JP2007334683A - Planning method, planning system, and planning program of facility for safe evacuation of building - Google Patents

Planning method, planning system, and planning program of facility for safe evacuation of building Download PDF

Info

Publication number
JP2007334683A
JP2007334683A JP2006166510A JP2006166510A JP2007334683A JP 2007334683 A JP2007334683 A JP 2007334683A JP 2006166510 A JP2006166510 A JP 2006166510A JP 2006166510 A JP2006166510 A JP 2006166510A JP 2007334683 A JP2007334683 A JP 2007334683A
Authority
JP
Japan
Prior art keywords
evacuation
smoke
time
room
facility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006166510A
Other languages
Japanese (ja)
Inventor
Tsutomu Nagaoka
勉 長岡
Shigeo Uehara
茂男 上原
Shonosuke Ozeki
昭之介 尾関
Kazuyuki Miyata
和幸 宮田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2006166510A priority Critical patent/JP2007334683A/en
Publication of JP2007334683A publication Critical patent/JP2007334683A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Alarm Systems (AREA)
  • Fire Alarms (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a planning method, a planning system, and a planning program for automatically changing a facility condition for safe evacuation of a building and verifying the safety thereof, and designating the priority when changing the condition. <P>SOLUTION: The degree of smoke spreading to the periphery from a fire breaking room in a building is simulated. The smoke fall time from the generation of a fire until an evacuating person hardly breathes due to the fall of the smoke from a ceiling in rooms 2, 4, etc., and in a passage 10 is calculated, and compared with the evacuation time required for a resident to evacuate from an arbitrary room to the outside of the room or to an evacuation gate from a floor of the room after the fire breaks. If the smoke fall time is longer than the evacuation time, the facility condition is acceptable. If the smoke fall time is shorter than the evacuation time, the facility condition is not acceptable. By repeating the above-described processes by improving the facility condition, a plurality of countermeasures are prepared, the ranking is given thereto based on the economical efficiency or the like, and the facility condition is automatically improved. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、建物の安全避難のための設備のプランニング方法、プランニングシステム、及びプランニング用のプログラム、特に避難安全検証法に適合する安全避難のためのプランニングを行うための方法、システム及びプログラムに関する。   The present invention relates to a facility planning method, a planning system, and a planning program for safe evacuation of a building, and more particularly to a method, system, and program for performing planning for safe evacuation that conforms to the evacuation safety verification method.

近年、火災に対する建物の安全な避難経路の確保が強く要請されている。この要請に応えるために避難安全検証法が規定されており、この法律は、次の計算方法を定めている。
(a)火災室に居る人(火災室を通らないと逃げられない人を含む)が室外に安全に避難できることを確認すること(居室避難計算)。
(b)火災室を含む検証階に居る人(その階を通らないと逃げられない人を含む)がその階から避難できることを確認すること(階避難計算)。
(c)建物全体からの避難を検討すること(全館避難計算)。
In recent years, there has been a strong demand for securing safe evacuation routes for buildings against fire. In order to respond to this request, the Evacuation Safety Verification Law has been defined, and this law defines the following calculation method.
(a) Confirm that people in the fire room (including those who cannot escape without passing through the fire room) can safely evacuate outside (room evacuation calculation).
(b) Confirm that people on the verification floor including the fire room (including those who cannot escape without passing through that floor) can evacuate from that floor (floor evacuation calculation).
(c) Consider evacuation from the entire building (entire evacuation calculation).

このうち(a)では、図9に示す如く、検証を行う階にある居室毎に、全居室者が居室外へ避難するための居室避難終了時間(=避難開始時間+歩行時間+出口通過時間)と、煙が居室の床面から所定の高さ(1.8m)のところまで降下するのに要する煙等降下時間とをそれぞれ計算する。そして前者が後者よりも短ければ居室からの安全避難が検証されたものとする。また(b)では、図10に示す如く、想定される火災室毎に、検証を行う階に居る全ての者が直通階段への避難を終えるための階避難終了時間と、煙が避難経路の床面から所定高さのところまで降下するのに要する煙等降下時間とをそれぞれ計算する。そして前者が後者よりも短ければ階からの安全避難が検証されたものとする。(c)の説明は省略する。   In (a), as shown in FIG. 9, the room evacuation end time (= evacuation start time + walking time + exit passage time) for all occupants to evacuate outside the room for each room on the floor to be verified. ) And the smoke descent time required for the smoke to descend from the floor of the room to a predetermined height (1.8 m). And if the former is shorter than the latter, the safe evacuation from a living room shall be verified. Also, in (b), as shown in FIG. 10, for each assumed fire room, the floor evacuation end time for all persons on the verification floor to finish evacuation to the direct staircase, and smoke on the evacuation route The smoke descent time required to descend from the floor to a predetermined height is calculated. And if the former is shorter than the latter, the safe evacuation from the floor is verified. The description of (c) is omitted.

これらの避難計算は面倒であるため、計算手順のプログラムを記憶させたコンピュータに簡単に数値を入力できるようにし、機械で計算することが行われている(特許文献1)。   Since these evacuation calculations are cumbersome, numerical values can be easily input to a computer storing a calculation procedure program, and calculation is performed by a machine (Patent Document 1).

また上述の階避難終了時間を計算するためには、避難経路を決定しなければならないが、この経路は、火災室から検証階に存する複数の避難階段口に至る経路のうち最長の経路とするべきものと理解されている。この最長経路は、設計の仕様によって代わってくるため、この避難経路の選定は容易ではない。そこで避難経路を自動的に選定して、避難終了時間を自動的に計算する装置も提案されている(特許文献2)。
特開2002−259467号 特開2004−362004号
In addition, in order to calculate the above-mentioned floor evacuation end time, an evacuation route must be determined. This route is the longest route from the fire room to multiple evacuation stairway exits on the verification floor. It is understood that it should be. Since this longest route changes depending on the design specifications, it is not easy to select this evacuation route. Therefore, an apparatus that automatically selects an evacuation route and automatically calculates an evacuation end time has been proposed (Patent Document 2).
JP 2002-259467 JP2004-362004

特許文献1及び特許文献2の装置は、ある設計仕様の建物に対して居室・階の安全避難の検証を行う際に、データの入力及び最長避難経路の計算を容易に行うことができるというだけであり、一つの仕様の検証結果が不良であった場合には、仕様を変更して再度検証を行わなければならない。この際に、どこをどのように変更すればよいかを作業員の勘に頼るのは、その作業に対する習熟度が問題となり、妥当ではない。また仮に手当たり次第に調べるとすれば膨大な時間を要する。更に実際の設計では、避難の安全性を確保した上で、インテリア性や施工性などの二次的要件が要請されることが多い。     The devices of Patent Document 1 and Patent Document 2 can only easily input data and calculate the longest evacuation route when verifying safe evacuation of a room / floor for a building with a certain design specification. If the verification result of one specification is defective, the specification must be changed and verified again. In this case, it is not appropriate to rely on the intuition of the worker as to where and how to change because the proficiency level of the work is a problem. In addition, if it is checked at random, it takes an enormous amount of time. Furthermore, in actual designs, secondary requirements such as interior and workability are often required while ensuring safety of evacuation.

本発明は、建物の安全避難のための設備のプランニング方法・システム及びプログラムであって、その設備条件の変更と安全性の検証とを連続して自動的に処理することができ、かつその条件を変更する際の優先順位を指定することができるものを提案することを目的とする。     The present invention is a facility planning method / system and program for safe evacuation of a building, which can automatically and continuously process changes in facility conditions and verification of safety. The purpose is to propose the one that can specify the priority order when changing.

第1の手段は、建物の安全避難のための設備のプランニング方法であり、
建物内の一つの階で避難路A,Bに通路10を経て連なる複数の室2,4…の一つから火災が生じたと仮定して、
A.火災室から周囲への煙の広がり具合を煙の経路毎に設備条件に応じてシミュレーションし、
B.シミュレーション結果に基づいて、火災発生時より、各室2,4…及び通路10内でその天井からの煙の降下で避難者の呼吸が困難になる迄の煙降下時間を計算し、
C.この煙降下時間を、火災発生時より、任意の室からの居室者が当該室からその室外へ或いはその室のある階から避難口へ脱出するのに要する避難時間と比較して、
D.煙降下時間が避難時間より長いときには、設備条件を可とし、
E.煙降下時間が避難時間よりも短いときには、設備条件を不可として、上記設備条件を改善して上記A〜Cの行程を繰り返すことを内容とする、安全避難のための設備のプランニング方法において、
上記設備条件の改善策として、発煙条件・排煙条件・遮煙条件・室の形状条件のうちの少なくとも一つを含む複数の方策を設定するとともに、
これら各設備条件の改善策に対して、経済性等のような価値基準に基づいて予め序列を付与して、その序列による順番で機械的に設備条件の改善を試みることを内容としている。
The first means is a facility planning method for safe evacuation of buildings,
Assuming that a fire broke out from one of a plurality of rooms 2, 4 ... connected to the evacuation routes A and B via the passage 10 on one floor in the building,
A. Simulate the spread of smoke from the fire room to the surroundings according to the equipment conditions for each smoke path,
B. Based on the simulation results, calculate the smoke fall time from the time of the fire until the evacuees have difficulty breathing due to the smoke fall from the ceiling in each of the rooms 2, 4.
C. Compared to the evacuation time required for a occupant from any room to escape from the room to the outside of the room or from the floor with the room to the evacuation exit from the time of the fire,
D. When the smoke fall time is longer than the evacuation time, the equipment conditions are acceptable,
E. When the smoke fall time is shorter than the evacuation time, in the facility planning method for safe evacuation, the facility condition is disabled, the facility condition is improved, and the steps A to C are repeated.
As measures to improve the above equipment conditions, a plurality of measures including at least one of smoke generation conditions, smoke emission conditions, smoke shielding conditions, and room shape conditions are set,
The content is to give an order to these measures for improving the equipment conditions in advance based on a value standard such as economic efficiency and to attempt to improve the equipment conditions mechanically in the order of the order.

本手段は、建物の避難安全の検証のための手順と、設備条件の設計・改善のための手順とからなり、良好な結果が得られるまで検証と改善を繰り返すようにしている。こうした手順は単純な演算処理と人間の価値判断との双方を必要とするが、本発明では、予め用意した方策に序列を付けることで全ての処理を自動で行うことができるようにしている。 尚、「機械的に」とは、コンピュータなどの機械で処理するのに適しているという意味で、必ずしも全ての手順を機械でしなければならない訳ではない。   This measure consists of a procedure for verification of building evacuation safety and a procedure for design / improvement of equipment conditions, and verification and improvement are repeated until a satisfactory result is obtained. Such a procedure requires both simple arithmetic processing and human value judgment. However, in the present invention, all processes can be automatically performed by adding an order to prepared measures. Note that “mechanically” means that it is suitable for processing by a machine such as a computer, and all procedures are not necessarily performed by a machine.

「煙降下時間」とは、避難安全検証法にいう居室煙降下時間及び階煙降下時間の何れをも含む概念であり、又「避難時間」とは、同法にいう居室避難時間及び階避難時間の何れも含む概念である。   "Smoke fall time" is a concept that includes both the room smoke fall time and floor smoke fall time referred to in the Evacuation Safety Verification Act, and "evacuation time" refers to the room evacuation time and floor evacuation referred to in the law. It is a concept that includes all of time.

「室」とは、天井と床と壁とで囲われた一定の空間をいう。人の居住に用いられる室を特に居室といい、単に室というときには、機械室などを含むものとする。   A “room” is a certain space surrounded by a ceiling, a floor, and a wall. A room used for a person's residence is particularly called a living room, and a simple room includes a machine room.

「設備条件の改善策」は、例示した排煙条件・排煙条件・遮煙条件・室の形状条件のうち少なくとも一つを含めばよく、これ以外の条件を含んでいても良い。ここで発煙条件とは、室に使用される内装材の種類など発煙量や発煙速度に関する条件であり、排煙条件とは、排気ファンの種類や排煙量の設定値等の排煙設備の能力に関する能力に関する条件であり、遮煙条件とは、防火扉の性能の等級(グレード)などに関する条件であり、また、室の形状条件とは、室の天井の高さや出入口の高さなどの条件である。尚、例えば排煙条件であれば、ファンの種類の変更を伴う排煙量の増加と、変更を伴わない排煙量の増加のように、各種条件に異なる事項が幾つあっても良い。   The “facility improvement measures” may include at least one of the exemplified smoke emission conditions, smoke emission conditions, smoke shielding conditions, and room shape conditions, and may include other conditions. Here, the smoke generation conditions are conditions related to the volume and speed of smoke, such as the type of interior material used in the room, and the smoke emission conditions are the conditions of the smoke exhaust equipment, such as the type of exhaust fan and the set value of the volume of smoke. It is a condition related to the capacity, the smoke shielding condition is a condition related to the grade of the performance of the fire door, and the room shape condition is the height of the ceiling of the room or the height of the entrance / exit It is a condition. For example, in the case of smoke emission conditions, there may be any number of different matters in various conditions, such as an increase in smoke emission amount accompanied by a change in the type of fan and an increase in smoke emission amount not accompanied by a change.

「序列」というのは、どの条件を先に試行するのかの順番をいう。例えば経済性重視の排気条件1(ファンの種類を伴わない排煙量増)→遮煙条件1(防火設備の採用)→遮煙条件2(遮煙防火設備)→排煙条件2(ファンの種類変更を伴う排煙量増)の如くである。同じ条件に関する事柄でも序列が異なるのは、条件の種類が同じであっても、例えば排気ファンを取り替える場合とそうでない場合とでは、施工費に大きな差があるからである。     “Order” refers to the order in which conditions are tried first. For example, exhaustion condition 1 with an emphasis on economy (increased smoke emission without fan type) → smoke prevention condition 1 (adoption of fire prevention equipment) → smoke prevention condition 2 (smoke prevention fire prevention equipment) → smoke emission condition 2 (fan This is like an increase in the amount of smoke that accompanies the type change. The reason why the order is different even for the same condition is that, even if the type of condition is the same, for example, there is a large difference in construction cost between when the exhaust fan is replaced and when it is not.

第2の手段は、第1の手段を有し、かつ
上述の価値基準として、経済性、意匠性、施工性などの種類の異なる基準を設けて、それぞれの基準毎に、予め上記各設備条件の改善策の序列を定めておき、その価値基準を変更することで、設備条件の改善を試みる順番を切り替えることができるようにしている。
The second means includes the first means and, as the above-mentioned value standard, provides different kinds of standards such as economic efficiency, designability, workability, etc., and each equipment condition is previously set for each standard. In order to improve the equipment conditions, the order of improvement measures can be switched by changing the value criteria.

例えば内装を変更することは、防火設備の導入等に比べれば、コスト面から比較的容易に出来るが、意匠面からは材料が限定されるために避けたいという場合がある。逆に排気ファンの種類を変更することは、コスト面からは困難であるが、意匠面からは、建物の内装に手を加える必要がないので、比較的容易に出来る。これらの観点から、各基準毎に序列を定め、例えば施工主の要望に応じて経済性重視の設計、意匠重視の設計など、好適な改善プランを提案することができる。   For example, changing the interior can be relatively easy in terms of cost compared to the introduction of fire prevention equipment, but there are cases where it is desired to avoid the design because the material is limited. On the other hand, changing the type of exhaust fan is difficult from a cost standpoint, but it is relatively easy from a design standpoint because there is no need to modify the interior of the building. From these viewpoints, it is possible to determine an order for each standard, and to propose a suitable improvement plan such as a design with an emphasis on economy and a design with an emphasis on design according to the request of the contractor.

Figure 2007334683
ここで各基準毎に上記の如く方策を配列した理由に関して説明する。経済性重視の基準に関しては、排煙量はファンの変更が生じない範囲なら簡易な変更であり、まずはこの範囲で変更を行う。次に内装の変更を行うが、使用できる内装材に制限が生ずるためにコストへの影響がある。扉のグレード(等級)をあげると、扉コストの増加が生ずる(防火設備・遮煙防火設備共通)。天井高さをあげると、壁の面積が増加しコスト増となる。尚、階高などにより天井高さに制限が生ずる。ファンの変更となる排気量の増加は、ファンと非常用電源のコスト増が生ずるため、出来るだけ避けたい方策である。デザイン重視の基準に関しては、排煙量はデザインには影響しないので、まず最初に検討する。内装材の変更は利用できる壁材に制限が生ずるが、選べる範囲で設計者の意匠に適合したものを選択する。また扉を防火扉などに変更すると扉のデザインが無骨となり易いのでなるべくなら避けたい。更に天井高さの変更は、部屋のイメージが大きく変わるため、出来るだけ避けたい。施工性重視の基準では、経済性重視の基準に近いが、天井高さの変更は工期との関係で避けたいため、ファンの変更を先に検討する。
Figure 2007334683
Here, the reason why the measures are arranged as described above for each reference will be described. With regard to the economy-oriented standard, the smoke emission amount is a simple change if it does not change the fan, and is first changed within this range. Next, the interior is changed, but there is a cost impact because there are restrictions on the interior materials that can be used. Increasing the door grade will increase the door cost (common to fire and smoke and fire prevention equipment). Increasing the ceiling height increases the wall area and costs. The ceiling height is limited by the floor height. The increase in exhaust volume resulting from a change in the fan increases the cost of the fan and the emergency power supply. Regarding design-oriented standards, the amount of flue gas will not affect the design, so we will consider it first. The change of the interior material is limited in the wall material that can be used, but select the one that fits the designer's design within the range that can be selected. Also, if you change the door to a fire door, etc., the door design tends to be rugged, so you should avoid it if possible. In addition, changing the ceiling height should be avoided as much as possible because the image of the room changes greatly. In terms of workability-oriented standards, it is close to the economy-oriented standards, but since it is desirable to avoid changing the ceiling height in relation to the construction period, consider changing the fan first.

尚、表1の内容は好ましい方策の順序の例示であって、適宜変更することができることは言うまでもない。例えば建物の用途や建築主の意向に応じて上記した方策の一部を省略したり、別の方策を追加することもできる。又、異なる基準、例えば上述した施工性重視の基準による方策の順序を、新たな列として表に加えることもできる。     It should be noted that the contents of Table 1 are examples of a preferable policy order, and it is needless to say that the contents can be changed as appropriate. For example, a part of the above-described measures can be omitted or another measure can be added according to the purpose of the building or the intention of the architect. It is also possible to add the order of measures according to different criteria, for example, the above-mentioned criteria for emphasizing workability, as a new column.

第3の手段は、第2の手段を有し、かつ
上述の経済性の価値基準において、複数の方策のうち、排気ファンの排気量の第1の序列とし、かつ2番目以降の方策を試行するにあたって排気量の初期値を零にすることを特徴としている。
The third means has the second means, and in the above-mentioned economic value standard, out of the plurality of measures, the first order of the exhaust fan exhaust amount and the second and subsequent measures are tried. In this case, the initial value of the displacement is set to zero.

本手段では、経済性重視のプランニングにおいて、最も低コストである排煙量の増量を第1の試行策とする。排煙量を一定量毎に増やして検証を行い、排煙量が限界になっても検証が良とならないときには、次の試行策を試みるが、その場合には、排煙量の初期値を零として、各試行策について最適の排煙量を選定できるようにしている。   In this measure, in the planning with an emphasis on economy, the first trial measure is to increase the amount of smoke that is the lowest cost. The verification is performed by increasing the amount of smoke exhausted by a certain amount, and if the verification is not good even if the amount of smoke exhaust reaches the limit, the next trial is attempted. As zero, the optimum amount of smoke emission can be selected for each trial measure.

第4の手段、第1の手段乃至第3の手段の何れかを有し、かつ
上記建物の各室2,4…から避難路A,Bへ至る複数の煙経路のうち、避難時間が長い経路から順番に、煙降下時間と避難時間との計算及び対比の作業を行うこととしている。
The evacuation time is long among a plurality of smoke paths from the rooms 2, 4... To the evacuation paths A and B having any one of the fourth means and the first to third means. In order from the route, calculation and comparison of smoke fall time and evacuation time are performed.

第5の手段は、第1の手段乃至第4の手段の何れかのプランニング方法を行うのに適したプランニングシステムであって、
プランニングに必要な数値などの情報を入力するための入力手段12と、
入力された数値などの情報を記憶しておく記憶手段14と、
各室ごとに避難時間や煙降下時間を計算する演算手段16と、
これら避難時間と煙降下時間とから避難の安全性を判定する判定手段18と、
その判定結果を表す表示手段20と、
上記安全性が確保されなかった場合に、設備条件の改善を行う改善手段22と、
を備えており、
上記記憶手段14には、予め用意した設備条件の改善策がデータベース化して記憶されており、上記改善手段22は、上記改善策を予め定められた序列で順次試行することができるように構成している。
The fifth means is a planning system suitable for performing the planning method of any one of the first means to the fourth means,
Input means 12 for inputting information such as numerical values necessary for planning;
Storage means 14 for storing information such as inputted numerical values;
Computing means 16 for calculating the evacuation time and smoke descent time for each room;
A judging means 18 for judging safety of evacuation from these evacuation time and smoke descent time;
Display means 20 representing the determination result;
Improvement means 22 for improving the equipment conditions when the safety is not ensured,
With
The storage unit 14 stores a database of improvement measures for facility conditions prepared in advance, and the improvement unit 22 is configured so that the improvement measures can be tried sequentially in a predetermined order. ing.

本手段は、前述のプランニング方法に適したプランニングシステムを提案している。「適した」というのは、それ以外のプランニング方法をも実行できるものを除外しないという意味である。改善手段に関して、「予め定められた序列で順次試行することができる。」としているのは、その順序で機械的に試行することを標準的な機能とし、更に機械と人との共同作業で検証を行うものをも含む意味である。例えば操作者が序列に含まれない方策を追加することを指令したり、方策に関する指示(排気量や天井高さの増加分の指定など)をするものであっても良い。   This means proposes a planning system suitable for the above-described planning method. “Suitable” means not excluding those that can also perform other planning methods. Regarding improvement measures, “You can try sequentially in a predetermined order.” The standard function is to try mechanically in that order, and it is verified by joint work between machines and people. It is meant to include what performs. For example, the operator may instruct to add a policy that is not included in the order, or may give an instruction related to the policy (designation of an increase in displacement or ceiling height, etc.).

第6の手段は、プランニング用のコンピュータプログラムであって、第5の手段を有し、かつ上記改善手段22は、上述の避難安全性が確保されなかった場合に、安全性確保の検証に関係する全ての室に関して避難時間と煙降下時間とを表示手段20に表示させ、
また改善手段22は、プランニング用のコンピュータプログラムであって、上記序列に従った改善策を含む複数の方策を表示手段20に表示させ、利用者が選択した方策を試行するように形成している。
The sixth means is a computer program for planning, has the fifth means, and the improvement means 22 relates to verification of ensuring safety when the above-mentioned evacuation safety is not ensured. Display the evacuation time and smoke descent time on the display means 20 for all rooms
The improvement means 22 is a computer program for planning, and is configured to display on the display means 20 a plurality of measures including improvement measures according to the above-mentioned order and to try the measures selected by the user. .

本手段では、検証のための演算を機械に処理させ、要所要所での判断を人間が行うことができるようにしたものである。その判断に必要なデータを表示手段に表示するようにしている。一般に居室避難安全検証では、各室の避難時間と煙降下時間とを、又階避難安全検証では、各階の最長の階避難時間と最短の階煙降下時間とを比較すれば足りるが、本手段では、例えば検証対象階の全ての室の避難時間及び煙降下時間を好ましくは一覧できる形式のリスト乃至表形式で表示するようにしている。これにより、経路の一部だけに問題があるのか、軒並み全ての経路に問題があるのかなどといった総合的な判断が可能となり、的確な方策を選択することができる。   In this means, a calculation for verification is processed by a machine so that a person can make a judgment at a necessary place. Data necessary for the determination is displayed on the display means. In general, it is sufficient to compare the evacuation time and smoke fall time of each room in the room evacuation safety verification, and in the floor evacuation safety verification, it is sufficient to compare the longest floor evacuation time and the shortest floor smoke fall time of each floor. Then, for example, the evacuation time and smoke drop time of all the rooms on the verification target floor are preferably displayed in a list or a table format that can be listed. As a result, it is possible to make a comprehensive determination such as whether there is a problem in only a part of the route or whether there is a problem in all the routes, and an appropriate measure can be selected.

第7の手段は、コンピュータを前記第5の手段又は第6の手段に記載した入力・記憶・演算・判定・改善の各手段として機能させるように構成したことを特徴としている。     A seventh means is characterized in that the computer is configured to function as each means of input / storage / calculation / determination / improvement described in the fifth or sixth means.

第1の手段に係る発明によれば、次の効果を奏する。
○設備条件の改善策を複数設け、一つの方策で安全避難検証を行い、検証結果が不良であれば、次の方策で検証を試みるようにしたから、検証と設計変更を自動的にかつ迅速に行うことができる。
○各方式に、それぞれに一定の価値基準に基づく序列を設けたから、人間の価値基準を機械の判断に反映させて価値の高い設計変更を提案することができる。
The invention according to the first means has the following effects.
○ Establish multiple measures to improve equipment conditions, perform safe evacuation verification with one measure, and if the verification result is bad, try to verify with the next measure, so verification and design change automatically and quickly Can be done.
○ Since each system has an order based on certain value standards, it is possible to propose design changes with high value by reflecting human value standards in machine judgment.

第2の手段に係る発明によれば、経済性・意匠性・施工性などの複数の価値基準に応じて、設備条件の序列を定めておき、その価値基準を切り替えることで、各基準に応じてもっとも優れた設計変更を実現できる。   According to the invention relating to the second means, the order of the equipment conditions is determined in accordance with a plurality of value standards such as economy, designability, and workability, and the value standards are switched, so that each standard is met. The best design change can be achieved.

第3の手段に係る発明によれば、経済性の価値基準において、複数の方策のうち、排気ファンの排気量を序列の第1とするとともに、2番目以降の方策を試行する際に初期値を零にするから、2番目以降の方式のうち最適なものを選択すると同時に排気量も最適にすることができ、有利である。   According to the invention relating to the third means, in the economic value standard, among the plurality of measures, the exhaust air amount of the exhaust fan is the first in the order, and the initial value when the second and subsequent measures are tried. Since zero is set to zero, the most suitable one of the second and subsequent methods can be selected, and at the same time, the displacement can be optimized, which is advantageous.

第4の手段に係る発明によれば、避難時間が長い経路から順に安全避難の検証を行うこととしたから、より少ない労力で検証を行うことができる。   According to the fourth aspect of the invention, since the safety evacuation verification is performed in order from the route with the long evacuation time, the verification can be performed with less effort.

第5の手段に係る発明によれば、第1の手段乃至第4の手段の方法を、プランニングシステムによって実行させることで、機械の演算能力に人の判断及び経験を反映させることができ、迅速かつ的確な避難検証を行うことができる。   According to the invention relating to the fifth means, by executing the methods of the first means to the fourth means by the planning system, it is possible to reflect the judgment and experience of the person in the computing ability of the machine, and quickly. Accurate evacuation verification can be performed.

第6の手段に係る発明によれば、現実の人の判断と機械の演算による検証手順とを組み合わせたから、より柔軟で確実な検証が可能となる。   According to the sixth aspect of the invention, since the judgment of an actual person and the verification procedure based on the machine operation are combined, more flexible and reliable verification is possible.

第7の手段に係る発明によれば、そのプログラムを既存のコンピュータに読み込ませることで、第5の手段に係るプランニングシステムを構成することができる。   According to the seventh aspect of the invention, the planning system according to the fifth means can be configured by causing the existing computer to read the program.

図1〜図6は、本発明に係る建物の安全避難のための設備のプランニング方法を説明するための図である。   1-6 is a figure for demonstrating the planning method of the facility for the safe evacuation of the building based on this invention.

まず説明の都合上から、図2及び図3に示す本発明方法を適用する建物の対象階の構造を示す。図2は、その対象階の平面図であり、この階を長手方向を横切る廊下(或いは通路)10の両側に事務室1・2・6と、会議室7・8・9とを設けている。またそれら事務室1・2と廊下10との間には、前室3・4・5を設けている。上記廊下10の両端は、それぞれ階段(或いは避難路)A,Bに通じている。   First, for convenience of explanation, the structure of the target floor of a building to which the method of the present invention shown in FIGS. 2 and 3 is applied is shown. FIG. 2 is a plan view of the target floor, and offices 1, 2, 6 and conference rooms 7, 8, 9 are provided on both sides of a corridor (or passage) 10 that crosses the floor in the longitudinal direction. . In addition, the front rooms 3, 4, and 5 are provided between the office rooms 1 and 2 and the hallway 10. Both ends of the corridor 10 lead to stairs (or evacuation paths) A and B, respectively.

避難安全検証法では、これら全ての室1…と廊下10が火災になった場合のそれぞれに関して、各室から階段A及び階段Bへ安全に避難することができるか否か検証することを求めている。図2には各室から避難経路が点線で示されている。これら各室には、居室床面積Aroom・平均天井高さHroom・煙等発生量Vs・有効排煙量Veなどが予め設定されており、下記の数式1のように法令で定める煙降下時間tsを設定しておく。尚、図3には最も煙降下時間が短い事務室6→廊下10→階段Aという経路の経路方向に沿っての断面図を表している。
[数式1]ts=Aroom×(Hroom−1.8)/max(Vs−Ve,0.01)
また各室の広さや用途、廊下の長さから避難開始時間や歩行時間を、室乃至廊下の出口の構造から出口通過時間を設定し、それらを累計して各室毎に階避難時間を設定する。図4には階避難時間が最も長い事務室2→前室5→廊下10→階段Aという経路の断面図を示している。
In the evacuation safety verification method, it is required to verify whether it is possible to evacuate safely from each room to stairs A and B for each of the cases where all of the rooms 1 and the corridor 10 are in a fire. Yes. In FIG. 2, the evacuation route from each room is indicated by a dotted line. Each of these rooms is preset with room floor area A room , average ceiling height H room , smoke generation amount Vs, effective smoke emission Ve, etc. Time ts is set in advance. FIG. 3 shows a cross-sectional view along the route direction of the office room 6 → the corridor 10 → the staircase A with the shortest smoke fall time.
[Formula 1] ts = A room × (H room −1.8) / max (Vs−Ve, 0.01)
In addition, the evacuation start time and walking time are set based on the size and use of each room and the length of the corridor, and the exit passage time is set based on the structure of the exit of the room or corridor, and these are accumulated to set the floor evacuation time for each room. To do. FIG. 4 shows a cross-sectional view of the route of the office room 2 → the front room 5 → the corridor 10 → the stairs A having the longest floor evacuation time.

図5は、各室から廊下を経て階段に至る経路を系統的に表している。また、この図には、原設計として、各室ごとに、室面積・避難人数・天井高さ・内装材・排煙設備・室内歩行時間・階歩行時間などのデータを、また出口ごとに、扉幅・扉高・扉防火設備などのデータをそれぞれ記載させている。同表中の扉d〜d13は、全て避難安全検証法に言う「その他の扉」、即ち、防火設備ではない扉である。内装材は準不燃材料とし、天井高さは全て2.8m、各室の排煙量は床面積1m当り1m/分の排煙量とする。更に居室安全避難検証に必要な詳細なデータは次の表2に示しておく。 FIG. 5 systematically represents a route from each room to the staircase through the hallway. Also, in this figure, as the original design, for each room, data such as room area, number of evacuation, ceiling height, interior materials, smoke exhausting equipment, indoor walking time, floor walking time, etc., and for each exit, Data such as door width, door height, and door fire prevention equipment are listed. Doors d 1 to d 13 in the table are all “other doors” referred to in the evacuation safety verification method, that is, doors that are not fire prevention equipment. The interior materials shall be semi-incombustible materials, the ceiling height shall be 2.8m, and the smoke emission in each room shall be 1m 3 / min per 1m 2 of floor area. The detailed data necessary for verification of room safety evacuation is shown in Table 2 below.

Figure 2007334683
次に図1に基づいて本発明のプログラミング方法の手順を説明する。
(1)各室に関して、室安全避難検証を行う。
Figure 2007334683
Next, the procedure of the programming method of the present invention will be described with reference to FIG.
(1) Conduct room safety evacuation verification for each room.

検証の方法自体は公知なので簡単に説明する。この検証方法に使用する避難開始時間tstart、歩行時間ttravel、出土通過所要時間tqueueはそれぞれ次の数式2〜4に与えられる。図5及び表2の中のデータを用いて、各室毎に各時間を計算して、その数値を累計して居室避難時間を得る。事務室2について計算すると、tescape=tstart+ttravel+tqueue=0.236+0.129+0.078=0.443(分)となる。また、煙降下時間は前述の数式1より、ts=50×(2.8-1.8)/max(131.828-20.0,0.01)=0.447となる。同様の計算を全ての室に計算する。
[数式2]tstart=(√(ΣAarea))/30,(但しAareaは居室面積)
[数式3]ttravel=max(Σ(h/v))
[数式4]tqueue=(ΣpAarea)/(Neffeff) ,(但しΣpAareaは在室人数(当該室の出口を避難に使う他室の人を含む)、Neffは有効流動係数、Beffは有効出口係数)
以上の計算から、次の表3の居室避難時間及び煙降下時間の欄の結果を得る。これら居室避難時間及び煙降下時間を比較すると、何れの室でも居室避難時間が煙降下時間より短く、従って室安全避難検証の条件を満たしている。
Since the verification method itself is known, it will be briefly described. The evacuation start time that is used to validate the method t start, walking time t travel i, excavated passes required time t queue are respectively applied to the following formula 2-4. Using the data in FIG. 5 and Table 2, each time is calculated for each room, and the numerical values are accumulated to obtain the room evacuation time. When calculating for the office room 2, t escape = t start + t travel + t queue = 0.236 + 0.129 + 0.078 = 0.443 (minutes). Moreover, smoke fall time becomes ts = 50 * (2.8-1.8) / max (131.828-20.0,0.01) = 0.447 from the above-mentioned numerical formula 1. Similar calculations are made for all rooms.
[Formula 2] t start = (√ (ΣA area )) / 30, where A area is a room area
[Formula 3] t travel = max (Σ (h / v))
[Formula 4] t queue = (ΣpA area ) / (N eff B eff ), where ΣpA area is the number of people in the room (including people in other rooms who use the exit of the room for evacuation), and N eff is the effective flow coefficient , B eff is the effective outlet coefficient)
From the above calculation, the results in the column of room evacuation time and smoke fall time in Table 3 below are obtained. Comparing the room evacuation time and the smoke fall time, the room evacuation time is shorter than the smoke fall time in any room, and therefore the conditions for the room safety evacuation verification are satisfied.

Figure 2007334683
(2)階全体に関して階避難安全検証を行う。
Figure 2007334683
(2) Verify evacuation safety verification for the entire floor.

この検証方法に使用する避難開始時間tstart、歩行時間ttravel、出土通過所要時間tqueueはそれぞれ次の数式5〜7に与えられる。歩行時間に関しては表2のデータを用いて、また、床面積合計Afloor=900m,在館人数ΣpAarea=100人,有効流動係数Neff=90人/min*m,階段出口巾Bst=0.9m(階段A及び階段B共通)として、これら避難開始時間・歩行時間・出口通過所要時間を計算する。それらの数値を累計して居室避難時間を得る。事務室2について計算すると、tescape=tstart+ttravel+tqueue=4.0+0.449+0.618=5.067(分)となる。
[数式5]tstart=(Afloor/30)+3
[数式6]ttravel=max(Σ(h/v)),(但しhは各室から階の出口までの歩行距離、vは歩行速度)
[数式7]tqueue=(ΣpAarea)/(Neffst
The evacuation start time t start , the walking time t travel , and the excavation passage required time t queue used in this verification method are given by the following equations 5 to 7, respectively. Regarding the walking time, using the data in Table 2, the floor area total A floor = 900 m 2 , the number of people in the building ΣpA area = 100 people, the effective flow coefficient N eff = 90 people / min * m, the stairway exit width B st = Evacuation start time / walking time / time required to pass through exit is calculated as 0.9 m (common to stairs A and B). Accumulate those numbers to get the room evacuation time. When calculating for the office room 2, t escape = t start + t travel + t queue = 4.0 + 0.449 + 0.618 = 5.067 (minutes).
[Formula 5] t start = (A floor / 30) +3
[Formula 6] t travel = max (Σ (h / v)), where h is the walking distance from each room to the exit of the floor, and v is the walking speed.
[Formula 7] t queue = (ΣpA area ) / (N eff B st )

Figure 2007334683
次に階煙降下時間tsは、一般に次の数式8で与えられる。居室(火災室)→前室(伝播室)→階出口に臨む廊下(検証対象室)の順序で煙が流れるものとし、ここで火災室での煙降下時間をtS1、伝播室での煙降下時間をtS2、対象エリアでの煙降下時間をtS3とすると、tS=tS1+tS2+tS3となる。但し、Hlimは限界煙層高さであり、常時閉鎖式の防火設備又は自動閉鎖装置付き防火設備の場合には床面から出口上端までの最大高さの1/2,その他の構造の場合には、床面から出口上端までの最大高さである。
[数式8]ts=Aroom×(Hroom−Hlim)/max(Vs−Ve,0.01)
火災室での煙降下時間の計算に必要なデータを表5に、また伝播室・対象エリアでの煙降下時間の計算に必要なデータを表6にそれぞれ記載する。
Figure 2007334683
Next, the floor smoke fall time ts is generally given by the following formula 8. Smoke flows in the order of living room (fire room) → anterior room (propagation room) → corridor (room to be verified) facing the floor exit, where smoke fall time in the fire room is t S1 , smoke in the propagation room When the fall time is t S2 and the smoke fall time in the target area is t S3 , t S = t S1 + t S2 + t S3 . However, H lim is the limit smoke layer height. In the case of a normally closed fire prevention equipment or a fire prevention equipment with an automatic closing device, it is 1/2 of the maximum height from the floor surface to the top of the exit, in the case of other structures Is the maximum height from the floor to the top of the exit.
[Formula 8] ts = A room × (H room −H lim ) / max (Vs−Ve, 0.01)
Table 5 shows the data necessary for calculating the smoke fall time in the fire room, and Table 6 shows the data required for calculating the smoke fall time in the propagation room / target area.

Figure 2007334683
Figure 2007334683

Figure 2007334683
事務室6→廊下10→階段Aという経路では、tS=tS1+tS2+tS3=0.440+0+0.67=1.12(分)となる。表3の右半分に示す階避難安全検証の結果を見ると、各室から避難階段に至る経路に関して、階避難時間が最長の経路は事務室2からの避難経路であり、その階避難時間は5.067分である。また階煙降下時間が最短の経路は上述の事務室6からの避難経路であり、その階煙降下時間は1.116分である。従って階避難時間の最長値max(tstart)が階煙降下時間の最短値min(tescape)よりも長いので、階避難安全検証は不良である。また、参考までに、各経路からの避難経路の階避難時間と、階煙降下時間の最短値とを比較すると、全ての経路の階避難時間が階煙降下時間の最短値よりも長い。従って全ての経路に関して設備の改善策を施すことが必要である。
(3)設備条件を改善する。
Figure 2007334683
In the route of office room 6 → corridor 10 → stairs A, t S = t S1 + t S2 + t S3 = 0.440 + 0 + 0.67 = 1.12 (minutes). Looking at the results of the floor evacuation safety verification shown in the right half of Table 3, regarding the route from each room to the evacuation stairs, the route with the longest floor evacuation time is the evacuation route from the office 2 and the floor evacuation time is 5.067 minutes. The route with the shortest floor smoke fall time is the escape route from the office 6 described above, and the floor smoke fall time is 1.116 minutes. Accordingly, since the maximum value max (t start ) of the floor evacuation time is longer than the minimum value min (t escape ) of the floor smoke fall time, the floor evacuation safety verification is poor. For reference, when comparing the floor evacuation time of the evacuation route from each route and the shortest value of the floor smoke fall time, the floor evacuation time of all routes is longer than the shortest value of the floor smoke fall time. Therefore, it is necessary to take measures to improve the equipment for all routes.
(3) Improve equipment conditions.

階避難安全検証で各室から避難口へ至る経路の一つに関して、検証階からの避難時間が最短の煙降下時間よりも短いときには、図1に示す如く、次の手順で予め用意していた各方策で改善を行う。尚、方策自体は従来から行われていたものであり、本発明の重点は、それら方策を行う順序とその組み替え(方策の手順)にある。
(a)排気ファンの変更を伴わない排気量の増加。
For one of the routes from each room to the evacuation exit in the floor evacuation safety verification, when the evacuation time from the verification floor is shorter than the shortest smoke fall time, it was prepared in advance by the following procedure as shown in FIG. Make improvements in each measure. Note that the measures themselves have been conventionally performed, and the emphasis of the present invention is on the order in which these measures are performed and their rearrangements (policy procedures).
(a) Increase in displacement without changing the exhaust fan.

例えば現在使用している排気ファンの最大排気量がVmax1であるとしても、通常は排気エネルギーを節約するため、排気量をVmax1未満の所定量に留めるのが一般的である。現在の排気量VeがVmax1未満であれば、これをδVだけ増加させて、数式8により改善後の煙降下時間を再計算し、その階からの避難時間と比較し、避難時間が煙降下時間以下であれば検証結果を良(OK)とし,そうでなければ排気量がVmax1となるまで、同じ手順を繰り返す。排気量を最大値Vmax1としても良好な結果が得られないときには、次の段階に進む。
(b)内装材の変更。
For example, even if the maximum exhaust amount of an exhaust fan currently used is V max1 , the exhaust amount is generally kept at a predetermined amount less than V max1 in order to save exhaust energy. If the current is less than the exhaust amount Ve is V max1, which is increased by .DELTA.V, recalculates the smoke fall time after improvement by Equation 8, as compared to the evacuation time from that floor, the evacuation time smoke drops If it is less than the time, the verification result is good (OK), otherwise the same procedure is repeated until the displacement becomes V max1 . When not good results even exhaust amount as the maximum value V max1 proceeds to the next step.
(b) Change of interior materials.

内装材の候補として例えば準不燃材と不燃材とを用意する。現在の材料が準不燃材であれば不燃材に変更し、併せて排気ファンの排気量を初期値V(<Vmax1)に戻して、煙降下時間を再計算し、上述の階避難安全検証を繰り返す。現在の材料が不燃材であるときには、次の段階に進む。
(c)扉の種類の変更1。
For example, a semi-incombustible material and a non-combustible material are prepared as interior material candidates. If the current material is a quasi-incombustible material, change to non-combustible material, and return the exhaust fan exhaust amount to the initial value V 0 (<V max1 ), recalculate the smoke fall time, and the above floor evacuation safety Repeat verification. If the current material is a non-combustible material, proceed to the next stage.
(c) Change of door type 1.

扉の等級として、通常の扉<防火扉<遮煙防火扉とし、現在の扉の等級が防火扉以上でないならば、防火扉に変更し、併せて排気ファンの排気量を初期値Vに戻して、煙降下時間を再計算し、上述の階避難安全検証を繰り返す。現在の材料が防火扉以上であるときには、次の段階に進む。
(d)扉の種類の変更1。
If the current door grade is not equal to or higher than the fire door, change it to a fire door and set the exhaust fan exhaust amount to the initial value V 0 . Return, recalculate the smoke fall time, and repeat the above floor evacuation safety verification. If the current material is above the fire door, proceed to the next stage.
(d) Change of door type 1.

現在の扉の等級が遮煙
防火扉以上でないならば、遮煙防火扉に変更し、併せて排気ファンの排気量を初期値Vに戻して、煙降下時間を再計算し、上述の階避難安全検証を繰り返す。現在の材料が遮煙防火扉以上であるときには、次の段階に進む。
(e)天井高さの増加。
If the current door grade is not equal to or higher than the smoke-proof fire door, change it to a smoke-proof fire door. At the same time, return the exhaust fan to the initial value V 0 and recalculate the smoke fall time. Repeat evacuation safety verification. When the current material is more than a smoke-proof fire door, proceed to the next stage.
(e) Increase in ceiling height.

建物の階高を変えずに天井裏空間を狭くすることで高くすることができる天井高さの上限値をHmaxとする。現在の天井高さが上限値未満であれば、併せて天井高さをδHだけ増加するとともに、排気ファンの排気量を初期値V(<V)に戻して、煙降下時間を再計算し、上述の階避難安全検証を繰り返す。現在の天井高さが上限値であるときには、次の段階に進む。
(f) 排気ファンの変更を伴なう排気量の増加。
Let Hmax be the upper limit of the ceiling height that can be increased by narrowing the ceiling space without changing the floor height of the building. If the current ceiling height is less than the upper limit, the ceiling height is also increased by δH and the exhaust fan exhaust amount is returned to the initial value V 0 (<V 1 ) to recalculate the smoke fall time. Repeat the above-mentioned floor evacuation safety verification. When the current ceiling height is the upper limit value, the process proceeds to the next stage.
(f) Increased displacement with changes in exhaust fan.

既使用の排気ファンよりも大きな最大排気量Vを有する排気ファンを予め用意する。現在の排気ファンの排気量の設定値がVmax2未満であるときには、排気ファンを変更するとともに、現在の排気量をδVだけ増加させて、上述の階避難安全検証を繰り返す。排気ファンの排気量がVmax2を越えるときには、次の段階に進む。 Prepared in advance exhaust fan having a large maximum displacement volume V 2 of the exhaust fan already used. When the current exhaust fan exhaust amount setting value is less than Vmax2 , the exhaust fan is changed, the current exhaust amount is increased by δV, and the above-described floor evacuation safety verification is repeated. When the exhaust amount of the exhaust fan exceeds Vmax2 , the process proceeds to the next stage.

図示例では、これで、用意していた方策は全て試みたことになる。以上の行程をコンピュータに行わせるときには、用意した方策を全て試みて良好な検証結果が得られたかった場合には、その旨を利用者に報告するようにすると良い。   In the illustrated example, all the prepared measures have been tried. When the above process is performed by the computer, if all the prepared measures are tried and a satisfactory verification result is not obtained, it is preferable to report the fact to the user.

以上の手順は、前記図1に基づき、経済性重視の基準で検証を行った結果であるが、前述の表1に基づいて、方策を試行する順序を入れ替えることができる。例えば図6は、同表中の意匠重視の基準で改善を試みる場合である。表1には、経済性重視、意匠重視、施工性重視の3つの例が挙げてあるが、必要に応じて他の基準による方策の順序を追加しても良い。   The above procedure is the result of verification based on the economy-oriented standard based on FIG. 1, but the order in which the measures are tried can be changed based on Table 1 described above. For example, FIG. 6 shows a case where improvement is attempted based on the design-oriented criteria in the table. Table 1 lists three examples of economic emphasis, design emphasis, and workability emphasis, but the order of measures based on other criteria may be added as necessary.

以上のように各室から避難口への経路の一つについて改善を終了したときには、残りの経路に関して(2)の階避難安全検証を継続すれば良い。   As described above, when the improvement for one of the routes from each room to the evacuation exit is completed, the floor evacuation safety verification of (2) may be continued for the remaining routes.

尚、上の(a)〜(f)では、全工程を機械的に処理するため、排気量の増加分δV及び天井高さの増加分δを予め設定している。これら増加分は適宜調整できるようにしておくことができる。また、増加分を機械的に加えるのではなく、計算の途中で機械(コンピュータ)が操作者の指示を要求し、人の判断で増加分を設定する半全自動の形式とすることもできる。更に必要に応じて、人の判断により、表1に定める方策の手順の一部を変更したり、手順を追加又は省略することができるようにコンピュータを構成するようにすることもできる。   In the above (a) to (f), the exhaust amount increase δV and the ceiling height increase δ are preset in order to mechanically process all processes. These increases can be adjusted as appropriate. Further, instead of adding the increment mechanically, it is possible to adopt a semi-automatic format in which the machine (computer) requests an operator's instruction during the calculation and the increment is set by human judgment. Furthermore, if necessary, the computer can be configured so that a part of the procedure of the measures defined in Table 1 can be changed or a procedure can be added or omitted at the discretion of a person.

更に上記(a)〜(f)の各行程では、次の行程に移る際に排気ファンの排気量を初期値に戻す(リセットする)ことを行っているが、排気量以外の方策(内燃材の変更・扉の変更・天井高さの変更)に関して、前の段階の方策を基に戻すリセット操作を行うことができる。そのような操作をする理由は、例えば経済性重視の基準を採用した場合には、優先順位が低い方策であるほど、コストがかかる代わりに避難安全への改善効果が高い場合が多く、従って後の方策を採用するのであれば、重複して先の方策を実行する必要がないときがあるからである。これに関しては後述する。そうした操作は機械に予めプログラムすることにより、或いは人の判断により行うことができる。   Further, in each of the above steps (a) to (f), the exhaust amount of the exhaust fan is returned to the initial value (reset) when moving to the next step. , Change of doors, change of ceiling height), it is possible to perform a reset operation to return to the previous stage. The reason for such an operation is that, for example, when a standard that emphasizes economic efficiency is adopted, the lower the priority, the more costly the improvement effect to evacuation safety is. This is because there is a case where it is not necessary to execute the previous policy redundantly. This will be described later. Such operations can be performed by preprogramming the machine or at the discretion of a person.

次に、その様に人の判断を含む形式で図5の設備構成を改善する実施例を示す。   Next, an embodiment in which the equipment configuration of FIG. 5 is improved in such a form that includes human judgment will be described.

まず図5の設備構成より、廊下10の排煙量を100m/分から200m/分に増加させた。その結果を検証したのが、次の表7である。事務室2からの避難経路に関して階煙降下時間が1.443分から1.639分となるなど若干の改善があったが、依然として全ての室の避難経路で階避難安全検証の結果が不良である。 First from system configuration of Figure 5, increasing the flue gas of the corridor 10 to 100 m 3 / min to 200 meters 3 / minute. The results are shown in Table 7 below. There was some improvement in the smoke evacuation time from the office room 2 to 1.439 minutes from 1.443 minutes, but the floor evacuation safety verification results are still poor for all rooms. .

Figure 2007334683
次に全室の内装材を準不燃材料から不燃材料に変更した。その結果を検証したのが、次の表8である。室3・4・5からの避難経路に関して避難時間よりも階煙降下時間が長くなるというようにかなりの改善がみられたが、依然として全体としての階避難安全検証の結果は不良である。
Figure 2007334683
Next, the interior materials in all rooms were changed from semi-incombustible materials to non-combustible materials. The results are verified in Table 8 below. Although significant improvements have been made in terms of the evacuation route from rooms 3, 4 and 5 such that the smoke fall time is longer than the evacuation time, the overall floor evacuation safety verification results are still poor.

Figure 2007334683
更に廊下10の扉を防火扉に変更した。この場合には、火災室から廊下への煙の流入量が大幅に減少して、廊下での煙発生量のVsの改善が見込まれるので、これと同時に内燃材を不燃材から準不燃材に戻し、更に廊下10の排煙量を100m/分に減少させた。その結果を検証したのが、次の表9である。全ての室からの避難経路において階煙降下時間が階避難時間を大幅に上回っており、十分なゆとりをもって階安全避難検証をクリアしていることが判る。この設計を表したものが図7である。
Figure 2007334683
Furthermore, the door of the hallway 10 was changed to a fire door. In this case, the amount of smoke flowing from the fire room to the corridor is greatly reduced, and the Vs of the amount of smoke generated in the corridor is expected to improve. At the same time, the internal combustion material is changed from non-combustible material to semi-incombustible material. In addition, the amount of smoke discharged from the corridor 10 was further reduced to 100 m 3 / min. The results are verified in Table 9 below. It can be seen that the smoke evacuation time in the evacuation route from all rooms significantly exceeds the floor evacuation time, and that the floor safety evacuation verification has been cleared with sufficient clearance. FIG. 7 shows this design.

Figure 2007334683
以上で改善処理を完了しても良いのであるが、前述の通り表8の改善策で避難安全検証に余裕があったことから、試みに廊下10での排気ファンの排気量の設定を0にした。その結果を表10に示す。表9に比べて階煙降下時間は短くなったが、それでもなお階避難時間に比べて余裕があり、階避難安全検証をクリアできることが判る。
Figure 2007334683
Although the improvement process may be completed as described above, since the evacuation safety verification has been afforded by the improvement measures in Table 8 as described above, the exhaust fan exhaust amount setting in the corridor 10 is set to 0 in an attempt. did. The results are shown in Table 10. Although the smoke drop time is shorter than that in Table 9, it is still clear that the floor evacuation safety verification can be cleared because there is a margin compared to the floor evacuation time.

Figure 2007334683
図8は本発明に係る建物の安全避難のための設備のプランニングシステムの構成図である。このプランニングシステムは、入力手段12と、記憶手段14と、演算手段16と、判定手段18と、表示手段20と、改善手段22と、出力手段24とで構成している。
Figure 2007334683
FIG. 8 is a block diagram of a facility planning system for building safe evacuation according to the present invention. This planning system includes an input unit 12, a storage unit 14, a calculation unit 16, a determination unit 18, a display unit 20, an improvement unit 22, and an output unit 24.

入力手段12は、安全避難のためのプランニングに必要な数値などの情報を入力するためのものであり、コンピュータのキーボードなどで構成すればよい。   The input means 12 is for inputting information such as numerical values necessary for planning for safe evacuation, and may be constituted by a computer keyboard or the like.

記憶手段14は、入力された数値を記憶するとともに、検証に必要な数値及び数式、予め容易した方策などをデータベース化して記憶している。   The storage unit 14 stores the input numerical values, and stores the numerical values and mathematical formulas necessary for the verification, previously easy measures and the like in a database.

演算手段16は、各室毎に、居室避難時間及び居室煙降下時間を計算し、更に階避難時間及び階煙降下時間を計算する機能を有する。   The calculation means 16 has a function of calculating the room evacuation time and the room smoke fall time for each room, and further calculating the floor evacuation time and the floor smoke fall time.

判定手段18は、居室避難安全検証に関しては、各室毎の居室避難時間と居室煙降下時間とを比較して、また階避難安全検証に関しては、最長の階避難時間と最短の階煙降下時間とを比較して、各検証毎に安全性を判定する。   The judgment means 18 compares the room evacuation time for each room with the room smoke fall time for the room evacuation safety verification, and the floor evacuation safety verification for the longest floor evacuation time and the shortest floor smoke fall time. And the safety is determined for each verification.

表示手段20は、判定結果を好ましくは視覚的に表示する。例えば表3のように計算結果を表形式で表示させることができる。   The display means 20 preferably displays the determination result visually. For example, as shown in Table 3, the calculation results can be displayed in a table format.

改善手段22は、検証の結果として上記安全性を確保されなかった場合に、現在の設計に改善策を施す。この改善策は記憶装置に記憶されたものを用いると良い。改善策は、表1に示された順序で試行するものとする。利用者は図示しない釦により改善策に関して詳しい指令を与えるようにすることができる。改善策を施したときには、演算手段に戻って同じ作業を繰り返す。   The improvement means 22 applies an improvement measure to the current design when the safety is not ensured as a result of the verification. As this improvement measure, it is preferable to use one stored in the storage device. The improvement measures shall be tried in the order shown in Table 1. The user can give a detailed command regarding improvement measures using a button (not shown). When improvement measures are taken, return to the computing means and repeat the same operation.

出力手段22は、検証結果を外部に出力するように構成されている。   The output unit 22 is configured to output the verification result to the outside.

本発明に係る方法の手順を表すフローチャートである。It is a flowchart showing the procedure of the method which concerns on this invention. 図1の方法が適用される階の平面図である。It is a top view of the floor where the method of FIG. 1 is applied. 図2の階のうちの一つの避難経路の縦断面図である。It is a longitudinal cross-sectional view of one evacuation route in the floor of FIG. 図2の階のうちの他の一つの避難経路の縦断面図である。It is a longitudinal cross-sectional view of the other one evacuation route in the floor of FIG. 図2の階の設備を経路主体で表現した説明図である。It is explanatory drawing which expressed the installation of the floor of FIG. 2 by the path | route main body. 図1の手順を入れ替えて示すフローチャートである。It is a flowchart which replaces and shows the procedure of FIG. 検証終了後の図5に対応する図面である。It is drawing corresponding to FIG. 5 after completion | finish of verification. 本発明に係るシステムの構成図である。1 is a configuration diagram of a system according to the present invention. 法令で定める居室避難安全検証のフローチャートである。It is a flowchart of the room evacuation safety verification stipulated by law. 法令で定める階避難安全検証のフローチャートである。It is a flowchart of the floor evacuation safety verification stipulated by law.

符号の説明Explanation of symbols

1・2・6…事務室 3・4…前室 7・8・9…会議室 10…廊下
12…入力手段 14…記憶手段 16…演算手段 18…判定手段
20…表示手段 22…改善手段 24…出力手段
A,B…避難階段 d〜d13…各室出口
1 · 2 · 6… Office 3 · 4 · Previous room 7 · 8 · 9 ··· Conference room 10 ··· Corridor 12 ··· Input means 14 ··· Storage means 16 ··· Calculating means 18 ························································ ... Output means
A, B ... fire escape d 1 ~d 13 ... each room exit

Claims (7)

建物内の一つの階で避難路A,Bに通路10を経て連なる複数の室2,4…の一つから火災が生じたと仮定して、
A.火災室から周囲への煙の広がり具合を煙の経路毎に設備条件に応じてシミュレーションし、
B.シミュレーション結果に基づいて、火災発生時より、各室2,4…及び通路10内でその天井からの煙の降下で避難者の呼吸が困難になる迄の煙降下時間を計算し、
C.この煙降下時間を、火災発生時より、任意の室からの居室者が当該室からその室外へ或いはその室のある階から避難口へ脱出するのに要する避難時間と比較して、
D.煙降下時間が避難時間より長いときには、設備条件を可とし、
E.煙降下時間が避難時間よりも短いときには、設備条件を不可として、上記設備条件を改善して上記A〜Cの行程を繰り返すことを内容とする、安全避難のための設備のプランニング方法において、
上記設備条件の改善策として、発煙条件・排煙条件・遮煙条件・室の形状条件のうちの少なくとも一つを含む複数の方策を設定するとともに、
これら各設備条件の改善策に対して、経済性等のような価値基準に基づいて予め序列を付与して、その序列による順番で機械的に設備条件の改善を試みることを特徴とする、建物の安全避難のための設備のプランニング方法。
Assuming that a fire broke out from one of a plurality of rooms 2, 4 ... connected to the evacuation routes A and B via the passage 10 on one floor in the building,
A. Simulate the spread of smoke from the fire room to the surroundings according to the equipment conditions for each smoke path,
B. Based on the simulation results, calculate the smoke fall time from the time of the fire until the evacuees have difficulty breathing due to the smoke fall from the ceiling in each of the rooms 2, 4.
C. Compared to the evacuation time required for a occupant from any room to escape from the room to the outside of the room or from the floor with the room to the evacuation exit from the time of the fire,
D. When the smoke fall time is longer than the evacuation time, the equipment conditions are acceptable,
E. When the smoke fall time is shorter than the evacuation time, in the facility planning method for safe evacuation, the facility condition is disabled, the facility condition is improved, and the steps A to C are repeated.
As measures to improve the above equipment conditions, a plurality of measures including at least one of smoke generation conditions, smoke emission conditions, smoke shielding conditions, and room shape conditions are set,
A building characterized by giving an order to these improvement measures for each equipment condition in advance based on value criteria such as economy, and mechanically trying to improve the equipment conditions in the order of the order. For planning facilities for safe evacuation.
上述の価値基準として、経済性、意匠性、施工性などの種類の異なる基準を設けて、それぞれの基準毎に、予め上記各設備条件の改善策の序列を定めておき、その価値基準を変更することで、設備条件の改善を試みる順番を切り替えることができるようにしたことを特徴とする請求項1記載の建物の安全避難のための設備のプランニング方法。   As the above-mentioned value standards, different standards such as economic efficiency, designability, workability, etc. are set, and the order of improvement measures for each equipment condition is determined in advance for each standard, and the value standards are changed. The facility planning method for safe evacuation of a building according to claim 1, wherein the order of trying to improve the facility conditions can be switched. 上述の経済性の価値基準において、複数の方策のうち、排気ファンの排気量の第1の序列とし、かつ2番目以降の方策を試行するにあたって排気量の初期値を零にすることを特徴とする、請求項2記載の建物の安全避難のための設備のプランニング方法。   In the above-mentioned economic value standard, it is characterized in that, among the plurality of measures, the first order of the exhaust amount of the exhaust fan is used, and the initial value of the exhaust amount is set to zero when trying the second and subsequent measures. The method of planning a facility for safe evacuation of a building according to claim 2. 上記建物の各室2,4…から避難路A,Bへ至る複数の煙経路のうち、避難時間が長い経路から順番に、煙降下時間と避難時間との計算及び対比の作業を行うことを特徴とする、請求項1乃至請求項3記載の建物の安全避難のための設備のプランニング方法。   Among the multiple smoke routes from each room 2, 4 ... to the evacuation routes A and B, the calculation and comparison of the smoke descent time and the evacuation time are performed in order from the route with the longer evacuation time. 4. A facility planning method for safe evacuation of a building according to claim 1, wherein the facility is safe. 請求項1乃至請求項4に記載した建物の安全避難のための設備のプランニング方法を行うのに適したプランニングシステムであって、
プランニングに必要な数値などの情報を入力するための入力手段12と、
入力された数値などの情報を記憶しておく記憶手段14と、
各室ごとに避難時間や煙降下時間を計算する演算手段16と、
これら避難時間と煙降下時間とから避難の安全性を判定する判定手段18と、
その判定結果を表す表示手段20と、
上記安全性が確保されなかった場合に、設備条件の改善を行う改善手段22と、
を備えており、
上記記憶手段14には、予め用意した設備条件の改善策がデータベース化して記憶されており、上記改善手段22は、上記改善策を予め定められた序列で順次試行することができるように構成したことを特徴とする、建物の安全避難のためのプランニングシステム。
A planning system suitable for performing the facility planning method for safe evacuation of a building according to claim 1,
Input means 12 for inputting information such as numerical values necessary for planning;
Storage means 14 for storing information such as inputted numerical values;
Computing means 16 for calculating the evacuation time and smoke descent time for each room;
A judging means 18 for judging safety of evacuation from these evacuation time and smoke descent time;
Display means 20 representing the determination result;
Improvement means 22 for improving the equipment conditions when the safety is not ensured,
With
The storage means 14 stores a database of improvement measures for facility conditions prepared in advance, and the improvement means 22 is configured so that the improvement measures can be sequentially tried in a predetermined order. A planning system for safe evacuation of buildings.
上記改善手段22は、上述の避難安全性が確保されなかった場合に、安全性確保の検証に関係する全ての室に関して避難時間と煙降下時間とを表示手段20に表示させ、
また改善手段22は、上記序列に従った改善策を含む複数の方策を表示手段20に表示させ、利用者が選択した方策を試行するように形成したことを特徴とする、請求項5記載のプランニングシステム。
When the above evacuation safety is not ensured, the improvement means 22 causes the display means 20 to display the evacuation time and the smoke descent time for all the rooms related to verification of safety assurance,
6. The improvement means 22 is configured to display on the display means 20 a plurality of measures including improvement measures according to the order, and to try a measure selected by the user. Planning system.
コンピュータを前記請求項5又は請求項6に記載した各手段として機能させるように構成したことを特徴とする、コンピュータプログラム。


A computer program configured to cause a computer to function as each of the means described in claim 5 or claim 6.


JP2006166510A 2006-06-15 2006-06-15 Planning method, planning system, and planning program of facility for safe evacuation of building Pending JP2007334683A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006166510A JP2007334683A (en) 2006-06-15 2006-06-15 Planning method, planning system, and planning program of facility for safe evacuation of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006166510A JP2007334683A (en) 2006-06-15 2006-06-15 Planning method, planning system, and planning program of facility for safe evacuation of building

Publications (1)

Publication Number Publication Date
JP2007334683A true JP2007334683A (en) 2007-12-27

Family

ID=38934100

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006166510A Pending JP2007334683A (en) 2006-06-15 2006-06-15 Planning method, planning system, and planning program of facility for safe evacuation of building

Country Status (1)

Country Link
JP (1) JP2007334683A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010157121A (en) * 2008-12-26 2010-07-15 Ohbayashi Corp Method, program and system for determining refuge safety
JP2010160658A (en) * 2009-01-07 2010-07-22 Ohbayashi Corp Warning zone classification method
JP2010158363A (en) * 2009-01-07 2010-07-22 Ohbayashi Corp Planning method
JP2010159571A (en) * 2009-01-07 2010-07-22 Ohbayashi Corp Method for designing arrangement of smoke blocking portion
JP2011058275A (en) * 2009-09-10 2011-03-24 Toshiba It Service Kk Office disaster prevention check diagnosis system
KR101101219B1 (en) * 2011-01-18 2012-01-04 한국수력원자력 주식회사 Fire propagation search system and fire propagation search method
JP2012029905A (en) * 2010-07-30 2012-02-16 Nikken Sekkei Ltd Calculation method of parent room ratio in living room in building
JP2012033028A (en) * 2010-07-30 2012-02-16 Nikken Sekkei Ltd Method for calculating evacuation start time
JP2019016312A (en) * 2017-07-11 2019-01-31 株式会社大林組 Evacuation safety performance evaluation method, evacuation safety performance evaluation system, and program
CN116862089A (en) * 2023-07-06 2023-10-10 山东头一锅餐饮管理连锁有限公司 Exhaust path planning system in food production factory building

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010157121A (en) * 2008-12-26 2010-07-15 Ohbayashi Corp Method, program and system for determining refuge safety
JP2010160658A (en) * 2009-01-07 2010-07-22 Ohbayashi Corp Warning zone classification method
JP2010158363A (en) * 2009-01-07 2010-07-22 Ohbayashi Corp Planning method
JP2010159571A (en) * 2009-01-07 2010-07-22 Ohbayashi Corp Method for designing arrangement of smoke blocking portion
JP2011058275A (en) * 2009-09-10 2011-03-24 Toshiba It Service Kk Office disaster prevention check diagnosis system
JP2012029905A (en) * 2010-07-30 2012-02-16 Nikken Sekkei Ltd Calculation method of parent room ratio in living room in building
JP2012033028A (en) * 2010-07-30 2012-02-16 Nikken Sekkei Ltd Method for calculating evacuation start time
KR101101219B1 (en) * 2011-01-18 2012-01-04 한국수력원자력 주식회사 Fire propagation search system and fire propagation search method
JP2019016312A (en) * 2017-07-11 2019-01-31 株式会社大林組 Evacuation safety performance evaluation method, evacuation safety performance evaluation system, and program
CN116862089A (en) * 2023-07-06 2023-10-10 山东头一锅餐饮管理连锁有限公司 Exhaust path planning system in food production factory building
CN116862089B (en) * 2023-07-06 2024-01-09 山东头一锅餐饮管理连锁有限公司 Exhaust path planning system in food production factory building

Similar Documents

Publication Publication Date Title
JP2007334683A (en) Planning method, planning system, and planning program of facility for safe evacuation of building
KR101669455B1 (en) Automatic checking system for fire fighting regulation and anti-disaster regulation of building structure, and method for the same
Ronchi et al. Fire evacuation in high-rise buildings: a review of human behaviour and modelling research
Kodur et al. Egress parameters influencing emergency evacuation in high-rise buildings
Aleksandrov et al. Modelling and finding optimal evacuation strategy for tall buildings
JP4822812B2 (en) Evacuee Behavior Prediction Device and Evacuee Behavior Prediction Method
Lotfi et al. A BIM-based framework for evacuation assessment of high-rise buildings under post-earthquake fires
KR102004903B1 (en) Method, apparatus and computer-readable medium for analyzing fire dangerousness of old building
JP4678934B2 (en) Building fire risk evaluation apparatus, building fire risk evaluation method, and storage medium
JP6143061B2 (en) Evacuation behavior prediction system and evacuation behavior prediction program
Alianto et al. High-rise building fire safety using mechanical ventilation and stairwell pressurization: A review
Shih et al. A virtual-reality-based feasibility study of evacuation time compared to the traditional calculation method
Deere et al. An evacuation model validation data-set for high-rise construction sites
Nguyen et al. Novel modelling approach for evacuation strategies of tall towers-A case study of Lotus Tower
JP4915550B2 (en) Evacuation behavior prediction system and evacuation behavior prediction method
Li et al. A review on fire safety engineering: Key issues for high-rise buildings
JP2011058275A (en) Office disaster prevention check diagnosis system
JP6950309B2 (en) Evacuation safety performance evaluation method, evacuation safety performance evaluation system, and program
JP4372457B2 (en) Evacuation time calculation device
JP4595462B2 (en) Computer system for evaluating evacuation safety performance, program, and recording medium recording the program
JP2017134703A (en) Smoke control design device, method, and program
JP2006107231A (en) Evacuation behavior predicting system and evacuation behavior predicting method
Hammarberg et al. Incorporation of elevator evacuation from a specific floor–A numerical study of an office building
Averill Performance-based codes: economics, documentation, and design
Chen et al. Evacuation strategies for vertical ship lift during initial fire: Integrated application of stairs and elevators