JP2007113340A - Shaft excavation equipment - Google Patents

Shaft excavation equipment Download PDF

Info

Publication number
JP2007113340A
JP2007113340A JP2005308226A JP2005308226A JP2007113340A JP 2007113340 A JP2007113340 A JP 2007113340A JP 2005308226 A JP2005308226 A JP 2005308226A JP 2005308226 A JP2005308226 A JP 2005308226A JP 2007113340 A JP2007113340 A JP 2007113340A
Authority
JP
Japan
Prior art keywords
concrete
shaft
bucket
excavation
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005308226A
Other languages
Japanese (ja)
Inventor
Kazuo Taguchi
一生 田口
Noritoki Sabetsuto
法時 佐別當
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taguchi Industry Inc
Original Assignee
Taguchi Industry Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taguchi Industry Inc filed Critical Taguchi Industry Inc
Priority to JP2005308226A priority Critical patent/JP2007113340A/en
Publication of JP2007113340A publication Critical patent/JP2007113340A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide shaft excavation equipment which enables efficient feeding of concrete and placement of the concrete in a manner eliminating a waiting time. <P>SOLUTION: The shaft excavation equipment is provided with a muck bucket for taking out excavation muck to the outside of a shaft, and a concrete bucket 10 for taking in concrete C from the outside of the shaft, so that the buckets are vertically movable in the shaft T. Then each floor of a scaffold 1 has a through hole 1a to allow the muck bucket to vertically pass therethrough, and a concrete hopper 9 detachably attached to the through hole 1a. Thus during excavation, the muck bucket passes through the through hole 1a of the scaffold 1 to take out the excavation muck to the outside of the shaft. On the other hand during concrete placement, the concrete hopper 9 is attached to the through hole 1a of the scaffold 1, and thereafter the concrete C taken into the shaft by the concrete bucket 10 is transported to be placed on a side wall of the shaft T. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、立坑掘削設備に関し、詳しくはコンクリートを効率良く供給して打設できるようにする技術に関する。   The present invention relates to a shaft excavation facility, and more particularly to a technique that enables concrete to be efficiently supplied and placed.

従来、掘削機を備えたスカフォードを立坑内に吊下して地盤を掘削し、掘削ズリを坑外に搬出して掘削後の立坑の側壁にコンクリートを打設する立坑掘削設備がある。掘削ズリは立坑内をワイヤーロープで吊下して昇降するズリバケットで搬出し、コンクリートは立坑内をワイヤーロープで吊下して昇降する移動コンクリートホッパーで搬入して供給している。   2. Description of the Related Art Conventionally, there is a shaft excavation facility in which a scaffold equipped with an excavator is suspended in a shaft to excavate the ground, and excavation sludge is carried out of the shaft to place concrete on the side wall of the shaft after excavation. The excavation sludge is carried out by a sludge bucket that is lifted and lowered by hanging the inside of the shaft with a wire rope, and the concrete is carried by a moving concrete hopper that is hung by the wire rope and moved up and down.

ところで、コンクリートは一度に使用できる量を予め調整して搬入させる必要がある。打設中にコンクリートが不足すると打設を中断し、コンクリートホッパーを坑外へ搬出してコンクリートを補充して坑内へ再度搬入しなければならず、コンクリートホッパーの搬入出時は打設することができず待機となり、時間のロスが生じる問題があった。   By the way, it is necessary to adjust the amount of concrete that can be used at one time in advance. If there is a shortage of concrete during placement, the placement will be interrupted, the concrete hopper must be carried out of the mine, the concrete must be replenished and reintroduced into the mine, and the concrete hopper can be placed in and out. There was a problem that time was lost due to waiting.

また、コンクリートホッパーは通過穴とは別位置のスカフォード上に配置して打設作業するから、小径の立坑を構築する場合はスカフォード上にコンクリートホッパーの占有スペースを十分に確保できない問題もあった。
特開2003−106084号公報
In addition, since the concrete hopper is placed on a scaffold that is separate from the passage hole and is placed, there is a problem that when the small-diameter shaft is constructed, the space occupied by the concrete hopper cannot be secured on the scaffold. It was.
JP 2003-106084 A

本発明が解決しようとする課題は、従来のこれらの問題点を解消し、コンクリートの供給を効率的に行い待ち時間を生じることなく打設できるようにした立坑掘削設備を提供することにある。   The problem to be solved by the present invention is to provide a shaft excavation facility that solves these conventional problems and that can efficiently supply concrete and can be placed without waiting time.

かかる課題を解決した本発明の構成は、
1) 掘削機を備えたスカフォードを立坑内に吊下して地盤を掘削し、掘削ズリを坑外に搬出して掘削後の立坑の側壁にコンクリートを打設する立坑掘削設備において、掘削ズリを坑外に搬出するズリバケットとコンクリートを坑外から搬入するコンクリートバケットを立坑内にワイヤーロープで吊下して昇降可能とし、スカフォードにズリバケットが上下に通過できる通過穴を形成し、下部に排出シュートを備えた通過穴を通過できる大きさのコンクリートホッパーを通過穴に脱着自在に取り付け、掘削時はコンクリートホッパーを通過穴から取り外した後ズリバケットをスカフォードの通過穴から通過させて掘削ズリを坑外へ搬出し、コンクリート打設時はスカフォードの通過穴にコンクリートホッパーを取り付けた後コンクリートバケットで搬入したコンクリートをコンクリートホッパーに移送して排出シュートから立坑の側壁にコンクリートを供給して打設できるようにしたことを特徴とする、立坑掘削設備
2) スカフォードが複床式で、各床にズリバケット・コンクリートホッパー及びコンクリートバケットが通過できる通過穴をそれぞれ同じ位置に形成した、前記1)記載の立坑掘削設備
3) コンクリートホッパーの上部に複数のアームを放射状に展開可能に設け、コンクリートホッパーをスカフォードの通過穴に落とし込んで展開させたアームを通過穴の周部に掛止して取り付けるようにした、前記1)又は2)記載の立坑掘削設備
4) 立坑の坑口に扉を設け、坑口と坑口から離れた位置との間にコンクリートバケットの運搬台車を走行させる軌道を設け、坑口から離れた位置の軌道上にコンクリートをコンクリートバケットに供給する供給コンベヤを配設した、前記1)〜3)いずれか記載の立坑掘削設備
にある。
The configuration of the present invention that solves this problem is as follows.
1) In a shaft excavation facility in which a scaffold equipped with an excavator is suspended in a shaft, the ground is excavated, the excavation sludge is carried out of the shaft, and concrete is placed on the side wall of the shaft after excavation. Sliding buckets that carry out the mine and concrete buckets that carry concrete from the outside of the mine can be lifted by suspending them with a wire rope inside the vertical shaft, and a through hole is formed in the scaffold to allow the zuri bucket to pass up and down, and discharged to the bottom. A concrete hopper of a size that can pass through a passage hole equipped with a chute is detachably attached to the passage hole, and during excavation, the concrete hopper is removed from the passage hole, and then the slip bucket is passed through the passage hole of the Scaffold to remove the excavation slip. When unloading the concrete and placing concrete, attach a concrete hopper to the passage hole of the scaffold and then close the concrete bucket. The concrete excavation equipment is transported to the concrete hopper and supplied to the side wall of the shaft from the discharge chute so that it can be placed. The shaft excavation equipment as described in 1) above, wherein the floor is formed with through-holes through which the slip bucket / concrete hopper and the concrete bucket can pass 3) The concrete hopper is provided with a plurality of arms on the top of the concrete hopper so as to be radially deployable. The shaft excavation equipment described in 1) or 2) above, wherein the arm that is expanded by dropping into the passage hole of Scaffold is attached to the periphery of the passage hole. 4) A door is provided at the entrance of the shaft. A track for running a concrete bucket truck is provided between the wellhead and a position away from the wellhead. Is concrete in orbit positions were provided with feed conveyor for supplying the concrete bucket, the 1) to 3) in shaft excavation equipment according to any one.

本発明によれば、打設中もコンクリートバケットでコンクリートの補充が並行して行え、打設を中断させることなく効率的且つ短時間に供給できるようになる。また、コンクリートホッパーはズリバケットの通過穴に配置するようにしたから、従来の占有スペースを省略して小径の立坑でも打設作業が行えるようになる。   According to the present invention, concrete can be replenished in parallel with a concrete bucket even during placement, and can be supplied efficiently and in a short time without interrupting placement. Further, since the concrete hopper is arranged in the passage hole of the slip bucket, the conventional occupation space can be omitted and the driving work can be performed even with a small diameter shaft.

本発明では、スカフォードは2床や3床等の複床式にして小径の立坑構築における作業領域やバケット置き場を確保し、複数のズリバケットを交代させながら効率的に掘削ズリを排出できるようにしてもよい。また、立坑の坑口に扉を設け、コンクリートバケットへのコンクリート補充は坑口から離れた位置で行うようにして、補充時におけるコンクリートの立坑内への落下を防止するのが望ましい。以下、本発明の実施例を図面に基づいて具体的に説明する。   In the present invention, the Scaffold is a double-floor type such as two or three floors to secure a work area and a bucket storage place for construction of a small-diameter shaft, and to efficiently discharge excavation sludge while changing a plurality of sludge buckets. Also good. Further, it is desirable to provide a door at the shaft entrance of the shaft and replenish concrete into the concrete bucket at a position away from the shaft entrance to prevent the concrete from falling into the shaft during replenishment. Embodiments of the present invention will be specifically described below with reference to the drawings.

図1,2は実施例の立坑掘削設備の説明図、図3は実施例のコンクリート供給設備の平面図、図4は実施例のコンクリートホッパーの説明図、図5は実施例のコンクリートバケットの説明図、図6は実施例のコンクリートの打設を示す一部断面説明図、図7は実施例のスカフォードにコンクリートホッパーを配置した状態を示す平面図である。   1 and 2 are explanatory views of the shaft excavation equipment of the embodiment, FIG. 3 is a plan view of the concrete supply equipment of the embodiment, FIG. 4 is an explanatory view of the concrete hopper of the embodiment, and FIG. 5 is an explanation of the concrete bucket of the embodiment. FIG. 6 is a partial cross-sectional explanatory view showing placement of concrete in the embodiment, and FIG. 7 is a plan view showing a state in which a concrete hopper is arranged on the scaffold in the embodiment.

図中、1はスカフォード、1aは通過穴、1bは油圧ジャッキ、1cは支柱、1dは吊シーブ、2は掘削機、3は掘削やぐら、3aはズリシュート、4は吊ワイヤー、5はスカフォード巻上機、6はズリバケット、7は吊ワイヤー、8はズリバケット巻上機、9はコンクリートホッパー、9aはシュート、9bはアーム、9cは切換弁、9dは型枠、9eはホース、10はコンクリートバケット、10aは吊具、11は扉、12は軌道、13は供給コンベヤ、14は運搬台車、15はミキサー車、16はズリ置き場、17はコンクリートバケット置き場、18はズリバケット置き場、Cはコンクリート、Gは地盤、Hは作業者、Tは立坑である。   In the figure, 1 is a scaffold, 1a is a passage hole, 1b is a hydraulic jack, 1c is a support, 1d is a suspension sheave, 2 is an excavator, 3 is a drilling tower, 3a is a slip chute, 4 is a suspension wire, 5 is a scaffold Ford hoisting machine, 6 is slot bucket, 7 is hanging wire, 8 is slot bucket hoisting machine, 9 is concrete hopper, 9a is chute, 9b is arm, 9c is switching valve, 9d is formwork, 9e is hose, 10 is Concrete bucket, 10a is a hanging tool, 11 is a door, 12 is a track, 13 is a supply conveyor, 14 is a transport cart, 15 is a mixer truck, 16 is a slipping place, 17 is a concrete bucket place, 18 is a slipping place, C is concrete , G is the ground, H is an operator, and T is a shaft.

本実施例の立坑掘削設備は、図1,2に示すように支柱1cで上下に連設した3床式のスカフォード1の最下床に掘削機2を旋回自在に備え、各床の周部には立坑Tの側壁に圧接して保持する油圧ジャッキ1bを備え、各床にズリバケット6・コンクリートホッパー9・コンクリートバケット10が通過できる径の通過穴1aがそれぞれ同じ位置に形成され、スカフォード巻上機5の吊ワイヤー4を掘削やぐら3の頂部を介して最上床に備えた吊シーブ1dに巻回して昇降自在に吊下している。   As shown in FIGS. 1 and 2, the shaft excavation equipment of this embodiment is provided with an excavator 2 on the lowermost floor of a three-floor type scaffold 1 connected up and down by a column 1 c so that the excavator 2 can turn freely. The section is provided with a hydraulic jack 1b held in pressure contact with the side wall of the shaft T, and through holes 1a having diameters through which the slip bucket 6, the concrete hopper 9, and the concrete bucket 10 can pass are formed at the same position on each floor. The hoisting wire 4 of the hoisting machine 5 is wound around the hoisting sheave 1d provided on the uppermost floor through the top of the excavator and the tower 3 and hung up and down freely.

立坑Tの坑口には図3に示すように扉11を備え、扉11と扉11から離れた位置との間にコンクリートバケット10の運搬台車14を走行させる軌道12を設け、軌道12の途中の上方位置に運搬台車14で移動するコンクリートバケット10にコンクリートCを供給する供給コンベヤ13を配設している。   As shown in FIG. 3, the shaft T of the vertical shaft T is provided with a door 11, and a track 12 is provided between the door 11 and a position away from the door 11. A supply conveyor 13 for supplying concrete C to the concrete bucket 10 that is moved by the transport carriage 14 is disposed at an upper position.

コンクリートホッパー9は、図4に示すように下部にシュート9aを備え、上部には下向きから水平へ回動する4体のアーム9bを放射状に展開自在に取り付けている。コンクリートホッパー9はスカフォード1の通過穴1aを通過できる大きさで、アーム9bを水平に展開した状態の各アーム9b端間距離は通過穴1aの内径より大きく形成される。コンクリートバケット10は図5に示すように上部に吊具10aを備えており、ズリバケット巻上機8と吊ワイヤー7を兼用して昇降させる。   As shown in FIG. 4, the concrete hopper 9 is provided with a chute 9a at the lower part, and four arms 9b that rotate horizontally from the downward direction are attached to the upper part in a radially expandable manner. The concrete hopper 9 is large enough to pass through the passage hole 1a of the scaffold 1, and the distance between the ends of the arms 9b when the arms 9b are horizontally deployed is formed to be larger than the inner diameter of the passage hole 1a. As shown in FIG. 5, the concrete bucket 10 is provided with a hanging tool 10 a at the upper part, and is lifted and lowered by using both the sliding bucket hoist 8 and the hanging wire 7.

本実施例では、コンクリートホッパー9をスカフォード1上に搭載してスカフォード1を立坑T内で吊下し、掘削機2で地盤Gを掘削する。ズリバケット6は吊ワイヤー7でスカフォード1の通過穴1aを通過させて坑底に配置して掘削ズリを投入し、満杯となったズリバケット6を通過穴1aに通過させて上昇させ、扉11を開放して坑外へ搬出して掘削ズリをズリ置き場16に排出する。   In this embodiment, the concrete hopper 9 is mounted on the scaffold 1, the scaffold 1 is suspended in the shaft T, and the ground G is excavated by the excavator 2. The slip bucket 6 is passed through the passage hole 1a of the scaffold 1 by the hanging wire 7 and placed in the bottom of the well, and the excavation slot is inserted. The full bucket bucket 6 is passed through the passage hole 1a to be raised, and the door 11 is moved. It is opened and carried out of the mine, and the excavation slot is discharged to the slot 16.

所定深さに掘削すると掘削を一旦中断し、ズリバケット6を坑外又はスカフォード1上の空きスペースに仮置き、コンクリートホッパー9を吊ワイヤー7で持ち上げてスカフォード1の最下床の通過穴1aに途中まで落とし込み、アーム9bを水平位置に展開させて通過穴1aの周縁に掛止して吊設する。シュート9aにはホース9eを接続し、打設すべき側壁に型枠9dを配置する。   When excavating to a predetermined depth, the excavation is temporarily interrupted, the slip bucket 6 is temporarily placed in the outside of the mine or in an empty space on the scaffold 1, and the concrete hopper 9 is lifted by the suspension wire 7 so that the passage hole 1a on the lowest floor of the scaffold 1 is reached. The arm 9b is developed to a horizontal position and hooked around the periphery of the passage hole 1a. A hose 9e is connected to the chute 9a, and a mold 9d is arranged on the side wall to be driven.

コンクリートバケット10は運搬台車14に載せて供給コンベヤ13の下方まで移動し、供給コンベヤ13を作動する。供給コンベヤ13の隣接位置にはコンクリートCを運搬したミキサー車15が横付けされており、供給コンベヤ13の始端にコンクリートCを投下してコンクリートバケット10に投入する。所定量となったコンクリートバケット10は扉11の位置まで移動して吊ワイヤー7で吊り上げ、扉11を開放して立坑Tを降下させる。降下中は扉11を閉塞する。   The concrete bucket 10 is placed on the transport carriage 14 and moved below the supply conveyor 13 to operate the supply conveyor 13. A mixer truck 15 that transports concrete C is placed next to the supply conveyor 13, and the concrete C is dropped at the starting end of the supply conveyor 13 and put into the concrete bucket 10. The concrete bucket 10 having reached a predetermined amount moves to the position of the door 11 and is lifted by the suspension wire 7, and the door 11 is opened to lower the shaft T. During the descent, the door 11 is closed.

コンクリートバケット10はスカフォード1の通過穴1aを通過させて図6に示すようにコンクリートホッパー9の上部に載せ、コンクリートCをコンクリートホッパー9に移送してホース9eで型枠9d内に流し込んで打設する。コンクリートホッパー9内のコンクリートCが不足するようだと、無くなる前に打設作業と並行してコンクリートバケット10を坑外へ搬出して前記と同様にコンクリートCを投入し、再度坑内へ搬入してコンクリートホッパー9に補充する。   The concrete bucket 10 is passed through the passage hole 1a of the scaffold 1 and placed on the top of the concrete hopper 9 as shown in FIG. 6, and the concrete C is transferred to the concrete hopper 9 and poured into the mold 9d by the hose 9e. Set up. If the concrete C in the concrete hopper 9 seems to be insufficient, the concrete bucket 10 is taken out of the mine in parallel with the placing work before it disappears, and the concrete C is put in the same manner as described above, and again in the mine. Refill the concrete hopper 9.

このように、本実施例では打設中もコンクリートバケット10は並行してコンクリートCの補充が行え、打設を中断させることなく効率的且つ短時間に供給できるようになった。また、コンクリートホッパー9はズリバケット6の通過穴1aに配置するようにしたから、従来の占有スペースを省略して小径の立坑でも打設作業が行えるようになった。   As described above, in this embodiment, the concrete bucket 10 can be replenished with the concrete C in parallel during the placement, and can be supplied efficiently and in a short time without interrupting the placement. In addition, since the concrete hopper 9 is arranged in the passage hole 1a of the slip bucket 6, the conventional occupation space can be omitted and the driving work can be performed even with a small diameter shaft.

本発明の立坑掘削設備は、大深度の立坑の構築に好ましく利用される。   The shaft excavation equipment of the present invention is preferably used for construction of a deep shaft.

実施例の立坑掘削設備の説明図である。It is explanatory drawing of the shaft excavation equipment of an Example. 実施例の立坑掘削設備の説明図である。It is explanatory drawing of the shaft excavation equipment of an Example. 実施例のコンクリート供給設備の平面図である。It is a top view of the concrete supply equipment of an Example. 実施例のコンクリートホッパーの説明図である。It is explanatory drawing of the concrete hopper of an Example. 実施例のコンクリートバケットの説明図である。It is explanatory drawing of the concrete bucket of an Example. 実施例のコンクリートの打設を示す一部断面説明図である。It is a partial cross section explanatory view showing placement of concrete of an example. 実施例のスカフォードにコンクリートホッパーを配置した状態を示す平面図である。It is a top view which shows the state which has arrange | positioned the concrete hopper to the scaffold of an Example.

符号の説明Explanation of symbols

1 スカフォード
1a 通過穴
1b 油圧ジャッキ
1c 支柱
1d 吊シーブ
2 掘削機
3 掘削やぐら
3a ズリシュート
4 吊ワイヤー
5 スカフォード巻上機
6 ズリバケット
7 吊ワイヤー
8 ズリバケット巻上機
9 コンクリートホッパー
9a シュート
9b アーム
9c 切換弁
9d 型枠
9e ホース
10 コンクリートバケット
10a 吊具
11 扉
12 軌道
13 供給コンベヤ
14 運搬台車
15 ミキサー車
16 ズリ置き場
17 コンクリートバケット置き場
18 ズリバケット置き場
C コンクリート
G 地盤
H 作業者
T 立坑
DESCRIPTION OF SYMBOLS 1 Scaffold 1a Passing hole 1b Hydraulic jack 1c Prop 1d Suspension sheave 2 Excavator 3 Excavator 3a Slitch 4 Suspension wire 5 Scaffold hoist 6 Slipper bucket 7 Suspension wire 8 Slipper bucket hoist 9 Concrete hopper 9a Chute 9b Arm Changeover valve 9d Formwork 9e Hose 10 Concrete bucket 10a Lifting tool 11 Door 12 Track 13 Supply conveyor 14 Carriage truck 15 Mixer truck 16 Sliding place 17 Concrete bucket place 18 Slipping bucket place C Concrete G Ground H Worker T Vertical shaft

Claims (4)

掘削機を備えたスカフォードを立坑内に吊下して地盤を掘削し、掘削ズリを坑外に搬出して掘削後の立坑の側壁にコンクリートを打設する立坑掘削設備において、掘削ズリを坑外に搬出するズリバケットとコンクリートを坑外から搬入するコンクリートバケットを立坑内にワイヤーロープで吊下して昇降可能とし、スカフォードにズリバケットが上下に通過できる通過穴を形成し、下部に排出シュートを備えた通過穴を通過できる大きさのコンクリートホッパーを通過穴に脱着自在に取り付け、掘削時はコンクリートホッパーを通過穴から取り外した後ズリバケットをスカフォードの通過穴から通過させて掘削ズリを坑外へ搬出し、コンクリート打設時はスカフォードの通過穴にコンクリートホッパーを取り付けた後コンクリートバケットで搬入したコンクリートをコンクリートホッパーに移送して排出シュートから立坑の側壁にコンクリートを供給して打設できるようにしたことを特徴とする、立坑掘削設備。   In a shaft excavation facility in which a scaffold equipped with an excavator is suspended in the shaft to excavate the ground, the excavation sludge is carried out of the shaft, and concrete is placed on the side wall of the shaft after excavation. Sliding buckets to be transported outside and concrete buckets to carry concrete from the outside of the mine can be lifted by suspending them with wire ropes inside the vertical shaft, and a through hole is formed in the scaffold to allow the slipping bucket to pass up and down, and a discharge chute is provided at the bottom. A concrete hopper of a size that can pass through the provided through hole is detachably attached to the through hole, and during excavation, the concrete hopper is removed from the through hole, and then the sludge bucket is passed through the through hole of the Scaffold to move the excavation sludge to the outside of the tunnel. When unloading and placing concrete, attach a concrete hopper to the passage hole of the scaffold and use a concrete bucket. The incoming concrete, characterized in that to allow pouring by supplying concrete to the side wall of the vertical shaft from the discharge chute and transported to the concrete hopper, vertical shaft drilling equipment. スカフォードが複床式で、各床にズリバケット・コンクリートホッパー及びコンクリートバケットが通過できる通過穴をそれぞれ同じ位置に形成した、請求項1記載の立坑掘削設備。   The shaft excavation equipment according to claim 1, wherein the scaffold is a double floor type, and each floor has a passage hole through which a slip bucket, a concrete hopper and a concrete bucket can pass. コンクリートホッパーの上部に複数のアームを放射状に展開可能に設け、コンクリートホッパーをスカフォードの通過穴に落とし込んで展開させたアームを通過穴の周部に掛止して取り付けるようにした、請求項1又は2記載の立坑掘削設備。   A plurality of arms are provided on the upper part of the concrete hopper so as to be radially deployable, and the concrete hopper is dropped into the passage hole of the scaffold and the developed arm is attached to the periphery of the passage hole. Or the shaft excavation equipment of 2 description. 立坑の坑口に扉を設け、坑口と坑口から離れた位置との間にコンクリートバケットの運搬台車を走行させる軌道を設け、坑口から離れた位置の軌道上にコンクリートをコンクリートバケットに供給する供給コンベヤを配設した、請求項1〜3いずれか記載の立坑掘削設備。   A supply conveyor that supplies a concrete bucket to a concrete bucket on a track at a position away from the wellhead by providing a door at the wellhead and providing a track for transporting the concrete bucket carriage between the wellhead and the position away from the wellhead. The shaft excavation equipment according to any one of claims 1 to 3, which is arranged.
JP2005308226A 2005-10-24 2005-10-24 Shaft excavation equipment Pending JP2007113340A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005308226A JP2007113340A (en) 2005-10-24 2005-10-24 Shaft excavation equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005308226A JP2007113340A (en) 2005-10-24 2005-10-24 Shaft excavation equipment

Publications (1)

Publication Number Publication Date
JP2007113340A true JP2007113340A (en) 2007-05-10

Family

ID=38095785

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005308226A Pending JP2007113340A (en) 2005-10-24 2005-10-24 Shaft excavation equipment

Country Status (1)

Country Link
JP (1) JP2007113340A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014078878A1 (en) * 2012-11-19 2014-05-22 Aveng Africa Ltd Shaft sinking apparatus and method
WO2023025341A1 (en) * 2021-08-27 2023-03-02 Redpath Deilmann Gmbh Shaft excavator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014078878A1 (en) * 2012-11-19 2014-05-22 Aveng Africa Ltd Shaft sinking apparatus and method
WO2023025341A1 (en) * 2021-08-27 2023-03-02 Redpath Deilmann Gmbh Shaft excavator

Similar Documents

Publication Publication Date Title
CN102472101A (en) Forming a shaft for an underground mine
JP2007113340A (en) Shaft excavation equipment
JP2016164347A (en) Earth removing method based on pneumatic caisson method
CN105492724B (en) Truck and crosshead
JP2018091130A (en) Underwater mining device and mining method
JP5749581B2 (en) Shaft excavation soil discharging apparatus and bucket excavation soil discharging method using bucket elevator
JP4562927B2 (en) Load test method for work ships
EP2241677B1 (en) A device for ground compaction
JP2681333B2 (en) Slime processing method and apparatus for cast-in-place pile method
JP6974991B2 (en) Transport system
JP3405537B2 (en) Pneumatic caisson
JP5339991B2 (en) Shaft formation method
JP2012001894A (en) Continuous lifting device
JP5557667B2 (en) Equipment capacity determination method and equipment in pneumatic caisson method
JP4272591B2 (en) Shaft excavator
JP2009002056A (en) Existing pile removing method and apparatus for use therein
JPH10205263A (en) Earth-removing device for excavator
JP2008031803A (en) Hammer grab bucket and its crown apparatus
RU2662500C2 (en) Method of moving component or material to and within level of shaft boring system
JP5339992B2 (en) Shaft and shaft formation method
JP7174681B2 (en) Conveying system and drilling method
CA2040716C (en) Mine shaft sinking
KR101229614B1 (en) The Device of Moving Soil for excavating underground
JP4077281B2 (en) Shaft excavator
CN109072696B (en) Drilling method and wellbore drilling system

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070907

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070911

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080225