en) | 2009-04-28 | 2009-04-28 | Scheduling device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009109671A JP5543129B2 (en) | 2009-04-28 | 2009-04-28 | Scheduling device |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2010257407A true JP2010257407A (en) | 2010-11-11 |
JP5543129B2 JP5543129B2 (en) | 2014-07-09 |
Family
ID=43318205
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2009109671A Active JP5543129B2 (en) | 2009-04-28 | 2009-04-28 | Scheduling device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5543129B2 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013200804A (en) * | 2012-03-26 | 2013-10-03 | Jx Nippon Oil & Energy Corp | Filling plan preparation support device |
KR20150113720A (en) * | 2014-03-31 | 2015-10-08 | 에스케이이노베이션 주식회사 | Method and apparatus for determining optimal production of petroleum products |
JP2016004477A (en) * | 2014-06-18 | 2016-01-12 | Jx日鉱日石エネルギー株式会社 | Production plan creation device |
WO2017217127A1 (en) * | 2016-06-13 | 2017-12-21 | 協同油脂株式会社 | Inspection device and production management method |
CN112204588A (en) * | 2018-05-31 | 2021-01-08 | 利乐拉瓦尔集团及财务有限公司 | Scheduling of production of packaged dairy products in an existing production plant by simulation |
JP7456298B2 (en) | 2020-06-04 | 2024-03-27 | 富士通株式会社 | Optimization device, optimization method, and optimization program |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1153006A (en) * | 1997-07-31 | 1999-02-26 | Furukawa Electric Co Ltd:The | Scheduling method |
JPH11167652A (en) * | 1997-12-02 | 1999-06-22 | Idemitsu Kosan Co Ltd | Tank schedule creation supporting device and program recording medium |
JP2000137502A (en) * | 1998-11-02 | 2000-05-16 | Nippon Petrochem Co Ltd | Raw material tank reception/discharge system |
JP2002529860A (en) * | 1998-11-06 | 2002-09-10 | ハネウエル・インコーポレーテッド | Automatic finite capacity scheduler |
JP2004162756A (en) * | 2002-11-11 | 2004-06-10 | Kirin Engineering Co Ltd | Piping system |
-
2009
- 2009-04-28 JP JP2009109671A patent/JP5543129B2/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1153006A (en) * | 1997-07-31 | 1999-02-26 | Furukawa Electric Co Ltd:The | Scheduling method |
JPH11167652A (en) * | 1997-12-02 | 1999-06-22 | Idemitsu Kosan Co Ltd | Tank schedule creation supporting device and program recording medium |
JP2000137502A (en) * | 1998-11-02 | 2000-05-16 | Nippon Petrochem Co Ltd | Raw material tank reception/discharge system |
JP2002529860A (en) * | 1998-11-06 | 2002-09-10 | ハネウエル・インコーポレーテッド | Automatic finite capacity scheduler |
JP2004162756A (en) * | 2002-11-11 | 2004-06-10 | Kirin Engineering Co Ltd | Piping system |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013200804A (en) * | 2012-03-26 | 2013-10-03 | Jx Nippon Oil & Energy Corp | Filling plan preparation support device |
KR20150113720A (en) * | 2014-03-31 | 2015-10-08 | 에스케이이노베이션 주식회사 | Method and apparatus for determining optimal production of petroleum products |
KR102147511B1 (en) | 2014-03-31 | 2020-08-24 | 에스케이이노베이션 주식회사 | Method and apparatus for determining optimal production of petroleum products |
JP2016004477A (en) * | 2014-06-18 | 2016-01-12 | Jx日鉱日石エネルギー株式会社 | Production plan creation device |
WO2017217127A1 (en) * | 2016-06-13 | 2017-12-21 | 協同油脂株式会社 | Inspection device and production management method |
JP2017223474A (en) * | 2016-06-13 | 2017-12-21 | 協同油脂株式会社 | Inspection device and production management method |
US10766654B2 (en) | 2016-06-13 | 2020-09-08 | Kyodo Yushi Co., Ltd. | Inspection device and production management method |
CN112204588A (en) * | 2018-05-31 | 2021-01-08 | 利乐拉瓦尔集团及财务有限公司 | Scheduling of production of packaged dairy products in an existing production plant by simulation |
JP7456298B2 (en) | 2020-06-04 | 2024-03-27 | 富士通株式会社 | Optimization device, optimization method, and optimization program |
Also Published As
Publication number | Publication date |
---|---|
JP5543129B2 (en) | 2014-07-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Harjunkoski et al. | Scope for industrial applications of production scheduling models and solution methods | |
JP5543129B2 (en) | Scheduling device | |
Jans et al. | Modeling industrial lot sizing problems: a review | |
EP2507672B1 (en) | Method and apparatus for optimizing a performance index of a bulk product blending and packaging plant | |
US6836689B2 (en) | Collaborative batch aggregation and scheduling in a manufacturing environment | |
Masoud et al. | Integrated cost optimization in a two-stage, automotive supply chain | |
Miranda et al. | A decomposition heuristic for a rich production routing problem | |
US20130246107A1 (en) | Method and Device for Assigning Surplus Slabs in the Slab Yard before Hot Rolling Process | |
JPH05225205A (en) | Sequential defined production planning system | |
Chargui et al. | Berth and quay crane allocation and scheduling with worker performance variability and yard truck deployment in container terminals | |
CN115136164A (en) | Computer-implemented method for production planning and/or control of a production system and production planning and/or production control system with production optimization | |
Hill et al. | Efficient multi-product multi-BOM batch scheduling for a petrochemical blending plant with a shared pipeline network | |
Castillo et al. | Inventory pinch based, multiscale models for integrated planning and scheduling‐part II: Gasoline blend scheduling | |
Klanke et al. | Scheduling and batching with evolutionary algorithms in simulation–optimization of an industrial formulation plant | |
US7383337B2 (en) | Method for fair sharing limited resources between multiple customers | |
JP2006107167A (en) | Scheduling system, scheduling program and scheduling method | |
Pacciarelli et al. | Models and methods for production scheduling in the pharmaceutical industry | |
Leite et al. | Solving the integrated planning and scheduling problem using variable neighborhood search based algorithms | |
CN111815148B (en) | Scheduling method, scheduling device, electronic equipment and computer readable storage medium | |
Kalay et al. | A branch-and-price algorithm for parallel machine campaign planning under sequence dependent family setups and co-production | |
Alvarez et al. | The consistent production routing problem | |
JP2006202038A (en) | Production scheduling system | |
CN116308069B (en) | Optimization method of production scheduling control system and related components | |
Hoogendoorn | A capacity-driven due date assignment and workload spreading approach in a make-to-order production environment | |
Brant | Driving Eurol's production scheduling forward with scheduling algorithms: A case study |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20111028 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20130226 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20130228 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20131203 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20140129 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140422 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140508 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5543129 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |