JP2009019360A - Structure and method for jointing bridge pier and footing - Google Patents
Structure and method for jointing bridge pier and footing Download PDFInfo
- Publication number
- JP2009019360A JP2009019360A JP2007181102A JP2007181102A JP2009019360A JP 2009019360 A JP2009019360 A JP 2009019360A JP 2007181102 A JP2007181102 A JP 2007181102A JP 2007181102 A JP2007181102 A JP 2007181102A JP 2009019360 A JP2009019360 A JP 2009019360A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- footing
- joining
- pier
- rebar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は、鋼製橋脚の下端をRC製フーチングに接合する際に用いられる橋脚とフーチングとの接合構造及び方法に関する。 The present invention relates to a joining structure and method of a pier and a footing used when joining a lower end of a steel pier to an RC footing.
鋼製橋脚の下端を基礎に接合するにあたっては、アンカーフレームと呼ばれる鋼製フレームを予め製作した上、これを鉄筋コンクリート基礎であるフーチング内に埋設し、次いで、アンカーフレームから延びるアンカーボルトを利用して鋼製橋脚の下端をアンカーフレームにボルト接合する方法が従来から広く用いられている。 When joining the lower end of a steel pier to the foundation, a steel frame called an anchor frame is manufactured in advance, and then embedded in a footing, which is a reinforced concrete foundation, and then anchor bolts extending from the anchor frame are used. A method of bolting the lower end of a steel pier to an anchor frame has been widely used.
最近では、かかる方法に加えて、地盤内に構築された基礎にソケット鋼管と呼ばれる太径の鋼管を設置し、次いで、該ソケット鋼管内に鋼製橋脚の下端を挿入した後、鋼製橋脚の外面とソケット鋼管の内面との間にコンクリートを充填することによって、鋼製橋脚の下端、ソケット鋼管及び基礎を一体化する方法も知られており、かかる方法によれば、急速施工が可能であることから、交通量の多い場所で短工期に工事を進めることが可能となる。 Recently, in addition to such a method, a steel pipe with a large diameter called a socket steel pipe is installed on the foundation constructed in the ground, and then the lower end of the steel pier is inserted into the socket steel pipe, and then the steel pier A method of integrating the lower end of the steel pier, the socket steel pipe and the foundation by filling concrete between the outer surface and the inner surface of the socket steel pipe is also known, and according to such a method, rapid construction is possible. Therefore, it is possible to proceed with construction in a short construction period in a place with a lot of traffic.
一方、アンカーフレームを用いた接合工法は、本来的にアンカーフレームの製作費が高いため、橋梁の規模が大きくなると、アンカーフレームの大型化や鋼材の高強度化によってその製作費用がますます高くなるとともに、ソケット鋼管を用いたいわゆる二重管工法も、鋼管を二重に用いることから必然的に施工費用が高くなる。 On the other hand, the joining method using an anchor frame is inherently expensive to produce an anchor frame. Therefore, when the size of a bridge is increased, the production cost is increased due to the increase in the size of the anchor frame and the strengthening of steel. In addition, the so-called double pipe construction method using the socket steel pipe inevitably increases the construction cost because the steel pipe is used twice.
このような状況下、コスト低減可能な接合工法が研究開発されており、例えば橋脚を構成する鋼管の内面にリブを設けるとともに該リブと対向する位置に鉄筋を配筋し、かかる状態で鋼管内にコンクリートを打設する工法(特許文献1,2)が開発されている。
Under such circumstances, a joint construction method capable of reducing costs has been researched and developed. For example, a rib is provided on the inner surface of a steel pipe constituting a pier and a reinforcing bar is arranged at a position facing the rib, and in this state, A construction method (
かかる従来工法によれば、鋼管内に充填されたコンクリートと該コンクリートに埋設定着された鉄筋が鋼管内に鉄筋コンクリート体を形成することとなり、鋼管から受ける引抜き荷重や橋脚頭部の水平変位による強制回転変形に抵抗する。 According to such a conventional construction method, the concrete filled in the steel pipe and the reinforcing bars embedded in the concrete form a reinforced concrete body in the steel pipe, and the forced rotation due to the pulling load received from the steel pipe and the horizontal displacement of the pier head Resist deformation.
したがって、アンカーフレームを使用せずとも鋼製橋脚をフーチングに強固に接合することが可能となるのみならず、鋼管によるコンクリートの拘束効果も期待することができる。また、コンクリート打設の際の型枠設置や脱型作業が必要なRC橋脚よりも有利な工法となる。 Therefore, not only the anchor frame but also the steel pier can be firmly joined to the footing, and a concrete restraining effect by the steel pipe can be expected. In addition, the construction method is more advantageous than RC piers that require formwork and demolding work when placing concrete.
しかしながら、鉄筋の周囲に所定のコンクリート被り厚を確保しなければならない関係上、鋼管内面のリブと対向するように鉄筋を配置するにあたっては、鉄筋の配筋位置を、リブの突設分だけ、鋼管内側に後退させねばならない。 However, in order to arrange the reinforcing bars so as to face the ribs on the inner surface of the steel pipe on the relationship that a predetermined concrete covering thickness must be secured around the reinforcing bars, the reinforcing bars are arranged by the protruding portion of the ribs. It must be retracted inside the steel pipe.
ここで、リブと鉄筋との荷重伝達は、リブと鉄筋との間に形成される圧縮ストラットやコンクリート自体のせん断抵抗を介して行われることになるが、リブの支圧面積が小さいために圧縮ストラットを介した荷重伝達は多くを期待することができず、コンクリートのせん断抵抗についてもコンクリートの物性上、荷重伝達機能としてはやはり限度がある。 Here, the load transmission between the ribs and the reinforcing bars is performed via the compression struts formed between the ribs and the reinforcing bars, and the shear resistance of the concrete itself. Load transmission via struts cannot be expected to be much, and the concrete shear resistance is still limited due to the physical properties of concrete.
そのため、鉄筋コンクリート体の引抜き強度や回転変形に対する曲げ強度を十分に確保することができないという問題を生じていた。 For this reason, there has been a problem that the pullout strength of the reinforced concrete body and the bending strength against rotational deformation cannot be sufficiently ensured.
本発明は、上述した事情を考慮してなされたもので、合理的なコストでかつ引抜き強度や回転変形に対する曲げ強度を十分高めることが可能な橋脚とフーチングとの接合構造及び方法を提供することを目的とする。 The present invention has been made in view of the above-described circumstances, and provides a structure and method for joining a pier and a footing that can sufficiently increase the pulling strength and the bending strength against rotational deformation at a reasonable cost. With the goal.
上記目的を達成するため、本発明に係る橋脚とフーチングとの接合構造は請求項1に記載したように、鉄筋コンクリートで形成されたフーチングと、該フーチングの上面との間に所定の隙間が形成されるように鉛直姿勢にて前記フーチングの上方に配置された鋼管と、前記フーチングに一端が埋設定着された鋼管接合用鉄筋及び前記鋼管内に充填され前記鋼管接合用鉄筋の他端が埋設定着されるコンクリートで形成された鉄筋コンクリート体と、該鉄筋コンクリート体に埋設されるように前記鋼管内面に取り付けられた支圧部材とから構成するとともに、前記鋼管接合用鉄筋を取り囲むように前記支圧部材を形成することにより、前記鋼管接合用鉄筋の材軸を中心としたほぼ円錐状の圧縮ストラットが形成されるようにしたものである。
In order to achieve the above object, the joining structure of the pier and the footing according to the present invention has a predetermined gap formed between the footing formed of reinforced concrete and the upper surface of the footing as described in
また、本発明に係る橋脚とフーチングとの接合構造は、前記支圧部材を、前記鋼管の内面から前記鋼管の中心に向かう方向に沿って所定幅を有し幅中心近傍に挿通孔が形成された環状、矩形枠状又は多角形枠状の支圧板で構成するとともに、前記挿通孔に前記鋼管接合用鉄筋を挿通したものである。 Further, in the joining structure between the pier and the footing according to the present invention, the supporting member has a predetermined width along the direction from the inner surface of the steel pipe toward the center of the steel pipe, and an insertion hole is formed in the vicinity of the width center. In addition, the steel pipe jointing reinforcing bar is inserted into the insertion hole.
また、本発明に係る橋脚とフーチングとの接合構造は、前記支圧部材を、前記鋼管の内面から前記鋼管の中心に向かう方向に沿って所定幅を有し鋼管中心側縁部に切り欠きが形成された環状、矩形枠状又は多角形枠状の支圧板で構成するとともに、前記切り欠きに前記鋼管接合用鉄筋を配置したものである。 Further, in the joining structure of the bridge pier and the footing according to the present invention, the bearing member has a predetermined width along a direction from the inner surface of the steel pipe toward the center of the steel pipe, and a notch is formed in the steel pipe center side edge. In addition to the formed pressure bearing plate having an annular, rectangular or polygonal frame shape, the steel pipe joining rebar is disposed in the notch.
また、本発明に係る橋脚とフーチングとの接合方法は請求項4に記載したように、鋼管で構成された橋脚を鉄筋コンクリートで形成されたフーチングに接合する橋脚とフーチングとの接合方法において、
Further, as described in
鋼管接合用鉄筋の一端が前記フーチングに埋設定着されるように該フーチングを形成し、前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるようにかつ前記鋼管接合用鉄筋の他端が前記鋼管内に配置されるように該鋼管を鉛直姿勢にて前記フーチングの上方に位置決めし、前記隙間を所定の型枠材で塞ぎ、前記鋼管接合用鉄筋の他端が埋設定着されるように前記鋼管内にコンクリートを充填して前記鋼管内に鉄筋コンクリート体を形成する各工程からなり、前記鉄筋コンクリート体に埋設されるように前記鋼管内面に支圧部材を取り付けるとともに、前記鋼管接合用鉄筋を取り囲むように前記支圧部材を形成することにより、前記鋼管接合用鉄筋の材軸を中心としたほぼ円錐状の圧縮ストラットが形成されるようにしたものである。 The steel pipe joining rebar is formed so that one end of the steel pipe joining rebar is embedded in the footing, and a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing. The steel pipe is positioned above the footing in a vertical posture so that the other end of the steel pipe is disposed in the steel pipe, the gap is closed with a predetermined formwork material, and the other end of the steel pipe joining rebar is embedded. The steel pipe is filled with concrete to form a reinforced concrete body in the steel pipe, and a supporting member is attached to the inner surface of the steel pipe so as to be embedded in the reinforced concrete body, and the steel pipe joining By forming the bearing member so as to surround the reinforcing steel bar, a substantially conical compression strut centering on the material axis of the steel pipe joining reinforcing bar is formed. Than is.
また、本発明に係る橋脚とフーチングとの接合方法は、前記支圧部材を、前記鋼管の内面から前記鋼管の中心に向かう方向に沿って所定幅を有し幅中心近傍に挿通孔が形成された環状、矩形枠状又は多角形枠状の支圧板で構成するとともに、前記挿通孔に前記鋼管接合用鉄筋を挿通したものである。 Further, in the joining method of the pier and the footing according to the present invention, the supporting member has a predetermined width along a direction from the inner surface of the steel pipe toward the center of the steel pipe, and an insertion hole is formed in the vicinity of the width center. In addition, the steel pipe jointing reinforcing bar is inserted into the insertion hole.
また、本発明に係る橋脚とフーチングとの接合方法は、前記支圧部材を、前記鋼管の内面から前記鋼管の中心に向かう方向に沿って所定幅を有し鋼管中心側縁部に切り欠きが形成された環状、矩形枠状又は多角形枠状の支圧板で構成するとともに、前記切り欠きに前記鋼管接合用鉄筋を配置したものである。 Further, in the method for joining the pier and the footing according to the present invention, the bearing member has a predetermined width along a direction from the inner surface of the steel pipe toward the center of the steel pipe, and a notch is formed in the steel pipe center side edge. In addition to the formed pressure bearing plate having an annular, rectangular or polygonal frame shape, the steel pipe joining rebar is disposed in the notch.
また、本発明に係る橋脚とフーチングとの接合方法は、前記鋼管の鉛直荷重を仮受けできるように前記型枠材を構成するとともに、前記鋼管内に充填したコンクリートが硬化した後、前記型枠材を取り外すものである。 The method for joining the pier and the footing according to the present invention is to form the mold material so that the vertical load of the steel pipe can be temporarily received, and after the concrete filled in the steel pipe is hardened, The material is removed.
本出願人は、上述した問題点をいかに解決すべきか、研究開発を積み重ねた結果、鋼管内に形成された鉄筋コンクリート体に埋設されるように、鋼管内面に支圧部材を取り付けるとともに、鋼管接合用鉄筋を取り囲むように支圧部材を形成することにより、鋼管接合用鉄筋の材軸を中心としたほぼ円錐状の圧縮ストラットが形成されるようにしてなる新規な発明をなすに至ったものである。 As a result of accumulating research and development, the present applicant attached a support member to the inner surface of the steel pipe so as to be embedded in the reinforced concrete body formed in the steel pipe, and for steel pipe joining. By forming the bearing member so as to surround the reinforcing bar, a novel invention has been made in which a substantially conical compression strut centering on the material axis of the reinforcing rod for steel pipe joining is formed. .
このようにすれば、ほぼ円錐状に形成された圧縮ストラットの鉛直成分合力は従来に比べてはるかに大きくなり、橋脚上方から引抜き荷重が鋼管に作用したときや、橋脚頂部に作用する水平力によって鋼管から強制回転変形を受けたとき、鉄筋コンクリート体の引張断面において、より大きな支圧反力で引抜き荷重や強制回転変形に抵抗することが可能となる。 In this way, the vertical component resultant force of the compression strut formed in a substantially conical shape becomes much larger than before, and when a pulling load acts on the steel pipe from above the pier, or due to a horizontal force acting on the pier top When subjected to forced rotational deformation from a steel pipe, it becomes possible to resist pull-out load and forced rotational deformation with a larger bearing pressure reaction force in the tensile cross section of the reinforced concrete body.
一方、ほぼ円錐状に形成された圧縮ストラットの水平成分合力は概ね相殺されるため、コンクリートが横方向に膨張しようとする力は従来に比べて大幅に小さくなり、それゆえ、鋼管の拘束力に依存しない安定した鉄筋の付着が可能となる。 On the other hand, since the resultant horizontal component force of the compression strut formed in a substantially conical shape is almost canceled out, the force that the concrete tends to expand in the lateral direction is significantly smaller than in the conventional case, and therefore, the restraining force of the steel pipe is reduced. Reliable adhesion of reinforcing bars is possible.
ここで、鋼管内面にリブを突設し該リブからコンクリート被り厚だけ鉄筋を離間配置した従来技術においては、鉄筋とリブとの間に形成される圧縮ストラットは、リブに向かって鉄筋から斜め下方に延びるため、鋼管による拘束作用の大きさや鋼管の形状にもよるが、圧縮ストラットの水平成分応力によってコンクリートが横方向に膨張し、リブの付着強度が低下するので、好ましくない状況となる。 Here, in the prior art in which ribs are provided on the inner surface of the steel pipe and the reinforcing bars are spaced apart from the ribs by the concrete covering thickness, the compression struts formed between the reinforcing bars and the ribs are obliquely downward from the reinforcing bars toward the ribs. Therefore, although depending on the size of the restraint action by the steel pipe and the shape of the steel pipe, the concrete expands in the lateral direction due to the horizontal component stress of the compression strut and the bond strength of the ribs is lowered, which is not preferable.
特に、充填コンクリートを拘束する力が比較的大きな円形鋼管よりも、拘束力が小さい角形鋼管において、リブ付着強度の低下が問題となる。 In particular, in a square steel pipe having a smaller restraining force than a circular steel pipe having a relatively large restraining force for filling concrete, a decrease in rib adhesion strength becomes a problem.
しかしながら、本発明においては、上述したように鋼管の拘束力に依存することなく、引抜き荷重や強制回転変形に抵抗することが可能となるため、どのような断面形状の鋼管にも適用可能であり、特にリブ付着強度が低下しがちであった角形鋼管に本発明を適用した場合、その作用効果は顕著である。 However, in the present invention, as described above, it is possible to resist the drawing load and forced rotation deformation without depending on the restraining force of the steel pipe, so that it can be applied to a steel pipe having any cross-sectional shape. In particular, when the present invention is applied to a rectangular steel pipe in which the rib adhesion strength tends to decrease, the effect is remarkable.
このように本発明が対象とする鋼管は、断面形状を任意とすることが可能であり、例えば円形、角形、多角形等の断面形状が考えられる。また、例えば山間部に橋梁を建設する場合、橋脚が高くなることがあり、その際には、鋼管を溶接等で継ぎ足していくことになる。 As described above, the steel pipe targeted by the present invention can have any cross-sectional shape, and for example, a cross-sectional shape such as a circle, a square, or a polygon can be considered. For example, when a bridge is constructed in a mountainous area, the pier may become high, and in that case, the steel pipe is added by welding or the like.
橋脚が複数の鋼管で構成される場合、本発明の鋼管を単一の鋼管で構成することができるほか、複数の鋼管で構成することも可能であり、かかる場合には、支圧部材を最下段の鋼管に設けるほか、二段目、三段目といった鋼管にも支圧部材を設けることができる。 When the pier is composed of a plurality of steel pipes, the steel pipe of the present invention can be composed of a single steel pipe, or can be composed of a plurality of steel pipes. In addition to the lower steel pipe, a supporting member can be provided on the second and third steel pipes.
なお、橋脚を構成する鋼管を鋼殻と称することも多いが、本発明では、便宜上、鋼殻も含める概念として鋼管と呼ぶこととする。 In addition, although the steel pipe which comprises a pier is often called a steel shell, in this invention, it shall call a steel pipe as a concept also including a steel shell for convenience.
フーチングは、鉄筋コンクリートで形成されたものであって、一般的には杭を伴う場合が多いが、本発明においては、フーチングだけで基礎構造が構成されるのか、杭とその頭部に接合されたフーチングとで基礎構造が構成されるのかは問わない。 The footing is made of reinforced concrete and generally accompanied by a pile, but in the present invention, the foundation structure is constituted only by the footing or it is joined to the pile and its head. It does not matter whether the foundation structure is composed of footing.
鋼管接合用鉄筋は、一端がフーチングに埋設定着され、他端が鋼管内に充填形成されたコンクリート内に埋設定着されるものであり、例えば異形鉄筋で構成することができる。 The steel pipe joining rebar is one in which one end is embedded in the footing and the other end is embedded in the concrete filled in the steel pipe, and can be composed of a deformed reinforcing bar, for example.
支圧部材は、該支圧部材に生じる支圧反力と鋼管接合用鉄筋の周囲に生じる引張付着応力とによって、鋼管接合用鉄筋の材軸を中心としたほぼ円錐状の領域に圧縮ストラットが生じるように構成する限り、その構成は任意である。 The bearing member has a compression strut in a substantially conical region around the material axis of the steel pipe joining rebar due to the bearing reaction force generated in the bearing member and the tensile adhesion stress generated around the steel pipe joining rebar. As long as it is configured to occur, the configuration is arbitrary.
ここで、圧縮ストラットとは一般的には、所定の外力が鉄筋コンクリート部材に作用したときに該鉄筋コンクリート部材内に形成される束状に連なった圧縮応力領域を意味するものであって、例えば鉄筋コンクリート梁に発生するアーチリブが該当するが、本明細書においては特に、鋼管内面に取り付けられた支圧部材と鉄筋との間に束状に連なって形成される圧縮応力領域を指すものとする。 Here, the compression strut generally means a bundle of compressive stress regions formed in the reinforced concrete member when a predetermined external force is applied to the reinforced concrete member. In the present specification, it particularly refers to a compressive stress region formed in a bundle between the bearing member attached to the inner surface of the steel pipe and the reinforcing bar.
圧縮ストラットが鋼管接合用鉄筋の材軸を中心としたほぼ円錐状に形成されるためには、支圧部材が鋼管接合用鉄筋を取り囲むように配置されることが必要となるが、本発明でいうところの円錐状とは、底面がほぼ円形の円錐だけを意味するものではなく、開き角度が180度程度以上の扇形底面を有する円錐形状も含むものとする。かかる場合であっても、従来より十分大きな支圧面積を確保することが可能である。同様な意味で、鋼管接合用鉄筋を取り囲むように支圧部材を構成するとは、完全な包囲を意味するものではなく、概ね半円錐以上の圧縮ストラットが形成される程度の支圧面積が確保される包囲、すなわち鋼管接合用鉄筋を180度程度以上包囲できれば足りる。 In order for the compression strut to be formed in a substantially conical shape centered on the material axis of the steel pipe joining rebar, it is necessary that the bearing member be disposed so as to surround the steel pipe joining rebar. The term “conical shape” does not mean only a cone having a substantially circular bottom surface, but also includes a cone shape having a fan-shaped bottom surface with an opening angle of about 180 degrees or more. Even in such a case, it is possible to secure a sufficiently large bearing area as compared with the conventional case. In the same sense, the structure of the bearing member so as to surround the steel pipe joining rebar does not mean a complete envelopment, but a bearing area to the extent that a compression strut having a half cone or more is formed is secured. It is sufficient to surround the steel pipe joining rebars by about 180 degrees or more.
支圧部材の具体例としては例えば、鋼管の内面から鋼管の中心に向かう方向に沿って所定幅を有し幅中心近傍に挿通孔が形成された環状、矩形枠状又は多角形枠状の支圧板で支圧部材を構成するとともに、該挿通孔に鋼管接合用鉄筋を挿通する構成が考えられる。 Specific examples of the supporting member include, for example, an annular, rectangular frame, or polygonal frame-shaped support having a predetermined width along the direction from the inner surface of the steel pipe toward the center of the steel pipe and an insertion hole formed in the vicinity of the width center. A structure in which the supporting member is configured by the pressure plate and a steel pipe joining rebar is inserted through the insertion hole is conceivable.
また、鋼管の内面から鋼管の中心に向かう方向に沿って所定幅を有し鋼管中心側縁部に切り欠きが形成された環状、矩形枠状又は多角形枠状の支圧板で支圧部材を構成するとともに、該切り欠きに鋼管接合用鉄筋を配置する構成が考えられる。 Further, the bearing member is supported by an annular, rectangular frame-shaped or polygonal frame-shaped bearing plate having a predetermined width along the direction from the inner surface of the steel tube toward the center of the steel tube and having a notch formed at the edge on the steel tube center side. A configuration in which a steel pipe joining rebar is arranged in the notch is conceivable.
本発明に係る橋脚とフーチングとの接合構造を構築するには、まず、鋼管接合用鉄筋の一端がフーチングに埋設定着されるように該フーチングを形成し、次いで、鋼管の下端とフーチングの上面との間に所定の隙間が形成されるようにかつ鋼管接合用鉄筋の他端が鋼管内に配置されるように該鋼管を鉛直姿勢にてフーチングの上方に位置決めし、次いで、隙間を所定の型枠材で塞ぎ、しかる後、鋼管接合用鉄筋の他端が埋設定着されるように、鋼管内にコンクリートを充填すればよい。 In order to construct a joint structure between a pier and a footing according to the present invention, first, the footing is formed so that one end of a steel pipe joining rebar is embedded in the footing, and then the lower end of the steel pipe and the upper surface of the footing The steel pipe is positioned above the footing in a vertical posture so that a predetermined gap is formed between the steel pipe and the other end of the steel pipe joining rebar is disposed in the steel pipe. The steel pipe may be filled with concrete so that the other end of the steel pipe joining rebar is buried and sealed with the frame material.
ここで、鋼管の鉛直荷重を仮受けできるように型枠材を構成すれば、コンクリート充填打設の前における鋼管の仮受けを容易に行うことが可能となる。なお、かかる場合には、鋼管内に充填したコンクリートが硬化した後、型枠材を取り外す。 Here, if the formwork material is configured so that the vertical load of the steel pipe can be temporarily received, it is possible to easily perform the temporary reception of the steel pipe before the concrete filling and placing. In such a case, the mold material is removed after the concrete filled in the steel pipe is cured.
以下、本発明に係る橋脚とフーチングとの接合構造及び方法の実施の形態について、添付図面を参照して説明する。なお、従来技術と実質的に同一の部品等については同一の符号を付してその説明を省略する。 DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of a structure and a method for joining a pier and footing according to the present invention will be described below with reference to the accompanying drawings. Note that components that are substantially the same as those of the prior art are assigned the same reference numerals, and descriptions thereof are omitted.
図1は、本実施形態に係る橋脚とフーチングとの接合構造を示した図である。同図でわかるように、本実施形態に係る橋脚とフーチングとの接合構造1は、鋼管2で構成された橋脚3を鉄筋コンクリートで形成されたフーチング4に接合してなる。
FIG. 1 is a view showing a joint structure between a pier and a footing according to the present embodiment. As can be seen from the figure, the pier and footing
鋼管2の下端とフーチング4の上面との間には、隙間hが形成されるように鋼管2を鉛直姿勢にてフーチング4の上方に配置してある。
Between the lower end of the
フーチング4には、鋼管接合用鉄筋としての異形鉄筋6の一端を埋設定着してあり、該異形鉄筋の他端は、鋼管2内に充填されたコンクリート7に埋設定着してある。
One end of a
異形鉄筋6は、鋼管2内に充填されたコンクリート7とともに鉄筋コンクリート体8を形成しており、該鉄筋コンクリート体8は後述するように、橋脚3から引抜き力が作用したとき、該引抜き力に抵抗してフーチング4に伝達するとともに、橋脚3の頭部に水平力が作用したとき、該水平力による鋼管2の回転変形に対して曲げ抵抗し、該水平力をフーチング4に伝達する役目を果たす。
The deformed reinforcing
ここで、鋼管2の内面には、鉄筋コンクリート体8に埋設されるように支圧部材としての支圧板21を取り付けてある。
図2は、支圧板21を全体斜視図及び平面図で示したものである。
同図でわかるように支圧板21は、中央に矩形開口23が形成された矩形枠状をなし、鋼管2の内面から鋼管2の中心に向かう方向に沿って幅Wを有するとともに、幅中心近傍に複数の挿通孔22を形成してあり、該挿通孔に異形鉄筋6をそれぞれ挿通することで、該異形鉄筋の周囲を支圧板21を構成する板材で取り囲むようになっている。
Here, a bearing
FIG. 2 shows the bearing
As can be seen from the figure, the bearing
支圧板21は、鋼管2に作用する引抜き力の大きさや、鋼管2から受ける強制回転変形の大きさによって、高さ方向の設置ピッチや設置段数を適宜設定すればよい。
The bearing
挿通孔22は、異形鉄筋6が挿通しやすいよう、該異形鉄筋の外径よりも内径が大きくなるように形成するが、施工上問題のない範囲で、内径を異形鉄筋6の外径に近づけるのが支圧面積を大きくする上で望ましい。
The
異形鉄筋6は、それぞれ直棒状に構成してあり、図1(b)に示すように鋼管2が角形鋼管であれば所定ピッチで矩形状に配置すればよいし、円形鋼管であれば円形に配置すればよい。
The deformed reinforcing
本実施形態に係る橋脚とフーチングとの接合構造1を構築するには、まず図3に示すように、杭11を地盤(図示せず)に打ち込んだ後、該杭の頭部にフーチング4を形成するが、かかる基礎工事の際には、異形鉄筋6の一端がフーチング4内に埋設定着されるように該フーチングを形成する。
In order to construct the
異形鉄筋6は、後工程で立設する鋼管2の内面に取り付けられた支圧板21の挿通孔22に挿通できるよう、フーチング4内に適宜埋設すればよい。
The deformed reinforcing
次に図4に示すように、型枠材12をフーチング4の上面に載置する。型枠材12は、L状断面を有する矩形フレームで構成してあり、内周側に形成された肩部13に鋼管2の下端を載せることにより、該鋼管の下端とフーチング4の上面との間の隙間hを塞ぐとともに、鋼管2の荷重を仮受けすることができるようになっている。
Next, as shown in FIG. 4, the
型枠材12は、次工程で立設する鋼管2の内面に取り付けられた支圧板21の挿通孔22に異形鉄筋6が挿通できるよう、フーチング4の上面に位置決めする。
The
次に、支圧板21の挿通孔22に異形鉄筋6を挿通しながら、型枠材12の肩部13に鋼管2の下端を載せるようにして、鋼管2をフーチング4の上方に鉛直姿勢で吊り込み、鋼管2を型枠材12で仮受けする。
Next, the
次に、異形鉄筋6が埋設される高さまで、鋼管2内にコンクリート7を打設充填する。
Next,
打設したコンクリート7が硬化したならば、最後に型枠材12を撤去する。
When the
このように構築された橋脚とフーチングとの接合構造1においては、図5に示すように、橋脚3上方から圧縮荷重が作用するが、かかる圧縮荷重は、鋼管2の内面に取り付けられた支圧板21を介して鉄筋コンクリート体8に伝達し、さらにフーチング4へと伝達して圧縮荷重が支持される。
In the pier and footing
また、橋脚3の頭部に水平力が右方向に作用する場合を想定すると、鋼管2は、該水平力によって時計回りに回転しようとする。
Further, assuming that a horizontal force acts on the head of the pier 3 in the right direction, the
そのため、鉄筋コンクリート体8の側面には図6(a)に示す分布形状の水平力Pが鋼管2から作用するとともに、左側に位置する異形鉄筋6からの引張力Tが左側底面に、右側に位置する異形鉄筋6からの圧縮力C1とフーチング4の右上面からの圧縮力C2が右側底面に、フーチング4からの水平反力Hが底面にそれぞれ作用するが、鉄筋コンクリート体8は、異形鉄筋6及び充填コンクリート7からなるRC部材としてこれらの力に曲げせん断で抵抗する。
Therefore, the horizontal force P having the distributed shape shown in FIG. 6 (a) acts on the side surface of the reinforced
ここで、鉄筋コンクリート体8の左側引張断面では同図(b)に示すように、異形鉄筋6に引張付着応力が下向きに作用するが、異形鉄筋6を支圧板21の挿通孔22に挿通してあるため、支圧板21には、上向きの支圧反力が異形鉄筋6を取り囲むように発生し、かくして異形鉄筋6と支圧板21との間には、異形鉄筋6の材軸を中心としたほぼ円錐状の圧縮ストラット23が形成される。
Here, in the left tensile cross section of the reinforced
そして、この圧縮ストラット23によって、鋼管2に作用する引張力が支持されることとなり、かくして鉄筋コンクリート体8の曲げ強度が高くなり、鋼管2から受ける大きな強制回転変形にも抵抗することができる。
The compressive struts 23 support the tensile force acting on the
鋼管2に大きな引抜き力が作用して鉄筋コンクリート体8の全断面が引張となる場合には、上述した圧縮ストラット23が鋼管2の内面に設けられた支圧板21の全周でかつ全段で生じ、これらが鋼管2に作用する大きな引抜き力に抵抗し、最終的にはフーチング4に伝達される。
When a large pulling force acts on the
以上説明したように、本実施形態に係る橋脚とフーチングとの接合構造1によれば、鋼管2内に形成された鉄筋コンクリート体8に埋設されるように、支圧板21を鋼管2の内面に取り付けるとともに、該支圧板に形成された挿通孔22に異形鉄筋6を挿通するようにしたので、橋脚3の頭部に作用する水平力によって鋼管2に強制回転変形を生じたとき、あるいは鋼管2に大きな引抜き力が作用したとき、引張断面に配置されている異形鉄筋6と支圧板21との間には、異形鉄筋6の材軸を中心とするほぼ円錐状の圧縮ストラット23が形成される。
As described above, according to the pier and footing
すなわち、支圧板21は、異形鉄筋6を取り囲むように配置されているため、異形鉄筋6の引張付着応力とバランスする支圧反力が支圧板21の広い面積範囲で発生するとともに、これらの間には、大きなボリュームを有する圧縮ストラット23が形成される。
That is, since the bearing
そのため、フーチング4との接合箇所における引張強度や曲げ強度を格段に向上させることが可能となる。
Therefore, the tensile strength and bending strength at the joint with the
また、円錐状に形成された圧縮ストラット23の水平成分合力は概ね相殺されるため、充填コンクリート7が横方向に膨張しようとする力は従来に比べて大幅に小さくなり、鋼管2による拘束作用と相俟って、コンクリート7のひび割れを抑制することも可能となる。
Further, since the resultant horizontal component force of the compression struts 23 formed in a conical shape is substantially canceled out, the force that the filled
本実施形態では特に言及しなかったが、橋脚3が長い場合、鋼管2の上に該鋼管と同様の鋼管を溶接等で順次継ぎ足していくことが可能である。
Although not particularly mentioned in the present embodiment, when the pier 3 is long, a steel pipe similar to the steel pipe can be successively added onto the
また、本実施形態では、型枠材12に鋼管2の自重を仮受けする機能を持たせたが、鋼管2を別の公知手段で仮受けし、型枠材12は、型枠の機能だけを持たせるようにしてもかまわない。この場合、コンクリート硬化後に型枠材12を撤去するかどうかは任意である。
Further, in this embodiment, the
また、本実施形態では、鋼管2が角形鋼管である関係上、矩形枠状の支圧板21で支圧部材を構成したが、本発明に係る支圧部材はかかる形状に限定されるものではなく、鋼管が円形鋼管であれば環状の支圧板とし、多角形鋼管であれば多角形枠状の支圧板とすることが可能である。
Further, in the present embodiment, because the
また、本実施形態では、異形鉄筋6を挿通する挿通孔22が形成された支圧板21で支圧部材を構成したが、本発明に係る支圧部材はかかる構成に限定されるものではなく、鋼管接合用鉄筋との間でほぼ円錐状の圧縮ストラットが形成され得る支圧部材であれば、いかなる支圧部材でもかまわない。
Moreover, in this embodiment, although the supporting member was comprised with the bearing
例えば、図7(a)に示すように、鋼管2の内面からその中心に向かう方向に沿って幅Wを有し、鋼管中心側縁部に切り欠き71が形成された矩形枠状の支圧板72で本発明の支圧部材を構成することが可能である。
For example, as shown in FIG. 7 (a), a rectangular frame-shaped bearing plate having a width W along the direction from the inner surface of the
かかる変形例においては、切り欠き71に異形鉄筋6を嵌め込む関係上、鋼管中心側縁部よりも内側では、異形鉄筋6の引張付着応力とバランスする支圧部分がなく、そのため、圧縮ストラット23aは、同図(b)に示すように半円錐形となる。
In such a modified example, because the deformed reinforcing
しかし、従来よりも支圧面積が大幅に増大していることに変わりはなく、上述した作用効果は本変形例においても同様に当てはまる。加えて、本変形例によれば、異形鉄筋6を側方から嵌め込むことができるので、施工時の作業性が高いという作用効果を奏する。なお、かかる変形例における接合方法については、上述した実施形態とほぼ同様であるので、ここではその詳細な説明を省略する。
However, the bearing area is greatly increased as compared with the prior art, and the above-described effects are similarly applied to this modification. In addition, according to the present modification, the deformed reinforcing
1 橋脚とフーチングとの接合構造
2 鋼管
3 橋脚
4 フーチング
6 異形鉄筋(鋼管接合用鉄筋)
7 充填コンクリート
8 鉄筋コンクリート体
12 型枠材
21,72 支圧板(支圧部材)
22 挿通孔
23,23a 圧縮ストラット
71 切り欠き
1 Joint structure of pier and
7 Filled
22
Claims (7)
鋼管接合用鉄筋の一端が前記フーチングに埋設定着されるように該フーチングを形成し、前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるようにかつ前記鋼管接合用鉄筋の他端が前記鋼管内に配置されるように該鋼管を鉛直姿勢にて前記フーチングの上方に位置決めし、前記隙間を所定の型枠材で塞ぎ、前記鋼管接合用鉄筋の他端が埋設定着されるように前記鋼管内にコンクリートを充填して前記鋼管内に鉄筋コンクリート体を形成する各工程からなり、前記鉄筋コンクリート体に埋設されるように前記鋼管内面に支圧部材を取り付けるとともに、前記鋼管接合用鉄筋を取り囲むように前記支圧部材を形成することにより、前記鋼管接合用鉄筋の材軸を中心としたほぼ円錐状の圧縮ストラットが形成されるようにしたことを特徴とする橋脚とフーチングとの接合方法。 In the joining method of the pier and footing that joins the pier composed of steel pipes to the footing formed of reinforced concrete,
The steel pipe joining rebar is formed so that one end of the steel pipe joining rebar is embedded in the footing, and a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing. The steel pipe is positioned above the footing in a vertical posture so that the other end of the steel pipe is placed in the steel pipe, the gap is closed with a predetermined formwork material, and the other end of the steel pipe joining rebar is buried. The steel pipe is filled with concrete to form a reinforced concrete body in the steel pipe, and a supporting member is attached to the inner surface of the steel pipe so as to be embedded in the reinforced concrete body, and the steel pipe joint By forming the bearing member so as to surround the reinforcing steel bar, a substantially conical compression strut centered on the material axis of the steel pipe joining reinforcing bar is formed. Method of joining the piers and footings characterized and.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007181102A JP5207108B2 (en) | 2007-07-10 | 2007-07-10 | Structure and method for joining pier and footing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007181102A JP5207108B2 (en) | 2007-07-10 | 2007-07-10 | Structure and method for joining pier and footing |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2009019360A true JP2009019360A (en) | 2009-01-29 |
JP5207108B2 JP5207108B2 (en) | 2013-06-12 |
Family
ID=40359236
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007181102A Expired - Fee Related JP5207108B2 (en) | 2007-07-10 | 2007-07-10 | Structure and method for joining pier and footing |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5207108B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013241732A (en) * | 2012-05-18 | 2013-12-05 | Tac:Kk | Semi-cylindrical body for constituting tool for column steel bar assembly |
JP2015071938A (en) * | 2014-12-08 | 2015-04-16 | 株式会社タック | Template and fixing plate for assembling post reinforced with reinforcing steels |
JP2019027103A (en) * | 2017-07-28 | 2019-02-21 | 公益財団法人鉄道総合技術研究所 | Concrete filled steel tube column structure |
CN108570923B (en) * | 2018-05-06 | 2020-11-27 | 北京工业大学 | Reinforced concrete pier structure capable of being quickly repaired after earthquake |
-
2007
- 2007-07-10 JP JP2007181102A patent/JP5207108B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013241732A (en) * | 2012-05-18 | 2013-12-05 | Tac:Kk | Semi-cylindrical body for constituting tool for column steel bar assembly |
JP2015071938A (en) * | 2014-12-08 | 2015-04-16 | 株式会社タック | Template and fixing plate for assembling post reinforced with reinforcing steels |
JP2019027103A (en) * | 2017-07-28 | 2019-02-21 | 公益財団法人鉄道総合技術研究所 | Concrete filled steel tube column structure |
CN108570923B (en) * | 2018-05-06 | 2020-11-27 | 北京工业大学 | Reinforced concrete pier structure capable of being quickly repaired after earthquake |
Also Published As
Publication number | Publication date |
---|---|
JP5207108B2 (en) | 2013-06-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20060185279A1 (en) | Foundations for constructions | |
JP5955108B2 (en) | Pile reinforcement structure of existing building and its construction method | |
WO2006030893A1 (en) | Foundation structure of tower | |
KR20160109629A (en) | Connection structure for internally confined hollow rc column-foundation connection reinforced with external tube and the method for the same | |
JP4844928B2 (en) | Pile head joint structure and construction method | |
JP2004285737A (en) | Construction method for steel tower foundation using concrete restraining connecting member | |
KR101418978B1 (en) | Structure of pile coupling | |
JP5207108B2 (en) | Structure and method for joining pier and footing | |
JP7304248B2 (en) | Pile head connection structure and construction method of pile head connection structure | |
JP2009293349A (en) | Joint structure between pile and foundation, construction method thereof, and joint method of pile to foundation | |
JP4957418B2 (en) | Structure and method for joining pier and footing | |
JP3649717B2 (en) | Joints and structures for joining steel pipe pile heads to concrete foundations | |
JP5527932B2 (en) | Design method of pier joint structure | |
JP5152689B2 (en) | Structure and method for joining pier and footing | |
JP2006257710A (en) | Joint structure of cast-in-situ concrete pile to foundation | |
JP6542036B2 (en) | Pile foundation structure | |
KR20110026206A (en) | Joint for concrete pile | |
JP5253316B2 (en) | Method for strengthening shear strength of ready-made concrete piles | |
JP5423134B2 (en) | Foundation structure | |
JP6461690B2 (en) | Foundation structure and foundation construction method | |
JP2005307676A (en) | Connection structure of foundation pile head and upper foundation | |
JP5104080B2 (en) | Structure and method for joining pier and footing | |
JP2004011130A (en) | Jacket structure and its construction method | |
JP2016223092A (en) | Pile foundation structure | |
JP4713218B2 (en) | Foundation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20100608 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20111228 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20130125 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20130207 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160301 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
LAPS | Cancellation because of no payment of annual fees |