JP2010077605A - Construction method for widening tunnel - Google Patents

Construction method for widening tunnel Download PDF

Info

Publication number
JP2010077605A
JP2010077605A JP2008244172A JP2008244172A JP2010077605A JP 2010077605 A JP2010077605 A JP 2010077605A JP 2008244172 A JP2008244172 A JP 2008244172A JP 2008244172 A JP2008244172 A JP 2008244172A JP 2010077605 A JP2010077605 A JP 2010077605A
Authority
JP
Japan
Prior art keywords
tunnel
constructed
receiving work
widening
underground wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008244172A
Other languages
Japanese (ja)
Inventor
Kazuhiro Fukuda
和寛 福田
Shunji Hosono
俊司 細野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2008244172A priority Critical patent/JP2010077605A/en
Publication of JP2010077605A publication Critical patent/JP2010077605A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To reasonably construct a laterally enlarged tunnel with a laterally elongated cross section by enlarging a tunnel sideways. <P>SOLUTION: A pilot tunnel 2 (a second tunnel 2a) is constructed at least on the side of a circular tunnel 1 (first tunnel) to be laterally enlarged, and an underground wall 4 positioned on the side of the circular tunnel is constructed from the inside of the pilot tunnel. An arch-shaped forepole 5 is installed between the upper parts of the pilot tunnel and the circular tunnel, and the area surrounded by the pilot tunnel, underground wall, and the forepole is excavated to laterally enlarge the circular tunnel sideways for constructing the laterally enlarged tunnel 3. A second tunnel 2a and a third tunnel 2b are constructed as pilot tunnels 2 in two upper and lower stages, and an underground wall is constructed therebetween. The underground wall is constructed in the form of a column-arranged wall formed by densely arranging columns. A forepole is formed of a pipe roof, and the front end thereof is joined to the upper part of the circular tunnel, a secondary forepole formed of a steel pipe forepole is provided to the lower part of a curved pipe roof, or a steel pipe forepole is constructed, as a forepole, in place of the curved pipe roof. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、先行構築したトンネルを側方に拡幅して横長断面の拡幅トンネルを施工するための工法に関する。   The present invention relates to a construction method for constructing a widened tunnel having a horizontally long cross section by widening a previously constructed tunnel to the side.

この種の工法としては特許文献1,2に示すものが周知である。これらはいずれも横2連に設けた2つの円形トンネルの間を掘削することにより双方の円形トンネルを連通させて横長断面のトンネルを施工するものである。
特開2006−183280号公報 特開2007−9430号公報
As this type of construction method, those shown in Patent Documents 1 and 2 are well known. These are all constructed by excavating between two circular tunnels provided in two horizontal rows so that both circular tunnels communicate with each other and a tunnel having a horizontally long cross section is constructed.
JP 2006-183280 A JP 2007-9430 A

上記従来の工法はトンネル全長にわたって拡幅を行う場合、つまり全長にわたって横長の大断面トンネルを構築する場合には好適に採用可能な工法であるが、たとえば道路トンネルにおける分岐合流部のようにトンネルの全長のうちのごく一部のみを拡幅すれば良い場合においては施工が大がかりに過ぎて必ずしも合理的ではなく、そのような場合に好適に採用し得る有効適切な工法の開発が望まれているのが実状である。   The conventional method described above is a method that can be suitably used when widening the entire length of the tunnel, that is, when constructing a horizontally large cross-section tunnel over the entire length. In the case where only a small part of it is required to be widened, the construction is too large and not necessarily rational, and the development of an effective and appropriate construction method that can be suitably used in such a case is desired. It's real.

上記事情に鑑み、本発明は第1のトンネルを側方に拡幅して横長断面の拡幅トンネルを施工するためのトンネル拡幅工法であって、拡幅すべき第1のトンネルの少なくとも側方に第2のトンネルを施工して、該第2のトンネル内から前記第1のトンネルの側方に位置する地中壁を施工するとともに、前記第2のトンネルと前記第1のトンネルの上部相互間にアーチ形状の先受工を施工し、それら第1のトンネルと先受工と第2のトンネルと地中壁とにより囲まれる領域を掘削することにより第1のトンネルを側方に拡幅して拡幅トンネルを施工することを特徴とする。   In view of the above circumstances, the present invention is a tunnel widening method for widening a first tunnel laterally to construct a widened tunnel having a laterally long cross section, and the second tunnel is formed at least laterally of the first tunnel to be widened. And an underground wall located on the side of the first tunnel from within the second tunnel, and an arch between the upper part of the second tunnel and the first tunnel. A wide-width tunnel is constructed by excavating a region surrounded by the first tunnel, the first-hand construction, the second tunnel, and the underground wall, and then widening the first tunnel to the side. It is characterized by constructing.

本発明においては、前記第2のトンネルの下方に間隔をおいて第3のトンネルを設け、第2のトンネルから前記先受工を施工し、第2のトンネルと第3のトンネルの間に前記地中壁を施工することが考えられる。
また、前記地中壁を柱体を密に配列してなる柱列壁として施工することが好ましい。
In the present invention, a third tunnel is provided at an interval below the second tunnel, the pre-construction is performed from the second tunnel, and the second tunnel and the third tunnel It is conceivable to construct underground walls.
Moreover, it is preferable to construct the underground wall as a columnar wall formed by densely arranging columns.

本発明においては、前記先受工を前記第2のトンネルから前記第1のトンネルの上部に達する曲線パイプルーフにより形成して該曲線パイプルーフの先端部を前記第1のトンネルの上部に接合し、該曲線パイプルーフの下方を掘削することが好ましい。
あるいは、前記先受工を前記第2のトンネルから前記第1のトンネルの上方に達する曲線パイプルーフにより形成し、該曲線パイプルーフの下方において前記第2のトンネルと前記第1のトンネルの間に鋼管先受工からなる二次先受工を前記第1のトンネルの軸方向に形成していきつつ該二次先受工の下方を掘削しても良い。
もしくは、前記先受工として前記第2のトンネルと前記第1のトンネルの間に鋼管先受工を形成し、該鋼管先受工を前記第1のトンネルの軸方向に施工していきつつ該鋼管先受工の下方を掘削することも考えられる。
In the present invention, the receiving work is formed by a curved pipe roof that reaches the upper part of the first tunnel from the second tunnel, and the tip of the curved pipe roof is joined to the upper part of the first tunnel. It is preferable to excavate below the curved pipe roof.
Alternatively, the first construction is formed by a curved pipe roof reaching from above the second tunnel to the upper side of the first tunnel, and between the second tunnel and the first tunnel below the curved pipe roof. You may excavate the lower part of the secondary receiving work while forming a secondary receiving work made of a steel pipe receiving work in the axial direction of the first tunnel.
Alternatively, a steel pipe tip receiver is formed between the second tunnel and the first tunnel as the tip receiver, and the steel pipe tip receiver is being constructed in the axial direction of the first tunnel. It is also conceivable to excavate below the steel pipe tip receiving work.

本発明によれば、拡幅予定領域を第1のトンネルと先受工と第2のトンネルと地中壁とにより取り囲んだうえでその内側を掘削して拡幅部を施工するので、拡幅掘削時の地盤安定性を確保できるものであり,特に上半アーチ部にかかる応力を先受工と第2のトンネルと地中壁との全体で安定に保持し得て沈下抑制を充分に図ることができるし、側方変位も地中壁により確実に抑制することができる。
また、地中壁と先受工を施工するための小断面の第2のトンネルを拡幅予定位置に設ければ良いので、従来工法のように拡幅予定位置に2本の大断面の円形トンネルを併設する場合に較べて全体作業を合理化でき、工費削減と工期短縮を実現することができる。
According to the present invention, since the widened area is surrounded by the first tunnel, the first receiver, the second tunnel, and the underground wall, and the widened portion is constructed by excavating the inner side, The ground stability can be ensured. Especially, the stress applied to the upper half arch part can be stably maintained in the entire receiving work, the second tunnel and the underground wall, and the settlement can be sufficiently suppressed. In addition, lateral displacement can be reliably suppressed by the underground wall.
Moreover, it is only necessary to provide a second tunnel with a small cross-section for constructing the underground wall and the receiving work at the planned widening position, so two circular tunnels with a large cross-section at the planned widening position as in the conventional construction method. Compared to the case where it is installed side by side, the overall work can be streamlined, and the construction cost and the construction period can be shortened.

「第1実施形態」
図1は本発明の第1実施形態を示すものである。これは、最終的に(f)に示すような横長断面形状(転倒ダルマ形)の拡幅トンネル3を施工するに際し、まず(a)に示すように円形トンネル(第1のトンネル)1を施工するとともにその側方に2本の小断面の導坑2(上段の第2のトンネル2a、および下段の第3のトンネル2b)を上下2段に設けて、それらの間を掘削することによって拡幅トンネル3を施工するようにしたものである。
“First Embodiment”
FIG. 1 shows a first embodiment of the present invention. When constructing the widening tunnel 3 having a laterally long cross-sectional shape (falling dharma shape) as shown in (f), the circular tunnel (first tunnel) 1 is first constructed as shown in (a). In addition, two narrow tunnels 2 (upper second tunnel 2a and lower third tunnel 2b) are provided in the upper and lower two stages, and the widening tunnel is excavated between them. 3 is constructed.

具体的には,通常のシールド工法により円形トンネル1を施工するとともに、その側方に上下に間隔をおいて2段の導坑2を設ける。それら円形トンネル1および導坑2の施工順序は適宜で良く、導坑2を先進導坑として円形トンネル1に先行して施工することでも良いし、あるいはそれらを同時並行作業により施工することでも良い。   Specifically, the circular tunnel 1 is constructed by a normal shield method, and a two-stage guide shaft 2 is provided on the side of the circular tunnel 1 with a vertical interval. The order of construction of the circular tunnel 1 and the guide tunnel 2 may be appropriate, and the guide tunnel 2 may be installed prior to the circular tunnel 1 as an advanced guide tunnel, or they may be installed by simultaneous parallel work. .

そして、(b)に示すように上下の導坑2間に地中壁4を施工するとともに、上段の導坑2と円形トンネル1との間にアーチ状の先受工5を施工する。
地中壁4としては鋼管柱等の柱体を密に配列した構造の柱列壁として施工することが好適であるが、可能であれば地中連続壁の如き構成のものでも良い。いずれにしても地中壁4としては後段の掘削工程(円形トンネル1の側方への切り開き工程)において山留めとして機能し得るとともに、その際に上下の導坑2および先受工5とともに上半アーチ部にかかる応力を支保し得る機能を有するものとして施工する。
アーチ状の先受工5としては曲線パイプルーフによるもの、特に円弧状に湾曲させた鋼管を導坑2から円形トンネル1の上部に向けて打設してその内部にH形鋼等の心材を挿入してコンクリートを充填した構造のものが好適に採用可能である。いずれにしても本実施形態においては先受工5の先端部を円形トンネル1の上部に到達させてそこに接合することにより、この先受工5により導坑2と円形トンネル1とを構造的に一体に連結してそれらの全体で堅固な支保構造体を構成する。
And as shown in (b), while constructing the underground wall 4 between the upper and lower guide shafts 2, an arched receiving work 5 is installed between the upper guide shaft 2 and the circular tunnel 1.
The underground wall 4 is preferably constructed as a columnar wall having a structure in which columns such as steel pipe columns are densely arranged. However, if possible, the underground wall 4 may have a structure such as an underground continuous wall. In any case, the underground wall 4 can function as a mountain stop in a subsequent excavation process (a side opening process of the circular tunnel 1), and at that time, the upper half along with the upper and lower guide shafts 2 and the first receiving work 5. It is constructed with a function capable of supporting the stress applied to the arch.
As the arch-shaped receiving work 5, a curved pipe roof is used, in particular, a steel pipe curved in an arc shape is driven from the guide shaft 2 toward the upper part of the circular tunnel 1, and a core material such as H-shaped steel is placed inside the steel pipe. A structure that is inserted and filled with concrete can be suitably employed. In any case, in the present embodiment, the leading end of the receiving work 5 reaches the upper part of the circular tunnel 1 and is joined thereto, so that the guiding work 2 and the circular tunnel 1 are structurally formed by the receiving work 5. They are connected together to form a solid support structure as a whole.

以上のように、円形トンネル1の側方の拡幅予定領域をその下方を除いて円形トンネル1と上下の導坑2と地中壁4と先受工5とにより取り囲んだ後、その内側を掘削していく。
具体的には、まず(c)に示すように先受工5の直下の上半アーチ部(斜線を付した部分)を掘削し、続いて(d)に示すように地中壁4の側方(同)を掘削し、さらに(e)に示すように下半アーチ部(同)を掘削する。
以上の掘削は、導坑2あるいは円形トンネル1もしくはそれらの双方の要所のセグメントを解体撤去してそれらの内部を通して行えば良く、その際には必要に応じて円形トンネル1内に適宜の支保工6を設置し、また掘削に伴って円形トンネル1と導坑2との間にも適宜の支保工7を設置していけば良い。
As described above, after the area to be widened on the side of the circular tunnel 1 is surrounded by the circular tunnel 1, the upper and lower guide shafts 2, the underground wall 4, and the receiving work 5 except for the lower part thereof, the inside thereof is excavated. I will do it.
Specifically, first, as shown in (c), the upper half arch part (the hatched part) just below the receiving work 5 is excavated, and then the side of the underground wall 4 as shown in (d). Then, the lower half arch part (same as above) is excavated as shown in (e).
The above excavation can be performed by dismantling and removing the main tunnel 2 or the circular tunnel 1 or the segments of both of them, and passing through the inside of them. The work 6 may be installed, and an appropriate support 7 may be installed between the circular tunnel 1 and the guide pit 2 along with the excavation.

拡幅予定領域に対する掘削完了後、(f)に示すように拡幅部に面する円形トンネルのセグメントを解体撤去して拡幅部の内面全体に一連の覆工壁8を施工して拡幅トンネル3を完成させる。   After completion of excavation for the area to be widened, as shown in (f), the segment of the circular tunnel facing the widened part is dismantled and a series of lining walls 8 are constructed on the entire inner surface of the widened part to complete the widened tunnel 3 Let

「第2実施形態」
図2は本発明の第2実施形態を示すものである。なお、上記の第1実施形態と同一要素には同一符号を付して説明を簡略化する。
本第2実施形態においては(a)に示すように円形トンネル1の側方に1本の導坑2を施工し、(b)に示すようにその下方に地中壁4を施工する。
また、先受工5は第1実施形態と同様に曲線パイプルーフにより形成するが、その先端は円形トンネル1には接合せずにその上方を覆う形態で施工し、(c)に示すようにその曲線パイプルーフの下方に二次先受工9としての鋼管先受工をさらに施工する。
二次先受工9としての鋼管先受工としてはいわゆるAGF工法によるものが好適に採用可能であり、それを導坑2と円形トンネル1間において円形トンネル1の軸方向に所定長さづつ施工していきつつその下方を掘削する。
“Second Embodiment”
FIG. 2 shows a second embodiment of the present invention. In addition, the same code | symbol is attached | subjected to the same element as said 1st Embodiment, and description is simplified.
In this 2nd Embodiment, as shown to (a), one guide shaft 2 is constructed to the side of the circular tunnel 1, and the underground wall 4 is constructed below as shown to (b).
In addition, the front receiving work 5 is formed by a curved pipe roof as in the first embodiment, but the tip is constructed so as to cover the upper part of the circular tunnel 1 without joining it, as shown in FIG. Under the curved pipe roof, a steel pipe tip receiver as a secondary tip receiver 9 is further constructed.
The steel pipe tip receiving work as the secondary receiving work 9 can be suitably adopted by the so-called AGF method, and it is constructed by a predetermined length in the axial direction of the circular tunnel 1 between the guide tunnel 2 and the circular tunnel 1. While drilling, drill below.

以降は第1実施形態と同様に、(c)〜(e)に示すように円形トンネル1と二次先受工(鋼管先受工)9と導坑2と地中壁4とにより囲まれる領域を掘削していき、拡幅部に覆工壁8を施工して拡幅トンネル3を完成させる。   Thereafter, as in the first embodiment, as shown in (c) to (e), it is surrounded by the circular tunnel 1, the secondary tip receiving (steel pipe tip receiving) 9, the guide tunnel 2, and the underground wall 4. The area is excavated, and the lining wall 8 is constructed in the widened portion to complete the widened tunnel 3.

「第3実施形態」
図3は本発明の第3実施形態を示す。これは導坑2を馬蹄形断面とし、導坑2と円形トンネル1との間に鋼管先受工からなる先受工10を施工するものである。すなわち、本第3実施形態では上記第2実施形態において二次先受工9とした鋼管先受工自体を曲線パイプルーフに代わる本来の先受工10として施工するものであり、その鋼管先受工からなる先受工10を導坑2と円形トンネル1の間において施工していきつつその下方を掘削するようにしたものであり、その他の工程は上記実施形態と同様である。
“Third Embodiment”
FIG. 3 shows a third embodiment of the present invention. In this, the guiding mine 2 has a horseshoe-shaped cross section, and a receiving work 10 composed of a steel pipe receiving work is constructed between the guiding mine 2 and the circular tunnel 1. That is, in the third embodiment, the steel pipe tip receiver itself that is the secondary tip receiver 9 in the second embodiment is constructed as an original tip receiver 10 that replaces the curved pipe roof. While a receiving work 10 made of a work is being constructed between the guide tunnel 2 and the circular tunnel 1, the lower part is excavated, and the other steps are the same as in the above embodiment.

以上で説明した第1〜第3実施形態のトンネル拡幅工法によれば、いずれも拡幅部の周囲を円形トンネル(第1のトンネル)1と、導坑2(第2のトンネル2aおよび第3のトンネル2b)と、先受工5(曲線パイプルーフ)あるいは先受工10(鋼管先受工)と、地中壁4により取り囲んだうえでその内側を掘削して拡幅部を施工するので、拡幅掘削時の地盤安定性を確保できるものであり,特に上半アーチ部にかかる応力を先受工5,10と導坑2と地中壁4により安定に保持し得て沈下抑制を充分に図ることができるし、地中壁4により側方変位を確実に抑制することができる。
また、地中壁4と先受工5,10を施工するための小断面の導坑2(第2のトンネル2aおよび第3のトンネル2b)を拡幅予定位置に設ければ良いので、従来技術のように拡幅予定位置に2本の大断面の円形トンネルを併設する場合に較べて全体作業を合理化でき、工費削減と工期短縮を実現することができる。
According to the tunnel widening method of the first to third embodiments described above, the circular tunnel (first tunnel) 1 and the guide tunnel 2 (second tunnel 2a and third tunnel) are provided around the widened portion. Since the tunnel 2b), the front receiving work 5 (curved pipe roof) or the front receiving work 10 (steel pipe front receiving work), and the underground wall 4 are excavated to construct the widened part, The ground stability during excavation can be ensured. In particular, the stress applied to the upper half arch can be stably held by the first and second receiving works 5 and 10, the guide shaft 2 and the underground wall 4 to sufficiently suppress subsidence. The lateral displacement can be reliably suppressed by the underground wall 4.
In addition, since the underground tunnel 4 and the downholes 2 (second tunnel 2a and third tunnel 2b) for constructing the receiving works 5 and 10 may be provided at the planned widening position, the prior art Thus, compared with the case where two large-section circular tunnels are additionally provided at the position to be widened, the overall work can be streamlined, and the construction cost and the construction period can be shortened.

なお,本発明は上記各実施形態に限定されるものでは勿論なく、施工するべき拡幅トンネルの規模や断面形状、地盤状況その他の諸条件に応じて、本発明の要旨を逸脱しない範囲でで適宜の設計的変更が可能であることは言うまでもない。
たとえば第1実施形態において採用した上下2段の導坑(第2のトンネルおよび第3のトンネル)の間に地中壁を設けることは他の実施形態においても採用可能であるし、第3実施形態において採用した馬蹄形断面の導坑(第2のトンネル)は他の実施形態においても採用可能である。
Of course, the present invention is not limited to the above embodiments, and may be appropriately selected within a range not departing from the gist of the present invention, depending on the scale, cross-sectional shape, ground condition, and other conditions of the widening tunnel to be constructed. Needless to say, the design can be changed.
For example, providing an underground wall between the upper and lower two-stage shafts (second tunnel and third tunnel) adopted in the first embodiment can also be adopted in other embodiments, and the third embodiment The horseshoe-shaped cross-section shaft (second tunnel) employed in the embodiment can be employed in other embodiments.

本発明の第1実施形態であるトンネル拡幅工法の概略工程を示す図である。It is a figure which shows the schematic process of the tunnel widening method which is 1st Embodiment of this invention. 本発明の第2実施形態であるトンネル拡幅工法の概略工程を示す図である。It is a figure which shows the schematic process of the tunnel widening method which is 2nd Embodiment of this invention. 本発明の第3実施形態であるトンネル拡幅工法の概略工程を示す図である。It is a figure which shows the schematic process of the tunnel widening method which is 3rd Embodiment of this invention.

符号の説明Explanation of symbols

1 円形トンネル(第1のトンネル)
2 導坑
2a 第2のトンネル
2b 第3のトンネル
3 拡幅トンネル
4 地中壁(柱列壁)
5 先受工(曲線パイプルーフ)
6,7 支保工
8 覆工壁
9 二次先受工(鋼管先受工)
10 先受工(鋼管先受工)
1 Circular tunnel (first tunnel)
2 tunnel 2a 2nd tunnel 2b 3rd tunnel 3 widening tunnel 4 underground wall (column wall)
5 Prior construction (curved pipe roof)
6, 7 Supporting work 8 Lining wall 9 Secondary receiving work (steel pipe receiving work)
10 Prior construction (steel pipe prior construction)

Claims (6)

第1のトンネルを側方に拡幅して横長断面の拡幅トンネルを施工するためのトンネル拡幅工法であって、
拡幅すべき第1のトンネルの少なくとも側方に第2のトンネルを施工して、該第2のトンネル内から前記第1のトンネルの側方に位置する地中壁を施工するとともに、前記第2のトンネルと前記第1のトンネルの上部相互間にアーチ形状の先受工を施工し、
それら第1のトンネルと先受工と第2のトンネルと地中壁とにより囲まれる領域を掘削することにより第1のトンネルを側方に拡幅して拡幅トンネルを施工することを特徴とするトンネル拡幅工法。
A tunnel widening method for widening a first tunnel to the side and constructing a wide tunnel with a transverse section,
A second tunnel is constructed at least on the side of the first tunnel to be widened, an underground wall located on the side of the first tunnel is constructed from within the second tunnel, and the second tunnel is constructed. An arch-shaped receiving work is constructed between the upper part of the tunnel and the upper part of the first tunnel,
A tunnel characterized in that a widening tunnel is constructed by widening the first tunnel laterally by excavating a region surrounded by the first tunnel, the first receiving work, the second tunnel, and the underground wall. Widening method.
請求項1記載のトンネル拡幅工法であって、
前記第2のトンネルの下方に間隔をおいて第3のトンネルを設け、第2のトンネルから前記先受工を施工し、第2のトンネルと第3のトンネルの間に前記地中壁を施工することを特徴とするトンネル拡幅工法。
The tunnel widening method according to claim 1,
A third tunnel is provided at an interval below the second tunnel, the pre-construction is constructed from the second tunnel, and the underground wall is constructed between the second tunnel and the third tunnel. A tunnel widening method characterized by:
請求項1または2記載のトンネル拡幅工法であって、
前記地中壁を柱体を密に配列してなる柱列壁として施工することを特徴とするトンネル拡幅工法。
The tunnel widening method according to claim 1 or 2,
A tunnel widening method characterized in that the underground wall is constructed as a columnar wall formed by densely arranging columns.
請求項1,2または3記載のトンネル拡幅工法であって、
前記先受工を前記第2のトンネルから前記第1のトンネルの上部に達する曲線パイプルーフにより形成して該曲線パイプルーフの先端部を前記第1のトンネルの上部に接合し、該曲線パイプルーフの下方を掘削することを特徴とするトンネル拡幅工法。
The tunnel widening method according to claim 1, 2 or 3,
The leading construction is formed by a curved pipe roof extending from the second tunnel to the upper part of the first tunnel, and a tip end portion of the curved pipe roof is joined to the upper part of the first tunnel. A tunnel widening method characterized by excavating the lower part of the tunnel.
請求項1,2または3記載のトンネル拡幅工法であって、
前記先受工を前記第2のトンネルから前記第1のトンネルの上方に達する曲線パイプルーフにより形成し、該曲線パイプルーフの下方において前記第2のトンネルと前記第1のトンネルの間に鋼管先受工からなる二次先受工を前記第1のトンネルの軸方向に形成していきつつ該二次先受工の下方を掘削することを特徴とするトンネル拡幅工法。
The tunnel widening method according to claim 1, 2 or 3,
The receiving work is formed by a curved pipe roof that extends from the second tunnel to the upper side of the first tunnel, and a steel pipe tip is provided between the second tunnel and the first tunnel below the curved pipe roof. A tunnel widening method characterized by excavating a lower side of the secondary front receiving work while forming a secondary front receiving work made of the receiving work in the axial direction of the first tunnel.
請求項1,2または3記載のトンネル拡幅工法であって、
前記先受工として前記第2のトンネルと前記第1のトンネルの間に鋼管先受工を形成し、該鋼管先受工を前記第1のトンネルの軸方向に施工していきつつ該鋼管先受工の下方を掘削することを特徴とするトンネル拡幅工法。
The tunnel widening method according to claim 1, 2 or 3,
A steel pipe tip receiving work is formed between the second tunnel and the first tunnel as the prior receiving work, and the steel pipe tip receiving work is carried out in the axial direction of the first tunnel. Tunnel widening method, characterized by excavating under the receiving work.
JP2008244172A 2008-09-24 2008-09-24 Construction method for widening tunnel Pending JP2010077605A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008244172A JP2010077605A (en) 2008-09-24 2008-09-24 Construction method for widening tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008244172A JP2010077605A (en) 2008-09-24 2008-09-24 Construction method for widening tunnel

Publications (1)

Publication Number Publication Date
JP2010077605A true JP2010077605A (en) 2010-04-08

Family

ID=42208332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008244172A Pending JP2010077605A (en) 2008-09-24 2008-09-24 Construction method for widening tunnel

Country Status (1)

Country Link
JP (1) JP2010077605A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015098685A (en) * 2013-11-18 2015-05-28 株式会社大林組 Natural ground reinforcement material and natural ground reinforcement structure
CN104832185A (en) * 2015-06-05 2015-08-12 刘玉秋 Double-arched top pipe construction equipment
CN113969796A (en) * 2021-11-02 2022-01-25 中铁二十四局集团有限公司 Sector excavation and supporting method for cross pilot tunnel of dome of large-span tank room

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07208065A (en) * 1994-01-25 1995-08-08 Mitsui Constr Co Ltd Tunnel construction method
JP2007277904A (en) * 2006-04-06 2007-10-25 Toda Constr Co Ltd Tunnel excavation method, construction method of tunnel branch/confluent width expanding part using this method and tunnel branch/confluent width expending part constructed thereby
JP2008169577A (en) * 2007-01-10 2008-07-24 Shimizu Corp Tunnel structure and tunnel construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07208065A (en) * 1994-01-25 1995-08-08 Mitsui Constr Co Ltd Tunnel construction method
JP2007277904A (en) * 2006-04-06 2007-10-25 Toda Constr Co Ltd Tunnel excavation method, construction method of tunnel branch/confluent width expanding part using this method and tunnel branch/confluent width expending part constructed thereby
JP2008169577A (en) * 2007-01-10 2008-07-24 Shimizu Corp Tunnel structure and tunnel construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015098685A (en) * 2013-11-18 2015-05-28 株式会社大林組 Natural ground reinforcement material and natural ground reinforcement structure
CN104832185A (en) * 2015-06-05 2015-08-12 刘玉秋 Double-arched top pipe construction equipment
CN113969796A (en) * 2021-11-02 2022-01-25 中铁二十四局集团有限公司 Sector excavation and supporting method for cross pilot tunnel of dome of large-span tank room
CN113969796B (en) * 2021-11-02 2023-08-11 中铁二十四局集团有限公司 Sector excavation and support method for large-span tank room dome cross pilot tunnel

Similar Documents

Publication Publication Date Title
JP4803428B2 (en) Tunnel construction method
JP4803429B2 (en) Construction method of underground cavity
JP4958035B2 (en) Shield roof construction method
JP2008274705A (en) Tunnel construction method
JP2006322222A (en) Construction method of large-sectional tunnel
JP2011184899A (en) Shield roof construction method
JP2012036624A (en) Tunnel construction method
JP2008156907A (en) Construction method for underground cavern
JP2007303155A (en) Construction method of underground cavity and tunnel construction method
JP2010174464A (en) Method of overhauling tunnel boring machine
JP4296549B2 (en) Underground support structure, its construction method and tunnel construction method
JP2010077605A (en) Construction method for widening tunnel
JP4844929B2 (en) Tunnel construction method
JP4730595B2 (en) Construction method of underground cavity
JP2006219914A (en) Method of forming communicating section of juxtaposed shield tunnels
JP2010116739A (en) Tunnel supporting method and tunnel supporting structure
JP5012149B2 (en) Ground support structure and ground support method
KR20090011442A (en) Tunnel boring method using sheet pile and tunnel structure therof
JP5806576B2 (en) Pipe roof and pipe roof construction method
JP2009074309A (en) Vertical shaft and its construction method
JP4824653B2 (en) Tunnel junction and method of constructing tunnel junction
JP2007332720A (en) Construction method for underground structure
KR101091081B1 (en) Excavation method and construction of dual tunnel
JP5158631B2 (en) Construction method of tunnel junction
JP2013245533A (en) Reinforcing method for proximity mountain tunnel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110303

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120222

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120228

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20120626