JP2006113691A - Duct work management system for underground electric line - Google Patents

Duct work management system for underground electric line Download PDF

Info

Publication number
JP2006113691A
JP2006113691A JP2004298176A JP2004298176A JP2006113691A JP 2006113691 A JP2006113691 A JP 2006113691A JP 2004298176 A JP2004298176 A JP 2004298176A JP 2004298176 A JP2004298176 A JP 2004298176A JP 2006113691 A JP2006113691 A JP 2006113691A
Authority
JP
Japan
Prior art keywords
construction
laying
design
database
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004298176A
Other languages
Japanese (ja)
Inventor
Manabu Sugimoto
学 杉本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2004298176A priority Critical patent/JP2006113691A/en
Publication of JP2006113691A publication Critical patent/JP2006113691A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a duct work management system for an underground electric line allowing efficient and accurate execution of the optimum design for laying work in piping, when laying pipes for the underground electric line. <P>SOLUTION: This duct work management system for the underground electric line for laying the pipes for the underground electric line is provided with a database 200 including at least an existing facility database 210 including all the existing facilities in the underground electric line, a laying information database 220 including all the information pieces and acts to be investigated for laying the underground electric line, and a work reference database 230 including all the work references and acts of the various facilities, and a duct work designing means 110 for designing the laying work for the pipes while referring to the database 200, based on a laying design 130 specifying at least a laying route of the underground electric line, a laying system, and sizes and number of laid cables, and for returning the laying design 130 back to a redesigning stage when the work design 140 is difficult to be executed. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、地中電線路を布設する際にケーブルが挿通される配管を布設する管路工事管理システムに関する。   The present invention relates to a pipeline construction management system for laying a pipe through which a cable is inserted when laying an underground electric line.

従来より、発電所や変電所などから各家庭や工場などの顧客に対して電力を供給するには、電柱及び鉄塔等を用いた架空電線路やケーブルを地中に埋設した地中電線路が用いられてきた。ここで、地中電線路を布設する場合、ケーブルを地中に直接埋設する方法や、金属製や樹脂製などの配管内に布設する方法や、水道管やガス管などの他の配管と共に共同溝内に直接布設する方法がある。また、地中電線路に用いられる配管は、地中に直接埋設される場合や、共同溝内に布設される場合などがある。   Conventionally, in order to supply power to customers such as households and factories from power stations and substations, underground power lines and cables using underground power poles and steel towers have been buried in the ground. Has been used. Here, when laying underground cables, the method of laying cables directly in the ground, the method of laying in metal or resin pipes, and other pipes such as water pipes and gas pipes are used together. There is a method of laying directly in the groove. In addition, piping used for underground cable tracks may be buried directly in the ground or laid in a common groove.

また、従来の地中電線路の配管の管路工事では、電力供給計画に基づいて設計された布設設計のケーブル、ルート及び布設方式に合わせて、配管の管種、管路数及び管内径などの工事設計を行っていた。しかしながら、実際に配管工事を行った際に、上下水道やガスなどの既存の配管や、マンホール等の既設設備が存在したり、近接したりする場合、予め布設設計で選定されたルートを変更しなくてはならず、ルートの変更に伴いケーブルの選定、布設方式などの布設設計自体を全て変更する必要がある虞がある。また、布設設計を変更することにより、地中電線路の配管工事の詳細な工事設計を再設計しなくてはならず、煩雑であるという問題がある。   In addition, in conventional pipe work for underground underground conduits, pipe types, number of pipes, pipe inner diameter, etc. according to the laying design cable, route, and laying method designed based on the power supply plan I was doing the construction design. However, when existing piping works such as water and sewage and gas, and existing equipment such as manholes exist or are close to each other, the route previously selected in the laying design is changed. It is necessary to change all the laying designs such as cable selection and laying method with the change of route. In addition, by changing the laying design, it is necessary to redesign the detailed construction design of the piping work of the underground cable conduit, which is complicated.

また、従来、地中電線路の配管の布設工法については種々の改良技術が提案されているが(例えば、特許文献1及び2参照)、電力供給計画に基づいて設計された布設計画に基づいて、地中電線路の配管の管路設計及び工事計画を管理する手法については全く検討されていないのが現状である。   Conventionally, various improved techniques have been proposed for laying pipes for underground cables (see, for example, Patent Documents 1 and 2), but based on a cloth design image designed based on a power supply plan. At present, the method of managing the pipe design and construction plan of the underground electric line has not been studied at all.

特許第3286256号公報(第2頁、第1〜9図)Japanese Patent No. 3286256 (2nd page, FIGS. 1-9) 実開平7−16531号公報(第8〜14頁、第1〜6図)Japanese Utility Model Publication No. 7-16531 (pages 8-14, FIGS. 1-6)

本発明はこのような事情に鑑み、地中電線路の配管を布設する際に、配管の布設工事の最適な設計を効率的に且つ正確に行うことができる地中電線路の管路工事管理システムを提供することを課題とする。   In view of such circumstances, the present invention is able to efficiently and accurately perform an optimal design of the piping installation work when laying the piping of the underground cable wiring. The problem is to provide a system.

上記課題を解決する本発明の第1の態様は、地中電線路の配管を布設するための地中電線路の管路工事管理システムであって、地中電線路の既設設備を網羅した既設設備データベースと、地中電線路を布設するために検討すべき情報及び法令を網羅した布設情報データベースと、各種設備の工事基準及び法令を網羅した工事基準データベースとを少なくとも含むデータベースを具備すると共に、地中電線路の布設ルート、布設方式及び布設されるケーブルの太さ及び条数を少なくとも規定した布設設計に基づいて、前記データベースを参照しながら前記配管の布設工事の設計を行うと共に、工事設計が困難な場合には前記布設設計を再設計させる段階に戻す管路工事設計手段を具備することを特徴とする地中電線路の管路工事管理システムにある。   A first aspect of the present invention that solves the above problems is an underground conduit management system for laying underground conduits, and is an existing installation that covers existing facilities of underground conduits. A database including at least a facility database, a construction information database that covers information and laws to be considered for laying underground cables, and a construction standard database that covers construction standards and laws of various facilities, Based on the laying design that stipulates at least the laying route, the laying method and the thickness and number of cables to be laid, the piping laying work is designed with reference to the database and the construction design. In a conduit construction management system for underground cable conduits, comprising conduit construction design means for returning to the stage of redesigning the laying design when it is difficult to That.

かかる第1の態様では、地中電線路の布設設計に基づいて配管の布設工事の設計を効率的に且つ正確に行うことができる。   According to the first aspect, it is possible to efficiently and accurately design the piping construction work based on the underground wiring path construction design.

本発明の第2の態様は、第1の態様において、前記データベースは、総合的な地中設備の情報を網羅した地域管理センターデータベースをさらに含むことを特徴とする地中電線路の管路工事管理システムにある。   According to a second aspect of the present invention, in the first aspect, the database further includes a regional management center database covering comprehensive underground facility information. In the management system.

かかる第2の態様では、総合的な地中設備の情報を参照して工事設計を行うので、工事設計を行った後、総合的な地中設備との兼ね合いで工事設計を再設計することがなくなり、効率的に作業を行うことができる。   In the second aspect, since the construction design is performed with reference to the information of the comprehensive underground facilities, the construction design can be redesigned in balance with the comprehensive underground facilities after the construction design is performed. This eliminates the need for efficient work.

本発明の第3の態様は、第1又は2の態様において、前記管路工事設計手段は、工事設計が完了した時点で必要に応じて前記既設設備データベースを更新することを特徴とする地中電線路の管路工事管理システムにある。   According to a third aspect of the present invention, in the first or second aspect, the pipeline construction design means updates the existing equipment database as necessary when the construction design is completed. It is in the conduit construction management system for electric lines.

かかる第3の態様では、設計の段階で当該工事設計をデータベースに反映することで、続けて関連する工事設計を行う際に参照することができ、効率的な工事設計が可能となる。   In the third aspect, by reflecting the construction design in the database at the design stage, it is possible to refer to it when performing related construction design continuously, and efficient construction design is possible.

本発明の第4の態様は、第1〜3の何れかの態様において、前記管路工事設計手段は、前記工事設計に基づいて配管の布設工事を施工する現場を検証した検証データに基づいて前記工事設計の実施が困難と判断した場合には、工事設計を再設計することを特徴とする地中電線路の管路工事管理システムにある。   According to a fourth aspect of the present invention, in any one of the first to third aspects, the pipeline construction design means is based on verification data that verifies a site where pipe laying construction is performed based on the construction design. When it is determined that the construction design is difficult to implement, the construction design is redesigned.

かかる第4の態様では、配管の工事設計に基づいて現場を検証した際に、布設工事の実施が困難な場合であっても、工事設計を再設計することにより、工事設計を効率的に且つ正確に行うことができる。   In the fourth aspect, when the site is verified on the basis of the piping work design, even if it is difficult to carry out the laying work, the work design can be efficiently performed by re-designing the work design. Can be done accurately.

本発明の第5の態様は、第4の態様において、前記検証データが前記検証手段にネットワークを介して接続された携帯端末から送られたものであることを特徴とする地中電線路の管路工事管理システムにある。   According to a fifth aspect of the present invention, in the fourth aspect, the verification data is sent from a portable terminal connected to the verification means via a network. It is in the road construction management system.

かかる第5の態様では、施工現場で工事設計の再設計を行わせることができ、作業効率を向上することができる。   In the fifth aspect, the work design can be redesigned at the construction site, and the work efficiency can be improved.

本発明の第6の態様は、第1〜5の何れかの態様において、前記データベースには、前記配管の布設工事に関する作業手順を網羅した作業手順データベースが含まれ、且つ工事設計に基づいて必要な作業手順を抽出して布設工事を行う施工者の携帯端末に提示する作業手順提示手段をさらに具備することを特徴とする地中電線路の管路工事管理システムにある。   According to a sixth aspect of the present invention, in any one of the first to fifth aspects, the database includes a work procedure database that covers work procedures related to the piping laying work, and is necessary based on the work design. The present invention is a conduit construction management system for underground conduits, further comprising work procedure presentation means for extracting a simple work procedure and presenting it to a portable terminal of a builder who performs laying work.

かかる第6の態様では、施工者が端末を介して配管の布設工事の進行状況に従って、必要な作業手順を参照することができるため、作業者の知識及び技術の差に拘わらず正確な布設工事を効率的に行うことができると共に、第3者が布設工事の進行状況を確認することができる。   In the sixth aspect, since the construction worker can refer to the necessary work procedure according to the progress of the piping construction work through the terminal, the accurate construction work regardless of the knowledge and skill of the worker. The third party can check the progress of the laying work.

本発明によれば、地中電線路の布設設計に基づいて、布設工事の設計を効率的且つ正確に行うことができるという効果を奏する。   According to the present invention, there is an effect that the laying work can be designed efficiently and accurately based on the laying design of the underground electric line.

以下に本発明を実施形態に基づいて詳細に説明する。   Hereinafter, the present invention will be described in detail based on embodiments.

(実施形態1)
図1は、本発明の実施形態1に係る地中電線路の管路工事管理システムを示す概略構成を示す図であり、図2は、管路工事管理システムの設計データを示す図である。
(Embodiment 1)
FIG. 1 is a diagram showing a schematic configuration of an underground conduit management system according to Embodiment 1 of the present invention, and FIG. 2 is a diagram showing design data of the pipeline construction management system.

図1に示すように、管路工事管理システムは、管路工事管理サーバ100を具備し、管路工事管理サーバ100には、配管の布設工事を行うために必要な各種データが蓄積されたデータベース(DB)200と、地中電線路のケーブル、ルート及び布設方式が選定された布設設計130に基づいてデータベース200を参照しながら配管の工事設計140を行う管路工事設計手段110とが備えられている。   As shown in FIG. 1, the pipeline construction management system includes a pipeline construction management server 100, and the pipeline construction management server 100 is a database in which various data necessary for laying pipes are stored. (DB) 200 and pipeline construction design means 110 for performing piping construction design 140 while referring to the database 200 based on the laying design 130 in which the cable, route, and laying method of the underground cable conduit are selected. ing.

かかる管路工事管理サーバ100には、所定のネットワーク10を介して所定の端末20が接続できるようになっている。ここで端末20は、上述した工事設計140を行う社内部署の端末、又は工事請負会社等の外部会社の端末、あるいは布設工事を行う施工者が携帯する端末等であり、本実施形態では社内部署の端末とした。また、ネットワーク10は、LANや専用線やインターネットを介しての接続手段をいう。   A predetermined terminal 20 can be connected to the pipeline construction management server 100 via a predetermined network 10. Here, the terminal 20 is a terminal of an internal department that performs the above-described construction design 140, a terminal of an external company such as a construction contractor, or a terminal that is carried by a builder who performs laying work. Terminal. The network 10 is a connection means via a LAN, a dedicated line, or the Internet.

地中電線路の布設設計130は、図2に示すように、電力供給計画に基づいて地中電線路のケーブル131、ルート132及び布設方式133が選定されたものである。地中電線路のケーブル131とは、布設されるケーブルが特別高圧線、高圧線、高圧引込線、低圧幹線、低圧引込線、保安通信線であるかといった線種や、ケーブルの太さ、条数などが選定されたものである。   As shown in FIG. 2, the underground cable path laying design 130 is obtained by selecting the cable 131, the route 132, and the laying method 133 of the underground cable path based on the power supply plan. The underground cable 131 is a cable type such as whether the installed cable is a special high-voltage line, high-voltage line, high-voltage lead-in line, low-voltage trunk line, low-voltage lead-in line, security communication line, the thickness of the cable, the number of strips, etc. Was selected.

また、地中電線路のルート132とは、ケーブル131を布設する道筋を表すものであり、地図データに照らし合わせて道路などの布設可能な領域に沿って設計されたものであるが、既存の布設設備を利用する領域や既設の管路や共同溝を利用する領域も含めてルートという。   The underground cable route 132 represents a route for laying the cable 131 and is designed along a layable area such as a road in light of map data. The route includes the area where the laying facilities are used and the area where existing pipes and common grooves are used.

さらに地中電線路の布設方式133とは、ケーブル131を地中に直接埋設する方法、ケーブル131を配管で埋設する方法及び上下水やガスなどの他の配管と共に共同溝に布設する方法などが選定されたものである。この布設方式は、ルート132と関連付けて設定されることで、ルート132を所定の領域で区画して設定されている。例えば、布設されるケーブル131のルート132の一部の領域に既設の共同溝がある場合には、その領域が共同溝で設定され、その他の領域が直埋式や配管式などの他の方式で設定される。   Further, the underground cableway laying method 133 includes a method of directly burying the cable 131 in the ground, a method of burying the cable 131 in a pipe, and a method of laying in a common groove together with other pipes such as water, sewage and gas. It has been selected. This laying method is set in association with the route 132, thereby dividing the route 132 into predetermined areas. For example, when there is an existing common groove in a part of the route 132 of the cable 131 to be laid, the region is set as the common groove, and the other regions are other methods such as a direct buried type and a piping type. Set by.

このような布設設計130は、本実施形態では、端末20から入力されるようにしたが、特にこれに限定されるものではなく、例えば、布設設計130を行う布設設計サーバをネットワーク10を介して接続し、この布設設計サーバから布設設計130が入力されるようにしてもよい。   In the present embodiment, such a laying design 130 is input from the terminal 20, but is not particularly limited thereto. For example, a laying design server that performs the laying design 130 is provided via the network 10. The laying design server 130 may be input from the laying design server.

一方、データベース(DB)200は、地中電線路の既設設備を網羅した既設設備データベース210と、地中電線路を布設するために検討すべき情報及び法令を網羅した布設情報データベース220と、各種設備の工事基準及び法令を網羅した工事基準データベース230とを少なくとも含むものであり、本実施形態では、さらに、総合的な地中設備の情報を網羅した地域管理センターデータベース240を具備する。データベース200は、これに限定されるものではなく、さらに必要な情報を備えるものであってもよい。また、データベース200は、管路工事管理サーバ100に設けられているように図示しているが、これに限定されず、全部又は一部がネットワーク等を介して接続され、管路工事設計手段110が参照できるものであればよい。   On the other hand, the database (DB) 200 includes an existing equipment database 210 that covers existing facilities of underground cables, a laying information database 220 that covers information and laws to be examined for laying underground cables, It includes at least a construction standard database 230 that covers the construction standards and laws of equipment, and in this embodiment, further includes a regional management center database 240 that covers comprehensive information on underground facilities. The database 200 is not limited to this, and may further include necessary information. Further, the database 200 is illustrated as being provided in the pipeline construction management server 100, but the database 200 is not limited to this, and all or part of the database 200 is connected via a network or the like, and the pipeline construction design means 110 is provided. Anything can be referred to.

ここで、既設設備データベース210は、既設の地中電線路に関する布設設計や各種設備の工事設計などが蓄積されている。管路工事設計手段110は、このような既設設備データベースを参照することで、詳しくは後述するが、例えば、既設のルートにケーブルを追加できるか、新たな配管等の設備が必要かなどの配管の工事設計140を詳細に行うことができる。   Here, the existing facility database 210 stores installation design related to existing underground electric lines, construction designs of various facilities, and the like. The pipe construction design means 110 refers to such an existing equipment database, and will be described in detail later. For example, piping such as whether a cable can be added to the existing route or equipment such as new piping is necessary. The construction design 140 can be performed in detail.

また、布設情報データベース220は、地中電線路を布設するために検討すべき情報及び法令を網羅したものであり、技術的課題である地形情報や、地域情報、道路法や河川法などの各種法令情報などである。具体的には、例えば、埋立地などの地盤に関するデータや、道路の幅及び勾配などの道路に関するデータや、道路標識の位置、消火栓の位置、電柱などの施設に関するデータや、地中電線路の禁止区域のデータなどが挙げられる。管路工事設計手段110は、このような布設情報データベース220を参照することで、詳しくは後述するが、軟弱地盤など不等沈下の虞が有る場合など土壌によって基礎工事の方法を選定したり、海や鉄道線路までの距離による配管の管種の選定などの配管の工事設計140を詳細に行うことができる。   In addition, the laying information database 220 covers information and laws that should be considered for laying underground cables, and various technical information such as terrain information, regional information, road law, river law, etc. Legal information. Specifically, for example, data on the ground such as landfills, data on roads such as road width and slope, data on facilities such as the position of road signs, the position of fire hydrants, utility poles, Examples include prohibited area data. The pipe construction design means 110 refers to such a laying information database 220, which will be described in detail later, but selects the method of foundation work depending on the soil, such as when there is a possibility of uneven settlement such as soft ground, The piping construction design 140 such as selection of the pipe type of the pipe depending on the distance to the sea or the railroad track can be performed in detail.

さらに、工事基準データベース230は、地中電線路の配管の布設工事に関する工事基準及び法令を網羅したものである。具体的には、工事基準データベース230には、管路工事設計手段110によって布設設計130の選定されたケーブルに基づいて管種を選定するための管種選定データ、管路数を選定する管路数選定データ、管内径を選定する内径選定データ、軟弱地盤で不等沈下の虞がある場所などの土壌によって基礎工事の方法を選定する基礎工事選定データ、管孔数によって管配列を選定する管配列選定データ、地中埋設物を避ける際に管配列を変更する管配列変更選定データ、曲り配管を使用した際の高低差に対する水平長などを選定する曲り管選定データ、管の接続を選定する管接続データ、管枕の使用を選定する管枕選定データ、埋設管路の標示を選定する埋設管路標示選定データ、配管の埋戻しを選定する埋戻しデータ、管路の電柱立上りを選定する管立上り選定データなどが蓄積されている。   Furthermore, the construction standard database 230 covers construction standards and laws related to the construction work of underground conduit lines. Specifically, in the construction standard database 230, pipe type selection data for selecting the pipe type based on the cable selected by the laying design 130 by the pipe construction design means 110, and a pipe line for selecting the number of pipe lines Number selection data, inner diameter selection data for selecting the inner diameter of the pipe, foundation construction selection data for selecting the method of foundation work depending on the soil, such as where there is a risk of uneven settlement on soft ground, pipes for selecting the pipe arrangement according to the number of holes Arrangement selection data, pipe arrangement change selection data for changing pipe arrangement when avoiding underground objects, bent pipe selection data for selecting horizontal length against height difference when using bent pipe, and pipe connection selection Pipe connection data, pipe pillow selection data for selecting the use of pipe pillows, buried pipe marking selection data for selecting markings for buried pipes, backfill data for selecting pipe backfilling, rise of power poles for pipes Such as a constant tubes rising selection data is stored.

ここで、工事基準データベース230に含まれる選定データの一例を図3及び図4に示す。なお、図3は、管種選定データを示すテーブルであり、図4(a)は、管路数選定データを示すテーブル、図4(b)は、管内径選定データを示すテーブルである。図3に示すように、工事基準データベース230に含まれる管種選定データは、布設設計130で選定されたケーブル131の線種に対応する配管の管種が選択できるようにテーブルとして蓄積されたものである。また、図4(a)に示すように、工事基準データベース230に含まれる管路数選定データは、布設設計130で選定されたルート132やケーブル131の線種などによって決定される管路の種類に対応する管路数が選択できるようにテーブルとして蓄積されたものである。さらに、図4(b)に示すように、工事基準データベース230に含まれる管内径選定データは、布設設計130で選定されたケーブル131の線種に対応する配管の内径が選択できるようにテーブルとして蓄積されたものである。   An example of selection data included in the construction standard database 230 is shown in FIGS. 3 is a table showing pipe type selection data, FIG. 4A is a table showing pipe number selection data, and FIG. 4B is a table showing pipe inner diameter selection data. As shown in FIG. 3, the pipe type selection data included in the construction standard database 230 is stored as a table so that the pipe type corresponding to the line type of the cable 131 selected in the laying design 130 can be selected. It is. Further, as shown in FIG. 4A, the pipe number selection data included in the construction standard database 230 is the type of pipe line determined by the route 132 selected by the laying design 130, the line type of the cable 131, and the like. Are stored as a table so that the number of pipes corresponding to the number can be selected. Further, as shown in FIG. 4B, the pipe inner diameter selection data included in the construction standard database 230 is a table so that the inner diameter of the pipe corresponding to the line type of the cable 131 selected in the laying design 130 can be selected. It has been accumulated.

なお、工事基準データベース230には、地中電線路の他の設備工事に関する工事基準及び法令が蓄積されるようにしてもよい。ここで他の地中電線路の他の設備工事としては、例えば、マンホール、ハンドホール、機器及び地上引き込み線等の各種工事が挙げられる。   Note that the construction standards database 230 may store construction standards and laws related to other equipment construction of underground cable conduits. Here, as other installation work of other underground electric lines, various works such as manholes, hand holes, equipment, and ground lead-in lines can be cited.

また、地域管理センターデータベース240は、総合的な地中設備の情報を網羅したものであり、例えば、地中電線路以外の上下水道やガスなど他の配管のルート、管路数、管径及び布設方法や、水道管用のマンホールなどの設備及び機器の位置、構造などが挙げられる。なお、地域管理センターデータベース240は、管路工事管理システムのデータベース200に蓄積されていなくてもよく、外部に設置されているものであってもよい。   In addition, the regional management center database 240 covers comprehensive underground facility information. For example, other piping routes such as water and sewage and gas other than underground electric lines, the number of pipes, pipe diameter, Examples include the laying method and the location and structure of equipment and equipment such as manholes for water pipes. The regional management center database 240 may not be stored in the database 200 of the pipeline construction management system, and may be installed outside.

このようなデータベース200の各種データを参照しながら、管路工事設計手段110は、入力された布設設計130に基づいて配管の工事設計140を行う。ここで管路工事設計手段110が設計する工事設計140は、図2に示すように、配管の管種141、管路数142、管内径143などの配管の選定や、配管の基礎工事144、管配列145や、管配列の変更である配列変更146、配管同士の接続方法である管接続147、埋設管路の標示である管路標示148、管枕の間隔などの管枕149、配管の埋戻し150、電柱立上り工事151などの配管の詳細な工事の選定などの設計が挙げられる。   While referring to such various data in the database 200, the pipe work design means 110 performs a pipe work design 140 based on the input laying design 130. Here, the construction design 140 designed by the pipeline construction design means 110 includes, as shown in FIG. 2, selection of pipes such as the pipe type 141, the number of pipes 142, the pipe inner diameter 143, and the pipe foundation work 144, Tube arrangement 145, arrangement change 146, which is a change in pipe arrangement, pipe connection 147, which is a method of connecting pipes, pipe indication 148, which is an indication of a buried pipe, pipe pillow 149 such as the interval between pipe pillows, Examples of the design include selection of detailed construction of piping such as backfill 150 and telephone pole rising construction 151.

具体的には、配管の管種141は、管路工事設計手段110が上述した工事基準データベース230に含まれる図3に示す管路種別選定テーブルを参照することによって、布設設計130のケーブル131の線種に合わせて設計される。すなわち、上述したように工事基準データベース230には、布設設計130に含まれるケーブル131の線種によって管種を選定するための管路種別選定テーブルが蓄積されており、管路工事設計手段110は、布設設計130に基づいて管路種別選定テーブルを参照することで管種141を選定するようになっている。例えば、布設設計130のケーブル131の線種が、高低圧地中配電線の場合、配管は強化プラスチック複合管、C型強化プラスチック複合管、耐衝撃性硬質塩化ビニル管及び亜鉛めっき軽量鋼管から選択される。このとき、管路工事設計手段110は、布設情報データベース220を参照することで、地中電線路が布設されるルート132に埋立地など塩水が浸潤する虞がある場所があるか判断し、埋立地などがある場合には、亜鉛めっき軽量鋼管以外の配管を選択するようになっている。また、図3では、ケーブル131の線種に応じて複数の管種から選択できるが、例えば、コストを優先した優先順位を付して選択するようにすればよい。   Specifically, the pipe type 141 of the pipe is determined by referring to the pipe type selection table shown in FIG. Designed to match the line type. That is, as described above, the construction standard database 230 stores the pipe type selection table for selecting the pipe type according to the line type of the cable 131 included in the laying design 130. The pipe type 141 is selected by referring to the pipe type selection table based on the laying design 130. For example, when the line type of the cable 131 of the laying design 130 is a high-low voltage underground distribution line, the pipe is selected from a reinforced plastic composite pipe, a C-type reinforced plastic composite pipe, an impact-resistant hard polyvinyl chloride pipe, and a galvanized lightweight steel pipe. Is done. At this time, the pipeline construction design means 110 refers to the laying information database 220 to determine whether there is a place where there is a possibility of salt water infiltrating the route 132 where the underground electric wire is laid, such as a landfill. When there is a ground or the like, a pipe other than the galvanized lightweight steel pipe is selected. Further, in FIG. 3, a plurality of tube types can be selected according to the line type of the cable 131, but for example, selection may be made with a priority given priority to cost.

また、配管の管路数142は、管路工事設計手段110が上述した工事基準データベース230に含まれる図4(a)に示す管路数選定テーブルを参照することによって、布設設計130のケーブル131の線種によって設計される。すなわち、上述したように工事基準データベース230には、布設設計130に含まれるケーブル131の条数や線種などにによって管路数142を選定するための管路数選定テーブルが蓄積されており、管路工事設計手段110は、布設設計130に基づいて管路数選定テーブルを参照することで管路数142を選定するようになっている。例えば、布設設計130のケーブル131の線種が、低圧幹線の場合、管路数は1つになるが、ケーブル131の線種が供給線の場合、管路数は1+1(予備用)の合計2つとなる。   Further, the pipe number 142 is determined by referring to the pipe number selection table shown in FIG. 4A included in the construction standard database 230 described above by the pipe construction design means 110. Designed by the line type. That is, as described above, the construction standard database 230 stores a pipe number selection table for selecting the pipe number 142 according to the number of lines and the line type of the cable 131 included in the laying design 130. The pipe construction design means 110 selects the pipe number 142 by referring to the pipe number selection table based on the laying design 130. For example, when the line type of the cable 131 of the laying design 130 is a low-voltage trunk line, the number of pipes is one, but when the line type of the cable 131 is a supply line, the number of pipe lines is a sum of 1 + 1 (for backup). There will be two.

さらに、配管の管内径143は、管路工事設計手段110が上述した工事基準データベース230に含まれる図4(b)に示す管内径選定テーブルを参照することによって、布設設計130のケーブル131の線種によって設計される。すなわち、上述したように工事基準データベース230には、布設設計130に含まれるケーブル131の線種によって管内径を選定するための管内径選定テーブルが蓄積されており、管路工事設計手段110は、布設設計130に基づいて管内径選定テーブルを参照することで管内径143を選定するようになっている。例えば、布設設計130のケーブル131の線種が、特別高圧線のCVT100を用いた場合、管内径は125mmが選定される。   Further, the pipe inner diameter 143 of the pipe is determined by referring to the pipe inner diameter selection table shown in FIG. Designed by seed. That is, as described above, the construction standard database 230 stores a pipe inner diameter selection table for selecting the pipe inner diameter according to the line type of the cable 131 included in the laying design 130. The pipe inner diameter 143 is selected by referring to the pipe inner diameter selection table based on the laying design 130. For example, when the line type of the cable 131 of the laying design 130 uses a special high-voltage line CVT100, the inner diameter of the pipe is selected to be 125 mm.

このように、管路工事設計手段110は、布設設計130に基づいて、データベース200を参照しながら総合的に判断して、地中電線路の配管の詳細な工事設計140を出力する。   As described above, the pipeline construction design means 110 comprehensively makes a judgment based on the laying design 130 while referring to the database 200, and outputs the detailed construction design 140 of the underground conduit.

また、管路工事設計手段110は、種々検討した結果、配管の工事設計140が困難な場合には布設設計130を再設計させる段階に戻すようにする。また、再設計された布設設計130について更に検討し、工事設計140を作成する。すなわち、管路工事設計手段110は、布設設計130に基づいて、データベース200を参照しながら工事設計140を行うが、データベース200に蓄積された種々のデータから工事設計140の作成が困難な場合、すなわち、工事設計140を作成できない場合には、布設設計130を再設計させる段階に戻すことで、ケーブル131、ルート132及び布設方式133の変更などを行わせるようになっている。そして、管路工事設計手段110は、ケーブル131、ルート132及び布設方式133の選定が変更された布設設計130に基づいて、データベース200を参照しながら、工事設計140を再設計するようになっている。このように、管路工事設計手段110は、データベース200を参照して工事設計140が困難な場合には、布設設計130を再設計させる段階に戻し、工事設計140を繰り返し行うことで、電力供給計画に基づいた最適な配管の工事設計140を効率的に且つ正確に行うことができる。   In addition, as a result of various studies, the pipeline construction design means 110 returns to the stage of redesigning the laying design 130 when the piping construction design 140 is difficult. Further, the redesigned laying design 130 is further examined, and a construction design 140 is created. That is, the pipeline construction design means 110 performs the construction design 140 with reference to the database 200 based on the laying design 130. However, when it is difficult to create the construction design 140 from various data stored in the database 200, That is, when the construction design 140 cannot be created, the cable 131, the route 132, and the laying method 133 are changed by returning to the stage where the laying design 130 is redesigned. The pipeline construction design means 110 redesigns the construction design 140 while referring to the database 200 based on the laying design 130 in which the selection of the cable 131, the route 132, and the laying method 133 is changed. Yes. As described above, the pipe work design means 110 refers to the database 200, and when the construction design 140 is difficult, the pipeline construction design means 110 returns to the stage of redesigning the laying design 130, and repeats the construction design 140 to supply power. The optimum piping construction design 140 based on the plan can be efficiently and accurately performed.

なお、工事設計140が完了すると、この布設工事が実行される可能性が高いので、例えば、既設設備データベース210に登録するようにする。これは、次の布設設計130に基づいて設計される工事設計140に利用させるためである。勿論、計画中の設備専用のデータベースを作成して、参照できるようにしておいてもよい。   When the construction design 140 is completed, there is a high possibility that this laying work will be executed. For example, the construction design 140 is registered in the existing equipment database 210. This is because the construction design 140 designed based on the next laying design 130 is used. Of course, a database dedicated to the planned facility may be created so that it can be referred to.

また、本実施形態では、工事設計140に基づいて施工者などが配管の布設工事を施工する現場を検証した検証データ160を管路工事設計手段110が受け取り、管路工事設計手段110は、受け取った検証データ160と設計した工事設計140とに基づいて配管の布設工事を行うのが困難か判断する。そして、管路工事設計手段110は、布設工事が困難と判断した場合には、検証データ160を参照して工事設計140を再設計するようになっている。   In the present embodiment, the pipeline construction design means 110 receives verification data 160 that verifies the site where the builder constructs the pipe laying work based on the construction design 140, and the pipeline construction design means 110 receives the verification data 160. Based on the verification data 160 and the designed construction design 140, it is determined whether it is difficult to perform the piping laying construction. When it is determined that the laying work is difficult, the pipeline work design unit 110 refers to the verification data 160 and redesigns the work design 140.

ここで、配管の布設工事を行うのが困難な場合とは、工事設計140に基づいて実際に施工される現場検証を行った結果、例えば、他の地中設備によって必要な管路数を布設できない場合や、布設情報データベース220の地形情報では通常の道路に沿ったルートで管種等が選定されていたのに対し、実際には途中に用水路などがあって配管の管種や曲り配管等を変更しなくてはならない場合など、工事設計140の変更が必要となる場合である。このような場合には、端末20を介して検証データ160が管路工事設計手段110に送られることで、管路工事設計手段110は工事設計140の変更が必要か判断し、必要と判断した場合には、工事設計140の再設計を行うようになっている。   Here, the case where it is difficult to lay the piping is the result of the field verification actually performed based on the construction design 140. For example, the number of necessary pipelines is laid by other underground facilities. If it is not possible or the topography information in the laying information database 220 has been selected with a route along the normal road, the pipe type, etc. This is a case where the construction design 140 needs to be changed. In such a case, the verification data 160 is sent to the pipe work design means 110 via the terminal 20, so that the pipe work design means 110 determines whether the work design 140 needs to be changed and determines that it is necessary. In such a case, the construction design 140 is redesigned.

ここで、このような管路工事管理システムの動作について詳細に説明する。なお、図5は、管路工事管理システムの動作を示すフローチャートである。   Here, the operation of such a pipeline construction management system will be described in detail. FIG. 5 is a flowchart showing the operation of the pipeline construction management system.

まず、ステップS1で電力供給計画に基づいて布設設計130が設計されると、ステップS2で管路工事設計手段110が布設設計130に基づいて、データベース200を参照しながら工事設計140を開始する。そして、ステップS3で管路工事設計手段110が配管の工事設計140ができたか判断し、工事設計140ができた場合には(ステップS3;Yes)、ステップS4で管路工事設計手段110による工事設計140が完了すると共に工事設計140が出力される。そして、ステップS5で管路工事設計手段110が工事設計140で既設設備データベース210を更新する。また、ステップS3で工事設計ができなかった場合には(ステップS3;No)、ステップS1に戻り布設設計130が再設計される。   First, when the laying design 130 is designed based on the power supply plan in step S1, the pipeline construction design means 110 starts the construction design 140 referring to the database 200 based on the laying design 130 in step S2. Then, in step S3, the pipeline construction design means 110 determines whether the piping construction design 140 has been completed. If the construction design 140 has been completed (step S3; Yes), the construction by the pipeline construction design means 110 in step S4. When the design 140 is completed, the construction design 140 is output. In step S5, the pipeline construction design means 110 updates the existing equipment database 210 with the construction design 140. If the construction design cannot be performed in step S3 (step S3; No), the process returns to step S1 and the laying design 130 is redesigned.

その後は、ステップS6で管路工事設計手段110が、工事設計140に基づいて施工者が実際に配管の布設工事ができるか現場の検証を行った検証データ160を受け取り、管路工事設計手段110が検証データ160と工事設計140とに基づいて配管の布設工事ができないと判断した場合には(ステップS6;No)、ステップS2〜ステップS5を繰り返し行い、配管の工事設計140を再設計すると共に新たな工事設計140で既設設備データベース210を更新する。また、ステップS6で管路工事設計手段110が検証データ160を受け取ったにも拘わらず、検証データ160と工事設計140とに基づいて配管の布設工事ができると判断した場合には(ステップS6;Yes)、ステップS7で実際に配管の布設工事を行う。   After that, in step S6, the pipeline construction design means 110 receives the verification data 160 obtained by performing on-site verification based on the construction design 140 so that the builder can actually perform the piping construction work, and the pipeline construction design means 110. If it is determined that the pipe laying work cannot be performed based on the verification data 160 and the work design 140 (step S6; No), the steps S2 to S5 are repeated to redesign the pipe work design 140. The existing equipment database 210 is updated with the new construction design 140. Further, when it is determined in step S6 that the pipe construction design means 110 has received the verification data 160, the pipe construction work can be performed based on the verification data 160 and the construction design 140 (step S6; Yes), in step S7, the piping is actually laid.

なお、このステップS6で、管路工事設計手段110が受け取る検証データ160は、施工者が配管の布設工事を施工している最中に、予期せぬ障害物等で配管の工事設計140を再設計しなければならない場合のデータも含むものである。   In this step S6, the verification data 160 received by the pipeline construction design means 110 is used to reconstruct the piping construction design 140 with an unexpected obstacle while the construction work is being performed by the installer. It also includes data when it must be designed.

(実施形態2)
図6は、本発明の実施形態2に係る管路工事管理システムの概略構成を示す図である。図6に示すように、本実施形態の管路工事管理サーバ100Aには、配管の布設工事を施工する施工者が携帯する端末20Aがネットワーク10を介して接続されている。
(Embodiment 2)
FIG. 6 is a diagram showing a schematic configuration of a pipeline construction management system according to Embodiment 2 of the present invention. As shown in FIG. 6, a terminal 20 </ b> A carried by a builder who constructs piping is connected to the pipeline construction management server 100 </ b> A of this embodiment via a network 10.

また、管路工事管理サーバ100Aに備えられたデータベース200Aには、配管の布設工事に関する作業手順170が蓄積された作業手順データベース250が含まれている。さらに、管路工事管理サーバ100Aには、この作業手順データベース250から配管の工事設計140に関する必要な作業手順170を抽出し、施工者が携帯する端末20Aに提示する作業手順提示手段120を具備する。   In addition, the database 200A provided in the pipe work management server 100A includes a work procedure database 250 in which work procedures 170 related to piping installation work are accumulated. Further, the pipe work management server 100A includes work procedure presenting means 120 that extracts a necessary work procedure 170 related to the piping work design 140 from the work procedure database 250 and presents it to the terminal 20A carried by the installer. .

作業手順提示手段120は、端末20Aからの要求180に応じて、工事設計140に基づいて配管の布設工事の進行状況に適した作業手順170を作業手順データベース250から抽出し、端末20Aに送信する。そして、施工者は、端末20Aの画面に表示された作業手順170に従って配管の布設工事を進めることができる。このように、施工者が、配管の工事設計140に基づく作業手順170を参照しながら、布設工事を行うことができるため、施工者の知識や技術力の差に拘わらず、配管の布設工事を効率的に且つ正確に行うことができる。また、施工者の端末20Aから送られる要求180には作業の進行状況が含まれており、作業手順提示手段120は、要求180に含まれる作業の進行状況に合わせて作業手順170を端末20Aに提示するようになっている。このため、管路工事管理サーバ100Aは、配管の布設工事の進行状況を常に把握することができ、端末20を介して第3者に作業の進行状況を確認させることができる。これにより、布設工事の管理を効率的に行うことができる。   In response to the request 180 from the terminal 20A, the work procedure presenting means 120 extracts a work procedure 170 suitable for the progress of the pipe laying work based on the work design 140 from the work procedure database 250 and transmits it to the terminal 20A. . Then, the builder can proceed with the piping laying work according to the work procedure 170 displayed on the screen of the terminal 20A. In this way, since the builder can perform the laying work while referring to the work procedure 170 based on the piping work design 140, the laying work of the pipe can be performed regardless of the difference in the knowledge and technical ability of the builder. It can be done efficiently and accurately. Further, the request 180 sent from the builder's terminal 20A includes the progress of the work, and the work procedure presenting means 120 sends the work procedure 170 to the terminal 20A in accordance with the work progress included in the request 180. It comes to present. For this reason, the pipeline construction management server 100A can always grasp the progress of the pipe laying work, and can allow the third party to confirm the progress of the work via the terminal 20. Thereby, management of laying work can be performed efficiently.

また、本実施形態では、施工者が携帯した端末20Aから、検証データ160が送信できるようになっている。このため、配管の布設工事の最中であっても、工事設計140を再設計させることができると共に、再設計された工事設計140を施工者が布設工事を行っている現場で確認することができ、さらに配管の布設工事を効率的に且つ正確に行うことができる。   In the present embodiment, the verification data 160 can be transmitted from the terminal 20A carried by the installer. For this reason, the construction design 140 can be redesigned even during the piping laying work, and the redesigned construction design 140 can be confirmed at the site where the builder is laying the work. In addition, the piping construction work can be performed efficiently and accurately.

(他の実施形態)
以上、本発明の各実施形態について説明したが、本発明は上述したものに限定されるものではない。例えば、上述した実施形態1及び2では、データベース200、200Aに既設設備データベース210と地域管理センターデータベース240とが含まれるようにしたが、既設設備データベース210が地域管理センターデータベース240に含まれるようにしてもよい。すなわち、地域管理センターデータベースには、地中電線路の既設設備の情報と、その他の既設の地中設備の情報との全ての地中設備に関する情報が蓄積されて一元管理できるようにしてもよい。
(Other embodiments)
As mentioned above, although each embodiment of this invention was described, this invention is not limited to what was mentioned above. For example, in the first and second embodiments described above, the existing facilities database 210 and the regional management center database 240 are included in the databases 200 and 200A. However, the existing facilities database 210 is included in the regional management center database 240. May be. That is, in the regional management center database, information on all underground facilities including information on existing facilities on the underground cableway and information on other existing underground facilities may be accumulated and managed centrally. .

また、例えば、データベース200、200Aに蓄積される各種データは、端末20、20Aを用いて更新されるようにすればよい。すなわち、地中電線路以外の上下水管、ガスなどの他の配管や、上下水管用のマンホール、機器などの地中設備が布設された際に、端末20、20Aによって地域管理センターデータベース240を更新するようにすればよい。   Further, for example, various data stored in the databases 200 and 200A may be updated using the terminals 20 and 20A. In other words, when underground facilities such as water and sewer pipes other than underground cable lines, gas pipes, manholes for water and sewer pipes, and equipment are installed, the regional management center database 240 is updated by the terminals 20 and 20A. You just have to do it.

さらに、上述した実施形態1及び2では、管路工事管理サーバ100、100Aと、この管路工事管理サーバ100、100Aにネットワーク10を介して接続される端末20、20Aとで管路工事管理システムを構成するようにしたが、特にこれに限定されず、例えば、管路工事管理サーバに、各種データの入出力を行う入出力手段を設けることで、管路工事管理サーバが独立した管路工事管理システムとして機能するようにしてもよい。   Further, in the first and second embodiments described above, the pipeline construction management server 100, 100A and the pipeline construction management server 100, 100A and the terminals 20, 20A connected to the pipeline construction management server 100, 100A via the network 10 are used. However, the present invention is not particularly limited to this. For example, by providing input / output means for inputting / outputting various data to the pipe work management server, the pipe work management server becomes independent. It may function as a management system.

本発明の実施形態1に係る管路工事管理システムの概略構成を示す図である。It is a figure showing a schematic structure of a pipeline construction management system concerning Embodiment 1 of the present invention. 本発明の実施形態1に係る設計データを示す図である。It is a figure which shows the design data which concerns on Embodiment 1 of this invention. 本発明の実施形態1に係る工事基準データベースのデータの一例を示す図である。It is a figure which shows an example of the data of the construction standard database which concerns on Embodiment 1 of this invention. 本発明の実施形態1に係る工事基準データベースのデータの一例を示す図である。It is a figure which shows an example of the data of the construction standard database which concerns on Embodiment 1 of this invention. 本発明の実施形態1に係る管路工事管理システムの動作を説明するフローチャートである。It is a flowchart explaining operation | movement of the pipeline construction management system which concerns on Embodiment 1 of this invention. 本発明の実施形態2に係る管路工事管理システムの概略構成を示す図である。It is a figure which shows schematic structure of the pipeline construction management system which concerns on Embodiment 2 of this invention.

符号の説明Explanation of symbols

10 ネットワーク
20、20A 端末
100、100A 管路工事管理サーバ
110 管路工事設計手段
120 作業手順提示手段
130 布設設計
140 工事設計
160 検証データ
170 作業手順
180 要求
200、200A データベース
210 既設設備データベース
220 布設情報データベース
230 工事基準データベース
240 地域管理センターデータベース
250 作業手順データベース
250 作業手順データベース

DESCRIPTION OF SYMBOLS 10 Network 20, 20A Terminal 100, 100A Pipeline construction management server 110 Pipeline construction design means 120 Work procedure presentation means 130 Installation design 140 Construction design 160 Verification data 170 Operation procedure 180 Request 200, 200A Database 210 Existing equipment database 220 Installation information Database 230 Construction standard database 240 Regional management center database 250 Work procedure database 250 Work procedure database

Claims (6)

地中電線路の配管を布設するための地中電線路の管路工事管理システムであって、
地中電線路の既設設備を網羅した既設設備データベースと、地中電線路を布設するために検討すべき情報及び法令を網羅した布設情報データベースと、各種設備の工事基準及び法令を網羅した工事基準データベースとを少なくとも含むデータベースを具備すると共に、
地中電線路の布設ルート、布設方式及び布設されるケーブルの太さ及び条数を少なくとも規定した布設設計に基づいて、前記データベースを参照しながら前記配管の布設工事の設計を行うと共に、工事設計が困難な場合には前記布設設計を再設計させる段階に戻す管路工事設計手段を具備することを特徴とする地中電線路の管路工事管理システム。
An underground conduit construction management system for laying underground conduit pipes,
Existing equipment database that covers existing equipment for underground cables, construction information database that covers information and laws that should be considered for laying underground cables, and construction standards that cover construction standards and laws for various equipment A database including at least a database,
Based on the laying design that stipulates at least the laying route, the laying method and the thickness and number of cables to be laid, the piping laying work is designed with reference to the database and the construction design. A conduit construction management system for underground cable conduits, characterized by comprising conduit construction design means for returning the laying design to the stage of redesign when it is difficult.
請求項1において、前記データベースは、総合的な地中設備の情報を網羅した地域管理センターデータベースをさらに含むことを特徴とする地中電線路の管路工事管理システム。 2. The underground conduit management system according to claim 1, wherein the database further includes a regional management center database covering comprehensive underground facility information. 請求項1又は2において、前記管路工事設計手段は、工事設計が完了した時点で必要に応じて前記既設設備データベースを更新することを特徴とする地中電線路の管路工事管理システム。 3. The conduit construction management system for underground conduits according to claim 1, wherein the conduit construction design means updates the existing equipment database as necessary when construction design is completed. 請求項1〜3の何れかにおいて、前記管路工事設計手段は、前記工事設計に基づいて配管の布設工事を施工する現場を検証した検証データに基づいて前記工事設計の実施が困難と判断した場合には、工事設計を再設計することを特徴とする地中電線路の管路工事管理システム。 In any one of Claims 1-3, the said pipe construction design means judged that implementation of the said construction design was difficult based on the verification data which verified the field | site which constructs the piping construction work based on the said construction design In the case of an underground conduit management system characterized by redesigning the construction design. 請求項4において、前記検証データが前記管路工事設計手段にネットワークを介して接続された携帯端末から送られたものであることを特徴とする地中電線路の管路工事管理システム。 5. The conduit construction management system for underground cable conduits according to claim 4, wherein the verification data is sent from a portable terminal connected to the conduit construction design means via a network. 請求項1〜5の何れかにおいて、前記データベースには、前記配管の布設工事に関する作業手順を網羅した作業手順データベースが含まれ、且つ工事設計に基づいて必要な作業手順を抽出して布設工事を行う施工者の携帯端末に提示する作業手順提示手段をさらに具備することを特徴とする地中電線路の管路工事管理システム。
In any one of Claims 1-5, the said database contains the work procedure database which covered the work procedure regarding the construction work of the said piping, and extracts a required work procedure based on construction design, and performs construction work. A conduit construction management system for underground cable conduits, further comprising work procedure presentation means for presenting on a portable terminal of a contractor to perform.
JP2004298176A 2004-10-12 2004-10-12 Duct work management system for underground electric line Pending JP2006113691A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004298176A JP2006113691A (en) 2004-10-12 2004-10-12 Duct work management system for underground electric line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004298176A JP2006113691A (en) 2004-10-12 2004-10-12 Duct work management system for underground electric line

Publications (1)

Publication Number Publication Date
JP2006113691A true JP2006113691A (en) 2006-04-27

Family

ID=36382178

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004298176A Pending JP2006113691A (en) 2004-10-12 2004-10-12 Duct work management system for underground electric line

Country Status (1)

Country Link
JP (1) JP2006113691A (en)

Similar Documents

Publication Publication Date Title
CN106530391A (en) GIS-based urban underground cable three-dimensional design method
Canto-Perello et al. Analysing utility tunnels and highway networks coordination dilemma
Chang et al. Underground pipeline management based on road information modeling to assist in road management
JP2007004497A (en) Ground facility information management system
CN108536934B (en) Underground power pipeline planning method with geological judgment
JP2006113691A (en) Duct work management system for underground electric line
Gupta et al. A survey of sewer rehabilitation in Malaysia: application of trenchless technologies
Vaseli Application of micro-trenching for fiber to the home
Atalah et al. Comparison study of installing fiber optic cable in university campuses using trenchless techniques relative to open cut
Boyd et al. Guidelines for selecting lead pipe rehabilitation and replacement technologies
JP2006115569A (en) Underground electric line laying management system
JP2006067766A (en) Management system for handhole installation construction
JP2006115570A (en) Cable work control system of underground electric line
JP2006113692A (en) Underground lead-in wire work management system for underground electric line
JP2006063750A (en) Management system for manhole installation
JP2012003320A (en) Licensing management support apparatus
Rogers et al. Mapping the underworld
JP2003176693A (en) Method and system for planning construction work using road
Hashemi et al. Cost of underground infrastructure renewal: A comparison of open-cut and trenchless methods
Monahan Sr et al. Pipeline engineering and practice: Installing a steam pipeline
Slavin et al. Buried Duct Network for Utility Cables Along Roads and Highways: Results of Field Trials
Herrmann The Rolkon Way
Lehrburger et al. WISE Local Infrastructure Project in the Town of Castle Rock Demanded a Unique Set of Design and Construction Solutions
Ambroziak et al. Development and Construction of the Nation's Largest Water Main Rehab Project
Lehrburger et al. Water Wise