JP2008052461A - Power distribution construction management system - Google Patents

Power distribution construction management system Download PDF

Info

Publication number
JP2008052461A
JP2008052461A JP2006227276A JP2006227276A JP2008052461A JP 2008052461 A JP2008052461 A JP 2008052461A JP 2006227276 A JP2006227276 A JP 2006227276A JP 2006227276 A JP2006227276 A JP 2006227276A JP 2008052461 A JP2008052461 A JP 2008052461A
Authority
JP
Japan
Prior art keywords
distribution work
power distribution
work
construction
predetermined
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006227276A
Other languages
Japanese (ja)
Inventor
Akitoshi Fukushima
昭稔 福島
Shiyouei Takatsu
章栄 高津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TOOTEC KK
Original Assignee
TOOTEC KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TOOTEC KK filed Critical TOOTEC KK
Priority to JP2006227276A priority Critical patent/JP2008052461A/en
Publication of JP2008052461A publication Critical patent/JP2008052461A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Instructional Devices (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To broadly notify power distribution construction information in real time. <P>SOLUTION: This power distribution construction management system comprises: a server installed in a management department to display map information including the region of power distribution construction; terminal equipment owned by the general consumer of a power connected through a communication line to the server; a construction content input means for inputting predetermined construction content relating to power distribution construction scheduled to a server; a construction mark addition means for adding predetermined marks showing power distribution construction places in the map information based on the input predetermined construction content; a map information display means for displaying the content of the map information on the display screen of the terminal equipment; a designation means for designating the predetermined spots on the map displayed on the display screen; and an enlargement display means for executing the enlargement display of the predetermined range including the designated predetermined spots including the construction marks A, B and C. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は配電工事管理システムに係り、特に配電工事における各段階の工事進捗状況に関する各種の情報を一般需要家・工事関係者等に効率よく提供できるようにするとともに、配電工事に係る各種業務を効率よく処理できるようにした配電工事管理システムに関する。   The present invention relates to a power distribution management system, and in particular, can efficiently provide various information related to the progress of construction at each stage of power distribution work to general consumers, construction workers, etc., and perform various work related to power distribution work. The present invention relates to a distribution work management system that can be processed efficiently.

従来、配電工事が行われる場合は、その配電工事が行われる旨の内容が記載されている印刷物(チラシ)が配電工事場所近くに貼付されると共に、その配電工事で影響を受ける一般需要家である各家庭や工場等に配布され、配電工事予定日時が知らされている。   Conventionally, when power distribution work is performed, printed materials (flyers) describing the details of the power distribution work are pasted near the power distribution site, and are also affected by general consumers affected by the power distribution work. It is distributed to certain households and factories, etc., and the date and time of distribution work is informed.

また、配電工事を施工する会社においては、配電工事の発注元である例えば電力供給会社から発注工事を受託(受注)すると、その後の管理業務処理は手作業で、かつペーパーベースを主とした処理で業務が行われている。   In addition, in a company that conducts power distribution work, when the power supply company, for example, the power distribution company that orders the power distribution work is entrusted (ordered), the subsequent management work is a manual process that is mainly paper-based. The business is done in.

すなわち、受注後の配電工事受託業務はペーパーベースの受託台帳が作成されるとともに、品質計画書が個別に発行され、配電工程管理業務においては工程管理台帳及び設計管理台帳もペーパーベースで行われ、配電資材業務においては必要な資材の集計及び入力も手作業で行われているとともに、在庫管理も現物ベースで行われ、そして、配電工事精算業務も手作業による各種データの入力で行われている。
特になし
In other words, a paper-based consignment ledger is created for the distribution work consignment work after an order is received, and a quality plan is issued separately.In the distribution process management work, the process management ledger and the design management ledger are also carried out on a paper basis In the distribution materials business, necessary materials are summed up and entered manually, inventory management is also performed on an actual basis, and distribution work settlement work is also performed by manually inputting various data. .
nothing special

上述のように、配電工事が行われる場合は、配電工事が行われる近辺の一般需要家にチラシでその旨が周知されるが、これを広範囲に、かつリアルタイムで報知することが望まれていた。すなわち、配電工事が行われる場所はその工事のために道路の一部が占用されるために交通渋滞が発生しやすく、ドライバーその他の往来者にとって、その場所を事前に知って回避したいという要望もあった。さらに、一般需要家においても、配電工事に伴う停電等に起因する電子機器を保護するために、開始時・終了時・工事内容等の配電工事情報を確実に入手したいという要望があった。さらにまた、発注者である電力供給会社においても、配電工事の進捗状況をリアルタイムで把握したいという要望があった。   As mentioned above, when power distribution work is performed, it is known to the general consumers in the vicinity where the power distribution work is performed by flyers, but it has been desired to notify this in a wide range and in real time. . In other words, the place where power distribution work is performed is likely to cause traffic congestion because part of the road is occupied for the work, and there is also a demand for drivers and other visitors to know the place in advance and avoid it there were. Furthermore, there is a demand for general consumers to reliably obtain information on power distribution work such as start time, end time, and work contents in order to protect electronic devices caused by power outages associated with power distribution work. Furthermore, there was a request from the power supply company as the orderer to grasp the progress of power distribution work in real time.

また、上述のように、配電工事を受注後の施工会社の管理業務は主として手作業で、かつペーパーベースで行われていたので、データが散在しやすく、集計処理の不一致等が発生しやすい等の不都合があった。   In addition, as mentioned above, the management work of the construction company after receiving an order for power distribution work was mainly done manually and on a paper basis, so data is likely to be scattered and discrepancies in the aggregation process are likely to occur. There was an inconvenience.

そこで本発明は、これらの要望に応えるとともに、従来存した諸欠点を解決するためになされるものであって、その目的は、開始時・終了時・工事内容・工事箇所等の配電工事情報を広範囲にわたってリアルタイムに需要家その他に報知できるとともに、配電工事の施工会社における管理業務を効率よく行えるようにした配電工事管理システムを提供することにある。   Therefore, the present invention is made in order to meet these demands and to solve the existing defects, and its purpose is to distribute power distribution work information such as start time, end time, work content, work location, etc. It is intended to provide a distribution work management system capable of notifying consumers and others in real time over a wide range and efficiently performing management work in a distribution work construction company.

上記目標を達成するために本発明に係る配電工事管理システムは、配電工事を担当する所定の地域を含む地図情報を表示するよう管理部門に設置されているサーバ1と、サーバ1と通信回線7を介して接続されている端末装置12,13と、予定されている配電工事に係る所定の工事内容をサーバ1に入力する工事内容入力手段と、工事内容入力手段を介して入力された所定の工事内容に基づいて地図情報中に配電工事箇所を示す所定のマークを付加する工事マーク付加手段と、端末装置12,13の表示画面に地図情報の内容を表示する地図情報表示手段と、端末装置12,13の表示画面に表示されている地図上の所定の地点を指定する指定手段と、指定手段により指定された所定の地点を含む所定範囲を工事マーク付加手段により付加された所定マークA,B,Cを含めて拡大表示する端末表示手段とを有することを特徴としている。
上記構成からなる配電工事管理システムは、配電工事を施工する施工会社の管理部門、例えば本社等に設置されているサーバ1を介して地図情報中に工事内容入力手段により予定されている配電工事の所定の工事内容が入力される。そして、その入力に基づいて地図情報中に配電工事が行われる箇所に所定のマークA,B,Cが付加される。他方サーバ1に対応するクライアントに当たる端末装置12,13は、サーバ1から出力される地図情報の内容(地図)が表示され、その地図の所定の場所が指定されると(クリックされると)、その部分が拡大表示される。その拡大表示された地図には、配電工事の行われる箇所が工事の進捗状況に対応した表示のマークA,B,Cで表示される。
本発明に係る配電工事管理システムにおいて、端末装置12,13は配電工事の発注元又は電力の一般需要家に設置されるものであることを特徴としている。
本発明に係る配電工事管理システムにおいて、通信回線7には、配電工事担当者が所持する携帯端末機14が接続されたり、配電工事を監視する監視要員が所持する携帯端末機16が接続されたりする。
本発明に係る配電工事管理システムにおいて、配電工事箇所を示す所定のマークA,B,Cは、配電工事の予定、配電工事中及び配電工事終了を区別して表示するものである。
本発明に係る配電工事管理システムにおいて、サーバ1には、配電工事の受託業務を管理する受託業務管理用処理装置、配電工事の工程を管理する工程管理用処理装置、配電工事で用いられる部品、材料、機材その他の配電工事用資材を手配する材料管理用処理装置10、配電工事に伴う精算処理業務を管理する精算管理用処理装置11の少なくともいずれかが更に接続されることで構成することができる。
In order to achieve the above goal, a power distribution work management system according to the present invention includes a server 1, a server 1 and a communication line 7 installed in a management department so as to display map information including a predetermined area in charge of power distribution work. The terminal devices 12 and 13 connected via the server, the construction content input means for inputting the predetermined construction contents relating to the planned power distribution work to the server 1, and the predetermined input inputted via the construction content input means Construction mark adding means for adding a predetermined mark indicating the distribution work location in the map information based on the construction contents, map information display means for displaying the contents of the map information on the display screens of the terminal devices 12 and 13, and the terminal device A designation means for designating a predetermined point on the map displayed on the display screens 12 and 13 and a predetermined range including the predetermined point designated by the designation means are added by the construction mark adding means. Predetermined mark A which, B, it is characterized by having a terminal display unit to enlarge including C.
The distribution work management system configured as described above is used for the distribution work scheduled by the construction content input means in the map information via the server 1 installed in the head office or the like of the construction company that performs the distribution work. Predetermined construction details are entered. Based on the input, predetermined marks A, B, and C are added to locations where power distribution work is performed in the map information. On the other hand, the terminal devices 12 and 13 corresponding to the client corresponding to the server 1 display the contents (map) of the map information output from the server 1, and when a predetermined location of the map is designated (clicked), That part is enlarged and displayed. In the enlarged map, locations where power distribution work is performed are displayed with display marks A, B, and C corresponding to the progress of the work.
In the distribution work management system according to the present invention, the terminal devices 12 and 13 are installed at an ordering party of distribution work or a general consumer of electric power.
In the distribution work management system according to the present invention, the communication line 7 is connected to the portable terminal 14 possessed by the person in charge of the distribution work, or the portable terminal 16 possessed by the monitoring personnel monitoring the distribution work. To do.
In the distribution work management system according to the present invention, the predetermined marks A, B, and C indicating the distribution work place are used to distinguish between the schedule of the distribution work, during the distribution work, and the end of the distribution work.
In the distribution work management system according to the present invention, the server 1 includes a commissioned work management processing apparatus that manages the commissioned work of the distribution work, a process management processing apparatus that manages the power distribution work process, parts used in the power distribution work, It may be configured by further connecting at least one of a material management processing device 10 that arranges materials, equipment, and other materials for power distribution work, and a payment management processing device 11 that manages the payment processing work associated with the power distribution work. it can.

本発明に係る配電工事管理システムは、配電工事を担当する所定の地域を含む地図情報を表示するよう管理部門に設置されているサーバ1と、サーバ1と通信回線7を介して接続されている端末装置12,13と、予定されている配電工事に係る所定の工事内容をサーバ1に入力する工事内容入力手段と、入力された所定の工事内容に基づいて地図情報中に配電工事箇所を示す所定のマークを付加する工事マーク付加手段と、端末装置12,13の表示画面に地図情報の内容を表示する地図情報表示手段と、表示されている地図上の所定の地点を指定する指定手段と、指定された所定の地点を含む所定範囲を工事マーク付加手段により付加された所定マークA,B.Cを含めて拡大表示する拡大表示手段とからなるので、配電工事箇所を広範囲にわたってリアルタイムに知らせることができる。   A power distribution work management system according to the present invention is connected to a server 1 installed in a management department so as to display map information including a predetermined area in charge of power distribution work, and the server 1 via a communication line 7. Terminal apparatus 12 and 13, construction content input means for inputting predetermined construction contents relating to planned distribution work to server 1, and distribution work location in map information based on the inputted predetermined construction contents Construction mark adding means for adding a predetermined mark, map information display means for displaying the contents of the map information on the display screens of the terminal devices 12 and 13, and designation means for designating a predetermined point on the displayed map The predetermined marks A, B,... Added by the construction mark adding means include a predetermined range including the specified predetermined point. Since it is composed of an enlarged display means for enlarging display including C, it is possible to notify the distribution work location over a wide range in real time.

また、端末装置12,13が配電工事の発注元又は電力の一般需要家に設置されるものであるから、配電工事の発注元である電力供給会社においては配電工事の進捗状況をリアルタイムで把握することができ、また、電力の一般需要家においても配電工事情報をリアルタイムで入手することができる。   In addition, since the terminal devices 12 and 13 are installed at the distribution orderer or the general consumer of power, the power supply company that is the distribution orderer grasps the progress of the distribution work in real time. In addition, distribution information can be obtained in real time even for general consumers of electric power.

通信回線7に配電工事担当者が所持する携帯端末機14が接続されているので、その携帯端末機14を介して配電工事情報を現場において入力してその情報をサーバ1に送出することができる。また、通信回線7に、配電工事を監視する監視要員が所持する携帯端末機16が接続されているので、その携帯端末機16を介して配電工事情報を現場において入力してその情報をサーバ1に送出することができる。   Since the portable terminal 14 possessed by the person in charge of distribution work is connected to the communication line 7, it is possible to input distribution work information on the site via the portable terminal 14 and send the information to the server 1. . In addition, since the mobile terminal 16 possessed by the monitoring personnel monitoring the power distribution work is connected to the communication line 7, the power distribution work information is input in the field via the mobile terminal 16 and the information is stored in the server 1. Can be sent to.

配電工事箇所を示す所定のマークA,B,Cが、配電工事の予定、配電工事中及び配電工事終了等を区別して表示するから、そのマークの表示内容により配電工事の進捗状況が一目瞭然となる。   Predetermined marks A, B, and C indicating the location of power distribution work indicate the distribution work schedule, during power distribution work, and the completion of power distribution work, etc., so the progress of the power distribution work becomes clear at a glance depending on the display contents of the mark .

サーバ1に、配電工事の受託業務を管理する受託業務管理用処理装置8が接続されているので、受託業務の自動化を図ることができる。また、サーバ1には配電工事の工程を管理する工程管理用処理装置9が接続されることで、工程管理表を自動作成することができる。サーバ1に配電工事で用いられる部品、材料又は機材を手配する材料管理用処理装置10が接続されることで、配電工事で用いられる部品、材料、機材その他の配電工事用資材を自動的に手配することができる。サーバ1に配電工事に伴う精算処理業務を管理する精算管理用処理装置11が接続されることで、精算処理業務の自動化を図ることができる。   Since the server 1 is connected to the processing apparatus 8 for managing the commissioned work for managing the commissioned work for the power distribution work, the commissioned work can be automated. In addition, a process management table 9 can be automatically created by connecting the server 1 with a process management processing device 9 that manages the process of power distribution work. By connecting the server 1 with a material management processing device 10 that arranges parts, materials, or equipment used in power distribution work, parts, materials, equipment, and other materials used in power distribution work are automatically arranged. can do. When the settlement management processing device 11 that manages the settlement processing work associated with the power distribution work is connected to the server 1, the settlement processing work can be automated.

尚、上記の課題を解決するための手段、発明の効果の項夫々において付記した符号は、図面中に記載した構成各部を示す部分との参照を容易にするために付した。本発明は図面中の符号によって示された構造・形状等に限定されない。   In addition, the code | symbol attached | subjected in the means for solving said subject, and each item of the effect of invention was attached | subjected in order to make easy reference with the part which shows each structure part described in drawing. The present invention is not limited to the structure and shape indicated by the reference numerals in the drawings.

以下図面を参照して本発明を実施するための最良の形態を説明する。図1は本発明に係る配電工事管理システムのブロック図であって、図中の符号1は、配電工事を施工する工事担当業者における例えば管理部門(図示では施工会社の本社)に設置されている、比較的大型のコンピュータからなるサーバである。すなわち、このサーバ1はメモリ2に格納されている所定のシステムプログラム及びワーキングデータを用いて所定の演算処理を行う演算部(CPU)3を有している。   The best mode for carrying out the present invention will be described below with reference to the drawings. FIG. 1 is a block diagram of a power distribution work management system according to the present invention. Reference numeral 1 in the figure is installed in, for example, a management department (in the drawing, the head office of a construction company) in a construction contractor who performs power distribution work. A server composed of a relatively large computer. That is, the server 1 includes a calculation unit (CPU) 3 that performs a predetermined calculation process using a predetermined system program and working data stored in the memory 2.

この演算部(CPU)3には、地図データ記憶部4が接続されている。地図データ記憶部4には、配電工事施工業者が担当する地域の地図情報(後述する図3参照)が記憶されている。この地図データ記憶部4への地図データの記憶は入力ユニット5を介して入力することもできるが、通信制御部6を介して外部から入力して最新の地図情報が記憶できるように構成されている。すなわち、通信制御部6及びインターネットを含んで構成される通信回線7を介して地図情報提供業者から提供されている地図情報を取り込んで地図データ記憶部4に記憶されている。なお、地図情報は地図情報提供業者が提供する地図データにリンクさせることで、この地図データ記憶部4を含めないで構成することもできる。   A map data storage unit 4 is connected to the calculation unit (CPU) 3. The map data storage unit 4 stores map information (see FIG. 3 to be described later) of the area in charge of the power distribution construction contractor. The storage of the map data in the map data storage unit 4 can be input via the input unit 5, but is configured so that the latest map information can be stored by inputting from the outside via the communication control unit 6. Yes. That is, the map information provided by the map information provider via the communication control unit 6 and the communication line 7 including the Internet is taken in and stored in the map data storage unit 4. The map information can be configured without the map data storage unit 4 by linking to the map data provided by the map information provider.

入力ユニット5はキーボードやテンキー等の公知の入力機器を含んで構成されていて、配電工事の発注元である電力供給会社から配電工事を受託(受注)したときに、その受託に係る所定の工事内容その他の配電工事に係る各種のデータ等の工事内容データを入力できるように構成されている。この工事内容データは配電工事の行われる例えば電柱の識別データ、設計事項・期限・時期・場所その他の工事内容等で形成されている。なお、この工事内容データの入力は、その全部又は一部を配電工事の発注元(電力供給会社)の配電管理用ホストコンピュータから通信制御部6及び通信基地局を介して自動的に取り込むようにしても良い。   The input unit 5 is configured to include known input devices such as a keyboard and a numeric keypad, and when the distribution work is entrusted (order received) from the power supply company that is the orderer of the distribution work, the predetermined construction related to the entrustment is performed. The work content data such as various data related to the content and other power distribution work can be input. This construction content data is formed by, for example, identification data of telephone poles for which power distribution work is performed, design matters, deadlines, timing, places, and other construction details. Note that all or a part of the construction content data is automatically input from the distribution management host computer of the distribution work orderer (power supply company) via the communication control unit 6 and the communication base station. May be.

工事内容として、一般に表示される情報は、例えば工事地の住所・地域名称、規制範囲、工事開始・終了予定日、工事規模、地上・地下・架空等の区別、その他とすることができる。   Information generally displayed as the contents of construction can be, for example, the address / region name of the construction site, the scope of regulation, the scheduled start / end date of construction, the scale of construction, the distinction between ground, underground, aerial, etc.

また図中符号6は演算部(CPU)3に接続されている出力ユニットであり、表示画面及びプリンタ等からなる公知の出力機器で構成されている。また、演算部(CPU)3には、通信制御部6を介して配電工事の発注元から配電工事を受託したときの受託台帳や品質計画書等の配電工事受託に伴う帳票を作成する、コンピュータを中心に構成される受託業務管理用処理装置8が接続されている。また、配電工事の工程を個別に画面表示できるようにすると共に、設計書の所在等を統括的に管理する、コンピュータを中心に構成される工程管理用処理装置9が接続されている。また、配電工事に必要なクランプ等の部品、電線等の材料、機材等の配電工事用の各種の資材を手配するとともに、在庫管理を行う、コンピュータを中心に構成される材料管理用処理装置10が接続されている。また、配電工事に伴う費用の請求金額を処理するとともに、期末においては設計書棚卸を自動集計する、コンピュータを中心に構成される精算管理用処理装置11が接続されている。なお、上述の各処理装置8,…11は、サーバ1と別体構成とされているが、各処理装置8,…11の機能の一部又は全部をサーバ1に持たせるようにしてもよい。   Reference numeral 6 in the figure denotes an output unit connected to the calculation unit (CPU) 3 and is composed of a known output device including a display screen and a printer. In addition, the computing unit (CPU) 3 is a computer that creates a form accompanying a power distribution work contract such as a consignment ledger and a quality plan when the power distribution work is commissioned from a distribution work ordering source via the communication control unit 6. Is connected to a processing apparatus 8 for contracted work management. Further, a process management processing device 9 mainly connected to a computer is connected to the power distribution work process so that the process can be individually displayed on the screen, and the location of the design document and the like are managed in an integrated manner. In addition, a material management processing apparatus 10 mainly composed of a computer that arranges various materials for power distribution work such as clamps necessary for power distribution work, materials such as electric wires, and equipment, and inventory management. Is connected. In addition, a billing management processing device 11 mainly connected to a computer is connected, which processes the amount charged for the costs associated with power distribution work and automatically totals the design inventory at the end of the period. In addition, although each said processing apparatus 8, ... 11 is made into the different structure from the server 1, you may make it give the server 1 a part or all of the function of each processing apparatus 8, ... 11. .

図中符号12は、配電工事の発注元である電力供給会社に設置されていて通信回線7に接続されている、サーバ1に対応するクライアントに相当するパーソナルコンピュータからなる端末装置である。同じく符号13は、電力の一般需要家である一般家庭、工場、事務所等に設置されていて通信回線7に接続されている端末装置(クライアント)である。   Reference numeral 12 in the figure is a terminal device that is installed at a power supply company that is an orderer of power distribution work and is connected to the communication line 7 and is composed of a personal computer corresponding to a client corresponding to the server 1. Similarly, reference numeral 13 denotes a terminal device (client) that is installed in a general household, a factory, an office, or the like that is a general consumer of electric power and connected to the communication line 7.

図中符号14は、通信基地局15を介して通信回線7に接続される配電工事の作業員が所持する無線通信機能を有する携帯端末機である。また符号16は、同様に通信基地局15を介して通信基地局に接続される、配電工事を監視する監視要員が所持する無線機能を有する携帯端末機である。これら携帯端末機14,16は、公知のPADを用いることもできる。また、携帯電話機(PHSを含む)に情報入力機能を持たせて携帯端末機とすることもできる。   Reference numeral 14 in the figure denotes a portable terminal device having a wireless communication function possessed by a power distribution worker connected to the communication line 7 via the communication base station 15. Reference numeral 16 denotes a portable terminal having a wireless function possessed by a monitoring person who monitors power distribution work, which is similarly connected to the communication base station via the communication base station 15. These portable terminals 14 and 16 can also use known PADs. In addition, a mobile phone (including PHS) can be provided with an information input function to be a mobile terminal.

次に図2のフローチャートを用いてサーバ1における地図データ記憶部4へのデータ記憶制御動作について説明する。今、配電工事の発注元(電力供給会社)から所定の配電工事の受託があったとする(ステップ100工程。以下ステップ「S」とする。)。この場合、入力ユニット5を介してその配電工事を設定する所定の識別情報(以下「ID」という)、施工日時情報、配電工事に係る電柱ID、工事内容等の所定の工事内容が入力される(S102)。   Next, the data storage control operation to the map data storage unit 4 in the server 1 will be described using the flowchart of FIG. Now, it is assumed that a predetermined distribution work has been entrusted from a power distribution company (power supply company) (step 100, hereinafter referred to as step “S”). In this case, predetermined construction information such as predetermined identification information (hereinafter referred to as “ID”), construction date and time information, power pole ID related to the power distribution work, construction content, etc. is set via the input unit 5. (S102).

入力ユニット5によって所定の工事内容に係る各種のデータが入力されると、配電工事の施工場所が決まるので、その施工に係る設置電柱その他の場所が確定する。すると、その設置場所に対応する地図データ記憶部4に記憶されている地図データ情報中に、配電工事の予定を示す所定の工事予定マークAが付加される(S104)。すなわち、地図データ記憶部4には配電工事の施工業者が担当する地域の地図情報が記憶されているので、この中に工事予定を示す所定の工事予定マーク(後述する図6の符号A参照)の情報が付加される。   When various types of data related to predetermined construction contents are input by the input unit 5, the installation location of the power distribution work is determined, so that the installed power pole and other locations related to the construction are determined. Then, a predetermined construction schedule mark A indicating the schedule of the power distribution work is added to the map data information stored in the map data storage unit 4 corresponding to the installation location (S104). That is, since the map data storage unit 4 stores the map information of the area in charge of the distribution contractor, a predetermined construction schedule mark indicating the construction schedule (see reference numeral A in FIG. 6 described later). Is added.

このように配電工事の予定を示す工事予定マークAが付加された地図情報は配電工事用の所定日数前(例えば10日前)になると、通信回線(インターネット)7を介して公開されるように構成されている(S106工程、S108)。そして、この公開された地図情報において、配電工事中は工事中マークBが表示され、配電工事終了後は工事終了マークCに切替表示され、数日(例えば10日)経過すると配電工事に係る全てのマークが消去されるように構成されている(S110工程)。   Thus, the map information to which the construction schedule mark A indicating the schedule of the power distribution work is added is made public via the communication line (Internet) 7 when a predetermined number of days before the power distribution work (for example, 10 days before). (S106 step, S108). In the published map information, the construction mark B is displayed during the power distribution work, and after the power distribution work is completed, it is switched to the work completion mark C. After several days (for example, 10 days), all of the power distribution work The mark is erased (step S110).

次に図4のフローチャートを用いて配電工事の発注元(電力供給会社)の有する端末装置12及び一般需要家の有する端末装置13を用いた配電工事の入手方法について説明する。なお、両装置12,13の情報入手方法は同じであるので、ここでは一般需要家の端末装置13を例に説明する。なお、この配電工事情報は通信回線(インターネット)7に接続されている端末装置であれば制限なく入手することができる。したがって、道路交通情報を提供している業者等においても入手でき、その入手した配電工事情報を基に適切な道路交通情報を提供することができる。   Next, a method for obtaining power distribution work using the terminal device 12 possessed by the orderer (power supply company) of the power distribution work and the terminal device 13 possessed by the general consumer will be described using the flowchart of FIG. In addition, since the information acquisition method of both the apparatuses 12 and 13 is the same, it demonstrates here taking the terminal device 13 of a general consumer as an example. The power distribution work information can be obtained without limitation as long as it is a terminal device connected to the communication line (Internet) 7. Therefore, it can also be obtained by a trader or the like who provides road traffic information, and appropriate road traffic information can be provided based on the obtained power distribution work information.

さて、今、一般需要家の有する端末装置13が起動されて配電工事検索モードにされたとする(S200工程)。このモード設定により、その端末装置13の表示画面には、図3に示される配電工事の施工業者が担当する全体地図が表示される(S202)。そして、一般需要家が例えば、自分の家の近くを指定すると(クリックすると)(S204工程)、その指定された地域(例えば工事施工会社における営業所・営業管轄単位)を含む第1の拡大された地図情報の内容が表示される(S206)。この第1の拡大された地図情報の一例が図5に示されており、これは周辺地域に比し例えば1.2〜1.5倍程度で拡大表示されて選択した地域が一目でわかるようにしている。   Now, it is assumed that the terminal device 13 of a general consumer is activated and is set to a distribution work search mode (step S200). With this mode setting, the entire screen in charge of the power distribution contractor shown in FIG. 3 is displayed on the display screen of the terminal device 13 (S202). For example, when the general consumer designates the vicinity of his / her own house (clicking) (step S204), the first enlarged area including the designated area (for example, a sales office / business jurisdiction unit in a construction company) is expanded. The contents of the map information are displayed (S206). An example of the first enlarged map information is shown in FIG. 5, which is enlarged and displayed, for example, about 1.2 to 1.5 times the surrounding area so that the selected area can be seen at a glance. I have to.

第1の拡大された地図によって、確認しようとする地域を明瞭にでき、例えば自分の家の近くを指定することが可能となる。一般需要家がその第1の拡大表示された地図の所定箇所を詳しく指定すると(クリックすると)、図6に示されるような第1の拡大された地図よりもさらに拡大された第2の地図情報の内容が表示される(S208工程、S210)。この第2の拡大された地図中には工事の進捗状況に対応して、黒丸(図6の符号A参照)で示される配電工事の予定を示す工事予定マーク、作業中の車両(図6の符号B参照)で示される配電工事中を示す工事中マーク、及び白丸(図6の符号C参照)で示される配電工事終了を示す工事終了マークが表示される。   The first enlarged map makes it possible to clarify the area to be confirmed, for example, to specify the vicinity of his / her home. When a general consumer designates a predetermined location of the first enlarged map in detail (clicking), the second map information further enlarged than the first enlarged map as shown in FIG. Is displayed (steps S208 and S210). In the second enlarged map, a construction schedule mark indicating a schedule of power distribution work indicated by a black circle (see symbol A in FIG. 6), a vehicle under construction (in FIG. 6), corresponding to the progress of construction. A work in progress mark indicating that the power distribution work is being performed indicated by a symbol B) and a work completion mark indicating the end of the power distribution work indicated by a white circle (refer to the symbol C in FIG. 6) are displayed.

上述の工事予定マークAは、上述したように入力ユニット5を介して工事内容の入力により付加される。そして、工事中マークB及び工事終了マークCは、配電工事の作業員が所持する携帯端末機14から配電工事の開始に先立って、作業中を示す所定の情報がサーバ1に受信されたときに工事予定マークAが工事中マークBに切り換えられる。さらに、その配電工事が終了したときに、その携帯端末機14から工事終了を示す所定の情報がサーバ1に受信されたときに工事中マークBが工事終了マークCに切り換えられる。   The construction schedule mark A described above is added by inputting construction details via the input unit 5 as described above. The construction in progress mark B and the construction end mark C are received when the server 1 receives predetermined information indicating that the work is in progress prior to the start of the power distribution work from the portable terminal 14 possessed by the worker of the power distribution work. The construction schedule mark A is switched to the construction mark B. Further, when the power distribution work is completed, the construction mark B is switched to the work completion mark C when the server 1 receives predetermined information indicating the completion of the work from the mobile terminal 14.

一般需要家によって配電工事に係る所定マークA,B,Cの箇所が指定されると(クリックされると)、さらに詳細な情報が表示される現場拡大地図の内容(図4のフローチャートでは第3の拡大された表示)が表示される(S212工程、S214)。この詳細な情報を表示する現場拡大地図は、画面における第2の拡大地図上にダイアログ的に重ねて表示され、ドラッグ操作によって画面上で移動可能にしてある。図7は図6中にある一つの配電工事の予定を示す工事予定マークAが指定されたときの現場拡大地図の内容の一例である(図7中の符号Aは工事予定マークを示している。)。図8は、図6中のある一つの配電工事中を示す工事中マークBが指定されるときの現場拡大地図の内容の一例である(図8中の符号Bは工事中マークを示している。)。そして、図9は図6中のある一つの配電工事の終了を示す工事終了マークCが指定されたときの現場拡大地図の内容の一例である(図9中の符号Cは工事終了マークを示している。)。これらの工事内容の進捗状況に関する情報の表示は配電工事検索モード終了まで行われる(S216工程)。これらの詳細な現場拡大地図では、地図表示と共に配電工事現場の住所地が掲載され、施工会社のメッセージも表示されるようにしている。   When the location of the predetermined marks A, B, and C related to power distribution work is designated (clicked) by a general customer, the details of the on-site enlarged map in which more detailed information is displayed (the third in the flowchart of FIG. 4) Is displayed) (steps S212 and S214). The on-site enlarged map for displaying this detailed information is displayed in a dialog-like manner on the second enlarged map on the screen, and can be moved on the screen by a drag operation. FIG. 7 is an example of the contents of the site expansion map when the construction schedule mark A indicating the schedule of one power distribution work in FIG. 6 is designated (the symbol A in FIG. 7 indicates the construction schedule mark). .) FIG. 8 is an example of the contents of the on-site enlarged map when a construction mark B indicating that one power distribution work in FIG. 6 is designated (the symbol B in FIG. 8 indicates the construction mark). .) FIG. 9 is an example of the contents of the site expansion map when the construction end mark C indicating the end of one distribution work in FIG. 6 is designated (the reference C in FIG. 9 indicates the construction end mark). ing.). The display of information regarding the progress status of these construction contents is performed until the distribution work search mode is completed (step S216). In these detailed site expansion maps, the address of the distribution work site is posted along with the map display, and the message of the construction company is also displayed.

上述のように本発明に係る配電工事管理システムは、端末装置12,13を介して広く配電工事の状況をリアルタイムに報知できる特長を有している。又、サーバ1には配電工事を監視する監視員の所持する携帯端末機16からも情報が入力されるので、例えば追加工事が必要な場合であっても速やかに対処することができる。   As described above, the power distribution work management system according to the present invention has a feature that it can widely notify the status of power distribution work in real time via the terminal devices 12 and 13. Further, since information is also input to the server 1 from the portable terminal 16 possessed by the supervisor who monitors the power distribution work, for example, even if additional work is required, it can be dealt with promptly.

加えて、作業員の所持する携帯端末機14からは、配電工事のIDとともにその進み具合がサーバ1に入力されるので、工程管理が自動的に行えるだけでなく、作業日報等の日常業務に係る各種報告書等の書類作成が自動化されるという特長を有している。   In addition, since the progress of the distribution work ID is input to the server 1 from the portable terminal 14 possessed by the worker, not only the process management can be automatically performed but also daily work such as daily work reports. It has a feature that the creation of documents such as various reports is automated.

なお、上述の例では端末装置12,13に表示する地図情報は3段階に拡大して表示するようにしたが、これを2段階にすることもできる。この場合は、図3に示される当初の表示内容から図5に示される内容が省略されて、例えば図6に示される内容とされる。   In the above-described example, the map information displayed on the terminal devices 12 and 13 is enlarged and displayed in three stages. However, this can be made in two stages. In this case, the content shown in FIG. 5 is omitted from the initial display content shown in FIG. 3, and the content shown in FIG. 6, for example, is obtained.

本発明に係る配電工事管理システムは、電力供給の配電設備、特にそのケーブル敷設経路における各種の配電工事の進捗状況のリアルタイムな把握を可能とさせるも、これを各種の工事管理システムに利用することもできる。例えば水道工事、ガス工事更には各種の道路工事における進捗状況の報知に応用することができる。   The distribution work management system according to the present invention makes it possible to grasp in real time the progress status of various power distribution works in the power distribution facilities, in particular, the cable laying route. You can also. For example, it can be applied to notification of progress in waterworks, gas works and various road works.

本発明に係る配電工事管理システムのブロック図である。It is a block diagram of a power distribution work management system according to the present invention. 制御動作を示すフローチャートである。It is a flowchart which shows control operation. 配電工事の施工業者が担当する地図情報の内容の一例である。It is an example of the content of the map information which the construction contractor of power distribution construction takes charge of. 制御動作を示すフローチャートである。It is a flowchart which shows control operation. 第1の拡大された地図情報の内容の一例である。It is an example of the content of the 1st enlarged map information. 第2の拡大された地図情報の内容の一例である。It is an example of the content of the 2nd expanded map information. 配電工事の工事予定マークが表示された現場拡大地図の一例である。It is an example of the site expansion map on which the construction schedule mark of power distribution work is displayed. 配電工事中を示す工事中マークが表示された現場拡大地図の一例である。It is an example of the site expansion map on which the under construction mark indicating that the power distribution work is in progress is displayed. 配電工事終了を示す工事終了マークが表示された現場拡大地図の一例である。It is an example of the site expansion map in which the construction completion mark which shows the distribution work completion is displayed.

符号の説明Explanation of symbols

1…サーバ 2…メモリ
3…演算部(CPU) 4…地図データ記憶部
5…入力ユニット 6…通信制御部
7…通信回線 8…受託業務管理用処理装置
9…工程管理用処理装置 10…材料管理用処理装置
11…精算管理用処理装置 12…端末装置
13…端末装置 14…携帯端末機
15…通信基地局 16…携帯端末機
A…工事予定マーク B…工事中マーク
C…工事終了マーク
DESCRIPTION OF SYMBOLS 1 ... Server 2 ... Memory 3 ... Operation part (CPU) 4 ... Map data memory | storage part 5 ... Input unit 6 ... Communication control part 7 ... Communication line 8 ... Processing apparatus 9 for consigned work management ... Process management processing apparatus 10 ... Material Management processing device 11 ... Payment management processing device 12 ... Terminal device 13 ... Terminal device 14 ... Mobile terminal 15 ... Communication base station 16 ... Mobile terminal A ... Construction schedule mark B ... Under construction mark C ... Construction end mark

Claims (9)

配電工事を担当する所定の地域を含む地図情報を表示するよう管理部門に設置されているサーバと、サーバと通信回線を介して接続されている端末装置と、予定されている配電工事に係る所定の工事内容をサーバに入力する工事内容入力手段と、工事内容入力手段を介して入力された所定の工事内容に基づいて地図情報中に配電工事箇所を示す所定のマークを付加する工事マーク付加手段と、端末装置の表示画面に地図情報の内容を表示する地図情報表示手段と、端末装置の表示画面に表示されている地図上の所定の地点を指定する指定手段と、指定手段により指定された所定の地点を含む所定範囲を工事マーク付加手段により付加された所定マークを含めて拡大表示する端末表示手段とを有することを特徴とする配電工事管理システム。   A server installed in the management department to display map information including a predetermined area in charge of power distribution work, a terminal device connected to the server via a communication line, and a predetermined power distribution work Construction content input means for inputting the construction content of the server to the server, and construction mark addition means for adding a predetermined mark indicating the distribution work location in the map information based on the predetermined construction content input via the construction content input means A map information display means for displaying the contents of the map information on the display screen of the terminal device, a designation means for designating a predetermined point on the map displayed on the display screen of the terminal device, and a designation means designated by the designation means A power distribution work management system comprising terminal display means for enlarging and displaying a predetermined range including a predetermined point including the predetermined mark added by the work mark adding means. 請求項1に記載の配電工事管理システムにおいて、端末装置は、配電工事の発注元又は電力の一般需要家に設置されるものであることを特徴とする配電工事管理システム。   2. The distribution work management system according to claim 1, wherein the terminal device is installed at an ordering party of distribution work or a general consumer of electric power. 請求項1又は2に記載の配電工事管理システムにおいて、通信回線には、配電工事担当者が所持する携帯端末機が接続されていることを特徴とする配電工事管理システム。   3. The distribution work management system according to claim 1 or 2, wherein a portable terminal possessed by a person in charge of the distribution work is connected to the communication line. 請求項1乃至3のいずれかに記載の配電工事管理システムにおいて、通信回線には、配電工事を監視する監視要員が所持する携帯端末機が接続されていることを特徴とする配電工事管理システム。   4. The distribution work management system according to claim 1, wherein a portable terminal possessed by a monitoring person who monitors the distribution work is connected to the communication line. 請求項1乃至4のいずれかに記載の配電工事管理システムにおいて、配電工事箇所を示す所定のマークは、配電工事の予定、配電工事中及び配電工事終了を区別して表示するものであることを特徴とする配電工事管理システム。   The distribution work management system according to any one of claims 1 to 4, wherein the predetermined mark indicating the location of the power distribution work distinguishes between the schedule of the power distribution work, during the power distribution work, and the end of the power distribution work. Distribution system management system. 請求項1乃至5のいずれかに記載の配電工事管理システムにおいて、配電工事の受託業務を管理する受託業務管理用処理装置が接続されていることを特徴とする配電工事管理システム。   6. The distribution work management system according to claim 1, further comprising a contract work management processing device for managing the trust work of the power distribution work. 請求項1乃至6のいずれかに記載の配電工事管理システムにおいて、サーバは配電工事の工程を管理する工程管理用処理装置が接続されていることを特徴とする配電工事管理システム。   The distribution work management system according to any one of claims 1 to 6, wherein the server is connected to a process management processing device for managing a distribution work process. 請求項1乃至7のいずれかに記載の配電工事管理システムにおいて、サーバは配電工事で用いられる部品、材料、機材その他の配電工事用資材を手配する材料管理用処理装置が接続されていることを特徴とする配電工事管理システム。   The distribution management system according to any one of claims 1 to 7, wherein the server is connected to a material management processing device that arranges parts, materials, equipment and other materials used in the distribution. A distribution system management system that is characterized. 請求項1乃至8のいずれかに記載の配電工事管理システムにおいて、サーバには、配電工事に伴う精算処理業務を管理する精算管理用処理装置が接続されていることを特徴とする配電工事管理システム。
9. The distribution work management system according to claim 1, wherein a settlement management processing device for managing a settlement process associated with the distribution work is connected to the server. .
JP2006227276A 2006-08-24 2006-08-24 Power distribution construction management system Pending JP2008052461A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006227276A JP2008052461A (en) 2006-08-24 2006-08-24 Power distribution construction management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006227276A JP2008052461A (en) 2006-08-24 2006-08-24 Power distribution construction management system

Publications (1)

Publication Number Publication Date
JP2008052461A true JP2008052461A (en) 2008-03-06

Family

ID=39236467

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006227276A Pending JP2008052461A (en) 2006-08-24 2006-08-24 Power distribution construction management system

Country Status (1)

Country Link
JP (1) JP2008052461A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011141625A (en) * 2010-01-05 2011-07-21 Chugoku Electric Power Co Inc:The Construction work management device, construction work management system, and construction work management method
JP2012234231A (en) * 2011-04-28 2012-11-29 Nakanihon Kensetsu Consultant Kk Site investigation support system and program therefor
CN104091514A (en) * 2014-07-24 2014-10-08 国网浙江奉化市供电公司 Power grid dispatching personnel training simulation system
US10540890B2 (en) 2016-12-12 2020-01-21 Toyota Jidosha Kabushiki Kaisha Construction-related information estimation system
JP2020144716A (en) * 2019-03-07 2020-09-10 OpenStreet株式会社 Information processor, information processing method, and information processing program
JP2021117897A (en) * 2020-01-29 2021-08-10 東京瓦斯株式会社 Assistance system and program
JP7494091B2 (en) 2020-10-29 2024-06-03 東京瓦斯株式会社 Construction management device and construction management method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030808A (en) * 2000-07-19 2002-01-31 Ktk Telecommunications Engineering Co Ltd Electronic work control system
JP2003295757A (en) * 2002-03-29 2003-10-15 Osaka Gas Co Ltd Application permission and managing system and construction managing system
JP2004104375A (en) * 2002-09-09 2004-04-02 Haruta Kazuhiko Information transmission method system
JP2004178454A (en) * 2002-11-29 2004-06-24 Asahi Tsushin Kk Construction business integration management system and method
JP2005295701A (en) * 2004-03-31 2005-10-20 Chugoku Electric Power Co Inc:The Power distribution automation system and power interruption work management method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030808A (en) * 2000-07-19 2002-01-31 Ktk Telecommunications Engineering Co Ltd Electronic work control system
JP2003295757A (en) * 2002-03-29 2003-10-15 Osaka Gas Co Ltd Application permission and managing system and construction managing system
JP2004104375A (en) * 2002-09-09 2004-04-02 Haruta Kazuhiko Information transmission method system
JP2004178454A (en) * 2002-11-29 2004-06-24 Asahi Tsushin Kk Construction business integration management system and method
JP2005295701A (en) * 2004-03-31 2005-10-20 Chugoku Electric Power Co Inc:The Power distribution automation system and power interruption work management method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"いまどきのケータイをビジネスに生かす", 日経INTERNET SOLUTIONS, vol. 第77号, JPN6009014389, 22 November 2003 (2003-11-22), JP, pages 44 - 47, ISSN: 0001285269 *
湯野康隆, KDDI、GPSケータイを利用した位置情報管理サービス, JPN6009014386, 18 July 2002 (2002-07-18), ISSN: 0001285270 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011141625A (en) * 2010-01-05 2011-07-21 Chugoku Electric Power Co Inc:The Construction work management device, construction work management system, and construction work management method
JP2012234231A (en) * 2011-04-28 2012-11-29 Nakanihon Kensetsu Consultant Kk Site investigation support system and program therefor
CN104091514A (en) * 2014-07-24 2014-10-08 国网浙江奉化市供电公司 Power grid dispatching personnel training simulation system
US10540890B2 (en) 2016-12-12 2020-01-21 Toyota Jidosha Kabushiki Kaisha Construction-related information estimation system
JP2020144716A (en) * 2019-03-07 2020-09-10 OpenStreet株式会社 Information processor, information processing method, and information processing program
JP2021117897A (en) * 2020-01-29 2021-08-10 東京瓦斯株式会社 Assistance system and program
JP7494091B2 (en) 2020-10-29 2024-06-03 東京瓦斯株式会社 Construction management device and construction management method

Similar Documents

Publication Publication Date Title
US9177280B2 (en) Methods, apparatus, and systems for acquiring an enhanced positive response for underground facility locate and marking operations based on an electronic manifest documenting physical locate marks on ground, pavement, or other surface
US8280969B2 (en) Methods, apparatus and systems for requesting underground facility locate and marking operations and managing associated notifications
JP2008052461A (en) Power distribution construction management system
JP2014174852A (en) Information provision device, contractor management device, information presentation device, program, communication system, and information provision method
KR20100035481A (en) Real time construction management system and method using personal digital assistant(pda) being linked with geographic information system(gis)
US20090157488A1 (en) Work order management system and method
JP4684043B2 (en) Power facility information provision system
JP2006268717A (en) Civil engineering cost integration system
JP6348335B2 (en) Electronic application data processing system, electronic application data processing method, and program
JP5197556B2 (en) Stamp service-linked map providing apparatus, method, and program
US11386364B1 (en) Construction project information and document access system
JP2009187244A (en) Information providing system for mobile terminal and information providing method for mobile terminal
JP5652907B2 (en) Distribution status confirmation system, method and program
JP4625191B2 (en) Land brokerage system, land brokerage method, and land brokerage program
JP2004295286A (en) Gas fitting work management system
JP2002366718A (en) Method and system for work information management
JP4010495B2 (en) Facility management business support system
KR102471034B1 (en) Home repair service system, server and method
JP4595723B2 (en) Security control system
JP2021196973A (en) Material management method, program and material management system
JP2019133296A (en) Device, method and program for job assistance for craftsmen
JP2005148338A (en) Method, system, and program for geographic information use, and information recording medium readable by computer

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090331

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090525

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090623

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20091110