JP2008144571A - Fixture for placing reinforcement - Google Patents

Fixture for placing reinforcement Download PDF

Info

Publication number
JP2008144571A
JP2008144571A JP2007205419A JP2007205419A JP2008144571A JP 2008144571 A JP2008144571 A JP 2008144571A JP 2007205419 A JP2007205419 A JP 2007205419A JP 2007205419 A JP2007205419 A JP 2007205419A JP 2008144571 A JP2008144571 A JP 2008144571A
Authority
JP
Japan
Prior art keywords
hook
bar
bar arrangement
main rope
reference body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2007205419A
Other languages
Japanese (ja)
Other versions
JP4947464B2 (en
Inventor
Ron Taki
論 瀧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2007205419A priority Critical patent/JP4947464B2/en
Publication of JP2008144571A publication Critical patent/JP2008144571A/en
Application granted granted Critical
Publication of JP4947464B2 publication Critical patent/JP4947464B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a fixture for placing reinforcements which can be carried easily and does not require a worker to hold a vertical reinforcement and a horizontal reinforcement or a main reinforcement and a hoop in the case of either placing the horizontal reinforcement on the vertical reinforcement or placing the hoop on the main reinforcement and easily carried. <P>SOLUTION: The fixture for placing reinforcements comprises a main rope suspended from an existing structure and a plurality of hooks provided on the main rope 2 for holding reinforcements in the direction crossing the main rope when the main rope is suspended from the existing structure 2. The main rope 2 is constructed to be flexible to allow any one of the hooks to move, in the vertical direction, out of the region where the other hook right above the one hook itself is located in the state of suspending the rope 2 from the existing structure. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、横筋の結束作業、あるいはフープ筋の結束作業に有用な配筋用治具に関するものである。   The present invention relates to a bar arrangement jig useful for bundling of horizontal bars or bundling of hoops.

従来、縦筋に横筋を配筋する場合には、作業員が縦筋と横筋とを把持した状態で、縦筋と横筋とを番線(針金)により結束しなければならかった。また、主筋にフープ筋を配筋する場合にも、作業員が主筋とフープ筋とを把持した状態で、主筋とフープ筋とを番線により結束しなければならなかった。このように、縦筋に横筋を配筋する場合、あるいは、主筋にフープ筋を配筋する場合には、鉄筋(横筋あるいはフープ筋)把持のためだけに相番作業員が必要となることがあった。   Conventionally, when placing a horizontal bar in the vertical bar, it has been necessary to bind the vertical bar and the horizontal bar with a wire (wire) while the worker holds the vertical bar and the horizontal bar. Also, when hoop muscles are arranged in the main muscle, the main muscle and the hoop muscle have to be tied together with a wire number while the operator holds the main muscle and the hoop muscle. As described above, when the horizontal bars are arranged in the vertical bars, or when the hoops are arranged in the main bars, it may be necessary to have a worker who only needs to hold the reinforcing bars (the horizontal bars or the hoop bars). there were.

縦筋に横筋を結束する作業、主筋にフープ筋を結束する作業を容易なものとし、横筋あるいはフープ筋の把持のためだけに相番作業員が必要となる事態を解消するために、以下に示すような配筋用治具が提案されている。   In order to facilitate the work of binding the horizontal muscle to the vertical muscle and the work of binding the hoop muscle to the main muscle, and to eliminate the situation where a number of workers are required only for gripping the horizontal or hoop muscle, A bar arrangement jig as shown is proposed.

横筋を保持するアームを所定間隔ごとに固定したコンクリート打設用鉄筋が提案されている。このコンクリート打設用鉄筋は、既設の横筋に吊り下げた状態で、アームに鉄筋を保持可能となっている。したがって、このコンクリート打設用鉄筋を用いれば、縦筋に横筋を配筋する場合であっても、作業員が縦筋と横筋とを把持する必要がない。このコンクリート打設用鉄筋は、アームが鉤型形状を有するものであって、コンクリート打設用鉄筋に固定されている(例えば、特許文献1参照)。   There has been proposed a concrete placement reinforcing bar in which arms for holding horizontal bars are fixed at predetermined intervals. The concrete placing reinforcing bar can hold the reinforcing bar on the arm in a state where it is suspended from the existing horizontal reinforcing bar. Therefore, if this concrete placement reinforcing bar is used, even if the horizontal bar is arranged in the vertical bar, the operator does not need to hold the vertical bar and the horizontal bar. In this concrete placement reinforcing bar, the arm has a saddle shape, and is fixed to the concrete placement reinforcing bar (see, for example, Patent Document 1).

しかしながら、特許文献1に記載されたコンクリート打設用鉄筋は、既設の横筋に吊り下げた後に、別途横筋を保持させると、それ以降は、保持した横筋により拘束されるので、既設の横筋を支点として一体となって回動することしかできない。したがって、真っ直ぐな横筋を複数保持させることはできても、一端と他端とを接続したフープ筋を複数保持させることができなかった。   However, the concrete placement reinforcing bar described in Patent Document 1 is suspended by the existing horizontal bars and then held separately. After that, the concrete horizontal bars are restrained by the held horizontal bars. Can only be rotated together. Therefore, even if a plurality of straight transverse lines can be held, a plurality of hoop lines connecting one end and the other end cannot be held.

一方、所定間隔ごとに横筋を保持するストッパを回動可能に取り付けた補助バーが提案されている。この補助バーは、上述したコンクリート打設用鉄筋と同様に、既設の横筋に吊り下げた状態で、横筋が保持可能となっている。したがって、この補助バーを用いれば、縦筋に横筋を配筋する場合であっても作業員が縦筋と横筋とを把持する必要がなく、また、主筋にフープ筋を配筋する場合であってもストッパが回動するので補助バーに新たにフープ筋を保持させることができ、作業員が主筋とフープ筋とを把持する必要がない(例えば、特許文献2参照)。   On the other hand, an auxiliary bar has been proposed in which a stopper for holding a horizontal stripe is attached to be rotatable at predetermined intervals. The auxiliary bar can hold the horizontal bar in a state where it is suspended from the existing horizontal bar, in the same manner as the concrete placing reinforcing bar described above. Therefore, when this auxiliary bar is used, it is not necessary for an operator to hold the vertical and horizontal muscles even when the horizontal muscles are arranged in the vertical muscles, and the hoop muscles are arranged in the main muscles. However, since the stopper rotates, the auxiliary bar can newly hold the hoop muscle, and the operator does not need to grasp the main muscle and the hoop muscle (for example, see Patent Document 2).

特開2001−115600号公報JP 2001-115600 A 特開平8−218637号公報JP-A-8-218637

しかしながら、特許文献2に記載された補助バーは、所定間隔ごとに横筋を保持するストッパを回動可能に取り付けた長尺な部材であって、持ち運びが不便であった。   However, the auxiliary bar described in Patent Document 2 is a long member to which a stopper that holds the horizontal stripe is rotatably attached at every predetermined interval, and is inconvenient to carry.

本発明は、上記に鑑みてなされたものであって、縦筋に横筋を配筋する場合、主筋にフープ筋を配筋する場合のいずれの場合であっても作業員が縦筋と横筋あるいは主筋とフープ筋を把持する必要がなく、しかも持ち運びが容易な配筋用治具を提供することを目的とする。   The present invention has been made in view of the above, and in the case where the horizontal muscle is arranged in the vertical muscle, or in the case where the hoop muscle is arranged in the main muscle, the worker can An object of the present invention is to provide a bar arrangement jig that does not need to hold a main bar and a hoop bar and is easy to carry.

上述した課題を解決し、目的を達成するために、本発明の請求項1に係る配筋用治具は、既設の構造物に吊り下げられる基準体と、該基準体に複数設けられ、既設の構造物に基準体が吊り下げられた場合に、該基準体と交差する方向に鉄筋をそれぞれ保持する鉤状のフックとを備えた配筋用治具であって、前記既設の構造物に吊り下げた状態において、複数のフックのそれぞれが自身の直上に位置するものの鉛直下方域外に移動できるように、前記基準体を曲折可能に構成したことを特徴とする。   In order to solve the above-described problems and achieve the object, a bar arrangement jig according to claim 1 of the present invention is provided with a reference body that is suspended from an existing structure, and a plurality of reference bodies are provided on the reference body. When the reference body is hung from the structure, the bar arrangement jig includes hook-shaped hooks each holding a reinforcing bar in a direction crossing the reference body, and the existing structure In the suspended state, the reference body is configured to be bendable so that each of the plurality of hooks can be moved out of the vertically lower region although it is located directly above itself.

また、本発明の請求項2に係る配筋用治具は、上記請求項1において、既設の構造物と前記基準体とを接続する吊下具を備えたことを特徴とする。   According to a second aspect of the present invention, the reinforcing bar arrangement jig according to the first aspect further includes a hanging tool for connecting the existing structure and the reference body.

また、本発明の請求項3に係る配筋用治具は、上記請求項2において、前記吊下具は、既設の構造物と前記基準体との間隔を調整する調整手段を備えたことを特徴とする。   Further, in the bar arrangement jig according to claim 3 of the present invention, in the above-mentioned claim 2, the hanging tool includes an adjusting means for adjusting an interval between the existing structure and the reference body. Features.

また、本発明の請求項4に係る配筋用治具は、上記請求項1〜3のいずれか一つにおいて、前記基準体に上部と下部とを接合することにより、該上部と該下部との間に挿通部を構成するパッチを備え、前記フックを前記挿通部に挿通することにより、前記基準体に前記フックを取り付けたことを特徴とする。   According to a fourth aspect of the present invention, in the bar arrangement jig according to any one of the first to third aspects, the upper portion and the lower portion are joined by joining the upper portion and the lower portion to the reference body. And a patch constituting an insertion portion, and the hook is attached to the reference body by inserting the hook into the insertion portion.

また、本発明の請求項5に係る配筋用治具は、上記請求項4において、前記基準体の断面が扁平であって、一の面には複数の鉄筋を保持した場合に鉄筋相互間の間隔が第一の間隔となるように複数のパッチが接合してあり、他の面には複数の鉄筋を保持した場合に鉄筋相互間の間隔が第二の間隔となるように複数のパッチが接合してあることを特徴とする。   According to a fifth aspect of the present invention, there is provided a bar arrangement jig according to the fourth aspect, wherein the reference body has a flat cross section and a plurality of reinforcing bars are held on one surface. A plurality of patches are bonded so that the interval between the reinforcing bars is the first interval, and when a plurality of reinforcing bars are held on the other surface, the plurality of patches are set so that the interval between the reinforcing bars becomes the second interval. Are joined.

また、本発明の請求項6に係る配筋用治具は、上記請求項4において、前記基準体と前記パッチとは、一方に突起を有し、他方にパイル状のループを有した面ファスナーにより接合されたことを特徴とする。   According to claim 6 of the present invention, the jig for bar arrangement according to claim 4 is characterized in that the reference body and the patch have protrusions on one side and pile loops on the other side. It is characterized by being joined by.

また、本発明の請求項7に係る配筋用治具は、上記請求項1において、前記基準体は、一端に環状の吊下部を有するとともに、他端に環状の連結部を有したことを特徴とする。   In the bar arrangement jig according to claim 7 of the present invention, in the above-mentioned claim 1, the reference body has an annular hanging portion at one end and an annular connecting portion at the other end. Features.

また、本発明の請求項8に係る配筋用治具は、上記請求項2において、前記吊下具は、開閉可能であって、閉塞した状態を維持可能な対となる金具で構成したことを特徴とする。   Further, in the bar arrangement jig according to claim 8 of the present invention, in the above-mentioned claim 2, the hanging tool is configured by a pair of metal fittings that can be opened and closed and can maintain a closed state. It is characterized by.

本発明に係る配筋用治具は、既設の構造物に吊り下げられる基準体と、基準体に複数設けられ、既設の構造物に基準体が吊り下げられた場合に、基準体と交差する方向に鉄筋をそれぞれ保持する鉤状のフックとを備えたので、作業員が縦筋と横筋とを把持することなく、縦筋に横筋を結束することができる。また、本発明に係る配筋用治具は、既設の構造物に吊り下げた場合において、複数のフックのそれぞれが自身の直上に位置するものの鉛直下方域外に移動できるように、基準体を曲折可能に構成したので、本発明に係る配筋用治具を用いれば、曲折部が曲折することにより、新たに保持されるフープ筋はフックを回避した後に、フックに保持される。したがって、作業員が主筋とフープ筋とを把持することなく、主筋にフープ筋を結束することができる。しかも、本発明に係る配筋用治具を任意の位置で折り畳むことにより、持ち運びも容易となる。   The bar arrangement jig according to the present invention is provided with a reference body that is suspended from an existing structure and a plurality of reference bodies, and intersects the reference body when the reference body is suspended from the existing structure. Since the hook-like hooks that respectively hold the reinforcing bars are provided in the direction, the operator can bind the horizontal bars to the vertical bars without holding the vertical bars and the horizontal bars. In addition, the bar arrangement jig according to the present invention bends the reference body so that when it is suspended from an existing structure, each of the plurality of hooks can be moved out of the vertical downward region, although it is located directly above itself. Since it has been configured to be possible, if the bending tool according to the present invention is used, the bent portion is bent so that the newly held hoop muscle is held by the hook after avoiding the hook. Therefore, the operator can bind the hoop muscles to the main muscles without grasping the main muscles and the hoop muscles. Moreover, by folding the bar arrangement jig according to the present invention at an arbitrary position, it is easy to carry.

以下に、本発明に係る配筋用治具の実施例を図面に基づいて詳細に説明する。なお、この実施例によりこの発明が限定されるものではない。   Below, the Example of the jig for bar arrangement concerning this invention is described in detail based on drawing. Note that the present invention is not limited to the embodiments.

(実施の形態1)
図1は本発明の実施の形態1に係る配筋用治具を示す正面図、図2は図1に示した配筋用治具を示す側面図、図3は図1に示したフック及びパッチを示す拡大正面図、図4は図1に示したフック及びパッチを示す拡大側面図、図5は既に張架された横筋に本発明の実施の形態1に係る配筋用治具を吊り下げた状態を示す斜視図である。
(Embodiment 1)
1 is a front view showing a bar arrangement jig according to Embodiment 1 of the present invention, FIG. 2 is a side view showing the bar arrangement jig shown in FIG. 1, and FIG. Fig. 4 is an enlarged front view showing the patch, Fig. 4 is an enlarged side view showing the hook and patch shown in Fig. 1, and Fig. 5 is a hanging bar arrangement jig according to the first embodiment of the present invention on the already stretched horizontal stripe. It is a perspective view which shows the state lowered | hung.

本発明の実施の形態1に係る配筋用治具は、縦筋に横筋を結束する場合、及び主筋にフープ筋を結束する場合に用いられる治具であって、既設の構造物に吊り下げた状態で所定の間隔で横筋あるいはフープ筋を保持可能となっている。既設の構造物は、例えば、既に張架された横筋、既に張架された鉄骨梁、既に敷設された上階床、あるいは、既に主筋に結束されたフープ筋である。   The bar arrangement jig according to the first embodiment of the present invention is a jig used when binding horizontal bars to vertical bars and binding hoop bars to main bars, and is suspended from an existing structure. In this state, the horizontal stripes or the hoop stripes can be held at predetermined intervals. The existing structures are, for example, already stretched horizontal bars, already stretched steel beams, already laid upper floors, or hoop bars already bound to the main bars.

配筋用治具1は、メインロープ2、吊下具3、フック4を備えている。メインロープ2は、既設の構造物に吊り下げ可能であって、既設の構造物に吊り下げた場合に、鉄筋(横筋あるいはフープ筋)の配筋基準をなす基準体を構成する。メインロープ2は、既設の構造物に吊り下げた状態において、複数のフック4のそれぞれが自身(フック4)の直上に位置するもの(フック4)の鉛直下方域外に移動できるように、曲折可能に構成したものであって、具体的には、任意の位置で曲折可能な柔軟性を有するベルトスリングと称される繊維製の帯状部材により構成してある。   The bar arrangement jig 1 includes a main rope 2, a hanging tool 3, and a hook 4. The main rope 2 can be hung from an existing structure, and constitutes a reference body that serves as a bar arrangement reference for reinforcing bars (horizontal bars or hoop bars) when the main rope 2 is hung from an existing structure. The main rope 2 can be bent so that each of the plurality of hooks 4 can be moved out of the vertically lower area of the hook (hook 4) when it is suspended from an existing structure (hook 4). Specifically, it is constituted by a belt-like member made of fiber called a belt sling having flexibility that can be bent at an arbitrary position.

図1及び図2に示すように、メインロープ2は、断面が扁平であって、表面と裏面の二つの面を有している。そして、図5に示すように、メインロープ2の一端は、折り返して自身(メインロープ2)に縫合してあり、当該部分は環状となった吊下部2aを構成している。なお、吊下部2aは、メインロープ2の一端を折り返して自身(メインロープ)に織り込むことにより構成しても良い。   As shown in FIGS. 1 and 2, the main rope 2 has a flat cross section and has two surfaces, a front surface and a back surface. As shown in FIG. 5, one end of the main rope 2 is folded back and sewn to itself (the main rope 2), and this portion constitutes a suspended portion 2a that is annular. The suspended portion 2a may be configured by folding one end of the main rope 2 and weaving it into the main rope (main rope).

図1及び図2並びに図5に示すように、この環状となった吊下部2aには、吊下具3が装着してある。吊下具3は、メインロープ2を既設の構造物に吊り下げるためのもので、ターンバックル(調整手段)31とシャックル32とを組み合わせて構成してある。ターンバックル31は、長さ調整が可能な掛け金具であって、一端に左ネジを形成し他端に右ネジを形成した枠体31a、端部が鉤状のフックボルト31b、端部が環状のリングボルト31cから構成されている。シャックル32は、長さ調整が不能な掛け金具であって、U字型のクラウン32aと、クラウン32aの一端を貫通しクラウン32aの他端に螺合するボルト32bとから構成されている。そして、吊下具3は、ターンバックル31のリングにシャックル32のボルト32bを挿通することにより組み合わされて構成され、メインロープ2の吊下部2aにシャックル32のクラウン32aを挿通することにより、メインロープ2の吊下部2aに吊下具3が装着されている。   As shown in FIGS. 1, 2, and 5, a hanging tool 3 is attached to the annular hanging portion 2 a. The hanging tool 3 is used to suspend the main rope 2 from an existing structure, and is configured by combining a turnbuckle (adjusting means) 31 and a shackle 32. The turnbuckle 31 is a metal fitting that can be adjusted in length. A frame 31a is formed with a left-hand thread at one end and a right-hand thread at the other end, a hook-shaped hook bolt 31b at the end, and an annular end. Ring bolt 31c. The shackle 32 is a hook that cannot be adjusted in length, and includes a U-shaped crown 32a and a bolt 32b that passes through one end of the crown 32a and is screwed into the other end of the crown 32a. The hanging tool 3 is configured by being inserted into the ring of the turnbuckle 31 by inserting the bolt 32b of the shackle 32, and by inserting the crown 32a of the shackle 32 into the hanging part 2a of the main rope 2, A hanging tool 3 is attached to the hanging portion 2 a of the rope 2.

また、メインロープ2の一方の面(以下、この一方の面を表面とする)には、複数の鉄筋を保持した場合に鉄筋相互間の間隔が第一の間隔(例えば、100ミリ間隔)となるように、複数のパッチ21が縫合してあり、メインロープ2の他方の面(以下、この他方の面を裏面とする)には、複数の鉄筋を保持した場合に鉄筋相互間の間隔が第二の間隔(例えば、150ミリ間隔)となるように、複数のパッチ21が縫合してある。図3及び図4に示すように、パッチ21は、メインロープ2にフック4を取り付けるためのもので、メインロープ2よりも薄い柔軟な繊維製の帯状部材により構成してある。パッチ21は、断面が扁平であって、メインロープ2とパッチ21との間にフック4が挿通するためのたるみを有するように、上部と下部とをメインロープ2に縫合してある。このため、メインロープ2とパッチ21との間であって、パッチ21の上部と下部との間には、フック4が挿通する挿通部22が形成される。   Further, on one surface of the main rope 2 (hereinafter, this one surface is referred to as the surface), when a plurality of reinforcing bars are held, the interval between the reinforcing bars is a first interval (for example, an interval of 100 mm). The plurality of patches 21 are stitched so that the other surface of the main rope 2 (hereinafter, the other surface is referred to as the back surface) has a space between the reinforcing bars when the plurality of reinforcing bars are held. The plurality of patches 21 are stitched so as to be the second interval (for example, 150 mm interval). As shown in FIGS. 3 and 4, the patch 21 is for attaching the hook 4 to the main rope 2, and is constituted by a strip member made of a flexible fiber thinner than the main rope 2. The patch 21 has a flat cross section, and an upper portion and a lower portion are sewn to the main rope 2 so as to have a slack for the hook 4 to be inserted between the main rope 2 and the patch 21. For this reason, an insertion portion 22 through which the hook 4 is inserted is formed between the main rope 2 and the patch 21 and between the upper portion and the lower portion of the patch 21.

メインロープ2の表面と裏面のうち、配筋する鉄筋(横筋あるいはフープ筋)と鉄筋との間隔(配筋間隔)に合致する間隔(第一の間隔あるいは第二の間隔)でパッチ21が縫合してある面には、フック4が取り付けてある。即ち、配筋間隔が第一の間隔(例えば、100ミリ間隔)の場合には、メインロープ2の表面にフック4が取り付けてあり、配筋間隔が第二の間隔(例えば、150ミリ間隔)の場合には、メインロープ2の裏面にフック4が取り付けてある。   Of the front and back surfaces of the main rope 2, the patch 21 is sewn at an interval (first interval or second interval) that matches the interval between the reinforcing bars (horizontal bars or hoop bars) and the reinforcing bars. The hook 4 is attached to the surface. That is, when the bar arrangement interval is the first interval (for example, 100 mm interval), the hook 4 is attached to the surface of the main rope 2, and the bar arrangement interval is the second interval (for example, 150 mm interval). In this case, the hook 4 is attached to the back surface of the main rope 2.

フック4は、メインロープ2が既設の構造物に吊り下げられた場合に、メインロープ2と交差する方向に鉄筋(横筋あるいはフープ筋)をそれぞれ保持するものであって、側面視鉤状を呈している。フック4は、丸棒状の鋼材を折り曲げることにより構成したものであり、軸部41、一対となる脚部42及び一対となるフック部43を有している。軸部41は、上述したメインロープ2とパッチ21との間に形成された挿通部22に挿通する部分であって、図3に示すように、少なくともパッチ21よりも幅広となるように形成してある。一対の脚部42は、軸部41の一端と他端とからそれぞれ中央に向けて傾斜するように延在しており、その先端は、上述したパッチ21の厚みよりも広くなるように形成してある。したがって、脚部42の先端が交差しないものの、上述した軸部41とともに二等辺三角形の形状を呈することになる。一対のフック部43は、所定の間隔を維持したまま所定の径を有するように脚部から手前側に延在させた後、斜め上方に略135度折り返すことにより、開角αが略45度となるように形成してある。尚、フック部43の形状は、鉄筋(横筋、フープ筋)を保持可能な範囲で所定の径を小さなものとし、開角αを鋭角なものとすることが望ましいが、折返し角度は略135度に限られるものではなく、配筋途上の鉄筋(横筋、フープ筋)がフック4とメインロープ2との間に引っ掛かりにくいものであれば、略180度折り返して形成し、開角を0度としても良い。   When the main rope 2 is suspended from an existing structure, the hook 4 holds a reinforcing bar (lateral or hoop) in a direction intersecting with the main rope 2 and has a saddle shape in side view. ing. The hook 4 is configured by bending a round bar-shaped steel material, and includes a shaft portion 41, a pair of leg portions 42, and a pair of hook portions 43. The shaft portion 41 is a portion that is inserted into the insertion portion 22 formed between the main rope 2 and the patch 21 described above, and is formed to be at least wider than the patch 21 as shown in FIG. It is. The pair of leg portions 42 extend from the one end and the other end of the shaft portion 41 so as to incline toward the center, and the tips thereof are formed to be wider than the thickness of the patch 21 described above. It is. Therefore, although the tips of the leg portions 42 do not intersect, the shape of the isosceles triangle is exhibited together with the shaft portion 41 described above. The pair of hook portions 43 are extended from the leg portions to the near side so as to have a predetermined diameter while maintaining a predetermined distance, and then folded back approximately 135 degrees obliquely upward, so that the opening angle α is approximately 45 degrees. It is formed so that The hook portion 43 preferably has a small diameter within a range that can hold a reinforcing bar (horizontal bar, hoop bar) and an open angle α, but the turn-back angle is approximately 135 degrees. If the reinforcing bars (horizontal bars, hoop bars) are not easily caught between the hook 4 and the main rope 2, they are formed by folding back approximately 180 degrees and the opening angle is set to 0 degrees. Also good.

このように構成したフック4は、フック部43、脚部42、軸部41の順に挿通部22に挿通させることにより、挿通部22に軸部41が挿通し、メインロープ2にフック4が回動可能に取り付けられる。   The hook 4 configured in this manner is inserted through the insertion portion 22 in the order of the hook portion 43, the leg portion 42, and the shaft portion 41, so that the shaft portion 41 is inserted into the insertion portion 22 and the hook 4 is rotated around the main rope 2. Mounted movably.

上述した実施の形態1では、吊下具3にターンバックル31とシャックル32とを組み合わせたものを採用したが、必ずしもターンバックル31とシャックル32とを組み合わせたものでなくても良く、ターンバックルのみで構成しても良いし、シャックルのみで構成しても良い。   In the first embodiment described above, a combination of the turnbuckle 31 and the shackle 32 is used for the hanging tool 3, but the combination of the turnbuckle 31 and the shackle 32 is not necessarily required, and only the turnbuckle is used. You may comprise by only a shackle.

また、上述した実施の形態1では、メインロープ2にパッチ21を縫合したが、一方に突起を有し他方にパイル状のループを有した面ファスナーにより、メインロープ2とパッチ21とを接合しても良い。このように、メインロープ2とパッチ21とを面ファスナーにより接合すれば、任意の配筋間隔に合わせてフック4を取り付けることができる。   In the first embodiment described above, the patch 21 is stitched to the main rope 2, but the main rope 2 and the patch 21 are joined by a hook-and-loop fastener having a protrusion on one side and a pile-like loop on the other side. May be. Thus, if the main rope 2 and the patch 21 are joined by the hook-and-loop fastener, the hook 4 can be attached in accordance with an arbitrary bar arrangement interval.

次に、図6に基づいて、本発明の実施の形態1に係る配筋用治具1を用いた横筋Yの配筋作業を説明する。図6は、既に張架された鉄骨梁に本発明の実施の形態1に係る配筋用治具を吊り下げた状態を示す説明図である。図6に示す配筋作業は、既に張架された鉄骨梁Iを既設の構造物としたものであって、吊下部2aに上述したターンバックル31とシャックル32とを組み合わせたものを使用している。   Next, based on FIG. 6, the bar arrangement work of the horizontal bar Y using the bar arrangement jig 1 according to the first embodiment of the present invention will be described. FIG. 6 is an explanatory diagram showing a state in which the reinforcing bar jig according to Embodiment 1 of the present invention is suspended from a steel beam already stretched. The bar arrangement work shown in FIG. 6 uses an already stretched steel beam I as an existing structure, and uses a combination of the above-described turnbuckle 31 and shackle 32 on the suspended portion 2a. Yes.

図6に示す例では、既設の鉄骨梁IのフランジにキャッチクランプCを固定し、このキャッチクランプCに配筋用治具1を吊り下げて配筋作業が行われる。図6に示す例では、三つの配筋用治具1を用い、隣り合う配筋用治具1を一対としてその間に横筋Yが張架されるようにしたものであって、中央の配筋用治具1において横筋Yが重なるようになっている。そして、配筋用治具1の吊下具3、即ちターンバックル31を調整することにより、左側に配筋される横筋Yと右側に配筋される横筋Yとが交差することなく重なるように調整される。   In the example shown in FIG. 6, the catch clamp C is fixed to the flange of the existing steel beam I, and the bar placement jig 1 is suspended from the catch clamp C to perform the bar placement work. In the example shown in FIG. 6, three bar arrangement jigs 1 are used, and the adjacent bar arrangement jigs 1 are paired so that the horizontal bar Y is stretched between them. In the jig 1, the horizontal stripes Y are overlapped. Then, by adjusting the suspension 3 of the bar arrangement jig 1, that is, the turnbuckle 31, the horizontal bar Y arranged on the left side and the horizontal bar Y arranged on the right side overlap without intersecting. Adjusted.

そして、隣り合う配筋用治具1のフック4とフック4との間に上段から下段に順番に横筋Yを保持させ、横筋Yを既設の縦筋Tに結束する。その後、ターンバックル31を緩めることにより、最上段のフック4とキャッチクランプCとの間隔を拡げ、配筋用治具1をキャッチクランプCから取り外す。そして、既設の鉄骨梁IのフランジからキャッチクランプCを取り外して配筋作業を終了する。   Then, the horizontal bars Y are held in order from the upper stage to the lower stage between the hooks 4 and hooks 4 of the adjacent bar arrangement jigs 1, and the horizontal bars Y are bound to the existing vertical bars T. Thereafter, the turnbuckle 31 is loosened to widen the gap between the uppermost hook 4 and the catch clamp C, and the bar arrangement jig 1 is removed from the catch clamp C. And the catch clamp C is removed from the flange of the existing steel beam I, and a bar arrangement work is complete | finished.

次に、図7に基づいて、本発明の実施の形態1に係る配筋用治具を用いた横筋の配筋作業を説明する。図7は、既に敷設された上階床に本発明の実施の形態1に係る配筋用治具を吊り下げた状態を示す説明図である。図7に示す配筋作業は、下面にアンカーを打ち込み可能な上階床Fが敷設されている場合に有効であって、吊下具3に上述したターンバックル31とシャックル32とを組み合わせたものを使用している。   Next, based on FIG. 7, the horizontal bar arrangement work using the bar arrangement jig according to the first embodiment of the present invention will be described. FIG. 7 is an explanatory diagram showing a state in which the bar arrangement jig according to the first embodiment of the present invention is suspended from an already laid upper floor. The bar arrangement work shown in FIG. 7 is effective when an upper floor F on which the anchor can be driven is laid on the lower surface, and the suspension 3 is combined with the turnbuckle 31 and the shackle 32 described above. Is used.

図7に示す例では、既設の上階床Fの下面にアンカーを打ち込んであり、このアンカーにアイボルトBを螺合させてある。このアイボルトBに配筋用治具1を吊り下げて配筋作業が行われる。図7に示す例では、三つの配筋用治具1を用い、隣り合う配筋用治具1を一対としてその間に横筋Yを保持させるようにしたものであって、中央の配筋用治具1において横筋Yが重なるようになっている。そして、配筋用治具1の吊下具3、即ち、ターンバックル31を調整することより、左側に配筋される横筋Yと右側に配筋される横筋Yとが交差することなく重なるように調整される。   In the example shown in FIG. 7, an anchor is driven into the lower surface of an existing upper floor F, and an eyebolt B is screwed into this anchor. The bar arrangement work is performed by suspending the bar arrangement jig 1 on the eyebolt B. In the example shown in FIG. 7, three bar arrangement jigs 1 are used, and adjacent bar arrangement jigs 1 are paired to hold the horizontal bar Y between them. In the tool 1, the horizontal stripes Y overlap. Then, by adjusting the suspension 3 of the bar arrangement jig 1, that is, the turnbuckle 31, the horizontal bar Y arranged on the left side and the horizontal bar Y arranged on the right side overlap without intersecting. Adjusted to

そして、隣り合う配筋用治具1のフック4とフック4との間に上段から下段に順番に横筋Yを保持させ、横筋Yを既設の縦筋Tに結束する。その後、ターンバックル31を緩めることにより、最上段のフック4とアイボルトBとの間隔を拡げ、配筋用治具1をアイボルトBから取り外す。そして、既設の上階床Fの下面からアイボルトBを取り外して配筋作業を終了する。   Then, the horizontal bars Y are held in order from the upper stage to the lower stage between the hooks 4 and hooks 4 of the adjacent bar arrangement jigs 1, and the horizontal bars Y are bound to the existing vertical bars T. Thereafter, the turnbuckle 31 is loosened to widen the space between the uppermost hook 4 and the eyebolt B, and the reinforcing bar 1 is removed from the eyebolt B. Then, the eyebolt B is removed from the lower surface of the existing upper floor F to finish the bar arrangement work.

次に、図8及び図9に基づいて、本発明の実施の形態1に係る配筋用治具を用いたフープ筋の配筋作業を説明する。図8は、フープ筋の配筋作業において本発明の実施の形態1に係る配筋用治具の配置を示した平面図、図9−1はフープ筋の配筋作業を示す側面図、図9−2は配筋用治具の取り外し作業を示す側面図である。図8及び図9に示す配筋作業は、既設の主筋Sにフープ筋Hを配設する場合に有効であって、吊下具3に上述したターンバックル31とシャックル32とを組み合わせたものを使用している。   Next, based on FIG.8 and FIG.9, the hoop reinforcement arrangement | positioning operation | work using the jig | tool for reinforcement arrangement concerning Embodiment 1 of this invention is demonstrated. FIG. 8 is a plan view showing the arrangement of the bar arrangement jig according to the first embodiment of the present invention in the hoop reinforcement arrangement, and FIG. 9-1 is a side view showing the arrangement of the hoop reinforcement. 9-2 is a side view showing the work of removing the bar arrangement jig. The bar arrangement work shown in FIG. 8 and FIG. 9 is effective when the hoop bar H is disposed on the existing main bar S, and a combination of the above-described turnbuckle 31 and shackle 32 is applied to the suspension 3. I am using it.

図8及び図9に示す配筋作業では、既設の主筋Sに配筋基準となるフープ筋Hを結束する。そして、このフープ筋Hにフック4が内側を向くように配筋用治具1を吊り下げて配筋作業が行われる。図8及び図9に示す例では、対向する二辺にそれぞれ二つの配筋用治具1を用いて配筋作業が行われる。このとき、複数のフック4のそれぞれが自身(フック4)の直上に位置するもの(フック4)の鉛直下方域外に移動するので、上段から下段に順番にフープ筋Hが保持される。そして、各フック4に保持されたフープ筋Hは、作業員により、既設の主筋Sに結束される(図9−1参照)。その後、ターンバックル31を緩めることにより、配筋基準としたフープ筋Hと最上段のフック4との間隔を拡げ、配筋用治具1を配筋基準としたフープ筋Hから取り外し、配筋作業を終了する(図9−2参照)。なお、ターンバックル31を緩めることなく、シャックル32からボルト32bを取り外すことにより、シャックル32からメインロープ2を取り外すとともに、配筋基準としたフープ筋Hからターンバックル31を取り外し、配筋作業を終了しても良い。   In the bar arrangement work shown in FIGS. 8 and 9, the hoop muscle H serving as the bar arrangement reference is bound to the existing main reinforcement S. Then, the bar placement work is performed by suspending the bar placement jig 1 so that the hook 4 faces the inside of the hoop bar H. In the example shown in FIG. 8 and FIG. 9, the bar arrangement work is performed using two bar arrangement jigs 1 on two opposite sides. At this time, each of the plurality of hooks 4 moves outside the vertical lower region of the hook (hook 4) located directly above itself (hook 4), so that the hoop muscles H are held in order from the upper stage to the lower stage. And the hoop muscle H hold | maintained at each hook 4 is tied to the existing main reinforcement S by an operator (refer FIG. 9-1). Thereafter, the turnbuckle 31 is loosened to widen the distance between the hoop muscle H based on the bar arrangement and the uppermost hook 4, and the jig 1 for bar arrangement is removed from the hoop bar H based on the bar arrangement. The work is finished (see FIG. 9-2). In addition, by removing the bolt 32b from the shackle 32 without loosening the turnbuckle 31, the main rope 2 is removed from the shackle 32, and the turnbuckle 31 is removed from the hoop muscle H based on the bar arrangement reference to complete the bar arrangement work. You may do it.

上述した本発明の実施の形態1である配筋用治具1は、既設の構造物に吊り下げられるメインロープ2と、メインロープ2に複数設けられ、既設の構造物にメインロープ2が吊り下げられた場合に、メインロープ2と交差する方向に鉄筋(横筋Y)をそれぞれ保持するフック4とを備えたので、作業員が縦筋Tと横筋Yとを把持することなく、縦筋Tに横筋Yを結束することができる。また、本実施の形態1である配筋用治具1は、既設の構造物に吊り下げた状態において、複数のフック4のそれぞれが自身の直上に位置するものの鉛直下方域外に移動できるように、基準体を柔軟な繊維製のメインロープ2により構成したので、メインロープ2が曲折することにより、新たに保持されるフープ筋Hは、フック4を回避した後に、フック4に保持される。したがって、作業員が主筋Sとフープ筋Hとを把持することなく、主筋Sにフープ筋Hを結束することができる。しかも、本実施の形態1である配筋用治具1(メインロープ2)を任意の位置で折り畳むことにより、配筋用治具1の持ち運びが容易となる。   The above-described bar arrangement jig 1 according to the first embodiment of the present invention is provided with a main rope 2 suspended from an existing structure and a plurality of main ropes 2, and the main rope 2 is suspended from the existing structure. Since the hook 4 that holds the reinforcing bars (lateral bars Y) in the direction intersecting with the main rope 2 is provided when the lower bars are lowered, the vertical bars T can be obtained without the operator holding the vertical bars T and the horizontal bars Y. The transverse muscles Y can be bound together. In addition, the bar arrangement jig 1 according to the first embodiment can be moved out of the vertically lower area of each of the plurality of hooks 4 in a state where it is suspended from an existing structure. Since the reference body is constituted by the main rope 2 made of flexible fiber, the hoop muscle H newly held by the main rope 2 being bent is held by the hook 4 after avoiding the hook 4. Therefore, the operator can bind the hoop muscle H to the main muscle S without holding the main muscle S and the hoop muscle H. Moreover, by folding the bar arrangement jig 1 (main rope 2) according to the first embodiment at an arbitrary position, the bar arrangement jig 1 can be easily carried.

また、配筋用治具1の吊下具3にターンバックル31を用いることにより、メインロープ2の吊り下げ位置が調整可能となる。また、ターンバックル31を緩めることにより、既設の構造物と最上段のフック4との間隔を拡げることができ、横筋Yあるいはフープ筋Hの結束後に配筋用治具1を取り外すことができる。   Moreover, the suspension position of the main rope 2 can be adjusted by using the turnbuckle 31 for the hanging tool 3 of the reinforcing bar 1. Further, by loosening the turnbuckle 31, the distance between the existing structure and the uppermost hook 4 can be widened, and the bar arrangement jig 1 can be removed after the horizontal bars Y or the hoop bars H are bound.

また、配筋用治具1は、表面に第一の間隔を有するようにパッチ21を縫合するとともに、裏面に第二の間隔を有するようにパッチ21を縫合し、表面と裏面の一方を選択してフック4を取り付けるようにしたので、表面を選択してフック4を取り付けた場合には、第一の間隔で横筋Yあるいはフープ筋Hを配筋することができ、裏面を選択してフック4を取り付けた場合には、第二の間隔で横筋Yあるいはフープ筋Hを配筋することができる。   Further, the bar arrangement jig 1 sews the patch 21 so as to have the first interval on the surface, and sews the patch 21 so as to have the second interval on the back surface, and selects one of the front surface and the back surface. Since the hook 4 is attached, when the surface is selected and the hook 4 is attached, the horizontal stripe Y or the hoop reinforcement H can be arranged at the first interval, and the rear face is selected and the hook is attached. When 4 is attached, the horizontal stripe Y or the hoop reinforcement H can be arranged at the second interval.

(実施の形態2)
図10は本発明の実施の形態2に係る配筋用治具を示す正面図、図11は図10に示した配筋用治具の側面図、図12は図10に示したフック及びパッチを示す拡大正面図、図13は図10に示したフック及びパッチを示す拡大側面図である。
(Embodiment 2)
10 is a front view showing a bar arrangement jig according to Embodiment 2 of the present invention, FIG. 11 is a side view of the bar arrangement jig shown in FIG. 10, and FIG. 12 is a hook and patch shown in FIG. FIG. 13 is an enlarged side view showing the hook and patch shown in FIG.

実施の形態2に係る配筋用治具6は、上述した実施の形態1に係る配筋用治具に改良を加えたものであって、実施の形態1に係る配筋用治具と同様に、メインロープ7、吊下具8、フック9を備えている。   The bar arrangement jig 6 according to the second embodiment is an improvement of the bar arrangement jig according to the first embodiment described above, and is similar to the bar arrangement jig according to the first embodiment. The main rope 7, the hanging tool 8, and the hook 9 are provided.

メインロープ7は、実施の形態1に係る配筋用治具と同様に、既設の構造物に吊り下げ可能であって、既設の構造物に吊り下げた場合に、鉄筋(横筋あるいはフープ筋)の配筋基準をなす基準体を構成する。メインロープ7は、実施の形態1に係る配筋用治具と同様に、既設の構造物に吊り下げた状態において、複数のフック9のそれぞれが自身(フック9)の直上に位置するもの(フック9)の鉛直下方域外に移動できるように、曲折可能に構成したものであって、具体的には、任意の位置で曲折可能な柔軟性を有するベルトスリングと称される繊維製の帯状部材により構成してある。   The main rope 7 can be hung from an existing structure, similarly to the bar arrangement jig according to the first embodiment. When the main rope 7 is hung from the existing structure, the main rope 7 is a reinforcing bar (horizontal bar or hoop bar). A reference body that constitutes the bar arrangement reference is constructed. As with the bar arrangement jig according to the first embodiment, the main rope 7 is such that each of the plurality of hooks 9 is located immediately above itself (the hook 9) in a state of being suspended from an existing structure ( A belt-like member made of a fiber called a belt sling which is configured to be bendable so that it can move outside the vertical lower area of the hook 9), and specifically has a flexibility that can be bent at an arbitrary position. It is comprised by.

図10及び図11に示すように、メインロープ7は、断面が偏平であって、表面と裏面の二つの面を有している。図11に示すように、実施の形態1に係る配筋用治具と異なり、メインロープ7は一端のみならず両端がそれぞれ折り返して自身(メインロープ7)に縫合してあり、一方の端部は、実施の形態1に係る配筋用治具と同様に、環状となった吊下部7aを構成する。そして、他方の端部は、環状となった連結部7bを構成する。なお、吊下部7a及び連結部7bは、折り返した端部を自身(メインロープ)に織り込むことにより構成しても良い。   As shown in FIGS. 10 and 11, the main rope 7 has a flat cross section and has two surfaces, a front surface and a back surface. As shown in FIG. 11, unlike the bar arrangement jig according to the first embodiment, the main rope 7 is folded not only at one end but also at both ends, and is sewn to itself (main rope 7). Constitutes an annular hanging portion 7a, similar to the bar arrangement jig according to the first embodiment. The other end constitutes a connecting portion 7b that is annular. In addition, you may comprise the hanging part 7a and the connection part 7b by weaving the folded-back edge part to itself (main rope).

図10及び図11に示すように、この吊下部7aには、実施の形態1に係る配筋用治具と同様に、吊下具8が装着してある。吊下具8は、メインロープ7を既設の構造物に吊り下げるためのものであるが、実施の形態1に係る配筋用治具と異なり、カラビナ81とクランプ82とを組み合わせて構成してある。カラビナ81は、一部を開放可能としたO字型の環状の連結手段である。クランプ82は、一対で円筒状となる半円筒状の金具821,822をヒンジ823で接続することにより開閉可能としたもので、一方の半円筒状の金具821を挿通した蝶ボルト824を他方の半円筒状の金具822に形成したネジ孔にねじ込むことにより、金具821,822が閉じた状態を維持することができるようになっている。なお、一方の金具821を挿通した蝶ボルト824に内側に歯を有する内歯座金825を取り付けることにより、一方の金具821から蝶ボルト824が脱落することがないようになっている。   As shown in FIGS. 10 and 11, a hanging tool 8 is attached to the hanging portion 7 a in the same manner as the bar arrangement jig according to the first embodiment. The hanger 8 is for suspending the main rope 7 from an existing structure. Unlike the bar arrangement jig according to the first embodiment, the hanger 8 is configured by combining a carabiner 81 and a clamp 82. is there. The carabiner 81 is an O-shaped annular connecting means that can be partially opened. The clamp 82 can be opened and closed by connecting a pair of semi-cylindrical metal fittings 821 and 822 with a hinge 823, and a butterfly bolt 824 inserted through one semi-cylindrical metal fitting 821 is connected to the other. By screwing into a screw hole formed in the semi-cylindrical metal fitting 822, the metal fittings 821 and 822 can be kept closed. In addition, by attaching an internal tooth washer 825 having teeth on the inside of the butterfly bolt 824 through which one of the metal fittings 821 is inserted, the butterfly bolt 824 is not dropped from the one metal fitting 821.

一方、連結部7bには、カラビナあるいはシャックル等の連結手段(図示せず)によって、配筋用治具6を連結することができるようにしたものであって、配筋用治具6を連結することによって、必要な鉄筋を一度に配筋することができるようになっている。   On the other hand, the bar arrangement jig 6 can be connected to the connection portion 7b by connection means (not shown) such as a carabiner or a shackle. By doing so, it is possible to arrange the necessary reinforcing bars at once.

また、メインロープ7の一方の面には、実施の形態1に係る配筋用治具と同様に、複数の鉄筋を保持した場合に鉄筋相互間の間隔が所定の間隔(例えば、100ミリ間隔)となるように、複数のパッチ71が縫合してある。図12及び図13に示すように、パッチ71は、メインロープ7にフック9を取り付けるためのもので、メインロープ7と異なる色(例えば、メインロープ7が緑色の場合に青色とする)であって、メインロープ7よりも薄い柔軟な繊維製の帯状部材により構成してある。パッチ71は、実施の形態1に係る配筋用治具と同様に、断面が偏平であって、メインロープ7とパッチ71との間にフック9が挿通するためのたるみを有するように、上部と下部とをメインロープ7に縫合してある。ここで、上部と下部とを縫合する縫合糸の色は、メインロープ7及びパッチ71と異なる色(例えば、橙色)で、少なくとも下部は、上下二重となるように縫合してある。   In addition, on one surface of the main rope 7, as in the case of the bar arrangement jig according to the first embodiment, when a plurality of reinforcing bars are held, the interval between the reinforcing bars is a predetermined interval (for example, an interval of 100 mm). ), A plurality of patches 71 are stitched together. As shown in FIGS. 12 and 13, the patch 71 is for attaching the hook 9 to the main rope 7 and has a color different from that of the main rope 7 (for example, blue when the main rope 7 is green). The belt is made of a flexible fiber-like member thinner than the main rope 7. Similarly to the bar arrangement jig according to the first embodiment, the patch 71 has a flat cross section and has a slack for allowing the hook 9 to be inserted between the main rope 7 and the patch 71. And the lower part are sewn to the main rope 7. Here, the color of the suture thread that sews the upper part and the lower part is different from the main rope 7 and the patch 71 (for example, orange), and at least the lower part is sewn so as to be double vertically.

このようにメインロープ7に縫合したパッチ71には、番号が付してある。番号は、配筋用治具6を吊り下げた場合に上方から下方に向けて一つずつ繰り上がるように付してあり、フック9に鉄筋を保持させるときの目安にすることができるようになっている。   The patch 71 sewn to the main rope 7 is numbered. The numbers are attached so as to be raised one by one from the upper side to the lower side when the bar arrangement jig 6 is suspended, so that it can be used as a guide when the hook 9 holds the reinforcing bar. It has become.

このように、パッチ71を縫合したメインロープ7は、実施の形態1に係る配筋用治具と同様に、メインロープ7とパッチ71との間であって、パッチ71の上部と下部との間には、フック9が挿通する挿通部72が形成される。この挿通部72にフック9を挿通させることにより、メインロープ7にフック9が取り付けられている。   As described above, the main rope 7 sewed with the patch 71 is between the main rope 7 and the patch 71 and between the upper and lower portions of the patch 71 in the same manner as the bar arrangement jig according to the first embodiment. An insertion portion 72 through which the hook 9 is inserted is formed therebetween. The hook 9 is attached to the main rope 7 by inserting the hook 9 through the insertion portion 72.

フック9は、実施の形態1に係る配筋用治具と同様に、メインロープ7が既設の構造物に吊り下げられた場合に、メインロープ7と交差する方向に鉄筋(横筋あるいはフープ筋)をそれぞれ保持するものであって、フック9の大きさは、鉄筋の配筋間隔の二分の一以下の大きさとなるように構成してある。フック9は、側面視鉤状を呈するものであり、丸棒状の鋼材を折り曲げることにより構成してある。フックは、軸部91、一対となる脚部92及び一対となるフック部93を有している。軸部91は、上述したメインロープ7とパッチ71との間に形成された挿通部72に挿通する部分であって、少なくともパッチ71よりも幅広となるように形成してある。一対の脚部92は、軸部91の一端と他端とからそれぞれ中央に向けて傾斜するように延在しており、その先端は、上述したパッチの厚みよりも広くなるように形成してある。したがって、脚部92の先端が交差しないものの、上述した軸部91とともに二等辺三角形の形状を呈することになる。一対のフック部93は、所定の間隔を維持したまま所定の径を有するように脚部92から手前側に延在させた後、斜め上方に略135度折り返すことにより、開角αが略45度となるように形成してある。尚、フック部93の形状は、鉄筋(横筋、フープ筋)を保持可能な範囲で所定の径を小さなものとし、開角αを鋭角なものとすることが望ましいが、折返し角度は略135度に限られるものではなく、配筋途上の鉄筋(横筋、フープ筋)がフック9とメインロープ7との間に引っ掛かりにくいものであれば、略180度折り返して形成し、開角を0度としても良い。   Similarly to the bar arrangement jig according to the first embodiment, the hook 9 is a reinforcing bar (horizontal bar or hoop bar) in a direction crossing the main rope 7 when the main rope 7 is suspended from an existing structure. Each of the hooks 9 is configured so that the size of the hook 9 is not more than one half of the reinforcing bar arrangement interval. The hook 9 has a bowl-like shape when viewed from the side, and is configured by bending a round bar-shaped steel material. The hook includes a shaft portion 91, a pair of leg portions 92, and a pair of hook portions 93. The shaft portion 91 is a portion that is inserted into an insertion portion 72 formed between the main rope 7 and the patch 71 described above, and is formed to be at least wider than the patch 71. The pair of leg portions 92 extend from one end and the other end of the shaft portion 91 so as to incline toward the center, and the tips thereof are formed to be wider than the thickness of the patch described above. is there. Therefore, although the tips of the leg portions 92 do not intersect, the shape of the isosceles triangle is exhibited together with the shaft portion 91 described above. The pair of hook portions 93 are extended from the leg portion 92 to the near side so as to have a predetermined diameter while maintaining a predetermined interval, and then folded back obliquely upward by approximately 135 degrees, so that the opening angle α is approximately 45 degrees. It is formed to be a degree. The hook portion 93 preferably has a small diameter and a sharp opening angle α within a range in which the reinforcing bars (horizontal bars and hoop bars) can be held, but the turning angle is approximately 135 degrees. If the reinforcing bars (horizontal bars, hoop bars) are not easily caught between the hook 9 and the main rope 7, they are folded back approximately 180 degrees and the opening angle is set to 0 degrees. Also good.

このように構成したフック9は、フック部93、脚部92、軸部91の順に挿通部72に挿通させることにより、挿通部72に軸部91が挿通し、メインロープ7にフック9が回動可能に取り付けられる。   The hook 9 configured as described above is inserted through the insertion portion 72 in the order of the hook portion 93, the leg portion 92, and the shaft portion 91, whereby the shaft portion 91 is inserted into the insertion portion 72 and the hook 9 is rotated around the main rope 7. Mounted movably.

上述した実施の形態1に係る配筋用治具1は、吊下具3としてターンバックル31とシャックル32とを組み合わせて構成してある。このため、吊下具3の全長が長くならざるをえず、配筋用治具1を吊り下げた既設の鉄筋と配筋用治具1の最上段に配筋した鉄筋の間隔が所望の間隔を超えてしまう場合がある。この場合には配筋用治具によらず、別途鉄筋を配筋する必要が生じることになる。   The bar arrangement jig 1 according to Embodiment 1 described above is configured by combining the turnbuckle 31 and the shackle 32 as the suspending tool 3. For this reason, the overall length of the hanging tool 3 must be long, and the interval between the existing reinforcing bar in which the reinforcing bar 1 is suspended and the reinforcing bar in the uppermost stage of the reinforcing bar 1 is desired. The interval may be exceeded. In this case, it is necessary to separately arrange the reinforcing bars regardless of the reinforcing bars.

これに対して、実施の形態2に係る配筋用治具6は、吊下具8としてカラビナ81とクランプ82とを組み合わせて構成してある。このため、吊下具3の全長を短くすることができ、配筋用治具6を吊り下げて既設の鉄筋と配筋用治具6の最上段に配筋した鉄筋の間隔を確保することができる。したがって、実施の形態1に係る配筋用治具のように、別途鉄筋を配筋する必要が生じることはない。   In contrast, the bar arrangement jig 6 according to the second embodiment is configured by combining a carabiner 81 and a clamp 82 as the hanging tool 8. For this reason, the overall length of the hanging tool 3 can be shortened, and the interval between the existing reinforcing bar and the reinforcing bar arranged on the uppermost stage of the reinforcing bar 6 is secured by suspending the reinforcing bar 6. Can do. Therefore, unlike the bar arrangement jig according to the first embodiment, it is not necessary to separately arrange reinforcing bars.

上述した実施の形態1に係る配筋用治具1において、全てのフック4に鉄筋を配筋した場合には、吊下具3に大きな荷重が作用することになる。このため、既設の鉄筋に吊り下げられた吊下具3(特にターンバックル31)と配筋用治具1の最上段に配筋された鉄筋(結束された鉄筋)との間には大きな力が残存することになり、配筋用治具1が取り外し難いものとなる。   In the bar arrangement jig 1 according to the first embodiment described above, when reinforcing bars are arranged on all the hooks 4, a large load acts on the hanging tool 3. For this reason, there is a large force between the hanger 3 (particularly the turnbuckle 31) suspended from the existing reinforcing bars and the reinforcing bars arranged at the uppermost stage of the reinforcing bar 1 (reinforcing bars). Will remain, making it difficult to remove the reinforcing bar jig 1.

これに対して実施の形態2に係る配筋用治具1は、カラビナ81とクランプ82とを組み合わせて吊下具8を構成したので、クランプ82には大きな荷重が作用することになるものの、蝶ボルト824に大きな荷重が作用するわけではないので、配筋用治具6が実施の形態1に係る配筋用治具に比して取り外し易いものとなる。   On the other hand, the bar arrangement jig 1 according to the second embodiment configures the hanging tool 8 by combining the carabiner 81 and the clamp 82, so that a large load acts on the clamp 82. Since a large load does not act on the butterfly bolt 824, the bar arrangement jig 6 is easier to remove than the bar arrangement jig according to the first embodiment.

また、本実施の形態2に係る配筋用治具6は、メインロープ7に連結部7bを構成してあるので、カラビナあるいはシャックル等の連結手段によって配筋用治具6を必要に応じて連結することができる。したがって、配筋用治具を付け替えることなく、多様な高さの柱や壁の配筋を一度で行うことができる。   In addition, since the bar arrangement jig 6 according to the second embodiment is configured with the connecting portion 7b on the main rope 7, the bar arrangement jig 6 can be connected to the main rope 7 by connecting means such as a carabiner or a shackle as required. Can be linked. Therefore, it is possible to perform bar arrangement of various heights and walls at once without changing the bar arrangement jig.

また、本実施の形態2に係る配筋用治具6は、全て異なる色でメインロープ7、パッチ71、縫合糸を構成したので、各部材の摩耗状況を判断し易くなる。また、大きな力が作用するパッチ71の下部は、上下二重となるように縫合してあるので、一方の縫合糸が切れてもフック9が直ちに落下する事態を防止できる。   Further, since the bar arrangement jig 6 according to the second embodiment is composed of the main rope 7, the patch 71, and the suture with different colors, it is easy to determine the wear state of each member. Further, since the lower part of the patch 71 to which a large force acts is sewn so as to be doubled up and down, it is possible to prevent the hook 9 from immediately falling even if one suture thread is cut.

さらに、本実施の形態2に係る配筋用治具6は、フック9の大きさを鉄筋の配筋間隔の二分の一以下の大きさとなるように構成してあるので、下側に位置するフック9に鉄筋が干渉し、フック9が裏返っても下側に位置するフック9と上側に位置するフック9とが干渉する事態を防止できる。   Further, the bar arrangement jig 6 according to the second embodiment is configured so that the size of the hook 9 is not more than one half of the bar arrangement interval of the reinforcing bars, and therefore is located on the lower side. Even if the reinforcing bar interferes with the hook 9 and the hook 9 is turned over, it is possible to prevent the hook 9 positioned on the lower side and the hook 9 positioned on the upper side from interfering with each other.

本発明の実施の形態1に係る配筋用治具を示す正面図である。It is a front view which shows the jig | tool for bar arrangement concerning Embodiment 1 of this invention. 図1に示した配筋用治具の側面図である。It is a side view of the jig for bar arrangement shown in FIG. 図1に示したフック及びパッチを示す拡大正面図である。It is an enlarged front view which shows the hook and patch shown in FIG. 図1に示したフック及びパッチを示す拡大側面図である。It is an enlarged side view which shows the hook and patch shown in FIG. 既に張架された横筋に本発明の実施の形態1に係る配筋用治具を吊り下げた状態を示す斜視図である。It is a perspective view which shows the state which suspended the reinforcement jig | tool which concerns on Embodiment 1 of this invention on the horizontal bar already stretched. 既に張架された鉄骨梁に本発明の実施の形態1に係る配筋用治具を吊り下げた状態を示す正面図である。It is a front view which shows the state which suspended the reinforcement jig | tool which concerns on Embodiment 1 of this invention on the steel beam already stretched. 既に敷設された上階床に本発明の実施の形態1に係る配筋用治具を吊り下げた状態を示す正面図である。It is a front view which shows the state which suspended the reinforcement jig | tool which concerns on Embodiment 1 of this invention on the upper floor already laid. フープ筋の配筋作業において本発明の実施の形態1に係る配筋用治具の配置を示した平面図である。It is the top view which showed arrangement | positioning of the jig for bar arrangement which concerns on Embodiment 1 of this invention in the bar arrangement work of a hoop bar. フープ筋の配筋作業を示す側面図である。It is a side view which shows the arrangement | positioning work of a hoop muscle. 配筋用治具の取り外し作業を示す側面図である。It is a side view which shows the removal operation | work of the jig for bar arrangement. 本発明の実施の形態2に係る配筋用治具を示す正面図である。It is a front view which shows the jig for bar arrangement which concerns on Embodiment 2 of this invention. 図10に示した配筋用治具の側面図である。It is a side view of the jig for bar arrangement shown in FIG. 図10に示したフック及びパッチを示す拡大正面図である。It is an enlarged front view which shows the hook and patch shown in FIG. 図10に示したフック及びパッチを示す拡大側面図である。It is an enlarged side view which shows the hook and patch shown in FIG.

符号の説明Explanation of symbols

1 配筋用治具
2 メインロープ(基準体)
2a 吊下部
21 パッチ
22 挿通部
3 吊下具
31 ターンバックル(調整手段)
32 シャックル
4 フック
41 軸部
42 脚部
43 フック部
6 配筋用治具
7 メインロープ(基準体)
7a 吊下部
7b 連結部
71 パッチ
72 挿通部
8 吊下具
81 カラビナ
82 クランプ(対となる金具)
821,822 半円筒形の金具
823 ヒンジ
824 蝶ボルト
825 内歯座金
9 フック
91 軸部
92 脚部
93 フック部
B アイボルト
C キャッチクランプ
F 上階床
H フープ筋
I 鉄骨梁
S 主筋
T 縦筋
Y 横筋
1 Jig for bar arrangement 2 Main rope (reference body)
2a Suspension part 21 Patch 22 Insertion part 3 Suspension tool 31 Turn buckle (Adjustment means)
32 Shackle 4 Hook 41 Shaft part 42 Leg part 43 Hook part 6 Bar arrangement jig 7 Main rope (reference body)
7a Suspension part 7b Connection part 71 Patch 72 Insertion part 8 Suspension tool 81 Carabiner 82 Clamp (a pair of metal fittings)
821,822 Semi-cylindrical metal fittings 823 Hinge 824 Butterfly bolt 825 Internal washer 9 Hook 91 Shaft 92 Leg 93 Hook B Eyebolt C Catch clamp F Upper floor H Hoop muscle I Steel beam S Main muscle T Longitudinal muscle Y Horizontal muscle

Claims (8)

既設の構造物に吊り下げられる基準体と、該基準体に複数設けられ、既設の構造物に基準体が吊り下げられた場合に、該基準体と交差する方向に鉄筋をそれぞれ保持する鉤状のフックとを備えた配筋用治具であって、
前記既設の構造物に吊り下げた状態において、複数のフックのそれぞれが自身の直上に位置するものの鉛直下方域外に移動できるように、前記基準体を曲折可能に構成したことを特徴とする配筋用治具。
A reference body that can be suspended from an existing structure, and a plurality of reference bodies that are provided on the reference body, and when the reference body is suspended from the existing structure, a hook that holds the reinforcing bars in a direction that intersects the reference body. A bar arrangement jig with a hook of
A bar arrangement in which the reference body is configured to be bent so that each of the plurality of hooks can be moved out of the vertically lower region while being suspended from the existing structure. Jig.
既設の構造物と前記基準体とを接続する吊下具を備えたことを特徴とする請求項1に記載の配筋用治具。   The bar arrangement jig according to claim 1, further comprising a hanging tool that connects an existing structure and the reference body. 前記吊下具は、既設の構造物と前記基準体との間隔を調整する調整手段を備えたことを特徴とする請求項2に記載の配筋用治具。   3. The bar arrangement jig according to claim 2, wherein the hanging tool includes an adjusting means for adjusting an interval between an existing structure and the reference body. 前記基準体に上部と下部とを接合することにより、該上部と該下部との間に挿通部を構成するパッチを備え、
前記フックを前記挿通部に挿通することにより、前記基準体に前記フックを取り付けたことを特徴とする請求項1〜3のいずれか一つに記載の配筋用治具。
By joining the upper part and the lower part to the reference body, it comprises a patch that constitutes an insertion part between the upper part and the lower part,
The bar arrangement jig according to any one of claims 1 to 3, wherein the hook is attached to the reference body by inserting the hook into the insertion portion.
前記基準体の断面が扁平であって、
一の面には複数の鉄筋を保持した場合に鉄筋相互間の間隔が第一の間隔となるように複数のパッチが接合してあり、
他の面には複数の鉄筋を保持した場合に鉄筋相互間の間隔が第二の間隔となるように複数のパッチが接合してあることを特徴とする請求項4に記載の配筋用治具。
The cross section of the reference body is flat,
A plurality of patches are joined to one surface so that the interval between the reinforcing bars becomes the first interval when holding the plurality of reinforcing bars,
5. The reinforcing bar treatment according to claim 4, wherein a plurality of patches are joined to the other surface such that when a plurality of reinforcing bars are held, the interval between the reinforcing bars becomes a second interval. Ingredients.
前記基準体と前記パッチとは、一方に突起を有し、他方にパイル状のループを有した面ファスナーにより接合されたことを特徴とする請求項4に記載の配筋用治具。   The bar arrangement jig according to claim 4, wherein the reference body and the patch are joined by a hook-and-loop fastener having a protrusion on one side and a pile-shaped loop on the other side. 前記基準体は、一端に環状の吊下部を有するとともに、他端に環状の連結部を有したことを特徴とする請求項1に記載の配筋用治具。   The bar arrangement jig according to claim 1, wherein the reference body has an annular hanging portion at one end and an annular connecting portion at the other end. 前記吊下具は、開閉可能であって、閉塞した状態を維持可能な対となる金具で構成したことを特徴とする請求項2に記載の配筋用治具。   The bar arrangement jig according to claim 2, wherein the hanging tool is configured by a pair of fittings that can be opened and closed and can maintain a closed state.
JP2007205419A 2006-11-15 2007-08-07 Bar arrangement jig Expired - Fee Related JP4947464B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007205419A JP4947464B2 (en) 2006-11-15 2007-08-07 Bar arrangement jig

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2006309615 2006-11-15
JP2006309615 2006-11-15
JP2007205419A JP4947464B2 (en) 2006-11-15 2007-08-07 Bar arrangement jig

Publications (2)

Publication Number Publication Date
JP2008144571A true JP2008144571A (en) 2008-06-26
JP4947464B2 JP4947464B2 (en) 2012-06-06

Family

ID=39605031

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007205419A Expired - Fee Related JP4947464B2 (en) 2006-11-15 2007-08-07 Bar arrangement jig

Country Status (1)

Country Link
JP (1) JP4947464B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012183470A (en) * 2011-03-04 2012-09-27 Kubota Corp Hanging jig of membrane module, membrane module, and method of using hanging jig of membrane module
CN113685061A (en) * 2021-09-29 2021-11-23 南京长江都市建筑设计股份有限公司 High-altitude sheet longitudinal bar anchoring structure and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0337076U (en) * 1989-08-23 1991-04-10
JPH11324329A (en) * 1998-05-20 1999-11-26 Ks Staff:Kk Reinforcement hanging band
JP2001115600A (en) * 1999-10-15 2001-04-24 Nishimura Kogyosho:Kk Reinforcing bar for placing concrete

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0337076U (en) * 1989-08-23 1991-04-10
JPH11324329A (en) * 1998-05-20 1999-11-26 Ks Staff:Kk Reinforcement hanging band
JP2001115600A (en) * 1999-10-15 2001-04-24 Nishimura Kogyosho:Kk Reinforcing bar for placing concrete

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012183470A (en) * 2011-03-04 2012-09-27 Kubota Corp Hanging jig of membrane module, membrane module, and method of using hanging jig of membrane module
CN113685061A (en) * 2021-09-29 2021-11-23 南京长江都市建筑设计股份有限公司 High-altitude sheet longitudinal bar anchoring structure and construction method thereof
CN113685061B (en) * 2021-09-29 2023-09-22 南京长江都市建筑设计股份有限公司 High-altitude thin plate longitudinal rib anchoring structure and construction method thereof

Also Published As

Publication number Publication date
JP4947464B2 (en) 2012-06-06

Similar Documents

Publication Publication Date Title
US5673769A (en) Safety/debris net system
JP4947464B2 (en) Bar arrangement jig
US6161648A (en) Safety/debris net system
JP6195810B2 (en) Sheet folding method and eyelet hooking device
JP3170262U (en) Safety belt
US6000498A (en) Safety/debris net system
JPH11264252A (en) Curing sheet fitting structure
JP2013055857A (en) Fall prevention net
JP3608155B2 (en) Curtain hanging device
JPS5931846Y2 (en) Rebar binding wire
JP3237258U (en) Bracket for loading and unloading
JP6085874B1 (en) Continuous hook for mesh sheet eyelet
JP3243737U (en) Bags for civil engineering work
JP6106367B2 (en) Hanger for exterior wall materials
JP4504780B2 (en) Curing sheet tension structure
JP3294817B2 (en) A strap for fixing a sheet for civil engineering work
JP6771733B2 (en) A net or sheet for an indoor space, and a method for moving the net or sheet for the indoor space.
JP5959431B2 (en) tent
JP3035741U (en) Belt for construction work
TW200920622A (en) Cargo net
JP6899346B2 (en) Protective equipment, how to install protective equipment
JP2009046254A (en) Sling protector
JP4149906B2 (en) Method and apparatus for laying block mat
JP3044743U (en) Moving rope for fall prevention
JP2534601Y2 (en) Seat tie

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091225

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110819

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110830

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20111024

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120214

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120224

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150316

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees