JP2004190266A - Construction method of grade separated crossing road and connection method of foundation structure of viaduct and pier used for the same - Google Patents

Construction method of grade separated crossing road and connection method of foundation structure of viaduct and pier used for the same Download PDF

Info

Publication number
JP2004190266A
JP2004190266A JP2002357157A JP2002357157A JP2004190266A JP 2004190266 A JP2004190266 A JP 2004190266A JP 2002357157 A JP2002357157 A JP 2002357157A JP 2002357157 A JP2002357157 A JP 2002357157A JP 2004190266 A JP2004190266 A JP 2004190266A
Authority
JP
Japan
Prior art keywords
pier
foundation structure
piers
bridge
viaduct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002357157A
Other languages
Japanese (ja)
Other versions
JP4094416B2 (en
Inventor
Tomiyasu Furuta
富保 古田
Satoji Oshita
里治 尾下
Koji Mogi
浩二 茂木
Noriyoshi Umeda
法義 梅田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yokogawa Bridge Corp
Shiraishi Co Ltd
Original Assignee
Yokogawa Bridge Corp
Shiraishi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yokogawa Bridge Corp, Shiraishi Co Ltd filed Critical Yokogawa Bridge Corp
Priority to JP2002357157A priority Critical patent/JP4094416B2/en
Publication of JP2004190266A publication Critical patent/JP2004190266A/en
Application granted granted Critical
Publication of JP4094416B2 publication Critical patent/JP4094416B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To construct a grade separated crossing road in an extremely short period of time and solve the construction site securing problem. <P>SOLUTION: A foundation structure for supporting piers is constructed between the installation sections of a viaduct. Two bridge girders are assembled on the ground at a site adjacent to both ends of the installation sections in parallel with the above works and the piers are assembled with the piers and further, the soil between filling sections connecting to both ends of the installation sections is improved. Subsequently, the two bridge girders together with the piers are transferred to the installation sites by a transportation truck. The bridge girders are arranged above the foundation structure previously constructed and then, the bridge girders are lowered to a specified level together with the piers. In this condition, the piers are temporarily fixed to the foundation structure. Next, a bank is constructed between the filling sections and foundation concrete to fix the piers to the foundation structure is placed and cured. Next, the mutually opposite ends of the two bridge girders are connected together to form the whole bridge girder. Finally, pavement is spread on the bridge face on the bridge girder and the filling to form a viaduct and a slope of filling. <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
この発明は、高架橋と盛土傾斜路とを具える立体交差路の施工方法および、その方法に用い得る高架橋の基礎構造と橋脚との接合方法に関するものである。
【0002】
【従来の技術】
近年の都市内における交通渋滞は激化の一途をたどっており、これを解消する一つの方策として、交差点を平面から立体交差に改良整備することが必要になっている。
【0003】
ところで、上記改良工事の際の従来の立体交差の施工方法においては、先ず、一般に鋼製アンカーフレームをコンクリートで囲んだフーチング構成の基礎構造を高架橋の架設区間に沿って複数形成し、次いで、それらの基礎構造の上にそれぞれ橋脚を立設し、次いで、それらの橋脚上に橋桁を順次架け渡して橋桁全体を組み立て、併せてその橋桁全体の両端に連なる盛土区間に地盤改良を行ってから盛土を形成し、その後、橋桁上の橋面および盛土に舗装を施して高架橋および盛土傾斜路を形成している(例えば、非特許文献1および非特許文献2参照)。
【0004】
【非特許文献1】
土木施工管理チェックポイント「基礎工事II」,株式会社山海堂,2000年8月25日第1版発行
【非特許文献2】
土木工学ハンドブック,土木学会編,技報堂出版株式会社,1989年11月18日第4版発行
【0005】
【発明が解決しようとする課題】
しかしながら上記従来の施工方法では、時間のかかるフーチング構成の基礎構造の構築等のコンクリート工事を行った後に橋桁を架設しているため、工事期間が1〜2年の長期間にわたることが避けられず、しかもその間、高架橋の架設区間に並行する道路上に大型クレーンを置いて橋桁の架設工事等を行う必要があるので、交通規制や広範囲な通行止めを必要としており、それゆえ、新たな交通渋滞を生じさせることになってしまうことから、工事中の騒音の問題とも相俟って周囲の住民等の理解を得るのが難しいという問題があった。さらに都市部では、橋脚や橋桁の予備組立等のための工事用地を確保するのも難しいという問題があった。
【0006】
【課題を解決するための手段およびその作用・効果】
この発明は、上記課題を有利に解決した立体交差路の施工方法および、その方法に用い得る高架橋の基礎構造と橋脚との接合方法を提供することを目的とするものであり、この発明の立体交差路の施工方法は、高架橋と盛土傾斜路とを具える立体交差路を施工するに際し、前記高架橋の架設区間に、橋脚を支持するための基礎構造を施工し、これと並行して、前記架設区間の両端に対し道路延在方向両方向に隣接する場所で、橋桁全体を道路延在方向に二分割した二つの橋桁をそれぞれ地組立するとともにそれらの橋桁に橋脚を組み付け、併せて前記架設区間の両端に連なる盛土区間の地盤改良を行い、次いで、前記二つの橋桁をそれぞれ橋脚と一緒に運搬台車で架設場所に移動させて、先に施工した基礎構造の上方にその橋脚を配置してから、前記橋桁を前記橋脚とともに所定高さまで下降させ、その状態で前記橋脚を前記基礎構造に仮固定し、次いで、前記盛土区間に盛土を施工するとともに、前記橋脚を前記基礎構造に固定する基礎コンクリートを打設して養生し、次いで、前記二つの橋桁の互いに対向する端部同士を互いに連結して橋桁全体を形成し、最後に、前記橋桁上の橋面および前記盛土に舗装を施して前記高架橋および前記盛土傾斜路を形成することを特徴とするものである。
【0007】
かかるこの発明の施工方法によれば、高架橋の架設区間に橋脚を支持するための基礎構造の施工と、その架設区間の両端に対し道路延在方向両方向に隣接する場所で二つの橋桁をそれぞれ地組立するとともにそれらの橋桁に橋脚を組み付ける上部構造の組立と、その架設区間の両端に連なる盛土区間の地盤改良とを並行して行うことで工事期間を短縮し、さらに、二つの橋桁をそれぞれ橋脚と一緒に架設区間に移動させ、先に施工した基礎構造の上方にその橋脚を配置してから橋桁を橋脚とともに所定高さまで下降させて橋脚を基礎構造に仮固定した後、盛土区間への盛土の施工と、橋脚を基礎構造に固定する基礎コンクリートの打設および養生とを並行して行うことで工事期間を短縮するので、立体交差路の施工を例えば3カ月間程度と極めて短い期間で行い得て、周囲の住民等の理解を比較的容易に得ることができる。
【0008】
しかもこの発明の施工方法によれば、架設区間の両端に対し道路延在方向両方向に隣接する場所でそれぞれ、橋桁全体を道路延在方向に二分割した二つの橋桁をそれぞれ地組立するとともにそれらの橋桁に橋脚を組み付け、次いで橋脚と一緒にそれら二つの橋桁をそれぞれ運搬台車で、順次にまたは同時に架設場所に移動させるので、道路内用地のみを占用することから交通規制を最小限に留め得て、新たな交通渋滞を緩和することができるとともに、工事用地の確保の問題も解決することができる。
【0009】
なお、この発明の立体交差路の施工方法においては、前記基礎構造は井筒工法で施工することとしても良く、基礎構造を井筒工法で施工すれば、筒状のブロックを地盤中に圧入するので比較的低騒音で基礎構造を形成することができ、しかも時間のかかるフーチング構築等の大規模なコンクリート工事を行わないので基礎構造ひいては立体交差路全体の工事期間を短縮することができる。
【0010】
また、上記施工方法に用い得るこの発明の高架橋の基礎構造と橋脚との接合方法は、高架橋の基礎構造と橋脚とを接合するに際し、筒状のブロックを地盤中に圧入する井筒工法により前記基礎構造を施工するとともに、その基礎構造に複数本の鋼棒を植設し、次いで、前記基礎構造の中央孔内に鋼製の前記橋脚を挿入して、前記橋脚を仮置きし、次いで、前記橋脚に設けたフランジ部にそれぞれ挿通した複数本の鋼棒を、前記基礎構造に植設した複数本の鋼棒に結合し、もしくは前記基礎構造に植設した複数本の鋼棒を、前記橋脚に設けたフランジ部にそれぞれ挿通し、それら挿通した鋼棒にジャッキで軸力を与えつつ前記橋脚の高さおよび傾きを修正してから、それら挿通した鋼棒の軸力を維持することにより前記橋脚を自立させ、次いで、前記基礎構造と前記橋脚との間にモルタルあるいはコンクリートを打設して養生することを特徴とするものである。
【0011】
かかる接合方法によれば、時間のかかるフーチング構築等の大規模なコンクリート工事を行わないので、基礎構造ひいては高架橋の工事期間を短縮することができ、しかも高架橋の橋脚を基礎構造に精度良くかつ短時間で接合することができる。
【0012】
【発明の実施の形態】
以下に、この発明の実施の形態を実施例によって、図面に基づき詳細に説明する。ここに、図1(a)〜(d)は、この発明の立体交差路の施工方法の一実施例の概略手順を示す説明図であり、図1(a)は平面図、図1(b)〜(d)は側面図である。また図2(a),(b)は、上記実施例の施工方法で施工する立体交差路を示す平面図および側面図である。
【0013】
この実施例の立体交差路の施工方法は、図2に示すように、互いに交差する二本の道路CW1,CW2のうち、図では左右方向へ延在する道路CW1のセンターラインを挟む中央二車線に、高架橋EBと盛土傾斜路FRとを具える立体交差路OWを施工するためのもので、先ず、図1(a),(b)に示すように、その中央二車線の、高架橋EBの架設区間BZに、橋脚P1〜P4および橋桁支点A1,A2を支持するための基礎構造(下部工)としての六本のPCウェルWP1〜WP6を施工し、これと並行して、架設区間BZの両端に対し道路延在方向(図では左右方向)両方向に隣接する場所の中央二車線プラス片側一車線を夜間規制範囲NZとしてそれらの夜間規制範囲NZでそれぞれ、橋桁全体HBBを道路延在方向に二分割した二つの橋桁BBをそれぞれ地組立するとともに、それら二つの橋桁BBの下面にそれぞれ二本ずつ、図1(c)に示す如き橋脚P1,P2およびP3,P4を組み付けて、上部構造(上部工)を途中まで組み立て、併せて、架設区間BZの両端に連なる盛土区間RZの地盤改良を行う。
【0014】
ここで、各PCウェルWP1〜WP6を施工するに際しては、図3および図4(a),(b)に示す如きPCウェル工法で行う。すなわち、架設区間BZの六ヶ所にそれぞれ例えば図3に示すように、PCウェル圧入装置WIと、発動発電機と、グラウトミキサと、グラウトポンプと、油圧ポンプユニットと、スラッシュタンクとを設置するとともに、ダンプトラックDTと、クローラクレーンCCとを配置し、さらに掘削設備やPCウェルの仮置き場を設定して、図4に示すように、油圧作動するPCウェル圧入装置WIで筒状のブロックとしての例えば直径3mの単位PCウェルを順次継ぎ足すとともに内部のPC鋼棒に張力を与えながら地盤中に例えば概略20m〜40m程度の深さまで圧入してゆき、そのPCウェルの中央穴内の土砂を、クローラクレーンCCで昇降させるハンマーグラブHGで掘り出してダンプトラックDTで搬出する。そしてこれにより形成した各PCウェルの中央穴の底部にはコンクリートを流し込んで底盤を形成する。
【0015】
またここで、二つの橋桁BBをそれぞれ地組立するとともにそれら二つの橋桁BBの下面にそれぞれ二本ずつ橋脚P1,P2およびP3,P4を組み付けるに際しては、例えば代表で図1の左側の橋桁BBについて図5〜図7に示す如き、トラッククレーン・ベント工法で行う。すなわち、先ず図5(a)〜(c)に示すように、架設区間BZの、盛土区間RZに隣接する場所の地面に立設したベントB1〜B3上に大型の油圧クレーンHCでトレーラTRから吊り上げた鋼製橋桁材BMを載置して、そこで鋼製橋桁材BM同士を組み付け、次いで図6(a)に示すように、地面に立設したベントB4上まで同様にして鋼製橋桁材BMを組み付けるとともに、図6(b)に示すように、ベントB4の位置にて鋼製橋桁材BMの下面に鋼製橋脚P1を組み付け、さらに、図7(a)に示すように、地面に立設したベントB5〜B7上まで同様にして鋼製橋桁材BMを組み付けるとともに、図7(b)に示すように、ベントB6の位置にて鋼製橋桁材BMの下面に鋼製橋脚P2を組み付けることで、盛土区間RZに隣接する端部側から交差点側へ向けて橋桁BBをベント上に架設して地組立してゆく。また、図1の右側の橋桁BBについても同様にしてベント上に架設して地組立してゆく。そしてこれらの橋桁BBの地組立後は、地覆(路肩部)および高欄(ガード壁部)まで設置しておく。
【0016】
先に述べた下部工としての六本のPCウェルWP1〜WP6が完成したら、次に、高さ調整ジャッキ(デッキリフト)およびベントを搭載した運搬台車としてのドーリー(クローラ式トレーラ)DRを橋桁BBの下に移動させ、図1(c)に示すように、二つの橋桁BBをそれぞれ、橋脚P1〜P4と一緒にドーリーDRで持ち上げて架設場所に移動させて、先に施工した下部工としての六本のPCウェルWP1〜WP6のうちの交差点寄りの四本のPCウェルWP2,WP3,WP4,WP5の上方にそれらの橋脚P1〜P4を配置し、橋桁BBをそれらの橋脚P1〜P4とともに所定高さまで下降させる。
【0017】
この移動はこの実施例では二つの橋桁BBについて片側ずつ行い、例えば図1では左側の橋桁BBの移動の際、先ず、例えば図8(a)に示すように、片方の橋桁BB当たり図では八台のドーリーDRを橋桁BBの下に進入させ、次いで高さ調整ジャッキ(デッキリフト)を作動させて橋桁BBを二本の橋脚P1,P2とともに持ち上げ、次いで図8(b)に示すように、ドーリーDRの走行経路に掛かるベントを道路脇方向へ移動させあるいは撤去するとともにPCウェルWP1〜WP3の上端をそれぞれ鋼板で覆ってから、全てのドーリーDRを同時に交差点へ向けて走行させて橋桁BBを橋脚P1,P2と一緒に架設場所に移動させ、次いで、PCウェルWP1〜WP3を覆う鋼板を外すとともに、PCウェルWP1上に支点A1を設置してから、図9(a),(b)に示すようにデッキリフトを下げて橋桁BBを全体的に例えば概略2m下降させ、図9(a)に示すように、橋脚P1,P2の下端部をPCウェルWP2,WP3の中央穴内にそれぞれ挿入し、後述する方法でそれらのPCウェルWP2,WP3に仮固定する。また、図1の右側の橋桁BBについても同様にして架設場所に移動させて下降させ、橋脚P3,P4の下端部をPCウェルWP4,WP5の中央穴内にそれぞれ挿入し、それらのPCウェルWP4,WP5に仮固定する。なお、図9(c)は、後述する工程で形成する盛土傾斜路FRの端部のアバットを示している。
【0018】
上記仮固定の後、盛土区間RZに盛土およびアバットを施工するとともに、四本の橋脚P1〜P4を四本のPCウェルWP2〜WP5にそれぞれ固定する基礎コンクリートを打設して養生する。図10(a),(b)は、PCウェルの中央穴内に挿入した橋脚の下端部を上記仮固定およびその後の固定によってPCウェルに接合するための、この発明の接合方法の一実施例を示す説明図であり、この実施例の接合方法では、図10(a)に示すように、PCウェルWP2〜WP5の中央穴内に橋脚P1〜P4を挿入する以前に、PCウェルWP2〜WP5にグラウトを用いて植設してある複数本の鋼棒SRの地表近くに位置する上端部にそれぞれカップラー(雌ねじ部材)CRを螺合させておき、次いで、PCウェルWP2〜WP5の中央穴内に鋼製の橋脚P1〜P4を挿入して、その中央穴内にコンクリートで設けた仮支持面FS上に高さ調整用ライナー(鋼板)HLを介して橋脚P1〜P4の下端を仮置きする。
【0019】
次いで、橋脚P1〜P4の周囲に設けてあるフランジ部FLにそれぞれ挿通した、先のものとは別の複数本の鋼棒SRを先の鋼棒に結合するためにカップラーCRにそれぞれ螺合させ、それら後者の鋼棒SRにナットNTを螺着するとともに、図10(b)に破線で示すように、それらの鋼棒SRにジャッキJKで軸力を与えつつ橋脚P1〜P4の高さおよび傾きを修正してから、ナットNTとフランジ部FLとの間に適当な長さのスペーサーSPを挟み込んでそれらの鋼棒SRの軸力を維持することにより橋脚P1〜P4を自立させ、これにより橋脚P1〜P4をPCウェルWP2〜WP5に仮固定する。
【0020】
次いで、図10(b)に示すように、間詰めモルタルMTをPCウェルWP2〜WP5の内壁面および仮支持面FSと橋脚P1〜P4との間に打設して養生するとともに、中詰めコンクリートCTを橋脚P1〜P4の内部に打設して養生することで、橋脚P1〜P4の下端部をPCウェルWP2〜WP5に強固に固定する。
【0021】
上述の如くして二つの橋桁BBを位置決め固定した後、図1(d)および図8(c)に示すように、二つの橋桁BBの互いに対向する端部同士を位置調整してから互いに連結して橋桁全体HBBを形成し、最後に、橋桁HBB上の橋面および盛土区間RZに施工した盛土に舗装を施して、高架橋EBおよび盛土傾斜路FRを形成する。
【0022】
上記実施例の立体交差路の施工方法によれば、高架橋EBの架設区間BZに橋脚P1〜P4を支持するためのPCウェルP2〜P5の施工と、その架設区間BZの両端に対し道路延在方向両方向に隣接する場所で二つの橋桁BBをそれぞれ地組立するとともにそれらの橋桁BBに橋脚P1〜P4を組み付ける上部構造と、その架設区間BZの両端に連なる盛土区間RZの地盤改良とを並行して行うことで工事期間を短縮し、さらに、二つの橋桁BBをそれぞれ橋脚P1〜P4と一緒に架設区間BZに移動させ、先に施工したPCウェルP2〜P5の上方にその橋脚P1〜P4を配置してから橋桁BBを橋脚P1〜P4とともに所定高さまで下降させて橋脚BBをPCウェルP2〜P5に仮固定した後、盛土区間RZへの盛土の施工と、橋脚P1〜P4をPCウェルP2〜P5に固定する基礎コンクリートの打設および養生とを並行して行うことで工事期間を短縮するので、立体交差路OWの施工を例えば3カ月間程度と極めて短い期間で行い得て、周囲の住民等の理解を比較的容易に得ることができる。
【0023】
しかも上記実施例の施工方法によれば、架設区間BZの両端に対し道路延在方向両方向に隣接する場所でそれぞれ、橋桁全体HBBを道路延在方向に二分割した二つの橋桁BBをそれぞれ地組立するとともにそれらの橋桁BBに橋脚P1〜P4を組み付けて、次いで橋脚P1〜P4と一緒にそれら二つの橋桁BBをそれぞれドーリーDRで、順次にまたは同時に架設場所に移動させるので、道路内用地のみを占用することから交通規制を最小限に留め得て、新たな交通渋滞を緩和することができるとともに、工事用地の確保の問題も解決することができる。
【0024】
さらに上記実施例の立体交差路の施工方法によれば、基礎構造をPCウェル工法で施工することから、円筒状のPCウェルWP1〜WP6を地盤中に圧入するので比較的低騒音で基礎構造を形成することができ、しかも時間のかかるフーチング構築等の大規模なコンクリート工事を行わないので基礎構造ひいては立体交差路全体の工事期間を短縮することができる。
【0025】
そして上記実施例の高架橋の基礎構造と橋脚との接合方法によれば、時間のかかるフーチング構築等の大規模なコンクリート工事を行わずPCウェルWP1〜WP6で基礎構造を形成するので、基礎構造ひいては高架橋EBの工事期間を短縮することができ、しかも鋼棒で仮固定するので、高架橋EBの橋脚P1〜P4を基礎構造としてのPCウェルP2〜P5に精度良くかつ短時間で接合することができる。
【0026】
以上、図示例に基づき説明したが、この発明は上述の例に限定されるものでなく、例えば、上記実施例では二つの橋桁BBを順次に架設場所に移動させているが、街路の交通規制やドーリーの都合等が許せば二つの橋桁BBを同時に架設場所に移動させたり、全体を一方向から移動させても良い。またこの発明の立体交差路の施工方法における二つの橋桁BBは、橋桁全体HBBを中央で二分割したものでなく、不等分割や三分割以上の複数分割したものでも良い。さらにこの発明の立体交差路の施工方法における基礎構造はPCウェルでなくても良く、その場合には橋脚を基礎構造の穴内に挿入しなくても良い。
【0027】
一方、この発明の高架橋の基礎構造と橋脚との接合方法では、PCウェルに植設してあるPC鋼棒にカップラーを螺合させるようにしても良く、基礎構造をPCウェル以外の井筒工法で施工しても良い。
【図面の簡単な説明】
【図1】(a)〜(d)は、この発明の立体交差路の施工方法の一実施例の概略手順を示す説明図である。
【図2】(a),(b)は、上記実施例の施工方法で施工する立体交差路を示す平面図および側面図である。
【図3】上記実施例の施工方法で行う井筒工法の設備を例示する平面図である。
【図4】(a),(b)は、上記井筒工法の実施状況を示す平面図および側面図である。
【図5】(a),(b),(c)は、上記実施例の施工方法で行う橋桁の地組立の最初の段階を示す側面図と、その(a)のA−A断面図およびB−B断面図である。
【図6】(a),(b)は、上記実施例の施工方法で行う橋桁の地組立の次の段階を示す側面図および、その(a)のC−C断面図である。
【図7】(a),(b)は、上記実施例の施工方法で行う橋桁の地組立の最後の段階を示す側面図および、その(a)のD−D断面図である。
【図8】(a),(b),(c)は、上記実施例の施工方法で行う橋桁の移動の最初の状態を示す側面図と、橋桁の移動後の状態を示す平面図と、その後の橋桁の降下後の状態を示す側面図である。
【図9】(a),(b),(c)は、上記実施例の施工方法で行う橋桁の移動の後の橋桁の降下後の状態を示す側面図と、その橋脚付近の断面図と、橋桁の端部付近の断面図である。
【図10】(a),(b)は、上記実施例の施工方法で行う、この発明の高架橋の基礎構造と橋脚との接合方法の一実施例を示す説明図である。
【符号の説明】
A1,A2 支点
B1〜B7 ベント
BB 橋桁
BM 橋桁材
BZ 架設区間
CC クローラクレーン
CR カップラー
CT 中詰めコンクリート
CW1,CW2 道路
DR ドーリー
DT ダンプトラック
EB 高架橋
FL フランジ部
FR 盛土傾斜路
FS 仮支持面
HBB 橋桁全体
HC 油圧クレーン
HG ハンマーグラブ
HL ライナー
JK ジャッキ
MT 間詰めモルタル
NT ナット
NZ 夜間規制区間
OW 立体交差路
P1〜P4 橋脚
RZ 盛土区間
SP スペーサー
SR 鋼棒
TR トレーラ
WI PCウェル圧入装置
WP1〜WP6 PCウェル
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method of constructing a three-dimensional intersection having a viaduct and an embankment slope, and a method of joining a bridge pier with a foundation structure of the viaduct that can be used in the method.
[0002]
[Prior art]
In recent years, traffic congestion in cities has been intensifying, and as one measure for resolving this, it is necessary to improve and maintain intersections from flat to overpasses.
[0003]
By the way, in the conventional method of constructing an overpass at the time of the above-mentioned improvement work, first, in general, a plurality of footing-structured basic structures in which a steel anchor frame is surrounded by concrete are formed along an elevated bridge erection section. The bridge piers are erected on the foundations of the bridge, and then the bridge girders are sequentially bridged on those piers to assemble the entire bridge girder. Then, the bridge surface and the embankment on the bridge girder are paved to form a viaduct and an embankment slope (for example, see Non-Patent Documents 1 and 2).
[0004]
[Non-patent document 1]
Civil engineering construction management checkpoint "Foundation II", Sankaido Co., Ltd., first edition issued on August 25, 2000 [Non-Patent Document 2]
Civil Engineering Handbook, edited by the Japan Society of Civil Engineers, Gihodo Publishing Co., Ltd., published the fourth edition on November 18, 1989.
[Problems to be solved by the invention]
However, in the above-mentioned conventional construction method, since the bridge girder is erected after the concrete work such as the construction of the foundation structure of the time-consuming footing structure is performed, the construction period is inevitably extended for one to two years. In the meantime, it is necessary to place a large crane on the road parallel to the viaduct erection section to carry out erection work for bridge girder, etc., which requires traffic regulation and widespread traffic closure, thus creating new traffic congestion. Therefore, there is a problem that it is difficult to obtain the understanding of the surrounding residents, etc. in combination with the problem of noise during construction. Furthermore, in urban areas, there is a problem that it is difficult to secure construction sites for pre-assembly of piers and bridge girders.
[0006]
[Means for Solving the Problems and Their Functions and Effects]
SUMMARY OF THE INVENTION An object of the present invention is to provide a method of constructing a three-dimensional intersection that advantageously solves the above-mentioned problems, and a method of joining a viaduct foundation and a pier that can be used in the method. The construction method of the intersection, when constructing a three-dimensional intersection with a viaduct and an embankment slope, in the erection section of the viaduct, construct a foundation structure to support a pier, in parallel with this, At a location adjacent to both ends of the erection section in both directions of the road extending direction, two bridge girders obtained by dividing the entire bridge girder into two in the road extending direction are respectively ground-assembled, and piers are attached to those bridge girders. The ground improvement of the embankment section connected to both ends of the bridge, and then move the two bridge girders together with the piers to the erection site with a transport trolley, and place the piers above the foundation structure previously constructed. Lowering the bridge girder to a predetermined height together with the pier, temporarily fixing the pier to the foundation structure in that state, and then applying embankment to the embankment section and fixing the pier to the foundation structure. After curing, the opposite ends of the two bridge girders are connected to each other to form the entire bridge girder, and finally, the bridge surface on the bridge girder and the embankment are paved to form the bridge girder. It is characterized by forming a viaduct and the embankment ramp.
[0007]
According to the construction method of the present invention, the foundation structure for supporting the bridge pier in the erection section of the viaduct, and the two bridge girders are grounded at locations adjacent to both ends of the erection section in both directions of the road extending direction. The construction period is shortened by assembling the superstructure to attach the piers to those bridge girders and the ground improvement of the embankment section connected to both ends of the erection section in parallel, shortening the construction period. Together with the pier, place the pier above the previously constructed foundation structure, lower the bridge girder together with the pier to a predetermined height, temporarily fix the pier to the foundation structure, and then fill the embankment section Construction work and the placement and curing of the foundation concrete to fix the piers to the foundation structure are performed in parallel, shortening the construction period. Te resulting performed in a short period, it is possible to obtain an understanding of such residents around relatively easily.
[0008]
Moreover, according to the construction method of the present invention, two bridge girders obtained by dividing the entire bridge girder into two in the road extending direction are respectively assembled at the locations adjacent to both ends of the erection section in both directions of the road extending direction, and the respective parts are assembled on the ground. Assembling the piers to the bridge girders, and then moving the two bridge girders together with the piers to the erection site by transport trolleys sequentially or simultaneously, so that traffic control can be minimized by occupying only the land inside the road. In addition, new traffic congestion can be alleviated, and the problem of securing a construction site can be solved.
[0009]
Note that, in the method of constructing an overpass of the present invention, the foundation structure may be constructed by a well construction method, and if the foundation structure is constructed by a construction method, a cylindrical block is pressed into the ground. Since the foundation structure can be formed with extremely low noise, and a large-scale concrete construction such as a time-consuming footing construction is not performed, the construction period of the foundation structure and, consequently, the entire overpass can be shortened.
[0010]
In addition, the method for joining the viaduct foundation structure and the pier of the present invention which can be used in the above construction method is a method for joining the viaduct foundation structure and the pier by the well tube method of press-fitting a cylindrical block into the ground. While constructing the structure, planting a plurality of steel rods in the foundation structure, then inserting the steel pier into the central hole of the foundation structure, temporarily placing the pier, and then A plurality of steel rods respectively inserted into the flange portions provided on the pier are joined to a plurality of steel rods planted in the foundation structure, or the plurality of steel rods planted in the foundation structure are connected to the pier. The flanges provided in each are inserted, and the height and inclination of the pier are corrected while applying axial force to the inserted steel rods with a jack, and then the axial force of the inserted steel rods is maintained. Let the pier stand alone, then It is characterized in that curing by Da設 mortar or concrete between the pier and the substructure.
[0011]
According to such a joining method, since large-scale concrete work such as time-consuming footing construction is not performed, the construction period of the foundation structure and, eventually, the viaduct can be shortened, and the bridge pier of the viaduct can be accurately and shortly attached to the foundation structure. Can be joined in time.
[0012]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail by way of examples with reference to the drawings. 1 (a) to 1 (d) are explanatory views showing a schematic procedure of an embodiment of a method of constructing a grade separation road according to the present invention. FIG. 1 (a) is a plan view, and FIG. 4) to 4 (d) are side views. FIGS. 2A and 2B are a plan view and a side view, respectively, showing a three-dimensional intersection constructed by the construction method of the above embodiment.
[0013]
As shown in FIG. 2, the method of constructing a three-dimensional intersection according to this embodiment is a two-lane central lane sandwiching a center line of a road CW1 extending in the left-right direction among two roads CW1 and CW2 intersecting each other. In order to construct a three-dimensional intersection OW having a viaduct EB and an embankment slope FR, first, as shown in FIGS. 1 (a) and 1 (b), a central two-lane In the erection section BZ, six PC wells WP1 to WP6 as a foundation structure (substructure) for supporting the piers P1 to P4 and the bridge girder fulcrums A1 and A2 are constructed. The central two lanes plus one lane on either side of the location adjacent to both ends in the road extending direction (left-right direction in the figure) are defined as the night restricted range NZ, and the entire bridge girder HBB in the night restricted range NZ in the road extending direction. Divided into two The two bridge girders BB are respectively assembled on the ground, and two piers P1, P2 and P3, P4 as shown in FIG. 1 (c) are attached to the lower surface of the two bridge girders BB, respectively, to form an upper structure (superstructure). Assemble halfway, and at the same time, improve the ground of the embankment section RZ connected to both ends of the erection section BZ.
[0014]
Here, when the PC wells WP1 to WP6 are constructed, the PC well method is used as shown in FIGS. 3 and 4A and 4B. That is, as shown in FIG. 3, for example, the PC well press-fitting device WI, the power generator, the grout mixer, the grout pump, the hydraulic pump unit, and the slash tank are installed at six locations in the erection section BZ, respectively. , A dump truck DT and a crawler crane CC, and a digging facility and a temporary storage area for a PC well are set. As shown in FIG. 4, a hydraulically operated PC well press-fitting device WI serves as a cylindrical block. For example, unit PC wells having a diameter of 3 m are successively added, and at the same time, tension is applied to the internal PC steel rods and pressed into the ground to a depth of, for example, about 20 m to 40 m, and the soil in the central hole of the PC well is crawled. It is dug out by a hammer grab HG that is raised and lowered by a crane CC and carried out by a dump truck DT. Then, concrete is poured into the bottom of the central hole of each PC well thus formed to form a bottom plate.
[0015]
Here, when assembling the two bridge girders BB, respectively, and assembling the piers P1, P2 and P3, P4 two by two on the lower surface of the two bridge girders BB, for example, as a representative, the bridge girder BB on the left side of FIG. As shown in FIGS. 5 to 7, the truck crane and the vent method are used. That is, first, as shown in FIGS. 5A to 5C, a large hydraulic crane HC is used to move the trailer TR from the trailer TR onto vents B1 to B3 erected on the ground in a place adjacent to the embankment section RZ in the erection section BZ. The suspended steel bridge girder material BM is placed thereon, and the steel bridge girder materials BM are assembled together. Then, as shown in FIG. 6A, the steel bridge girder material BM is similarly extended up to the vent B4 erected on the ground. As shown in FIG. 6 (b), the steel pier P1 is assembled on the lower surface of the steel bridge girder BM at the position of the vent B4, and further, as shown in FIG. In the same manner as above, the steel bridge girder material BM is assembled on the upright vents B5 to B7. As shown in FIG. 7B, the steel bridge pier P2 is attached to the lower surface of the steel bridge girder material BM at the position of the vent B6. By assembling, adjacent to the embankment section RZ Slide into the earth assembled the bridge girder BB toward the intersection side bridged on the vent from the department side. Also, the bridge girder BB on the right side in FIG. 1 is erected on the vent and assembled on the ground. After the bridge girder BB is assembled on the ground, the bridge girder is installed up to the ground cover (road shoulder) and the railing (guard wall).
[0016]
When the six PC wells WP1 to WP6 as the substructure described above have been completed, a dolly (crawler type trailer) DR as a transport vehicle equipped with a height adjustment jack (deck lift) and a vent is then connected to the bridge girder BB. 1C, as shown in FIG. 1 (c), the two bridge girders BB are respectively lifted by the dolly DR together with the piers P1 to P4 and moved to the erection place, and the substructure as the previously constructed substructure is constructed. The piers P1 to P4 are arranged above the four PC wells WP2, WP3, WP4, and WP5 near the intersection among the six PC wells WP1 to WP6, and the bridge girder BB is fixed together with the piers P1 to P4. Lower to height.
[0017]
In this embodiment, this movement is performed on one side of each of the two bridge girders BB. For example, when the left bridge girder BB is moved in FIG. 1, first, as shown in FIG. The dolly DR is moved under the bridge girder BB, and then the height adjusting jack (deck lift) is operated to lift the bridge girder BB together with the two piers P1 and P2. Then, as shown in FIG. After moving or removing the vents along the travel path of the dolly DR in the sideways direction of the road and covering the upper ends of the PC wells WP1 to WP3 with steel plates, all the dolly DR are simultaneously driven toward the intersection to run the bridge girder BB. It is moved to the erection site together with the piers P1 and P2, and then the steel plate covering the PC wells WP1 to WP3 is removed and a fulcrum A1 is set on the PC well WP1. After that, as shown in FIGS. 9A and 9B, the deck lift is lowered to lower the bridge girder BB by, for example, about 2 m as a whole, and as shown in FIG. 9A, the lower ends of the piers P1 and P2. The parts are respectively inserted into the central holes of the PC wells WP2, WP3, and temporarily fixed to the PC wells WP2, WP3 by a method described later. Similarly, the bridge girder BB on the right side of FIG. 1 is similarly moved to the erection place and lowered, and the lower ends of the piers P3 and P4 are inserted into the center holes of the PC wells WP4 and WP5, respectively. Temporarily fix to WP5. FIG. 9C shows an abutment at the end of the embankment ramp FR formed in a step described later.
[0018]
After the temporary fixing, embankment and abutment are constructed in the embankment section RZ, and foundation concrete for fixing the four piers P1 to P4 to the four PC wells WP2 to WP5 is cast and cured. FIGS. 10A and 10B show an embodiment of the joining method of the present invention for joining the lower end of the pier inserted into the central hole of the PC well to the PC well by the above-mentioned temporary fixing and subsequent fixing. In the joining method of this embodiment, as shown in FIG. 10 (a), grout is inserted into the PC wells WP2 to WP5 before the piers P1 to P4 are inserted into the central holes of the PC wells WP2 to WP5. A coupler (female screw member) CR is screwed into each of upper ends of the plurality of steel rods SR planted near the ground surface, and then steel is inserted into the central holes of the PC wells WP2 to WP5. And the lower ends of the piers P1 to P4 are temporarily placed on a temporary support surface FS made of concrete in the central hole thereof via a height adjusting liner (steel plate) HL.
[0019]
Next, a plurality of steel rods SR different from those previously inserted through the flange portions FL provided around the piers P1 to P4, respectively, are screwed into the couplers CR in order to couple the steel rods SR to the previous steel rods. The nuts NT are screwed onto the latter steel rods SR, and the heights of the piers P1 to P4 are increased while giving an axial force to the steel rods SR with jacks JK, as shown by the broken lines in FIG. After correcting the inclination, the bridge piers P1 to P4 become independent by inserting a spacer SP of an appropriate length between the nut NT and the flange portion FL to maintain the axial force of the steel rods SR. The piers P1 to P4 are temporarily fixed to the PC wells WP2 to WP5.
[0020]
Next, as shown in FIG. 10B, the filling mortar MT is cast between the inner wall surfaces and the temporary supporting surfaces FS of the PC wells WP2 to WP5 and the piers P1 to P4 to cure, and the filling concrete is filled. The lower ends of the piers P1 to P4 are firmly fixed to the PC wells WP2 to WP5 by placing and curing the CT inside the piers P1 to P4.
[0021]
After the two bridge girders BB are positioned and fixed as described above, as shown in FIGS. 1D and 8C, the opposing ends of the two bridge girders BB are adjusted and then connected to each other. Then, the entire bridge girder HBB is formed, and finally, the bridge surface on the bridge girder HBB and the embankment constructed on the embankment section RZ are paved to form the viaduct EB and the embankment ramp FR.
[0022]
According to the method of constructing an overpass in the above embodiment, the PC wells P2 to P5 for supporting the piers P1 to P4 in the erection section BZ of the viaduct EB, and the road extending to both ends of the erection section BZ. At the same time, the two bridge girders BB are ground-assembled at locations adjacent in both directions, and the upper structure for assembling the piers P1 to P4 to the bridge girders BB and the ground improvement of the embankment section RZ connected to both ends of the erection section BZ are performed in parallel. To shorten the construction period, and furthermore, move the two bridge girders BB together with the piers P1 to P4 to the erection section BZ, and place the piers P1 to P4 above the PC wells P2 to P5 previously constructed. After the arrangement, the bridge girder BB is lowered to a predetermined height together with the piers P1 to P4, and the pier BB is temporarily fixed to the PC wells P2 to P5. PP4 is fixed to the PC wells P2 to P5 in parallel with the placement and curing of the foundation concrete, so that the construction period is shortened. It is possible to relatively easily obtain the understanding of the surrounding residents and the like.
[0023]
Moreover, according to the construction method of the above embodiment, two bridge girders BB obtained by dividing the entire bridge girder HBB into two in the road extending direction are respectively assembled at locations adjacent to both ends of the erection section BZ in both directions of the road extending direction. At the same time, the piers P1 to P4 are assembled to the bridge girders BB, and then the two bridge girders BB are moved together with the piers P1 to P4 to the erection site by the dolly DR, respectively, sequentially or simultaneously. Occupancy can minimize traffic restrictions, reduce new traffic congestion, and solve the problem of securing construction sites.
[0024]
Further, according to the method of constructing a three-dimensional intersection in the above embodiment, since the foundation structure is constructed by the PC well method, the cylindrical PC wells WP1 to WP6 are pressed into the ground, so that the foundation structure can be formed with relatively low noise. Since large-scale concrete work such as a footing construction that takes time can be formed without performing a large-scale concrete work, the work period of the basic structure and, consequently, the entire grade-crossing can be shortened.
[0025]
According to the method of joining the viaduct foundation structure and the pier of the above-described embodiment, the foundation structure is formed by the PC wells WP1 to WP6 without performing large-scale concrete work such as time-consuming footing construction. Since the construction period of the viaduct EB can be shortened and the steel bridge is temporarily fixed, the bridge piers P1 to P4 of the viaduct EB can be accurately and quickly joined to the PC wells P2 to P5 as the foundation structure. .
[0026]
As described above, the present invention has been described based on the illustrated example. However, the present invention is not limited to the above example. For example, in the above-described embodiment, two bridge girders BB are sequentially moved to the erection place. Alternatively, the two bridge girders BB may be moved to the erection place at the same time, or the whole may be moved from one direction if the circumstances of the dolly allow. Further, the two bridge girders BB in the method of constructing an overpass according to the present invention may not be divided into two parts at the center of the entire bridge girder HBB, but may be divided into unequal or three or more divided parts. Further, the foundation structure in the method of constructing a grade separation according to the present invention may not be a PC well, and in that case, the pier does not have to be inserted into the hole of the foundation structure.
[0027]
On the other hand, in the method of joining the viaduct foundation structure and the bridge pier according to the present invention, the coupler may be screwed into a PC steel rod planted in the PC well. May be constructed.
[Brief description of the drawings]
1 (a) to 1 (d) are explanatory views showing a schematic procedure of an embodiment of a method for constructing an overpass according to the present invention.
FIGS. 2 (a) and 2 (b) are a plan view and a side view showing a three-dimensional intersection constructed by the construction method of the embodiment.
FIG. 3 is a plan view illustrating facilities of a well pipe method performed by the construction method of the embodiment.
FIGS. 4 (a) and (b) are a plan view and a side view showing an implementation state of the well pipe method.
FIGS. 5A, 5B, and 5C are side views showing the first stage of ground assembly of a bridge girder performed by the construction method of the above embodiment, and a sectional view taken along line AA of FIG. It is BB sectional drawing.
FIGS. 6 (a) and 6 (b) are a side view showing a next stage of the ground assembling of the bridge girder performed by the construction method of the embodiment, and a cross-sectional view taken along the line CC of FIG. 6 (a).
FIGS. 7 (a) and 7 (b) are a side view showing the final stage of assembling the bridge girder by the construction method of the above embodiment, and a cross-sectional view taken along line DD of FIG. 7 (a).
8A, 8B, and 8C are side views showing an initial state of movement of a bridge girder performed by the construction method of the above embodiment, and plan views showing a state after movement of the bridge girder; It is a side view which shows the state after the descent of the subsequent bridge girder.
FIGS. 9A, 9B, and 9C are side views showing a state after the bridge girder is lowered after the bridge girder is moved by the construction method of the above embodiment, and a cross-sectional view near the pier; It is sectional drawing near the edge part of a bridge girder.
FIGS. 10 (a) and (b) are explanatory views showing one embodiment of a method for joining a viaduct foundation structure and a bridge pier according to the present invention, which is performed by the construction method of the above embodiment.
[Explanation of symbols]
A1, A2 Support points B1 to B7 Vent BB Bridge girder BM Bridge girder material BZ Construction section CC Crawler crane CR Coupler CT Filled concrete CW1, CW2 Road DR Dolly DT Dump truck EB Viaduct FL Flange FR Embankment ramp FS Temporary support surface HBB Bridge girder HC Hydraulic crane HG Hammer grab HL Liner JK Jack MT Filling mortar NT Nut NZ Night regulation section OW Overpass P1-P4 Pier RZ Embankment section SP Spacer SR Steel rod TR Trailer WI PC well press-in device WP1-WP6 PC well

Claims (3)

高架橋と盛土傾斜路とを具える立体交差路を施工するに際し、
前記高架橋の架設区間に、橋脚を支持するための基礎構造を施工し、
これと並行して、前記架設区間の両端に対し道路延在方向両方向に隣接する場所で、橋桁全体を道路延在方向に二分割した二つの橋桁をそれぞれ地組立するとともにそれらの橋桁に橋脚を組み付け、併せて前記架設区間の両端に連なる盛土区間の地盤改良を行い、
次いで、前記二つの橋桁をそれぞれ橋脚と一緒に運搬台車で架設場所に移動させて、先に施工した基礎構造の上方にその橋脚を配置してから、前記橋桁を前記橋脚とともに所定高さまで下降させ、その状態で前記橋脚を前記基礎構造に仮固定し、
次いで、前記盛土区間に盛土を施工するとともに、前記橋脚を前記基礎構造に固定する基礎コンクリートを打設して養生し、
次いで、前記二つの橋桁の互いに対向する端部同士を互いに連結して橋桁全体を形成し、
最後に、前記橋桁上の橋面および前記盛土に舗装を施して前記高架橋および前記盛土傾斜路を形成することを特徴とする、立体交差路の施工方法。
When constructing a three-dimensional intersection with a viaduct and embankment ramp,
In the erection section of the viaduct, construct a foundation structure to support the pier,
In parallel with this, two bridge girders obtained by dividing the entire bridge girder into two in the road extending direction are assembled at the places adjacent to both ends of the erection section in both directions of the road extending direction, and piers are attached to the bridge girders. Assembling, along with the ground improvement of the embankment section connected to both ends of the erection section,
Next, each of the two bridge girders is moved to the erection place with a transport trolley together with the pier, and the pier is arranged above the previously constructed foundation structure, and then the bridge girder is lowered to a predetermined height together with the pier. In that state, the pier is temporarily fixed to the foundation structure,
Next, while embankment is being constructed in the embankment section, curing is performed by placing foundation concrete for fixing the pier to the foundation structure,
Then, the opposite ends of the two bridge girders are connected to each other to form the entire bridge girder,
Finally, a pavement is applied to the bridge surface on the bridge girder and the embankment to form the viaduct and the embankment slope, and a method of constructing a three-dimensional intersection is provided.
前記基礎構造は井筒工法で施工することを特徴とする、請求項1記載の立体交差路の施工方法。The method according to claim 1, wherein the foundation structure is constructed by a well pipe method. 高架橋の基礎構造と橋脚とを接合するに際し、
筒状のブロックを地盤中に圧入する井筒工法により前記基礎構造を施工するとともに、その基礎構造に複数本の鋼棒を植設し、
次いで、前記基礎構造の中央孔内に鋼製の前記橋脚を挿入して、前記橋脚を仮置きし、
次いで、前記橋脚に設けたフランジ部にそれぞれ挿通した複数本の鋼棒を、前記基礎構造に植設した複数本の鋼棒の地表近くに位置する上端部に結合し、もしくは前記基礎構造に植設した複数本の鋼棒を、前記橋脚に設けたフランジ部にそれぞれ挿通し、それら挿通した鋼棒にジャッキで軸力を与えつつ前記橋脚の高さおよび傾きを修正してから、それら挿通した鋼棒の軸力を維持することにより前記橋脚を自立させ、
次いで、前記基礎構造と前記橋脚との間にモルタルあるいはコンクリートを打設して養生することを特徴とする、高架橋の基礎構造と橋脚との接合方法。
When joining the viaduct foundation and the pier,
Along with constructing the above-mentioned foundation structure by means of a well cylinder method of pressing a cylindrical block into the ground, planting a plurality of steel rods in the foundation structure,
Next, the steel pier is inserted into the central hole of the foundation structure, and the pier is temporarily placed,
Next, a plurality of steel rods respectively inserted into the flange portions provided on the pier are connected to upper ends of the plurality of steel rods planted in the foundation structure located near the ground surface, or are planted in the foundation structure. A plurality of steel rods were inserted through the flange portions provided on the piers, and the height and inclination of the piers were corrected while applying axial force to the inserted steel rods with jacks, and then they were inserted. Self-supporting the pier by maintaining the axial force of the steel bar,
Then, a mortar or concrete is poured between the foundation and the pier to cure the foundation, and the vial is joined to the pier.
JP2002357157A 2002-12-09 2002-12-09 Construction method of multilevel intersection Expired - Lifetime JP4094416B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002357157A JP4094416B2 (en) 2002-12-09 2002-12-09 Construction method of multilevel intersection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002357157A JP4094416B2 (en) 2002-12-09 2002-12-09 Construction method of multilevel intersection

Publications (2)

Publication Number Publication Date
JP2004190266A true JP2004190266A (en) 2004-07-08
JP4094416B2 JP4094416B2 (en) 2008-06-04

Family

ID=32757285

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002357157A Expired - Lifetime JP4094416B2 (en) 2002-12-09 2002-12-09 Construction method of multilevel intersection

Country Status (1)

Country Link
JP (1) JP4094416B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006083519A (en) * 2004-09-14 2006-03-30 Kajima Corp Construction method for grade separated crossing
JP2008101394A (en) * 2006-10-19 2008-05-01 Katayama Stratec Kk Prestressed concrete well and method of constructing bridge
CN108411763A (en) * 2018-02-09 2018-08-17 华东交通大学 Pre-splicing bridge and its construction method
CN108867664A (en) * 2018-09-04 2018-11-23 临沂大学 A kind of road based on contrary sequence method changes bridge section foundation pit supporting construction and its construction method
CN114990979A (en) * 2022-07-28 2022-09-02 白兴烈 Compaction leveling device for repairing highway pavement

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006083519A (en) * 2004-09-14 2006-03-30 Kajima Corp Construction method for grade separated crossing
JP4519588B2 (en) * 2004-09-14 2010-08-04 鹿島建設株式会社 Three-dimensional intersection construction method
JP2008101394A (en) * 2006-10-19 2008-05-01 Katayama Stratec Kk Prestressed concrete well and method of constructing bridge
CN108411763A (en) * 2018-02-09 2018-08-17 华东交通大学 Pre-splicing bridge and its construction method
CN108411763B (en) * 2018-02-09 2023-12-12 华东交通大学 Pre-spliced bridge and construction method thereof
CN108867664A (en) * 2018-09-04 2018-11-23 临沂大学 A kind of road based on contrary sequence method changes bridge section foundation pit supporting construction and its construction method
CN108867664B (en) * 2018-09-04 2023-09-15 临沂大学 Road-to-bridge Duan Jikeng supporting structure based on reverse construction method and construction method thereof
CN114990979A (en) * 2022-07-28 2022-09-02 白兴烈 Compaction leveling device for repairing highway pavement

Also Published As

Publication number Publication date
JP4094416B2 (en) 2008-06-04

Similar Documents

Publication Publication Date Title
US4051570A (en) Road bridge construction with precast concrete modules
KR101344063B1 (en) The construction method of steel-concrete underpass
AU646897B2 (en) Method of constructing a roadway
JP7061002B2 (en) How to repair a bridge
CN109403170B (en) Steep slope road and construction method thereof
KR100814388B1 (en) A bridge lifting method during vehicle passing
CN210238260U (en) Full-prefabricated assembled structural bridge suitable for grassland wetland
CN211922133U (en) Large cantilever structure suitable for widening old road of cliff road section
US20100272509A1 (en) Traffic barrier section
JP4094416B2 (en) Construction method of multilevel intersection
CN112627035A (en) Design and construction method of large-span Bailey steel trestle
JP4685341B2 (en) Viaduct construction method
JP2003129403A (en) Block type traffic road, dividing bridge type traffic road and bridge traffic road
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
CN110219235A (en) A kind of full precast assembly structural bridge and its construction method suitable for grassland wetland
JP4422978B2 (en) Steel shell for footing foundation, bridge structure, bridge construction method, and three-dimensional intersection bridge construction method
CN113668399B (en) Construction method of half-through tied steel box arch bridge
CN210163739U (en) Town road constructed based on prestressed concrete sheet piles
CN114439041A (en) Under-bridge side-through vehicle side construction foundation pit covering and excavating structure and construction method
CN112031495A (en) Prefabricated cabin transformer substation assembled steel structure foundation and construction splicing method thereof
CN217758292U (en) Transition bridge between tunnels under gully landform
KR100556629B1 (en) Fabricated temporary junction bridge with easy construction and dismantlement and building method thereof
JP3940587B2 (en) Construction method of divided bridge type traffic route
CN216338977U (en) Bridge is with striding rebuilding device and bridge
CN218713281U (en) Near-track foundation pit external construction platform

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051118

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071114

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071120

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20071211

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20071212

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080111

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080212

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080305

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110314

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4094416

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110314

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110314

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110314

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120314

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120314

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120314

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130314

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140314

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term