JP2006213501A - Implement for hanging of structure and hanging method of structure using the same - Google Patents

Implement for hanging of structure and hanging method of structure using the same Download PDF

Info

Publication number
JP2006213501A
JP2006213501A JP2005030179A JP2005030179A JP2006213501A JP 2006213501 A JP2006213501 A JP 2006213501A JP 2005030179 A JP2005030179 A JP 2005030179A JP 2005030179 A JP2005030179 A JP 2005030179A JP 2006213501 A JP2006213501 A JP 2006213501A
Authority
JP
Japan
Prior art keywords
lifting
wire rope
jig
hanging
suspension ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005030179A
Other languages
Japanese (ja)
Other versions
JP4703205B2 (en
Inventor
Koichi Jingu
幸一 神宮
Toshihiro Kitayama
俊弘 北山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Universal Shipbuilding Corp
Original Assignee
Universal Shipbuilding Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Universal Shipbuilding Corp filed Critical Universal Shipbuilding Corp
Priority to JP2005030179A priority Critical patent/JP4703205B2/en
Publication of JP2006213501A publication Critical patent/JP2006213501A/en
Application granted granted Critical
Publication of JP4703205B2 publication Critical patent/JP4703205B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a safety implement for hanging of a structure and a hanging method of the structure using with the same capable of reducing man-hour for hoisting, rotating, and raising the structure without interference of a wire rope with an obstacle provided on the structure. <P>SOLUTION: The implement 1 for hanging is composed of a body part 3 wherein a top part ring 4a and a lower part ring 4b are provided, and balances 5a, 5b which are fixed to both sides of the body part 3 and wherein receiving frames 6a, 6b are inclinably provided on the tip end part through a hinge part 8. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、構造物を吊上げる際に使用する吊上げ用治具及びこれを用いた構造物の吊上げ方法に関するものである。   The present invention relates to a lifting jig used for lifting a structure and a method for lifting a structure using the same.

図11(a)は従来の構造物の吊上げ方法の一例を示す説明図である。図において、30は吊上げる側面ほぼ凹状の構造物で、図には船体を分割した重量の大きい船体ブロックが示してある。
この構造物30の前部側31(上甲板)には、例えば配管群からなる障害物34が設けられているため、吊上げに際してワイヤロープが干渉すると、障害物34を損傷したり破壊したりするおそれがある。そのため保護部材により障害物34を保護するようにしていたが、その装着、取外しがきわめて面倒である。このようなことから、障害物34にワイヤロープが干渉しないようにした吊上げ方法が行われている。以下にこのような従来の構造物の吊上げ方法について説明する。
Fig.11 (a) is explanatory drawing which shows an example of the lifting method of the conventional structure. In the figure, reference numeral 30 denotes a structure having a substantially concave side surface to be lifted. In the figure, a heavy hull block obtained by dividing the hull is shown.
Since the front side 31 (upper deck) of the structure 30 is provided with an obstacle 34 made of, for example, a pipe group, if the wire rope interferes during lifting, the obstacle 34 is damaged or destroyed. There is a fear. For this reason, the obstacle 34 is protected by the protective member, but it is very troublesome to attach and remove it. For this reason, a lifting method in which the wire rope does not interfere with the obstacle 34 is performed. A conventional method for lifting such a structure will be described below.

図11(a)において、前部側31の下部の幅方向(図面の垂直方向)には所定の間隔で設けた複数の前部吊り環33aが設けられており、また障害物34の上方には幅方向に所定の間隔で複数の上部吊り環33c,33dがそれぞれ設けられている。また、後部側32(船底)の上部の幅方向には所定の間隔で複数の後部吊り環33bが設けられている。35は前部側31と後部側32との間に設けられた補強材、36は構造物30の重心位置を示す。なお、40は地上に設けられて構造物30が載置される盤木である。   In FIG. 11A, a plurality of front suspension rings 33 a provided at predetermined intervals are provided in the width direction (vertical direction in the drawing) of the lower portion of the front side 31, and above the obstacle 34. Are provided with a plurality of upper suspension rings 33c and 33d at predetermined intervals in the width direction. A plurality of rear suspension rings 33b are provided at predetermined intervals in the width direction of the upper portion of the rear side 32 (ship bottom). Reference numeral 35 denotes a reinforcing material provided between the front side 31 and the rear side 32, and 36 denotes the position of the center of gravity of the structure 30. Reference numeral 40 denotes a board provided on the ground on which the structure 30 is placed.

上記のような構造物30を吊上げるには、先ず、図11(a)に示すように、上部がイコライザー天秤を介してクレーンに設けた第1のウインチのドラム(いずれも図示せず)に巻かれたワイヤロープ37aの下端部を上部吊り環33c,33dにそれぞれ掛け、また、前部吊り環33aに一端がフリー状態にあるワイヤロープ37bの他端を掛ける。さらに、後部吊り環33bに、上部がイコライザー天秤を介してクレーンに設けた第2のウインチのドラムに巻かれたワイヤロープ37cの下端部を掛ける。
そして、第1、第2のウインチによりワイヤロープ37a,37cを若干巻上げて、構造物30を盤木40から浮かせて、ワイヤロープ37cを固定する。
In order to lift the structure 30 as described above, first, as shown in FIG. 11A, the upper part is attached to a drum of a first winch (not shown) provided on the crane via an equalizer balance. The lower end of the wound wire rope 37a is hung on the upper suspension rings 33c and 33d, respectively, and the other end of the wire rope 37b with one end in a free state is hung on the front suspension ring 33a. Furthermore, the lower part of the wire rope 37c wound around the drum of the second winch provided on the crane is hung on the rear suspension ring 33b via the equalizer balance.
Then, the wire ropes 37a and 37c are slightly wound up by the first and second winches, the structure 30 is lifted from the board 40, and the wire rope 37c is fixed.

次に、第1のウインチによりワイヤロープ37aを巻上げて、図11(b)に示すように構造物30の前部側31を引き上げ、構造物30を回転させて傾斜させ、ワイヤロープ37aを固定する。そして、構造物30の下に高所作業車38を移動し、ワイヤロープ37bの下端部を保持させる。
ついで、ワイヤロープ37cを後部吊り環33bから外してこれが巻かれたウインチを図の左方に移動させ、ワイヤロープ37cをワイヤロープ37bと接続して、高所作業車38を移動させる。
Next, the wire rope 37a is wound up by the first winch, the front side 31 of the structure 30 is pulled up as shown in FIG. 11B, the structure 30 is rotated and tilted, and the wire rope 37a is fixed. To do. And the aerial work vehicle 38 is moved under the structure 30, and the lower end part of the wire rope 37b is hold | maintained.
Next, the wire rope 37c is removed from the rear suspension ring 33b, the winch around which the wire rope 37c is wound is moved to the left in the figure, the wire rope 37c is connected to the wire rope 37b, and the aerial work vehicle 38 is moved.

そして、第2のウインチによりワイヤロープ37cを巻上げると共に、第1のウインチによりワイヤロープ37aを若干巻戻すことにより、図11(c)に示すように、構造物30を90°回転させて起立させる。これにより、構造物30の吊上げ、回転作業が終了する。なお、必要に応じてクレーンやウインチを操作して吊上げられた構造物30を所定の場所へ移動する(上記の構造物の吊上げ方法を従来技術という。なお、この従来技術が記載された刊行物はなかった)。   Then, the wire rope 37c is wound up by the second winch and the wire rope 37a is slightly rewound by the first winch, so that the structure 30 is rotated 90 ° as shown in FIG. Let Thereby, lifting of the structure 30 and rotation work are complete | finished. If necessary, the suspended structure 30 is moved to a predetermined place by operating a crane or a winch (the above-described method of lifting a structure is referred to as a conventional technique. In addition, a publication in which this conventional technique is described. There was no).

また、マスブロックの4か所にワイヤロープを掛けてクレーンで吊上げる際に、マスブロックとワイヤロープとの間に磁石を有するプロテクタを配置して、マスブロックとワイヤロープを保護するようにした技術が提案されている(例えば、特許文献1参照)。
実願昭58−51002号(実開昭59−156078号)のマイクロフイルム
In addition, a protector with magnets was placed between the mass block and the wire rope to protect the mass block and the wire rope when hanging the wire rope on four places of the mass block and lifting it with a crane. A technique has been proposed (see, for example, Patent Document 1).
Microfilm of Japanese Utility Model No. 58-50002 (Japanese Utility Model Publication No. 59-1556078)

従来技術においては、構造物30を吊上げる際に、保護部材で障害物34を保護する必要はないが、構造物30の吊上げ作業の途中でワイヤロープ37cを後部吊り環33bから外して、高所作業車38により前部吊り環33aに掛けたワイヤロープ37bと接続しなければならないため、きわめて面倒で作業工数が増加するばかりでなく、作業中に作業者が傾斜して吊上げた構造物30からワイヤロープ37cを外し、このワイヤロープ37cを高所作業車38上でワイヤロープ37bに接続しなければならないため、危険であった。   In the prior art, when the structure 30 is lifted, it is not necessary to protect the obstacle 34 with the protective member. However, the wire rope 37c is removed from the rear suspension ring 33b in the middle of lifting the structure 30, and Since it is necessary to connect to the wire rope 37b hung on the front suspension ring 33a by the work vehicle 38, the work 30 is not only very troublesome and increases the work man-hours, but also the structure 30 that the worker inclines and lifts during the work. It is dangerous because the wire rope 37c must be removed from the wire rope 37c and connected to the wire rope 37b on the aerial work vehicle 38.

また、特許文献1に記載の技術は、マスブロックを吊上げるだけで、吊上げ作業中にマスブロックを傾動させたり回転させたりすることができないので、上記の従来技術のような構造物の吊上げ作業に適用することはできない。   Moreover, since the technique described in Patent Document 1 simply lifts the mass block and cannot tilt or rotate the mass block during the lifting work, the lifting work of the structure as in the conventional technique described above. It cannot be applied to.

本発明は、上記の課題を解決するためになされたもので、構造物に設けた障害物にワイヤロープが干渉することがなく、構造物の吊上げ、回転、起立等の作業工数を低減することができ、その上安全な構造物の吊上げ用治具及びこの吊上げ用治具を用いた構造物の吊上げ方法を提供することを目的としたものである。   The present invention has been made to solve the above-described problems, and the wire rope does not interfere with an obstacle provided in the structure, and the number of work steps such as lifting, rotating, and standing up the structure is reduced. Further, it is an object of the present invention to provide a safe structure lifting jig and a structure lifting method using the lifting jig.

本発明に係る構造物の吊上げ用治具は、頂部吊り環及び下部吊り環が設けられた胴体部と、該胴体部の一方の側又は両側に固定され、先端部にヒンジ部を介して傾動可能に受け枠が設けられた天秤とを備えたものである。   A lifting tool for a structure according to the present invention is fixed to a body portion provided with a top suspension ring and a lower suspension ring, and one side or both sides of the body portion, and tilted to the front end portion via a hinge portion. And a balance provided with a receiving frame.

上記の胴体部に固定された天秤を、下方に10〜20°傾斜させた。
また、上記の吊上げ用治具を所定の間隔で2基並設し、これら2基の吊上げ用治具を複数の連結部材により一体に固定した。
The balance fixed to the body part was tilted downward by 10 to 20 °.
Further, two lifting jigs are arranged side by side at a predetermined interval, and these two lifting jigs are integrally fixed by a plurality of connecting members.

本発明に係る構造物の吊上げ方法は、上記の吊上げ用治具の胴体部の上部に第1の吊上げワイヤロープを取付けると共に、該胴体部の下部にワイヤロープを取付けて該ワイヤロープの先端部を構造物の前部側下部に掛止させて前記吊上げ用治具の受け枠を前記構造物の前部側に当接させ、また第2の吊上げワイヤロープを前記構造物の後部側上部に掛止させ、前記第1の吊上げワイヤロープを巻上げて前記構造物を起立させるようにしたものである。   In the method for lifting a structure according to the present invention, the first lifting wire rope is attached to the upper portion of the body portion of the lifting jig, and the wire rope is attached to the lower portion of the body portion so that the tip portion of the wire rope is attached. Is hung on the lower part on the front side of the structure, the receiving frame of the lifting jig is brought into contact with the front part side of the structure, and the second lifting wire rope is placed on the upper part on the rear side of the structure. The structure is erected by winding and winding the first lifting wire rope.

本発明によれば、構造物の吊上げにあたって吊上げ用治具を用いることによりワイヤロープが障害物に干渉することがないので、障害物に保護部材を設ける必要がない。また、従来技術のようにワイヤロープの接続替えをする必要がないので、作業工数を大幅に低減することができ、その上吊上げ作業中に作業者が構造物の周辺に立入ることもないので、安全である。   According to the present invention, since the wire rope does not interfere with the obstacle by using the lifting jig when lifting the structure, it is not necessary to provide a protection member on the obstacle. Moreover, since it is not necessary to change the wire rope connection as in the prior art, the work man-hours can be greatly reduced, and the operator does not enter the periphery of the structure during the lifting work. , Safe.

[実施の形態1]
図1は本発明の実施の形態1に係る構造物の吊上げ用治具の平面図、図2は図1の正面図、図3は一部の部材を付加した吊上げ用治具の正面図である。
鋼材からなる吊上げ用治具1において、2はほぼやじろべえのような形状の本体部で、胴体部3の上端部には頂部吊り環4aが設けられており、下端部には下部吊り環4bが設けられている。5a,5b(以下、単に5と記すことがある)は頂部吊り環4aの下方において、基部が胴体部3の両側に溶接等により互いに下方にθ1(例えば、θ1=10°〜20°)傾斜して取付けられた左右一対の天秤である。
[Embodiment 1]
1 is a plan view of a lifting jig for a structure according to Embodiment 1 of the present invention, FIG. 2 is a front view of FIG. 1, and FIG. 3 is a front view of a lifting jig with some members added thereto. is there.
In the lifting jig 1 made of a steel material, 2 is a main body portion having a shape almost like a head. A top suspension ring 4a is provided at the upper end portion of the body portion 3, and a lower suspension ring 4b is disposed at the lower end portion. Is provided. 5a and 5b (hereinafter may be simply referred to as 5) are located below the top suspension ring 4a, and the base portions are mutually below θ 1 (for example, θ 1 = 10 ° to 20 ° by welding or the like on both sides of the body portion 3). ) A pair of left and right balances mounted at an angle.

この天秤5a,5bには、ヒンジ腕7を有しヒンジ部8を介して天秤5a,5bと直交して装着された受け枠6a,6b(以下、単に6と記すことがある)が設けられており、この受け枠6a,6bはヒンジ部8により、図3に破線で示すように、所定の角度θ2(例えば、θ2=30°)で上部が内側(胴体部3側)に傾動できるようになっている。なお、胴体部3と受け枠6a,6b間の距離Lは、図11で示した障害物34の前部側31からの高さより長く形成されている。
9は胴体部3と天秤5a,5bとの間に設けられた補強板、10はヒンジ部8の近傍において天秤5a,5bの下面に設けられた補強板、11は受け枠6a,6bとヒンジ腕7との間に設けられた補強板で、補強板10と11との間には、受け枠6a,6bの傾動範囲を規制するストッパ12が設けられている。
The balances 5 a and 5 b are provided with receiving frames 6 a and 6 b (hereinafter simply referred to as 6) that have a hinge arm 7 and are mounted orthogonally to the balances 5 a and 5 b via a hinge portion 8. The receiving frames 6a and 6b are tilted inward (toward the body part 3) at a predetermined angle θ 2 (for example, θ 2 = 30 °) by the hinge part 8 as shown by a broken line in FIG. It can be done. In addition, the distance L between the trunk | drum 3 and receiving frame 6a, 6b is formed longer than the height from the front part side 31 of the obstruction 34 shown in FIG.
9 is a reinforcing plate provided between the body portion 3 and the balances 5a and 5b, 10 is a reinforcing plate provided on the lower surface of the balances 5a and 5b in the vicinity of the hinge portion 8, and 11 is a receiving frame 6a and 6b and a hinge. A stopper 12 that restricts the tilting range of the receiving frames 6 a and 6 b is provided between the reinforcing plates 10 and 11, which is a reinforcing plate provided between the arms 7.

上記のように構成した2基の本体部2は、図1に示すように、所定の間隔を隔てて複数の連結部材14により一体に固定されており、これにより本実施の形態に係る吊上げ用治具1が構成されている。   As shown in FIG. 1, the two main body portions 2 configured as described above are integrally fixed by a plurality of connecting members 14 at a predetermined interval, whereby the lifting body according to the present embodiment is used. A jig 1 is configured.

13aは頂部吊り環4aに回動可能に取付けられた頂部シャックル、13bは下部吊り環4bに回動可能に取付けられた下部シャックルである。
20はワイヤロープで、両端部には上部玉掛けロープ21a、下部玉掛けロープ21bが設けられており、上部玉掛けロープ21aは吊上げ用治具1の下部シャックル13bに着脱可能に取付けられ、下部玉掛けロープ21bには玉掛けシャックル22が取付けられている。23は第1の吊上げワイヤロープで、その一端に設けた頂部玉掛けロープ24(図4参照)が頂部シャックル13aに着脱可能に取付けられ、他端は後述のイコライザー天秤に取付けられている。
Reference numeral 13a denotes a top shackle that is rotatably attached to the top suspension ring 4a, and 13b is a lower shackle that is rotatably attached to the lower suspension ring 4b.
Reference numeral 20 denotes a wire rope, which is provided with an upper sling rope 21a and a lower sling rope 21b at both ends. A sling shackle 22 is attached to the. Reference numeral 23 denotes a first lifting wire rope. A top sling rope 24 (see FIG. 4) provided at one end thereof is detachably attached to the top shackle 13a, and the other end is attached to an equalizer balance described later.

次に、上記のように構成した吊上げ用治具1を用いて構造物1を吊上げる作業の一例を図4〜図6により説明する。なお、図11で説明した従来技術と同じ部分にはこれと同じ符号を付し、説明を省略する。
本実施の形態においては、図11の構造物30の前部側31に設けた上部吊り環33c,33dは設けられていない。また、図5は構造物30の前部側31の正面図で、吊上げ用治具1に連結された第1の吊上げワイヤロープ23の他端はそれぞれイコライザー天秤25に取付けられており、イコライザー天秤25は、クレーンに設けた第1のウインチのドラムに巻かれたワイヤロープに連結されている。
Next, an example of the operation | work which lifts the structure 1 using the lifting jig | tool 1 comprised as mentioned above is demonstrated with reference to FIGS. In addition, the same code | symbol is attached | subjected to the same part as the prior art demonstrated in FIG. 11, and description is abbreviate | omitted.
In the present embodiment, the upper suspension rings 33c and 33d provided on the front side 31 of the structure 30 in FIG. 11 are not provided. FIG. 5 is a front view of the front side 31 of the structure 30, and the other ends of the first lifting wire ropes 23 connected to the lifting jig 1 are respectively attached to an equalizer balance 25. 25 is connected to a wire rope wound around a drum of a first winch provided in the crane.

先ず、図4(a)に示すように、第1のウインチにより第1の吊上げワイヤロープ23を巻戻して、これに取付けた吊上げ用治具1を障害物34の下まで下降させる。このとき、ワイヤロープ20に設けた玉掛けシャックル22は、前部吊り環33aの近傍に位置する。そして、図4(b)に示すように、玉掛けシャックル22を前部吊り環33aに掛止させると、吊上げ用治具1の受け枠6bが構造物30の前部側31に当接する。
また、図6(a)に示すように、イコライザー天秤(図示せず)を介して第2のウインチのドラムに巻かれた第2の吊上げワイヤロープ26の下端部を、構造物30の後部側32に設けた後部吊り環33bに掛止させる。
First, as shown in FIG. 4A, the first lifting wire rope 23 is rewound by the first winch, and the lifting jig 1 attached thereto is lowered below the obstacle 34. At this time, the sling shackle 22 provided on the wire rope 20 is located in the vicinity of the front suspension ring 33a. Then, as shown in FIG. 4B, when the slinging shackle 22 is hooked on the front suspension ring 33 a, the receiving frame 6 b of the lifting jig 1 comes into contact with the front portion 31 of the structure 30.
6A, the lower end portion of the second lifting wire rope 26 wound around the drum of the second winch via an equalizer balance (not shown) is connected to the rear side of the structure 30. The rear suspension ring 33b provided on the second suspension ring 33 is hooked.

このとき、吊上げ用治具1の受け枠6a,6bはヒンジ8により傾動できるようになっているので、構造物30の前部側に確実に当接する。また、吊上げ用治具1の天秤5a,5bと受け枠6a,6bの長さLは、障害物34の高さより長いので、第1の吊上げワイヤロープ23が障害物34に干渉することはない。   At this time, since the receiving frames 6 a and 6 b of the lifting jig 1 can be tilted by the hinge 8, they are surely brought into contact with the front side of the structure 30. Further, since the length L of the balances 5a and 5b and the receiving frames 6a and 6b of the lifting jig 1 is longer than the height of the obstacle 34, the first lifting wire rope 23 does not interfere with the obstacle 34. .

次に、図6(a)に示すように、第1、第2のウインチにより第1、第2の吊上げワイヤロープ23,26を若干巻上げて、構造物30を盤木40から浮かせる。
ついで、図6(b)に示すように、後部側32の第2の吊上げワイヤロープ26を固定し、前部側31の第1の吊上げワイヤロープ23を第1のウインチで巻上げ、構造物30の前部側31を吊上げて傾斜(回転)させる。
Next, as shown in FIG. 6A, the first and second lifting wire ropes 23 and 26 are slightly wound up by the first and second winches, and the structure 30 is floated from the board 40.
Next, as shown in FIG. 6B, the second lifting wire rope 26 on the rear side 32 is fixed, and the first lifting wire rope 23 on the front side 31 is wound up by the first winch, and the structure 30 The front side 31 is lifted and inclined (rotated).

吊上げの当初においては、構造物30が傾斜しても、吊上げ用治具1に荷重による負荷が作用するため、受け枠6bの面が構造物30の前部側31にバランスよく均等に当接する。また、天秤5bは下方にθ1°傾斜しているので、天秤5bの基部に作用する玉掛けワイヤロープ24による曲げ応力を低減することができる。
構造物30を吊上げて傾斜すると、吊上げ用治具1は構造物30から徐々に離れ、最終的には、ワイヤロープ20と第2の吊上げワイヤロープ23は一直線になる。
At the beginning of lifting, even if the structure 30 is inclined, a load due to the load acts on the lifting jig 1, so that the surface of the receiving frame 6 b comes into contact with the front side 31 of the structure 30 evenly in a balanced manner. . Further, since the balance 5b is inclined downward by θ 1 °, the bending stress due to the sling wire rope 24 acting on the base of the balance 5b can be reduced.
When the structure 30 is lifted and inclined, the lifting jig 1 is gradually separated from the structure 30, and finally, the wire rope 20 and the second lifting wire rope 23 are in a straight line.

引続き第1の吊上げワイヤロープ23を巻上げると、図6(c)に示すように、構造物30は90°回転して起立する。このとき、第2の吊上げワイヤロープ26は構造物30の上端部(図の右側)に摺接する。これにより、構造物30の吊上げ(回転)作業が終了する。なお、必要に応じて、クレーンやウインチを操作することにより、構造物30を所望の位置に移動させることができる。   When the first lifting wire rope 23 is continuously wound up, as shown in FIG. 6 (c), the structure 30 is rotated 90 degrees to stand. At this time, the second lifting wire rope 26 comes into sliding contact with the upper end portion (right side in the drawing) of the structure 30. Thereby, the lifting (rotation) work of the structure 30 is completed. In addition, the structure 30 can be moved to a desired position by operating a crane and a winch as needed.

上記のように、本実施の形態によれば、構造物30の吊上げにあたって吊上げ用治具1を用いることにより、ワイヤロープが障害物34に干渉することがないので、障害物34に保護部材を設ける必要がない。また、従来技術のように構造物30に上部吊り環33c,33dを設ける必要がないので、コストを低減できる。
さらに、従来技術のようにワイヤロープの接続替えをする必要がないので作業工数を大幅に低減することができるばかりでなく、吊上げ作業の周辺に作業者が立入ることもないので、きわめて安全である。
As described above, according to the present embodiment, since the wire rope does not interfere with the obstacle 34 by using the lifting jig 1 when lifting the structure 30, the protection member is attached to the obstacle 34. There is no need to provide it. Moreover, since it is not necessary to provide the upper suspension rings 33c and 33d in the structure 30 unlike the prior art, the cost can be reduced.
In addition, since it is not necessary to change the wire rope connection as in the prior art, not only can the work man-hours be greatly reduced, but the operator does not enter the vicinity of the lifting work, which is extremely safe. is there.

[実施の形態2]
図7は本発明の実施の形態2に係る構造物の吊上げ用治具の正面図である。なお、実施の形態1と同じ部分にはこれと同じ符号を付し、説明を省略する。
実施の形態1においては、吊上げ用治具1の本体部2の胴体部3の両側に、先端部に受け枠6a,6bを有する天秤5a,5bを設けた場合を示したが、本実施の形態は、胴体部3の左右いずれか一方の側にのみ、先端部に受け枠6を有する天秤5を設けたものである。
本実施の形態においても、実施の形態1の場合とほぼ同様の作用、効果を得ることができる。
[Embodiment 2]
FIG. 7 is a front view of a lifting tool for a structure according to Embodiment 2 of the present invention. The same parts as those in the first embodiment are denoted by the same reference numerals, and description thereof is omitted.
In Embodiment 1, although the case where the balances 5a and 5b which have the receiving frames 6a and 6b in the front-end | tip part were provided in the both sides of the trunk | drum 3 of the main-body part 2 of the lifting jig | tool 1 was shown, In the form, a balance 5 having a receiving frame 6 at the tip is provided only on either the left or right side of the body portion 3.
Also in the present embodiment, substantially the same operations and effects as in the case of the first embodiment can be obtained.

[実施の形態3]
実施の形態1においては、2基の本体部2を連結部材14で一体に固定して吊上げ用治具1を構成した場合を示したが、本実施の形態においては、1基の本体部2により吊上げ用治具1を構成したものである。
本実施の形態によれば、比較的軽量の構造物の吊上げや回転に実施することができる。
[Embodiment 3]
In the first embodiment, the case where the lifting jig 1 is configured by integrally fixing the two main body portions 2 with the connecting member 14 is shown. However, in the present embodiment, one main body portion 2 is provided. Thus, the lifting jig 1 is constructed.
According to this embodiment, it can be carried out for lifting and rotation of a relatively lightweight structure.

図8〜図10は本発明に係る吊上げ用治具の他の使用例を示すものである。
図8は上部に突起部34aを有する構造物30aを、本発明に係る吊上げ用治具1を使用し、吊上げて回転させる場合を示すもので、その手順、効果は実施の形態1の場合とほぼ同様である。
8 to 10 show other examples of use of the lifting jig according to the present invention.
FIG. 8 shows a case where the structure 30a having the protrusion 34a on the upper part is lifted and rotated by using the lifting jig 1 according to the present invention, and the procedure and effects thereof are the same as those in the first embodiment. It is almost the same.

図9は浮体構造物45を曳航する場合に、本発明に係る吊上げ用治具1を利用したものである。曳航にあたっては、浮体構造物45の上面に設けた吊り環46に吊上げ用治具1に連結したワイヤロープ20の玉掛けシャックル22を掛止させると共に、吊上げ用治具1の受け枠6を上面に当接し、吊上げ用治具1に連結した第1の吊上げワイヤロープ23を曳船に連結して曳航するようにしたものである。なお、この場合、吊上げ用治具1の受け枠6のヒンジ8を固定しておくことが望ましい。   FIG. 9 uses the lifting jig 1 according to the present invention when towing the floating structure 45. In towing, the sling shackle 22 of the wire rope 20 connected to the lifting jig 1 is hooked on a suspension ring 46 provided on the upper surface of the floating structure 45, and the receiving frame 6 of the lifting jig 1 is placed on the upper surface. The first lifting wire rope 23 abutting and connected to the lifting jig 1 is connected to the tugboat and towed. In this case, it is desirable to fix the hinge 8 of the receiving frame 6 of the lifting jig 1 in advance.

図10はブロック状の構造物47を吊上げる際に、本発明に係る吊上げ用治具1を利用したもので、吊上げ用治具1に連結したワイヤロープ20の玉掛けシャックル22を構造物47の上面に設けた吊り環48に掛止させ、吊上げ用治具1に連結した第1の吊上げワイヤロープ23をウインチにより巻上げて構造物47を吊上げるようにしたものである。このように、本発明に係る吊上げ用治具1は、障害物がない構造物47を単に吊上げるだけの場合にも利用することができる。   FIG. 10 uses the lifting jig 1 according to the present invention when lifting the block-shaped structure 47, and the slinging shackle 22 of the wire rope 20 connected to the lifting jig 1 is attached to the structure 47. The structure 47 is lifted by a winch which is hooked on a lifting ring 48 provided on the upper surface and wound by a winch on the first lifting wire rope 23 connected to the lifting jig 1. Thus, the lifting jig 1 according to the present invention can also be used when the structure 47 without an obstacle is simply lifted.

本発明の実施の形態1に係る構造物の吊上げ用治具の平面図である。It is a top view of the jig | tool for lifting of the structure based on Embodiment 1 of this invention. 図1の正面図である。It is a front view of FIG. 図2の吊上げ用治具に一部の部材を付加した状態を示す正面図である。It is a front view which shows the state which added some members to the jig | tool for lifting of FIG. 実施の形態1に係る吊上げ用治具を用いた構造物の吊上げ方法の説明図である。It is explanatory drawing of the lifting method of the structure using the lifting jig | tool which concerns on Embodiment 1. FIG. 実施の形態1に係る吊上げ用治具を用いた構造物の吊上げ方法の説明図である。It is explanatory drawing of the lifting method of the structure using the lifting jig | tool which concerns on Embodiment 1. FIG. 実施の形態1に係る吊上げ用治具を用いた構造物の吊上げ方法の説明図である。It is explanatory drawing of the lifting method of the structure using the lifting jig | tool which concerns on Embodiment 1. FIG. 本発明の実施の形態2に係る一部の部材を付加した構造物の吊上げ用治具の正面図である。It is a front view of the jig | tool for lifting of the structure which added the one part member which concerns on Embodiment 2 of this invention. 本発明に係る吊上げ用治具の他の使用例の説明図である。It is explanatory drawing of the other usage example of the lifting jig | tool which concerns on this invention. 本発明に係る吊上げ用治具の他の使用例の説明図である。It is explanatory drawing of the other usage example of the lifting jig | tool which concerns on this invention. 本発明に係る吊上げ用治具の他の使用例の説明図である。It is explanatory drawing of the other usage example of the lifting jig | tool which concerns on this invention. 従来の構造物の吊上げ方法の一例を示す説明図である。It is explanatory drawing which shows an example of the conventional lifting method of a structure.

符号の説明Explanation of symbols

1 吊上げ用治具、2 本体部、3 胴体部、4a 頂部吊り環、4b 下部吊り環、5a,5b 天秤、6a,6b 受け枠、8 ヒンジ部、14 連結部材、20 ワイヤロープ、22 玉掛けシャックル、23 第1の吊上げワイヤロープ、26 第2の吊上げワイヤロープ、30 構造物、33a 前部吊り環、33b 後部吊り環、34 障害物。
DESCRIPTION OF SYMBOLS 1 Lifting jig, 2 Main body part, 3 Body part, 4a Top part hanging ring, 4b Bottom hanging ring, 5a, 5b Balance, 6a, 6b Receiving frame, 8 Hinge part, 14 Connecting member, 20 Wire rope, 22 sling shackle , 23 first lifting wire rope, 26 second lifting wire rope, 30 structure, 33a front suspension ring, 33b rear suspension ring, 34 obstacle.

Claims (4)

頂部吊り環及び下部吊り環が設けられた胴体部と、該胴体部の一方の側又は両側に固定され、先端部にヒンジ部を介して傾動可能に受け枠が設けられた天秤とを備えたことを特徴とする構造物の吊上げ用治具。   A body portion provided with a top suspension ring and a lower suspension ring, and a balance fixed to one side or both sides of the body portion and provided with a receiving frame at a tip end thereof so as to be tiltable via a hinge portion. A lifting tool for a structure characterized by the above. 前記胴体部に固定された天秤を、下方に10〜20°傾斜させたことを特徴とする請求項1記載の構造物の吊上げ用治具。   The lifting jig for a structure according to claim 1, wherein the balance fixed to the body part is inclined downward by 10 to 20 °. 前記吊上げ用治具を所定の間隔で2基並設し、これら2基の吊上げ用治具を複数の連結部材により一体に固定したことを特徴とする請求項1〜3のいずれかに記載の構造物の吊上げ用治具。   The two lifting jigs are arranged side by side at a predetermined interval, and the two lifting jigs are integrally fixed by a plurality of connecting members. Jig for lifting structures. 請求項1〜3のいずれかの吊上げ用治具の胴体部の上部に第1の吊上げワイヤロープを取付けると共に、該胴体部の下部にワイヤロープを取付けて該ワイヤロープの先端部を構造物の前部側下部に掛止させて前記吊上げ用治具の受け枠を前記構造物の前部側に当接させ、また第2の吊上げワイヤロープを前記構造物の後部側上部に掛止させ、前記第1の吊上げワイヤロープを巻上げて前記構造物を起立させることを特徴とする構造物の吊上げ方法。
The first lifting wire rope is attached to the upper portion of the trunk portion of the lifting jig according to any one of claims 1 to 3, and the wire rope is attached to the lower portion of the trunk portion so that the tip of the wire rope is attached to the structure. Hang on the lower part on the front side, the receiving frame of the lifting jig is brought into contact with the front side of the structure, and the second lifting wire rope is hooked on the upper part on the rear side of the structure, A method for lifting a structure, wherein the structure is erected by winding up the first lifting wire rope.
JP2005030179A 2005-02-07 2005-02-07 Structure lifting jig and structure lifting method using the same Expired - Fee Related JP4703205B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005030179A JP4703205B2 (en) 2005-02-07 2005-02-07 Structure lifting jig and structure lifting method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005030179A JP4703205B2 (en) 2005-02-07 2005-02-07 Structure lifting jig and structure lifting method using the same

Publications (2)

Publication Number Publication Date
JP2006213501A true JP2006213501A (en) 2006-08-17
JP4703205B2 JP4703205B2 (en) 2011-06-15

Family

ID=36977045

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005030179A Expired - Fee Related JP4703205B2 (en) 2005-02-07 2005-02-07 Structure lifting jig and structure lifting method using the same

Country Status (1)

Country Link
JP (1) JP4703205B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103086258A (en) * 2013-01-28 2013-05-08 安徽同盛环件股份有限公司 Ring discharging hanger
CN104627816A (en) * 2015-01-27 2015-05-20 安徽同盛环件股份有限公司 Large-size annular piece hoisting frame convenient to hoist

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54102027A (en) * 1978-01-27 1979-08-11 Taisei Corp Method of inverting solid concrete member
JPS58120170U (en) * 1982-02-12 1983-08-16 川崎製鉄株式会社 Ring member reversing device
JPS6311483U (en) * 1986-07-04 1988-01-25
JPS6388610U (en) * 1986-11-26 1988-06-09
JPH0475884U (en) * 1990-11-09 1992-07-02

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54102027A (en) * 1978-01-27 1979-08-11 Taisei Corp Method of inverting solid concrete member
JPS58120170U (en) * 1982-02-12 1983-08-16 川崎製鉄株式会社 Ring member reversing device
JPS6311483U (en) * 1986-07-04 1988-01-25
JPS6388610U (en) * 1986-11-26 1988-06-09
JPH0475884U (en) * 1990-11-09 1992-07-02

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103086258A (en) * 2013-01-28 2013-05-08 安徽同盛环件股份有限公司 Ring discharging hanger
CN104627816A (en) * 2015-01-27 2015-05-20 安徽同盛环件股份有限公司 Large-size annular piece hoisting frame convenient to hoist

Also Published As

Publication number Publication date
JP4703205B2 (en) 2011-06-15

Similar Documents

Publication Publication Date Title
JP2017538881A (en) Pile appending system
CN108149928B (en) Tower end installation method of stay cable
CN100400410C (en) Crane
JP3258493B2 (en) Anti-vibration device for suspended load using ship&#39;s up-down type frame
JP4703205B2 (en) Structure lifting jig and structure lifting method using the same
JP4881523B2 (en) Hook structure for lifting crane equipment
JP6098453B2 (en) Jib hanger
JP6396256B2 (en) Jib crane
JP5374915B2 (en) Crane weight structure
WO2015152235A1 (en) Method for manufacturing crane and system for mounting superstructure of crane
JP3297292B2 (en) Elevating type portal crane device with suspension mechanism for hanging load
JPH0778332B2 (en) Boat lifting device
JP6984395B2 (en) Crane and crane assembly method
JP2017154838A (en) crane
JP6393954B2 (en) Crane overhead structure system and crane manufacturing method
JP2003312987A (en) Floating crane
JPS6348798B2 (en)
EP3453670B1 (en) Crane
CN219990902U (en) Lifting appliance for realizing beam plate installation construction by transferring overhead lifting point of crane
GB2226539A (en) Improvements in load handling
JP7468499B2 (en) Sieve device
JP7293921B2 (en) Pin anti-rotation structure
JPS6322922A (en) Multipurpose working ship
JP2007099402A (en) Sling unit for lengthy material
JP3436360B2 (en) Quay crane

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071203

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100908

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101019

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101217

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110301

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110308

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140318

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees