JP2006115570A - Cable work control system of underground electric line - Google Patents

Cable work control system of underground electric line Download PDF

Info

Publication number
JP2006115570A
JP2006115570A JP2004298177A JP2004298177A JP2006115570A JP 2006115570 A JP2006115570 A JP 2006115570A JP 2004298177 A JP2004298177 A JP 2004298177A JP 2004298177 A JP2004298177 A JP 2004298177A JP 2006115570 A JP2006115570 A JP 2006115570A
Authority
JP
Japan
Prior art keywords
cable
design
work
construction
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004298177A
Other languages
Japanese (ja)
Inventor
Manabu Sugimoto
学 杉本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2004298177A priority Critical patent/JP2006115570A/en
Publication of JP2006115570A publication Critical patent/JP2006115570A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a cable work control system of underground electric line in which the optimal design of cable laying work can be carried out efficiently and accurately when the cable of underground electric line is laid. <P>SOLUTION: The cable work control system of underground electric line comprises a database 200 including at least the existing facility database 210 including all existing facilities of an underground electric line, a laying information database 220 including all information and laws to be studied in order to lay an underground electric line, a work standard database 230 including all work standards and laws of various facilities, and a work design database 240 storing the work design of laying work of other facilities than the cable related to the underground electric line, and carries out design of laying work of the cable with reference to the database 200 based on a laying design 130 regulating the route, laying system, and the size and numbers of cables being laid of the underground electric line. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、地中電線路のケーブルを布設する際の布設工事の管理を行うケーブル工事管理システムに関する。   The present invention relates to a cable work management system for managing a laying work when laying a cable of an underground cableway.

従来より、発電所や変電所などから各家庭や工場などの顧客に対して電力を供給するには、電柱及び鉄塔等を用いた架空電線路やケーブルを地中に埋設した地中電線路が用いられてきた。ここで、地中電線路を布設する場合、ケーブルを地中に直接埋設する方法や、金属製や樹脂製などの配管内に布設する方法や、水道管やガス管などの他の配管と共に共同溝内に直接布設する方法がある。また、地中電線路に用いられる配管は、地中に直接埋設される場合や、共同溝内に布設される場合などがある。   Conventionally, in order to supply power to customers such as households and factories from power stations and substations, underground power lines and cables using underground power poles and steel towers have been buried in the ground. Has been used. Here, when laying underground cables, the method of laying cables directly in the ground, the method of laying in metal or resin pipes, and other pipes such as water pipes and gas pipes are used together. There is a method of laying directly in the groove. In addition, piping used for underground cable tracks may be buried directly in the ground or laid in a common groove.

また、従来の地中電線路のケーブルの布設工事では、電力供給計画に基づいて設計された布設設計のルート、布設方式及びケーブルの少なくとも太さ及び条数に合わせて、ケーブルの布設工事の詳細な工事設計を行っていた。しかしながら、ケーブルの工事設計を行った場合には、マンホールの位置によってケーブルの引込工事が困難であったり、配管の曲率半径がケーブルの許容曲げ半径以下の場合など、ケーブル工事設計以外の他の設備、すなわち、管路、マンホール、ハンドホール、機器設置及び地中引込線などの工事設計を変更する必要があった。また、地中電線路のケーブル以外の他の設備の工事設計を変更することで、ケーブル工事設計を再設計しなくてはならず、整合性を保つのが困難であると共に煩雑であるという問題がある。   In addition, in the conventional cable laying work for underground cables, the details of the cable laying work are set according to the laying design route, the laying method, and at least the thickness and number of cables designed based on the power supply plan. I was doing a proper construction design. However, when cable construction design is performed, other equipment other than cable construction design, such as when cable drawing work is difficult due to the position of the manhole, or when the radius of curvature of piping is less than the allowable bending radius of the cable, etc. In other words, it was necessary to change the construction design such as pipes, manholes, hand holes, equipment installation and underground service lines. In addition, it is necessary to redesign the cable work design by changing the work design of equipment other than the cable of the underground cableway, and it is difficult to maintain consistency and is troublesome. There is.

また、従来、地中電線路のケーブル自体やケーブルの布設工法については種々の改良技術が提案されているが(例えば、特許文献1〜3参照)、電力供給計画に基づいて設計された布設計画に基づいて、地中電線路のケーブルの布設工事の工事設計を管理する手法については全く検討されていないのが現状である。   Conventionally, various improvement techniques have been proposed for the cable itself of the underground cableway and the cable laying method (see, for example, Patent Documents 1 to 3), but the cloth design image designed based on the power supply plan. Based on the above, the method of managing the construction design of the cable laying work for underground cables has not been studied at all.

特開平7−272547号公報JP 7-272547 A 特許第3032462号公報Japanese Patent No. 3032462 特開2002−246079号公報JP 2002-246079 A

本発明はこのような課題に鑑み、地中電線路のケーブルを布設する際に、ケーブルの布設工事の最適な設計を効率的に且つ正確に行うことができる地中電線路のケーブル工事管理システムを提供することを課題とする。   In view of such problems, the present invention is a cable work management system for underground cable paths that can efficiently and accurately perform optimum design for cable installation work when laying cables for underground cable paths. It is an issue to provide.

上記課題を解決する本発明の第1の態様は、地中電線路のケーブルを布設するための地中電線路のケーブル工事管理システムであって、地中電線路の既設設備を網羅した既設設備データベースと、地中電線路を布設するために検討すべき情報及び法令を網羅した布設情報データベースと、各種設備の工事基準及び法令を網羅した工事基準データベースと、地中電線路に関わるケーブル以外の他の設備の布設工事の工事設計が蓄積された工事設計データベースとを少なくとも含むデータベースを具備すると共に、地中電線路のルート、布設方式及び布設されるケーブルの太さ及び条数を少なくとも規定した布設設計に基づいて、前記データベースを参照しながら前記ケーブルの布設工事の設計を行うと共に、ケーブル工事設計が困難な場合には他の設備の工事設計を再検討させる段階に戻すケーブル工事設計手段を具備することを特徴とする地中電線路のケーブル工事管理システムにある。   A first aspect of the present invention that solves the above problems is a cable work management system for underground cables for laying cables for underground cables, and the existing equipment that covers existing cables for underground cables Database, installation information database covering information and laws to be considered for laying underground cables, construction standards database covering construction standards and laws of various facilities, and cables other than cables related to underground cables It has a database including at least a construction design database in which construction designs of construction work of other facilities are accumulated, and at least defines the route of the underground cableway, the construction method, and the thickness and number of the cables to be laid. Based on the laying design, design the cable laying work while referring to the database, and if the cable work design is difficult Sometimes having a cable construction design means for returning to the step of reviewing the construction design of the equipment to the cable construction management system of the underground electric line, characterized in.

かかる第1の態様では、地中電線路の布設設計及び他の工事設計に基づいてケーブルの布設工事の設計を効率的に且つ正確に行うことができる。   In the first aspect, the cable laying work design can be efficiently and accurately performed based on the underground wiring line laying design and the other work design.

本発明の第2の態様は、第1の態様において、前記データベースは、総合的な地中設備の情報を網羅した地域管理センターデータベースをさらに含むことを特徴とする地中電線路のケーブル工事管理システムにある。   According to a second aspect of the present invention, in the first aspect, the database further includes a regional management center database that covers comprehensive underground facility information. In the system.

かかる第2の態様では、総合的な地中設備の情報を参照してケーブル工事設計を行うので、ケーブル工事設計を行った後、総合的な地中設備との兼ね合いでケーブル工事設計を再設計することがなくなり、効率的に作業を行うことができる。   In this second aspect, the cable work design is performed with reference to the information of the comprehensive underground facilities. After the cable work design, the cable work design is redesigned in balance with the comprehensive underground facilities. So that you can work efficiently.

本発明の第3の態様は、第1又は2の態様において、前記ケーブル工事設計手段は、工事設計が完了した時点で必要に応じて前記既設設備データベースを更新することを特徴とする地中電線路のケーブル工事管理システムにある。   According to a third aspect of the present invention, in the first or second aspect, the cable construction design means updates the existing equipment database as necessary when the construction design is completed. It is in the road cable construction management system.

かかる第3の態様では、ケーブルの設計の段階で当該ケーブル工事設計をデータベースに反映することで、続けて関連するケーブル工事設計を行う際に参照することができ、効率的なケーブル工事設計が可能となる。   In the third aspect, by reflecting the cable work design in the database at the cable design stage, it can be referred to when the related cable work design is subsequently performed, and efficient cable work design is possible. It becomes.

本発明の第4の態様は、第1〜3の何れかの態様において、前記ケーブルの工事設計手段は、前記ケーブル工事設計に基づいてケーブルの布設工事を施工する現場を検証した検証データに基づいて前記ケーブル工事設計の実施が困難と判断した場合には、ケーブル工事設計を再設計することを特徴とする地中電線路のケーブル工事管理システムにある。   According to a fourth aspect of the present invention, in any one of the first to third aspects, the cable construction design means is based on verification data obtained by verifying a site where cable laying construction is performed based on the cable construction design. When the cable work design is determined to be difficult, the cable work management system for the underground cableway is characterized by redesigning the cable work design.

かかる第4の態様では、ケーブル工事設計に基づいて現場を検証した際に、ケーブルの布設工事の実施が困難な場合であっても、ケーブル工事設計を再設計することにより、ケーブル工事設計を効率的に且つ正確に行うことができる。   According to the fourth aspect, when the site is verified based on the cable work design, even if it is difficult to carry out the cable laying work, the cable work design is redesigned to improve the efficiency of the cable work design. And accurately.

本発明の第5の態様は、第4の態様において、前記検証データが前記ケーブル工事設計手段にネットワークを介して接続された携帯端末から送られたものであることを特徴とする地中電線路のケーブル工事管理システムにある。   According to a fifth aspect of the present invention, in the fourth aspect, the verification data is sent from a portable terminal connected to the cable construction design means via a network. The cable construction management system.

かかる第5の態様では、施工現場でケーブル工事設計の再設計を行わせることができ、作業効率を向上することができる。   In the fifth aspect, the cable work design can be redesigned at the construction site, and the work efficiency can be improved.

本発明の第6の態様は、第1〜5の何れかの態様において、前記データベースには、前記ケーブルの布設工事に関する作業手順を網羅した作業手順データベースが含まれ、且つ前記ケーブル工事設計に基づいて必要な作業手順を抽出して布設工事を行う施工者の携帯端末に提示する作業手順提示手段をさらに具備することを特徴とする地中電線路のケーブル工事管理システムにある。   According to a sixth aspect of the present invention, in any one of the first to fifth aspects, the database includes a work procedure database covering work procedures relating to the cable laying work, and is based on the cable work design. In the cable work management system for underground cable tracks, further comprising work procedure presenting means for extracting necessary work procedures and presenting them to a portable terminal of a builder who performs laying work.

かかる第6の態様では、施工者が端末を介してケーブルの布設工事の進行状況に従って、必要な作業手順を参照することができるため、作業者の知識及び技術の差に拘わらず正確なケーブルの布設工事を効率的に行うことができると共に、第3者がケーブルの布設工事の進行状況を確認することができる。   In the sixth aspect, since the contractor can refer to the necessary work procedure according to the progress of the cable laying work through the terminal, the correct cable can be obtained regardless of the difference in the knowledge and skill of the worker. The laying work can be performed efficiently, and a third party can check the progress of the cable laying work.

本発明の第7の態様は、第1〜6の何れかの態様において、前記他工事設計が、配管の管路工事設計、マンホール工事設計、ハンドホール工事設計、機器設置工事設計及び地中引込線工事設計から選択される少なくとも1つからなることを特徴とする地中電線路のケーブル工事管理システムにある。   According to a seventh aspect of the present invention, in any one of the first to sixth aspects, the other construction design is a pipe construction design, a manhole construction design, a handhole construction design, an equipment installation construction design, and an underground service line. The cable construction management system of the underground cableway is characterized by comprising at least one selected from construction design.

かかる第7の態様では、ケーブルの布設工事の設計を行う際に、管路工事設計、マンホール工事設計、ハンドホール工事設計、機器設置工事設計及び地中引込線工事設計の少なくとも1つを参照することにより、他の工事設計に最適なケーブル工事設計を設計することができると共に、効率的に設計することができる。   In the seventh aspect, when designing the cable laying work, refer to at least one of the pipe work design, the manhole work design, the handhole work design, the equipment installation work design, and the underground service line work design. As a result, it is possible to design a cable work design that is optimal for other work designs and to design efficiently.

本発明によれば、地中電線路の布設設計及び他の工事設計に基づいて、ケーブルの布設工事の設計を効率的且つ正確に行うことができるという効果を奏する。   Advantageous Effects of Invention According to the present invention, there is an effect that a cable laying design can be efficiently and accurately performed based on an underground cable laying design and other construction designs.

以下に本発明を実施形態に基づいて詳細に説明する。   Hereinafter, the present invention will be described in detail based on embodiments.

(実施形態1)
図1は、本発明の実施形態1に係る地中電線路のケーブル工事管理システムの概略構成を示す図であり、図2は、ケーブル工事管理システムの設計データを示す図である。
(Embodiment 1)
FIG. 1 is a diagram showing a schematic configuration of a cable work management system for underground cable tracks according to Embodiment 1 of the present invention, and FIG. 2 is a diagram showing design data of the cable work management system.

図1に示すように、ケーブル工事管理システムは、ケーブル工事管理サーバ100を具備し、ケーブル工事管理サーバ100には、ケーブルの布設工事を行うために必要な各種データが蓄積されたデータベース(DB)200と、地中電線路のケーブル、ルート及び布設方式が選定された布設設計130に基づいてデータベース200を参照しながらケーブル工事設計140を行うケーブル工事設計手段110とが備えられている。   As shown in FIG. 1, the cable work management system includes a cable work management server 100, and the cable work management server 100 stores a database (DB) in which various data necessary for cable laying work are stored. 200 and a cable construction design means 110 that performs a cable construction design 140 while referring to the database 200 based on the laying design 130 in which the cable, the route, and the laying method of the underground electric line are selected.

かかるケーブル工事管理サーバ100には、所定のネットワーク10を介して所定の端末20が接続できるようになっている。ここで端末20は、上述したケーブル工事設計140を行う社内部署の端末、又は工事請負会社等の外部会社の端末、あるいは布設工事を行う施工者が携帯する端末等であり、本実施形態では社内部署の端末とした。また、ネットワーク10は、LANや専用線やインターネットを介しての接続手段をいう。   A predetermined terminal 20 can be connected to the cable construction management server 100 via a predetermined network 10. Here, the terminal 20 is a terminal of an in-house department that performs the cable construction design 140 described above, a terminal of an external company such as a construction contractor, or a terminal that is carried by a builder who performs laying work. It was a department terminal. The network 10 is a connection means via a LAN, a dedicated line, or the Internet.

地中電線路の布設設計130は、図2に示すように、電力供給計画に基づいて地中電線路のケーブル131の線種、ルート132及び布設方式133が少なくとも選定されたものである。地中電線路のケーブル131とは、布設されるケーブルが特別高圧線、高圧線、高圧引込線、低圧幹線、低圧引込線又は保安通信線等の線種や、ケーブルの太さ、条数などが少なくとも選定されたものである。   As shown in FIG. 2, the underground cable laying design 130 is such that at least the line type of the cable 131, the route 132, and the laying method 133 are selected based on the power supply plan. The cable 131 of the underground cableway is at least a line type such as a special high-voltage line, high-voltage line, high-voltage lead-in line, low-voltage trunk line, low-voltage lead-in line or security communication line, the thickness of the cable, the number of strips, etc. It has been selected.

また、地中電線路のルート132とは、ケーブル131を布設する道筋を表すものであり、地図データに照らし合わせて道路などの布設可能な領域に沿って設計されたものであるが、既存の布設設備を利用する領域や既設の管路や共同溝を利用する領域も含めてルートという。   The underground cable route 132 represents a route for laying the cable 131 and is designed along a layable area such as a road in light of map data. The route includes the area where the laying facilities are used and the area where existing pipes and common grooves are used.

さらに地中電線路の布設方式133とは、ケーブル131を地中に直接埋設する方法、ケーブル131を配管で埋設する方法及び上下水やガスなどの他の配管と共に共同溝に布設する方法などが選定されたものである。この布設方式133は、ルート132と関連付けて設定されることで、ルート132を所定の領域で区画して設定されている。例えば、布設されるケーブル131のルート132の一部の領域に既設の共同溝がある場合には、その領域が共同溝で設定され、その他の領域が直埋式や配管式などの他の方式で設定される。   Further, the underground cableway laying method 133 includes a method of directly burying the cable 131 in the ground, a method of burying the cable 131 in a pipe, and a method of laying in a common groove together with other pipes such as water, sewage and gas. It has been selected. The laying method 133 is set in association with the route 132, thereby dividing the route 132 into predetermined areas. For example, when there is an existing common groove in a part of the route 132 of the cable 131 to be laid, the region is set as the common groove, and the other regions are other methods such as a direct buried type and a piping type. Set by.

このような布設設計130は、本実施形態では、端末20から入力されるようにしたが、特にこれに限定されるものではなく、例えば、布設設計130を行う布設設計サーバをネットワーク10を介して接続し、この布設設計サーバから布設設計130が入力されるようにしてもよい。   In the present embodiment, such a laying design 130 is input from the terminal 20, but is not particularly limited thereto. For example, a laying design server that performs the laying design 130 is provided via the network 10. The laying design server 130 may be input from the laying design server.

一方、データベース(DB)200は、地中電線路の既存設備を網羅した既設設備データベース210と、地中電線路を布設するために検討すべき情報及び法令を網羅した布設情報データベース220と、各種設備の工事基準及び法令を網羅した工事基準データベース230と、ケーブル工事設計以外の他の設備の布設工事の工事設計を含む工事設計データベース240とを少なくとも含むものであり、本実施形態では、さらに、総合的な地中設備の情報を網羅した地域管理センターデータベース250を具備する。データベース200は、これに限定されるものではなく、さらに必要な情報を備えるものであってもよい。また、データベース200は、ケーブル工事管理サーバ100に設けられているように図示しているが、これに限定されず、全部又は一部がネットワーク等を介して接続され、ケーブル工事設計手段110が参照できるものであればよい。   On the other hand, the database (DB) 200 includes an existing equipment database 210 that covers existing equipment for underground cables, a laying information database 220 that covers information and laws to be examined for laying underground cables, It includes at least a construction standard database 230 that covers the construction standards and laws and regulations of equipment, and a construction design database 240 that includes construction design of installation work other than cable construction design. In this embodiment, A regional management center database 250 that includes comprehensive underground facility information is provided. The database 200 is not limited to this, and may further include necessary information. Further, the database 200 is illustrated as being provided in the cable construction management server 100, but is not limited to this, and all or part of the database 200 is connected via a network or the like, and the cable construction design unit 110 refers to the database 200. Anything is possible.

ここで、既存設備データベース210は、既設の地中電線路のルート、布設方式、ケーブル、配管の詳細な仕様、マンホール、ハンドホール及び機器の位置及び構造などの既存の地中電線路に関するあらゆる情報が蓄積されている。   Here, the existing equipment database 210 is all information related to existing underground cables such as existing underground cable routes, installation methods, detailed specifications of cables, piping, manholes, hand holes and equipment positions and structures. Is accumulated.

また、布設情報データベース220は、地中電線路を布設するために検討すべき情報及び法令を網羅したものであり、技術的課題である地形情報や、地域情報、道路法や河川法などの各種法令情報などである。具体的には、例えば、埋立地などの地盤に関するデータや、道路の幅及び勾配などの道路に関するデータや、道路標識の位置、消火栓の位置、電柱などの施設に関するデータや、地中電線路の禁止区域のデータなどが挙げられる。   In addition, the laying information database 220 covers information and laws that should be considered for laying underground cables, and various technical information such as terrain information, regional information, road law, river law, etc. Legal information. Specifically, for example, data on the ground such as landfills, data on roads such as road width and slope, data on facilities such as the position of road signs, the position of fire hydrants, utility poles, Examples include prohibited area data.

さらに、工事基準データベース230は、地中電線路のケーブルの布設工事に関する工事基準及び法令を網羅したものである。具体的には、工事基準データベース230には、ケーブルの布設工事の工法に関する布設工法選定データ、マンホール等の施設にケーブルを布設する際の布設選定データ、ケーブルの接地に関する接地選定データなどが挙げられる。   Furthermore, the construction standard database 230 covers construction standards and laws and regulations relating to cable laying work for underground cable tracks. Specifically, the construction standard database 230 includes laying method selection data relating to the cable laying construction method, laying selection data when laying the cable in a facility such as a manhole, and grounding selection data relating to cable grounding. .

布設工法選定データとしては、例えば、ケーブルと引込用ワイヤロープとを接続する際にワイヤーグリップ又はプーリングアイなどの治具の選定、ケーブルを引入れる際に用いられるドラムの胴径の選定、引入れ方向の選定、導線の有無の選定、滑剤の有無の選定、管路の清掃及び導通試験の選定、引入れ用ワイヤロープのよりもどし器の有無の選定などの引入れ選定データや、引入式管路のケーブル撤去工事に関する選定データなどが挙げられる。   For example, when selecting the laying method selection data, select a jig such as a wire grip or pooling eye when connecting the cable and the pull-in wire rope, select the drum diameter used when pulling in the cable, and pull in. Inlet selection data, such as selection of direction, selection of presence / absence of conductor, selection of presence / absence of lubricant, selection of pipe line cleaning and continuity test, selection of presence / absence of twister of lead-in wire rope, and retractable pipe This includes selection data on road cable removal work.

また、布設選定データとしては、例えば、マンホール内でのケーブルの配置間隔及び支持間隔の選定データや、洞道内でのケーブルの配置間隔と支持間隔の選定データや、マンホール及び洞道内でケーブルを支持するケーブル立金物、ケーブル受金物、ケーブル受枕等の支持部材の選定データや、ケーブルのオフセットの選定データや、ケーブルを傾斜地に布設する際の防水栓の有無の選定データや、電柱立上り箇所の設定や、ケーブルの直線接続や端末処理の選定データなどが挙げられる。   In addition, as the laying selection data, for example, the selection data of the cable arrangement interval and the support interval in the manhole, the selection data of the cable arrangement interval and the support interval in the cavern, and the cable support in the manhole and the cavern Selection data for supporting members such as cable brackets, cable brackets and cable pillows, selection data for cable offsets, selection data for the presence or absence of waterproof plugs when laying cables on sloping ground, For example, setting data, straight line connection of a cable, selection data for terminal processing, and the like.

さらに、接地選定データとしては、例えば、誘起電圧によるケーブルの片端接地や両端接地などの接地の選定データや、架空線と地中線との接続箇所における接地の共有方法の選定データなどが挙げられる。   Furthermore, as the ground selection data, for example, ground selection data such as one-end grounding or both-end grounding of the cable by induced voltage, grounding sharing method selection data at the connection point between the overhead wire and the underground wire, etc. .

なお、工事基準データベース230には、地中電線路の他の設備工事に関する工事基準及び法令が蓄積されるようにしてもよい。ここで他の地中電線路の他の設備工事としては、例えば、配管、マンホール、ハンドホール、機器及び地中引込線等の各種工事が挙げられる。   Note that the construction standards database 230 may store construction standards and laws related to other equipment construction of underground cable conduits. Here, as other installation work of other underground electric lines, for example, various works such as piping, manholes, hand holes, equipment, underground service lines and the like can be cited.

また、工事設計データベース240には、布設設計130に基づいて設計された地中電線路のケーブル工事設計140以外の他の設備の工事設計が蓄積されている。他の工事設計としては、例えば、配管の管種、管内径及び管路数等を規定した管路工事設計、マンホールの設置場所や構造などを規定したマンホール工事設計、ハンドホールの設置場所や構造などを規定したハンドホール工事設計、ハンドホール等に設置される機器の種類及び設置方法などを規定した機器設置工事設計、地中引込線の布設方法や地中電線路との接続等を規定した地中引込線工事設計などが挙げられる。   In addition, the work design database 240 stores work designs of facilities other than the cable work design 140 of the underground cableway designed based on the laying design 130. Other construction designs include, for example, pipe construction design that specifies pipe types, pipe inner diameter and number of pipes, manhole construction design that specifies manhole installation locations and structures, and handhole installation locations and structures. Handhole construction design that stipulates, etc., equipment installation work design that stipulates the type and installation method of equipment installed in handholes, etc. Middle lead-in line construction design.

また、地域管理センターデータベース250は、総合的な地中設備の情報を網羅したものであり、例えば、地中電線路以外の上下水道やガスなど他の配管のルート、管路数、管径及び布設方法や、水道管用のマンホールなどの設備及び機器の位置、構造などが挙げられる。なお、地域管理センターデータベース250は、ケーブル工事管理システムのデータベース200に蓄積されていなくてもよく、外部に設置されているものであってもよい。   In addition, the regional management center database 250 covers comprehensive underground facility information. For example, other piping routes such as water and sewage and gas other than underground electric lines, the number of pipes, pipe diameters, Examples include the laying method and the location and structure of equipment and equipment such as manholes for water pipes. The regional management center database 250 may not be stored in the database 200 of the cable construction management system, and may be installed outside.

このようなデータベース200の各種データを参照しながら、ケーブル工事設計手段110は、入力された布設設計130に基づいてケーブルの布設工事のケーブル工事設計140を行う。ここでケーブル工事設計手段110が設計するケーブル工事設計140は、図2に示すように、ケーブルの布設工法141、マンホール等の施設への布設方法などを含むケーブルの布設方法142及びケーブルの接地方法143等が挙げられる。   The cable construction design means 110 performs the cable construction design 140 of the cable laying construction based on the inputted laying design 130 while referring to such various data in the database 200. Here, the cable construction design 140 designed by the cable construction design means 110 includes, as shown in FIG. 2, a cable laying method 141 including a cable laying method 141, a laying method in a facility such as a manhole, and a cable grounding method. 143 etc. are mentioned.

ここで、ケーブルの布設工法141としては、例えば、管路工事設計によって設計された配管にマンホール工事設計によって設計されたマンホールからケーブルを引き入れる際のケーブルを巻き付けるドラムの胴径の設計や、引入れ方向の設計や、導線の有無の選定、滑剤の有無の設計、管路の清掃及び導通試験の設計、引入れ用ワイヤロープのよりもどし器の有無の設計などが挙げられる。   Here, as the cable laying method 141, for example, the design of the drum diameter for winding the cable when the cable is drawn from the manhole designed by the manhole construction design into the pipe designed by the pipe construction design, Design of direction, selection of presence / absence of conducting wire, design of presence / absence of lubricant, design of conduit cleaning and continuity test, design of presence / absence of twister of lead-in wire rope, and the like.

例えば、ケーブル工事設計手段110は、布設設計130によって設計されたケーブルの線種が多心(遮蔽なし)ケーブルの場合、布設設計130によって設計されたケーブルの線径をDmmとすると、ケーブルを巻き付けるドラムの胴径が12Dmm以上となるように設計する。また、ケーブル工事設計手段110は、ドラムの胴径を設計する際に、布設情報データベース220の地域情報を参照することによって、ケーブルを引入れるマンホールの近くにドラムを配置できるかなどを考慮するようになっている。   For example, when the cable type designed by the laying design 130 is a multi-core (unshielded) cable, the cable construction design means 110 winds the cable when the diameter of the cable designed by the laying design 130 is Dmm. The drum diameter is designed to be 12 Dmm or more. Further, when designing the drum diameter, the cable construction design means 110 refers to the regional information in the laying information database 220 so as to consider whether the drum can be arranged near the manhole into which the cable is drawn. It has become.

また、例えば、ケーブル工事設計手段110は、ケーブルを引き入れる際の引入張力が小さい方から引入れるように引入れ方向を設計する。この引入張力は、例えば、布設する配管や洞道に高低差がある場合には、ケーブルを高い方から引入れるように設計し、また、配管や洞道の途中に屈曲箇所がある場合には、屈曲箇所に近い方から引入れるように設計する。このようにケーブル工事設計手段110が引入れ方向を設計する際に参照する高低差や屈曲箇所等の情報は、既設設備データベース210の既設の配管情報、布設情報データベース220の地形情報、工事設計データベース240の配管工事設計、地域管理センターデータベース250のケーブル以外のガス、上下水道管などが布設された共同溝の情報などから取得することができる。   In addition, for example, the cable construction design unit 110 designs the drawing direction so that the cable is drawn from the one with the smaller drawing tension when the cable is drawn. This pull-in tension is designed so that the cable is pulled in from the higher side, for example, when there is a height difference in the pipes and caverns to be installed, and when there is a bent part in the middle of the pipes and caverns Designed to be pulled in from the side closer to the bend. As described above, the information such as the height difference and the bent portion referred to when the cable construction design means 110 designs the pull-in direction is the existing piping information in the existing equipment database 210, the terrain information in the laying information database 220, and the construction design database. It can be acquired from 240 piping work design, gas other than cables in the regional management center database 250, information on common grooves where water and sewage pipes are laid, and the like.

また、ケーブルの布設方法142の設計は、例えば、マンホール内でのケーブルの配置間隔及び支持間隔の設計や、洞道内でのケーブルの配置間隔と支持間隔の設計や、マンホール及び洞道内でケーブルを支持するケーブル立金物、ケーブル受金物、ケーブル受枕等の支持部材の設計や、ケーブルのオフセットの設計や、ケーブルを傾斜地に布設する際の防水栓の有無の設計や、電柱立上り箇所の設計や、ケーブルの直接接続や端末処理の設計などが挙げられる。   In addition, the cable laying method 142 may be designed, for example, by designing the arrangement interval and the support interval of the cable in the manhole, designing the arrangement interval and the support interval of the cable in the sinus, Design of supporting members such as cable brackets to be supported, cable brackets, cable pillows, offset design of cables, design of presence or absence of waterproof plugs when laying cables on sloping ground, design of rising parts of utility poles, , Direct cable connection and terminal processing design.

例えば、ケーブル工事設計手段110は、布設設計130により設計されたケーブルの線種が高圧ケーブルの場合、マンホール内でケーブルの接続部で床から最低接続部までの高さが380mmとなるように設計する。また、高圧ケーブルのマンホール内での支持間隔が500mmとなるように設計する。このとき、工事設計データベース240に蓄積されたマンホール工事設計を参照することで、マンホールの幅、奥行き及び深さを取得し、マンホールの構造に合わせてケーブルの接続部の高さやケーブルの支持間隔を適宜設計することができる。   For example, the cable construction design means 110 is designed so that the height from the floor to the lowest connection portion in the manhole is 380 mm when the line type of the cable designed by the laying design 130 is a high voltage cable. To do. Also, the support interval in the manhole of the high voltage cable is designed to be 500 mm. At this time, by referring to the manhole construction design stored in the construction design database 240, the width, depth, and depth of the manhole are obtained, and the height of the cable connection portion and the cable support interval are determined in accordance with the manhole structure. It can be designed as appropriate.

さらに、ケーブルの接地設計は、例えば、誘起電圧によるケーブルの片端接地や両端接地などの接地の設計や、架空線と地中線との接続箇所における接地の共有方法の設計などが挙げられる。   Further, the grounding design of the cable includes, for example, a grounding design such as single-sided grounding or double-sided grounding of the cable by an induced voltage, and a design of a ground sharing method at a connection point between the overhead wire and the underground wire.

例えば、ケーブル工事設計手段110は、ケーブル立ち上がり柱に変圧器が施設される場合、第2種設置工事を単独で施工するように設計する。このときの変圧器の有無は、例えば、工事設計データベース240や、既設設備データベース210などを参照することで取得することができる。   For example, when the transformer is installed on the cable rising column, the cable construction design means 110 designs so that the second type installation work is performed independently. The presence or absence of the transformer at this time can be acquired by referring to the construction design database 240, the existing equipment database 210, or the like, for example.

このように、ケーブル工事設計手段110は、布設設計130に基づいて、データベース200を参照しながら総合的に判断して、地中電線路のケーブルの布設工事の詳細なケーブル工事設計140を出力する。   As described above, the cable construction design means 110 comprehensively makes a judgment based on the laying design 130 while referring to the database 200, and outputs the detailed cable construction design 140 of the cable laying work of the underground cableway. .

また、ケーブル工事設計手段110は、種々検討した結果、ケーブルの布設工事のケーブル工事設計140が困難な場合にはデータベース200に蓄積された他の工事設計を再検討させる段階に戻すようにする。そして、再設計された他の工事設計を参照しながら検討し、ケーブル工事設計を作成する。   In addition, as a result of various studies, the cable work design unit 110 returns to the stage of reviewing other work designs stored in the database 200 when the cable work design 140 of the cable laying work is difficult. Then, the cable work design is created by examining the redesigned other work design.

ここで、ケーブル工事設計手段110によるケーブル工事設計140が困難な場合とは、例えば、管路工事設計で設計された配管の曲率半径が、ケーブルの許容曲げ半径よりも小さい場合などが挙げられる。このような場合には、ケーブル工事設計手段110は、ケーブルの許容曲げ半径に適した配管の管路工事設計を検討させて、管路工事設計を再設計させるようにする。   Here, the case where the cable work design 140 by the cable work design means 110 is difficult includes, for example, the case where the curvature radius of the pipe designed by the pipe work design is smaller than the allowable bending radius of the cable. In such a case, the cable work design means 110 examines the pipe work design suitable for the allowable bending radius of the cable and redesigns the pipe work design.

このように、ケーブル工事設計手段110は、布設設計130に基づいて、データベース200を参照しながらケーブル工事設計140を行うが、データベース200に蓄積された種々のデータからケーブル工事設計140の作成が困難な場合、すなわち、ケーブル工事設計140を作成できない場合には、他の工事設計を再設計(再検討)させる段階に戻すことで、管路工事設計、マンホール工事設計、ハンドホール工事設計、機器工事設計及び地中引込線工事設計などの再設計を行わせるようになっている。そして、ケーブル工事設計手段110は、布設設計130に基づいて、再設計された他の工事設計を含むデータベース200を参照しながら、ケーブル工事設計140を再設計するようになっている。このように、ケーブル工事設計手段110は、データベース200を参照してケーブル工事設計140が困難な場合には、他の工事設計を再設計させる段階に戻し、ケーブル工事設計140を繰り返し行うことで、電力供給計画に基づいた最適なケーブルの布設工事のケーブル工事設計140を効率的に且つ正確に行うことができる。   As described above, the cable work design unit 110 performs the cable work design 140 while referring to the database 200 based on the laying design 130. However, it is difficult to create the cable work design 140 from various data stored in the database 200. In other words, that is, when the cable work design 140 cannot be created, it is returned to the stage where another work design is redesigned (reconsidered), so that the pipe work design, the manhole work design, the handhole work design, the equipment work It is designed to perform redesign such as design and underground service line construction design. Then, the cable work design means 110 redesigns the cable work design 140 based on the laying design 130 while referring to the database 200 including other redesigned work designs. As described above, the cable construction design unit 110 refers to the database 200, and when the cable construction design 140 is difficult, the cable construction design unit 110 returns to the stage of redesigning another construction design, and repeatedly performs the cable construction design 140. It is possible to efficiently and accurately perform the cable work design 140 of the optimal cable laying work based on the power supply plan.

なお、ケーブル工事設計140が完了すると、この布設工事が実行される可能性が高いので、例えば、既設設備データベース210に登録するようにする。これは、次の布設設計130に基づいて設計されるケーブル工事設計140に利用させるためである。勿論、計画中の設備専用のデータベースを作成して、参照できるようにしておいてもよい。   Note that, when the cable work design 140 is completed, there is a high possibility that this laying work will be executed. This is for use in the cable work design 140 designed based on the next laying design 130. Of course, it is also possible to create a dedicated database for the planned facility so that it can be referred to.

また、本実施形態では、ケーブル工事設計140に基づいて施工者などがケーブルの布設工事を施工する現場を検証した検証データ160をケーブル工事設計手段110が受け取り、ケーブル工事設計手段110は、受け取った検証データ160と設計したケーブル工事設計140とに基づいてケーブルの布設工事を行うのが困難か判断する。そして、ケーブル工事設計手段110は、ケーブルの布設工事が困難と判断した場合には、検証データ160を参照してケーブル工事設計140を再設計するようになっている。   In the present embodiment, the cable construction design means 110 receives the verification data 160 that verifies the site where the installer lays the cable laying work based on the cable construction design 140, and the cable construction design means 110 receives the verification data 160. Based on the verification data 160 and the designed cable work design 140, it is determined whether it is difficult to perform the cable laying work. The cable construction design means 110 redesigns the cable construction design 140 with reference to the verification data 160 when it is determined that the cable laying construction is difficult.

ここで、ケーブルの布設工事を行うのが困難な場合とは、工事設計140に基づいて実際に施工される現場検証を行った結果、例えば、他の地中設備によってケーブルの引込工事が行えない場合や、地上建造物等の影響でケーブルの引込工事が行えない場合や、マンホールやハンドホールの接地位置の変更などが必要となる場合などである。このような場合には、端末20を介して検証データ160がケーブル工事設計手段110に送られることで、ケーブル工事設計手段110はケーブル工事設計140の変更が必要か判断し、必要と判断した場合には、ケーブル工事設計の再設計を行ったり、他の工事設計を検討させるようになっている。   Here, the case where it is difficult to carry out cable laying work means that, as a result of performing on-site verification based on the construction design 140, for example, the cable drawing work cannot be performed by other underground facilities. There are cases where the cable pull-in work cannot be performed due to the influence of the ground structure, etc., or when the grounding position of the manhole or handhole needs to be changed. In such a case, when the verification data 160 is sent to the cable construction design means 110 via the terminal 20, the cable construction design means 110 judges whether or not the cable construction design 140 needs to be changed. The company redesigns the cable work design and considers other work designs.

ここで、このようなケーブル工事管理システムの動作について詳細に説明する。なお、図3は、ケーブル工事管理システムの動作を示すフローチャートである。   Here, the operation of such a cable work management system will be described in detail. FIG. 3 is a flowchart showing the operation of the cable construction management system.

まず、ステップS1で電力供給計画に基づいて布設設計130が設計されると、ステップS2で地中電線路の管路工事設計、マンホール工事設計、ハンドホール工事設計、機器工事設計及び地中引込線工事設計などのケーブル工事設計以外の他の工事設計が行われる。そして、ステップS3でケーブル工事設計手段110が布設設計130に基づいて、データベース200を参照しながらケーブルの布設工事のケーブル工事設計140の設計を開始する。そして、ステップS4でケーブル工事設計手段110がケーブルの布設工事のケーブル工事設計140ができたか判断し、ケーブル工事設計140ができた場合には(ステップS4;Yes)、ステップS5でケーブル工事設計手段110によるケーブル工事設計140が完了すると共にケーブル工事設計140が出力される。そして、ステップS6でケーブル工事設計手段110がケーブル工事設計140で既設設備データベース210を更新する。また、ステップS4でケーブル工事設計ができなかった場合には(ステップS4;No)、ステップS2に戻り他の工事設計が再設計される。   First, when the laying design 130 is designed based on the power supply plan in step S1, the conduit construction design, the manhole construction design, the handhole construction design, the equipment construction design, and the underground lead-in construction for the underground cable conduit in step S2. Other construction designs other than cable construction design such as design are performed. In step S <b> 3, the cable work design unit 110 starts designing the cable work design 140 of the cable laying work with reference to the database 200 based on the laying design 130. In step S4, the cable construction design means 110 determines whether or not the cable construction design 140 for cable laying construction has been completed. If the cable construction design 140 has been completed (step S4; Yes), the cable construction design means in step S5. When the cable work design 140 according to 110 is completed, the cable work design 140 is output. In step S6, the cable work design unit 110 updates the existing equipment database 210 with the cable work design 140. If the cable work design cannot be performed in step S4 (step S4; No), the process returns to step S2 and another work design is redesigned.

その後は、ステップS7でケーブル工事設計手段110が、ケーブル工事設計140に基づいて施工者が実際にケーブルの布設工事ができるか現場の検証を行った検証データ160を受け取り、ケーブル工事設計手段110が検証データ160とケーブル工事設計140とに基づいてケーブルの布設工事ができないと判断した場合には(ステップS7;No)、ステップS3〜ステップS6を繰り返し行い、ケーブルの布設工事のケーブル工事設計140を再設計すると共に新たなケーブル工事設計140で既設設備データベースを更新する。また、ステップS7でケーブル工事設計手段110が検証データ160を受け取ったにも拘わらず、検証データ160とケーブル工事設計140とに基づいてケーブルの布設工事ができると判断した場合には(ステップS7;Yes)、ステップS8で実際にケーブルの布設工事を行う。   After that, in step S7, the cable construction design means 110 receives the verification data 160 obtained by performing on-site verification based on the cable construction design 140 so that the builder can actually perform the cable laying work. If it is determined that the cable laying work cannot be performed based on the verification data 160 and the cable work design 140 (No at Step S7), Steps S3 to S6 are repeated to perform the cable work design 140 for the cable laying work. While redesigning, the existing equipment database is updated with the new cable construction design 140. If it is determined in step S7 that the cable construction design means 110 has received the verification data 160, but the cable laying construction can be performed based on the verification data 160 and the cable construction design 140 (step S7; Yes), cable laying work is actually performed in step S8.

なお、このステップS7で、ケーブル工事設計手段110が受け取る検証データ160は、施工者がケーブルの布設工事を施工している最中に、予期せぬ障害物等でケーブルの布設工事のケーブル工事設計140を再設計しなければならない場合のデータも含むものである。   In this step S7, the verification data 160 received by the cable construction design means 110 is the cable construction design of the cable laying work with an unexpected obstacle while the builder is laying the cable. It also includes data when 140 has to be redesigned.

(実施形態2)
図4は、本発明の実施形態2に係る地中電線路のケーブル工事管理システムの概略構成を示す図である。図4に示すように、本実施形態の地中電線路のケーブル工事管理サーバ100Aには、ケーブルの布設工事を施工する施工者が携帯する端末20Aがネットワーク10を介して接続されている。
(Embodiment 2)
FIG. 4: is a figure which shows schematic structure of the cable construction management system of the underground cable track which concerns on Embodiment 2 of this invention. As shown in FIG. 4, a terminal 20 </ b> A carried by a contractor who performs cable laying work is connected to the cable work management server 100 </ b> A of the underground cableway of this embodiment via a network 10.

また、ケーブル工事管理サーバ100Aに備えられたデータベース200Aには、ケーブルの布設工事に関する作業手順170が蓄積された作業手順データベース260が含まれている。さらに、ケーブル工事管理サーバ100Aには、この作業手順データベース260からケーブル工事設計140に関する必要な作業手順170を抽出し、施工者が携帯する端末20Aに提示する作業手順提示手段120を具備する。   Further, the database 200A provided in the cable construction management server 100A includes a work procedure database 260 in which work procedures 170 relating to cable installation work are stored. Furthermore, the cable work management server 100A includes work procedure presenting means 120 that extracts a necessary work procedure 170 related to the cable work design 140 from the work procedure database 260 and presents the work procedure 170 to the terminal 20A carried by the installer.

作業手順提示手段120は、端末20Aからの要求180に応じて、ケーブル工事設計140に基づいてケーブルの布設工事に適した作業手順170を作業手順データベース260から抽出し、端末20Aに送信する。そして、施工者は、端末20Aの画面に表示された作業手順170に従ってケーブルの布設工事を進めることができる。このように、施工者が、ケーブル工事設計140に基づく作業手順170を参照しながら、ケーブルの布設工事を行うことができるため、施工者の知識や技術力の差に拘わらず、ケーブルの布設工事を効率的に且つ正確に行うことができる。また、施工者の端末20Aから送られる要求180には作業の進行状況を含むものとしてもよく、これにより作業手順提示手段120は、要求180に含まれる作業の進行状況に合わせて作業手順170を端末20Aに提示することができる。また、要求180に作業の進行状況を含ませることにより、管理工事管理サーバ100Aは、ケーブルの布設工事の進行状況を常に把握することができ、端末20を介して第3者に作業の進行状況を確認させることができる。これにより、ケーブルの布設工事の管理を効率的に行うことができる。   In response to a request 180 from the terminal 20A, the work procedure presenting means 120 extracts a work procedure 170 suitable for cable laying work from the work procedure database 260 based on the cable work design 140, and transmits it to the terminal 20A. Then, the installer can proceed with the cable laying work in accordance with the work procedure 170 displayed on the screen of the terminal 20A. As described above, the cable laying work can be performed by the builder while referring to the work procedure 170 based on the cable work design 140. Therefore, the cable laying work is performed regardless of the difference in the knowledge and technical ability of the builder. Can be performed efficiently and accurately. Further, the request 180 sent from the builder's terminal 20A may include the progress status of the work, whereby the work procedure presenting means 120 can change the work procedure 170 in accordance with the progress status of the work included in the request 180. It can be presented to the terminal 20A. Also, by including the work progress status in the request 180, the management work management server 100A can always grasp the progress status of the cable laying work, and the work progress status is sent to the third party via the terminal 20. Can be confirmed. Thereby, management of the cable laying work can be performed efficiently.

また、本実施形態では、施工者が携帯した端末20Aから、検証データ160が送信できるようになっている。これは、ケーブルの布設工事の最中であっても、ケーブル工事設計140を再設計させることができると共に、再設計されたケーブル工事設計140を施工者が布設工事を行っている現場で確認することができ、さらにケーブルの布設工事を効率的に且つ正確に行うことができる。   In the present embodiment, the verification data 160 can be transmitted from the terminal 20A carried by the installer. This is because the cable work design 140 can be redesigned even during the cable laying work, and the redesigned cable work design 140 is confirmed at the site where the builder is performing the laying work. In addition, the cable laying work can be performed efficiently and accurately.

(他の実施形態)
以上、本発明の各実施形態について説明したが、本発明は上述したものに限定されるものではない。例えば、上述した実施形態1及び2では、データベース200、200Aに既設設備データベース210と地域管理センターデータベース250とが含まれるようにしたが、既設設備データベース210が地域管理センターデータベース250に含まれるようにしてもよい。すなわち、地域管理センターデータベースには、地中電線路の既設設備の情報と、地中電線路以外の他の既設の地中設備の情報との全ての地中設備に関する情報が蓄積されて一元管理できるようにしてもよい。
(Other embodiments)
As mentioned above, although each embodiment of this invention was described, this invention is not limited to what was mentioned above. For example, in the first and second embodiments described above, the existing facilities database 210 and the regional management center database 250 are included in the databases 200 and 200A, but the existing facilities database 210 is included in the regional management center database 250. May be. In other words, in the regional management center database, information on all underground facilities, including information on existing facilities on underground cables and information on existing underground facilities other than underground cables, is accumulated and managed centrally. You may be able to do it.

また、例えば、データベース200、200Aに蓄積される各種データは、端末20、20Aを用いて更新されるようにすればよい。すなわち、地中電線路以外の上下水管、ガスなどの他の配管や、上下水管用のマンホール、機器などの地中設備が布設された際に、端末20、20Aによって地域管理センターデータベース250を更新するようにすればよい。   Further, for example, various data stored in the databases 200 and 200A may be updated using the terminals 20 and 20A. In other words, when underground facilities such as water and sewage pipes other than underground cables, gas pipes, manholes for water and sewage pipes, and equipment are installed, the regional management center database 250 is updated by the terminals 20 and 20A. You just have to do it.

さらに、上述した実施形態1及び2では、ケーブル工事管理サーバ100、100Aと、このケーブル工事管理サーバ100、100Aにネットワーク10を介して接続される端末20、20Aとでケーブル工事管理システムを構成するようにしたが、特にこれに限定されず、例えば、ケーブル工事管理サーバに、各種データの入出力を行う入出力手段を設けることで、ケーブル工事管理サーバが独立したケーブル工事管理システムとして機能するようにしてもよい。   Further, in the first and second embodiments described above, the cable work management server 100, 100A and the terminal 20, 20A connected to the cable work management server 100, 100A via the network 10 constitute a cable work management system. However, the present invention is not limited to this. For example, by providing the cable construction management server with input / output means for inputting / outputting various data, the cable construction management server functions as an independent cable construction management system. It may be.

本発明の実施形態1に係る地中電線路のケーブル工事管理システムの概略構成を示す図である。BRIEF DESCRIPTION OF THE DRAWINGS It is a figure which shows schematic structure of the cable construction management system of the underground electric wire way which concerns on Embodiment 1 of this invention. 本発明の実施形態1に係るケーブル工事管理システムの設計データを示す図である。It is a figure which shows the design data of the cable construction management system which concerns on Embodiment 1 of this invention. 本発明の実施形態1に係る地中電線路のケーブル工事管理システムの動作を示すフローチャートである。It is a flowchart which shows operation | movement of the cable construction management system of the underground electric wire way which concerns on Embodiment 1 of this invention. 本発明の実施形態2に係る地中電線路のケーブル工事管理システムの概略構成を示す図である。It is a figure which shows schematic structure of the cable construction management system of the underground electric wire way which concerns on Embodiment 2 of this invention.

符号の説明Explanation of symbols

10 ネットワーク
20、20A 端末
100、100A ケーブル工事管理サーバ
110 ケーブル工事設計手段
120 作業手順提示手段
130 布設設計
140 ケーブル工事設計
160 検証データ
170 作業手順
180 要求
200、200A データベース
210 既設設備データベース
220 布設情報データベース
230 工事基準データベース
240 工事設計データベース
250 地域管理センターデータベース
260 作業手順データベース


DESCRIPTION OF SYMBOLS 10 Network 20, 20A Terminal 100, 100A Cable construction management server 110 Cable construction design means 120 Work procedure presentation means 130 Installation design 140 Cable construction design 160 Verification data 170 Operation procedure 180 Request 200, 200A Database 210 Existing equipment database 220 Installation information database 230 Construction Standard Database 240 Construction Design Database 250 Regional Management Center Database 260 Work Procedure Database


Claims (7)

地中電線路のケーブルを布設するための地中電線路のケーブル工事管理システムであって、
地中電線路の既設設備を網羅した既設設備データベースと、地中電線路を布設するために検討すべき情報及び法令を網羅した布設情報データベースと、各種設備の工事基準及び法令を網羅した工事基準データベースと、地中電線路に関わるケーブル以外の他の設備の布設工事の工事設計が蓄積された工事設計データベースとを少なくとも含むデータベースを具備すると共に、
地中電線路のルート、布設方式及び布設されるケーブルの太さ及び条数を少なくとも規定した布設設計に基づいて、前記データベースを参照しながら前記ケーブルの布設工事の設計を行うと共に、ケーブル工事設計が困難な場合には他の設備の工事設計を再検討させる段階に戻すケーブル工事設計手段を具備することを特徴とする地中電線路のケーブル工事管理システム。
A cable construction management system for underground cables for laying cables for underground cables,
Existing equipment database that covers existing equipment for underground cables, construction information database that covers information and laws that should be considered for laying underground cables, and construction standards that cover construction standards and laws for various equipment A database including at least a database and a construction design database in which construction designs for laying work of equipment other than cables related to underground cables are stored;
Based on the laying design that defines at least the route of the underground cableway, the laying method and the thickness and number of the laid cables, the cable laying work is designed with reference to the database and the cable work design. A cable construction management system for underground cable tracks, characterized by comprising cable construction design means for returning to the stage of reconsidering the construction design of other facilities when it is difficult.
請求項1において、前記データベースは、総合的な地中設備の情報を網羅した地域管理センターデータベースをさらに含むことを特徴とする地中電線路のケーブル工事管理システム。 The cable construction management system according to claim 1, wherein the database further includes a regional management center database covering comprehensive underground facility information. 請求項1又は2において、前記ケーブル工事設計手段は、工事設計が完了した時点で必要に応じて前記既設設備データベースを更新することを特徴とする地中電線路のケーブル工事管理システム。 The cable work management system according to claim 1 or 2, wherein the cable work design means updates the existing equipment database as necessary when the work design is completed. 請求項1〜3の何れかにおいて、前記ケーブル工事設計手段は、前記ケーブル工事設計に基づいてケーブルの布設工事を施工する現場を検証した検証データに基づいて前記ケーブル工事設計の実施が困難と判断した場合には、ケーブル工事設計を再設計することを特徴とする地中電線路のケーブル工事管理システム。 4. The cable construction design means according to claim 1, wherein the cable construction design means determines that it is difficult to implement the cable construction design based on verification data obtained by verifying a site where cable laying construction is performed based on the cable construction design. In this case, the cable work management system for underground cable tracks is characterized by redesigning the cable work design. 請求項4において、前記検証データが前記ケーブル工事設計手段にネットワークを介して接続された携帯端末から送られたものであることを特徴とする地中電線路のケーブル工事管理システム。 5. The cable work management system for underground cableway according to claim 4, wherein the verification data is sent from a portable terminal connected to the cable work design means via a network. 請求項1〜5の何れかにおいて、前記データベースには、前記ケーブルの布設工事に関する作業手順を網羅した作業手順データベースが含まれ、且つ前記ケーブル工事設計に基づいて必要な作業手順を抽出して布設工事を行う施工者の携帯端末に提示する作業手順提示手段をさらに具備することを特徴とする地中電線路のケーブル工事管理システム。 6. The database according to claim 1, wherein the database includes a work procedure database covering work procedures relating to the cable laying work, and a necessary work procedure is extracted based on the cable work design. A cable construction management system for an underground cableway, further comprising work procedure presentation means for presenting on a portable terminal of a constructor who performs the construction. 請求項1〜6の何れかにおいて、前記他工事設計が、配管の管路工事設計、マンホール工事設計、ハンドホール工事設計、機器設置工事設計及び地中引込線工事設計から選択される少なくとも1つからなることを特徴とする地中電線路のケーブル工事管理システム。
In any one of Claims 1-6, the said other construction design is from at least one selected from the pipe construction design of a piping, the manhole construction design, the handhole construction design, the equipment installation construction design, and the underground service line construction design. A cable construction management system for underground cable tracks.
JP2004298177A 2004-10-12 2004-10-12 Cable work control system of underground electric line Pending JP2006115570A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004298177A JP2006115570A (en) 2004-10-12 2004-10-12 Cable work control system of underground electric line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004298177A JP2006115570A (en) 2004-10-12 2004-10-12 Cable work control system of underground electric line

Publications (1)

Publication Number Publication Date
JP2006115570A true JP2006115570A (en) 2006-04-27

Family

ID=36383593

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004298177A Pending JP2006115570A (en) 2004-10-12 2004-10-12 Cable work control system of underground electric line

Country Status (1)

Country Link
JP (1) JP2006115570A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010250559A (en) * 2009-04-15 2010-11-04 Chugoku Electric Power Co Inc:The Low-voltage lead-in wire design management method using map information system
CN109087058A (en) * 2018-07-05 2018-12-25 国家电网有限公司 Field operation terminal, server and system for the laying of substation's cable

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010250559A (en) * 2009-04-15 2010-11-04 Chugoku Electric Power Co Inc:The Low-voltage lead-in wire design management method using map information system
CN109087058A (en) * 2018-07-05 2018-12-25 国家电网有限公司 Field operation terminal, server and system for the laying of substation's cable

Similar Documents

Publication Publication Date Title
JP4054763B2 (en) Inspection tunnel for underground pipes and cables
CA2348062A1 (en) Method for installing a fiber optic conduit system
JP2006115570A (en) Cable work control system of underground electric line
JP2003234708A (en) Optical network system in sewerage
JP2006115569A (en) Underground electric line laying management system
JP2006113692A (en) Underground lead-in wire work management system for underground electric line
JP5312167B2 (en) Low voltage service line design management method by map information system.
JPH0849285A (en) Duct for gutter
JP4355594B2 (en) Cable laying structure
JP2006067767A (en) Management system for equipment installation construction
JP2006067766A (en) Management system for handhole installation construction
JP2006063750A (en) Management system for manhole installation
JP2006113691A (en) Duct work management system for underground electric line
JP2848745B2 (en) Direct laying method of optical fiber cable
JP2005348459A (en) Overhead line laying management system
Goyal Installation, testing and jointing of LT and HT power cables up to 33 kV
Slavin et al. Buried Duct Network for Utility Cables Along Roads and Highways: Results of Field Trials
JP3004711B2 (en) Optical communication path and its laying method
Weatherbee 270741-Telephone-Data Installation Requirements
CN105390994A (en) Ground shallow trench wiring method for mechanical processing and assembling plant
EP1158106A1 (en) Building provided with a duct for cables and fluid pipes
Luscher et al. Automatic generation of network schematics from cadastral databases: Applications for an electric utility company
Wei et al. Research on critical technology application of power electronic technology in substation cable laying
JPH10290517A (en) Manhole for communication cable
Newton Underground distribution systems