JP2008169658A - Method of connecting steel beam to reinforced concrete column - Google Patents
Method of connecting steel beam to reinforced concrete column Download PDFInfo
- Publication number
- JP2008169658A JP2008169658A JP2007005334A JP2007005334A JP2008169658A JP 2008169658 A JP2008169658 A JP 2008169658A JP 2007005334 A JP2007005334 A JP 2007005334A JP 2007005334 A JP2007005334 A JP 2007005334A JP 2008169658 A JP2008169658 A JP 2008169658A
- Authority
- JP
- Japan
- Prior art keywords
- column
- reinforced concrete
- reinforcing bar
- steel beam
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
この発明は、鉄骨梁の端部を鉄筋コンクリート製とし、鉄筋コンクリート製柱とで骨組み構造が構成される建物における前記鉄骨梁の梁への施工方法に関する。 This invention relates to the construction method to the beam of the said steel beam in the building in which the edge part of a steel beam is made from reinforced concrete, and a framework structure is comprised with a reinforced concrete pillar.
従来、鉄筋コンクリート製柱の既施工部分の上端に、鉄骨梁を設置し、その上にさらに鉄筋コンクリート柱を施工する施工方法が広く採用されている(例えば、特許文献1参照)。図8および図9は、このような施工法の一例を示している。
図8および図9は、鉄骨梁53の端部のプレキャスト鉄筋コンクリート部54を、鉄筋コンクリート製柱50の既施工柱51の上端に設置した上で、既施工柱51の上方部分にコンクリートを打設して新たな柱(上階柱)52を施工し、これを繰り返して鉄筋コンクリート製建物の骨格を構築する状態を示している。プレキャスト鉄筋コンクリート部54には梁下端主筋55および梁上端主筋56が配筋され、その一部がプレキャスト鉄筋コンクリート部54の前端部に突出している。また、既施工柱51の上端には、柱主筋51aの一部が突出している。
2. Description of the Related Art Conventionally, a construction method in which a steel beam is installed on the upper end of an already-constructed portion of a reinforced concrete column and a reinforced concrete column is further constructed thereon (see, for example, Patent Document 1). 8 and 9 show an example of such a construction method.
8 and FIG. 9, the precast reinforced
この例の場合、前記プレキャスト鉄筋コンクリート部54の前端下部に、段状のあご部54aを設け、このあご部54aを既施工柱51の上端に載せることで、鉄骨梁53の端部を既施工柱51に支持させ、この支持させた状態で上方部分の柱52の施工を行うようにしている。
また、鉄骨梁5の端部にプレキャスト鉄筋コンクリート部54を設けないものでは、鉄骨梁53の先端部分をあご部として、既施工柱51の上端に載せて上記施工を行うこともある。
Further, in the case where the precast reinforced
図8および図9に示す施工方法の場合、図9に示すように鉄筋コンクリート製柱50の中に、プレキャスト鉄筋コンクリート54の一部からなるあご部54a、または鉄骨梁53の一部が入り込んでしまう。したがって、その影響を考慮した十字型実験等が必要になり、開発に時間を要することになる。また、あご部54aの形状が複雑となり、工場でのプレキャスト化が困難となる。
In the case of the construction method shown in FIGS. 8 and 9, as shown in FIG. 9, the
この発明の目的は、鉄骨梁の端部の構造をシンプルなものとでき、工場でのプレキャスト化が容易となり、かつ低コスト化が図られる鉄骨梁の鉄筋コンクリート柱への施工方法を提供することである。
この発明の他の目的は、鉄骨梁の端部の構造をシンプルなものとでき、かつ低コスト化が図られる鉄骨梁の鉄筋コンクリート柱への施工方法を提供することである。
An object of the present invention is to provide a method for constructing a steel beam to a reinforced concrete column that can simplify the structure of the end portion of the steel beam, facilitate precasting at a factory, and reduce costs. is there.
Another object of the present invention is to provide a method of constructing a steel beam to a reinforced concrete column that can simplify the structure of the end of the steel beam and reduce the cost.
この発明の第一の発明である鉄骨梁の鉄筋コンクリート柱への施工方法は、端部がプレキャスト鉄筋コンクリート構造とされた鉄骨梁を、鉄筋コンクリート製の柱の既施工部分の上端に設置する施工方法であって、前記鉄骨梁の端部のプレキャスト鉄筋コンクリート部から梁長さ方向に鉄筋を突出させた鉄筋突出部を設け、この鉄筋突出部を前記柱の既施工部分の上端に載せることで、鉄骨梁の端部を前記柱に支持させた状態で、前記柱の前記既施工部分よりも上方の部分のコンクリートを打設することを特徴とする。
この施工方法によれば、鉄骨梁の端部のプレキャスト鉄筋コンクリート部から突出させた鉄筋突出部を鉄筋コンクリート柱の既施工部分の上端に載せることで、鉄骨梁の端部を前記鉄筋コンクリート柱に支持させ、この状態で、前記柱の前記既施工部分よりも上方の部分のコンクリートを打設する。このため、鉄骨梁の端部のプレキャスト鉄筋コンクリート部にあご部を突出させることを要さず、プレキャスト鉄筋コンクリート部の形状,構造がシンプルとなる。したがって、工場でのプレキャスト化を容易に行うことができる。また、鉄筋突出部が前記あご部に代わることになり、必要なものは鉄筋突出部だけであるため、低コスト化も図ることができる。さらに、鉄筋コンクリート柱の既施工部分に載せる部分に鉄筋を使用しているため、力学的に明解であり、商品化にも有利である。
The construction method of a steel beam on a reinforced concrete column according to the first aspect of the present invention is a construction method in which a steel beam having a precast reinforced concrete structure at the end is installed on the upper end of an already constructed part of a reinforced concrete column. By providing a reinforcing bar protruding part in which the reinforcing bar protrudes from the precast reinforced concrete part at the end of the steel beam in the beam length direction, and placing the reinforcing bar protruding part on the upper end of the existing construction part of the column, Concrete in the portion above the already-constructed portion of the column is placed with the end portion supported by the column.
According to this construction method, the end of the steel beam is supported on the reinforced concrete column by placing the reinforcing bar protruding from the precast reinforced concrete part at the end of the steel beam on the upper end of the existing construction part of the reinforced concrete column, In this state, concrete is placed in a portion above the already-constructed portion of the pillar. For this reason, it is not necessary to project a jaw part to the precast reinforced concrete part of the edge part of a steel beam, and the shape and structure of a precast reinforced concrete part become simple. Therefore, precasting at a factory can be easily performed. Moreover, since the reinforcing bar protrusion replaces the jaw part and only the reinforcing bar protrusion is required, the cost can be reduced. Furthermore, since the reinforcing bar is used for the part put on the already-constructed part of the reinforced concrete column, it is mechanically clear and advantageous for commercialization.
この発明において、前記鉄筋突出部を、前記プレキャスト鉄筋コンクリート部の梁下端主筋の一部とし、前記プレキャスト鉄筋コンクリート部から斜め下向きに突出して先端部が前記主筋からなる鉄筋突出部に接合されたトラス形成用鉄筋を設け、前記柱の前記既施工部分の上端に、アンカーを介して設置された前記鉄筋突出部を高さ調整可能に受ける鉄筋受け部材を設けても良い。
このように、プレキャスト鉄筋コンクリート部から斜め下向きに突出するトラス形成用鉄筋の先端部を梁下端主筋からなる鉄筋突出部に接合させるようにした場合は、鉄筋突出部が補強され、既施工部分よりも上方の部分のコンクリートを打設して形成される鉄筋コンクリート柱と鉄骨梁との結合一体化がより強固になされる。主筋の一部を鉄筋突出とするため、構成がより一層簡素となる。また、柱の既施工部分の上端にアンカーを介して設置された鉄筋受け部材によって、鉄筋突出部を高さ調整可能に受けることができるから、現場での状態に合わせた高さ調整等が行い易く、かつ的確になされる。
In this invention, the reinforcing bar protrusion is a part of the beam lower end main reinforcing bar of the precast reinforced concrete part, and protrudes obliquely downward from the precast reinforced concrete part, and the tip part is joined to the reinforcing bar protruding part of the main reinforcing bar. A reinforcing bar may be provided, and a reinforcing bar receiving member may be provided at the upper end of the already-executed portion of the column so as to receive the reinforcing bar protruding portion installed via an anchor so that the height can be adjusted.
In this way, when the tip of the truss-forming reinforcing bar that protrudes diagonally downward from the precast reinforced concrete part is joined to the reinforcing bar protruding part consisting of the beam bottom main reinforcing bar, the reinforcing bar protruding part is reinforced and more than the existing construction part. The combined integration of the reinforced concrete column formed by placing the concrete in the upper part and the steel beam is made stronger. Since a part of the main bar is a reinforcing bar protrusion, the configuration is further simplified. In addition, since the reinforcing bar protrusion can be received by the reinforcing bar receiving member installed at the upper end of the already installed part of the column via an anchor, the height can be adjusted according to the conditions at the site. It is easy and accurate.
また、この発明の第二の発明である鉄骨梁の鉄筋コンクリート柱への施工方法は、全体が鋼材からなる鉄骨梁を、鉄筋コンクリート製の柱の既施工部分の上端に設置する施工方法であって、前記鉄骨梁の端部から梁長さ方向に鉄筋を突出させた鉄筋突出部を設け、この鉄筋突出部を前記柱の既施工部分の上端に載せることで、鉄骨梁の端部を前記柱に支持させた状態で、前記柱の前記既施工部分よりも上方の部分と梁端部のコンクリートを打設することを特徴とする。
この施工方法は、鉄骨梁の端部がプレキャスト鉄筋コンクリート構造とされていない場合に適用される方法であり、鉄骨梁自体の端部を既施工の柱部分の上端に載せることなく、鉄筋のみによって上記と同様の施工がなされるから、構成が簡素で、施工性に優れ、低コスト化および商品化にも有利である。
Further, the construction method of the steel beam according to the second aspect of the present invention to the reinforced concrete column is a construction method in which the steel beam composed entirely of steel is installed at the upper end of the existing construction part of the column made of reinforced concrete, Reinforcing bar projecting part that protrudes the reinforcing bar in the beam length direction from the end part of the steel beam is provided, and this reinforcing bar projecting part is placed on the upper end of the already-constructed part of the column, so that the end part of the steel beam is attached to the column. In a state of being supported, concrete is placed in a portion above the already-constructed portion of the column and the concrete at the end of the beam.
This construction method is applied when the end of the steel beam is not a precast reinforced concrete structure, and the above-mentioned method is applied only by the reinforcing bar without placing the end of the steel beam itself on the upper end of the already-constructed column part. Therefore, the construction is simple, the construction is excellent, and it is advantageous for cost reduction and commercialization.
この発明における第一の発明の鉄骨梁の鉄筋コンクリート柱への施工方法は、端部がプレキャスト鉄筋コンクリート構造とされた鉄骨梁を、鉄筋コンクリート製の柱の既施工部分の上端に設置する施工方法であって、前記鉄骨梁の端部のプレキャスト鉄筋コンクリート部から梁長さ方向に鉄筋を突出させた鉄筋突出部を設け、この鉄筋突出部を前記柱の既施工部分の上端に載せることで、鉄骨梁の端部を前記柱に支持させた状態で、前記柱の前記既施工部分よりも上方の部分のコンクリートを打設するため、鉄骨梁の端部の構造がシンプルとなり、工場でのプレキャスト化が行い易く、また低コスト化も図ることができ、さらに、鉄筋を鉄骨梁の支持部に用いるから力学的に明解であり、商品化においても有利となる。 The construction method of the steel beam to the reinforced concrete column according to the first aspect of the present invention is a construction method in which the steel beam having an end portion of a precast reinforced concrete structure is installed at the upper end of the existing construction portion of the reinforced concrete column. The end of the steel beam is provided by providing a reinforcing bar protruding part in which the reinforcing bar protrudes in the beam length direction from the precast reinforced concrete part at the end of the steel beam, and placing the reinforcing bar protruding part on the upper end of the existing part of the column. With the part supported by the pillar, the concrete in the upper part of the pillar is placed and the structure of the end of the steel beam is simplified, making it easy to precast at the factory. Further, the cost can be reduced, and further, since the reinforcing bar is used for the support portion of the steel beam, it is mechanically clear and advantageous in commercialization.
この発明における第二の発明の鉄骨梁の鉄筋コンクリート柱への施工方法は、全体が鋼材からなる鉄骨梁を、鉄筋コンクリート製の柱の既施工部分の上端に設置する施工方法であって、前記鉄骨梁の端部から梁長さ方向に鉄筋を突出させた鉄筋突出部を設け、この鉄筋突出部を前記柱の既施工部分の上端に載せることで、鉄骨梁の端部を前記柱に支持させた状態で、前記柱の前記既施工部分よりも上方の部分のコンクリートを打設するため、上記と同様に、鉄骨梁の端部の構造がシンプルとなり、低コスト化も図ることができる。さらに、鉄筋を鉄骨梁の支持部に用いるから力学的に明解であり、商品化においても有利となる、などの効果が得られる。 The construction method of the steel beam according to the second aspect of the present invention for the reinforced concrete column is a construction method in which a steel beam composed entirely of steel is installed at the upper end of an already constructed part of a reinforced concrete column, wherein the steel beam The end of the steel beam was supported by the column by providing a reinforcing bar projection that protruded from the end of the beam in the beam length direction and placing the reinforcing bar projection on the upper end of the already-constructed part of the column. In this state, since the concrete in the portion above the already-constructed portion of the column is cast, the structure of the end portion of the steel beam is simplified and the cost can be reduced as described above. Furthermore, since a reinforcing bar is used for the support portion of the steel beam, it is mechanically clear and advantageous in commercialization.
この発明の鉄骨梁の鉄筋コンクリート柱への施工方法の一実施形態を、図1ないし図3と共に説明する。図1は鉄筋コンクリート製の柱1の既施工部分2の上端に、端部5がプレキャスト鉄筋コンクリート構造とされた鉄骨梁4を設置し、既施工部分の柱(以下、既施工柱と言う)2の上方部分にコンクリートを打設して上階部分の柱(以下、上階柱と言う)3を構築する状態を示している。既施工柱2の上端四隅部には、この既施工柱2内に配筋された鉄筋製柱主筋2aが突出する。この既施工柱2の上面における、鉄骨梁4が設置される側の隣合う隅部の柱主筋2a間には、既施工柱2に設けられたアンカーボルト6aを介して断面L字形の鉄筋受け部材6が設置されている。この鉄筋受け部材6はアングル材の切断片等からなり、その上下を挟むようにアンカーボルト6aに螺合された2つのナット6bにより、高さ調整可能に支持されている。アンカーボルト6aには、ホールインアンカが用いられている。このアンカーとしては、例示のようなアンカーボルト6aの他に、ケミカルアンカー等も用いても良い。
An embodiment of a method for constructing a steel beam according to the present invention on a reinforced concrete column will be described with reference to FIGS. In FIG. 1, a
鉄骨梁4は、H形鋼(もしくはI形鋼)からなり、この鉄骨梁4のプレキャスト鉄筋コンクリート構造とされた端部(以下、プレキャスト鉄筋コンクリート部と言う)5には、鉄骨梁4の下フランジ4aの下面に沿って溶接等によって固着された4本の梁下端主筋7および上フランジ4bの上面に沿って溶接等によって固着された4本の梁上端主筋8が配筋されている。この梁下端主筋7および梁上端主筋8の一部は、プレキャスト鉄筋コンクリート部5の前端部より梁長さ方向に突出する鉄筋突出部7a,8aとされている。また、プレキャスト鉄筋コンクリート部5の前端部には、斜め下向きに突出する4本のトラス形成用鉄筋9が設けられ、この4本のトラス形成用鉄筋9の先端部9aは、梁下端主筋7の各鉄筋突出部7aに溶接もしくは針金(図示せず)の巻き締めによって接合されている。このトラス形成用鉄筋9のプレキャスト鉄筋コンクリート部5に埋設された後端部9bには定着板9cが固着され、これによって、プレキャスト鉄筋コンクリート部5に対するトラス形成用鉄筋9の埋設強度の強化が図られる。
The
次に、上記のように調製された既施工柱2の上端に上記鉄骨梁4を設置し、既施工柱2の上方部分にコンクリートを打設して上階柱3を施工する方法について説明する。図1および図2に示すように、トラス形成用鉄筋9の先端部9aを接合一体とした梁下端主筋7の鉄筋突出部7aを鉄筋受け部材6上に載せ、水平面域方向の位置決めを行うと共に、前記ナット6bによって鉄筋受け部材6の高さ調整を行う。このように、既施工柱2の上端角部とプレキャスト鉄筋コンクリート部5の前端下角部とが対合するようにして仮置き支持させる。既施工柱2に対し、施工場所に応じて対向二方、あるいは三方、さらには四方に、同様にして、鉄骨梁4を仮置きする。このように鉄骨柱4の端部を既施工柱2の上端に支持させた状態で、既施工柱2の上方に上階柱3用の鉄筋(図示せず)を配筋し、その周りに型枠(図示せず)を組立て、この型枠内にコンクリートを打設する。
Next, a method for constructing the
図3は、上記方法によって構築した鉄筋コンクリート柱1と鉄骨梁4との鉄筋コンクリート構造体の縦断面図であり、既施工柱2の上端に、対向する2方向の鉄骨梁4を設置施工した場合の例を示している。対向する鉄骨梁4のプレキャスト鉄筋コンクリート部5からそれぞれ突出する梁下端主筋7の鉄筋突出部7a、梁上端主筋8の鉄筋突出部8aおよびトラス形成用鉄筋9の突出部は、鉄筋受け部材6、アンカーボルト6aおよびナット6bと共に上階柱3を構成する打設コンクリート内に埋設され、これによって、既施工柱2、対向する鉄骨梁4,4、プレキャスト鉄筋コンクリート部5,5および上階柱3が強固に一体とされた鉄筋コンクリート構造体が構成される。
なお、図3では既施工柱2内に配筋された柱主筋2a(図1,2参照)、上階柱3内に配筋された柱主筋やこれらのフープ筋等の図示を省略している。
FIG. 3 is a longitudinal sectional view of a reinforced concrete structure composed of the reinforced
In FIG. 3, the column
図4は上記実施形態の変形例における、図2と同様の図である。この例では、梁下端主筋7の鉄筋突出部7aとトラス形成用鉄筋9の先端部9aとの接合部を受ける鉄筋受け部材6が、断面倒C形(すなわち凹形)とされている。この鉄筋受け部材6は、前記L形のものに比べ、前記鉄骨梁4の仮置きの際の安定性に優れるが、これらの形状は、コストや、あるいはナット6bによる工具を用いた高さ調整の作業性等を勘案して適宜選択採用される。その他の構成は、図1ないし図3に示す例と同様であるから、共通部分に同一の符号を付し、その説明を省略する。
FIG. 4 is a view similar to FIG. 2 in a modification of the above embodiment. In this example, the reinforcing
図5は上記実施形態の他の変形例の図2と同様の図である。この例では、プレキャスト鉄筋コンクリート部5の上面に鉄骨梁4の上フランジ4bの表面が露出し、さらにプレキャスト鉄筋コンクリート部5の前端側上部に段状切欠部5aを有し、この切欠部5aに上フランジ4bおよびウエブ4cの一部が露出するよう構成されている。この例では、プレキャスト鉄筋コンクリート部5には上記のような梁上端主筋8はなく、これに代え、既施工柱2の上方部分にコンクリートを打設する際の配筋および型枠の組み立て時に、段状切欠部5aの上に別の鉄筋10を載せ、鉄筋10の一部が既施工柱2の上方に位置するよう他の図示しない鉄筋と共に配筋する。型枠の組み立ては、段状切欠部5aによる空間部分にもコンクリートが打設されるようになされる。コンクリートの打設施工後の構造体においては、段状切欠部5aに打設されたコンクリートとこの部分に配筋された鉄筋10との鉄筋コンクリート構造と、上記同様の梁下端主筋7の鉄筋突出部7aおよびトラス形成用鉄筋9の突出部とコンクリートとの一体化による鉄筋コンクリート構造との相乗効果によって、強固な構造体が得られる。その他の構成は、図1ないし図3に示す例と同様であるから、共通部分に同一の符号を付し、ここでもその説明を省略する。
FIG. 5 is a view similar to FIG. 2 of another modification of the above embodiment. In this example, the surface of the
図6および図7は、第2の実施形態を示す。この実施形態では、鉄骨梁4の全体がH形鋼(I形鋼)からなる場合、すなわち鉄骨梁4の端部がプレキャスト鉄筋コンクリート構造とされていない場合の実施形態である。鉄骨梁4の端部から梁長さ方向に突出する鉄筋突出部11aを備えた鉄筋11が、鉄骨梁4の下フランジ4aの上面にその基端部11bをして溶接等により固着されている。また、鉄骨梁4の上フランジ4bの下面に基端部12bをして溶接等により固着され、鉄骨梁4の端部より斜め下向きに突出して先端部12aが上記鉄筋突出部11aに接合されたトラス形成用鉄筋12が設けられている。既施工柱2の上端には、アンカーボルト6aおよび2つのナット2bを介して、断面倒C形(凹形)の鉄筋受け部材6が高さ調整可能に設けられている。この鉄筋受け部材6は、図2と同様に断面L形状のものであっても良い。
6 and 7 show a second embodiment. In this embodiment, the
上記鉄骨梁4の既施工柱2への施工に際し、先ず上記鉄筋受け部材6の上に、接合された鉄筋11の鉄筋突出部11aおよびトラス形成用鉄筋12の先端部12aを載せ、水平面域方向の位置決めと鉄筋受け部材6の高さ調整を行い、鉄骨梁4を既施工柱2の上端に仮置き支持させる。次いで、鉄骨梁4の端部に梁端鉄筋コンクリート部3A(図7参照)を形成するための配筋を行う。図6および図7ではこの配筋を構成する主鉄筋13の一部を図示し、フープ筋等の図示は省略している。また、上階柱用の配筋(図示せず)も行い、これら配筋周りに型枠(図示せず)を組み立て、型枠内にコンクリートを打設する。
When the
図7は、上記方法によって構築した鉄筋コンクリート柱1と鉄骨梁4との鉄筋コンクリート構造体の縦断面図であり、既施工柱2の上端に、対向する2方向の鉄骨梁4を設置する場合の例を示している。図示するように、対向する鉄骨梁4の端部からそれぞれ突出する鉄筋11の鉄筋突出部11a、トラス形成用鉄筋12の突出部および鉄骨梁4の端部の所定の範囲部分は、鉄筋受け部材6、アンカーボルト6aおよびナット6bと共に上階柱3および梁端鉄筋コンクリート部3Aを構成する打設コンクリート内に埋設され、これによって、既施工柱2、対向する鉄骨梁4,4および上階柱3が強固に一体とされた鉄筋コンクリート構造体が構成される。
FIG. 7 is a longitudinal sectional view of a reinforced concrete structure composed of a reinforced
上記いずれの実施形態においても、既施工柱2の上端に対する鉄骨梁4の設置部分には、前述のようなコンクリートや鉄骨によるあご部が存在しないから、鉄骨梁4の梁端部分の形状がシンプルであり、工場でのプレキャスト化が非常に容易となる。また、柱の中に鉄骨の一部や鉄筋コンクリートの一部が入り込むことによる影響を考慮した十字型実験等が不要とされ、開発時間の短縮が図られる。さらに、上記各鉄筋が鉄骨梁4を既施工柱2の上端に支持し、その設置部分を担うことになるから、コストがかからず、力学的に明解であって商品化も行い易く、構造体の強度も十分に確保される。
In any of the above-described embodiments, since the
なお、図3および図7では、対向する2方向の鉄骨梁4を柱1に施工する例を示しているが、施工される柱の種類(側柱、隅柱、間柱等)に応じた鉄骨梁4の他の施工態様にもこの発明を適用することができる。また、上階柱の鉄筋の配筋施工は、施工階毎に行っても良く、あるいは、複数階分を通しで施工しても良いが、この発明では鉄筋コンクリート柱1のコンクリートの打設は各階の施工毎に行う。さらに、上記の実施形態では、いずれもトラス形成用鉄筋9,12を設けた例を示したが、強度が十分に得られる場合はこれを省略してもよい。
3 and 7 show an example in which the opposite two-
1…鉄筋コンクリート製の柱
2…既施工柱(鉄筋コンクリート製の柱の既施工部分)
3…上階柱(既施工部分よりも上方の部分)
4…鉄骨梁
5…プレキャスト鉄筋コンクリート部(鉄骨梁の端部)
6…鉄筋受け部材
6a…アンカーボルト(アンカー)
7…梁下端主筋(鉄筋)
7a…鉄筋突出部
9…トラス形成用鉄筋
9a…先端部
11…鉄筋
11a…鉄筋突出部
1 ... Columns made of reinforced
3 ... Upper column (upper part of the existing construction)
4 ...
6 ... Reinforcing
7 ... Beam bottom bar (rebar)
7a ... Reinforcing
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007005334A JP2008169658A (en) | 2007-01-15 | 2007-01-15 | Method of connecting steel beam to reinforced concrete column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007005334A JP2008169658A (en) | 2007-01-15 | 2007-01-15 | Method of connecting steel beam to reinforced concrete column |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2008169658A true JP2008169658A (en) | 2008-07-24 |
Family
ID=39698000
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007005334A Pending JP2008169658A (en) | 2007-01-15 | 2007-01-15 | Method of connecting steel beam to reinforced concrete column |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2008169658A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101743509B1 (en) * | 2016-12-26 | 2017-06-07 | 주식회사 더빔 | Rahmen bridge with temporary hinge structure reinforced seismic capability and the con struction method therefor |
-
2007
- 2007-01-15 JP JP2007005334A patent/JP2008169658A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101743509B1 (en) * | 2016-12-26 | 2017-06-07 | 주식회사 더빔 | Rahmen bridge with temporary hinge structure reinforced seismic capability and the con struction method therefor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20210003315A (en) | Column form system using deckplate form | |
JP2006283333A (en) | Construction method of reinforced concrete column/steel beam building | |
JP2001342679A (en) | CONNECTING METHOD FOR PCa BEAM MEMBER AT COLUMN/BEAM JUNCTION AND PCa BEAM MEMBER FOR IT | |
JP7449685B2 (en) | Precast concrete shear wall joint structure | |
JP4577004B2 (en) | Construction method for building frames consisting of steel-concrete composite beams and SRC columns | |
JP6574336B2 (en) | Steel-framed reinforced concrete columns and buildings using the same | |
KR100759041B1 (en) | Link structure for steel beam and column of building and methods using the same | |
JP4657993B2 (en) | Beam-column joint structure and construction method thereof | |
JP2011089390A (en) | Rigid connection structure of corner section | |
JP2008169658A (en) | Method of connecting steel beam to reinforced concrete column | |
KR101954387B1 (en) | Grid precast concrete structure and constructing method thereof | |
JP4841446B2 (en) | Construction method for steel beam columns with RC beam ends | |
JP5870455B2 (en) | Precast concrete wall and joint structure between column and beam | |
JP2018123644A (en) | Junction structure of precast concrete member | |
JP2758208B2 (en) | Joint method between column and steel reinforced concrete beam | |
JP2007154565A (en) | Joint structure and construction method of column and beam-less slab | |
JP2020063634A (en) | Junction structure and junction method for precast concrete beam member | |
JP2006169837A (en) | Column-beam joint structure of reinforced concrete construction | |
JP2003041516A (en) | Integral structure of upper and lower parts of continuous girder bridge and method of constructing it | |
JPH09177240A (en) | Precast ferro-concrete beam and its installing method | |
JP2019085780A (en) | Joint structure of precast concrete beam member and joining method | |
JP2006188881A (en) | Joint structure of beam and floor board | |
JP2004218288A (en) | Seismic-response controlled structure of structure, and mounting method for seismic-response controlled device | |
KR102349442B1 (en) | Coupling structure of column and girder having single girder in lateral direction, double girder in backward direction and concrete part around the column | |
JP6380507B2 (en) | Structure and construction method of structure |