JP2004204602A - Joint structure between steel main girder and pier and joint method - Google Patents
Joint structure between steel main girder and pier and joint method Download PDFInfo
- Publication number
- JP2004204602A JP2004204602A JP2002376669A JP2002376669A JP2004204602A JP 2004204602 A JP2004204602 A JP 2004204602A JP 2002376669 A JP2002376669 A JP 2002376669A JP 2002376669 A JP2002376669 A JP 2002376669A JP 2004204602 A JP2004204602 A JP 2004204602A
- Authority
- JP
- Japan
- Prior art keywords
- steel
- cell
- pier
- girder
- chamber
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、鋼主桁と橋脚との接合構造及び接合方法に係り、さらに詳しくは、鋼主桁と橋脚とを剛結合するための構造及び方法に関するものである。
【0002】
【従来の技術】
鉄骨コンクリート橋脚としては、突起付きH形鋼の周囲に定着補強鉄筋を配置し、割裂ひび割れの進展を抑制することによって高い定着耐力を得ること(REED工法)が基本とされている。
また、鋼桁と鉄骨コンクリート橋脚との剛結構造については、橋脚内に埋設された外面リブ付き鋼管を、橋脚頂部において主桁又は横桁に直接連結して力を伝達させ、かつ、主桁はウェブにスタッドを設置することにより、横桁と平行して配置した型枠鋼板は孔あき鋼板シベルを設置することにより、それぞれ鉄骨コンクリート橋脚と剛結するようにしたものがある(例えば、非特許文献1参照)。
【0003】
【非特許文献1】
土木学会第57回年次学術講演概要集「鋼管・コンクリート合成橋脚を用いた複合ラーメン橋の合理的接合法に関する基礎的研究」(第757頁〜第758頁) 平成14年9月
【0004】
【発明が解決しようとする課題】
REED工法を鋼桁と鉄骨コンクリート橋脚との接合構造に適用すると、定着補強鉄筋の組立作業を主桁と横桁に囲まれた狭い空間で行わなければならないので作業性が悪く、多くの労力と時間が必要になる。また、鉄骨を定着させる鋼桁の高さがフーチングに比べて一般に低いため、この定着方法では定着長さが不足する場合が生じる。
【0005】
また、非特許文献1に記載された桁と鉄骨コンクリート橋脚との剛結構造では、橋脚内に埋設された外面リブ付き鋼管を、橋脚の頂部において主桁又は横桁に直接連結するため、橋脚内の鉄骨の施工誤差を許容できない。また、スタッドの設置に付随して多量の鉄筋が必要になり、配筋が困難であるばかりでなくコンクリートの施工性が悪い。さらに、剛桁から鉄骨コンクリート橋脚への荷重の伝達は、鋼桁から鉄骨に直接、主桁ウェブのスタッドからコンクリートを介して、及び型枠鋼板の孔あき鋼板ジベルからコンクリートを介しての3経路があり、剛結部を設計する際、各経路から伝達される力の割合が明確でないため、合理的な設計ができない。
【0006】
本発明は、上記のような課題を解決するためになされたもので、鋼主桁と橋脚との剛結部の鉄筋を大幅に削減し、かつ施工性を改善できると共に、合理的な設計が可能な鋼主桁と橋脚との接合構造及び接合方法を提供することを目的としたものである。
【0007】
【課題を解決するための手段】
(1)本発明に係る鋼主桁と橋脚との接合構造は、対向配置されたウェブ及びこれらウェブの間を仕切るセル鋼板により複数のセル室を形成し、これら各セル室内においてウェブ及びセル鋼板の両者又はいずれか一方にずれ止めが設けられた多室セル横桁と、橋脚上の橋軸方向に設置された鋼桁とを有し、該鋼桁の間に前記多室セル横桁を配置してそのセル室を、下部が橋脚に埋設された突起付き鉄骨の上部にそれぞれ嵌合し、その両端部を前記鋼桁に接合して鋼主桁を構成し、前記多室セル横桁のセル室にコンクリートを充填して前記鋼主桁と橋脚とを剛結合したものである。
【0008】
(2)上記(1)の多室セル横桁に設けたずれ止めにスタッドを用いた。
(3)上記(2)の多室セル横桁に設けたスタッドにあらかじめ補強筋を結束した。
【0009】
(4)本発明に係る鋼主桁と橋脚との接合方法は、上記(1)〜(3)のいずれかの多室セル横桁をあらかじめ工場等で製作する工程と、下部が橋脚に埋設された突起付き鉄骨の両側において前記橋脚の橋軸方向に鋼桁を設置する工程と、多室セル横桁のセル室を前記突起付き鉄骨の上部に嵌合し、その両端部を前記鋼桁に接合して鋼主桁を構成する工程と、前記多室セル横桁のセル室にコンクリートを充填して鋼主桁と橋脚とを剛結合する工程とを含むものである。
【0010】
【発明の実施の形態】
図7は本発明に係る鋼主桁と橋脚との接合構造の基本的構成を示す模式図で、Pは鉄骨コンクリート橋脚(以下、単に橋脚という)、Aはアバット、Sは沓、Gは橋脚P上に設けた鋼主桁、Dは鋼主桁G上に設置した床版で、これら鋼主桁Gと床版Dにより上部構造Bを構成し、橋脚Pと鋼主桁Gは剛結されている。
図8は図7のC−C断面図で、1は鋼主桁Gを構成する鋼桁、10は同じく多室セル横桁で、4は橋面を構成する舗装である。
【0011】
[実施の形態1]
図1は本発明の実施の形態1の模式的縦断面図、図2は図1のA−A断面図、図3は図2の正面図、図4は図2のB−B断面図である。
図において、30は例えばフランジ外面に多数の突起等が設けられたH形断面の鋼材からなる突起付き鉄骨で、上部(突出部)を残して橋脚Pに埋設されている。なお、鋼主桁Gの外側に位置する突起付き鉄骨30a及び対向配置された多室セル横桁10の間に位置する突起付き鉄骨30aは、突起付き鉄骨30より短かく形成され、全長が橋脚Pに埋設されている(以下の説明では、突起付き鉄骨30,30aを併せて符号30で示すことがある)。
【0012】
上記の説明では、突起付き鉄骨30にH形断面で突起つきの鋼材を用いた場合を示したが、円形若しくは角形断面で表面に突起つきの鋼管を用いてもよい。また、突起のない通常のH形断面の鋼材又は鋼管の表面に、コンクリートと一体化をはかることのできるスタッドなどの突起物を設けてもよい。
【0013】
1は鋼主桁Gを構成するI形断面の一対の鋼桁で、突出した突起付き鉄骨30の両側において橋脚P上の橋軸方向に設置されている。そして、両鋼桁1のウェブ1aの対向面には、突起付き鉄骨30の突出部に対応し、かつ多室セル横桁10の幅に対応した間隔で、上下方向の中央部よりやや上方から下フランジ1bにかけて、ウェブ1aと直交してそれぞれ一対の連結鋼板2が溶接により接合されている。なお、この連結鋼板2は、あらかじめ工場等において鋼桁1に接合される。
【0014】
鋼桁1と共に鋼主桁Gを構成する一対の多室セル横桁10の一例を図5に示す。図5において、11a,11bは、対向する鋼桁1の連結鋼板2間の距離に対応した長さで、連結鋼板2の高さに対応した高さのI形断面又は板状の側板(以下、ウェブという)で、ウェブ11a,11bの間には所定の間隔で複数のセル鋼板12が溶接により接合されており、これにより、突起付き鉄骨30の断面積に対して余裕をもった大きさの複数のセル室13が形成されている。
【0015】
そして、各セル室13内において、ウェブ11a,11bの対向面(図には一方のウェブ11aのみ示してある)の長手方向にずれ止めである複数のスタッド14が、上下方向に複数列設けられており、また、対向するセル鋼板12の間には、これらスタッド14に対応して補強筋15が設けられ、この補強筋15はそれぞれスタッド14に結束されている。
このように、各セル室13にスタッド14及び補強筋15が設けられた多室セル横桁10は、あらかじめ工場等で製作され、工事現場に輸送される。
【0016】
上記の説明では、多室セル横桁10の各セル室13において、ウェブ11a,11bの対向面に複数のスタッド14を設けると共に、対向するセル鋼板12の間に設けた補強筋15をスタッド14に結束した場合を示したが、ウェブ11a,11bとセル鋼板12の対向面にそれぞれスタッド14とこれに結束される補強筋15を設けてもよく、あるいは、セル鋼板12の対向面にスタッド14を設け、ウェブ11a,11bの間にこれに結束される補強筋15を設けてもよい。
また、上記の補強筋15を省略し、スタッド14のみを設けてもよい。
【0017】
次に、上記のような本実施の形態の施工手順の一例について説明する。なお、橋脚Pには突起付き鉄骨30が埋込まれているものとし、また、鋼桁1のウェブ1aにはあらかじめ工場等において連結鋼板2が接合されており、多室セル横桁10もあらかじめ工場等で製作され、これらは工事現場に搬入されているものとする。
【0018】
先ず、橋脚P上の上面から突出した突起付き鉄骨30の両側の橋軸方向に、所定の距離を隔てて鋼桁1を対向配置する。
次に、両鋼桁1の間において、多室セル横桁10のセル室13を橋脚Pの上面から突出した突起付き鉄筋30にそれぞれ上方から嵌合し、橋脚P上に設置する。そして、多室セル横桁10のウェブ11a,11bの両端部を、鋼桁1に設けた連結鋼板2と位置合わせし、添接板3により両者を一体に接合する。これにより鋼主桁Gが構成される。
【0019】
ついで、橋脚Pと鋼主桁Gとの間にコンクリートを打設すると共に、多重セル横桁10の各セル室13にコンクリートを充填して突起付き鉄骨30と一体化し、鋼主桁Gを橋脚Pに剛結合する。この場合、多室セル横桁10の各セル鋼板12に1個又は複数個の穴を設け、コンクリートの打設個所数を低減するなどの施工性の向上をはかると共に、コンクリートと多重セル横桁10間の一体化に寄与させるようにしてもよい。
また、必要に応じて対向する多室セル横桁10の間に形成された空間領域SP(図4)にもコンクリートを打設し、剛結部の剛度をさらに向上させてもよい。
最後に多室セル横桁10の上面に、上面フランジ16を取付ける。
【0020】
上記のような橋脚Pと鋼主桁Gとの剛結部においては、多室セル横桁10から橋脚Pの突起付き鉄骨30への力の伝達は、多室セル横桁10のウェブ11a,11bにスタッド14を設けたことにより、多室セル横桁10→スタッド14→充填コンクリート→突起付き鉄骨30と行われる。このように鋼主桁Gから橋脚Pへの応力の伝達が明確なので、合理的な設計が可能である。
【0021】
[実施の形態2]
図6は本発明の実施の形態2の縦断面図である。
本実施の形態は、実施の形態1の鋼主桁Gを構成する鋼桁1に代えて、鋼箱桁5を設けたもので、その他の構成、作用効果は、実施の形態1の場合とほぼ同様である(以下の説明では、鋼桁1と鋼箱桁5を合せて鋼桁ということがある)。なお、実施の形態1,2では橋脚Pが鉄骨コンクリート橋脚の場合を示したが、軸方向鉄筋を併用した鉄骨鉄筋コンクリート橋脚にも本発明を実施することができる。
【0022】
【実施例】
本発明に係る各部の諸元については、対象となる構造物の種類、規模等に応じて種々異なるが、実施の形態1における各部の寸法の一例を示せず、次の通りである。
橋脚Pの断面は7m(橋軸直角方向)×3m(橋軸方向)で、突起付き鉄骨30は200×204×8×12mmの突起付きH形鋼であり、橋軸直角方向に等間隔に7本を橋軸方向に2列設置して、各列の両側の突起付き鉄骨30aを除き、コンクリートの上面より1.5m突出させた。
【0023】
鋼桁1は、高さ2.5mで、ウェブ1aの板厚は22mm、上下フランジ1b,1cの幅は0.65m、板厚は50mmであり、対向する鋼桁1間の距離は5mである。
また、多室セル横桁10のウェブ11a,11bの高さは2mで板厚12mm、上下のフランジの幅は0.25m、板厚は25mmである。セル鋼板12の板厚は12mmで、これによって一体化されたウェブ11a,11bの間隔は0.7m、セル鋼板12の間隔は1mである。また、ウェブ11a,11bに設けたスタッド14は、直径22mm、長さ0.15mで、セル室13内においてウェブ11a,11bのセル鋼板12間に2本、上下方向に4列設けた。補強筋15はD16である。
【0024】
上記のような寸法の鋼桁1及び多室セル横桁10を用いて、突起付き鉄骨30が設けられた橋脚Pに前述の要領で施工したところ、短時間でスムーズに鋼主桁Gを橋脚Pに剛結合することができた。
【0025】
上記のように構成した本発明によれば、突起付き鉄骨30の多室セル横桁10への定着において、スタッド14を設けた多室セル横桁10の鋼板が定着補強効果を発揮するため、定着補強鉄筋が不要になり、現場作業が大幅に簡略化できる。また、定着補強効果が大きいため、定着長を短かくすることができる。
さらに、多室セル横桁10のスタッド14の周囲に配置する鉄筋の量を零にし、又は少量に抑えることができるので、現場作業を大幅に簡略化できると共に、コンクリート打設時の施工性を向上することができる。
【0026】
また、多室セル横桁10のスタッド14の周囲に補強筋15を配置する場合は、補強筋15をあらかじめ工場等においてスタッド14に結束するので、現場作業を大幅に簡略化することができる。さらに、鋼主桁Gと橋脚Pとを付着接合するため、橋脚Pの施工誤差をある程度吸収することができ、これらにより、施工費を低減し、工期を短縮することができる。
【0027】
【発明の効果】
本発明に係る鋼主桁と橋脚との接合構造は、鋼桁の間に多室セル横桁を配置してそのセル室を、下部が橋脚に埋設された突起付き鉄骨の上部にそれぞれ嵌合し、その両端部を鋼桁に接合して鋼主桁を構成し、多室セル横桁のセル室にコンクリートを充填して鋼主桁と橋脚とを剛結合するようにしたので、剛結合部の鉄筋を大幅に削減し、かつ施工性を改善できると共に、合理的な設計を行うことができる。
【図面の簡単な説明】
【図1】本発明の実施の形態1に係る鋼主桁と橋脚との接合構造の模式的縦断面図である。
【図2】図1のA−A断面図である。
【図3】図2の正面図である。
【図4】図2のB−B断面図である。
【図5】一部を断面で示した多室セル横桁の斜視図である。
【図6】本発明の実施の形態2に係る鋼主桁と橋脚との接合構造の模式的縦断面図である。
【図7】本発明に係る鋼主桁と橋脚との接合構造の基本的構成を示す模式図である。
【図8】図7のC−C断面図である。
【符号の説明】
P 橋脚
G 鋼主桁
1 鋼桁
5 鋼箱桁
10 多室セル横桁
11a,11b ウェブ
12 セル鋼板
13 セル室
14 スタッド
15 補強筋
30 突起付き鉄骨[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a joining structure and a joining method between a steel main girder and a pier, and more particularly, to a structure and a method for rigidly connecting a steel main girder and a pier.
[0002]
[Prior art]
The basic principle of a steel concrete pier is to provide a high anchoring strength by arranging anchoring reinforcing steel around an H-beam with protrusions and suppressing the progress of split cracks (REED method).
For the rigid connection structure between a steel girder and a steel concrete pier, a steel pipe with external ribs embedded in the pier is directly connected to the main girder or cross girder at the top of the pier to transmit force, and For example, there is a type in which a stud is installed on a web, and a form steel plate arranged in parallel with a cross beam is rigidly connected to a steel concrete bridge pier by installing a perforated steel plate shovel (for example, Patent Document 1).
[0003]
[Non-patent document 1]
Proceedings of the 57th Annual Meeting of the Japan Society of Civil Engineers “Basic Study on Rational Jointing Method of Composite Rahmen Bridge Using Steel Pipe / Concrete Composite Pier” (pages 757 to 758) September, 2002
[Problems to be solved by the invention]
When the REED method is applied to the joint structure between a steel girder and a steel concrete pier, the work of assembling the reinforcing reinforcing steel must be performed in a narrow space surrounded by the main girder and the cross girder, resulting in poor workability and a lot of labor and labor. It takes time. Further, since the height of the steel girder for fixing the steel frame is generally lower than that of the footing, the fixing length may be insufficient in this fixing method.
[0005]
In the rigid connection structure between a girder and a steel concrete pier described in Non-Patent
[0006]
The present invention has been made in order to solve the above-described problems, and it is possible to significantly reduce the reinforcing steel at the rigid connection portion between the steel main girder and the pier, improve the workability, and achieve a rational design. It is an object of the present invention to provide a joining structure and a joining method between a steel main girder and a pier.
[0007]
[Means for Solving the Problems]
(1) In the joint structure between a steel main girder and a pier according to the present invention, a plurality of cell chambers are formed by opposed webs and a cell steel sheet partitioning between the webs, and a web and a cell steel sheet are formed in each of these cell chambers. A multi-chamber cell girder provided with a slip stopper on both or one of them, and a steel girder installed in the bridge axis direction on the pier, the multi-chamber cell girder between the steel girder. The cell chamber is arranged and the lower part is fitted to the upper part of the steel frame with projections buried in the pier, and both ends are joined to the steel girder to form a steel main girder, and the multi-cell horizontal girder is formed. Is filled with concrete, and the steel main girder and the pier are rigidly connected.
[0008]
(2) Studs were used for the stoppers provided in the multi-chamber horizontal beam of (1).
(3) Reinforcing bars were tied in advance to the studs provided on the multi-room cell cross beam of (2).
[0009]
(4) The method of joining a steel main girder and a pier according to the present invention includes the steps of previously manufacturing a multi-chamber cell cross girder according to any of the above (1) to (3) in a factory or the like, and embedding the lower part in a pier. Installing a steel girder in the bridge axis direction of the pier on both sides of the projected steel frame, fitting a cell chamber of a multi-compartment cell horizontal girder to the upper part of the steel frame with the projection, and attaching both ends of the steel girder to the steel girder. To form a steel main girder, and a step of filling concrete in the cell chamber of the multi-chamber horizontal girder to rigidly connect the steel main girder and the pier.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
FIG. 7 is a schematic diagram showing a basic configuration of a joint structure between a steel main girder and a pier according to the present invention, where P is a steel concrete pier (hereinafter simply referred to as a pier), A is an abutment, S is a shoe, and G is a pier. Steel main girder provided on P, D is a floor slab installed on steel main girder G, and these steel main girder G and floor slab D constitute upper structure B, and pier P and steel main girder G are rigidly connected. Have been.
FIG. 8 is a cross-sectional view taken along the line CC of FIG. 7, where 1 is a steel girder forming the main steel girder G, 10 is a multi-cell horizontal girder, and 4 is a pavement forming a bridge surface.
[0011]
[Embodiment 1]
1 is a schematic longitudinal sectional view of
In the figure,
[0012]
In the above description, a case where a steel material having a protrusion in an H-shaped cross section is used for the
[0013]
[0014]
FIG. 5 shows an example of a pair of multi-chamber cell
[0015]
In each of the
As described above, the multi-chamber
[0016]
In the above description, in each
Further, the reinforcing
[0017]
Next, an example of the construction procedure of the present embodiment as described above will be described. It is assumed that a
[0018]
First, the
Next, between the two
[0019]
Next, concrete is poured between the pier P and the steel main girder G, and each
Further, if necessary, concrete may be poured into the space region SP (FIG. 4) formed between the opposing multi-chamber cell cross beams 10 to further improve the rigidity of the rigid connection portion.
Finally, the
[0020]
At the rigid connection between the pier P and the steel main girder G as described above, the transmission of the force from the
[0021]
[Embodiment 2]
FIG. 6 is a longitudinal sectional view of
In the present embodiment, a
[0022]
【Example】
The specifications of each part according to the present invention are variously varied depending on the type, scale, etc. of the target structure, but examples of the dimensions of each part in the first embodiment are not shown, but are as follows.
The cross section of the pier P is 7 m (in the direction perpendicular to the bridge axis) × 3 m (in the direction of the bridge axis), and the
[0023]
The
The height of the
[0024]
Using the
[0025]
According to the present invention configured as described above, in fixing the
Furthermore, since the amount of rebar arranged around the
[0026]
Further, when the reinforcing
[0027]
【The invention's effect】
In the joint structure between the main steel girder and the pier according to the present invention, the multi-chamber cell cross girder is arranged between the steel girder, and the cell chamber is fitted to the upper part of the steel frame with projections, the lower part of which is embedded in the pier. The steel girder was joined at both ends to form a steel girder, and the cell room of the multi-chamber horizontal girder was filled with concrete to make a rigid connection between the steel girder and the pier. The rebar of the part can be greatly reduced, the workability can be improved, and a rational design can be performed.
[Brief description of the drawings]
FIG. 1 is a schematic longitudinal sectional view of a joint structure between a steel main girder and a pier according to
FIG. 2 is a sectional view taken along line AA of FIG.
FIG. 3 is a front view of FIG. 2;
FIG. 4 is a sectional view taken along line BB of FIG. 2;
FIG. 5 is a perspective view of a multi-room cell cross beam partially shown in cross section.
FIG. 6 is a schematic longitudinal sectional view of a joint structure between a steel main girder and a pier according to
FIG. 7 is a schematic diagram showing a basic configuration of a joint structure between a steel main girder and a pier according to the present invention.
FIG. 8 is a sectional view taken along line CC of FIG. 7;
[Explanation of symbols]
P Pier G Steel
Claims (4)
該鋼桁の間に前記多室セル横桁を配置してそのセル室を、下部が橋脚に埋設された突起付き鉄骨の上部にそれぞれ嵌合し、その両端部を前記鋼桁に接合して鋼主桁を構成し、前記多室セル横桁のセル室にコンクリートを充填して前記鋼主桁と橋脚とを剛結合することを特徴とする鋼主桁と橋脚との接合構造。A multi-chamber cell cross beam in which a plurality of cell chambers are formed by webs arranged opposite to each other and a cell steel plate separating these webs, and in each of these cell chambers, both or one of the web and the cell steel plate is provided with a stopper. And a steel girder installed in the bridge axis direction on the pier,
The multi-chamber cell cross girder is arranged between the steel girders, and the cell chamber is fitted to the upper part of the protruding steel frame whose lower part is embedded in the pier, and both ends are joined to the steel girder. A joint structure between a steel main girder and a pier, comprising a steel main girder, wherein concrete is filled in a cell room of the multi-chamber horizontal girder, and the steel main girder and the pier are rigidly connected.
下部が橋脚に埋設された突起付き鉄骨の両側において前記橋脚の橋軸方向に鋼桁を設置する工程と、
多室セル横桁のセル室を前記突起付き鉄骨の上部に嵌合し、その両端部を前記鋼桁に接合して鋼主桁を構成する工程と、
前記多室セル横桁のセル室にコンクリートを充填して鋼主桁と橋脚とを剛結合する工程とを含むことを特徴とする鋼主桁と橋脚との接合方法。A step of manufacturing the multi-room cell cross beam according to any one of claims 1 to 3 in a factory or the like in advance;
A step of installing steel girders in the bridge axis direction of the pier on both sides of the protruding steel frame having a lower part embedded in the pier,
A step of fitting a cell chamber of a multi-chamber cell girder to the upper part of the steel frame with projections, and joining both ends to the steel girder to form a main steel girder,
A method of joining a steel main girder and a pier, comprising a step of filling concrete into a cell room of the multi-chamber horizontal girder and rigidly connecting the steel main girder and the pier.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002376669A JP3994873B2 (en) | 2002-12-26 | 2002-12-26 | Joining structure and joining method of steel main girder and pier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002376669A JP3994873B2 (en) | 2002-12-26 | 2002-12-26 | Joining structure and joining method of steel main girder and pier |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004204602A true JP2004204602A (en) | 2004-07-22 |
JP3994873B2 JP3994873B2 (en) | 2007-10-24 |
Family
ID=32814073
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002376669A Expired - Lifetime JP3994873B2 (en) | 2002-12-26 | 2002-12-26 | Joining structure and joining method of steel main girder and pier |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3994873B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007032232A (en) * | 2005-07-29 | 2007-02-08 | Maeda Corp | Joint structure of bridge pier and cross beam and construction method for bridge |
JP2009052283A (en) * | 2007-08-27 | 2009-03-12 | Ihi Corp | Method and apparatus for connecting between steel member and concrete member |
-
2002
- 2002-12-26 JP JP2002376669A patent/JP3994873B2/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007032232A (en) * | 2005-07-29 | 2007-02-08 | Maeda Corp | Joint structure of bridge pier and cross beam and construction method for bridge |
JP4537906B2 (en) * | 2005-07-29 | 2010-09-08 | 前田建設工業株式会社 | Junction structure between bridge pier and girder, bridge construction method and bridge |
JP2009052283A (en) * | 2007-08-27 | 2009-03-12 | Ihi Corp | Method and apparatus for connecting between steel member and concrete member |
Also Published As
Publication number | Publication date |
---|---|
JP3994873B2 (en) | 2007-10-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2015246120B2 (en) | Open web composite shear connector construction | |
JP2006316580A (en) | Corrugated steel plate web pc composite beam and construction method of bridge using corrugated steel plate web pc composite beam | |
KR101851557B1 (en) | Arch structure with reinforced arch rib segment and arch structure construction method therefor | |
JP7118507B2 (en) | Steel reinforced concrete wall pillar building structure | |
JP4537906B2 (en) | Junction structure between bridge pier and girder, bridge construction method and bridge | |
JP7394256B1 (en) | Joint structure | |
JP2014105547A (en) | Structure for fixing precast floor slab | |
JP3752999B2 (en) | Upper and lower integrated bridge and its construction method | |
KR20180026286A (en) | Grid precast concrete structure and constructing method thereof | |
JP4086079B2 (en) | Joint structure and joining method of main girder and reinforced concrete pier | |
KR101426155B1 (en) | The hybrid rahmen structure which can add prestress on steel girder of horizontal member by gap difference of connection face between vertical member and steel girder of horizontal member | |
KR101583401B1 (en) | The continuous hybrid girder consist of concrete block and steel block which is can add prestress by gap difference between top and bottom of connection face of blocks | |
KR100622452B1 (en) | Multi-H section steel girder compounded part | |
JP2004204602A (en) | Joint structure between steel main girder and pier and joint method | |
JP2005127056A (en) | Joint structure of column and beam in rigid frame structural body | |
JP2003105861A (en) | Medium-rise and high-rise building using hfc column and hfc beam or the like | |
KR20170139873A (en) | Coupling structure of double type for girder and column capable of reducing girder height | |
JP7265343B2 (en) | steel building | |
JP3239867U (en) | culvert structure | |
KR101457796B1 (en) | Hybrid Structures Using Steel Framework and Precast Concrete Slab | |
JP7476836B2 (en) | Composite structure and construction method | |
JP7138542B2 (en) | Concrete beam structure | |
KR20090093585A (en) | Connecting structure for form-less column and steel beams, and constructing method thereof | |
JP2006188881A (en) | Joint structure of beam and floor board | |
JPH0762740A (en) | Joint method for precast steel framed reinforced concrete construction pillar and beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050817 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070628 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070710 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070723 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3994873 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100810 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110810 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120810 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130810 Year of fee payment: 6 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313532 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
EXPY | Cancellation because of completion of term |