JP2007009640A - Shore strut for supporting retaining wall and its construction method - Google Patents
Shore strut for supporting retaining wall and its construction method Download PDFInfo
- Publication number
- JP2007009640A JP2007009640A JP2005195119A JP2005195119A JP2007009640A JP 2007009640 A JP2007009640 A JP 2007009640A JP 2005195119 A JP2005195119 A JP 2005195119A JP 2005195119 A JP2005195119 A JP 2005195119A JP 2007009640 A JP2007009640 A JP 2007009640A
- Authority
- JP
- Japan
- Prior art keywords
- retaining wall
- concrete
- retaining
- wall supporting
- retaining walls
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
本発明は、例えば、立体交差道路の下側道路構築の際に用いる土留め壁を支持する土留め壁支持用切梁及びその架設方法に関する。 TECHNICAL FIELD The present invention relates to a retaining wall supporting beam for supporting a retaining wall used when constructing a lower road of a three-dimensional crossing road and a method for laying the retaining wall.
従来、掘下げ型立体交差道路の構築に際し、地盤中の下側道路予定構築領域(掘削領域)の両側部に互いに側縁を突き合わせた連続配置に多数のPC矢板或いはH型PC杭等のコンクリート杭を打設して土留め壁を設置し、この土留め壁により隣接する非掘削部分の土圧を支持させたうえで両土留め壁間の土砂を掘削することにより立体交差道路の下側道路を構築する方法が知られている。 Conventionally, when constructing a dugdown type three-dimensional crossing road, concrete piles such as a large number of PC sheet piles or H-shaped PC piles in a continuous arrangement with the side edges abutting each other on both sides of the planned lower road construction area (excavation area) in the ground The lower road of the three-dimensional crossing road is excavated with the earth retaining wall between the two retaining walls after supporting the earth pressure of the adjacent non-excavated part with this retaining wall. The method of building is known.
このような工法において、例えば、掘削深さが深く隣接する未掘削部からの土圧が大きい為、自立式土留め壁の耐力のみでは十分でない場合や土留め壁の縦方向長さを短くしたい場合には、土留め壁間の掘削予定地盤を所定深さ掘削した後、両土留め壁間に切梁(ストラット)を架け渡すことによって、各土留め壁を互いに切梁を介して他方の土留め壁に支持させ、隣接する未掘削部の土圧を支持させるようになっている。 In such a construction method, for example, since the earth pressure from the unexcavated part adjacent to the deep excavation is large, the proof strength of the self-supporting earth retaining wall is not enough or the longitudinal length of the earth retaining wall is to be shortened. In this case, after excavating a predetermined depth of the ground between the retaining walls to a predetermined depth, the retaining walls are connected to each other through the beams by piercing the struts between the retaining walls. It is supported by the earth retaining wall, and the earth pressure of the adjacent unexcavated part is supported.
しかしながら、上述の如き従来の技術では、掘削領域の幅や奥行きが大きい場合、大量の切梁(ストラット)が必要となる為、工費が嵩むという問題がある。また、掘削領域が大きい場合には、両土留め壁にかかる曲げモーメントによる切梁(ストラット)に作用する圧縮力も増大する為、それに対応して切梁も大型化するので重量が嵩み、運搬や設置作業が容易でないという問題があった。 However, the conventional techniques as described above have a problem in that, when the excavation area has a large width and depth, a large amount of beams (struts) are required, which increases the construction cost. In addition, when the excavation area is large, the compressive force acting on the beam (strut) due to the bending moment applied to the both retaining walls also increases, so the beam becomes larger correspondingly, increasing the weight and transporting. There was a problem that the installation work was not easy.
そこで本発明は、上述の如き従来の問題を鑑み、作業性に優れ、安価に製作可能な土留め壁支持用切梁及びその架設方法の提供を目的とする。 SUMMARY OF THE INVENTION In view of the above-described conventional problems, an object of the present invention is to provide a retaining wall supporting beam that is excellent in workability and that can be manufactured at low cost, and a method for laying the same.
上述の如き従来の問題を解決し、所期の目的を達成するための請求項1に記載の発明は、互いに間隔をおいて配置された一対の土留め壁間に架け渡され、両土留め壁を互いに支持させるための土留め壁支持用切梁において、両側部に配置された鋼製の側部梁材と、該両側部梁材間に挟まれたコンクリート製のコンクリート梁材とを備え、前記両側部梁材とコンクリート梁材とが一体化された土留壁支持用切梁であることを特徴とする。 In order to solve the above-mentioned conventional problems and achieve the intended object, the invention according to claim 1 is provided between a pair of earth retaining walls arranged at a distance from each other. A retaining wall supporting beam for supporting walls with each other, comprising steel side beam members arranged on both sides, and concrete concrete beam members sandwiched between the both side beam members The retaining wall supporting cut beam in which the both-side beam material and the concrete beam material are integrated.
請求項2に記載の発明は、請求項1の構成に加え、両側部梁材間部の下面を閉鎖する型枠部材を有することを特徴とする。 The invention according to claim 2 is characterized in that, in addition to the structure of claim 1, it has a formwork member that closes the lower surface of the part between both side beam members.
請求項3に記載の発明は、請求項1又は2の構成に加え、側部梁材は、上縁及び/又は下縁より外向きに突出したフランジ部を一体に有することを特徴とする。 According to a third aspect of the present invention, in addition to the configuration of the first or second aspect, the side beam member integrally has a flange portion protruding outward from the upper edge and / or the lower edge.
請求項4に記載の発明は、請求項3の構成に加え、前記フランジ部は、前記土留め壁の上縁より上向きに突出したアンカー部材が挿通されるアンカー挿通孔を有することを特徴とする。 According to a fourth aspect of the present invention, in addition to the configuration of the third aspect, the flange portion has an anchor insertion hole through which an anchor member protruding upward from the upper edge of the retaining wall is inserted. .
請求項5に記載の発明は、請求項1〜3又は4の構成に加え、前記コンクリート梁材を貫通し、両端が前記両側部梁材の外側面側に突出したボルトを備え、該外側面側に突出したボルト端部にナットを締め付けることにより前記コンクリート梁材と両側部梁材とが一体化されたことを特徴とする。 The invention according to claim 5 includes, in addition to the configuration of claims 1 to 3 or 4, a bolt that penetrates the concrete beam material and has both ends projecting to the outer surface side of the both side beam materials, The concrete beam member and the both side beam members are integrated by tightening a nut to a bolt end protruding to the side.
請求項6に記載の発明は、請求項1〜4又は5の構成に加え、側部梁材は、縦向きのウエブの上下両端部片側にそれぞれ横向きのフランジが一体に突設された断面コ字型の溝型鋼により構成されたことを特徴とする。 According to the sixth aspect of the present invention, in addition to the configuration of the first to fourth or fifth aspects, the side beam member is a cross-sectional core member in which a lateral flange is integrally projected on one side of both upper and lower ends of a longitudinal web. It is characterized by the fact that it is made of a U-shaped channel steel.
請求項7に記載の発明は、互いに間隔をおいて配置された一対の土留め壁間に架け渡され、前記両土留め壁を互いに支持させるための土留め壁支持用切梁を前記土留め壁間に架設するに際し、互いに間隔をおいて配置された一対の側部梁材を前記両土留め壁間に架け渡した後、前記両側部梁材間にコンクリートを打設してコンクリート梁材を形成し、前記両側部梁材とコンクリート梁材とを一体化させて前記土留め壁支持用切梁とする土留め壁支持用切梁の架設方法であることを特徴とする。 According to a seventh aspect of the present invention, there is provided a retaining wall supporting cut beam that is spanned between a pair of retaining walls that are spaced apart from each other and that supports the both retaining walls. When laying between the walls, a pair of side beam members spaced apart from each other are bridged between the two retaining walls, and then concrete is placed between the both side beam members to provide the concrete beam material. The retaining wall supporting beam is constructed by integrating the both side beam members and the concrete beam material to form the retaining wall supporting beam.
請求項8に記載の発明は、請求項7の構成に加え、側部梁材を前記両土留め壁間距離に合わせて切断した後、前記両土留め壁間に架け渡すことを特徴とする。 According to an eighth aspect of the invention, in addition to the configuration of the seventh aspect, the side beam member is cut according to the distance between the both retaining walls, and then spanned between the both retaining walls. .
本発明に係る土留め壁支持用切梁は、互いに間隔をおいて配置された一対の土留め壁間に架け渡され、各土留め壁を互いに支持させる為の土留め壁支持用切梁において、両側部に配置された鋼製の側部梁材と、該両側部梁材間に挟まれたコンクリート製のコンクリート梁材とを備え、前記両側部梁材とコンクリート梁材とが一体化されたことによって、高い座屈耐力が得られるとともに、構造が簡便であるので安価に製造することができ、工費を削減することができる。 The retaining wall supporting beam according to the present invention is a retaining wall supporting beam for supporting each retaining wall, which is spanned between a pair of retaining walls arranged at a distance from each other. A steel side beam member disposed on both sides and a concrete concrete beam member sandwiched between the both side beam members, and the both side beam member and the concrete beam member are integrated. As a result, a high buckling strength can be obtained, and since the structure is simple, it can be manufactured at low cost and the construction cost can be reduced.
両側部梁材間部の下面を閉鎖する型枠部材を有することによって、側部梁材間に場所打ちによりコンクリートを打設することができるので、両土留め壁間に両側部梁材を架け渡した後に、コンクリート梁材を形成することが可能となり、両土留め壁間に架設するまで、鋼製の側部梁材を独立して扱えるので運搬や設置作業を容易に行うことができる。 By having a formwork member that closes the lower surface of the space between both side beam members, it is possible to place concrete between the side beam members by spot casting. After passing, the concrete beam material can be formed, and the steel side beam material can be handled independently until it is installed between the two retaining walls, so that it can be easily transported and installed.
側部梁材は、上縁及び/又は下縁より外向きに突出したフランジ部を一体に有することによって、切梁を土留め壁上縁部又は腹起こし等に好適に固定することができる。 Since the side beam member integrally has a flange portion that protrudes outward from the upper edge and / or the lower edge, the cut beam can be suitably fixed to the upper edge portion of the earth retaining wall or the flank.
前記フランジ部は、前記土留め壁の上縁より上向きに突出したアンカー部材が挿通されるアンカー挿通孔を有することによって、切梁の端部を好適に土留め壁に固定することができる。 The flange portion has an anchor insertion hole through which an anchor member protruding upward from the upper edge of the retaining wall is inserted, so that the end portion of the beam can be suitably fixed to the retaining wall.
前記コンクリート梁材を貫通し、両端が前記両側部梁材の外側面側に突出したボルトを備え、該外側面側に突出したボルト端部にナットを締め付けることにより前記コンクリート梁材と両側部梁材とが一体化されたことによって、使用後は、ナットを外すことにより容易に側部梁材とコンクリート梁材とを分離することができ、容易に搬送することができるとともに、側部梁材を再利用することができる。 The concrete beam material and the both side beams are provided by including bolts penetrating the concrete beam material, both ends projecting to the outer surface side of the both side beam materials, and tightening nuts to the bolt end portions projecting to the outer surface side. After the use, the side beam material and the concrete beam material can be easily separated after use, and can be easily transported after use. Can be reused.
側部梁材は、縦向きのウエブの上下両端部片側にそれぞれ横向きのフランジが一体に突設された断面コ字型の溝型鋼により構成されたことによって、両土留め壁間の距離に合わせて容易に切断又はアンカー挿通孔を形成することができ、好適に長さ調整を行うことができる。 The side beams are made of U-shaped channel steel with a horizontal flange projecting integrally on one side of the top and bottom ends of the vertical web, to match the distance between the two retaining walls. Thus, cutting or anchor insertion holes can be easily formed, and the length can be adjusted suitably.
本発明に係る土留め壁支持用切梁の架設方法は、互いに間隔をおいて配置された一対の土留め壁間に架け渡され、前記両土留め壁を互いに支持させるための土留め壁支持用切梁を前記土留め壁間に架設するに際し、互いに間隔をおいて配置された一対の側部梁材を前記両土留め壁間に架け渡した後、前記両側部梁材間にコンクリートを打設してコンクリート梁材を形成し、前記両側部梁材とコンクリート梁材とを一体化させて前記土留め壁支持用切梁とすることによって、重量の嵩むコンクリート梁材が両土留め壁間に側部梁材を架け渡した後に成形されるので、運搬や設置作業を容易に行うことができる。 According to the present invention, there is provided a retaining wall support for spanning between a pair of retaining walls arranged at a distance from each other and for supporting the both retaining walls. When laying a cutting beam between the retaining walls, a pair of side beam members spaced apart from each other are bridged between the both retaining walls, and then concrete is placed between the both side beam members. A concrete beam material is formed by casting, and the both side beam materials and the concrete beam material are integrated to form the retaining wall supporting cut beam. Since it is formed after the side beam members are bridged between them, transportation and installation work can be easily performed.
側部梁材を前記両土留め壁間距離に合わせて切断した後、前記両土留め壁間に架け渡すことによって、切梁の長さ調整を現場にて容易に行うことができる。 After the side beam material is cut according to the distance between the both retaining walls, the length of the beam can be easily adjusted at the site by bridging between the both retaining walls.
次に、本発明に係る土留め壁支持用切梁の実施形態について図に基づいて説明する。 Next, an embodiment of a retaining wall supporting beam according to the present invention will be described with reference to the drawings.
土留め壁支持用切梁1は、図1、図2に示すように、両側部に配置された鋼製の側部梁材2と、両側部梁材2,2間に挟まれて配置されたコンクリート製のコンクリート梁材3とを備え、両側部梁材2,2とコンクリート梁材3とが一体化された鋼・コンクリート複合梁であり、間隔をおいて配置された土留め壁間に架け渡され、両土留め壁を互いに支持させるようになっている。 As shown in FIG. 1 and FIG. 2, the retaining wall supporting cut beam 1 is sandwiched between the steel side beam members 2 arranged on both sides and the both side beam materials 2 and 2. A steel-concrete composite beam comprising two concrete beam members 2 and 2 and a concrete beam member 3 integrated between the retaining walls arranged at intervals. It is built over and supports both retaining walls.
また、この切梁1には、両側部梁材2,2の下縁及び両端に着脱可能に支持され、両側部梁材2,2間部の下面及び両端面を閉鎖する型枠部材4及び型枠部材5,5が備えられている。 Further, the cut beam 1 is removably supported on the lower edge and both ends of the side beam members 2 and 2, and is formed with a mold member 4 for closing the lower surface and both end surfaces of the portion between the side beam members 2 and 2. Formwork members 5 and 5 are provided.
側部梁材2は、縦向きのウエブ6の上下両端部片側にそれぞれ横向きの上下のフランジ7,8が一体に突設された断面コ字型の溝型鋼をもって構成され、両側部梁材2,2は、互いにフランジ7,8を外側(他方の側部梁材2とは反対側)に向けて互いに並べて配置されている。 The side beam member 2 is composed of a U-shaped cross-section steel sheet in which upper and lower flanges 7 and 8 are integrally projected on one side of the upper and lower ends of the vertical web 6. , 2 are arranged side by side with the flanges 7 and 8 facing each other outward (on the side opposite to the other side beam member 2).
ウエブ6には、所定の間隔をおいてボルト挿通孔9,9…が形成され、このボルト挿通孔9を通して両ウエブ6,6間にボルト10が挿通され、両ウエブ6,6の外側に突出したボルト端部にそれぞれナット11,11が螺合されている。 Bolt insertion holes 9, 9... Are formed in the web 6 at a predetermined interval, and bolts 10 are inserted between the webs 6 and 6 through the bolt insertion holes 9 and project outside the webs 6 and 6. Nuts 11 and 11 are screwed into the bolt ends.
また、下部フランジ8には、その長手方向両端部にアンカー挿通孔12が形成され、このアンカー挿通孔12を通して土留め壁の上縁部又は腹起こし等に上向きに突設されたアンカーボルトが下部フランジ8に貫通され、そのアンカーボルトにナットを締め付けることにより切梁1の端部を土留め壁に固定できるようになっている。 The lower flange 8 is formed with anchor insertion holes 12 at both ends in the longitudinal direction, and anchor bolts projecting upward from the anchor insertion holes 12 to the upper edge of the earth retaining wall or the flank are provided at the lower part. The end of the beam 1 can be fixed to the retaining wall by being penetrated by the flange 8 and tightening a nut to the anchor bolt.
コンクリート梁材3は、図示しない鉄筋が配筋された鉄筋構造を有し、下面及び両端面を型枠部材4,5により閉鎖され、上面のみが開口した両側部梁材2,2間部に場所打ちコンクリートを打設することにより形成されている。 The concrete beam 3 has a reinforcing bar structure in which reinforcing bars (not shown) are arranged, and the lower surface and both end surfaces thereof are closed by the formwork members 4 and 5, and only the upper surface is opened between both side beam members 2 and 2. It is formed by casting cast-in-place concrete.
このように構成された切梁1は、ボルト10,10…がコンクリート梁材3を貫通し、その両端部が両ウエブ6,6の外側面側に突出しており、そのボルトの端部にナット11,11が締め付けられていることによりコンクリート梁材3と両側部梁材2,2とが一体化されている。 In the cut beam 1 constructed in this manner, the bolts 10, 10... Penetrate through the concrete beam material 3, and both end portions thereof protrude to the outer surface side of both webs 6, 6, and nuts are provided at the end portions of the bolts. By tightening 11 and 11, the concrete beam material 3 and the side beam materials 2 and 2 are integrated.
次に、この土留め壁支持用切梁を使用した切梁式土留め工法について説明する。 Next, a cut beam type retaining method using the retaining wall supporting cut beam will be described.
まず、図3に示すように、例えば、掘下げ型立体交差道路の下側道路を構築する箇所の地盤、即ち掘削予定区域20の両側部に土留め壁21,21を設置し、隣接する非掘削部22の土圧を支持させる。 First, as shown in FIG. 3, for example, earth retaining walls 21 and 21 are installed on both sides of the ground where the lower road of the dugdown type three-dimensional intersection road is constructed, that is, the planned excavation area 20, and adjacent non-excavated The earth pressure of the part 22 is supported.
この土留め壁21は、例えば、多数のH型PC杭を、互いに側縁を突き合わせた配置に順次地表面より鉛直下向きに打設し、必要に応じて各H型PC杭間の隙間にコンクリートを充填する等して形成されている。 The retaining wall 21 is formed by, for example, placing a number of H-type PC piles in a vertically downward direction from the ground surface in an arrangement in which the side edges are in contact with each other, and if necessary, concrete in the gaps between the H-type PC piles. It is formed by filling.
次に、両土留め壁21,21間の掘削予定区域20地盤を所定の深さ、即ち予定掘削深さの約半分程度の深さまで掘削する。 Next, the planned excavation area 20 ground between the both retaining walls 21 and 21 is excavated to a predetermined depth, that is, about half the planned excavation depth.
このように所定の深さまで掘削が完了したら、図4に示すように、両土留め壁21,21の上端縁に笠コンクリート23を打設する。このとき、笠コンクリート23の所定の位置、即ち切梁1の設置位置に合わせてアンカーボルト24を上向きに突設する。 When excavation is completed to a predetermined depth in this way, as shown in FIG. 4, the cap concrete 23 is placed on the upper edge of the both retaining walls 21, 21. At this time, the anchor bolt 24 is projected upward in accordance with a predetermined position of the cap concrete 23, that is, the installation position of the cut beam 1.
そして、この両土留め壁21,21間、即ち笠コンクリート23,23間に壁方向に間隔をおいて複数の土留め壁支持用切梁1,1…を架け渡し、各土留め壁21を互いに土留め壁支持用切梁1を介して他方の土留め壁21に支持させる。 Then, a plurality of retaining wall supporting beams 1, 1... Are bridged between the both retaining walls 21, 21, that is, the cap concrete 23, 23 in the wall direction. The other retaining wall 21 is supported through the retaining wall supporting beam 1.
この土留め壁支持用切梁1の架設方法は、まず、側部梁材2,2を現場に搬入し、両土留め壁21,21間の距離に合わせて側部梁材2を切断して長さを調整するとともに、アンカーボルト24,24…の位置に合わせて、下部フランジ8にドリル等によりアンカー挿通孔12を形成する。 The method of laying the retaining wall supporting cut beam 1 is as follows. First, the side beam members 2 and 2 are brought into the field, and the side beam members 2 are cut in accordance with the distance between the both retaining walls 21 and 21. The anchor insertion hole 12 is formed in the lower flange 8 by a drill or the like in accordance with the position of the anchor bolts 24, 24.
このように側部梁材2を溝型鋼のみから構成したことによって、自重が小さく容易に搬送することができるうえ、設置状況に応じて切断や孔開けを容易に行うことができ、作業効率がよい。 As described above, the side beam member 2 is composed only of grooved steel, so that its own weight is small and it can be easily transported, and cutting and drilling can be easily performed according to installation conditions, so that work efficiency is improved. Good.
次に、フランジ7,8を外側(他方の側部梁材2とは反対側)に向けた一対の側部梁材2,2を互いに間隔をおいて配置した後、両側部梁材2,2のボルト挿通孔9,9…にボルト10を通し、両側部梁材2,2間に挿通させ、外側に突出したボルト端部にナット11,11を締め付ける。 Next, after arranging a pair of side beam members 2 and 2 with the flanges 7 and 8 facing outward (opposite side of the other side beam member 2), the two side beam members 2, The bolts 10 are passed through the two bolt insertion holes 9, 9... And inserted between the beam members 2 and 2 on both sides, and the nuts 11 are tightened to the bolt ends protruding outward.
更に、両側部梁材2,2間部の下面及び両端部を型枠部材4,5により閉鎖し、上面のみが開口したコンクリート梁材成型用型枠25を形成する。 Further, the lower surface and both ends of the portion between the side beam members 2 and 2 are closed by the mold members 4 and 5 to form the concrete beam molding mold 25 with only the upper surface opened.
このコンクリート梁材成型用型枠25をクレーン等により吊り上げ、図5に示すように、土留め壁21,21間、即ち笠コンクリート23,23間に架け渡し、笠コンクリート23より上向きに突出したアンカーボルト24をアンカー挿通孔12に通した状態で型枠25の端部を笠コンクリート23上に戴置する。 The concrete beam forming mold 25 is lifted by a crane or the like, and as shown in FIG. 5, it is bridged between the retaining walls 21, 21, that is, between the cap concrete 23, 23, and protrudes upward from the cap concrete 23. The end of the mold 25 is placed on the cap concrete 23 in a state where the bolt 24 is passed through the anchor insertion hole 12.
そして、アンカーボルト24にナット26を締め付けることにより、コンクリート梁材成型用型枠25を両土留め壁21,21間に架け渡した状態に固定する。 Then, by tightening the nut 26 to the anchor bolt 24, the concrete beam forming mold 25 is fixed in a state of being bridged between the both retaining walls 21, 21.
次に、この型枠25内に鉄筋その他の必要なものを配置し、上面開口より型枠25内、即ち両側部梁材2,2間に場所打ちによりコンクリートを充填する。 Next, reinforcing bars and other necessary items are placed in the mold 25, and concrete is filled into the mold 25 from the upper surface opening, that is, between the beam members 2 and 2 on both sides by spot casting.
そして、コンクリートを充分に養生させ、両側部梁材2,2と一体化されたコンクリート梁材3を形成し、両側部梁材2,2とコンクリート梁材3とが一体化された複合桁が形成される。 Then, the concrete is sufficiently cured to form a concrete beam 3 integrated with the beam members 2 and 2 on both sides, and a composite girder in which the beam members 2 and 2 and the concrete beam material 3 are integrated. It is formed.
尚、型枠部材4,5は、コンクリートが固化した後取り外しても良く、また、取り付けたまま切梁1の一部としてもよい。 The formwork members 4 and 5 may be removed after the concrete is solidified, or may be part of the beam 1 while attached.
次に、切梁1を介して土留め壁21が互いに相手側土留め壁21に支持された状態で、掘削予定地盤の残りの部分を予定の深さまで掘削する。 Next, the remaining portion of the planned excavation ground is excavated to a predetermined depth in a state where the retaining wall 21 is supported by the counterpart retaining wall 21 through the beam 1.
掘削予定区域の土砂を全て掘削し終えたら、図6に示すように、その底部に場所打ちによりコンクリートを打設して底版27を形成する。 When all of the earth and sand in the planned excavation area has been excavated, as shown in FIG. 6, concrete is cast on the bottom portion thereof to form a bottom slab 27.
そして、切梁1を両土留め壁21,21上縁部、即ち笠コンクリート23より取り外し、クレーン等により吊り上げて撤去する。 Then, the cut beam 1 is detached from the upper edge portions of the both retaining walls 21 and 21, that is, the shaded concrete 23, and lifted and removed by a crane or the like.
尚、両土留め壁21,21は、コンクリート底版27を形成した事により、切梁1,1…を撤去しても、自立して未掘削部分の土圧に耐え得るようになっている。 The both retaining walls 21 and 21 are formed with the concrete bottom slab 27 so that they can stand up to withstand the earth pressure of the unexcavated portion even if the cut beams 1, 1... Are removed.
また、両土留め壁21,21は、その位置に残して下側道路等の構造物の側壁として使用する。 Moreover, both the earth retaining walls 21 and 21 are used as side walls of a structure such as a lower road while being left in that position.
一方、除去された切梁1は、両側部梁材2,2間に架け渡されたボルト両端のナット11,11を緩め、取り外すことにより、両側部梁材2,2とコンクリート梁材3との結合が解除され、両側部梁材2,2とコンクリート梁材3とに分けることができる。 On the other hand, the cut beam 1 is removed by loosening and removing the nuts 11, 11 at both ends of the bolt spanned between the side beam members 2, 2. Can be separated into the side beam members 2 and 2 and the concrete beam member 3.
よって、施工現場より切梁1を搬送するに際し、自重の軽い側部梁材2をコンクリート梁材3より分けて搬送することができ効率がよい。一方、コンクリート梁材3は、その場にて粉砕し、廃材として搬送することができる。 Therefore, when the cut beam 1 is transported from the construction site, the side beam material 2 having a light weight can be transported separately from the concrete beam material 3, which is efficient. On the other hand, the concrete beam material 3 can be crushed on the spot and conveyed as waste material.
更に、側部梁材2とコンクリート梁材3とを分離することにより、側部梁材2を再利用することができるようになっている。 Further, by separating the side beam material 2 and the concrete beam material 3, the side beam material 2 can be reused.
尚、上述の実施例では、側部梁材2に断面コ字型の溝型鋼を使用した例について説明したが、溝型鋼に替えてH型鋼、I型鋼又は角型鋼管等を使用しても良い。 In the above-described embodiment, an example in which a U-shaped grooved steel is used for the side beam member 2 has been described, but an H-shaped steel, an I-shaped steel, a rectangular steel pipe, or the like may be used instead of the grooved steel. good.
更に、上述の実施例では、側部梁材を両土留め壁間に架け渡した後、側部梁材間にコンクリートを打設してコンクリート梁材を形成した例について説明したが、施工現場において側部梁材とコンクリート梁材とを一体化させた後、両土留め壁間に架設するようにしてもよい。 Furthermore, in the above-described embodiment, the example in which the concrete beam material is formed by placing the side beam material between the both retaining walls and then placing concrete between the side beam materials has been described. Then, after the side beam material and the concrete beam material are integrated, they may be installed between the two retaining walls.
また、切梁は、予め別々に成型されたコンクリート梁材と側部梁材とを結合して形成してもよい。 Further, the cut beam may be formed by combining a concrete beam material and a side beam material separately molded in advance.
更に、上述の実施例では、H型PC杭からなる土留め壁を例に示したが、土留め壁は、PC矢板やその他のコンクリートを用いた杭等を用いたものでもよく、連続地中壁であってもよい。 Furthermore, in the above-mentioned embodiment, the earth retaining wall made of the H-type PC pile is shown as an example. However, the earth retaining wall may be one using a PC sheet pile or other concrete piles, etc. It may be a wall.
1 土留め壁支持用切梁
2 側部梁材
3 コンクリート梁材
4,5 型枠部材
6 ウエブ
7 上部フランジ
8 下部フランジ
18 ボルト挿通孔
10 ボルト
11 ナット
12 アンカー挿通孔
20 掘削予定区域
21 土留め壁
22 非掘削部
23 笠コンクリート
24 アンカーボルト
25 コンクリート梁材成型用型枠
26 ナット
27 コンクリート底版
DESCRIPTION OF SYMBOLS 1 Retaining wall support cut beam 2 Side beam material 3 Concrete beam material 4,5 Formwork member 6 Web 7 Upper flange 8 Lower flange 18 Bolt insertion hole 10 Bolt 11 Nut 12 Anchor insertion hole 20 Planned excavation area 21 Earth retaining Wall 22 Non-excavated portion 23 Shade concrete 24 Anchor bolt 25 Form for molding concrete beam material 26 Nut 27 Concrete bottom plate
Claims (8)
両側部に配置された鋼製の側部梁材と、該両側部梁材間に挟まれたコンクリート製のコンクリート梁材とを備え、前記両側部梁材とコンクリート梁材とが一体化されたことを特徴としてなる土留め壁支持用切梁。 In the retaining wall supporting beam that is spanned between a pair of retaining walls arranged at a distance from each other and supports both retaining walls.
Steel side beam members arranged on both sides and concrete concrete beam members sandwiched between the both side beam members, and the both side beam materials and the concrete beam material are integrated. A retaining wall supporting cut-off beam.
互いに間隔をおいて配置された一対の側部梁材を前記両土留め壁間に架け渡した後、前記両側部梁材間にコンクリートを打設してコンクリート梁材を形成し、前記両側部梁材とコンクリート梁材とを一体化させて前記土留め壁支持用切梁とすることを特徴としてなる土留め壁支持用切梁の架設方法。 When spanning between a pair of retaining walls arranged between a pair of retaining walls spaced apart from each other, the retaining wall supporting beam for supporting the both retaining walls is constructed between the retaining walls,
A pair of side beam members spaced apart from each other are bridged between the two retaining walls, and then concrete is placed between the both side beam members to form a concrete beam member. A construction method for a retaining wall supporting cut beam, characterized in that a beam material and a concrete beam material are integrated into the retaining wall supporting cut beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2005195119A JP2007009640A (en) | 2005-07-04 | 2005-07-04 | Shore strut for supporting retaining wall and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2005195119A JP2007009640A (en) | 2005-07-04 | 2005-07-04 | Shore strut for supporting retaining wall and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2007009640A true JP2007009640A (en) | 2007-01-18 |
Family
ID=37748492
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2005195119A Pending JP2007009640A (en) | 2005-07-04 | 2005-07-04 | Shore strut for supporting retaining wall and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2007009640A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018112035A (en) * | 2017-01-13 | 2018-07-19 | 株式会社大林組 | Earth-retaining timbering unit, earth-retaining timbering and construction method of earth-retaining timbering |
CN114960673A (en) * | 2022-06-13 | 2022-08-30 | 中国一冶集团有限公司 | Quickly-formed deep foundation pit PC (polycarbonate) component supporting structure and construction method |
-
2005
- 2005-07-04 JP JP2005195119A patent/JP2007009640A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018112035A (en) * | 2017-01-13 | 2018-07-19 | 株式会社大林組 | Earth-retaining timbering unit, earth-retaining timbering and construction method of earth-retaining timbering |
CN114960673A (en) * | 2022-06-13 | 2022-08-30 | 中国一冶集团有限公司 | Quickly-formed deep foundation pit PC (polycarbonate) component supporting structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101179770B1 (en) | Soil protection against build structure and the method | |
WO2011114507A1 (en) | Method of constructing underground structure to be newly built | |
JP4851881B2 (en) | Embankment structure and method for reinforcing embankment structure | |
JP2007023713A (en) | Steel/concrete composite rigid-frame bridge and its construction method | |
JP2005256341A (en) | Corrugated steel-plate web u component bridge | |
JP2018168600A (en) | Concrete structure and method for constructing the same | |
JP4347846B2 (en) | Bridge pier reinforcement method | |
KR20070052109A (en) | Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor | |
KR101862208B1 (en) | Earth retaining wall structure and constructuon mothod thereof | |
JP6678487B2 (en) | How to build an underground structure | |
KR102104932B1 (en) | Precast modular system retaining wall | |
JP2007009640A (en) | Shore strut for supporting retaining wall and its construction method | |
JP2004027609A (en) | Construction method for subterranean structure and subterranean structure | |
KR101473218B1 (en) | A construction method of an underground structure | |
KR102482690B1 (en) | Bridge foundation construction method using formwork integrated PC panels | |
JP2007126936A (en) | Semisubterranean road and its construction method | |
JP4438540B2 (en) | Stress bearing material and construction method for underground continuous wall | |
JP2004108088A (en) | Road widening method, and structure of widened road | |
JP2003003556A (en) | Shear reinforcement method of culvert | |
JPS63280153A (en) | Underground inverted lining method | |
JP2005282115A (en) | Construction method of steel element concrete type underground structure | |
JP2020076277A (en) | Method for constructing earth retaining wall | |
JP5062418B2 (en) | Plane frame structure with precast concrete girder | |
JP2004084367A (en) | Foundation structure and elevated traffic way | |
KR102482691B1 (en) | Foundation structures using strut-tie reinforcement and its construction method |