JP2007016549A - Conveying equipment of concrete and its conveying method - Google Patents

Conveying equipment of concrete and its conveying method Download PDF

Info

Publication number
JP2007016549A
JP2007016549A JP2005201702A JP2005201702A JP2007016549A JP 2007016549 A JP2007016549 A JP 2007016549A JP 2005201702 A JP2005201702 A JP 2005201702A JP 2005201702 A JP2005201702 A JP 2005201702A JP 2007016549 A JP2007016549 A JP 2007016549A
Authority
JP
Japan
Prior art keywords
concrete
dam
dam body
lift
conveying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005201702A
Other languages
Japanese (ja)
Other versions
JP4387334B2 (en
Inventor
Susumu Otsuga
進 大津賀
Yoshikazu Miyauchi
良和 宮内
Matsuo Tsuruoka
松生 鶴岡
Mutsuo Ueki
睦央 植木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2005201702A priority Critical patent/JP4387334B2/en
Publication of JP2007016549A publication Critical patent/JP2007016549A/en
Application granted granted Critical
Publication of JP4387334B2 publication Critical patent/JP4387334B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To get conveying equipment of a concrete and its conveying method capable of not being required for moving the concrete to transfer from a dump truck to a conveying holder or the like when the concrete conveyed to the river bed section by the dump truck is moved on a dam body, not being required for again moving it also from the conveying holder to the dump truck on the upper section of the dam body and improving workability by simultaneously carrying out the lifting and lowering of a plurality of holders without increasing the number of installations of winch. <P>SOLUTION: In the conveying equipment of the concrete conveying the concrete on the dam body from the river bed side by a conveyer erected by making it approach the dam body 1, a mast 3 reaching the upper part of the dam body 1 is erected on the river bed section 2, concrete conveying lifts 4a and 4b are respectively fixed to a free end and a middle part of a wire rope 9 wound on a sheave 8 provided to the upper part of the mast 3, and a winding device 5 of the wire rope 9 is placed to the river bed section 2. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、コンクリートダムを築造する際に、ダム堤内にコンクリートを搬送するコンクリート搬送設備に関するものである。   The present invention relates to a concrete transport facility for transporting concrete into a dam dyke when building a concrete dam.

ダム堤体の建設では、コンクリート打設層を積み重ねて上方に構築していく工法が採用されているが、ダム堤体上へ順次新たな層を構築するためのコンクリートを搬送する必要がある。   In the construction of a dam dam body, a construction method is used in which concrete casting layers are stacked and constructed upward, but it is necessary to transport concrete to construct a new layer sequentially on the dam dam body.

このコンクリートを搬送する設備としては、従来、例えば、コンクリート混錬設備から搬送されるコンクリートを移し替えることなくダム堤体上のダンプカーに搬送できるコンクリート搬送装置がある(例えば、特許文献1参照)。   As a facility for transporting this concrete, for example, there is a concrete transport device that can transport the concrete transported from a concrete kneading facility to a dump truck on a dam body without transferring the concrete (see, for example, Patent Document 1).

これは、河床部から立設した複数のマストで支持されたダム堤体上面より上部に設けた架台と、該架台にダム堤体上に延出したスタッカクレーンとを設け、河床側に設けたウインチによって昇降する下部吊具を該架台に設けたプーリを介して設けるとともに該スタッカクレーンに上部吊具を設け、コンクリートを積載したバケットを下部吊具で吊り上げて上部吊具によってダム堤体上に搬送するものである。   This is provided on the riverbed side, with a platform provided above the upper surface of the dam dam body supported by a plurality of masts erected from the riverbed, and a stacker crane extending on the dam dam body. A lower suspension that is raised and lowered by a winch is provided via a pulley provided on the gantry, and an upper suspension is provided on the stacker crane. It is to be transported.

また、バケットを吊り下げる下部吊具を複数個設置し、一方の下部吊具はコンクリートを積載したバケットを、他方の下部吊具は排出後の空のバケットを搬送するようにしている。
特開2000−160538号公報
In addition, a plurality of lower suspenders for suspending the bucket are installed, and one lower suspender conveys a bucket loaded with concrete, and the other lower suspender conveys an empty bucket after discharge.
JP 2000-160538 A

前記従来例は、ホッパーなどを使用してコンクリートを昇降用のバケットへダンプカーから移し替える必要はないが、搬送車に搭載されてきたコンクリートを詰めたバケットを下部吊具でダム堤体上に吊り上げ、さらに上部吊具によってダム堤体上に待機するダンプカーに移送する必要があり、手間を要して施工性がよくない。   In the conventional example, it is not necessary to transfer the concrete from the dump truck to the lifting bucket using a hopper or the like, but the bucket filled with concrete that has been mounted on the transport vehicle is lifted on the dam body by the lower suspension Furthermore, it is necessary to transfer to a dump truck waiting on the dam dam body by an upper suspension tool, which requires labor and is not workable.

また、下部吊具を複数個設置して複数の下部吊具を同時に昇降させるようにしているが、これは、空のバケットを下ろす側のウインチを簡素なものにするためであり、下部吊具の設置数と同数のウインチを設置する必要があり、設備規模が大きくなる。   In addition, a plurality of lower suspenders are installed so that the plurality of lower suspenders are moved up and down simultaneously. This is to simplify the winch on the side where the empty bucket is lowered. It is necessary to install the same number of winches as the number of installed, which increases the scale of the equipment.

本発明の目的は前記従来例の不都合を解消し、ダンプトラックで河床部に搬送してきたコンクリートを堤体上に移送するに際し、移送用の架台などにコンクリートをダンプトラックから移し替える必要がなく、また、移送用の架台からも堤体上部においてダンプトラックに再度移し替える必要がなく、さらに、ウインチの設置数を増加させずに複数の架台の昇降を同時に行えて施工性の向上を図ることができるコンクリートの搬送設備および搬送方法を提供することにある。   The purpose of the present invention is to eliminate the inconvenience of the conventional example, and when transferring the concrete transported to the river bed by the dump truck onto the dam body, it is not necessary to transfer the concrete from the dump truck to a transfer stand, Moreover, it is not necessary to transfer again from the transfer platform to the dump truck in the upper part of the dam body, and it is possible to raise and lower a plurality of platforms at the same time without increasing the number of winches installed, thereby improving workability. An object of the present invention is to provide a concrete transport facility and a transport method that can be used.

本発明は前記目的を達成するため、設備として、第1に、ダム堤体に近接させて立設した搬送装置によって河床側からダム堤体上へコンクリートを搬送するコンクリートの搬送設備において、ダム堤体の上に達するマストを河床部に立設し、該マストの上部に設けたシーブに巻回したワイヤーロープの自由端と途中とにそれぞれコンクリート搬送用のリフトを固定し、河床部にワイヤーロープの巻上装置を配設したことを要旨とするものである。   In order to achieve the above object, the present invention provides, as a facility, a concrete transport facility for transporting concrete from a river bed side onto a dam dam body by a transport device erected in the vicinity of the dam dam body. A mast that reaches the top of the body is erected on the riverbed, and concrete lifts are fixed to the free end and midway of the wire rope wound around the sheave provided at the top of the mast. The gist is that a hoisting device is provided.

第2に、リフトは、コンクリート搬送用の車両を搭載することを要旨とするものである。   Secondly, the gist of the lift is to mount a concrete conveying vehicle.

搬送方法として、第3に、ダム堤体に近接させて立設した搬送装置によって河床側からダム堤体上へコンクリートを搬送するコンクリートの搬送設備において、ダム堤体の上に達するマストを河床部に立設し、該マストの上部に設けたシーブに巻回したワイヤーロープの自由端と途中とにそれぞれコンクリート搬送用のリフトを固定し、河床部にワイヤーロープの巻上装置を配設し、該巻上装置でワイヤーロープを巻き取りまたは繰り出して、一方リフトが上昇または下降すると同時に、他方のリフトが下降または上昇するようにしたことを要旨とするものである。   Thirdly, in the concrete transport facility that transports concrete from the riverbed side onto the dam dam body by a transport device that stands up close to the dam dam body, the mast reaching the dam dam body is removed from the riverbed. The lift for concrete conveyance is fixed to the free end and the middle of the wire rope wound around the sheave provided at the top of the mast, respectively, and the wire rope hoisting device is disposed on the river bed, The gist of the invention is that the wire rope is wound or unwound by the hoisting device so that one lift is raised or lowered while the other lift is lowered or raised.

請求項1、請求項3記載の本発明によれば、巻上装置によってワイヤーロープを巻き取りまたは繰り出すことにより、ワイヤーロープの自由端に固定されている一方のリフトは上昇または下降し、途中に固定されている他方のリフトは同時に下降または上昇する。よって、一台の巻上装置で複数のリフトを同時に昇降でき、設備が大掛かりになることなく、施工性を向上できるとともに、節電にもなる。   According to the first and third aspects of the present invention, one of the lifts fixed to the free end of the wire rope is raised or lowered by winding or unwinding the wire rope by the hoisting device. The other lift that is fixed is lowered or raised simultaneously. Therefore, a plurality of lifts can be lifted and lowered at the same time with a single hoisting device, and the workability can be improved and the power can be saved without increasing the equipment.

請求項2記載の本発明によれば、前記作用に加えて、リフトは、コンクリート搬送用の車両を搭載するようにしたから、コンクリートを積載した車両をそのままリフトに搭載し、リフトを上昇させた後、車両をそのまま堤体上部に移動することで、コンクリートの移し替えがなくなり、施工性が向上する。   According to the second aspect of the present invention, in addition to the above action, the lift is mounted with a concrete transporting vehicle, so the vehicle loaded with concrete is mounted on the lift as it is and the lift is raised. Later, by moving the vehicle as it is to the upper part of the dam body, there is no transfer of concrete, and workability is improved.

以上述べたように本発明のコンクリート搬送設備およぴ搬送方法は、ダンプトラックで河床部に搬送してきたコンクリートをダム堤体上に移送するに際し、移送用の架台などにコンクリートをダンプトラックから移し替える必要がなく、また、架台からも堤体上部においてダンプトラックに再度移し替える必要がなく、さらに、ウインチの設置数を増加させずに複数の架台の昇降を同時に行えて施工性の向上を図ることができるものである。   As described above, the concrete transfer equipment and transfer method of the present invention transfers concrete from the dump truck to a transfer stand or the like when transferring the concrete transferred to the river bed by the dump truck onto the dam dam body. There is no need to replace it, and there is no need to transfer it again to the dump truck at the upper part of the dam body. In addition, it is possible to raise and lower multiple platforms simultaneously without increasing the number of winches installed, thereby improving workability. It is something that can be done.

以下、図面について本発明の実施の形態を詳細に説明する。図1は、本発明のコンクリートの搬送設備の実施形態を示す正面図、図2は、同上側面図で、本発明のコンクリート搬送設備は、ダム堤体1の近傍において河床部2から鉛直に立設されたマスト3、このマスト3を昇降するリフト4a、4b、およびリフト4a、4bを昇降させる巻上装置5とで構成される。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a front view showing an embodiment of a concrete transport facility of the present invention, FIG. 2 is a side view of the same, and the concrete transport facility of the present invention stands vertically from a riverbed 2 in the vicinity of a dam dam body 1. The mast 3 is provided, lifts 4a and 4b for raising and lowering the mast 3, and a hoisting device 5 for raising and lowering the lifts 4a and 4b.

マスト3は、上端がダム堤体1の頂部に達するものとしてダム堤体1の築造にしたがい順次上方に継ぎ足すことのできる構成となっている。かかるマスト3の左右両側にガイドレール6を鉛直方向に設け、それぞれのガイドレール6にこれにそって昇降移動するリフト4a、4bを取りつける。リフト4a、4bは、コンクリート搬送用の車両12a、12bであるダンプトラックを搭載するものとして、その前後部は車両転落防止のために上方に回動する転落防止板10に形成した。   The mast 3 is configured such that the upper end reaches the top of the dam dam body 1 and can be added upward sequentially as the dam dam body 1 is constructed. Guide rails 6 are provided in the vertical direction on both the left and right sides of the mast 3, and lifts 4 a and 4 b that move up and down along the guide rails 6 are attached to the guide rails 6. The lifts 4a and 4b are mounted with dump trucks which are vehicles 12a and 12b for transporting concrete, and the front and rear portions thereof are formed on a fall prevention plate 10 that rotates upward to prevent the vehicle from falling.

図中7はリフト4a、4bを支持しガイドレール6にそって移動するフレーム、11はマスト3の中間をダム堤体1の側壁で支持するための中間支持部材であるフレームを示す。   In the figure, reference numeral 7 denotes a frame that supports the lifts 4 a and 4 b and moves along the guide rail 6, and 11 denotes a frame that is an intermediate support member for supporting the middle of the mast 3 by the side wall of the dam dam body 1.

リフト4の昇降装置として、マスト3の基部に位置させて巻上装置5であるウインチを設置するとともに、マスト3の頂部に複数のシーブ8を配設し、ウインチに巻回したワイヤーロープ9の自由端を一方のリフト4aに固定し、ワイヤーロープ9の途中を他方のリフト4bに固定する。これにより、2基のリフト4a、4bはワイヤーロープ9の巻き取り、繰り出しにより同時にシーソーのようにして一方が上昇または下降、他方が下降または上昇するように構成される。   As a lifting device of the lift 4, a winch that is a hoisting device 5 is installed at the base of the mast 3, and a plurality of sheaves 8 are arranged on the top of the mast 3, and the wire rope 9 wound around the winch The free end is fixed to one lift 4a, and the middle of the wire rope 9 is fixed to the other lift 4b. Accordingly, the two lifts 4a and 4b are configured such that one of the lifts 4a and 4b is simultaneously lifted or lowered and the other is lowered or lifted up like a seesaw by winding and unwinding the wire rope 9.

次にコンクリートの運搬方法について説明する。築造中のコンクリートダムの堤体1の頂部にコンクリートを搬送するには、図1、図2に示すように一方リフト4bを下方の河床部2に、他方のリフト4aを上方のダム堤体1の頂部に位置させる。この場合、一方のリフト4bを河床部2に位置させれば、他方のリフト4aは自動的にダム堤体1の頂部に位置する。   Next, a concrete transport method will be described. In order to convey concrete to the top of the dam body 1 of the concrete dam under construction, as shown in FIGS. 1 and 2, one lift 4b is placed on the lower riverbed 2 and the other lift 4a is placed on the upper dam dam body 1. Located on top of In this case, if one lift 4 b is positioned on the river bed 2, the other lift 4 a is automatically positioned on the top of the dam body 1.

そして、河床部2では、コンクリートを積載した車両12bであるダンプトラックを下方のリフト4bの上に搭載する。同時に、ダム堤体1の頂部では他方のリフト4aに、コンクリートの搬送が終了した後の荷台が空の車両12aを搭載する。この状態で、巻上装置5を駆動してワイヤーロープ9を巻き取れば、下方のリフト4bが上昇し、同時に上方のリフト4bが下降する。   And in the riverbed part 2, the dump truck which is the vehicle 12b which loaded concrete is mounted on the downward lift 4b. At the same time, on the top of the dam body 1, the other lift 4 a is loaded with the vehicle 12 a that is empty in the loading platform after the concrete transport is completed. In this state, when the hoisting device 5 is driven and the wire rope 9 is wound up, the lower lift 4b is raised, and at the same time, the upper lift 4b is lowered.

よって、下方のリフト4bがダム堤体1の頂部に到達すれば、コンクリートを積載した車両12bをリフト4bから降ろし、そのままコンクリートの打設現場へと移動させる。同時に、上方から下降した他方のリフト4aは、下方の河床部2に到達したならば、空の車両12aをそのままリフト4aから降ろして、コンクリート積載のために移動する。   Therefore, when the lower lift 4b reaches the top of the dam dam body 1, the vehicle 12b loaded with concrete is lowered from the lift 4b and moved to the concrete placement site as it is. At the same time, when the other lift 4a descending from above reaches the lower riverbed 2, the empty vehicle 12a is lowered from the lift 4a and moved for concrete loading.

このようにしてコンクリートを積載した車両12bのダム堤体1頂部への移動と、空の車両12aのダム堤体1から河床部2への移動とを1台の巻上装置5を使用して同時に行う。   The movement of the vehicle 12b loaded with concrete in this way to the top of the dam dam body 1 and the movement of the empty vehicle 12a from the dam dam body 1 to the river bed 2 are performed using one hoisting device 5. Do it at the same time.

また、リフト4bへのコンクリートの積載は、コンクリートを積載してきた車両12bをそのまま搭載することで行うことができ、リフト4bからダム堤体1のコンクリート打設現場へのコンクリートの移送も、リフト4bに搭載してきた車両12bをそのままリフト4bから降ろして移動することで行うことができる。   The concrete can be loaded on the lift 4b by mounting the vehicle 12b loaded with the concrete as it is, and the concrete can be transferred from the lift 4b to the concrete placement site of the dam dam body 1 by the lift 4b. The vehicle 12b mounted on the vehicle can be moved down from the lift 4b as it is.

本発明のコンクリートの運搬設備および搬送方法の実施形態を示す正面図である。It is a front view which shows embodiment of the conveyance equipment and conveyance method of the concrete of this invention. 本発明のコンクリートの運搬設備および搬送方法の実施形態を示す側面図である。It is a side view which shows embodiment of the conveyance equipment and conveyance method of the concrete of this invention. 本発明のコンクリートの運搬設備および搬送方法の実施形態を示す図2のA−A線断面図である。It is the sectional view on the AA line of FIG. 2 which shows embodiment of the concrete conveyance facility and conveyance method of this invention.

符号の説明Explanation of symbols

1…ダム堤体 2…河床部
3…マスト 4a、4b…リフト
5…巻上装置 6…ガイドレール
7…フレーム 8…シーブ
9…ワイヤーロープ 10…転落防止板
11…フレーム 12a、12b…車両
DESCRIPTION OF SYMBOLS 1 ... Dam bank body 2 ... River bed part 3 ... Mast 4a, 4b ... Lift 5 ... Hoisting device 6 ... Guide rail 7 ... Frame 8 ... Sheave 9 ... Wire rope 10 ... Fall prevention plate 11 ... Frame 12a, 12b ... Vehicle

Claims (3)

ダム堤体に近接させて立設した搬送装置によって河床側からダム堤体上へコンクリートを搬送するコンクリートの搬送設備において、ダム堤体の上に達するマストを河床部に立設し、該マストの上部に設けたシーブに巻回したワイヤーロープの自由端と途中とにそれぞれコンクリート搬送用のリフトを固定し、河床部にワイヤーロープの巻上装置を配設したことを特徴とするコンクリートの搬送設備。   In a concrete transport facility that transports concrete from the riverbed side onto the dam dam body by means of a transport device erected close to the dam dam body, a mast that reaches the top of the dam dam body is erected on the river bed, and the mast Concrete transport equipment characterized in that a concrete rope lift is fixed to the free end and midway of the wire rope wound around the sheave provided on the upper part, and a wire rope hoisting device is arranged on the river bed. . リフトは、コンクリート搬送用の車両を搭載する請求項1記載のコンクリートの搬送設備。   The concrete transport facility according to claim 1, wherein the lift is equipped with a concrete transport vehicle. ダム堤体に近接させて立設した搬送装置によって河床側からダム堤体上へコンクリートを搬送するコンクリートの搬送設備において、ダム堤体の上に達するマストを河床部に立設し、該マストの上部に設けたシーブに巻回したワイヤーロープの自由端と途中とにそれぞれコンクリート搬送用のリフトを固定し、河床部にワイヤーロープの巻上装置を配設し、該巻上装置でワイヤーロープを巻き取りまたは繰り出して、一方リフトが上昇または下降すると同時に、他方のリフトが下降または上昇するようにしたことを特徴とするコンクリート搬送方法。   In a concrete transport facility that transports concrete from the riverbed side onto the dam dam body by means of a transport device erected close to the dam dam body, a mast that reaches the top of the dam dam body is erected on the river bed, and the mast The concrete transport lift is fixed to the free end and halfway of the wire rope wound around the sheave provided on the upper part, and the wire rope hoisting device is arranged on the river bed, and the wire rope is attached to the hoisting device. A concrete conveying method characterized by winding or unwinding, wherein one lift is raised or lowered and at the same time the other lift is lowered or raised.
JP2005201702A 2005-07-11 2005-07-11 Concrete conveying equipment and conveying method Active JP4387334B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005201702A JP4387334B2 (en) 2005-07-11 2005-07-11 Concrete conveying equipment and conveying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005201702A JP4387334B2 (en) 2005-07-11 2005-07-11 Concrete conveying equipment and conveying method

Publications (2)

Publication Number Publication Date
JP2007016549A true JP2007016549A (en) 2007-01-25
JP4387334B2 JP4387334B2 (en) 2009-12-16

Family

ID=37753942

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005201702A Active JP4387334B2 (en) 2005-07-11 2005-07-11 Concrete conveying equipment and conveying method

Country Status (1)

Country Link
JP (1) JP4387334B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014201922A (en) * 2013-04-03 2014-10-27 大成建設株式会社 Concrete conveying equipment

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101566130B1 (en) * 2014-12-18 2015-11-19 (주)대우건설 Method for constructing dam dock and mono rail using incline equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014201922A (en) * 2013-04-03 2014-10-27 大成建設株式会社 Concrete conveying equipment

Also Published As

Publication number Publication date
JP4387334B2 (en) 2009-12-16

Similar Documents

Publication Publication Date Title
JP6537720B2 (en) Elevator hoist installation method
JP5818533B2 (en) Jig for lifting a structure with a crane
JPH03264482A (en) Method for installing elevator
JP4387334B2 (en) Concrete conveying equipment and conveying method
KR101160273B1 (en) Straddle carrier for bridge construction
JP2008248664A (en) Hoisting method of curtain wall
CN105800417A (en) Method for carrying elevator counterweight
JP4509875B2 (en) Material transfer system for building exterior wall construction
JP3994458B2 (en) Operation method of vertical and horizontal transfer device
JP3796434B2 (en) Lifting device in multistory parking lot
JPS63300100A (en) Heavy article conveyor
CN111689390B (en) Method for transferring rail crane
JP2000344468A (en) Material handling equipment and method for conveying dam concrete using the same
JP2549726Y2 (en) Construction lift
JP2008247568A (en) Elevating/lowering body fall preventive device for stacker crane, and stacker crane
JP2000160538A (en) Concrete carrying device
JP2003292263A (en) Elevator apparatus lifting device and method
JPH1037238A (en) Excavated earth and sand crane and earth and sand transfer method using the crane
KR20040027804A (en) Container crane possible rotating of level and vertical
JP2000336632A (en) Concrete conveying device and construction method therefor
JP2775206B2 (en) Material transport equipment for building construction
JPH11255468A (en) Vertical hoisting conveyer device
JPH11157777A (en) Container crane
JP2023128271A (en) construction elevator
JP6116972B2 (en) Concrete conveyor

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20080402

Free format text: JAPANESE INTERMEDIATE CODE: A621

A977 Report on retrieval

Effective date: 20090827

Free format text: JAPANESE INTERMEDIATE CODE: A971007

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20090929

Free format text: JAPANESE INTERMEDIATE CODE: A01

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090930

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121009

Year of fee payment: 3