JP2005090066A - Method of setting suspended scaffold - Google Patents

Method of setting suspended scaffold Download PDF

Info

Publication number
JP2005090066A
JP2005090066A JP2003324042A JP2003324042A JP2005090066A JP 2005090066 A JP2005090066 A JP 2005090066A JP 2003324042 A JP2003324042 A JP 2003324042A JP 2003324042 A JP2003324042 A JP 2003324042A JP 2005090066 A JP2005090066 A JP 2005090066A
Authority
JP
Japan
Prior art keywords
bridge girder
scaffold
anchoring means
fixing means
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003324042A
Other languages
Japanese (ja)
Inventor
Nobuhiko Kimura
信彦 木村
Yoshihiro Shigeta
善裕 繁田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kidoh Construction Co Ltd
Original Assignee
Kidoh Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kidoh Construction Co Ltd filed Critical Kidoh Construction Co Ltd
Priority to JP2003324042A priority Critical patent/JP2005090066A/en
Publication of JP2005090066A publication Critical patent/JP2005090066A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Movable Scaffolding (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method of setting a suspended scaffold which is for use in a survey, reinforcing work, and repairing work under a viaduct, does not require a large-scale traffic regulation on a road etc. under the viaduct, and achieves the erection of the suspended scaffold while reducing the number of post-driven anchors driven into a bridge girder. <P>SOLUTION: In the method of setting the suspended scaffold which is built under the viaduct, first a plurality of anchoring means are set in each pier (or abutment) of a bridge girder at predetermined intervals in a direction at right angles to the bridge girder, and a plurality of prestressing concrete steels (PC steel) are extended from one of the anchoring means to the other anchoring means. Then a straining means provided for one of or both of the anchoring means functions to apply a predetermined straining force to the prestressing concrete steels (PC steel), and scaffold members built up from one of the anchoring means are successively supplied to the other anchoring means. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、高架橋下での調査、補強、補修工事において、落下防護工や工事足場工を施工する当たり、交通規制を極力少なくする吊り足場の設置方法に関するものである。   The present invention relates to a suspension scaffold installation method for reducing traffic restrictions as much as possible when constructing a fall protection work or a construction scaffold in survey, reinforcement, and repair work under a viaduct.

我が国の社会資本は、高度経済成長期に比較的短い期間に急速に整備されてきた。その中で、代表的な構造物として橋梁がある。この橋梁構造物は、主に鋼とコンクリート材料で構成されているが、これらの構造物は寿命50年を目標に建設され、コンクリートの耐用年数を経過したものが徐々に多くなってきている。また、中性化や塩害等の構造物の劣化、社会ニーズにあった物流の増大(車両の大型化)等の様々な要因で、調査や補修工事が頻繁に行なわれるようになってきた。   Japan's social capital has been rapidly developed in a relatively short period during the period of high economic growth. Among them, there is a bridge as a typical structure. This bridge structure is mainly composed of steel and concrete materials, but these structures are constructed with a target of 50 years of life, and the number of concrete structures that have reached the end of their useful life is gradually increasing. In addition, investigations and repair work are frequently performed due to various factors such as neutralization and deterioration of structures such as salt damage, and an increase in physical distribution that meets social needs (larger vehicles).

橋梁の調査や補修工事の一般的な足場は、吊り足場と高所作業車(リフトやオーバーハング)が主流となっている。低価格で安全に施工できる単管吊り足場は、単管足場設置のために橋桁へのアンカー打設や単管の配置のための大規模な交通規制や夜間工事となることから架設費用が高価となる点や、単管を固定するために多くの後打アンカーを桁に打設するため、橋桁を痛めるという問題がある。また、高所作業車の場合は、作業人数の制限があることや作業面積が小さくなることから、作業能率が落ちるために工期がかかり、高価となる。   Suspended scaffolding and aerial work platforms (lifts and overhangs) are the mainstreams for general scaffolding and repair work. Single-tube suspension scaffolds that can be safely constructed at low cost are expensive to construct due to large-scale traffic regulations and night construction for anchor placement on bridge girders and single pipe placement for single-tube scaffolding installation There is a problem that the bridge girder is damaged because a large number of post strike anchors are placed on the girder in order to fix the single pipe. Further, in the case of an aerial work vehicle, the number of workers is limited and the work area is reduced, so that the work efficiency is lowered and the work period is increased and the work is expensive.

また、本線上にトラベラー等の大型移動足場を設置する方法があるが、本線道路の規制を必要とする点や、設計上、壁の高欄や張り出し部に大きな荷重(集中荷重で10t)をかけられないという問題がある。さらに、大型移動足場の製作費用が高くなるという問題もある。   In addition, there is a method to install a large-scale mobile scaffolding such as a traveler on the main line. However, it is necessary to regulate the main road, and a large load (10 tons by concentrated load) is applied to the railing and overhanging part of the design. There is a problem that can not be. In addition, there is a problem that the production cost of the large mobile scaffold becomes high.

このため、大規模な交通規制を必要とせず、比較的安価なワイヤーブリッジ方式が実用化されている。この方式は、両端の橋脚(または橋台)にアンカー金具を設置し、橋桁の下方に複数状のメッセンジャーワイヤーを伸展して両端を各アンカー金具に固定する。メッセンジャーワイヤー上には、橋桁と直角方向に所定の間隔を置いて、ころがしと呼ばれる単管等が配置されている。そして、ころがし上に足場板を並べて通路を確保する方法である。当然、ころがし部には、落下防止用の安全ネットが設置されている。この方法により、大規模な交通規制は必要としなくなったが、メッセンジャーワイヤーが中央で大きく撓むため、橋桁下方の通行車両等の支障となることや、中央部分おいて桁と作業床の間隔が大きくなって、調査や補修作業が困難になるという問題が出てくる。このため、橋桁と作業床の間隔を一定とするために、桁にアンカーを設けて吊り金具でメッセンジャーワイヤーを吊り固定する方法が用いられるが、吊り金具の間隔が1m前後と短くなり、桁本体に多くの後打アンカーを必要とする点や吊り金具が支障となって調査や補修作業の効率が悪くなるという問題がある。また、メッセンジャーワイヤーの撓みを少 なくするために、橋脚部分でウインチ等による巻取機で張力を与える方法が提案されているが、メッセンジャーワイヤー自体に大きな張力を期待することができなく、長い橋長の場合には余り効果がないという問題がある。
特開平6−185020号公報
For this reason, a relatively inexpensive wire bridge system has been put into practical use without requiring large-scale traffic regulation. In this method, anchor metal fittings are installed on the bridge piers (or abutments) at both ends, and a plurality of messenger wires are extended below the bridge girder to fix both ends to each anchor metal fitting. On the messenger wire, a single pipe or the like called rolling is arranged at a predetermined interval in a direction perpendicular to the bridge girder. And it is the method of arranging a scaffold board on rolling and ensuring a channel | path. Naturally, a safety net for preventing the fall is installed in the rolling part. This method eliminates the need for large-scale traffic regulation, but because the messenger wire bends greatly in the center, it can interfere with passing vehicles under the bridge girder, and the gap between the girder and the work floor in the center. The problem will be that it will become difficult to investigate and repair. For this reason, in order to keep the distance between the bridge girder and the work floor constant, a method is used in which anchors are installed on the girder and the messenger wire is suspended and fixed with a hanging bracket. In addition, there are problems in that a large number of post-fixed anchors are required and suspension metal fittings hinder the efficiency of investigation and repair work. In order to reduce the deflection of the messenger wire, a method has been proposed in which tension is applied to the bridge pier with a winder using a winch or the like. However, a large tension cannot be expected in the messenger wire itself. In the case of long, there is a problem that there is not much effect.
JP-A-6-185020

解決しようとする課題は、高架橋下での調査及び補修工事において、下方道路に大規模な交通規制を必要とすることや、吊り足場を架設するために、橋桁本体に多くの後打アンカーを必要とすることや、作業環境が悪いという点である。   The problem to be solved is that large-scale traffic regulation is required on the lower road in the investigation and repair work under the viaduct, and a large number of rear anchors are required on the bridge girder body to construct the suspension scaffold And the work environment is bad.

本発明は、両端の橋脚(または橋台)に定着手段を設け、橋桁の下方にPC鋼材を緊張し、下方の道路の交通規制を極力少なくするとともに、PC鋼材の大きな緊張力によってPC鋼材の撓みを少なくして、作業性の良い吊り足場と架設費用の低減を行なうことを最も主要とする。   In the present invention, fixing means are provided at both piers (or abutments), the PC steel is tensioned below the bridge girder, traffic restrictions on the roads below are minimized, and the PC steel is bent by the large tension of the PC steel. The main focus is to reduce suspension costs and to reduce the cost of erection.

本発明の吊り足場の設置方法は、橋桁の両橋脚部(または橋台部)に固定した複数本のPC鋼材に一定の緊張力を与えることによって、橋桁中央部分の撓みを極力抑えることができる。このため、PC鋼材を橋桁から支持する吊り金具も非常に少なくてすみ、橋桁の損傷も少なく、作業性も向上する。また、橋桁下方の道路規制もPC鋼材の設置時及び撤去時のみとなり、工事公害の少ない吊り足場を提供できるという利点がある。   The suspension scaffold installation method of the present invention can suppress the bending of the central part of the bridge girder as much as possible by giving a certain tension to a plurality of PC steel members fixed to both bridge piers (or abutment parts) of the bridge girder. For this reason, the number of suspension brackets for supporting the PC steel material from the bridge girder is very small, damage to the bridge girder is small, and workability is improved. In addition, the road regulation under the bridge girder is only at the time of installation and removal of PC steel, and there is an advantage that a suspension scaffold with less construction pollution can be provided.

両橋脚(橋台)間に大きな引張強度を持つPC鋼材で橋桁間との間隔を一定に保つという目的で、効率の良い作業性や橋桁本体への損傷を軽減した吊り足場の設置方法を実現した。   For the purpose of keeping the distance between the bridge girders constant with PC steel with high tensile strength between both piers (abutments), we realized an efficient workability and a method of installing a suspension scaffold that reduced damage to the bridge girder body. .

図1は、本発明の吊り足場の設置方法を説明する全体図である。橋桁1の両橋台2の前面には、橋桁1の下端から一定の間隔をあけて定着手段7が設置されている。定着手段7は、橋桁1と直角方向に所定の間隔を置いて複数個橋台2に固定される。一方の定着手段7から他方の定着手段7にPC鋼材3を通し、どちらかの定着手段7部分でPC鋼材3に緊張力を与える。そしてどちらかの定着手段7側から足場材4である滑車付クランプところばしを組み立てて送り出していく。足場材4を送り出していく過程で所定の間隔を置いて橋桁より吊り金具6を設置して、橋桁との離間を一定にする。この時、作業床となる足場板5も、同時に配置されていく。     FIG. 1 is an overall view illustrating a method for installing a suspended scaffold according to the present invention. Fixing means 7 is installed on the front surface of both abutments 2 of the bridge girder 1 with a certain distance from the lower end of the bridge girder 1. A plurality of fixing means 7 are fixed to the abutment 2 at a predetermined interval in a direction perpendicular to the bridge girder 1. The PC steel material 3 is passed from one fixing means 7 to the other fixing means 7, and tension is applied to the PC steel material 3 at either fixing means 7 portion. And the clamp part with a pulley which is the scaffolding material 4 is assembled and sent out from either fixing means 7 side. In the process of sending out the scaffold material 4, the hanging bracket 6 is installed from the bridge girder at a predetermined interval, and the distance from the bridge girder is made constant. At this time, the scaffolding plate 5 serving as a work floor is also disposed at the same time.

図2から図4までは、本発明の吊り足場の設置手順を示す説明図である。両橋台2の前面に、枠組み足場8を設置し、橋桁1の下端から一定の間隔を置いて後打アンカー9を橋台2に打設する。後打アンカー9の設置本数は、橋桁1の全幅を調査、補修できるように、橋桁1の幅によって変化させる。後打アンカー9の設置が完了すると、橋台2の壁面に定着手段7を後打アンカー9で固定する。(図2)   2 to 4 are explanatory views showing the installation procedure of the suspension scaffold according to the present invention. A frame scaffolding 8 is installed in front of both abutments 2 and a post anchor 9 is driven on the abutment 2 at a certain distance from the lower end of the bridge girder 1. The number of post-hit anchors 9 is changed according to the width of the bridge girder 1 so that the entire width of the bridge girder 1 can be investigated and repaired. When the installation of the post strike anchor 9 is completed, the fixing means 7 is fixed to the wall surface of the abutment 2 with the post strike anchor 9. (Figure 2)

定着手段7の下方の隣接した枠組み足場8上に滑車11を設置し、地上よりメッセンジャーワイヤー10を滑車11から定着手段7を通して、他方の定着手段7及び滑車11を通して地上の巻付機(図示省略)に取り付ける。メッセンジャーワイヤー10の後端部には、PC鋼材3を接続し、巻取機によりメッセンジャーワイヤー10を巻き取ることによって、PC鋼材3を橋桁の下方に展張していく。(図3)   A pulley 11 is installed on an adjacent framework scaffold 8 below the fixing means 7, and a messenger wire 10 is passed from the pulley through the fixing means 7 through the fixing means 7 and the other fixing means 7 and the pulley 11 from the ground (not shown). ). The PC steel material 3 is connected to the rear end portion of the messenger wire 10, and the PC steel material 3 is expanded below the bridge girder by winding the messenger wire 10 with a winder. (Figure 3)

両側の定着手段7へのPC鋼材3の展張が完了すると、どちらかの定着手段7内に設置した緊張手段により、PC鋼材3に所定の緊張力を与え、定着手段7で固定する。PC鋼材3の緊張が完了すると、どちらか一方の枠組み足場8より、単管であるころばしと滑車付クランプを組み立てた足場材4を送り出していく。足場材4上には、作業床となる足場板5も設置されている。足場材4を送り出していく過程で、橋桁1の下方と足場材4とを吊り金具6で緊結して支持し、橋桁1方向に所定の間隔で設置していく。(図4)   When the extension of the PC steel material 3 to the fixing means 7 on both sides is completed, a predetermined tension force is applied to the PC steel material 3 by the tension means installed in one of the fixing means 7 and the fixing means 7 fixes the PC steel material 3. When the tension of the PC steel material 3 is completed, the scaffolding material 4 in which the rolls that are single tubes and the clamps with pulleys are assembled is sent out from either one of the frame scaffolds 8. On the scaffold material 4, a scaffold plate 5 serving as a work floor is also installed. In the process of sending out the scaffolding material 4, the lower part of the bridge girder 1 and the scaffolding material 4 are tightly supported by the hanging metal fittings 6, and installed in the direction of the bridge girder 1 at a predetermined interval. (Fig. 4)

足場材4と吊り金具6の設置とともに、落下防止用に足場材4全面に安全ネットを設置する。吊り足場の解体方法は、前記した設置方法の逆の作業を行なえば良い。   Along with the installation of the scaffolding material 4 and the suspension bracket 6, a safety net is installed on the entire surface of the scaffolding material 4 to prevent the fall. The suspension scaffold dismantling method may be performed by performing the reverse operation of the installation method described above.

図5は、定着手段7内の緊結手段を示す説明図である。定着手段7は、後打アンカー9によって固設されている。定着手段7の前部には、PC鋼材3を通す貫通孔が設けられたプレート14が取り付けられている。プレート14の後方には、PC鋼材3に緊張力を与える緊張手段である緊張ジャッキ12が設置されている。PC鋼材3は、緊張ジャッキ12本体の中央部からプレート14の貫通孔を通し、橋桁1の下方を通して他方の橋脚2の定着手段7の貫通孔に入れて定着具13でプレートに固定されている。PC鋼材の緊張は、緊張ジャッキ12の頭部を定着具13で固定し、緊張ジャッキ12を伸長することによって、PC鋼材3に緊張力を与える。PC鋼材3へ所定の緊張力が導入されると、プレート14後方の定着具13を締めてPC鋼材3へのプレストレス導入を完了する。   FIG. 5 is an explanatory view showing the fastening means in the fixing means 7. The fixing means 7 is fixed by a post-hit anchor 9. A plate 14 provided with a through hole through which the PC steel material 3 passes is attached to the front portion of the fixing means 7. Behind the plate 14, a tension jack 12, which is a tension means that gives tension to the PC steel material 3, is installed. The PC steel material 3 passes through the through hole of the plate 14 from the central portion of the tension jack 12 main body, passes through the lower part of the bridge girder 1, enters the through hole of the fixing means 7 of the other bridge pier 2, and is fixed to the plate by the fixing tool 13. . The tension | tensile_strength of PC steel materials gives tension | tensile_strength to PC steel materials 3 by fixing the head of the tension | tensile_strength jack 12 with the fixing tool 13, and extending | stretching the tension | tensile_strength jack 12. FIG. When a predetermined tension force is introduced into the PC steel material 3, the fixing tool 13 behind the plate 14 is tightened to complete the prestress introduction into the PC steel material 3.

PC鋼材3としては、PC鋼棒やPC鋼線を使用することも可能であるが、緊張力が大きく、曲げに対して取り扱いやすいPC鋼より線が最適である。   As the PC steel material 3, it is possible to use a PC steel rod or a PC steel wire, but a wire is most suitable from PC steel which has a large tension and is easy to handle against bending.

図6は、吊り金具を詳細に説明する断面図である。橋桁1がI桁の吊り金具6の設置方法として、橋桁1に後打アンカーを設けない方法である。I桁の下部フランジのハンチ部分を走行できるローラ16を装備し、I桁の下方フランジを挟むように製作した移動金具15を設置し、その下方に吊り金具6を取り付けてPC鋼材3を支持する。この方法により、橋桁1本体に後付アンカーを設けることがなくなり、橋桁1の本体強度を低下させることがなくなる。   FIG. 6 is a cross-sectional view illustrating the hanging metal fitting in detail. The bridge girder 1 is a method of installing the hanging bracket 6 having the I girder in which no post anchor is provided on the bridge girder 1. Equipped with a roller 16 that can run on the haunch part of the lower flange of the I-girder, a moving metal fitting 15 that is manufactured so as to sandwich the lower flange of the I-girder is installed, and a hanging metal fitting 6 is attached below the metal fitting 15 to support the PC steel 3 . By this method, it is no longer necessary to provide a retrofitting anchor on the main body of the bridge girder 1 and the main body strength of the bridge girder 1 is not reduced.

本実施形態では、調査、補修工事における吊り足場の設置方法を開示したが、本吊り足場の設置方法は、新設工事においても適用ができる。   In the present embodiment, the method for installing the suspension scaffold in the investigation and repair work is disclosed. However, the method for installing the suspension scaffold can also be applied to the new construction.

高架橋下の調査や補修工事の交通規制等が少なく、一般道や鉄道を横断する高架橋の調査、補修工事の吊り足場設置方法に適用できる。   There are few traffic regulations for surveys and repair work under the viaduct, and it can be applied to surveys on viaducts that cross ordinary roads and railways, and to install suspension scaffolds for repair work.

本発明の吊り足場の設置方法を説明する全体図である。It is a general view explaining the installation method of the suspension scaffold of this invention. 本発明の吊り足場の設置手順を示す説明図である。It is explanatory drawing which shows the installation procedure of the suspension scaffold of this invention. 本発明の吊り足場の設置手順を示す説明図である。It is explanatory drawing which shows the installation procedure of the suspension scaffold of this invention. 本発明の吊り足場の設置手順を示す説明図である。It is explanatory drawing which shows the installation procedure of the suspension scaffold of this invention. 定着手段7内の緊結手段を示す説明図である。FIG. 6 is an explanatory view showing a fastening means in the fixing means 7. 吊り金具を詳細に説明する断面図である。It is sectional drawing explaining a hanging metal fitting in detail.

符号の説明Explanation of symbols

1 橋桁
2 橋台
3 PC鋼材
4 足場材
5 足場板
6 吊り金具
7 定着手段
8 枠組み足場
9 後打アンカー
10 メッセンジャーワイヤー
11 滑車
12 緊張ジャッキ
13 定着具
14 プレート
15 移動金具
16 ローラ
DESCRIPTION OF SYMBOLS 1 Bridge girder 2 Abutment 3 PC steel material 4 Scaffolding material 5 Scaffold plate 6 Suspension metal fitting 7 Fixing means 8 Frame scaffolding 9 Post strike anchor 10 Messenger wire 11 Pulley 12 Tension jack 13 Fixing tool 14 Plate 15 Moving metal 16 Roller

Claims (1)

橋梁下に組み立てられる吊り足場の設置方法において、橋桁の両橋脚部(または橋台部)に橋桁と直角方向に所定の間隔を置いて複数の定着手段を設置し、その一方の定着手段から他方の定着手段に複数本のPC鋼材を引き渡し、前記定着手段のどちらか一方かまたは両方に設けた緊張手段により複数本のPC鋼材に一定の緊張力を与え、どちらかの定着手段側から組み上げた足場材を他方の定着手段側へ送り出していくことを特徴とする吊り足場の設置方法。   In the installation method of the suspension scaffold assembled under the bridge, a plurality of fixing means are installed at predetermined intervals in the direction perpendicular to the bridge girder on both piers (or abutments) of the bridge girder. Scaffold assembled from either side of fixing means by delivering a plurality of PC steel materials to fixing means, applying a certain tension to the plurality of PC steel materials by means of tensioning means provided on one or both of the fixing means A method for installing a suspension scaffold, wherein the material is sent to the other fixing means side.
JP2003324042A 2003-09-17 2003-09-17 Method of setting suspended scaffold Pending JP2005090066A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003324042A JP2005090066A (en) 2003-09-17 2003-09-17 Method of setting suspended scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003324042A JP2005090066A (en) 2003-09-17 2003-09-17 Method of setting suspended scaffold

Publications (1)

Publication Number Publication Date
JP2005090066A true JP2005090066A (en) 2005-04-07

Family

ID=34454907

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003324042A Pending JP2005090066A (en) 2003-09-17 2003-09-17 Method of setting suspended scaffold

Country Status (1)

Country Link
JP (1) JP2005090066A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011058266A (en) * 2009-09-10 2011-03-24 West Japan Railway Co Temporary installation method of work stage for viaduct
JP5022524B1 (en) * 2012-04-17 2012-09-12 株式会社Osk Hanging scaffold construction method
KR101549231B1 (en) 2013-09-27 2015-09-03 삼성중공업 주식회사 Apparatus for managing heli-deck
CN111827124A (en) * 2020-07-29 2020-10-27 中铁二局集团有限公司 T-beam transverse prestress tensioning auxiliary device, mounting method and using method
CN113668396A (en) * 2021-08-17 2021-11-19 广西路桥工程集团有限公司 Portable portable hogging moment stretch-draw equipment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011058266A (en) * 2009-09-10 2011-03-24 West Japan Railway Co Temporary installation method of work stage for viaduct
JP5022524B1 (en) * 2012-04-17 2012-09-12 株式会社Osk Hanging scaffold construction method
KR101549231B1 (en) 2013-09-27 2015-09-03 삼성중공업 주식회사 Apparatus for managing heli-deck
CN111827124A (en) * 2020-07-29 2020-10-27 中铁二局集团有限公司 T-beam transverse prestress tensioning auxiliary device, mounting method and using method
CN113668396A (en) * 2021-08-17 2021-11-19 广西路桥工程集团有限公司 Portable portable hogging moment stretch-draw equipment

Similar Documents

Publication Publication Date Title
KR101171039B1 (en) Partially and fully earth-anchored cable-stayed bridge using main span prestressing appratus and construction method for the same
KR100727172B1 (en) Precast Concrete Panel and Nonsupport Construction Method of Bridge&#39;s Cantilever Work Utilizing P.C.P
JP5097313B2 (en) Suspended scaffold and its installation method
JP3440422B2 (en) Bridge construction method and bridge construction device
JP2019007206A (en) Method of installing non-scaffold for bridge inspection permanent scaffold
KR20100025161A (en) Girder bridge connected to abutment and the construction method thereof
CN109138431A (en) A kind of Super High pump line Overbridge device and its construction method
KR101152444B1 (en) The pre-stress concrete bim and that making method using a pre-tensioning construction
JP3635004B2 (en) Bridge cantilever construction method
CN110295548A (en) The makeshift device of mechanical balance is maintained under the bridge construction technique of fitting the arch first then fitting the girder
JP2734987B2 (en) Existing bridge repair method
JP2005090066A (en) Method of setting suspended scaffold
KR20170107308A (en) Bracket for cantilever and cantilever construction method using the bracket
KR100592196B1 (en) large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
CN210713755U (en) High-altitude combined type steel beam component mounting and operating platform
KR20100057446A (en) Apparatus for preventing vertical structure from falling sideward
KR20090130516A (en) Temporary reinforcing apparatus for increasing cast height of concrete in concrete filled tube column
JP2744955B2 (en) Reinforcement structure and reinforcement method of hinge part of gel bar bridge
KR20060095149A (en) Dead load composite system by temporary tensioning method
CN212641470U (en) Prestressed fish-bellied beam steel strand construction guiding device
JP3950284B2 (en) Method for reinforcing concrete slabs
JP4375788B2 (en) Construction method of upper-floor type suspension floor slab bridge
KR100426611B1 (en) Connecting device for enhancing steel wire for a bridge
RU2506367C2 (en) Method to dismantle t-shaped frame of bridge span and top-trolley beam for realisation of this method
KR20040084438A (en) Section enlargement repairing and reinforcing apparatus for reinforcing earing power of reinforced concrete structures by introducing prestress to entended section and repairing and reinforcing construction method using the apparatus