JP2008280680A - Construction method for hanging structure building, and hanging structure building - Google Patents

Construction method for hanging structure building, and hanging structure building Download PDF

Info

Publication number
JP2008280680A
JP2008280680A JP2007123754A JP2007123754A JP2008280680A JP 2008280680 A JP2008280680 A JP 2008280680A JP 2007123754 A JP2007123754 A JP 2007123754A JP 2007123754 A JP2007123754 A JP 2007123754A JP 2008280680 A JP2008280680 A JP 2008280680A
Authority
JP
Japan
Prior art keywords
floor
suspension
beam member
predetermined
range
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007123754A
Other languages
Japanese (ja)
Inventor
Yuichi Ikeda
雄一 池田
Noriyuki Furuya
則之 古屋
Hiroyoshi Tokinoya
浩良 時野谷
Yasumasa Suzui
康正 鈴井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2007123754A priority Critical patent/JP2008280680A/en
Publication of JP2008280680A publication Critical patent/JP2008280680A/en
Pending legal-status Critical Current

Links

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method for a hanging structure building, which enables the fine adjustment of the inclination and height of a beam floor member to be easily performed even during a lifting operation. <P>SOLUTION: This construction method comprises: a step of constructing a horizontal member 10 at a predetermined height; a step of connecting the beam floor members of stories within the range of the predetermined number of stories by means of a temporary hanging column 120 by constructing the beam floor members 40 of the stories within the range of the predetermined number of stories on ground; a step of removing the temporary hanging column 120 of the operation target story in the state of supporting the beam floor members 40 from the uppermost story to the story directly above the operation target story within the range of the predetermined number of stories and supporting the beam floor members 40 of the lowermost story or the stories from the lowermost story to the operation target story within the range of the predetermined number of stories, while making the horizontal member 10 bear the reaction, by means of a beam-floor-member lifting/lowering device 130, in such a manner that the respective stories, except the uppermost story, among the stories within the range of the predetermined number of stories are set as the operation target stories in a proper order; a step of lifting the beam floor members 40 from the uppermost story to the story directly above the operation target story within the range of the predetermined number of stories by using the lifting/lowering device 130, until the story height of the operation target story reaches a predetermine height; and a step of constructing the finally-installed hanging column of the operation target story. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、メガフレームに複数の梁床部材が吊持されて構成されてなる吊構造建物の構築方法に関する。   The present invention relates to a method for constructing a suspended structure building in which a plurality of beam floor members are suspended from a megaframe.

従来より、複数の垂直部材の間に水平部材が架設されてなるメガフレームと、各階の床を構成する梁床部材と、各階の梁床部材の間及び最上階の梁床部材とメガフレームとの間を連結する吊柱とにより構成された吊構造建物が構築されている。   Conventionally, a mega frame in which a horizontal member is installed between a plurality of vertical members, a beam floor member constituting a floor of each floor, a beam floor member of each floor and a beam floor member and a mega frame of the uppermost floor Suspension structure building comprised with the suspension pillar which connects between is constructed.

このような吊構造建物の構築方法として、例えば、特許文献1には、メガフレームを構築した後、地上において各階の梁床部材を積層した状態で成形し、これらの梁床部材をロッドにより連結し、水平部材の上に設置された昇降装置によりロッドを引き上げ、ロッドの上端をメガフレームを構成する水平部材に固定することにより、吊構造建物を構築する方法が記載されている。
特許2717142号公報
As a method for constructing such a suspended structure building, for example, in Patent Document 1, after constructing a mega frame, the beam floor members of each floor are molded on the ground, and these beam floor members are connected by rods. A method of constructing a suspended structure building by lifting a rod by an elevating device installed on a horizontal member and fixing the upper end of the rod to a horizontal member constituting a mega frame is described.
Japanese Patent No. 2717142

しかしながら、上記の方法では、全ての梁床部材をロッドにより連結した状態で吊上げ作業を行うため、一度吊上げ作業を開始してしまうと、梁床部材が傾きを調整したり、梁床部材の高さを微調整したりすることができない。このため、梁床部材の傾きの調整や高さの微調整を行うためには、吊上げ作業を中止し、全ての梁床部材を地上に下ろして、ロッドを付け替え、再び吊上げ作業を行わなければならない。   However, in the above method, since the lifting work is performed in a state where all the beam floor members are connected by the rods, once the lifting work is started, the beam floor member is adjusted in inclination or the height of the beam floor member is increased. You cannot fine-tune the height. Therefore, in order to adjust the inclination of the beam floor member and finely adjust the height, the lifting work must be stopped, all the beam floor members must be lowered to the ground, the rods must be replaced, and the lifting work must be performed again. Don't be.

本発明は、上記の問題に鑑みなされたものであり、その目的は、吊上げ作業中でも容易に梁床部材の傾きの調整や高さの微調整を行うことのできる吊構造建物の構築方法を提供することである。   The present invention has been made in view of the above problems, and an object of the present invention is to provide a construction method of a suspended structure building that can easily adjust the inclination of the beam floor member and finely adjust the height even during the lifting work. It is to be.

本発明の吊構造建物の構築方法は、所定の階数範囲の各階の梁部材、梁床部材又は床部材(以下、梁部材等という)が、所定の高さに支持された主ビームから、当該梁部材等と同じ階及びこれより上階の本設の吊柱を介して吊下された構成を有する吊構造建物を構築する方法であって、前記主ビームを所定の高さに支持されるように構築又は設置する主ビーム構築工程と、地上において、前記所定の階数範囲の階の梁部材等を構築し、前記所定の階数範囲の階の梁部材等を前記本設の吊柱よりも短く、撤去可能な仮設の吊柱により連結する梁部材等連結工程と、を行い、前記所定の階数範囲の最上階を除く少なくとも一部の階を適宜な順序で作業対象階として、梁部材等昇降装置により前記主ビームに反力をとりながら、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの階の梁部材等を支持するとともに、前記所定の階数範囲のうちの最下階又は最下階から前記作業対象階までの階の梁部材等を支持した状態で、前記作業対象階の前記仮設の吊柱を撤去する仮設の吊柱撤去工程と、前記梁部材等昇降装置により前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの階の前記梁部材等を前記作業対象階の階高が所定の高さになるまで上昇させる梁部材等上昇工程と、前記作業対象階の梁部材等を、前記作業対象階の直情の階の梁部材等に本設の吊柱により接続する吊柱接続工程と、を行うことを特徴とする。なお、前記少なくとも一部の階以外の階については、本発明の方法に限らず、適宜な方法により構築すればよい。   The method for constructing a suspended structure building according to the present invention includes a beam member, a beam floor member, or a floor member (hereinafter referred to as a beam member, etc.) on each floor in a predetermined floor range, from the main beam supported at a predetermined height. A method for constructing a suspended structure building having a structure suspended from a main suspension pole on the same floor as a beam member and the upper floor, wherein the main beam is supported at a predetermined height. The main beam construction step of constructing or installing as described above, and on the ground, constructing a beam member or the like of the floor within the predetermined floor range, and the beam member or the like of the floor within the predetermined floor range from the main suspension column A beam member connecting step using a short and removable temporary suspension pillar, and at least a part of the floors excluding the uppermost floor in the predetermined floor range as work floors in an appropriate order. While taking the reaction force to the main beam by the lifting device, the predetermined floor range The beam of the floor from the top floor to the floor directly above the work floor and the floor from the bottom floor or the floor to the work floor in the predetermined floor range The temporary suspension column removing step of removing the temporary suspension column on the work target floor in a state where the member is supported, and the work target from the uppermost floor in the predetermined floor range by the lifting device such as the beam member A beam member ascending step for raising the beam members and the like up to the floor immediately above the floor until the floor height of the work target floor reaches a predetermined height, and the beam members and the like of the work target floor A suspension column connecting step of connecting to a beam member or the like on the floor of the target floor with a permanent suspension column is performed. The floors other than the at least some of the floors are not limited to the method of the present invention, and may be constructed by an appropriate method.

ここで、上記の吊構造建物の構築方法において前記梁部材等昇降装置により、前記所定の階数範囲のうちの最下階の梁部材等が所定の高さになるまで、前記所定の階数範囲の全ての階の梁部材等を上昇させる最下階上昇工程と、前記所定の階数範囲のうちの最上階の本設の吊柱を構築する最上階吊柱構築工程と、をさらに行ってもよい。   Here, in the construction method of the above suspended structure building, the beam member elevating device causes the beam member of the lowest floor of the predetermined floor range to reach a predetermined height until the beam member of the predetermined floor range has a predetermined height. The lowermost floor raising step for raising beam members and the like of all the floors and the uppermost floor hanging pillar construction step for constructing the main suspension pillar on the uppermost floor of the predetermined floor number range may be further performed. .

また、前記最下階上昇工程は、前記梁部材等連結工程の後段に行い、前記所定の階数範囲の最下階から上方に向かって前記作業対象階としてもよい。   Further, the lowermost floor ascending step may be performed after the beam member connecting step, and may be set as the work target floor from the lowermost floor in the predetermined floor range upward.

また、前記主ビームは、前記梁部材等の周囲に立設された支持部材により所定の高さに支持されており、前記所定の階数範囲内の各階の前記梁部材等と前記支持部材とは、連結部材を介して接続されており、前記吊柱構築工程では、さらに、前記作業対象階の直上の階の梁部材等と、前記支持部材とを連結部材を介して接続してもよい。   Further, the main beam is supported at a predetermined height by a support member standing around the beam member, and the beam member and the support member on each floor within the predetermined floor range are In the suspension column construction step, the beam member on the floor immediately above the work target floor and the support member may be further connected via the connecting member.

また、前記梁部材等昇降装置は、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの何れかの階の梁部材等に下端が定着された吊り材と、前記主ビームに取り付けられ、前記吊り材の上部を支持するとともに前記吊り材を昇降させることが可能な昇降機構とで構成され、前記梁部材等上昇工程では、前記昇降機構が前記吊り材を上昇させることにより、前記作業対象階の直上の階から前記所定の階数範囲のうちの最上階までの階の梁部材等を上昇させてもよい。   Further, the beam member lifting device includes a suspension member having a lower end fixed to a beam member or the like of any floor from the uppermost floor of the predetermined floor range to the floor immediately above the work target floor, A lifting mechanism that is attached to a main beam and supports the upper part of the suspension member and that can lift the suspension member; and in the beam member ascending step, the lifting mechanism raises the suspension member Accordingly, the beam members and the like of the floors from the floor immediately above the work target floor to the top floor in the predetermined floor range may be raised.

また、前記梁部材等昇降装置は、前記主ビームに上端が定着された吊り材と、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの何れかの階の梁部材等の下側に取り付けられ、前記吊り材を支持するとともに、前記吊り材に沿って昇降可能な昇降機構と、で構成され、前記梁部材等上昇工程では、前記昇降機構が前記吊り材に沿って上昇することにより、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの階の梁部材等を上昇させさせてもよい。   The elevating device such as a beam member includes a suspension member having an upper end fixed to the main beam, and a beam on any floor from the top floor to the floor immediately above the work floor in the predetermined floor range. An elevating mechanism that is attached to a lower side of a member or the like and supports the hanger, and that can be moved up and down along the hanger. In the elevating step of the beam member, the elevating mechanism is attached to the hanger. The beam members and the like on the floor from the uppermost floor of the predetermined floor range to the floor immediately above the work target floor may be lifted by rising along the floor.

また、前記仮設の吊柱は、内部に前記吊り材を挿通可能であり、前記梁部材等の前記仮設の吊柱が接続された部位には貫通孔が設けられており、前記昇降装置設置工程では、前記吊り材を前記吊柱の内部及び前記梁部材等の貫通孔を貫通するように前記梁部材等昇降装置を設置してもよい。   Further, the temporary suspension pillar can be inserted with the suspension material therein, and a through-hole is provided in a portion to which the temporary suspension pillar such as the beam member is connected, and the lifting device installation step Then, you may install the raising / lowering apparatus, such as said beam member, so that the said suspension material may penetrate the inside of the said suspension column, and through-holes, such as the said beam member.

また、前記昇降装置設置工程では、前記梁部材等の前記仮設の吊柱の接続された位置以外の部位に鉛直方向に並ぶように貫通孔を設け、前記吊り材を前記貫通孔を挿通するように前記吊り材を設置してもよい。   Further, in the elevating device installation step, a through hole is provided so as to be arranged in a vertical direction at a portion other than the position where the temporary suspension pillar such as the beam member is connected, and the suspension member is inserted through the through hole. You may install the said suspension material in.

また、前記昇降装置設置工程では、前記昇降装置を、前記主ビームに反力を取りながら、前記所定の階数範囲の最上階の梁部材等を昇降させるように設置してもよい。
また、本発明の吊構造建物は、上記の方法により構築されたことを特徴とする。
Further, in the lifting device installation step, the lifting device may be installed so as to lift and lower the beam member on the uppermost floor in the predetermined floor range while taking a reaction force on the main beam.
Moreover, the suspended structure building of this invention was constructed | assembled by said method.

本発明によれば、昇降装置により作業対象階の直上の階の梁床部材の高さ及び吊柱の長さを適宜調整することにより、リフトアップ作業中であっても、全ての階の梁床部材を地上に降ろすことなく、階高の微調整や梁床部材の傾きを調整することができる。   According to the present invention, the beam of all floors can be adjusted even during lift-up work by appropriately adjusting the height of the beam floor member and the length of the suspension column on the floor directly above the work target floor by the lifting device. Fine adjustment of the floor height and inclination of the beam floor member can be adjusted without lowering the floor member to the ground.

以下、本発明の吊構造の建物の構築方法の一実施形態を図面を参照しながら説明する。
図1は、本実施形態の構築方法により構築された吊構造建物100の構成を示す正面図である。同図に示すように、本実施形態の吊構造建物100は、複数の垂直部材(特許請求の範囲における支持部材に相当)20及びこれらの垂直部材20の間に架設された水平部材(特許請求の範囲における主ビームに相当)10からなるメガフレーム30と、2〜8階の床を構成する床スラブ及び梁が一体となった梁床部材40と、水平部材10と最上階(8階)の梁床部材40の間及び各階の梁床部材40の間を連結する吊柱50と、垂直部材20と各階の梁床部材40とを連結する連結部材60と、を備える。
Hereinafter, an embodiment of a construction method of a suspended structure building of the present invention will be described with reference to the drawings.
FIG. 1 is a front view showing a configuration of a suspended structure building 100 constructed by the construction method of the present embodiment. As shown in the figure, a suspended structure building 100 according to the present embodiment includes a plurality of vertical members (corresponding to support members in claims) 20 and a horizontal member laid between these vertical members 20 (claims). 10), a beam floor member 40 in which floor slabs and beams constituting the floors of the second to eighth floors are integrated, a horizontal member 10 and the uppermost floor (eighth floor). The suspension pillar 50 which connects between the beam floor members 40 and between the beam floor members 40 of each floor, and the connection member 60 which connects the vertical member 20 and the beam floor member 40 of each floor are provided.

図2は、吊柱50を構成する部材を示す斜視図である。同図に示すように、吊柱50は、軸方向に分割された一対の鋼管152をボルト接合することにより構成されている。これにより、後述するように梁床部材昇降装置130のロッド132を挿通可能であるとともに、組立及び撤去を容易に行うことができる。   FIG. 2 is a perspective view showing members constituting the suspension pillar 50. As shown in the figure, the suspension column 50 is configured by bolting a pair of steel pipes 152 divided in the axial direction. Thereby, as will be described later, the rod 132 of the beam floor member elevating device 130 can be inserted, and assembly and removal can be easily performed.

図1に戻り、連結部材60としては、梁床部材40をメガフレーム30の垂直部材20に対して剛に接続できるように、剛性部材を用いる構成としてもよいし、ばね部材やダンパーなどを用いる構成としてもよい。   Returning to FIG. 1, the connecting member 60 may be configured to use a rigid member so that the beam floor member 40 can be rigidly connected to the vertical member 20 of the megaframe 30, or a spring member or a damper may be used. It is good also as a structure.

以下、このような吊構造建物100の構築方法を説明する。
図3〜図7は、本実施形態の吊構造の建物の構築方法を説明するための図である。
図3に示すように、まず、STEP1において、メガフレーム30を構成する垂直部材20を構築し、この垂直部材20の上部に反力をとるように鋼製の節つきのロッド112及びジャッキ111からなる水平部材昇降装置110を設置する。すなわち、垂直部材20の上端にジャッキ111を設置し、このジャッキ111にロッド112の上部を取付ける。なお、垂直部材20は、予め、構築されたものを搬入し、設置してもよい。
Hereinafter, the construction method of such a suspended structure building 100 will be described.
3-7 is a figure for demonstrating the construction method of the building of the suspension structure of this embodiment.
As shown in FIG. 3, first, in STEP 1, the vertical member 20 constituting the mega frame 30 is constructed, and is composed of a steel-jointed rod 112 and a jack 111 so as to apply a reaction force to the upper portion of the vertical member 20. The horizontal member elevating device 110 is installed. That is, the jack 111 is installed at the upper end of the vertical member 20, and the upper portion of the rod 112 is attached to the jack 111. In addition, the vertical member 20 may carry in and install what was built beforehand.

なお、このようなジャッキ111としては、例えば、ロッド112に沿って昇降可能なシャックル付きのジャッキ(例えば、JFEシビル株式会社製)などが適している。また、ロッド112に代えて、鋼線や鋼材などを用いることもできる。   As such a jack 111, for example, a jack with a shackle that can be moved up and down along the rod 112 (for example, manufactured by JFE Civil Co., Ltd.) is suitable. Moreover, it can replace with the rod 112 and a steel wire, steel materials, etc. can also be used.

次に、STEP2において、地上に設置されたベント140上で、メガフレーム30を構成する水平部材10を構築する。なお、この水平部材10を構築する工程は、STEP1における水平部材昇降装置110を設置する工程の前に行ってもよい。また、水平部材10は、予め、構築されたものを搬入してもよい。そして、ジャッキ111より下方に延びるロッド112の下部に、定着部113により水平部材10を定着させる。   Next, in STEP 2, the horizontal member 10 constituting the mega frame 30 is constructed on the vent 140 installed on the ground. In addition, you may perform the process of constructing this horizontal member 10 before the process of installing the horizontal member raising / lowering apparatus 110 in STEP1. Moreover, the horizontal member 10 may carry in what was constructed | assembled previously. Then, the horizontal member 10 is fixed by the fixing unit 113 under the rod 112 extending downward from the jack 111.

次に、STEP3において、水平部材10を水平部材昇降装置110により吊上げ、水平部材10を垂直部材20と接続する。
次に、STEP4において、水平部材昇降装置110を解体し、撤去する。
Next, in STEP 3, the horizontal member 10 is lifted by the horizontal member lifting device 110, and the horizontal member 10 is connected to the vertical member 20.
Next, in STEP 4, the horizontal member elevating device 110 is disassembled and removed.

次に、STEP5において、地上のベント140上において、2〜8階の梁床部材を構築し、これらの梁床部材40の間を仮設の吊柱120により連結する。なお、仮設の吊柱120は、本設の吊柱50と同様に、図2に示すような長さ方向に複数に分割された鋼管152からなり、内部にロッド132を挿通することができ、また、容易に組立て及び撤去することができる。また、2〜8階の梁床部材40の仮設の吊柱120が接続される位置にも、ロッド132を貫通することができるように開口を設けておく。   Next, in STEP 5, the beam floor members of the second to eighth floors are constructed on the ground vent 140, and the beam floor members 40 are connected by the temporary suspension pillars 120. The temporary suspension column 120 is formed of a steel pipe 152 divided into a plurality of pieces in the length direction as shown in FIG. 2, like the permanent suspension column 50, and the rod 132 can be inserted therein. Also, it can be easily assembled and removed. Moreover, the opening is provided so that the rod 132 can be penetrated also in the position where the temporary suspension pillar 120 of the beam floor member 40 of the 2nd-8th floor is connected.

そして、ジャッキ131と、ロッド132とで構成された梁床部材昇降装置130を、水平部材10に反力をとりながら、2階の梁床部材40を昇降可能なように設置する。すなわち、ロッド132を2〜8階の梁床部材40の開口及び仮設の吊柱120の内部に挿通させ、ロッド132の上端部に水平部材10に支持されるようにジャッキ131を取り付け、ロッド132の下端部を定着部133により2階の梁床部材40を下方から支持するように取付ける。   And the beam floor member raising / lowering apparatus 130 comprised with the jack 131 and the rod 132 is installed so that the beam floor member 40 of the 2nd floor can be raised / lowered, taking reaction force to the horizontal member 10. FIG. That is, the rod 132 is inserted into the opening of the beam floor member 40 on the second to eighth floors and the inside of the temporary suspension column 120, and the jack 131 is attached to the upper end portion of the rod 132 so as to be supported by the horizontal member 10. The lower end of the beam is attached by the fixing unit 133 so as to support the beam floor member 40 on the second floor from below.

次に、STEP6において、梁床部材昇降装置130により、2〜8階の梁床部材40を、2階の梁床部材40が所定の高さに到達するまで上昇させる。
次に、図4のSTEP7において、地上部のベント140により2階の梁床部材40を下方より支持することができるように、ベント140の高さを調整する。そして、2階の梁床部材40と垂直部材20とを連結部材60により接続し、2階の梁床部材40の下方に取付けられた定着部133を取り外す。
Next, in STEP 6, the beam floor member lifting device 130 raises the beam floor members 40 on the second to eighth floors until the beam floor members 40 on the second floor reach a predetermined height.
Next, in STEP 7 in FIG. 4, the height of the vent 140 is adjusted so that the beam floor member 40 on the second floor can be supported from below by the vent 140 on the ground. Then, the beam floor member 40 on the second floor and the vertical member 20 are connected by the connecting member 60, and the fixing portion 133 attached below the beam floor member 40 on the second floor is removed.

次に、STEP8において、3階の梁床部材40を梁床部材昇降装置130により支持することができるように、3階の梁床部材40の下方に定着部133を取付ける。この際、2階の梁床部材40は、ベント140により支持されるため、落下することはない。そして、2階の仮設の吊柱120を撤去する。   Next, in STEP 8, the fixing unit 133 is attached below the beam floor member 40 on the third floor so that the beam floor member 40 on the third floor can be supported by the beam floor member lifting device 130. At this time, since the beam floor member 40 on the second floor is supported by the vent 140, it does not fall. Then, the temporary suspension pole 120 on the second floor is removed.

次に、STEP9において、梁床部材昇降装置130により、3〜8階の梁床部材40を、3階の梁床部材40が3階のレベルに到達する(すなわち、2階の階高が所定の高さになる)まで上昇させる。   Next, in STEP 9, the beam floor member lifting device 130 causes the beam floor member 40 of the third to eighth floors to reach the level of the third floor of the beam floor member 40 of the third floor (that is, the floor height of the second floor is predetermined). To the height of

次に、STEP10において、3階の梁床部材40を支持するように、2階と3階の梁床部材40の間に仮設の支持部材150を設置する。そして、3階の梁床部材40と垂直部材20とを連結部材60により接続し、3階の梁床部材40の下方に取り付けられた定着部133を取り外す。この際、3階の梁床部材40は、仮設の支持部材150により支持されるため、落下することはない。   Next, in STEP 10, a temporary support member 150 is installed between the second floor and the third floor beam floor member 40 so as to support the third floor beam floor member 40. Then, the beam floor member 40 on the third floor and the vertical member 20 are connected by the connecting member 60, and the fixing portion 133 attached below the beam floor member 40 on the third floor is removed. At this time, the beam floor member 40 on the third floor is supported by the temporary support member 150 and therefore does not fall.

次に、STEP11において、4階の梁床部材40を梁床部材昇降装置130により支持することができるように、4階の梁床部材40の下方に定着部133を取付ける。そして、2階の本設の吊柱50を構築し、2階の仮設の支持部材150を撤去する。また、3階の仮設の吊柱を撤去する。   Next, in STEP 11, the fixing unit 133 is attached below the fourth floor beam floor member 40 so that the fourth floor beam floor member 40 can be supported by the beam floor member lifting device 130. Then, the main suspension pole 50 on the second floor is constructed, and the temporary support member 150 on the second floor is removed. Also, the temporary suspension pillar on the third floor will be removed.

次に、STEP12において、梁床部材昇降装置130により、4〜8階の梁床部材40を、4階の梁床部材40が4階のレベルに到達する(すなわち、3階の階高が所定の高さになる)まで上昇させる。   Next, in STEP 12, the beam floor member 40 reaches the level of the fourth floor by the beam floor member lifting device 130 (that is, the floor height of the third floor is predetermined). To the height of

次に、図5のSTEP13において、4階の梁床部材40を支持するように、3階と4階の梁床部材40の間に仮設の支持部材150を設置する。そして、4階の梁床部材40と垂直部材20とを連結部材60により接続し、4階の梁床部材40の下方に取り付けられた定着部133を取り外す。この際、4階の梁床部材40は、仮設の支持部材150により支持されるため、落下することはない。   Next, in STEP 13 of FIG. 5, a temporary support member 150 is installed between the third and fourth floor beam floor members 40 so as to support the fourth floor beam floor members 40. Then, the fourth floor beam floor member 40 and the vertical member 20 are connected by the connecting member 60, and the fixing unit 133 attached below the fourth floor beam floor member 40 is removed. At this time, the beam floor member 40 on the fourth floor is supported by the temporary support member 150 and therefore does not fall.

以下、図5のSTEP14〜図6のSTEP22において、図4のSTEP11〜図5のSTEP13と同様に、4階から6階の順序で各階を作業対象階として、作業対象階の上階の梁床部材40を梁床部材昇降装置130により支持することができるように、作業対象階の上階の梁床部材40の下方に定着部133を取付け、作業対象階の下階の本設の吊柱50を構築し、作業対象階の下階の仮設の支持部材150を撤去し、作業対象階の仮設の吊柱120を撤去し、作業対象階の上階から最上階までの梁床部材40を作業対象階の階高が所定の高さになるまで上昇させ、作業対象階の下階に仮設の支持部材を設置し、作業対象階の連結部材を取り付け、作業対象階の梁床部材40の下方に取り付けられた定着部133を取り外す工程を行う。
これにより、STEP22に示すような状態となる。
Hereinafter, in STEP 14 of FIG. 5 to STEP 22 of FIG. 6, as in STEP 11 of FIG. 4 to STEP 13 of FIG. 4, each floor is set as the work floor in the order from the 4th floor to the 6th floor. A fixing unit 133 is attached below the beam floor member 40 on the upper floor of the work floor so that the member 40 can be supported by the beam floor member lifting device 130, and the main suspension pillar on the lower floor of the work floor is installed. 50, the temporary support member 150 on the lower floor of the work target floor is removed, the temporary suspension column 120 on the work target floor is removed, and the beam floor member 40 from the upper floor to the uppermost floor of the work target floor is removed. The work target floor is raised until the floor height reaches a predetermined height, a temporary support member is installed on the lower floor of the work target floor, a connection member of the work target floor is attached, and the beam floor member 40 of the work target floor is installed. The process of removing the fixing unit 133 attached below is performed. .
As a result, the state shown in STEP 22 is obtained.

次に、図6のSTEP23において、最上階(8階)の梁床部材40の下方に定着部133を取付ける。そして、6階の本設の吊柱50を構築するとともに、7階の仮設の吊柱120を撤去する。
次に、STEP24において、梁床部材昇降装置130により、最上階(8階)の梁床部材が8階のレベルに到達するまで、上昇させる。
Next, in STEP23 of FIG. 6, the fixing part 133 is attached below the beam floor member 40 on the uppermost floor (eighth floor). Then, the permanent suspension pillar 50 on the sixth floor is constructed, and the temporary suspension pillar 120 on the seventh floor is removed.
Next, in STEP 24, the beam floor member elevating device 130 raises the beam floor member on the top floor (eighth floor) until it reaches the level of the eighth floor.

次に、図7のSTEP25において、7階と8階の梁床部材40の間に仮設の支持部材150を設置する。また、8階の梁床部材40と垂直部材20とを連結部材60により接続する。そして、8階の本設の吊柱50を構築する。
次に、STEP26において、梁床部材昇降装置130を解体し、撤去する。
次に、STEP27において、7階の本設の吊柱50を構築し、7階の仮設の支持部材150を撤去する。
以上の工程により吊構造建物100を構築することができる。
Next, in STEP 25 of FIG. 7, a temporary support member 150 is installed between the beam floor members 40 on the seventh floor and the eighth floor. Further, the beam floor member 40 on the eighth floor and the vertical member 20 are connected by a connecting member 60. And the main suspension pole 50 of the 8th floor is constructed.
Next, in STEP 26, the beam floor member lifting device 130 is disassembled and removed.
Next, in STEP 27, the 7th-floor main suspension pole 50 is constructed, and the 7th-floor temporary support member 150 is removed.
The suspended structure building 100 can be constructed by the above steps.

以上説明したように、本実施形態の吊構造建物の構築方法によれば、梁床部材昇降装置130により作業対象階の直上の階の梁床部材40の高さ及び本設の吊柱50の長さを適宜調整することにより、リフトアップ作業中であっても、全ての階の梁床部材40を地上に降ろすことなく、階高の微調整や梁床部材40の傾きを調整することができる。   As described above, according to the method for constructing a suspended structure building of the present embodiment, the height of the beam floor member 40 on the floor immediately above the work floor and the height of the suspension column 50 of the main installation by the beam floor member lifting device 130. By adjusting the length appropriately, fine adjustment of the floor height and the inclination of the beam floor member 40 can be performed without lowering the beam floor member 40 of all the floors to the ground even during lift-up work. it can.

なお、上記実施形態では、梁床部材昇降装置130のロッド132を本設の吊柱50内を挿通するように設ける構成としたが、これに限らず、梁床部材40の吊柱50以外の位置に鉛直方法に並ぶように貫通孔を設けておき、この貫通孔を挿通するようにロッド132を設け、吊柱50以外の位置に梁床部材昇降装置130を設置してもよい。   In the above embodiment, the rod 132 of the beam floor member elevating device 130 is provided so as to be inserted through the main suspension column 50. However, the present invention is not limited to this, and the rods other than the suspension column 50 of the beam floor member 40 may be used. A through hole may be provided at a position so as to be aligned in a vertical manner, a rod 132 may be provided so as to be inserted through the through hole, and the beam floor member lifting device 130 may be installed at a position other than the suspension column 50.

また、上記実施形態では、梁床部材昇降装置130のロッド132を作業対象階の直上の階の梁床部材40に定着させる構成としたが、これに限らず、作業対象階よりも上の階であれば、何れの階の梁床部材40に定着させてもよい。   In the above embodiment, the rod 132 of the beam floor member lifting device 130 is fixed to the beam floor member 40 on the floor immediately above the work target floor. However, the present invention is not limited to this, and the floor above the work target floor is used. If so, the beam floor member 40 on any floor may be fixed.

以下、このように吊柱50以外の位置に梁床部材昇降装置130を設置し、ロッド132を8階の梁床部材40に定着させる場合の吊構造建物の構築方法について、図8及び図9を参照しながら説明する。なお、このように、吊柱50以外の位置に梁床部材昇降装置130を設置する場合には、本設の吊柱50及び仮設の吊柱120は内部にロッド132を挿通可能な構成としなくてもよい。   Hereinafter, a construction method of a suspended structure building in which the beam floor member lifting device 130 is installed at a position other than the suspension column 50 and the rod 132 is fixed to the beam floor member 40 on the eighth floor will be described with reference to FIGS. Will be described with reference to FIG. In this way, when the beam floor member lifting device 130 is installed at a position other than the suspension column 50, the main suspension column 50 and the temporary suspension column 120 are not configured to allow the rod 132 to be inserted therein. May be.

まず、上記実施形態と同様にメガフレーム30を構築する。なお、メガフレーム30を構築する工程は、図3におけるSTEP1〜4と同じ工程であるので、説明を省略する。   First, the mega frame 30 is constructed as in the above embodiment. In addition, since the process of constructing the mega frame 30 is the same process as STEP 1 to STEP 4 in FIG.

メガフレーム30を構築した後、図8に示すように、STEP5´において、梁床部材40を構築し、これらの梁床部材40を仮設の吊柱120で連結する。この際、梁床部材昇降装置130のロッド132を挿通するため、梁床部材40の仮設の吊柱120と異なる位置に鉛直方向に直線上に並ぶように貫通孔を設けておく。そして、この貫通孔にロッド132を2〜8階の梁床部材40の貫通孔に挿通させ、ロッド132の上端部に水平部材10に支持されるようにジャッキ131を取り付け、ロッド132の下端部を定着部133により8階の梁床部材40を下方から支持するように取付け、梁床部材昇降装置130を組み立てる。   After the mega frame 30 is constructed, as shown in FIG. 8, the beam floor members 40 are constructed in STEP 5 ′, and these beam floor members 40 are connected by temporary suspension pillars 120. At this time, in order to insert the rod 132 of the beam floor member elevating device 130, through holes are provided so as to be arranged in a straight line in the vertical direction at a position different from the temporary suspension column 120 of the beam floor member 40. The rod 132 is inserted into the through hole of the beam floor member 40 on the second to eighth floors, and the jack 131 is attached to the upper end portion of the rod 132 so as to be supported by the horizontal member 10. Is attached so that the beam floor member 40 on the eighth floor is supported from below by the fixing unit 133, and the beam floor member lifting device 130 is assembled.

次に、STEP6´において、梁床部材昇降装置130により、2〜8階の梁床部材40を、2階の梁床部材40が所定の高さに到達するまで上昇させる。
次に、STEP7´において、地上部のベント140により2階の梁床部材40を下方より支持することができるように、ベント140の高さを調整する。そして、2階の梁床部材40と垂直部材20とを連結部材60により接続する。
Next, in STEP 6 ′, the beam floor member lifting device 130 raises the beam floor member 40 on the second to eighth floors until the beam floor member 40 on the second floor reaches a predetermined height.
Next, in STEP 7 ′, the height of the vent 140 is adjusted so that the beam floor member 40 on the second floor can be supported from below by the vent 140 on the ground. Then, the beam floor member 40 on the second floor and the vertical member 20 are connected by the connecting member 60.

次に、STEP8´において、2階の仮設の吊柱120を撤去する。
次に、STEP9´において、梁床部材昇降装置130により、3〜8階の梁床部材40を、3階の梁床部材40が3階のレベルに到達する(すなわち、2階の階高が所定の高さになる)まで上昇させる。
Next, in STEP 8 ′, the temporary suspension pillar 120 on the second floor is removed.
Next, in STEP 9 ′, the beam floor member lifting device 130 causes the beam floor member 40 of the third to eighth floors to reach the level of the third floor. To a predetermined height).

次に、STEP10´において、2階の本設の吊柱50を構築するとともに、3階の梁床部材40と垂直部材20とを連結部材60により接続する。
次に、図9のSTEP11´において、3階の仮設の吊柱120を撤去する。
Next, in STEP 10 ′, the main suspension pillar 50 on the second floor is constructed, and the beam floor member 40 and the vertical member 20 on the third floor are connected by the connecting member 60.
Next, in STEP 11 ′ of FIG. 9, the temporary suspension pole 120 on the third floor is removed.

次に、STEP12´において、4〜8階の梁床部材40を、4階の梁床部材40が4階のレベルに到達する(すなわち、3階の階高が所定の高さになる)まで上昇させる。
次に、STEP13´において、2階の本設の吊柱50を構築するとともに、4階の連結部材60を設置する。
Next, in STEP 12 ', the beam floor member 40 of the 4th to 8th floors is reached until the beam floor member 40 of the 4th floor reaches the level of the 4th floor (that is, the floor height of the 3rd floor becomes a predetermined height). Raise.
Next, in STEP 13 ′, the second-floor main suspension pillar 50 is constructed, and the fourth-floor connecting member 60 is installed.

以下、STEP11´〜13´のように、4〜7階についても、作業対象階として、作業対象階の仮設の吊柱120を撤去し、作業対象階の上階から最上階までの梁床部材40を上昇させ、作業対象階の本設の吊柱120を構築するとともに、作業対象階の上階の梁床部材40を連結部材60により垂直部材20に接続する作業を行う。これにより、STEP15´に示すような状態となる。   Hereinafter, as in STEP 11 ′ to 13 ′, the temporary suspension pillar 120 on the work target floor is removed as the work target floor on the fourth to seventh floors, and the beam floor member from the upper floor to the top floor of the work target floor is removed. 40 is raised to construct the main suspension column 120 on the work target floor and connect the beam floor member 40 on the upper floor of the work target floor to the vertical member 20 by the connecting member 60. As a result, the state shown in STEP 15 ′ is obtained.

次に、STEP16´において、8階の本設の吊柱50を構築する。
次に、STEP17´において、梁床部材昇降装置130を撤去する。以上の工程により、吊構造建物100を構築することができる。
Next, in STEP16 ′, a main suspension pillar 50 on the eighth floor is constructed.
Next, in STEP 17 ′, the beam floor member lifting device 130 is removed. The suspended structure building 100 can be constructed through the above steps.

以上説明したように、梁床部材昇降装置130を仮設の吊柱120と異なる位置に取付けることにより、仮設の支持部材150を取付ける工程及び仮設の支持部材150を取り外す工程を省略することができる。また、梁床部材昇降装置130を最上階の梁床部材40に定着させる構成とすることで、定着部133を盛替える作業が不要となる。   As described above, the step of attaching the temporary support member 150 and the step of removing the temporary support member 150 can be omitted by attaching the beam floor member lifting device 130 to a position different from the temporary suspension column 120. Further, by adopting a configuration in which the beam floor member elevating device 130 is fixed to the beam floor member 40 on the uppermost floor, the work of replacing the fixing unit 133 becomes unnecessary.

なお、上記各実施形態では、下階から上階の順序でリフトアップする構成としたが、これに限らず、上階から下階の順序でリフトアップする構成としてもよく、また、中間の階からリフトアップしてもよく、要するにどのような順序でリフトアップしてもかまわない。   In each of the above embodiments, the lift is configured in the order from the lower floor to the upper floor. However, the present invention is not limited to this, and the lift may be performed in the order from the upper floor to the lower floor. It may be lifted up, and in any order, it may be lifted up in any order.

また、上記の各実施形態では、梁床部材昇降装置130を、ロッド132の下端部を定着部133により作業対象階の上階の梁床部材40に定着し、ロッド132の上端部にジャッキ131を水平部材10上に反力を取ることができるように設置する構成としたが、これに限らず、ロッド132の上部を定着部133により水平部材10に定着させ、ジャッキ131をロッド132の作業対象階の上階の梁床部材40を下方から支持するように設置する構成としてもよい。   In each of the above embodiments, the beam floor member lifting device 130 is fixed to the beam floor member 40 on the upper floor of the work floor by the fixing unit 133 at the lower end of the rod 132, and the jack 131 is fixed to the upper end of the rod 132. However, the present invention is not limited to this, and the upper portion of the rod 132 is fixed to the horizontal member 10 by the fixing portion 133, and the jack 131 is operated on the rod 132. It is good also as a structure installed so that the beam floor member 40 of the upper floor of a target floor may be supported from the downward direction.

また、上記各実施形態では、梁床部材40と垂直部材20の間に連結部材60が介装された構成の吊構造建物100を構築する場合についえて説明したが、これに限らず、連結部材60を省略することも可能であり、この場合には、連結部材60を取付ける工程が不要となる。   Further, in each of the above embodiments, the case where the suspended structure building 100 having the configuration in which the connecting member 60 is interposed between the beam floor member 40 and the vertical member 20 has been described, but not limited thereto, the connecting member is not limited thereto. It is also possible to omit 60, and in this case, the step of attaching the connecting member 60 becomes unnecessary.

また、上記各実施形態では、各階の梁と床が一体となった梁床部材40が吊持された吊構造建物100を構築する場合について説明したが、これに限らず、梁と床が別体であり梁部材のみが吊持された吊構造建物に対しても本発明を適用することができる。   Moreover, although each said embodiment demonstrated the case where the suspended structure building 100 with which the beam floor member 40 with which the beam and floor of each floor were united was constructed | assembled was not limited to this, a beam and a floor were separated. The present invention can also be applied to a suspended building in which only a beam member is suspended.

また、上記各実施形態では、2階の梁床部材40を、地上と2階の梁床部材40との間に1階の階高に合わせたベント140を介装させることにより支持する構成としたが、これに限らず、地上と2階の梁床部材40との間に1階の階高に合わせた仮設の支持部材を設置する方法や、ロッドや鋼線などの吊り材の上端を水平部材10に定着させるとともに下端を2階の梁床部材40を下方より支持するように定着させ、吊り材により2階の梁床部材40を吊持する方法により支持する構成としてもよく、要するに、階高調整階及びそれよりも下階の梁床部材40を支持することができれば、どのような構成であってもよい。
また、上記各実施形態では、吊柱50により吊持された全ての階の梁床部材40を本発明の方法により構築する場合について説明したが、これに限らず、一部の階のみを本発明の方法により構築することも可能である。
Moreover, in each said embodiment, the structure which supports the beam floor member 40 of the 2nd floor by interposing the vent 140 matched with the floor height of the 1st floor between the ground and the beam floor member 40 of the 2nd floor, However, the present invention is not limited to this, and a method of installing a temporary support member that matches the floor height of the first floor between the ground and the second floor beam floor member 40, or the upper end of a suspension material such as a rod or steel wire The horizontal member 10 may be fixed, and the lower end may be fixed so as to support the second-floor beam floor member 40 from below, and the second-floor beam floor member 40 may be supported by a suspension material. Any configuration may be used as long as the beam floor member 40 on the floor height adjustment floor and lower floors can be supported.
Moreover, although each said embodiment demonstrated the case where the beam floor member 40 of all the floors suspended by the suspension pillar 50 was constructed | assembled by the method of this invention, not only this but only a part of floors is this. It can also be constructed by the method of the invention.

本実施形態の吊構造建物の構成を示す正面図である。It is a front view which shows the structure of the suspension structure building of this embodiment. 吊柱を構成する部材を示す斜視図である。It is a perspective view which shows the member which comprises a suspension pillar. 本実施形態の吊構造の建物の構築方法を説明するための図(その1)である。It is FIG. (1) for demonstrating the construction method of the building of the suspension structure of this embodiment. 本実施形態の吊構造の建物の構築方法を説明するための図(その2)である。It is FIG. (2) for demonstrating the construction method of the building of the suspension structure of this embodiment. 本実施形態の吊構造の建物の構築方法を説明するための図(その3)である。It is FIG. (3) for demonstrating the construction method of the building of the suspension structure of this embodiment. 本実施形態の吊構造の建物の構築方法を説明するための図(その4)である。It is FIG. (4) for demonstrating the construction method of the building of the suspension structure of this embodiment. 本実施形態の吊構造の建物の構築方法を説明するための図(その5)である。It is FIG. (5) for demonstrating the construction method of the building of the suspension structure of this embodiment. 吊柱以外の位置に梁床部材昇降装置を設置した場合の別の実施形態の吊構造建物の構築方法を説明するための図(その1)である。It is FIG. (1) for demonstrating the construction method of the suspension structure building of another embodiment at the time of installing a beam floor member raising / lowering apparatus in positions other than a suspension column. 吊柱以外の位置に梁床部材昇降装置を設置した場合の別の実施形態の吊構造建物の構築方法を説明するための図(その1)である。It is FIG. (1) for demonstrating the construction method of the suspension structure building of another embodiment at the time of installing a beam floor member raising / lowering apparatus in positions other than a suspension column.

符号の説明Explanation of symbols

10 水平部材
20 垂直部材
30 メガフレーム
40 梁床部材
50 (本設の)吊柱
60 連結部材
100 吊構造建物
110 水平部材昇降装置
111 ジャッキ
112 ロッド
113 定着部
130 梁床部材昇降装置
131 ジャッキ
132 ロッド
133 定着部
150 仮設の支持部材
152 分割された鋼管
DESCRIPTION OF SYMBOLS 10 Horizontal member 20 Vertical member 30 Mega frame 40 Beam floor member 50 (Main installation) Suspension pillar 60 Connecting member 100 Hanging structure 110 Horizontal member lifting device 111 Jack 112 Rod 113 Fixing part 130 Beam floor member lifting device 131 Jack 132 Rod 133 Fixing portion 150 Temporary support member 152 Divided steel pipe

Claims (10)

所定の階数範囲の各階の梁部材、梁床部材又は床部材(以下、梁部材等という)が、所定の高さに支持された主ビームから、当該梁部材等と同じ階及びこれより上階の本設の吊柱を介して吊下された構成を有する吊構造建物を構築する方法であって、
前記主ビームを所定の高さに支持されるように構築又は設置する主ビーム構築工程と、
地上において、前記所定の階数範囲の階の梁部材等を構築し、前記所定の階数範囲の階の梁部材等を前記本設の吊柱よりも短く、撤去可能な仮設の吊柱により連結する梁部材等連結工程と、を行い、
前記所定の階数範囲の最上階を除く少なくとも一部の階を適宜な順序で作業対象階として、
梁部材等昇降装置により前記主ビームに反力をとりながら、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの階の梁部材等を支持するとともに、前記所定の階数範囲のうちの最下階又は最下階から前記作業対象階までの階の梁部材等を支持した状態で、前記作業対象階の前記仮設の吊柱を撤去する仮設の吊柱撤去工程と、
前記梁部材等昇降装置により前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの階の前記梁部材等を前記作業対象階の階高が所定の高さになるまで上昇させる梁部材等上昇工程と、
前記作業対象階の梁部材等を、前記作業対象階の直情の階の梁部材等に本設の吊柱により接続する吊柱接続工程と、を行うことを特徴とする吊構造建物の構築方法。
A beam member, beam floor member or floor member (hereinafter referred to as a beam member, etc.) in each floor within a predetermined number of floors from the main beam supported at a predetermined height from the same floor as the beam member, etc. A method of constructing a suspended structure building having a configuration suspended via a main suspension pole of
A main beam construction step of constructing or installing the main beam to be supported at a predetermined height;
On the ground, a beam member or the like of the floor of the predetermined floor range is constructed, and the beam member or the like of the floor of the predetermined floor range is connected by a temporary suspension pillar that is shorter than the main suspension pillar and can be removed. A beam member connection process,
At least some of the floors excluding the top floor within the predetermined floor range as work floors in an appropriate order,
While supporting a beam member or the like on the floor from the uppermost floor of the predetermined floor range to the floor immediately above the work target floor while taking a reaction force on the main beam by a beam member lifting and lowering device, Temporary suspension column removal step of removing the temporary suspension column of the work target floor in a state where the beam member of the floor from the lowest floor or the lowest floor to the work target floor in the floor range is supported ,
The beam member or the like of the floor from the uppermost floor of the predetermined floor range to the floor immediately above the work target floor by the beam member lifting / lowering apparatus until the floor height of the work target floor reaches a predetermined height Ascending process of beam members to be raised,
A suspension column connecting step of connecting a beam member or the like of the work target floor to a beam member or the like of the floor of the work target floor by a main suspension column .
請求項1記載の吊構造建物の構築方法であって、
前記梁部材等昇降装置により、前記所定の階数範囲のうちの最下階の梁部材等が所定の高さになるまで、前記所定の階数範囲の全ての階の梁部材等を上昇させる最下階上昇工程と、
前記所定の階数範囲のうちの最上階の本設の吊柱を構築する最上階吊柱構築工程と、をさらに行うことを特徴とする吊構造建物の構築方法。
A construction method for a suspended structure building according to claim 1,
The lowest elevating device for raising the beam members, etc., of all the floors in the predetermined floor range until the beam members, etc. of the lowermost floor of the predetermined floor range reach a predetermined height The ascending process,
A method for constructing a suspended structure building, further comprising a top-floor suspension pillar construction step of constructing a main suspension pillar on the top floor in the predetermined floor number range.
前記最下階上昇工程は、前記梁部材等連結工程の後段に行い、
前記所定の階数範囲の最下階から上方に向かって前記作業対象階とすることを特徴とする請求項2記載の吊構造建物の構築方法。
The lowermost floor rising step is performed after the connecting step of the beam member,
The construction method for a suspended structure building according to claim 2, wherein the floor is the work target floor from the lowest floor within the predetermined floor range.
前記主ビームは、前記梁部材等の周囲に立設された支持部材により所定の高さに支持されており、
前記所定の階数範囲内の各階の前記梁部材等と前記支持部材とは、連結部材を介して接続されており、
前記吊柱構築工程では、さらに、前記作業対象階の直上の階の梁部材等と、前記支持部材とを連結部材を介して接続することを特徴とする請求項3記載の吊構造建物の構築方法。
The main beam is supported at a predetermined height by a support member erected around the beam member or the like,
The beam member and the like on each floor within the predetermined floor range and the support member are connected via a connecting member,
4. The construction of a suspended structure building according to claim 3, wherein, in the suspension pillar construction step, a beam member on a floor immediately above the work target floor and the support member are connected via a connecting member. Method.
前記梁部材等昇降装置は、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの何れかの階の梁部材等に下端が定着された吊り材と、
前記主ビームに取り付けられ、前記吊り材の上部を支持するとともに前記吊り材を昇降させることが可能な昇降機構とで構成され、
前記梁部材等上昇工程では、前記昇降機構が前記吊り材を上昇させることにより、前記作業対象階の直上の階から前記所定の階数範囲のうちの最上階までの階の梁部材等を上昇させることを特徴とする請求項1から4何れかに記載の吊構造建物の構築方法。
The beam member elevating device is a suspension member having a lower end fixed to a beam member or the like of any floor from the uppermost floor of the predetermined floor range to the floor immediately above the work target floor,
An elevating mechanism attached to the main beam and supporting an upper portion of the suspension material and capable of elevating the suspension material;
In the beam member raising step, the elevating mechanism raises the suspension member to raise the beam member or the like on the floor from the floor immediately above the work target floor to the top floor in the predetermined floor range. The construction method of a suspended structure building according to any one of claims 1 to 4.
前記梁部材等昇降装置は、前記主ビームに上端が定着された吊り材と、
前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの何れかの階の梁部材等の下側に取り付けられ、前記吊り材を支持するとともに、前記吊り材に沿って昇降可能な昇降機構と、で構成され、
前記梁部材等上昇工程では、前記昇降機構が前記吊り材に沿って上昇することにより、前記所定の階数範囲のうちの最上階から前記作業対象階の直上の階までの階の梁部材等を上昇させることを特徴とする請求項1から4何れかに記載の吊構造建物の構築方法。
The elevating device such as the beam member is a suspension member having an upper end fixed to the main beam;
Attached to the lower side of a beam member or the like of any floor from the top floor of the predetermined floor range to the floor immediately above the work target floor, and supports the suspension material, along the suspension material And an elevating mechanism capable of elevating,
In the beam member ascending step, the elevating mechanism ascends along the suspension member, so that the beam member or the like of the floor from the uppermost floor of the predetermined floor range to the floor immediately above the work target floor is It raises, The construction method of the suspension structure building in any one of Claim 1 to 4 characterized by the above-mentioned.
前記仮設の吊柱は、内部に前記吊り材を挿通可能であり、
前記梁部材等の前記仮設の吊柱が接続された部位には貫通孔が設けられており、
前記昇降装置設置工程では、前記吊り材を前記吊柱の内部及び前記梁部材等の貫通孔を貫通するように前記梁部材等昇降装置を設置することを特徴とする請求項5又は6記載の吊構造建物の構築方法。
The temporary suspension pillar is capable of inserting the suspension material therein,
A through hole is provided in a portion where the temporary suspension pillar such as the beam member is connected,
The said lifting / lowering apparatus installation process installs said lifting / lowering apparatuses, such as a beam member, so that the said suspension material may penetrate the inside of the said suspension column, and through-holes, such as the said beam member. How to build a suspended structure building.
前記昇降装置設置工程では、前記梁部材等の前記仮設の吊柱の接続された位置以外の部位に鉛直方向に並ぶように貫通孔を設け、前記吊り材を前記貫通孔を挿通するように前記吊り材を設置することを特徴とする請求項5又は6記載の吊構造建物の構築方法。   In the lifting / lowering device installation step, through holes are provided so as to be arranged in a vertical direction at a portion other than the position where the temporary suspension pillar such as the beam member is connected, and the suspension member is inserted through the through hole. The method for constructing a suspended structure building according to claim 5 or 6, wherein a suspended material is installed. 前記昇降装置設置工程では、
前記梁部材等昇降装置を、前記主ビームに反力を取りながら、前記所定の階数範囲の最上階の梁部材等を昇降させるように設置することを特徴とする請求項1から8何れかに記載の吊構造建物の構築方法。
In the lifting device installation process,
9. The beam member elevating device is installed so as to elevate and lower an uppermost beam member in the predetermined floor range while taking a reaction force on the main beam. The construction method of the suspension structure building as described.
請求項1から9何れかに記載の方法により構築されたことを特徴とする吊構造建物。   A suspended structure building constructed by the method according to claim 1.
JP2007123754A 2007-05-08 2007-05-08 Construction method for hanging structure building, and hanging structure building Pending JP2008280680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007123754A JP2008280680A (en) 2007-05-08 2007-05-08 Construction method for hanging structure building, and hanging structure building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007123754A JP2008280680A (en) 2007-05-08 2007-05-08 Construction method for hanging structure building, and hanging structure building

Publications (1)

Publication Number Publication Date
JP2008280680A true JP2008280680A (en) 2008-11-20

Family

ID=40141736

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007123754A Pending JP2008280680A (en) 2007-05-08 2007-05-08 Construction method for hanging structure building, and hanging structure building

Country Status (1)

Country Link
JP (1) JP2008280680A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06322827A (en) * 1993-05-11 1994-11-22 Shimizu Corp Super rigid-frame frame construction, and its constructing method
JPH08239906A (en) * 1995-03-03 1996-09-17 Tomoe Corp Construction of building
JP2000073573A (en) * 1998-08-31 2000-03-07 Taisei Corp Constructing method for multistoried building

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06322827A (en) * 1993-05-11 1994-11-22 Shimizu Corp Super rigid-frame frame construction, and its constructing method
JPH08239906A (en) * 1995-03-03 1996-09-17 Tomoe Corp Construction of building
JP2000073573A (en) * 1998-08-31 2000-03-07 Taisei Corp Constructing method for multistoried building

Similar Documents

Publication Publication Date Title
KR100968068B1 (en) Multi-Horizontal Structure Member Forming Method
JP6503716B2 (en) Demolition system and demolition method
KR100799360B1 (en) Slip form device for forming supporting wall in vertical tunnel
JP5200416B2 (en) Construction method of suspended structure building, suspended structure building
JP5200417B2 (en) Construction method of suspended structure building, suspended structure building
JP2008280680A (en) Construction method for hanging structure building, and hanging structure building
KR101250482B1 (en) Underground slab construction method using wire rope and curing pannel flame
JP2008280677A (en) Construction method for hanging structure building, and hanging structure building
JP2005226295A (en) Dismantling method and dismantling device for cylindrical structure
JP4816548B2 (en) How to change the height of a suspended structure building, hanging pillar
JP6438931B2 (en) Temporary column, temporary column installation structure, and roof frame construction method
JP6976887B2 (en) How to build a building
CN102535854A (en) Climbing support, climbing method thereof, concrete pavement rod and climbing method thereof
JP2008280678A (en) Construction method for hanging structure building, and hanging structure building
JP5402508B2 (en) Lift-up method, tower-like structure construction method, building construction method, lift-up device
JP6910110B2 (en) How to assemble a tower using a tower assembly jig and a mast for raising the tower assembly jig
JP6355801B2 (en) Construction method of dome-like roof structure
JP2006316409A (en) Compound steel pipe steel tower and construction method therefor
JP6159197B2 (en) Steel tower dismantling method and dismantling apparatus
JP7005262B2 (en) How to build a building
JP6971178B2 (en) How to replace work scaffolding
JP6253179B2 (en) Construction method of dome-like roof structure
JP5402509B2 (en) Lift-up method, tower-like structure construction method, building construction method
JP6967383B2 (en) How to dismantle an existing structure
JP2022089713A (en) Scattering prevention system and demolition method of existing building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100420

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120213

A131 Notification of reasons for refusal

Effective date: 20120221

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20120619