JP2009235894A - Concrete curing method and system - Google Patents

Concrete curing method and system Download PDF

Info

Publication number
JP2009235894A
JP2009235894A JP2009140723A JP2009140723A JP2009235894A JP 2009235894 A JP2009235894 A JP 2009235894A JP 2009140723 A JP2009140723 A JP 2009140723A JP 2009140723 A JP2009140723 A JP 2009140723A JP 2009235894 A JP2009235894 A JP 2009235894A
Authority
JP
Japan
Prior art keywords
concrete
tunnel
water
hours
support member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009140723A
Other languages
Japanese (ja)
Other versions
JP4866939B2 (en
Inventor
Masanobu Sakamoto
全布 坂本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mashino Co Ltd
Original Assignee
Mashino Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mashino Co Ltd filed Critical Mashino Co Ltd
Priority to JP2009140723A priority Critical patent/JP4866939B2/en
Publication of JP2009235894A publication Critical patent/JP2009235894A/en
Application granted granted Critical
Publication of JP4866939B2 publication Critical patent/JP4866939B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a concrete curing system and method having movable water spray equipment as a measure method for preventing cracking of concrete constructed on a continuum of a tunnel or box culvert. <P>SOLUTION: A support member is assembled at a position separated from the concrete surface of a body structure by 100-300 mm. Wheels are attached to the leg parts of the support member. Water spray tools 3 are installed, and the support member is covered with a waterproof sheet 2. The concrete curing system is installed immediately after removing concrete placing forms, and water spraying is started and continued for 24-72 hours. After completing the water spraying, the concrete curing system can move in this state by one span of concrete placing. A device warming water to adjust water spray temperature can be mounted. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、トンネルやボックスカルバート等の連続体で施工する新設コンクリートのひび割れを防止するためのコンクリート養生設備・方法に関するものである。   The present invention relates to a concrete curing equipment and method for preventing cracking of newly-installed concrete constructed with a continuous body such as a tunnel or a box culvert.

コンクリートの養生方法は、一般にマット養生、散水養生、湛水養生、ムシロ養生、シート養生、養生剤散布等が実施されている。一般コンクリート構造物は、コンクリート打設型枠取り外し後に72時間から168時間程度実施され、コンクリートのひび割れ発生を防いでいる。しかしながら、トンネル二次覆工コンクリートやボックスカルバート等の連続体で施工する構造物は、型枠取り外し後に、その坑内の空間を材料搬出入や掘削土砂・岩の積み出し等で使用するため コンクリートの養生は行われていないのが現状である。その結果、これらのコンクリートにはひび割れが発生している。このひび割れは、施工引渡し時には、ひび割れ幅が増大してエポキシ樹脂等で補修を実施しており、この工程や費用が多く必要となっている。またひび割れ幅0.2ミリメートル以下は補修を実施しないで完成引渡しを行い、そのひび割れが進行さらにひび割れ幅が増大して、コンクリートの剥離・剥落の原因となっている。   As for concrete curing methods, mat curing, watering curing, flooded curing, mushiro curing, sheet curing, curing agent spraying and the like are generally performed. The general concrete structure is carried out for 72 to 168 hours after the concrete casting form is removed to prevent cracking of the concrete. However, for structures constructed with continuums such as tunnel secondary lining concrete and box culverts, the concrete is cured because the space inside the mine is used for material loading and unloading and excavation of sediments and rocks after removing the formwork. Is currently not done. As a result, these concretes are cracked. These cracks are repaired with an epoxy resin or the like because the crack width increases at the time of construction delivery, and this process and cost are required to be large. If the crack width is 0.2 mm or less, the completed delivery is performed without carrying out repairs, and the crack progresses and the crack width increases, causing peeling and peeling of the concrete.

特開2001−248398号公報(審査時引用文献)JP 2001-248398 A (reference document at the time of examination) 特開2000−73696号公報(審判時引用文献)Japanese Unexamined Patent Publication No. 2000-73696 (reference document at the time of trial)

前記したトンネル二次覆工コンクリートやボックスカルバートのひび割れを防止する方法としてコンクリート養生を行うに当たり次のような問題点がある。
「イ」坑内は、コンクリート養生中も通路として開放しなければならない。
「ロ」コンクリート養生設備は、その組み立て設置取り外しが簡便でなければならない。
「ハ」コンクリート表面からの覆い位置は、400mm以内でなければならない。
「ニ」散水した水は、坑内の通路に落としてはいけない。
「ホ」養生の覆いは、コンクリート表面を湿潤に保つことができなければならない。
「ヘ」冬季においては、散水温度を調節できることが必要である。
As a method for preventing cracking of the tunnel secondary lining concrete and box culvert described above, there are the following problems in performing concrete curing.
The “I” mine must be opened as a passageway during concrete curing.
“B” concrete curing equipment must be easy to assemble and remove.
“C” The covering position from the concrete surface must be within 400 mm.
"D" Water sprinkled should not be dropped into a passage in the mine.
The “e” curing cover must be able to keep the concrete surface moist.
“F” In winter, it is necessary to be able to adjust the watering temperature.

本発明は上記したような問題を解決するためになされたもので、トンネル二次覆工コンクリートやボックスカルバートのひび割れを防止する方法として移動式のコンクリート養生設備・方法を提供することを目的とする。   The present invention has been made to solve the above-described problems, and it is an object of the present invention to provide a mobile concrete curing equipment and method as a method for preventing cracking of tunnel secondary lining concrete and box culvert. .

上記のような目的を達成するために、本発明のコンクリート養生設備・方法は、コンクリート打設型枠を取り外し後、直ぐにトンネルリング方向でコンクリート表面から100〜300ミリメートル離れた位置に支保部材を組み立て、その脚部に車輪を取り付ける。次に支保部材に散水設備を設け、この支保部材の全面をコンクリート面側に防水シートで覆い、スプリンクラー方式で散水を開始し24時間〜72時間連続散水することにより、コンクリートのひび割れを防止するものである。この設備は移動式車輪を設置しているため、このままの状態で次の1スパンに移動させることができる。
また、本発明設備は散水温度を調節するための水を温める装置を装着することもできる。
[コンクリートの初期ひび割れ対策]
In order to achieve the above object, the concrete curing equipment / method of the present invention assembles a support member at a position 100 to 300 mm away from the concrete surface in the tunnel ring direction immediately after removing the concrete casting formwork. Attach the wheel to the leg. Next, the supporting member is provided with watering equipment, the entire surface of the supporting member is covered with a waterproof sheet on the concrete surface side, water spraying is started by a sprinkler system, and water is continuously sprinkled for 24 to 72 hours to prevent concrete cracking. It is. Since this equipment has mobile wheels, it can be moved to the next one span in this state.
The facility of the present invention can also be equipped with a device for warming water for adjusting the watering temperature.
[Measures against initial cracks in concrete]

コンクリートは、水とセメントが水和反応を起こし、この水和熱が発生することにより硬化が始り材齢28日で所要の強度に達する。コンクリートの硬化過程の極く初期の段階において水和熱が発生し、コンクリート表面と中心部で温度差が生じ、この温度差による温度応力とコンクリートそのものが持っているその時の引張応力と比べて、コンクリートの引張応力が小さい時にひび割れが発生する。この極く初期においてコンクリート表面を外気に触れないように、さらに散水することにより乾燥しないようにすればコンクリート表面と中心部の温度差が小さくなりひび割れの発生する確率が小さくなる。
また、コンクリート表面が乾燥状態となった場合には、乾燥によるひび割れが発生する。このひび割れを防止するためコンクリートの表面に散水を実施している。
これらの散水養生は、一般のコンクリート構造物で実施されている。しかしながら、これまでトンネル二次覆工コンクリートやボックスカルバート等の連続体で施工を継続する構造物は、養生として何も実施していない。このためコンクリートにひび割れが発生している。本発明は、「コンクリートは養生を行うこと」この基本に基づき、コンクリートの表面を乾燥させないように極く初期の一定期間、スプリンクラー方式で水を霧状にし、それぞれの個所で回転させながら散水することによりひび割れを防止するものである。
[本発明の設備]
In concrete, water and cement undergo a hydration reaction, and the heat of hydration is generated, so that hardening starts and reaches the required strength at the age of 28 days. The heat of hydration occurs at the very early stage of the hardening process of concrete, resulting in a temperature difference between the concrete surface and the central part. Compared with the temperature stress due to this temperature difference and the tensile stress of the concrete itself, Cracks occur when the tensile stress of concrete is small. In this very early stage, if the concrete surface is not exposed to the outside air, and if the concrete surface is not dried by spraying water, the temperature difference between the concrete surface and the central portion is reduced, and the probability of occurrence of cracks is reduced.
Further, when the concrete surface becomes dry, cracks due to drying occur. Water is sprayed on the concrete surface to prevent this crack.
These watering curings are carried out on general concrete structures. However, the structure which continues construction with continuous bodies, such as a tunnel secondary lining concrete and a box culvert, has not been implemented as a curing until now. For this reason, cracks are generated in the concrete. The present invention is based on this principle, “Concrete is cured”. Sprinkler water is sprayed for a very initial period of time so that the concrete surface is not dried, and water is sprinkled while rotating at each location. This prevents cracking.
[Equipment of the present invention]

本発明の設備は、トンネル坑内の覆工コンクリート表面から100〜300ミリメートルの空間に支保部材でフレームを組む。この間隔が100ミリメートルより狭いと散水用の器具の設置間隔が狭くなり散水器具の材料費取り付け費等が多く必要となり不経済となる。また300ミリメートルより間隔を拡大するとトンネル坑内を作業車等が通過するために必要なコンクリート表面より400ミリメートルの車両限界を守れなくなる。フレームに散水用のスプリンクラーを1〜3m間隔で設ける。フレームのコンクリート面側を防水シートで覆い。(トンネル打設毎のトンネル方向の妻部にも防水シートで覆い)セメントの水和熱によりこのシート中の湿度は90%以上保たれ、さらにこの空間には風も入らないようにする。コンクリート表面に散水し当たった水は、防水シートを伝わり下部に流れ落ちる。本発明の1回当たりの長さは、トンネル覆工コンクリートのフォーマー長さに随時合わせて行うことができ、長さ調整は容易に実施できる。また、曲線部の対応は、トンネルリング方法において1本毎の支保部材位置を曲線に合わせることにより可能となる。
支保部材の下部には、レール式の車輪またはタイヤ式の車輪を装着し、1スパン毎に簡便に移動できる設備を有している。
[散水時間]
The equipment of the present invention forms a frame with a support member in a space of 100 to 300 mm from the lining concrete surface in the tunnel mine. If this interval is narrower than 100 millimeters, the installation interval of the watering device becomes narrow, and a large amount of material costs for the watering device are required, which is uneconomical. Further, if the interval is increased from 300 mm, the vehicle limit of 400 mm cannot be observed from the concrete surface necessary for a work vehicle or the like to pass through the tunnel mine. Sprinklers for watering are provided on the frame at intervals of 1 to 3 m. Cover the concrete side of the frame with a waterproof sheet. (The tread in the tunnel direction at each tunnel placement is also covered with a waterproof sheet.) The humidity in this sheet is maintained at 90% or more by the heat of hydration of the cement, and further, no wind enters this space. The water sprayed on the concrete surface flows down the waterproof sheet and flows down to the bottom. The length per time of the present invention can be adjusted according to the former length of the tunnel lining concrete, and the length can be easily adjusted. In addition, the correspondence of the curved portion is possible by matching the position of each supporting member to the curved line in the tunnel ring method.
A rail-type wheel or a tire-type wheel is attached to the lower part of the support member, and equipment that can be easily moved for each span is provided.
[Watering time]

散水する水は、コンクリートの品質に悪影響を及ぼさない水であれば工業用水、地下水、水道水等いずれも適用できる。また、冬季施工でコンクリート温度が低く、散水用水の温度が低い場合は、この散水温度を10〜20℃の温水にする設備を有することもできる。
表1に実トンネルにおける試験の散水時間とひび割れ長さ合計比率の関係を示す。この試験結果から明らかなように、従来の養生時間が無い場合100%に比べて、散水時間が24時間でひび割れ長さ合計は約20%、48時間で11%、72時間で4%、96時間で4%。別の試験結果図1では、24時間で10%、48時間で3%、72時間と96時間はひび割れが発生していない。
通常のトンネル二次覆工コンクリートの打設サイクルは2日に1回である。このサイクルを踏まえて、二次覆工コンクリート打設後、翌日に型枠を取り外し、直ぐに本発明設備を設置して散水を開始し連続72時間実施するのがよい。
散水量はスプリンクラー方式で回転しながら0.1〜5リットル/分/個所が望ましい。

Figure 2009235894
図1にA試験およびB試験の本発明方法とトンネル二次覆工コンクリートひび割れ長さ合計の関係図を示す。
[発明の効果] As the water to be sprinkled, any industrial water, underground water, tap water or the like can be applied as long as it does not adversely affect the quality of concrete. Moreover, when the concrete temperature is low in winter construction and the temperature of water for spraying is low, it can also have the equipment which makes this watering temperature 10-20 degreeC warm water.
Table 1 shows the relationship between the watering time and the total crack length ratio in the actual tunnel. As is apparent from this test result, compared to 100% when there is no conventional curing time, the watering time is 24 hours and the total crack length is about 20%, 11% at 48 hours, 4% at 72 hours, 96%. 4% in time. Another test result In FIG. 1, no cracks occurred in 24 hours 10%, 48 hours 3%, 72 hours and 96 hours.
The normal tunnel secondary lining concrete placement cycle is once every two days. Based on this cycle, after placing the secondary lining concrete, it is preferable to remove the form the next day, immediately install the equipment of the present invention, start watering, and continue for 72 hours.
The amount of water spray is preferably 0.1 to 5 liters / minute / location while rotating by a sprinkler system.
Figure 2009235894
FIG. 1 shows the relationship between the method of the present invention for the A test and the B test and the total crack length of the tunnel secondary lining concrete.
[The invention's effect]

本発明の移動式で散水設備を有したコンクリート養生方法は、以上説明したようになるから次の効果を得ることができる。
「イ」トンネルやボックスカルバート等の連続体で施工するコンクリートのひび割れを防止することができる
「ロ」移動式でかつトンネル坑内の空間を確保できるため他の工事に影響を与えないで実施できる。
「ハ」組み立てや取り外しが簡単で容易であるため、その時間や費用が少なくなる。
「ニ」部材や器具は別工事にも数回にわたり使用でき、廃棄するものがないため環境に優しい工法になる。
「ホ」従来のひび割れ補修に比べて工期が短く、費用がコストダウンできる。
Since the mobile curing method of the present invention having a watering facility is as described above, the following effects can be obtained.
It can be carried out without affecting other constructions because it is a “b” mobile type that can prevent cracking of concrete that is constructed with a continuous body such as “I” tunnel or box culvert and can secure space in the tunnel mine.
“C” Assembling and removing are simple and easy, so the time and cost are reduced.
“D” members and instruments can be used several times for different construction, and there is nothing to be discarded, making it an environmentally friendly method.
"E" The construction period is shorter than conventional crack repair, and the cost can be reduced.

A試験およびB試験の本発明方法とトンネル二次覆工コンクリートひび割れ長さ合計の関係図Relationship diagram between the method of the present invention of A test and B test and total crack length of tunnel secondary lining concrete 本発明の設備図Facility diagram of the present invention トンネル二次覆工コンクリートの実施例Example of tunnel secondary lining concrete ボックスカルバートコンクリートの実施例Example of box culvert concrete

以下図面を参照しながら本発明の実施の形態について説明する。
[支保部材]
Embodiments of the present invention will be described below with reference to the drawings.
[Supporting members]

トンネルリング方向の支保部材1aは、H鋼材またはアルミ軽金属等でもよくトンネル構造物の形状に合わせて、工場で加工し現場に搬入する。トンネル方向の支保部材1bもH鋼材またはアルミ軽金属等でもよい。コンクリート表面から100〜300ミリメートル離れた位置に設置する。1回当たりのトンネル方向長さは、トンネルリング方向の支保部材に合わせて随時調整できるように鋼棒等で合わせる。
[防水シート]
The supporting member 1a in the tunnel ring direction may be H steel, aluminum light metal, or the like, and is processed at a factory in accordance with the shape of the tunnel structure and is carried to the site. The supporting member 1b in the tunnel direction may also be H steel or aluminum light metal. Install at a position 100 to 300 mm away from the concrete surface. The length in one tunnel direction is adjusted with a steel rod or the like so that it can be adjusted at any time according to the support member in the tunnel ring direction.
[Waterproof sheet]

防水シート2は、散水した水がトンネル坑内に落ちなければよく、この材質は一般に用いられているポリエチレンシート系(トンネルの防水シート)、通常のオレフィン系化学合成シート、ゴム系シート等いずれでもよい。
[散水器具]
The waterproof sheet 2 does not have to drop the sprinkled water into the tunnel tunnel, and this material may be any of commonly used polyethylene sheet (tunnel waterproof sheet), ordinary olefin-based chemical synthetic sheet, rubber sheet, and the like. .
[Watering equipment]

散水器具3について、スプリンクラー方式はコンクリート表面に均一散水できるため最も適している。回転は360度行えるものがよい。散水量はコンクリートの厚さやコンクリートの温度により適切な量が異なるが、コンクリート厚さが300mmでコンクリート温度が10℃と低い場合には0.1〜2リットル/分の範囲、コンクリート厚さが500mmでコンクリート温度が30℃と高い場合には1〜5リットル/分の範囲がよい。
[移動式車輪]
For the watering device 3, the sprinkler system is most suitable because it can uniformly spray water on the concrete surface. It is preferable to rotate 360 degrees. The amount of water spray varies depending on the concrete thickness and concrete temperature, but when the concrete thickness is 300 mm and the concrete temperature is as low as 10 ° C, the range is 0.1 to 2 liters / minute, and the concrete thickness is 500 mm. When the concrete temperature is as high as 30 ° C., the range of 1 to 5 liters / minute is preferable.
[Mobile wheel]

移動するための車輪4は、レールに合わせた鋼材式の丸型でその直径は10〜15cmがよい。タイヤ式の場合はゴム系でその直径はレール式と同様に10〜15cmが適している。
以下図面を参照しながら本発明の実施例について説明する。
[本発明方法によるひび割れ対策効果]
The wheel 4 for moving is a steel material type round shape matched to the rail, and the diameter is preferably 10 to 15 cm. In the case of a tire type, a rubber type and a diameter of 10 to 15 cm is suitable similarly to the rail type.
Embodiments of the present invention will be described below with reference to the drawings.
[Crack countermeasure effect by the method of the present invention]

図1に本発明方法によるひび割れ対策効果の一例を示す。トンネル二次覆工コンクリートにおいて、本発明方法により散水時間を24時間から96時間実施したことによりトンネル二次覆工コンクリートのひび割れは極めて減少していることが明らかになった。その散水時間は24時間〜72時間が適している結果であった。   FIG. 1 shows an example of a crack countermeasure effect by the method of the present invention. In the tunnel secondary lining concrete, it was revealed that the cracking of the tunnel secondary lining concrete was extremely reduced by performing the watering time from 24 hours to 96 hours by the method of the present invention. The watering time was a result suitable for 24 to 72 hours.

以下図面を参照しながら本発明の実施例について説明する。
[トンネル二次覆工コンクリートに設置する例]
Embodiments of the present invention will be described below with reference to the drawings.
[Example of installing on tunnel secondary lining concrete]

トンネル二次覆工コンクリート5の内側に、支保部材1aおよび支保部材1bを組み立て下側に車輪4aを取り付ける。次に支保部材に散水器具3を設置する。この後に防水シート2で覆う。コンクリートを打設し、型枠を取り外した後に直ぐに散水を開始する。散水時間は24時間〜72時間継続する。
[ボックスカルバートに設置する例]
Inside the tunnel secondary lining concrete 5, the support member 1a and the support member 1b are assembled, and the wheel 4a is attached to the lower side. Next, the watering device 3 is installed on the support member. Thereafter, it is covered with a waterproof sheet 2. Watering starts immediately after placing concrete and removing the formwork. The watering time lasts from 24 hours to 72 hours.
[Example of installation in a box culvert]

ボックスカルバートコンクリート6の内側に、支保部材1aおよび支保部材1bを組み立て下側に車輪4bを取り付ける。次に支保部材に散水器具3を設置する。この後に防水シート2で覆う。コンクリートを打設し、型枠を取り外した後直ぐに散水を開始する。散水時間は24時間〜72時間継続する。   Inside the box culvert concrete 6, the support member 1a and the support member 1b are assembled, and the wheel 4b is attached to the lower side. Next, the watering device 3 is installed on the support member. Thereafter, it is covered with a waterproof sheet 2. Watering starts immediately after placing concrete and removing the formwork. The watering time lasts from 24 hours to 72 hours.

1・・・支保部材
2・・・防水シート
3・・・散水器具
4・・・車輪
5・・・トンネル二次覆工コンクリート
6・・・ボックスカルバートコンクリート
DESCRIPTION OF SYMBOLS 1 ... Supporting member 2 ... Waterproof sheet 3 ... Watering device 4 ... Wheel 5 ... Tunnel secondary lining concrete 6 ... Box culvert concrete

Claims (1)

トンネルやボックスカルバート等の連続体で施工するコンクリートにおいて、
ンクリート打設型枠取り外し後、直ぐにそのコンクリート表面から100〜300ミリメートル離れた位置に支保部材を組み立て、その脚部に車輪を取り付け、この支保部材に散水設備を設置し、同支保部材のコンクリート面側全面シートで覆い、コンクリート表面に散水を開始して24時間〜72時間連続散水すること及びこの設備が移動できることを特徴とするコンクリートの養生方法。
In concrete constructed with a continuous body such as a tunnel or box culvert,
Concrete hitting設型frame after removal, immediately assembled supporting coercive member at a distance from 100 to 300 mm from the concrete surface, mounting the wheel on its legs, and installed sprinkler systems in this支保member, the same支保member covering the concrete surface side entire surface sheet, 24 hours to 72 hours of continuous water spray to be the start of the watering concrete surface, and curing method of the concrete, characterized in that the equipment can be moved.
JP2009140723A 2009-06-12 2009-06-12 Concrete curing method and curing equipment Expired - Lifetime JP4866939B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009140723A JP4866939B2 (en) 2009-06-12 2009-06-12 Concrete curing method and curing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009140723A JP4866939B2 (en) 2009-06-12 2009-06-12 Concrete curing method and curing equipment

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2003119078A Division JP2004285803A (en) 2003-03-20 2003-03-20 Curing method of concrete

Publications (2)

Publication Number Publication Date
JP2009235894A true JP2009235894A (en) 2009-10-15
JP4866939B2 JP4866939B2 (en) 2012-02-01

Family

ID=41250167

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009140723A Expired - Lifetime JP4866939B2 (en) 2009-06-12 2009-06-12 Concrete curing method and curing equipment

Country Status (1)

Country Link
JP (1) JP4866939B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014152527A (en) * 2013-02-08 2014-08-25 Mashino:Kk Curing water supply system for concrete curing facility and the like
CN108180023A (en) * 2018-01-17 2018-06-19 浙江交工集团股份有限公司 A kind of automatic track-type two serves as a contrast curing system and maintenance process
WO2018196101A1 (en) * 2017-04-28 2018-11-01 东北大学 Integrated formwork for utility tunnel, and method of using same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109236326B (en) * 2018-09-30 2020-11-13 中铁一局集团有限公司 Intelligent tunnel two-lining spraying maintenance trolley

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073696A (en) * 1998-08-28 2000-03-07 Ohbayashi Corp Method and apparatus for curing lining concrete
JP2001248398A (en) * 2000-03-03 2001-09-14 Ohbayashi Corp Automatic sprinkler system for tunnel lining concrete

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073696A (en) * 1998-08-28 2000-03-07 Ohbayashi Corp Method and apparatus for curing lining concrete
JP2001248398A (en) * 2000-03-03 2001-09-14 Ohbayashi Corp Automatic sprinkler system for tunnel lining concrete

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014152527A (en) * 2013-02-08 2014-08-25 Mashino:Kk Curing water supply system for concrete curing facility and the like
WO2018196101A1 (en) * 2017-04-28 2018-11-01 东北大学 Integrated formwork for utility tunnel, and method of using same
CN108180023A (en) * 2018-01-17 2018-06-19 浙江交工集团股份有限公司 A kind of automatic track-type two serves as a contrast curing system and maintenance process

Also Published As

Publication number Publication date
JP4866939B2 (en) 2012-02-01

Similar Documents

Publication Publication Date Title
JP2008223372A (en) Concrete curing method
JP6758841B2 (en) Deterioration detection method and corrosion sensor
CN105178980B (en) Put in a skylight liner structure restorative procedure for a kind of tunnel
WO2018036445A1 (en) Method for engineering fair-faced concrete protective agent for downstream dam face of roller compacted concrete dam
JP2009235894A (en) Concrete curing method and system
JP5275115B2 (en) Curing device and curing method for concrete continuum
JP2004285803A (en) Curing method of concrete
CN105256839A (en) Method for repairing inspection well and similar structure
JP5778455B2 (en) Repair machine for repairing deteriorated part of inner circumference of steel pipe and repair method using the repair machine
KR101894590B1 (en) A method for repairing the pipe
JP2010189834A (en) Method for repairing concrete structure in acid corrosion environment
JP2004218352A (en) Repairing method for separation/falling place of concrete piece
JP2011106219A (en) Curing device for tunnel lining concrete of widened section
WO2009075647A1 (en) Method of manually restoring an inner surface of a corrugated steel tube
CN110860448A (en) Novel polyurethane coating process for nodular cast iron pipe fitting
CN108301844B (en) Tunnel is with spraying maintenance support
WO2018107753A1 (en) Construction method for erosion and wear resistant protective coating for structure against high velocity water flow
CN111253117A (en) Anti-erosion and anti-corrosion concrete shield segment
KR100394991B1 (en) sprinkler for tunnel
JP6955923B2 (en) Repair method for girders
CN110936490A (en) Reinforced concrete drain pipe and manufacturing process thereof
CN105672687B (en) A kind of substation truss concrete frame reinforcement means
CN215981451U (en) Joint of slurry circulating pump of desulfurization absorption tower
KR102610390B1 (en) Traction type pipe repair apparatus and pipe repair method using the same
KR101489227B1 (en) lining method of tunnels using fiber rods, polymer mortar and adhesion waterproofer

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110815

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110913

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20111020

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111108

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111114

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141118

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4866939

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term