JP2007146538A - Method of treating pile head of on-site-formed pile - Google Patents

Method of treating pile head of on-site-formed pile Download PDF

Info

Publication number
JP2007146538A
JP2007146538A JP2005343837A JP2005343837A JP2007146538A JP 2007146538 A JP2007146538 A JP 2007146538A JP 2005343837 A JP2005343837 A JP 2005343837A JP 2005343837 A JP2005343837 A JP 2005343837A JP 2007146538 A JP2007146538 A JP 2007146538A
Authority
JP
Japan
Prior art keywords
pile
diameter
concrete
pile head
guide ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005343837A
Other languages
Japanese (ja)
Other versions
JP4176104B2 (en
Inventor
Mikio Shimizu
美木夫 清水
Osamu Saito
治 齋藤
Toshiyuki Yoshimatsu
敏行 吉松
Hidetaka Funaki
秀尊 舟木
Masafumi Hata
雅史 秦
Ichiro Yamaura
一郎 山浦
Masatoshi Kato
政利 加藤
Noriaki Isemoto
昇昭 伊勢本
Yoshitoshi Yasui
美敏 保井
Osamu Kaneko
治 金子
Kiyoshi Hotta
潔 堀田
Yoshito Kawakami
義人 川上
Yoshio Takeuchi
義夫 武内
Toshiaki Arai
寿昭 新井
Isamu Sugiura
勇 杉浦
Goryu Imanishi
語龍 今西
Naomasa Kamogawa
直昌 鴨川
Kazuhiko Onishi
和彦 大西
Hitoshi Kobayashi
仁 小林
Akihito Horikoshi
章仁 堀越
Noriyoshi Nishimura
憲義 西村
Takayuki Aoyama
隆行 青山
Mitsuo Motoi
光生 許斐
Yoshiyuki Murata
義行 村田
Takayoshi Okano
崇宜 岡野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MATSUI CONSTRUCTION CO Ltd
Neturen Co Ltd
Kajima Corp
Tobishima Corp
Nishimatsu Construction Co Ltd
Penta Ocean Construction Co Ltd
Okumura Corp
Toda Corp
Sumitomo Mitsui Construction Co Ltd
Haseko Corp
Original Assignee
MATSUI CONSTRUCTION CO Ltd
Neturen Co Ltd
Kajima Corp
Tobishima Corp
Nishimatsu Construction Co Ltd
Penta Ocean Construction Co Ltd
Okumura Corp
Toda Corp
Sumitomo Mitsui Construction Co Ltd
Haseko Corp
Hasegawa Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MATSUI CONSTRUCTION CO Ltd, Neturen Co Ltd, Kajima Corp, Tobishima Corp, Nishimatsu Construction Co Ltd, Penta Ocean Construction Co Ltd, Okumura Corp, Toda Corp, Sumitomo Mitsui Construction Co Ltd, Haseko Corp, Hasegawa Komuten Co Ltd filed Critical MATSUI CONSTRUCTION CO Ltd
Priority to JP2005343837A priority Critical patent/JP4176104B2/en
Publication of JP2007146538A publication Critical patent/JP2007146538A/en
Application granted granted Critical
Publication of JP4176104B2 publication Critical patent/JP4176104B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method of treating a pile head of an on-site-formed pile by which the treatment of the pile head in accordance with a designed diameter of the on-site-formed pile can be easily carried out without causing a damage like a chip accompanied by the treatment of the pile head. <P>SOLUTION: A reinforcing cage 2 is placed in an excavated vertical hole 1. A pile-diameter-forming guide ring 3 is formed to have the same or substantially the same diameter as the designed diameter of the pile 6 which is to be formed, and is provided with a projecting cap-ring mounting guide 3a to mount a cap ring 7 on the outer periphery. The guide ring 3 is concentrically mounted on an upper end part of the reinforcing cage 2 at the same position or substantially the same position as that of a designed level of the pile 6. Concrete 4 is placed in the vertical hole 1 to the level higher than that of the guide ring 3. After the concrete 4 is cured, the concrete in a part higher than the mounting level of the guide ring 3 is removed. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は現場造成杭の杭頭処理方法に関し、設計径の杭頭を容易に確保し、欠け等の損傷を未然に防止して杭頭の処理をきわめて簡単に行えるようにしたものである。   The present invention relates to a method for treating a pile head of a field-built pile, which easily secures a pile head having a design diameter, prevents damage such as chipping, and allows the pile head to be treated very easily.

一般に、場所打ちコンクリートによる現場造成杭は、コンクリートの打設時に杭頭部分にスライム等の不純物が浮上しそのまま固化してしまうため、施工直後の杭頭部分には杭としての強度を期待できない。   Generally, in-situ piles made of cast-in-place concrete cannot be expected to have strength as piles immediately after construction because impurities such as slime float on the pile heads when concrete is placed and solidify.

そのため、杭の設計レベルよりある程度高い位置までコンクリートを、いわゆる余盛りし、この余盛りした部分を硬化後、はつる等して杭頭を処理している。   Therefore, concrete is so-called surplus to a position that is somewhat higher than the design level of the pile, and after the surplus portion is hardened, the pile head is processed by hanging.

従来、この杭頭処理は、コンクリートが硬化した後、杭頭の外周に設計レベルに合わせてカッター等によって切込みを入れ、この切込みから余盛りした部分のコンクリートを砕いて除去するのが一般的であった。さらに、設計径の杭頭を得るには、杭頭を設計径に合わせて周囲をはつり落とすことが一般的であった。   Conventionally, this pile head treatment is generally performed by cutting the outer periphery of the pile head with a cutter or the like according to the design level, and then crushing and removing the excess concrete from this cut. there were. Furthermore, in order to obtain a pile head with a design diameter, it is common to hang the pile head around the design diameter.

ところで、こうして造成された基礎杭と当該基礎杭の上部に構築される上部基礎とを接合する基礎杭頭部の構造として、当出願人はこれまで、例えば図5(a),(b)に図示するように、基礎杭6の杭頭部にプレキャストコンクリートからなるリング形状のキャプリング7を被せ、当該キャプリング7を介して基礎杭6と上部基礎13とを接合する基礎杭頭部の構造を開発した(特許文献1参照)。   By the way, as a structure of the foundation pile head which joins the foundation pile constructed in this way and the upper foundation constructed on the upper part of the foundation pile, the present applicant has so far shown in FIGS. 5 (a) and 5 (b), for example. As shown in the figure, the pile head of the foundation pile 6 is covered with a ring-shaped coupling 7 made of precast concrete, and the foundation pile 6 and the upper foundation 13 are joined to each other via the coupling 7. (See Patent Document 1).

当該基礎杭頭部の構造によれば、基礎杭6の杭頭部と上部基礎13との接合部を半固定状態とすることで、すなわち杭頭部に作用するせん断力と鉛直力(軸圧縮力)は基礎杭6側に伝わるものの回転力(曲げ力)は伝わらないようにすることができ、これにより基礎杭6の頭部に集中する地震時の応力を緩和することができるため、基礎杭頭部の損傷等を未然に防ぐことができるだけでなく、杭や基礎などのコスト低減が図れる。   According to the structure of the foundation pile head, the joint between the pile head of the foundation pile 6 and the upper foundation 13 is in a semi-fixed state, that is, shear force and vertical force (axial compression acting on the pile head). Force) is transmitted to the foundation pile 6 side, but the rotational force (bending force) can be prevented from being transmitted, and this can relieve the stress during the earthquake concentrated on the foundation pile 6 head. In addition to preventing damage to the pile head, the cost of piles and foundations can be reduced.

特開2002−167776号公報JP 2002-167776 A 特公平6−21454号公報Japanese Examined Patent Publication No. 6-21454 特開平8−105041号公報JP-A-8-105041 特開2001−200536号公報Japanese Patent Laid-Open No. 2001-200536

しかし、余盛りした部分のコンクリートを砕いて除去する際に、破砕用の冶具による振動や衝撃などによって切込み位置より下側の設計径の内側の部分まで欠いてしまうことが多く、その部分の補修に多くの労力を必要とした。   However, when crushing and removing the overlying concrete, the part inside the design diameter below the cut position is often missing due to vibrations or impacts caused by the crushing jig, and repairing that part. It required a lot of effort.

また、はつった後の杭頭部が設計径より大きい場合に、円形状にカッターを入れることは困難であり、カッターを入れることなく設計径の周囲をはつりおとそうとすると、設計径の内部の部分まで欠いてしまって補修を強いられた。   In addition, when the pile head after staking is larger than the design diameter, it is difficult to insert a cutter into a circular shape, and if you try to lift around the design diameter without inserting a cutter, The inside part was missing and forced to repair.

なお、振動や衝撃などに伴う損傷を未然に防ぐ方法として、余盛りしたコンクリートが硬化した後でも剥離しやすいように構成された冶具を、コンクリートを打設した直後、杭の設計レベル位置に取り付けることも行われているが(特許文献2)、構造が複雑化してコストが嵩む等の課題があった。   In addition, as a method to prevent damage due to vibration or impact, a jig configured to easily peel off even after the overlaid concrete has hardened is attached to the design level position of the pile immediately after placing the concrete. Although this has been done (Patent Document 2), there is a problem that the structure is complicated and the cost is increased.

本発明は、以上の課題を解決するためになされたもので、杭頭処理を容易に行うことができて設計径の杭頭を容易に確保することができる現場造成杭の杭頭処理方法を提供することを目的とする。   The present invention was made in order to solve the above-described problems, and provides a pile head treatment method for a field-built pile that can easily perform pile head treatment and easily secure a pile head having a design diameter. The purpose is to provide.

請求項1記載の現場造成杭の杭頭処理方法は、削孔した孔内に鉄筋かごを立て込み、当該孔内にコンクリートを打設し、かつ上端部にキャプリングを設置することにより構築する現場造成杭の杭頭処理方法であって、造成される杭の設計径と同径若しくは略同径に形成され、外周に前記キャプリングを設置するためのキャプリング設置ガイドが突設された杭径整形ガイドリングを、前記鉄筋かごの上端部に前記杭の設計レベルと同一若しくは略同一の位置に同心円状に取り付けた後、前記孔内にコンクリートを前記杭径整形ガイドリングより高いレベルまで打設し、当該コンクリートが硬化した後、前記杭径整形ガイドリングの設置位置より上方部分のコンクリートを除去することを特徴とするものである。   The pile head processing method for a field-built pile according to claim 1 is constructed by placing a reinforcing steel cage into a drilled hole, placing concrete in the hole, and installing a cap on the upper end. A pile head treatment method for an on-site pile, wherein the pile is formed to have the same diameter as or approximately the same diameter as the pile to be created, and a pile installation guide is provided on the outer periphery of the pile. After the diameter shaping guide ring is concentrically attached to the upper end of the reinforcing bar at the same or substantially the same position as the pile design level, concrete is put into the hole to a level higher than the pile diameter shaping guide ring. After the concrete is hardened, the concrete in the upper part from the installation position of the pile diameter shaping guide ring is removed.

本発明は、掘削した孔内にコンクリートを打設する前、当該孔内に立て込んだ鉄筋かごの上端部に、造成される杭の設計径と同径若しくは略同径に形成され、外周にキャプリングを設置するためのキャプリング設置ガイドが突設された杭径整形ガイドリングを取り付けておくことで、杭の設計レベルより上側の、いわゆる余盛りした部分のコンクリートを当該コンクリートが硬化した後に砕いて容易に除去することができ、これにより設計径の杭頭を容易に確保することができ、かつ杭頭処理後の当該杭頭にキャプリングをすぐに設置できて施工の効率化を可能にしたものである。   The present invention is such that, before placing concrete in an excavated hole, it is formed at the upper end of a reinforcing steel cage standing in the hole with the same or substantially the same diameter as the designed diameter of the pile to be built, By attaching a pile diameter shaping guide ring with a capling installation guide for installing the ring, the so-called surplus concrete above the pile design level is crushed after the concrete has hardened. This makes it possible to easily secure the pile head of the design diameter, and to quickly install the coupling on the pile head after the pile head treatment, thus making it possible to improve the efficiency of construction. It is a thing.

なお、ここで用いる杭径整形ガイドリングは、帯鋼などの所定厚の鋼板を湾曲させて簡単に形成することができ、また当該杭径整形ガイドリングは鉄筋かごを組み立てる際、あるいは鉄筋かごを孔内に建て込んだ後のいずれの時点で取り付けてもよい。また、杭径整形ガイドリングの高さ(鋼板の幅)は、造成される杭の設計径や使用されるコンクリートの強度などを適宜参酌して決定してよい。   In addition, the pile diameter shaping guide ring used here can be easily formed by curving a steel plate of a predetermined thickness such as a strip steel, and the pile diameter shaping guide ring is used when assembling the rebar cage or rebar cage. It may be attached at any time after being built into the hole. The height of the pile diameter shaping guide ring (the width of the steel plate) may be determined by appropriately taking into account the design diameter of the pile to be created, the strength of the concrete used, and the like.

請求項2記載の現場造成杭の杭頭処理方法は、請求項1記載の現場造成杭の杭頭処理方法において、キャプリング設置ガイドは、杭径整形ガイドリングの円周方向に複数突設することを特徴とするものである。キャプリング設置ガイドは、少なくとも3個を等間隔に突設することでキャプリングを安定した状態に設置することができる。なお、キャプリング設置ガイドは、杭径整形ガイドリングと一体に形成されていてもよく、ボルト止め若しくはクリップ止め、さらには溶接等によって後付けとすることもできる。   The pile head processing method for an on-site formation pile according to claim 2 is the pile head processing method for an on-site formation pile according to claim 1, wherein a plurality of capping installation guides project in the circumferential direction of the pile diameter shaping guide ring. It is characterized by this. Capturing installation guides can be installed in a stable state by protruding at least three at equal intervals. The coupling installation guide may be formed integrally with the pile diameter shaping guide ring, and can be retrofitted by bolting or clipping, further welding or the like.

請求項3記載の現場造成杭の杭頭処理方法は、請求項1または2記載の現場造成杭の杭頭処理方法において、キャプリング設置ガイドにレベル調整ピースを突設することを特徴とするものである。キャプリングのレベル調整を行えるようにしたものである。   The pile head processing method for a site-created pile according to claim 3 is characterized in that in the pile head treatment method for a site-created pile according to claim 1 or 2, a level adjustment piece protrudes from the coupling installation guide. It is. The level of coupling can be adjusted.

請求項4記載の現場造成杭の杭頭処理方法は、請求項1〜3のいずれかに記載の現場造成杭の杭頭処理方法において、キャプリング設置ガイドに杭頭レベル確認用ブロックを突設したことを特徴とするものである。   The pile head processing method for a field-built pile according to claim 4 is a pile head processing method for a field-built pile according to any one of claims 1 to 3, wherein a pile head level confirmation block is provided in a projecting installation guide. It is characterized by that.

本発明は、杭頭レベル確認用ブロックの外周部がコンクリート面に露出していることで、杭頭をはつる際にこのブロックを取り外すことで、杭頭レベルの位置を簡単に確認することができ、はつり作業を容易に行うことができる。   In the present invention, the outer periphery of the pile head level confirmation block is exposed on the concrete surface, and by removing this block when hanging the pile head, the position of the pile head level can be easily confirmed. Can be carried out easily.

なお、この場合の杭頭レベル確認用ブロックには発泡スチロール等を用いることができ、キャプリング設置ガイドを突き刺す等の方法により簡単に取り付けることができる。   In this case, a foam head or the like can be used for the pile head level confirmation block, and it can be easily attached by a method such as piercing a coupling installation guide.

本発明は特に、掘削した孔内にコンクリートを打設する前、当該孔内に立て込んだ鉄筋かごの上端部に、造成される杭の設計径と同径または略同径の杭径整形ガイドリングを杭の設計レベルに合わせ、かつ前記鉄筋かごと同心円状に取り付けておくことで、設計レベルより上のいわゆる余盛りした部分のコンクリートを硬化後砕いて除去する際、品質上重要な杭頭部のかけ等の損傷を未然に防止することができる等の効果を有する。   In particular, the present invention particularly relates to a pile diameter shaping guide ring having the same or substantially the same diameter as the designed diameter of the pile to be formed on the upper end of the reinforcing steel cage standing in the hole before placing concrete in the excavated hole. The pile head, which is important in terms of quality, is removed when the so-called surplus part of the concrete above the design level is hardened and removed by crushing it according to the design level of the pile and concentrically with the rebar cage. It has the effect of preventing damage such as staking.

図1と図2は、杭頭(杭の天端)が掘削用ケーシングの下端より浅い場合の場所打ちコンクリートによる現場造成杭の施工過程を示し、図において、削孔した縦孔1内に鉄筋かご2が立て込まれ、当該鉄筋かご2の上端部に杭径整形ガイドリング3が水平に取り付けられている。   1 and 2 show the construction process of a site-built pile made of cast-in-place concrete when the pile head (the top of the pile) is shallower than the lower end of the excavation casing. A car 2 is stood up and a pile diameter shaping guide ring 3 is horizontally attached to an upper end portion of the reinforcing steel car 2.

また、縦孔1内にコンクリート4が打設され、当該コンクリート4は最終的に、例えば図2(a)に図示するように杭径整形ガイドリング3より上方の所定の高さまでいわゆる余盛りされる。   Further, concrete 4 is placed in the vertical hole 1, and the concrete 4 is finally piled up to a predetermined height above the pile diameter shaping guide ring 3 as shown in FIG. 2A, for example. The

鉄筋かご2は複数の主筋2aと当該主筋2a,2a間の外側に巻き掛けられた複数のフープ筋2bとから円筒状に組み立てられている。当該鉄筋かご2を組み立てるには、例えば、図3(a),(b)に図示するような、鉄筋かご2のフープ筋2bと同心円状に設置された補強リング5が用いられ、鉄筋かご2の各主筋2aの上端部は補強リング5にそれぞれ固定されている。   The reinforcing bar 2 is assembled in a cylindrical shape from a plurality of main bars 2a and a plurality of hoop bars 2b wound around the outside of the main bars 2a, 2a. In order to assemble the rebar cage 2, for example, a reinforcing ring 5 installed concentrically with the hoop bar 2 b of the rebar cage 2 as shown in FIGS. 3A and 3B is used. The upper ends of the main bars 2a are fixed to the reinforcing ring 5, respectively.

杭径整形ガイドリング3は造成される杭6の設計径と同じ径に、かつ補強リング5より大きい径に形成され、外周にはキャプリング7を載置するためのキャプリング設置ガイド3aが円周方向に等間隔に複数突設されている。   The pile diameter shaping guide ring 3 is formed to have the same diameter as the designed diameter of the pile 6 to be constructed and larger than the reinforcing ring 5, and a coupling installation guide 3 a for mounting the coupling 7 is circular on the outer periphery. A plurality of protrusions are provided at equal intervals in the circumferential direction.

また、当該杭径整形ガイドリング3は鉄筋かご2の上端部に当該鉄筋かご2のフープ筋2bおよび補強リング5と同心円状に設置され、かつ補強リング5の外側に水平に突設された複数の連結バー8によって補強リング5に固定されている。   Further, the pile diameter shaping guide ring 3 is installed on the upper end of the reinforcing bar 2 concentrically with the hoop bar 2b of the reinforcing bar 2 and the reinforcing ring 5 and horizontally protrudes outside the reinforcing ring 5. The connecting bar 8 is fixed to the reinforcing ring 5.

なお、杭径整形ガイドリング3、当該杭径整形ガイドリング3のキャプリング設置ガイド3a、補強リング5および連結バー8は、いずれも所定厚・所定幅の鋼板から形成され、またこれらの部材は溶接によって互いに結合されている。   In addition, the pile diameter shaping guide ring 3, the capping installation guide 3a of the pile diameter shaping guide ring 3, the reinforcing ring 5, and the connecting bar 8 are all formed from a steel plate having a predetermined thickness and a predetermined width. They are joined together by welding.

また、杭径整形ガイドリング3は補強リング5の外側に予め取り付けられ、キャプリング設置ガイド3aは杭径整形ガイドリング3の外周に予め突設されている。   Further, the pile diameter shaping guide ring 3 is attached in advance to the outside of the reinforcing ring 5, and the coupling installation guide 3 a is projected in advance on the outer periphery of the pile diameter shaping guide ring 3.

このような構成において、次に、本発明の杭頭処理方法を現場造成杭の施工手順とともに説明する。
In such a configuration, the pile head processing method of the present invention will be described together with the construction procedure of the on-site creation pile.

a.最初に、現場造成杭6を造成するための縦孔1を削孔する。この場合の削孔には一般に広く用いられている削孔方法を利用することができ、また削孔用ケーシング9は孔壁の保護および掘り始め部分の施工上必要なものである。
a. First, the vertical hole 1 for creating the on-site creation pile 6 is drilled. In this case, a drilling method which is generally widely used can be used for drilling, and the drilling casing 9 is necessary for protecting the hole wall and constructing the digging start portion.

b.次に、予め組み立てられた鉄筋かご2の上端部に別途形成した杭径整形ガイドリング3を補強リング5と連結バー8を用いて取り付ける。杭径整形ガイドリング3は造成される現場造成杭6の設計レベルに合わせ、かつ鉄筋かご2と同心円状に取り付ける。
b. Next, a pile diameter shaping guide ring 3 separately formed on the upper end portion of the rebar cage 2 assembled in advance is attached using the reinforcing ring 5 and the connecting bar 8. The pile diameter shaping guide ring 3 is attached to the rebar cage 2 and concentrically according to the design level of the on-site created pile 6 to be created.

c.次に、鉄筋かご2を縦孔1内に立て込み、当該鉄筋かご2を縦孔1の中央にセットする。この場合、鉄筋かご2は杭頭の設計レベルが地表より低い位置にあるようにセットし、また上端部が地表より低い位置に位置するように立て込むものとする。なお、この段階で鉄筋かご2の上端部に杭径整形ガイドリング3を取り付けてもよい。
c. Next, the reinforcing bar 2 is stood in the vertical hole 1 and the reinforcing bar 2 is set at the center of the vertical hole 1. In this case, the rebar cage 2 is set so that the design level of the pile head is lower than the ground surface, and is stood so that the upper end is positioned lower than the ground surface. At this stage, the pile diameter shaping guide ring 3 may be attached to the upper end of the reinforcing bar 2.

d.次に、縦孔1内にコンクリート4を打設する。コンクリート4は杭径整形ガイドリング3の上方の所定の高さまで連続して打設する。いわゆるコンクリート4の余盛りをする。
d. Next, concrete 4 is placed in the vertical hole 1. The concrete 4 is continuously placed up to a predetermined height above the pile diameter shaping guide ring 3. So-called concrete 4 is added.

e.次に、コンクリート4の打設が完了したら、コンクリート4が硬化する前に掘削用ケーシング9を引き抜いて撤去する。また、こうして造成した現場造成杭6の周囲の地盤10を根切りによって掘り下げる。根切りは杭径整形ガイドリング3の下側まで行う。
e. Next, when the placement of the concrete 4 is completed, the excavation casing 9 is pulled out and removed before the concrete 4 is hardened. Further, the ground 10 around the site-built pile 6 thus created is dug down by root cutting. Root cutting is performed to the lower side of the pile diameter shaping guide ring 3.

f.次に、現場造成杭6の杭頭部の外周に杭径整形リング3の上側に沿って切込み6aを入れる。そして、この切込み6aより上側部分の余盛りを砕いて除去する。
f. Next, an incision 6 a is made along the upper side of the pile diameter shaping ring 3 on the outer periphery of the pile head of the on-site created pile 6. And the surplus of the upper part from this notch 6a is crushed and removed.

g.杭頭部に露出した整形ガイドリング3に合わせて設計径より外側の周囲のコンクリートをはつり落とす。このようにすることにより、天端に円形状にカッターを入れることなく、また設計径の内側を損傷することなく、設計径の杭頭を得ることができる。 g. The concrete surrounding outside the design diameter is suspended in accordance with the shaping guide ring 3 exposed to the pile head. By doing in this way, the pile head of a design diameter can be obtained, without putting a cutter circularly in a top end and without damaging the inner side of a design diameter.

図4(a)は、キャプリング設置ガイド3aにレベル調整用部材11を上下方向に移動自在に取り付け、このレベル調整用部材11を上げ下げすることで当該レベル調整部材11の上に載置されたキャプリング7のレベル調整を簡単に行えるようにしたものである。   In FIG. 4A, the level adjustment member 11 is attached to the coupling installation guide 3a so as to be movable in the vertical direction, and the level adjustment member 11 is raised and lowered to be placed on the level adjustment member 11. The level of the coupling 7 can be easily adjusted.

また、図4(b)は、キャプリング設置ガイド3aに発泡スチロール等からなる杭頭レベル確認用ブロック12を取り付けることにより、掘削用ケーシング9を撤去した後、余盛りしたコンクリートを除去する際、造成される現場造成杭6の杭頭レベルを一目で確認できるようにしたものである。   FIG. 4 (b) shows that when removing piled concrete after removing the excavating casing 9 by attaching a pile head level confirmation block 12 made of foamed polystyrene or the like to the coupling installation guide 3a. This makes it possible to confirm at a glance the pile head level of the site-built pile 6 to be used.

この場合、杭頭レベル確認用ブロック12は、コンクリート4を打設する前に各キャプリング設置ガイド3aに取り付けておくことで、掘削用ケーシング9を撤去した際、コンクリート4の表面に露出するため、現場造成杭6の杭頭レベルを一目で確認することができる。   In this case, the pile head level confirmation block 12 is attached to each coupling installation guide 3a before placing the concrete 4, so that when the excavating casing 9 is removed, the pile head level confirmation block 12 is exposed to the surface of the concrete 4. The pile head level of the on-site creation pile 6 can be confirmed at a glance.

本発明は、場所打ちコンクリートによる現場造成杭の杭頭処理を、設計径の杭頭を容易に確保してきわめて簡単に行うことができる。   INDUSTRIAL APPLICABILITY According to the present invention, a pile head treatment of a field-built pile by cast-in-place concrete can be performed very easily by easily securing a pile head having a design diameter.

杭頭(杭の天端)が掘削用ケーシングの下端より浅い位置にある現場造成杭の施工方法を示し、(a)はコンクリートを打設する前の杭頭部の平面図、(b)はその縦断面図である。The pile head (top end of the pile) shows the construction method of the site-built pile in a position shallower than the lower end of the excavation casing, (a) is a plan view of the pile head before placing concrete, (b) It is the longitudinal cross-sectional view. 杭頭処理の施工手順を示し、(a)はコンクリートを打設した後の杭頭部を示す一部縦断面図、(b)は現場造成杭の周囲の地盤を根切りによって杭頭整形ガイドリングの下端まで掘り下げた一部縦断面図、(c)は余盛りした部分のコンクリートを除去した後の杭頭部を示す一部縦断面図、(d)は周囲のコンクリートを除去した後の杭頭部を示す一部縦断面図である。The construction procedure of the pile head treatment is shown, (a) is a partial longitudinal sectional view showing the pile head after placing concrete, (b) is a pile head shaping guide by rooting the ground around the site-built pile. Partial longitudinal cross-sectional view dug down to the lower end of the ring, (c) is a partial longitudinal sectional view showing the pile head after removing the overlying portion of concrete, (d) is after removing the surrounding concrete It is a partial longitudinal cross-sectional view which shows a pile head. 杭径整形リングの取付方法を示し、(a)は杭頭部の平面図、(b)は(a)におけるイ−イ線縦断面図である。The method for attaching the pile diameter shaping ring is shown, (a) is a plan view of the pile head, (b) is a longitudinal sectional view taken along line II in (a). (a),(b)は本発明の他の例を示し、杭頭部の縦断面図である。(a), (b) shows the other example of this invention, and is a longitudinal cross-sectional view of a pile head. 基礎杭と上部基礎がキャプリングによって接合された基礎杭頭部の構造を示し、(a)は縦断面図、(b)は(a)におけるロ−ロ線断面図である。The structure of the foundation pile head where the foundation pile and the upper foundation were joined by the coupling is shown, (a) is a longitudinal sectional view, and (b) is a roll line sectional view in (a).

符号の説明Explanation of symbols

1 削孔した縦孔
2 鉄筋かご
2a 主筋
2b フープ筋
3 杭径整形ガイドリング
3a キャプリング設置ガイド
4 コンクリート
5 補強リング
6 基礎杭、現場造成杭
7 キャプリング
8 連結バー
9 掘削用ケーシング
10 地盤
11 レベル調整用部材
12 杭頭レベル確認用ブロック
13 上部基礎
DESCRIPTION OF SYMBOLS 1 Drilled vertical hole 2 Reinforcing bar 2a Main bar 2b Hoop bar 3 Pile diameter shaping guide ring 3a Caping installation guide 4 Concrete 5 Reinforcement ring 6 Foundation pile, site-built pile 7 Capturing 8 Connection bar 9 Excavation casing 10 Ground 11 Level adjustment member 12 Pile head level confirmation block 13 Upper foundation

Claims (4)

削孔した孔内に鉄筋かごを立て込み、当該孔内にコンクリートを打設し、かつ上端部にキャプリングを設置することにより構築する現場造成杭の杭頭処理方法であって、造成される杭の設計径と同径若しくは略同径に形成され、かつ外周に前記キャプリングを設置するためのキャプリング設置ガイドが突設された杭径整形ガイドリングを、前記鉄筋かごの上端部に前記杭の設計レベルと同一若しくは略同一の位置に同心円状に設けた後、前記孔内にコンクリートを前記杭径整形ガイドリングより高いレベルまで打設し、当該コンクリートが硬化した後、前記杭径整形ガイドリングの設置位置より上方部分のコンクリートを除去することを特徴とする現場造成杭の杭頭処理方法。   A pile head treatment method for a site-built pile constructed by placing a rebar cage in a drilled hole, placing concrete in the hole, and installing a cap on the upper end. A pile diameter shaping guide ring that is formed to have the same diameter as or approximately the same diameter as the design diameter of the pile and that has a coupling installation guide for projecting the cap ring installed on the outer periphery is provided at the upper end of the rebar cage. After concentrically providing at the same or substantially the same position as the pile design level, after placing concrete in the hole to a level higher than the pile diameter shaping guide ring and hardening the concrete, the pile diameter shaping A pile head processing method for a site-built pile, characterized by removing the concrete above the guide ring installation position. 前記キャプリング設置ガイドは、杭径整形ガイドリングの円周方向に複数突設することを特徴とする請求項1記載の現場造成杭の杭頭処理方法。   The pile head processing method for a field-built pile according to claim 1, wherein a plurality of the coupling installation guides protrude in the circumferential direction of the pile diameter shaping guide ring. 前記キャプリング設置ガイドにレベル調整用ピースを突設することを特徴とする請求項1または2記載の現場造成杭の杭頭処理方法。   The pile head processing method for a field-built pile according to claim 1 or 2, wherein a level adjusting piece projects from the coupling installation guide. 前記キャプリング設置ガイドに杭頭レベル確認用ブロックを突設することを特徴とする請求項1〜3のいずれかに記載の現場造成杭の杭頭処理方法。

The pile head processing method for a field-built pile according to any one of claims 1 to 3, wherein a block for checking a pile head level is provided on the coupling installation guide.

JP2005343837A 2005-11-29 2005-11-29 Pile head treatment method for site-built piles Active JP4176104B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005343837A JP4176104B2 (en) 2005-11-29 2005-11-29 Pile head treatment method for site-built piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005343837A JP4176104B2 (en) 2005-11-29 2005-11-29 Pile head treatment method for site-built piles

Publications (2)

Publication Number Publication Date
JP2007146538A true JP2007146538A (en) 2007-06-14
JP4176104B2 JP4176104B2 (en) 2008-11-05

Family

ID=38208259

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005343837A Active JP4176104B2 (en) 2005-11-29 2005-11-29 Pile head treatment method for site-built piles

Country Status (1)

Country Link
JP (1) JP4176104B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425157A (en) * 2011-08-26 2012-04-25 中天建设集团有限公司 Structure for locating protective layer of cast-in-place pile
JP2013167114A (en) * 2012-02-16 2013-08-29 Ohbayashi Corp Underground structure and construction method thereof
JP2021042606A (en) * 2019-09-12 2021-03-18 東急建設株式会社 Pile head connection structure, and construction method of pile head connection structure
JP2022133967A (en) * 2021-03-02 2022-09-14 東急建設株式会社 Pile head connection structure and method for constructing pile head connection structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425157A (en) * 2011-08-26 2012-04-25 中天建设集团有限公司 Structure for locating protective layer of cast-in-place pile
JP2013167114A (en) * 2012-02-16 2013-08-29 Ohbayashi Corp Underground structure and construction method thereof
JP2021042606A (en) * 2019-09-12 2021-03-18 東急建設株式会社 Pile head connection structure, and construction method of pile head connection structure
JP7304248B2 (en) 2019-09-12 2023-07-06 東急建設株式会社 Pile head connection structure and construction method of pile head connection structure
JP2022133967A (en) * 2021-03-02 2022-09-14 東急建設株式会社 Pile head connection structure and method for constructing pile head connection structure
JP7308871B2 (en) 2021-03-02 2023-07-14 東急建設株式会社 Pile head connection structure and construction method of pile head connection structure

Also Published As

Publication number Publication date
JP4176104B2 (en) 2008-11-05

Similar Documents

Publication Publication Date Title
JP5033068B2 (en) Pile head treatment method in cast-in-place concrete pile method
JP4623574B2 (en) How to build a pile
JP4693423B2 (en) Pile head reinforcement method
JP4176104B2 (en) Pile head treatment method for site-built piles
JP2005120663A (en) Structure of earth retaining wall
JP2007162266A (en) Two-step earth retaining wall and its construction method
JP4388413B2 (en) Pile head treatment method for cast-in-place concrete piles
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP2007023602A (en) Construction method for foundation structure
JP2010126900A (en) Construction method for mounting base-isolating device
JP2021042606A (en) Pile head connection structure, and construction method of pile head connection structure
KR101818428B1 (en) Filler for forming mating surface of concrete pile and construction method of concrete pile using the same
KR101105853B1 (en) Constructing method of cast-in-place concrete pile using mold case
JP5016521B2 (en) Earth anchor and its removal method
KR101404007B1 (en) Reinforced concrete pile construction method for which steel pipe casing structure for steel pipe casing recovery this were used
JP6322490B2 (en) Pile head treatment method for severing material and site-built pile
JP4778386B2 (en) Construction method of pile head fixing structure in pile
JPH08209686A (en) Pile head processing tool and pile head processing construction method for cast-in-place pile
JP4311625B2 (en) Cast-in-place concrete pile construction method and rebar cage
JP3805342B2 (en) Yamadome wall structure
JP4820325B2 (en) caisson
JP6909607B2 (en) How to build cast-in-place piles and foundations
JP2000144742A (en) Artesian countermeasure method in ground excavation work
JP2004100281A (en) Positioning method for permanent substructural column without using casing
JP6233753B2 (en) Pile head structure and construction method of pile head structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080430

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080627

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080819

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080819

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110829

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4176104

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110829

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140829

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250