JP2009108482A - Ground stabilization method for extraction of existing pile - Google Patents
Ground stabilization method for extraction of existing pile Download PDFInfo
- Publication number
- JP2009108482A JP2009108482A JP2007278599A JP2007278599A JP2009108482A JP 2009108482 A JP2009108482 A JP 2009108482A JP 2007278599 A JP2007278599 A JP 2007278599A JP 2007278599 A JP2007278599 A JP 2007278599A JP 2009108482 A JP2009108482 A JP 2009108482A
- Authority
- JP
- Japan
- Prior art keywords
- box
- pile
- existing pile
- wedge
- reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
本発明は、既設杭引抜きの際に引抜き機等の重機の安定化を図るための地盤の安定化工法に関する。 The present invention relates to a ground stabilization method for stabilizing a heavy machine such as a drawing machine when pulling an existing pile.
構築物を撤去した際に残る基礎杭は、通常1〜1.5m位地中に杭頭があり、これを掘り当てて杭頭を露現させ、ここに杭引抜き機を進入させて引抜き作業を開始する。しかし、このような作業現場は、杭引抜きのための注水や建物撤去後の瓦礫等できわめて荒れている。そして前記したように杭頭が地中に埋入されているため、引抜き作業に当っては、地面を逆台形状に掘り下げるため、作業中に斜面が崩れ引抜きのために進入する重機は極めて不安定で、転倒等の事故があり常に危険が伴っている。
埋設されている既設杭はその現場にもよるが、大体8m程度の長さと、30〜45cm位の直径のあるコンクリート杭が4〜5本一ヶ所に打設されている。このため作業に当っては、この長さに相当する引抜き用のケーシングと、これを垂直に支えるためのリーダーと、作業をするためのキャタピラ付きの引抜き機(以下重機と称する)が必要であり、一般には既設杭の杭頭の周囲に、杭を掘り出した際の土を埋め戻しながらさらに鉄板を敷いて地盤の安定を図っているが、作業機の重量があるため、掘削穴が崩れ鉄板が傾き、ケーシングによる掘り出し穴が傾き、これを修正するためしばしば作業を中断することとなり、工事の遅延があるばかりか、重機の転倒等の危険が伴う。 Although the existing piles that are buried depend on the site, concrete piles with a length of about 8 m and a diameter of about 30 to 45 cm are placed in one place. For this reason, a drawing casing corresponding to this length, a leader for supporting this vertically, and a drawing machine with a caterpillar for working (hereinafter referred to as a heavy machine) are required. In general, an iron plate is laid around the pile head of the existing pile while backfilling the soil when the pile is dug to stabilize the ground. However, due to the weight of the work equipment, the excavation hole collapses and the iron plate , The digging hole in the casing is tilted, and work is often interrupted to correct this, which not only delays construction work but also involves the risk of falling heavy machinery.
発明者はこのような危険が伴う原因となっている地盤の安定化について鋭意研究を重ねた結果本発明の工法に到達したものであって、本発明は、掘削穴の中央に補強のための四角形の箱体Aを配設し、この両側辺に楔形状のボックスBを配置して一体とすることによって掘削穴を埋め、この箱体A・B上に掘削した穴を跨いで鉄板Fを敷設することによって杭抜き機の進入地盤を形成した。 The inventor has reached the construction method of the present invention as a result of intensive research on the stabilization of the ground that is a cause of such danger, and the present invention is for reinforcement at the center of the excavation hole. A rectangular box A is arranged, and a wedge-shaped box B is arranged on both sides so as to be integrated to fill the excavation hole, and the iron plate F is straddled across the hole excavated on the box A / B. The laying ground of the pile remover was formed by laying.
この形成された進入地盤は図示するように掘削穴(2)の中央に四角形の箱体Aを配置し、この箱体Aの側辺に楔状のボックスBを挿入してB・A・Bと列置することで、掘削穴(2)の斜面は楔状ボックスBの斜面に当接される。図2中の矢印は掘削穴(2)と四角形の箱体A、楔状ブロックBにかかる重力の分布に示すもので、四角形の箱体にかかる
力をS、楔状ブロックBにかかる力Rのように分散されて軽減される。
As shown in the figure, this formed approach ground has a square box A arranged in the center of the excavation hole (2), and a wedge-shaped box B is inserted into the side of the box A so that B, A, B By arranging them, the slope of the excavation hole (2) is brought into contact with the slope of the wedge-shaped box B. The arrows in FIG. 2 indicate the distribution of gravity applied to the excavation hole (2), the square box A, and the wedge-shaped block B. The force applied to the square box B is represented as S and the force R applied to the wedge-shaped block B. Is distributed and reduced.
従って鉄板F上で引抜機D(図示では作図上キャタピラのみを示している)が進入して杭引抜作業をしていても堀削穴(2)の傾斜面は楔状ブロックBの斜面に圧えられているため崩れることなく、鉄板Fも安定して杭抜き機Dの安全が保たれる。 Therefore, even if the drawing machine D (only the caterpillar is shown in the drawing) enters on the iron plate F and the pile drawing work is performed, the inclined surface of the excavation hole (2) is pressed against the inclined surface of the wedge-shaped block B. Therefore, the iron plate F is also stable without being broken, and the safety of the pile cutting machine D is maintained.
本発明は地味で目立たない作業で、しかも常に危険が伴う既設杭の引抜き作業を安全で確実に行うことを目的とするもので、構造的にも四角形の箱体Aと楔状ブロックBを組合せるのみで重機Dからかかる力を分散させて地盤の安定化が図れるもので安全作業の迅速に貢献し、その効果は極めて顕著である。 The present invention is a simple and inconspicuous operation, and is intended to safely and surely carry out the work of pulling existing piles, which is always dangerous, and is a combination of a square box A and a wedge-shaped block B structurally. Only by dispersing the force applied from the heavy equipment D, the ground can be stabilized, contributing to the speed of safety work, and the effect is extremely remarkable.
添付図面により、本考案を実施するための最良の形態を説明すると、図1は、本発明の杭引抜きの際の実施例図であって、Aは杭引抜機(以下重機と称す)であり、キャタピラーにより移動する。この重機Dは既設杭引抜きのためのケーシング及びリーダーを垂直に保つためのリーダーを立設して構成されている。この引抜き工法は、前記特許文献1に示される工法であって、既設杭に対してケーシングを挿入しながらオーガーの回転により作動する排土作用をする回転羽根の回動によって埋設されている杭の周囲を掘りながら羽根を進入させる。この際直立しているリーダーによってケーシングの垂直の進入を保つこととする。したがって、この際重機が傾いた場合には、直立しているケーシングが傾き、これによって杭に沿って進入している掘り出しの羽根が杭に接触して杭の掘出しが不能となる。このため杭引抜き作業を中断するばかりか、重機の転倒による事故も多発している。 The best mode for carrying out the present invention will be described with reference to the accompanying drawings. FIG. 1 is a diagram showing an embodiment of the present invention when a pile is pulled out, and A is a pile puller (hereinafter referred to as a heavy machine). Move by caterpillar. This heavy machine D is constructed by standing a casing for pulling an existing pile and a leader for keeping the leader vertical. This drawing method is a method shown in the above-mentioned Patent Document 1, and is a method of a pile embedded by rotating a rotating blade that performs a soil removing action that operates by rotating an auger while inserting a casing into an existing pile. Let the blades enter while digging around. At this time, the vertical approach of the casing is maintained by an upright leader. Therefore, when the heavy machinery is tilted at this time, the upright casing is tilted, so that the excavation blades entering along the pile come into contact with the pile and the excavation of the pile becomes impossible. For this reason, not only is the pile pullout operation interrupted, but there are many accidents caused by the fall of heavy machinery.
既設杭の杭頭を露現させるため掘削穴(2)は、図示するように逆台形に形成されているため傾斜面は崩れ易く、したがって穴(2)の上面に鉄板Fを渡しても重量のある重機Dが載った場合にその重量によって斜面が崩れる。このため本発明にあっては掘削穴(2)に四角形の補強箱Aとこれを支える楔形のボックスBを配置し、この上に鉄板Fを掘削穴(2)を跨いで敷設することによって重機にかかる重力は掘削穴(2)の真下方向と傾斜面方向とに分散されて鉄板Fは水平を保つことができる。このため重機の傾きを防ぎ、リーダーやケーシングの傾きをなくして安全で作業の進行を早めることが可能となった。 In order to reveal the pile head of the existing pile, the excavation hole (2) is formed in an inverted trapezoidal shape as shown in the figure, so that the inclined surface is easy to collapse, so even if the iron plate F is passed over the upper surface of the hole (2) When a heavy machine D with a load is placed, the slope collapses due to its weight. Therefore, in the present invention, a rectangular reinforcing box A and a wedge-shaped box B that supports the rectangular reinforcing box A are arranged in the excavation hole (2), and an iron plate F is laid over the excavation hole (2) on the heavy machine. The gravity applied to the steel plate F is distributed in the direction directly below the excavation hole (2) and the direction of the inclined surface, so that the iron plate F can be kept horizontal. For this reason, it was possible to prevent heavy machinery from tilting and to eliminate the tilt of the leader and casing, and to accelerate the work progress safely.
図2は既設杭と掘削穴(2)に配置される四角形の補強箱体A及び楔形ボックスBさらにこの上面に渡す鉄板F、さらにこの上に載る重機(キャタピラのみを示す)の関係図を示す。なお、図中の(3)は補強筋を示している。 FIG. 2 shows the relationship between the existing piles, the rectangular reinforcing box A and the wedge-shaped box B arranged in the excavation hole (2), the iron plate F passed to the upper surface, and the heavy machinery (only the caterpillar is shown) placed on this. . In addition, (3) in a figure has shown the reinforcing bar.
図3は作業現場に敷設する鉄板Fと露現している既設杭の杭頭を表わす平面図であって、四角形の補強箱Aの先端には半裁の四角形の補強箱A1が配置されていて、引抜作業を容易とし、これと接続をして方形の補強箱A2を配置する。 FIG. 3 is a plan view showing the steel plate F to be laid at the work site and the exposed pile head of the existing pile, and a rectangular reinforcing box A1 is disposed at the tip of the rectangular reinforcing box A, The pull-out operation is facilitated, and a rectangular reinforcing box A2 is arranged in connection with the pull-out operation.
図4は補強箱体A・Bと既設杭との関係を表わす平面図であって、図4の鉄板Fを除いた部分詳細図であって、図にあっては各箱体にフック掛け用の金具を設けてある。図5は補強箱体A・Bの全体を示す斜視図であって、Xは四角形の補強箱A、Yは楔形ボックスBの斜視図であり、ZはB・A・Bの組合せた掘削穴(2)内の配置図を示している。 FIG. 4 is a plan view showing the relationship between the reinforcing box bodies A and B and the existing piles, and is a partial detail view excluding the iron plate F of FIG. 4. The metal fittings are provided. FIG. 5 is a perspective view showing the entirety of the reinforcing box bodies A and B, where X is a rectangular reinforcing box A, Y is a perspective view of a wedge-shaped box B, and Z is a drilling hole in which B, A, and B are combined. The arrangement | positioning figure in (2) is shown.
添付図面により本発明工法の実施例を説明すると、図3、図4を参照して、埋設されている既設杭は5本のコンクリート杭で、径は30cm、長さは8mであり、杭間はそれぞれ1.5mである。杭頭は地中1.5m位置に露現している。したがって、この杭頭が露現するように溝穴(2)を掘削する。本発明に用いる杭の引抜き工法は前記特許文献1に示す工法を用いる。即ち螺旋羽根によって杭周囲にケーシングを進入させて掘り、杭を露出させて引抜く工法を用いるもので、ケーシングが杭に沿って垂直に進入することが作業効率を上げる条件である。 Examples of the method of the present invention will be described with reference to the accompanying drawings. Referring to FIGS. 3 and 4, the existing piles are five concrete piles, the diameter is 30 cm, and the length is 8 m. Is 1.5 m respectively. The pile head is exposed 1.5m underground. Therefore, the slot (2) is excavated so that the pile head is exposed. The pile drawing method used in the present invention uses the method shown in Patent Document 1. That is, a method is used in which a casing is made to dig around a pile by a spiral blade, and the pile is exposed and pulled out. The condition that the casing enters vertically along the pile is a condition for improving work efficiency.
本発明の地盤安定化工法は、既設杭の杭頭を露現させた掘削穴(2)に四角形の補強箱Aと、この両側に楔形の補強ボックスBを一体として埋設配置してこの上から鉄板Fを掘削穴(2)を跨いで敷設することによって、重機の進入足場とするもので、重機の重量は鉄板Fを介して補強箱Aにより直下方向の力Sと、楔形ボックスBによる傾斜方向の力Rに分散される。特に楔形ボックスBを挿入することにより掘削穴(2)の斜面を圧えるため穴の崩壊を防止する効果があり、鉄板Fの傾きを防いでいる。 According to the ground stabilization method of the present invention, a rectangular reinforcing box A and wedge-shaped reinforcing boxes B are embedded and arranged integrally in an excavation hole (2) exposing a pile head of an existing pile. By laying the iron plate F across the excavation hole (2), the heavy machinery is used as a scaffold for the heavy machinery. The heavy machinery weight is inclined by the reinforcing box A via the iron plate F and the force S in the downward direction and the wedge-shaped box B. Dispersed in the direction force R. In particular, by inserting the wedge-shaped box B, the slope of the excavation hole (2) is pressed, which has the effect of preventing the collapse of the hole, and the tilt of the iron plate F is prevented.
実施例において使用した補強箱A2の大きさは1250m/m×2300m/m×1250m/m、長方形の補強箱A1は1250m/m×2300m/m×1250m/mとし、楔形ボックスBは方形の補強箱Aに見合う高さ及び幅として一体に結合する。図示していないが、この補強箱の内部には補強のための梁や筋かい(3)を設ける。また掘削穴(2)に渡す鉄板Fは、22m/m×1500m/m×6000m/mであり、重機のキャタピラーの幅4mに十分間に合う大きさとする。 The size of the reinforcing box A2 used in the examples is 1250 m / m × 2300 m / m × 1250 m / m, the rectangular reinforcing box A1 is 1250 m / m × 2300 m / m × 1250 m / m, and the wedge-shaped box B is a square reinforcement. Combined as a height and width suitable for box A. Although not shown, a reinforcing beam and brace (3) are provided inside the reinforcing box. Further, the iron plate F passed to the excavation hole (2) is 22 m / m × 1500 m / m × 6000 m / m, and has a size that is sufficiently in time for the width 4 m of the caterpillar of the heavy machinery.
上述のように本発明工法は、既設杭の引抜きという地味な作業であるが、常に危険が伴う作業を安全に迅速に遂行できるため、地域の開発等に大いに期待貢献できる点で、この利用可能性は大きい。 As described above, the method of the present invention is a plain work of pulling out existing piles, but it can always be used safely because it can safely and quickly carry out work that involves danger, so it can contribute greatly to the development of the region. Sex is great.
2…掘削穴
A…四角形の補強箱
B…楔形の補強箱
F…鉄板
D…杭抜き機
2 ... Drilling hole
A ... Rectangular reinforcement box
B ... Wedge shaped reinforcement box
F ... Iron plate
D ... Pile removal machine
Claims (3)
2. The ground stabilization method for pulling an existing pile according to claim 1, wherein the reinforcing boxes A and B are reinforced by providing a brace or the like inside the constituting box.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007278599A JP2009108482A (en) | 2007-10-26 | 2007-10-26 | Ground stabilization method for extraction of existing pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007278599A JP2009108482A (en) | 2007-10-26 | 2007-10-26 | Ground stabilization method for extraction of existing pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2009108482A true JP2009108482A (en) | 2009-05-21 |
Family
ID=40777255
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007278599A Pending JP2009108482A (en) | 2007-10-26 | 2007-10-26 | Ground stabilization method for extraction of existing pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2009108482A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56163318A (en) * | 1980-05-16 | 1981-12-15 | Nippon Concrete Kogyo Kk | Settling guider for foundation pile |
JPH01187225A (en) * | 1987-03-23 | 1989-07-26 | Seiji Tsuji | Centering base frame and casing or steel tubular pile penetrating work therewith |
JPH04185889A (en) * | 1990-11-19 | 1992-07-02 | Mitani Sekisan Co Ltd | Surface layer casing device in case of excavation of hole for stud |
JP2002227190A (en) * | 2001-02-02 | 2002-08-14 | East Japan Railway Co | Surface layer casing pipe for cast-in-place concrete pile and method of executing surface layer casing pipe for cast-in-place concrete pile |
JP2006057258A (en) * | 2004-08-17 | 2006-03-02 | Tone Geo Tech Co Ltd | Removal method for foundation pile |
-
2007
- 2007-10-26 JP JP2007278599A patent/JP2009108482A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56163318A (en) * | 1980-05-16 | 1981-12-15 | Nippon Concrete Kogyo Kk | Settling guider for foundation pile |
JPH01187225A (en) * | 1987-03-23 | 1989-07-26 | Seiji Tsuji | Centering base frame and casing or steel tubular pile penetrating work therewith |
JPH04185889A (en) * | 1990-11-19 | 1992-07-02 | Mitani Sekisan Co Ltd | Surface layer casing device in case of excavation of hole for stud |
JP2002227190A (en) * | 2001-02-02 | 2002-08-14 | East Japan Railway Co | Surface layer casing pipe for cast-in-place concrete pile and method of executing surface layer casing pipe for cast-in-place concrete pile |
JP2006057258A (en) * | 2004-08-17 | 2006-03-02 | Tone Geo Tech Co Ltd | Removal method for foundation pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4820276B2 (en) | Construction method and structure of mountain retaining support | |
CN107938683A (en) | One kind tilts pile pit supporting construction and its construction method | |
JP2008190116A (en) | Liquefaction countermeasure structure of foundation ground of building | |
KR101506880B1 (en) | Shoring apparatus | |
KR100877974B1 (en) | Reverse removing method of underground retaining wall using bottom-up cut and gradual land infilling with struts | |
EP3225746B1 (en) | A bearing structure | |
JP3886261B2 (en) | Slope stabilization method and slope independent pressure receiving device | |
CN108978661B (en) | Construction method for removing cast-in-situ bored pile | |
KR20200013275A (en) | A device that can be separated after entering a PHC pile using a steel pipe | |
JPH0960028A (en) | Method for increasing strength of existing steel pipe pile | |
KR20110052321A (en) | Steel pipe pile for sheet pile wall and construction method using that | |
JP5950598B2 (en) | Sheet pile extraction part filling method | |
JP2007177488A (en) | Permeable tube embedding method and work machine for use therein | |
JP2009108482A (en) | Ground stabilization method for extraction of existing pile | |
JP2868651B2 (en) | Earth retaining method above existing underground structure | |
JP6735138B2 (en) | Construction method of retaining wall structure and retaining wall structure | |
KR100567853B1 (en) | Structure for retaining wall | |
KR101465111B1 (en) | Reinforcing structure for protecting landslide and construction method structure for protecting landslide using the same | |
CN113882431A (en) | Construction method for dismantling end cofferdam | |
JP2001207452A (en) | Method for burying pipe | |
JP2004218378A (en) | Removing method for existing pile | |
JP3766423B2 (en) | Retaining wall construction method | |
JP2000178966A (en) | Structure of diaphragm wall | |
JP2013199772A (en) | Shield drilling method | |
JP2011043047A (en) | Improved/reinforced structure of existing gravity type quay |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090203 |
|
RD04 | Notification of resignation of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7424 Effective date: 20090918 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20100506 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20110913 |