JP2006214472A - Editing method for working drawing of piping support, drawing editing system, and editing support device - Google Patents
Editing method for working drawing of piping support, drawing editing system, and editing support device Download PDFInfo
- Publication number
- JP2006214472A JP2006214472A JP2005025860A JP2005025860A JP2006214472A JP 2006214472 A JP2006214472 A JP 2006214472A JP 2005025860 A JP2005025860 A JP 2005025860A JP 2005025860 A JP2005025860 A JP 2005025860A JP 2006214472 A JP2006214472 A JP 2006214472A
- Authority
- JP
- Japan
- Prior art keywords
- editing
- support
- piping support
- piping
- construction drawing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
本発明は、ICタグ(Radio Frequency Identification、RFID)を用いて配管サポート施工図を編集する図面編集システムに関するものである。 The present invention relates to a drawing editing system for editing a piping support construction drawing using an IC tag (Radio Frequency Identification, RFID).
従来、地中埋設された供給管に取り付けたICタグから当該供給管に関する情報を読み出して供給管の管理を行っていた(例えば、特許文献1参照)。
しかしながら、特許文献1に記載された方法では、ICタグを用いて供給管の管理を行うものの、配管サポートの施工図の編集を行うために用いられていなかった。配管サポートは、プラントなどの施工を行う際に取り付ける必要があるものであり、施工者は、配管サポートを取り付ける際、その施工図の内容を現場で確認しながら、埋込金物にて取り付けることとなる。施工図には、埋込金物のタイプや設置位置などが詳細に記載されている。
しかし、施工時には、建屋の構造や他の機器との位置調整などにより、例えば、埋込金物の打設位置が施工図の記載どおりにならない場合がある。
そこで、このような場合、配管サポートの施工を円滑に行うため、配管サポートの施工図を現場の実状況に応じてより正確に編集しなければならなかった。
However, in the method described in
However, at the time of construction, for example, the placement position of the embedded metal may not be as described in the construction drawing due to the position adjustment with the structure of the building or other equipment.
Therefore, in such a case, in order to smoothly perform the piping support construction, the piping support construction drawing had to be edited more accurately according to the actual situation at the site.
本発明は、このような状況下においてなされたものであり、その目的は、配管サポートの施工図を現場の実状況に応じてより正確に編集することである。 The present invention has been made under such circumstances, and an object thereof is to edit the construction drawing of the piping support more accurately according to the actual situation at the site.
前記課題を解決するために本発明は、配管サポートを埋込金物にて計画位置に施工するために用いる第1配管サポート施工図を編集する図面編集装置と、前記第1配管サポート施工図の編集を支援する編集支援装置とを備えるコンピュータシステムにおける配管サポート施工図の編集方法であって、前記編集支援装置が、前記第1配管サポート施工図に記載された埋込金物の打設後、位置測定器によって測定された当該埋込金物の打設後の位置と、当該埋込金物に取り付けられているICタグの読取器によって読み取られた当該埋込金物の金物用識別情報とを関連付けて受信するステップと、前記受信した金物用識別情報に対応する前記埋込金物の計画位置を記憶部から読み出し、当該読み出した埋込金物の計画位置と前記受信した打設後の位置とを比較するステップと、前記比較により双方の埋込金物間の位置ずれの程度を示す位置ずれ量を算出するステップと、前記位置ずれの対策として用いる補強材を選定するための補強材選定条件を前記記憶部から読み出し、当該補強材選定条件に基づいて、前記算出した位置ずれ量に適合する補強材を選定するステップと、前記打設後の埋込金物および前記選定した補強材にて前記配管サポートを施工するために用いる第2配管サポート施工図に前記第1配管サポート施工図を編集するための編集条件を生成するステップと、前記生成した編集条件を前記図面編集装置に送信するステップと、を実行する。また、前記図面編集装置が、前記編集支援装置からの前記編集条件を受信するステップと、前記受信した編集条件に関する前記第1配管サポート施工図を記憶部から読み出し、当該編集条件に基づいて、当該第1配管サポート施工図を前記第2配管サポート施工図に編集するステップと、前記編集した第2配管サポート施工図を外部出力するステップと、を実行する。 In order to solve the above problems, the present invention provides a drawing editing apparatus for editing a first piping support construction drawing used for constructing a piping support at a planned position with an embedded metal fitting, and editing the first piping support construction drawing. A piping support construction drawing editing method in a computer system comprising an editing support device for supporting the position, wherein the editing support device measures the position after placing the embedded hardware described in the first piping support construction drawing. The position after placement of the embedded metal measured by the instrument and the hardware identification information of the embedded hardware read by the reader of the IC tag attached to the embedded metal are received in association with each other. A plan position of the embedded hardware corresponding to the received hardware identification information is read from the storage unit, and the read planned position of the embedded hardware and the received post-placement A step of calculating a displacement, a step of calculating a displacement amount indicating a degree of displacement between both embedded metal fittings by the comparison, and a reinforcement selection for selecting a reinforcement used as a countermeasure against the displacement A condition is read from the storage unit, and based on the reinforcing material selection condition, a step of selecting a reinforcing material that matches the calculated displacement amount, the embedded metal post-placement, and the selected reinforcing material Generating an editing condition for editing the first piping support construction diagram in a second piping support construction diagram used for constructing the piping support, and transmitting the generated editing condition to the drawing editing apparatus; And execute. In addition, the drawing editing device receives the editing conditions from the editing support device, reads the first piping support construction drawing related to the received editing conditions from the storage unit, based on the editing conditions, The step of editing the first piping support construction drawing into the second piping support construction drawing and the step of outputting the edited second piping support construction drawing to the outside are executed.
本発明によれば、配管サポートの施工図を現場の実状況に応じてより正確に編集することができる。 ADVANTAGE OF THE INVENTION According to this invention, the construction drawing of piping support can be edited more correctly according to the actual condition of the field.
図1は、本発明の実施の形態に係る図面編集システムの全体構成を示すブロック図である。ここでは、発電所などの建屋工事の際に設置されるプラント用配管サポートの施工図(以下「配管サポート施工図」という)を編集する場合を例にして説明する。
図1において、図面編集システムは、サーバ(編集支援装置)10、CAD装置(図面編集装置)30、管理者用端末40、リーダライタ(読取器)50および位置測定器60を備えている。サーバ10は、LAN(Local Area Network)20を介して、CAD装置30および管理者用端末40に接続されている。これらサーバ10、CAD装置30および管理者用端末40はいずれも、例えば管理室に設置されている。
FIG. 1 is a block diagram showing the overall configuration of a drawing editing system according to an embodiment of the present invention. Here, a case where a construction drawing of a plant piping support (hereinafter referred to as “piping support construction drawing”) installed at the time of building construction such as a power plant is described as an example.
In FIG. 1, the drawing editing system includes a server (editing support device) 10, a CAD device (drawing editing device) 30, an
これに対して、リーダライタ50および位置測定器60は、施工者が現場にて用いるものである。リーダライタ50は、ICタグ70a,80aに記録されている情報を非接触で読み取ったり、あるいはICタグ70a,80aに情報を非接触で書き込んだりするためのものである。ICタグ70a,80aは、アンテナが内蔵されている非接触型ICチップのことである。なお、リーダライタ50は、携帯式を準備することとする。
ICタグ70aは、後記する個々の配管サポート70にそれぞれ取り付けられ、また、ICタグ80aも、後記する個々の埋込金物80にそれぞれ取り付けられる。そして、ICタグ70aには、個々の配管サポート70を一意に特定するためのサポート番号(サポート用識別情報)d1が記録され、また、ICタグ80aにも、個々の埋込金物80を一意に特定するための金物番号(金物用識別情報)d2が記録されている。
On the other hand, the reader /
The
位置測定器60は、例えば、レーザやCCDカメラを利用した既知の非接触3次元測定器であり、得られた測定点群の各点をもとに、後記する埋込金物80の打設後の位置d26や、後記する配管サポート70の実寸法を測定するように構成されている。以下、サーバ10、CAD装置30および管理者用端末40について詳述する。
The
まず、CAD装置30について詳述する。CAD装置30は、後記する配管サポート施工図f1,f2を編集するためのものであり、具体的には、入力部31、表示部32、通信部33、記憶部34およびこれらを制御する処理部35を具備している。入力部31は、キーボード、マウスなどの入力装置であり、表示部32は、コンピュータディスプレイなどの表示装置である。通信部33は、LANボードなどの通信インターフェースであり、記憶部34は、メモリ、ハードディスクなどの記憶装置である。処理部35は、CPUなどの処理装置である。
First, the
記憶部34には、配管サポート施工図f1,f2が格納されている。配管サポート施工図(第1配管サポート施工図)f1は、後記する配管サポート70の施工を実現するために当初計画されたものであり、施工者は、まず、この配管サポート施工図f1をもとに施工を行うこととなる。
配管サポート施工図(第2配管サポート施工図)f2は、施工の進捗状況に応じ、配管サポート施工図f1が編集されたものである。
The
The piping support construction diagram (second piping support construction diagram) f2 is obtained by editing the piping support construction diagram f1 according to the progress of construction.
ここで、まず、前記した配管サポート施工図f1の一例を図2に示す。図2によると、側面図および正面図の別に、埋込金物80にて壁面に固定された配管サポート70が記載されている。正面図は、側面図に記載のX1−X1矢視図、すなわち配管サポート70を壁正面から見た図を表している。
また、この配管サポート施工図f1には、サポート番号d1や配置番号、位置番号が記載され、さらに配管サポート70の設計寸法を示すサポート寸法d13が記載されている。サポート番号d1は、図1に示したICタグ70aに記録されるサポート番号d1と同じものである。これにより、配管サポート施工図f1に記載の配管サポート70と、ICタグ70aに取り付けられた配管サポート70との対応関係が、1対1の関係となり、双方の配管サポート70を対応付けることが可能となる。
サポート寸法d13として、側面図に記載の「A」、「B」、および正面図に記載の「C」の各寸法を記載することとしている。なお、このようなサポート寸法d13の内訳を変更するようにしてもよい。
Here, first, an example of the piping support construction drawing f1 described above is shown in FIG. According to FIG. 2, the
Further, in this piping support construction drawing f1, a support number d1, an arrangement number, and a position number are described, and further, a support dimension d13 indicating a design dimension of the
As the support dimension d13, each dimension of “A” and “B” described in the side view and “C” described in the front view is described. The breakdown of the support dimension d13 may be changed.
続いて、前記した配管サポート施工図f2の一例を図3に示す。図3によると、図2に示した埋込金物80のうち、中央に位置する埋込金物80の位置が下方にずれ、かつ、その下方にずれた埋込金物80と配管サポート70との間には、プレートたる補強材81が介装されている。
つまり、この配管サポート施工図f2の特徴は、実際に打設された埋込金物80の位置を反映して配管サポート施工図f1を編集した点にある。
例えば、現場では、施工者が、図2に示した配管サポート施工図f1をもとに埋込金物80をその記載どおりの位置に打設しようとするが、現場調整などにより埋込金物80の位置を変更して打設する場合がある。このような場合に、実際に打設された埋込金物80の位置に記載するように配管サポート施工図f1を作成しなおし、以降の配管サポート70の施工図として示したのが、この配管サポート施工図f2である。なお、図3のサポート寸法d13には、この編集内容に合致した値が記載されている。
Subsequently, an example of the above-described piping support construction drawing f2 is shown in FIG. According to FIG. 3, the position of the embedded
That is, the feature of the piping support construction drawing f2 is that the piping support construction drawing f1 is edited to reflect the position of the embedded
For example, at the site, the builder attempts to place the embedded
このように、施工者は、まず、配管サポート施工図f1をもとに埋込金物80を設置することになるが、その位置は、図4に示す配置図をもとに行うこととなる。図4に示す配置図には、ある工事工区における埋込金物80の打設位置を示したものである。
具体的には、「R5」−「R6」通りおよび「RC」−「RD」通りからなるスパンが記載され、このスパンには、埋込金物80の打設位置が四角印でプロットされている。そして、このプロットには、「1」などの金物番号d2も記載されている。金物番号d2は、図1に示したICタグ80aに記録された金物番号d2と同じものである。これにより、図2に示した配管サポート施工図f1に記載の埋込金物80と、図1に示したICタグ80aに取り付けられた埋込金物80との対応関係が、1対1の関係となり、双方の埋込金物80を対応付けることが可能となる。
As described above, the installer first installs the embedded
Specifically, spans composed of “R5”-“R6” streets and “RC”-“RD” streets are described, and the placement positions of the embedded
そして、この配置図には、金物番号d2ごとに、計画位置d25やタイプd21、要求元d3が記載されている。
計画位置d25には、「X」、「Y」および「Z」が含まれているが、これらは、通り芯を基準にしている。具体的には、「X」はR5−R6通り方向の位置を、「Y」はRC−RD通り方向の位置を、「Z」は高さ方向の位置をそれぞれあらわしている。例えば、「X」にはR5通りからの距離が記載され、「Y」にはRC通りからの距離が記載され、「Z」にはエレベーション(基準からの高さ)が記載される。
なお、タイプd21としては、例えば形状や大きさなどがあり、要求元d3としては、例えばプラントメーカなどがある。これにより、施工者は、個々の埋込金物80を計画位置d25に設置することが可能となる。
In this layout diagram, the planned position d25, the type d21, and the request source d3 are described for each hardware number d2.
The planned position d25 includes “X”, “Y”, and “Z”, which are based on the core. Specifically, “X” represents a position in the R5-R6 direction, “Y” represents a position in the RC-RD direction, and “Z” represents a position in the height direction. For example, “X” describes the distance from the R5 street, “Y” describes the distance from the RC street, and “Z” describes the elevation (height from the reference).
The type d21 includes, for example, the shape and size, and the request source d3 includes, for example, a plant manufacturer. Thereby, the builder can install the individual embedded metal objects 80 at the planned position d25.
図1に戻って、サーバ10について詳述する。サーバ10は、前記した配管サポート施工図f1,f2の編集を支援するためのものであり、具体的には、通信部11、記憶部12およびこれらを制御する処理部13を具備している。処理部13は、CPUなどの処理装置である。通信部11は、リーダライタ50、CAD装置30および管理者用端末40との間の通信を実現するためのものである。例えば、無線ボードやLANボードなどの通信インターフェースがこれに該当する。
Returning to FIG. 1, the
記憶部12は、メモリ、ハードディスクなどの記憶装置である。この記憶部12には、配管サポート別金物対応表121、配管サポート一覧表122、金物一覧表123、位置ずれ量一覧表124および補強材選定条件125が格納されている。以下、これらについて順を追って詳述する。
配管サポート別金物対応表121には、図5に示すように、前記したサポート番号d1(図1,図2,図3参照)と前記した金物番号d2(図1,図4参照)との対応関係が格納されている。これにより、配管サポート施工図f1,f2に記載された配管サポート70および埋込金物80の組み合わせパターンを管理することが可能となる。
The
In the hardware correspondence table 121 by piping support, as shown in FIG. 5, the correspondence between the support number d1 (see FIGS. 1, 2 and 3) and the hardware number d2 (see FIGS. 1 and 4). Relationships are stored. Thereby, it becomes possible to manage the combination pattern of the
配管サポート一覧表122には、図6に示すように、前記したサポート番号d1(図1,図2,図3参照)、種別d11、拘束方向・荷重d12、サポート寸法d13(図2,図3参照)および計画位置d14が、相互に関連付けられている。種別d11は、形状や大きさなどを特定するためのものである。拘束方向・荷重d12には、垂直方向への荷重などの条件が含まれる。これにより、配管サポート施工図f1,f2(図2,図3参照)に記載された配管サポート70の一覧を管理することが可能となる。 In the piping support list 122, as shown in FIG. 6, the support number d1 (see FIGS. 1, 2 and 3), the type d11, the restraining direction / load d12, the support dimension d13 (FIGS. 2 and 3). And the planned position d14 are associated with each other. The type d11 is for specifying the shape and size. The constraint direction / load d12 includes conditions such as a load in the vertical direction. Thereby, it becomes possible to manage the list of the piping supports 70 described in the piping support construction drawings f1 and f2 (see FIGS. 2 and 3).
金物一覧表123には、図7に示すように、前記した金物番号d2(図1,図4参照)、タイプd21(図4参照)、許容荷重d22、形状・寸法d23、スタッドジベルd24および計画位置d25(図4参照)が、相互に関連付けられている。タイプd21としては、例えば、プレートの大きさやスタッドジベルの本数などがある。スタッドジベルd24は、プレートに溶接される棒状の脚を意味する。
In the
位置ずれ量一覧表124には、図8に示すように、前記した金物番号d2(図1,図4参照)、計画位置d25(図4参照)、打設後の位置d26および位置ずれ量d27が、相互に関連付けられている。ここにいう打設後の位置d26は、配管サポート施工図f1に記載の埋込金物80が実際に打設された位置を意味する。位置ずれ量d27は、この打設後の位置d26と、計画位置d25(図4参照)との位置ずれの程度を意味する。
As shown in FIG. 8, the positional
補強材選定条件125は、配管サポート施工図f2に記載の補強材81を選定するための条件である。すなわち、配管サポート施工図f1に記載の埋込金物80が打設された後、配管サポート70を補強するために用いるプレートなどの補強材81を選定するための条件である。具体的には、図8に示した位置ずれ量d27に適合する、配管サポート70および埋込金物80との組み合わせがこれに含まれている。ここにいう適合というのは、強度などの性能を総合的に評価して支障がないという意味である。
The reinforcing material selection condition 125 is a condition for selecting the reinforcing
図1に戻って、管理者用端末40は、例えばパーソナルコンピュータであり、マウスなどの入力装置、コンピュータディスプレイなどの表示装置、メモリなどの記憶装置およびCPUなどの処理装置を具備している。
Returning to FIG. 1, the
次に、施工者が、配管サポート施工図f1(図2参照)および配置図(図4参照)を参照しながら施工した結果を反映して配管サポート施工図f2(図3参照)に自動で編集する処理手順について説明する。
図9は、図面編集システムを用いて配管サポート施工図を編集する処理手順を示す図である。ここでは、まず、施工者が、現場調整などにより、埋込金物80を製作して所定の位置に打設した場合を前提に説明する。また、この打設の際、施工者が、リーダライタ50を用いて、その埋込金物80のICタグ80aに、該当する金物番号d2を書き込むことを前提に説明することとする。なお、ICタグ80aには、金物番号d2のほかにも、タイプd21などを書き込むようにしてもよい。
Next, the installer automatically edits the piping support construction diagram f2 (see FIG. 3) to reflect the construction results while referring to the piping support construction diagram f1 (see FIG. 2) and the layout diagram (see FIG. 4). A processing procedure to be performed will be described.
FIG. 9 is a diagram showing a processing procedure for editing a piping support construction drawing using the drawing editing system. Here, description will be made on the premise that the construction person manufactures the embedded
この場合、まず、施工者による位置測定器60への操作により、位置測定器60が、施工者によって打設された埋込金物80の位置、すなわち埋込金物80の打設後の位置d26を測定してリーダライタ50に送信する(S1)。この送信は、例えば、施工者が、位置測定器60とリーダライタ50とを専用ケーブルで接続した後に行われる。
続いて、施工者が、リーダライタ50を用いて、埋込金物80に取り付けたICタグ80aに記録された金物番号d2を読み取る。そして、施工者によるリーダライタ50の操作により、リーダライタ50が、位置測定器60から送信された打設後の位置d26を、その金物番号d2ごとにサーバ10に送信する(S2)。このようにして、施工者が配管サポート施工図f1を参照しながら打設した埋込金物80の位置が、打設後の位置d26としてサーバ10に送信される。
なお、S2では、埋込金物80の金物番号d2を送信することとしたが、さらに、埋込金物80のタイプd21も送信するようにしてもよい。また、S2においては、リーダライタ50が、位置測定器60によって測定された打設後の位置d26をサーバ10に送信することとしたが、例えば、位置測定器60が、打設後の位置d26を金物番号d2と関連付けて、直接、サーバ10に送信するようにしてもよい。
In this case, first, the
Subsequently, the installer uses the reader /
In S2, the hardware number d2 of the embedded
次に、リーダライタ50からの送信を受けて、サーバ10の処理部13が、打設後の位置d26を金物番号d2ごとに受信する(S3)。続いて、処理部13が、受信した金物番号d2に対応する計画位置d25を記憶部12の金物一覧表123(図7参照)から読み出し、S3で受信した打設後の位置d26と、前記読み出した計画位置d25とを金物番号d2ごとに比較する(S4)。
そして、比較の結果、双方の位置が一致した場合(S5のYes)、処理部13は、その旨をリーダライタ50に送信する(S6)。これにより、例えば、前記一致の旨が、リーダライタ50上の表示パネルに表示され、施工者は、配管サポート施工図f1の計画位置d25どおりに埋込金物80が打設されたことを確認することが可能となる。この場合、施工者は、配管サポート施工図f1を用いて、引き続き施工を続けることとなる。
Next, in response to transmission from the reader /
If the positions match as a result of the comparison (Yes in S5), the processing unit 13 transmits that fact to the reader / writer 50 (S6). Thereby, for example, the fact of the agreement is displayed on the display panel on the reader /
これに対して、前記した比較の結果、双方の位置が不一致の場合(S5のNo)、処理部13は、双方の位置ずれの程度を示す位置ずれ量d27を算出する(S7)。位置ずれ量d27には、図4に示した計画位置d25と同様、「X」、「Y」および「Z」が含まれる。これにより、埋込金物80の位置ずれの程度を客観的に指標することが可能となる。なお、S7で算出された位置ずれ量d27は、図8の位置ずれ量一覧表124に金物番号d2ごとに登録される。
On the other hand, if the two positions do not match as a result of the comparison (No in S5), the processing unit 13 calculates a positional deviation amount d27 indicating the degree of the positional deviation between the two (S7). The positional deviation amount d27 includes “X”, “Y”, and “Z” as in the planned position d25 illustrated in FIG. Thereby, it is possible to objectively indicate the degree of displacement of the embedded
なお、サーバ10の処理部13は、S4で比較をする場合、S3で受信した打設後の位置d26に対応する金物番号d2と、図7の金物一覧表123の中の金物番号d2とを照合し、照合の結果(不一致,一致)をリーダライタ50に送信して、そのリーダライタ50上に表示させるようにしてもよい。このようにすると、施工者は、埋込金物80の要否の確認作業を行うことが可能となる。
そして、施工者が、リーダライタ50を用いて、埋込金物80の要否の確認作業を終了する旨の情報をサーバ10に送信した場合においては、サーバ10の処理部13は、次のような処理を行うようにしてもよい。まず、処理部13は、チェック済みの埋込金物80の金物番号d2と、図7の金物一覧表123の中の金物番号d2とを比較して、埋込金物80のチェック漏れの有無を判断する。そして、処理部13は、その判断の結果(チェック漏れの有無)をリーダライタ50に送信する。このようにすると、施工者は、埋込金物80のチェック漏れの有無を確認することが可能となり、円滑な施工が促進されることとなる。
When the processing unit 13 of the
And when a construction person transmits the information to the effect that the confirmation work of the necessity of the embedded
次に、S8では、サーバ10の処理部13は、記憶部12の補強材選定条件125に基づいて、S7で算出した位置ずれ量d27に適合する補強材81を選定する。そして、処理部13は、その補強材81にて配管サポート70を施工するための配管サポート施工図f2に配管サポート施工図f1を編集するための編集条件を生成する。編集条件には、補強材81に関する情報(大きさ・寸法など)や、編集後の配管サポート70のサポート寸法d13、該当する配管サポート70のサポート番号d1などが含まれる。そして、処理部13は、その編集条件をLAN20を介してCAD装置30に送信する(S9)。
Next, in S <b> 8, the processing unit 13 of the
このようにすると、たとえ埋込金物80が、配管サポート施工図f1どおりの計画位置d25に打設されなかったとしても、その状況に応じた補強材81を埋込金物80の位置ずれ対策として選択し、その補強材81にて配管サポート70を施工する具体的な方法を後記する配管サポート施工図f2として示すことが可能となる。
なお、処理部13は、S9の送信の際、編集条件に合致するように、図6の配管サポート一覧表122や、図7の金物一覧表123を更新する。
In this case, even if the embedded
Note that the processing unit 13 updates the piping support list 122 in FIG. 6 and the
次に、S10では、サーバ10からの送信を受けて、CAD装置30の処理部35は、前記した編集条件を受信し、その編集条件に関する配管サポート施工図f1を記憶部34から読み出し、その配管サポート施工図f1に当該編集条件を反映した配管サポート施工図f2を作成する。なお、配管サポート施工図f1の読み出しは、例えば、編集条件に含まれているサポート番号d1をキーとして行う。
Next, in S10, in response to the transmission from the
これにより、その後、管理者が、例えば、CAD装置30の入力部31を用いて操作することにより、S10で作成された配管サポート施工図f2が、CAD装置30の表示部32に外部出力されて表示されることとなる。また、その配管サポート施工図f2が、図示しないプリンタに外部出力されて印刷されることとなる。このようにすると、施工者は、図3の配管サポート施工図f2を参照しながら、配管サポート70の施工を続けることが可能となる。
Thereby, after that, when the administrator operates, for example, using the
次に、施工者が配管サポート施工図f2を参照しながら施工した結果を反映して、配管サポート70の完成図f3を自動で作成する処理手順について説明する。
図10は、図面編集システムを用いて配管サポートの完成図を作成する処理手順を示す図である。
まず、施工者は、配管サポート施工図f2に記載された配管サポート70を製作して現場で組み立てる際、リーダライタ50を用いて、その配管サポート70に取り付けたICタグ70aのサポート番号d1を読み取る。そして、施工者は、リーダライタ50を用いて、そのサポート番号d1をサーバ10に無線で送信する。そうすると、この送信を受けて、サーバ10の処理部13が、サポート番号d1を受信する(S20)。
Next, a processing procedure for automatically creating a completed drawing f3 of the
FIG. 10 is a diagram showing a processing procedure for creating a completed piping support drawing using the drawing editing system.
First, when manufacturing the
また、施工者は、リーダライタ50を用いて、その配管サポート70に係合する埋込金物80に取り付けたICタグ80aの金物番号d2を読み取る。そして、施工者は、リーダライタ50を用いて、その金物番号d2をサーバ10に無線で送信する。そうすると、この送信を受けて、サーバ10の処理部13が、金物番号d2を受信する(S21)。
Further, using the reader /
次に、サーバ10の処理部13は、S20で受信したサポート番号d1、およびS21で受信した金物番号d2の対応関係を、図5の配管サポート別金物対応表121と照合し(S22)、照合の結果、不一致の場合(S23のNo)、その旨をリーダライタ50に送信する(S24)。これにより、例えば、リーダライタ50の表示パネル上には、前記不一致の旨が表示され、施工者は、配管サポート70と埋込金物80との組み合わせを見直すことが可能となる。なお、このような場合、リーダライタ50が、サーバ10からの送信を受けて、アラームなどの音声で報知するようにしてもよい。
Next, the processing unit 13 of the
これに対して、前記した照合の結果、双方の対応関係が一致した場合(S23のYes)、サーバ10の処理部13は、その旨をリーダライタ50に送信する(S25)。これにより、例えば、リーダライタ50の表示パネル上には、前記一致の旨が表示され、施工者は、配管サポート70を予定通り施工してもよいことを確認することが可能となる。これにより、施工者は、安心して配管サポート70を埋込金物80に係合させることが可能となる。
On the other hand, as a result of the collation described above, if the correspondence between the two matches (Yes in S23), the processing unit 13 of the
このようにして、施工者が配管サポート70を組み立てた場合、次に、施工者は、位置測定器60を用いて、施工後の配管サポート70の実寸法を測定する。ここにいう実寸法は、図3に示した配管サポート70の「A」、「B」および「C」の各寸法を意味する。
そして、施工者は、位置測定器60を用いて、測定した配管サポート70の実寸法をリーダライタ50に送信する。これにより、位置測定器60が、配管サポート70の実寸法をリーダライタ50に送信することとなる(S26)。
In this way, when the builder assembles the
Then, the installer uses the
続いて、施工者によるリーダライタ50の操作により、リーダライタ50が、S26で送信された配管サポート70の実寸法を、該当する配管サポート70のサポート番号d1ごとにサーバ10に送信する。サポート番号d1は、リーダライタ50が配管サポート70に取り付けられたICタグ70aから読み取る。
そうすると、この送信を受けて、サーバ10の処理部13は、配管サポート70の実寸法をサポート番号d1ごとに受信する(S27)。
Subsequently, the reader /
Then, receiving this transmission, the processing unit 13 of the
ここで、このようにして、施工者が組み立てた配管サポート70の完成例を図11に示す。図11(a)は配管サポート70を壁側面から見た図であり、図11(b)は配管サポート70を壁正面から見た図である。
図11(a)によると、各配管サポート70は、各埋込金物(実線部分)80および補強材81にて壁面で固定されている。そして、個々の配管サポート70には、施工者によって貼り付けられたICタグ70aが取り付けられている。なお、破線で示した埋込金物80は、当初の計画位置、すなわち配置図(図4参照)に記載された計画位置d25に相当するものである。
また、図11(b)によると、個々の埋込金物80には、施工者によって貼り付けられたICタグ80aが取り付けられている。このようにして、配管サポート70が、埋込金物80および補強材81にて壁面に組み立てられる。
Here, a completed example of the
According to FIG. 11A, each
Further, according to FIG. 11B, an
図11に戻って説明を続ける。次のS28では、サーバ10の処理部13が、まず、S27で受信したサポート番号d1に対応するサポート寸法d13を記憶部12の配管サポート一覧表122(図6参照)から読み出す。読み出されたサポート寸法d13は、配管サポート施工図f2に記載された配管サポート70の設計寸法である。
そして、処理部13は、S27で受信した配管サポート70の実寸法と、前記読み出したサポート寸法d13との寸法差を算出する(S28)。ここにいう寸法差は、図3に示した配管サポート70の「A」、「B」および「C」の各寸法差を意味する。これにより、施工者によって実際に組み立てられた配管サポート70が、配管サポート施工図f2に記載の配管サポート70に比べて、どの程度の寸法差が生じたかを客観的に指標することが可能となる。
そして、処理部13は、S28で算出後の寸法差を、該当する配管サポート70のサポート番号d1に関連付けて、LAN20を介してCAD装置30に送信する(S29)。
Returning to FIG. 11, the description will be continued. In next S28, the processing unit 13 of the
Then, the processing unit 13 calculates a dimensional difference between the actual dimension of the
Then, the processing unit 13 transmits the dimensional difference calculated in S28 to the
そうすると、サーバ10からの送信を受けて、CAD装置30の処理部35は、S29で送信された寸法差を受信し、その寸法差に関する配管サポート施工図f2を記憶部34から読み出し、その配管サポート施工図f2に当該寸法差を反映して配管サポート70の完成図f3を作成する(S30)。なお、配管サポート施工図f1の読み出しは、例えば、サポート番号d1をキーとして行う。
そして、処理部35は、作成後の完成図f3をサーバ10に送信する(S31)。これにより、サーバ10の処理部13は、管理者用端末40からの要求に応じて、S31で送信された完成図f3を記憶部12から読み出し、管理者用端末40に外部出力(表示,プリント)することとなる。この完成図f3の出力例を図12に示す。
Then, in response to the transmission from the
And the
図12によると、各配管サポート70は、各埋込金物80および補強材81にて壁面で固定され、このときのサポート寸法が記載されている。つまり、図11(a)(b)に示した配管サポート70の完成例に相当するものとして記載されている。これにより、管理者は、いつでも、配管サポート70の完成図f3を確認することができ、有用である。
According to FIG. 12, each piping
なお、本発明は、前記した実施の形態に限定されない。図面編集システムの構成、データ構造および処理手順は、本発明の趣旨を逸脱しない限り、変更して構成するようにしてもよい。例えば、サーバ10およびCAD装置30の2台を用いて構成する場合について説明したが、1台や3台のコンピュータを用いて構成するようにしてもよい。例えば、CAD装置30にサーバ10の機能を兼ね備えるようにして構成してもよい。
The present invention is not limited to the embodiment described above. The configuration, data structure, and processing procedure of the drawing editing system may be changed and configured without departing from the spirit of the present invention. For example, although the case where the
10 サーバ(編集支援装置)
12,34 記憶部
13,35 処理部
30 CAD装置(図面編集装置)
50 リーダライタ(読取器)
60 位置測定器
70a,80a ICタグ
d1 サポート番号(サポート用識別番号)
d2 金物番号(金物用識別番号)
10 server (editing support device)
12, 34
50 Reader / Writer
60
d2 Hardware number (identification number for hardware)
Claims (10)
前記編集支援装置が、
前記第1配管サポート施工図に記載された埋込金物の打設後、位置測定器によって測定された当該埋込金物の打設後の位置と、当該埋込金物に取り付けられているICタグの読取器によって読み取られた当該埋込金物の金物用識別情報とを関連付けて受信するステップと、
前記受信した金物用識別情報に対応する前記埋込金物の計画位置を記憶部から読み出し、当該読み出した埋込金物の計画位置と前記受信した打設後の位置とを比較するステップと、
前記比較により双方の埋込金物間の位置ずれの程度を示す位置ずれ量を算出するステップと、
前記位置ずれの対策として用いる補強材を選定するための補強材選定条件を前記記憶部から読み出し、当該補強材選定条件に基づいて、前記算出した位置ずれ量に適合する補強材を選定するステップと、
前記打設後の埋込金物および前記選定した補強材にて前記配管サポートを施工するために用いる第2配管サポート施工図に前記第1配管サポート施工図を編集するための編集条件を生成するステップと、
前記生成した編集条件を前記図面編集装置に送信するステップと、を実行し、
前記図面編集装置が、
前記編集支援装置からの前記編集条件を受信するステップと、
前記受信した編集条件に関する前記第1配管サポート施工図を記憶部から読み出し、当該編集条件に基づいて、当該第1配管サポート施工図を前記第2配管サポート施工図に編集するステップと、
前記編集した第2配管サポート施工図を外部出力するステップと、
を実行することを特徴とする配管サポート施工図の編集方法。 A computer system comprising a drawing editing device for editing a first piping support construction drawing used for constructing a piping support at a planned position with an embedded hardware, and an editing support device for supporting editing of the first piping support construction drawing. Editing method of piping support construction drawing in
The editing support device is
After placement of the embedded metal object described in the first piping support construction drawing, the position after placement of the embedded metal object measured by the position measuring device, and the IC tag attached to the embedded metal object Receiving in association with the hardware identification information of the embedded hardware read by the reader;
Reading the planned position of the embedded hardware corresponding to the received hardware identification information from the storage unit, and comparing the read planned position of the embedded hardware with the received post-placement position;
Calculating a misregistration amount indicating a degree of misregistration between the two embedded metal objects by the comparison;
A step of reading out a reinforcing material selection condition for selecting a reinforcing material to be used as a countermeasure for the positional deviation from the storage unit, and selecting a reinforcing material that matches the calculated positional deviation amount based on the reinforcing material selection condition; ,
A step of generating an editing condition for editing the first piping support construction drawing in a second piping support construction drawing used for constructing the piping support with the embedded metal fitting after placement and the selected reinforcing material; When,
Transmitting the generated editing conditions to the drawing editing device; and
The drawing editing apparatus comprises:
Receiving the editing conditions from the editing support device;
Reading out the first piping support construction drawing related to the received editing conditions from the storage unit, and editing the first piping support construction drawing into the second piping support construction drawing based on the editing conditions;
Outputting the edited second piping support construction drawing to the outside;
A method for editing a piping support construction diagram, characterized in that is executed.
前記編集支援装置は、
前記第2配管サポート施工図に記載された配管サポートの施工後に前記位置測定器によって測定された当該配管サポートの実寸法と、当該配管サポートに取り付けられているICタグの前記読取器によって読み取られた当該配管サポートのサポート用識別情報とを関連付けて受信するステップと、
前記受信したサポート用識別情報に対応する前記配管サポートの設計寸法を前記記憶部から読み出し、当該設計寸法と前記受信した配管サポートの実寸法との寸法差を算出するステップと、
前記算出した寸法差を前記図面編集装置に送信するステップと、をさらに実行し、
前記図面編集装置は、
前記編集支援装置からの前記寸法差を受信するステップと、
前記受信した寸法差を前記第2配管サポート施工図に反映して、施工完了後の配管サポートの完成図を作成するステップと、
前記作成した完成図を外部出力するステップと、をさらに実行することを特徴とする請求項1に記載の配管サポート施工図の編集方法。 In the second piping support construction drawing, the design dimensions of the piping support are described.
The editing support device includes:
It was read by the reader of the IC tag attached to the piping support and the actual dimension of the piping support measured by the position measuring device after the piping support described in the second piping support construction drawing. Receiving in association with identification information for support of the pipe support;
Reading a design dimension of the pipe support corresponding to the received support identification information from the storage unit, and calculating a dimensional difference between the design dimension and the actual dimension of the received pipe support;
Transmitting the calculated dimensional difference to the drawing editing device; and
The drawing editing apparatus comprises:
Receiving the dimensional difference from the editing support device;
Reflecting the received dimensional difference in the second piping support construction drawing and creating a completed drawing of the piping support after the completion of construction;
The piping support construction drawing editing method according to claim 1, further comprising the step of externally outputting the created completed drawing.
前記編集支援装置が、
前記第1配管サポート施工図に記載された埋込金物の打設後、位置測定器によって測定された当該埋込金物の打設後の位置と、当該埋込金物に取り付けられているICタグの読取器によって読み取られた当該埋込金物の金物用識別情報とを関連付けて受信する処理と、
前記受信した金物用識別情報に対応する前記埋込金物の計画位置を記憶部から読み出し、当該読み出した埋込金物の計画位置と前記受信した打設後の位置とを比較する処理と、
前記比較により双方の埋込金物間の位置ずれの程度を示す位置ずれ量を算出する処理と、
前記位置ずれの対策として用いる補強材を選定するための補強材選定条件を前記記憶部から読み出し、当該補強材選定条件に基づいて、前記算出した位置ずれ量に適合する補強材を選定する処理と、
前記打設後の埋込金物および前記選定した補強材にて前記配管サポートを施工するために用いる第2配管サポート施工図に前記第1配管サポート施工図を編集するための編集条件を生成する処理と、
前記生成した編集条件を前記図面編集装置に送信する処理と、を実行し、
前記図面編集装置が、
前記編集支援装置からの前記編集条件を受信する処理と、
前記受信した編集条件に関する前記第1配管サポート施工図を記憶部から読み出し、当該編集条件に基づいて、当該第1配管サポート施工図を前記第2配管サポート施工図に編集する処理と、
前記編集した第2配管サポート施工図を外部出力する処理と、
を実行することを特徴とする図面編集システム。 Drawing editing apparatus comprising a drawing editing device for editing a first piping support construction drawing used for constructing a piping support at a planned position with an embedded hardware, and an editing support device for supporting the editing of the first piping support construction drawing. A system,
The editing support device is
After the placement of the embedded metal object described in the first piping support construction drawing, the position of the embedded metal object measured by the position measuring device and the IC tag attached to the embedded metal object A process of receiving in association with the hardware identification information of the embedded hardware read by the reader;
A process of reading the planned position of the embedded hardware corresponding to the received hardware identification information from the storage unit, and comparing the read planned position of the embedded hardware with the received post-placement position;
A process of calculating a misregistration amount indicating a degree of misregistration between the two embedded metal objects by the comparison;
A process of selecting a reinforcing material selection condition for selecting a reinforcing material to be used as a countermeasure for the positional deviation from the storage unit, and selecting a reinforcing material that matches the calculated positional deviation amount based on the reinforcing material selection condition; ,
Processing for generating an editing condition for editing the first piping support construction diagram in the second piping support construction diagram used for constructing the piping support with the embedded metal fitting and the selected reinforcing material When,
A process of transmitting the generated editing condition to the drawing editing device;
The drawing editing device,
Processing for receiving the editing conditions from the editing support device;
Reading out the first piping support construction drawing related to the received editing conditions from the storage unit, and editing the first piping support construction drawing into the second piping support construction drawing based on the editing conditions;
Processing to output the edited second piping support construction drawing to the outside;
The drawing editing system characterized by executing.
前記編集支援装置は、
前記第2配管サポート施工図に記載された配管サポートの施工後に前記位置測定器によって測定された当該配管サポートの実寸法と、当該配管サポートに取り付けられているICタグの前記読取器によって読み取られた当該配管サポートのサポート用識別情報とを関連付けて受信する処理と、
前記受信したサポート用識別情報に対応する前記配管サポートの設計寸法を前記記憶部から読み出し、当該設計寸法と前記受信した配管サポートの実寸法との寸法差を算出する処理と、
前記算出した寸法差を前記図面編集装置に送信する処理と、をさらに実行し、
前記図面編集装置は、
前記編集支援装置からの前記寸法差を受信する処理と、
前記受信した寸法差を前記第2配管サポート施工図に反映して、施工完了後の配管サポートの完成図を作成する処理と、
前記作成した完成図を外部出力する処理と、をさらに実行することを特徴とする請求項3に記載の図面編集システム。 In the second piping support construction drawing, the design dimensions of the piping support are described.
The editing support device includes:
It was read by the reader of the IC tag attached to the piping support and the actual dimension of the piping support measured by the position measuring device after the piping support described in the second piping support construction drawing. A process of receiving the identification information for support of the pipe support in association with the information;
A process of reading the design dimension of the pipe support corresponding to the received support identification information from the storage unit, and calculating a dimensional difference between the design dimension and the actual dimension of the received pipe support;
A process of transmitting the calculated dimensional difference to the drawing editing apparatus; and
The drawing editing apparatus comprises:
Processing for receiving the dimensional difference from the editing support device;
A process of reflecting the received dimensional difference in the second piping support construction drawing and creating a finished drawing of the piping support after the completion of construction;
4. The drawing editing system according to claim 3, further comprising a process of externally outputting the created completed drawing.
前記編集支援装置は、前記配管サポートの設計寸法と前記配管サポートの実寸法との寸法差を算出する場合、
前記読取器によって読み取られた前記サポート用識別情報と、前記読取器によって読み取られた前記金物用識別情報とを対応付けて受信するとともに、
前記受信した金物用識別情報および当該サポート用識別情報の対応関係と、前記記憶部に格納されている前記対応関係とを照合し、
前記照合の結果、双方の対応関係が一致したことを条件に前記寸法差を算出することを特徴とする請求項4に記載の図面編集システム。 In the storage unit of the editing support device, the correspondence between the piping support and the embedded hardware described in the second piping support construction drawing uses the correspondence between the identification information for support and the identification information for hardware. Stored,
When the edit support device calculates a dimensional difference between the design dimension of the pipe support and the actual dimension of the pipe support,
Receiving the support identification information read by the reader in association with the hardware identification information read by the reader;
Collating the correspondence between the received hardware identification information and the support identification information with the correspondence stored in the storage unit;
5. The drawing editing system according to claim 4, wherein the dimensional difference is calculated on the condition that the correspondence between the two matches as a result of the collation.
前記照合の結果、双方の対応関係が不一致の場合、その旨の情報を前記読取器に送信することを特徴とする請求項5に記載の図面編集システム。 The editing support device includes:
The drawing editing system according to claim 5, wherein, as a result of the collation, if the correspondence between the two does not match, information to that effect is transmitted to the reader.
情報の記憶部および処理部を備え、
前記処理部が、
前記第1配管サポート施工図に記載された埋込金物の打設後、位置測定器によって測定された当該埋込金物の打設後の位置と、当該埋込金物に取り付けられているICタグの読取器によって読み取られた当該埋込金物の金物用識別情報とを関連付けて受信する処理と、
前記受信した金物用識別情報に対応する前記埋込金物の計画位置を記憶部から読み出し、当該読み出した埋込金物の計画位置と前記受信した打設後の位置とを比較する処理と、
前記比較により双方の埋込金物間の位置ずれの程度を示す位置ずれ量を算出する処理と、
前記位置ずれの対策として用いる補強材を選定するための補強材選定条件を前記記憶部から読み出し、当該補強材選定条件に基づいて、前記算出した位置ずれ量に適合する補強材を選定する処理と、
前記打設後の埋込金物および前記選定した補強材にて前記配管サポートを施工するために用いる第2配管サポート施工図に前記第1配管サポート施工図を編集するための編集条件を生成する処理と、
前記生成した編集条件に基づいて前記第1配管サポート施工図を前記第2配管サポート施工図に編集させるために、当該編集条件を図面編集装置に送信する処理と、
を実行することを特徴とする編集支援装置。 An editing support device for supporting the editing of the first piping support construction drawing used to construct the piping support at the planned position with the embedded hardware,
An information storage unit and a processing unit;
The processing unit is
After placement of the embedded metal object described in the first piping support construction drawing, the position after placement of the embedded metal object measured by the position measuring device, and the IC tag attached to the embedded metal object A process of receiving in association with the hardware identification information of the embedded hardware read by the reader;
A process of reading the planned position of the embedded hardware corresponding to the received hardware identification information from the storage unit, and comparing the read planned position of the embedded hardware with the received post-placement position;
A process of calculating a misregistration amount indicating a degree of misregistration between the two embedded metal objects by the comparison;
A process of selecting a reinforcing material selection condition for selecting a reinforcing material to be used as a countermeasure for the positional deviation from the storage unit, and selecting a reinforcing material that matches the calculated positional deviation amount based on the reinforcing material selection condition; ,
Processing for generating an editing condition for editing the first piping support construction drawing in the second piping support construction drawing used for constructing the piping support with the embedded metal fitting after placement and the selected reinforcing material When,
In order to edit the first piping support construction drawing into the second piping support construction drawing based on the generated editing conditions, a process of transmitting the editing conditions to the drawing editing device;
An editing support apparatus characterized by executing
前記処理部は、
前記第2配管サポート施工図に記載された配管サポートの施工後に前記位置測定器によって測定された当該配管サポートの実寸法と、当該配管サポートに取り付けられているICタグの前記読取器によって読み取られた当該配管サポートのサポート用識別情報とを関連付けて受信する処理と、
前記受信したサポート用識別情報に対応する前記配管サポートの設計寸法を前記記憶部から読み出し、当該設計寸法と前記受信した配管サポートの実寸法との寸法差を算出する処理と、
前記算出した寸法差を前記第2配管サポート施工図に反映して、施工完了後の配管サポートの完成図を作成させるために、当該寸法差を前記図面編集装置に送信する処理と、
をさらに実行することを特徴とする請求項7に記載の編集支援装置。 In the second piping support construction drawing, the design dimensions of the piping support are described.
The processor is
It was read by the reader of the IC tag attached to the piping support and the actual dimension of the piping support measured by the position measuring device after the piping support described in the second piping support construction drawing. A process of receiving the identification information for support of the pipe support in association with the information;
A process of reading the design dimension of the pipe support corresponding to the received support identification information from the storage unit, and calculating a dimensional difference between the design dimension and the actual dimension of the received pipe support;
In order to reflect the calculated dimensional difference in the second piping support construction drawing and create a completed drawing of the piping support after completion of the construction, a process of transmitting the dimensional difference to the drawing editing device;
The editing support apparatus according to claim 7, further comprising:
前記処理部は、前記配管サポートの設計寸法と前記配管サポートの実寸法との寸法差を算出する場合、
前記読取器によって読み取られた前記サポート用識別情報と、前記読取器によって読み取られた前記金物用識別情報とを対応付けて受信するとともに、
前記受信した金物用識別情報および当該サポート用識別情報の対応関係と、前記記憶部に格納されている前記対応関係とを照合し、
前記照合の結果、双方の対応関係が一致したことを条件に前記寸法差を算出することを特徴とする請求項8に記載の編集支援装置。 In the storage unit, the correspondence between the pipe support and the embedded hardware described in the second piping support construction drawing is stored using the correspondence between the support identification information and the hardware identification information. ,
When the processing unit calculates the dimensional difference between the design dimension of the pipe support and the actual dimension of the pipe support,
Receiving the support identification information read by the reader in association with the hardware identification information read by the reader;
Collating the correspondence between the received hardware identification information and the support identification information with the correspondence stored in the storage unit;
9. The editing support apparatus according to claim 8, wherein the dimensional difference is calculated on the condition that the correspondence between both matches as a result of the collation.
前記照合の結果、双方の対応関係が不一致の場合、その旨の情報を前記読取器に送信することを特徴とする請求項9に記載の編集支援装置。 The processor is
The editing support apparatus according to claim 9, wherein, as a result of the collation, if both correspondences do not match, information to that effect is transmitted to the reader.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2005025860A JP4452190B2 (en) | 2005-02-02 | 2005-02-02 | Piping support construction drawing editing method, drawing editing system and editing support device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2005025860A JP4452190B2 (en) | 2005-02-02 | 2005-02-02 | Piping support construction drawing editing method, drawing editing system and editing support device |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2006214472A true JP2006214472A (en) | 2006-08-17 |
JP4452190B2 JP4452190B2 (en) | 2010-04-21 |
Family
ID=36977874
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2005025860A Expired - Fee Related JP4452190B2 (en) | 2005-02-02 | 2005-02-02 | Piping support construction drawing editing method, drawing editing system and editing support device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4452190B2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007167915A (en) * | 2005-12-22 | 2007-07-05 | Ohbayashi Corp | Welding control method, welding control system, steel frame structure, and ic tag |
JP2009053790A (en) * | 2007-08-24 | 2009-03-12 | Bug Inc | Reader/writer system, reader/writer, and server |
JP2009133082A (en) * | 2007-11-29 | 2009-06-18 | Hitachi Plant Technologies Ltd | Insert installation position collating method and insert installation position collating system |
JP2009211454A (en) * | 2008-03-05 | 2009-09-17 | Hitachi Ltd | Execution confirmation apparatus and design support system using it |
JP2010048581A (en) * | 2008-08-19 | 2010-03-04 | Hitachi Plant Technologies Ltd | Method and system for verifying installation position of metal insert |
KR101317850B1 (en) * | 2012-02-20 | 2013-10-15 | 제이씨이엔씨(주) | Optimal Determination of Pipe Support Types in Flare System |
JP2013540990A (en) * | 2010-08-27 | 2013-11-07 | ヒエロニミ、ベネディクト | High frequency transceiver detection system and method of using the same |
WO2016062985A1 (en) * | 2014-10-24 | 2016-04-28 | Endel | Method and system for custom-manufacturing pipe retainers |
WO2016062986A1 (en) * | 2014-10-24 | 2016-04-28 | Endel | Improved method and system for custom manufacturing pipe retainers |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05114012A (en) * | 1991-07-26 | 1993-05-07 | Hitachi Ltd | Device for supporting detailed design of piping supporting device |
JPH10293776A (en) * | 1997-04-21 | 1998-11-04 | Hitachi Plant Eng & Constr Co Ltd | Piping temporary set simulation device and piping manufacture method |
JP2000348085A (en) * | 1999-06-08 | 2000-12-15 | Ishikawajima Harima Heavy Ind Co Ltd | Method for creating piping support chart by cad |
JP2003182820A (en) * | 2001-12-12 | 2003-07-03 | Mitsubishi Electric Corp | Book and document file location automatic search device |
-
2005
- 2005-02-02 JP JP2005025860A patent/JP4452190B2/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05114012A (en) * | 1991-07-26 | 1993-05-07 | Hitachi Ltd | Device for supporting detailed design of piping supporting device |
JPH10293776A (en) * | 1997-04-21 | 1998-11-04 | Hitachi Plant Eng & Constr Co Ltd | Piping temporary set simulation device and piping manufacture method |
JP2000348085A (en) * | 1999-06-08 | 2000-12-15 | Ishikawajima Harima Heavy Ind Co Ltd | Method for creating piping support chart by cad |
JP2003182820A (en) * | 2001-12-12 | 2003-07-03 | Mitsubishi Electric Corp | Book and document file location automatic search device |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007167915A (en) * | 2005-12-22 | 2007-07-05 | Ohbayashi Corp | Welding control method, welding control system, steel frame structure, and ic tag |
JP2009053790A (en) * | 2007-08-24 | 2009-03-12 | Bug Inc | Reader/writer system, reader/writer, and server |
JP2009133082A (en) * | 2007-11-29 | 2009-06-18 | Hitachi Plant Technologies Ltd | Insert installation position collating method and insert installation position collating system |
US8718358B2 (en) | 2007-11-29 | 2014-05-06 | Hitachi, Ltd. | Filler metal installation position checking method and filler metal installation position checking system |
JP2009211454A (en) * | 2008-03-05 | 2009-09-17 | Hitachi Ltd | Execution confirmation apparatus and design support system using it |
JP2010048581A (en) * | 2008-08-19 | 2010-03-04 | Hitachi Plant Technologies Ltd | Method and system for verifying installation position of metal insert |
JP2013540990A (en) * | 2010-08-27 | 2013-11-07 | ヒエロニミ、ベネディクト | High frequency transceiver detection system and method of using the same |
KR101317850B1 (en) * | 2012-02-20 | 2013-10-15 | 제이씨이엔씨(주) | Optimal Determination of Pipe Support Types in Flare System |
WO2016062985A1 (en) * | 2014-10-24 | 2016-04-28 | Endel | Method and system for custom-manufacturing pipe retainers |
WO2016062986A1 (en) * | 2014-10-24 | 2016-04-28 | Endel | Improved method and system for custom manufacturing pipe retainers |
GB2547162A (en) * | 2014-10-24 | 2017-08-09 | Endel | Improved method and system for custom manufacturing pipe retainers |
GB2547384A (en) * | 2014-10-24 | 2017-08-16 | Endel | Method and system for custom-manufacturing pipe retainers |
Also Published As
Publication number | Publication date |
---|---|
JP4452190B2 (en) | 2010-04-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4452190B2 (en) | Piping support construction drawing editing method, drawing editing system and editing support device | |
JP6975568B2 (en) | Construction support method and construction support system | |
Li et al. | An Internet of Things-enabled BIM platform for on-site assembly services in prefabricated construction | |
Akanmu et al. | Scenarios for cyber-physical systems integration in construction | |
US20120066019A1 (en) | Construction control system | |
Bloomberg et al. | BIM guidelines | |
US8125340B2 (en) | Smartbeam visibility network | |
JP2008117039A (en) | Patrol assistance system, patrol assistance method, patrol assistance program and program recording medium | |
Motamedi et al. | Extending BIM to incorporate information of RFID tags attached to building assets | |
JP4747831B2 (en) | Welding management method, welding management system, steel structure, IC tag | |
JP4211584B2 (en) | Member building method, member building program, and recording medium recording the same | |
JP2005327170A (en) | Quality check system in construction site | |
JP2005322059A (en) | Precut building material management system, precut building material management method, package management device, package management method and package management program | |
JP5943824B2 (en) | Results registration management system for building equipment maintenance work | |
US11394609B2 (en) | Equipment deploying system and method thereof | |
US11488268B2 (en) | Authenticity verification of a digital model | |
Dervishaj et al. | Enabling reuse of prefabricated concrete components through multiple tracking technologies and digital twins | |
JP4564371B2 (en) | Sleeve construction support method and sleeve construction support device | |
KR101417933B1 (en) | An NFC mobilephone repair and reinforcement simulation system with GIS techniques | |
CA3016079A1 (en) | Automated three-dimensional location verification of construction items | |
JP4843249B2 (en) | Tag information management device and IC tag | |
JP4688730B2 (en) | Control panel maintenance system | |
Shi | Framework for integration of BIM and RFID in steel construction | |
US20220405672A1 (en) | System for management of facility construction and maintenance | |
JP4391174B2 (en) | Product management support system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070403 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20091001 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100126 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100129 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130205 Year of fee payment: 3 |
|
LAPS | Cancellation because of no payment of annual fees |