JP2005179975A - Underground facility construction method - Google Patents
Underground facility construction method Download PDFInfo
- Publication number
- JP2005179975A JP2005179975A JP2003420748A JP2003420748A JP2005179975A JP 2005179975 A JP2005179975 A JP 2005179975A JP 2003420748 A JP2003420748 A JP 2003420748A JP 2003420748 A JP2003420748 A JP 2003420748A JP 2005179975 A JP2005179975 A JP 2005179975A
- Authority
- JP
- Japan
- Prior art keywords
- peripheral wall
- earth
- underground
- construction method
- sand
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
本発明は、地下施設を設けるための施工方法に関するものである。 The present invention relates to a construction method for providing an underground facility.
地下施設の一例である地下貯水施設の背景技術について説明する。 The background technology of an underground water storage facility, which is an example of an underground facility, will be described.
都市等には下水道が設けられている。そして、降雨時には、その雨水が、下水道や河川を流れて海等に流れるようにされている。 There are sewers in cities. When it rains, the rainwater flows through the sewers and rivers and flows into the sea.
ところで、時には、その下水道や河川の容量を超える豪雨が降る場合もある。その場合は、行き場を失った雨水は都市等に溢れ、洪水が発生することになる。このことは、近年の急激な都市化に伴って水田等が減少したこと等によって、顕著になっている。
このため、地下に貯水施設(地下貯水施設という)が設けられる場合がある。その地下貯水施設には、豪雨の際の雨水が一時的に貯められ、豪雨が過ぎた後に、その水が徐々に下水道や河川に排出される。
By the way, sometimes heavy rain falls that exceeds the capacity of the sewers and rivers. In that case, the rainwater that has lost its place overflows into the city and floods occur. This is remarkable due to a decrease in paddy fields and the like due to rapid urbanization in recent years.
For this reason, a water storage facility (called an underground water storage facility) may be provided underground. The underground water storage facility temporarily stores rainwater during heavy rain, and after the heavy rain has passed, the water is gradually discharged into sewers and rivers.
そして、地下貯水施設の施工方法として、従来、次のようなものがある。
第1の従来技術は、次のとおりである。
結合されることによって地下貯水施設(その底版・壁部・頂版)を構成することになる多数のピースが、予め工場において鉄筋コンクリートによって製造される。一方、現場においては、地盤に対して凹部(上方に開口する穴)が形成される。
そして、その凹部に対して、各ピースが設置され結合され、その後にその上に土砂類が戻されたり舗装等がされたりすることによって、地下貯水施設(地下施設)が形成される。
Conventional construction methods for underground water storage facilities include the following.
The first prior art is as follows.
A large number of pieces that together form the underground water storage facility (the bottom plate, the wall, and the top plate) are manufactured in advance at the factory by reinforced concrete. On the other hand, in the field, a recess (a hole opened upward) is formed in the ground.
And each piece is installed and couple | bonded with respect to the recessed part, and earth and sand are returned on that, or a pavement etc. are carried out after that, and an underground water storage facility (underground facility) is formed.
第2の従来技術は、次のとおりである。
各面に多数の孔部を有する樹脂製の中空の略立方体状のブロックが、工場において多数製造される。一方、現場においては、地盤に対して凹部(上方に開口する穴)が形成され、その凹部に対して防水シートが張られる。そして、その凹部(その内部)に対して上記の多数のブロックが充填され、その後にその上に土砂類が戻されたり舗装等がされたりすることによって、地下貯水施設(地下施設)が形成される。
The second prior art is as follows.
A large number of hollow, substantially cubic blocks made of resin having a large number of holes on each surface are manufactured in a factory. On the other hand, in the field, a recess (a hole opening upward) is formed in the ground, and a waterproof sheet is stretched on the recess. And the above-mentioned many blocks are filled in the concave portion (the inside), and then the earth and sand are returned or paved, thereby forming an underground water storage facility (underground facility). The
しかしながら、第1の従来技術では、鉄筋コンクリートの各ピースは大きな重量を有し、工場から現場への搬送及び設置等の作業が煩雑である。ピースの大きさを小型化すれば重量的には搬送の負担は軽減されるが、その分ピースの個数が大量のものとなり、数量的に搬送の手間が増加するとともに、設置及び結合のための負担が増大する。
このように、第1の従来技術では、現場でコンクリートを打設する場合と比較すれば能率的な施工ができるとしても、やはり非能率的である。
However, in the first prior art, each piece of reinforced concrete has a large weight, and operations such as transportation and installation from the factory to the site are complicated. If the size of the piece is reduced, the burden of transportation will be reduced in terms of weight, but the number of pieces will be increased accordingly, which will increase the amount of labor for transportation and increase installation and connection. The burden increases.
As described above, the first prior art is inefficient even if the construction can be performed more efficiently than when concrete is placed on site.
また、第2の従来技術では、現場の地盤に対して形成された凹部の底面・壁面・頂面に該当する部分のみならず、その凹部の内部すべてを充填するようにブロックを配設する必要があることから、大量のブロックが必要となり、その搬送等の作業が非常に煩雑となる。
このように、第2の従来技術も非能率的である。
In the second prior art, it is necessary to dispose the block so that not only the portion corresponding to the bottom surface, the wall surface, and the top surface of the recess formed on the ground at the site, but also the entire interior of the recess is filled. Therefore, a large number of blocks are required, and the work such as conveyance becomes very complicated.
Thus, the second prior art is also inefficient.
また、上述の第1の従来技術においては、凹部の内側となる部分の土砂類を除去することによって凹部を形成した後に、その凹部の壁部を形成するピース等を設置する。
第2の従来技術においても、凹部の内側となる部分の土砂類を除去することによって凹部を形成した後に、防水シートを張り、その後にその凹部の内部に多数のブロックを充填する。
そして、上述のいずれの従来技術においても、土砂類を除去して凹部を形成する際に、凹部の内壁面となる部分が安定していないため、その部分において土砂類の崩落が生ずるおそれがある。
In the first prior art described above, after forming the recess by removing the earth and sand at the inside of the recess, a piece or the like that forms the wall of the recess is installed.
Also in the second prior art, after forming the recess by removing the earth and sand at the inside of the recess, a waterproof sheet is stretched, and then the interior of the recess is filled with a number of blocks.
In any of the above-described prior arts, when removing the earth and sand to form the recess, the portion that becomes the inner wall surface of the recess is not stable. .
このため、上述の従来技術においては、その土砂類の崩落を防止するために、まず、仮の工事である土留め工を行う必要がある。すなわち、まず、凹部の内壁面となる部分及びその近傍を掘削してその部分の土砂類を除去し、複数の杭を打ち、その複数の杭にわたって板材を固定して、土砂類の崩落を防止するのである。
しかしながら、その仮の工事である土留め工のために、その分でも、施工の手間がかかって能率的でないとともに、コストも高いものとなる。
For this reason, in the above-described prior art, in order to prevent the earth and sand from collapsing, it is first necessary to perform earth retaining work which is temporary work. That is, first, the portion that becomes the inner wall surface of the concave portion and the vicinity thereof are excavated to remove the earth and sand of that portion, a plurality of piles are hit, and the plate material is fixed over the plurality of piles to prevent the collapse of the earth and sand. To do.
However, because of the earth retaining work, which is a temporary construction, it takes much time for construction and is not efficient and the cost is high.
本発明は、能率的に地下施設を設けることができる方法を提供することを課題とする。 An object of the present invention is to provide a method capable of efficiently providing an underground facility.
この課題を解決するために、請求項1に係る発明は、地下施設を設けるための地下施設施工方法であって、地盤を形成する土砂類に対して固化材を注入して周壁部を形成する周壁部形成工程と、前記周壁部の内側の土砂類を除去する土砂類除去工程と、前記周壁部の内部に底版部を設ける底版部形成工程と、前記周壁部の内部に対して複数の柱を立設する柱立設工程と、前記複数の柱の上端部にわたって頂版部を設ける頂版部形成工程とを有する、地下施設の施工方法である。 In order to solve this problem, the invention according to claim 1 is an underground facility construction method for providing an underground facility, and forms a peripheral wall portion by injecting a solidifying material into earth and sand forming the ground. A peripheral wall portion forming step, earth and sand removing step for removing earth and sand inside the peripheral wall portion, a bottom plate portion forming step for providing a bottom plate portion inside the peripheral wall portion, and a plurality of columns with respect to the inside of the peripheral wall portion Is a construction method of an underground facility having a column standing step for standing and a top plate forming step for providing a top plate over the upper ends of the plurality of columns.
「地下施設」の一例として、地下貯水施設,地下駐車場,地下通路,地下通路を伴う地下店舗(いわゆる地下街),地下の廃棄物処理場等が考えられる。
「地下貯水施設」とは、地下において雨水等を貯留するための施設であり、地下において雨水等を貯留するとともに周囲の土砂類に対して徐々にその雨水を流出(浸透)させるものも含まれる。
Examples of “underground facilities” include underground water storage facilities, underground parking lots, underground passages, underground stores with underground passages (so-called underground shopping streets), underground waste disposal plants, and the like.
"Underground water storage facilities" are facilities for storing rainwater, etc. underground, including those that store rainwater, etc. underground, and gradually drain (infiltrate) the rainwater into the surrounding sediments. .
また、「地盤を形成する土砂類に対して固化材を注入して周壁部を形成する…」の「注入」の代表例として、「土砂類に対する固化材の攪拌」を伴う態様がある。 Further, as a representative example of “injection” of “injecting a solidifying material into the earth and sand forming the ground to form a peripheral wall portion”, there is an aspect involving “stirring of the solidifying material into the earth and sand”.
地盤を形成する土砂類に対して固化材を注入(攪拌)するための具体的方法としては、請求項2に係る発明の態様のほか、上下に位置する一対のスプロケットにわたってチェーンがかけわたされている機械を使用し、スプロケットを回転させるこよによってチェーンを周回させ、そのチェーンによって土砂類に対して固化材が注入(攪拌)する、という態様等、種々のものが考えられる。
そして、請求項2に係る発明と同様に、その作業を近接した複数の地点において行うことによって壁部(周壁部)を形成することが考えられる。
As a specific method for injecting (stirring) the solidifying material to the earth and sand forming the ground, in addition to the aspect of the invention according to claim 2, a chain is extended over a pair of sprockets positioned above and below. There are various types such as a mode in which a chain is revolved by rotating a sprocket using a machine, and a solidifying material is injected (stirred) into the earth and sand by the chain.
And like the invention concerning Claim 2, it is possible to form a wall part (peripheral wall part) by performing the work in a plurality of points which adjoined.
この発明の地下施設施工方法では、次のようにして地下施設が施工される。
まず、周壁部形成工程において、地盤を形成する土砂類に対して固化材を注入して周壁部を形成する。
次に、土砂類除去工程において、周壁部の内側の土砂類を除去する。こうして、凹部が形成される。
次に、底版部形成工程において、周壁部の内部(凹部の内側)に底版部を設ける。
次に、柱立設工程において、周壁部の内部(凹部の内側)に対して複数の柱を立設する。
次に、頂版部形成工程において、複数の柱の上端部にわたって頂版部を設ける。
以上のようにして、地下施設が施工される。
このように、この発明の地下施設施工方法では、能率的に地下施設を設けることができる。
In the underground facility construction method of the present invention, the underground facility is constructed as follows.
First, in a surrounding wall part formation process, a solidification material is inject | poured with respect to the earth and sands which form a ground, and a surrounding wall part is formed.
Next, in the earth and sand removal step, earth and sand inside the peripheral wall portion is removed. Thus, a recess is formed.
Next, in the bottom plate portion forming step, the bottom plate portion is provided inside the peripheral wall portion (inside the recess).
Next, in the column erecting step, a plurality of columns are erect with respect to the inside of the peripheral wall portion (inside the recess).
Next, in the top plate portion forming step, a top plate portion is provided over the upper ends of the plurality of columns.
As described above, underground facilities are constructed.
Thus, in the underground facility construction method of the present invention, the underground facility can be provided efficiently.
また、この発明の地下施設施工方法では、土砂類除去工程(凹部の内側となる部分の土砂類を除去する)の前に周壁部形成工程において周壁部(その内側面が凹部の内壁面となる)が形成される。このため、土砂類を除去する際には、すでに凹部の内壁面となる部分が安定していて土砂類の崩落が防止されているため、仮の工事である土留め工を行う必要がなく、その点でも能率的な施工を行うことができる。 Further, in the underground facility construction method of the present invention, the peripheral wall portion (the inner side surface thereof becomes the inner wall surface of the concave portion) in the peripheral wall portion forming step before the earth and sand removal step (removing the portion of the earth and sand that is inside the concave portion). ) Is formed. For this reason, when removing earth and sand, since the part that will be the inner wall surface of the recess is already stable and the collapse of the earth and sand is prevented, there is no need to perform earth retaining work that is temporary work, In that respect, efficient construction can be performed.
請求項2に係る発明は、請求項1に係る発明の地下施設施工方法であって、前記周壁部形成工程は、軸状材をその軸線方向であって鉛直方向成分を有する方向に沿って地上から地下に向かって進行及び地上に向かって後退させつつ当該軸状材から前記固化材を流出させることによって柱状部を形成することを近接した複数の地点において行うものである、地下施設の施工方法である。 The invention according to claim 2 is the underground facility construction method of the invention according to claim 1, wherein the peripheral wall portion forming step is to ground the shaft-like material in the axial direction and having a vertical component. A method for constructing an underground facility, wherein the columnar portion is formed at a plurality of close points by causing the solidified material to flow out from the shaft-shaped material while proceeding toward the basement and retreating toward the ground. It is.
軸状材から固化材を流出させるのは、軸状材を地下に向かって進行させる時点及び/又は地上に向かって後退させる時点のうちのいずれの態様もあり得る。 The solidified material is allowed to flow out from the shaft-shaped material in any of the time point when the shaft-shaped material is advanced toward the underground and / or the time when the shaft-shaped material is retracted toward the ground.
この発明の地下施設施工方法では、請求項1に係る発明の地下施設施工方法の作用及び効果に加えて、次の作用及び効果が得られる。
すなわち、この発明の地下施設施工方法における周壁部形成工程では、軸状材をその軸線方向であって鉛直方向成分を有する方向に沿って地上から地下に向かって進行させたり、それとは逆に地上に向かって後退させたりしつつ、当該軸状材から固化材を流出させることによって、その軸状材の通過経路に沿って固化材を土砂類に対して注入する。こうして、その固化材が注入された部分に柱状部が形成される。
その作業を近接した複数の地点において行うことによって、複数の柱状部が近接した位置に形成され、その集合体によって壁部が形成され、最終的に周壁部が形成される。
このようにして、この発明の地下施設施工方法では、周壁部が能率的に形成され、請求項1に係る発明の地下施設施工方法(周壁部形成工程)がより具体的にかつ能率的に実現されることになる。
In the underground facility construction method of the present invention, the following operations and effects are obtained in addition to the operations and effects of the underground facility construction method of the invention according to claim 1.
That is, in the peripheral wall forming step in the underground facility construction method of the present invention, the shaft-like material is advanced from the ground toward the underground along the direction of the axial direction and having the vertical component, and conversely, The solidified material is poured into the earth and sand along the passage path of the shaft-shaped material by causing the solidified material to flow out from the shaft-shaped material while being moved backward. Thus, a columnar portion is formed in the portion where the solidifying material is injected.
By performing the work at a plurality of points close to each other, a plurality of columnar parts are formed at close positions, a wall part is formed by the aggregate, and finally a peripheral wall part is formed.
Thus, in the underground facility construction method of the present invention, the peripheral wall portion is efficiently formed, and the underground facility construction method (peripheral wall portion forming step) of the invention according to claim 1 is more specifically and efficiently realized. Will be.
[実施形態1]
次に、本発明の実施形態1について、図1〜図10に基づいて説明する。
[Embodiment 1]
Next, Embodiment 1 of the present invention will be described with reference to FIGS.
まず、図1〜図3に示すように、地盤を形成する土砂類Eに対して固化材を注入して、周壁部10を形成する(周壁部形成工程)。
そのために、ボーリング機(その全体については図示省略)が用意される。ボーリング機は、掘削軸(軸状材)D(図1参照)を有している。
掘削軸Dは、中空状をなし、その先端部には流出孔部(図示省略)が形成され、その外周部にはらせん状の刃部(符号省略)が形成されている。掘削軸Dには攪拌翼等の攪拌のための特別な要素(図示省略)が設けられていてもよい。掘削軸Dは、自身の中心軸線を中心に回転可能であるとともに、その軸線方向に往復移動可能である。
First, as shown in FIGS. 1-3, a solidification material is inject | poured with respect to the earth and sand E which forms the ground, and the surrounding
For this purpose, a boring machine (not shown in its entirety) is prepared. The boring machine has an excavation shaft (shaft-like material) D (see FIG. 1).
The excavation shaft D has a hollow shape, an outflow hole (not shown) is formed at the tip, and a helical blade (reference numeral is omitted) is formed at the outer periphery. The excavation shaft D may be provided with a special element (not shown) for stirring such as a stirring blade. The excavation axis D can rotate around its own central axis and can reciprocate in the axial direction.
そして、図1に示すように、地上(地表面Sの上)から掘削軸Dを回転させつつほぼ鉛直に地下に向かって進行させ、その後に逆回転させつつ地上に向かってほぼ鉛直に後退させるとともに、掘削軸Dの内部に導入された固化材(セメント系固化材)をその先端部の流出孔部から流出させる。
こうして、掘削軸Dの通過した部分(通過経路)の土砂類Eに対して固化材が注入(攪拌を伴う)され、柱状部12が形成される。
なお、掘削軸Dの先端部(流出孔部)が地表面Sに近い位置にある状態の際には、固化材を流出孔部から流出させず、柱状部12の上端部が地表面Sよりも若干低い位置に位置するようにする。
Then, as shown in FIG. 1, the excavation axis D is rotated from the ground (above the ground surface S) while proceeding substantially vertically toward the basement, and then reversely rotated and moved backward substantially vertically toward the ground. At the same time, the solidified material (cement-based solidified material) introduced into the inside of the excavation shaft D is caused to flow out from the outflow hole at the tip.
Thus, the solidified material is injected (with stirring) into the earth and sand E of the portion (passage path) through which the excavation axis D has passed, and the
In addition, when the tip part (outflow hole part) of the excavation shaft D is in a position close to the ground surface S, the solidified material is not allowed to flow out of the outflow hole part, and the upper end part of the
図2に示すように、上述の作業を、所定の線に沿って、近接した複数の地点において行う。1列のみでなく、複数列(例えば2列)の各地点において行うことが好ましい。これによって、所定の厚みを有する壁部14が形成される。
この作業を繰り返して、図3に示すように、例えば対向する2対の壁部14を形成する。こうして、地下に、直方体の壁部に相当する周壁部10が形成される。なお、図3以降においては、周壁部10(その各壁部14)の形状を便宜的に簡略に記載する。
As shown in FIG. 2, the above-described operation is performed at a plurality of close points along a predetermined line. It is preferable to carry out at each point in a plurality of rows (for example, 2 rows) instead of only one row. Thereby, the
By repeating this operation, as shown in FIG. 3, for example, two pairs of opposing
次に、図4に示すように、周壁部10の内側の土砂類Eを除去する(土砂類除去工程)。
すなわち、掘削機によって、その部分の土砂類Eを除去する。
正確にいえば、周壁部10を地表面Sまで仮想的に延長させたものによって囲まれる部分の土砂類Eを除去するとともに、周壁部10の上端部のうち内側部分(相対向する壁部14の側の部分)の上側の土砂類Eも除去する。
こうして、周壁部10に囲まれた凹部15(穴部)が形成される。
Next, as shown in FIG. 4, the earth and sand E inside the
That is, the earth and sand E of the portion is removed by the excavator.
To be precise, the earth and sand E of the portion surrounded by the virtual extension of the
Thus, a recess 15 (hole) surrounded by the
次に、図5に示すように、周壁部10の内部に底版部20を設ける(底版部形成工程)。
すなわち、凹部15の底部の土砂類Eに対して、固化材(セメント系固化材)を注入することによって、底版部20を形成する。
なお、コンクリートを打ったり、複数の鉄筋コンクリートのパネルを敷設したりすることによって、底版部20を形成してもよい。
Next, as shown in FIG. 5, the
That is, the
The
次に、図6及び図7に示すように、周壁部10の内部に対して複数の柱30を立設する(柱立設工程)。
すなわち、複数の柱30(図7参照)を用意するとともに、図6に示すように、底版部20のうちの各柱30の立設位置に、鉄筋コンクリート等からなる複数の基礎版32を設置する。
基礎版32には、複数のアンカーボルト挿入穴部33が形成されている。
なお、基礎版32が設置されなかった部分にコンクリートが打設されて、この施設の底面が面一状(すべて基礎版32の上面と同一高さ)とされてもよい。
Next, as shown in FIG.6 and FIG.7, the some
That is, a plurality of pillars 30 (see FIG. 7) are prepared, and a plurality of
A plurality of anchor bolt insertion holes 33 are formed in the
In addition, the concrete may be cast in a portion where the
各柱30(図7)は、鉄骨や鉄筋コンクリート等によって形成されている。鉄骨の場合には防錆のためのメッキや塗装がされている(特に、この地下施設が地下貯水施設の場合)。また、鉄骨の表面にコンクリートやモルタルの被覆がされているものでもよい。
各柱30の下端部には平板状の支持部35が設けられ、各支持部35にはアンカーボルト36が結合されている。各柱30の上端部には、張り出し部31が設けられている。張り出し部31は、原則として、四方に向かって設けられている。凹部15のうちの縁部や角部に立設される柱30においては、そのうちの一部が設けられない。
Each column 30 (FIG. 7) is formed of steel frame, reinforced concrete, or the like. In the case of a steel frame, it is plated or painted for rust prevention (especially when this underground facility is an underground water storage facility). Further, the surface of the steel frame may be covered with concrete or mortar.
A flat plate-
そして、各柱30を各基礎版32に対して載置し、各アンカーボルト挿入穴部33に各アンカーボルト36を挿入した後にモルタルを充填することによって、各柱30を各基礎板に対して固定する。
こうして、凹部15に対して複数の柱30を立設する。
柱30は、凹部15(周壁部10)の形状に沿って、縦方向(凹部15の幅方向)に複数行、横方向(凹部15の奥行方向)に複数列の配置で立設する。
And each
Thus, the plurality of
The
次に、図8に示すように、複数の柱30の上端部にわたって、梁40を設ける(梁配設工程)。すなわち、隣接する柱30(その張り出し部31)同士を連結するようにして、梁40を固定する。
Next, as shown in FIG. 8, a
次に、図9に示すように、複数の柱30の上端部にわたって頂版部50を設ける(頂版部形成工程)。
すなわち、梁40の上の鉄筋コンクリート等からなる複数のパネルを設置したり、梁40の上にコンクリートを打設したりすることによって、頂版部50を形成する。
Next, as shown in FIG. 9, the
That is, the
次に、図10に示すように、頂版部50(その近傍を含む)の上に土砂類Eを戻し(土砂類復元工程)、さらには、必要に応じて、コンクリートやアスファルト等によって舗装を行う。 Next, as shown in FIG. 10, the earth and sand E is returned on the top plate portion 50 (including the vicinity thereof) (the earth and sand restoration process), and further, paved with concrete or asphalt as necessary. Do.
以上のようにして、地下施設が能率的に形成される。
なお、この地下施設が雨水等を貯留するための地下貯水施設の場合には、適宜、上述の各作業とともに又は相前後して、雨水が流入する流入管との接続及び雨水を流出させるための流出管との接続が行われる。
また、地下施設が水密性を要するものの場合には、適宜、遮水材が配設され、水の流入及び流出が防止される。
As described above, underground facilities are efficiently formed.
In addition, when this underground facility is an underground water storage facility for storing rainwater, etc., the connection with the inflow pipe into which rainwater flows in and the rainwater flow out as appropriate, together with or in parallel with the above-described operations. Connection to the outflow pipe is made.
In addition, when the underground facility requires water tightness, a water shielding material is appropriately provided to prevent inflow and outflow of water.
[実施形態2]
次に、本発明の実施形態2について、実施形態1との相違点を中心に、図11に基づいて説明する。実施形態1と同一の要素については同一の符号を付して、その説明は適宜省略する。
[Embodiment 2]
Next, a second embodiment of the present invention will be described based on FIG. 11 with a focus on differences from the first embodiment. The same elements as those in the first embodiment are denoted by the same reference numerals, and the description thereof is omitted as appropriate.
実施形態2は、柱立設工程において実施形態1と相違する。
すなわち、複数の柱130は、杭状をなしており、実施形態1の柱30よりも長く形成されている。その先端は尖っていてもよい。
そして、各柱130を下方に向けて打つことによって、各柱130は、底版部20を貫通して(底版部20に予め貫通用の孔部122を形成してもよい)、各柱130のうちの下側部分は、底版部20の下に位置する土砂類Eに対して埋設状態で支持される。
こうして、各柱130が固定される。
その後は、実施形態1と同様の作業が行われる。
The second embodiment is different from the first embodiment in the column erecting step.
That is, the plurality of
Then, by striking each
Thus, each
Thereafter, the same operation as in the first embodiment is performed.
なお、上記のものはあくまで本発明の数例の実施形態にすぎず、当業者の知識に基づいて種々の変更を加えた態様で本発明を実施できることはもちろんである。 It should be noted that the above is only a few embodiments of the present invention, and it is needless to say that the present invention can be implemented in various modifications based on the knowledge of those skilled in the art.
10 周壁部
20 底版部
30 柱
50 頂版部
E 土砂類
10
Claims (2)
地盤を形成する土砂類に対して固化材を注入して周壁部を形成する周壁部形成工程と、
前記周壁部の内側の土砂類を除去する土砂類除去工程と、
前記周壁部の内部に底版部を設ける底版部形成工程と、
前記周壁部の内部に対して複数の柱を立設する柱立設工程と、
前記複数の柱の上端部にわたって頂版部を設ける頂版部形成工程と
を有する、地下施設の施工方法。 An underground facility construction method for establishing an underground facility,
A peripheral wall portion forming step for injecting a solidifying material into the earth and sand forming the ground to form a peripheral wall portion,
Earth and sand removal step of removing earth and sand inside the peripheral wall,
A bottom plate portion forming step of providing a bottom plate portion inside the peripheral wall portion;
A column erecting step of erecting a plurality of columns with respect to the inside of the peripheral wall portion;
And a top plate portion forming step of providing a top plate portion over the top ends of the plurality of pillars.
前記周壁部形成工程は、軸状材をその軸線方向であって鉛直方向成分を有する方向に沿って地上から地下に向かって進行及び地上に向かって後退させつつ当該軸状材から前記固化材を流出させることによって柱状部を形成することを近接した複数の地点において行うものである、
地下施設の施工方法。
The underground facility construction method according to claim 1,
The peripheral wall portion forming step includes moving the solidified material from the shaft-shaped material while moving the shaft-shaped material from the ground along the direction having the vertical component in the axial direction and moving backward from the shaft toward the ground. Forming the columnar part by allowing it to flow out is performed at a plurality of close points,
Construction method for underground facilities.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003420748A JP2005179975A (en) | 2003-12-18 | 2003-12-18 | Underground facility construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003420748A JP2005179975A (en) | 2003-12-18 | 2003-12-18 | Underground facility construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2005179975A true JP2005179975A (en) | 2005-07-07 |
Family
ID=34782182
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003420748A Pending JP2005179975A (en) | 2003-12-18 | 2003-12-18 | Underground facility construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2005179975A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101118263B1 (en) * | 2011-06-28 | 2012-03-20 | 주식회사 인우 | Rain retaining facility and constructing method thereof using precast concrete block |
-
2003
- 2003-12-18 JP JP2003420748A patent/JP2005179975A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101118263B1 (en) * | 2011-06-28 | 2012-03-20 | 주식회사 인우 | Rain retaining facility and constructing method thereof using precast concrete block |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2837128B2 (en) | Construction method of cast-in-place concrete pile | |
JP2014001542A (en) | Foundation for installation of column, and construction method for the column | |
JP3586864B2 (en) | Underground structure construction method and elevated traffic path | |
JP4611113B2 (en) | Integrated construction method of pile and column | |
JP2006132219A (en) | Underground structure construction method, underground structure, and precast concrete side wall or intermediate wall/pole for use in the same | |
JP2008308945A (en) | Concrete foundation combined with tension pile, and construction method thereof | |
JP2001329545A (en) | Bridge pier foundation construction method and floor slab for bridge pier | |
JP2005179975A (en) | Underground facility construction method | |
CN114875944A (en) | Open caisson supporting structure and construction method | |
JP6931876B2 (en) | How to build a permeable wall for slope reinforcement | |
CN109235453B (en) | Deep foundation pit PRC pipe pile assembled supporting method | |
JP2010121368A (en) | Method for constructing foundation structure for building, and the foundation structure for the building | |
KR100493516B1 (en) | Micro pile and assembly foundation reinforcement structure member and its method for pier | |
KR200224758Y1 (en) | Structure of caisson soil protection four concret caisson | |
JPH0517955A (en) | Execution method for direct foundation and form panel for direct foundation | |
JP2019108677A (en) | Drain pile and liquefaction countermeasures method | |
JP7132681B2 (en) | Foundation members of road protection fences, road protection fences, and construction methods thereof | |
KR100696882B1 (en) | Column-construction method for applying guide casing to column | |
JP2005240430A (en) | Building foundation and construction method therefor | |
KR200291370Y1 (en) | Concrete caisson structure for earth and sand guard of pier's basis | |
KR20090027490A (en) | Method for constructing underground structure | |
JP3105706B2 (en) | Construction method of piled raft foundation using existing foundation | |
KR100543284B1 (en) | The method of constructing support wall to use as pillar and slab | |
JP3593752B2 (en) | Retaining wall structure and built flat land structure or built road structure on steep slopes | |
JP2001295299A (en) | Precast block foundation for guardrail traffic, sign, etc. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20061006 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080627 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080707 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080904 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090206 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20090603 |