JP2010179998A - Renewal construction method for elevator - Google Patents

Renewal construction method for elevator Download PDF

Info

Publication number
JP2010179998A
JP2010179998A JP2009023875A JP2009023875A JP2010179998A JP 2010179998 A JP2010179998 A JP 2010179998A JP 2009023875 A JP2009023875 A JP 2009023875A JP 2009023875 A JP2009023875 A JP 2009023875A JP 2010179998 A JP2010179998 A JP 2010179998A
Authority
JP
Japan
Prior art keywords
new
elevator
equipment
old
operation panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009023875A
Other languages
Japanese (ja)
Other versions
JP5328396B2 (en
Inventor
Masami Kawamura
正美 川村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Mitsubishi Electric Building Solutions Corp
Original Assignee
Mitsubishi Electric Corp
Mitsubishi Electric Building Techno Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp, Mitsubishi Electric Building Techno Service Co Ltd filed Critical Mitsubishi Electric Corp
Priority to JP2009023875A priority Critical patent/JP5328396B2/en
Publication of JP2010179998A publication Critical patent/JP2010179998A/en
Application granted granted Critical
Publication of JP5328396B2 publication Critical patent/JP5328396B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Cage And Drive Apparatuses For Elevators (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a renewal construction method capable of achieving a work in a short time without using any temporarily-installed operational panel during the renewal work of an elevator. <P>SOLUTION: The renewal construction method for the elevator includes a step of mounting a new apparatus such as an operational panel which can be juxtaposed to an existing apparatus out of new apparatuses while enabling the operation by the existing apparatus during the night time in order to change the new and existing apparatuses of an existing elevator, and connecting the new apparatus and the existing apparatus to each other with a cable, a step of providing the operation by the existing apparatus to passengers during the day time, and a step of executing the operation by the new apparatus during the night time while the existing apparatus is replaced by the new apparatus which cannot be juxtaposed to the existing apparatus out of the new apparatuses. <P>COPYRIGHT: (C)2010,JPO&amp;INPIT

Description

本発明はエレベータのリニューアル工法に関するものである。   The present invention relates to an elevator renewal method.

エレベータのリニューアル作業には通常は数日掛かってしまうので、作業を実施する場合、エレベータの停止時間を極力短くして稼動時間を減少させないようにすることが客先より要求される。このための一般的工法としては、エレベータの乗客が多い昼間にはリニューアル工事を行わずにエレベータを稼動させ、エレベータの乗客が少ない夜間に作業を行うという工法が採用される。その場合、エレベータを昼間稼動させるためにかご内に操作盤を仮設して置き、この仮設の操作盤を用いてエレベータを稼動させていた。   Since the elevator renewal work usually takes several days, the customer is required to shorten the elevator stop time as much as possible so as not to reduce the operation time. As a general construction method, a construction method is adopted in which the elevator is operated without renewal work during the daytime when there are many elevator passengers, and the work is performed at night when there are few elevator passengers. In that case, in order to operate the elevator in the daytime, an operation panel is temporarily placed in the car, and the elevator is operated using the temporary operation panel.

例えば、連続不稼働時間を大幅に低減できるエレベータの改修方法として、既設かご位置表示器と既設枠体を取り外す工程と既設操作盤と既設側板を取り外す工程とを実施した後、既設枠体に替えて改修用枠体を乗りかごドアの上方に取り付ける工程と、既設側板に替えて改修用側板を乗りかごドアの右袖壁に取り付ける工程とを実施した後、仮設かご位置表示器及び既設操作盤を改修用側板に仮保持する工程とからなる第1工事工程を実施した後、エレベータの通常運転工程を実施し、その後、改修用側板に既設操作盤に替えて改修用操作盤を取り付ける工程と改修用側板に前記仮設かご位置表示器に替えて改修用操作盤を取り付ける工程とからなる第2工事工程を実施する工法が提案されている(例えば特許文献1参照)。   For example, as an elevator repair method that can significantly reduce the continuous downtime, after performing the process of removing the existing car position indicator and the existing frame and the process of removing the existing operation panel and the existing side plate, the existing frame is replaced. After the process of attaching the repair frame to the upper side of the car door and the process of attaching the repair side board to the right sleeve wall of the car door instead of the existing side board, the temporary car position indicator and the existing operation panel After the first construction process consisting of the process of temporarily holding the repair side plate to the repair side plate, the normal operation process of the elevator is performed, and then the repair operation panel is attached to the repair side plate in place of the existing operation panel; There has been proposed a construction method for performing a second construction process including a process of attaching a repair operation panel to the repair side plate instead of the temporary car position indicator (see, for example, Patent Document 1).

また、既設のエレベータ制御装置を新式のエレベータ制御装置に取り替える第1工事と、既設の乗りかごを新式の乗りかごに取り替える第2工事とを時期をずらして実施するエレベータの改修方法においては、第1工事を第2工事よりも先に行なうとともに、第1工事では、新式のエレベータ制御装置に対応する新式の操作盤を、既設の乗りかごの側板に取付部材を介して取り付け、また第2工事では、新式の操作盤を既設の乗りかごから取り外し、新設した新式の乗りかごに取り付ける工法もある(例えば特許文献2参照)。   Further, in the elevator refurbishment method in which the first construction for replacing the existing elevator control device with the new elevator control device and the second construction for replacing the existing passenger car with the new elevator car are performed at different times, The first work is performed before the second work. In the first work, a new operation panel corresponding to the new elevator control device is attached to the side plate of the existing car via a mounting member. Then, there is a construction method in which a new operation panel is removed from an existing car and attached to a newly installed car (see, for example, Patent Document 2).

さらに、連続停止期間を短縮してエレベータ利用者への迷惑を少なくすために、エレベータの運転を停止して行なう第2期作業の前後に、エレベータの運転を可能にする状態を伴う第1期作業と第3期作業を行なうと共に、エレベータの運転を停止して行なう第2期作業を機械室周辺作業と、乗かご周辺作業とに分け、しかもそれらを並行して実施するようにして、エレベータの連続停止となる作業時間を短縮する工法も提案されている(例えば特許文献3参照)。   Furthermore, in order to shorten the continuous stop period and reduce the trouble to the elevator user, the first period with a state enabling the operation of the elevator before and after the second period work performed by stopping the operation of the elevator. In addition to the work and the third stage work, the second stage work performed by stopping the operation of the elevator is divided into the machine room peripheral work and the car peripheral work, and these are performed in parallel. There has also been proposed a method for shortening the working time for continuous stoppage (see, for example, Patent Document 3).

特開2005−194019号公報JP 2005-194019 A 特開2004−10305号公報JP 2004-10305 A 特開平7−285754号公報JP-A-7-285754

このような従来のエレベータのリニューアル工法においては、既設操作盤を取り付ける同じ位置に新操作盤を取り付けていたが、かご内の操作盤の取り外し取り付けは特に複雑で時間の掛かる作業であるため、短時間での新旧操作盤の交換は困難で、リニューアル作業の途中で既設エレベータを稼動させる必要がある場合には、作業のために外した旧操作盤をかご内の別の位置に再度仮設する必要があった。   In such a conventional elevator renewal method, the new operation panel was installed at the same position where the existing operation panel was installed, but the removal and installation of the operation panel in the car is a particularly complicated and time-consuming operation. If it is difficult to replace the old and new operation panels in time, and it is necessary to operate the existing elevator in the middle of the renewal work, the old operation panel that was removed for the work needs to be temporarily re-installed in another position in the car was there.

そのため旧操作盤を取り外し、かご内に仮設操作盤を仮設し、リニューアル工事の終了後に仮設操作盤を取り外すという煩雑で余分な作業が発生して工事期間の増大の要因になっていた。またエレベータの利用者は慣れない仮設操作盤にて操作する必要があり、利便性の点でも問題があった。   For this reason, the old operation panel is removed, the temporary operation panel is temporarily installed in the car, and the temporary operation panel is removed after the renewal work is completed, resulting in an increase in the construction period. In addition, elevator users need to operate with a temporary operation panel that they are not used to, and there is a problem in terms of convenience.

従ってこの発明の目的は、エレベータのリニューアル作業時にかご内の仮設操作盤を用いる必要を無くし、既設の旧操作盤を利用しながらリニューアル作業を短時間で遂行できるエレベータのリニューアル工法を提供することである。   Accordingly, an object of the present invention is to provide an elevator renewal method that eliminates the need to use a temporary operation panel in a car at the time of elevator renewal work and can perform renewal work in a short time while using an existing old operation panel. is there.

この発明のエレベータのリニューアル工法は、既設エレベータの旧機器を新機器と交換してエレベータをリニューアルするエレベータのリニューアル工法であって、夜間に、旧機器は残して旧機器による運転を可能にしたまま、新機器のうち旧機器に対して併設することができる少なくともかご内の操作盤を含む併設可能新機器を取り付けてこれら併設可能新機器を互いにケーブルで接続する行程と、昼間に、乗客に旧機器による運転を供する行程と、夜間に、旧機器を新機器のうち旧機器に対して併設することができない併設不可能新機器で置き換え、新機器による運転を可能にする行程とを備えたことを特徴とするものである。   The elevator renewal method according to the present invention is an elevator renewal method in which the old equipment of the existing elevator is replaced with new equipment and the elevator is renewed, and the old equipment remains at night and can be operated by the old equipment. The new equipment can be installed alongside the old equipment at least, including the operation panel in the cage, and the new equipment can be connected to each other with cables, and in the daytime There was a process to operate with equipment and a process to replace the old equipment with a new equipment that cannot be installed in the new equipment at night and to enable operation with the new equipment. It is characterized by.

この発明のエレベータのリニューアル工法によれば、工期が短縮され、利用者に違和感を与えないで作業ができるという効果が得られる。   According to the elevator renewal construction method of the present invention, the construction period is shortened, and an effect is obtained that work can be performed without giving the user a sense of incongruity.

この発明のリニューアル工法を適用できるエレベータを示す概略図である。It is the schematic which shows the elevator which can apply the renewal construction method of this invention. この発明のリニューアル工法によってリニューアル中で、既設操作盤と新設操作盤とが併設されている状態を示すエレベータの扉装置の概略正面図である。FIG. 2 is a schematic front view of an elevator door device showing a state in which an existing operation panel and a new operation panel are provided side by side during renewal by the renewal method of the present invention. この発明のリニューアル工法を表す概略作業タイムチャートである。It is a general work time chart showing the renewal construction method of this invention.

以下、この発明の実施の形態について説明する。   Embodiments of the present invention will be described below.

図1は、この発明のリニューアル工法を適用できるエレベータ装置のシステムを構成する主要機器を示すものである。図1のエレベータ装置において、機械室1には巻上モータを含む巻上機2、制御盤3、調速機4が設けられており、昇降路5には、かご6、釣り合いおもり7、かご6と釣り合いおもり7を連結する主索8、ガイドレール9、終点スイッチ10が設けられており、かご6には、ドアモータを含むドア駆動装置11およびかご内の操作盤12が設けられており、乗場13には操作盤14が設けられており、ピット15には緩衝器16が設けられている。制御盤3とかご6の間は移動ケーブル17で接続され、かご6と昇降路5側の終点スイッチ10等の機器との通信のために中継装置18が設けられている。   FIG. 1 shows main equipment constituting an elevator apparatus system to which the renewal method of the present invention can be applied. In the elevator apparatus of FIG. 1, a machine room 1 is provided with a hoisting machine 2 including a hoisting motor, a control panel 3, and a speed governor 4. A hoistway 5 has a car 6, a counterweight 7, and a car. 6, a main rope 8 that connects the counterweight 7, a guide rail 9, and an end switch 10 are provided, and the car 6 is provided with a door driving device 11 including a door motor and an operation panel 12 in the car, An operation panel 14 is provided at the landing 13, and a shock absorber 16 is provided at the pit 15. The control panel 3 and the car 6 are connected by a moving cable 17, and a relay device 18 is provided for communication between the car 6 and devices such as the end point switch 10 on the hoistway 5 side.

実際のリニューアル工法においては、リニューアルの目的や、顧客の要求によってその内容は様々であり、エレベータの構造、台数や建物の高さなどによって工期も様々であるが、ここでは、図1に示すエレベータ装置において、交流制御方式をインバータ制御方式に切り替える場合のリニューアル工法を例として説明する。また、リニューアルの対象となる機器は、例えば機械室1の巻上機2の巻上モータおよび制御盤3、昇降路5の終点スイッチ10、かご6上のドア駆動装置11であり、またかご6内の操作盤12、乗場13の操作盤14、これら機器に関係する移動ケーブル17および中継装置18であるとする。このような場合、通常のリニューアル作業の工期は2〜3日程度であるが、昼間には乗客の搬送のために通常運転させることが要求されるので、作業は8時間の夜間作業を数回行い、間の昼間は作業を中断して通常運転を行わせる。   In the actual renewal method, the contents vary depending on the purpose of the renewal and customer requirements, and the construction period varies depending on the structure of the elevator, the number of units and the height of the building. Here, the elevator shown in Fig. 1 is used. A renewal method for switching the AC control method to the inverter control method in the apparatus will be described as an example. Further, the devices to be renewed are, for example, a hoisting motor and control panel 3 of the hoisting machine 2 in the machine room 1, an end point switch 10 of the hoistway 5, a door driving device 11 on the car 6, and the car 6 It is assumed that there are an operation panel 12 inside, an operation panel 14 at the hall 13, a moving cable 17 and a relay device 18 related to these devices. In such a case, the period of normal renewal work is about 2 to 3 days, but it is required to operate normally for transporting passengers during the daytime, so the work requires several night work for 8 hours. During the daytime, the operation is interrupted and normal operation is performed.

このような場合のこの発明によるリニューアル工法においては、第1作業段階は、既設エレベータの旧機器はそのままにして動作可能としておき、新機器のうち旧機器に対して付加的に併設できる少なくともかご内の操作盤を含む併設可能新機器を取り付ける段階であり、この作業段階の後には昼間のエレベータの通常運転が可能とされている。第2作業段階は、エレベータの旧機器を取り外して、新機器のうち旧機器に対して併設することができない併設不可能新機器で置き換え、新機器による運転に切り替える段階であり、この作業段階の後の昼間のエレベータの通常運転は新機器により行われる。第3作業段階は、取り外した旧機器の撤去、搬出作業や、各部の仕上げ作業をする段階である。次に各作業段階をさらに詳しく説明する。   In the renewal method according to the present invention in such a case, in the first work stage, the old equipment of the existing elevator is left as it is and can be operated, and at least in the car that can be additionally provided with the old equipment among the new equipment. This is the stage where new equipment that can be installed together with the operation panel is installed. After this work stage, the elevator can be operated normally in the daytime. The second work stage is a stage in which the old equipment of the elevator is removed and replaced with new equipment that cannot be installed in the old equipment, and the operation is switched to the new equipment. Later daytime normal operation of the elevator will be done by the new equipment. The third work stage is a stage in which the removed old equipment is removed, carried out, and each part is finished. Next, each work stage will be described in more detail.

第1作業段階:(新機器の併設取り付け)
第1回の夜間作業として、交換の必要な機器のうち旧機器に対して併設することができる併設可能新機器(例えば、制御盤3、終点スイッチ10、移動ケーブル17、中継装置18、新操作盤22(図2参照))を既設の旧機器に併設して取り付け、これら新機器を新ケーブルで接続する。この作業により新機器の取り付け作業が部分的に完了した状態となり、またエレベータの旧機器での運転を引き続き行うことができるようになる。この作業は、夜間の8時間程度を使って順次行うことが可能である。このとき併設して取り付けるべき新機器は、少なくともかご6内の新操作盤22である。
First work stage: (Installing new equipment together)
As the first night work, new equipment that can be installed in the old equipment among the equipment that needs to be replaced (for example, the control panel 3, the end point switch 10, the moving cable 17, the relay device 18, the new operation) A panel 22 (see FIG. 2) is installed alongside the existing old equipment, and these new equipment are connected by a new cable. By this work, the installation work of the new equipment is partially completed, and the operation of the elevator with the old equipment can be continued. This operation can be performed sequentially using about 8 hours at night. At this time, the new equipment to be attached together is at least the new operation panel 22 in the car 6.

図2には、かご6を内側から見た状態を描いて示すが、かご6には、扉19によって開閉される入り口20の両側に側板21が設けられていて、一方の側板21には既設の旧機器である既設の操作盤12が設けられている。この発明による夜間の新機器の併設取り付け作業の一部として、かご6の側板21に取り付けられた旧操作盤12はそのままに、入り口20の反対側の側板21に新操作盤22を取り付ける。このように新操作盤22は、旧操作盤12と相反する側に取り付けられる。取り付けに必要なかご内の追加加工もケーブル配線も同時に完了させておき、この作業期間中に行った他の新機器の併設作業も完了させる。乗場13側の操作盤14については交換作業が容易であるのでこのような併設作業は行なわない。この状態では旧機器には手が付けられていないので旧機器による運転ができる状態である。   FIG. 2 shows a state in which the car 6 is viewed from the inside, and the car 6 is provided with side plates 21 on both sides of the entrance 20 that is opened and closed by the door 19. An existing operation panel 12 which is an old device is provided. As part of the side-by-side installation of new equipment according to the present invention, the new operation panel 22 is attached to the side plate 21 on the side opposite to the entrance 20 while the old operation panel 12 attached to the side plate 21 of the car 6 is left as it is. Thus, the new operation panel 22 is attached to the side opposite to the old operation panel 12. Additional processing inside the car and cable wiring necessary for installation are completed at the same time, and the work of installing other new equipment performed during this work period is also completed. Since the operation panel 14 on the landing 13 side is easy to replace, such a side operation is not performed. In this state, since the old device is not touched, it can be operated by the old device.

この時、かご6内の旧機器である操作盤12は、元のままの状態であるので、昼間の運転には操作性を含めて支障を及ぼさないと同時に、新操作盤22を取り付けるに当たっては、操作盤12とは別の位置に取り付けるので、作業を急いで複雑な作業を無理に一晩で完了させる必要も無くなり、作業者のペースで作業でき、大きなメリットとなる。従来の工法によるこの作業は、かご6に追加加工や仕上げ加工が必要であり、かご6内での限られた作業スペースでの作業であることから、時間を要する作業であった。   At this time, since the operation panel 12 which is the old device in the car 6 is in the original state, there is no problem including operability in daytime operation, and at the same time, the new operation panel 22 is attached. Since it is attached at a position different from the operation panel 12, it is not necessary to rush the work and complete the complicated work forcibly overnight, and it is possible to work at the operator's pace, which is a great merit. This work by the conventional construction method is time-consuming work because additional work and finishing work are required for the car 6 and work is performed in a limited work space in the car 6.

このように、エレベータは少なくとも操作盤12を含む旧機器による運転ができる状態であるので、夜間の作業時間が終了した後には、昼間の通常の稼動ができる。すなわち、乗客にとってエレベータはリニューアル作業の開始前と同じ状態で、旧機器である乗場13の操作盤14とかご6内の操作盤12とを使用してエレベータを利用することができる。従前のように慣れない仮設の操作盤によって慣れない操作を強要されることが無く、乗客に不安を抱かせない。昼間の運転のためには、側板21に取り付けた新操作盤22をカバーで覆って置くのが望ましい。   As described above, since the elevator is in a state where it can be operated by the old equipment including at least the operation panel 12, normal operation during the daytime can be performed after the night working hours are completed. That is, for the passenger, the elevator can be used by using the operation panel 14 of the hall 13 and the operation panel 12 in the car 6 which are old devices in the same state as before the start of the renewal work. As in the past, temporary operation panels that are unfamiliar with the user are not forced to operate unfamiliar with the passengers, and passengers are not worried. For daytime operation, it is desirable to cover the new operation panel 22 attached to the side plate 21 with a cover.

第2作業段階:(新旧切り替え作業)
第2回の夜間作業として、第1回の夜間作業で残して置いた旧機器のうち操作盤12を除いた旧機器(例えば巻上機2、ドア駆動装置11および乗場操作盤14)を対応する併設不可能新機器(例えば巻上機2、ドア駆動装置11および乗場操作盤14に対応する新機器)で置き換え、交換すべき機器をすべて新機器とする。また、置き換えた新機器の配線作業も行い、エレベータの新機器による運転ができるようにする。これらの作業は分担してかつ独立作業が可能なため一晩(8時間)あれば各機器の交換は完了できる。
Second work phase: (new and old switching work)
For the second night work, the old equipment (for example, the hoisting machine 2, the door drive device 11 and the landing operation panel 14) excluding the operation panel 12 among the old equipment left in the first night work is supported. Replaced with new equipment that cannot be installed (for example, new equipment corresponding to the hoisting machine 2, the door driving device 11, and the hall operating panel 14), and all equipment to be replaced are new equipment. In addition, the new equipment will be wired so that it can be operated with the new equipment. Since these operations are shared and can be performed independently, replacement of each device can be completed in one night (8 hours).

このように、エレベータは新機器による運転ができる状態であるので、第2回の夜間作業が終了した後には、昼間の通常の稼動ができる。すなわち、乗客にとってエレベータはリニューアル作業が完了した状態であって、乗場13の新機器である操作盤14とかご6内の新操作盤22を使用してリニューアルされたエレベータを利用することができる。従前のように慣れない仮設の操作盤によって慣れない操作を強要されることが無く、乗客に不安を抱かせない。昼間の運転のためには、側板21に取り付けた新操作盤22をカバーで覆って置くのが望ましい。   Thus, since the elevator is in a state where it can be operated by the new equipment, normal operation during the daytime can be performed after the second night work is completed. That is, for the passenger, the elevator is in a state where the renewal work has been completed, and the elevator renewed using the operation panel 14 which is a new device of the hall 13 and the new operation panel 22 in the car 6 can be used. As in the past, temporary operation panels that are unfamiliar with the user are not forced to operate unfamiliar with the passengers, and passengers are not worried. For daytime operation, it is desirable to cover the new operation panel 22 attached to the side plate 21 with a cover.

第3作業段階:(既設機器の撤去)
夜間作業により、エレベータの旧機器のすべてをエレベータから撤去して搬出し、仕上げ作業を行う。これまで残して置いた既設操作盤を含めた既設機器の撤去及び旧機器である操作盤12を取り外した側板21の交換などの仕上げ作業を順次夜間に実施する。以上の作業について簡単にタイムチャートを図3に示す。
Third work phase: (Removal of existing equipment)
By night work, all the old elevator equipment is removed from the elevator and carried out for finishing work. Finishing operations such as removal of existing equipment including the existing operation panel left so far and replacement of the side plate 21 from which the operation panel 12 which is the old equipment is removed are sequentially performed at night. A simple time chart for the above operation is shown in FIG.

以上に説明したように、この発明のエレベータのリニューアル工法は、既設エレベータの旧機器を新機器と交換してエレベータをリニューアルするために、夜間に、上記旧機器は残して上記旧機器による運転を可能にしたまま、上記新機器のうち上記旧機器に対して併設することができる少なくともかご内の操作盤を含む併設可能新機器を取り付けて上記併設可能新機器を互いにケーブルで接続する行程と、昼間に、乗客に上記旧機器による運転を供する行程と、夜間に、上記旧機器を上記新機器のうち上記旧機器に対して併設することができない併設不可能新機器で置き換え、上記新機器による運転を可能にする行程とを備えている。   As described above, the elevator renewal construction method according to the present invention replaces the old equipment of the existing elevator with the new equipment and renews the elevator, so that the old equipment is left and operated by the old equipment at night. The process of attaching the new equipment that can be installed together including the operation panel in the cage that can be installed together with the old equipment among the new equipment, and connecting the new equipment that can be installed together with a cable, In the daytime, the process of providing passengers with the old equipment, and at night, the old equipment is replaced with a new equipment that cannot be attached to the old equipment among the new equipment. And a process for enabling driving.

しかしながら、併設可能新機器を取り付けてこれら併設可能新機器を互いにケーブルで接続する行程と、昼間に乗客に旧機器による運転を供する行程とをリニューアル作業の進捗状況に応じて繰り返すこともできるし、併設可能新機器が、制御盤、昇降路の終点スイッチ、移動ケーブルおよび中継装置を含んでいてもよい。   However, it is possible to repeat the process of attaching new equipment that can be installed together and connecting these new equipment with cables with each other, and the process of providing passengers with the old equipment during the day, depending on the progress of the renewal work, The new equipment that can be installed side by side may include a control panel, a hoistway end switch, a moving cable, and a relay device.

また、かご内の新操作盤は、旧機器である操作盤が設けられている位置と異なる位置に設けられるようにしてもよいし、新操作盤は、操作盤が取り付けられた側板と入り口を挟んで反対側の側板に取り付けられるようにしてもよい。さらに新機器による運転を可能にする行程の後に、エレベータから旧機器をすべて撤去する行程を備えていてもよい。   In addition, the new operation panel in the car may be provided at a position different from the position where the operation panel, which is the old device, is provided. The new operation panel has a side plate and an entrance on which the operation panel is attached. You may make it attach to the side plate on the opposite side on both sides. Furthermore, a process of removing all the old equipment from the elevator may be provided after the process of enabling operation by the new equipment.

以上に図示して説明したエレベータ装置は単なる例であって様々な変形が可能であり、またそれぞれの具体例の特徴を全てあるいは選択的に組み合わせて用いることもできる。例えば、発明の説明のためにリニューアル作業として交流制御をインバータ制御に切り替えるためのものとして説明したが、その他の目的のためのリニューアル工法にも適用できる。またリニューアルする機器の範囲も上に説明した範囲に限られない。   The elevator apparatus illustrated and described above is merely an example, and various modifications can be made, and the features of each specific example can be used altogether or selectively combined. For example, for the purpose of explaining the invention, the renewal operation has been described as switching AC control to inverter control, but the present invention can also be applied to a renewal method for other purposes. Further, the range of devices to be renewed is not limited to the range described above.

本発明は、エレベータのリニューアル工期の短縮に活用できる。   The present invention can be utilized for shortening an elevator renewal construction period.

1 機械室、2 巻上機、3 制御盤、4 調速機、5 昇降路、6 かご、7 つり合いおもり、8 主索、9 ガイドレール、10 終点スイッチ、11 ドア駆動装置、12 操作盤、13 乗場、14 操作盤、15 ピット、16 緩衝器、17 移動ケーブル、18 中継装置、19 扉、20 入り口、21 側板、22 新操作盤。   1 machine room, 2 hoisting machine, 3 control panel, 4 governor, 5 hoistway, 6 cage, 7 counterweight, 8 main rope, 9 guide rail, 10 end switch, 11 door drive device, 12 operation panel, 13 landing, 14 operation panel, 15 pit, 16 shock absorber, 17 moving cable, 18 relay device, 19 door, 20 entrance, 21 side plate, 22 new operation panel.

Claims (6)

既設エレベータの旧機器を新機器と交換してエレベータをリニューアルするエレベータのリニューアル工法であって、
夜間に、上記旧機器は残して上記旧機器による運転を可能にしたまま、上記新機器のうち上記旧機器に対して併設することができる少なくともかご内の操作盤を含む併設可能新機器を取り付けて上記併設可能新機器を互いにケーブルで接続する行程と、
昼間に、乗客に上記旧機器による運転を供する行程と、
夜間に、上記旧機器を上記新機器のうち上記旧機器に対して併設することができない併設不可能新機器で置き換え、上記新機器による運転を可能にする行程とを備えたことを特徴とするエレベータのリニューアル工法。
An elevator renewal method that replaces the old equipment of the existing elevator with new equipment and renews the elevator,
At night, install the new equipment that can be installed at least including the operation panel in the cage that can be attached to the old equipment among the new equipment, while the old equipment remains and can be operated by the old equipment. The process of connecting the above-mentioned new devices that can be installed together with cables,
In the daytime, the process of providing passengers with the old equipment,
The above-mentioned old device is replaced with a new device that cannot be installed together with the old device among the new devices at night, and a process for enabling operation by the new device is provided. Elevator renewal method.
上記併設可能新機器を取り付けてこれら併設可能新機器を互いにケーブルで接続する行程と、上記昼間に、乗客に上記旧機器による運転を供する行程とをリニューアル作業の進捗状況に応じて繰り返すことを特徴とする請求項1に記載のエレベータのリニューアル工法。   The process of attaching the new equipment that can be installed together and connecting the new equipment that can be installed together with a cable, and the process of supplying the passengers with the old equipment in the daytime are repeated according to the progress of the renewal work. The elevator renewal construction method according to claim 1. 上記併設可能新機器が、制御盤、昇降路の終点スイッチ、移動ケーブルおよび中継装置を含むことを特徴とする請求項1あるいは2に記載のエレベータのリニューアル工法。   The elevator renewal method according to claim 1 or 2, wherein the new equipment that can be installed together includes a control panel, an end switch of a hoistway, a moving cable, and a relay device. 上記かご内の新操作盤は、上記旧機器である上記操作盤が設けられている位置と異なる位置に設けられることを特徴とする請求項1〜3のいずれか一項に記載のエレベータのリニューアル工法。   The renewal of the elevator according to any one of claims 1 to 3, wherein the new operation panel in the car is provided at a position different from a position where the operation panel as the old equipment is provided. Construction method. 上記新操作盤が、上記操作盤が取り付けられた側板と入り口を挟んで反対側の側板に取り付けられることを特徴とする請求項4に記載のエレベータのリニューアル工法。   5. The elevator renewal method according to claim 4, wherein the new operation panel is attached to a side plate opposite to the side plate to which the operation panel is attached and an entrance. 上記新機器による運転を可能にする行程の後に、エレベータから上記旧機器をすべて撤去する行程を備えたことを特徴とする請求項1〜5のいずれか一項に記載のエレベータのリニューアル工法。   The elevator renewal method according to any one of claims 1 to 5, further comprising a step of removing all the old devices from the elevator after the step of enabling operation by the new devices.
JP2009023875A 2009-02-04 2009-02-04 Elevator renewal method Active JP5328396B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009023875A JP5328396B2 (en) 2009-02-04 2009-02-04 Elevator renewal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009023875A JP5328396B2 (en) 2009-02-04 2009-02-04 Elevator renewal method

Publications (2)

Publication Number Publication Date
JP2010179998A true JP2010179998A (en) 2010-08-19
JP5328396B2 JP5328396B2 (en) 2013-10-30

Family

ID=42761838

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009023875A Active JP5328396B2 (en) 2009-02-04 2009-02-04 Elevator renewal method

Country Status (1)

Country Link
JP (1) JP5328396B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9079750B2 (en) 2009-06-29 2015-07-14 Mitsubishi Electric Corporation Elevator renovation method including a relay panel
CN113677613A (en) * 2019-04-11 2021-11-19 三菱电机株式会社 Method for renovating elevator

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000238973A (en) * 1999-02-19 2000-09-05 Mitsubishi Electric Corp Method for repairing elevator
JP2004067334A (en) * 2002-08-07 2004-03-04 Mitsubishi Electric Corp Elevator cage
JP2008081243A (en) * 2006-09-27 2008-04-10 Toshiba Elevator Co Ltd Method for renewal of elevator

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000238973A (en) * 1999-02-19 2000-09-05 Mitsubishi Electric Corp Method for repairing elevator
JP2004067334A (en) * 2002-08-07 2004-03-04 Mitsubishi Electric Corp Elevator cage
JP2008081243A (en) * 2006-09-27 2008-04-10 Toshiba Elevator Co Ltd Method for renewal of elevator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9079750B2 (en) 2009-06-29 2015-07-14 Mitsubishi Electric Corporation Elevator renovation method including a relay panel
CN113677613A (en) * 2019-04-11 2021-11-19 三菱电机株式会社 Method for renovating elevator

Also Published As

Publication number Publication date
JP5328396B2 (en) 2013-10-30

Similar Documents

Publication Publication Date Title
EP2450303B1 (en) Elevator renewal method
JP6851394B2 (en) Elevator renewal method and elevator control panel
JP5328396B2 (en) Elevator renewal method
JP2022040402A (en) Renewal method for elevator, and elevator attachment panel
JP2001220078A (en) Modifying method for elevator
JP2008273644A (en) Replacing method of elevator device, and elevator device
JP5750034B2 (en) Elevator hall button replacement device and elevator hall button replacement method
JP2008081243A (en) Method for renewal of elevator
JP2013112478A (en) Elevator control device
JP6595681B1 (en) Hall button device replacement jig and method
JP5806166B2 (en) Elevator repair equipment installation method
JP7134343B2 (en) Elevator renewal method
JP4344619B2 (en) Elevator repair method
CN113677613B (en) Method for renovating elevator
JP7241087B2 (en) Replacement work method
JP2000198638A (en) Reforming method of elevator
CN101407294A (en) Control apparatus for elevator and installation construction method for elevator
JP2005047679A (en) Elevator control device
JP2012201417A (en) Method for replacing control board of elevator
JPS63258385A (en) Method of renewal construction of elevator
JPH072453A (en) Improving method for elevator
JP2013001493A (en) Renewal construction method of elevator
JPH0745312B2 (en) How to modify the elevator
JP2000327243A (en) Control device remodelling method for elevator
JPH04153182A (en) Remodeling method of elevator

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20111201

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130529

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130625

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130723

R150 Certificate of patent or registration of utility model

Ref document number: 5328396

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350