Prior art keywords
pile
jig
pile construction
coupling bar
pile head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008208305A
Other languages
Japanese (ja)
Other versions
JP5111291B2 (en
Inventor
Seiji Umezawa
正治 梅澤
Masami Tominaga
政巳 富永
Isamu Urushibata
勇 漆畑
Kenichi Kaneko
健一 金子
Toru Okabe
徹 岡部
Masahiro Kamimura
昌弘 上村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Concrete Industries Co Ltd
Original Assignee
Nippon Concrete Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Concrete Industries Co Ltd filed Critical Nippon Concrete Industries Co Ltd
Priority to JP2008208305A priority Critical patent/JP5111291B2/en
Publication of JP2010043471A publication Critical patent/JP2010043471A/en
Application granted granted Critical
Publication of JP5111291B2 publication Critical patent/JP5111291B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a pile construction apparatus for laying a pile body to which a pile head connection reinforcement is exposed. <P>SOLUTION: The pile construction apparatus 14 is provided on the upper side of the pile body 11. The pile construction apparatus 14 includes a pile construction tool 16 having a connection reinforcement storage space 15 fitted onto a pile head of the pile body 11 to which the pile head connection reinforcement 13 is exposed, and a lifting operating body 17 performing at least the lifting operation of the pile body 11 through the pile construction tool 16. The pile construction tool 16 includes a plurality of fitting groove parts 23 at the lower part of a tool body 21 formed in cylindrical shape. The fitting groove parts 23 are detachably fittable to a plurality of projecting parts 22 projected to the upper end side face of the pile body 11 according to the rotating direction of the tool body 21. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、杭頭結合筋が露出された杭体を布設する杭施工装置および杭施工方法に関する。   The present invention relates to a pile construction device and a pile construction method for laying a pile body in which a pile head coupling bar is exposed.

図8に示されるように、杭体1の杭頭2内には杭頭結合筋3が埋め込まれていて、この杭頭結合筋3が所定のレベル、一般的にはグランドレベル4より低いレベルに布設される。その後、基礎ベースコンクリートが構築された後、杭体1の杭頭2内に埋め込まれた杭頭結合筋3を露出する作業が行なわれる(例えば、引用文献1、2参照)。   As shown in FIG. 8, a pile head coupling bar 3 is embedded in the pile head 2 of the pile body 1, and the pile head coupling bar 3 is at a predetermined level, generally a level lower than the ground level 4. Is laid. Then, after foundation base concrete is constructed, the work which exposes the pile head connecting reinforcement 3 embedded in the pile head 2 of the pile body 1 is performed (for example, refer to cited documents 1 and 2).

要するに、杭頭結合筋3を露出させた杭体1をそのままの状態で布設する施工方法は、従来技術にはなく、杭体1を布設した後に、例えば、パイルカッタを用いて杭頭2のコンクリート部分を切断し、杭頭結合筋3を露出させるようにしている。鋼管コンクリート杭(いわゆるSC杭)では、酸素溶断、もしくはグラインダにて鋼管をカットしてコンクリート中に埋め込んだ杭頭結合筋3をはつり出すカットオフ作業が行なわれる。   In short, the construction method for laying the pile body 1 with the head joint bars 3 exposed as it is is not in the prior art, and after laying the pile body 1, for example, the concrete of the pile head 2 using a pile cutter The portion is cut so that the pile head connecting muscle 3 is exposed. In steel pipe concrete piles (so-called SC piles), cut-off work is performed in which the steel pipes are cut with an oxygen fusing or a grinder and the pile head connecting bars 3 embedded in the concrete are lifted.

そして、これらの杭頭結合筋3に橋脚などの地上構造物5の基礎部6が施工される。
特開2002−054136号公報(第2−3頁、図1−3) 特開2005−213963号公報(第4−5頁、図2−5)
And the foundation part 6 of ground structures 5, such as a bridge pier, is constructed to these pile head connecting muscles 3. FIG.
JP 2002-054136 A (page 2-3, FIG. 1-3) Japanese Patent Laying-Open No. 2005-213963 (page 4-5, FIG. 2-5)

この従来の方法には、杭頭結合筋3を長く突出させる必要があり、杭頭結合筋3をはつり出すカットオフ作業に要する工費および工期がかかり、カットオフ作業に伴ないスクラップなどの産業廃棄物が発生するなどの問題もある。   In this conventional method, it is necessary to make the pile head connecting bar 3 protrude long, and the construction cost and work period required for cutting off the pile head connecting bar 3 are increased. There are also problems such as the generation of things.

一方、杭頭から杭頭結合筋を露出させた杭体を成形すれば、上記のような杭頭のカットオフ作業をする必要はないが、このような杭頭結合筋が露出したままの状態の杭体を布設する施工方法は、従来考えられていない。   On the other hand, if the pile body with the pile head coupling bar exposed from the pile head is molded, it is not necessary to perform the cut-off work of the pile head as described above, but such a pile head coupling bar is still exposed. A construction method for laying a pile body has not been considered.

本発明は、このような点に鑑みなされたもので、杭頭結合筋が露出された杭体を布設するための杭施工装置および杭施工方法を提供することを目的とする。   This invention is made | formed in view of such a point, and it aims at providing the pile construction apparatus and the pile construction method for laying the pile body from which the pile head joint reinforcement was exposed.

請求項1に記載された発明は、杭頭結合筋が露出された杭体の杭頭上に被嵌される結合筋収納空間を有する杭施工治具と、この杭施工治具を介して杭体を少なくとも昇降操作する昇降操作体とを具備した杭施工装置である。   The invention described in claim 1 includes a pile construction jig having a coupling bar storage space fitted on a pile head of a pile body in which the pile head coupling bars are exposed, and a pile body via the pile construction jig. It is the pile construction apparatus which comprised the raising / lowering operation body which raises / lowers at least.

請求項2に記載された発明は、請求項1記載の杭施工装置における杭施工治具が、円筒状に形成された治具本体と、この治具本体の下部に設けられ治具本体の回転方向により杭体の上端部側面に突出された突起部に対し嵌脱自在の嵌合溝部とを具備したものである。   According to a second aspect of the present invention, the pile construction jig in the pile construction apparatus according to the first aspect is provided with a jig body formed in a cylindrical shape, and a rotation of the jig body provided at a lower portion of the jig body. It is provided with a fitting groove part that can be freely inserted into and removed from the protruding part that protrudes from the side of the upper end part of the pile body depending on the direction.

請求項3に記載された発明は、請求項1または2記載の杭施工装置における杭施工治具の治具本体が、嵌合溝部を備えた外筒部と、この外筒部の内側に同心状に設けられ中空に形成された杭体の内径面と連続的に設けられた内径面を有する内筒部と、この内筒部の上端に開口されて掘削用のオーガスクリューが挿入されるスクリュー挿入口とを備え、昇降操作体は、杭施工治具のスクリュー挿入口上に連続するスクリュー挿入筒部を備えたものである。   According to a third aspect of the present invention, the jig body of the pile construction jig in the pile construction device according to the first or second aspect is concentric with the outer cylinder part provided with the fitting groove part and the inner side of the outer cylinder part. An inner cylinder portion having an inner diameter surface continuously provided with an inner diameter surface of a pile body that is provided in a hollow shape, and a screw that is opened at the upper end of the inner cylinder portion and into which an auger screw for excavation is inserted The raising / lowering operation body is provided with the screw insertion cylinder part which continues on the screw insertion port of a pile construction jig.

請求項4に記載された発明は、請求項1または2記載の杭施工装置における杭施工治具が、中空に形成された杭体の内部を経て上昇するプレボーリング孔内充填材排出用の排出穴を備えたものである。   The invention described in claim 4 is a discharge for discharging the filling material in the pre-boring hole in which the pile construction jig in the pile construction apparatus according to claim 1 or 2 rises through the inside of the pile body formed hollow. It has a hole.

請求項5に記載された発明は、請求項1乃至4のいずれか記載の杭施工装置における昇降操作体として、ヤットコを用いるものである。   The invention described in claim 5 uses a yatco as a lifting operation body in the pile construction device according to any one of claims 1 to 4.

請求項6に記載された発明は、杭頭結合筋が露出された杭体の杭頭上に結合筋収納空間を有する杭施工治具を被嵌して一体化し、この杭施工治具を介して昇降操作体により杭体を布設する杭施工方法である。   In the invention described in claim 6, a pile construction jig having a coupling bar storage space is fitted and integrated on the pile head of the pile body where the pile head coupling bars are exposed, and the pile construction jig is inserted through the pile construction jig. This is a pile construction method in which a pile body is laid by a lifting operation body.

請求項1に記載された発明によれば、杭頭結合筋が露出された杭体を、その杭頭上に被嵌される結合筋収納空間を有する杭施工治具を介して、昇降操作体により少なくとも昇降操作するので、杭頭結合筋が露出されたままの杭体を布設することができ、杭頭結合筋をはつり出すカットオフ作業を行なう場合の問題点を解消できる。   According to the invention described in claim 1, the pile body in which the pile head coupling bar is exposed is moved by the lifting operation body through the pile construction jig having the coupling bar storage space fitted on the pile head. Since at least the lifting operation is performed, it is possible to lay a pile body in which the pile head connecting bars are exposed, and it is possible to solve the problem in the case of performing the cut-off work for lifting the pile head connecting bars.

請求項2に記載された発明によれば、治具本体の下部に、その回転方向により杭体の上端部側面に突出された突起部に対し嵌脱自在の嵌合溝部を設けたので、昇降操作体により治具本体を回転させる方向によって、杭施工治具の嵌合溝部と杭体の突起部とを簡単に脱着できる。   According to the second aspect of the present invention, the fitting groove portion that can be fitted and removed with respect to the protruding portion that protrudes from the side of the upper end portion of the pile body according to the rotation direction is provided at the lower portion of the jig body. The fitting groove portion of the pile construction jig and the protrusion portion of the pile body can be easily detached according to the direction in which the jig body is rotated by the operating body.

請求項3に記載された発明によれば、杭施工治具の治具本体は、外筒部の内側に杭体の内径面と連続的な内筒部を設け、この内筒部の上端にスクリュー挿入口を開口し、このスクリュー挿入口上に昇降操作体のスクリュー挿入筒部を連続的に設けたので、これらの内筒部、スクリュー挿入口およびスクリュー挿入筒部を通して、掘削用のオーガスクリューを挿入する中掘り工法にこの杭施工装置を適用でき、中掘り工法においても、杭頭結合筋が露出されたままの杭体を布設することができ、杭頭結合筋をはつり出すカットオフ作業を行なう場合の問題点を解消できる。   According to the invention described in claim 3, the jig body of the pile construction jig is provided with the inner cylinder part continuous with the inner diameter surface of the pile body inside the outer cylinder part, and at the upper end of the inner cylinder part. Since the screw insertion opening is opened and the screw insertion cylinder part of the lifting operation body is continuously provided on the screw insertion opening, the auger screw for excavation is passed through these inner cylinder part, screw insertion opening and screw insertion cylinder part. This pile construction device can be applied to the medium digging method to be inserted, and even in the medium digging method, the pile body with the pile head coupling bar exposed can be laid, and the cut-off work to lift the pile head coupling bar can be performed. You can solve the problem of doing it.

請求項4に記載された発明によれば、杭体内を上昇したプレボーリング孔内充填材を、杭施工治具に設けられた排出穴から外部へ排出できるので、充填材が投入された掘削穴に杭体を挿入するプレボーリング工法にこの杭施工装置を適用でき、プレボーリング工法においても、杭頭結合筋が露出されたままの杭体を布設することができ、杭頭結合筋をはつり出すカットオフ作業を行なう場合の問題点を解消できる。   According to the invention described in claim 4, the filler in the pre-boring hole that has risen in the pile body can be discharged to the outside from the discharge hole provided in the pile construction jig. This pile construction device can be applied to the pre-boring method that inserts the pile body into the pile body, and even in the pre-boring method, it is possible to lay the pile body with the pile head connecting bar exposed, and hang out the pile head connecting bar Problems associated with the cut-off work can be solved.

請求項5に記載された発明によれば、必要な長さのヤットコにより、杭体の杭頭および杭頭結合筋をグランドレベルから任意の深さのレベルに布設できる。   According to the invention described in claim 5, the pile head of the pile body and the pile head coupling bar can be laid from the ground level to an arbitrary depth level with the necessary length of the yatco.

請求項6に記載された発明によれば、杭頭結合筋が露出された杭体の杭頭上に被嵌された杭施工治具を介して、昇降操作体により杭体を布設する杭施工方法であるので、杭頭結合筋をはつり出すカットオフ作業を不要にでき、カットオフ作業を行なう場合の問題点を解消できる。   According to the invention described in claim 6, the pile construction method of laying the pile body by the lifting operation body through the pile construction jig fitted on the pile head of the pile body where the pile head coupling bar is exposed. Therefore, it is possible to eliminate the cut-off work for lifting the pile head connecting bars, and to solve the problems in the case of performing the cut-off work.

以下、本発明を、図1乃至図3に示された第1実施の形態、図4および図5に示された第2実施の形態、図6に示された第3実施の形態、図7に示された第4実施の形態を参照しながら詳細に説明する。   Hereinafter, the present invention will be described with reference to the first embodiment shown in FIGS. 1 to 3, the second embodiment shown in FIGS. 4 and 5, the third embodiment shown in FIG. This will be described in detail with reference to the fourth embodiment shown in FIG.

先ず、図1乃至図3に示された第1実施の形態を説明する。   First, the first embodiment shown in FIGS. 1 to 3 will be described.

図1に示される杭体11は、杭頭の上端プレート12から杭頭結合筋13が杭成形時から突出された鋼管コンクリート杭(いわゆるSC杭)である。この種の杭体11は、杭本体11aから露出した鉄筋である杭頭結合筋13の防錆対策として、例えば、セメントペーストが充填された袋等で杭頭結合筋13の露出部分を覆うか、あるいは、ポリエステルフィルムなどを杭頭結合筋13の露出部分に巻き付けるなどの方法を採用することで、杭体11を施工する前に露出した杭頭結合筋13が錆びないように保護する。   The pile body 11 shown in FIG. 1 is a steel pipe concrete pile (so-called SC pile) in which a pile head coupling bar 13 protrudes from the upper end plate 12 of the pile head from the time of pile formation. This type of pile body 11 is, for example, a cover filled with cement paste that covers the exposed portion of the pile head joint bar 13 as a rust prevention measure for the pile head joint bar 13 that is a reinforcing bar exposed from the pile body 11a. Alternatively, by adopting a method such as wrapping a polyester film or the like around the exposed portion of the pile head coupling bar 13, the exposed pile head coupling bar 13 is protected from rusting before the pile body 11 is constructed.

この杭体11の上側に設けられた杭施工装置14は、杭頭結合筋13が露出された杭体11の杭頭上に被嵌される結合筋収納空間15を有する杭施工治具16と、この杭施工治具16を介して杭体11を少なくとも昇降操作する昇降操作体17とを具備したものである。   The pile construction device 14 provided on the upper side of the pile body 11 includes a pile construction jig 16 having a coupling bar storage space 15 fitted on the pile head of the pile body 11 where the pile head coupling bar 13 is exposed, An elevating operation body 17 for at least elevating and lowering the pile body 11 through the pile construction jig 16 is provided.

杭施工治具16は、図1に示されるように円筒状に形成された治具本体21の下部に、図2に示されるように治具本体21の回転方向により杭体11の上端部側面に突出された複数の突起部22に対し嵌脱自在の複数の嵌合溝部23が設けられている。   As shown in FIG. 1, the pile construction jig 16 is arranged on the lower side of the jig body 21 formed in a cylindrical shape, and on the side of the upper end of the pile body 11 depending on the rotation direction of the jig body 21 as shown in FIG. 2. A plurality of fitting groove portions 23 that are detachable with respect to the plurality of projecting portions 22 projecting from each other are provided.

複数の突起部22は、鋼管24または鋼製のバンドに溶接され、複数の嵌合溝部23は、図2に示されるように治具本体21の下端から上方へ切込形成された縦溝25と、この縦溝25の上端から横方向に切込形成された横溝26とがL字状に設けられたものである。   The plurality of protrusions 22 are welded to a steel pipe 24 or a steel band, and the plurality of fitting grooves 23 are longitudinal grooves 25 formed by cutting upward from the lower end of the jig body 21 as shown in FIG. In addition, a horizontal groove 26 cut in the horizontal direction from the upper end of the vertical groove 25 is provided in an L shape.

図1および図3に示されるように、杭施工治具16の治具本体21は、嵌合溝部23を備えた外筒部21aと、この外筒部21aの内側に同心状に設けられた内筒部21bとを備えている。この内筒部21bは、中空に形成された杭体11の内径面と連続的に設けられた内径面を有し、その内部には、スクリュー挿入空間27が設けられている。   As shown in FIG. 1 and FIG. 3, the jig body 21 of the pile construction jig 16 is provided concentrically with the outer cylinder part 21a having the fitting groove part 23 and the inner side of the outer cylinder part 21a. And an inner cylinder portion 21b. The inner cylinder portion 21b has an inner diameter surface provided continuously with the inner diameter surface of the pile body 11 formed in a hollow shape, and a screw insertion space 27 is provided therein.

図1および図3に示されるように、外筒部21aと内筒部21bとの下部間には、杭体11の上端プレート12に係合されるリング状の係止プレート28が溶接され、この係止プレート28には、図3に示されるように複数の杭頭結合筋13をそれぞれ挿通するための円弧状の結合筋挿通穴29が穿設されており、さらに、各結合筋挿通穴29,29間には、外筒部21aと内筒部21bとの間に放射状に溶接された複数の補強リブ30が配置されている。   As shown in FIGS. 1 and 3, a ring-shaped locking plate 28 that is engaged with the upper end plate 12 of the pile body 11 is welded between the lower portions of the outer cylinder portion 21a and the inner cylinder portion 21b. As shown in FIG. 3, the locking plate 28 is formed with arc-shaped connecting bar insertion holes 29 for inserting the plurality of pile head connecting bars 13, and each connecting bar insertion hole is further inserted. Between the 29 and 29, a plurality of reinforcing ribs 30 that are radially welded are disposed between the outer cylinder portion 21a and the inner cylinder portion 21b.

図1に示されるように、杭施工治具16の治具本体21は、内筒部21bの上端に開口されて掘削用のオーガスクリューSが挿入されるスクリュー挿入口31を備えている。一方、昇降操作体17は、杭施工治具16のスクリュー挿入口31上に連続するスクリュー挿入筒部32を備えている。   As shown in FIG. 1, the jig body 21 of the pile construction jig 16 includes a screw insertion port 31 that is opened at the upper end of the inner cylinder portion 21b and into which an auger screw S for excavation is inserted. On the other hand, the lifting operation body 17 includes a screw insertion cylinder portion 32 continuous on the screw insertion port 31 of the pile construction jig 16.

この昇降操作体17としては、ヤットコを用いる。このヤットコは、杭頭布設レベルが深い場合を想定して、種々のサイズのものを、ボルト33により杭施工治具16の上端プレート部34と脱着可能に連結できる構造とする。すなわち、このヤットコは、オーガスクリューSを挿入するためのスクリュー挿入筒部32の下端部に杭施工治具16の上端プレート部34と連結されるフランジ状プレート35が溶接され、このフランジ状プレート35上に複数の補強リブ36が放射状に配置されて溶接され、各補強リブ36間に上記ボルト33が配置されている。   A Yatco is used as the lifting operation body 17. Assuming that the pile head laying level is deep, this Yatco has a structure in which various sizes can be detachably connected to the upper end plate portion 34 of the pile construction jig 16 by bolts 33. That is, in this YATCO, a flange-like plate 35 connected to the upper end plate portion 34 of the pile construction jig 16 is welded to the lower end portion of the screw insertion cylinder portion 32 for inserting the auger screw S. A plurality of reinforcing ribs 36 are arranged radially and welded thereon, and the bolts 33 are arranged between the reinforcing ribs 36.

次に、この第1実施の形態の作用効果を説明する。   Next, the function and effect of the first embodiment will be described.

杭体11内に掘削用のオーガスクリューSを挿入する中掘り工法において、杭頭結合筋13が露出された杭体11の杭頭上に結合筋収納空間15を有する杭施工治具16を被嵌して一体的に係着する。その係着は、杭体11の上端部側面に突出された突起部22に杭施工治具16の嵌合溝部23の縦溝25を位置合わせして、昇降操作体17により杭施工治具16を下げることで、相対的に縦溝25内に突起部22を挿入し、さらに、昇降操作体17により杭施工治具16を回動することで、相対的に横溝26内に突起部22を挿入する。杭施工治具16を反対方向へ回動することで、突起部22を嵌合溝部23内から外すことができる。   In the middle digging method in which the auger screw S for excavation is inserted into the pile body 11, the pile construction jig 16 having the coupling bar storage space 15 is fitted on the pile head of the pile body 11 where the pile head coupling bar 13 is exposed. And engage with each other. The engagement is performed by aligning the vertical groove 25 of the fitting groove portion 23 of the pile construction jig 16 with the protrusion 22 projecting from the side surface of the upper end of the pile body 11, and the pile construction jig 16 by the lifting operation body 17. The protrusion 22 is relatively inserted into the longitudinal groove 25 by lowering the height, and further, the pile construction jig 16 is rotated by the lifting operation body 17, so that the protrusion 22 is relatively inserted into the lateral groove 26. insert. By rotating the pile construction jig 16 in the opposite direction, the protrusion 22 can be removed from the fitting groove 23.

このようにして杭体11の上部に係着された杭施工治具16を介して、昇降操作体17により杭体11をオーガスクリューSとともに下降させ布設する。このとき、オーガスクリューSにより杭体11内を上昇された土砂などは、杭施工治具16のスクリュー挿入空間27および昇降操作体17のスクリュー挿入筒部32を経て、外部へ排出される。   In this manner, the pile body 11 is lowered together with the auger screw S by the lifting operation body 17 through the pile construction jig 16 attached to the upper portion of the pile body 11 and installed. At this time, the soil and the like raised in the pile body 11 by the auger screw S is discharged to the outside through the screw insertion space 27 of the pile construction jig 16 and the screw insertion cylinder portion 32 of the lifting operation body 17.

この実施の形態によれば、杭頭結合筋13が露出された杭体11を、その杭頭上に被嵌された結合筋収納空間15を有する杭施工治具16を介して、昇降操作体17により昇降操作するので、杭頭結合筋13が露出されたままの杭体11を布設することができ、杭頭結合筋13をはつり出すカットオフ作業が不要となり、このカットオフ作業を行なう場合の問題点を解消できる。   According to this embodiment, the pile body 11 with the pile head coupling bar 13 exposed is moved up and down through the pile construction jig 16 having the coupling bar storage space 15 fitted on the pile head. Therefore, the pile body 11 with the pile head connecting bars 13 exposed can be laid, and the cut-off work for lifting the pile head connecting bars 13 becomes unnecessary. The problem can be solved.

すなわち、杭頭結合筋13の埋め込み部分での杭材コストの削減、カットオフが不要となるためにカット費用の削減、カットオフにより生ずるスクラップ処理費の削減に伴うコスト縮減を図れるとともに、下部工事における工期が大きく短縮される効果が顕著となる。また、カットオフでのエネルギー削減とスクラップ化される鋼材およびコンクリートの資源環境対策効果も大きい。   In other words, the pile material cost at the embedded portion of the pile head coupling bar 13 is reduced, and cut-off is not required, so cut costs can be reduced, and the cost reduction associated with the reduction of scrap processing costs caused by the cut-off can be achieved. The effect of greatly shortening the construction period is remarkable. In addition, energy saving measures at the cut-off and resource environment countermeasure effect of steel and concrete to be scrapped are great.

また、治具本体21の下部に、その回転方向により杭体11の上端部側面に突出された突起部22に対し嵌脱自在の嵌合溝部23を設けたので、昇降操作体17により治具本体21を回転させる方向によって、杭施工治具16の嵌合溝部23と杭体11の突起部22とを簡単に脱着できる。   In addition, since a fitting groove 23 is provided at the lower part of the jig main body 21 so as to be detachable with respect to the protrusion 22 protruding from the side surface of the upper end portion of the pile body 11 in the rotational direction. Depending on the direction in which the main body 21 is rotated, the fitting groove 23 of the pile construction jig 16 and the protrusion 22 of the pile body 11 can be easily detached.

杭施工治具16の治具本体21は、外筒部21aの内側に杭体11の内径面と連続的な内筒部21bを設け、この内筒部21bの上端にスクリュー挿入口31を開口し、このスクリュー挿入口31上に昇降操作体17のスクリュー挿入筒部32を連続的に設けたので、これらの内筒部21b、スクリュー挿入口31およびスクリュー挿入筒部32を通して、オーガスクリューSを挿入する中掘り工法にこの杭施工装置14を適用でき、中掘り工法においても、杭頭結合筋13が露出されたままの杭体11を布設することができ、杭頭結合筋13をはつり出すカットオフ作業を行なう場合の問題点を解消できる。   The jig body 21 of the pile construction jig 16 is provided with an inner cylinder part 21b continuous with the inner diameter surface of the pile body 11 inside the outer cylinder part 21a, and a screw insertion port 31 is opened at the upper end of the inner cylinder part 21b. Since the screw insertion cylinder portion 32 of the lifting operation body 17 is continuously provided on the screw insertion port 31, the auger screw S is passed through the inner cylinder portion 21b, the screw insertion port 31, and the screw insertion cylinder portion 32. This pile construction device 14 can be applied to the intermediate digging method to be inserted, and also in the medium digging method, the pile body 11 with the pile head coupling bar 13 exposed can be laid, and the pile head coupling bar 13 is pulled out. Problems associated with the cut-off work can be solved.

昇降操作体17として、必要な長さのヤットコを用いることで、杭体11の杭頭および杭頭結合筋13をグランドレベルから任意の深さのレベルに布設できる。   By using a Yatco having a required length as the lifting operation body 17, the pile head of the pile body 11 and the pile head coupling bar 13 can be laid from the ground level to an arbitrary depth level.

次に、図4および図5に示された第2実施の形態を説明する。   Next, a second embodiment shown in FIGS. 4 and 5 will be described.

この第2実施の形態の杭施工装置14は、図4に示されるように外筒部21aの上部と内筒部21bの上部との間に複数の補強リブ30aが、放射状に溶接されているとともに、図5に示されるように複数の杭頭結合筋13を挿通するための結合筋挿通穴29aが、外筒部21aに溶接されたリング状の係止プレート28aと、内筒部21bに溶接されたリング状の係止プレート28bとの間に、連続的に形成されている。他の構成および作用効果は、第1実施の形態と同様であるから、その説明を省略する。   In the pile construction apparatus 14 of the second embodiment, a plurality of reinforcing ribs 30a are radially welded between the upper part of the outer cylinder part 21a and the upper part of the inner cylinder part 21b as shown in FIG. In addition, as shown in FIG. 5, a connecting bar insertion hole 29a for inserting a plurality of pile head connecting bars 13 is formed in a ring-shaped locking plate 28a welded to the outer cylinder part 21a and the inner cylinder part 21b. It is continuously formed between the welded ring-shaped locking plate 28b. Other configurations and operational effects are the same as those of the first embodiment, and thus the description thereof is omitted.

次に、図6に示された第3実施の形態を説明する。   Next, a third embodiment shown in FIG. 6 will be described.

図6に示された杭施工装置14は、杭頭結合筋13が露出された杭体11の杭頭上に被嵌される結合筋収納空間15を有する杭施工治具16と、この杭施工治具16を介して杭体11を昇降操作する昇降操作体17とを具備した点で、第1実施の形態と同様である。   The pile construction device 14 shown in FIG. 6 includes a pile construction jig 16 having a joint reinforcement storage space 15 fitted on the pile head of the pile body 11 from which the pile head joint reinforcement 13 is exposed, and this pile construction treatment. It is the same as that of 1st Embodiment by the point which comprised the raising / lowering operation body 17 which raises / lowers the pile body 11 via the tool 16. FIG.

杭施工治具16は、円筒状に形成された治具本体21と、この治具本体21の下部に設けられ治具本体21の回転方向により杭体11の上端部側面に突出された突起部22に対し嵌脱自在の嵌合溝部23とを具備した点でも、第1実施の形態と同様である。   The pile construction jig 16 includes a jig body 21 formed in a cylindrical shape, and a protrusion provided on the lower side of the jig body 21 and projecting from the side of the upper end of the pile body 11 by the rotation direction of the jig body 21. The second embodiment is the same as the first embodiment also in that a fitting groove portion 23 that can be fitted and detached with respect to 22 is provided.

さらに、この杭施工装置14における杭施工治具16の上端プレート部34は、閉じられた閉塞型であるので、治具本体21の側面部に、中空に形成された杭体11の内部を経て上昇するプレボーリング孔内充填材排出用の排出穴38を備えている。すなわち、プレボーリング孔内での杭体11の下降に伴なって、プレボーリング孔内に投入されているセメントミルクなどの充填材が杭体11内で上昇するので、この充填材を排出穴38より外部へ排出する。   Furthermore, since the upper end plate portion 34 of the pile construction jig 16 in the pile construction apparatus 14 is a closed block type, it passes through the inside of the pile body 11 formed hollow on the side surface portion of the jig body 21. A discharge hole 38 for discharging the filler in the rising pre-boring hole is provided. That is, as the pile body 11 descends in the pre-boring hole, the filler such as cement milk that has been put into the pre-boring hole rises in the pile body 11, so that this filler is discharged into the discharge hole 38. Discharge more outside.

また、昇降操作体17としては、杭施工治具16の上端プレート部34の中央部にヤットコ連結部材39aが溶接され、このヤットコ連結部材39aの上端凸部39bに中空ロッド状のヤットコ39cを嵌着してこれらのピン穴に挿入された連結ピン39dにより、ヤットコ連結部材39aとヤットコ39cとを脱着可能に連結させたものであり、必要な長さのヤットコ39cを用いることにより、杭体11の杭頭および杭頭結合筋13をグランドレベルから任意の深さのレベルに布設できる。   Further, as the lifting operation body 17, a Yatco connecting member 39a is welded to the center of the upper end plate portion 34 of the pile construction jig 16, and a hollow rod-shaped Yatco 39c is fitted to the upper end convex portion 39b of the Yatco connecting member 39a. The connecting pin 39d inserted and inserted into these pin holes is connected to the Yatco connecting member 39a and the Yatco 39c so as to be detachable. By using the Yatco 39c of a necessary length, the pile body 11 The pile head and the pile head connecting muscle 13 can be laid from the ground level to an arbitrary depth level.

そして、セメントミルクなどの充填材が充填されたプレボーリング孔内に杭体11を挿入するプレボーリング工法において、杭頭結合筋13が露出された杭体11の杭頭上に結合筋収納空間15を有する杭施工治具16を被嵌して一体化し、この杭施工治具16を介して昇降操作体17により杭体11を布設する。   Then, in the pre-boring method in which the pile body 11 is inserted into the pre-boring hole filled with a filler such as cement milk, the coupling bar storage space 15 is formed on the pile head of the pile body 11 where the pile head coupling bar 13 is exposed. The pile construction jig 16 that is included is fitted and integrated, and the pile body 11 is laid by the lifting operation body 17 via the pile construction jig 16.

この第3実施の形態によれば、充填材が充填された掘削穴に杭体11を挿入するプレボーリング工法においても、杭体内を上昇したプレボーリング孔内充填材を、杭施工治具16に設けられた排出穴38から外部へ排出できるので、この杭施工治具16を介して、杭頭結合筋13が露出されたままの杭体11を布設することができ、杭頭結合筋13をはつり出すカットオフ作業を行なう場合の問題点を解消できる。   According to the third embodiment, even in the pre-boring method in which the pile body 11 is inserted into the excavation hole filled with the filler, the filler in the pre-boring hole that has risen in the pile body is used as the pile construction jig 16. Since it can be discharged to the outside through the provided discharge hole 38, the pile body 11 with the pile head coupling bar 13 exposed can be laid through the pile construction jig 16, and the pile head coupling bar 13 can be This eliminates the problems associated with carrying out cut-off work.

次に、図7は、第4実施の形態を示し、図6に示された実施の形態の昇降操作体17として、図1に示されたヤットコを用いたものであり、必要な長さのヤットコを用いることにより、杭体11の杭頭および杭頭結合筋13をグランドレベルから任意の深さのレベルに布設できる。他の構成および作用効果は、図6に示されたものと同様である。   Next, FIG. 7 shows a fourth embodiment, in which the yacht shown in FIG. 1 is used as the lifting operation body 17 of the embodiment shown in FIG. By using a Yatco, the pile head of the pile body 11 and the pile head coupling bar 13 can be laid from the ground level to a level of an arbitrary depth. Other configurations and operational effects are the same as those shown in FIG.

以上のように、中掘り工法においても、プレボーリング工法においても、杭頭結合筋13が露出された杭体11の杭頭上に被嵌された杭施工治具16を介して、昇降操作体17により杭体11を布設する杭施工方法を採用し、杭頭結合筋13をはつり出すカットオフ作業を不要にでき、カットオフ作業を行なう場合の問題点を解消できる。   As described above, in both the underground digging method and the pre-boring method, the lifting operation body 17 is provided via the pile construction jig 16 fitted on the pile head of the pile body 11 where the pile head coupling bar 13 is exposed. By adopting a pile construction method for laying the pile body 11 by the above, it is possible to eliminate the need for the cut-off work for lifting the pile head connecting bars 13 and to solve the problems in the case of performing the cut-off work.

すなわち、杭頭結合筋13が露出した杭体11を製造して、杭施工治具16により、この杭頭結合筋13が露出した状態でグランドレベルより低い所定のレベル位置に杭頭部を揃えて布設するので、杭頭結合筋13の長さを最初から短くして余長部分を削除でき、また、鉄筋はつり出しカットオフ作業を不要にできるので、工費を削減できるとともに工期を短縮でき、さらに、杭頭結合筋のはつり出しカットオフ作業に伴うスクラップの発生がなくなり、廃棄物を削減でき、経済的である。   That is, the pile body 11 with the pile head connecting bars 13 exposed is manufactured, and the pile heads are aligned at a predetermined level position lower than the ground level by the pile construction jig 16 with the pile head connecting bars 13 exposed. Therefore, the length of the pile head connecting bar 13 can be shortened from the beginning and the extra length part can be deleted, and the reinforcing bar can be erected and cut-off work can be eliminated. In addition, the pile head connecting bars can be scrapped due to the lifting cut-off operation, and the waste can be reduced, which is economical.

なお、杭施工治具の嵌合溝部は、治具本体の下端から切込状に形成した例を示したが、治具本体の下端から内面に凹溝を付けるように形成しても良い。また、杭体11として鋼管コンクリート杭(SC杭)の例を示したが、突起部22を設けた鋼管24を杭体11の全長より短くしたコンクリート杭(いわゆるPC杭またはPRC杭)でも良い。   In addition, although the fitting groove part of the pile construction jig | tool showed the example formed in the cut shape from the lower end of a jig | tool main body, you may form so that a concave groove may be attached to the inner surface from the lower end of a jig | tool main body. Moreover, although the example of the steel pipe concrete pile (SC pile) was shown as the pile body 11, the concrete pile (what is called PC pile or PRC pile) which made the steel pipe 24 which provided the projection part 22 shorter than the full length of the pile body 11 may be sufficient.

本発明は、プレボーリング工法または中掘り工法などにより、所定深度に杭体を布設する際に利用可能である。   INDUSTRIAL APPLICABILITY The present invention can be used when laying a pile body at a predetermined depth by a pre-boring method or a digging method.

本発明に係る杭施工装置の第1実施の形態を示す断面図である。It is sectional drawing which shows 1st Embodiment of the pile construction apparatus which concerns on this invention. 同上杭施工装置の正面図である。It is a front view of a pile construction apparatus same as the above. 図1のIII−III線断面図である。It is the III-III sectional view taken on the line of FIG. 同上杭施工装置の第2実施の形態を示す断面図である。It is sectional drawing which shows 2nd Embodiment of a pile construction apparatus same as the above. 図4のV−V線断面図である。It is the VV sectional view taken on the line of FIG. 同上杭施工装置の第3実施の形態を示す断面図である。It is sectional drawing which shows 3rd Embodiment of a pile construction apparatus same as the above. 同上杭施工装置の第4実施の形態を示す断面図である。It is sectional drawing which shows 4th Embodiment of a pile construction apparatus same as the above. 杭頭結合筋の施工例を示す断面図である。It is sectional drawing which shows the construction example of a pile head coupling | bonding reinforcement.

符号の説明Explanation of symbols

11 杭体
13 杭頭結合筋
14 杭施工装置
15 結合筋収納空間
16 杭施工治具
17 昇降操作体
21 治具本体
21a 外筒部
21b 内筒部
22 突起部
23 嵌合溝部
31 スクリュー挿入口
32 スクリュー挿入筒部
38 排出穴
S オーガスクリュー
11 Pile
13 Pile head connecting muscle
14 Pile construction equipment
15 Connecting muscle storage space
16 Pile construction jig
17 Lifting operation body
21 Jig body
21a Outer tube
21b Inner tube
22 Protrusion
23 Mating groove
31 Screw insertion slot
32 Screw insertion tube
38 discharge hole S auger screw

Claims (6)

杭頭結合筋が露出された杭体の杭頭上に被嵌される結合筋収納空間を有する杭施工治具と、
この杭施工治具を介して杭体を少なくとも昇降操作する昇降操作体と
を具備したことを特徴とする杭施工装置。
A pile construction jig having a coupling bar storage space fitted on the pile head of the pile body where the pile head coupling bar is exposed;
A pile construction device comprising: a lifting operation body that at least lifts and lowers the pile body through the pile construction jig.
杭施工治具は、
円筒状に形成された治具本体と、
この治具本体の下部に設けられ治具本体の回転方向により杭体の上端部側面に突出された突起部に対し嵌脱自在の嵌合溝部と
を具備したことを特徴とする請求項1記載の杭施工装置。
Pile construction jig
A jig body formed in a cylindrical shape;
The fitting groove part which was provided in the lower part of this jig | tool main body, and was able to be fitted or detached with respect to the protrusion part which protruded from the upper end part side surface of the pile body with the rotation direction of the jig | tool main body was comprised. Pile construction equipment.
杭施工治具の治具本体は、
嵌合溝部を備えた外筒部と、
この外筒部の内側に同心状に設けられ中空に形成された杭体の内径面と連続的に設けられた内径面を有する内筒部と、
この内筒部の上端に開口されて掘削用のオーガスクリューが挿入されるスクリュー挿入口とを備え、
昇降操作体は、
杭施工治具のスクリュー挿入口上に連続するスクリュー挿入筒部を備えた
ことを特徴とする請求項1または2記載の杭施工装置。
The jig body of the pile construction jig is
An outer cylinder portion having a fitting groove portion;
An inner cylinder portion having an inner diameter surface provided continuously with an inner diameter surface of a pile body concentrically provided inside the outer cylinder portion,
A screw insertion opening that is opened at the upper end of the inner cylinder and into which an auger screw for excavation is inserted;
The lifting operation body is
The pile construction device according to claim 1 or 2, further comprising a screw insertion tube portion continuous on the screw insertion port of the pile construction jig.
杭施工治具は、中空に形成された杭体の内部を経て上昇するプレボーリング孔内充填材排出用の排出穴を備えた
ことを特徴とする請求項1または2記載の杭施工装置。
The pile construction device according to claim 1 or 2, wherein the pile construction jig includes a discharge hole for discharging the filler in the pre-boring hole that rises through the inside of the pile body formed in a hollow shape.
昇降操作体として、ヤットコを用いる
ことを特徴とする請求項1乃至4のいずれか記載の杭施工装置。
The pile construction device according to any one of claims 1 to 4, wherein a yatco is used as the lifting operation body.
杭頭結合筋が露出された杭体の杭頭上に結合筋収納空間を有する杭施工治具を被嵌して一体化し、
この杭施工治具を介して昇降操作体により杭体を布設する
ことを特徴とする杭施工方法。
A pile construction jig having a coupling bar storage space is fitted and integrated on the pile head of the pile body where the pile head coupling bar is exposed,
A pile construction method characterized in that a pile body is laid by a lifting operation body through the pile construction jig.
JP2008208305A 2008-08-13 2008-08-13 Pile construction equipment Active JP5111291B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008208305A JP5111291B2 (en) 2008-08-13 2008-08-13 Pile construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008208305A JP5111291B2 (en) 2008-08-13 2008-08-13 Pile construction equipment

Publications (2)

Publication Number Publication Date
JP2010043471A true JP2010043471A (en) 2010-02-25
JP5111291B2 JP5111291B2 (en) 2013-01-09

Family

ID=42015050

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008208305A Active JP5111291B2 (en) 2008-08-13 2008-08-13 Pile construction equipment

Country Status (1)

Country Link
JP (1) JP5111291B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013002047A (en) * 2011-06-13 2013-01-07 Maeta Seihin Hanbai Ltd Steel pipe concrete composite pile
CN106013153A (en) * 2016-07-08 2016-10-12 上海长凯岩土工程有限公司 End protector for construction of steel pipe pile and working method thereof
JP2023016396A (en) * 2021-07-21 2023-02-02 稔之 田畑 Reinforcement material
JP2023016395A (en) * 2021-07-21 2023-02-02 稔之 田畑 Reinforcement material

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6217228A (en) * 1985-07-16 1987-01-26 Nippon Concrete Ind Co Ltd Suspending tongs for prc-like pile
JPH0771032A (en) * 1993-06-30 1995-03-14 Mitani Sekisan Co Ltd Prefabricated pile and installation method thereof
JPH11166232A (en) * 1997-12-05 1999-06-22 Asahi Chem Ind Co Ltd Pile hanging jig

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6217228A (en) * 1985-07-16 1987-01-26 Nippon Concrete Ind Co Ltd Suspending tongs for prc-like pile
JPH0771032A (en) * 1993-06-30 1995-03-14 Mitani Sekisan Co Ltd Prefabricated pile and installation method thereof
JPH11166232A (en) * 1997-12-05 1999-06-22 Asahi Chem Ind Co Ltd Pile hanging jig

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013002047A (en) * 2011-06-13 2013-01-07 Maeta Seihin Hanbai Ltd Steel pipe concrete composite pile
CN106013153A (en) * 2016-07-08 2016-10-12 上海长凯岩土工程有限公司 End protector for construction of steel pipe pile and working method thereof
JP2023016396A (en) * 2021-07-21 2023-02-02 稔之 田畑 Reinforcement material
JP2023016395A (en) * 2021-07-21 2023-02-02 稔之 田畑 Reinforcement material

Also Published As

Publication number Publication date
JP5111291B2 (en) 2013-01-09

Similar Documents

Publication Publication Date Title
AU724933B2 (en) Method and apparatus for forming piles in-situ
US9371623B2 (en) Diaphragm wall apparatus and methods
JP5199166B2 (en) Foundation pile structure by site construction and construction method of foundation pile
JP2011106190A (en) Liner plate connection structure and liner plate connection structural body
JP5111291B2 (en) Pile construction equipment
EP3318677B1 (en) Method for forming a reinforced pile and use of an accessory therein
JP2015218516A (en) Construction method of foundation pile whose pile head is reinforced, foundation pile structure whose pile head is reinforced
CN102619215A (en) Lock catch type steel pipe pile structure and construction method thereof
JP5280257B2 (en) Foundation pile structure and construction method of foundation pile
US20150299976A1 (en) Method for manufacturing a pile
KR101021302B1 (en) Pile for underground foundation working and construction method thereof
JP5478225B2 (en) Yatco for pile construction
JP2009174302A (en) Pile head treating method
JP2007224657A (en) Cast-in-place concrete pile construction method
US7429148B2 (en) Method for making a foundation pile
JP4809728B2 (en) manhole
EP1046753B1 (en) Method and apparatus for forming piles in place
AU763775B2 (en) Method and apparatus for forming piles in place
JP2010095907A (en) Reinforcing structure and reinforcing method for existing foundation
JP2009138388A (en) Segment, and construction method for widened section of tunnel
CA2264197C (en) Method and apparatus for forming piles in place
KR102702783B1 (en) Waterproofing method of steel temporary facilities
CN217923617U (en) Joint box for foundation pit supporting occluded plain pile forming
JP4778805B2 (en) Construction method of foundation pile
JP2011021378A (en) Vertical shaft and construction method for the vertical shaft

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110516

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120516

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120523

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120711

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121003

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121009

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151019

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5111291

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250