JP2004346664A - Dividable caisson, and method of constructing large cross-sectional tunnel using the dividable caisson - Google Patents
Dividable caisson, and method of constructing large cross-sectional tunnel using the dividable caisson Download PDFInfo
- Publication number
- JP2004346664A JP2004346664A JP2003146830A JP2003146830A JP2004346664A JP 2004346664 A JP2004346664 A JP 2004346664A JP 2003146830 A JP2003146830 A JP 2003146830A JP 2003146830 A JP2003146830 A JP 2003146830A JP 2004346664 A JP2004346664 A JP 2004346664A
- Authority
- JP
- Japan
- Prior art keywords
- box
- divided
- floor slab
- split
- constructing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、小断面の分割函体を利用しながら大断面トンネルを構築する際に使用する分割函体及びかかる分割函体を使用した大断面トンネルの施工方法に関するものである。
【0002】
【従来の技術】
地下にトンネルを構築する場合、トンネル軸に沿ってトンネルの両側に山留壁を構築し、その内部を掘削してトンネル函体を構築した後に埋戻しをおこない、山留壁を撤去する開削工法がおこなわれている。
一方、道路や鉄道などの下に地下立体交差トンネルを構築する場合は、上記する開削工法による地上交通への障害を回避するために、シールド工法や推進工法による施工が一般的である。
ところで、近年の交通量の増加や地下トンネルの適用の多様化などから、地下トンネルが大断面化してきている。かかる大断面トンネルを構築する場合、シールド工法にて複数の小断面トンネルを構築して連結させて大断面トンネルを構築している。また、開削工法では、地盤改良等の補助工法を併用し、広範な作業帯を占有しながら施工をおこなっている。
発明者等においては、図12に示すように、大断面トンネルの構築に際し、複数の小断面トンネルを相互に隣接させるように推進工法にて設置する方法を考案し、開示している(特許文献1参照)。ここで、推進管aの推進は、一方の側壁に刻設した溝bに他方の側壁に設けた突条cを嵌装させながら設置していく。
【0003】
また、開削工法とシールド工法の利点を兼ね備えた工法としてオープンシールド工法が使用されている。オープンシールド工法とは、前方および上方を開放したシールド掘進機を使用し、切羽掘削チャンバー内の地山をバックホウで掘削排土し、油圧ジャッキにより敷設函体を反力にシールド掘進機を推進し、函体を敷設し、テールボイドの注入をおこない、函体上部を埋戻していく工法である。なお、特許文献2にオープンシールド機およびかかるオープンシールド機を使用したオープンシールド工法について開示している。
【0004】
【特許文献1】
特開2001−214699号公報
【特許文献2】
特開2002−70481号公報
【0005】
【発明が解決しようとする課題】
前記した従来の大断面トンネルの施工方法にあっては、次のような問題点がある。
<イ>開削工法では大型機械の必要性などから広範な作業帯を占有するため、地上の交通渋滞の要因となり得る。
<ロ>開削工法においては、施工場所に近接した周辺施設への影響が大きいため、地盤改良等の補助工法の併用が不可避となる。
<ハ>大断面を小断面に分割した分割体を結合して大断面トンネルを構築する場合であっても、分割函体が大きくなると、分割函体の施工場所への運搬車輌及び分割函体の設置用重機の規模が大型化し得る。
<ニ>シールド工法では大断面に対応した掘削が困難となる。また、大断面を小断面に分割した分割体を結合して大断面トンネルを構築する場合であっても、土被りが少ない場合にはシールド工法の使用は困難となる。
【0006】
【発明の目的】
本発明は上記したような従来の問題を解決するためになされたもので、大断面トンネルの施工時に地上に広範な作業帯を占有する必要のない分割函体及び分割函体を使用した大断面トンネルの施工方法を提供することを目的とする。また、施工場所に近接した周辺施設への影響が少ない分割函体及び分割函体を使用した大断面トンネルの施工方法を提供することを目的とする。また、分割函体の規模を小型化し得る分割函体及び分割函体を使用した大断面トンネルの施工方法を提供することを目的とする。さらに、土被りが少ない条件下での大断面トンネルの施工を可能とする分割函体及び分割函体を使用した大断面トンネルの施工方法を提供することを目的とする。
本発明は、これらの目的の少なくとも一つを達成するものである。
【0007】
【課題を解決するための手段】
上記のような目的を達成するために、本発明の大断面トンネルの施工方法に使用する分割函体は、大断面トンネルを分割施工する際に使用する、上床版、下床版、右側壁、左側壁からなる四角柱の筒状の分割函体であって、前記分割函体の筒体軸に垂直に切断した断面において、前記上床版の上面が台形の長手底辺となる台形柱体が前記上床版の一部を構成する上床版台形柱体と、前記分割函体の筒体軸に垂直に切断した断面において、前記下床版の下面が台形の長手底辺となる台形柱体が前記下床版の一部を構成する下床版台形柱体と、前記上床版台形柱体及び前記下床版台形柱体を除いた前記分割函体を構成する分割函体左側柱体及び分割函体右側柱体と、からなることを特徴とする分割函体である。
【0008】
また、本発明の大断面トンネルの施工方法に使用する分割函体は、前記する分割函体において、前記上床版と前記下床版の間に、前記上床版及び前記下床版と略並行に中床版を設け、前記分割函体の筒体軸に垂直に切断した断面において、前記中床版の上面が台形の長手底辺となる台形柱体が前記上床版の一部を構成する中床版台形柱体を備えたことを特徴とする分割函体を使用できる。
【0009】
また、前記する分割函体において、前記中床版を複数備えたことを特徴とする分割函体を使用できる。
【0010】
さらに、本発明の分割函体を使用した大断面トンネルの施工方法は、前記する分割函体を使用した大断面トンネルの施工方法であって、地盤に断面視矩形の掘削溝を造成しながら、前記下床版台形柱体を設置し、前記分割函体左側柱体及び前記分割函体右側柱体を設置し、前記上床版台形柱体を設置することによって前記分割函体を構築し、掘削溝に複数の前記分割函体を鉛直方向に積み上げ設置して分割函体群を構成し、前記掘削溝に分割函体群を隣接設置していく分割函体設置工程と、前記分割函体群の上部を埋戻す埋戻し工程と、によって分割函体群列を構築し、間隔を置いて略並行に構築した複数の前記分割函体群列の間を掘削し、前記分割函体郡列を山留め支保部材として利用しながら本設大断面トンネルを構築することを特徴とする分割函体を使用した大断面トンネルの施工方法である。
【0011】
また、本発明の分割函体を使用した大断面トンネルの施工方法は、前記する分割函体を使用した大断面トンネルの施工方法であって、地盤に断面視矩形の掘削溝を造成しながら、前記下床版台形柱体を設置し、前記分割函体左側柱体及び前記分割函体右側柱体を設置し、前記中床版台形柱体を設置し、前記上床版台形柱体を設置することによって前記分割函体を構築し、掘削溝に前記分割函体を隣接設置していく分割函体設置工程と、前記分割函体の上部を埋戻す埋戻し工程と、によって分割函体列を構築し、間隔を置いて略並行に構築した複数の前記分割函体列の間を掘削し、前記分割函体列を山留め支保部材として利用しながら本設大断面トンネルを構築することを特徴とする分割函体を使用した大断面トンネルの施工方法を使用できる。
【0012】
また、本発明の分割函体を使用した大断面トンネルの施工方法は、前記する分割函体を使用した大断面トンネルの施工方法において、前面に掘削カッタを備えた密閉型の下段部と少なくとも前面を開放した開放型の上段部とからなり、前記上段部はスライド式の庇部とスライド式の側壁部とを備えたシールド掘進機を使用して前記掘削溝を造成することを特徴とする分割函体を使用した大断面トンネルの施工方法を使用できる。
【0013】
さらに、本発明の分割函体を使用した大断面トンネルの施工方法は、異形断面を掘進可能な異形断面シールド掘進機を使用して矩形シールド函体を設置していく函体設置工程と、前記矩形シールド函体の上床版に沿って地盤に掘削溝を造成しながら、前記矩形シールド函体上に前記分割函体を隣接設置していく分割函体設置工程と、前記分割函体の上部を埋戻す埋戻し工程と、によって矩形シールド函体及び分割函体からなる函体列を構築し、間隔を置いて略並行に構築した複数の前記函体列の間を掘削し、前記函体列を山留め支保部材として利用しながら本設大断面トンネルを構築することを特徴とする分割函体を使用した大断面トンネルの施工方法を使用できる。
【0014】
【発明の実施の形態1】
以下、図面を参照しながら本発明の実施の形態1について説明する。
【0015】
<イ>分割函体(図1)
本発明の大断面トンネルの施工方法において使用する分割函体1は、上床版15、下床版16、右側壁17、左側壁18からなる筒状の四角柱を4分割した函体ピースから構成される。4分割した函体ピースの一つ目は、分割函体1を筒体軸に垂直に切断した断面において、上床版15の上面が台形の長手底辺となるような台形の柱体が上床版15の一部を構成する上床版台形柱体10である。4分割した函体ピースの二つ目は、分割函体1を筒体軸に垂直に切断した断面において、下床版16の下面が台形の長手底辺となるような台形の柱体が下床版16の一部を構成する下床版台形柱体11である。4分割した函体ピースのその他は、上記する上床版台形柱体10及び下床版台形柱体11を除いた分割函体1を構成する、右側壁17と上床版15及び下床版16の一部より構成される分割函体右側柱体12と、左側壁18と上床版15及び下床版16の一部より構成される分割函体左側柱体13である。
【0016】
下床版台形柱体11を上記のような断面視形状(ハの字状)に成形するのは、分割函体1の組立て時に下床版台形柱体10の両端部のテーパー面に沿って分割函体右側柱体12及び分割函体左側柱体13を設置し易くするためである。
また、上床版台形柱体10を上記のような断面視形状(逆ハの字状)に成形するのは、分割函体1の最終組立て時に上床版台形柱体10を分割函体右側柱体12及び分割函体左側柱体13の端部のテーパー面に嵌合させるためである。
【0017】
下床版台形柱体11、上床版台形柱体10、分割函体右側柱体12、分割函体左側柱体13の組立て時には、各柱体をボルトなどにて仮止めしておくのがよい。かかる分割函体1は仮設部材であることから、施工中に分割体同士が相互にずれたりしても何ら問題はない。もっとも、分割函体1を本設部材の一部として使用することもできるが、かかる場合には例えばボルトなどにて確実に連結させる必要がある。
【0018】
分割函体1は、鋼製函体、コンクリート函体として製作することができる。
【0019】
大断面トンネルの構築時に使用する分割函体1を本発明のようにさらに複数の分割ピースに分割することによって、地上61からのクレーン等による分割ピース吊り下ろし時の分割体重量の軽減を図ることができるため、地上61にて旋回する重機の規模を小さくすることが可能となる。分割体重量の軽減は、さらに分割体運搬車輌の小型化にもつながる。
【0020】
また、地上61から地下トンネルへと通ずるアプローチ部は、分割函体1を構成する側壁8(右側壁17及び左側壁18の高さを調整して側壁途中で上部を切断して構成した側壁)上に覆工板9を設置することによって施工できる(図11参照)。覆工板9はゴム板等の緩衝具93を介して側壁8上に設置し、ボルト91やずれ止めアングル92などによって側壁8に係止するのがよい。
【0021】
<ロ>シールド掘進機(図3、図4)
シールド掘進機5は上段部51と下段部52から構成される。上段部51は少なくとも前面が開放された開放型掘進機である。また、下段部52は前面に掘削カッタ521を備えた密閉型掘進機である。上段部51は下段部52よりも掘進方向に突出させておくのが好ましい。このように上段部51を突出させることで、下段部52の前面を密閉状態にでき、下段部52を土圧式シールド機とした場合の排土を円滑に行うことができる。
シールド掘進機5の後方には、分割函体1と外殻の間からの地下水や土砂の侵入を阻止するための公知のテールシール53を配置する。また、掘進用のシールドジャッキ54を必要箇所に配置する。
また、シールド掘進機5は、曲線区間を施工する場合には、外殻をトンネル軸方向で分割し、中折れジャッキ55を配置するなどして公知の中折れ構造とすることが好ましい。
【0022】
下段部52は、シールド掘進機5の下部を構成する部分であり、掘削カッタ521で掘削しながら掘進を行う部分である。下段部52の断面視は、例えば矩形や正方形などの四角形や、上段部51との境界で截頭した円形に形成することができる。
前面に配置する掘削カッタ521には、公知の密閉型のシールド掘進機用の掘削カッタが使用できる。また、図4に示すように、掘進軸方向の掘進軸回りに揺動する揺動カッタ521を複数配備して使用することもできる。かかる複数の揺動カッタ521は夫々の揺動カッタ521の掘削範囲を重複させないように制御することができる。例えば2基の揺動カッタ521を同一平面内又は双方が前後するように配置して、夫々の揺動カッタ521を自己の持分範囲のみを掘削させる。矩形断面を掘進する場合には、矩形断面を例えば均等に2分割して、2基の揺動カッタ521が各分割範囲内を揺動しながら地盤を切削することができる。この場合に、揺動カッタ521の揺動は揺動軸を中心に双方が相反する方向に揺動するように制御することができる。かかる制御によって、2基の揺動カッタ521は相互に干渉することなく、またシールド掘進機5の進行方向を一定方向に確保しながら掘進させることが可能となる。
【0023】
下段部52を土圧式にした場合は、排土のためのスクリューコンベア522を配置する。また、スクリューコンベア522の後方には、例えば掘削土砂をトンネル内で搬送するためのベルトコンベア523を配置して、下段部52の掘削土砂を下段部52で搬出させることができる。
【0024】
上段部51は、シールド掘進機5の上部を構成する部分である。上段部51の断面視は、矩形や正方形などの四角形に形成することができる。上段部51は、天井及び側壁と、必要に応じて下段部52との境界に配置する底板で構成する。
上段部51の側壁の掘進方向の最前部は、スライド式の側壁部512とする。側壁部512は、スライド用ジャッキ514などで掘進方向に向けて伸びたり、縮んだりすることができる。側壁部512は一体となって伸縮するようにも構成できるが、複数段に分けて、それぞれ別個に稼動できるように構成するのが好ましい。図3、4に示した側壁部512は、3段に分割した側壁部512の実施例である。
また、上段部51の天井の掘進方向の最前部は、スライド式の庇部511とする。庇部511も側壁部512と同様に、スライド用ジャッキ514などで伸縮が可能である。ただし、庇部511と側壁部512は、独立して別個に稼動するように構成する。庇部511も側壁部512と同様に複数に分割して構成することができる。図4のように組み合わせると、庇部511の両端は側壁部512の役割も果たすことになる。庇部511や側壁部512の先端は、地盤に押し込み易いように刃型に形成するのが好ましい。
【0025】
地上61から上段部51を掘削する場合は、庇部511を縮めて地上61に設置した大型のバックホウ7などを使用して掘削をおこなう。また、庇部511を伸ばして上段部51の内側から掘削を行う場合は、油圧ショベルや回転カッタなどの公知の開放型シールド機で使用する掘削機を使用したり、小型のバックホウなどの掘削機械を上段部51に設置したりして掘削をおこなう。
また、上段部51の天井には、開閉式の開口部513を設けるのが好ましい。開口部513は、地上61から掘削を行うときには開放し、シールド掘進機5の天井が地中に埋もれる場合には閉塞させる。開口部513の開閉は機械式に限定されるものではなく、必要に応じて鋼板などで穴を塞ぐという構成であってもよい。開口部513は、分割函体1や資材の搬入、掘削土砂の排出などに使用することができる。
上段部51の排土は、地上から掘削を行う場合は地上に排出することができるが、内側から掘削を行う場合は、ベルトコンベア516などを配置して掘削土砂の搬送を行う。また、上段部51の姿勢を制御するために公知の可動ソリ515などを上段部51の側面に配置することもできる。
【0026】
上段部51を地上61から掘削する場合は、地上61と上段部51の上端の間を山留めするための切削山留め体56を配置するのが好ましい。切削山留め体56はシールド掘進機5の上段部51の天井に着脱可能な構造で取り付ける。
ここで、切削山留め体56とは、例えば2つの山留め板561をシールド掘進機5の幅程度の間隔を置いてほぼ並行に直立させて配置し、かかる間隔に複数の間隔保持部材562を夫々の山留め板561に垂直に連結させて製作したものである。山留め板561としては例えば鋼製板など山留め部材としての剛性を有する材料を使用するのが好ましい。また、間隔保持部材562としては、例えばH型鋼材を使用できる。
切削山留め体56を使用する目的は、シールド掘進機5の掘進に応じて山留め板561を地盤内に推進させ、かかる山留め板561で土留めをしながら、山留め板561内を地上からバックホウ7等で掘削するためである。
【0027】
なお、本発明の施工方法において使用するシールド掘進機5は上記するシールド掘進機5に拘泥するものではない。すなわち、縦長の開放型掘進機(その下方に密閉型シールド掘進機を備えていない掘進機)を使用して掘削溝2を施工しながら分割函体1を設置することもできる。また、掘削溝2の下方を密閉型シールド掘進機にて先行施工して分割体を設置した後に、その上方を開放型掘進機にて掘削するとともに分割函体1を設置することもできる。
【0028】
以下、図面を参照しながら本発明の分割函体を使用した大断面トンネルの施工方法1について説明する。
【0029】
<イ>分割函体設置工程
シールド掘進機5を使用して、地盤に断面視矩形の掘削溝2を造成する。掘削溝2を造成しながら分割函体1(を構成する部材)を地上からクレーン等で吊り下ろして掘削溝2内に設置する。かかる分割函体1の構成部材の設置状況を図5に示す。
まず、下床版台形柱体11を掘削溝2内に設置した後、分割函体右側柱体12及び分割函体左側柱体13を下床版台形柱体11の端部のテーパー面に係合設置し、その後、上床版台形柱体10を設置して分割函体1を構築する(図6(a)、(b)、図7(a)参照)。
構築した分割函体1上に上記と同様の手順で分割函体1を構築して分割函体群110を構築する(図7(b)参照)。
【0030】
<ロ>埋戻し工程及び分割函体群列の構築
分割函体群110を構築しながら、かかる分割函体群110の上部の埋戻し62をおこなう。すなわち、埋戻し工程は、上記の分割函体設置工程と並行しながら進めていくのが好ましい。分割函体群110を隣接設置していくことによってトンネル延長方向に伸びた1列の分割函体群列120が構築される(図5参照)。
本発明においては、上記の分割函体群列120を間隔3をおいてほぼ並行に複数構築するため(図8(a)参照)、かかる複数の分割函体群列120の構築は、工期や工費を勘案して1列ごとにおこなうこともできるし、シールド掘進機5を複数使用して各列を同時に構築することもできる。
埋戻し工程完了後は舗装を施工することで、地上道路として供用することができる。
【0031】
<ハ>分割函体群列の間の掘削
分割函体群列120、120の間の間隔3の掘削において、分割函体群110の土被り部分については、例えば、地上から所定の法面を形成しながら開削施工をおこない、分割函体群110、110の間の掘削は分割函体群110を山留め支保部材として利用しながら掘り下げていくことができる(図8(b)参照)。
【0032】
<ニ>本設大断面トンネルの構築
分割函体群列120、120の間の掘削完了後、または分割函体郡列120、120の間の掘削と並行して本設大断面トンネル4の構築をおこなう。分割函体郡列120を構成する各構成部材を外型枠とし、分割函体郡列120の構成部材を撤去しながら本設大断面トンネル4を構成する構成部材(上床版、側壁、柱脚、底版など)を構築する。また、分割函体郡列120を本設大断面トンネル4の構成部材の一部として使用する場合には、分割函体郡列120を構成する構成部材を巻き込んで本設大断面トンネル4の構成部材を構築するとともに、不要な分割函体郡列120構成部材は撤去しながら本設大断面トンネルを完成させる(図9参照)。
【0033】
以下、本発明の分割函体を使用した大断面トンネルの施工方法2について説明する。なお、上記する施工方法1と重複する工程については省略する。
【0034】
<イ>函体設置工程
異形断面シールド掘進機(シールド掘進機5の下段部52に相当する)を使用して矩形のシールド函体を設置して矩形シールド函体列を構築する。かかる函体列は間隔3を置いて複数設置できる(図示せず)。
<ロ>分割函体設置工程
矩形シールド函体の上床版に沿って地盤に掘削溝2を造成しながら、矩形シールド函体上に分割函体1を設置していく。ここで、掘削溝2の造成は、シールド掘進機5の上段部51に相当する開放型掘進機を使用するのが好ましい。分割函体1の設置方法は上記する施工方法1と同様である。なお、分割函体1は矩形シールド函体の上床版上に1段設置することもできるし、2段以上設置することもできる(図示せず)。
<ハ>埋戻し工程及び本設大断面トンネルの構築
最上段の分割函体1上部を埋戻して矩形断面シールド函体及び分割函体1からなる函体列を構築する。かかる函体列は間隔3を置いて複数設置する(図示せず)。
その後の間隔3の掘削及び本設大断面トンネルの構築は施工方法1と同様である。
【0035】
【発明の実施の形態2】
以下、図面を参照しながら本発明の実施の形態2について説明する。
【0036】
分割函体1を構成する上床版15と下床版16の間に、上床版15及び下床版16と並行(またはほぼ並行)に中床版19を備えた分割函体1を使用する(図2(a)参照)。ここで、分割函体1を筒体軸に垂直に切断した断面において、中床版19の上面が台形の長手底辺となるような台形の柱体を中床版19から分割して構成される中床版台形柱体14を備えた中床版19とする。すなわち、本実施形態における分割函体1は、上床版台形柱体10、下床版台形柱体11、分割函体右側柱体12、分割函体左側柱体13、及び中床版台形柱体14から構成された分割函体1である。
なお、中床版19(及び中床版台形柱体14)を上床版15と下床版16の間に複数設けることもできる。図2(b)には、中床版19を2箇所設けた場合の分割函体1を示している。
【0037】
中床版19を備えた分割函体1を使用することによって、中床版19のない分割函体1(実施形態1の分割函体1)を使用する場合に要していた複数の分割函体1を鉛直方向に積み上げ設置していく工程を省略することができるため、作業効率の向上を図ることができる。
【0038】
以下、図面を参照しながら中床版19を備えた分割函体1を使用した大断面トンネルの施工方法について説明する。なお、実施の形態1における施工方法と重複する工程については省略する。
【0039】
分割函体設置工程として、掘削溝2内に中床版を備えた分割函体1を設置する(図10(a)参照)。すなわち、下床版台形柱体11を掘削溝2内に設置した後、分割函体右側柱体12及び分割函体左側柱体13を下床版台形柱体11の端部のテーパー面に係合設置し、その後、中床版台形柱体14を設置し、上床版台形柱体10を設置して分割函体1を構築する。
上記する分割函体1を掘削溝2内で隣接設置するとともに分割函体1の上部を埋戻して分割函体列130を構築し(埋戻し工程)、略並行に複数設けた分割函体列130の間の間隔3を掘削(図10(b)参照)及び本設大断面トンネル4の構築は実施の形態1における施工方法と同様である。
【0040】
【発明の効果】
本発明の大断面トンネルの施工方法は以上説明したようになるから次のような効果を得ることができる。
<イ>広範な作業帯を占有しないため、地上の交通障害を少なくして工事をおこなうことができる。
<ロ>切削山留め体を備えた開放型シールド機及び密閉型シールド掘進機からなるシールド掘進機を使用して地上に掘削溝を造成するため、掘削の影響が周辺におよび難い。
<ハ>分割函体をさらに複数の分割ピースに分割するため、函体を吊り下ろす重機及び運搬車輌の小型化を図ることができる。
<ニ>仮設用の函体や本設の分割函体が土留め壁および土留め支保部材としての役割を担うため、土留め壁の施工や切梁設置などの必要がなく、全体工程を短縮できる。
【図面の簡単な説明】
【図1】(a)本発明の分割函体を示した斜視図。(b)分割函体を上床版台形柱体と下床版台形柱体と分割函体左側柱体と分割函体右側柱体に分割した場合の斜視図。
【図2】中床版を備えた分割函体を示した斜視図であり、(a)中床版を1段備えた分割函体を示した斜視図。(b)中床版を2段備えた分割函体を示した斜視図。
【図3】本発明の施工方法に使用するシールド掘進機の縦断図。
【図4】本発明の施工方法に使用するシールド掘進機の正面図。
【図5】本発明の施工方法においてシールド掘進機で掘進しながら分割函体を吊り下ろしている状況を説明した説明図。
【図6】本発明の施工方法を説明した説明図であり、(a)下床版台形柱体を設置したことを説明した説明図。(b)下床版台形柱体設置後に分割函体左側柱体を設置し、分割函体右側柱体を設置している状況を説明した説明図。
【図7】本発明の施工方法を説明した説明図であり、(a)下床版台形柱体、分割函体左側柱体、分割函体右側柱体設置後に上床版台形柱体を設置している状況を説明した説明図。(b)2段目分割函体のうち、上床版台形柱体を設置している状況を説明した説明図。
【図8】本発明の施工方法を説明した説明図であり、(a)間隔を置いて2列の分割函体群列の構築が完成した状況を説明した説明図。(b)間隔を掘削している状況を説明した説明図。
【図9】本設大断面トンネルの構築が完成した状況を説明した説明図。
【図10】中床版を備えた分割函体を使用した本発明の施工方法を説明した説明図であり、(a)中床版台形柱体を設置している状況を説明した説明図。(b)間隔を掘削している状況を説明した説明図。
【図11】アプローチ部の分割函体を設置した状況を説明した説明図。
【図12】従来の大断面トンネルの施工方法を説明した説明図。
【符号の説明】
1・・・分割函体
10・・上床版台形柱体
11・・下床版台形柱体
12・・分割函体右側柱体
13・・分割函体左側柱体
14・・中床版台形柱体
15・・上床版
16・・下床版
17・・右側壁
18・・左側壁
19・・中床版
110・分割函体群
120・分割函体群列
130・分割函体列
2・・・掘削溝
3・・・間隔
4・・・本設大断面トンネル
5・・・シールド掘進機
51・・上段部
52・・下段部
511・庇部
512・側壁部
521・掘削カッタ[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a divided box used when constructing a large-section tunnel using a small-section divided box, and a method of constructing a large-section tunnel using such a divided box.
[0002]
[Prior art]
When constructing a tunnel underground, open-cutting method is to construct a retaining wall on both sides of the tunnel along the tunnel axis, excavate the inside of the tunnel, construct a tunnel body, and then bury the tunnel and remove the retaining wall. Is being performed.
On the other hand, when constructing an underground flyover tunnel under a road, a railway, or the like, construction using a shield method or a propulsion method is generally performed in order to avoid obstacles to ground traffic due to the above-mentioned excavation method.
By the way, underground tunnels have been increasing in cross section due to an increase in traffic volume and diversification of applications of underground tunnels in recent years. When such a large-section tunnel is constructed, a plurality of small-section tunnels are constructed and connected by a shield method to construct a large-section tunnel. In the excavation method, an auxiliary method such as ground improvement is used in combination, and construction is performed while occupying a wide work zone.
As shown in FIG. 12, the present inventors have devised and disclosed a method of installing a plurality of small-section tunnels by a propulsion method so as to make them adjacent to each other when constructing a large-section tunnel. 1). Here, the propulsion of the propulsion pipe a is performed while fitting the protrusions c provided on the other side wall into the grooves b engraved on one side wall.
[0003]
Also, an open shield method is used as a method combining the advantages of the open-cut method and the shield method. With the open shield method, a shield excavator whose front and upper sides are opened is used to excavate and excavate the ground in the face excavation chamber with a backhoe, and a hydraulic jack is used to propel the shield excavator in reaction to the laying box. In this method, a box is laid, tail voids are injected, and the upper part of the box is buried.
[0004]
[Patent Document 1]
JP 2001-214699A [Patent Document 2]
JP-A-2002-70481 [0005]
[Problems to be solved by the invention]
The above-described conventional method for constructing a large-section tunnel has the following problems.
<B> The open-cutting method occupies a wide range of work zones due to the necessity of large machines and the like, which may cause ground traffic congestion.
<B> In the open-cutting method, the peripheral facilities near the construction site are greatly affected, so it is inevitable to use auxiliary methods such as ground improvement.
<C> Even if a large cross section is divided into small cross sections and a large cross section tunnel is constructed, if the split box becomes large, the transport vehicle and the split box to the construction site of the split box The size of the heavy equipment for installation can be increased.
<D> With the shield method, it is difficult to excavate large sections. In addition, even when a large-section tunnel is constructed by combining divided bodies obtained by dividing a large section into small sections, it is difficult to use the shield method when there is little earth covering.
[0006]
[Object of the invention]
The present invention has been made in order to solve the above-described conventional problems, and has a divided box that does not need to occupy a wide working zone on the ground when constructing a large-section tunnel, and a large section using the divided box. The purpose is to provide a construction method of a tunnel. It is another object of the present invention to provide a divided box and a method for constructing a large-section tunnel using the divided box, which has little effect on peripheral facilities close to the construction site. It is another object of the present invention to provide a split box capable of reducing the size of the split box and a method for constructing a large-section tunnel using the split box. It is still another object of the present invention to provide a divided box capable of constructing a large-section tunnel under conditions of low earth covering and a method of constructing a large-section tunnel using the divided box.
The present invention achieves at least one of these objects.
[0007]
[Means for Solving the Problems]
In order to achieve the above object, the split box used in the method for constructing a large-section tunnel of the present invention is used when dividing and constructing a large-section tunnel, an upper deck, a lower deck, a right wall, A quadrangular prism cylindrical split box composed of a left side wall, and in a cross section cut perpendicularly to a cylindrical axis of the split box, the trapezoidal column in which the upper surface of the upper floor slab is a trapezoidal long base. The upper floor slab trapezoidal column constituting a part of the upper floor slab, and in a cross section cut perpendicular to the cylinder axis of the divided box, the trapezoidal column in which the lower surface of the lower floor slab is the longitudinal base of the trapezoid is the lower part. A lower slab trapezoidal column constituting a part of the slab, and a divided box left column and a divided box constituting the divided box excluding the upper slab trapezoidal column and the lower slab trapezoidal column And a right-hand column.
[0008]
Further, the split box used in the method for constructing a large-section tunnel of the present invention, in the split box, between the upper slab and the lower slab, substantially parallel to the upper slab and the lower slab. A middle floor where a middle floor slab is provided and a trapezoidal column in which a top surface of the middle floor slab is a long base of a trapezoid in a cross section cut perpendicular to the cylinder axis of the divided box constitutes a part of the upper floor slab. A divided box having a trapezoidal column can be used.
[0009]
In the above-mentioned divided box, a divided box provided with a plurality of the middle floor slabs can be used.
[0010]
Furthermore, the method of constructing a large-section tunnel using the divided box of the present invention is a method of constructing a large-section tunnel using the divided box described above, while forming an excavation groove having a rectangular cross section in the ground. The lower floor slab trapezoidal column is installed, the split box left side column and the split box right side column are installed, and the upper floor slab trapezoidal column is installed to construct the split box and excavate. A plurality of the divided boxes are vertically stacked in the trench to form a divided box group, and the divided box group is installed adjacent to the excavation groove, and the divided box group is provided. A backfilling step of backfilling the upper part of the frame, constructing a divided box group sequence, excavating between the plurality of divided box group lines constructed substantially in parallel at intervals, the divided box group sequence The main feature is to construct a permanent large section tunnel while using it as a retaining member A large sectional tunnel construction method using the split box making body that.
[0011]
The method of constructing a large-section tunnel using the divided box of the present invention is a method of constructing a large-section tunnel using the divided box described above, while forming a rectangular excavation groove having a rectangular cross section in the ground. The lower floor slab trapezoidal column is installed, the split box left side column and the split box right side column are installed, the middle floor slab trapezoidal column is installed, and the upper floor slab trapezoidal column is installed. By constructing the divided box, a divided box installation step of installing the divided box adjacent to the excavation groove, and a back-filling step of backfilling the upper part of the divided box, the divided box row by Constructing, excavating between the plurality of divided box rows constructed substantially in parallel at intervals, and constructing a permanent large section tunnel while using the divided box rows as mountain retaining support members. Construction method of large section tunnel using split box can be used
[0012]
In addition, the method for constructing a large-section tunnel using the divided box of the present invention is the method for constructing a large-section tunnel using the divided box described above, wherein the closed lower portion having an excavation cutter on the front and at least the front. And an open type upper step portion having an open end, wherein the upper step portion is formed by using a shield excavator having a slide type eaves portion and a slide type side wall portion to form the excavation groove. The construction method of a large section tunnel using a box can be used.
[0013]
Further, the construction method of the large section tunnel using the split box of the present invention, a box installation step of installing a rectangular shield box using a deformed section shield excavator capable of excavating a deformed section, While forming an excavation groove in the ground along the upper floor slab of the rectangular shield box, a split box installation step of installing the split box adjacently on the rectangular shield box, and the upper part of the split box A backfilling step, backfilling, by constructing a box row consisting of a rectangular shield box and a divided box, excavating between a plurality of said box rows constructed in parallel at intervals, said box row The method for constructing a large-section tunnel using a split box, which is characterized in that a permanent large-section tunnel is constructed while using the ridge as a retaining member, can be used.
[0014]
Hereinafter,
[0015]
<B> Split box (Fig. 1)
The divided
[0016]
The lower floor slab
The upper floor slab
[0017]
When assembling the lower floor slab
[0018]
The divided
[0019]
By dividing the divided
[0020]
In addition, the approach part that leads from the
[0021]
<B> Shield excavator (Figs. 3 and 4)
The
A well-known
When constructing a curved section, the
[0022]
The
As the
[0023]
When the
[0024]
The
The foremost part of the side wall of the
The foremost part of the ceiling of the
[0025]
When excavating the
Further, it is preferable to provide an opening /
When excavating from the ground, the
[0026]
When the
Here, the cutting
The purpose of using the cutting
[0027]
The
[0028]
Hereinafter, a
[0029]
<B> Split Box Installation Step Using the
First, after the lower floor slab
The divided
[0030]
<B> Backfilling process and construction of divided box group sequence While the divided
In the present invention, since a plurality of the divided
After the completion of the backfilling process, it can be used as a ground road by constructing pavement.
[0031]
<C> Excavation between divided box group rows In the excavation at the interval 3 between the divided
[0032]
<D> Construction of the permanent large section tunnel Construction of the permanent large section tunnel 4 after the excavation between the divided
[0033]
Hereinafter, a
[0034]
<A> Box installation process A rectangular shield box is installed using a deformed section shield excavator (corresponding to the
<B> Split Box Installation Step The
<C> Backfilling process and construction of a permanent large section tunnel The upper part of the uppermost divided
Subsequent excavation at the interval 3 and construction of the permanent large section tunnel are the same as in the
[0035]
Hereinafter, a second embodiment of the present invention will be described with reference to the drawings.
[0036]
Between the
In addition, a plurality of middle floor slabs 19 (and the middle floor slab trapezoidal pillars 14) may be provided between the
[0037]
By using the divided
[0038]
Hereinafter, a method of constructing a large-section tunnel using the divided
[0039]
As a divided box installation step, the divided
The above-mentioned
[0040]
【The invention's effect】
Since the method for constructing a large-section tunnel according to the present invention is as described above, the following effects can be obtained.
<B> Since it does not occupy a wide range of work zones, construction work can be performed with less traffic obstacles on the ground.
<B> Since the excavation groove is formed on the ground using a shield excavator including an open shield machine and a closed shield excavator equipped with a cutting mountain retaining body, the influence of excavation is hard to reach the periphery.
<C> Since the divided box is further divided into a plurality of divided pieces, it is possible to reduce the size of the heavy equipment for hanging the box and the transport vehicle.
<D> Temporary housing and permanent split housing play the role of retaining walls and retaining members, so there is no need to construct retaining walls or install cutting beams, thus shortening the overall process. it can.
[Brief description of the drawings]
FIG. 1A is a perspective view showing a divided box of the present invention. (B) A perspective view of the case where the divided box is divided into a trapezoidal column of upper floor slab, a trapezoidal column of lower floor slab, a left column of the divided box, and a right column of the divided box.
FIG. 2 is a perspective view showing a divided box provided with an intermediate floor slab, and FIG. 2 (a) is a perspective view showing a divided box provided with one step of an intermediate floor slab. (B) The perspective view which showed the division | segmentation box body provided with the two steps of the middle floor slabs.
FIG. 3 is a longitudinal sectional view of a shield machine used in the construction method of the present invention.
FIG. 4 is a front view of a shield machine used in the construction method of the present invention.
FIG. 5 is an explanatory view illustrating a state in which a divided box is suspended while excavating with a shield machine in the construction method of the present invention.
FIG. 6 is an explanatory view for explaining the construction method of the present invention, and (a) an explanatory view for explaining that a lower floor slab trapezoidal column is installed. (B) Explanatory drawing explaining the situation where the split box left column is installed after the lower floor slab trapezoidal column is installed, and the split box right column is installed.
FIG. 7 is an explanatory view for explaining a construction method of the present invention, in which (a) an upper floor slab trapezoidal column is set after a lower slab trapezoidal column, a split box left column, and a split box right column are installed. FIG. (B) Explanatory drawing explaining the situation in which the upper floor slab trapezoidal column is installed among the second-stage divided boxes.
FIG. 8 is an explanatory view for explaining the construction method of the present invention, and (a) is an explanatory view for explaining a situation where the construction of two divided box group rows at intervals is completed. (B) Explanatory drawing explaining the situation which is excavating the space | interval.
FIG. 9 is an explanatory view illustrating a situation in which the construction of the permanent large section tunnel is completed.
FIGS. 10A and 10B are explanatory views illustrating a construction method of the present invention using a divided box provided with an intermediate floor slab, and FIG. 10A is an explanatory view illustrating a situation where a trapezoidal column of an intermediate floor slab is installed. (B) Explanatory drawing explaining the situation which is excavating the space | interval.
FIG. 11 is an explanatory diagram illustrating a situation in which a divided box of the approach section is installed.
FIG. 12 is an explanatory view illustrating a conventional method for constructing a large-section tunnel.
[Explanation of symbols]
1 ・ ・ ・
Claims (7)
前記分割函体の筒体軸に垂直に切断した断面において、前記上床版の上面が台形の長手底辺となる台形柱体が前記上床版の一部を構成する上床版台形柱体と、
前記分割函体の筒体軸に垂直に切断した断面において、前記下床版の下面が台形の長手底辺となる台形柱体が前記下床版の一部を構成する下床版台形柱体と、
前記上床版台形柱体及び前記下床版台形柱体を除いた前記分割函体を構成する分割函体左側柱体及び分割函体右側柱体と、からなることを特徴とする、
分割函体。A quadrangular prism-shaped split box consisting of an upper floor slab, a lower floor slab, a right side wall, and a left side wall, which is used when splitting a large section tunnel.
An upper floor slab trapezoidal column in which a trapezoidal column in which the upper surface of the upper slab is a longitudinal base of the trapezoid forms a part of the upper slab,
In a cross section cut perpendicular to the cylinder axis of the divided box, a trapezoidal column in which the lower surface of the lower floor slab is a long base of a trapezoid is a lower floor slab trapezoidal column constituting a part of the lower floor slab. ,
The upper box slab trapezoidal column and the lower box slab trapezoidal column except for the divided box left column and the divided box right column that constitute the divided box,
Split box.
前記上床版と前記下床版の間に、前記上床版及び前記下床版と略並行に中床版を設け、前記分割函体の筒体軸に垂直に切断した断面において、前記中床版の上面が台形の長手底辺となる台形柱体が前記上床版の一部を構成する中床版台形柱体を備えたことを特徴とする、
分割函体。The divided box according to claim 1,
Between the upper floor slab and the lower floor slab, an intermediate floor slab is provided substantially in parallel with the upper floor slab and the lower floor slab, and in a cross section cut perpendicular to the cylinder axis of the divided box, the intermediate floor slab A trapezoidal column whose upper surface is a trapezoidal longitudinal base has an intermediate floor slab trapezoidal column constituting a part of the upper floor slab,
Split box.
分割函体。The divided box according to claim 2, wherein a plurality of the intermediate floor slabs are provided,
Split box.
地盤に断面視矩形の掘削溝を造成しながら、前記下床版台形柱体を設置し、前記分割函体左側柱体及び前記分割函体右側柱体を設置し、前記上床版台形柱体を設置することによって前記分割函体を構築し、掘削溝に複数の前記分割函体を鉛直方向に積み上げ設置して分割函体群を構成し、前記掘削溝に分割函体群を隣接設置していく分割函体設置工程と、
前記分割函体群の上部を埋戻す埋戻し工程と、によって分割函体群列を構築し、
間隔を置いて略並行に構築した複数の前記分割函体群列の間を掘削し、
前記分割函体郡列を山留め支保部材として利用しながら本設大断面トンネルを構築することを特徴とする、
分割函体を使用した大断面トンネルの施工方法。A method for constructing a large-section tunnel using the divided box according to claim 1,
While creating a rectangular excavation groove in cross section in the ground, installing the lower floor slab trapezoidal column, installing the split box left column and the split box right column, and forming the upper floor slab trapezoidal column. By constructing the divided box by installing, a plurality of the divided boxes are vertically stacked in the excavation groove to form a divided box group, and the divided box group is installed adjacent to the excavation groove. The split box installation process,
A backfilling step of backfilling the upper part of the divided box group, thereby constructing a divided box group sequence,
Excavating between the plurality of divided box group rows constructed substantially in parallel at intervals,
Constructing a large-scale tunnel with the divided box body group as a retaining member using a mountain retaining structure,
Construction method of large section tunnel using split box.
地盤に断面視矩形の掘削溝を造成しながら、前記下床版台形柱体を設置し、前記分割函体左側柱体及び前記分割函体右側柱体を設置し、前記中床版台形柱体を設置し、前記上床版台形柱体を設置することによって前記分割函体を構築し、掘削溝に前記分割函体を隣接設置していく分割函体設置工程と、
前記分割函体の上部を埋戻す埋戻し工程と、によって分割函体列を構築し、
間隔を置いて略並行に構築した複数の前記分割函体列の間を掘削し、
前記分割函体列を山留め支保部材として利用しながら本設大断面トンネルを構築することを特徴とする、
分割函体を使用した大断面トンネルの施工方法。A method for constructing a large-section tunnel using the divided box according to claim 2 or 3,
While forming a rectangular excavation groove of a rectangular cross section in the ground, installing the lower floor slab trapezoidal column, installing the split box left column and the split box right column, the middle slab trapezoidal column Installed, constructing the divided box by installing the trapezoidal column of the upper floor slab, a divided box installation step of installing the divided box adjacent to the excavation groove,
A backfilling step of backfilling the upper part of the split box, to build a split box row,
Excavating between the plurality of divided box rows constructed substantially in parallel at intervals,
It is characterized by constructing a permanent large section tunnel while using the divided box row as a mountain retaining support member,
Construction method of large section tunnel using split box.
前面に掘削カッタを備えた密閉型の下段部と少なくとも前面を開放した開放型の上段部とからなり、前記上段部はスライド式の庇部とスライド式の側壁部とを備えたシールド掘進機を使用して前記掘削溝を造成することを特徴とする、
分割函体を使用した大断面トンネルの施工方法。In a method for constructing a large-section tunnel using the divided box according to claim 4 or 5,
The shield excavator includes a closed lower portion having a drilling cutter on the front surface and an open upper portion having at least the front surface opened, and the upper portion has a sliding eaves portion and a sliding side wall portion. Characterized in that it is used to create the dig trench,
Construction method of large section tunnel using split box.
前記矩形シールド函体の上床版に沿って地盤に掘削溝を造成しながら、前記矩形シールド函体上に請求項1記載の分割函体を隣接設置していく分割函体設置工程と、
前記分割函体の上部を埋戻す埋戻し工程と、によって矩形シールド函体及び分割函体からなる函体列を構築し、
間隔を置いて略並行に構築した複数の前記函体列の間を掘削し、
前記函体列を山留め支保部材として利用しながら本設大断面トンネルを構築することを特徴とする、
分割函体を使用した大断面トンネルの施工方法。A box installation process of installing a rectangular shield box using a deformed section shield excavator that can excavate a deformed section,
A split box installation step of installing the split box according to claim 1 adjacently on the rectangular shield box while forming an excavation groove in the ground along the upper floor slab of the rectangular shield box,
A backfilling step of backfilling the upper part of the split box, by constructing a box row consisting of a rectangular shield box and a split box,
Excavating between a plurality of the box rows constructed substantially in parallel at intervals,
It is characterized by constructing a permanent large section tunnel while using the box row as a mountain retaining support member,
Construction method of large section tunnel using split box.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003146830A JP4185401B2 (en) | 2003-05-23 | 2003-05-23 | Construction method of large section tunnel using divided box |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003146830A JP4185401B2 (en) | 2003-05-23 | 2003-05-23 | Construction method of large section tunnel using divided box |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004346664A true JP2004346664A (en) | 2004-12-09 |
JP4185401B2 JP4185401B2 (en) | 2008-11-26 |
Family
ID=33533572
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003146830A Expired - Fee Related JP4185401B2 (en) | 2003-05-23 | 2003-05-23 | Construction method of large section tunnel using divided box |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4185401B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006348612A (en) * | 2005-06-16 | 2006-12-28 | Ohbayashi Corp | Construction method of underground structure, and underground structure constructed by the construction method |
US20180130779A1 (en) * | 2016-04-15 | 2018-05-10 | Glo Ab | Method of forming an array of a multi-device unit cell |
-
2003
- 2003-05-23 JP JP2003146830A patent/JP4185401B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006348612A (en) * | 2005-06-16 | 2006-12-28 | Ohbayashi Corp | Construction method of underground structure, and underground structure constructed by the construction method |
US20180130779A1 (en) * | 2016-04-15 | 2018-05-10 | Glo Ab | Method of forming an array of a multi-device unit cell |
Also Published As
Publication number | Publication date |
---|---|
JP4185401B2 (en) | 2008-11-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4309219B2 (en) | Tunnel construction method | |
JP2020084474A (en) | Widening construction method of existing tunnel | |
JP5597800B2 (en) | Construction method of underground structure | |
JP3941055B2 (en) | Method of branching and joining the shield tunnel | |
JP4303512B2 (en) | Construction method of large section tunnel | |
JP4074214B2 (en) | Shield excavation machine and ground excavation method using the same | |
JP4303511B2 (en) | Construction method of large section tunnel | |
JP2004346664A (en) | Dividable caisson, and method of constructing large cross-sectional tunnel using the dividable caisson | |
JP2594863B2 (en) | Underground tunnel widening method and branching / merging section construction method | |
JP4705467B2 (en) | Construction method of underground structure | |
JP4349570B2 (en) | Construction method of division box and underground level crossing | |
JPH07331998A (en) | Constructing method of rock cavern | |
JP2668648B2 (en) | Construction method of underground structure and starting pit used for it | |
JPH0654016B2 (en) | Underground space construction method | |
JPH04309692A (en) | Underground space construction method | |
JP3487416B2 (en) | Construction method of underground structure and concrete box used for it | |
CN220414786U (en) | Construction platform structure at inner side of foundation pit in narrow space | |
JP3868959B2 (en) | Waterway construction method | |
JP4397797B2 (en) | Construction method of underground structure | |
JP4253806B2 (en) | Method of branching and joining the shield tunnel | |
JP2840122B2 (en) | Shield excavator and tunnel construction method using the shield excavator | |
JP3646698B2 (en) | Construction method for underground structures | |
JP2023007861A (en) | Tunnel caisson group unit and construction method thereof | |
JPH0235190A (en) | Multicore-parallel optional section shield machine | |
JP3333770B2 (en) | Construction method for underground structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060405 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080229 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080325 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080526 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080819 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080905 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110912 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110912 Year of fee payment: 3 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110912 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120912 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130912 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |