JP2006104909A - Foundation construction method of independent steel mat - Google Patents
Foundation construction method of independent steel mat Download PDFInfo
- Publication number
- JP2006104909A JP2006104909A JP2004317162A JP2004317162A JP2006104909A JP 2006104909 A JP2006104909 A JP 2006104909A JP 2004317162 A JP2004317162 A JP 2004317162A JP 2004317162 A JP2004317162 A JP 2004317162A JP 2006104909 A JP2006104909 A JP 2006104909A
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- foundation construction
- construction method
- construction
- independent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
Description
本発明は、住宅建築の基礎工事において鉄筋コンクリート布基礎の替わりにH鋼材を使用する工法である。 The present invention is a method of using H steel in place of a reinforced concrete cloth foundation in foundation construction of a residential building.
これまで住宅基礎工事の工法としては▲1▼布基礎、▲2▼ベタ基礎一体布基礎が一般的であった。 Until now, (1) cloth foundation and (2) solid foundation integrated cloth foundation have been generally used as the construction methods for housing foundation work.
従来の工法は、▲1▼及び▲2▼とも伐根量、搬出残土量が多く重機を必要とし、さらに使用コンクリート、型枠、鉄筋量が多く物的、人的コストが高くなる傾向にあった。さらに、従来の工法は不同沈下が生じる可能性があり、生じた場合根本的な対応策が無い等の問題点がある。 The conventional construction methods in both (1) and (2) have a large amount of felling roots and a large amount of unloading soil, and require heavy machinery. In addition, there is a large amount of concrete, formwork and rebar used, and physical and human costs tend to increase. It was. Furthermore, there is a possibility that the conventional construction method may cause uneven settlement, and there is a problem that there is no fundamental countermeasure when it occurs.
本工法は、従来鉄筋コンクリートを用いていた布基礎部分にH鋼材(以下鋼製布基礎と呼ぶ)を使用し、独立基礎(耐圧盤)に各々緊結するものである。 This construction method uses H steel (hereinafter referred to as a steel cloth foundation) for the cloth foundation part that has conventionally used reinforced concrete, and is each tightly connected to an independent foundation (pressure board).
本工法は、鋼製布基礎が工場生産可能なため、基礎工事の熟練工の必要が無く施工精度の向上が期待され、また、鋼製布基礎を独立基礎(耐圧盤)と緊結するためコンクリートの使用量が大幅に削減され、さらに工期が大幅に短縮されること等が期待される。結果として基礎工事における人的、物的コストが大幅に削減されることになる。さらに、万一不同沈下が生じた場合でも鋼製布基礎が架台の役割を担うことで有圧昇降機による嵩上げ工事が可能となる。 This construction method can produce steel fabric foundations at the factory, so there is no need for skilled workers in foundation work, and improvement in construction accuracy is expected. Also, since the steel fabric foundation is tied to an independent foundation (pressure platen), It is expected that the amount used will be greatly reduced and the construction period will be greatly shortened. As a result, the human and material costs in the foundation work are greatly reduced. Furthermore, even if uneven settlement occurs, the steel cloth foundation serves as a gantry, so that it is possible to perform a lifting work with a pressure elevator.
以下、本工法の実施の形態について説明する。
(イ)従来の鉄筋コンクリート布基礎に替え鋼製布基礎を使用する。
(ロ)独立基礎(耐圧盤)と緊結する。Hereinafter, embodiments of the present construction method will be described.
(B) Use a steel cloth foundation instead of the conventional reinforced concrete cloth foundation.
(B) Tightly coupled with the independent foundation (pressure board).
(1)H鋼材
(2)独立基礎
(3)鉄筋
(4)地盤(1) H steel (2) Independent foundation (3) Reinforcement (4) Ground
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004317162A JP2006104909A (en) | 2004-10-01 | 2004-10-01 | Foundation construction method of independent steel mat |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004317162A JP2006104909A (en) | 2004-10-01 | 2004-10-01 | Foundation construction method of independent steel mat |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2006104909A true JP2006104909A (en) | 2006-04-20 |
Family
ID=36374956
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004317162A Pending JP2006104909A (en) | 2004-10-01 | 2004-10-01 | Foundation construction method of independent steel mat |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2006104909A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165184A (en) * | 2017-07-17 | 2017-09-15 | 安徽晶润新能源有限公司 | A kind of wind-solar hybrid power generation station foundation structure |
CN107165183A (en) * | 2017-07-17 | 2017-09-15 | 安徽晶润新能源有限公司 | A kind of solar power plant foundation construction method |
CN107165189A (en) * | 2017-07-17 | 2017-09-15 | 安徽晶润新能源有限公司 | A kind of solar power plant foundation structure |
CN107190723A (en) * | 2017-07-17 | 2017-09-22 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening system |
CN107227869A (en) * | 2017-07-17 | 2017-10-03 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening system based on wind-solar hybrid power generation station |
CN107245995A (en) * | 2017-07-17 | 2017-10-13 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening method based on wind-solar hybrid power generation station |
CN107338805A (en) * | 2017-07-17 | 2017-11-10 | 安徽晶润新能源有限公司 | A kind of wind-solar hybrid power generation station foundation construction method |
CN107360751A (en) * | 2017-07-17 | 2017-11-21 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening method |
-
2004
- 2004-10-01 JP JP2004317162A patent/JP2006104909A/en active Pending
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165184A (en) * | 2017-07-17 | 2017-09-15 | 安徽晶润新能源有限公司 | A kind of wind-solar hybrid power generation station foundation structure |
CN107165183A (en) * | 2017-07-17 | 2017-09-15 | 安徽晶润新能源有限公司 | A kind of solar power plant foundation construction method |
CN107165189A (en) * | 2017-07-17 | 2017-09-15 | 安徽晶润新能源有限公司 | A kind of solar power plant foundation structure |
CN107190723A (en) * | 2017-07-17 | 2017-09-22 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening system |
CN107227869A (en) * | 2017-07-17 | 2017-10-03 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening system based on wind-solar hybrid power generation station |
CN107245995A (en) * | 2017-07-17 | 2017-10-13 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening method based on wind-solar hybrid power generation station |
CN107338805A (en) * | 2017-07-17 | 2017-11-10 | 安徽晶润新能源有限公司 | A kind of wind-solar hybrid power generation station foundation construction method |
CN107360751A (en) * | 2017-07-17 | 2017-11-21 | 安徽光鼎晶新能源科技有限公司 | A kind of sand-fixing greening method |
CN107165184B (en) * | 2017-07-17 | 2019-09-27 | 合肥市智慧桥信息科技有限公司 | A kind of wind-solar hybrid power generation station foundation structure |
CN107165189B (en) * | 2017-07-17 | 2019-10-01 | 安徽晶润新能源有限公司 | A kind of solar power plant foundation structure |
CN107338805B (en) * | 2017-07-17 | 2019-10-01 | 合肥市智慧桥信息科技有限公司 | A kind of wind-solar hybrid power generation station foundation construction method |
CN107165183B (en) * | 2017-07-17 | 2019-10-01 | 安徽晶润新能源有限公司 | A kind of solar power plant foundation construction method |
CN107227869B (en) * | 2017-07-17 | 2020-03-31 | 合肥市智慧桥信息科技有限公司 | Sand fixation and greening system based on wind-solar hybrid power station |
CN107190723B (en) * | 2017-07-17 | 2020-04-03 | 合肥市智慧桥信息科技有限公司 | Sand stabilization greening system |
CN107245995B (en) * | 2017-07-17 | 2020-04-03 | 合肥市智慧桥信息科技有限公司 | Sand fixation and greening method based on wind-solar hybrid power station |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206503150U (en) | A kind of basalt composite reinforcing material anchor lattice beam retaining structure | |
CN205742175U (en) | A kind of steel construction protection wall of bored pile | |
CN1195133C (en) | Ordinary concrete block bunker-jump casting crack control method | |
JP2006104909A (en) | Foundation construction method of independent steel mat | |
KR100995815B1 (en) | Shortcrete retaining wall construction method | |
CN203603525U (en) | Reinforcing structure with clamp plate girder and clamp plate column externally arranged for stone structure | |
CN207348067U (en) | A kind of deep foundation pit supporting structure | |
CN108412036A (en) | Assembled H profile steel column-isolated footing-concrete collar tie beam cross connecting node | |
CN108625491A (en) | Assembled H profile steel column-isolated footing-concrete collar tie beam L-shaped connecting node | |
JP6099261B2 (en) | Building construction method and structure | |
CN204080851U (en) | The precast combined distribution transformer box basis of concrete bulk-breaking | |
CN113482036A (en) | Column base structure of reinforced concrete and construction method thereof | |
CN207776228U (en) | A kind of building-block structure suitable for loam wall external corner | |
JPH11303062A (en) | Soil-cement wall | |
JP2009052234A (en) | Construction ground constructing method and construction ground | |
US8024905B2 (en) | Structural reinforcement system for concrete structures | |
CN206090606U (en) | Integrated basis of low layer steel construction building | |
CN213773450U (en) | Tower crane retaining wall construction equipment | |
CN210797664U (en) | Be applied to waterproof structure in bottom plate post-cast strip of basement | |
CN210767255U (en) | Building prefabricated plate assembled structure | |
CN208733696U (en) | A kind of made of metal inclinometer pipe casing | |
CN108360575A (en) | A kind of construction method of ground | |
JP2008231896A (en) | Berm integrated with foundation | |
CN206521757U (en) | Ultra-deep super-span reinforced concrete inner support platform structure | |
CN208533520U (en) | A kind of core concrete project support pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Effective date: 20060928 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070116 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20070605 |