JP2005030034A - Stairs structure and construction method of stairs structure - Google Patents
Stairs structure and construction method of stairs structure Download PDFInfo
- Publication number
- JP2005030034A JP2005030034A JP2003195420A JP2003195420A JP2005030034A JP 2005030034 A JP2005030034 A JP 2005030034A JP 2003195420 A JP2003195420 A JP 2003195420A JP 2003195420 A JP2003195420 A JP 2003195420A JP 2005030034 A JP2005030034 A JP 2005030034A
- Authority
- JP
- Japan
- Prior art keywords
- staircase
- formwork
- concrete
- slab
- stairs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、鉄筋コンクリート建築物における階段構造物及び階段構造物の施工方法に関する。
【0002】
【従来の技術】
従来の階段構造物としては、例えば、特許第2535256号に示すように、斜設された階段用スラブ型枠と、該階段用スラブ型枠の上面に配筋された階段鉄筋と、階段用スラブ型枠及び階段鉄筋の上に配される埋込み式のメタルラスの階段型枠と、階段用スラブ型枠及び階段型枠の間に充填されるコンクリートとから構成されたものが公知になっている。
【0003】
そして、工場で予め加工しておいたメタルラスの階段型枠を階段鉄筋に設置することで、階段型枠の設置作業の短縮を図ると共に、階段型枠の網目から浸出するコンクリートを平滑化することで、階段型枠の表面仕上げにかかる作業時間の短縮を図り、工期全体の短縮を図っている。
【0004】
また、他の従来の階段構造物としては、特開平11―270090号に示すように、斜設された階段用スラブ型枠と、該階段用スラブ型枠の上面に配筋された階段鉄筋と、階段用スラブ型枠及び階段鉄筋の上に配される階段型枠と、階段用スラブ型枠及び階段型枠の間に充填されるコンクリートとから構成されたものが公知になっている。
【0005】
階段型枠は、コンクリート充填口が形成された段板と、蹴込み板とを一体化した一段分の階段構成要素が複数連結されて組み立てられる。さらに、各階段構成要素は固定金具によって、階段壁型枠にそれぞれ固定される(図示せず)。
【0006】
そして、各階段構成要素の段板のコンクリート充填口からコンクリートを充填し、各階段構成要素を固着することで、工期の短縮化を図っている。
【0007】
【発明が解決しようとする課題】
しかしながら、前者の場合、メタルラスの階段型枠の網目から浸出するコンクリートを平滑化する階段型枠の表面仕上げ工程が必要になるため、その作業時間に時間を要するという問題がある。
【0008】
また、後者の場合、現場において、複数の階段構成要素を組み立てる必要があるため、その組立て作業に時間を要するという問題がある。しかも、階段構成要素の段板のコンクリート充填口からコンクリートを充填するため、段板の上面にコンクリートが付着することになり、その仕上げ作業が付加されることになる。
【0009】
ところで、上述した従来の階段構造物は、いずれの場合も、階段用スラブ型枠と、階段鉄筋と、階段型枠とから構成されているが、特許第3196043号に示すように、鉄筋コンクリート躯体物に先行して構築される階段構造物として、階段室を構成する階段壁型枠と、複数の階段壁型枠の掛止金具が設けられた簓桁を有する階段型枠とから構成されているものが公知になっている。この場合、階段構造物は鉄筋コンクリート躯体物に先行して構築されるため、鉄筋コンクリート躯体物全体としての強度は考慮されておらず、上述した従来の階段構造物(特許第2535256号、及び、特開平11―270090号)とは、構造を異にするものである。したがって、特許第3196043号に示す階段型枠を、構造の異なる階段構造物(特許第2535256号、及び、特開平11―270090号)には、容易に適用できるものではない。
【0010】
そこで、本発明は上記問題点に鑑み、仕上げ作業や組立て作業を少なくして作業時間を確実に短縮できる階段構造物及び階段構造物の施工方法を提供することを目的とする。
【0011】
【課題を解決するための手段】
上記課題を解決するために、本発明の階段構造物は、請求項1に示す如く、斜設された階段用スラブ型枠と、該階段用スラブ型枠の上面に配筋された階段鉄筋と、階段用スラブ型枠及び階段鉄筋の上に配される階段型枠と、階段用スラブ型枠及び階段型枠の間に充填されるコンクリートとから構成される階段構造物において、階段型枠は、段板及び蹴込み板が交互に配設されて一体化され、しかも、階段型枠の段板には、複数のコンクリート充填点検穴が穿設され、さらに、各コンクリート充填点検穴は、着脱可能な蓋体、又は、モルタルによって密閉されてなるものである。
【0012】
したがって、階段鉄筋に階段型枠を設置するだけでよく、現場での階段型枠の組立てが不要になり、組立作業工程が不要になる。さらに、例えば、階段型枠の側面から階段用スラブ型枠と階段型枠との間にコンクリートを充填すれば、階段型枠の段板の上面にコンクリートが付着することもなく、段板の表面仕上げも不要になる。よって、工期の短縮化が確実に行われる。加えて、充填したコンクリートを段板のコンクリート充填点検穴から点検できるため、階段型枠を確実に固定できる。
【0013】
また、請求項2に示す如く、排水溝を階段型枠の段板の両端部にそれぞれ形成し、段板の排水溝、又は、段板の段鼻の少なくともいずれか一方への水勾配を、階段型枠の段板に形成すると共に、滑り止めを段板の段鼻に設ける。
【0014】
そうすれば、階段構造物を構築した後に、段板の滑り止めや水勾配を形成する必要もないので、より作業効率が向上されることになる。
【0015】
さらに、請求項3に示す如く、階段用スラブ型枠と階段型枠とを連結して一体化するようにしたものである。
【0016】
この場合、階段用スラブ型枠と階段型枠とを連結して一体化することで、コンクリートを充填しなくても、作業者の通行が可能になる。さらに、階段用スラブ型枠と階段型枠とを連結して一体化することで、コンクリートの充填圧によって階段型枠が押し上げられず、確実に固着される。
【0017】
また、本発明の階段構造物の施工方法は、請求項4に示す如く、階段用スラブ型枠を斜設した後、該階段用スラブ型枠の上面に階段鉄筋を配筋し、つぎに、階段用スラブ型枠及び階段鉄筋の上に階段型枠を配し、続いて、階段用スラブ型枠と階段型枠とを連結部材によって連結し、その後、階段構造物の踊り場、又は、階段型枠の側面の少なくともいずれか一方からコンクリートを充填し、階段型枠の段板に穿設された複数のコンクリート充填点検穴からコンクリートの充填度合いを確認するようにしたものである。
【0018】
よって、従来からの階段施工における、階段型枠の組立て作業、階段型枠の脱型作業、仕上げ作業が不要になり、作業時間の短縮が確実に実現される。
【0019】
【発明の実施の形態】
本発明の一実施形態につき、図1乃至図3を参照して説明する。
本発明の階段構造物は、斜設された階段用スラブ型枠1と、該階段用スラブ型枠1の上面に配筋された階段鉄筋2と、階段用スラブ型枠1及び階段鉄筋2の上に配される階段型枠10と、階段用スラブ型枠1及び階段型枠10の連結手段と、階段用スラブ型枠1及び階段型枠10の間に充填されるコンクリート35とから構成されている。
【0020】
階段鉄筋2は、階段用スラブ型枠1の傾斜面に沿って所定の間隔をおいて平行して配筋された下端筋3,…と、下端筋3,…の長手方向に沿って各下端筋3,…に固着されたいなずま筋4,…と、いなずま筋4,…各段の基端部に固着された段押さえ筋5,…と、いなずま筋4,…各段の先端部(段鼻)に固着された主筋6,…とを具備している。
【0021】
そして、階段鉄筋2には、階段鉄筋2のいなずま筋4,…や主筋6,…と、階段型枠10の内面との距離、即ちかぶり量を確保するための環状の間隔保持部材7,…が主筋6,…に沿って複数設けられている。
【0022】
階段型枠10は、左右の両側に配設された傾斜桁11,11と、両傾斜桁11,11の間に設けられた複数の水平方向の段板12,…、及び、各段板12,…の先端部(段鼻)から垂下された上下方向の蹴込み板13,…とを備えている。
そして、階段型枠10の段板12,…、及び、蹴込み板13,…の厚さは、5mm〜20mm程度で、薄型になっている。さらに、階段型枠10は、セメント系又は樹脂の材料によって成形されたものである。
【0023】
傾斜桁11,11は、その上側が、最上段の蹴込み板13の側端部から延設された上延設部11aと、該上延設部11aから下降傾斜した傾斜部11bと、最下段の段板12の側端部から延設された下延設部(図示せず)とを有している。
その下側が、各段板12,…の側端部と各蹴込み板13,…の側端部とで形成されるいなずま形状に合わせて、各段板12,…及び各蹴込み板13,…と一体化されている。
【0024】
さらに、各段板12,…及び各蹴込み板13,…の左右の両側端部には、排水溝15,…が各段板12,…と各蹴込み板13,…とで形成されるいなずま形状に合わせて形成されている。加えて、段板12の左右の両排水溝15,15に排水すべく、各段板12の中央部から両排水溝15,15にかけて緩やかに下降傾斜する水勾配16,16が形成されている。しかも、段板12の先端部には、段板12の長手方向に沿って形成された複数の凸条の滑り止め17,…が形成されている。
【0025】
また、段板12の滑り止め17,…の後方には、鉄筋と階段型枠10との間に充填されるコンクリート充填点検穴18,…が、段板12の長手方向に添って複数穿設されている。各コンクリート充填点検穴18,…は蓋体19,…とパッキン19a,…によって密閉され、浸水防止できるようになっている。さらに、蓋体19,…と段板12,…との段差は、人が階段構造物を昇降する際にも支障をきたさない程度の段差になっている。
【0026】
連結手段は、第一連結部材20と第二連結部材25とから構成されている。第一連結部材20は、各段板12,…の裏面に溶着された大連結具21,…と、階段用スラブ型枠1の上面に溶着された小連結具22,…と、両連結具21,…,22,…を連結固定するための短尺のボルト23,…及びナット30,…とを具備している。第二連結部材25は、各段板12,…と蹴込み板13,…との境界部位に穿設された貫通穴26,…と、階段型枠10と階段用スラブ型枠1との距離を確保するためのスペーサ28,…と、貫通穴26,…の外面に固着された略円錐形状のブッシング31,…と、階段用スラブ型枠1と階段型枠10とを連結する長尺のボルト29,…及びナット30,…とを具備している。
【0027】
そして、コンクリート35は、階段の踊り場、又は、階段型枠10の側面から充填される。また、階段型枠10の両側には、図示しない階段壁型枠が立設されている。
【0028】
つぎに階段構造物の施工手順について説明する。まず、階段用スラブ型枠1を斜設した後、該階段用スラブ型枠1の上面に階段鉄筋2を配筋する。この際、階段鉄筋2は、鉄筋コンクリート躯体物の鉄筋と結束線によって筋結される(図示せず)。
【0029】
つぎに、階段用スラブ型枠1及び階段鉄筋2の上に階段型枠10を配する。この際、階段鉄筋2の間隔保持部材7,…に階段型枠10の内面が当接し、階段鉄筋2と階段型枠10との距離(かぶり量)が間隔保持部材7,…によって確保される。
【0030】
続いて、階段用スラブ型枠1と階段型枠10とを位置合わせする。即ち、階段型枠10の大連結具21,…と、階段用スラブ型枠1の小連結具22,…とを当接すると共に、階段型枠10と階段用スラブ型枠1との間にスペーサ28,…を設ける。
【0031】
その後、大連結具21,…と、小連結具22,…とを短尺のボルト23,…及びナット30,…で連結固定すると共に、長尺のボルト29,…をスペーサ28,…、及び、ブッシング31,…に挿通して、階段用スラブ型枠1と階段型枠10とを長尺のボルト29,…及びナット30,…で連結固定する。
【0032】
つぎに、階段構造物の踊り場、又は、階段型枠10の側面の少なくともいずれか一方からコンクリート35を充填する。そして、階段型枠10の各段板12,…に穿設された複数のコンクリート充填点検穴18,…からコンクリート35の充填度合い、即ち、階段鉄筋2と階段型枠10との間にコンクリート35が略均一に充填されているか否かを確認する。
【0033】
確認後、階段型枠10のコンクリート充填点検穴18,…を蓋体19,…によって密閉する。そして、コンクリート35が固化するまで放置し、コンクリート35の固化後、第二連結部材25のナット30,…を緩めて長尺のボルト29,…を抜き取り、階段型枠10のブッシング31,…の挿通穴をモルタルで埋め込み(図示せず)、階段構造物が完成する。なお、第一連結部材20はコンクリート35によって埋設される。この階段構造物の完成によって、鉄筋コンクリート躯体物全体の建築強度が確保される。
【0034】
完成された階段構造物は、固着された階段型枠10の段板12,…、及び、蹴込み板13,…が露出することになり、階段型枠10の脱型作業、及び、階段型枠10の段板12,…の上面の仕上げ作業は要しない。
【0035】
なお、前記実施形態の場合、段板12の中央部から左右の排水溝15,15にかけて緩やかに下降傾斜する水勾配16,16としたが、段板12の先端部(段鼻)にも排水できるように、段板12の基端部から先端部(段鼻)側にかけて緩やかに下降傾斜する水勾配16であってもよい。要するに、水勾配16としては、段板12の左側、右側、先端部の少なくともいずれか一方に排水できればよい。
【0036】
また、前記実施形態の場合、階段用スラブ型枠1と階段型枠10とを連結した後に、コンクリート35を充填したが、階段用スラブ型枠1と階段型枠10とを連結するだけで、作業者の歩行は充分可能である。
【0037】
さらに、前記実施形態の場合、階段型枠10を階段用スラブ型枠1に連結固定するようにしたが、階段壁型枠に連結固定するようにしてもよい。
【0038】
加えて、階段型枠10の傾斜桁11,11は、必須要件ではなく、設置される場所によっては不要になる場合もある。但し、階段壁型枠が必要になる場合には、階段壁Bの仕上げ作業が必要になるため、好ましくは、傾斜桁11,11を一体化した階段型枠10を使用した方が作業性がよくなる。傾斜枠11,11としては、簓桁、側桁のいずれであってもよい。
【0039】
また、前記実施形態の場合、第一連結部材20、第二連結部材25を有する階段型枠10及び階段用スラブ型枠1を使用したが、第一連結部材20、第二連結部材25を既設の階段用スラブ型枠に設けて、階段型枠10と連結するようにしてもよい。
【0040】
さらに、前記実施形態の場合、第一連結部材20の連結具21,22は、階段型枠10に溶着するようにしたが、階段型枠10と一体に形成するようにしてもよい。
【0041】
加えて、前記実施形態の場合、階段型枠10のコンクリート充填点検穴18,…を蓋体19,…によって密閉するようにしたが、モルタルをコンクリート充填点検穴18,…に充填してコンクリート充填点検穴18,…を密閉するようにしてもよい。
【0042】
また、前記実施形態の場合、階段型枠10の両側には、階段壁Bが立設されていたが、階段型枠10の両側の少なくともいずれか一方に手摺を取り付けるようにしてもよい。この場合、手すりは、階段型枠10と一体成形であってもよいし、別途取り付けるようにしてもよい。
【0043】
【発明の効果】
以上説明したように、本発明の階段構造物によれば、段板及び蹴込み板が交互に配設されて一体化された階段型枠を使用するため、現場においての階段型枠の組立作業が不要になる。
【0044】
さらに、階段型枠の段板には、複数のコンクリート充填点検穴が穿設されているため、階段用スラブ型枠と階段型枠との間に充填されるコンクリートを略均一に充填できる効果がある。
【0045】
加えて、コンクリートの充填は、階段用スラブ型枠と階段型枠との間のみであるため、階段型枠の段板及び蹴込み板の仕上げ作業が不要になる。
【0046】
また、階段型枠の段板において、排水溝や水勾配を形成したり、段板の段鼻において、滑り止めを設けたりすることで、排水処理及び安全性の確保を実現できる。
【0047】
さらに、階段用スラブ型枠と階段型枠とを連結して一体化するようにしたので、作業者の通行路、及び、階段型枠の固着強度を確保するのに有効である。
【図面の簡単な説明】
【図1】本発明の階段構造物の完成概略斜視図である。
【図2】コンクリート充填前の階段構造物の切断正面図である。
【図3】コンクリート充填前の階段構造物の側断面図である。
【符号の説明】
1 階段用スラブ型枠
2 階段鉄筋
3 下端筋
4 いなずま筋
5 段押さえ筋
6 主筋
7 間隔保持部材
10 階段型枠
11 傾斜桁
11a 上延設部
11b 傾斜部
12 段板
13 蹴込み板
15 排水溝
16 水勾配
17 滑り止め
18 コンクリート充填点検穴
19 蓋体
19a パッキン
20 第一連結部材
21 大連結具
22 小連結具
23、30 ボルト
25 第二連結部材
26 貫通穴
28 スペーサ
29 ブッシング
30 ナット
31 ブッシング
35 コンクリート
B 階段壁[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a staircase structure in a reinforced concrete building and a construction method of the staircase structure.
[0002]
[Prior art]
As a conventional staircase structure, for example, as shown in Japanese Patent No. 2535256, an oblique staircase slab form, a staircase reinforcing bar arranged on the upper surface of the staircase slab form, and a
[0003]
And, by installing a metal lath staircase form that has been pre-processed at the factory on the staircase reinforcement, it is possible to shorten the installation work of the staircase form and smooth out the concrete leached from the mesh of the staircase formwork. Therefore, the work time required for surface finishing of the staircase formwork is shortened, and the entire construction period is shortened.
[0004]
As another conventional staircase structure, as shown in Japanese Patent Laid-Open No. 11-270090, a staircase slab mold frame provided obliquely, a staircase reinforcing bar arranged on the upper surface of the staircase slab mold frame, and It is well known that it is composed of a staircase mold disposed on the staircase slab mold and the staircase reinforcing bar, and a concrete filled between the staircase slab mold and the staircase mold.
[0005]
The staircase formwork is assembled by connecting a plurality of one-step staircase components, each of which is a stepboard formed with a concrete filling port and a kick plate. Further, each staircase component is fixed to a staircase wall form by a fixing bracket (not shown).
[0006]
And the concrete is filled from the concrete filling port of the step board of each staircase component, and the construction period is shortened by fixing each staircase component.
[0007]
[Problems to be solved by the invention]
However, in the former case, the surface finishing process of the staircase form for smoothing the concrete leached out from the mesh of the metal lath staircase form is required, so that there is a problem that it takes time for the work.
[0008]
In the latter case, since it is necessary to assemble a plurality of staircase components on site, there is a problem that the assembling work takes time. And since concrete is filled from the concrete filling port of the step board of a staircase component, concrete will adhere to the upper surface of a step board, and the finishing operation | work will be added.
[0009]
By the way, the conventional staircase structure described above is composed of a slab mold for staircases, a staircase reinforcing bar, and a staircase mold in any case, but as shown in Japanese Patent No. 3196043, a reinforced concrete frame As a staircase structure that is constructed prior to, a staircase wall formwork that forms a staircase and a staircase formwork having a girder provided with a plurality of staircase wall hanging brackets Things are known. In this case, since the staircase structure is constructed prior to the reinforced concrete frame, the strength of the reinforced concrete frame as a whole is not taken into consideration. 11-270090) has a different structure. Therefore, the staircase form shown in Japanese Patent No. 3196043 cannot be easily applied to staircase structures having different structures (Japanese Patent No. 2535256 and Japanese Patent Laid-Open No. 11-270090).
[0010]
Then, in view of the said problem, this invention aims at providing the construction method of the staircase structure and staircase structure which can reduce finishing work and an assembly work, and can shorten work time reliably.
[0011]
[Means for Solving the Problems]
In order to solve the above-described problems, a staircase structure according to the present invention includes, as shown in
[0012]
Therefore, it is only necessary to install the staircase formwork on the staircase reinforcing bars, and the assembly of the staircase formwork at the site becomes unnecessary, and the assembly work process becomes unnecessary. Furthermore, for example, if concrete is filled between the staircase slab formwork and the staircase formwork from the side of the staircase formwork, the concrete will not adhere to the upper surface of the staircase formwork board, and the surface of the stepboard form No need for finishing. Therefore, the construction period can be shortened reliably. In addition, since the filled concrete can be inspected from the concrete filling inspection hole of the corrugated board, the staircase formwork can be fixed securely.
[0013]
According to a second aspect of the present invention, drainage grooves are formed at both ends of the step plate of the staircase mold frame, respectively, and a water gradient to at least one of the drainage groove of the step plate or the step nose of the step plate is provided. It is formed on the step plate of the formwork, and a non-slip is provided on the nose of the step plate.
[0014]
Then, after constructing the staircase structure, it is not necessary to form a slip stopper or a water gradient on the step board, so that the working efficiency is further improved.
[0015]
Furthermore, as shown in
[0016]
In this case, by connecting and integrating the stair slab formwork and the staircase formwork, the operator can pass without filling the concrete. Furthermore, by connecting and integrating the stair slab formwork and the staircase formwork, the staircase formwork is not pushed up by the filling pressure of the concrete, and is securely fixed.
[0017]
Further, in the construction method of the staircase structure of the present invention, as shown in claim 4, after the slab formwork for staircase is obliquely arranged, staircase reinforcing bars are arranged on the upper surface of the slab formwork for staircase, A staircase form is placed on the staircase slab formwork and staircase reinforcing bar, and then the staircase slab formwork and the staircase formwork are connected by a connecting member, and then the landing of the staircase structure or the staircase form Concrete is filled from at least one of the side surfaces of the frame, and the concrete filling degree is confirmed from a plurality of concrete filling inspection holes formed in the step plate of the staircase mold.
[0018]
Therefore, the assembling work of the staircase formwork, the demolding work of the staircase formwork, and the finishing work in the conventional staircase construction are not required, and the working time can be surely shortened.
[0019]
DETAILED DESCRIPTION OF THE INVENTION
An embodiment of the present invention will be described with reference to FIGS.
The staircase structure of the present invention includes a staircase
[0020]
The
[0021]
Further, the
[0022]
The
And the thickness of the step board 12, ... of the
[0023]
The upper sides of the
The lower side of each step plate 12,... And each kick plate 13, according to the shape of the sparrow formed by the side end portion of each step plate 12,. It is integrated with ...
[0024]
Further, drainage grooves 15 are formed at the left and right end portions of each step plate 12,... And each kick plate 13,. It is formed to match the shape of the rod. In addition,
[0025]
Further, a plurality of concrete filling inspection holes 18 filled between the reinforcing bars and the
[0026]
The connecting means includes a first connecting
[0027]
And the concrete 35 is filled from the side of the staircase landing or the
[0028]
Next, the construction procedure of the staircase structure will be described. First, after
[0029]
Next, the
[0030]
Subsequently, the
[0031]
Then, the
[0032]
Next, the concrete 35 is filled from at least one of the landing of the staircase structure or the side surface of the
[0033]
After the confirmation, the concrete filling inspection holes 18,... Of the
[0034]
In the completed staircase structure, the step plates 12,..., And the kick plates 13,... Of the fixed
[0035]
In the case of the above embodiment, the
[0036]
Moreover, in the case of the said embodiment, after connecting the
[0037]
Furthermore, in the case of the said embodiment, although the
[0038]
In addition, the
[0039]
Moreover, in the case of the said embodiment, although the
[0040]
Furthermore, in the case of the said embodiment, although the
[0041]
In addition, in the case of the above embodiment, the concrete filling inspection holes 18,... Of the
[0042]
In the above embodiment, the staircase walls B are erected on both sides of the
[0043]
【The invention's effect】
As described above, according to the staircase structure of the present invention, since the staircase form in which the step board and the kick board are alternately arranged and integrated is used, the assembly work of the staircase formwork at the site is performed. Is no longer necessary.
[0044]
Furthermore, since the step plate of the staircase mold has a plurality of concrete filling inspection holes, the concrete filled between the staircase slab mold and the staircase mold can be filled substantially uniformly. is there.
[0045]
In addition, since the filling of the concrete is only between the slab formwork for staircase and the staircase formwork, the finishing work of the step plate and the kick plate of the staircase form becomes unnecessary.
[0046]
Also, drainage treatment and safety can be ensured by forming drainage grooves and water gradients in the stepped plate of the staircase form, and providing anti-slip in the nose of the stepboard.
[0047]
Furthermore, since the stair slab form and the stair form are connected and integrated, it is effective to secure the passage of the operator and the fixing strength of the stair form.
[Brief description of the drawings]
FIG. 1 is a completed schematic perspective view of a staircase structure according to the present invention.
FIG. 2 is a cut front view of a staircase structure before filling concrete.
FIG. 3 is a side sectional view of a staircase structure before filling concrete.
[Explanation of symbols]
DESCRIPTION OF
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003195420A JP4106688B2 (en) | 2003-07-11 | 2003-07-11 | Stair structure and construction method of stair structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003195420A JP4106688B2 (en) | 2003-07-11 | 2003-07-11 | Stair structure and construction method of stair structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005030034A true JP2005030034A (en) | 2005-02-03 |
JP4106688B2 JP4106688B2 (en) | 2008-06-25 |
Family
ID=34206238
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003195420A Expired - Fee Related JP4106688B2 (en) | 2003-07-11 | 2003-07-11 | Stair structure and construction method of stair structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4106688B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008111486A1 (en) | 2007-03-15 | 2008-09-18 | Miura Co., Ltd. | CATALYST DETERIORATION PREVENTING APPARATUS AND LOW NOx COMBUSTION APPARATUS |
WO2008120530A1 (en) | 2007-03-29 | 2008-10-09 | Miura Co., Ltd. | Low nox combustion apparatus |
CN104141367A (en) * | 2014-07-07 | 2014-11-12 | 张跃 | Concrete stairs with hoisting seats and connecting pieces |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06127748A (en) * | 1992-10-15 | 1994-05-10 | Nec Corp | Gap correcting mechanism for paper processing device |
-
2003
- 2003-07-11 JP JP2003195420A patent/JP4106688B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008111486A1 (en) | 2007-03-15 | 2008-09-18 | Miura Co., Ltd. | CATALYST DETERIORATION PREVENTING APPARATUS AND LOW NOx COMBUSTION APPARATUS |
WO2008120530A1 (en) | 2007-03-29 | 2008-10-09 | Miura Co., Ltd. | Low nox combustion apparatus |
CN104141367A (en) * | 2014-07-07 | 2014-11-12 | 张跃 | Concrete stairs with hoisting seats and connecting pieces |
Also Published As
Publication number | Publication date |
---|---|
JP4106688B2 (en) | 2008-06-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10500760B2 (en) | Method and apparatus for production of precision precast concrete flights of stairs | |
US7976746B2 (en) | Method installing a modular concrete stair system | |
KR100695275B1 (en) | Step construction and method for building step | |
JP4106688B2 (en) | Stair structure and construction method of stair structure | |
KR101522022B1 (en) | Mold for kick plate with anchor bolt for handrail and stairway construction method using the same | |
KR0141463B1 (en) | Method of prefabricating stairway | |
KR20070009061A (en) | Simultaneous working type installation method for stair hall equipped prefabricated stair using pc form | |
KR19990051530A (en) | Precast Concrete Stair System and Stair Construction Method Using It | |
US3341639A (en) | Method for grouting girders supporting concrete slabs | |
JPH08312090A (en) | Construction method of concrete stair with stepped form left, and stepped form | |
KR200196692Y1 (en) | A stairway mould | |
JPH11270090A (en) | Concrete staircase constitution method and staircase constitution element | |
KR100550458B1 (en) | Precast concrete stairway structure of edifice and construction method thereof | |
CN112609867A (en) | Prefabricated shear wall cavity with three-dimensional efficient connection structure and connection node configuration | |
KR100487893B1 (en) | System and method of precasted concrete staircase | |
JP2004204508A (en) | Construction method of staircase, and form for staircase | |
KR100459613B1 (en) | Continuous construction of core wall for precasted concrete staircase | |
KR100464594B1 (en) | The method of constructing the prefabricated step on reinforced concrete building | |
KR100930281B1 (en) | Attachment bracket of steel stairway and attachment device and attachment method of steel stairway | |
CN214995394U (en) | Prefabricated staircase convenient to handling and installation | |
JPH01190866A (en) | Stair made of concrete and building method thereof | |
KR200270297Y1 (en) | A stairway mould | |
JP4061611B2 (en) | PCa stairs mounting structure, PCa stairs mounting method, PCa stairs | |
KR101962709B1 (en) | Composite deck slab construction method with trench | |
JP2846426B2 (en) | How to build concrete stairs |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060310 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20071023 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071025 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071219 |
|
RD12 | Notification of acceptance of power of sub attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7432 Effective date: 20080104 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20080107 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080305 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080321 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110411 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120411 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140411 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |