JP2004270440A - Construction method for foundation pile, and prefabricated pile - Google Patents

Construction method for foundation pile, and prefabricated pile Download PDF

Info

Publication number
JP2004270440A
JP2004270440A JP2004039553A JP2004039553A JP2004270440A JP 2004270440 A JP2004270440 A JP 2004270440A JP 2004039553 A JP2004039553 A JP 2004039553A JP 2004039553 A JP2004039553 A JP 2004039553A JP 2004270440 A JP2004270440 A JP 2004270440A
Authority
JP
Japan
Prior art keywords
pile
ready
spiral blade
ground
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004039553A
Other languages
Japanese (ja)
Other versions
JP4496553B2 (en
Inventor
Yoichi Kato
洋一 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitani Sekisan Co Ltd
Original Assignee
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitani Sekisan Co Ltd filed Critical Mitani Sekisan Co Ltd
Priority to JP2004039553A priority Critical patent/JP4496553B2/en
Publication of JP2004270440A publication Critical patent/JP2004270440A/en
Application granted granted Critical
Publication of JP4496553B2 publication Critical patent/JP4496553B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To obtain about twice a bearing capacity than before by eliminating earth removal in the burial of a prefabricated pile. <P>SOLUTION: A spiral blade 8 and an auxiliary spiral blade 12 are formed on the outer periphery of the lower end of outer-hull steel pipe concrete so as to serve as the prefabricated pile 16. An excavating rod 18 wherein an earth removing means is not formed is inserted into a hollow part 3 of the prefabricated pile 16 (a). A posthole shaft 24 with a diameter D<SB>21</SB>is excavated by means of an excavating head 20 without the use of excavation liquid or the earth removal so that ground can be unstiffened. The prefabricated pile 16 is concurrently or alternately pushed in while being rotated, and made to penetrate into the ground while being screwed into the ground by means of the spiral blade 12 (b). An expanded foot protection part 25 with a diameter D<SB>22</SB>is formed on the bearing ground (c). After cement milk is injected into excavated soil in the foot protection part 25 so that a soil cement layer 26 can be formed, the excavating rod 18 is pulled up on the ground 29 (d), and the prefabricated pile 16 is screwed for burial in such a manner that the spiral blade 8 and the auxiliarly spiral blade 12 are positioned in the cement layer 26, so that the foundation pile 28 can be constructed (e). <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

この発明は、既製杭を使用した基礎杭の造成方法において、主として、螺旋翼付き既製杭を用いて、従来より高支持力および掘削時の排土低減を実現する基礎杭の造成方法及びこの造成方法に使用する既製杭に関するものである。   The present invention relates to a method of constructing a foundation pile using a prefabricated pile, and more particularly to a method of constructing a foundation pile realizing a higher bearing capacity and a reduction in earth removal during excavation by using a prefabricated pile with spiral blades, and this construction. It relates to ready-made piles used in the method.

従来の杭基礎の造成方法:主として先端支持力が利用されているコンクリート製の既製杭を用いた杭基礎は、その経済性確保のために、主として掘削速度が寄与する施工性がある程度確保され実用化されているが、杭穴造成時に発生する掘削土が土泥として多量に排出されているのが実体であり、性能、経済性を維持しながら環境面からの排土の低減が長年の課題であった。   Conventional pile foundation creation method: Pile foundation using precast concrete piles, which mainly use tip bearing capacity, has a certain level of workability, mainly due to the excavation speed, to ensure economic efficiency. However, the excavated soil generated during the construction of pile holes is actually discharged in large quantities as mud, and it has been a long-standing issue to reduce environmentally unloaded soil while maintaining performance and economy. Met.

(1)従来のコンクリート杭の中掘工法
中掘工法では、コンクリート製の円筒形既製杭の中空部に、杭の上方から掘削ヘッド付きロッドを挿通させ、既製杭の下端から突出させた掘削ヘッドを広げ、掘削ロッドを介してそのロッドを回転させて地盤を掘削し、ほぼ杭径寸法の杭穴を形成しながら該杭を漸次下降させ沈設させて、基礎杭を造成していた。従って、比較的掘削し易いあるいは崩落しやすい地盤等には有効であった。
このような中掘工法では、施工性を良くするために(既製杭の沈設速度を早くするために)、掘削土の上方への排出性を良くする必要がある。従って、この杭穴掘削時に、掘削水あるいはエアをロッドを通じて注出させて掘削土を粉砕化し、かつ、ロッドはスパイラル形状として掘削土を押し上げ・搬出し易くしており、杭の押し入れ時に土泥による押し入れ障害が少なくなるように排土性に各種工夫が行われて来ている。
また、中掘用の掘削ロッドは、杭穴内壁への接触可能部分が少ないために、土泥の練り付け用ドラムの装着も難しいため、掘削土を杭穴内壁に練りつけ地盤補強することも難しいため周面摩擦力が不充分となり、かつ掘削土がそのまま掘削量に比例して排出されているので排土量も多い工法となっている。
即ち、環境面から、排土を低減することは既製杭の沈設が困難で施工性が悪くなり一般的には実務上採用できないレベルであった。
(1) Conventional excavation method of concrete pile In the excavation method, a rod with an excavation head is inserted into the hollow part of a concrete cylindrical precast pile from above the pile and protrudes from the lower end of the precast pile. And the ground is excavated by rotating the rod through a drilling rod, and the pile is gradually lowered and settled while forming a pile hole having substantially the diameter of the pile, thereby forming a foundation pile. Therefore, it is effective for the ground which is relatively easily excavated or easily collapses.
In such an underground excavation method, it is necessary to improve the excavation property of the excavated soil upward in order to improve the workability (in order to increase the setting speed of the ready-made pile). Therefore, at the time of excavating the pile hole, drilling water or air is poured out through the rod to pulverize the excavated soil, and the rod has a spiral shape to facilitate lifting and carrying out the excavated soil. Various methods have been devised for the earth discharging property so as to reduce the push-in obstacle caused by the intrusion.
In addition, since the excavation rods for excavation have few parts that can contact the inner wall of the pile hole, it is difficult to install a drum for kneading mud.Therefore, the excavated soil can be kneaded on the inner wall of the pile hole to reinforce the ground. Due to the difficulty, the frictional force on the peripheral surface becomes insufficient, and the excavated soil is discharged in proportion to the excavated amount.
That is, from the environmental point of view, it was difficult to reduce the earth removal because it was difficult to lay down the ready-made piles, and the workability was poor.

(2)従来のコンクリート杭の先掘工法
掘削ヘッドと撹拌棒、場合によっては練り付けドラムを装着した掘削ロッドを用いて、掘削ロッドを回転させながら地盤を掘削して、杭の最大外径に見合う杭穴を形成する。途中、掘削性を良くするために水等の掘削水を注水しながら掘削している。また、必要により、掘削土とセメントミルク等の固化材を撹拌混合して所定固化強度のソイルセメント層を形成した後、既製杭を沈設して、基礎杭を造成していた。
中掘り工法に比べ、ロッドに練りつけドラム等が複数装着できるために、掘削土が杭穴内壁に練り付けられ、その内壁が補強され周辺摩擦力はかなり改善され、同時に、掘削土の排出もある程度低減されているが、基本的には掘削土と固化材あるいは水等の混合した土泥が多量に排出されているので、その排土処理の経済性の問題とあわせて環境面から問題であった。
即ち、環境面から、排土を大幅に低減することは、通常の地盤ではコンクリート杭を沈設することが実務上採用できないレベルであった。
また、打撃工法もあるが、衝撃・振動が激しくて住宅地では日常生活が困難なレベルであった。
(2) Conventional excavation method for concrete piles Using a drilling head and a stirring rod, and in some cases, a drilling rod equipped with a kneading drum, excavate the ground while rotating the drilling rod to obtain the maximum outer diameter of the pile. Form suitable pile holes. During the excavation, excavation is performed while injecting excavation water such as water to improve excavation properties. Also, if necessary, after excavated soil and a solidifying material such as cement milk are stirred and mixed to form a soil cement layer having a predetermined solidifying strength, an existing pile is laid to form a foundation pile.
Compared to the middle digging method, the rod can be equipped with a plurality of kneading drums, so that the excavated soil is kneaded to the inner wall of the pile hole, the inner wall is reinforced and the peripheral frictional force is considerably improved, and at the same time, the excavated soil is discharged. Although it has been reduced to some extent, basically excavated soil and solidified material or a large amount of mud mixed with water, etc. are discharged, so it is not only environmentally friendly, but also environmentally friendly. there were.
That is, from the environmental point of view, it is practically impossible to lay concrete stakes on ordinary ground to significantly reduce soil removal.
There is also a blow method, but the level of impact and vibration was so great that daily living was difficult in residential areas.

(3)螺旋翼付き鋼管杭をねじ込み沈設する杭基礎の施工方法
螺旋翼付き鋼管杭をねじ込み沈設するので、排土が殆どなく環境に優しい工法となっている。一般に、ねじ込み時の地盤からの反力が少ない、即ち地盤強度の良くない軟弱な地盤において有効な工法である。
即ち、ねじ込み強度を向上するには、捻りに耐えなければならず、鋼管の肉厚を厚くする必要が生じ、支持力に必要な厚さと整合せず、必要以上に厚くなるので、軟らかくない地盤では、コンクリート杭に比較して経済的に成り立たなかった。
また、掘削することなく、螺旋翼により杭をねじ込み排土しないので、杭穴軸部の地盤をあまり乱すことなく杭を沈設しているので、螺旋翼を用いてのいわゆる周面摩擦力が効率的に利用できている。
しかし、杭の先端支持力に関しては全く不充分で、コンクリート製杭による杭基礎の先端支持力に比べ約半分となっていること及び、施工地盤が限られていることからも耐荷重の点から用途が限定されており、さらに、鋼管杭がコンクリート杭に比較して高価なことによる経済性の点から用途が限定されていた。
このような中、螺旋翼付きのコンクリート製の既製杭の提案が成されている(特許文献1〜4)。
実公平4−14500 特公昭58−54211 特開平1−94112 特開昭60−123620 特公平7−49655 特開2002−61179
(3) Construction method of pile foundation for screwing and laying steel pipe pile with spiral wings Since the steel pipe pile with spiral wings is screwed and settled, there is almost no earth removal and the construction method is environmentally friendly. Generally, it is an effective construction method for a weak ground where the reaction force from the ground at the time of screwing is small, that is, the ground strength is not good.
In other words, in order to improve the screwing strength, it is necessary to withstand torsion, and it is necessary to increase the wall thickness of the steel pipe, and it does not match the thickness required for the supporting force, and becomes thicker than necessary. Then, it was not economically viable compared to concrete piles.
Also, without excavation, the pile is screwed down by the spiral wing and the soil is not discharged, so the pile is laid down without disturbing the ground at the shaft of the pile hole, so the so-called peripheral friction force using the spiral wing is efficient. It is available for use.
However, the bearing capacity at the tip of the pile is quite inadequate, and is about half that of the tip support of the pile foundation made of concrete piles. The applications are limited, and furthermore, the applications are limited in terms of economy due to the expensive steel pipe piles compared to concrete piles.
Under such circumstances, proposals have been made for ready-made concrete piles with spiral blades (Patent Documents 1 to 4).
4-14500 Japanese Patent Publication No. 58-54211 JP-A-1-94112 JP-A-60-123620 Tokuho 7-49655 JP-A-2002-61179

上記各従来技術は、以下のような問題点があった。   Each of the above prior arts has the following problems.

(1)特許文献1:実公平4−14500
この公報は、大径のらせん状つばを有する先端コンクリート杭の上部に小径コンクリートパイルを連結し、前記先端コンクリート杭に螺旋つば付き推進ケースを掛合して、推進ケースを介して杭に回転力を与え、杭をねじ込みながら沈設し、杭沈設後に推進ケースを抜き取る考案が、開示されている。
この発明では、排土は減少すると記載されているが、先端コンクリート杭のつばがコンクリート製であるため、ねじ込み時の強度が不足しており、施工地盤が柔らかい特定の地盤に限定されており、実務上の効果が不確かであり、更に、杭基礎構造として高耐力(せん断が効率的に伝搬する構造)化ヘの配慮も不足している。
(1) Patent Document 1: Japanese Utility Model 4-14500
This publication discloses that a small-diameter concrete pile is connected to the top of a tip concrete pile having a large-diameter helical collar, a propulsion case with a spiral collar is engaged with the tip concrete pile, and rotational force is applied to the pile via the propulsion case. A device is disclosed in which a pile is provided, the pile is sunk while being screwed in, and the propulsion case is extracted after the pile is sunk.
In this invention, it is described that the earth removal is reduced, but since the tip of the concrete pile is made of concrete, the strength at the time of screwing is insufficient, and the construction ground is limited to a specific ground with a soft ground, Practical effects are uncertain, and furthermore, consideration is not given to the construction of high strength (structure in which shear propagates efficiently) as the pile foundation structure.

(2)特許文献2:特公昭58−54211
この公報に記載の発明は、らせん状つば部を有するコンクリート杭において、らせん状つばの形状およびコンクリート杭の強度などを工夫してねじり込みによる杭の貫入性を改善している。
この発明では、杭貫入時に、コンクリート製のらせん状つばの上下面の角度を調整してねじりのトルクを調整して、杭の貫人性と掘削土の排土性を改良しているとしているが、強度の低いコンクリート製の杭では多少改良しても施工可能な地盤が限られており、さらに杭基礎構造として耐荷重の増強(せん断が効率的に伝搬する構造)への配慮も不足している。
(2) Patent Document 2: Japanese Patent Publication No. 58-54211
In the invention described in this publication, in a concrete pile having a spiral collar, the shape of the spiral collar and the strength of the concrete pile are devised to improve the penetration of the pile by screwing.
According to the invention, when the pile is penetrated, the angle of the upper and lower surfaces of the spiral spiral collar made of concrete is adjusted to adjust the torque of torsion, thereby improving the penetration property of the pile and the discharging property of the excavated soil. However, low-strength concrete piles are limited in the ground that can be constructed even if they are slightly improved, and there is also a lack of consideration for reinforcement of load capacity (structure in which shear propagates efficiently) as the pile foundation structure. I have.

(3)特許文献3:特開平1−94112
この公報に記載の発明は、杭先端内壁にねじ状突起を形成した鋼管杭の中空部に、スパイラルオーガーを挿入し、杭の先端部を掘削しながら杭を圧入し、先端が支持層部に到達したならば杭をねじ込み貫入し、最後に打撃して杭を固定させ先端支持力を確保している。
この発明では、杭先端内壁のねじ状突起及びスパイラルオーガーを排土に利用しているので、掘削土の押し上げが容易となり杭の貫入速度は改善されており、支持力もかなり得られていると記載されているが、掘削土の排出は従来通り多量であり、耐荷重の増強に関しても杭基礎構造としての記載がなく配慮(せん断が効率的に伝搬する構造)が不足している。
(3) Patent Document 3: JP-A-1-94112
The invention described in this publication discloses that a spiral auger is inserted into a hollow portion of a steel pipe pile having a threaded protrusion formed on an inner wall of the pile tip, and the pile is pressed into the pile while excavating the tip of the pile. When it arrives, the pile is screwed and penetrated, and finally hit to secure the pile and secure the tip support force.
According to the present invention, since the screw-shaped protrusions and the spiral auger on the inner wall of the pile tip are used for discharging the soil, it is easy to push up the excavated soil, the penetration speed of the pile is improved, and the bearing capacity is considerably obtained. However, the amount of excavated soil is large as before, and there is no description of the pile foundation structure as to the enhancement of load-bearing capacity, and there is insufficient consideration (structure for efficient propagation of shear).

(4)特許文献4:特開昭60−123620
この公報では、杭先端に、らせん形ブレイドを設けた鋼管コンクリート複合杭の中央部に、角形の嵌合孔を形成し、角形ブロックの回転シャフトを挿入して回転力を与えながら杭の沈設をする工法が開示されている。
この発明では、らせん形ブレイド等杭の外殻材が鋼材であるので、回転押し込み時の強度に対して、らせん形ブレイド自身の強度は充分であるが、回転シヤフトと該ブレイド間に介在させているコンクリート部(ねじり強度の小さい)にねじり強度が作用しているために、施工地盤が柔らかい特定の土質に限られ、更に上載荷重が限られている。
更に、各種杭材で適用可能としてあるが、継ぎ杭の場合には各継ぎ杭に同様な回転力を与える嵌合部を形成する必要があり、沈設長に限度がある。また、耐荷重の増強に対しても基礎杭構造として配慮(せん断が効率的に伝搬する構造)が不足している。
(4) Patent Document 4: JP-A-60-123620
In this publication, a square fitting hole is formed in the center of a steel-pipe concrete composite pile provided with a spiral blade at the tip of the pile, and the pile is settled while inserting a rotating shaft of a square block and applying a rotating force. Is disclosed.
In the present invention, since the outer shell material of the pile such as the spiral blade is a steel material, the strength of the spiral blade itself is sufficient with respect to the strength at the time of rotating and pushing, but it is interposed between the rotating shaft and the blade. Due to the torsional strength acting on the concrete part (having a low torsional strength), the construction ground is limited to a specific soil with soft ground, and the overload is also limited.
Furthermore, although it can be applied to various pile materials, in the case of a joint pile, it is necessary to form a fitting portion that gives a similar rotational force to each joint pile, and there is a limit on the length of settlement. In addition, there is a lack of consideration as a foundation pile structure (structure in which shear propagates efficiently) to increase the load bearing capacity.

(5)特許文献5:特公平7−49655
この公報には、螺旋翼付き推進パイルの基盤部に、中空パイルの端部を嵌合した遊動環を固定し、該遊動環と中空パイルの端板とを熔接接合した基礎杭の発明が記載されている。
基礎杭は、推進パイルの螺旋翼の推進作用で沈設するので、上部に連結された中空パイルにはねじりモーメントは作用せず保護されるが、先端に位置する推進パイルはコンクリート部にねじりモーメントが作用し、強度が不足しており施工範囲(施工地盤および上載荷重等)が限られる。また、耐荷重の増強に関しても基礎杭構造として配慮(せん断が効率的に伝搬する構造)が不足している。
(5) Patent Document 5: Japanese Patent Publication No. 7-49655
This publication describes an invention of a foundation pile in which a floating ring in which an end of a hollow pile is fitted is fixed to a base portion of a propulsion pile with spiral wings, and the floating ring and an end plate of the hollow pile are welded and joined. Have been.
The foundation pile is submerged by the propulsion action of the spiral wings of the propulsion pile, so the hollow pile connected to the upper part is protected without a torsional moment, but the propulsion pile located at the tip has a torsional moment in the concrete part. Acts, lacks strength, and limits the construction range (construction ground, overlay load, etc.). In addition, there is a lack of consideration as a foundation pile structure (structure in which shear propagates efficiently) with regard to the enhancement of load bearing capacity.

(6)特許文献6:特開2002−61179
この公報に記載の発明では、螺旋翼付き杭の中空部を挿通した中掘り用掘削ヘッドで地盤を掘削しながら貫入させ、杭先端部の支持層では、掘削ヘッドで杭の下端を閉栓すると共に、更にねじ込み、掘削ロッドを掘削ヘッド部から分離し、該掘削ヘッド部を残置して支持力高めている。
この発明では、中空杭は下開端で従来の中掘り方式であるので容易に貫入でき、先端支持力に関しては、杭先端の地盤に掘削ヘッドが押し込みされ、通常の螺旋翼付き杭より高い支持力が期待されるが、掘削ヘッドを残置するので経済的にロスがあることおよび、効果が記載されていないが多量の掘削土の排出が見込まれ、さらに、耐荷重の増強に関する基礎杭構造としての配慮(せん断が効率的に伝搬する構造)が不足している。
(6) Patent Document 6: JP-A-2002-61179
In the invention described in this publication, the ground is excavated and penetrated by a digging head for medium digging in which the hollow portion of the pile with a spiral wing is inserted, and in the support layer at the tip of the pile, the lower end of the pile is closed with the digging head. Further, the drilling rod is separated from the drilling head part by further screwing, and the drilling head part is left to increase the supporting force.
In the present invention, the hollow pile is a conventional hollow digging method with a lower open end, so that it can easily penetrate. Regarding the tip supporting force, the excavating head is pushed into the ground at the tip of the pile, and the supporting force is higher than that of a normal pile with a spiral wing. However, it is economical loss because the excavation head is left behind, and a large amount of excavated soil is expected to be discharged although the effect is not described. Insufficient considerations (structure in which shear propagates efficiently).

以上、(1)〜(6)のように、螺旋翼付きコンクリート杭等においては、ねじ込みに各種提案がなされているが、各種強度の施工地盤で、螺旋付翼をねじ込むときに必要な杭全体の耐力が不足しており、かつ、螺旋翼面で、効率的な支持が得られていないので、低排土と経済性が両立する工法となっていないのが実情であった。   As described above, as in (1) to (6), various proposals have been made for screwing in concrete piles with spiral wings, but the entire pile required for screwing the spiral wings on construction ground of various strengths. Because of the lack of proof stress and the lack of efficient support on the spiral wing surface, the current situation was that the construction method was not compatible with low soil removal and economic efficiency.

然るにこの発明では、外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して既製杭を構成し、掘削液を使用せずに杭穴を掘削し、あるいはほぐした地盤とすると共に、螺旋羽根で杭穴の周辺地盤にねじ込みながら既製杭を埋設するので、前記各問題点を解決した。   However, in the present invention, a prefabricated pile is formed by forming spiral blades on the outer periphery of the lower end of a concrete pile body whose outside is covered with a steel pipe, and a pile hole is excavated without using a drilling liquid, or the ground is unraveled. In addition, since the ready-made pile is buried while being screwed into the ground around the pile hole with the spiral blade, each of the above problems is solved.

即ち、この方法の発明は、
(1) 外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して既製杭を構成する。
(2) 前記既製杭の中空部を、排土手段を形成していない掘削ロッドを貫通し、該掘削ロッドの掘削ヘッドを前記既製杭の下端から突出させる。
(3) 前記掘削ヘッドを回転して、地盤強度に対応して前記既製杭のねじ込みが可能となる径で、掘削液を使用せず、かつ排土をせずに杭穴を掘削しながら、ほぐした地盤を形成する。これと同時に又は交互に、前記既製杭を回転して、前記螺旋羽根で地盤にねじ込みながら前記既製杭を地盤に貫入する。
(4) 前記掘削ヘッドで所定の支持地盤に根固め部を形成したならば、前記掘削ヘッドを収容して、前記既製杭の中空部を通って、地上に引き上げると共に、前記根固め部内に前記螺旋羽根が位置するように、前記既製杭を埋設して、基礎杭を造成する。
(5) 以上のようにして、既製杭を埋設することを特徴とする基礎杭の造成方法である。
That is, the invention of this method is:
(1) Spiral blades are formed on the outer periphery of the lower end of a concrete pile body whose outside is covered with a steel pipe to constitute a ready-made pile.
(2) The hollow portion of the ready-made stake is penetrated by a digging rod that does not form a soil discharging means, and the digging head of the digging rod protrudes from the lower end of the ready-made stake.
(3) By rotating the excavation head, with a diameter that allows the ready-made pile to be screwed in accordance with the ground strength, without using a drilling liquid, and while excavating a pile hole without discharging the soil, Form loose ground. At the same time or alternately, the ready-made pile is rotated, and the ready-made pile is penetrated into the ground while being screwed into the ground with the spiral blade.
(4) When the excavation head has formed a solidification portion on a predetermined support ground, the excavation head is accommodated, and the hole is lifted to the ground through the hollow portion of the ready-made pile, and the above-mentioned solidification portion is formed in the solidification portion. The foundation pile is formed by burying the ready-made pile so that the spiral blade is positioned.
(5) A method for forming a foundation pile characterized by burying a ready-made pile as described above.

また、他の方法の発明は、
(1) 外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して、既製杭を構成する。
(2) 掘削ロッドの先端の掘削ヘッドで、地盤強度に対応して前記既製杭のねじ込みが可能となる径で、掘削液を使用せずに、かつ排土をせずに、地盤を掘削しながら地盤をほぐして、所定の支持地盤に根固め部を有する杭穴を形成する。
(3) 前記杭穴内に、前記既製杭を回転しつつ、前記螺旋羽根で、杭穴壁周辺の地盤にねじ込みながら貫入し、前記螺旋羽根が前記根固め部内に位置するように、前記既製杭を埋設して、基礎杭を造成する。
(4) 以上のようにして、既製杭を埋設することを特徴とする基礎杭の造成方法である。
Also, the invention of another method is
(1) Spiral blades are formed on the outer periphery of the lower end of a concrete pile body whose outside is covered with a steel pipe to constitute a ready-made pile.
(2) The excavation head at the tip of the excavation rod has a diameter that allows the ready-made pile to be screwed in accordance with the soil strength, and excavates the ground without using drilling fluid and without discharging the soil. While the ground is loosened, a pile hole having a rooted portion is formed in a predetermined supporting ground.
(3) The prefabricated pile is rotated so that the prefabricated pile is screwed into the ground around the pile hole wall while rotating the prefabricated pile into the pile hole, and the spiral blade is positioned in the root compaction portion. Is buried to create a foundation pile.
(4) A method for forming a foundation pile characterized by burying a ready-made pile as described above.

前記方法の発明において、掘削ヘッドで、螺旋羽根の外径と同等又はより大径の拡大根固め部を掘削し、該拡大根固め部内に形成するソイルセメント層内に、既製杭の螺旋羽根を位置させる基礎杭の造成方法である。また、掘削ヘッドで、杭本体の外径と同等又は大径で掘削しつつ、杭穴又はほぐした地盤を形成する基礎杭の造成方法である。また、外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して構成した既製杭を下杭として、他のコンクリート杭を上杭として、埋設する対象の既製杭を構成し、上杭を被覆したケーシングの下端部を前記下杭に係止し、該ケーシングの上端部を回転して、前記下杭を回転させる基礎杭の造成方法である。   In the invention of the above method, the excavating head excavates an enlarged root consolidation portion having a diameter equal to or larger than the outer diameter of the spiral blade, and the spiral blade of the ready-made pile is placed in the soil cement layer formed in the enlarged root consolidation portion. This is the method of constructing the foundation pile to be located. Further, the present invention is a method for forming a foundation pile for forming a pile hole or loosened ground while excavating with a drilling head at a diameter equal to or larger than the outer diameter of the pile body. In addition, a ready-made pile composed of spiral blades formed on the outer periphery of the lower end of a concrete pile body covered with steel pipe on the outside is used as a lower pile, and another concrete pile is used as an upper pile, and an existing pile to be buried is constructed. Then, a lower pile of the casing covering the upper pile is locked to the lower pile, and the upper pile of the casing is rotated to rotate the lower pile.

また、既製杭の発明は、外側を鋼管で被覆したコンクリート製の杭本体で、下端部外周に螺旋羽根を形成したことを特徴とする既製杭である。   Further, the invention of the ready-made pile is a concrete pile main body whose outside is covered with a steel pipe, wherein a spiral blade is formed on an outer periphery of a lower end portion.

また、前記において、半周分の半ドーナッツ状の螺旋羽根片の2つを、回転対称な位置に螺旋状に固定して螺旋羽根としたことを特徴とする既製杭である。また、杭本体の下端を塞ぐと共に、該杭本体の下端に、掘削手段を突設したことを特徴とする既製杭である。また、杭本体の下端部に、半周分の半ドーナッツ状の螺旋羽根片の2つを、回転対称な位置に螺旋状に固定して螺旋羽根とし、該螺旋羽根の下端に掘削突片を突設し、前記杭本体で前記螺旋羽根の上方に、前記螺旋羽根の径より小径の補助螺旋羽根を形成したことを特徴とする既製杭である。更に、杭本体で、螺旋羽根の上方に、補助螺旋羽根より小径の螺旋条を形成した既製杭である。   Further, in the above-mentioned, a prefabricated pile, wherein two of the half donut-shaped spiral blade pieces for a half circumference are spirally fixed at rotationally symmetric positions to form a spiral blade. Further, the present invention is a ready-made pile, wherein the lower end of the pile main body is closed and a drilling means is protruded from the lower end of the pile main body. At the lower end of the pile main body, two half donut-shaped spiral blade pieces for a half circumference are spirally fixed at rotationally symmetric positions to form a spiral blade, and a drilling protrusion is protruded from the lower end of the spiral blade. A prefabricated pile, wherein an auxiliary spiral blade having a diameter smaller than the diameter of the spiral blade is formed above the spiral blade in the pile main body. Further, the pile is a ready-made pile in which a spiral strip having a smaller diameter than the auxiliary spiral blade is formed above the spiral blade in the pile main body.

前記における「ほぐした地盤」は、杭穴壁が明確には形成されず、崩された杭穴内に、ほぐされた掘削土が詰まったような状態となっている。   In the above “loose ground”, the pile hole wall is not clearly formed, and the broken pile hole is filled with loosened excavated soil.

(1) この発明では、既製杭の螺旋羽根を杭穴の根固め部内の所定深度に位置するように、既製杭を埋設して基礎杭を構成するので、大径の螺旋羽根を有する既製杭で、螺旋羽根の上下面を支持力として利用でき、基礎杭の鉛直支持力を増強することができる効果がある。従来使用される螺旋羽根付きの既製杭に比して、螺旋羽根の使用面積当りで従来の約2倍の支持力が得ることができる。
また、引抜き力に関しても。同様な効果が得られる。
(1) In the present invention, since the foundation pile is constructed by burying the prefabricated pile so that the spiral blade of the prefabricated pile is located at a predetermined depth in the root consolidation part of the pile hole, the prefabricated pile having the large diameter spiral blade is Thus, the upper and lower surfaces of the spiral blade can be used as a supporting force, and there is an effect that the vertical supporting force of the foundation pile can be enhanced. As compared with a conventional pile with a spiral blade used conventionally, it is possible to obtain about twice the supporting force per unit area of the spiral blade.
Also regarding the pull-out force. Similar effects can be obtained.

(2) コンクリート体を有する既製杭で、排土手段を有さない掘削ロッドを使用して、杭穴を掘削するので、コンクリート杭において、前記の高い支持力を維持しながら掘削土の排出を大幅に削減できる。セメントミルクを注入して、根固め部にセメントミルク層を形成する場合であっても、排土量は、注入したセメントミルクに相当する分量に留めることができる。 (2) Drilling of a pile hole using a drilling rod that does not have a means for discharging soil is performed on a ready-made pile having a concrete body. Can be significantly reduced. Even when cement milk is injected and a cement milk layer is formed on the consolidation portion, the amount of soil removal can be limited to the amount corresponding to the injected cement milk.

(3) 先行して、杭埋設地盤をほぐして、螺旋羽根付きのコンクリート体を有する既製杭を埋設するので、従来の2倍の高い支持力を維持しながら、螺旋羽根付きのコンクリート体を有する既製杭を、特定な軟弱な地盤に限定されることなく、通常の地盤で埋設して基礎杭を構成できる効果がある。また、この場合、通常の実用的な掘削速度で無排土の既製杭の貫入を実現できる。 (3) Previously, the pile buried ground was loosened and a ready-made pile having a spiral bladed concrete body was buried. There is an effect that a foundation pile can be constructed by burying a ready-made pile in ordinary ground without being limited to a specific soft ground. Further, in this case, it is possible to realize the penetration of the ready-made pile without soil removal at a normal practical excavation speed.

(4) 杭穴軸部の掘削径を大きく(例えば、根固め部の最大径程度まで)形成することにより、螺旋羽根付きの既製杭のねじ込む際に、生じるねじりを小さく制御できるので、外郭鋼管や螺旋羽根の厚さを薄くするなど、既製杭のねじ込み強度に限定されることなく、施工地盤に必要とされる支持力に応じて既製杭の設計をすることができる。従って、施工地盤に限定されることなく、本発明を適用でき、経済的にも合致させることができる。 (4) By making the excavation diameter of the pile hole shaft part large (for example, up to the maximum diameter of the root consolidation part), the torsion that occurs when screwing a ready-made pile with spiral blades can be controlled to be small. It is possible to design a ready-made pile according to the supporting force required for the construction ground, without being limited to the screw-in strength of the ready-made pile, for example, by reducing the thickness of the spiral blade. Therefore, the present invention can be applied without being limited to the construction ground, and can be economically matched.

(5) また、杭穴軸部の地盤が良くない場合には、その軸部地盤のみを地盤改良して、安定かつ所定の高い支持力を得ることもできる。 (5) In addition, when the ground of the shaft portion of the pile hole is not good, it is possible to obtain a stable and predetermined high supporting force by improving only the ground of the shaft portion.

(6) 施工地盤の強度によっては、掘削刃による軸部掘削径(地盤をほぐす範囲)を既製杭の杭径より小さくして、軸部の周辺部摩擦抵抗を有効に利用することもできる。 (6) Depending on the strength of the construction ground, it is possible to make effective use of the frictional resistance of the periphery of the shaft by making the diameter of the shaft excavated by the excavation blade (the range of loosening the ground) smaller than the diameter of the prefabricated pile.

(1) コンクリート体2の外側を外郭鋼管4で被覆した杭本体1の下端部外周に螺旋羽根8、補助螺旋羽根12を形成して既製杭16を構成する(図2)。既製杭16の中空部3は上下に開放している。
(2) 既製杭16の中空部3を、排土手段を形成していないロッド本体19の先端に掘削ヘッド20を連結してなる掘削ロッド18を貫通し、掘削ヘッド20を既製杭16の下端から突出させる(図4(a))。
(3) 掘削ヘッド20を回転して、杭本体より若干大径のD21の杭穴軸部24を、掘削液を使用せず、かつ、排土をせずに掘削し地盤をほぐしていく(図4(b))。これと同時に又は交互に、既製杭16を回転しながら押し込め、螺旋羽根8で地盤にねじ込みながら既製杭16を地盤に貫入する(図4(b))。
(4) 掘削ヘッド20で所定の支持地盤に径D22の拡大根固め部25を形成する(図4(c))。
(5) 掘削ヘッド20の下端部から拡大根固め部25内の掘削土内に、セメントミルクを注入して、撹拌混合してソイルセメント層26を形成した後、掘削ヘッド20を既製杭16の中空部3を通って、地上に引き上げる。ソイルセメント層26を形成した後に、拡大根固め部25のソイルセメント層26内に螺旋羽根8、補助螺旋羽根12が位置するように、既製杭をねじ込み埋設して、基礎杭28を造成する(図4(d)(e))。
(6) この基礎杭28は、掘削ヘッド20の掘削径D21を調節することにより、この既製杭16に生じるねじりを小さくすることができるので、求められる基礎杭の支持力に応じて厚さを設定でき、外郭鋼管4の厚さ等を薄くすることができる。つまり、この基礎杭では、掘削ヘッド20が掘削する掘削径D21を調節することにより、地盤のほぐし具合、即ち既製杭16に生じるねじり力を制御するので、汎用の鋼管を使用して既製杭16を製造できる。尚、この厚さは、既製杭の外径、螺旋羽根の外径等により多少異なる。
(1) The spiral blade 8 and the auxiliary spiral blade 12 are formed on the outer periphery of the lower end portion of the pile body 1 in which the outside of the concrete body 2 is covered with the outer steel pipe 4 to form a ready-made pile 16 (FIG. 2). The hollow portion 3 of the ready-made pile 16 is open vertically.
(2) The hollow part 3 of the ready-made pile 16 is penetrated by a drilling rod 18 formed by connecting a drilling head 20 to the tip of a rod body 19 that does not form a soil discharging means. (FIG. 4A).
(3) The excavating head 20 is rotated to excavate the pile shaft portion 24 of the D 21 having a slightly larger diameter than the pile body without using drilling fluid and without discharging the soil. (FIG. 4 (b)). Simultaneously or alternately, the prefabricated pile 16 is pushed in while rotating, and the prefabricated pile 16 penetrates the ground while being screwed into the ground by the spiral blade 8 (FIG. 4B).
(4) to form an enlarged root consolidated portion 25 of diameter D 22 to a predetermined supporting ground drilling head 20 (FIG. 4 (c)).
(5) Cement milk is poured from the lower end of the excavation head 20 into the excavated soil in the enlarged root compaction part 25, and is stirred and mixed to form a soil cement layer 26. Through the hollow part 3, it is raised to the ground. After the soil cement layer 26 is formed, the prefabricated pile is screwed and buried so that the spiral blade 8 and the auxiliary spiral blade 12 are located in the soil cement layer 26 of the expanded root compaction part 25 to form the foundation pile 28 ( FIG. 4 (d) (e)).
(6) The foundation pile 28, by adjusting the drilling diameter D 21 of the excavation head 20, it is possible to reduce the twisting occurring to the ready-made pile 16, the thickness depending on the bearing capacity of the foundation obtained piles of Can be set, and the thickness and the like of the outer steel pipe 4 can be reduced. That is, in this foundation pile, the degree of loosening of the ground, that is, the torsional force generated in the ready-made pile 16 is controlled by adjusting the excavation diameter D21 excavated by the excavation head 20. Can be manufactured. Note that this thickness is slightly different depending on the outer diameter of the ready-made pile, the outer diameter of the spiral blade, and the like.

図1、図2、図5に基づきこの発明の基礎杭の実施例を説明する。   An embodiment of the foundation pile of the present invention will be described with reference to FIGS.

[A]基礎杭の構成 [A] Structure of foundation pile

中空部3を有するコンクリート体2の外周を、外径D11、厚さt11、長さL11の外郭鋼管4で被覆して、杭本体1を形成する。 The outer periphery of the concrete body 2 having the hollow portion 3 is covered with an outer steel pipe 4 having an outer diameter D 11 , a thickness t 11 , and a length L 11 to form the pile main body 1.

杭本体1の下端1a、即ち端板7の下面に、掘削羽根(掘削手段)6、6が突設されている。掘削羽根6は、杭本体1の中心軸部分が高い三角形状の板片を等間隔に3枚配置して形成されている。また、ここで、端板7には、中空部7aが形成されており、コンクリート体2の中空部3と連通している。   Excavation blades (excavation means) 6, 6 protrude from the lower end 1 a of the pile body 1, that is, the lower surface of the end plate 7. The excavation blade 6 is formed by arranging three triangular plate pieces having a high center axis portion of the pile main body 1 at equal intervals. Here, a hollow portion 7 a is formed in the end plate 7 and communicates with the hollow portion 3 of the concrete body 2.

杭本体1の下端部外周に、ドーナツ状の半周分の螺旋羽根片9の2つを、同一の回転方向で回転対称の位置に(位相を180°ずらした位置に。あるいは直線対称な位置に。いずれも同じ等価な構造である)固着して、螺旋羽根8を構成する。螺旋羽根片9は、外径D12で、厚さt12の鋼板からなり、上端9bから下端9aまでの距離L12となるように、螺旋状に捻って固着されている。また、螺旋羽根8の下端9aは、杭本体1の下端1aより若干下方に突出し、下端部に掘削用の掘削突片10、10が突設されている。掘削突片10、10は、掘削羽根8の下方をもれなく掘削できるように、平面視で、位置を違えて配置されている(図1(c))。 On the outer periphery of the lower end of the pile main body 1, two donut-shaped spiral blade pieces 9 for a half circumference are placed at rotationally symmetric positions in the same rotational direction (at positions shifted by 180 ° in phase or at linearly symmetric positions). Are fixed to form a spiral blade 8. Spiral blade pieces 9, an outer diameter D 12, made of a steel plate having a thickness of t 12, so that the distance L 12 from the upper end 9b to the lower end 9a, and is secured by twisting spirally. The lower end 9a of the spiral blade 8 protrudes slightly below the lower end 1a of the pile main body 1, and excavation projections 10, 10 for excavation protrude from the lower end. The excavating pieces 10, 10 are arranged at different positions in plan view so as to excavate below the excavating blade 8 without fail (FIG. 1 (c)).

杭本体1の下端部外周で、螺旋羽根8の上方に、外径D14、厚さt14のドーナツ状の1周分の鋼板を螺旋状に捻って固着し、補助螺旋羽根12を構成する。補助螺旋羽根12は、ねじ込み時の土圧抵抗の少ない螺旋状(スパイラル形状)がねじ込み時の杭のねじり込み力を低減できるので望ましい。また、補助螺旋羽根12の上端から下端までの長さL14で形成されている。また、螺旋羽根8と補助螺旋羽根12の間隔はL13で形成されている。通常間隔L13は、ねじ込み効率や根固め層内でのせん断力の伝搬の確実性等を考慮すれば、杭径D11程度可能ならばそれ以上とするのが好ましいが、要は作用する荷重に耐え得るソイルセメントの固化した拡底根固め部自体の圧縮強度を満たす範囲で調節すれば良い。 At the outer periphery of the lower end portion of the pile main body 1, one round of a donut-shaped steel plate having an outer diameter D 14 and a thickness t 14 is spirally twisted and fixed above the spiral blade 8 to form the auxiliary spiral blade 12. . The auxiliary spiral blade 12 is desirably a spiral shape (spiral shape) having a small earth pressure resistance at the time of screwing in, since the screwing force of the pile at the time of screwing can be reduced. Also formed by a length L 14 to the lower end from an upper end of the auxiliary spiral vane 12. The distance between the spiral blade 8 the auxiliary spiral vane 12 are formed by L 13. Normal distance L 13 is, considering the reliability or the like of the propagation of the shear force at screwing efficiency and roots consolidated layer, it is preferred to the more if possible about pile diameter D 11, short acting load It can be adjusted within a range that satisfies the compressive strength of the solidified expanded bottom rooted portion itself of soil cement that can withstand the above.

以上のようにして、既製杭を構成する(図1)。   A ready-made pile is constituted as described above (FIG. 1).

[B]他の実施例 [B] Another embodiment

(1) 前記実施例において、おいて、杭本体1の外周部で、補助螺旋羽根12の上方に、異形鉄筋14を螺旋状に巻き付け固着することもできる(図1鎖線図示)。 (1) In the above embodiment, a deformed reinforcing bar 14 may be spirally wound and fixed above the auxiliary spiral blade 12 on the outer peripheral portion of the pile main body 1 (shown by a chain line in FIG. 1).

(2) また、前記実施例において、中空部3を塞ぐように、端板7に蓋5を固定して、蓋5の下面に掘削羽根6、6を固定することもできる(図1(d))。また、地盤強度により、掘削羽根6、6を省略することもできる(図示していない)。 (2) In the above embodiment, the cover 5 may be fixed to the end plate 7 so as to cover the hollow portion 3 and the excavating blades 6 may be fixed to the lower surface of the cover 5 (FIG. 1 (d)). )). Further, the excavating blades 6, 6 can be omitted depending on the ground strength (not shown).

(3) また、前記実施例において、中掘工法に使用する場合には、掘削羽根6を取り外して、かつ蓋5を使用せず、中空部3を上下に開放して、既製杭16を構成する(図2)。 (3) In the above-described embodiment, when the drill is used for the inner digging method, the excavating blades 6 are removed, and the hollow portion 3 is opened up and down without using the lid 5 to form the ready-made pile 16. (FIG. 2).

(4) また、前記実施例において、杭本体1を少なくとも螺旋羽根8及び補助螺旋羽根12を含む長さLとして(図1(a))、既製杭17を構成することもできる(図5(b))。この場合、既製杭17の上方に、他の各種のコンクリート杭31(鋼管被覆コンクリート杭、コンクリート杭)を連結して、使用する(図5(b))。 (4) Further, in the above embodiments, the pile body 1 as the length L 0 that includes at least the spiral blade 8 and the auxiliary spiral vane 12 (FIG. 1 (a)), can be configured off-the-shelf piles 17 (FIG. 5 (B)). In this case, various other concrete piles 31 (steel pipe-covered concrete piles, concrete piles) are connected above the ready-made piles 17 and used (FIG. 5B).

(5) また、前記実施例において、補助螺旋羽根12も螺旋羽根8と同様に、2枚の半周分のドーナッツ状の鋼板を使用して、同一の回転方向で回転対称の位置に(位相を180°ずらした位置に。または直線対称な位置に。いずれも同じ等価な構造である)配置して、構成することもできる(図示していない)。これにより、支持力を補強できると共に、既製杭のねじ込み性が更に良くなり、螺旋羽根8のねじ込み耐力も低減できる。 (5) In the above-described embodiment, the auxiliary spiral blades 12 are also made of two half-circle donut-shaped steel plates in the same rotational direction as the spiral blades 8 in the rotationally symmetric position (in the same rotational direction). 180 ° or a position symmetrical with a straight line, both of which have the same equivalent structure) (not shown). Thereby, the supporting force can be reinforced, the screwing property of the ready-made pile is further improved, and the screwing strength of the spiral blade 8 can be reduced.

(6) また、前記実施例において、補助螺旋羽根12を省略することもできる。また、螺旋羽根8は、下端部に少なくとも1つ形成されていれば良く、逆に、杭本体1の全長に亘り複数個追加して設けることもできる(図示していない)。即ち、ソイルセメントとの付着強度、せん断耐力を考慮して、所要支持力に適合させるべく適宜形成する。 (6) In the above embodiment, the auxiliary spiral blade 12 may be omitted. Further, it is sufficient that at least one spiral blade 8 is formed at the lower end, and conversely, a plurality of spiral blades 8 can be additionally provided over the entire length of the pile main body 1 (not shown). That is, in consideration of the adhesive strength to the soil cement and the shear strength, it is appropriately formed so as to be adapted to the required supporting force.

(7) また、前記実施例において、螺旋羽根8は、ドーナツ状の半周分の螺旋羽根片9の2つを使用したので、既製杭15(16)を地盤にねじ込み易いので好ましいが、地盤強度によっては、補助螺旋羽根12と同様に、ドーナツ状の1周分の鋼板を螺旋状に捻って構成することもできる(図示していない)。 (7) In the above embodiment, the spiral blades 8 are two donut-shaped spiral blade pieces 9 for a half circumference, so that the ready-made pile 15 (16) is easily screwed into the ground, which is preferable. Depending on the case, a steel plate for one round of a donut shape may be spirally twisted (not shown), similarly to the auxiliary spiral blade 12.

図2〜図5に基づき、上記実施例1の下端を開放した既製杭16を使用し、中掘工法による基礎杭28の造成方法を説明する。   Based on FIGS. 2 to 5, a method of forming the foundation pile 28 by the inside digging method using the ready-made pile 16 having the lower end opened in the first embodiment will be described.

[A]掘削ロッド18の構成 [A] Configuration of drill rod 18

使用する掘削ロッド18は、排土用のスパイラルを形成していないストレート状のロッド本体19の下端部に、掘削ヘッド20を取り付けて構成する(図3)。掘削ヘッド20は、下端部に掘削刃21a、21aを形成したヘッド本体21に、先端に掘削刃22a、22aを形成した掘削腕22、22の基端部を揺動自在に取り付けて構成する。   The drilling rod 18 to be used is configured by attaching a drilling head 20 to the lower end of a straight rod body 19 having no spiral for discharging the earth (FIG. 3). The excavating head 20 is configured such that base ends of excavating arms 22, 22 having excavating blades 22a, 22a formed at the tip are swingably attached to a head body 21 having excavated blades 21a, 21a formed at the lower end.

尚、掘削ロッド18は、土質が悪く砕け難い施工地盤の場合には、ロッド本体19の中間部に撹拌棒等を突設して、掘削ヘッド20による地盤のほぐしを補助することもできる。   When the excavating rod 18 is a construction ground having poor soil quality and is difficult to break, a stirring rod or the like may be protruded at an intermediate portion of the rod main body 19 to assist the excavation head 20 to loosen the ground.

掘削腕22は、一側に揺動して(図3)、通常の杭穴軸部径に対応した掘削ができ、他側に揺動して杭穴の拡底部に対応した拡大掘削ができ、揺動せずに下方に垂れた状態で、既製杭の中空部を通過できるようになっている。   The excavating arm 22 swings to one side (FIG. 3), and can perform excavation corresponding to a normal shaft diameter of the pile hole, and can swing to the other side to perform enlarged excavation corresponding to the enlarged bottom of the pile hole. It can pass through the hollow part of the ready-made pile without swinging and hanging downward.

ここで、掘削ヘッド20の掘削径D21は、既製杭を押し込む際に生じるねじり力を、使用する既製杭16が保有するねじり耐力に適合するように調節している。 Here, the drilling diameter D 21 of the excavation head 20, the torsional force generated when pressing the ready-made pile, are adjusted to prefabricated pile 16 to be used to match the torsional strength held.

[B]基礎杭の造成方法 [B] Construction method of foundation pile

(1) 掘削ロッド18を既製杭16の中空部3を挿通して、既製杭16の先端1aから掘削ヘッド20を突出した状態で、既製杭16及び掘削ロッド18を杭打ち機(図示していない)に支持する(図4(a))。 (1) With the drilling rod 18 inserted through the hollow portion 3 of the ready-made stake 16, and with the digging head 20 protruding from the tip 1a of the ready-made stake 16, the ready-made stake 16 and the drilling rod 18 are connected to a pile driver (shown in the figure). (Not shown) (FIG. 4A).

次に、掘削ロッド18を正回転して、外径D21の杭穴軸部24を掘削し地盤をほぐす。同時に、掘削ヘッド20の上方で、既製杭16の外郭鋼管4を正回転させて既製杭16を正回転して、螺旋羽根8で、ねじ込む(図4(b))。この際、大径の螺旋羽根8の上方で、小径の補助螺旋羽根12を回転させているので、容易に地盤にねじ込みながら、押し固めることができる。 Next, the drill rod 18 rotates in the forward direction, and excavating the Kuiana shaft portion 24 of the outer diameter D 21 loosen the soil. At the same time, the outer steel pipe 4 of the ready-made pile 16 is rotated forwardly above the excavation head 20, and the ready-made pile 16 is rotated forward and screwed in with the spiral blade 8 (FIG. 4B). At this time, since the small-diameter auxiliary spiral blade 12 is rotated above the large-diameter spiral blade 8, it can be easily screwed into the ground and compacted.

また、この際、掘削ロッド18のロッド本体19に排土用のスパイラルが形成されていないので、掘削ヘッド20でほぐされた掘削土は、地上29に排出されずに、杭穴内に留まる。   At this time, since the spiral for discharging the earth is not formed in the rod body 19 of the excavating rod 18, the excavated soil loosened by the excavating head 20 is not discharged to the ground 29 but remains in the pile hole.

また、ここで、掘削ヘッド20の上方で、既製杭16の螺旋羽根8までの間は径D21の杭穴軸部24が形成されるが、螺旋羽根8の上方では、地盤に螺旋羽根8でねじ込まれているので、径D21の杭穴壁は崩され、既製杭16の外周にほぐされた掘削土が押し込まれた状態となっている。 Also, here, above the drilling head 20, but Kuiana shaft portion 24 of the diameter D 21 Until helical blade 8 of prefabricated pile 16 is formed, the upper helical blade 8, helix ground blade 8 since the screwed in, Kuianakabe diameter D 21 is collapsed, in a state of excavated soil which loosened the outer periphery of the ready-made pile 16 is pushed.

(2) 掘削ヘッド20が、所定の支持地盤に達したならば、既製杭16の沈下を停止し、掘削ロッド18の回転を正回転から逆回転に切り替え、掘削ヘッド20の掘削腕22、22を他側に揺動させて、掘削ヘッド20で、外径D22の拡大根固め部25を掘削する(図4(c))。掘削ヘッド20で、掘削しながら、掘削土を撹拌し、更に、掘削ロッド18の中空部を通して、掘削ヘッド20から所定固化強度のセメンミルクを吐出し、拡大根固め部25内に均質なソイルセメント層26を形成する。 (2) When the excavating head 20 reaches a predetermined supporting ground, the sinking of the ready-made pile 16 is stopped, the rotation of the excavating rod 18 is switched from forward rotation to reverse rotation, and the excavating arms 22 and 22 of the excavating head 20 are rotated. the is swung to the other side, in the drilling head 20, drilling a larger root consolidated portion 25 of the outer diameter D 22 (FIG. 4 (c)). The excavated soil is agitated while excavating with the excavating head 20, and furthermore, cement milk having a predetermined solidification strength is discharged from the excavating head 20 through the hollow portion of the excavating rod 18, and a uniform soil cement layer is formed in the expanded root compaction unit 25. 26 is formed.

(3) 続いて、掘削ロッド1の回転を一旦止め、掘削腕22、22を下方に垂れた状態とし、既製杭16の中空部3を通して地上29に引き上げ(図4(d))、回収する。同時に、既製杭16を回転させて所定固化強度のソイルセメント層26内に、ねじ込み、螺旋羽根8が、拡大根固め部25の下端部の所定の位置するまで既製杭16を沈下させる。 (3) Subsequently, the rotation of the excavating rod 1 is temporarily stopped, and the excavating arms 22 and 22 are suspended downward, pulled up to the ground 29 through the hollow portion 3 of the ready-made pile 16 (FIG. 4D), and collected. . At the same time, the prefabricated pile 16 is screwed into the soil cement layer 26 having a predetermined solidification strength by rotating the prefabricated pile 16 and the prefabricated pile 16 is settled until the spiral blade 8 is located at a predetermined position at the lower end of the enlarged root compaction part 25.

(4) ソイルセメント層26が固化発現したならば、基礎杭28の築造が完了する(図4(e))。 (4) When the soil cement layer 26 is solidified, the construction of the foundation pile 28 is completed (FIG. 4E).

前記において、杭穴は全長L23で、外径D21の杭穴軸部は長さL21、外径D22の杭穴拡底部25は長さL22で形成される(図4(e))。 In the above, Kuiana the total length L 23, Kuiana shank length L 21 of the outer diameter D 21, Kuiana拡底portion 25 of the outer diameter D 22 is formed with a length L 22 (FIG. 4 (e )).

)。 ).

[C]他の実施例 [C] Another embodiment

(1) 前記実施例において、長さLの杭本体1を使用して構成した既製杭17を使用して、上部にコンクリート杭(既製杭。外郭鋼管の被覆が無い)31を連結した場合には、コンクリート杭31の外側を鋼管(ケーシング)33で覆い、鋼管33の下端部34を既製杭17の外郭鋼管4と係止して施工する。係止は、例えば、外郭鋼管4の外面に突出した突起36に鋼管31の切欠きを係止して行う(図5(a))。 (1) In the above embodiment, a case where a concrete pile (a ready-made pile, which is not covered with an outer steel pipe) 31 is connected to an upper part using a ready-made pile 17 constituted by using a pile body 1 having a length L 0 . In this case, the outside of the concrete pile 31 is covered with a steel pipe (casing) 33, and the lower end 34 of the steel pipe 33 is engaged with the outer steel pipe 4 of the ready-made pile 17 for construction. The locking is performed, for example, by locking the notch of the steel pipe 31 to the protrusion 36 protruding from the outer surface of the outer steel pipe 4 (FIG. 5A).

即ち、鋼管33を被覆した既製杭31、17の中空部3を掘削ロッド17を挿通して、前記同様に掘削ヘッド22で、地盤を崩しながら、鋼管33を介して、既製杭17を回転させて、地盤にねじ込みながら沈設する(図5(a))。既製杭17を回転する際には、杭打ち機で、鋼管33の上端部34aを回転させて、既製杭17に回転推進力を付与して行えば、コンクリート杭31に構造上、害のある捻りを作用させないので、好ましい。また、更に、Lが短いので既製杭17の肉厚t11も薄くできる。 That is, the excavation rod 17 is inserted through the hollow portion 3 of the ready-made piles 31 and 17 covered with the steel pipe 33, and the excavation head 22 rotates the pre-made pile 17 via the steel pipe 33 while breaking the ground in the same manner as described above. Then, it sinks while screwing into the ground (FIG. 5 (a)). When rotating the ready-made pile 17 by rotating the upper end portion 34a of the steel pipe 33 with a pile driving machine and applying a rotational propulsive force to the ready-made pile 17, the concrete pile 31 is structurally harmful. This is preferable because twisting is not applied. In addition, In addition, because the L 0 is short can be thinner wall thickness t 11 of the ready-made pile 17.

所定支持地盤まで、既製杭17を沈設させたならば、鋼管33を取り外して、地上に回収して(図5(b))、既製杭17、31を杭穴内に埋設した基礎杭を構成できる。この場合、鋼管33は、他の基礎杭造成における既製杭17に対しても繰り返し使用できる。   When the ready-made pile 17 is laid down to the predetermined supporting ground, the steel pipe 33 is removed and collected on the ground (FIG. 5B), and a foundation pile in which the ready-made piles 17 and 31 are buried in the pile holes can be formed. . In this case, the steel pipe 33 can be repeatedly used for the ready-made pile 17 in another foundation pile construction.

この場合、既製杭17とコンクリート杭31との連結部を拡大根固め部25(ソイルセメント層26)内に位置させて、埋め込むことが望ましい。これにより、連結部の強度を補強することもできる。   In this case, it is desirable that the connecting portion between the ready-made pile 17 and the concrete pile 31 is positioned and embedded in the enlarged root consolidation portion 25 (soil cement layer 26). Thereby, the strength of the connecting portion can be reinforced.

(2) また、前記実施例において、支持地盤に比して、杭穴軸部24の地盤強度が弱い場合には、杭穴軸部24でも地盤改良することができる(図示していない)。地盤改良は、例えば、各種固化強度のセメントミルクを杭穴軸部内に注入して、行う。ただし、その注入分だけ排土が生じる。 (2) In the above embodiment, when the ground strength of the pile hole shaft portion 24 is lower than that of the support ground, the ground can also be improved with the pile hole shaft portion 24 (not shown). The ground improvement is performed, for example, by injecting cement milk having various solidification strengths into the shaft of the pile hole. However, earth removal occurs only for the injection amount.

(3) また、前記実施例において、掘削ヘッド20は、薄型で、下方に向けて先細となるヘッド本体21に、薄型でかつ下方に向けてのヘッド本体21に沿って内側に屈曲され下端部で更に外側に向けて屈曲して外側に向けた掘削刃22aが突設されている(図示していない。図6同様)。従って、掘削時に掘削効率が良く、引き上げ時にも掘削土の抵抗を受け難い形状となっているが、図6の形状構造の掘削ヘッド40を使用すれば、更に、掘削効率を高めて、実施例3に記載の諸効果を得られる。 (3) In the above-described embodiment, the excavating head 20 has a thin, downwardly tapering head body 21 and a thin, downwardly bent inner side along the head body 21. In addition, a digging blade 22a that is bent outward and is directed outward is provided (not shown, similar to FIG. 6). Therefore, the excavation efficiency is good at the time of excavation, and the shape of the excavation soil is hardly affected by the excavation soil at the time of lifting. However, if the excavation head 40 having the shape structure shown in FIG. 3 are obtained.

また、掘削ヘッド20、40を使用することが望ましいが、他の構造の中掘用の掘削ヘッドを使用することもできる(図示していない)。   It is also desirable to use drilling heads 20, 40, but it is also possible to use a drilling head for digging in other structures (not shown).

次に、図1、図6、図7に基づき、先掘工法に適用した場合について、説明する。   Next, a case where the present invention is applied to the pre-drilling method will be described with reference to FIGS.

[A]掘削ロッド38の構成 [A] Configuration of drill rod 38

この発明の実施例に使用する掘削ロッド38も実施例2と同様に、スパイラルその他の排土を促進する手段や練り付け手段、撹拌手段を取り付けていないストレート状のロッド本体39の下端に掘削ヘッド40を取り付けて構成する(図6(a)(b))。   The drilling rod 38 used in the embodiment of the present invention is also provided with a drilling head at the lower end of a straight rod body 39 to which spiral or other means for promoting earth removal, kneading means, and stirring means are not attached, as in the second embodiment. 40 (FIGS. 6A and 6B).

掘削ヘッド40は、下端部に固定した掘削刃21a、21aを形成し、ロッド本体39に接合できるヘッド本体21に、先端に掘削刃22a、22aを形成した掘削腕22、22の基端部を揺動自在に取り付けて構成する。   The excavating head 40 is formed with excavating blades 21a, 21a fixed to the lower end thereof, and the base end of the excavating arms 22, 22 having excavating blades 22a, 22a formed at the tip thereof, on the head body 21 which can be joined to the rod main body 39. It is configured to be mounted swingably.

ヘッド本体21には、正回転時に掘削腕22の揺動の最大振幅を規制して、杭穴の軸部掘削径D21を規定するストッパー41、41、また、逆回転時に掘削腕22の揺動の最大振幅を規制して、杭穴の拡底部径D22を規定するストッパー42、42が夫々取り付けられている。また、逆回転時に掘削腕22の裏面と係合して、掘削腕22の揺動の最大振幅を維持する為のストッパー43も取り付けられている(図6(b)(c))。 The head body 21, to regulate the maximum amplitude of oscillation of the drilling arm 22 during normal rotation stopper 41, 41 defines a shank drill diameter D 21 of Kuiana, also rocking drilling arm 22 during reverse rotation to regulate the maximum amplitude of movement, the stopper 42, 42 defines a拡底portion diameter D 22 of Kuiana are attached respectively. In addition, a stopper 43 for engaging with the back surface of the excavating arm 22 during the reverse rotation and maintaining the maximum amplitude of the swing of the excavating arm 22 is also attached (FIGS. 6B and 6C).

ここで、軸部掘削径D21は、既製杭15が押し込み時に生じるねじり込み力が、既製杭15が保有するねじり耐力に適合するように調節されている。   Here, the shaft portion excavation diameter D21 is adjusted so that the torsion force generated when the ready-made pile 15 is pushed in conforms to the torsional strength of the ready-made pile 15.

尚、掘削ロッド38は、実施例2と同様に、土質が悪く砕け難い施工地盤の場合には、ロッド本体39の中間部に撹拌棒等を突設して、掘削ヘッド40による地盤のほぐしを補助することもできる。   As in the second embodiment, the excavation rod 38 is provided with a stirring rod or the like at an intermediate portion of the rod body 39 so that the excavation head 40 loosens the ground in the case of construction ground having poor soil quality and hard to break. You can also help.

以上のようにして、掘削ロッド38を構成する(図6)。   The drill rod 38 is configured as described above (FIG. 6).

この掘削ヘッド40では、ヘッド本体21が、平面視で板状の直方体形状となっておりかつ下方向けて先細に形成されている(図6(a)(b)(c))。また、掘削腕22、22も薄い形状であり、ヘッド本体21に沿って、下方に向けて内側に屈曲されており、下端部で外側に向けて更に屈曲され、外側に向けた掘削刃22a、22aが取付けられている(図6(b))。   In the excavating head 40, the head main body 21 has a plate-like rectangular parallelepiped shape in plan view and is tapered downward (FIGS. 6A, 6B, and 6C). The excavating arms 22, 22 are also thin, are bent inward downward along the head main body 21, are further bent outward at the lower end, and are directed outward. 22a is attached (FIG. 6B).

従って、掘削ヘッド40では掘削時には、掘削刃22a、22a周辺の掘削土は、直上には揚上されるので、掘削刃21a、22aの押し上げ抵抗を軽減して掘削速度を向上させることができる。よって、掘削効率が良い。また、掘削径D21に比して、掘削ヘッド40が占める横断面積が小さいので(図6(d))、引き上げる際に、杭穴内に存在する掘削土の抵抗を受け難いので、引き上げが容易である。ここで、掘削ヘッド40の横断面積が、掘削横断面の60%以下であることが必要であり、3分の1以下が望ましい。この掘削ヘッド40を使用することにより、総体として、掘削土を排土することなく、施工地盤を掘削してほぐし易く、掘削ヘッド40が容易に引き抜きできる経済的な工法としての本発明の実施に好適である。 Therefore, when the excavation head 40 excavates, the excavated soil around the excavation blades 22a, 22a is lifted immediately above, so that the resistance of the excavation blades 21a, 22a to be pushed up can be reduced and the excavation speed can be improved. Therefore, excavation efficiency is good. Further, as compared with the drilling diameter D 21, the cross-sectional area excavation head 40 is occupied by a small (FIG. 6 (d)), when pulled, since less susceptible to resistance of excavated soil present in the pile hole, easy pulling It is. Here, the cross-sectional area of the excavation head 40 needs to be 60% or less of the excavation cross-section, and is desirably 1/3 or less. By using this excavation head 40, as a whole, it is easy to excavate and loosen the construction ground without discharging the excavated soil, and to implement the present invention as an economical construction method in which the excavation head 40 can be easily pulled out. It is suitable.

[B]基礎杭28の造成方法 [B] Construction method of foundation pile 28

(1) 掘削ロッド38を所定位置に支持して、正回転して、掘削腕22を一側に揺動して(図6(c)(d)鎖線図示22A)、押し込み、径D21、長さL21の杭穴軸部24を掘削する(図7(a))。この際、掘削水を使用せず、排土をしない。 (1) the drill rod 38 is supported at a predetermined position, and rotates forward, the drilling arm 22 swings to one side (FIG. 6 (c) (d) a chain line shown 22A), pushing, diameter D 21, drilling Kuiana shaft portion 24 of the length L 21 (FIG. 7 (a)). At this time, no excavated water is used and no earth discharging is performed.

(2) 掘削ヘッド40が、所定の支持地盤に達したならば、沈下を停止し、掘削ロッド40の回転を正回転から逆回転に切り替え、掘削腕22を他側に揺動して(図6(c)(d)鎖線図示22B)、径D22、長さL22の杭穴拡底部25を掘削する。 (2) When the excavating head 40 reaches a predetermined supporting ground, subsidence is stopped, the rotation of the excavating rod 40 is switched from forward rotation to reverse rotation, and the excavating arm 22 is swung to the other side (see FIG. 6 (c) (d) The excavated bottom 25 of the pile hole having a diameter D 22 and a length L 22 is excavated.

続いて、掘削ロッド38の中空部を通して、掘削ヘッド40から所定固化強度のセメンミルクを吐出し、拡大根固め部25内に均質なソイルセメント層26を形成し(図7(b))、掘削ロッド38を地上29に引き上げる。   Subsequently, cement milk having a predetermined solidification strength is discharged from the excavating head 40 through the hollow portion of the excavating rod 38 to form a uniform soil cement layer 26 in the enlarged root compaction part 25 (FIG. 7B). 38 is raised to 29 above the ground.

この際、地上29に排土をしていないので、杭穴軸部24内は、空洞が形成されておらず、ほぐされた掘削土が詰まった状態になっている。   At this time, since the soil is not discharged to the ground 29, no cavity is formed in the pile hole shaft portion 24, and the loosened excavated soil is packed.

(3) 続いて、下端に掘削羽根6、6を突出させた既製杭15を使用して(図1(a)〜(c))、杭穴内に既製杭15を回転しながら、螺旋羽根8で、杭穴壁の地盤にねじ込みつつ、下降する。螺旋羽根8、補助螺旋羽根12をソイルセメント層26の所定位置に位置させ、保持する。 (3) Subsequently, using the ready-made pile 15 having the excavating blades 6, 6 projecting from the lower end (FIGS. 1A to 1C), the spiral blade 8 is rotated while rotating the ready-made pile 15 in the pile hole. Then, descend while screwing into the ground of the pile hole wall. The spiral blade 8 and the auxiliary spiral blade 12 are positioned and held at predetermined positions on the soil cement layer 26.

ソイルセメント層26が固化発現したならば、基礎杭28を構成する(図7(c))。   When the soil cement layer 26 is solidified, the foundation pile 28 is formed (FIG. 7C).

[C]他の実施例 [C] Another embodiment

(1) 前記実施例において、長さLの既製杭17を使用して、他のコンクリート杭31を連結して使用する場合には(図5(b)参照)、前記実施例2と同様に、既製杭17、31の外側を鋼管33で被覆して、下端部34を外郭鋼管4に係止した鋼管31を回転して行う(図5(a)参照)。 (1) In the examples, using the ready-made pile 17 of length L 0, when used in conjunction with other concrete pile 31 (see FIG. 5 (b)), similarly as in Example 2 Next, the outside of the ready-made piles 17, 31 is covered with a steel pipe 33, and the steel pipe 31 whose lower end 34 is locked to the outer steel pipe 4 is rotated (see FIG. 5A).

この場合、既製杭17とコンクリート杭31との連結部を拡大根固め部25(ソイルセメント層26)内に位置させて、埋め込むことが望ましい。これにより、連結部の強度を補強することもできる。   In this case, it is desirable that the connecting portion between the ready-made pile 17 and the concrete pile 31 is positioned and embedded in the enlarged root consolidation portion 25 (soil cement layer 26). Thereby, the strength of the connecting portion can be reinforced.

(2) また、前記実施例において、掘削ロッド39(掘削ヘッド40)を使用したが、例えば、前記実施例2の掘削ロッド20等他の掘削ロッドを使用することもできる(図示していない)。 (2) In the above embodiment, the excavating rod 39 (the excavating head 40) is used. However, for example, another excavating rod such as the excavating rod 20 of the second embodiment can be used (not shown). .

(3) また、前記実施例において、既製杭15を使用したが、底に蓋5を被せた既製杭15(図1(d))、掘削羽根6、6を省略した既製杭16(図2)を使用することもできる。 (3) In the above embodiment, the ready-made pile 15 was used, but the ready-made pile 15 (FIG. 1 (d)) with the cover 5 covered on the bottom, and the ready-made pile 16 (FIG. ) Can also be used.

底に蓋5を設けず、中空部3を開放した場合には、掘削土を中空部3に入れることもできるので、必要とするねじ込み力を軽減させることができる。また、底に蓋5を固定して、中空部3を閉塞した構造とした場合には、既製杭15を埋設した後又は埋設中に、既製杭15の中空部3に固化強度の高いセメントミルクや生コンクリートを充填することができ、より高強度の基礎杭を構成できる(図示していない)。   When the hollow portion 3 is opened without providing the lid 5 at the bottom, the excavated soil can be put into the hollow portion 3, so that the required screwing force can be reduced. When the lid 5 is fixed to the bottom and the hollow portion 3 is closed, the cement milk having high solidification strength is formed in the hollow portion 3 of the ready-made pile 15 after or during the embedding of the ready-made pile 15. And fresh concrete can be filled, and a higher strength foundation pile can be constructed (not shown).

(4) また、前記実施例において、拡大根固め部25を形成したが、軸部径D21の根固め部とすることもできる(図示していない)。 (4) Further, in the above embodiment has formed the enlarged root hardened portion 25 may be a root consolidated portion of the shaft portion diameter D 21 (not shown).

(5) また、前記実施例において、撹拌翼45を取り付けた他の掘削ヘッド40を使用することもできる(図8)。この掘削ヘッド40は、撹拌翼45を除けば、前記図6に記載の掘削ヘッド40と同一構造である。 (5) In the above-described embodiment, another excavating head 40 to which the stirring blade 45 is attached can be used (FIG. 8). This excavating head 40 has the same structure as the excavating head 40 shown in FIG.

即ち、掘削ロッド38は、ロッド本体39の下端に掘削ヘッド40を取り付けて構成する(図8)。   That is, the excavation rod 38 is configured by attaching the excavation head 40 to the lower end of the rod body 39 (FIG. 8).

掘削ヘッド40は、下端部に固定した掘削刃21a、21aを形成しロッド本体39に接合できるヘッド本体21に、先端に掘削刃22a、22aを形成した掘削腕22、22の基端部を揺動自在に取り付けて構成する。   The excavating head 40 swings the base ends of the excavating arms 22, 22 having excavating blades 22 a, 22 a formed at the distal end, on the head body 21 forming excavating blades 21 a, 21 a fixed to the lower end and being connectable to the rod main body 39. It is configured to be mounted movably.

ヘッド本体21は下部に角形状の膨大部44が形成され、上部と膨大部44とに撹拌翼45を取り付けてある。また、ヘッド本体38には、正回転時に掘削腕22の揺動の最大振幅を規制して、杭穴の軸部掘削径D21を規定するストッパー41、41、また、逆回転時に掘削腕22の揺動の最大振幅を規制して、杭穴の拡底部径D22を規定するストッパー42、42が夫々取り付けられている。また、逆回転時に掘削腕22の裏面と係合して、掘削腕22の揺動の最大振幅を維持する為のストッパー43も取り付けられている(図8(b)(c))。 The head main body 21 has an angular enlarged portion 44 formed at a lower portion, and a stirring blade 45 is attached to the upper portion and the enlarged portion 44. Also, the head body 38 is to regulate the maximum amplitude of oscillation of the drilling arm 22 during normal rotation stopper 41, 41 defines a shank drill diameter D 21 of Kuiana, also drilling arm during reverse rotation 22 to regulate the maximum amplitude of the swing stopper 42, 42 defines a拡底portion diameter D 22 of Kuiana are attached respectively. In addition, a stopper 43 is attached to engage with the back surface of the excavating arm 22 during the reverse rotation to maintain the maximum amplitude of the swing of the excavating arm 22 (FIGS. 8B and 8C).

以上のようにして、掘削ロッド33を構成する(図8)。   The drill rod 33 is configured as described above (FIG. 8).

この掘削ヘッド40では、ヘッド本体21が、平面視で板状の直方体形状となっておりかつ下方に向けて先細に形成されている(図8(a)(b)(c))。また、掘削腕22、22も薄い形状であり、ヘッド本体21に沿って、下方に向けて内側に屈曲されており、下端部で外側に向けて更に屈曲され、外側に向けた掘削刃22a、22aが取付けられている(図8(b))。   In the excavation head 40, the head main body 21 has a plate-like rectangular parallelepiped shape in plan view and is tapered downward (FIGS. 8A, 8B, and 8C). The excavating arms 22, 22 are also thin, are bent inward downward along the head main body 21, are further bent outward at the lower end, and are directed outward. 22a is attached (FIG. 8B).

従って、掘削ヘッド40では掘削時には、掘削刃21a、22a周辺の掘削土は、直上に揚上されるので、掘削刃22a、22aの押し上げ抵抗を軽減して掘削速度を向上させることができる。掘削土掘削効率が良い。また、掘削径D21に比して、掘削ヘッド40が占める横断面積が小さいので(図8(d))、引き上げる際に、杭穴内に存在するソイルセメントの抵抗を受け難いので、引き上げが容易である。ここで、掘削ヘッド40の横断面積が、掘削横断面の60%以下であることが必要であり、3分の1以下が望ましい。 Therefore, when the excavation head 40 excavates, the excavated soil around the excavation blades 21a, 22a is lifted immediately above, so that the resistance of the excavation blades 22a, 22a to be pushed up can be reduced and the excavation speed can be improved. Excavated soil excavation efficiency is good. Further, as compared with the drilling diameter D 21, the cross-sectional area excavation head 40 is occupied by a small (FIG. 8 (d)), when pulled, since less susceptible to resistance of soil cement present in the pile hole, easy pulling It is. Here, the cross-sectional area of the excavation head 40 needs to be 60% or less of the excavation cross-section, and is desirably 1/3 or less.

試験結果Test results

実施例3のいわゆる先掘工法で、既製杭15を埋設して形成した基礎杭28について(図7(c))、鉛直載荷試験等を行った。   A vertical loading test and the like were performed on the foundation pile 28 formed by burying the ready-made pile 15 by the so-called excavation method of the third embodiment (FIG. 7C).

[A]基礎杭28の構築 [A] Construction of foundation pile 28

(1)施工地盤性状
既製杭15の先端部の平均N値:30
土質:砂質土
(1) Construction ground properties Average N value of the tip of the ready-made pile 15: 30
Soil: sandy soil

(2)既製杭15の仕様
既製杭15の杭本体1の長さL11=15m
既製杭15の杭本体1の外径D11=600mm
既製杭15の杭本体1の外郭鋼管4の肉厚t11=12mm
螺旋羽根8の外径D12=1200mm
螺旋羽根8の板厚t12=40mm
螺旋羽根8の上下端9b、9a間の長さL12=200mm
補助螺旋羽根12の外径D14=900mm
補助螺旋羽根12の板厚t14=40mm
補助螺旋羽根12の上下端の長さL14=200mm
螺旋羽根8と補助螺旋羽根12の間隔L13=600mm
(2) Specifications of ready-made pile 15 Length L 11 of pile body 1 of ready-made pile 15 = 15 m
Outer diameter D 11 = 600 mm of pile body 1 of ready-made pile 15
Wall thickness t 11 = 12 mm of outer steel pipe 4 of pile body 1 of ready-made pile 15
Outer diameter D 12 of spiral blade 8 = 1200 mm
Plate thickness t 12 of spiral blade 8 = 40 mm
Length L 12 between upper and lower ends 9b and 9a of spiral blade 8 = 200 mm
Outer diameter D 14 of auxiliary spiral blade 12 = 900 mm
The thickness t 14 of the auxiliary spiral blade 12 is 40 mm.
Length L 14 of upper and lower ends of auxiliary spiral blade 12 = 200 mm
The distance L 13 between the spiral blade 8 and the auxiliary spiral blade 12 is 600 mm.

(3)杭穴の仕様
杭穴:拡大根固め部あり
軸部24の掘削経D21=600+30mm
軸部24の掘削長L21=13.5m
拡大根固め部25の径D22=1200mm
拡大根固め部25の長さL22=2500mm
拡大根固め部25でのソイルセメント固化強度:20N/mm
(3) Kuiana specifications Kuiana: drilling enlarged root hardened portion located shank 24 through D 21 = 600 + 30mm
The excavation length L 21 of the shaft portion 24 = 13.5 m
Diameter D 22 of expanded root compaction part 25 = 1200 mm
Length L 22 of the expanded root compaction part 25 = 2500 mm
Soil cement solidification strength at the expanded root solidification part 25: 20 N / mm 2

[B]試験結果 [B] Test results

(1)鉛直載荷試験の結果
長期先端支持力Rの式で、
=α×N×A
:杭先端平均N値 杭下端より下方D、上方4D間の平均値
D=既製杭の外径(=D12
:既製杭の螺旋羽根8を含む断面積(有効利用部分)
において、支持力係数α=400 程度の値が得られた。
(1) In formula results long tip supporting force R p in the vertical loading test,
R p = α × N p × A p
N p: Pile tip average N values pile bottom from below D, the outer diameter of the average value D = ready pile between the upper 4D (= D 12)
A p : Cross-sectional area including spiral blade 8 of ready-made pile (effective use part)
In the above, a value of the supporting force coefficient α = about 400 was obtained.

(2) 地上29への排土量は、杭穴の根固め部等に注入したセメントミルクの量程度であった。 (2) The amount of soil dumped on the ground 29 was about the amount of cement milk injected into the consolidation of pile holes.

(3) 従来の施工速度と同程度で、既製杭の埋設ができた。 (3) The existing piles were buried at the same speed as the conventional construction speed.

この発明の実施例の既製杭で(a)は正面図、(b)は側面図、(c)は底面図、(d)は他の実施例の一部縦断面図である。(A) is a front view, (b) is a side view, (c) is a bottom view, and (d) is a partial longitudinal sectional view of another embodiment of the ready-made pile according to the embodiment of the present invention. この発明の実施例の他の既製杭で(a)は正面図、(b)は側面図、(c)は底面図である。FIG. 3A is a front view, FIG. 3B is a side view, and FIG. 3C is a bottom view of another ready-made pile according to the embodiment of the present invention. この発明の実施例2で使用する掘削ロッドの正面図で、(a)は軸部掘削時、(b)は拡底部掘削時を夫々表す。FIGS. 6A and 6B are front views of a drill rod used in a second embodiment of the present invention, wherein FIG. (a)〜(e)は、この発明の実施例2の構築方法を説明する概略した縦断面図である。(A)-(e) is the outline longitudinal cross-sectional view explaining the construction method of Example 2 of this invention. この発明の他の実施例の既製杭で、(a)は埋設時の一部を破折した正面図、(b)は正面図である。FIG. 4A is a front view of a ready-made pile according to another embodiment of the present invention, in which FIG. 4A is a partially broken front view and FIG. この発明の実施例3に使用する掘削ロッドで、(a)は非回転時の正面図、(b)は同じく側面図、(c)は回転時の正面図、(d)は同じく底面図を夫々表す。(A) is a non-rotating front view, (b) is a side view, (c) is a rotating front view, and (d) is a bottom view. Represent each. (a)〜(c)は、この発明の実施例3の構築方法を説明する概略した縦断面図である。(A)-(c) is the outline longitudinal cross-sectional view explaining the construction method of Example 3 of this invention. この発明の実施例3に使用する他のロッドで、(a)は非回転時の正面図、(b)は同じく側面図、(c)は回転時の正面図、(d)は同じく底面図を夫々表す。Other rods used in Embodiment 3 of the present invention, (a) is a front view when not rotating, (b) is a side view, (c) is a front view when rotating, and (d) is a bottom view. Respectively.

符号の説明Explanation of reference numerals

1 杭本体
2 コンクリート体
3 中空部
4 外郭鋼管
5 蓋
6 掘削羽根(掘削手段)
7 端板
8 螺旋羽根
9 螺旋羽根片
10 掘削突片
12 補助螺旋羽根
14 異形鉄筋(螺旋条)
15 既製杭
16 既製杭
17 既製杭
18 掘削ロッド
19 ロッド本体
20 掘削ヘッド
21 ヘッド本体
22 掘削腕
24 杭穴軸部
25 拡大根固め部
26 ソイルセメント層
28 基礎杭
29 地上
31 コンクリート杭
33 鋼管(ケーシング)
38 掘削ロッド
39 ロッド本体
40 掘削ヘッド
41 ストッパー
42 ストッパー
43 ストッパー
DESCRIPTION OF SYMBOLS 1 Pile main body 2 Concrete body 3 Hollow part 4 Shell steel pipe 5 Lid 6 Drilling blade (drilling means)
7 End plate 8 Spiral blade 9 Spiral blade piece 10 Drilling protrusion 12 Auxiliary spiral blade 14 Deformed bar (spiral strip)
15 Ready-made pile 16 Ready-made pile 17 Ready-made pile 18 Drilling rod 19 Rod body 20 Drilling head 21 Head body 22 Drilling arm 24 Pile hole shaft part 25 Expanded root compaction part 26 Soil cement layer 28 Foundation pile 29 Ground 31 Concrete pile 33 Steel pipe (casing) )
38 drilling rod 39 rod body 40 drilling head 41 stopper 42 stopper 43 stopper

Claims (10)

(1) 外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して既製杭を構成する。
(2) 前記既製杭の中空部を、排土手段を形成していない掘削ロッドを貫通し、該掘削ロッドの掘削ヘッドを前記既製杭の下端から突出させる。
(3) 前記掘削ヘッドを回転して、地盤強度に対応して前記既製杭のねじ込みが可能となる径で、掘削液を使用せず、かつ排土をせずに杭穴を掘削しながら、ほぐした地盤を形成する。これと同時に又は交互に、前記既製杭を回転して、前記螺旋羽根で地盤にねじ込みながら前記既製杭を地盤に貫入する。
(4) 前記掘削ヘッドで所定の支持地盤に根固め部を形成したならば、前記掘削ヘッドを収容して、前記既製杭の中空部を通って、地上に引き上げると共に、前記根固め部内に前記螺旋羽根が位置するように、前記既製杭を埋設して、基礎杭を造成する。
(5) 以上のようにして、既製杭を埋設することを特徴とする基礎杭の造成方法。
(1) Spiral blades are formed on the outer periphery of the lower end of a concrete pile body whose outside is covered with a steel pipe to constitute a ready-made pile.
(2) The hollow portion of the ready-made stake is penetrated by a digging rod that does not form a soil discharging means, and the digging head of the digging rod protrudes from the lower end of the ready-made stake.
(3) By rotating the excavation head, with a diameter that allows the ready-made pile to be screwed in accordance with the ground strength, without using a drilling liquid, and while excavating a pile hole without discharging the soil, Form loose ground. At the same time or alternately, the ready-made pile is rotated, and the ready-made pile is penetrated into the ground while being screwed into the ground with the spiral blade.
(4) When the excavation head has formed a solidification portion on a predetermined support ground, the excavation head is accommodated, and the hole is lifted to the ground through the hollow portion of the ready-made pile, and the above-mentioned solidification portion is formed in the solidification portion. The foundation pile is formed by burying the ready-made pile so that the spiral blade is positioned.
(5) A method for forming a foundation pile, comprising burying a ready-made pile as described above.
(1) 外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して、既製杭を構成する。
(2) 掘削ロッドの先端の掘削ヘッドで、地盤強度に対応して前記既製杭のねじ込みが可能となる径で、掘削液を使用せずに、かつ排土をせずに、地盤を掘削しながら地盤をほぐして、所定の支持地盤に根固め部を有する杭穴を形成する。
(3) 前記杭穴内に、前記既製杭を回転しつつ、前記螺旋羽根で、杭穴壁周辺の地盤にねじ込みながら貫入し、前記螺旋羽根が前記根固め部内に位置するように、前記既製杭を埋設して、基礎杭を造成する。
(4) 以上のようにして、既製杭を埋設することを特徴とする基礎杭の造成方法。
(1) Spiral blades are formed on the outer periphery of the lower end of a concrete pile body whose outside is covered with a steel pipe to constitute a ready-made pile.
(2) The excavation head at the tip of the excavation rod has a diameter that allows the ready-made pile to be screwed in accordance with the soil strength, and excavates the ground without using drilling fluid and without discharging the soil. While the ground is loosened, a pile hole having a rooted portion is formed in a predetermined supporting ground.
(3) The prefabricated pile is rotated so that the prefabricated pile is screwed into the ground around the pile hole wall while rotating the prefabricated pile into the pile hole, and the spiral blade is positioned in the root compaction portion. Is buried to create a foundation pile.
(4) A method for forming a foundation pile, comprising burying a ready-made pile as described above.
掘削ヘッドで、螺旋羽根の外径と同等又はより大径の拡大根固め部を掘削し、該拡大根固め部内に形成するソイルセメント層内に、既製杭の螺旋羽根を位置させる請求項1又は2記載の基礎杭の造成方法。 The drilling head excavates an enlarged root compaction having a diameter equal to or larger than the outer diameter of the spiral blade, and positions the spiral blade of the ready-made pile in a soil cement layer formed in the enlarged root compaction. 2. The method for creating a foundation pile according to 2. 掘削ヘッドで、杭本体の外径と同等又は大径で掘削しつつ、杭穴又はほぐした地盤を形成する請求項1乃至3のいずれか1項に記載の基礎杭の造成方法。 The method for forming a foundation pile according to any one of claims 1 to 3, wherein the excavation head forms a pile hole or a loosened ground while excavating with a diameter equal to or larger than the outer diameter of the pile body. 外側を鋼管で被覆したコンクリート製の杭本体の下端部外周に螺旋羽根を形成して構成した既製杭を下杭として、他のコンクリート杭を上杭として、埋設する対象の既製杭を構成し、
上杭を被覆したケーシングの下端部を前記下杭に係止し、該ケーシングの上端部を回転して、前記下杭を回転させる請求項1乃至4のいずれか1項に記載の基礎杭の造成方法。
Construct a ready-made pile to be buried, using a pre-made pile formed by forming spiral blades around the lower end of the concrete pile body whose outside is covered with steel pipe as a lower pile, and other concrete piles as an upper pile,
The foundation pile according to any one of claims 1 to 4, wherein a lower end of the casing covering the upper pile is locked to the lower pile, and an upper end of the casing is rotated to rotate the lower pile. Construction method.
外側を鋼管で被覆したコンクリート製の杭本体で、下端部外周に螺旋羽根を形成したことを特徴とする既製杭。 A ready-made pile comprising a concrete pile body whose outside is covered with a steel pipe, and a spiral blade formed on an outer periphery of a lower end portion. 半周分の半ドーナッツ状の螺旋羽根片の2つを、回転対称な位置に螺旋状に固定して螺旋羽根としたことを特徴とする請求項6記載の既製杭。 7. The ready-made pile according to claim 6, wherein two of the half donut-shaped spiral blade pieces for a half circumference are spirally fixed at rotationally symmetric positions to form a spiral blade. 杭本体の下端を塞ぐと共に、該杭本体の下端に、掘削手段を突設したことを特徴とする請求項6又は7記載の既製杭。 The ready-made pile according to claim 6 or 7, wherein a lower end of the pile main body is closed, and a digging means is protruded from a lower end of the pile main body. 杭本体の下端部に、半周分の半ドーナッツ状の螺旋羽根片の2つを、回転対称な位置に螺旋状に固定して螺旋羽根とし、該螺旋羽根の下端に掘削突片を突設し、前記杭本体で前記螺旋羽根の上方に、前記螺旋羽根の径より小径の補助螺旋羽根を形成したことを特徴とする請求項6乃至8のいずれか1項に記載の既製杭。 At the lower end of the pile main body, two half-donut-shaped spiral blade pieces for a half circumference are spirally fixed at rotationally symmetric positions to form a spiral blade, and an excavation protrusion is protruded from the lower end of the spiral blade. The ready-made pile according to any one of claims 6 to 8, wherein an auxiliary spiral blade having a diameter smaller than the diameter of the spiral blade is formed above the spiral blade in the pile main body. 杭本体で、螺旋羽根の上方に、補助螺旋羽根より小径の螺旋条を形成した請求項6乃至9のいずれか1項に記載の既製杭。   The ready-made pile according to any one of claims 6 to 9, wherein a spiral strip having a smaller diameter than the auxiliary spiral blade is formed above the spiral blade in the pile main body.
JP2004039553A 2003-02-17 2004-02-17 Construction method of foundation pile and ready-made pile Expired - Lifetime JP4496553B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004039553A JP4496553B2 (en) 2003-02-17 2004-02-17 Construction method of foundation pile and ready-made pile

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2003038163 2003-02-17
JP2004039553A JP4496553B2 (en) 2003-02-17 2004-02-17 Construction method of foundation pile and ready-made pile

Publications (2)

Publication Number Publication Date
JP2004270440A true JP2004270440A (en) 2004-09-30
JP4496553B2 JP4496553B2 (en) 2010-07-07

Family

ID=33134029

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004039553A Expired - Lifetime JP4496553B2 (en) 2003-02-17 2004-02-17 Construction method of foundation pile and ready-made pile

Country Status (1)

Country Link
JP (1) JP4496553B2 (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006037491A (en) * 2004-07-27 2006-02-09 Jfe Steel Kk Expanded head pile and construction method of expanded head pile
CN102383430A (en) * 2011-02-23 2012-03-21 上海城地建设发展有限公司 Method for improving bearing capacity of pile bottom of pre-stressed centrifugal pipe pile (square pile) through in-pile boring
CN101319499B (en) * 2007-06-07 2012-03-28 刘润郊 Pile forming method and device for screwed pedestal pile with large flow concrete filled by hole drilling pump
KR101144312B1 (en) * 2008-12-23 2012-05-11 한국건설기술연구원 Steel pipe pile equipped with base enlargement device and the construction method
CN103882862A (en) * 2014-02-18 2014-06-25 周兆弟 Quincuncial cement mixing pile and forming method
JP2014122541A (en) * 2012-11-21 2014-07-03 Nippon Steel & Sumitomo Metal Joint structure of piles and erection method of piles
CN103938624A (en) * 2014-04-30 2014-07-23 杭州小尔科技有限公司 Quincunx high-strength bored pile and forming method
CN104032731A (en) * 2014-04-29 2014-09-10 周兆弟 Plum-blossom-shaped cement soil mixing pile and forming method thereof
CN104032735A (en) * 2014-04-29 2014-09-10 周兆弟 Triangular plum-blossom-shaped cement soil mixing pile and forming method thereof
CN104863125A (en) * 2014-04-29 2015-08-26 周兆弟 Bougainvillea spectabilis willd-shaped drilling pile and shaping method thereof
CN104863127A (en) * 2014-04-29 2015-08-26 周兆弟 Polygonal boring pile and formation method thereof
WO2016095144A1 (en) * 2014-12-17 2016-06-23 贺德新 Drill pipe and pile driver for construction of belled threaded pile, and construction method of belled threaded pile
JP2017106229A (en) * 2015-12-09 2017-06-15 梅岡 美喜男 Steel pipe pile
JPWO2021157699A1 (en) * 2020-02-07 2021-08-12
CN115125939A (en) * 2022-08-03 2022-09-30 中电建路桥集团有限公司 Construction equipment and construction method of prefabricated ultra-deep pile for soft soil foundation
KR102472139B1 (en) * 2021-12-08 2022-11-29 (주)삼일이엔씨 Cutting arms for forming reinforced apparatus of piles and construction method of piles with reinforced apparatus

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209690A (en) * 1995-02-06 1996-08-13 Kokudo Kiso:Kk Steel pipe pile and burying method for steel pipe pile
JPH11303069A (en) * 1998-04-17 1999-11-02 Nkk Corp Screwed type steel pipe pile with blade and execution method therefor
JP2000104253A (en) * 1998-09-29 2000-04-11 Nippon Steel Corp Rotary press-in pile method and pipe pile penetration device
JP2000291002A (en) * 1999-04-12 2000-10-17 Tenox Corp Construction method for composite pile, steel pipe pile used for the method, and composite pile
JP2002180462A (en) * 2000-12-11 2002-06-26 Asahi Kasei Corp Method for embedding existing pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209690A (en) * 1995-02-06 1996-08-13 Kokudo Kiso:Kk Steel pipe pile and burying method for steel pipe pile
JPH11303069A (en) * 1998-04-17 1999-11-02 Nkk Corp Screwed type steel pipe pile with blade and execution method therefor
JP2000104253A (en) * 1998-09-29 2000-04-11 Nippon Steel Corp Rotary press-in pile method and pipe pile penetration device
JP2000291002A (en) * 1999-04-12 2000-10-17 Tenox Corp Construction method for composite pile, steel pipe pile used for the method, and composite pile
JP2002180462A (en) * 2000-12-11 2002-06-26 Asahi Kasei Corp Method for embedding existing pile

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006037491A (en) * 2004-07-27 2006-02-09 Jfe Steel Kk Expanded head pile and construction method of expanded head pile
JP4645091B2 (en) * 2004-07-27 2011-03-09 Jfeスチール株式会社 Expanded pile and construction method of the expanded pile
CN101319499B (en) * 2007-06-07 2012-03-28 刘润郊 Pile forming method and device for screwed pedestal pile with large flow concrete filled by hole drilling pump
KR101144312B1 (en) * 2008-12-23 2012-05-11 한국건설기술연구원 Steel pipe pile equipped with base enlargement device and the construction method
CN102383430A (en) * 2011-02-23 2012-03-21 上海城地建设发展有限公司 Method for improving bearing capacity of pile bottom of pre-stressed centrifugal pipe pile (square pile) through in-pile boring
JP2014122541A (en) * 2012-11-21 2014-07-03 Nippon Steel & Sumitomo Metal Joint structure of piles and erection method of piles
CN103882862A (en) * 2014-02-18 2014-06-25 周兆弟 Quincuncial cement mixing pile and forming method
CN104032735B (en) * 2014-04-29 2016-09-28 周兆弟 Triangle Flos Mume cement mixing method and manufacturing process
CN104032731A (en) * 2014-04-29 2014-09-10 周兆弟 Plum-blossom-shaped cement soil mixing pile and forming method thereof
CN104032735A (en) * 2014-04-29 2014-09-10 周兆弟 Triangular plum-blossom-shaped cement soil mixing pile and forming method thereof
CN104863125A (en) * 2014-04-29 2015-08-26 周兆弟 Bougainvillea spectabilis willd-shaped drilling pile and shaping method thereof
CN104863127A (en) * 2014-04-29 2015-08-26 周兆弟 Polygonal boring pile and formation method thereof
CN103938624B (en) * 2014-04-30 2016-03-30 杭州小尔科技有限公司 Quincunx high strength drilled pile and manufacturing process
CN103938624A (en) * 2014-04-30 2014-07-23 杭州小尔科技有限公司 Quincunx high-strength bored pile and forming method
WO2016095144A1 (en) * 2014-12-17 2016-06-23 贺德新 Drill pipe and pile driver for construction of belled threaded pile, and construction method of belled threaded pile
JP2017106229A (en) * 2015-12-09 2017-06-15 梅岡 美喜男 Steel pipe pile
JPWO2021157699A1 (en) * 2020-02-07 2021-08-12
WO2021157699A1 (en) * 2020-02-07 2021-08-12 Jfeスチール株式会社 Steel pipe pile
JP7272444B2 (en) 2020-02-07 2023-05-12 Jfeスチール株式会社 steel pipe pile
KR102472139B1 (en) * 2021-12-08 2022-11-29 (주)삼일이엔씨 Cutting arms for forming reinforced apparatus of piles and construction method of piles with reinforced apparatus
WO2023106785A1 (en) * 2021-12-08 2023-06-15 (주)삼일이엔씨 Cutting arm for forming enlarged-tip-reinforcing part of pile, and method for constructing pile having enlarged-tip-reinforcing part
WO2023106788A1 (en) * 2021-12-08 2023-06-15 (주)삼일이엔씨 Cutting arm for composite steel pipe pile, rotary penetration-type composite steel pipe pile having extended base reinforcement part, and construction method therefor
CN115125939A (en) * 2022-08-03 2022-09-30 中电建路桥集团有限公司 Construction equipment and construction method of prefabricated ultra-deep pile for soft soil foundation
CN115125939B (en) * 2022-08-03 2024-04-12 中电建路桥集团有限公司 Prefabricated ultra-deep pile construction equipment and construction method for soft soil foundation

Also Published As

Publication number Publication date
JP4496553B2 (en) 2010-07-07

Similar Documents

Publication Publication Date Title
JP5265500B2 (en) Pile digging method, foundation pile structure
JP4496553B2 (en) Construction method of foundation pile and ready-made pile
JP2002155530A (en) Embedding method and tip metal fitting of existing pile
JP4817156B2 (en) Ready-made pile
JP3960372B2 (en) Foundation pile structure
JP2008297864A (en) Construction method of cast-in-place pile
JP2003268767A (en) Construction method for double tube digging small diameter pile using hole excavating rod
JP4189550B2 (en) Construction method of ready-made pile with spiral blade, casing for propulsion
JP5024692B2 (en) Construction method of foundation pile, ready-made pile, pile hole drilling rod
JP2004308411A (en) Existing concrete pile foundation having large diameter and method for burying existing pile
JP4129836B2 (en) Construction method of foundation pile, ready-made pile with spiral wing
KR101794112B1 (en) Rrotating-press type pile construction device by using tip-enlarged pile
JP2001271347A (en) Drop method for ready-made pile
JP2003147770A (en) Pile burying construction method and its device
KR102315113B1 (en) Helical pile and construction method for increasing peripheral friction and tip bearing capacity
JPS59192125A (en) Settlement work of concrete pile with screw
JP4156313B2 (en) Rotating method for ready-made piles
JP2005240395A (en) Rotary embedding method for pile
JP4517234B2 (en) Construction method of foundation pile, ready-made pile with propulsion cylinder
JP4641369B2 (en) Partially built soil cement composite pile
JP2004339917A (en) Rotary embedding method for pile
JP2002054135A (en) Composite structure
JP2003003464A (en) Internal excavation method through steel pipe pile
JPS6319390Y2 (en)
JP2003147768A (en) Ready-made pile burying method for reducing removal earth

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070205

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080827

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080930

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081201

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090217

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090420

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091110

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091201

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100302

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100402

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130423

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4496553

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130423

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140423

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250