Prior art keywords
transport
conveyance
destination
branch
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005005319A
Other languages
Japanese (ja)
Other versions
JP4264831B2 (en
Inventor
Katsuharu Onishi
克治 大西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daifuku Co Ltd
Original Assignee
Daifuku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daifuku Co Ltd filed Critical Daifuku Co Ltd
Priority to JP2005005319A priority Critical patent/JP4264831B2/en
Publication of JP2006193254A publication Critical patent/JP2006193254A/en
Application granted granted Critical
Publication of JP4264831B2 publication Critical patent/JP4264831B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Discharge Of Articles From Conveyors (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide conveying equipment capable of continuing conveying work even in the condition wherein one spot among a plurality of conveying spots become impossible to do conveying work. <P>SOLUTION: This conveying equipment is provided with a control means for controlling operation of a conveying means so that a conveyed material is conveyed to the conveying spot corresponding to a conveyance destination on the basis of conveyance destination information, which instructs one conveying spot corresponding to the conveyance destination of each of the conveyed material among the plurality of conveying spots, and so that the conveyed material, of which conveyance destination is the conveying spot impossible to do conveying work, is conveyed to a substitute conveyance destination, to which the conveyed material can be conveyed, on the basis of monitor information of a conveyance trouble monitor means. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、供給部から供給される搬送物を複数の搬送箇所に分岐搬送するように構成された搬送手段と、各搬送物の搬送先が前記複数の搬送箇所のうちのどれであるかを示す搬送先情報に基づいて、搬送物を搬送先に対応する搬送箇所に搬送するように前記搬送手段の作動を制御する制御手段とが設けられた搬送設備に関する。   The present invention relates to a conveying means configured to branch and convey a conveyed product supplied from a supply unit to a plurality of conveying locations, and to which of the plurality of conveying locations a conveyance destination of each conveyed item is The present invention relates to a transport facility provided with control means for controlling the operation of the transport means so as to transport a transported object to a transport location corresponding to the transport destination based on transport destination information shown.

かかる搬送設備は、例えば、搬送物を複数の収納棚に搬入したり、収納棚からの搬送物を外部に搬出するのに用いられるものであって、供給部に供給された搬送物を収納棚に搬入する場合では、供給部に供給された搬送物を、その搬送物を収納する収納棚に対応する搬送箇所に分岐搬送させ、また、収納棚から取り出されて供給部に供給された搬送物を外部に搬出する場合では、供給部に供給された搬送物を、その搬送物を外部に搬出させる搬送手段に対応する搬送箇所に分岐搬送させるようにして用いられるものである。
このような搬送設備として、搬送先情報を記憶する情報記憶用タグが各搬送物に設けられ、搬送物における情報記憶用タグに記憶された搬送先情報を読み取る読み取り手段が搬送手段における搬送物を分岐させる分岐箇所の夫々に対応して設けられ、制御手段が、読み取り手段にて読み取られた搬送先情報に基づいて、搬送先情報が読み取られた搬送物を搬送先に対応する搬送箇所に向けて分岐搬送するように構成されているものがあった(例えば、特許文献1参照。)。
Such a transport facility is used, for example, to transport a transported object to a plurality of storage shelves or to transport a transported object from the storage shelves to the outside. In the case of carrying in, the transported material supplied to the supply unit is branched and transported to a transport location corresponding to the storage shelf for storing the transported product, and the transported product taken out from the storage shelf and supplied to the supply unit In the case of unloading to the outside, the conveyed product supplied to the supply unit is used to be branched and conveyed to a conveyance location corresponding to a conveying means for carrying the conveyed product to the outside.
As such a transport facility, an information storage tag for storing transport destination information is provided for each transport object, and reading means for reading the transport destination information stored in the information storage tag in the transport object is used to transfer the transport object in the transport means. Based on the transport destination information read by the reading means, the control means directs the transported object whose transport destination information is read to the transport position corresponding to the transport destination. There are some which are configured to be branched and conveyed (for example, see Patent Document 1).

特開2000−255716号公報JP 2000-255716 A

上記のような搬送設備において、搬送手段の搬送経路中における一部が故障により停止した場合や、複数の搬送箇所のうちの一部の搬送箇所が、搬送されてきた搬送物の搬出が適正通り行われないことにより搬送物の満杯状態となった場合等に起因して、複数の搬送箇所のうちの一部が供給部からの搬送物を搬送不能な搬送箇所となることがあり、このような場合には、供給部に供給された搬送物を搬送箇所に向けて搬送せずに供給部で停止させるようにする、又は、搬送物を搬送箇所に向けて搬送して搬送経路中における故障した箇所の搬送上手側で停止させるようにする等、搬送物の搬送を停止させるべく制御手段にて搬送手段の作動を制御することになる。しかしながら、このように複数の搬送箇所のうちの一部が搬送物を搬送不能な搬送箇所となった場合に搬送物の搬送を停止させるようにすると、搬送手段の修理や搬送箇所から搬送物が搬出される等の修復処理が行われるまで、搬送可能な搬送箇所に対する搬送物の搬送をも停止するものとなってしまうものであった。   In the above transport equipment, when a part of the transport route of the transport means stops due to a failure, or when a part of the plurality of transport points is transported, the transported material that has been transported is properly delivered. Due to not being performed, a part of the plurality of transport points may become a transport part that cannot transport the transported object from the supply unit due to a case where the transported object becomes full, etc. In such a case, the transported object supplied to the supply unit should not be transported toward the transport point and stopped at the supply unit, or the transported object may be transported toward the transport point and broken in the transport path. The operation of the transport means is controlled by the control means so as to stop the transport of the transported object, such as stopping at the upper transport side of the spot. However, when the conveyance of the conveyed product is stopped when a part of the plurality of conveyance locations becomes a conveyance location where the conveyed product cannot be conveyed in this way, the conveyance item is repaired from the conveyance means or the conveyance item is removed from the conveyance location. Until the restoration process such as unloading is performed, the conveyance of the conveyed object to the conveyance position where the conveyance is possible is also stopped.

本発明は、上記実状に鑑みて為されたものであって、その目的は、複数の搬送箇所のうちの一部の搬送箇所が搬送不能な状態となっても、搬送作業を継続することができる搬送設備を提供する点にある。   The present invention has been made in view of the above situation, and the purpose thereof is to continue the transport work even if some of the plurality of transport locations are in a state in which they cannot be transported. It is in the point which provides the conveyance equipment which can be done.

この目的を達成するために、本発明にかかる搬送設備の第1特徴構成は、供給部から供給される搬送物を複数の搬送箇所に分岐搬送するように構成された搬送手段と、各搬送物の搬送先が前記複数の搬送箇所のうちのどれであるかを示す搬送先情報に基づいて、搬送物を搬送先に対応する搬送箇所に搬送するように前記搬送手段の作動を制御する制御手段とが設けられた搬送設備において、
前記搬送手段の搬送経路における搬送状況を監視して、複数の搬送箇所のうちで前記供給部からの搬送物を搬送不能な搬送箇所を管理する搬送トラブル監視手段が設けられ、前記制御手段が、前記搬送トラブル監視手段の監視情報に基づいて、搬送先が搬送不能な搬送箇所である搬送物については、搬送可能な搬送箇所を代替え搬送先に設定して搬送するように構成されている点にある。
In order to achieve this object, the first characteristic configuration of the transport facility according to the present invention includes a transport unit configured to branch and transport a transport object supplied from a supply unit to a plurality of transport points, and each transport object. Control means for controlling the operation of the transport means to transport the transported object to the transport location corresponding to the transport destination based on the transport destination information indicating which of the plurality of transport locations is the transport destination In the transfer facility provided with
A conveyance trouble monitoring unit is provided for monitoring a conveyance state in the conveyance path of the conveyance unit, and managing a conveyance point where the conveyance object from the supply unit cannot be conveyed among a plurality of conveyance points, and the control unit includes: Based on the monitoring information of the transport trouble monitoring means, the transport destination is a transport location that cannot be transported, and is configured to be transported by setting the transportable transport location as an alternative transport destination. is there.

すなわち、搬送トラブル監視手段にて、搬送手段の搬送経路における搬送状況を監視して複数の搬送箇所のうちで供給部からの搬送物を搬送不能な搬送箇所を管理し、この搬送トラブル監視手段の監視情報と搬送先情報とに基づいて、搬送先に対応する搬送箇所が搬送可能な搬送箇所である搬送物については、搬送先に対応する搬送箇所に搬送し、搬送先に対応する搬送箇所が搬送不能な搬送箇所である搬送物については、搬送先に対応する搬送箇所とは別の代替え搬送先に対応する搬送可能な搬送箇所に搬送するように構成されている。ちなみに、この代替え搬送先は、供給部からの搬送物を搬送可能な搬送箇所であることは勿論である。   That is, the conveyance trouble monitoring means monitors the conveyance status in the conveyance path of the conveyance means and manages the conveyance places where the conveyance object from the supply unit cannot be conveyed among the plurality of conveyance places. Based on the monitoring information and the transport destination information, the transport object corresponding to the transport destination is transported to the transport point corresponding to the transport destination, and the transport point corresponding to the transport destination is About the conveyed product which is a conveyance location which cannot be conveyed, it is comprised so that it may convey to the conveyance location which can be conveyed corresponding to an alternative conveyance destination different from the conveyance location corresponding to a conveyance destination. Incidentally, it is needless to say that this alternative transport destination is a transport location where the transported material from the supply unit can be transported.

従って、複数の搬送箇所のうちの一部が供給部からの搬送物を搬送不能な搬送箇所となった場合でも、搬送先が搬送不能な搬送箇所である搬送物については代替え搬送先に対応する搬送可能な搬送箇所に搬送して、搬送可能な搬送箇所に対する搬送物の搬送を停止させないものであり、もって、複数の搬送箇所のうちの一部の搬送箇所が搬送不能な状態となっても、搬送作業を継続することができる搬送設備を提供することができるに至った。   Therefore, even when a part of the plurality of conveyance points becomes a conveyance point where the conveyance object from the supply unit cannot be conveyed, the conveyance object whose conveyance destination is the conveyance point where the conveyance is impossible corresponds to the alternative conveyance destination. It is intended to be transported to a transportable transport location and does not stop the transport of the transported object to the transportable transport location, and even if some of the transport locations cannot be transported. It has become possible to provide a transport facility that can continue the transport work.

本発明にかかる搬送設備の第2特徴構成は、第1特徴構成において、前記搬送先情報を記憶する情報記憶用タグが各搬送物に設けられ、前記情報記憶用タグに前記搬送先情報を記憶させる書き込み手段が前記供給部に対応して設けられ、搬送物における前記情報記憶用タグに記憶された前記搬送先情報を読み取る読み取り手段が前記搬送手段における搬送物を分岐させる分岐箇所の夫々に対応して設けられ、前記制御手段が、前記読み取り手段にて読み取られた前記搬送先情報並びに前記搬送トラブル監視手段の前記監視情報に基づいて、前記搬送先情報が読み取られた搬送物を搬送先に対応する搬送箇所に向けて分岐搬送し、且つ、搬送先が搬送不能な搬送箇所である搬送物については代替え搬送先に対応する搬送箇所に向けて分岐搬送するように構成されている点にある。   A second feature configuration of the transport facility according to the present invention is the first feature configuration, wherein an information storage tag for storing the transport destination information is provided in each transport object, and the transport destination information is stored in the information storage tag. A writing means is provided corresponding to the supply unit, and a reading means for reading the transport destination information stored in the information storage tag in the transported object corresponds to each of the branch points where the transported object in the transport means branches. And the control means sets the transported object whose transport destination information is read as a transport destination based on the transport destination information read by the reading means and the monitoring information of the transport trouble monitoring means. Branched and transported to the corresponding transport location, and for transported items whose transport destination cannot be transported, branch and transport to the transport location corresponding to the alternative transport destination In that it is configured to.

すなわち、供給部に搬送物が供給された際に、書き込み手段にて搬送物に設けられた情報用記憶用タグに搬送先情報を記憶させておき、その搬送物が搬送手段における搬送物を分岐させる分岐箇所に搬送されると、その分岐箇所に搬送されてくる搬送物の情報記憶用タグに記憶されている搬送先情報を読み取り手段にて読み取り、その搬送先情報が示す搬送先に対応する搬送箇所が搬送可能な搬送箇所である搬送物については、搬送先に対応する搬送箇所に向けて分岐搬送し、搬送先情報が示す搬送先に対応する搬送箇所が搬送不能な搬送箇所である搬送物については、搬送先に対応する搬送箇所とは別の代替え搬送先に対応する搬送箇所に向けて分岐搬送するように構成されている。   That is, when the conveyed product is supplied to the supply unit, the writing destination information is stored in the information storage tag provided on the conveyed product by the writing unit, and the conveyed product branches the conveyed product in the conveying unit. When it is transported to the branch location to be transported, the transport destination information stored in the information storage tag of the transported product transported to the branch location is read by the reading means and corresponds to the transport destination indicated by the transport destination information. For a transported object that is a transportable part that can be transported, it is branched and transported toward the transporting part corresponding to the transporting destination, and the transporting part corresponding to the transporting destination indicated by the transporting destination information is a transporting part that cannot be transported. The object is configured to be branched and conveyed toward a conveyance location corresponding to an alternative conveyance destination different from the conveyance location corresponding to the conveyance destination.

従って、搬送先情報が記憶された情報記憶用タグを搬送物に設け、搬送手段における搬送物を分岐させる分岐箇所において搬送先情報に基づいて搬送物を分岐搬送させるため、搬送手段の修復処理を行うために搬送物を搬送手段から降ろした場合でも、その搬送物を搬送経路中の分岐箇所の搬送上手側に再投入させることによって、搬送先に対応する搬送箇所、あるいは、代替え搬送先に対応する搬送箇所に向けて分岐搬送することができる。   Therefore, an information storage tag in which transport destination information is stored is provided on the transported object, and the transporting means is branched and transported based on the transport destination information at the branching point where the transported object is branched in the transporting means. Even if the transported object is unloaded from the transport means, the transported part can be re-introduced to the upper transport side of the branching point in the transport path to support the transport point corresponding to the transport destination or an alternative transport destination. Can be branched and transported toward the transport location.

本発明にかかる搬送設備の第3特徴構成は、第2特徴構成において、前記制御装置が、中央コントローラから送信された前記搬送先情報並びに前記搬送トラブル監視手段から送信された前記監視情報を受信し、その受信した前記搬送先情報並びに前記監視情報を管理する統括コントローラと、前記書き込み手段に対応して設けられ、前記統括コントローラから送信された前記搬送先情報を受信し、その受信した前記搬送先情報に基づいて前記書き込み手段の作動を制御する供給部制御部と、前記読み取り手段の夫々に対応して設けられ、前記統括コントローラから送信された前記監視情報並びに前記読み取り手段から送信された前記搬送先情報を受信し、その受信した前記監視情報と前記搬送先情報とに基づいて前記搬送手段における前記分岐箇所に備えられた分岐搬送部の作動を制御する分岐制御部とを備えて構成されている点にある。   According to a third characteristic configuration of the transport facility according to the present invention, in the second characteristic configuration, the control device receives the transport destination information transmitted from a central controller and the monitoring information transmitted from the transport trouble monitoring means. An overall controller that manages the received transport destination information and the monitoring information; and the transport destination information that is provided in correspondence with the writing means and receives the transport destination information transmitted from the overall controller; The supply unit controller that controls the operation of the writing unit based on the information, and the monitoring information transmitted from the general controller provided corresponding to each of the reading unit and the conveyance transmitted from the reading unit Receiving the destination information, and based on the received monitoring information and the destination information, In that it is constituted by a branch control unit for controlling the operation of the branch conveying section provided at a location.

すなわち、前記搬送先情報並びに前記監視情報を統括コントローラにて管理し、搬送先情報に基づく書き込み手段の作動の制御を供給部制御部にて制御し、監視情報と搬送先情報とに基づく分岐搬送部の作動を分岐制御部にて制御するように、搬送設備の制御を統括コントローラや供給部制御部、分岐制御部にて分散して制御することにより、統括コントローラの負担を軽減させることができる。   That is, the transport destination information and the monitoring information are managed by an overall controller, the operation of the writing means based on the transport destination information is controlled by the supply unit control unit, and the branch transport based on the monitoring information and the transport destination information The control of the transportation equipment is distributed and controlled by the general controller, the supply unit control unit, and the branch control unit so that the operation of the unit is controlled by the branch control unit, so that the burden on the general controller can be reduced. .

以下、本発明の実施の形態を図面に基づいて説明する。
図1に示すように、搬送設備には、供給部Aから供給される搬送物Wを複数の搬送箇所Cに搬送するように構成された搬送手段1が設けられており、図外の収納棚から取り出された搬送物Wを供給部Aに供給し、搬送コンベア1にて搬送物Wの搬送先に対応する搬送箇所Cに分岐搬送し、その搬送箇所Cに搬送された搬送物Wを図外の搬送車にて外部に搬出するように構成されている。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
As shown in FIG. 1, the transport facility is provided with transport means 1 configured to transport a conveyed product W supplied from a supply unit A to a plurality of transport locations C, and a storage shelf outside the figure. The conveyed product W taken out from the carrier is supplied to the supply unit A, branched and conveyed to the conveyance location C corresponding to the conveyance destination of the conveyed product W by the conveyance conveyor 1, and the conveyed product W conveyed to the conveyance location C is illustrated in FIG. It is comprised so that it may carry out outside with an outside conveyance vehicle.

搬送手段1は、主搬送コンベア2と、供給部Aに供給された搬送物Wを主搬送コンベア2に合流搬送させる2つの合流搬送コンベア3と、主搬送コンベア2から分岐搬送された搬送物Wを搬送箇所Cに搬送させる3つの分岐搬送コンベア4とを備えて構成されている。つまり、搬送手段1は、合流搬送コンベア3夫々の搬送上手側に位置する2箇所の供給部Aに供給された搬送物Wを主搬送コンベア2に合流させた後、3つの分岐搬送コンベア4のいずれかに分岐搬送し、分岐搬送コンベア4夫々の搬送下手側に位置する3箇所の搬送箇所Cに分岐搬送するように構成されている。   The conveyance means 1 includes a main conveyance conveyor 2, two merging conveyance conveyors 3 that merge and convey the conveyance object W supplied to the supply unit A to the main conveyance conveyor 2, and a conveyance object W that is branched and conveyed from the main conveyance conveyor 2. And three branch transfer conveyors 4 for transferring the paper to the transfer point C. That is, the conveying means 1 merges the conveyed product W supplied to the two supply units A located on the upper conveyance side of each of the merging conveying conveyors 3 into the main conveying conveyor 2, and then the three conveying conveyors 4 It is configured to branch and transport to any one, and branch and transport to three transport points C located on the lower transport side of each of the branch transport conveyors 4.

主搬送コンベア2には、合流搬送コンベア3からの搬送物Wを合流させる合流箇所に合流搬送部2aが設けられ、分岐搬送コンベア4へ搬送物Wを分岐させる分岐箇所Bには分岐搬送部2bが設けられ、搬送下手側端部に切換搬送部2cが設けられており、これら合流搬送部2a、分岐搬送部2b及び切換搬送部2cの夫々は、搬送物Wを載置搬送する搬送部を旋回させることにより搬送方向を変更させる旋回式に構成されている。
そして、合流搬送部2aは、搬送方向を合流搬送コンベア3の搬送方向に沿うように変更した状態で合流搬送コンベア3から搬送物Wを受け取り、搬送方向を主搬送コンベア2の搬送方向に沿うように変更した状態で搬送下手側に搬送物Wを搬送するように構成されている。
また、分岐搬送部2bは、搬送方向を主搬送コンベア2の搬送方向に沿うように変更した状態で搬送上手側から搬送物Wを受け取り、そのままの状態で搬送物W搬送下手側に受け渡す、あるいは、搬送方向を分岐搬送コンベア4の搬送方向に沿うように変更した状態で分岐搬送コンベア4に搬送物Wを受け渡すように構成されている。
また、切換搬送部2cは、搬送方向を主搬送コンベア2の搬送方向に沿うように変更した状態で搬送上手側から搬送物Wを受け取り、搬送方向を分岐搬送コンベア4の搬送方向に沿うように変更して分岐搬送コンベア4に受け渡すように構成されている。
The main conveyor 2 is provided with a merging / conveying unit 2a at a merging point where the conveyed product W from the merging / conveying conveyor 3 is merged. And a switching transport unit 2c is provided at the lower end of the transport, and each of the merging transport unit 2a, the branch transport unit 2b, and the switching transport unit 2c is a transport unit for placing and transporting the transported product W. It is configured in a swivel type that changes the transport direction by swiveling.
And the confluence | merging conveyance part 2a receives the conveyed product W from the confluence | conveyance conveyer 3 in the state which changed the conveyance direction so that the conveyance direction of the confluence | conveyance conveyor 3 may be met, and the conveyance direction follows the conveyance direction of the main conveyance conveyor 2 In the state changed to, the transported object W is transported to the lower transport side.
Further, the branch conveyance unit 2b receives the conveyed product W from the upper conveyance side in a state in which the conveyance direction is changed along the conveyance direction of the main conveyance conveyor 2, and delivers the conveyed product W to the lower conveyance side as it is. Alternatively, the transported object W is delivered to the branch transport conveyor 4 in a state where the transport direction is changed along the transport direction of the branch transport conveyor 4.
Further, the switching transport unit 2c receives the transported object W from the upper transport side in a state where the transport direction is changed to be along the transport direction of the main transport conveyor 2, and the transport direction is along the transport direction of the branch transport conveyor 4 It changes and is comprised so that it may pass to the branch conveyance conveyor 4. FIG.

図1に示すように、前記搬送先情報を記憶する情報記憶用タグとしてのICタグ6が各搬送物Wに設けられている。そして、前記ICタグ6に前記搬送先情報を記憶させる書き込み手段としての書き込み用のリーダライタ装置7が前記供給部Aに対応して設けられ、搬送物Wにおける前記ICタグ6に記憶された前記搬送先情報を読み取る読み取り手段としての読み取り用のリーダライタ装置8が前記搬送コンベア1における搬送物Wを分岐させる分岐箇所Bの夫々に対応して設けられている。また、図2に示すように、前記搬送手段1の搬送経路における搬送状況を監視して、複数の搬送箇所Cのうちで前記供給部Aからの搬送物Wを搬送不能な搬送箇所Cを管理する搬送トラブル監視手段5が設けられている。   As shown in FIG. 1, an IC tag 6 serving as an information storage tag for storing the transport destination information is provided on each transport object W. A reader / writer device 7 for writing as a writing means for storing the transport destination information in the IC tag 6 is provided corresponding to the supply unit A, and the IC tag 6 in the transported object W is stored in the IC tag 6. A reader / writer device 8 for reading as reading means for reading the conveyance destination information is provided corresponding to each of the branch points B where the conveyance object W is branched on the conveyance conveyor 1. Further, as shown in FIG. 2, the conveyance status in the conveyance path of the conveyance means 1 is monitored, and among the plurality of conveyance locations C, the conveyance location C that cannot convey the conveyed product W from the supply unit A is managed. Conveyance trouble monitoring means 5 is provided.

つまり、ICタグ6は、書き込み用のリーダライタ装置7にて搬送先情報を非接触通信にて書き込み可能で且つ読み取り用のリーダライタ装置8にて搬送先情報を非接触通信にて読み取り可能に構成されており、予め搬送物Wの横側面に貼付状態で設けられている。
そして、書き込み用のリーダライタ装置7は、供給部Aに対応して供給部A夫々に設けられて、供給部Aに供給された搬送物WのICタグ6に対して搬送先情報を記憶させることができるように構成され、また、読み取り用のリーダライタ装置8は、分岐箇所Bに対応して分岐箇所B夫々の搬送上手側に設けられて、分岐箇所Bに搬送される搬送物WのICタグ6に記憶された搬送用情報を読み取ることができるように構成されている。尚、図1に示すように、書き込み用のリーダライタ装置7の搬送下手側には、供給部Aには供給部Aに供給された搬送物Wを検出する供給用在荷センサ9が設けられ、読み取り用のリーダライタ装置8の搬送下手側には、分岐箇所Bに搬送される搬送物Wを検出する分岐用在荷センサ10が設けられている。
また、搬送箇所Cには搬送箇所Cに搬送された搬送物Wを検出する搬送用在荷センサ11が設けられ、搬送箇所Cの搬送上手側には搬送箇所Cに搬送される搬送物Wを検出する待機用在荷センサ12が設けられており、待機用在荷センサ12は、搬送箇所Cに搬送物Wが存在する場合に搬送箇所Cの搬送上手側に停止させた搬送物Wを検出するように設けられている。
In other words, the IC tag 6 can write the transport destination information by the non-contact communication by the reader / writer device 7 for writing, and can read the transport destination information by the non-contact communication by the reader / writer device 8 for reading. It is comprised, and is previously provided in the sticking state on the side surface of the conveyed product W.
The reader / writer device 7 for writing is provided in each of the supply units A corresponding to the supply unit A, and stores the transfer destination information in the IC tag 6 of the conveyed product W supplied to the supply unit A. The reader / writer device 8 for reading is provided on the upper transfer side of each of the branch points B corresponding to the branch point B, so that the transport object W to be transported to the branch point B is provided. The conveyance information stored in the IC tag 6 can be read. As shown in FIG. 1, on the lower conveyance side of the writing reader / writer device 7, the supply unit A is provided with a supply load sensor 9 for detecting the conveyed product W supplied to the supply unit A. On the lower transport side of the reader / writer device 8 for reading, a branching stock sensor 10 for detecting the transported object W transported to the branch point B is provided.
In addition, a conveyance load sensor 11 that detects a conveyed product W that has been conveyed to the conveyance location C is provided at the conveyance location C, and the conveyance product W that is conveyed to the conveyance location C is placed on the upper conveyance side of the conveyance location C. A standby stock sensor 12 for detecting is provided, and the standby stock sensor 12 detects the transported object W stopped on the upper transport side of the transport location C when the transported product W is present at the transport location C. It is provided to do.

搬送トラブル監視手段5は、搬送手段1を駆動させる複数の搬送モータの回転数を検出する図外の回転数センサの検出情報や、供給用在荷センサ9、分岐用在荷センサ10、搬送用在荷センサ11、待機用在荷センサ12の検出情報に基づいて、搬送不能な搬送箇所Cを判別するように構成されている。つまり、搬送モータが駆動状態であるにも拘らず搬送モータの回転数が増加しない場合では、搬送手段1における回転数が増加しない搬送モータにて駆動される箇所より搬送下手側の搬送箇所Cを搬送不能な搬送箇所Cと判別し、供給用在荷センサ9、分岐用在荷センサ10並びに搬送用在荷センサ11の検出状態が設定以上継続する場合では、そのセンサより搬送下手側の搬送箇所Cを搬送不能な搬送箇所Cと判別し、さらに、搬送上手側の供給用在荷センサ9や分岐用在荷センサ10が非検出状態となってから設定時間経過しても搬送下手側の分岐用在荷センサ10や搬送用在荷センサ11が検出状態とならない場合では、搬送上手側のセンサより搬送下手側の搬送箇所Cを搬送不能な搬送箇所Cと判別するように構成されている。そして、搬送トラブル監視手段5は、搬送不能な搬送箇所Cの情報を監視情報として制御手段Hに送信するように構成されている。   The conveyance trouble monitoring means 5 includes detection information of a rotation speed sensor (not shown) for detecting the rotation speeds of a plurality of conveyance motors that drive the conveyance means 1, a supply load sensor 9, a branch load sensor 10, Based on the detection information of the stock sensor 11 and the stock sensor 12 for standby, it is configured to determine a transport location C that cannot be transported. That is, when the rotation speed of the conveyance motor does not increase even though the conveyance motor is in a driving state, the conveyance position C on the lower conveyance side than the position driven by the conveyance motor where the rotation number of the conveyance means 1 does not increase. When the detection state of the supply stock sensor 9, the branch stock sensor 10 and the transport stock sensor 11 continues to be set or more than the set, the transport location on the lower side of the transport from that sensor. C is determined as a conveyance point C that cannot be conveyed, and the branch on the lower conveyance side is branched even after the set time has elapsed since the supply inventory sensor 9 and the branch inventory sensor 10 on the upper conveyance side are not detected. In the case where the in-stock sensor 10 and the in-conveyance sensor 11 are not in the detection state, the transport location C on the lower transport side is determined as the transport location C that cannot be transported by the sensor on the upper transport side. And the conveyance trouble monitoring means 5 is comprised so that the information of the conveyance location C which cannot be conveyed will be transmitted to the control means H as monitoring information.

図2に示すように、搬送設備には、各搬送物Wの搬送先が前記複数の搬送箇所Cのうちのどれであるかを示す搬送先情報に基づいて、搬送物Wを搬送先に対応する搬送箇所Cに搬送するように前記搬送手段1の作動を制御する制御手段Hが設けられ、この制御手段Hが、前記搬送トラブル監視手段5の監視情報に基づいて、搬送先が搬送不能な搬送箇所Cである搬送物Wについては、搬送可能な搬送箇所Cを代替え搬送先に設定して搬送するように構成されている。
そして、前記制御手段Hが、前記読み取り用のリーダライタ装置8にて読み取られた前記搬送先情報並びに前記搬送トラブル監視手段5の前記監視情報に基づいて、前記搬送先情報が読み取られた搬送物Wを搬送先に対応する搬送箇所Cに向けて分岐搬送し、且つ、搬送先が搬送不能な搬送箇所Cである搬送物Wについては代替え搬送先に対応する搬送箇所Cに向けて分岐搬送するように構成されている。
尚、搬送トラブル監視手段5にて、複数の搬送箇所Cのうちの全ての搬送箇所Cが搬送不能な搬送箇所Cと判別された場合には、全ての搬送箇所Cが搬送不能であることを示す監視情報を受信した制御手段Hは、搬送物の搬送を停止させるように搬送手段1の作動を制御するように構成されている。搬送物Wに設けられたICタグ6には搬送先情報が記憶されているため、搬送手段1の作動を停止させて搬送手段1の修復処理を行うために搬送物Wを搬送手段1から降ろした場合でも、搬送経路中の分岐箇所Bの搬送上手側に再投入させることによって、搬送先に対応する搬送箇所C、あるいは、代替え搬送先に対応する搬送箇所Cに向けて分岐搬送することができる。
As shown in FIG. 2, the transport facility corresponds to the transport destination based on transport destination information indicating which of the plurality of transport locations C is the transport destination of each transport object W. Control means H for controlling the operation of the transport means 1 is provided so as to transport to the transport location C where the transport destination cannot be transported based on the monitoring information of the transport trouble monitoring means 5. About the conveyed product W which is the conveyance location C, it is comprised so that the conveyance location C which can be conveyed is set as an alternative conveyance destination, and it conveys.
Then, the control unit H carries the conveyance destination information read based on the conveyance destination information read by the reader / writer device 8 for reading and the monitoring information of the conveyance trouble monitoring unit 5. Branching and transporting W toward the transport point C corresponding to the transport destination, and branching and transporting the transported object W, which is the transport point C where the transport destination cannot be transported, toward the transport point C corresponding to the alternative transport destination It is configured as follows.
When the conveyance trouble monitoring means 5 determines that all the conveyance points C among the plurality of conveyance points C are unconveyable conveyance points C, it is determined that all the conveyance points C are unconveyable. The control unit H that has received the monitoring information shown is configured to control the operation of the transport unit 1 so as to stop the transport of the transported object. Since the transport destination information is stored in the IC tag 6 provided on the transport object W, the transport object W is lowered from the transport means 1 in order to stop the operation of the transport means 1 and perform the repair process of the transport means 1. Even in this case, it is possible to branch and transport toward the transport location C corresponding to the transport destination or the transport location C corresponding to the alternative transport destination by re-introducing the branch location B in the transport path to the upper transport side. it can.

また、制御手段Hは、中央コントローラ14から送信された前記搬送先情報並びに前記搬送トラブル監視手段5から送信された前記監視情報を受信し、その受信した前記搬送先情報並びに前記監視情報を管理する統括コントローラ15と、前記書き込み用のリーダライタ装置7に対応して設けられ、前記統括コントローラ15から送信された前記搬送先情報を受信し、その受信した前記搬送先情報に基づいて前記書き込み用のリーダライタ装置7の作動を制御する供給部制御部16と、前記読み取り用のリーダライタ装置8の夫々に対応して設けられ、前記統括コントローラ15から送信された前記監視情報並びに前記読み取り手段8から送信された前記搬送先情報を受信し、その受信した前記監視情報と前記搬送先情報とに基づいて前記搬送手段1における前記分岐箇所Bに備えられた分岐搬送部2bの作動を制御する分岐制御部17とを備えて構成されている。   The control unit H receives the transport destination information transmitted from the central controller 14 and the monitoring information transmitted from the transport trouble monitoring unit 5, and manages the received transport destination information and the monitoring information. An overall controller 15 is provided corresponding to the reader / writer device 7 for writing. The transport destination information transmitted from the overall controller 15 is received, and the write destination information is received based on the received transport destination information. From the monitoring information transmitted from the overall controller 15 and the reading means 8 provided corresponding to each of the supply controller 16 for controlling the operation of the reader / writer device 7 and the reader / writer device 8 for reading. The transport destination information transmitted is received and the transport destination information is received based on the received monitoring information and the transport destination information. It is constituted by a branch control unit 17 for controlling the operation of the branch conveying portion 2b provided in the branch point B in section 1.

つまり、中央コントローラ14は、収納棚から搬送物を取り出して供給部Aに供給する図外のスタッカークレーンや搬送箇所Cに搬送された搬送物Wを多数の搬送場所のうちのいずれかに搬送する搬送車の作動を制御するとともに、スタッカークレーンにて供給部Aに供給された搬送物Wに対応する搬送先情報を統括コントローラ15に送信するように構成されており、統括コントローラ15は、中央コントローラ14にて送信された搬送先情報を受信し、その受信した搬送先情報を搬送物Wが供給された供給部Aに対応する供給部制御部16に送信するように構成されている。
そして、供給部制御部16は、統括コントローラ15にて送信された搬送先情報を受信し、図3に示すように、供給部Aに搬送物Wが供給されたことが供給用在荷センサ9にて検出されると、書き込み用のリーダライタ装置7を作動させて、供給された搬送物Wに設けられたICタグ6に、その搬送物Wの搬送先を示す搬送先情報をICタグ6に記憶させる供給制御を実行するように構成されている。
尚、統括コントローラ15は、供給部Aに搬送物Wが供給する際には合流搬送コンベア3の作動を停止させ、供給部Aに搬送物Wを供給し、書き込み用のリーダライタ装置7にて搬送用情報をICタグ6に書き込むに要する時間が経過した後に、合流搬送コンベア3を駆動させて搬送物Wの搬送を開始するように構成されている。また、統括コントローラ15は、搬送物Wの搬送に応じて搬送方向を適宜切り換えるように合流搬送部2aの作動も制御するように構成されている。
That is, the central controller 14 takes the conveyed product from the storage shelf and supplies it to the supply unit A, and conveys the conveyed product W transported to the unillustrated stacker crane or the transport location C to one of a number of transport locations. The operation of the transport vehicle is controlled, and the transport destination information corresponding to the transport object W supplied to the supply unit A by the stacker crane is transmitted to the general controller 15. The transport destination information transmitted at 14 is received, and the received transport destination information is transmitted to the supply unit control unit 16 corresponding to the supply unit A to which the transported product W is supplied.
And the supply part control part 16 receives the conveyance destination information transmitted in the integrated controller 15, and, as shown in FIG. , The reader / writer device 7 for writing is operated, and the IC tag 6 provided with the transported object W is provided with transport destination information indicating the transport destination of the transported object W. It is comprised so that the supply control memorize | stored in may be performed.
The general controller 15 stops the operation of the merging / conveying conveyor 3 when the conveyed product W is supplied to the supply unit A, supplies the conveyed product W to the supply unit A, and the writing reader / writer device 7 After the time required for writing the conveyance information to the IC tag 6 elapses, the merging / conveying conveyor 3 is driven to start conveying the conveyed product W. The overall controller 15 is also configured to control the operation of the merging / conveying unit 2a so as to appropriately switch the conveyance direction in accordance with the conveyance of the conveyed product W.

また、搬送トラブル監視手段5は、監視情報を統括コントローラ15に送信するように構成されており、統括コントローラ15は、搬送トラブル監視手段5にて送信された監視情報を受信し、その受信した監視情報を分岐制御部17の夫々に送信するように構成されている。
そして、分岐制御部17は、図4に示すように、分岐箇所Bの手前まで搬送物Wが搬送されたことが分岐用在荷センサ10にて検出されると、読み取り用のリーダライタ装置8を作動させて搬送物Wに設けられたICタグ6に記憶されている搬送先情報を読み取り、その読み取った搬送先情報にて示される搬送先に対応する搬送箇所Cが搬送可能な搬送箇所Cであれば、その搬送箇所Cに向けて搬送物Wを分岐搬送し、読み取った搬送先情報にて示される搬送先に対応する搬送箇所Cが搬送不能な搬送箇所Cであれば、搬送先とは別の代替え搬送先に対応する搬送箇所Cに向けて搬送物Wを分岐搬送するように分岐搬送部2bの作動を制御する分岐制御を実行するように構成されている。
尚、統括コントローラ15は、搬送物Wの搬送に応じて切換搬送部2cの搬送方向を適宜切り換えるように切換搬送部2cの作動を制御するように構成されている。
Moreover, the conveyance trouble monitoring means 5 is configured to transmit monitoring information to the general controller 15, and the general controller 15 receives the monitoring information transmitted from the conveyance trouble monitoring means 5, and receives the received monitoring information. Information is transmitted to each of the branch control units 17.
Then, as shown in FIG. 4, the branch control unit 17 reads the reader / writer device 8 for reading when the branch load sensor 10 detects that the transported object W has been transported to the front of the branch point B. Is operated, the transport destination information stored in the IC tag 6 provided on the transported object W is read, and the transport location C corresponding to the transport destination indicated by the read transport destination information can be transported. If the transport location C corresponding to the transport destination indicated by the read transport destination information is the transport location C that cannot be transported, the transport destination W is branched and transported toward the transport location C. Is configured to execute branch control for controlling the operation of the branch transport unit 2b so as to branch and transport the transported object W toward the transport point C corresponding to another alternative transport destination.
The overall controller 15 is configured to control the operation of the switching transport unit 2c so as to appropriately switch the transport direction of the switching transport unit 2c according to the transport of the transported object W.

分岐制御部17の夫々には、統括コントローラ15から送信された分岐情報が予め受信されており、この分岐情報は、搬送箇所Cの夫々に対する分岐箇所Bにおける分岐方向を示す情報である。また、分岐制御部17には、統括コントローラ15から適宜送信された代替え搬送先情報が受信されており、この代替え搬送先情報は、代替え搬送先が複数の搬送箇所Cのうちのどれであるかを示す情報である。
つまり、分岐箇所Bにおいて搬送物Wを搬送先に対応する搬送箇所Cに向けて分岐搬送する際では、搬送先情報と分岐情報とに基づいて、主搬送コンベア2の搬送下手側に搬送する直進搬送又は分岐搬送コンベア4に搬送する切換搬送を選択して、搬送物Wを搬送先に対応する搬送箇所Cに向けて分岐搬送するように構成されている。
そして、分岐箇所Bにおいて搬送物Wを代替え搬送先に対応する搬送箇所Cに向けて分岐搬送する際では、代替え搬送先情報と分岐情報とに基づいて、主搬送コンベア2の搬送下手側に搬送する直進搬送又は分岐搬送コンベア4に搬送する切換搬送を選択して、搬送物Wを代替え搬送先に対応する搬送箇所Cに向けて分岐搬送するように構成されている。尚、搬送物Wの搬送先を代替え搬送先に変更させるに合わせて、この搬送物Wを外部に搬出させる搬送車を、搬送物Wの搬送先ではなく代替え搬送先に移動させる。
The branch information transmitted from the overall controller 15 is received in advance by each of the branch control units 17, and this branch information is information indicating the branch direction at the branch point B with respect to each of the transport points C. The branch control unit 17 receives the alternative transport destination information appropriately transmitted from the overall controller 15, and the alternative transport destination information indicates which of the plurality of transport locations C the alternative transport destination is. It is information which shows.
That is, when branching and transporting the transported object W toward the transporting point C corresponding to the transporting destination at the branching point B, the straight line transporting to the lower transport side of the main transporting conveyor 2 based on the transporting destination information and the branching information. It is configured to select the transfer transport to be transported or transported to the branch transport conveyor 4 and branch and transport the transported object W toward the transport location C corresponding to the transport destination.
When branching and transporting the transported object W toward the transporting point C corresponding to the alternative transport destination at the branching point B, the transported product W is transported to the lower transport side of the main transport conveyor 2 based on the alternative transport destination information and the branching information. It is configured to select the straight conveyance or the switching conveyance to be conveyed to the branch conveyance conveyor 4 and branch and convey the conveyed product W toward the conveyance location C corresponding to the conveyance destination. In addition, according to changing the conveyance destination of the conveyed product W to an alternative conveyance destination, the conveyance vehicle which carries out this conveyed item W outside is moved not to the conveyance destination of the conveyed product W but to an alternative conveyance destination.

従って、供給部Aに搬送物Wが供給されたことが供給用在荷センサ9にて検出されると、供給された搬送物Wに設けられたICタグ6に、書き込み用のリーダライタ装置7にて搬送物Wの搬送先、つまりは、搬送箇所Cのいずれかに対応する搬送先を示す搬送先情報を記憶させる。
合流搬送コンベア3、主搬送コンベア2と順次搬送されて、分岐箇所Bの手前まで搬送物Wが搬送されたことが分岐用在荷センサ10にて検出されると、読み取り用のリーダライタ装置8にて搬送物Wに設けられたICタグ6に記憶されている搬送先情報を読み取る。そして、この搬送先情報と監視情報とに基づいて、搬送先に対応する搬送箇所Cが搬送可能な搬送箇所Cであると判断すると、分岐箇所Bにおいて搬送先に対応する搬送箇所Cに向けて分岐搬送する。つまり、搬送上手側の分岐箇所Bにおいては、搬送先に対応する搬送箇所Cが第1搬送箇所C1であれば切換搬送し、搬送先に対応する搬送箇所Cが第2搬送箇所C2又は第3搬送箇所C3であれば直進搬送するように分岐搬送し、搬送下手側の分岐箇所Bにおいては、搬送先に対応する搬送箇所Cが第2搬送箇所C2であれば切換搬送し、搬送先に対応する搬送箇所Cが第3搬送箇所C3であれば直進搬送するように分岐搬送する。
また、搬送先情報と監視情報とに基づいて、搬送先に対応する搬送箇所Cが搬送不能な搬送箇所Cであると判断すると、分岐箇所Bにおいて搬送先に対応する搬送箇所Cとは別の代替え搬送先に対応する搬送可能な搬送箇所Cに向けて分岐搬送する。つまり、搬送上手側の分岐箇所Bにおいては、代替え搬送先に対応する搬送箇所Cが第1搬送箇所C1であれば切換搬送し、代替え搬送先に対応する搬送箇所Cが第2搬送箇所C2又は第3搬送箇所C3であれば直進搬送するように分岐搬送し、搬送下手側の分岐箇所Bにおいては、代替え搬送先に対応する搬送箇所Cが第2搬送箇所C2であれば切換搬送し、代替え搬送先に対応する搬送箇所Cが第3搬送箇所C3であれば直進搬送するように分岐搬送する。
Therefore, when the supply stock sensor 9 detects that the conveyed product W is supplied to the supply unit A, the reader / writer device 7 for writing is written on the IC tag 6 provided on the supplied conveyed product W. The transport destination information indicating the transport destination of the transport object W, that is, the transport destination corresponding to one of the transport locations C is stored.
When it is detected by the branching stock sensor 10 that the transported object W has been transported to the junction transporting conveyor 3 and the main transporting conveyor 2 in sequence and transported to the front of the branching point B, the reader / writer device 8 for reading is read. The transport destination information stored in the IC tag 6 provided on the transported object W is read. And if it judges that the conveyance location C corresponding to a conveyance destination is the conveyance location C which can be conveyed based on this conveyance destination information and monitoring information, toward the conveyance location C corresponding to a conveyance destination in the branch location B Branch and transport. That is, at the branch point B on the upper side of the transfer, if the transfer point C corresponding to the transfer destination is the first transfer point C1, switching transfer is performed, and the transfer point C corresponding to the transfer destination is the second transfer point C2 or the third transfer point C1. If it is the transfer point C3, it is branched and transferred so that it is straightly transferred. In the branch point B on the lower transfer side, if the transfer point C corresponding to the transfer destination is the second transfer point C2, it is switched and transferred to the transfer destination. If the transporting point C to be carried out is the third transporting point C3, it is branched and transported so as to transport straight.
Further, when it is determined that the transport location C corresponding to the transport destination is a transport location C that cannot be transported based on the transport destination information and the monitoring information, the branch location B is different from the transport location C corresponding to the transport destination. Branch and transport toward a transportable transport location C corresponding to the alternative transport destination. That is, at the branch point B on the upper side of the transfer, if the transfer point C corresponding to the alternative transfer destination is the first transfer point C1, switching transfer is performed, and the transfer point C corresponding to the alternative transfer destination is the second transfer point C2 or If it is the third transfer location C3, it is branched and conveyed so that it is conveyed in a straight line. At the branch location B on the lower transfer side, if the transfer location C corresponding to the alternative transfer destination is the second transfer location C2, it is switched and transferred. If the transfer location C corresponding to the transfer destination is the third transfer location C3, the branch transfer is performed so that the straight transfer is performed.

〔別実施の形態〕
(1) 上記実施の形態では、書き込み手段7や読み取り手段8を備え、搬送先情報を情報記憶用タグ6に記憶させたが、書き込み手段7や読み取り手段8、情報記憶用タグ6を用いずに、搬送モータの回転数を回転数センサにて検出し、この回転数センサの検出情報に基づいて搬送物Wの現在位置を把握しながら、搬送先情報や監視情報に基づいて搬送手段1の作動を制御するように構成してもよい。
[Another embodiment]
(1) In the above embodiment, the writing unit 7 and the reading unit 8 are provided, and the transport destination information is stored in the information storage tag 6. However, the writing unit 7, the reading unit 8, and the information storage tag 6 are not used. In addition, the rotation number of the conveyance motor is detected by the rotation number sensor, and the current position of the conveyed object W is grasped based on the detection information of the rotation number sensor, and the conveyance means 1 is monitored based on the conveyance destination information and the monitoring information. You may comprise so that an action | operation may be controlled.

(2) 上記実施の形態では、供給部Aに対応して書き込み手段7を設けたが、書き込み手段7を設けずに供給部Aに供給される前に予め情報記憶用タグ6に搬送先情報を書き込んでおくように構成してもよい。
また、上記実施の形態では、情報記憶用タグ6を設けた状態で搬送物Wを供給部Aに供給したが、供給部Aに供給された搬送物Wに情報記憶用タグ6を貼付する貼付装置を供給部Aに設けて、供給部Aに供給された搬送物Wに情報記憶用タグ6を貼付させるように構成してもよい。
(2) In the above-described embodiment, the writing unit 7 is provided corresponding to the supply unit A. However, before the writing unit 7 is provided and the supply unit A is supplied to the supply unit A, the transport destination information is previously stored in the information storage tag 6. May be written.
Moreover, in the said embodiment, although the conveyed product W was supplied to the supply part A in the state which provided the tag 6 for information storage, the sticking which sticks the information storage tag 6 to the conveyed product W supplied to the supply part A An apparatus may be provided in the supply unit A, and the information storage tag 6 may be attached to the conveyed product W supplied to the supply unit A.

(3) 上記実施の形態では、搬送手段1に分岐箇所Bを2箇所に備えさせたが、搬送手段1に分岐箇所Bを1箇所にだけ備えさせる、又は、図5に示すように、分岐箇所Bを3箇所以上に備えさせてもよい。
また、上記実施の形態では、搬送手段1を分岐箇所Bにて搬送物を2方向に分岐搬送させるように構成したが、分岐箇所Bにて搬送物を3方向以上に分岐搬送させるように構成してもよい。
また、搬送手段1に供給部Aを2箇所に備えさせたが、搬送手段1に供給部を1箇所にだけ備えさせる、又は、供給部Aを3箇所以上に備えさせてもよい。
(3) In the above embodiment, the conveying means 1 is provided with two branch points B. However, the conveying means 1 is provided with only one branch point B, or as shown in FIG. The location B may be provided at 3 or more locations.
Moreover, in the said embodiment, although the conveyance means 1 was comprised so that a conveyed product may be branched and conveyed in two directions at the branch location B, it is comprised so that a conveyed product may be branched and conveyed in three or more directions at the branch location B May be.
Moreover, although the conveyance means 1 was provided with the supply part A in two places, the conveyance means 1 may be provided with the supply part only in one place, or the supply part A may be provided in three or more places.

(4) 上記実施の形態では、制御手段Hを統括コントローラ15と供給部制御部16と分岐制御部17とを備え、供給部制御部16にて書き込み手段7の作動を制御し、分岐制御部17にて読み取り手段8の作動を制御するように構成したが、制御手段Hに統括コントローラ15のみを備えさせ、この統括コントローラ15にて書き込み手段7と読み取り手段8との作動を制御するように構成してもよい。 (4) In the above embodiment, the control unit H includes the overall controller 15, the supply unit control unit 16, and the branch control unit 17, and the supply unit control unit 16 controls the operation of the writing unit 7, and the branch control unit 17, the operation of the reading unit 8 is controlled. However, the control unit H includes only the overall controller 15, and the overall controller 15 controls the operation of the writing unit 7 and the reading unit 8. It may be configured.

(5) 上記実施の形態では、搬送手段を搬送コンベアにて構成したが、搬送台車等の他の搬送手段でもよい。 (5) In the said embodiment, although the conveyance means was comprised with the conveyance conveyor, other conveyance means, such as a conveyance trolley, may be sufficient.

搬送手段の平面図Plan view of transport means 制御ブロック図Control block diagram 供給制御のフローチャートSupply control flowchart 分岐制御のフローチャートBranch control flowchart 別実施形態における搬送手段の平面図The top view of the conveyance means in another embodiment

符号の説明Explanation of symbols

1 搬送手段
2b 分岐搬送部
5 搬送トラブル監視手段
6 情報記憶用タグ
7 書き込み手段
8 読み取り手段
14 中央コントローラ
15 統括コントローラ
16 供給部制御部
17 分岐制御部
A 供給部
B 分岐箇所
C 搬送箇所
H 制御手段
W 搬送物
DESCRIPTION OF SYMBOLS 1 Conveyance means 2b Branch conveyance part 5 Conveyance trouble monitoring means 6 Information storage tag 7 Writing means 8 Reading means 14 Central controller 15 Central controller 16 Supply part control part 17 Branch control part A Supply part B Branch part C Conveyance part H Control part W Conveyed items

Claims (3)

供給部から供給される搬送物を複数の搬送箇所に分岐搬送するように構成された搬送手段と、
各搬送物の搬送先が前記複数の搬送箇所のうちのどれであるかを示す搬送先情報に基づいて、搬送物を搬送先に対応する搬送箇所に搬送するように前記搬送手段の作動を制御する制御手段とが設けられた搬送設備であって、
前記搬送手段の搬送経路における搬送状況を監視して、複数の搬送箇所のうちで前記供給部からの搬送物を搬送不能な搬送箇所を管理する搬送トラブル監視手段が設けられ、
前記制御手段が、前記搬送トラブル監視手段の監視情報に基づいて、搬送先が搬送不能な搬送箇所である搬送物については、搬送可能な搬送箇所を代替え搬送先に設定して搬送するように構成されている搬送設備。
A conveying means configured to branch and convey the conveyed product supplied from the supply unit to a plurality of conveying locations;
Based on the transport destination information indicating which of the plurality of transport locations is the transport destination of each transport object, the operation of the transport means is controlled so that the transport object is transported to a transport location corresponding to the transport destination. A transport facility provided with a control means for
A conveyance trouble monitoring unit is provided for monitoring a conveyance state in the conveyance path of the conveyance unit, and managing a conveyance point where the conveyance object from the supply unit cannot be conveyed among a plurality of conveyance points,
Based on the monitoring information of the conveyance trouble monitoring unit, the control unit is configured to convey a conveyance object whose conveyance destination is a conveyance point that cannot be conveyed, by setting a conveyance point that can be conveyed as an alternative conveyance destination. Transport equipment.
前記搬送先情報を記憶する情報記憶用タグが各搬送物に設けられ、
前記情報記憶用タグに前記搬送先情報を記憶させる書き込み手段が前記供給部に対応して設けられ、
搬送物における前記情報記憶用タグに記憶された前記搬送先情報を読み取る読み取り手段が前記搬送手段における搬送物を分岐させる分岐箇所の夫々に対応して設けられ、
前記制御手段が、前記読み取り手段にて読み取られた前記搬送先情報並びに前記搬送トラブル監視手段の前記監視情報に基づいて、前記搬送先情報が読み取られた搬送物を搬送先に対応する搬送箇所に向けて分岐搬送し、且つ、搬送先が搬送不能な搬送箇所である搬送物については代替え搬送先に対応する搬送箇所に向けて分岐搬送するように構成されている請求項1記載の搬送設備。
An information storage tag for storing the transport destination information is provided on each transport object,
Writing means for storing the transport destination information in the information storage tag is provided corresponding to the supply unit,
Reading means for reading the transport destination information stored in the information storage tag in the transported object is provided corresponding to each of the branch points that branch the transported object in the transport means,
Based on the transport destination information read by the reading means and the monitoring information of the transport trouble monitoring means, the control means turns the transported object whose transport destination information is read into a transport location corresponding to the transport destination. The transfer equipment according to claim 1, wherein the transfer facility is configured to branch and transfer toward a transfer point corresponding to an alternative transfer destination for a transfer object that is branched and transferred toward the transfer point and whose transfer destination is a transfer point that cannot be transferred.
前記制御装置が、中央コントローラから送信された前記搬送先情報並びに前記搬送トラブル監視手段から送信された前記監視情報を受信し、その受信した前記搬送先情報並びに前記監視情報を管理する統括コントローラと、
前記書き込み手段に対応して設けられ、前記統括コントローラから送信された前記搬送先情報を受信し、その受信した前記搬送先情報に基づいて前記書き込み手段の作動を制御する供給部制御部と、
前記読み取り手段の夫々に対応して設けられ、前記統括コントローラから送信された前記監視情報並びに前記読み取り手段から送信された前記搬送先情報を受信し、その受信した前記監視情報と前記搬送先情報とに基づいて前記搬送手段における前記分岐箇所に備えられた分岐搬送部の作動を制御する分岐制御部とを備えて構成されている請求項2記載の搬送設備。
The control device receives the transport destination information transmitted from a central controller and the monitoring information transmitted from the transport trouble monitoring means, and manages the received transport destination information and the monitoring information;
A supply unit controller provided corresponding to the writing means, receiving the transport destination information transmitted from the overall controller, and controlling the operation of the writing means based on the received transport destination information;
Each of the reading means is provided corresponding to each of the monitoring information transmitted from the overall controller and the destination information transmitted from the reading means, and the received monitoring information, the destination information, The transfer equipment according to claim 2, further comprising: a branch control unit that controls the operation of the branch transfer unit provided at the branch point in the transfer unit.
JP2005005319A 2005-01-12 2005-01-12 Transport equipment Expired - Fee Related JP4264831B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005005319A JP4264831B2 (en) 2005-01-12 2005-01-12 Transport equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005005319A JP4264831B2 (en) 2005-01-12 2005-01-12 Transport equipment

Publications (2)

Publication Number Publication Date
JP2006193254A true JP2006193254A (en) 2006-07-27
JP4264831B2 JP4264831B2 (en) 2009-05-20

Family

ID=36799636

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005005319A Expired - Fee Related JP4264831B2 (en) 2005-01-12 2005-01-12 Transport equipment

Country Status (1)

Country Link
JP (1) JP4264831B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009110382A (en) * 2007-10-31 2009-05-21 Saxa Inc Production system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05138510A (en) * 1991-11-22 1993-06-01 Toshiba Corp Production line system
JPH05155433A (en) * 1991-12-04 1993-06-22 Daifuku Co Ltd Sorting system
JPH10258930A (en) * 1997-03-18 1998-09-29 Mitsubishi Electric Corp Sorter for waste household electric appliance
JP2000255716A (en) * 1999-03-09 2000-09-19 Toshiba Corp Conveyer system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05138510A (en) * 1991-11-22 1993-06-01 Toshiba Corp Production line system
JPH05155433A (en) * 1991-12-04 1993-06-22 Daifuku Co Ltd Sorting system
JPH10258930A (en) * 1997-03-18 1998-09-29 Mitsubishi Electric Corp Sorter for waste household electric appliance
JP2000255716A (en) * 1999-03-09 2000-09-19 Toshiba Corp Conveyer system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009110382A (en) * 2007-10-31 2009-05-21 Saxa Inc Production system

Also Published As

Publication number Publication date
JP4264831B2 (en) 2009-05-20

Similar Documents

Publication Publication Date Title
JP6589649B2 (en) Goods storage facility
JP6123577B2 (en) Automatic picking equipment
JP2006096427A (en) Article storage facility
JP2006347682A (en) Article carrying device
JP5303914B2 (en) Automatic warehouse sorting system
JP2007269478A (en) Shaking cell device and its control method
JPH06177244A (en) Dicing system
JP4264831B2 (en) Transport equipment
JP2005243729A (en) Conveyer system
JP5735753B2 (en) Article conveying device
KR101991841B1 (en) Conveyor apparatus enable to decentralizedly controll transfer route
JP2009276823A (en) Carrying system
JP4895079B2 (en) Overhead traveling vehicle system
JP4563792B2 (en) Control system for game machine production line
JP2000095304A (en) Article storage facility
JP4352965B2 (en) Facilities for handling goods
KR101937687B1 (en) Conveyor apparatus enable to decentralizedly controll transfer route and method for decentralizedly controlling transfer route of conveyor apparatus
JP5585836B2 (en) Goods transport equipment
JP4224792B2 (en) Driving control device for traveling cart
JP4984147B2 (en) Article processing system
JPH0834505A (en) Stock control system
JP2007125996A (en) System and method for controlling traveling of traveling body
JP5374981B2 (en) Transport system
JP2014037313A (en) Article conveying facility and picking facility including the same
JP2005225582A (en) Object treating facility

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20061215

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080717

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080814

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081010

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090122

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090204

R150 Certificate of patent or registration of utility model

Ref document number: 4264831

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130227

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130227

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140227

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees